construction - Meyer Vandenberg Lawyers
Transcription
construction - Meyer Vandenberg Lawyers
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER ISSUE #152 SEPTEMBER/OCTOBER 2013 ACLN AUSTRALIAN CONSTRUCTION LAW NEWSLETTER ABN 55 138 594 706 ISSN 1032 0288 Published by: Swap Exchange Pty. Ltd. PO Box R1140 Royal Exchange SYDNEY NSW 1225 AUSTRALIA Email: publisher@acln.com.au Website: www.acln.com.au IMPORTANT NOTICE The material contained in ACLN is in the nature of general comment only and is not information or advice on any particular matter. No one should act on the basis of anything contained in this Newsletter without taking appropriate professional advice upon the particular circumstances. The publishers, editors and authors do not accept responsibility for the consequences of any action taken or omitted to be taken by any person, whether a subscriber to this Newsletter or not, as a consequence of anything contained in or omitted from this Newsletter. CONTENTS #152 ARTICLES EDITORIAL4 JOHN TWYFORD NEGLIGENCE6 THE DUTY OF CARE IN DESIGN—CAN ENGINEERS RELY ON CODES OF PRACTICE? DONALD CHARRETT AND ANDREW POTTS CONTRACTS16 GOOD FAITH IN CONTRACT PERFORMANCE—HAS THE LAW CHANGED? TOM GRACE AND JOCK HAMILTON ELECTRONIC TRANSACTIONS 24 HIT ‘SEND’ AND HOPE—PROBLEMS WITH CONTRACTUAL NOTICES BY EMAIL OWEN HAYFORD AND BETINA FRIEDEBERG SECURITY OF PAYMENT THREE EARLY SECURITY OF PAYMENT CASES IN SOUTH AUSTRALIA ROBERT FENWICK ELLIOTT 28 CONTRACTS30 PROPORTIONATE LIABILITY IN THE BUILDING AND CONSTRUCTION INDUSTRY FOLLOWING HUNT & HUNT V MITCHELL MORGAN JACLYN SMITH ARBITRATION45 ARBITRATION IN AUSTRALIA—SUPREME COURT SUPPORTS DOMESTIC ARBITRATION IRRESPECTIVE OF THE PROSPECT OF SPLIT PROCEEDINGS GEOFF HANSEN AND JENNIFER GALATAS COPYRIGHT Material published in the ACLN is copyright. Apart from fair dealing for the purposes of private study, research, criticism or review as permitted under the Copyright Act 1968 (Cth), no part may be produced by any process without written permission. SUBSCRIPTIONS Please see our website or contact us. PRINTING UTS Printing Services University of Technology, Sydney PO Box 123 BROADWAY NSW 2007 2 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 EDITOR John Twyford CONTENTS #152 ARTICLES SECURITY OF PAYMENT 48 DO YOU HAVE A STANDING TRADE CREDIT AGREEMENT TO SUPPLY CONSTRUCTION SERVICES OR MATERIALS? ALISA TAYLOR AND KIMBERLY MOORE PUBLISHER / ASSISTANT EDITOR Myra Nikolich EDITORIAL PANEL Matthew Bell Lecturer and Co–Director of Studies for SECURITY OF PAYMENT 50 Construction Law, Faculty of Law THE CURATE’S EGG REVISITED University of Melbourne, Melbourne PHILIP DAVENPORT Philip Davenport Solicitor, Sydney BUILDING REGULATION 52 Philip Dawson UNCERTAIN TIMES AHEAD—THE QUEENSLAND BUILDING SERVICES Partner AUTHORITY NO LONGER! Clayton Utz, Sydney REN NIEMANN AND GORAN GELIC Leigh Duthie SECURITY OF PAYMENT 54 Partner Baker & McKenzie, Melbourne SECURITY OF PAYMENT LEGISLATION MAY NOT APPLY TO CONTRACTS Graham Easton FOR WORKS INVOLVING MINING PLANT Arbitrator & Mediator SCOTT LAYCOCK AND ROHAN DIAS G R Easton Pty Ltd, Sydney COMPETITION LAW 56 Arch Fletcher Partner IMPACT OF COMPETITION LAW ON THE CONSTRUCTION INDUSTRY Clayton Utz, Brisbane MALCOLM CHIN AND MIRANDA NOBLE Robert Floreani Senior Partner CASE NOTES Floreani Coates, Adelaide CASE NOTE 59 Janet Grey Architect, Arbitrator & Mediator, Sydney NEW SOUTH WALES COURT OF APPEAL FINDS DEFECTS DUTY PETER PETHER, ADAM WALLWORK AND JENNIFER TURNER Phillip Greenham Partner Minter Ellison, Melbourne Laurie James Chairman of Partners Kott Gunning, Perth Doug Jones AO Partner Clayton Utz, Sydney Christopher Kerin Partner Teys Lawyers, Sydney Scott Laycock Partner Gadens Lawyers, Sydney Wendy Roydhouse Solicitor, Sydney CONTRIBUTIONS Contributions to the ACLN from readers are encouraged. Please submit articles for consideration to the publishers. PEER REVIEW We now offer the facility of peer review. If you would like to register your name with us as a potential referee—willing to peer review other professionals’ work— please send your details and area/s of expertise, marked for the attention of the Editor. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 3 EDITORIAL EDITORIAL John Twyford In the leading article of this issue of the ACLN, Donald Charrett and Andrew Potts consider the extent to which an engineer’s duty of care to a client is satisfied by the design complying with the relevant standards. It is a very interesting paper and well worth careful study. The work includes a detailed description of the Standard making process and the authors assert that for the design of ‘conventional infrastructure’ compliance with the relevant standards ought to satisfy the duty of care. The Courts, as is instanced in the Goonyella case, may not share this view. This case is discussed in detail and the authors fear that the end result requires an engineer to question the efficacy of any standard he or she is using. It is a decision of a single justice of the Supreme Court of Queensland and, given the sums of money that were probably at stake, is surprising that there was no appeal. In their text the authors have quoted one of your Editor’s favourite judicial statements: ‘The law does not require of a professional man that he be a paragon, combining the qualities of polymath and prophet,’ Eckersley v Binnie & Partners (1988) 18 Con LR 1. Our next paper concerns the arcane subject of the implication of a term into commercial contracts requiring the parties to act toward each other exercising ‘good faith’. The authors, Tom Grace and Jock Hamilton, have given us an excellent history of the development of the doctrine through its various manifestations. It would seem that the doctrine might have reached its high water mark in the South Australian decision of Alstom v YDMRL. There, a single justice of the Supreme Court decided that the doctrine was applicable to all commercial contracts. The authors conclude by discussing how a contract might be drafted to accommodate the principle. 4 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 Remaining on the question of arcane subjects, Owen Hayford and Betina Friedeberg discuss the difficulties that arise from the giving of contractual notices by email. The authors suggest some strategies to overcome the difficulties caused by the inability to prove the receipt and time of receipt of an email notice. Those strategies include both technical and legal steps, however, it is impossible to eliminate all of the risks associated with electronic communication. Although not discussed in the article, an even more fundamental question arises in respect of contract formation through the rules of offer and acceptance. We have all been bemused by Lord Herschell’s magisterial declaration of the postal acceptance rule in Henthorn v Fraser (1892) 2 Ch 27 but does that rule extend to acceptances sent by email? What is the impact of the various Electronic Transactions Acts? This legislation is repeated in most jurisdictions as it is based on the United Nations Commission on International Trade Law’s Model Law on Electronic Commerce. ACLN would love to publish and article on this topic. The South Australian Building and Construction Industry Security of Payment Act 2009 (SA), enacted in 2009, is something of a newcomer to this form of regulation of the industry. Because of its recent enactment, courts have had only three opportunities to consider its provisions. Robert Fenwick Elliott has provided a short summary of what has been decided in these cases. He concludes that thus far the courts have taken a slightly jaundiced view of the legislation. Robert is an old friend of ACLN and it is pleasing to see that he is now a member of the South Australian bar. Jaclyn Smith, who is becoming a regular contributor to the ACLN, in a detailed paper, analyses the impact on the construction industry of the proportionate liability statutes in the various States. The author asserts that the legal regimes have failed in their primary purpose of making damages awarded against multiple defendants more equitable. The recent High Court decision in Hunt & Hunt v Mitchell Morgan Nominees Pty Ltd [2013] HCA 10 has not resolved the uncertainty as to how the laws should operate. The matter is before the Standing Committee of Attorney’s–General who are considering the need for legislative reform. It would seem to be a matter of ‘watch this space’! Geoff Hansen and Jennifer Galatas give a brief outline of the recent legislative changes to both the domestic and international arbitration law in Australia. The work concludes with a discussion of a decision of the Victorian Supreme Court, Lysaght Building Solutions Pty Ltd v Blanalko Pty Ltd [No 3] [2013] VSC 435, where the power of the court to stay proceedings under the Commercial Arbitration Act 2011 (Vic) was considered. Under the Act, the Court must grant a stay where there is an arbitration clause in the contract. However, where the parties have referred particular disputes to another form of dispute resolution, this provision will be respected. This has the potential to culminate in split proceedings with additional costs to the parties. This is something that needs to be taken into consideration when drafting arbitration clauses. Alisa Taylor and Kimberly Moore note in a short article that in NSW and ACT it is not possible to enforce multiple invoices under a standing order contract in the same payment claim under the security of payment legislation. Each must be made the subject of a separate claim. Our old friend, Philip Davenport, brings us up to date on some of the latest decisions on the security of payment legislation. Ren Niemann and Goran Gelic tell us of the Queensland Government’s plans to restructure the regulation of the Queensland Building Industry by replacing the Queensland Building Services Authority with the Queensland Building Construction Commission. For the time being it will be business as usual but from the table of changes proposed the changes will be more than a ‘rearrangement of the deckchairs’. Scott Laycock and Rohan Dias discuss a Queensland decision in Agripower Australia Ltd v J & D Rigging Pty Ltd [2013] QSC 164 where it was held that the Building and Construction Industry Payments Act 2004 (Qld) did not apply to a contract for the removal of mining equipment from a mine site. It is an interesting case that raises questions about property law. The authors speculate whether this will be the case in other States. The decision comes as something of a surprise as the builder was held to owe a duty of care to the developer and the owners of the strata plan. In some respects it reinstates the much maligned decision in Bryan v Maloney (1995) 182 CLR 609. It will be interesting to see if there is an appeal to the High Court? APOLOGY We do make mistakes and when we do we like to put things right. The ACLN did not acknowledge the co–authorship of Mr Michael Lake, Solicitor, Herbert Smith Freehills, to Ms Elisabeth Maryanov’s two articles in the July/August 2013 issue of the ACLN. The articles in question, ‘The importance of getting your adjudication application and response right’ and ‘When is a rental agreement a ‘construction contract’?’ appeared on pages 26 and 42 respectively. The ACLN apologizes to Mr Lake for its error. An international flavour is added to this issue of ACLN by Malcolm Chin and Miranda Noble who use introduction of the Hong Kong Competition Ordinance as a basis for a review of anti–competitive regimes in other nearby jurisdictions. The discussion is wide ranging and covers Japan, Australia, Singapore and the United Kingdom. The article is a cautionary tale for the Construction Industry in Hong Kong and calls to mind the Giles Royal Commission in New South Wales. Peter Pether, Adam Wallwork and Jennifer Turner, in a case note, detail how the New South Wales Court of Appeal has overturned the first instance decision in The Owners—Strata Plan No 61288 v Brookfield Australia Investments Ltd (2013) NSWCA 317. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 5 NEGLIGENCE THE DUTY OF CARE IN DESIGN—CAN ENGINEERS RELY ON CODES OF PRACTICE? Dr Donald Charrett, Barrister, Arbitrator and Mediator Melbourne TEC Chambers and Chairman AMOG Holdings, Melbourne Dr Andrew Potts, Chief Executive Officer AMOG Holdings, Melbourne INTRODUCTION Contracts for engineering design normally include the obligation that the services will be performed with the reasonable skill, care and diligence that would be applied by a normally skilled member of the profession in similar circumstances. The profession makes considerable use of codes of practice, or ‘standards’, which codify current design practice. The prevailing view of the design profession is that such standards represent the ‘state of the art’ that they are expected to apply. But does compliance with the current applicable standard mean that the designer has discharged his/her contractual duty of care? Might something more be required? Does the designer need to anticipate how the design standards may evolve? This paper addresses these questions in the light of a recent case, in which the judge’s findings on the applicable standard of care in relation to the use of current design standards may be surprising to many designers. CODES OF PRACTICE AND STANDARDS WHAT IS A STANDARD? Standards can be guidance documents including the following types of documents: • Australian Standards • International Standards and Joint Standards • Codes of Practice • Specifications • Handbooks • Guidelines The following definitions from a UK publication define the different meanings ascribed by engineers to ‘Standards’ and ‘Codes of Practice’: 6 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 Standards ‘set out certain tests, dimensions, tolerances and qualities for a product or process. Historically in certain areas, e.g. structures, they have set out prescribed methods for specific calculations and even prescribe permissible stresses. More recently these kinds of standards have become normative’.1 Codes of Practice ‘are not standards but do set out the standard to be followed. The specific requirements in a code of practice must be followed either for best practice or because the document has a legal status. For example specific partial factors of safety are stated in structural codes. Requirements for tying together tall buildings, to ensure robustness and prevent progressive collapse are set out in the UK Building Regulations. The ways of complying are set out in codes that are deemed to satisfy that part of the Building Regulations’.2 In the context of the engineer’s duty of care and for the purposes of this paper, there is no significant difference between ‘Standards’ and ‘Codes of Practice, and the terms are used interchangeably. PROCESS FOR ISSUE OF AN AUSTRALIAN STANDARD Australian Standards are issued by ‘Standards Australia’, an independent company whose principal activity