Technical Assistance for Master Plan of Sisak New Port
Transcription
Technical Assistance for Master Plan of Sisak New Port
Project at a Glance CONTACTS Ministry of Maritime Affairs, Transport and Infrastructure Directorate for Transport Infrastructure 10 000 Zagreb, Krležin Gvozd 1a Overall objective Outputs Development of IWT on Master Plan for Sisak the Sava River Project objective Provision of Technical Assistance for the Master Plan of Sisak New Port Time frame Environmental Impact Assessment (EIA) Study An important part of the project work was dedicated to EIA PROCEDURE Data collection, public network impacts consultation, site visit Study. This Study is the legally prescribed procedure Ministry of Environmental where contingent impacts of the project on the environ- and Nature Protection: decision ment (including nature) are assessed and environmental on appropriate assessment protection measures, impact mitigation measures and monitoring programmes are prescribed. NO YES DRAFTING OF THE EIA REPORT and agriculture, nature, hunting, noise, population, land- (85% EU, 15% Croatia) Beneficiary Consultants iC consulenten (AT) TINA Vienna (AT) impacts on ecological network Hidrokonzalt (HR) Geokon-Zagreb (HR) End of ecological network The environmental experts of the Consultant consider compensated by a proposed set of measures. Therefore, Feasibility Study and Cost-Benefit Analysis (CBA) Environmental Impact Assessment (EIA) Draft Major Project Application for EU Funding Representation of the European Commission in the Republic of Croatia 10 000 Zagreb Ban Centre, Ulica Augusta Cesarca 4–10 T +385 1 46 81-300, F +322 2 985 796 comm-rep-zag@ec.europa.eu www.ec.europa.eu/index_hr.htm Central Finance and Contracting Agency – CFCA 10 000 Zagreb Ulica grada Vukovara 284, Object C T +385 1 45 91-245, F +385 1 45 91-075 info@safu.hr www.safu.hr Port Authority Sisak tehnicki.poslovi@luckaupravasisak.hr www.luckaupravasisak.hr Submission of the final EIA Report (=Study) to the Ministry of Environmental and Nature Protection: BEGINNING OF iC consulenten Ziviltechniker GesmbH THE ENVIRONMENTAL IMPACT ASSESSMENT PROCEDURE Technical Assistance for Master Plan of Sisak New Port 1120 Vienna, Schönbrunner Strasse 297 (November 2013) T +43 1 521 69-0, F +43 1 521 69-180 the negative environmental impact of the construction of Sisak New Port to be small which means that it can be Land Surveying Study www.mppi.hr T +385 44 524-810, F +385 44 524-809 impact assessment accidents. The Study provides a set of recommendations adverse factors. Port Infrastructure info@mppi.hr 44 000 Sisak, Rimska 28 scape as well as the impact of the project in case of and obligatory measures to avoid and/or to minimise · Preliminary Design for Budget The EIA Study assessed the impact of the project in the construction and operation phases on air, waters, soil · SWOT Analysis · Expropriation and (appropriate assessment of included in the EIA Report) · Transport Forecast · Geotechnical Study Port Authority Sisak the preparation of an Environmental Impact Assessment · Transport Analysis August 2012 – December 2013 1,435,120 EUR Screening of ecological New Port T +385 1 37 83-928, F +385 1 37 83-901 office@ic-group.org 1st committee meeting with site visit EuropeAid/130819/D/SER/HR www.ic-group.org Port layout at different development stages a positive decision of the responsible environmental authority in the course of the execution of the EIA is Comments, suggestions, amendments to the EIA Report expected. In the elaboration phase of the EIA Study, the Consultant consulted in a very early stage local and regional NGOs as well as the most affected inhabitants from near-by villages in the framework of several stake- Supported by Amended EIA Report delivered to the county which organises public insight and 1-month public hearing holder meetings. This open planning approach was chosen in order to enable the integration of citizens' know-how and to respect their fears and needs. European Union. Investing in future! Comments from public taken into account and final version The project is co-financed by the EU from of EIA Report drafted the European Regional Development Fund, Transport Operational Programme 2007–2013. 2nd committee meeting takes place where environmental and health protection measures are discussed – final agreement on the EIA Report reached The contents of this publication Ministry issues official decision – END OF THE EIA PROCEDURE are the responsibility of iC consulenten Ziviltechniker GesmbH. This Project is implemented by a consortium led by iC consulenten Ziviltechniker GesmbH in co-operation with the Ministry of Maritime Affairs, Transport and Infrastructure Project at a Glance CONTACTS Ministry of Maritime Affairs, Transport and Infrastructure Directorate for Transport Infrastructure 10 000 Zagreb, Krležin Gvozd 1a Overall objective Outputs Development of IWT on Master Plan for Sisak the Sava River Project objective Provision of Technical Assistance for the Master Plan of Sisak New Port Time frame Environmental Impact Assessment (EIA) Study An important part of the project work was dedicated to EIA PROCEDURE Data collection, public network impacts consultation, site visit Study. This Study is the legally prescribed procedure Ministry of Environmental where contingent impacts of the project on the environ- and Nature Protection: decision ment (including nature) are assessed and environmental on appropriate assessment protection measures, impact mitigation measures and monitoring programmes are prescribed. NO YES DRAFTING OF THE EIA REPORT and agriculture, nature, hunting, noise, population, land- (85% EU, 15% Croatia) Beneficiary Consultants iC consulenten (AT) TINA Vienna (AT) impacts on ecological network Hidrokonzalt (HR) Geokon-Zagreb (HR) End of ecological network The environmental experts of the Consultant consider compensated by a proposed set of measures. Therefore, Feasibility Study and Cost-Benefit Analysis (CBA) Environmental Impact Assessment (EIA) Draft Major Project Application for EU Funding Representation of the European Commission in the Republic of Croatia 10 000 Zagreb Ban Centre, Ulica Augusta Cesarca 4–10 T +385 1 46 81-300, F +322 2 985 796 comm-rep-zag@ec.europa.eu www.ec.europa.eu/index_hr.htm Central Finance and Contracting Agency – CFCA 10 000 Zagreb Ulica grada Vukovara 284, Object C T +385 1 45 91-245, F +385 1 45 91-075 info@safu.hr www.safu.hr Port Authority Sisak tehnicki.poslovi@luckaupravasisak.hr www.luckaupravasisak.hr Submission of the final EIA Report (=Study) to the Ministry of Environmental and Nature Protection: BEGINNING OF iC consulenten Ziviltechniker GesmbH THE ENVIRONMENTAL IMPACT ASSESSMENT PROCEDURE Technical Assistance for Master Plan of Sisak New Port 1120 Vienna, Schönbrunner Strasse 297 (November 2013) T +43 1 521 69-0, F +43 1 521 69-180 the negative environmental impact of the construction of Sisak New Port to be small which means that it can be Land Surveying Study www.mppi.hr T +385 44 524-810, F +385 44 524-809 impact assessment accidents. The Study provides a set of recommendations adverse factors. Port Infrastructure info@mppi.hr 44 000 Sisak, Rimska 28 scape as well as the impact of the project in case of and obligatory measures to avoid and/or to minimise · Preliminary Design for Budget The EIA Study assessed the impact of the project in the construction and operation phases on air, waters, soil · SWOT Analysis · Expropriation and (appropriate assessment of included in the EIA Report) · Transport Forecast · Geotechnical Study Port Authority Sisak the preparation of an Environmental Impact Assessment · Transport Analysis August 2012 – December 2013 1,435,120 EUR Screening of ecological New Port T +385 1 37 83-928, F +385 1 37 83-901 office@ic-group.org 1st committee meeting with site visit EuropeAid/130819/D/SER/HR www.ic-group.org Port layout at different development stages a positive decision of the responsible environmental authority in the course of the execution of the EIA is Comments, suggestions, amendments to the EIA Report expected. In the elaboration phase of the EIA Study, the Consultant consulted in a very early stage local and regional NGOs as well as the most affected inhabitants from near-by villages in the framework of several stake- Supported by Amended EIA Report delivered to the county which organises public insight and 1-month public hearing holder meetings. This open planning approach was chosen in order to enable the integration of citizens' know-how and to respect their fears and needs. European Union. Investing in future! Comments from public taken into account and final version The project is co-financed by the EU from of EIA Report drafted the European Regional Development Fund, Transport Operational Programme 2007–2013. 