power generation solutions

Transcription

power generation solutions
Progetto1:Layout 1 30/05/11 12:12 Pagina 3
POWER GENERATION
SOLUTIONS
Progetto1:Layout 1 30/05/11 12:12 Pagina 5
ANSALDO ENERGIA
Power Generation Solutions
Power Plant Flexibility
and Optimization
Ansaldo Energia is a global supplier of turn-key power
plants and offers the full set of the most reliable and
best performing solutions available today.
Ansaldo Energia is one of the few companies in the
world able to offer a broad range of products as manufacturer of all the main power plant components, supplying whole plants as well as power blocks in both
open and combined cycles.
Ansaldo Energia is fully acknowledged today as an EPC
for turnkey projects, and therefore as a global plant
engineering contractor.
Ansaldo Energia, whose customers include public bodies, independent power producers and industrial companies, is an independent operator with fully proven,
proprietary technologies.
Ansaldo Energia has references on all five continents
and enjoys an outstanding reliability record.
Today power plant operational flexibility is a key success
factor to ensure economic return in a liberalized market for
new and existing fossil power plants. Ansaldo Energia provides and develops tailor-made solutions to enhance power
plant operational flexibility by leveraging the full breadth of
experience accumulated from previous projects.
All products and plants are designed to offer:
•high flexibility
•maximum safety
•state-of-the art control systems
•highly environmental-friendly features such as zero
liquid discharge
•remote diagnostics and assistance
This is obtained through the accurate and effective simulation of both processes and plant components during the
design and test phases, and thanks to the quality of the
automation systems and I&C, supplied both for turnkey
plants and components. Taking care of the customer’s
needs during the entire lifetime of the supply is the starting point for Ansaldo Energia in every project and in each
relationship.
Thanks to full-cycle experience and a flexible approach
to power projects, the company’s role can range from
Original Equipment Manufacturer to parts & service
supplier, and from general contractor to co-developer.
All the main new plants are also covered by important
contracts for service and long term maintenance
assistance.
This scenario has translated into more than 33,000
MW installed in the first decade of the new century.
Ansaldo Energia
and equipment
Ansaldo Energia state-of-the-art power generation technology stems from about a century of experience in the
various engineering fields.
Ansaldo Energia invests constantly and increasingly to
provide significant resources for development programmes, particularly in relation to combustion, thermofluid dynamics, automation and special materials.
One example of this is growing market demand for high
efficiency and low emissions, which has led to the
development of the cutting-edge VeLoNOx™ burners
and to a series of new patents for use in all upgraded
gas turbines models.
Progetto1:Layout 1 30/05/11 12:12 Pagina 6
Service Offering
The Ansaldo Energia service offering leverages
advanced technologies, field expertise and flexibility in
relationships in order to enable utilities and plant managers to optimize plant efficiency and reliability, thus
reducing operating and life cycle costs.
In addition, Ansaldo Energia can offer service activities
for third party equipment thanks to its OSP™ business
line, which combines the expertise of the OEM with the
flexibility of the ISP.
Ansaldo Energia has chosen to focus on customer services in order to combine the proven design expertise,
manufacturing capabilities and commissioning skills of
its New Units business line with excellence in the aftersale phase, thanks in particular to rapidity of response
and intervention, technical capabilities and expertise, a
high quality supply chain, and well known flexibility in
matching customer needs.
The complete range of activities covers gas turbines,
steam turbines, generators and complete open/combined cycle plants, with services which are tailored to
the individual requirements of the customer:
•Long Term Service Agreements (LTSA)
•Field Service (Planned Maintenance,
Emergency Interventions)
•Solutions/Upgrades
•Spare parts
•Repair Activities
•Remote Monitoring and Diagnostics
•Second hand Power Plants/Equipment relocations
The company’s experience of long term collaborations
with its customers is demonstrated by current active
engagements: more than 40 gas turbine LTSAs on 68
units, 26 LTSA Customers in 12 countries, totalling
more than 22 GW.
Gas Turbines
generation and industrial applications), with output up to
800 MW. Ansaldo Energia has extensive design, manufacturing and installation experience, with more than
1,200 units in service or on order totalling 89 GW.
Of these more than 300 units are rated above 100MW.
The gas turbine offering is entirely based on fully proven,
proprietary technology. Ansaldo Energia gas turbines are
fully competitive in terms of all market drivers in the
heavy duty segment: efficiency, power output, reliability,
operational flexibility and emission levels.
Gas turbines ranging from 70 MW to more than 290 MW
are continuously improved by a dedicated R&D team.
Ansaldo Energia has received orders for more than 150
gas turbines and 27 GW worldwide, with an installed
fleet exceeding 6 Million Operating Hours.
Steam Turbines
Ansaldo Energia offers a comprehensive portfolio of
highly reliable, efficient and operationally flexible steam
turbines for all fossil-fired power plant applications (combined cycles, steam power plants and geothermal, co-
Turbo Generators
Ansaldo Energia experience in the design and construction of turbogenerators up to 1220 MVA dates back to
1920: it covers mainly gas, steam, and gas & steam for
single shaft configurations and geothermal applications,
and offers a wide range of air-cooled, hydrogen-cooled
and hydrogen/water-cooled turbogenerators, creating a
comprehensive portfolio of highly reliable, efficient and
operationally flexible machines.
Since 1950, more than 700 units (over 300 in the last
ten years) have been manufactured, for a total installed
generating capacity of over 100 GVA.
Progetto1:Layout 1 30/05/11 12:12 Pagina 4
Ansaldo Energia Contracts for large Power Plants
(Combined Cycle/Open Cycle) in the period 2001-2011
Contract
Site
Configuration
Type of supply
contract
Commercial
operation
Servola
Brownfield
200 MW (1+1) Multishaft syngas CC
EPC Contract
2001
Ballylumford
Brownfield
500 MW (2+1) Multishaft CC
+ 100 MW (1+1) Single shaft CC
EPC Contract
2003
Ferrera Erb.