is the development of Australian Standards. Whilst Standards Australia is an independent company, it is acknowledged by the Australian Government (via a Memorandum of Understanding) as Australia’s peak non–government Standards– writing body and the Australian representative on the International Organisation for Standardisation (ISO). In developing a Standard, Standards Australia uses a process based on: • Consensus; • Transparency; and • Balance of representation. Consensus means: ‘General agreement, characterised by the absence of sustained opposition to substantial issues by any important part of the concerned interests and by a process that involves seeking to take into account the views of all parties concerned and to reconcile any conflicting arguments’.3 Notwithstanding the requirement for general agreement, consensus need not imply unanimity within the broad spectrum of stakeholders brought together as the Standard Committee to draft the final Standard. Transparency means: ‘that information on current work programs and proposals is available to all interested parties. Transparency also includes the concept of openness, participation on a non–discriminatory basis, impartiality and a balanced participation in the development process by interests that will be significantly affected by the final Standard’.4 Transparency is intended to avoid the potential for skewing the provisions of a Standard towards particular commercial interests. However, where there are few, or only a single Australian manufacturer, it is often difficult to separate implicit commercial interests from provisions that appropriately cover the spectrum of Australian manufactured products. Thus, if these Australian manufactured products do not represent world’s best practice, then the Standard may reinforce inferior standards. However the movement towards bringing national standards in line with other major trading nations, and the associated drive towards greater commonality with International Standards Organisation (ISO) Standards, works against such parochial practices. Balance of Representation: ‘The membership of a Standards Australia Committee is formally balanced as part of the constitution of the Committee to represent the broadest possible spectrum of stakeholder interests’.5 In reality, participation on all Standards Australia Committees is voluntary in nature, as participants are not remunerated for their efforts by Standards Australia. Participation typically requires time given by employers, so membership on a Technical Committee may often be additional to normal work duties, and/or done in personal time as an extra curricula activity. Consequently, the best qualified persons or leading practitioners, are not always available for such sustained participation. Thus, the balance achieved in the ‘spectrum of stakeholder interests’ can be subjective and once established, can by its own make–up be self–perpetuating in the interests and expertise being represented. The entire process of writing Standards is itself formalized and documented in a series of Australian Standards: • SG–001 Preparing Standards • SG–002 Structure and Operation of Standardisation Committees • SG–003 Standards and Other Publications • SG–004 Roles and Responsibilities in Standardisation • SG–005 Technical Governance and Advisory Structures for the Standards Development Process • SG–006 Rules for the Structure of Australian Standards • SG–007 Adoption of International Standards • SG–009 Preparation of Standards for Legislative Adoption • SG–015 Australian Involvement in International Standardisation • SG–017 Drafting of Standards Referenced Under OH&S Legislation • SG–018 Standards Referenced by Water Utilities • SG–020 Participation by Consumers in Standardisation.6 INTERESTED PARTIES The content of a Standard is the responsibility of a Technical Committee. The basis for the composition of a Technical Committee is to ensure balanced participation by those interests that are significantly affected by the resulting Standard. Individual members of a Technical Committee are selected by Nominating Organisations that may include, but are not restricted to, government bodies, industry associations, community–based and consumer organisations, employee organisations and professional, technical or trade associations. For example, the following 17 interested parties represented on Committee BD–025 that was responsible for AS2870– 2011 Residential slabs and footings shows a wide range of representation: (1) Australian Building Code Board (2) Australian Chamber of Commerce and Industry (3) Australian Geomechanics Society (4) Australian Institute of Building Surveyors (5) Cement Concrete and Aggregates Australia (6) Concrete Masonry Association of Australia AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 7 (7) Construction Industry Advisory Council (8) Engineers Australia (9) Foundations and Footings Society of Australia (10) Housing Industry Association (11) Master Builders Australia (12) National Timber Development Council (13) Plastics and Chemicals Industries Association (14) Steel Reinforcement Institute of Australia (15) Think Brick Australia (16) University of Newcastle (17) University of South Australia The diversity of the interested parties being represented meets the charter ‘to represent the broadest possible spectrum of stakeholder interests’, but does not necessarily have influence over the personnel being nominated in terms of qualifications, expertise, currency of research or industry practice, etc. Indeed, without in any way casting aspersions on the example Committee cited above, it is readily apparent that whilst there are numerous ‘industry sector interest groups’ represented, it is not apparent whether their nominees are representing current ‘state–of–the–art’ products and practices, or leading–edge technology and practices that may arise from within each sectoral interest. Is the ‘industry sector interest group’ nominating an employee whose regular responsibilities involve commercial, promotional or technical support, or seeking interested, available and qualified personnel from within its sector? If the latter, what selection criteria are adopted? The nominees of its major corporate supporters, from its semi–retired members, or driven individuals with particular pet interests? OUTCOME OF STANDARD DEVELOPMENT PROCESS Australian Standards are published documents that set out specifications and procedures with the aim of ensuring that products, services and systems are safe, reliable and consistently perform the way they were intended to. They establish a common language which defines quality and safety criteria acceptable to a broad range of interested parties. All Australian Standards are expected to deliver a net benefit to the Australian community, taking into consideration: • public health and safety; • social and community impact; • environmental impact; • competition; and • economic impact.7 These are an appropriate set of expectations to strive for in terms of net benefit to the community at large. However, it is submitted that Standards should not introduce or engender provisions that have implicit or explicit negative impacts on the status quo of the above listed community considerations. Nor are, nor should, Standards be a channel for back–door social engineering. In essence, by documenting norms in a common language, Standards enable the community and industry to seek and contract for goods and services on a level playing field. They specify minimum acceptable requirements pertaining to the majority of transactions that were anticipated in conceiving and scoping the particular Standard. The minimum acceptable requirements may address safety, quality and reliability, with implications for environmental impact and public health and safety considerations. The ability to contract for goods and services 8 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 on a level playing field of minimum acceptable requirements is good for competition within the marketplace, with implications for society at large through the ensuing economic benefits. However, establishing such norms as the basis for putting out to tender and contracting for goods and services, also sets the technical basis for which these goods or services are priced and the commercial terms of offer. The upside of Standards is that the common forms of transaction for normal goods or services do not require a critical evaluation of the specific circumstances in order to establish alternate applications or project specific requirements or basis of design. This efficiency streamlines the process of scoping the goods and services sought and being offered, enables proceduralisation and standardisation of their delivery and removes uncertainty in the technical requirements for delivery and acceptance criteria. The downside can arise on the infrequent occasions when the Standards, or particular elements of a Standard, may not be adequate or appropriate for the circumstances in question. If not recognized and accepted upfront by either the client or the engineer, the request for tender may be an inadequate or unsound basis upon which to price and apply regular terms of offer. Thereafter, once the scope and commercial terms of contract are agreed, the momentum of the works will overwhelm the unnatural tendency to query the adequacy or applicability of the industry accepted Standard which is applied in most regularly contracted goods or services. Professionals generally accept that appropriate procedures have been applied in the drafting, review and adoption of a Standard, so that it represents the ‘state–of–the–art’. On what informed or qualified basis would the regular practitioner be aware of the specific basis of each provision of the Standards, background research and deliberations of the Technical Committee and its individual members? In the authors’ view, it is commercially impractical and contrary to the professional objective of Standards for a user to review the project specific circumstances to assess the applicability and adequacy of each and every provision of a contractually specified Standard. STATUTORY SIGNIFICANCE OF CODES AND STANDARDS As issued by Standards Australia, a private non–government organization, Australian Standards have no intrinsic statutory significance. Certain individual Standards achieve statutory force when they are incorporated into legislation. Many Standards are never incorporated into legislation, and thus have no statutory significance. Typically Standards are incorporated indirectly via subordinate legislation, as illustrated by the following Victorian example in the context of domestic housing. The Building Act 1993 (Vic) lists as one of its main purposes: ‘to regulate building work and building standards’. The Building Act empowers the Governor in Counsel to make Regulations in respect of, inter alia: ‘building permits, occupancy permits and temporary approvals, including the duration of permits and approvals and the matters to be complied with by the relevant building surveyor before a permit or approval can be issued’.8 The Building Regulations 1996 (Vic) includes amongst its objectives: ‘provide for matters relating to the accreditation of building products, construction methods, designs, components and systems connected with building work’.9 The Building Code of Australia (BCA) is incorporated in the Building Act 1993 (Vic) via the Building Regulations 1996 (Vic): ‘The BCA is adopted by and forms part of the Regulations as modified by this Part’.10 The BCA adopts a number of Australian Standards by listing specific editions in Table 1.4.1, including the following examples relevant to design: ... does compliance with the current applicable standard mean that the designer has discharged his/her contractual duty of care? Might something more be required? Does the designer need to anticipate how the design standards may evolve? • AS1170 Structural Design Actions • AS1657–1992 Fixed Platforms, Walkways, Stairways and Ladders—Design, Construction and Installation (SAA Code for Fixed Platforms Walkways, Stairways and Ladders) • AS2870–1996 and 2011 Residential slabs and footings • AS3600–2009 Concrete Structures • AS4055–2006 Wind Loads for Housing • AS4100–1998 Steel Structures. When an engineering failure is investigated by a government body, it will first seek to verify that the design, operation or equipment complies with the prevailing Australian Standard, or another recognised international Standard, if there is no appropriate Australian Standard. Notices of failure to comply and rectification, fines, shut–down notices, or progression to litigation, often result from an identified failure to meet recognised Standards. In the authors’ experience in litigation, the prevailing Standard is frequently used as the fundamental measuring stick of engineering adequacy. Often this is done on the advice of inspectors or practitioners, who may have little AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 9 knowledge as to the background and basis of development of the Standards they are citing, the operating paradigm for which they were conceived, or indeed the suitability of all the code provisions to the circumstances to which they are being applied. In these circumstances, Standards are implicitly assumed as embodying the ‘state–of–the–art’, where non–compliance is, prime facie, a fundamental breach of the duty of care by the professional practitioner. CONTRACTUAL SIGNIFICANCE OF CODES AND STANDARDS Many contracts specify that particular applicable Codes and Standards form part of the contract. For example the Federation Internationale des Ingenieurs– Conseils Conditions of Contract for Plant and Design Build and Conditions of Contract for EPC/ Turnkey Projects (FIDIC Silver Book) provides as follows: 5.3 Contractor’s Undertaking The contractor undertakes that the design, the contractor’s Documents, the execution and the completed works will be in accordance with: … the documents forming the contract …’ 5.4 Technical Standards and Regulations The design, the contractor’s documents, the execution and the completed works shall comply with the Country’s technical standards, building, construction and environmental Laws, Laws applicable to the product being produced from the works, and other standards specified in the Employer’s Requirements, applicable to the works, or defined by the applicable laws.’ … ‘Employer’s Requirements’ means the document entitled employer’s requirements, as included in the contract, and any additions and modifications to such document in accordance with the contract. Such document specifies the purpose, scope and/or design and/or other technical criteria, for the works. In addition to these overarching requirements in the FIDIC General Conditions, it is common for employers to specifically nominate an extensive list of Standards and Codes of Practice in the Particular Conditions that the designer is required to comply with. In these circumstances, compliance with Standards is a contractual obligation, in addition to obligations that might arise from a duty of care. DUTY OF CARE IN DESIGN COMMON LAW There are many judicial statements on the standard of the common law duty of care that a professional person must comply with, e.g. Where you get a situation which involves the use of some special skill or competence … the test is the standard of the ordinary skilled man exercising and professing to have that special skill. A man need not possess the highest expert skill … it is sufficient if he exercises the ordinary skill of the ordinary competent man exercising that particular art.11 And in somewhat more detail: … a professional man should command the corpus of knowledge which forms part of the professional equipment of the ordinary member of the profession. He should not lag behind other assiduous and intelligent members 10 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 of his profession in knowledge of new advances, discoveries and developments in his field. He should have such awareness as an ordinarily competent practitioner would have of the deficiencies in his knowledge and the limitations in his skills. He should be alert to the hazards and risks inherent in any profession or task he undertakes to the extent that other ordinarily competent members of his profession would be alert. He must bring to any professional task he undertakes no less expertise, skill and care than other ordinarily competent professional would bring, but need bring no more. The standard is that of the reasonably average. The law does not require of a professional man that he be a paragon, combining the properties of polymath and prophet.12 The message in these statements to designers is clear: be up to date with the knowledge of the profession in your area of expertise, and know your limitations! STATUTORY MODIFICATION OF THE COMMON LAW The Parliaments of the Australian States and Territories have legislated significant statutory modifications to the common law of negligence since the turn of the century. Some of these statutory modifications are directly applicable to an engineer’s duty of care. For example, the Wrongs Act 1958 (Vic) contains the following relevant sections: 59 Standard of Care for Professionals (1) A professional is not negligent in providing a professional service if it is established that the professional acted in a manner that (at the time the service was provided) was widely accepted in Australia by a significant number of respected practitioners in the field (peer professional opinion) as competent professional practice in the circumstances. care in giving that warning or other information. (2) However, peer professional opinion cannot be relied on for the purposes of this section if the Court determines that the opinion is unreasonable. Arguably, this is a subjective standard that does not provide the same measure of predictability that section 59 provides in relation to the ‘peer professional opinion standard’. (3) The fact that there are differing peer professional opinions widely accepted in Australia by a significant number of respected practitioners in the field concerning a matter does not prevent any one or more (or all) of those opinions being relied on for the purposes of this section. (4) Peer professional opinion does not have to be universally accepted to be considered widely accepted. (5) If, under this section, a Court determines peer professional opinion to be unreasonable, it must specify in writing the reasons for that determination. 60 Duty to Warn of Risk Section 59 does not apply to a liability arising in connection with the giving of (or the failure to give) a warning or other information in respect of a risk or other matter to a person if the giving of the warning or information is associated with the provision by a professional of a professional service. Section 60 thus contains an important carve–out from the ‘peer professional opinion standard’—it does not apply in relation to the duty to warn of a risk. That duty is somewhat unhelpfully articulated as follows: 50 Duty to Warn of Risk — Reasonable Care A person (the defendant) who owes a duty of care to another person (the plaintiff) to give a warning or other information to the plaintiff in respect of a risk or other matter, satisfies that duty of care if the defendant takes reasonable There are three potential sources for requiring a duty of care in design: (1) an implied or express term in the designer’s contract of engagement that the design will be prepared with reasonable skill, care and diligence; (2) a tortious duty of care under the common law that is generally co–extensive with the contractual obligation to exercise due care in preparing the design; and (3) statutory provisions on duty of care that codify and perhaps limit common law rules. IS THERE AN OBLIGATION FOR AN ENGINEER TO COMPLY WITH A CODE OR STANDARD? It is suggested that there are three possible sources of such an obligation: (1) a mandatory statutory requirement, such as incorporation of a Standard in legislation, e.g. the Building Act cites Building Regulations, which cites BCA which cites Standards; (2) a mandatory express provision of the contract to comply with a Standard, e.g. FIDIC Silver Book; and/or (3) a duty of care arising from either or both a contractual or tortuous duty to exercise reasonable skill, care and diligence in carrying out engineering. The statutory or contractual obligations to comply are known and unexceptional. However the issue of compliance arising from an engineer’s duty of care is less clear. It is contended that in most cases compliance satisfies the ‘peer professional opinion standard’. Arguably, a Standard documents the ‘state–of– the–art’ of the ordinarily competent professional, whereby: • it is the product of a formal, structured process; • the Technical Committee responsible is deemed competent in the relevant fields; • a broad and disparate spectrum of interested parties are represented on the Technical Committee; • the published Standard is the result of consensus between the Technical Committee members; • a broad range of community interests are considered in establishing the appropriate balance between conflicting requirements; and • amendments can be made, and communicated to the profession, if there are advances in the ‘state– of–the–art’ or deficiencies or errors in the Standard identified after publication. It should be borne in mind that Standards prescribe minimum requirements. Hence, any non–compliance with minimum specified criteria would need to satisfy the ‘reasonable professional’ test: Would the non–compliance be ‘widely accepted in Australia by a significant number of respected practitioners in the field (peer professional opinion) as competent professional practice in the circumstance? An engineer’s conscious decision not to follow the requirements of a Standard may create additional risks for their client. This is equally applicable to a conscious decision to substantially exceed a AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 11 ... in respect of conventional infrastructure, a Standard represents the ‘state–of–the–art’ endorsed by the profession, and compliance with it is consistent with acting ‘in a manner that ... was widely accepted in Australia by a significant number of respected practitioners in the field ... as competent professional practice in the circumstances’. Standard’s minimum requirements just as it is not to achieve them. There are cases in which an engineer has been found to be negligent in preparing a costly design that substantially exceeded a Standard’s requirements. Thus, there are risks and potential consequences if a Standard is not complied with. A prudent engineer electing not to comply with a Standard would therefore be well advised to warn their client of the risks and ensure that the client acquiesced in the decision. It should also be noted that the provisions of Standards and Codes of Practice are not suited to ‘mix and match’ clauses from different documents. Like a contract, a Standard needs to be construed as a whole document in which the individual provisions are integrated into an overarching conceptual framework. For example, the limit state design of steel structures in accordance with AS4100 Steel Structures Code needs to be carried out for loads derived from AS1170 Structural Design Actions. It could be quite unsafe to design a structure to AS4100 for loads derived from a Standard that was based on inconsistent assumptions in respect of partial factors for material strength. IS COMPLIANCE WITH A CODE OR STANDARD SUFFICIENT? The authors’ proposition is as follows: in respect of conventional infrastructure, a Standard represents the ‘state–of–the–art’ endorsed by the profession, and compliance with it is consistent with acting ‘in a manner that (at the time the service was provided) was widely accepted in Australia by a significant number of respected practitioners in the field (peer professional opinion) as competent professional practice in the circumstances’. 12 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 In other words, compliance with a Standard in the design of conventional infrastructure is an exercise of ‘the ordinary skill of the ordinary competent man exercising that particular art’. It is not suggested that this proposition would be valid in respect of major hazard facilities, or structures involving new or untested concepts. Highly skilled practitioners, or academics specializing in a particular field, may consider that the provisions of a Standard are inadequate, or are not ‘state of the art’ in the context of ‘leading edge’. The authors suggest that that does not immediately translate to the ‘state–of–the–art’ of the ordinarily competent practitioner. Standards are living documents, regularly updated either by specific amendments to particular provisions (which can occur when a significant deficiency becomes known), or by a general revision to incorporate advances in the ‘state of the art’. A major revision of a Standard may require the profession to undertake retraining to adopt new approaches. The profession usually accepts such revised Standards as an evolution of the ‘state of the art’ of the ordinarily competent practitioner. However, before a Standard is formally revised and re–issued, there may have been a number of draft revisions in progress at various times, and circulated for comment. Such draft revisions typically receive wide exposure in the technical community as part of the transparent and consensual process of Standard preparation, but they are by no measure adopted prior to the ‘official’ revision. Do the provisions of a draft revised Standard issued for review immediately translate to the ‘state–of–the–art’ of the ordinarily competent practitioner? The authors submit that it does not; by their nature ‘draft’ revisions are circulated for comment and review, and the finally adopted provisions in the revised Standard may bear little relation to the draft provisions, or the inclusion of subtle changes in a draft may significantly alter its interpretation and application to particular circumstances. The situation may be different if it was universally accepted in the profession that certain provisions of a Standard were deficient. In that case, the ordinarily competent practitioner would be aware of the deficiencies, and in the exercise of her/his duty of care, would make appropriate provision in the design (Note: A clear distinction is made between the profession adopting Amendments or Warning Notices pertaining to an existing Code or Standard, as opposed to observing the provisions of an incomplete or unadopted Draft version of a Code of Standard that has been distributed for comment). However if the inadequacy of certain provisions of a Standard was controversial, section 59(3) of the Wrongs Act 1958 (Vic) (or equivalent in other States) could provide a defence supporting compliance: ‘The fact that there are differing peer professional opinions widely accepted in Australia by a significant number of respected practitioners in the field concerning a matter does not prevent any one or more (or all) of those opinions being relied on for the purposes of this section’. A CASE STUDY BHP COAL PTY LTD & ORS V O&K ORENSTEIN & KOPPEL AG Some of the issues discussed above in relation to an engineer’s duty of care in respect of compliance with Standards and Codes were highlighted in BHP Coal Pty Ltd & Ors v O&K Orenstein & Koppel AG13 (Goonyella case). This case concerned the total collapse of a Bucket Wheel Excavator (BWE) at the Goonyella mine in Central Queensland. Design, supply and installation of the BWE took place between 1978 and 1981. In November/December 1984 grounding of the bucket wheel due to misoperation of the BWE caused buckling damage to the rear tower flanges. The owner arranged for an engineer from O&K (the designer and supplier of the BWE) to inspect the damage and prepare an on–site emergency repair proposal. The repair of the buckling and addition of eight stiffeners was executed by a third party under the supervision of an O&K supervisor, primarily there for stabilisation of the balanced machine before and after the repair works. Sometime after the repair was completed, fatigue cracks in the steel columns started to propagate from the repair welds at the ends of the added stiffeners. Between 1985 and 1999 TKEA carried out bi–annual inspections of the BWE structure, with the final inspection in March 1999. In March 2000 the BWE collapsed. There was a Mine Warden’s Court Inquiry into the collapse in 2002, and in 2003 BHP initiated legal proceedings against O&K and TKEA. The court hearing occupied a total of 120 sitting days between April 2007 and February 2008. In his judgment, McMurdo J found that, in respect of the design of the repair stiffeners, O&K had breached its duty of care and had engaged in misleading or deceptive conduct in breach of the Trade Practices Act. He also found that, in respect of the inspection of the BWE after the repair work had been completed, TKEA had breached its contract, breached its duty of care and had engaged in misleading or deceptive conduct in breach of the Trade Practices Act. The misleading and deceptive conduct ruling will not be discussed further herein, as it is not germane to the theme of this paper, which is covered by the other part of the ruling. The negligence case against O&K ultimately hinged on the judge’s findings in respect of detailed aspects of the design of the welding of the repair strengthening stiffeners, the location of the fatigue cracks that ultimately propagated sufficient to cause complete collapse of the BWE. The upper stiffener terminations terminated in an area with bending stresses higher than further up the tower. The design of these upper stiffener terminations was awkward and increased the local stress. The judge found that if the engineer had made proper fatigue stress calculations he would have identified that the upper stiffener terminations were in a critical spot. Further, if the engineer had identified the problems caused by the chosen details, he could without problems have extended the stiffeners to the end of the tower or designed a better detail that would not have been as susceptible to fatigue. The contract for construction of the BWE required it to be constructed according to the operative German Standard specific to BWEs at the time, BG60. This was still the operative standard for BWEs used by O&K in 1984, although a draft revision had been circulated for discussion within the drafting Committee in 1984. ISO 5049 was an alternative international standard applicable to mining machinery (including BWEs, though this was not its predominant area of focus) that resulted in lower fatigue strengths of welded joints than BG60. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 13 The welded detail of the upper stiffener termination implemented (FI) had adequate fatigue strength according to BG60, but not according to ISO 5049. ISO 5049 was developed for application to the design of bulk–ore handling machinery, such as stackers, reclaimers, bucket–wheel reclaimers and ship loaders, where the load duty handling excavated material in stockyards and the like, is more consistent than bucket– wheel excavators digging hard material directly from the earth. • O&K knew that ISO 5049 specified lower allowable fatigue stresses; ‘ISO 5049 should have alerted an engineer to the risk of using only BG60’. [Although ISO 5049 includes BWEs in its scope, it was not in general use by the industry for the design of BWEs as was BG60, where there are significant differences in load duties between the two codes. Also ISO 5049’s fatigue S–N curve for the FI category was significantly more conservative than BG60 and BG86.] As such, the fatigue load duty provisions of ISO 5049 was aligned to a more uniform load duty spectrum, which was not the case for fatigue load duty provisions in the design codes that were mostly in use of BWEs (including BG60 and its successor BG86). McMurdo J expressed his findings on this Standard issue as follows: McMurdo J considered the following issues relevant to his conclusion that BG60 was unreliable as a standard with which to design the FI welded detail. [The authors’ comments on these issues are in square brackets.] • BG60 was ‘being challenged by some and officially reviewed’ in 1984 and was replaced by BG86 in 1986. [It should be noted that the fatigue provisions of the 1984 Draft were more onerous than BG60 and were not adopted in the final Standard BG86. The welded repair details complied with the requirements of BG60 and BG86 but would have failed the 1984 Draft.] • BG60 did not take dynamic loads into account, although this was not necessarily a prevalent professional opinion in 1984. [BG60 did not include a specific dynamic load factor on the statically determined loads in its load case combinations, as did BG86, but BG86 was actually calibrated against BG60 to produce similar design outcomes.] ... But I do not accept that a reasonable engineer would have been obliged to give up a long– standing code (BG60), if otherwise considered to be reliable merely because some engineers, however eminent, were publishing an opinion suggesting otherwise ...14 ... I am not satisfied that such an engineer would have thought that BG60 overstated the fatigue strength of an FI detail ... However, any reasonable engineer in his position should have doubted the reliability of BG60. After all there was a review of BG60 which had been put in place by the relevant West German authority. The review committee had been constituted, made up of leading engineers from the major manufacturers and academics. … All of that amounted to more than a professional opinion being ventilated occasionally in published journals or seminars. … In the midst of that review the reasonable engineer in [the designer’s] position could not have said to himself at the same time that BG60 was reliable. ... Because BG60 was unreliable, that margin for error should not have been accepted as reasonable ...15 14 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 COMMENTS ON PRACTICAL DESIGN ENGINEERING ASPECTS OF JUDGMENT Merely because a Standard is under review by an eminent Committee, which as part of its remit is to update/modernise the code, with respect it does not follow that ‘a reasonable engineer should have doubted the reliability of BG60’. The ultimate ‘official’ revision, BG86, was in fact calibrated to BG60 because that had been found to produce reliable designs that had adequate fatigue service lives. If no notices of warning or amendments to the Standard had been issued, even during the Standard review phase, what if any basis was there for the conclusion that ‘a reasonable engineer should have doubted the reliability of BG60’? Indeed many Standards are subject to regular periodic review (with draft revisions in the public domain)—does this automatically oblige the design engineer to consider the current, unamended version as suspect and potentially ‘unreliable’? What would have been the legal standing of the design engineer in adopting the provisions of an interim draft Standard that was still subject to considerable deliberation by the Committee? In the case of the fatigue provisions of the 1984 Draft, these were ultimately rejected by the Committee in the final issue of BG86. Arguably, design of an entire machine to the 1984 draft provisions would have ultimately proved to have been unnecessarily conservative and added unwarranted cost. Design Codes are intended to be inherently conservative in their provisions, as they are intended to apply to the majority of applicable systems for which they have been developed. Factors of safety are applied to and allowable stresses are used in conjunction with conservatively compounded design loads. In the case of fatigue, the design load combinations are used in conjunction with lower bound S–N curves used for design purposes. When in design is it appropriate to apply even more conservative factors of safety over and above accepted and current codified values in Standards? Such additional conservatism has commercial and feasibility implications for the client to whom the engineer owes a duty of care. Thus, if there was no valid basis to conclude that ‘BG60 was unreliable’, why then should the codified ‘margin for error.. not have been accepted as reasonable. …’? Even if there was some concern as to the adequacy of the codified factors of safety, what would be an acceptable technical basis for employing higher values? (e.g. +5%, +10%, +25% ...? If the Standard is unreliable but you can’t put your finger on it, what is a ‘reasonable’ fix?). If a designer arbitrarily adopted, say an additional 10% margin for safety, to cover some unquantifiable reservations, and then the structure still failed at some time in the future, would the Court view this as the prudent act of a reasonable engineer, or an ill–fated guess in the absence of a more technically supported engineering design decision. At the heart of engineering design codes, there is an intent to provide inherent conservatism, not to sail close to the wind and thereby court regular failure. This enables engineers to make safe design decisions with a degree of comfort that they do not in most circumstances need to question the basis and applicability of the codes they are relying upon. The professional training of engineers, whilst not eliminating the prospect of codes being limited, or occasionally in error, is largely skewed towards engineers practicising their profession by following the provisions of the many codes that apply to their sector. Most engineers are ‘code practitioners’ not ‘code questioners’. If codes have required constant questioning, then the engineering profession has over the years progressively amended and improved the deficient elements of such codes. This has involved drawing on the expertise and experience from other countries with similar codes, and this has reduced the instances where codes need to questioned. The profession would have a fundamental problem were there a Court implied requirement that on all occasions the ‘code practitioners’ should become ‘code questioners’. CONCLUSION The genesis of Standards, the common law and relevant statutory provisions suggest that engineers should generally be able to rely on current relevant Standards and Codes of Practice when designing conventional infrastructure. practicing professional as to what is an acceptable degree of conservatism. The judgment in the Goonyella case contains some surprising and salutory warnings for practicing engineers: • There may be an obligation to question, monitor and understand the reliability of current codes in light of ‘potential’ amendments. • There may be an obligation to consider other Standards than those specified in the contract, and if more conservative apply such provisions. REFERENCES 1. New Dictionary of Civil Engineering (2005) 2. Ibid 3. Standards Australia website: www.standards.org.au 4. Ibid 5. Ibid 6. Ibid 7. Ibid 8. Section 261(1)(a) It would be chaotic for the majority of the engineering profession undertaking design on a daily basis if they were not able to rely upon current Codes and Standards. There is neither the time nor the fees for designers to undertake a critical review of the provisions of design Codes and Standards for conventional and well understood infrastructure for which they have been written. 9. R101 If in hindsight Courts judge that the conservatism in design Codes and Standards is inadequate, this brings into question the ‘professional consensus’ underlying their development and status within the engineering profession and as the basis of construction contracts. It provides no guidance to the 15. Ibid [160]–[162] 10. Building Regulations 1996 (Vic) R109 11. Bolam v Friern Hospital Management Committee [1957] 1 WR 582 HL, 586 per McNair J 12. Eckersley v Binnie & Partners (1988) 18 Con LR 1 13. [2008] QSC 141 14. Ibid [157] Donald Charrett and Andrew Potts’ paper is based on the authors’ presentation to the Society of Construction Law Conference in Sydney on 3 August 2013. Reprinted with permission. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 15 CONTRACTS GOOD FAITH IN CONTRACT PERFORMANCE—HAS THE LAW CHANGED? SUMMARY Tom Grace, Partner The reaches of the Trade Practices Act 1974 (Cth) and the Competition and Consumer Act 2010 (Cth) exemplify the nature and extent of the way in which lawmakers have sought to ensure that parties cannot hide unsatisfactory conduct behind the facade of a contract without the obligation to avoid misleading and deceptive conduct, or unconscionable conduct. Without doubt, there have been significant changes in the past and this paper looks at recent case law to assess whether those changes continue to occur. Jock Hamilton, Associate Fenwick Elliott Grace, Adelaide The doctrine of good faith in the performance of contracts has been gradually developed over the last few decades. In this paper we examine the doctrine of good faith and its implication into commercial contracts. The effects of this new view of the doctrine of good faith are becoming clearer now and it is timely for lawyers to consider the impacts on their clients and their contracts. The paper notes the particular practical impact on the commercial construction sector of this emerging doctrine. PERFORMING THE CONTRACT IN GOOD FAITH INTRODUCTION Commentary on good faith in the performance of contractual obligations is abundant.1 In this paper we trace the history of the development of the doctrine and conclude by examining the recent application of the principle in Alstom v YDMRL,2 decided in April 2012 by Justice Bleby. To give context, we consider the evolution of implied good faith in other Australian jurisdictions before concluding that to a large extent Justice Bleby has not sought to change the test for the implication 16 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 of the good faith duty. Rather, we conclude the Alstom decision sets a high water mark in construction law in terms of how far reaching can be the impact of the good faith doctrine. THE EVOLUTION OF THE DOCTRINE OF GOOD FAITH Before discussing Alstom in detail, it is useful to re–cap on the evolution of good faith in the performance of contracts as well as briefly summarise relevant cases with respect to implied terms. Good faith in Australia is a common law doctrine, usually implied by law,3 although some commentators have suggested Courts have implied a duty of good faith by fact. By way of brief summary, terms may be implied by fact subject to the five–pronged test set out by Privy Council in BP Refinery (Westernport) Pty Ltd v Hastings Shire Council:4 (1) it must be reasonable and equitable; (2) it must be necessary to give business efficacy to the contract so that no term will be implied if the contract is effective without it; (3) it must be so obvious that ‘it goes without saying’; (4) it must be capable of clear expression; and (5) it must not contradict any express term of the contract.5 Terms implied by law, traditionally, apply to specific types of contract. For example, sale of goods contracts have an implied term at law that the goods will be of merchantable quality.6 Thus, there firstly must be such an identifiable type of contract and secondly, such a term needs to be implied into all contracts within that type or class. In Liverpool City Council v Irwin,7 the Court used a ‘necessity’ test to determine whether a term should be implied as a matter at law. The landlord of a high rise residential dwelling building sought to absolve himself of liability to maintain lift and stair access facilities. Applying the necessity test, the Court implied a term into tenancy agreements that the landlord would maintain the lifts and stairs because life as a tenant was ‘not possible’ without the ‘essentials’ of the lift and stair facilities.8 McHugh and Gummow JJ in Byrne v Australian Airlines Ltd9 subsequently considered that the necessity test should apply in circumstances where ‘unless such a term [is] implied, the enjoyment of the rights conferred by the contract would or could be rendered nugatory, worthless, or, perhaps be seriously undermined’.10 Historically, judiciaries in Australia have not always been clear about whether good faith is implied in fact or in law. We consider some cases below. In the 1953 case Carr v Berriman,11 the High Court considered an architect’s ‘absolute discretion’ in administering a building contract. As is usual, the architect was acting as an agent for the principal–owner. A dispute arose when the owner sought to unilaterally exclude certain works from the contract, seeking to rely on the architect’s