2nd committee meeting takes place where environmental and health protection measures are discussed – final agreement on the EIA Report reached The contents of this publication Ministry issues official decision – END OF THE EIA PROCEDURE are the responsibility of iC consulenten Ziviltechniker GesmbH. This Project is implemented by a consortium led by iC consulenten Ziviltechniker GesmbH in co-operation with the Ministry of Maritime Affairs, Transport and Infrastructure Project at a Glance CONTACTS Ministry of Maritime Affairs, Transport and Infrastructure Directorate for Transport Infrastructure 10 000 Zagreb, Krležin Gvozd 1a Overall objective Outputs Development of IWT on Master Plan for Sisak the Sava River Project objective Provision of Technical Assistance for the Master Plan of Sisak New Port Time frame Environmental Impact Assessment (EIA) Study An important part of the project work was dedicated to EIA PROCEDURE Data collection, public network impacts consultation, site visit Study. This Study is the legally prescribed procedure Ministry of Environmental where contingent impacts of the project on the environ- and Nature Protection: decision ment (including nature) are assessed and environmental on appropriate assessment protection measures, impact mitigation measures and monitoring programmes are prescribed. NO YES DRAFTING OF THE EIA REPORT and agriculture, nature, hunting, noise, population, land- (85% EU, 15% Croatia) Beneficiary Consultants iC consulenten (AT) TINA Vienna (AT) impacts on ecological network Hidrokonzalt (HR) Geokon-Zagreb (HR) End of ecological network The environmental experts of the Consultant consider compensated by a proposed set of measures. Therefore, Feasibility Study and Cost-Benefit Analysis (CBA) Environmental Impact Assessment (EIA) Draft Major Project Application for EU Funding Representation of the European Commission in the Republic of Croatia 10 000 Zagreb Ban Centre, Ulica Augusta Cesarca 4–10 T +385 1 46 81-300, F +322 2 985 796 comm-rep-zag@ec.europa.eu www.ec.europa.eu/index_hr.htm Central Finance and Contracting Agency – CFCA 10 000 Zagreb Ulica grada Vukovara 284, Object C T +385 1 45 91-245, F +385 1 45 91-075 info@safu.hr www.safu.hr Port Authority Sisak tehnicki.poslovi@luckaupravasisak.hr www.luckaupravasisak.hr Submission of the final EIA Report (=Study) to the Ministry of Environmental and Nature Protection: BEGINNING OF iC consulenten Ziviltechniker GesmbH THE ENVIRONMENTAL IMPACT ASSESSMENT PROCEDURE Technical Assistance for Master Plan of Sisak New Port 1120 Vienna, Schönbrunner Strasse 297 (November 2013) T +43 1 521 69-0, F +43 1 521 69-180 the negative environmental impact of the construction of Sisak New Port to be small which means that it can be Land Surveying Study www.mppi.hr T +385 44 524-810, F +385 44 524-809 impact assessment accidents. The Study provides a set of recommendations adverse factors. Port Infrastructure info@mppi.hr 44 000 Sisak, Rimska 28 scape as well as the impact of the project in case of and obligatory measures to avoid and/or to minimise · Preliminary Design for Budget The EIA Study assessed the impact of the project in the construction and operation phases on air, waters, soil · SWOT Analysis · Expropriation and (appropriate assessment of included in the EIA Report) · Transport Forecast · Geotechnical Study Port Authority Sisak the preparation of an Environmental Impact Assessment · Transport Analysis August 2012 – December 2013 1,435,120 EUR Screening of ecological New Port T +385 1 37 83-928, F +385 1 37 83-901 office@ic-group.org 1st committee meeting with site visit EuropeAid/130819/D/SER/HR www.ic-group.org Port layout at different development stages a positive decision of the responsible environmental authority in the course of the execution of the EIA is Comments, suggestions, amendments to the EIA Report expected. In the elaboration phase of the EIA Study, the Consultant consulted in a very early stage local and regional NGOs as well as the most affected inhabitants from near-by villages in the framework of several stake- Supported by Amended EIA Report delivered to the county which organises public insight and 1-month public hearing holder meetings. This open planning approach was chosen in order to enable the integration of citizens' know-how and to respect their fears and needs. European Union. Investing in future! Comments from public taken into account and final version The project is co-financed by the EU from of EIA Report drafted the European Regional Development Fund, Transport Operational Programme 2007–2013. 2nd committee meeting takes place where environmental and health protection measures are discussed – final agreement on the EIA Report reached The contents of this publication Ministry issues official decision – END OF THE EIA PROCEDURE are the responsibility of iC consulenten Ziviltechniker GesmbH. This Project is implemented by a consortium led by iC consulenten Ziviltechniker GesmbH in co-operation with the Ministry of Maritime Affairs, Transport and Infrastructure Sisak New Port – Important Element of Croatian Waterway Transport Policy Port Engineering Appropriate infrastructure and a well-developed transport INTEGRATED PROJECT APPROACH system are essential prerequisites for a sustainable economic development. Therefore, the Republic of Croatia puts significant efforts into the improvement of the transport system based on national priorities and as part of the European transport networks. The promotion of river transportation is a core element of the Croatian transport strategy. Within the work of the International Sava River Basin Commission (ISRBC) a comprehensive plan for the rehabilitation of the Sava waterway was elaborated. The rehabilitation of the Sava River with guaranteed minimum fairway depths is an important prerequisite for a successful investment into Sisak New Port. Sisak New Port will function as: the entire area adjoining to the Sava River) was split into three time phases (2020, it was necessary to provide pertinent geo- database and carried out interviews with · Hub for waterborne transport 2025 and 2035). Each development phase technical designs of deep foundations, soil stakeholders of the regional manufactur- foresees an enlargement of dedicated port consolidation and improvements as well as ing industry and relevant transport and infrastructure as well as port superstruc- for the protection of building pits. logistics companies. This consolidated car- chains in the Greater Zagreb region & Sisak – Moslavina county · Logistics centre for local & regional industrial production & trade · Catalyst for (re-)industrialisation in a region with structural economic problems & high unemployment Ljubljana · Dynamic port development concept Corridor X (Road) Corridor X (Rail) Zagreb Brezice Rijeka (Port) SAVA RIVER Corridor Vb (Road) Corridor Vb (Rail) Sisak addressing infrastructure needs and financing