Customer Guide to Electric Service Requirements

Transcription

Customer Guide to Electric Service Requirements
Customer
Guide to
Electric Service
Requirements
Tillamook
People’s
Utility
District
Power Services Group
PO Box 433
1115 Pacific Avenue
Tillamook, Oregon 97141
OFFICE: 503.815.8629
FAX: 503.815.8648
TOLL FREE: 800.422.2535
www.tpud.org
MARCH 2008
Foreward
The information contained in this Customer Guide to Electric Service
Requirements is intended to serve as a guide for electrical
contractors, architects, building contractors, engineers, and other
customers; to provide information needed for determining
acceptable methods of receiving electric service from Tillamook
PUD; and is intended to promote a safe, efficient method for
receiving electrical service.
These requirements are based on Tillamook PUD policies and
standards in effect at the time of publication. Tillamook PUD
reserves the right to change the requirements, specifications, and
policies without prior notice. Contact Tillamook PUD for the
most current requirements.
This handbook does not include all possible standards and
specifications required by Tillamook PUD or by state, federal, or
local codes. It is the customer’s responsibility to conform to
Tillamook PUD policies and standards, as well as all applicable
state, federal, and local codes.
Prior to beginning any work, contact the Tillamook PUD
Engineering Department to determine the project requirements.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
i
Contact Information
Tillamook PUD Telephone Numbers
Engineering Department
503-815-8629
Operations Department
503-842-2122
Toll-free:
800-422-2535
FAX:
Engineering Department
Operations Department
503-815-8648
503-815-8642
Frequently Requested Telephone Numbers
Tillamook County Community Development
503-842-3408
Electrical Inspector
503-842-3440
Locate Service
Dial 8-1-1
Website Address
WWW.TPUD.ORG
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
ii
Table of Contents
Foreward ....................................................................................................................................... i
Contact Information ..................................................................................................................... ii
Section 1—General Requirements
1.1
Introduction................................................................................................................... 1-1
1.2
Request for Electrical Services Form ........................................................................... 1-2
1.3
Types of Service ........................................................................................................... 1-2
1.4
Line Extension Policy ................................................................................................... 1-3
1.5
Cost Estimates............................................................................................................... 1-3
1.6
Reimbursable Work Order Form (Form T-8) ............................................................... 1-3
1.7
Easements ..................................................................................................................... 1-4
1.8
Standard Service Voltages ............................................................................................ 1-4
1.9
Service Entrance Equipment......................................................................................... 1-4
1.10 Quality of Service ......................................................................................................... 1-5
1.11 Protective Devices ........................................................................................................ 1-6
1.12 Modifying Existing Electrical Service.......................................................................... 1-6
1.13 Flood Areas................................................................................................................... 1-7
1.14 Hazardous Electrical Service ........................................................................................ 1-7
1.15 Service Beyond the Meter............................................................................................. 1-7
1.16 Fault Current ................................................................................................................. 1-8
1.17 Location of Meter (Point of Delivery) .......................................................................... 1-8
1.18 Meter Seals.................................................................................................................... 1-8
1.19 Location of Pad-mounted Transformers ....................................................................... 1-8
1.20 Power Factor ................................................................................................................. 1-8
1.21 Clearance to Existing Lines .......................................................................................... 1-9
Section 2—Temporary Service, Overhead and Underground
2.1
General.......................................................................................................................... 2-1
2.2
Temporary Overhead Service ....................................................................................... 2-2
2.3
Temporary Underground Service ................................................................................. 2-2
Section 3—Overhead Permanent Service
3.1
General.......................................................................................................................... 3-1
3.2
Service Arrangements................................................................................................... 3-2
3.3
Service on Gable End of Building ................................................................................ 3-2
3.4
200- and 400-Ampere Mobile or Manufactured Home Service (Overhead to
Underground)................................................................................................................ 3-3
3.5
Service Locations-Manufactured Homes...................................................................... 3-3
3.6
Minimum Service Drop Clearances.............................................................................. 3-3
3.7
Travel Trailer Service ................................................................................................... 3-3
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
iii
Section 4—Underground Permanent Service
4.1
General.......................................................................................................................... 4-1
4.2
Service Arrangements................................................................................................... 4-2
4.3
Meter Pedestal Arrangement......................................................................................... 4-3
4.4
Manufactured or Mobile Homes................................................................................... 4-3
4.5
Locating Underground Facilities .................................................................................. 4-3
4.6
Three-Phase Service...................................................................................................... 4-4
Section 5—Trenching, Conduit, and Vault Specifications
5.1
Trenching Requirements............................................................................................... 5-1
5.2
Backfill.......................................................................................................................... 5-2
5.3
Locating Underground Facilities .................................................................................. 5-2
5.4
Conduit Installation Requirements ............................................................................... 5-2
5.5
Conduit Specifications .................................................................................................. 5-5
5.6
Vault Installation........................................................................................................... 5-5
5.7
Vault Purchase .............................................................................................................. 5-6
5.8
Vault and Lid Specifications......................................................................................... 5-6
Section 6—Metering
6.1
General.......................................................................................................................... 6-1
6.2
Energizing the Service .................................................................................................. 6-2
6.3
Meter Locations ............................................................................................................ 6-2
6.4
Sealing and Locking Requirements .............................................................................. 6-4
6.5
Clearances ..................................................................................................................... 6-5
6.6
Meter Base Requirements ............................................................................................. 6-5
6.7
Self-Contained versus CT Metering ............................................................................. 6-7
6.8
Current Transformer Enclosures................................................................................... 6-7
6.9
Current Transformer Installation .................................................................................. 6-8
6.10 Current Transformer Conduit ....................................................................................... 6-8
6.11 Instrument Transformer Rated Meter Worksheet ......................................................... 6-9
6.12 Current Transformer Switchboard Metering ................................................................ 6-9
6.13 Pulse Initiator Output.................................................................................................. 6-10
Section 7—Area Lights
7.1
General.......................................................................................................................... 7-1
Section 8—Right-of-Way Clearing
8.1
Customer Requirements................................................................................................ 8-1
Section 9—Generation – Permanent and Temporary
9.1
Generator Safety ........................................................................................................... 9-1
9.2
Portable Generators....................................................................................................... 9-1
9.3
Fixed Generators........................................................................................................... 9-1
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
iv
List of Figures
2-1
100- to 200-amp Meter Base Temporary Overhead Service ........................................ 2-3
2-2
100- to 200-amp Meter Base Temporary Underground Service .................................. 2-4
3-1
3-2
200- to 400-amp Meter Base Temporary Overhead Service ........................................ 3-4
Gable End of Building Service Requirements .............................................................. 3-5
4-1
4-2
4-3
200- to 400-amp Meter Base Required Underground Service Arrangement ............... 4-5
Conduit Installation Guidelines for Secondary Riser Poles.......................................... 4-6
200- to 400-amp Meter Base Underground Pedestal Installation................................. 4-7
5-3
5-4
5-5
5-6
5-7
5-8
5-9
5-11
5-12
5-20
5-21
5-22
5-23
Vault E11 ...................................................................................................................... 5-8
Single Phase Transformer Vault Cover ........................................................................ 5-9
Single Phase Vault Cover ........................................................................................... 5-10
Single Phase Sectionalizing Vault Cover ................................................................... 5-11
Vault E19 .................................................................................................................... 5-12
3 Phase Transformer Vault Cover............................................................................... 5-13
V or 3 Phase Vault Cover ........................................................................................... 5-14
V or 3 Phase Sectionalizing Vault Cover ................................................................... 5-15
1500 KVA Transformer Vault Cover ......................................................................... 5-16
Requirements for Conduit Routing into Vaults .......................................................... 5-17
Conduit Installation Guidelines for Secondary Pedestals........................................... 5-18
Trenching Requirements............................................................................................. 5-19
Underground Utility Equipment Locations ................................................................ 5-20
6-1
6-2
6-4
6-5
6-6
6-7
6-8
6-9
6-10
6-11
Service Entrance Equipment—Overhead 1-Phase...................................................... 6-11
Service Entrance Equipment – Three Phase Installations........................................... 6-12
Current Transformer Enclosure Overhead 1-Phase Installations................................ 6-13
Current Transformer Enclosure Underground 1-Phase Installations.......................... 6-14
Current Transformer Enclosure Overhead 3-Phase Installations................................ 6-15
Current Transformer Enclosure Underground 3-Phase Installations.......................... 6-16
Current Transformer Diagrams-Mounting Bracket .................................................... 6-17
Recessed Meter Clearances......................................................................................... 6-18
Meter Cabinet Enclosure............................................................................................. 6-19
Ring-type Meter Socket with Test Switch Provision Min. Socket Dimensions ........... 6-6
8-1
8-2
8-3
Right-of-Way Clearing Guide....................................................................................... 8-2
The Right Tree for the Right Place ............................................................................... 8-3
The Clear Zone ............................................................................................................. 8-4
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
v
List of Tables
1-1
Standard Service Voltages ............................................................................................ 1-4
5-1
Trenching Requirements............................................................................................... 5-1
5-2
Conduit Installation Requirements ............................................................................... 5-3
5-3
Conduit Specifications – Schedule 40 PVC.................................................................. 5-4
5-4
Conduit Specifications – HDPE.................................................................................... 5-5
5-5
Single-Phase Installations – Vault and Lid Specifications ........................................... 5-6
5-6
Three-Phase Installations – Vault and Lid Specifications ............................................ 5-7
6-1
Self-Contained versus CT Metering Requirements ...................................................... 6-7
6-2
CT Enclosure Minimum Dimensions ........................................................................... 6-7
6-3
Instrument Metering Wire Size and Color Codes......................................................... 6-9
8-1
Right-of-Way Clearances.............................................................................................. 8-1
Appendix A
Line Extension Agreement
Reimbursable Work Order Form (Form T-8)
Application for Service
Request for Electrical Services – Residential Service
Request for Electrical Services – Commercial Service
Request for Electrical Services – Land Development
Request for Electrical Services – Service Change
Instrument Transformer Rated Meter Worksheet
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
vi
Section 1
General Requirements
1.1
Introduction
The information in this handbook applies to Tillamook People’s Utility
District (Tillamook PUD) customers requiring electrical service. This
handbook provides the majority of the information and requirements that
will be needed by the customer. It does not include all possible standards,
specifications, and policies required by Tillamook PUD or by state,
federal, and local requirements. It is the customer’s responsibility to
adhere to existing policies or future changes. Please contact the Tillamook
PUD Engineering Department to determine the requirements of the
project.
The customer is responsible for:
9 Completing the appropriate Request for Electrical Services form. (See
samples in Appendix A.)
9 Completing the Application for Service card. (See sample in
Appendix A.)
