Commercial Sector EVM Implementation in Europe at Fabricom
Transcription
Commercial Sector EVM Implementation in Europe at Fabricom
COMMERCIAL SECTOR EVM IMPLEMENTATION IN EUROPE C A S E S T U DY Ing. Stephan Vandevoorde Manager Airport Systems, CofelyFabricom Director, EVM Europe Association PGCS, Canberra 2014 Cofely Fabricom, a GDF SUEZ Company 2 2 PGCS, Canberra 2014 ….active in most of today’s key sectors 3 ENERGY INDUSTRY INFRA STRUCTURE TERTIARY OIL, GAS & POWER High Voltage E&I High Voltage Electricity E&I Distribution networks P&M Distribution networks Communications & Networks Integration P&M Power Plants Process Solutions Underground Onshore & Offshore Data Centers Nuclear Renewable Maintenance & Specialized Services Rails, Roads, Waterways, Ports, Airports Power Plants Security Tanks Distribution Waste to Energy Bending & Prefab Environment Maintenance Services Maintenance Services PGCS, Canberra 2014 Maintenance services Maintenance Services … 2013 key figures 4 Turnover 894 MEUR Belgian Operations 88% Workforce 5160 Belgian Operations 4558 International Operations 12% International Operations 352 Central Services PGCS, Canberra 2014 250 Background 5 2002 – 2009: 3 major re-organisations • lot of people movements • loss of maturity • “troubled” projects PGCS, Canberra 2014 Background 6 How to define a project management training program? Launch of a working group Analysing project portfolio PGCS, Canberra 2014 Project landscape 7 Projects 2006 --> 2009 N= 1976 ( ca. 500 projects / year) 100% 80% 60% 40% 20% Values in Millions 2,0 1,8 1,6 1,4 1,2 1,0 0,8 0,6 0,4 0,2 0,0 0% Project landscape 8 Avg. Nrs. Of Projects / Year Contribution to Turn Over Portfolio Small / Medium Sized Projects Large / Complex Projects 500 450 50 100% 90% 10% 100% 25% 75% Small & Medium Sized Projects Large & Complex Projects ION Training Program 9 Training Program Type Small / Medium Projects National Allignment Large / Complex Projects International Allignment Reference Basic P.M. 6 Days / 2 Modules Advanced P.M. 11 Days / 3 Modules Language Dutch / French English EVM Related Basic EVM Advanced EVM ION Certificates M1 Hard Skills: 465 M2 Soft Skills: 499 M1 PM Awareness: 121 M2 Triple Constraint: 270 M3 Advanced PM: 252 EVM Roadmap 10 Step 1: Introducing EVM Principles Focus on cost control Status: implemented Step 2: Current Developments Focus on time control / Earned Schedule Status: being implemented on selected large / complex projects Advanced applications: p-factor Status: ad hoc applications Step 1: Cost Focus - Implemented 11 PGCS, Canberra 2014 Extract ETC procedure 12 P.M. provides on a regular way a ETC ETC has to be: “As good as possible” (direct influence on Profit / loss reports) Periodically discussed with B.C. / P.M. / Steering Committee PGCS, Canberra 2014 How we implement this 13 P.M. Input % Compl X PV X X ETC Performance Forecast PGCS, Canberra 2014 X X X B.C. X X X X EAC X X X X X X X Director X xPI Evaluate Review P.M. EV AC Status B.C. Bi Monthly Monthly X Based on D.O.D. evaluation rules 14 Once a contract is more than 15-20% complete, the final overrun will be worse than the present overrun (Christensen/Wilson 1992) CVfinal – CV20% < 0 Once a contract is over 20% complete, the CPI does not change by more than 10%, and in most cases it worsens (Christensen/Heise 1993) | CPIfinal - CPI20% | ∗ 0,10 Calculate a range of outcomes: CPI-based EAC is a floor to final cost (Christensen, 1996) SCI-based EAC is often the most accurate estimate (Fleming & Koppelman 2000, Humphreys & Associates 2002) EACcpi < EAC < EACSCI PGCS, Canberra 2014 Our experiences 15 Once a contract is more than 15-20% complete, the final overrun will be worse than the present overrun (Christensen/Wilson 1992) Give attention to deatiled planning in early stages Strict planning / control in the early stages is needed Once a contract is over 20% complete, the CPI does not change by more than 10%, and in most cases it worsens (Christensen/Heise 1993) CPI shows more variability during early & middle stage Compare TCPI & CPI Calculate a range of outcomes: CPI -EAC is a lower bound, SPI - EAC is an upper bound For critical projects, a cost simulation exercise is done PGCS, Canberra 2014 Real life application – status month 5 16 PROJECT INFO @ M5 Budget at Completion BAC Actual Cost AC from B.C. Progress % Compl from PM Estimate to Complete ETC from PM 2.875 1.562 51% 1.458 STATUS EV % SPENT Cost Variance Cost Performance Index Estimate at Completion EV = %Compl x BAC % Spent = AC / BAC PERFORMANCE CV CV = EV - AC CPI CPI = EV / AC FORECAST EAC EAC = AC + ETC 1.466 54% -96 0,94 3.020 To be analysed PGCS, Canberra 2014 Real life application – evaluation month 5 17 FORECAST EVALUATION @ M5 Iteration 1: EAC = 3.020 (given by PM) Rule 1: VAC > CV overrun increases from 96 --> 145 Rule 2: TCPI < CPI TCPI = 0,97 > CPI = 0,94 Rule 3: EACcpi < EACpm < EACsci 3.020 < 3.063 < 3.440 ok not ok not ok Iteration 2: EAC = 3.150 (done by B.C.) (TFA = Total Funds Available = BAC + MR) Rule 1: VAC > CV overrun increases from 96 --> 275 ok Rule 2: TCPI < CPI TCPI = 0,89 < CPI = 0,94 ok but… Rule 3: EACcpi < EACpm < EACsci 3.063 < 3.150 < 3.440 ok Iteration 3: EAC = 3.200 (decided during review) Rule 1: VAC > CV overrun increases from 96 --> 325 Rule 2: TCPI < CPI TCPI = 0,86 < CPI = 0,94 Rule 3: EACcpi < EACpm < EACsci 3.063 < 3.200 < 3.440 PGCS, Canberra 2014 ok ok ok Real life application 18 BAC EACcpi EACsci REVIEW COST RISK 70% By P.M. 3.700 3.600 3.500 3.400 3.300 3.200 3.100 3.000 2.900 2.800 M1 M2 PGCS, Canberra 2014 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 EVM application results 19 15% 10% Reported Deviation 5% 0% -5% -10% -15% -20% -25% After - ION Before - ION -30% -35% 0% 20% 40% 60% Progress PGCS, Canberra 2014 80% 100% Findings 20 ION trainings program increased project management maturity level Findings on project level: Cost forecasts are more reliable and stable Early visibility of potential cost overruns P.M.’s tend to estimate too optimistic A healthy baseline is needed, more effort needed during planning phase Findings on portfolio level: Cashflow profile has been reversed into positive (over 3 years) PGCS, Canberra 2014 Step 2: Focus on Time - selected projects 21 PGCS, Canberra 2014 Projects landscape -time 22 PGCS, Canberra 2014 The need for ES 23 Costs are better managed…and thus under control But project delays are becoming an issue Making a sound schedule is a difficult job In most cases there is no dedicated “scheduler” Updating schedules is very difficult So we are currently implementing Earned Schedule for large / complex projects PGCS, Canberra 2014 The need for ES 24 Chapter 3 Describes 3 real life cases Discusses the use of ES versus EV methods ES indicators / forecasts are reliable A healthy baseline is needed ES to be used in conjunction with a schedule PGCS, Canberra 2014 There is more with ES 25 PGCS, Canberra 2014 What really happens 26 PGCS, Canberra 2014 ES provides schedule information 27 PGCS, Canberra 2014 Schedule adherence = p-factor 28 PGCS, Canberra 2014 Effective earned value 29 PGCS, Canberra 2014 Effective earned value 30 PGCS, Canberra 2014 Final notes 31 EVM / ES: Training / assistance is needed requires an investment R.O.I. : More accurate and reliable cost / duration forecasts Better cashflow management Project orientated organisation may be makes it easier Give attention during bplanning phase: a sound baseline is needed ES Extensions: Use of P-Factor leads to more accurate / stable EAC predictions Looks very promising PGCS, Canberra 2014 Thanks 32 QUESTIONS? PGCS, Canberra 2014