possibilities (smart staging Samac Sr. Mitrovica Slovanski Bosanski Brod Brod Brcko Sabac DANUBE RIVER Belgrade Banja Luka Sarajevo Split Maritime corridor Corridor Vc (Road) Corridor Vc (Rail) Source: ISRBC Maritime corridor Ploce (Port) Maritime corridor Future port area of Sisak Constanta (Port) Maritime corridor to UNECE waterway class Vb (BelgradeBrcko) and IV (up to Sisak) and a guaranteed minimum fairway depth are conditio sine-qua-non for all development phases. Cost-effective navigation was assumed to be possible on the Sava River as of 2018. With a planned port throughput of stakeholders including NGOs DANUBE RIVER ture. The rehabilitation of the Sava River and phasing) · Cost-effective state of technology solutions · Highest environmental respect 435,000 tons of dry cargo for 2020 (main scenario) the construction of two berths is foreseen. The increase of cargo up to 609,000 tons by 2025 will require two more berths for optimal port opera- the impact of changes of the river channel three scenarios (low, main and high) representing different economic develop- tion measures. The calculations of water ment paths. The Study yielded economic- levels and flow velocities showed the ally sound transhipment volumes for the highest increase of water levels of new port in all scenarios: For 2035 as 800 +0.02 m/s on the upstream section and target year, they stretch from more than the highest increase of flow velocities 600,000 tons p. a. (low scenario) to on the downstream section of +0.10 m/s. Therefore, the construction of retention 600 The operating costs (OPEX) were broken down into three cate- Operating revenues (REVIN) amount to a total of approx. 147 gories: labour costs, public utilities costs (electricity, gas, water, million EUR of which: real estate revenues 103 million EUR, drainage, sewage), miscellaneous costs (including the maintenance equipment rental revenues 31 million EUR, port dues to cargo of infrastructure as well of superstructure). The operating ex- and ships revenues 12 million EUR, port revenues related to penses amount to approx. 22 million EUR of which the largest administrative operations 1.5 million EUR. part (62.9%) are miscellaneous costs, followed by labour costs (35%) and public utilities costs (2.1%). 400 200 FINANCIAL ANALYSIS ECONOMIC ANALYSIS RISK ANALYSIS The project requires an EU grant since The economic performance indicators Results are quite robust and therefore the results show a negative financial net (EIRR-economic Net Present Value, Eco- the project is considered to have an 1,100,000 p. a. (main scenario) to nearly present value – FNPV (C) and a financial nomic Internal rate of return – EIRR and acceptable level of risk due to low values 2,000,000 tons p. a. (high scenario). rate of return – FRR (C) below the bench- benefits to cost – B/C ratio) were calculat- of standard deviation. basins as compensation storage is suggest- marked nominal Financial Discount Rate – ed. The results show that the project is ed as the most favourable measure from FDR. The financial performance indicators feasible since economic performance The preliminary technical solution which technical, hydrological and ecological as regards national contribution (FRR(K) indicators show very good positive was based on a selection of three port aspects. >0, FNPV(K) <0) shows normal results for results (EIRR>social discount rate – SDR, a major public infrastructure project. ENPV is positive and amounts to approx. tions which allow further specialisation by cargo type. For the third phase with assumed 717,000 tons of dry cargo and 389,000 tons of liquid cargo the construction of an additional basin for liquid cargo with two berths is planned. port authority, customs and workshops. Agricultural products for Environment & Waterway well as all necessary internal transport Development in the Danube River infrastructure inlcuding railway lines with Coal Hydraulic modelling of port entrance – reduced flow velocity The port infrastructure planning for Sisak New Port was based on comprehensive 68 75 79 5 6 6 154 200 222 234 83 113 125 132 Food products 0 0 0 0 Textiles and products 0 0 0 0 21 28 31 33 7 10 11 12 90 139 156 164 104 136 151 159 8 13 14 15 Basic metals and products 94 136 152 160 Machinery and equipment 0 0 0 0 Transport and equipment 0 0 0 0 Other manufactured goods 0 0 0 0 60 79 88 92 collection of relevant geological, geotech- Refined petroleum products nical and seismological data. These data Fertilisers provided the input for drafting the prelim- Other chemical products inary technical solution and for executing Other non-metallic mineral pr. the Environmental Impact Assessment layers and on the ground water level were gained. Current speed [m/s] above 0.375 0.35–0.375 0.325–0.35 0.3–0.325 0.275–0.3 0.25–0.275 0.225–0.25 0.2–0.225 0.175–0.2 0.15–0.175 0.125–0.15 0.1–0.125 0.075–0.1 0.05–0.075 0.025–0.05 below 0.025 undefined value Sec. raw mat., scrap Other goods Total SENSITIVITY ANALYSIS Results indicate that operating revenues, CAPEX (capital investment) as well as cargo traffic flows are critical variables since the variation of FNPV/ENPV is bigger than +/-1%. society. 4 Policies 2035 the project is clearly beneficial for the 51 Wood and products 2030 MAIN SCENARIO 2035 geotechnical analyses which led to the 2025 110 million EUR; the B/C ratio is 2.3), and 2030 ment in line with EU Regional geometry and existence of characteristic 2020 2025 Metal ores & mineral products parking. the composition of the ground surface, the 2015 2020 Crude oil shunting station, internal roads and car on site and in laboratory, detailed data on 2010 Main scenario up to 2035 [‘000 tons] trative facilities including buildings for the Study. With the geotechnical investigations 0 TRANSPORT FORECAST FOR SISAK NEW PORT layout variants also foresees all adminis- sewage, electricity, etc. were defined as EU initiatives and projects upgrade 1.000 for flood protection and flood risk mitiga- intentions of the “Joint Statement · Interaction with related national & preparation (29%) and miscellaneous costs (20%). Sava waterway 1.200 The hydraulic study also provided results Up & downstream part of strategic regional develop- EUR of which 44% belong to infrastructure costs, followed by site 2018: tiated by commodities and elaborated in utilities such as communication, water, · Port development as integrated tingency costs). The CAPEX costs amount to approx. 128 million 2030 & 2035. All forecasts were differen- operations entering and leaving the port. Corridors and the layout of all relevant Basin” buildings, safety and security devices, planning and other con- 1.400 volumes were forecasted for 2020, 2025, contributed to ensure save nautical structure costs, miscellaneous costs (including facility services, 1.600 In a next step, the future transhipment served the environmental analysis and installations), transhipment facilities and equipment/super- Low scenario elaborated for 2015, 2025 and 2035. port development phase. This study aration, infrastructure costs (road, railway, waterway, outdoor Main scenario 1.800 this analysis the transport forecast was on the existing flow conditions in each They were divided into 4 categories: costs related to site prep- High scenario to transport on the Sava River. From COMMODITIES · Planning process based on the the project’s engineering design and associated cost estimates. national and international cargoes affine ling study was executed which assessed Investment costs/capital expenditures (CAPEX) are derived from 2.000 level to obtain a consistent transport flow go database includes the flows of existing In addition, a special 2-D hydraulic model- Cost and Benefit Analysis Forecast of Sisak New Port transhipment volume [‘000 tons] infrastructure build-up of Sisak New Port communities and other relevant Corridor Vb (Rail) borehole