9 Signing Tillamook PUD’s Line Extension Agreement or a
Reimbursable Work Order Form. (See samples in Appendix A).
9 Providing payment, obtaining an approved loan application for the
Line Extension Agreement, or signing a Reimbursable Work Order
Form. (For information regarding the loan program, contact the
Energy Services Department at 503-815-8646).
9 Signing or obtaining required notarized signatures for easement(s)
(if required). Easements will be prepared on Tillamook PUD forms for
the installation, operation, and maintenance of Tillamook PUD
facilities.
9 Obtaining applicable permits and inspections from appropriate public
agencies.
9 Notifying Tillamook PUD when the meter base(s) has (have) passed
electrical inspection ("green tagged").
9 Providing and installing all equipment to meet Tillamook PUD
specifications and policies.
9 Keeping the meter base(s) visible and accessible per Tillamook PUD
specifications and policies.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-1
9 Providing and clearing a right-of-way for overhead and underground
installations in accordance with Tillamook PUD specifications. (Refer
to Section 8, Right-of-Way Clearing.)
9 Meeting or exceeding all applicable provisions of the National Electric
Code (NEC); National Electrical Safety Code (NESC); State of Oregon
Electrical Specialty Code; and state, federal, and local applicable
requirements.
1.2
Request for Electrical Services Form
Each prospective customer desiring electrical service must complete a
Request for Electrical Services form and an Application for Service card
(See samples in Appendix A). The Request for Electrical Services form
initiates the new service process and provides Tillamook PUD personnel
with critical information needed to design the service.
The customer shall provide Tillamook PUD with accurate load data and
plot plan. The plot plan shall show the location of property corners,
property lines, and location of existing and proposed facilities (drain
fields, home site, outbuildings, or well).
It is recommended that customers contact Tillamook PUD early in the
project to ensure the successful design and installation of electric service
in a timely manner.
To obtain a copy of the Request for Electrical Services form:
Contact the Engineering Department at:
503-815-8629
800-422-2535
Visit the Tillamook PUD website at:
WWW.TPUD.ORG
1.3
Types of Service
Tillamook PUD provides both overhead and underground temporary and
permanent service. It is strongly recommended that permanent service be
underground. The service, whether single- or three-phase, will be 60 hertz
alternating current.
Refer to specific sections for more complete information
on the following types of service:
Temporary Service
Î
Section 2
Overhead Service
Î
Section 3
Underground Service
Î
Section 4
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-2
1.4
Line Extension Policy
It is the policy of Tillamook PUD to extend service to all customers within
its exclusive service territory provided that the service extensions comply
with Tillamook PUD policies and with all applicable provisions of the
NEC; NESC; State of Oregon Electrical Specialty Code; and other state,
federal, and local requirements.
The applicant for an electric line extension must own, have a contract to
purchase, or have a lease of sufficient duration (as determined by
Tillamook PUD) to the property or premises before Tillamook PUD will
provide the line extension.
To obtain a line extension, the applicant or their representative shall
complete the Request for Electrical Service form.
Tillamook PUD may require the applicant to supply evidence of approval
for construction by the city, county, or other governing agencies. Such
evidence of approval to construct is to provide assurance of the applicant's
intent to proceed with construction.
Tillamook PUD requires notification by the applicant of any property
deed restrictions or zoning requirements that may affect the installation of
Tillamook PUD electrical facilities.
1.5
Cost Estimate
Tillamook PUD will prepare a cost estimate for each line extension. The
cost estimate shall include all anticipated Tillamook PUD costs for the line
extension. All cost estimates are valid for 180 days and the construction of
the line extension must be completed within 180 days from the date of the
cost estimate letter.
If the construction is not completed within 180 days of the date of the
estimate letter, a new cost estimate and Line Extension Agreement will be
prepared.
1.6
Reimbursable Work Order Form Policy (Form T-8)
When the customer requests Tillamook PUD to relocate or modify
Tillamook PUD facilities for their convenience, Tillamook PUD will
prepare a cost estimate based on standard billing rates for man-hours,
materials, equipment, associated overhead expenses, and a 10 percent
contingency.
The cost estimate is valid for 180 days and construction must be
completed during the 180-day period. The estimated cost shall be paid by
the customer prior to the start of construction. A refund, if greater than
$100, will be made to the customer in the event the actual cost of
construction is less than the estimated cost.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-3
1.7
Easements
Tillamook PUD requires easements prepared on Tillamook PUD easement
forms providing for the installation, operation, and maintenance of all
primary voltage power lines and where necessary for secondary and
service lines. Prior to installation of facilities, it is the customer's
responsibility to provide a legal property description to Tillamook PUD
for easement preparation. The customer is responsible for signing or
obtaining all necessary notarized signatures on Tillamook PUD-prepared
easements.
The customer is responsible for signing or obtaining all
necessary notarized signatures on Tillamook PUDprepared easements.
For parcels owned by corporations, limited liability corporations, or
family trusts, documentation will be required indicating all parties legally
authorized to sign on behalf of the entity.
For land development(s), parcels being developed as subdivisions or
partition plats will require a metes and bounds description as well as a
copy of the most recently registered partition plat or subdivision plat.
Documentation will be required specifying all parties legally authorized
to sign on behalf of the entity.
1.8
Standard Service Voltages
The following table shows the standard services provided by Tillamook
PUD.
Table 1-1
Standard Service Voltages
Standard Service Voltages
Service Type
Single-Phase
1
Voltage
120 Volts
120/240 Volts
Three-Phase
208Y/120 Volts
480Y/277 Volts
Network
208Y/120 Volts
1
Any service greater than 600 amps shall be three-phase.
1.9
Service Entrance Equipment
The customer is responsible for providing, installing, and wiring service
entrance equipment to conform to or exceed all provisions of the NEC;
NESC; State of Oregon Specialty Code; and other state, federal, and local
applicable requirements.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-4
The customer or their contractor shall connect their equipment to keep the
load, under normal operating conditions, balanced within plus or minus
10 percent of the average load across the phase wires.
The customer is responsible for maintaining service entrance equipment;
therefore, Tillamook PUD strongly recommends stainless steel (meter
bases and current transformer enclosures) to mitigate rust and equipment
deterioration.
All individual three-phase service installations require a neutral (fourth)
wire to be provided and installed in the service mast. The neutral must
meet the minimum size as set out in the NEC and shall be color-coded
white.
When aluminum conductors are used, the service panel must be
Underwriters Laboratory (UL) listed or approved and clearly marked by
the manufacturer that it is acceptable for aluminum conductors.
Parallel conductors shall be uniquely identified with the appropriatecolored tape.
1.9.1
UL Listed Equipment
Only UL listed or approved service entrance equipment of the
proper rating may be installed.
1.9.2
Grounding Service Equipment
All service equipment shall be grounded in compliance with all
provisions of the NEC; NESC; State of Oregon Specialty Code;
and other state, federal, and local applicable requirements.
1.9.3
Service Panels and Disconnect Switches
Service panels and disconnect switches with associated
equipment exposed to the weather shall be of a rain-tight type
(NEMA 3R) and shall be manufactured for that purpose.
1.9.4
Service Entrance Wires and Cables
Service entrance wires and cables shall be sized in accordance
with the NEC and extend from the weatherhead a minimum of
18 inches.
1.10 Quality of Service
A customer shall not interfere with the quality of their own service or that
of another customer.
In situations where the customer desires voltage control within unusually
close limits, Tillamook PUD may require the customer to provide, at their
own expense, special or additional power-conditioning equipment.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-5
Loads greater than 100 kilowatts three-phase or 30 kilowatts single-phase
from Tillamook PUD’s secondary system shall not be switched on and off
more frequently than once each hour. The maximum increased load shall
not be greater unless authorized by the Tillamook PUD Engineering
Department.
The customer may be required to furnish and install special switching
equipment to reduce the magnitude of load which will be cycled on and
off. Inquiries as to the necessity of special equipment should be directed
to the Tillamook PUD Engineering Department.
Tillamook PUD requires the customer’s electrical facility to meet the
power quality standards presented in Section 10 of the latest IEEE Std. 519,
IEEE Recommended Practices and Requirements for Harmonic Control in
Electrical Power Systems, entitled “Recommended Practices for Individual
Customers.”
1.10.1
Motors
Single-phase motors, up to and including 10 horsepower (HP),
may be served by single-phase at 240 volts. Motors larger than
10 HP shall be three-phase, unless written approval is obtained
from the Tillamook PUD Engineering Department.
All single-phase motors shall not exceed the maximum locked
rotor amps listed in the National Electrical Manufacturers
Association (NEMA) Standards, unless approved in writing by
the Tillamook PUD Engineering Department.
1.11 Protective Devices
It shall be the sole responsibility of the customer to provide adequate
protection on all installations against single-phasing on three-phase
motors.
1.12 Modifying Existing Electrical Service
Customers modifying an existing service will be required to make repairs
and changes in order to conform to or exceed all provisions of the NEC;
NESC; State of Oregon Specialty Code; and other state, federal, and local
applicable requirements.
Notify the Tillamook PUD’s Operations Department
(503-842-2122 or 800-842-2122) as soon as possible for all
situations requiring disconnecting and reconnecting of
service.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-6
Capacity increases to existing residential, commercial, farm, industrial,
irrigation, pumping, lighting, and indeterminate electrical facilities shall
be treated as though the increased capacity requirements were a new load.
1.13 Flood Areas
Areas within Tillamook PUD’s service area that Tillamook PUD
determines are subject to flooding will require special consideration.
Tillamook PUD will not install its equipment or provide service to
customer-owned equipment that Tillamook PUD does not consider
suitable for such locations.
1.14 Hazardous Electrical Service
The customer’s service entrance equipment must be in accordance with
Tillamook PUD’s electrical service specifications and policies. If the
equipment is in such a condition to be dangerous to life or property, the
customer will be required to make the necessary repairs and changes in
order to conform to or exceed all provisions of the NEC; NESC; State of
Oregon Specialty Code; and other state, federal, and local applicable
requirements.
If a customer creates a violation of the NEC; NESC; State of Oregon
Specialty Code; or other state, federal, and local applicable requirements,
the customer will be required to take corrective action.
Tillamook PUD reserves the right to discontinue service to
any customer who fails to make repairs and/or changes
required to remove the danger to life or property.
The service will remain disconnected until hazardous conditions and/or
equipment are restored to a safe and secure condition. The service will
not be reconnected until there is an inspection and approval by the state
electrical inspector.
1.15 Service beyond the Meter
Customers requiring more than one overhead service beyond the
metering point may have such services installed by Tillamook PUD at the
customer's expense. Ownership of these services remains with the
customer. Underground services beyond the metering point will be
owned, installed, and maintained by the customer.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-7
1.16 Fault Current
Upon request, Tillamook PUD will supply the available fault current at
the customer's service entrance. It is the customer's responsibility to
install equipment with sufficient fault current interrupting capability.