Brownfield
800 MW 2x(1+1) Multishaft CC
Supply and installation of power block
+ 200 MW (1+1) Multishaft syngas CC
2003+2004
Ravenna
Brownfield
800 MW 2x(1+1) Multishaft CC
Supply and installation of power block
2004
Mantova
Brownfield
800 MW 2x(1+1) Multishaft CC
Supply and installation of power block
2005
Voghera
Greenfield
400 MW (1+1) Single shaft CC
Supply and installation of power block
2005
Brindisi
Brownfield
1200 MW 3x(1+1) Multishaft CC
Supply and installation of power block
2005
Rosignano
Brownfield
400 MW (1+1) Single shaft CC
EPC Contract
2007
Sparanise
Greenfield
800 MW 2x(1+1) Multishaft CC
EPC Contract
2007
Leinì
Greenfield
400 MW (1+1) Multishaft CC
EPC Contract
2007
Vado Ligure
Repowering
800 MW (2+1) Multishaft CC
EPC Contract
2007
Rizziconi
Greenfield
800 MW 2x(1+1) Multishaft CC
EPC Contract
2008
Moncalieri
Repowering
400 MW (1+1) Multishaft CC
EPC Contract
2008
Napoli Levante
Repowering
400 MW (1+1) Multishaft CC
EPC Contract
2008
Escatron
Brownfield
800 MW (2+1) Multishaft CC
Supply and installation of power block
2008
Ferrara
Brownfield
800 MW 2x(1+1) Multishaft CC
Supply and installation of power block
2008+2009
Larbaa
Greenfield
500 MW (4 TG) Open cycle
EPC Contract
2009
Batna
Greenfield
250 MW (2 TG) Open cycle
EPC Contract
2009
M'Sila
Brownfield
500 MW (2 TG) Open cycle
EPC Contract
2009
Algeçiras
Repowering
400 MW (1+1) Multishaft CC
800 MW 2x(1+1)
Supply and installation of power block
2010
Marcinelle
Greenfield
400 MW (1+1) Single shaft CC
Supply and installation of power block
2010
Thisvi
Greenfield
400 MW (1+1) Multishaft CC
Supply and installation of power block
2010
Turano Lodigiano Greenfield
800 MW (2+1) Multishaft CC
EPC Contract
2010
Aprilia
Greenfield
800 MW (2+1) Multishaft CC
EPC Contract
2011
San Severo
Greenfield
Single shaft CC
EPC Contract (1+1) 400 MW
2011
Bayet
Greenfield
Single shaft CC
EPC Contract (1+1) 400 MW
2011
Dunamenti
Greenfield
400 MW (1+1) Multishaft CC
Supply and installation of power block
2011
Torino Nord
Greenfield
400 MW (1+1) Multishaft CC
Supply and installation of power block
2011
Progetto1:Layout 1 30/05/11 12:12 Pagina 1
Scheda SanSevero_LO:San Severo 11/02/11 14:47 Pagina 1
San Severo 1 x 400 MW
Combined Cycle
Power Plant
Scheda SanSevero_LO:San Severo 11/02/11 14:47 Pagina 2
Contract: San Severo
Client: En Plus S.p.A. (Atel)
Type of supply contract: EPC Contract
Country: Italy
Site Type: Greenfield
Service Agreement: LTSA
Commercial operation: 2011
Configuration:
400 MW (1+1) Single shaft CC
GT
GEN
HRSG
ST
Cond.
Main characteristics
Plant main features
San Severo is composed of a 1+1 combined cycle unit in
single shaft configuration with air condenser for electrical
energy production. The expected plant efficiency is over
57%. This power plant is equipped with the new flexibility
package to fulfil the new energy market requirement.
The minimum technical load of the gas turbine, thanks
to the new VeLoNOxTM burners, will be lower than the 45%.
In this plant the new proprietary ZLD system has been
implemented to reduce the fresh water consumption and
to comply with the local regulation that prohibits any liquid effluents emission from the industrial sites. This system allows an industrial water recover of about the 98%.
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Gas Turbine
AE94.3A x 280 MW - 50 Hz
Main fuel: natural gas
Steam Turbine
MT15 x 135 MW - 50 Hz
118/30.3/4.63 bar - 546/536/265°C
Generator
50THR - L63 - 470 MVA - 20 kV - 50 Hz - H2 cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation,
drum type with integrated deareator.
Cooling System
Air Condenser, single row, 24 modules, double speed type.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Bayet_LO:Bayet 11/02/11 14:46 Pagina 1
Bayet 1 x 400 MW
Combined Cycle
Power Plant
Scheda Bayet_LO:Bayet 11/02/11 14:46 Pagina 2
Contract: Bayet
Client: 3CB SAS (Atel)
Type of supply contract: EPC contract
Country: France
Site Type: Greenfield
Service Agreement: LTSA
Commercial operation: 2011
Configuration:
400 MW (1+1) Single shaft CC
GT
GEN
HRSG
ST
Cond.
Main characteristics
Plant main features
Bayet is a 1+1 combined cycle unit in single shaft configuration with air condenser for electrical energy production.
The expected plant efficiency is over 57%.
This power plant is equipped with the new flexibility package to fulfil the energy market requirement.
The minimum technical load of the gas turbine, thanks
to the new VeLoNOxTM burners, will be lower than the 45%.
Moreover this plant is designed to hold also wide range
of ambient temperatures. It is also to highlight the
method of participation to the primary and secondary
frequency regulation that involves also the steam turbine.
Gas Turbine
AE94.3A x 280 MW - 50 Hz
Main fuel: natural gas
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Steam Turbine
MT15 x 135 MW - 50 Hz
118/30.3/4.63 bar - 546/536/265°C
Generator
50THR - L63 - 470 MVA - 20 kV - 50 Hz - H2 cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation,
drum type with integrated deareator.
Cooling System
Air Condenser, single row, 24 modules, double speed type.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Turano Lodigiano_AW:lodi 10/05/11 11:47 Pagina 1
Turano Lodigiano 1 x 800 MW
Combined Cycle
Power Plant
Scheda Turano Lodigiano_AW:lodi 10/05/11 11:47 Pagina 2
Turano Lodigiano 1 x 800 MW
Combined Cycle Power Plant
The Turano Lodigiano/Bertonico power plant, situated
near Lodi in northern Italy, is owned by Sorgenia S.p.A.,
an important private operator on the Italian market for
electric power and natural gas, with a strong focus on
respect for the environment and “clean” energy.