samples (drilling core) sources on the national and international seen site are rather unfavourable (like in and regional authorities, business Corridor Xb (Road) The Consultant analysed all statistical As the geotechnical conditions of the fore- activities and the transport demand, the · Close interaction with municipal RHINE – MAIN – DANUBE On-site investigations and In relation to the growth of economic Applied planning principles: Sava waterway within the transport network Transport and Market Study 8 10 11 12 685 936 1,043 1,100 Nominal costs in EUR PHASE I | 2020 PHASE II | 2025 PHASE III | 2035 TOTAL % TOTAL Capital investment A. Construction site preparation 11,148,317 9,661,874.30 16,350,864 37,161,055 29% B. Infrastructure costs 33,265,551 12,404,104 10,712,635 56,382,290 44% C. Transhipment facilities costs 6,368,636 2,601,274 0 8,969,910 7% D. Miscellaneous costs 14,864,422 5,381,946 5,381,946 25,628,314 20% Total (EUR) 65,646,926 30,049,198 32,445,445 128,141,569 100% Operating expenses 2,341,838 2,888,267 2,576,022 7,806,128 35% B. Public utilities costs A. Labour costs 126,008 154,009 186,678 466,695 2% C. Miscellaneous costs 6,446,960 3,924,236 3,643,934 14,015,130 63% Total (EUR) 8,914,806 6,966,513 6,406,634 22,287,953 100% ERDF/CF contribution 21,934,390 EIB loan 60,207,177 National contribution Total (EUR) 46,000,000 128,141,567 Sisak New Port – Important Element of Croatian Waterway Transport Policy Port Engineering Appropriate infrastructure and a well-developed transport INTEGRATED PROJECT APPROACH system are essential prerequisites for a sustainable economic development. Therefore, the Republic of Croatia puts significant efforts into the improvement of the transport system based on national priorities and as part of the European transport networks. The promotion of river transportation is a core element of the Croatian transport strategy. Within the work of the International Sava River Basin Commission (ISRBC) a comprehensive plan for the rehabilitation of the Sava waterway was elaborated. The rehabilitation of the Sava River with guaranteed minimum fairway depths is an important prerequisite for a successful investment into Sisak New Port. Sisak New Port will function as: the entire area adjoining to the Sava River) was split into three time phases (2020, it was necessary to provide pertinent geo- database and carried out interviews with · Hub for waterborne transport 2025 and 2035). Each development phase technical designs of deep foundations, soil stakeholders of the regional manufactur- foresees an enlargement of dedicated port consolidation and improvements as well as ing industry and relevant transport and infrastructure as well as port superstruc- for the protection of building pits. logistics companies. This consolidated car- chains in the Greater Zagreb region & Sisak – Moslavina county · Logistics centre for local & regional industrial production & trade · Catalyst for (re-)industrialisation in a region with structural economic problems & high unemployment Ljubljana · Dynamic port development concept Corridor X (Road) Corridor X (Rail) Zagreb Brezice Rijeka (Port) SAVA RIVER Corridor Vb (Road) Corridor Vb (Rail) Sisak addressing infrastructure needs and financing possibilities (smart staging Samac Sr. Mitrovica Slovanski Bosanski Brod Brod Brcko Sabac DANUBE RIVER Belgrade Banja Luka Sarajevo Split Maritime corridor Corridor Vc (Road) Corridor Vc (Rail) Source: ISRBC Maritime corridor Ploce (Port) Maritime corridor Future port area of Sisak Constanta (Port) Maritime corridor to UNECE waterway class Vb (BelgradeBrcko) and IV (up to Sisak) and a guaranteed minimum fairway depth are conditio sine-qua-non for all development phases. Cost-effective navigation was assumed to be possible on the Sava River as of 2018. With a planned port throughput of stakeholders including NGOs DANUBE RIVER ture. The rehabilitation of the Sava River and phasing) · Cost-effective state of technology solutions · Highest environmental respect 435,000 tons of dry cargo for 2020 (main scenario) the construction of two berths is foreseen. The increase of cargo up to 609,000 tons by 2025 will require two more berths for optimal port opera- the impact of changes of the river channel three scenarios (low, main and high) representing different economic develop- tion measures. The calculations of water ment paths. The Study yielded economic- levels and flow velocities showed the ally sound transhipment volumes for the highest increase of water levels of new port in all scenarios: For 2035 as 800 +0.02 m/s on the upstream section and target year, they stretch from more than the highest increase of flow velocities 600,000 tons p. a. (low scenario) to on the downstream section of +0.10 m/s. Therefore, the construction of retention 600 The operating costs (OPEX) were broken down into three cate- Operating revenues (REVIN) amount to a total of approx. 147 gories: labour costs, public utilities costs (electricity, gas, water, million EUR of which: real estate revenues 103 million EUR, drainage, sewage), miscellaneous costs (including the maintenance equipment rental revenues 31 million EUR, port dues to cargo of infrastructure as well of superstructure). The operating ex- and ships revenues 12 million EUR, port revenues related to penses amount to approx. 22 million EUR of which the largest administrative operations 1.5 million EUR. part (62.9%) are miscellaneous costs, followed by labour costs (35%) and public utilities costs (2.1%). 400 200 FINANCIAL ANALYSIS ECONOMIC ANALYSIS RISK ANALYSIS The project requires an EU grant since The economic performance indicators Results are quite robust and therefore the results show a negative financial net (EIRR-economic Net Present Value, Eco- the project is considered to have an 1,100,000 p. a. (main scenario) to nearly present value – FNPV (C) and a financial nomic Internal rate of return – EIRR and acceptable level of risk due to low values 2,000,000 tons p. a. (high scenario). rate of return – FRR (C) below the bench- benefits to cost – B/C ratio) were calculat- of standard deviation. basins as compensation storage is suggest- marked nominal Financial Discount Rate – ed. The results show that the project is ed as the most favourable measure from FDR. The financial performance indicators feasible since economic performance The preliminary technical solution which technical, hydrological and ecological as regards national contribution (FRR(K) indicators show very good positive was based on a selection of three port aspects. >0, FNPV(K) <0) shows normal results for results (EIRR>social discount rate – SDR, a major public infrastructure project. ENPV is positive and amounts to approx. tions which allow further specialisation by cargo type. For the third phase with assumed 717,000 tons of dry cargo and 389,000 tons of liquid cargo the construction of an additional basin for liquid cargo with two berths is planned. port authority, customs and workshops. Agricultural products for Environment & Waterway well as all necessary internal transport Development in the Danube River infrastructure inlcuding railway lines with Coal Hydraulic modelling of port entrance – reduced flow velocity The port infrastructure planning for Sisak New Port was based on comprehensive 68 75 79 5 6 6 154 200 222 234 83 113 125 132 Food products 0 0 0 0 Textiles and products 0 0 0 0 21 28 31 33 7 10 11 12 90 139 156 164 104 136 151 159 8 13 14 15 Basic metals and products 94 136 152 160 Machinery and equipment 0 0 0 0 Transport and equipment 0 0 0 0 Other manufactured goods 0 0 0 0 60 79 88 92 collection of relevant geological, geotech- Refined petroleum products nical and seismological data. These data Fertilisers provided the input for drafting the prelim- Other chemical products inary technical solution and for executing Other non-metallic mineral pr. the Environmental Impact Assessment layers and on the ground water level were gained. Current speed [m/s] above 0.375 0.35–0.375 0.325–0.35 0.3–0.325 0.275–0.3 0.25–0.275 0.225–0.25 0.2–0.225 0.175–0.2 0.15–0.175 0.125–0.15 0.1–0.125 0.075–0.1 0.05–0.075 0.025–0.05 below 0.025 undefined value Sec. raw mat., scrap Other goods Total SENSITIVITY ANALYSIS Results indicate that operating revenues, CAPEX (capital investment) as well as cargo traffic flows are critical variables since the variation of FNPV/ENPV is bigger than +/-1%. society. 