apparently unfettered discretion to administer the works. Fullagar J disagreed, holding that: [Those words] do not, in my opinion, authorise him to say that particular items so included shall be carried out not by the builder with whom the contract is made but by some other builder or contractor. The words used do not, in their natural meaning, extend so far, and [vest] a power in the architect to hand over at will any part of the contract to another contractor would be a most unreasonable power, which very clear words would be required to confer.12 Upon a dispute arising, the superintendent terminated the contract in accordance with the clause above. Note the lack of a formal reference to an implied term of good faith in this context. Notwithstanding, some academics have suggested that Fullagar J’s judgment was a ‘good faith interpretation’,13 presumably in its infancy. When the litigation reached the New South Wales Court of Appeal, Priestley JA held there were ‘terms implied by law’16 that the principal would exercise its powers reasonably: RENARD AND THE MINISTER OF WORKS In any event, the implied term of good faith was considered by Priestley, Meagher and Handley JJA in the landmark New South Wales case of Renard Constructions (ME) Pty Ltd v Minister for Public Works.14 The principal (Minister for Public Works) engaged Renard to construct pumping stations near Gosford on the NSW Central Coast. The contract between the two parties provided the superintendent (nominated by the principal) with relatively broad termination powers: ... if the contractor defaults in the performance or observance of any covenant, condition or stipulation in the contract or refuses or neglects to comply with any direction as defined in clause 23 but being one which either the principal or the superintendent is empowered to give, make, issue or serve under the contract and which is issued or given to or served or made upon the contractor by the principal in writing or by the superintendent in accordance with clause 23, the principal may suspend payment under the contract and may call upon the contractor, by notice in writing, to show cause within a period specified in the notice why the powers hereinafter contained in this clause should not be exercised.15 The contract can in my opinion only be effective as a workable business document under which the promises of each party to the other may be fulfilled, if the subclause is read in the way I have indicated, that is, as subject to requirements of reasonableness.17 Priestly JA then drew parallels between good faith and reasonableness: ‘[t]he kind of reasonableness I have been discussing seems to me to have much in common with the notions of good faith’,18 and thus the nexus between reasonableness and good faith appears to have been born. Priestly JA further considered good faith by reference to community expectations: ... people generally, including judges and other lawyers, from all strands of the community, have grown used to the courts applying standards of fairness to contract which are wholly consistent with the existence in all contracts of a duty upon the parties of good faith and fair dealing in its performance. In my view this is in these days the expected standard, and anything less is contrary to prevailing community expectations.19 SIR ANTHONY MASON’S THREE NOTIONS A year after the Renard decision in a speech at Cambridge University, Sir Anthony Mason considered extra–judicially that good faith ‘embraced no less than three notions’:20 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 17 (1) an obligation on the parties to cooperate in achieving the contractual objects (loyalty to the promise itself); (2) compliance with honest standards of conduct; and (3) compliance with standards of conduct which are reasonable having regard to the interests of the parties. OTHER CASES Finn J recognised the traction an implied duty of good faith was gaining in his discussion in Hughes Aircraft Systems Int’l v Airservices Australia:21 a ‘more open recognition [of an implied term of good faith] in our own contract law is now warranted’.22 Sir Anthony Mason’s three notion test was referred to with some approval by the Court in the 1998 case of Alcatel Australia Ltd v Scarcella.23 Sheller JA stated: If a contract confers power on a contracting party in terms wider than necessary for the protection of the legitimate interests of that party, the courts may interpret the power as not extending to the action proposed by the party in whom the power is vested or, alternatively, conclude that the powers are being exercised in a capricious or arbitrary manner or for an extraneous purpose, which is another [way] of saying the same thing. Thus, a vendor may not be allowed to exercise a contractual power where it would be unconscionable in the circumstances to do so: Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575 at 587.24 In 1999, Finkelstein J in Garry Rogers Motors v Subaru25 held that while good faith involved not acting ‘capriciously’, the doctrine was nevertheless tied with acting reasonably: ‘provided the party exercising the power acts reasonably in all the circumstances the duty to act fairly and in good faith will ordinarily be satisfied’.26 Interestingly, Finkelstein J noted that an implied term of good faith ‘would not operate so as to restrict actions designed to promote the legitimate interests of that party’.27 Towards the turn of the millennia, Courts were differing on their interpretation of the Renard decision. For example, in Aiton Australia Pty Ltd v Transfield Pty Ltd28 Einstein J, agreeing with Stapleton LJ, sought to distinguish between the implied duty of reasonableness and that of good faith: ... the inter–relationship of and difference between good faith and reasonableness is subtle but of great importance. A requirement to satisfy a standard of reasonable behaviour is more demanding than the requirement of good faith.29 Conversely and at about the same time, Byrne J of the Victorian Supreme Court commented in Far Horizons Pty Ltd v McDonald’s Australia that:30 I do not see myself as at liberty to depart from the considerable body of authority in this country which has followed the decision of the New South Wales Court of Appeal in Renard. I proceed, therefore, on the basis that there is to be implied in a franchise agreement a term of good faith and fair dealing which obliges each party to exercise the powers conferred upon it by the agreement in good faith and reasonably, and not capriciously or for some extraneous purpose. Such a term is a legal incident of such a contract.31 BURGER KING In 2001, the Court in Burger King v Hungry Jack’s summed: ‘[the Renard decision made] no distinction of substance between the implied term of reasonableness and that of good faith’.32 The Court in Burger King provides an instructive discussion on the evolution of good faith up to 2001. 18 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 Burger King had granted non– exclusive rights to Hungry Jack’s to develop fast food franchise restaurants under the marketing banner of Burger King, in accordance with the parties’ Development Agreement.33 Pursuant to the Development Agreement, Hungry Jack’s was required to open at least four new Burger King restaurants per year. For a variety of reasons, the parties’ commercial relationship deteriorated.34 In 1995, Burger King effectively barred Hungry Jack’s from fulfilling its obligations to develop new franchises by ‘withdrawing financial and operational approval from Hungry Jack’s’.35 Burger King also froze Hungry Jack’s ability to recruit third party franchises. In 1996, Burger King then sought to terminate the Development Agreement for Hungry Jack’s failure to develop the requisite number of new restaurants. Hungry Jack’s maintained that it was unable to fulfil its contractual obligations by virtue of Burger King’s lack of support as mentioned above. The Court held that: ... there is such an extraordinary range of detailed considerations, particularly in relation to whether operational requirements have been satisfied...unless there was an implied requirement of reasonableness and good faith, Burger King could, for the slightest of breaches, bring to an end the very valuable rights which Hungry Jack’s had under the Development Agreement.36 The Court also considered the balancing act between Burger King’s own ‘legitimate interests’ and acting reasonably (as discussed in Garry Rogers Motors v Subaru above): That does not mean that Burger King Corporation is not entitled to have regard only to its own legitimate interests in exercising its discretion. However, it must not do so for a purpose extraneous to the contract — for example, by withholding financial or operational approval where there is no basis to do so, so as to thwart Hungry Jack’s rights under the contract.37 Note that the Court did not find that Burger King had a fiduciary duty to Hungry Jack’s, but rather that Burger King’s discretion under the Development Approval: ... could not be used for a purpose foreign to that for which it was granted, such as to thwart [Hungry Jack’s] right to develop and ultimately procure a situation where the Agreement could be terminated.38 Notwithstanding the variety of cases since Renard considering the implied duty of good faith, an element of uncertainty remained post Burger King. In 2006, Gyles J, in the Federal Court case of City of Sydney v Goldspar Australia Pty Ltd39 noted that there was a ‘bewildering variety of opinions in the authorities and commentaries as to the implication of terms as to reasonableness and good faith in commercial contracts’.40 It is against this relatively imprecise background, and without any directly relevant High Court authority, that we consider the Alstom decision. ALSTOM V YDMRL—GOOD FAITH ASPECTS THE FACTS IN MORE DETAIL The Alstom decision extends over 460 pages, covering an extensive range of contract law principles and considering a remarkable number of authorities. Flinders Power Partnership (FPP) engaged Alstom as head contractor to refurbish part of the Playford Power Station at Port Augusta (project) pursuant to a ‘Turnkey Refurbishment Contract’ for approximately $150 million (head contract). A ‘Turnkey Contract’ is common in the construction industry where a principal engages a head contractor to design and build a project with relatively little further input from the principal. Often the head contractor then engages a number of subcontractors as required. Alstom then subcontracted about one fifth (approximately $33.88m) of the head contract works to YDMRL (subcontract). The refurbishment was a complex project involving ‘thousands of activities’:41 YDMRL was to supply and install some electrical equipment before allowing Alstom to complete various other associated works around that equipment. After Alstom’s had carried out some work, YDMRL was to again work around the same areas on the site for the final phase of the project. Accordingly, there was an obvious interdependence on one party’s ability to perform works dependant on the other party’s predecessor activity of works. To manage the interdependences and complexities generally, the head contract specified the use of programming software, Primavera P3 (program). A primary objective of the program was to allow the parties to determine the ‘critical path’ of the works. The ‘critical path’ is the sequence of activities from start to finish whose duration determines the overall project duration.42 If a certain activity or part of an activity is on the critical path, then the critical part of the activity needs to be completed43 before the subsequent activity can be commenced. Obviously, if there is a delay to a critical activity then there is likely to be a delay to the completion of the entire project.44 Contrast this with a delay to a non–critical activity which would not prevent further critical works being undertaken at the same time and therefore would be unlikely to delay the project as a whole. While both Alstom and YDMRL used Primavera to adjust ‘on–site changes’ to their own individual works schedule, the program could also be used as a form of communication, where both parties could reflect their individual requirements, progress and forecasts within an integrated version of the program. Primavera contains logic links within its data output, such that the software is capable of showing activities that are on the critical path. If there is to be a known delay to a future activity (for example construction materials being delayed in customs) that future delay can be programmed into the software to analyse whether the delay means that works would best be rearranged into a new sequence to avoid the completion date being extended for the full time period that the materials are delayed in customs. There are always delays in construction projects, and where information is not provided to subcontractors about future delays, there is a likelihood of inefficient deployment of resources. Ideally, in order to facilitate the integration of both parties’ works schedules, Alstom would have regularly provided an updated master program to YDMRL showing all the logic links and delays that were known to Alstom in respect of the entire project. While Alstom maintained it was not expressly obliged to provide its master program to YDMRL, doing so would have been immensely helpful to YDMRL’s planning because YDMRL, in many circumstances to a large extent, relied on Alstom completing critical activities before YDMRL could undertake some of its own critical path activities. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 19 The Project was ultimately delayed and Alstom was liable to FPP for a considerable amount by way of liquidated damages. Alstom settled its dispute with FPP. Alstom then sought to claim approximately $20m from YDMRL for delays and other claims. YDMRL denied liability for Alstom’s claims and counterclaimed for variations and disruption costs (among other claims) for approximately $11m. In its pleadings, YDMRL’s position was that, without relevant information being passed down from Alstom’s master program, YDMRL was unable to forecast its own critical path works effectively, and so its own works schedule was merely ‘hypothetical’:45 ... without regular access to Alstom’s programs, or at least to frequent and updated interface information from Alstom with appropriate logic links, it was impossible for YDRML to prepare a useful critical path program. It was therefore impossible for YDRML, through the regular supply of its updated programs, to indicate reliably when YDRML activities on which Alstom was dependent would be completed. This applied throughout the period of the contract.46 YDMRL further argued that its future programming requirements were essentially ‘little more than guesswork’47 in the absence of accurate programming information from Alstom. In failing to provide YDMRL with Alstom’s updated master program, YDMRL maintained that Alstom breached an implied term of law that Alstom had a duty to co– operate and a duty to act in good faith. Alstom sought to rely on a lack of an express contractual framework binding it to supply copies of its master program to YDMRL. Rather, Alstom’s position was that YDMRL ‘could and did prepare its own critical path program without Alstom’s aid. If YDMRL were delayed for any reason, such as access, in carrying out an activity on its critical path, it could give notice of delay and claim an EOT in accordance with the terms of the [Sub]contract, which it did not do’.48 In submitting this argument, Alstom suggested YDMRL could manage its dates and critical path as a ‘stand–alone’ program: ‘If YDRML were delayed, that delay was to be assessed against the critical path in YDRML’s program. If Alstom were delayed, that delay would be assessed against the critical path in Alstom’s program’.49 THE COURT’S FINDING ON IMPLICATION OF GOOD FAITH Bleby J rejected this contention of Alstom finding it ‘superficial ... misconceived and impracticable’.50 Bleby J, citing established authority,51 emphasised that the duty to co–operate was not limited to merely allowing the other ‘party to perform its obligations under the contract but extends to requiring each party to the contract to do all such things as are necessary on their part to enable the other party to have the benefit of the contract’.52 In relation to the obligation to act in good faith, Bleby J referred to the leading authorities discussed above. However, Bleby J went further, agreeing with Finn J, who in obiter in GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd53 considered that all contracts should be subject to the implied term of a duty of good faith and fair dealing.54 Consider the contrast between this notion (that an implication of good faith should be implied as a matter of law to all commercial contracts), and the traditional understanding of implied terms as a matter of law in relation to an identifiable class of 20 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 contracts. Bleby J appears to have departed from this concept. To that end, Bleby J said at paragraph 596, when referring to universally implying an obligation to act in good faith: I consider that it is a term to be implied in every commercial contract, despite doubts expressed in some earlier cases that it was to be implied unequivocally as a universal term.55 Bleby J noted that ‘universal implication is supported by the American Restatement (Second) of Contract (1981),56 and is part of the law of contract in Europe, the United States, Canada, New Zealand, China, Japan and other parts of the world’.57 Bleby J further cited the 2009 case of United Group Rail Services Ltd v Rail Corporation of New South Wales58 where the Court of Appeal, after referring to Renard, Burger King and Alcatel said that ‘good faith, in some degree or to some extent, is part of the law of performance of contracts’59 in support of universal implication into contracts of an obligation to act in good faith. In any event and notwithstanding the above, Bleby J considered the subcontract was ‘of the type of contract where it must be implied’.60 Bleby J ultimately referred to good faith as the ‘glue’ to the contractual terms: The Playford refurbishment was a complex project involving thousands of interrelated activities to be conducted by these two parties. Their respective contractual and operational requirements demanded a high degree of co–operation and reliance upon the good faith of each other. Without that glue to cement the contractual terms their relationships were likely to, as they did, break down. That in itself is a compelling indication of the existence of an implied obligation to act reasonably and in good faith.61 Reference was also made to the fact that, in the absence of an implied duty of good faith, YDMRL would be ‘unable to perform its contract effectively’: Without an obligation to act reasonably and in good faith on the part of Alstom, YDRML would be unable to perform its contract effectively. The absence of such an obligation would allow a situation to arise where, for example, YDRML might not even know what a particular Relevant Scheduled Date was to which it was required to work, because that information was being withheld by Alstom. It would also allow a situation where YDRML might not know which, if any, of YDRML’s work was on the critical path for a Relevant Scheduled Date. In such circumstances YDRML would be deprived of the contractual benefit to which it was entitled under the contract.62 WHAT ALSTOM SHOULD HAVE DONE From a practical viewpoint and perhaps the most striking aspect of Justice Bleby’s decision is what Alstom ought to have done if it was to perform its contractual obligations in accordance with an implied duty of good faith: I do find, however, that the implied obligation to co–operate, the implied obligation not to prevent or hinder YDRML’s performance of the EC&I contract and the implied obligation to act in good faith had the following effects, in this case: That Alstom was required to provide regularly to YDRML its updated and accurate works program showing at least all logic links to YDRML activities, all relevant interface and access information and the critical paths to the respective Milestone Dates, and particularly the Relevant Scheduled Dates; That that should have been provided whenever any material changes occurred which might affect YDRML’s program; and, That the programs provided should have been in Primavera P3 form and in a format capable of being integrated with YDRML’s own Primavera P3 program.63 Bleby J went on to find that some express terms of the subcontract supported implying a term of good faith. However, he noted that the considerations mentioned above were ‘sufficient in themselves to justify the necessary implication’64 and so no further analysis of the express terms supporting this implication is presently necessary. Justice Belby was critical of Alstom’s possible motives for failing to pass on its updated master program to YDMRL, suggesting that, on a ‘less generous’ view, Alstom may have withheld the master program to ‘conceal’ the effect of its own delays which may have entitled YDMRL to make an EOT claim. CONSEQUENCES FROM ALSTOM In our view, the Alstom decision applies the duty of good faith, implied as a matter of law, consistently with the trend since Burger King. The fundamental tests as they currently stand in Australia have not changed materially. However, it is significant that Bleby J considers the duty to perform contractual obligations in good faith is implied into all commercial contracts. It effectively means that in many projects similar to the Playford Refurbishment Project, head contractors would be prudent to ensure their master program is conveyed to a subcontractor in a workable form (as opposed to a PDF) from the outset and regularly, so the subcontractor can integrate the head contractor’s information with the subcontractor’s own works program. The practical difficulty that arises, as recognised by Bleby J at paragraph 641, is that changing circumstances may change the interests of the head contractor such that it would be preferable to effectively withhold certain information from their subcontractors. Might there be cases where it is in the ‘legitimate interests’ of the head contractor to withhold such information without it breaching any implied duty of good faith? Such determinations would require finely balancing relevant considerations and will necessarily turn on individual facts. WILL THE CHANGE REMAIN? As emphasised by Bleby J, other jurisdictions have statutorily implied and/or codified the implication of good faith. This is not the case in Australia, where the doctrine of good faith remains entrenched in the common law. To date, there is a lack of High Court direction on what the implied duty of good faith actually entails. In Royal Botanic Gardens and Domain Trust v South Sydney City Council65 the Court acknowledged the good faith doctrine but failed to consider it in detail, citing the circumstances of that case were an ‘inappropriate occasion’ to consider the issue. There is little doubt that some detailed High Court discussion would be welcome by lower courts and academia. DRAFTING AND NEGOTIATING CONTRACTS AND THE IMPLICATION OF GOOD FAITH The implication of terms has always been subject to any express term to the contrary. Parties who wish to be excused from acting in good faith might incorporate an appropriate express term into their contract. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 21 However, the other contracting party would be unlikely to be advised to enter into such a contract unless the contract was written in such a manner that it could not be misinterpreted. In our view, it would be commercially unrealistic to attempt to negotiate such a term. Further, efforts to withhold the tide of judicial thinking are frequently frustrated by the Courts and it is generally more acceptable when approaching the Court for an award of damages, to be coming from the position of higher moral ground. In the alternative, parties might seek to incorporate into their contracts a more detailed set of requirements as to function. In the construction industry in respect of programming information, such requirements would for example include setting out the precise nature and extent of the information that is to be exchanged. The recommendations adopted by the UK Society of Construction Law are referred to with approval in Alstom. The Society’s Delay and Disruption Protocol is an excellent reference point for parties requiring a workable set of rules governing the production and exchange of programming information in construction projects. CONCLUSION The law of contract has developed over the last two decades in Australia, particularly in respect of the requirement for good faith in the performance of contract. However, the High Court has not yet found a suitable vehicle to express a determinative view on the topic. The Alstom decision arises from a particular set of facts that may be distinguishable from other construction projects. However, the history of the progression of the law reveals that particular sets of facts often introduce a new approach to the law that then resounds to impact on more general situations. It remains to be seen whether higher courts agree with Bleby J when he says that it is a term to be implied in every commercial contract’66 or whether the factual matrix will decide whether implication of the term is appropriate. In the interim, prudent lawyers will operate on the assumption that the changes set out in this paper will remain. At least in South Australia, the precedent is now clearly established. REFERENCES 1. See, for example, Ms Elisabeth Peden and Mr Bill Dixon 2. Alstom Ltd v YDMRL Pty Ltd [2012] SASC 49 3. Terms can also be implied by custom but the threshold test is high and circumstances limited. That consideration is presently outside the scope of this discussion. Note that whether a duty of good faith is implied by fact or law has been the subject of considerable judicial comment, although the trend supports an implication at law. 4. BP Refinery (Westernport) Pty Ltd v Hastings Shire Council 180 CLR 266 5. Ibid 283 12. Ibid [347] 13. Our understanding of Ms Peden’s argument is that this case indicates that good faith is inherent in contract law and therefore no implied duty of good faith is necessary. Elizabeth Peden, ‘Implicit Good Faith – or do we still need an implied term of Good Faith’, (2009) 25 Journal of Contract Law. 14. Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR 234 15. Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR 234, 273 16. Ibid 273, 257 – 263 17. Ibid 258F 18. Ibid 273 19. Ibid 268 20. Sir Anthony Mason, ‘Contract and its relationship with equitable standards and the doctrine of good faith’—The Cambridge Lectures 1993, Canadian Institute of Advanced Legal Studies, Cambridge University (an amended version under the title ‘Contract, Good Faith and Equitable Standards in Fair Dealing’, submitted 30/9/99) appears in (2000) 116 Law Quarterly Review 66–94. 21. Hughes Aircraft Systems International v Airservices Australia [1997] FCA 558 6. Such terms are predominantly now statutorily implied in jurisdictions across Australia. 22. Ibid as discussed in Burger King Corporation v Hungry Jack’s Pty Ltd [2001] NSWCA 187, at [158] 7. Liverpool City Council v Irwin [1977] AC 239 23. Alcatel Australia Ltd v Scarcella & Ors [1998] NSWSC 483 8. Ibid 254 24. Ibid 368 9. Byrne v Australian Airlines Ltd (1995) 185 CLR 411 25. Garry Rogers Motors (Australia) Pty Ltd v Subaru (Australia) Pty Ltd [1999] FCA 903 10. Ibid 450 11. Carr v J A Berriman Pty Ltd (1953) 89 CLR 327 22 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 26. See Burger King Corporation v Hungry Jack’s Pty Ltd [2001] NSWCA 187 [172] 27. Garry Rogers Motors (Australia) Pty Ltd v Subaru (Australia) Pty Ltd [1999] FCA 903, at [37] 28. Aiton Australia Pty Ltd v Transfield Pty Ltd [1999] NSWSC 996 44. Note this may be subject to any acceleration works. 45. Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [544] 46. Ibid, at [521] 47. Ibid at [523] 29. Ibid [133] 48. Ibid at [527] 30. Far Horizons Pty Ltd v McDonald’s Australia Ltd [2000] VSC 310 49. Ibid at [547] 31. Ibid [120] 32. Burger King Corporation v Hungry Jack’s Pty Ltd [2001] NSWCA 187, at [169] 33. Note there were several agreements in place between the parties. For present purposes, we focus on the Development Agreement. 50. Ibid at [547] 51. Butt v McDonald (1896) 7 QLJ 68, 70–71 52. Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [570] 54. Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [586] 55. Alcatel Australia Ltd v Scarcella (1998) 44 NSWLR 349, 369; Vodafone Pacific Ltd v Mobile Innovations Ltd [2004] NSWCA 15, [188]–[189]; Esso Australia Resources Pty Ltd v Southern Pacific Petroleum NL [2005] VSCA 228, [25] 35. Burger King Corporation v Hungry Jack’s Pty Ltd [2001] NSWCA 187, at [38] 57. Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [596] 37. Ibid at [185] 38. Ibid [187] 39. Council of the City of Sydney v Goldspar Australia Pty Ltd [2006] FCA 472 40. Ibid [166] 41. Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [548] 42. The Society of Construction Law Delay and Disruption Protocol, October 2002, 54 43. Some critical path activities only need to be commenced before the subsequent activity starts, others need to be completed. Tom Grace and Jock Hamilton’s paper was presented at Legalwise Seminars on Contract Law: Risks and Disputes in Adelaide on 19 June 2013. Reprinted with permission. 53. GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd (2003) 128 FCR 1, 208–209 34. Burger King sought to expand its direct operations in Australia and this was obviously not in Hungry Jack’s interests. In doing so, Burger King sought to enter into an agreement with Shell Service Stations to the exclusion of Hungry Jack’s; commercial relations suffered. 