The plant is located in a recently reclaimed industrial
area that was previously occupied by a refinery demolished in the early 1980s, and there are plans to re-qualify
the surrounding area by developing industrial and artisan sites nearby.
In April 2008 Ansaldo Energia was awarded the EPC contract to build the power plant on a turnkey basis and a
Long Term Service Agreement (LTSA) to maintain the 2
gas turbines and relative generators. In 2009 the customer, based in part on positive experience gained at Turano, awarded Ansaldo Energia a similar contract for the
sister plant in Aprilia (Province of Latina).
The power plant comprises a combined cycle with two
gas turbines and one steam turbine (2+1 configuration),
delivering a nominal output of 800 MW.
The work assigned to Ansaldo Energia as EPC Contractor included the design, supply, on-site installation, startup and testing of the entire power plant, comprising the
main components in the power block.
The turnkey supply of which Ansaldo Energia is in charge
also covers the gas station, the thermal cycle, the auxiliary systems, including one auxiliary boiler and a water
demineralisation and recover plant (ZLD), the HV, MV
and LV electrical equipment, including one metal-clad
gas insulated switchgear (GIS) for connection to the
Terna substation, the plant automation system (DCS)
and the design and implementation of civil works for the
entire plant. Third parties commissioned directly by the
customer developed the natural gas feeding system and
the high voltage electric substation.
The distinctive features of the project are its focus on
environmental issues and excellent operating flexibility,
which are critical success factors for power producers
today, who are faced with an ever more competitive market and a society increasingly aware of environmental
problems. A combined cycle solution plus Ansaldo Energia technology delivers excellent plant performance with
low atmospheric emission impact. The class 4 AE94.3A
gas turbine with VeLoNOx™ burners has been successfully tested on other power plants and the base load efficiency measured during testing was higher than 57%,
with CO and NOx emissions much lower than 30 mg/Nm3.
The results of plant efficiency tests at partial load were
equally satisfactory. The management of water resources
was also a key focus and the plant has a Zero Liquid Discharge (ZLD) water treatment system that reduces the
input of process water from wells, as well as a powerful
air condenser used to condense the steam without resorting to external water resources for cooling.
Although the power plant is situated in an industrial area
away from population settlements, the design meets
Scheda Turano Lodigiano_AW:lodi 10/05/11 11:47 Pagina 3
specific architectural requirements to ensure environmental and landscape integration in such a way as to
reduce visual and acoustic impact. The buildings are
clad in panels that insulate from and absorb sound,
which represent one of the main visual features of the
plant, along with the big hexagonal concrete stack about
100 m high and the brick red colour used for various
plant sections, recalling the natural colours of the area
surrounding the plant. So far as power generation is concerned, the plant has been designed to meet the voltage
and frequency regulation requirements of the Italian
transmission network as stipulated by Terna (the Italian
National Grid operator), while on a functional level the
plant has been designed to deliver maximum operating
flexibility in accordance with legal atmospheric pollutant
emission criteria. The customer can vary load on a daily
basis in peak hours and during the weekend. Rapid
plant start up allows the customer to begin generating
power quickly, as well as to operate with different plant
configurations and variable loads, providing a rapid and
flexible response to network demand.
The project was given the “Notice to Proceed” by the customer in April 2008 and construction work began in February 2009. A constant focus on the real needs of the
customer and the climate of proactive collaboration
established, together with technical expertise and careful planning and monitoring of work, have made it possible to achieve the general project objectives and,
specifically, plant delivery (PAC issued by customer Sorgenia) in just 30 months from the NTP. Site work (civil
works, electromechanical assembly, start-up activities
and testing) involved up to about 850 people on site in
peak periods and was performed in such a way as to ensure the health and safety of both its own workers, and
those of associated companies and sub-contractors
working on site.
With the final hand-over of the plant to the customer,
planned for November 2010, the Long Term Service
Agreement covering maintenance will come into effect.
Under the terms of this contract Ansaldo Energia is committed for 7+7 years to managing and performing routine maintenance and repair work on the 2 gas turbine
sets, undertaking to maintain performance values with
minimum deterioration and high turbo generator availability values for the entire duration of the contract.
The agreement also entails operating parameter logging
and remote monitoring 24/7 from the diagnostic control
room at Ansaldo Energia’s Genoa production facility.
Scheda Turano Lodigiano_AW:lodi 10/05/11 11:48 Pagina 4
Contract: Turano Lodigiano
Client: Sorgenia
Type of supply contract: EPC Contract
Country: Italy
Site Type: Greenfield
Service Agreement: LTSA
Commercial operation: 2010
Configuration:
800 MW (2+1) Multishaft CC
GEN
GT
HRSG
GEN
ST
Cond.
GEN
GT
HRSG
Main characteristics
Plant main features
Turano Lodigiano is a 2+1 combined cycle unit with air
condenser for electrical energy production. The expected
plant efficiency is over 57%. The plant minimum technical
load, thanks to the new VeLoNOxTM burners, will be about
the 50%. This power plant is characterized by an architectonical cover solution for the main components and for the
HRSG stack to minimize the environmental impact and
promote the plant acceptance and territorial integration.
Moreover, to reduce the environmental impact, the new
proprietary ZLD system has been implemented to reduce
the fresh water consumption and to comply with the local
regulation that prohibits any liquid effluents emission from
the industrial sites. This system allows an industrial water
recover of about the 98%.
Gas Turbine
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
AE94.3A x 277.2 MW - 50 Hz
Main fuel: natural gas
Steam Turbine
RT30 x 268 MW - 50 Hz
123/28.5/4.9 bar - 544/549/231°C
Generator
GT units: TRY - L56 - 330 MVA - 18 kV - 50 Hz - air cooled
ST unit: TRX - L56 - 330 MVA - 18 kV - 50 Hz - air cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation,
drum type with integrated deareator.