4 Policies 2035 the project is clearly beneficial for the 51 Wood and products 2030 MAIN SCENARIO 2035 geotechnical analyses which led to the 2025 110 million EUR; the B/C ratio is 2.3), and 2030 ment in line with EU Regional geometry and existence of characteristic 2020 2025 Metal ores & mineral products parking. the composition of the ground surface, the 2015 2020 Crude oil shunting station, internal roads and car on site and in laboratory, detailed data on 2010 Main scenario up to 2035 [‘000 tons] trative facilities including buildings for the Study. With the geotechnical investigations 0 TRANSPORT FORECAST FOR SISAK NEW PORT layout variants also foresees all adminis- sewage, electricity, etc. were defined as EU initiatives and projects upgrade 1.000 for flood protection and flood risk mitiga- intentions of the “Joint Statement · Interaction with related national & preparation (29%) and miscellaneous costs (20%). Sava waterway 1.200 The hydraulic study also provided results Up & downstream part of strategic regional develop- EUR of which 44% belong to infrastructure costs, followed by site 2018: tiated by commodities and elaborated in utilities such as communication, water, · Port development as integrated tingency costs). The CAPEX costs amount to approx. 128 million 2030 & 2035. All forecasts were differen- operations entering and leaving the port. Corridors and the layout of all relevant Basin” buildings, safety and security devices, planning and other con- 1.400 volumes were forecasted for 2020, 2025, contributed to ensure save nautical structure costs, miscellaneous costs (including facility services, 1.600 In a next step, the future transhipment served the environmental analysis and installations), transhipment facilities and equipment/super- Low scenario elaborated for 2015, 2025 and 2035. port development phase. This study aration, infrastructure costs (road, railway, waterway, outdoor Main scenario 1.800 this analysis the transport forecast was on the existing flow conditions in each They were divided into 4 categories: costs related to site prep- High scenario to transport on the Sava River. From COMMODITIES · Planning process based on the the project’s engineering design and associated cost estimates. national and international cargoes affine ling study was executed which assessed Investment costs/capital expenditures (CAPEX) are derived from 2.000 level to obtain a consistent transport flow go database includes the flows of existing In addition, a special 2-D hydraulic model- Cost and Benefit Analysis Forecast of Sisak New Port transhipment volume [‘000 tons] infrastructure build-up of Sisak New Port communities and other relevant Corridor Vb (Rail) borehole samples (drilling core) sources on the national and international seen site are rather unfavourable (like in and regional authorities, business Corridor Xb (Road) The Consultant analysed all statistical As the geotechnical conditions of the fore- activities and the transport demand, the · Close interaction with municipal RHINE – MAIN – DANUBE On-site investigations and In relation to the growth of economic Applied planning principles: Sava waterway within the transport network Transport and Market Study 8 10 11 12 685 936 1,043 1,100 Nominal costs in EUR PHASE I | 2020 PHASE II | 2025 PHASE III | 2035 TOTAL % TOTAL Capital investment A. Construction site preparation 11,148,317 9,661,874.30 16,350,864 37,161,055 29% B. Infrastructure costs 33,265,551 12,404,104 10,712,635 56,382,290 44% C. Transhipment facilities costs 6,368,636 2,601,274 0 8,969,910 7% D. Miscellaneous costs 14,864,422 5,381,946 5,381,946 25,628,314 20% Total (EUR) 65,646,926 30,049,198 32,445,445 128,141,569 100% Operating expenses 2,341,838 2,888,267 2,576,022 7,806,128 35% B. Public utilities costs A. Labour costs 126,008 154,009 186,678 466,695 2% C. Miscellaneous costs 6,446,960 3,924,236 3,643,934 14,015,130 63% Total (EUR) 8,914,806 6,966,513 6,406,634 22,287,953 100% ERDF/CF contribution 21,934,390 EIB loan 60,207,177 National contribution Total (EUR) 46,000,000 128,141,567 Sisak New Port – Important Element of Croatian Waterway Transport Policy Port Engineering Appropriate infrastructure and a well-developed transport INTEGRATED PROJECT APPROACH system are essential prerequisites for a sustainable economic development. Therefore, the Republic of Croatia puts significant efforts into the improvement of the transport system based on national priorities and as part of the European transport networks. The promotion of river transportation is a core element of the Croatian transport strategy. Within the work of the International Sava River Basin Commission (ISRBC) a comprehensive plan for the rehabilitation of the Sava waterway was elaborated. The rehabilitation of the Sava River with guaranteed minimum fairway depths is an important prerequisite for a successful investment into Sisak New Port. Sisak New Port will function as: the entire area adjoining to the Sava River) was split into three time phases (2020, it was necessary to provide pertinent geo- database and carried out interviews with · Hub for waterborne transport 2025 and 2035). Each development phase technical designs of deep foundations, soil stakeholders of the regional manufactur- foresees an enlargement of dedicated port consolidation and improvements as well as ing industry and relevant transport and infrastructure as well as port superstruc- for the protection of building pits. logistics companies. This consolidated car- chains in the Greater Zagreb region & Sisak – Moslavina county · Logistics centre for local & regional industrial production & trade · Catalyst for (re-)industrialisation in a region with structural economic problems & high unemployment Ljubljana · Dynamic port development concept Corridor X (Road) Corridor X (Rail) Zagreb Brezice Rijeka (Port) SAVA RIVER Corridor Vb (Road) Corridor Vb (Rail) Sisak addressing infrastructure needs and financing possibilities (smart staging Samac Sr. Mitrovica Slovanski Bosanski Brod Brod Brcko Sabac DANUBE RIVER Belgrade Banja Luka Sarajevo Split Maritime corridor Corridor Vc (Road) Corridor Vc (Rail) Source: ISRBC Maritime corridor Ploce (Port) Maritime corridor Future port area of Sisak Constanta (Port) Maritime corridor to UNECE waterway class Vb (BelgradeBrcko) and IV (up to Sisak) and a guaranteed minimum fairway depth are conditio sine-qua-non for all development phases. Cost-effective navigation was assumed to be possible on the Sava River as of 2018. With a planned port throughput of stakeholders including NGOs DANUBE RIVER ture. The rehabilitation of the Sava River and phasing) · Cost-effective state of technology solutions · Highest environmental respect 435,000 tons of dry cargo for 2020 (main scenario) the construction of two berths is foreseen. The increase of cargo up to 609,000 tons by 2025 will require two more berths for optimal port opera- the impact of changes of the river channel three scenarios (low, main and high) representing different economic develop- tion measures. The calculations of water ment paths. The Study yielded economic- levels and flow velocities showed the ally sound transhipment volumes for the highest increase of water levels of new port in all scenarios: For 2035 as 800 +0.02 m/s on the upstream section and target year, they stretch from more than the highest increase of flow velocities 600,000 tons p. a. (low scenario) to on the downstream section of +0.10 m/s. Therefore, the construction of retention 600 The operating costs (OPEX) were broken down into three cate- Operating revenues (REVIN) amount to a total of approx. 