1.17 Location of Meter (Point of Delivery)
It is in the mutual interest of the customer and Tillamook PUD to locate
meters where reading, testing, and replacement can easily occur. See
Section 6 for guidelines.
The point of delivery, specified by Tillamook PUD, is that point where
Tillamook PUD-owned facilities connect to the customer-owned facilities.
Only one point of delivery to any dwelling or building is allowed except
by written permission by Tillamook PUD and the electrical inspector.
Customers desiring service must obtain Tillamook PUD's
approval of the meter location(s) prior to wiring the premises.
For specific information about meter location(s), refer to
Section 6, Meter Locations.
1.18 Meter Seals
Meter seals or locks are placed on meters and associated service
equipment to prevent injury or tampering. Seals or locks are not to be
removed except by Tillamook PUD personnel. Broken seals or locks are
justification for Tillamook PUD to initiate a theft of service investigation.
1.19 Location of Pad-mounted Transformers
Tillamook PUD requires that transformers be located at least ten feet from
a combustible structure (including a building with metal siding on wood
framing) to comply with applicable fire codes. A minimum of 3 feet is
required between non-combustible surfaces and pad-mounted
transformers.
1.20 Power Factor
The customer will maintain 100 percent power factor. A charge for power
factor less than 95 percent is specified in Tillamook PUD’s current rate
schedule. It is recommended that the customer install corrective shunt
capacitors to make the most effective use of the electrical system.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-8
1.21 Clearance to Existing Lines
Tillamook PUD’s goal is to ensure your project worksite is as safe as
possible for both the public and its employees. The High Voltage Overhead
Line Safety Act in part states the following:
1.21.1
Restricted Space
“For lines rated between 600 volts and 50 kV, the restricted
space extends 10 feet in all directions from the surface of the
line or equipment.
For lines rated over 50 kV, the restricted space extends 10
feet plus 0.4 inch for each 1 kV over 50 kV, or twice the length
of the insulator (but never less than 10 feet) in all directions
from the surface of the line or equipment.”
1.21.2
General Requirements
Do not enter or perform any function or activity (such as
handling, erecting, operating, transporting, and storing tools,
equipment, materials, and moving a building or structure)
within the restricted space surrounding an overhead highvoltage line or equipment unless proper notification is provided
to Tillamook PUD and the line and/or equipment is deenergized and visibly grounded by Tillamook PUD.
If a violation occurs, Tillamook PUD will request a stop work
order from the Tillamook County Community Development
Department. Work will not be allowed to resume until an
agreement is reached for construction to resume safely.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
1-9
Section
Section
22
Temporary
TemporaryService
Service
Overhead and Underground
2.1
General
Temporary services for construction work shall conform to Tillamook
PUD requirements and shall be located to provide protection to the meter
and situated to be usable throughout the construction period. Location of
the temporary service is to be approved by Tillamook PUD’s Engineering
Department prior to placement.
Customer installations shall meet or exceed all provisions of the NEC;
NESC; State of Oregon Specialty Code; and other state, federal, and local
applicable requirements. Temporary services will be disconnected upon
expiration of the building permit or when permanent service is installed.
Once the customer has completed the Request for Electrical Services Form
and Application for Service Card (see samples in Appendix A), an
Engineering Field Representative will visit the site to determine the
location of the temporary meter base and the route for the service lines.
The following items must be completed before temporary service can
be energized:
9 Request for Electrical Services form. (See samples in Appendix A.)
9 Application for Service card. (See sample in Appendix A.)
9 Signed Line Extension Agreement, if applicable. (See sample in
Appendix A.)
9 Providing payment, obtaining an approved loan application for the
Line Extension Agreement, or signing a Reimbursable Work Order
Form. (For information regarding the loan program, contact the
Energy Services Department at 503-815-8646).
9 Signing or obtaining required notarized signatures for easement(s) (if
required). Easements will be prepared on Tillamook PUD easement
forms and provide for the installation, operation, and maintenance of
Tillamook PUD facilities.
9 Obtaining applicable permits and inspections from appropriate public
agencies.
9 Notifying Tillamook PUD when the temporary meter base(s) has
(have) passed electrical inspection ("green tagged").
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
2-1
9 Providing, installing, and maintaining all equipment to meet
Tillamook PUD specifications and policies.
9 Keeping the meter base(s) visible and accessible per Tillamook PUD
specifications and policies.
9 Providing and maintaining a right-of-way clearing, if applicable, for
overhead and underground installations in accordance with Tillamook
PUD specifications and policies. (Refer to Section 8, Right-of-Way
Clearing.)
9 Installing temporary post, bracing and associated meter base, and
ground rods to meet or exceed all provisions of the NEC; NESC; State
of Oregon Specialty Code; and other state, federal, and local applicable
requirements.
2.2
Temporary Overhead Service—Figure 2-1
The customer shall install the temporary post, bracing, and associated
meter base. Temporary services may not be placed on trees or Tillamook
PUD poles. The meter base shall be UL listed, meeting NEC, NESC, and
Tillamook PUD’s specifications and policies as shown in Figure 2-1.
Two-hundred amperes temporary service assemblies shall use galvanized
rigid steel or rigid electrical conduit or Schedule 40 conduit. The
placement of an overhead temporary meter base should be within 10 feet
of a power pole where secondary voltage is available.
Temporary services shall be placed to avoid crossing overhead
conductors, streets, and driveways. Taller temporary posts may be
required if crossings cannot be avoided.
2.3
Temporary Underground Service—Figure 2-2
Underground temporary services are available in those areas where
existing electric facilities are underground. Placement of underground
temporaries should be within 10 feet of a secondary pedestal (see
Figure 2-2).
Conductor to serve a temporary WILL NOT be
installed in the permanent conduit.
The customer shall install the temporary post bracing with conduit, meter
base, and ground rod. All trenching and backfilling shall meet Tillamook
PUD specifications and is the responsibility of the customer. Conduits
may or may not be required from the temporary post to Tillamook PUD’s
point of connection.
The location of the temporary post must be approved by the Tillamook
PUD Engineering Department.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
2-2
Section 3
Overhead Permanent Service
3.1
General
The requirements of this section are for residential and small commercial
installations. For larger commercial or three-phase installations, contact
the Tillamook PUD Engineering Department.
Once the customer has completed the Request for Electrical Service Form
and Application for Service Card (see samples in Appendix A), an
Engineering Field Representative will visit the site to determine the
location of the meter base and the route for the overhead service lines. At
that time, the wire-out location on the building/structure shall be
approved by the Tillamook PUD Engineering Department.
The following items must be completed before overhead permanent
service will be energized:
9 Request for Electrical Services form. (See samples in Appendix A.)
9 Application for Service card. (See sample in Appendix A.)
9 Signed Line Extension Agreement (See sample in Appendix A).
9 Providing payment (or obtaining an approved loan application for the
Line Extension Agreement or Reimbursable Work Order Form). (For
information regarding the loan program, contact the Energy Services
Department at 503-815-8646).
9 Providing payment, obtaining an approved loan application for the
Line Extension Agreement, or signing a Reimbursable Work Order
Form. (For information regarding the loan program, contact the
Energy Services Department at 503-815-8646).
9 Obtaining applicable permits and inspections from appropriate public
agencies.
9 Notifying Tillamook PUD when the meter base(s) has (have) passed
electrical inspection ("green tagged").
9 Providing and installing all equipment to meet Tillamook PUD
specifications and policies.
9 Keeping meter base visible and accessible per Tillamook PUD
specifications and policies.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
3-1
9 Providing and clearing a right-of-way for overhead installations in
accordance with Tillamook PUD specifications and requirements.
(Refer to Section 8, Right-of-Way Clearing.)
9 Meeting or exceeding all applicable provisions of the National Electric
Code (NEC); National Electrical Safety Code (NESC); State of Oregon
Electrical Specialty Code; and state, federal, and local applicable
requirements.
3.2
Service Arrangements—Figure 3-1
3.2.1
Service Mast
The service mast for overhead 200- and 400-ampere services,
whether flush- or surface-mounted, must extend through the
roof a minimum of 36 inches. Service masts that extend more
than 36 inches shall be guyed. Two-hundred amperes service
assemblies shall be a minimum of 2-inch galvanized rigid steel.
Four-hundred ampere services shall use a minimum of 3-inch
galvanized rigid steel. Service conductors shall protrude a
minimum of 18 inches out of the weatherhead. The center of the
meter socket shall be located between 5½- and 6½-feet above
final grade.
The customer shall be required to supply, install, and maintain
meter-mounting equipment in accordance with Tillamook
PUD’s specifications and policies. All meter bases, masts, and
weatherheads remain the property of the customer.
3.2.2
Meter Location
The meter shall be located on the front or side of the structure
closest to utility facilities unless an alternate location is
approved by the Tillamook PUD Engineering Department. If a
meter is located on the side of a structure, it shall be placed
within 10 feet of the front corner.
For more specific information about meter location, refer to
Section 6, Meter Locations.
3.3
Service on Gable End of Building—Figure 3-2
Where conditions permit and upon approval of Tillamook PUD's
Engineering Department, a service mast may be installed on the gable end
of a building.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
3-2
The minimum requirements are:
9 The overhead service wire shall strike the building not less than 13 feet
above the finish grade.
9 A 5/8-inch eye bolt with 2¼-inch square washers is to be installed by
the customer through a secure 2-by-4 or larger wooden member.
9 The center of the meter is to be installed at 5½ to 6½ feet above the
final grade.
9 The eye bolt shall be positioned 22 inches to the side of and 8 inches
below the weatherhead. The eye bolt may be furnished by Tillamook
PUD. (See Figure 3-2.)
9 Standard duty pipe straps shall be installed every 3 feet along the
length of the service mast.
9 Service mast must be galvanized rigid steel or Schedule 40 PVC
electrical conduit.
9 Minimum clearances around windows, above decks, etc., shall be
three feet and meet or exceed all applicable provisions of the National
Electric Code (NEC); National Electrical Safety Code (NESC); State of
Oregon Electrical Specialty Code; and state, federal, and local
applicable requirements.
3.4
200- and 400-Ampere Services to Mobile or Manufactured
Home Service
All efforts should be made to mount meter sockets on the structure.
Exceptions may be approved by the Tillamook PUD Engineering
Department on a case-by-case basis.
3.5
Service Locations—Manufactured Home
A meter pole shall be located not more than 30 feet from the exterior wall
of the manufactured home it serves. When exceptions are approved for
meter poles, they shall be located along the front or along the side of the
structure within 10 feet from the front corner.
3.6
Minimum Service Drop Clearances
For minimum service drop clearances, contact the Tillamook PUD
Engineering Department.