Cooling System
Air Condenser, single row, 24 modules, double speed type.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda MʼSila_LO:MʼSila 13/10/10 11:30 Pagina 1
M'Sila 500 MW
Open Cycle
Power Plant
Scheda MʼSila_LO:MʼSila 13/10/10 11:30 Pagina 2
Contract: M’Sila
Client: Sonelgaz
Type of supply contract: EPC Contract
Country: Algeria
Type of site: Brownfield
Service Agreement: Spare Parts
Commercial operation: 2010
Configuration:
500 MW (2 GTs) OC
GT
GEN
GT
GEN
Main characteristics
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Plant main features
M'Sila projet is a 2 x 215 MW GT based power plant in
open cycle configuration delivered as turn-key contract.
It is provided for mulfifuel service with natural gas as
main fuel and light oil as back-up fuel.
The plant is equipped with gas reducing station, firefigthing
facilities, black start diesel, demi production and water
treatment units and auxiliaries buildings for administration
and workshop.
Conceived as an extension of the existing plant, the
scope of supply includes all facilities for the telesurveillance and anti-intrusion systems along the whole fence
for a perimeter longer than 3.5 km.
M’Sila power plant has been designed full in compliance
with Customer requirements to get high availability, performance and respect of natural and human environment.
Gas Turbine
AE94.3A x 215 MW - 50 Hz
Main fuel: natural gas /oil distillate
Generator
WY23Z-109LL - 300 MVA - 19 kV - 50 Hz - air cooled
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
E-mail: ansaldoenergia@aen.ansaldo.it - service2@aen.ansaldo.it - www.ansaldoenergia.it
Scheda Larbaa_LO:Larbaa 13/10/10 11:37 Pagina 1
Larbaa 500 MW
Open Cycle
Power Plant
Scheda Larbaa_LO:Larbaa 13/10/10 11:37 Pagina 2
Contract: Larbaa
Client: Sonelgaz
Type of supply contract: EPC Contract
Country: Algeria
Repowering: Greenfield
Service Agreement: Spare Parts
Commercial operation: 2010
Configuration:
500 MW (4 GTs) OC
GT
GEN
GT
GEN
GT
GEN
GT
GEN
Main characteristics
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Plant main features
Larbaa projet is a 4 x 140 MW GT based power plant in
open cycle configuration delivered as turn-key contract including extension of the existing 220 kV open air substation equipped with double bus-bar and 4 additional bays.
It is provided for mulfifuel service with natural gas as
main fuel and light oil as back-up fuel.
The plant is equipped with gas reducing station, fuel storage
tanks (4 x 9000 m3 capacity), black start diesel, firefigthing
facilities, demi production and water treatment units and
auxiliaries buildings for administration, workshop and store
for spare parts.
Conceived as greenfield installation, the scope of supply
includes all facilities for the telesurveillance and anti-intrusion systems along the whole fence for a perimeter
longer than 2.0 km.
Larbaa power plant has been designed in full compliance
with Customer requirements to get high availability, performance and respect of natural and human environment.
Performance tests have been succesfully completed with
improved power output (1.2% higher than guaranteed
value) and reduced fuel consumption (1.4% less than
guaranteed value) with important benefits as it regards
our Customer investment.
Gas Turbine
AE94.2 x 140 MW - 50 Hz
Main fuel: natural gas / oil distillate + w.inj
Generator
WY21Z-092RR - 190 MVA - 15.5 kV - 50 Hz - air cooled
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
E-mail: ansaldoenergia@aen.ansaldo.it - service2@aen.ansaldo.it - www.ansaldoenergia.it
Scheda Batna_LO:Batna 13/10/10 11:41 Pagina 1
Batna 250 MW
Open Cycle
Power Plant
Scheda Batna_LO:Batna 13/10/10 11:41 Pagina 2
Contract: Batna
Client: Sonelgaz
Type of supply contract: EPC Contract
Country: Algeria
Repowering: Greenfield
Service Agreement: Spare Parts
Commercial operation: 2010
Configuration:
250 MW (2 GTs) OC
GT
GEN
GT
GEN
Main characteristics
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Plant main features
Batna projet is a 2 x 127 MW GT based power plant in
open cycle configuration delivered as turn-key contract including a 220 kV open air substation with double bus-bar
system and 11 bays. It is provided for mulfifuel service
with natural gas as main fuel and light oil as back-up fuel.
The plant is equipped with gas reducing station, fuel storage
tanks (2 x 9000 m3 capacity), black start diesel, firefigthing
facilities, demi production and water treatment units and
auxiliaries buildings for administration, workshop and store
for spare parts.
Conceived as greenfield installation, the scope of supply
includes all facilities for the telesurveillance and anti-intrusion systems along the whole fence for a perimeter
longer than 3.0 km.
Batna power plant has been designed full in compliance
with Customer requirements to get high availability, performance and respect of natural and human environment.
Performance tests have been succesfully completed with
improved power output (2.8% higher than guaranteed
value) and reduced fuel Consumption (1.5% less than
guaranteed value) with important benefits as it regards
our Customer investment.
Gas Turbine
AE94.2 x 127 MW - 50 Hz
Main fuel: natural gas /oil distillate + w.inj
Generator
WY21Z-092RR - 190 MVA - 15.5 kV - 50 Hz - air cooled
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
E-mail: ansaldoenergia@aen.ansaldo.it - service2@aen.ansaldo.it - www.ansaldoenergia.it
Scheda Napoli_LO:Napoli 08/09/10 18:31 Pagina 1
Napoli Levante 1 x 387 MW
Combined Cycle
Power Plant
Scheda Napoli_LO:Napoli 08/09/10 18:31 Pagina 2
Contract: Napoli Levante
Client: Tirreno Power
Type of supply contract: EPC Contract
Country: Italy
Site Type: Repowering
Service Agreement: LTSA
Commercial operation: 2009
Configuration:
400 MW (1+1) Multishaft CC
GEN
GT
GEN
ST
HRSG
Cond.
Main characteristics
Plant main features
Napoli Levante is the repowering as 1+1 400 MW combined cycle unit of the existing 150 MW unit 3 of
Naples' power plant. The existing steam turbine and its
auxiliaries, the steam turbine pedestal, the steam turbine generator and the surface condenser were overhauled and refurbished to be reused in the new unit.