147 gories: labour costs, public utilities costs (electricity, gas, water, million EUR of which: real estate revenues 103 million EUR, drainage, sewage), miscellaneous costs (including the maintenance equipment rental revenues 31 million EUR, port dues to cargo of infrastructure as well of superstructure). The operating ex- and ships revenues 12 million EUR, port revenues related to penses amount to approx. 22 million EUR of which the largest administrative operations 1.5 million EUR. part (62.9%) are miscellaneous costs, followed by labour costs (35%) and public utilities costs (2.1%). 400 200 FINANCIAL ANALYSIS ECONOMIC ANALYSIS RISK ANALYSIS The project requires an EU grant since The economic performance indicators Results are quite robust and therefore the results show a negative financial net (EIRR-economic Net Present Value, Eco- the project is considered to have an 1,100,000 p. a. (main scenario) to nearly present value – FNPV (C) and a financial nomic Internal rate of return – EIRR and acceptable level of risk due to low values 2,000,000 tons p. a. (high scenario). rate of return – FRR (C) below the bench- benefits to cost – B/C ratio) were calculat- of standard deviation. basins as compensation storage is suggest- marked nominal Financial Discount Rate – ed. The results show that the project is ed as the most favourable measure from FDR. The financial performance indicators feasible since economic performance The preliminary technical solution which technical, hydrological and ecological as regards national contribution (FRR(K) indicators show very good positive was based on a selection of three port aspects. >0, FNPV(K) <0) shows normal results for results (EIRR>social discount rate – SDR, a major public infrastructure project. ENPV is positive and amounts to approx. tions which allow further specialisation by cargo type. For the third phase with assumed 717,000 tons of dry cargo and 389,000 tons of liquid cargo the construction of an additional basin for liquid cargo with two berths is planned. port authority, customs and workshops. Agricultural products for Environment & Waterway well as all necessary internal transport Development in the Danube River infrastructure inlcuding railway lines with Coal Hydraulic modelling of port entrance – reduced flow velocity The port infrastructure planning for Sisak New Port was based on comprehensive 68 75 79 5 6 6 154 200 222 234 83 113 125 132 Food products 0 0 0 0 Textiles and products 0 0 0 0 21 28 31 33 7 10 11 12 90 139 156 164 104 136 151 159 8 13 14 15 Basic metals and products 94 136 152 160 Machinery and equipment 0 0 0 0 Transport and equipment 0 0 0 0 Other manufactured goods 0 0 0 0 60 79 88 92 collection of relevant geological, geotech- Refined petroleum products nical and seismological data. These data Fertilisers provided the input for drafting the prelim- Other chemical products inary technical solution and for executing Other non-metallic mineral pr. the Environmental Impact Assessment layers and on the ground water level were gained. Current speed [m/s] above 0.375 0.35–0.375 0.325–0.35 0.3–0.325 0.275–0.3 0.25–0.275 0.225–0.25 0.2–0.225 0.175–0.2 0.15–0.175 0.125–0.15 0.1–0.125 0.075–0.1 0.05–0.075 0.025–0.05 below 0.025 undefined value Sec. raw mat., scrap Other goods Total SENSITIVITY ANALYSIS Results indicate that operating revenues, CAPEX (capital investment) as well as cargo traffic flows are critical variables since the variation of FNPV/ENPV is bigger than +/-1%. society. 4 Policies 2035 the project is clearly beneficial for the 51 Wood and products 2030 MAIN SCENARIO 2035 geotechnical analyses which led to the 2025 110 million EUR; the B/C ratio is 2.3), and 2030 ment in line with EU Regional geometry and existence of characteristic 2020 2025 Metal ores & mineral products parking. the composition of the ground surface, the 2015 2020 Crude oil shunting station, internal roads and car on site and in laboratory, detailed data on 2010 Main scenario up to 2035 [‘000 tons] trative facilities including buildings for the Study. With the geotechnical investigations 0 TRANSPORT FORECAST FOR SISAK NEW PORT layout variants also foresees all adminis- sewage, electricity, etc. were defined as EU initiatives and projects upgrade 1.000 for flood protection and flood risk mitiga- intentions of the “Joint Statement · Interaction with related national & preparation (29%) and miscellaneous costs (20%). Sava waterway 1.200 The hydraulic study also provided results Up & downstream part of strategic regional develop- EUR of which 44% belong to infrastructure costs, followed by site 2018: tiated by commodities and elaborated in utilities such as communication, water, · Port development as integrated tingency costs). The CAPEX costs amount to approx. 128 million 2030 & 2035. All forecasts were differen- operations entering and leaving the port. Corridors and the layout of all relevant Basin” buildings, safety and security devices, planning and other con- 1.400 volumes were forecasted for 2020, 2025, contributed to ensure save nautical structure costs, miscellaneous costs (including facility services, 1.600 In a next step, the future transhipment served the environmental analysis and installations), transhipment facilities and equipment/super- Low scenario elaborated for 2015, 2025 and 2035. port development phase. This study aration, infrastructure costs (road, railway, waterway, outdoor Main scenario 1.800 this analysis the transport forecast was on the existing flow conditions in each They were divided into 4 categories: costs related to site prep- High scenario to transport on the Sava River. From COMMODITIES · Planning process based on the the project’s engineering design and associated cost estimates. national and international cargoes affine ling study was executed which assessed Investment costs/capital expenditures (CAPEX) are derived from 2.000 level to obtain a consistent transport flow go database includes the flows of existing In addition, a special 2-D hydraulic model- Cost and Benefit Analysis Forecast of Sisak New Port transhipment volume [‘000 tons] infrastructure build-up of Sisak New Port communities and other relevant Corridor Vb (Rail) borehole samples (drilling core) sources on the national and international seen site are rather unfavourable (like in and regional authorities, business Corridor Xb (Road) The Consultant analysed all statistical As the geotechnical conditions of the fore- activities and the transport demand, the · Close interaction with municipal RHINE – MAIN – DANUBE On-site investigations and In relation to the growth of economic Applied planning principles: Sava waterway within the transport network Transport and Market Study 8 10 11 12 685 936 1,043 1,100 Nominal costs in EUR PHASE I | 2020 PHASE II | 2025 PHASE III | 2035 TOTAL % TOTAL Capital investment A. Construction site preparation 11,148,317 9,661,874.30 16,350,864 37,161,055 29% B. Infrastructure costs 33,265,551 12,404,104 10,712,635 56,382,290 44% C. Transhipment facilities costs 6,368,636 2,601,274 0 8,969,910 7% D. Miscellaneous costs 14,864,422 5,381,946 5,381,946 25,628,314 20% Total (EUR) 65,646,926 30,049,198 32,445,445 128,141,569 100% Operating expenses 2,341,838 2,888,267 2,576,022 7,806,128 35% B. Public utilities costs A. Labour costs 126,008 154,009 186,678 466,695 2% C. Miscellaneous costs 6,446,960 3,924,236 3,643,934 14,015,130 63% Total (EUR) 8,914,806 6,966,513 6,406,634 22,287,953 100% ERDF/CF contribution 21,934,390 EIB loan 60,207,177 National contribution Total (EUR) 46,000,000 128,141,567 Sisak New