3.7
Travel Trailer Service
Installations should be on post-mounted meter socket or a mobile home
pedestal. Exceptions may be granted by the Tillamook PUD Engineering
Department.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
3-3
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
3-4
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
3-5
Section 4
Underground Permanent Service
4.1
General
The requirements of this section are for residential and small commercial
installations. For larger commercial or three-phase installations, contact
the Tillamook PUD Engineering Department.
Once the customer has completed and submitted the Request for Electrical
Services form and Application for Service Card (see samples in
Appendix A), an Engineering Field Representative will visit the site to
determine the location of the meter base and the route for the
underground service lines. The meter base location on the structure shall
be approved by the Tillamook PUD Engineering Department.
The following items must be completed before underground service
will be energized:
9 Request for Electrical Services form. (See samples in Appendix A.)
9 Application for Service card. (See sample in Appendix A.)
9 Signed Line Extension Agreement. (See sample in Appendix A.)
9 Providing payment (or obtaining an approved loan application for the
Line Extension Agreement or Reimbursable Work Order Form). (For
information regarding the loan program, contact the Energy Services
Department at 503-815-8646).
9 Providing payment, obtaining an approved loan application for the
Line Extension Agreement, or signing a Reimbursable Work Order
Form. (For information regarding the loan program, contact the
Energy Services Department at 503-815-8646).
9 Obtaining applicable permits and inspections from appropriate public
agencies.
9 Notifying Tillamook PUD when the meter base(s) has (have) passed
electrical inspection ("green tagged").
9 Providing and installing all equipment to meet Tillamook PUD
specifications and policies.
9 Keeping meter base(s) visible and accessible per Tillamook PUD
specifications and policies.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
4-1
9 Providing and maintain a right-of-way for underground installations
in accordance with Tillamook PUD specifications and policies. (Refer
to Section 8, Right-of-Way Clearing.)
9 Meeting or exceeding all applicable provisions of the National Electric
Code (NEC); National Electrical Safety Code (NESC); State of Oregon
Electrical Specialty Code; and state, federal, and local applicable
requirements.
9 Complying with all conduit and vault installation requirements
specified in Section 5.
4.2
Service Arrangements—Figures 4-1 and 4-2
The 2-inch Schedule 40 PVC in the case of 200-ampere service or the 3-inch
Schedule 40 PVC in the case of a 400-ampere service shall be installed with
either surface- or flush-mounted meter bases. The center of the meter
socket is to be located 5½ to 6½ feet above final grade. The conduit must
be placed through the footing wall for flush-mounted or on the building
exterior for surface-mounted, with a 90-degree sweep, buried to a depth of
36 inches from final grade level to the top of the conduit.
The location of the meter on the building and route of the trench shall be
approved by the Tillamook PUD Engineering Department. (For specific
information, refer to Section 6, Metering for Specific Information.)
All service conduit will be installed by the customer. The customer shall
install Tillamook PUD-provided warning tape from the meter base to the
secondary pedestal, pad-mount transformer, or pole 12 inches above the
conduit. A ¼-inch poly pull rope or equivalent with a tensile strength of
600 pounds or greater shall be installed into the conduit.
Conduit installation must be inspected and approved by the
Tillamook PUD Engineering Department prior to backfilling.
Conduit installations must be inspected and approved by the Tillamook
PUD Engineering Department prior to backfilling.
4.2.1
Meter Location
The meter shall be located on the front or side of the structure
closest to the utility facilities unless an alternate location is
approved by the Tillamook PUD Engineering Department. If a
meter is located on the side of a structure, it shall be placed
within 10 feet of the front corner.
For more specific information about meter locations, refer to
Section 6, Meter Locations.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
4-2
4.3
Meter Pedestal Arrangements—Figure 4-3
Location of the meter pedestal shall be approved by the Tillamook PUD
Engineering Department. The meter pedestal may be a manufactured
meter pedestal or a customer-assembled meter pedestal. (See Figure 4-2
for specifications and requirements and Section 6, Meter Locations, for
additional information.)
Compacted gravel or concrete backfill is required around the pedestal.
The customer is responsible for trenching to meet Tillamook PUD
specifications and requirements, installing Tillamook PUD-provided
warning tape and a ¼-inch poly pull rope or equivalent with a tensile
strength of 600 pounds or greater and backfilling.
When a meter pedestal is located in a parking area, it must be located so
that parked vehicles will not restrict meter accessibility or be damaged by
vehicular traffic.
The customer is responsible for all underground services beyond the
metering point.
Conduit installation must be inspected and approved by the
Tillamook PUD Engineering Department prior to backfilling.
For more specific information about meter pedestal arrangement, refer to
Figure 4-2.
4.4
Manufactured or Mobile Homes
Manufactured or mobile home meter pedestals shall be located within
30 feet of the manufactured or mobile homes and within 10 feet of the
front corner.
4.5
Locating Underground Facilities
Before beginning to dig on any project, contact the locating service. There
is no charge to the customer for this service. All underground utilities in
the area will be located and identified.
CALL BEFORE YOU DIG!
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
4-3
4.6
Three-Phase Services
For all three-phase services larger than 100 kVA, the point of delivery
from a pad-mounted transformer shall be the secondary bushings of the
serving transformer, unless a better point of delivery is designated by the
Tillamook PUD’s Engineering Department.
The customer shall provide secondary compression lugs at the
transformer. If Tillamook PUD determines installation of a pad-mounted
transformer is not feasible, the installation of the underground service will
be from an overhead assembly (including conductor) to a splice vault or
pedestal near the base of the pole, unless a better point of delivery is
designated by the Tillamook PUD Engineering Department.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
4-4
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
4-5
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
4-6
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
4-7
Section 5
Trenching, Conduit, and Vault
Specifications
5.1
Trenching Requirements—Figure 5-22 and 5-23
Table 5-1 depicts general requirements for trenching. Refer to Figure 5-22
or contact the Tillamook PUD Engineering Department for further
information.
ALL exceptions must be approved by the Tillamook PUD
Engineering Department.
Table 5-1
Trenching Requirements
Requirement
Primary Voltage
Conduit
Secondary Voltage
Conduit
DEPTH
48 inches deep, measured
from top of conduit.
36 inches deep, measured
from top of conduit.
PLACEMENT IN
TRENCH
Center and bottom of the
trench.
Either on the right or left
side of trench and on the
bottom.
LAYOUT
Trench path must be approved by the TPUD Engineering
Department.
WARNING TAPE
Installed at a minimum of 12 inches above conduit.
JOINT TRENCHES
TELEPHONE AND
TELEVISION CABLES
12 inches above electric
service, placed on the right or
left side of trench. Refer to
Figure 5-22 and 5-23 for
specifications.
WATER AND SEWER
Electrical will be located below all water and sewer lines
with a minimum 2-foot horizontal and 2-foot vertical
separation.
Placed on the right or
left side of trench. Refer
to Figure 5-22 and 5-23
for specifications.
Exceptions:
All exceptions must be approved by the Tillamook PUD Engineering Department
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-1
5.2
Backfill
A selected earth cushion around conduits is required. Final backfill shall
be done on all conduit installations following inspection by the Tillamook
PUD Engineering Department. Complete backfill shall be done before
energization of the electrical system.
5.3
Locating Underground Facilities
Before beginning to dig on any project, contact free locating service. There
is no charge to the customer for this service. All underground utilities in
the area will be located and identified.
CALL BEFORE YOU DIG!
5.4
Conduit Installation Requirements
The customer is responsible for providing and installing the conduit from
the meter base to the secondary pedestal, pad-mount transformer, or pole.
No elbows or bends will be allowed in the wall between the bottom of the
meter base and the bottom of the trench.
When conduit will be placed into an existing energized vault
or secondary pedestal, contact the Tillamook PUD
Operations Department at 503-842-2122 or 1-800-422-2535
to arrange for Tillamook PUD personnel to be onsite.
The customer is responsible for ensuring that the conduit installations are
inspected and approved by the Tillamook PUD Engineering Department
prior to backfill.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-2
Table 5-2
Conduit Installation Requirements
Requirement
DEPTH
Primary Voltage
Conduit
48 inches deep, measured
from top of conduit.
Secondary Voltage
Conduit
36 inches deep, measured
from top of conduit.
CEMENT
PVC MATERIALS
All weather Rain-R-Shine™ PVC Cement
(No. 30891, blue medium) or equivalent.
CEMENT
HDPE MATERIALS
BonDuit® Conduit Adhesive
(No. 30891, blue medium) or equivalent.
PATH OR LAYOUT
The path of the trench or conduit layout must be
approved by the Tillamook PUD Engineering
Department prior to installation.
PULL ROPE
¼-inch poly pull rope or equivalent with a
tensile strength of 600 pounds or greater.
CAPPING AND MARKING
CONDUIT ENDS
All conduit ends shall be capped and plugged to
eliminate dirt, rocks, and other material from entering
the conduit.
When conduit is to be extended at a later time, a
Tillamook PUD-supplied red warning fiberglass sign
shall be placed at the end of the conduit to facilitate
its future uncovering.
CONDUIT RUNS
Continuous conduit runs shall not have more than a
total of 270 degrees in angle between the connection
to Tillamook PUD system and the customer’s facility.
INSPECTIONS OF
INSTALLATIONS
Conduit installations must be inspected and
approved by Tillamook PUD prior to backfill.
CONDUIT INSTALLATION
INTO VAULTS
WARNING TAPE
Vaults
See Figure 5-20.
200-amp
service
See Figure 5-21.
400-amp
service
See Figure 5-21.
Tillamook PUD provided warning tape must be placed a
minimum of 12 inches above conduit from meter base to
secondary pedestal, pad-mount transformer, or pole.
Note: When conduit will be placed into an existing energized vault or secondary pedestal,
contact the Tillamook PUD Operations Department at 503-842-2122 or 1-800-422-2535 to
arrange for Tillamook PUD personnel to be onsite.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-3
5.5
Conduit Specifications
Table 5-3
Conduit Specifications—Schedule 40 PVC
2-inch
Description
Schedule 40 PVC with integral bell ends, meeting:
UL Standard 651
NEMA TC-2-1978
Federal Specification WC-1094A
2-inch I.D.; wall thickness, 0.154 inches
Size
90-degree sweep (36” or 48” radius)
45-degree sweep (36” or 48” radius)
30-degree sweep (36” or 48” radius)
22½-degree sweep (36” or 48” radius)
Catalog No.