36. Ibid at [183] 66. Alcatel Australia Ltd v Scarcella (1998) 44 NSWLR 349, 369; Vodafone Pacific Ltd v Mobile Innovations Ltd [2004] NSWCA 15, [188]–[189]; Esso Australia Resources Pty Ltd v Southern Pacific Petroleum NL [2005] VSCA 228, at [25] 56. Section 205 58. United Group Rail Services Ltd v Rail Corporation of New South Wales (2009) 74 NSWLR 618 59. Ibid at 635 as discussed by Bleby J in Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [593] 60. Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [596] 61. Alstom Ltd v YDMRL Pty Ltd & Anor [2012] 49, at [597] 62. Ibid at [598] 63. Ibid at [606] 64. Ibid at [609] 65. Royal Botanic Gardens and Domain Trust v South Sydney City Council [2002] HCA 5 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 23 ELECTRONIC TRANSACTIONS HIT ‘SEND’ AND HOPE—PROBLEMS WITH CONTRACTUAL NOTICES BY EMAIL INTRODUCTION Owen Hayford, Partner Email has become the preferred means of sending written communications in business. It’s fast, cheap and convenient. So it is no surprise that people are using email to send purchase orders, payment claims and other contractual notifications. Nor is it any surprise that parties want their contracts to permit the use of email for contractual communications. Betina Friedeberg, Senior Associate Clayton Utz, Sydney Using email to send contractual notices can be risky, but there are things you can do to reduce the risks. However, the use of email for contractual communications is fraught with legal and technical risks. As such, it’s important that people understand these risks and take appropriate steps to manage them. This article explains the risks and how they can be managed. WHEN IS YOUR EMAIL TAKEN TO HAVE BEEN RECEIVED? The time at which a contractual notice is taken to have been received can have important contractual consequences. The time for payment often runs from the date a claim for payment is received. Contractual options, such as an option to renew or extend a lease, must typically be exercised by giving written notice by a particular date. Claims for extra money or extra time under a contract can be barred if not given within time. Accordingly, it can be critical for the sender of a contractual notice to be able to demonstrate when the notice was received by the recipient. Most written contracts include a clause dealing with contractual notices. The clause will usually set out addresses to which notices can be hand delivered, posted or faxed. It will also generally include a provision stating that the notice is deemed to have been received by the recipient: 24 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 • if it is hand delivered, at the time it is so delivered; • if it is sent by fax, at the time in the place to which it is sent which is equivalent to the time shown on the transmission confirmation report produced by the machine from which it is sent; and • if it is sent by pre–paid post, on the third business day after the date of posting to an address within Australia, and on the fifth business day after the date of posting by airmail to an address outside Australia. It has also become increasingly common for such clauses to include an email address to which notices can be sent, and to specify when a notice sent by email will be deemed to have been received by the recipient. However, for the reasons explained below, there is no universally accepted formulation for the deemed time of receipt of emails. RULES FOR TIME OF RECEIPT UNDER THE ELECTRONIC TRANSACTIONS ACTS Legislation has been enacted, at the Federal level and in each Australian State and Territory, dealing with emails. This legislation provides some rules for determining when emails have been received. In short, the rules are: • if the recipient has provided the sender with its email address, the time of receipt is when the email enters the recipient’s mail server (unless the parties agree otherwise); and • if the recipient has not provided the sender with its email address, the time of receipt is when it comes to the attention of the recipient (unless the parties agree otherwise). These rules seem sensible on first blush, but if you are the sender of the email, how will you prove the time at which the email was received by the recipient’s mail server if you don’t request and receive a ‘delivery receipt’ from the recipient’s server? Most people don’t regularly request ‘delivery receipts’. And even if you do, the recipient can set up his or her email system so that delivery receipts are never issued, even if you request one. What if the sender gets a response from the recipient’s email server saying that the email could not be delivered because it exceeded a specified number of megabytes? Alternatively, what if the sender gets an ‘out of office’ response, or an automated response advising that the recipient has left the organisation? In each case, the sender will have evidence that the email has entered the recipient’s mail server, and so the recipient will be deemed to have received the email at the time the sender received the response (if not earlier). But is this result fair for the receiver? You might consider it is, because the recipient’s organisation can allow the email to pass through its firewall, and can arrange for someone to read the recipient’s emails while the recipient is on leave or after the recipient has left the organisation. But if you’re the recipient and you fail to take such steps, there is a significant risk that you or your organisation will be deemed to have received emails that haven’t made it to your inbox, or that you haven’t read. ALTERNATIVE RULES FOR THE TIME OF RECEIPT OF EMAIL You can depart from the legislated rules for the time of receipt of emails by specifying alternative rules in your contract. Many parties do this. Alternative rules for the deemed receipt of emails which are often adopted include: • the time the email is sent by the sender; or • a specific period after the time it is sent by the sender. There are issues with both of these alternative rules. For the time of sending option, while emails are often received within seconds of being sent, delays can occur. Is it fair for the recipient to be deemed to have received the email before it has been received by the recipient’s email server? For the specific period option, there remains the risk that the email is not received within the specified period, or ever. Also, if the specified period is lengthy, for example 24 hours (as is often specified), then there is a significant risk that senders will forget this rule and assume that the email is received the moment (or shortly after) it is sent. Senders of emails can be easily caught out and the consequences of a late notice can be drastic, as demonstrated by some recent court cases. SOME RECENT COURT CASES— WITH UNEXPECTED OUTCOMES! THE BAUEN CASE—EMAIL CAUGHT IN SPAM FILTER In Bauen Constructions Pty Ltd v Sky General Services Pty Ltd [2012] NSWSC 1123, the Supreme Court of New South Wales had to determine the time of receipt of an email containing an adjudication response under the Building and Construction Industry Security of Payment Act 1999 (NSW) (BCISPA). The adjudication response was sent by email on 21 June 2012 to the adjudicator. However, the adjudicator was unaware of the email until 12 September 2012, when it discovered the email was caught in its spam filter. The court decided that the word ‘lodged’ in section 20 of the BCISPA meant ‘presented’ or ‘received’, and relied on the legislated rules in the Electronic Transactions Act to establish that receipt was when the email was capable of being retrieved by the recipient, meaning it was not necessary for it to be opened or read. Accordingly, the adjudicator had received it, and was able to access it, when the email was caught by its spam filter on 21 June 2012, which meant Bauen had lodged the adjudication response in time. Luckily for the sender, the recipient of the email disclosed evidence that the email had been caught in its spam filter and, therefore, had been received by the recipient’s email server. Had the recipient not done so, the sender may not have been able to prove that it had been sent in time. THE REED CASE—TIME OF RECEIPT OF EMAIL Reed Constructions Pty Limited v Eire Contractors Pty Limited [2009] NSWSC 678 considered a construction contract for civil works based on a NSW Government standard contract, GC21, which permitted service by email. The time of receipt of an email attaching a payment claim was crucial to the validity of an adjudicator’s determination under the BCISPA. The New South Wales Supreme Court considered the legislated rules discussed above. The court concluded, applying these rules, that a payment claim could be served by email and that the time of receipt was when the email was received by the recipient’s email server. The recipient of the email wanted the court to conclude that the email was received on 6 November, and not 7 November as determined by the adjudicator. There was AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 25 Email has become the preferred means of sending written communications in business. It’s fast, cheap and convenient. So it is no surprise that people are using email to send purchase orders, payment claims and other contractual notifications. Nor is it any surprise that parties want their contracts to permit the use of email for contractual communications. evidence before the adjudicator and the court that the email was sent by the sender on 6 November, and that it was read by the recipient on 7 November. However, the recipient failed to produce any evidence that the email was received by its email server any earlier than 7 November. Consequently, the court refused to overturn the adjudicator’s decision that the email was received on 7 November, and the adjudicator’s determination against the recipient was upheld. While this case is not an example of a sender being unable to prove the time at which an email was received by the recipient’s server, it does illustrate how the deemed time of receipt of an email notice can be critical to the outcome of a claim. A SOLUTION— AUTOMATIC RECEIPT NOTIFICATIONS There is at least one way to avoid the difficulties identified above, but it requires the agreement of both parties and some technical skills. The solution requires each contracting party to set up its email system so that it automatically issues a delivery receipt notification upon receipt of an email from another contracting party. The parties would then state in their contract that emails are deemed to be received at the time shown on the automatic receipt notification received by the sender. An automatic receipt notification is different to a delivery receipt, as it is automatically generated and sent by the recipient’s email system, whether or not the sender has requested it. The automatic receipt notification can be set up so it only generates a receipt once an email has passed through the firewall and arrived in the recipient’s inbox, thereby overcoming the problem of emails being deemed received if they are caught in the recipient’s firewall. 26 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 Where the sender and recipient are in different time zones, the deemed time of receipt requires careful consideration. Even if each party usually conducts its business in the same time zone, there may be occasions when you want to send a communication from a different time zone. Accordingly, the contract should specify the deemed time of receipt as the time in the place to which the email is sent equivalent to the time shown on the sender’s automatic receipt notification (unless received outside of business hours in that place, in which case it is deemed to be received at the commencement of the next business day). CONSIDER USING A CONTRACT SPECIFIC MAILBOX Sending automatic receipt notifications will generate a lot of email traffic if the recipient receives a lot of emails. Accordingly, you may want to set up your email system so that automatic receipt notifications are only sent when emails are received from specified senders. To address this issue, you may wish to establish a contract specific mailbox (e.g. contractnotices@company.com. au) so that all email traffic for a particular contract goes to and from the contract specific mailbox. This approach also has the advantage of: • enabling you to give alternative persons access to the mailbox as circumstances demand; • eliminating the need to change the email address if the person nominated to send and receive contractual notifications is replaced during the life of a contract; and • allowing tailored firewall and email size restrictions. ONUS ON SENDER With automatic receipt notifications, the onus is on the sender to ensure that it receives and retains the receipt notification so that it can prove the time of receipt. If the sender does not receive the automatic receipt notification, the onus is on the sender to resend the communication, perhaps by an alternative method, or confirm that the recipient did in fact receive the message. Some companies set up their contract specific mailboxes to automatically send a test email at regular intervals to check whether the recipient’s automatic receipt notification function is working. If an automatic receipt notification is not received within a predefined period of time, an alert is sent to a designated employee to investigate. ATTACHMENTS TO EMAILS It’s not uncommon for people to receive email attachments in a form which they cannot open without the relevant software. Such a situation recently came before the Supreme Court of Western Australia in the case of Triple M Mechanical Services Pty Ltd v Ellis (unreported 2 May 2013, BC201302298). In this case, an adjudicator to a security of payment claim decided that the attachments to an email (which was received in time) were received out of time because the adjudicator could not open the attachments. The attachments were sent as RAR files the first time and again as a ‘YouSendIt’ link, both within time, and then as hard copies the following day, out of time. The court was critical of the adjudicator’s reasoning for disregarding the attachments because reliable applications were readily accessible free of charge which would have allowed the adjudicator to open the attachments. The court could not, however, overturn the adjudicator’s decision because it was not reviewable. To avoid such situations and provide greater certainty, you should consider recording the agreed formats for email attachments in your contracts, so that you can ensure you have the software required to open and read any attachments which you’ll be deemed to have received. CONSIDER LIMITING EMAIL TO FORMAL COMMUNICATIONS Another risk associated with email communications is their