Coming the natural gas from SNAM town pipeline a compressor station was necessary. The automation system
is based upon field bus technology.
Gas Turbine
AE94.3A x 264 MW - 50 Hz
Main fuel: natural gas
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Steam Turbine
RT x 134 MW - 50 Hz
116/34/6.4 bar - 545/550/244°C
Generator
GT unit: WY23Z-109LL - 300 MVA - 20 kV - 50 Hz - air
cooled
ST unit: ATH 170000/2 - 170 MVA - 15 kV - 50 Hz - H2
cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator
Cooling System
Sea water surface condenser.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Moncalieri_LO:Moncalieri 08/09/10 18:29 Pagina 1
Moncalieri 1 x 389 MW
Combined Cycle
Power Plant
Scheda Moncalieri_LO:Moncalieri 08/09/10 18:29 Pagina 2
Contract: Moncalieri
Client: Iren
Type of supply contract: EPC Contract
Country: Italy
Site type: Repowering
Service Agreement: LTSA
Commercial operation: 2008
Configuration:
400 MW (1+1) Multishaft CC
GEN
GT
GEN
ST
HRSG
Cond.
Main characteristics
Plant main features
Moncalieri is a 1+1 combined cycle unit for electrical and
thermal energy production. It is connected to Torino district
heating grid and can produce a thermal power of over 260
MWt. Moncalieri is the repowering of an existing 141 MW
conventional unit and it is able to work not only in combined cycle configuration but also as a conventional cycle
thanks to the piping connections to the existing fired
steam generator. During the commissioning phase the
new authomatic start-up sequence was successfully
tested and applied to this plant. Due to transportation
constraints, the gas rurbine was assembled at site.
Gas Turbine
AE94.3A x 265 MW - 50 Hz
Main fuel: natural gas
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Steam Turbine
Existing ST x 130 MW - 50 Hz
85/24.5/3.68 bar - 536/536/221°C
Generator
GT unit: WY23Z-109LL - 300 MVA - 19 kV - 50 Hz - air
cooled
ST unit: WX21Z-092RR - 170 MVA - 15.75 kV - 50 Hz - air
cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator.
Cooling System
Surface condenser.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Rizziconi_LO:Rizziconi 08/09/10 18:30 Pagina 1
Rizziconi 2 x 385 MW
Combined Cycle
Power Plant
Scheda Rizziconi_LO:Rizziconi 08/09/10 18:30 Pagina 2
Contract: Rizziconi
Client: Rizziconi Energia (EGL)
Type of supply contract: EPC Contract
Country: Italy
Site type: Greenfield
Service Agreement: LTSA (GTF)
Commercial operation: 2008
Configuration:
800 MW 2x(1+1) Multishaft CC
GEN
GT
GEN
ST
HRSG
Cond.
GEN
GT
GEN
ST
HRSG
Cond.
Main characteristics
Plant main features
Rizziconi is composed of 2 x (1+1) combined cycle units
in multi shaft configuration with air condenser for electrical energy production. The plant efficiency is over
56%. These two units were designed to be as much as
possible similar to Sparanise combined cycle units for
maintenance and operating reasons.
Gas Turbine
AE94.3A x 263 MW - 50 Hz
Main fuel: natural gas
Steam Turbine
MT15 x 132 MW - 50 Hz
118/31/4.6 bar - 549/558/236°C
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Generator
GT units: WY23Z-109LL - 300 MVA - 19 kV - 50 Hz - air
cooled
ST units: WY21Z-092LLT - 170 MVA - 15.75 kV - 50 Hz air cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator.
Cooling System
Air Condenser, multi row, 21 modules, double speed type.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Escatron_LO:Escatron 08/09/10 18:27 Pagina 1
Escatron 1 x 800 MW
Combined Cycle
Power Plant
Scheda Escatron_LO:Escatron 08/09/10 18:28 Pagina 2
Contract: Escatron
Client: Enel
Type of supply contract:
Supply & install. of power block
Country: Spain
Site type: Brownfield
Service Agreement: FA (Field Activity)
Commercial operation: 2008
Configuration:
Multishaft CC (2+1) 800 MW
GEN
GT
HRSG
GEN
ST
Cond.
GEN
GT
HRSG
Main characteristics
Plant main features
Escatron is a 2+1 combined cycle unit. Ansaldo Energia
supplied the entire power block composed of the two gas
turbines with their generators, the two HRSGs and the
steam turbine with its generator. Escatron was the first
successful application of the new AE94.3A upgraded
model. Due to trasportation constraints, the gas turbine
was assembled at site.
Gas Turbine
AE94.3A x 267 MW - 50 Hz
Main fuel: natural gas/oil distillate as back up fuel
Steam Turbine
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
RT30 x 273 MW - 50 Hz
124/27.8/4.86 bar - 548/553/229°C
Generator
GT units: WY23Z-109LL - 300 MVA - 19 kV - 50 Hz - air
cooled
ST unit: WX23Z-109LL - 300 MVA - 19 kV - 50 Hz - air
cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator.
Cooling System
Surface condenser with closed cooling tower, supplied
by Enel.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Sparanise_LO:G_624/08_Ansaldo Scheda Sparanise 08/09/10 18:32 Pagina 1
Sparanise 2 x 385 MW
Combined Cycle
Power Plant
Scheda Sparanise_LO:G_624/08_Ansaldo Scheda Sparanise 08/09/10 18:32 Pagina 2
Contract: Sparanise
Client: Calenia Energia (EGL)
Type of supply contract: EPC Contract
Country: Italy
Site type: Greenfield
Service Agreement: LTSA (GTF)
Commercial operation: 2007
Configuration:
800 MW 2x(1+1) Multishaft CC
GEN
GT
GEN
ST
HRSG
Cond.
GEN
GT
GEN
ST
HRSG
Cond.
Main characteristics
Plant main features
Sparanise is composed of 2x(1+1) combined cycle units
in multi shaft configuration with air condenser for electrical energy production.