Carlon No. 49011 or
equivalent
36" radius
UA9FJBR
UA7FJBR
UA6FJB
UA5FAJB
48" radius
UA9HJBR
UA7HJB
UA6HJB
UA5HJB
3-inch
Description
Schedule 40 PVC with integral bell ends, meeting:
UL Standard 651
NEMA TC-2-1978
Federal Specification WC-1094A
3-inch I.D.; wall thickness, 0.216 inches
Size
90-degree sweep (36” or 48” radius)
45-degree sweep (36” or 48” radius)
30-degree sweep (36” or 48” radius)
22½-degree sweep (36” or 48” radius)
Catalog No.
Carlon No. 49013 or
equivalent
36" radius
UA9FLBR
UA7FLBR
UA6FLB
UA5FLB
48" radius
UA9HLBR
UA7HLB
UA6HLB
UA5HLB
4-inch
Description
Schedule 40 PVC with integral bell ends, meeting:
UL Standard 641
NEMA TC-2-1978
Federal Specification WC-1094A
5-inch I.D. or 6-inch I.D.; wall thickness, 0.258 in.
Size
90-degree sweep (48” or 60” radius)
45-degree sweep (48” or 60” radius)
30-degree sweep (48” or 60” radius)
22½-degree sweep (48” or 60” radius)
Catalog No.
Carlon No. 49015 or
equivalent
48" radius
UA9HPB
UA7HPB
UA6HPB
UA5HPB
60" radius
UA9IPB
UA7IPB
UA6IPB
UA5IP
6-inch
Description
Schedule 40 PVC with integral bell ends, meeting:
UL Standard 641
NEMA TC-2-1978
Federal Specification WC-1094A
6-inch I.D.; wall thickness, 0.280 in.
Size
90-degree sweep (48” or 60” radius)
45-degree sweep (48” or 60” radius)
30-degree sweep (48” or 60” radius)
22½-degree sweep (48” or 60” radius)
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
Catalog No.
Carlon No. 49017 or
equivalent
48" radius
UA9HRB
UA7HRB
UA6HRB
UA5ARB
60" radius
UA9IRB
N/A
UA6IRB
UA5IR
5-4
Table 5-4
Conduit Specifications—HDPE
2-inch
Description
HDPE ETL Schedule 40, meeting:
UL Standard 651B
ASTM F2160
NEMA TC-7
Color: Black with red stripes
Catalog No.
Carlon U13C4N1A3KB1000
or equivalent
3-inch
Description
HDPE ETL Schedule 40, meeting:
UL Standard 651B
ASTM F2160
NEMA TC-7
Color: Black with red stripes
Catalog No.
Carlon U15C4N1A3KB500
or equivalent
5-inch
Description
HDPE ETL Schedule 40, meeting:
UL Standard 651B
ASTM F2160
NEMA TC-7
Color: Black with red stripes
Catalog No.
Carlon U18C9N1A3KA550
or equivalent
6-inch
Description
HDPE ETL SDR 13.5, meeting:
UL Standard 651B
ASTM F2160
NEMA TC-7
Color: Black with red stripes
5.6
Catalog No.
Carlon U22C9N1A3KA450
or equivalent
Vault Installation
The customer provides and installs all vaults, trenching, Tillamook PUDprovided warning tape, ¼-inch poly pull rope or equivalent with a
tensile strength of 600 pounds or greater. All backfilling must comply
with Tillamook PUD's specifications.
Vaults shall be leveled upon installation. A minimum of a 6-inch gravel
base below the vault is required to provide drainage for the vault. Vault
lids shall not be sealed to the vault. Tillamook PUD will require
customers to remedy any deviations from Tillamook PUD specifications.
Deviations may delay scheduling of installation. Refer to applicable
figures for individual specifications.
Vault lids shall not be sealed to the vault.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-5
Conduits shall extend through the vault walls a distance of 4 inches with a
minimum of 2-inch separation between conduits. Conduit is to be sealed
from the outside. Tillamook PUD will indicate appropriate knockouts to
be used prior to installation. Grout shall be used to patch and seal the
holes in the vault created for the installation of the conduits. Conduits
shall be perpendicular to the wall.
It is best for the conduit installer to remove the “knockouts”
from the inside of the vault.
5.7
Vault Purchase
Vaults may be purchased from Oldcastle Precast / Utility Vault or other
suppliers of vaults that meet Tillamook PUD vault specification
requirements.
Oldcastle Precast / Utility Vault
28499 SW Boberg Road
PO Box 323
Wilsonville, OR 97207
Telephone: 503-682-2844
Toll Free:
800-967-3551
Website:
WWW.UVWILSONVILLE.COM
5.8
Vault and Lid Specifications
The following is a list of approved vaults and lids to be used in primary
and secondary underground installations.
Table 5-5
Single-Phase Installations—Vault and Lid Specifications
Vault E-11
Inside Dimensions: 50" x 50" x 37" deep
Lid No.
Use
CE-11
Transformers
CE-11S
Splice Vault
CE-11SE
Sectionalizing
Description
56” x 56” with
21” x 25” B.O.
56” x 56” with
36” x 36”
galvanized door
56” x 56” with
12” x 26” B.O. and
30” x 30” galvanized door
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
Oldcastle Precast/
Utility Vault No. 504-LA
(Figure 5-3)
Oldcastle
Precast/
Utility Vault No.
Spec Sheet
55-2125
Fig. 5-4
55-332P
Fig. 5-5
55-3030P-1226
Fig. 5-6
5-6
Table 5-6
Three-Phase Installations—Vault and Lid Specifications
Vault E-19
Inside Dimensions: 66" x 42" x 38" deep
Lid No.
CE-19R
Use
<1000 kVA
Transformers
CE-19S
Splice
CE-19SE
Sectionalizing
>1000 kVA
Transformers
CE-19-1500
Description
56” x 80” with
15” x 60” B.O.
48” x 72”
with 36” x 36”
galvanized Door
60” x 79” with
12” x 56” B.O. and
24” x 36”
90” x 80” x 6”
with 17” x 65” B.O.
Oldcastle Precast/
Utility Vault No. 644-LA
(Figure 5-7)
Oldcastle Precast/
Utility Vault No.
Spec
Sheet
64-1560
Fig. 5-8
64-332P
Fig. 5-9
6079-2436P-1256
Fig. 5-11
8090-1765
Fig. 5-12
For information regarding specialized vaults not listed in the preceding
tables, contact the Tillamook PUD Engineering Department.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-7
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-8
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-9
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-10
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-11
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-12
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-13
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-14
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-15
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-16
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-17
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-19
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
5-20
Section 6
Metering
6.1
General
The information contained in this section is intended to serve as a guide
for customers and is not intended to address all metering requirements.
Prior to beginning any work, contact the Tillamook PUD Engineering
Department for the requirements of your project and to obtain approval of
your metering equipment.
The customer shall supply, install, and maintain all meter equipment and
facilities to meet or exceed Tillamook PUD specifications except the
following:
9
Meter
9
Current transformers (CTs). (In most cases, the customer will
install Tillamook PUD-supplied CTs.)
9
Test switches
All meter bases, masts, CT enclosures, and weatherheads are the property
of the customer. Metering shall not be mounted on Tillamook PUD padmount transformers or transclosures.
Meter bases shall be mounted plumb and be securely fastened to the
structure or wall to withstand forces of installation or removal of the
meter.
Tillamook PUD requires ring-type meter bases. Link style, manual bypass
devices shall be required for services with meter base capacity in excess of
200 amperes.
Conduit runs from CT enclosures to the meter base shall be galvanized,
rigid conduit and be limited to 50 feet. The minimum conduit size will be
1 inch.
Meter bases with automatic circuit-closing devices are prohibited.
The line supply conductors to a meter base shall be connected to the top
terminals and the load supply conductors shall be connected to the bottom
terminals.
The customer shall provide sufficient access at all times in an area free of
stored materials and exercise proper care to protect Tillamook PUD
property on customer premises. In the event of loss or damage to
Tillamook PUD property on the customer’s premises arising from neglect,
carelessness, or misuse the cost of necessary repairs or replacement will be
billed to the customer.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-1
6.2
Energizing the Service
When a Tillamook PUD representative arrives to initially connect a new
service, access is required to the main electrical panel in order for the
service to be energized.
Service will not be connected until the following criteria have been
met:
6.3
9
An approval sticker ("green tag") issued by the state electrical
inspector is attached to the meter base.
9
The main breaker is turned off.
9
The panel cover is installed.
Meter Locations
The customer must comply with the following items regarding meter
location:
9
Customers desiring service must obtain Tillamook PUD's approval
of the meter locations prior to wiring the premises.
9
Residential and small commercial meters shall be installed
outdoors at a location readily accessible for reading, testing, and
replacement.
9
The meter shall be located on the front or side of the structure
closest to utility facilities unless an alternate location is approved
by the Tillamook PUD Engineering Department.
9
If the meter is located on the side of the structure, it shall be placed
within 10 feet of the front corner.
9
A meter installed in an alley or driveway shall be recessed in the
wall or protected adequately to prevent damage from vehicular
traffic. Refer to Figure 6-9.
9
Meters shall not be located on porches, in carports, garages, dog
runs, kennels, over window wells, steps in stairways or stairwells,
or other unsafe locations.
9
The meter must be free from vibration.
9
The meter location shall not be within a corrosive atmosphere.
9
The meter shall not be located in an area with abnormal
temperatures.
9
The equipment shall be protected from damage.
9
Permanent walking access to meters and equipment shall be
provided and maintained by the customer.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-2
9
When a meter pedestal is located in a parking area, it must be
located so that parked vehicles will not restrict meter accessibility
or be damaged by vehicular traffic.
9
Multiple unit buildings shall use grouped or ganged meters and
shall permanently install engraved placards for meter-to-apartment
identification.
9
When county regulations specify the meter base be located above
the flood plain (more than 6½ feet above the ground) a permanent
step or landing (a minimum of 4 feet by 4 feet) must be installed
below the meter base for accessibility of reading and routine
maintenance. The platform must be accessible by a permanent
stairway, which conforms to OSHA regulations.
Exceptions to any of the above requirements must be approved by
the Tillamook PUD Engineering Department.
6.3.1
Grouped Meter Locations
Installation of six meters or less shall be on the outside wall of a
building and shall be grouped in such a manner that a singleservice run will serve all meters. Meter bases shall have
permanently engraved placards on each meter base for meterto-unit identification.
6.3.2
Metering Rooms
The installation of seven or more meters may be located in a
dedicated metering room with 24-hour accessibility by
Tillamook PUD. Meter bases shall have permanently engraved
placards on each meter base for meter-to-unit identification.
When a metering room is to be used, a floor plan showing the
location of all proposed and existing equipment shall be
submitted to Tillamook PUD for approval prior to any wiring.
All meters shall be grouped on a common wall. The metering
room shall be dedicated and secured for electrical equipment
and never used for storage.