Port – Important Element of Croatian Waterway Transport Policy Port Engineering Appropriate infrastructure and a well-developed transport INTEGRATED PROJECT APPROACH system are essential prerequisites for a sustainable economic development. Therefore, the Republic of Croatia puts significant efforts into the improvement of the transport system based on national priorities and as part of the European transport networks. The promotion of river transportation is a core element of the Croatian transport strategy. Within the work of the International Sava River Basin Commission (ISRBC) a comprehensive plan for the rehabilitation of the Sava waterway was elaborated. The rehabilitation of the Sava River with guaranteed minimum fairway depths is an important prerequisite for a successful investment into Sisak New Port. Sisak New Port will function as: the entire area adjoining to the Sava River) was split into three time phases (2020, it was necessary to provide pertinent geo- database and carried out interviews with · Hub for waterborne transport 2025 and 2035). Each development phase technical designs of deep foundations, soil stakeholders of the regional manufactur- foresees an enlargement of dedicated port consolidation and improvements as well as ing industry and relevant transport and infrastructure as well as port superstruc- for the protection of building pits. logistics companies. This consolidated car- chains in the Greater Zagreb region & Sisak – Moslavina county · Logistics centre for local & regional industrial production & trade · Catalyst for (re-)industrialisation in a region with structural economic problems & high unemployment Ljubljana · Dynamic port development concept Corridor X (Road) Corridor X (Rail) Zagreb Brezice Rijeka (Port) SAVA RIVER Corridor Vb (Road) Corridor Vb (Rail) Sisak addressing infrastructure needs and financing possibilities (smart staging Samac Sr. Mitrovica Slovanski Bosanski Brod Brod Brcko Sabac DANUBE RIVER Belgrade Banja Luka Sarajevo Split Maritime corridor Corridor Vc (Road) Corridor Vc (Rail) Source: ISRBC Maritime corridor Ploce (Port) Maritime corridor Future port area of Sisak Constanta (Port) Maritime corridor to UNECE waterway class Vb (BelgradeBrcko) and IV (up to Sisak) and a guaranteed minimum fairway depth are conditio sine-qua-non for all development phases. Cost-effective navigation was assumed to be possible on the Sava River as of 2018. With a planned port throughput of stakeholders including NGOs DANUBE RIVER ture. The rehabilitation of the Sava River and phasing) · Cost-effective state of technology solutions · Highest environmental respect 435,000 tons of dry cargo for 2020 (main scenario) the construction of two berths is foreseen. The increase of cargo up to 609,000 tons by 2025 will require two more berths for optimal port opera- the impact of changes of the river channel three scenarios (low, main and high) representing different economic develop- tion measures. The calculations of water ment paths. The Study yielded economic- levels and flow velocities showed the ally sound transhipment volumes for the highest increase of water levels of new port in all scenarios: For 2035 as 800 +0.02 m/s on the upstream section and target year, they stretch from more than the highest increase of flow velocities 600,000 tons p. a. (low scenario) to on the downstream section of +0.10 m/s. Therefore, the construction of retention 600 The operating costs (OPEX) were broken down into three cate- Operating revenues (REVIN) amount to a total of approx. 147 gories: labour costs, public utilities costs (electricity, gas, water, million EUR of which: real estate revenues 103 million EUR, drainage, sewage), miscellaneous costs (including the maintenance equipment rental revenues 31 million EUR, port dues to cargo of infrastructure as well of superstructure). The operating ex- and ships revenues 12 million EUR, port revenues related to penses amount to approx. 22 million EUR of which the largest administrative operations 1.5 million EUR. part (62.9%) are miscellaneous costs, followed by labour costs (35%) and public utilities costs (2.1%). 400 200 FINANCIAL ANALYSIS ECONOMIC ANALYSIS RISK ANALYSIS The project requires an EU grant since The economic performance indicators Results are quite robust and therefore the results show a negative financial net (EIRR-economic Net Present Value, Eco- the project is considered to have an 1,100,000 p. a. (main scenario) to nearly present value – FNPV (C) and a financial nomic Internal rate of return – EIRR and acceptable level of risk due to low values 2,000,000 tons p. a. (high scenario). rate of return – FRR (C) below the bench- benefits to cost – B/C ratio) were calculat- of standard deviation. basins as compensation storage is suggest- marked nominal Financial Discount Rate – ed. The results show that the project is ed as the most favourable measure from FDR. The financial performance indicators feasible since economic performance The preliminary technical solution which technical, hydrological and ecological as regards national contribution (FRR(K) indicators show very good positive was based on a selection of three port aspects. >0, FNPV(K) <0) shows normal results for results (EIRR>social discount rate – SDR, a major public infrastructure project. ENPV is positive and amounts to approx. tions which allow further specialisation by cargo type. For the third phase with assumed 717,000 tons of dry cargo and 389,000 tons of liquid cargo the construction of an additional basin for liquid cargo with two berths is planned. port authority, customs and workshops. Agricultural products for Environment & Waterway well as all necessary internal transport Development in the Danube River infrastructure inlcuding railway lines with Coal Hydraulic modelling of port entrance – reduced flow velocity The port infrastructure planning for Sisak New Port was based on comprehensive 68 75 79 5 6 6 154 200 222 234 83 113 125 132 Food products 0 0 0 0 Textiles and products 0 0 0 0 21 28 31 33 7 10 11 12 90 139 156 164 104 136 151 159 8 13 14 15 Basic metals and products 94 136 152 160 Machinery and equipment 0 0 0 0 Transport and equipment 0 0 0 0 Other manufactured goods 0 0 0 0 60 79 88 92 collection of relevant geological, geotech- Refined petroleum products nical and seismological data. These data Fertilisers provided the input for drafting the prelim- Other chemical products inary technical solution and for executing Other non-metallic mineral pr. the Environmental Impact Assessment layers and on the ground water level were gained. Current speed [m/s] above 0.375 0.35–0.375 0.325–0.35 0.3–0.325 0.275–0.3 0.25–0.275 0.225–0.25 0.2–0.225 0.175–0.2 0.15–0.175 0.125–0.15 0.1–0.125 0.075–0.1 0.05–0.075 0.025–0.05 below 0.025 undefined value Sec. raw mat., scrap Other goods Total SENSITIVITY ANALYSIS Results indicate that operating revenues, CAPEX (capital investment) as well as cargo traffic flows are critical variables since the variation of FNPV/ENPV is bigger than +/-1%. society. 4 Policies 2035 the project is clearly beneficial for the 51 Wood and products 2030 MAIN SCENARIO 2035 geotechnical analyses which led to the 2025 110 million EUR; the B/C ratio is 2.3), and 2030 ment in line with EU Regional geometry and existence of characteristic 2020 2025 Metal ores & mineral products parking. the composition of the ground surface, the 2015 2020 Crude oil shunting station, internal roads and car on site and in laboratory, detailed data on 2010 Main scenario up to 2035 [‘000 tons] trative facilities including buildings for the Study. With the geotechnical investigations 0 TRANSPORT FORECAST FOR SISAK NEW PORT layout variants also foresees all adminis- sewage, electricity, etc. were defined as EU initiatives and projects upgrade 1.000 for flood protection and flood risk mitiga- intentions of the “Joint Statement · Interaction with related national & preparation (29%) and miscellaneous costs (20%). Sava waterway 1.200 The hydraulic study also provided results Up & downstream part of strategic regional develop- EUR of which 44% belong to infrastructure costs, followed by site 2018: tiated by commodities and elaborated in utilities such as communication, water, · Port development as integrated tingency costs). The CAPEX costs amount to approx. 