The plant efficiency is over 56%. The measured plant
availability during the first period of operation is well over
guaranteed figure. The plant often works delivering a
±20% band as secondary frequency regulation.
Sparanise is the first Italian power station realised for
EGL: it has been designed to get the maximum respect
for the natural and human environment; so advanced
technology guaranteed high efficiency and emissions
below European regulation limits, while innovative architectural solutions met client's request to reduce sight
impact. Both the high efficiency and the high availability
help the customer to get as much as possible return
from his investment.
Gas Turbine
AE94.3A x 263 MW - 50 Hz
Main fuel: natural gas.
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Steam Turbine
MT15 x 132 MW - 50 Hz
117/31.1/4.6 bar - 549/558/236°C
Generator
GT unit: WY23Z-199LL - 300 MVA - 19 kV - 50 Hz - air
cooled
ST unit: WY21Z-092LLT - 170 MVA - 15.75 kV - 50 Hz air cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator.
Cooling System
Air Condenser, multi row, 21 modules, double speed type.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Leini_LO:Leini 08/09/10 18:28 Pagina 1
Leinì 1 x 385 MW
Combined Cycle
Power Plant
Scheda Leini_LO:Leini 08/09/10 18:28 Pagina 2
Contract: Leinì
Client: AceaElectrabel
Type of supply contract: EPC Contract
Country: Italy
Site type: Greenfield
Service Agreement: LTSA
Commercial operation: 2007
Configuration:
400 MW (1+1) Multishaft CC
GEN
GT
GEN
ST
HRSG
Cond.
Main characteristics
Plant main features
Leinì is a 1+1 combined cycle unit in multi shaft arrangement with air condenser for electrical and thermal energy
production. The plant efficiency is over 56%. The plant is
able to discharge a total thermal energy for district heating
and cogeneration for industrial application of 200 MWt.
Gas Turbine
AE94.3A x 265 MW - 50 Hz
Main fuel: natural gas
Steam Turbine
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
RT20 x 128.5 MW - 50 Hz
115/31/4.6 bar - 545/553/236°C
Generator
GT unit: WY23Z-109LL - 300 MVA - 19 kV - 50 Hz - air
cooled
ST unit: WX21Z-092LLT - 160 MVA - 15.75 kV - 50 Hz air cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator.
Cooling System
Air Condenser, single row, 18 modules, double speed type.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Vado_LO:Vado 08/09/10 18:33 Pagina 1
Vado Ligure 1 x 781 MW
Combined Cycle
Power Plant
Scheda Vado_LO:Vado 08/09/10 18:33 Pagina 2
Contract: Vado Ligure
Client: Tirreno Power (Suez/Sorgenia)
Type of supply contract: EPC Contract
Country: Italy
Site type: Brownfield/Repowering
Service Agreement: LTSA
Commercial operation: 2007
Configuration:
800 MW (2+1) Multishaft CC
GEN
GT
HRSG
GEN
ST
Cond.
GEN
GT
HRSG
Main characteristics
Plant main features
Vado Ligure is a 2+1 combined cycle unit obtained repowering the existing heavy oil fired block of Vado Ligure
power plant. This choice allowed for the client a great
saving in terms of efficiency, spaces and emissions without considering that the steam turbine and its auxiliaries,
the existing pedestal, the sea water condenser and the
steam turbine generator were overhauled and refurbished to be reused in the new unit.
Moreover the new automation system based upon field
bus technology was successfully tested.
Gas Turbine
AE94.3A x 264 MW - 50 Hz
Main fuel: natural gas
Steam Turbine
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
RT x 267 MW - 50 Hz
126/31/4.2 bar - 551/556/244°C
Generator
GT units: WY23Z-109LL - 300 MVA - 20 kV - 50 Hz - air
cooled
ST unit: ATH 370000/2 - 370 MVA - 20 kV - 50 Hz H2/H2O cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator.
Cooling System
Sea water surface condenser. The circulating water system
uses the existing sea water intake and sea water discharge
channel with new circulating water pumps.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Rosignano_LO:Rosignano 08/09/10 18:29 Pagina 1
Rosignano 1 x 388 MW
Combined Cycle
Power Plant
Scheda Rosignano_LO:Rosignano 08/09/10 18:30 Pagina 2
Contract: Rosignano
Client: AceaTractebel
Type of supply contract: EPC Contract
Country: Italy
Site type: Brownfield
Service Agreement: LTSA
Commercial operation: 2007
Configuration:
400 MW (1+1) Single shaft CC
GT
GEN
HRSG
ST
Cond.
Main characteristics
Plant main features
Rosignano is a 1+1 combined cycle unit in single shaft
arrangement. This brownfield power plant shares some
auxiliary facilities with the existing CCU supplied by
Ansaldo Energia in 1996. It is the first 400 MW EPC in
single shaft configuration supplied by Ansaldo Energia.
Its efficiency is over 56%.
Gas Turbine
AE94.3A x 263 MW - 50 Hz
Main fuel: natural gas
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Steam Turbine
MT15 x 133.5 MW - 50 Hz
117/31 4.6 bar - 558/558/234°C
Generator
50THR - L63 - 480 MVA - 20 kV - 50 Hz - H2 cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator.
Cooling System
Surface condenser with closed cooling tower.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Voghera_LO:Voghera 08/09/10 18:33 Pagina 1
Voghera 1 x 400 MW
Combined Cycle
Power Plant
Scheda Voghera_LO:Voghera 08/09/10 18:34 Pagina 2
Contract: Voghera
Client: AceaElectrabel
Type of supply contract:
Supply & install. of power block
Country: Italy
Site type: Greenfield
Service Agreement: LTSA
Commercial operation: 2005
Configuration:
400 MW (1+1) Single shaft CC
GT
GEN
HRSG
ST
Cond.
Main characteristics
Plant main features
Voghera is a 1+1 combined cycle unit in single shaft
configuration. This greenfield plant with air condensing
system, is equipped with the first 400 MW power block
in single shaft configuration supplied by Ansaldo Energia. Power output higher then guaranteed (plus ~8.6 MW).