The only access to the metering room shall be from the exterior
of the building via a solid core door with minimum dimensions
of 2-foot 8-inch by 6-foot 8-inch. The access door shall be
installed such that it will not make contact with the meters or
other electrical equipment. Doors must open outward and be
equipped with a "panic bar."
The locking system shall not allow common access to
unauthorized individuals. The customer shall install a sign on
the exterior of the door stating "Metering Room." For
complexes which have multiple buildings, the building number
or name shall be permanently engraved on the placard with
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-3
lettering a minimum of 2 inches in size.
Telephone and cable television terminal equipment may occupy
this metering room provided they do not interfere with the
electrical equipment; each may have its own provision for
access.
The metering room shall be illuminated by permanent fixture(s)
providing a minimum of 10 foot candles per square foot with a
switch located inside the door next to the latch side of the door.
Water, gas, sewer, and drain pipes shall not terminate or pass
through the metering room. Proper drainage will be required
when there is a possibility of standing water.
6.4
Sealing and Locking Requirements
At the time of installation, the meter base and/or raceways containing
unmetered conductors or busbars shall be sealed. Unused threaded
openings and knockouts in enclosures must be fitted with an approved
plug locked in place from the inside. Meter seals are placed on meters and
associated service equipment to prevent injury and tampering. Seals are
not to be removed except by Tillamook PUD personnel. Broken seals are
justification for Tillamook PUD to initiate a theft of service investigation.
All Tillamook PUD seals shall be readily visible without having to open or
remove any covers or panels.
Seal tabs designed to accommodate lead meter seals are not
acceptable.
CT enclosures shall have padlocking provisions that are an integral part of
the door.
Service entrance equipment shall be arranged such that metered circuit
conductors or busbars do not enter or pass through raceways, enclosures,
or conduits containing unmetered circuit conductors or busbars. Refer to
Figure Nos. 6-4, 6-5, 6-6, and 6-7.
EXCEPTION:
That portion of service load-side conductors or busbars exiting the
meter base or current transformer enclosure.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-4
6.5
Clearances
All meters shall be readily accessible. Working space in front of meters or
metering equipment shall not be less than 36 inches, measured from the
front of the meter glass. The height in this area shall not be less than 8 feet
above the finished grade, floor, or working platform. The platform must
be accessible by a permanent stairway which conforms to OSHA
regulations.
Working space behind freestanding switchboards shall not be less than 36
inches from the panels or the rear wall with a provision for safe exit.
Electric meters shall be installed a minimum of 3 feet from natural gas
meters and 10 feet from propane regulators (NFPA 58). Measurement
shall be from edge to edge in accordance with the requirements from the
following references:
6.6
ƒ
National Electrical Safety Code (NESC), IEEEC2-2007.
ƒ
National Electrical Code (NEC), NFPA 70-2002.
ƒ
Flammable & Combustible Liquids Code, NFPA 30-1996.
ƒ
Standard for the Production, Storage & Handling of Liquefied Natural
Gas, NFPA 59A-1994.
Meter Base Requirements
6.6.1
Self-contained meter bases
Minimum self-contained meter base dimensions shall be:
Depth:
Width:
Height:
4 inches
10½ inches
14 inches
Exceptions must be approved by the Tillamook PUD Engineering
Department prior to installation.
Conduits entering underground meterbases shall not enter the
center of the bottom of the meter base, but shall be located to
one side to provide conductor clearance unless prior written
permission is received from the Tillamook PUD Engineering
Department.
6.6.2
CT meter bases
Minimum CT meter base dimensions shall be:
Depth:
Width:
Height:
4 inches
10 inches
20 inches
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-5
Exceptions must be approved by the Tillamook PUD Engineering
Department prior to installation.
CT metering arrangements require ring-type meterbases with
test switch provisions. The test switch shall be located behind a
sealable panel. See Figure 6-11.
When aluminum conductors are used, the meter base must be
UL-listed or approved and clearly marked by the manufacturer
that it is acceptable for aluminum conductor.
The neutral service conductor shall be bonded to the meter base
using the grounding screw or bonding terminal. The neutral
service conductor may be continuous from the weatherhead
through the meter base to the service panel or disconnect.
Figure 6-11
Ring-type Meter Socket with Test Switch Provision
Minimum Socket Dimensions
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-6
6.7
Self-Contained versus CT Metering
Table 6-1
Self-Contained versus CT Metering Requirements
Service Entrance
Conductor Ampacity
SINGLE PHASE
Metering
Equipment
Less than 400 amps
Self-Contained
401 – 600 amps
CT Rated with CT enclosure
NOTE: Single-phase service is not available for greater than 600 amps.
THREE PHASE
6.8
Less than 200 amps
Self-Contained
201 – 800
CT Rated with CT enclosure
Greater than 800 amps
Switchboard mounted CTs
Current Transformer Enclosures
A CT enclosure is a separate enclosure, furnished and installed by the
customer, which contains a prefabricated bracket to terminate the supply
and load conductors and for mounting the CTs.
CT enclosures shall be UL-approved. CT enclosures in wet locations shall
be rain-tight (NEMA 3R) and stainless steel is recommended. The CT
enclosure door shall be lockable with a padlock and utilize factoryinstalled side hinges for side opening. Locking provisions shall be an
integral part of the door for installation of Tillamook PUD locks.
The door on CT enclosures shall not be used for mounting meter(s) or
other equipment. Refer to Figure 6-10.
Table 6-2
CT Enclosure Minimum Dimensions
Service Entrance Conductor
Ampacity
Single-phase service
401 - 600 amps
Minimum Dimensions
(W x H x D)
36" x 36" x 11"
NOTE: Service equipment in excess of 600 amps shall be three-phase service.
Three-phase service
201 – 599 amps
36" x 36" x 11"
600 – 800 amps
36" x 48" x 11"
Above 800 amps
Consult Tillamook PUD Engineering Dept.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-7
Prefabricated brackets shall be installed in CT enclosures for terminating
conductors and mounting CTs. The brackets shall meet the requirements
specified in Figure 6-8 specifically for (Single phase CTs: Equipment
Utility Service Requirements Committee [EUSERC] Drawing No. 328A
and for three-phase CTs: EUSERC Drawing No. 329A).
CT enclosures shall be grounded.
The mounting height of CT enclosures shall be limited such that the top of
the enclosure shall not be more than 8 feet above the floor or working
platform of same unless exception is specifically permitted by Tillamook
PUD. The minimum height shall be 6 inches above the floor or working
platform level. Enclosures shall not be mounted in or under floor crawl
spaces.
CT enclosures shall be mounted on the outside walls of buildings. Other
locations require prior written approval by the Tillamook PUD
Engineering Department.
The CT enclosures shall contain only the CTs and associated equipment.
The CT enclosure shall not be used as a junction box for other wires or
conduits.
6.9
Current Transformer Installation
Tillamook PUD will provide bar or perch-type CTs. The customer shall
connect the load side service conductors to the load side of the CT
mounting brackets using customer-supplied connectors. Refer to Figure
Nos. 6-4, 6-5, 6-6, and 6-7.
The customer shall install the CT enclosures, CTs, CT wires, and related
equipment. Tillamook PUD will provide the CTs and Tillamook PUD’s
Engineering Department personnel will connect the metering wires at the
CT enclosures and the meter base.
9
Customers are responsible to install Tillamook PUD-furnished
current transformers.
9
CTs are available for pickup at the Tillamook PUD District Office.
9
CT polarity mark shall be installed on the supply side connection.
9
Customers shall furnish and install the CT wires specified in
Table 6-1 from the CTs to the meterbase.
9
Tillamook PUD will connect the CT wires at the meterbase and the
CTs.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-8
6.10
Current Transformer Conduit
Only CT wires shall be allowed in CT conduit.
The customer shall provide and install conduit for the metering
conductors between the meter base and the CTs. A minimum of 1-inch
rigid steel conduit is required; no opening condulets or flex will be
permitted.
CT enclosures must be connected to the meter base or meter enclosure
with conduit and shall be bonded by approved methods. A minimum of
1-inch rigid steel conduit is required; no opening conduit bodies or flex is
permitted.
Table 6-3
Instrument Metering Wire Size and Color Codes
Single Phase
Distance and
Conduit Size
50 feet or less
1” conduit
minimum
Voltage
Wires
Current
Wires
1 #12 Red
1 #10 Red
1 #12 Blue
Three Phase
Ground
Wire
Voltage
Wires
Current
Wires
1 #12 Red
1 #10 Red
1 #10 Blue
1 #12 Blue
1 #10 Blue
1 #10 White
1 #12 Black
1 #10 Black
1 #12 White
1 #10 White
1 #10
Green
Ground
Wire
1 #10
Green
Notes:
1. Wire must be stranded.
2. THW or better insulation is required. TW wire is not acceptable.
3. Tape color coding of wire is not allowed.
4. The customer shall provide proper size conduit and copper secondary metering conductors between the
meter base and the current transformers. Flexible conduit, condulets and LBs shall not be used.
5. A minimum of 1-inch rigid steel conduit is required.
6. At all current transformer metering bases, the length of the metering conductors shall be one and a half times
the length of the longest side of the meter base enclosure.
7. Meter base and CT enclosures to be grounded.
6.11
Instrument Transformer Rated Meter Worksheet
(See Appendix A)
The customer is to provide the meter base, conduit, and CT
enclosures with wiring, in accordance with the Instrument
Transformer Rated Meter Worksheet (See Appendix). No automatic
circuit-closing devices are allowed on any services.
For services in excess of 480 volts, consult the Tillamook PUD Engineering
Department for metering requirements.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-9
6.12
Current Transformer Switchboard Metering
On all services 801 amps and above, the CTs shall be installed in
switchboards.
All services installed in switchboards shall be metered with large window
CTs for installation on removable bus sections in the customer’s
switchboards. This compartment shall be lockable using a padlock.
The customer shall submit two copies of switchgear drawings to
Tillamook PUD for approval and determination of the type of meter or
meters that will be used, type, and size of CTs, and arrangements for
mounting prior to the manufacture of the switchgear. Switchboards
shall conform to EUSERC standards.
6.13
Pulse Initiator Output
When requested by the customer, Tillamook PUD will furnish pulse
initiator outputs from kilowatt hour or kilovar hour meters.
The pulse initiator's operation, benefit, and use are highly variable, subject
to the use to which the customer puts it. Therefore, the pulse initiator's
output is provided without statement or liability as to its usefulness in any
application that the customer may choose to pursue. Tillamook PUD
assumes no responsibility or liability in any way related to the pulse
initiator or related facilities or other operation, except direct Tillamook
PUD negligence in the installation or maintenance of the pulse initiator.
Tillamook PUD shall design, own, install, maintain, and repair all facilities
necessary for the pulse initiator output including, but not limited to the
meter, pulse initiator, isolation relays, test switches, and equipment
cabinets. Maintenance and repair will only be performed during normal
working hours.