128 million 2030 & 2035. All forecasts were differen- operations entering and leaving the port. Corridors and the layout of all relevant Basin” buildings, safety and security devices, planning and other con- 1.400 volumes were forecasted for 2020, 2025, contributed to ensure save nautical structure costs, miscellaneous costs (including facility services, 1.600 In a next step, the future transhipment served the environmental analysis and installations), transhipment facilities and equipment/super- Low scenario elaborated for 2015, 2025 and 2035. port development phase. This study aration, infrastructure costs (road, railway, waterway, outdoor Main scenario 1.800 this analysis the transport forecast was on the existing flow conditions in each They were divided into 4 categories: costs related to site prep- High scenario to transport on the Sava River. From COMMODITIES · Planning process based on the the project’s engineering design and associated cost estimates. national and international cargoes affine ling study was executed which assessed SISAK NEW PORT VISUALISATION Sava River km 584.5–586.5 Investment costs/capital expenditures (CAPEX) are derived from 2.000 level to obtain a consistent transport flow go database includes the flows of existing In addition, a special 2-D hydraulic model- Cost and Benefit Analysis Forecast of Sisak New Port transhipment volume [‘000 tons] infrastructure build-up of Sisak New Port communities and other relevant Corridor Vb (Rail) borehole samples (drilling core) sources on the national and international seen site are rather unfavourable (like in and regional authorities, business Corridor Xb (Road) The Consultant analysed all statistical As the geotechnical conditions of the fore- activities and the transport demand, the · Close interaction with municipal RHINE – MAIN – DANUBE On-site investigations and In relation to the growth of economic Applied planning principles: Sava waterway within the transport network Transport and Market Study 8 10 11 12 685 936 1,043 1,100 Nominal costs in EUR PHASE I | 2020 PHASE II | 2025 PHASE III | 2035 TOTAL % TOTAL Capital investment A. Construction site preparation 11,148,317 9,661,874.30 16,350,864 37,161,055 29% B. Infrastructure costs 33,265,551 12,404,104 10,712,635 56,382,290 44% C. Transhipment facilities costs 6,368,636 2,601,274 0 8,969,910 7% D. Miscellaneous costs 14,864,422 5,381,946 5,381,946 25,628,314 20% Total (EUR) 65,646,926 30,049,198 32,445,445 128,141,569 100% Operating expenses 2,341,838 2,888,267 2,576,022 7,806,128 35% B. Public utilities costs A. Labour costs 126,008 154,009 186,678 466,695 2% C. Miscellaneous costs 6,446,960 3,924,236 3,643,934 14,015,130 63% Total (EUR) 8,914,806 6,966,513 6,406,634 22,287,953 100% ERDF/CF contribution 21,934,390 EIB loan 60,207,177 National contribution Total (EUR) 46,000,000 128,141,567 Project at a Glance CONTACTS Ministry of Maritime Affairs, Transport and Infrastructure Directorate for Transport Infrastructure 10 000 Zagreb, Krležin Gvozd 1a Overall objective Outputs Development of IWT on Master Plan for Sisak the Sava River Project objective Provision of Technical Assistance for the Master Plan of Sisak New Port Time frame Environmental Impact Assessment (EIA) Study An important part of the project work was dedicated to EIA PROCEDURE Data collection, public network impacts consultation, site visit Study. This Study is the legally prescribed procedure Ministry of Environmental where contingent impacts of the project on the environ- and Nature Protection: decision ment (including nature) are assessed and environmental on appropriate assessment protection measures, impact mitigation measures and monitoring programmes are prescribed. NO YES DRAFTING OF THE EIA REPORT and agriculture, nature, hunting, noise, population, land- (85% EU, 15% Croatia) Beneficiary Consultants iC consulenten (AT) TINA Vienna (AT) impacts on ecological network Hidrokonzalt (HR) Geokon-Zagreb (HR) End of ecological network The environmental experts of the Consultant consider compensated by a proposed set of measures. Therefore, Feasibility Study and Cost-Benefit Analysis (CBA) Environmental Impact Assessment (EIA) Draft Major Project Application for EU Funding Representation of the European Commission in the Republic of Croatia 10 000 Zagreb Ban Centre, Ulica Augusta Cesarca 4–10 T +385 1 46 81-300, F +322 2 985 796 comm-rep-zag@ec.europa.eu www.ec.europa.eu/index_hr.htm Central Finance and Contracting Agency – CFCA 10 000 Zagreb Ulica grada Vukovara 284, Object C T +385 1 45 91-245, F +385 1 45 91-075 info@safu.hr www.safu.hr Port Authority Sisak tehnicki.poslovi@luckaupravasisak.hr www.luckaupravasisak.hr Submission of the final EIA Report (=Study) to the Ministry of Environmental and Nature Protection: BEGINNING OF iC consulenten Ziviltechniker GesmbH THE ENVIRONMENTAL IMPACT ASSESSMENT PROCEDURE Technical Assistance for Master Plan of Sisak New Port 1120 Vienna, Schönbrunner Strasse 297 (November 2013) T +43 1 521 69-0, F +43 1 521 69-180 the negative environmental impact of the construction of Sisak New Port to be small which means that it can be Land Surveying Study www.mppi.hr T +385 44 524-810, F +385 44 524-809 impact assessment accidents. The Study provides a set of recommendations adverse factors. Port Infrastructure info@mppi.hr 44 000 Sisak, Rimska 28 scape as well as the impact of the project in case of and obligatory measures to avoid and/or to minimise · Preliminary Design for Budget The EIA Study assessed the impact of the project in the construction and operation phases on air, waters, soil · SWOT Analysis · Expropriation and (appropriate assessment of included in the EIA Report) · Transport Forecast · Geotechnical Study Port Authority Sisak the preparation of an Environmental Impact Assessment · Transport Analysis August 2012 – December 2013 1,435,120 EUR Screening of ecological New Port T +385 1 37 83-928, F +385 1 37 83-901 office@ic-group.org 1st committee meeting with site visit EuropeAid/130819/D/SER/HR www.ic-group.org Port layout at different development stages a positive decision of the responsible environmental authority in the course of the execution of the EIA is Comments, suggestions, amendments to the EIA Report expected. In the elaboration phase of the EIA Study, the Consultant consulted in a very early stage local and regional NGOs as well as the most affected inhabitants from near-by villages in the framework of several stake- Supported by Amended EIA Report delivered to the county which organises public insight and 1-month public hearing holder meetings. This open planning approach was chosen in order to enable the integration of citizens' know-how and to respect their fears and needs. European Union. Investing in future! Comments from public taken into account and final version The project is co-financed by the EU from of EIA Report drafted the European Regional Development Fund, Transport Operational Programme 2007–2013. 2nd committee meeting takes place where environmental and health protection measures are discussed – final agreement on the EIA Report reached The contents of this publication Ministry issues official decision – END OF THE EIA PROCEDURE are the responsibility of iC consulenten Ziviltechniker GesmbH. This Project is implemented by a consortium led by iC consulenten Ziviltechniker GesmbH in co-operation with the Ministry of Maritime Affairs, Transport and Infrastructure