Fuel consumption lower then guaranteed (minus 1.72%).
Ambient emissions lower that guaranteed (NOx: 20 ppm
versus 25 guaranteed; CO: 0.98 ppm versus 10 guaranteed).
Gas Turbine
AE94.3A x 259 MW - 50 Hz
Main fuel: natural gas
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Steam Turbine
MT15 x 131.5 MW - 50 Hz
117/30.8/4.8 bar - 559/559/234°C
Generator
50THR - L63 - 470 MVA - 20 kV - 50 Hz - H2 cooled
Heat Recovery Steam Generator
Three pressure levels with RH, natural circulation, drum
type with integrated deareator. Out of Ansaldo Energia
Scope of supply.
Cooling System
Air Condenser, single row. Out of Ansaldo Energia Scope
of supply.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Ferrera_AW:G_624/08_Ansaldo Scheda Ferrera 10/05/11 11:49 Pagina 1
Ferrera Erbognone
2 x 400 MW + 1 x 250 MW
Combined Cycle
Power Palnt
Scheda Ferrera_AW:G_624/08_Ansaldo Scheda Ferrera 10/05/11 11:49 Pagina 2
Ferrera Erbognone Power Plant
Service activities performed by Ansaldo Energia
within the Long Term Service Agreement
In 2001 Ansaldo Energia was awarded the Long Therm
Service Agreement ( LTSA ) to perform services on the
gas turbine, steam turbines and relevant generators
of the entire Enipower combined cycle fleet.
The time frame validity of the above mentioned Contract is from the PAC of each power plant up to the
achievement of 50 KEOH of each Gas Turbine.
The main deliveries of the LTSA are the following:
• Unplanned maintenance activities
• Planned maintenance activities on GT, ST,
Generator, bypass valves, HVAC
All the power plant units are continuously monitored
by Ansaldo Energia with the purpose to supply an effective remote diagnostic assistance in the areas of
thermodynamic (Power Output, Efficiency, Turbine Inlet
Temperature, etc.), vibrations, emissions, combustion
analysis.
• Spare parts initial stock and stock replenishment
• Strategic spare parts (spare rotor, Hub, turbine
blade carrier, rotor cover)
• Gas turbine blades and vanes refurbishment
• Remote monitoring and diagnostic
• Warranties: Availability, Power & Efficiency, Emissions
The remote monitoring system is also the main tool
to support the predictive maintenance.
Among the Enipower fleet, Ferrera Erbognone represent a bright example of the first power plant installed
and then in operation, and having the AE94.3A gas
fired turbine as well as the AE94.2K gas turbine fed
with syngas.
Scheda Ferrera_AW:G_624/08_Ansaldo Scheda Ferrera 10/05/11 11:49 Pagina 3
Up to now, in the frame of the LTSA, Ansaldo Energia
already performed in Ferrera Erbognone the following
activities of planned maintenance:
• N. 5 Gas Turbine Major Overall
• N. 1 Gas Turbine Hot Gas Path Inspection
• N. 4 Generator Major Overall
• N. 5 Steam Turbine minor inspection (valve inspection)
• N. 24 minor inspection of gas turbine and generator
Obtaining excellent performance both in term of outage period and machine setting, gaining the Client’s
appreciation, having often exceeded the availability target guaranteed in the Contract.
During the LTSA period Ansaldo Energia proposed to
Enipower several upgrading and TILs with the aim to
improve power output, flexibility, reliability and to reduce emissions.
The main improvements ordered by Enipower and implemented by Ansaldo Energia in Ferrera Erbognone
power plant were:
• CMF+: Compressor mass flow increase for power
increase
• Fogging system for power increase
• VeLowNox for emission reduction
• Inlet Guide Vanes with Hydraulic actuator
for improve reliability and flexibility
• Third accelerometer for vibration monitoring
in order to improve the reliability
• Several software and hardware implementation
in order to improve load ramps, primary
and secondary frequency support, turn down.
Scheda Ferrera_AW:G_624/08_Ansaldo Scheda Ferrera 10/05/11 11:50 Pagina 4
Contract: Ferrera Erbognone
Client: Enipower
Type of supply contract: Supply & install.
of power block
Country: Italy
Site type: Greenfield
Service Agreement: LTSA (GTF)
Commercial operation: 2003, 2004
Configuration:
800 MW 2x(1+1) Multishaft CC +
250 MW (1+1) Multishaft syngas CC
GEN
GT
GEN
ST
GEN
GT
GEN
ST
GT
GEN
ST
The information contained in this publication is provided for illustrative purposes only. Product descriptions and content may change
in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at any time for technical
or commercial reasons.
GEN
HRSG
Main characteristics
Cond.
Plant main features
HRSG
Cond.
HRSG
Cond.
The contract of Ansaldo Energia with Enipower signed a milestone in terms of size, contents, services and Customer. Enipower
is the electric power operator with an important network of petrochemicals plants spread across Italy providing, ideal locations for
new capacity…and with this contract planning 8 combined cycles for installation in four industrial areas owned by the group,
will deliver a total of about 3,850 MW. The plant, the first of four,
rated 1,050 MW featuring two natural gas unit rated about 800
MW and a 250 MW syngas unit. One of the key factor of Ansaldo
Energia’ success was the maintenance and assistance proposal
formulated using innovative criteria. Maintenance and assistance
alone are worth roughly a quarter of the entire contract amount.
The plant also highlights the growing trend in power generation
machinery demand for high base load plant.
Gas Turbine
1 x AE94.2K x 167 MW, 2 x AE94.3A x 258 MW - 50 Hz
Main fuel: syngas (AE94.2K), natural gas (AE94.3A).
Steam Turbine
ST for 2x(1+1) CC: MT15 x 131.5 MW - 50 Hz
117/30.8/4.8 bar - 559/559/234°C;
ST for (1+1) CC: 1 x 88 MW - 50 Hz
95/29/6.5 bar - 510/510/260 °C
Generator
GT units: WY23Z-109LL - 300 MVA - 19 kV - 50 Hz
- air cooled
ST units: WX21Z-092LLT - 170 MVA - 15.75 kV - 50 Hz
- air cooled
GT Syngas unit: WY21Z-092LLT - 200 MVA - 15.75 kV
- 50 Hz - air cooled
Heat Recovery Steam Generator
Out of Ansaldo Energia Scope of supply.