The customer shall be responsible for all Tillamook PUD incurred
equipment and labor costs. Cost of purchase and installation must be in
accordance with Tillamook PUD’s Policy 4-15. The customer is also
responsible for the design, installation, and maintenance of all customerowned equipment on the customer's side of the isolation relay.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-10
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-11
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-12
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-13
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-14
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-15
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-16
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-17
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-18
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
6-19
Section 7
Area Lights
7.1
General
Tillamook PUD provides area lighting and public street lighting for
customers located within the Tillamook PUD service territory.
Lights provided are high-pressure sodium-type in the 100- and 200-watt
sizes. Wide-angle, high-pressure sodium lights are available in 200- and
400-watt sizes. Lighting provided by developers must meet Tillamook
PUD specifications and policies.
To request area lighting, contact the Tillamook PUD Engineering
Department. Once the necessary information is received, a Tillamook
PUD Engineering Field Representative will visit the proposed location to
determine if existing facilities are adequate or if additional facilities will be
required to serve the light (poles, conductor, or transformers).
If additional facilities are required to serve the light installation, costs will
be at the customer’s expense as specified in Tillamook PUD Policy
Bulletin 4-2.
Tillamook PUD requires the customer sign a one-year contract obligating
payment of a monthly service fee. The customer shall allow Tillamook
PUD free access to the customer’s property to inspect and maintain the
equipment or to remove the installation upon termination of service.
The customer shall exercise care to prevent damage to lighting fixtures.
Every effort shall be made to minimize the impact of light pollution on
neighboring properties.
The customer shall not place customer-owned area lighting on Tillamook
PUD-owned poles. The customer has the option of providing and
installing an area lighting system, provided service to these electrical
facilities is connected behind an approved disconnect.
The monthly billing of customer-owned area lighting will be a flat rate
schedule based on the connected load. Ownership and maintenance of the
complete lighting system behind the approved disconnect will remain the
responsibility of the owner.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
7-1
Section 8
Right-of-Way Clearing
8.1
Customer Requirements—Figures 8-1, 8-2, and 8-3
The customer is required to provide all right-of-way clearing when a new
service is established. It is imperative that Tillamook PUD employees can
quickly locate existing electrical facilities and have adequate space to
safely serve those facilities.
Tillamook PUD’s requirements for right-of-way clearances are listed
below:
Table 8-1
Right-of-Way Clearances
Overhead—Primary Service
Required
Right-of-Way
Pole Line
(Cleared Each
Side of Pole)
Three-phase
40’ wide
20’ wide
Single-phase
20’ wide
10’ wide
10’ wide
5’ wide
Type of Service
Overhead—Secondary Service
Secondary
NOTE: Tillamook PUD may require additional clearing of “danger trees” outside the right-of-way.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
8-1
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
8-2
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
8-3
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
8-4
Section 9
Generation—
Permanent and Temporary
9.1
Generator Safety
When any of the types of generation systems defined below are used, they
must be isolated from Tillamook PUD facilities to prevent serious danger
to Tillamook PUD personnel and damage to customer property. To assure
the safety of TPUD personnel and to avoid potential damage to customer
property when portable generators are used, all electrically-operated
devices shall be connected directly to the portable generator or approved
transfer switch.
Never overload the generator. Always operate the generator in
accordance with the manufacturer’s recommendations.
Never try to power the house wiring by plugging the generator into
a wall outlet, a practice known as “backfeeding.” This is an
extremely dangerous practice that presents an electrocution risk to
utility workers and neighbors served by the same utility
transformer. Backfeeding also presents a serious risk of damaging
the generator, owner’s property, and neighboring properties. It
also bypasses some of the built-in household protection devices.
Never operate the generator inside your home. Good ventilation is
important. Generators produce carbon monoxide, a colorless, odorless,
toxic gas that can result in serious injuries, or even death, if levels become
too high.
9.2
Portable Generators
The simplest way to use a portable generator is to plug appliances directly
into the generator. A heavy-duty, outdoor-rated extension cord can be
used but it should be rated (in watts or amps) at least equal to the sum of
the connected appliance loads.
9.3
Fixed Generators
The only approved method to connect a generator to building wiring is by
having a qualified electrician install a transfer switch. The transfer switch
is installed between the generator and the electrical panel. It allows
power to be fed from only one source at a time.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
9-1
This switch must be installed in accordance with the National Electrical
Code (NEC), which is published by the National Fire Protection
Association, and all applicable state and local electrical codes.
An electrical permit must be obtained from the Tillamook County
Department of Community Development and the installation must be
inspected and approved by the Oregon State Electrical Inspector prior to
operation.
TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS
MARCH 2008
9-2
INSTRUMENT TRANSFORMER RATED METER WORKSHEET
Name
Work Order #
Address
Address
=========================================================================================
WIRE REQUIREMENTS
All wire shall be stranded copper with THWN or THHN insulation. Provide one wire of each color and size as indicated for the meter
application as checked below. Wired meter loops shall have conductor tails of 4 foot at the top and 5 foot at the bottom.
CURRENT
1Ø 6 pt, Form 4S
3Ø 13 pt.
GROUND
#10
White
#10
Red
#10
Blue
#10
Black
#10
Green
9
9
9
9
9
9
9
9
9
VOLTAGE
#12
White
#12
Red
#12
Blue
#12
Black
9
9
9
9
9
==================================================================================================
METER BASE REQUIREMENTS
The meter socket enclosure is to have a separately accessible space below the socket for utility test switch. The enclosure is to contain
a perch, drilled and tapped, for a test switch. The test switch will be furnished and installed by the utility. Meter socket with circuit
closures or bypass clips will not be approved. Stainless Steel meterbases are recommended.
13 pt
____ 6 pt
pt = number of meter points or lugs
==================================================================================================
CONDUIT REQUIREMENTS
Conduit shall be 1" rigid steel conduit with no more than 2700 in bends. Removable conduit cover fittings must be secured by metal
screws with "break-off" type heads or by "one-way" screws, or arranged for sealing.
feet
Conduit Length:
==================================================================================================
CURRENT TRANSFORMER ENCLOSURE
The current transformers are to be provided by the Utility and installed by the Customer in a Customer owned sealable steel
cabinet, securely mounted on a rigid surface. The top of the cabinet shall be more than 8' above the floor or ground. This cabinet is
to contain only the service conductors and the Utility equipment and is to be mounted in a readily-accessible location. The cover shall
have factory installed hinges for side opening with pad lockable door. The minimum size current transformer cabinets acceptable are:
SERVICE ENTRANCE
TRANSFORMER
CONDUCTOR AMPACITY
CABINET SIZE
(W X H X D)
600 and below .......................36"x36"x11"
601- 800.................................36"x48"x11"
801 and above ...................... Panel Board
==================================================================================================
CURRENT TRANSFORMER REQUIREMENTS
Ratio
Quantity
Window Type
Bar Type
==================================================================================================
GROUNDING
The customer shall provide and install an approved Ground Rod, Ground Rod Clamp and Grounding Conductor. The
Grounding Conductor shall be #6 copper or larger.
Request #
TILLAMOOK PEOPLE'S UTILITY DISTRICT
LINE EXTENSION AGREEMENT
The Tillamook People's Utility District, hereinafter referred to as "District", and the Undersigned mutually agree to the terms and
conditions set forth below:
District hereby agrees to construct and maintain all electric lines, facilities, machinery, and apparatus which the District determines to be
required for the delivery of electricity to the point of delivery, approved by the District. Installation, construction, and maintenance of the above
shall be under the complete control of the District. The undersigned acknowledges that all electric lines, machinery, and facilities on the source
side of the point of delivery which may be required shall become the sole property of District. Before completion of construction and all
connections, Undersigned shall not assign any rights hereunder without District's prior written consent. The covenants, conditions, and terms of
this agreement shall be binding upon Undersigned, Undersigned's assigns, successors, heirs, and personal representatives. This connection
may require service be provided undersigned by way of a temporary connection. For this connection, as well as for the permanent connection,
undersigned hereby grants District an easement and, in this regard, undersigned shall sign such additional documents as District may reasonably
require.
dollars to be paid prior to
The District estimates that the cost for 1 connection(s) to be served under this Agreement shall be $
the commencement of construction. This estimate is valid for 180 days from [ENTER ESTIMATE LETTER DATE], and all electric lines, facilities,
machinery, and apparatus for this connection must be installed within this 180-day period or the Agreement and estimate become null and void.
New estimates will be prepared using policies in effect at the time the new estimate is prepared. The estimate does not include PUD account
processing fee(s) which will appear on first month's electrical bill. The Undersigned shall receive reimbursement from subsequent
permanent service connections made to this line extension provided that Undersigned's investment is over $5,000 dollars and
provided the subsequent extensions are made within five (5) years of the execution of this agreement. Such reimbursements shall be
applied first to the loan balance of the Undersigned in the event this line extension is financed through the District. The amount of
reimbursement will be calculated in accordance with District's Policy Bulletin 4-2. Reimbursements are not allowed for additional
connections off developer extensions, or the permanent service for area or street lighting purposes, or for approved attachments by
licensees of the District. At all times, District shall have complete right of inspection, ingress, and egress, rights-of-way, and all easements
necessary for the line extension work. The District reserves the right to interrupt service without notice for any reason, including but not limited to
repair or inspection of any aspect of the District's electrical system. The undersigned agrees to hold from any damage, loss, or injury to persons
or property resulting from any outage, interruption of service, or deviation in power quality not caused by the willful and intentional fault of the
District.
Undersigned shall abide by, perform, and be subject to all laws, rules, regulations, ordinances, and policies, now or hereafter enacted by
District and all federal, state, county, and city governmental bodies and agencies thereof, with particular reference herein made to District Policy
Nos. 4-2, 4-7, and 4-13. UNDERSIGNED HEREBY ACKNOWLEDGES THAT UNDERSIGNEDs HAS BEEN PROVIDED AN OPPORTUNITY
FOR REVIEW OF THE ABOVE POLICIES, WHICH ARE BY THIS REFERENCE MADE A PART OF THIS AGREEMENT.
On default by the Undersigned for any reason of this agreement, any policy of the District or any other agreement or obligation, the
District may stay further construction, maintenance, and service to the Undersigned until such default is cured. Upon ten (10) days written notice
of default by District and Undersigned's failure to cure such default within said period of time, District may terminate this agreement and all service
to Undersigned, without waiver of its right to collect any sum in damages owned to it by Undersigned. Assertion or non-assertion of any rights
and remedies by District shall not be a waiver of any rights or remedies.
All previous communications between the parties hereto, either verbal or written, with reference to the subject matter of this agreement
are hereby abrogated and this agreement shall constitute the complete agreement between the parties.