Cooling System
Out of Ansaldo Energia Scope of supply.
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
www.ansaldoenergia.it
Scheda Ballylumford_LO:Ballylumford 13/10/10 11:34 Pagina 1
Ballylumford
1 x 100 MW + 1 x 500 MW
Combined Cycle
Power Plant
Scheda Ballylumford_LO:Ballylumford 13/10/10 11:34 Pagina 2
Contract: Ballylumford
Client: Premier Power Limited
Type of supply contract: EPC Contract
Country: United Kingdom
Repowering: Brownfield
Service Agreement: LTSA
Commercial operation: 2003
Configuration:
500 MW (2+1) Multishaft CC +
100 MW (1+1) Single shaft CC
GEN
GT
HRSG
GEN
ST
Cond.
GEN
GT
HRSG
GEN
GT
GEN
ST
HRSG
Cond.
Main characteristics
Plant main features
Ballylumford is a 600 MW power plant divided in two
units: block 1 which is a 1+1 single shaft configuration
with the AE64.3A gas turbine, this block discharges over
100 MW of electrical power; block 2 which is a 2+1 configuration with two AE94.2 gas turbines to discharge over
500 MW of electrical power. Both the units are able to
fire not only natural gas, but also fuel oil as back up fuel.
Gas Turbine
2 x AE94.2 x 170 MW + 1 x AE64.3A x 67 MW - 50 Hz
Main fuel: natural gas /oil distillate
Steam Turbine
Block 1: 1 x 39 MW - 50 Hz
HP: 85 bar - 538 °C
Block 2: 1 x 189 MW - 50 Hz
HP: 105/23/3.8 bar - 527/304/224 °C
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
Generator
Block 1: WY21Z-073LLT - 135 MVA - 15 kV - 50 Hz air cooled
Block 2 GT units: WY21Z-097LLT - 217 MVA - 15 kV - 50 Hz air cooled
Block 2 ST unit: WX23Z-109LL - 250 MVA - 18 kV - 50 Hz air cooled
Heat Recovery Steam Generator
Block 1: three pressure levels with RH and integrated
deareator.
Block 2: three pressure levels with a common external
deareator
Cooling System
Sea water surface condenser
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
E-mail: ansaldoenergia@aen.ansaldo.it - service2@aen.ansaldo.it - www.ansaldoenergia.it
Scheda Servola_LO:Servola 13/10/10 11:29 Pagina 1
Servola 1 x 172 MW
Combined Cycle
Power Plant
Scheda Servola_LO:Servola 13/10/10 11:29 Pagina 2
Contract: Servola
Client: Elettra GLT
Type of supply contract: EPC Contract
Country: Italy
Repowering: Brownfield
Service Agreement: LTSA
Commercial operation: 2001
Configuration:
200 MW (1+1) Multishaft syngas CC
GEN
GT
GEN
ST
Main characteristics
HRSG
Plant main features
Cond.
Servola combined cycle power plant is a 1+1 configuration
with sea water surface condenser for electrical and thermal
energy production. The main feature to highlight of this
plant is that it is designed to fire waste gas from steel industry such as BFG (blast-furnace gas) and COG (coke-oven
gas). These two fuels are burnt into the combustion chamber of the gas turbine together with natural gas.
The BFG flow is of about 112000 Nm3/h and the COG flow
is of about 19000 Nm3/h. The system is equipped with a
gas turbine model dedicated to this application with two
compressors on its axial line. Thanks to the solution adopted
this plant has a CIP6 certification. Finally the plant can
discharge industrial steam for cogeneration use.
The most important benefit is the use, as fuel, of waste
gas from steel industry, mixed with natural gas.
Gas Turbine
AE94.2K x 109 MW - 50 Hz including two stages: LP axial
and HP centrifugal waste compressors (22 MW)
Fuel: waste gas from steel industry (BFG and COG) mixed
with natural gas
Steam Turbine
The information contained in this publication is provided for illustrative purposes
only. Product descriptions and content may change in consideration of specific market situations. Ansaldo Energia may make changes to the descriptions provided at
any time for technical or commercial reasons.
1 x 70 MW - 50 Hz
HP: 76/9.2 bar - 517/285 °C
Generator
GT & compr.: WY21Z-073LLT - 141 MVA - 15 kV - 50 Hz air cooled
ST unit: WY18Z-066LLT - 94 MVA - 11.5 kV - 50 Hz air cooled
Heat Recovery Steam Generator
Three pressure levels: HP level to feed the steam turbine; IP level to feed the steam turbine and/or for the
cogeneration industrial; the third LP level is to dearate
the condensate flow.
Cooling System
Sea water surface condenser
16152 Genova - Via N. Lorenzi, 8 - Italy
Phone: +39 010 6551 - Fax: +39 010 655 6209
E-mail: ansaldoenergia@aen.ansaldo.it - service2@aen.ansaldo.it - www.ansaldoenergia.it
Stampa Microart’s Spa - Recco (Ge) - 06/2007
Ansaldo Energia has over 150 years experience in
the electrical and mechanical engineering business.
It is a global player in the power generation sector
with an installed capacity of over 177,000 MW.
Ansaldo Energia offers the full range of manufacturing,
engineering, contracting and service activities, as
well as a flexible approach to power projects.
Steam Fossil fired, Gas Turbine and Combined
Cycle, Hydroelectric, Geothermal and Nuclear Power
Plants, supplied turnkey, in separate lots or by components.
The Quality Systems, certified as complying with ISO
9001 by a recognised certification society, cover all
aspects including, design, planning, manufacture,
testing, inspection, installation and servicing.
Petergraf
Progetto1:Layout 1 30/05/11 12:12 Pagina 2
16152 Genova - Italy - Via N. Lorenzi, 8
Phone. +39.010.6551 - Fax +39.010.6556209
E-mail: ansaldoenergia@aen.ansaldo.it
www.ansaldoenergia.it