Undersigned represents, warrants, and covenants that Undersigned is (are) the sole owner(s) in fee simple and all necessary persons
having any right, interest, claim or lien therein have executed this agreement except:
The parties hereto have executed this agreement in duplicate this ______ day of __________________, 2008.
UNDERSIGNED
TILLAMOOK PEOPLE'S UTILITY DISTRICT
______________________________________________
__________________________________________________
______________________________________________
__________________________________________________
FOR DISTRICT OFFICE USE ONLY
Actual Job Cost:
Reimbursement:
Total Paid:
Tap-off WO#:
Date Connected:
Amt. Reimbursed:
LOAD DATA SHEET
NON-RESIDENTIAL SERVICE
(TO BE RETURNED BEFORE ENGINEERING BEGINS)
Request No.
Date:
Project:
Location:
Owner:
Telephone:
Contractor:
Telephone:
Electrician:
Telephone:
Other:
Telephone:
Date Service Required:
Temporary:
Type of Service:
Phase:
Service Ent. Equip. Rating:
Amps:
Permanent:
Voltage:
Wire:
Other:
3-PHASE MOTOR LOAD LIST
QTY
HP
(EACH)
HP
(TOTAL)
USE
SUBTOTAL:
1-PHASE MOTOR LOAD LIST
HP
(EACH)
QTY
SUBTOTAL:
ADDITIONAL MISCELLANEOUS LOAD LIST
(Lighting/Heating, etc.)
DESCRIPTION (Use)
KW
NOTES:
SUBTOTAL
TOTALS:
3-Phase Motor Load:
HP
KVA
1-Phase Motor Load:
HP
KVA
Total Misc. Load:
KW
KVA
Total Est. Demand:
KVA
Owner/Agent:
Title:
HP
(TOTAL)
USE
TILLAMOOK PEOPLE'S UTILITY DISTRICT
REIMBURSABLE WORK ORDER FORM (T-8)
DATE: [DATE]
WORK ORDER NO.: [WO#]
REQUEST NO.: [REQ#]
CUSTOMER NAME AND MAILING ADDRESS:
[NAME]
[ADDRESS]
[CITY/STATE/ZIP]
DESCRIPTION OF WORK TO BE PERFORMED:
[SCOPE OF WORK]
==================================================================
ESTIMATED JOB COST:
$ [AMOUNT]
==================================================================
ATTENTION [CUSTOMER NAME]:
Pursuant to District Policy 4-5 (attached), this cost estimate is being submitted for your
consideration and signature. This estimate is based on standard billing rates for man-hours,
materials, equipment, associated District overhead expenses, and a 10 percent contingency. A
refund, if greater than $100.00, will be issued in the event the actual cost of construction is less
than the estimated cost.
The cost estimate is valid for 180 days and construction must be completed during the 180-day
period. The estimated cost shall be paid prior to the start of construction.
SIGNATURE
___________________________
DATE
PRINTED NAME
___________________________
TITLE
Request for Electrical Service
Service Change
Engineering Department 503-815-8629
REQUIRED INFORMATION
Applicant Information (Please print full, legal name, or business name)
Name:
Owner
Information:
Street:
City / State / ZIP:
Daytime Phone:
Cell Phone:
Contact Information
Contact
Information:
Name:
Same as above
Street:
City / State / ZIP:
Daytime Phone:
Cell Phone:
Project Location
Street address
City:
Project
Service Upgrade:
Electrical load:
Voltage (select one):
Disconnect required?
Main breaker size:
amps
120/240, 3-wire, 1Ø
120/208Y; 4-wire 3Ø
Yes
No
Desired amps:
277/480Y; 4-wire 3Ø
Other:
Service Change:
Relocate service?
Yes
No
Disconnect required?
Current location:
Desired location:
Yes
No
Overhead to Underground Conversion:
Yes
No
Describe:
Other:
Describe:
Disconnect required?
Applicant’s Signature:
Yes
No
Date:
MAIL COMPLETED FORM TO: PO BOX 433; TILLAMOOK, OR 97141
FAX TO: 503-815-8648
EMAIL: engineering-requests@tpud.org
REQUEST NO.: ___________
Tillamook PUD Plot Plan
Name:
Address:
Include roads, well, septic system, sidewalks, driveways, proposed future improvements, proposed location
of electric meter. A copy of the site plan submitted to Tillamook County may be attached.
REQUEST NO.: ___________
Request for New Electrical Services
Commercial Service
Engineering Department 503-815-8629
REQUIRED INFORMATION
Applicant Information (Please print full, legal name or business name)
Temporary service:
Name:
Owner’s name and address
or party responsible for
temporary service billing?
Street:
Permanent service:
Owner’s name and address
or party responsible for
permanent service billing?
City / State / ZIP:
Daytime Phone:
Name:
Cell Phone:
Same as above
Street:
City / State / ZIP:
Daytime Phone:
Cell Phone:
Project Description
Temporary service?
Permanent service?
Yes
No
Overhead
Underground
Date Desired:
Yes
No
Overhead
Underground
Date Desired:
Contractor Information
Name of contractor:
Mailing address:
City / State / ZIP:
Same as above
Daytime phone number:
Contact Information
Name of contact:
Role:
Mailing address:
City / State / ZIP:
Telephone Numbers:
Same as above
Daytime Phone:
Cell Phone:
Project Information
Street address and city
(EXAMPLE: 2N 10 29AC 1400)
OR assessor’s parcel
number:
Nearest cross street:
Who will trench, install
conduit, and backfill?
Trench services (check
all that apply):
Applicant
Contractor
Electric
Name:
Telephone
Cell Phone:
Cable
Other:
Water, propane, sewer, storm drains, gas, or oil facilities are not permitted in joint trench.
Electrical Load Information
Main breaker size:
Total square footage:
Voltage (select one):
amps ( COMPLETE ATTACHED LOAD SUMMARY)
square feet
120/240, 3-wire, 1Ø
277/480Y; 4-wire 3Ø
120/208Y; 4-wire 3Ø
Other:
Attachments
Provide a copy of the following documents:
•
Load summary sheet (attached).
•
County assessor’s parcel map indicating site, easements, and rights-of-way.
•
Detailed plot plan (see reverse).
Applicant’s Signature:
Date:
MAIL COMPLETED FORM TO: PO BOX 433; TILLAMOOK, OR 97141
FAX TO: 503-815-8648
EMAIL: engineering-requests@tpud.org
REQUEST NO.: ________
Tillamook PUD Plot Plan
Name:
Address:
Include roads, well, septic system, sidewalks, driveways, proposed future improvements, proposed location
of electric meter. A copy of the site plan submitted to Tillamook County may be attached.
REQUEST NO.: ________
Request for New Electrical Service
Land Development
Engineering Department 503-815-8629
REQUIRED INFORMATION
Developer/Contact Information (Please print full, legal name or business name)
Name:
Developer
Information:
Company Name:
Street:
City / State / ZIP:
Office Phone:
Cell Phone:
Name:
Contact
Information:
Same as above
Company Name:
Street:
City / State / ZIP:
Office Phone:
Cell Phone:
Project Type:
Subdivision
No. of lots:
Phase No.:
Date Desired:
Partition Plat
No. of lots:
Plat No.:
Date Desired:
Apartment Complex:
No. of units:
No of buildings:
Date Desired:
Condominiums
No. of units:
Phase No.:
Date Desired:
Townhouses / Row houses
No. of units:
Phase No.:
Date Desired:
Project Information
Name of development:
Who will trench, install
conduit, and backfill?
Applicant
Contractor
Trench services:
Electric
Name:
Telephone
Cell Phone:
Cable
Other:
Contractor Information
Name of contractor:
Mailing address:
Same as above
City / State / ZIP:
Daytime phone number:
Attachments
Provide a copy of the following:
•
•
•
Plans signed by a registered land surveyor and approved by Tillamook County Planning Department;
provide both a hard copy and a CD of the layout saved in “.DWG” format.
Property’s legal description or a metes and bounds description.
Documentation indicating legal party or parties authorized to sign documents.
Applicant’s Signature:
Date:
MAIL COMPLETED FORM TO: PO BOX 433; TILLAMOOK, OR 97141
FAX TO: 503-815-8648
EMAIL: engineering-requests@tpud.org
REQUEST NO.: _________
Request for New Electrical Service
Residential Service
Engineering Department 503-815-8629
REQUIRED INFORMATION
Applicant Information (Please print full, legal name or business name)
Name:
Temporary service:
Name and address of party
responsible for temporary
service billing?
Permanent service:
Name and address of party
responsible for permanent
service billing?
Street:
City / State / ZIP:
Daytime Phone:
Name:
Cell Phone:
Same as above
Street:
City / State / ZIP:
Daytime Phone:
Cell Phone:
Project
No. of Units:
Single-family residence
Duplex
Yes
No
Overhead
Underground
Yes
No
Overhead
Underground
Temporary service?
Permanent service?
Quad
Date Desired:
Date Desired:
Contractor Information
Name of contractor:
Same as above
Mailing address:
City / State / ZIP:
Daytime telephone:
Contact Information
Name of contact:
Mailing address:
City / State / ZIP:
Telephone Numbers:
Role:
Same as above
Daytime Phone:
Cell Phone:
Project Information
Street address and city OR
assessor’s parcel number
(EXAMPLE: 2N 10 29AC 1400):
Nearest cross street:
Who will trench, install
conduit, and backfill?
Trench services (check
all that apply):
Applicant
Contractor
Electric
Name:
Telephone
Cell Phone:
Cable
Other:
Water, propane, sewer, storm drains, gas, or oil facilities are not permitted in joint trench.
Electrical Load Information
Main breaker size:
Voltage:
Check all that apply:
Amps
120/240, 3-wire, 1Ø
Total square footage:
Other:
Standard residential loads (Lighting, refrigerator, freezer, dishwasher, washer)
Air-conditioner ( _____ tons)
Range/Oven
Spa
Domestic water pump (___ hp)
Clothes Dryer
Heat pump (___tons)
Other electric heat (____ kW)
Water Heater
Other __________
Attachments
Provide a copy of the following documents:
•
Legal description of property or copy of last recorded deed.
•
County assessor’s parcel map indicating homesite(s), easements, and rights-of-way.
•
Detailed plot plan (see reverse).
Applicant’s Signature:
Date:
MAIL COMPLETED FORM TO: PO BOX 433; TILLAMOOK, OR 97141
FAX TO: 503-815-8648
EMAIL: engineering-requests@tpud.org
REQUEST NO.: ___________
Tillamook PUD Plot Plan
Name:
Address:
Include roads, well, septic system, sidewalks, driveways, proposed future improvements, proposed location
of electric meter. A copy of the site plan submitted to Tillamook County may be attached.
REQUEST NO.: ___________