informality. People seem to think more carefully before signing letters or forms than they do before hitting the send button on an email. We’ve all said things in emails that perhaps we wouldn’t have said in a letter or other, more formal, communication. In most contexts, the consequences of such indiscretions are minor. But in the case of contractual communications, the consequences can be very significant indeed. Accordingly, you may consider mitigating this risk by including a provision in your contracts which states that: • contractual communications can only be sent by email if the communication is in the form of a PDF of a letter or document which has been signed by someone who is authorised to do so; • only the signed document (and any other attachments to the email which are referred to in the signed document) will be treated as a communication for the purposes of the contract; and ON–LINE DOCUMENT MANAGEMENT AND COMMUNICATION TOOLS If you expect to have a large number of communications under a contract, you may wish to consider utilising an online document management and communication tool. There are many products now available which allow contracting parties to transmit and store documents electronically. Many of these products have sophisticated mechanisms for recording the time at which documents were sent, received and read, which overcome many of the issues associated with emails. WHAT SHOULD YOU DO? There is no simple answer to the question of when a contract should deem a notice sent by email to have been received. Some approaches, such as the time it is sent by the sender, work for the sender, but can be unfair to the recipient. Others, such as the time it is received by the recipient’s server, can work for the recipient, but can be unfair for the sender. Further, there are numerous risks which you should consider before signing contracts which permit the use of email for contractual communications. If you want to use email for contractual notices, you should include appropriate provisions in your contracts to enable you to manage these risks. Owen Hayford and Betina Friedeberg’s article was previously published in (2013) 16 (8) Inhouse Counsel 147. Reprinted with permission kindly granted by LexisNexis Australia. • the text in the body and subject line of an email will not form part of the contractual communication. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 27 SECURITY OF PAYMENT THREE EARLY SECURITY OF PAYMENT CASES IN SOUTH AUSTRALIA Robert Fenwick Elliott, Barrister Howard Zelling Chambers, Adelaide The Building and Construction Industry Security of Payment Act 2009 (SA) (closely modelled on the NSW Act) was enacted in December 2009, but challenges under it have only just started reaching the courts. In part, this is because the Act does not apply to contracts entered into before 10 December 2011, and in part because it has taken a while for potential cases to work their way through the system. But there have now been three cases which provide an early indication of the reception that the Act has received from the courts. The Adelaide Interior Linings case first came before the District Court as Romaldi Constructions v Adelaide Interior Linings [2013] SADC 39 (3 April 2013). Judge Barrett granted an injunction restraining the enforcement of the determination for $51,219.83, saying: I find that there is a real risk of the defendant’s inability to repay the adjudication sum if the injunction is not granted. I find that the balance of convenience favours the granting of the injunction. The decision was remarkable, because there had been no challenge to the determination itself in the sense of any claim that it was without jurisdiction, or in breach of natural justice, or subject to judicial review— the application by the losing respondent was simply on the basis that the claimant had not demonstrated that it would have the financial resources to repay the sum awarded at the conclusion of full court proceedings to recover it. The order for an injunction was conditional on the respondent paying the determined amount into court. It is not unheard of for a court to stay enforcement of a determination pending the hearing of a challenge or exceptionally where there is a high level risk of insolvency, but there was no challenge here and the decision was based on much looser evidence of financial means and would—if followed—have had the effect of undermining the very purpose of the legislation: it is very frequently the case that a claimant under the legislation would be unable to prove its ability to afford full–scale proceedings, either in the courts or by way of arbitration. And that was the principal basis on which the decision was reversed on appeal as Adelaide Interior Linings Pty Ltd v Romaldi Constructions Pty Ltd [2013] SASC 110. Justice Anderson said: The respondent, having elected not to challenge the validity of the adjudication, cannot be permitted to circumvent the objects of the Act by taking its own action to prevent the adjudication certificate from being issued. Further, on the evidence, the Supreme Court was dismissive of the District Court’s relaxation of the usual insolvency test, finding that: 28 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 ... the information does not approach a high level of likelihood of insolvency using that as the test. It is understood that Romaldi has sought permission to appeal the case further to the Full Court. The second case to come before the Supreme Court was Built Environs Pty Ltd V Tali Engineering Pty Ltd & Ors [2013] SASC 84 (3 June 2013), in which a determination for $579,420.90 plus GST and costs was challenged on multiple grounds, of which two succeeded. The first concerned an issue that arises not infrequently, and exposes an inherent weakness in the approach of many adjudicators who are trained not to call for conferences and not to invite further submissions. It arises in this way: (1) A claimant puts in a payment claim. (2) The respondent puts in a payment schedule. In this case, the payment claim asserted a right to deduct liquidated damages. (3) The claimant puts in an adjudication application with submissions. Under the legislation, there is no express prohibition on the submissions including new matters that were not included in the payment claim. In this case, they included a submission that the respondent had prevented completion, so as to negative its entitlement to the liquidated damages that would otherwise be deductable. (4) The respondent puts in an adjudication response that must be limited to matters raised in the payment schedule. The payment schedule in this case did not refer to the prevention issues (and indeed could not possibly have done so, because the issue had not then been raised). The adjudication response does not therefore deal with the new matters. Thus, unless an adjudicator in these circumstances allows the respondent to respond to the new matters by way of conference and/or further submissions, the determination will be made without the respondent having had any opportunity at all to rebut the new matters. In this case, the adjudicator declined to allow further submissions on the new matters, and accordingly his determination was found to be in breach of natural justice, and set aside on that basis. It was also set aside on another basis. The manager of the nominating authority, Mr Sain, was also the chief executive officer of Edward Sain Associates, which had been advising the claimant as to its claim. Justice Blue found that the test of reasonable apprehension of bias applies not only to the adjudicator, but also to the ANA: For the reasons given above, a fair minded lay observer would regard the identity of the person selecting the decision maker to be as important as the identity of the decision maker himself or herself. The determination was also thus nullified on that basis. The judge thus found it unnecessary to decide on the judicial review challenges based on error of law alleged by the respondent, and preferred not to do so since they ‘may arise in the determination by arbitration or litigation of the ultimate rights of the parties’. This last consideration arose again in Kennett v Janssen (Supreme Court of South Australia 30 July 2013). The adjudicator, Adrian Ashman (D4), had been appointed by Adjudicate Today (D3), and made a determination in favour of J & S Janssen Bricklayers Pty Ltd (D2). The respondent asserted that its contract was not with D2, but with Mr Janssen personally (D1), and challenged the determination on multiple grounds, including the absence of any construction contract with D2. D3 and D4 put in limited appearances, agreeing to be bound by the outcome, and D1 and D2 indicated that they did not wish to be heard on the respondent’s claims that the determination be declared void or quashed. Since the issue of the identity of the contracting party (D1 or D2) was a live issue in the underlying dispute, the respondent, as plaintiff in the Supreme Court proceedings, elected to pursue its challenge to the determination by way of summary judgment application on just one of its other grounds, namely that D4 was not an eligible person within the meaning of regulation 6 of the Building and Construction Industry Security of Payment Regulations 2011 (SA). Since D4 did not hold either a relevant degree or a supervisor’s license, his only possible eligibility arose under regulation 6(b)(ii): a subjective test; that is, that it is a matter for the Council to determine what is sufficient to qualify a person for admission as an associate and it is not possible for the Court to identify objectively what those requirements are. There is also a requirement that the candidate be elected. For these reasons, the court found D4 to be ineligible, and declared the purported determination invalid and void. These early cases suggest that the courts in South Australia are not taking an uncritical approach to the legislation. The state’s courts have a history of taking a relatively jealous view of their jurisdiction, and there is no sign that they will be minded to turn a blind eye to relevant shortcomings in adjudicators’ determinations. (ii) is, or is eligible to be, a member (other than a student member) of any 1 or more of the following professional bodies: … (D) The Institute of Arbitrators and Mediators Australia; … D4 was not a member of IAMA, but asserted that he was eligible to be at least an associate member of IAMA. Justice Blue found otherwise; article 8 of AIMA’s Constitution imposes a requirement for candidates for associateship that (as found by the court): … the Council has to deem that they have such knowledge of, and interest in, the subject of arbitration, mediation and/or adjudication as the Council deems sufficient to qualify him or her for admission as an associate. It seems to me that that imposes AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 29 CONTRACTS PROPORTIONATE LIABILITY IN THE BUILDING AND CONSTRUCTION INDUSTRY FOLLOWING HUNT & HUNT V MITCHELL MORGAN Jaclyn Smith, Lawyer Corrs Chambers Westgarth, Melbourne INTRODUCTION each party could be liable for in the event of a dispute. It also has the potential to cut ‘across carefully negotiated allocation of risk’.5 Unless it is contracted out of, proportionate liability replaces the contractual risk allocation as arrived at between the parties in their contract to the extent that the two are inconsistent. If the regime is contracted out of, there can be gaps exposed in the parties’ insurance cover, and while this is an area heavily commented upon it will not be discussed in this article.6 This article will examine the development of the proportionate liability regime focussing on how it applies to the building and construction industry, particularly in light of the recent High Court of Australia decision in Hunt & Hunt v Mitchell Morgan Nominees Pty Ltd (Hunt & Hunt v Mitchell Morgan).3 It is highly relevant to discuss the regime as it applies specifically to this industry given that it was within that context that the regime was first introduced in Australia.4 While these industry–specific regimes have been abrogated following the introduction of the general proportionality liability regime, their initial existence symbolises the significant impact that issues surrounding apportionment and concurrent wrongdoers have on the Australian building and construction industry. Aside from the direct impact that the regime has on the contractual risk allocation, the policy behind the regime makes a legitimate attempt to make dispute resolution a more fair and equitable process. The effect of the regime, however, is not intended to ‘do more by way of apportionment than in theory could previously be achieved by contribution’ under joint and several liability.7 Proportionate liability, as it is utilised across Australian jurisdictions, remains an inconsistent,1 thus ineffective, means of allocating risk despite the ambitious policy attempt to make damages awarded against multiple defendants more equitable. Despite the practical issues with the application of the regime, the focus on apportionment of loss between concurrent wrongdoers is ‘sound and now entrenched in the Australian legal framework’.2 Within the building and construction industry there is a high degree of emphasis on the pre–allocation of risk either contractually, through tort law or through insurance. Proportionate liability is a relatively unknown variable entirely dependent upon an act or omission, that causes a party loss, occurring. It is a risk that is unable to be allocated under a contract beyond the general allocations already in place, particularly in regard to the quantum of damage that 30 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 The recent High Court decision in Hunt & Hunt v Mitchell Morgan has confirmed the role that the statutory proportionate liability regime has in disputes with multiple parties causing the loss claimed.8 It is the first judgment handed down by the High Court that involves a detailed analysis of the proportionate liability regime, the New South Wales legislation in particular.9 The decision clarifies the meaning of ‘damage or loss that is the subject of the claim’ in the legislation and further use of ‘damage’ in the legislative provisions. The uncertainty surrounding the expression of ‘damage or loss’ has been a source of considerable speculation since the introduction of the regime across the Australian jurisdictions, and while the Hunt & Hunt v Mitchell Morgan decision adds to the definition there is still room for further clarification.10 This article will work through the case history of this particular dispute as a means of demonstrating the development that the law has taken on this point in particular. It will also look at the impact of the decision on the building and construction industry and attempt to anticipate its impact on contractual risk allocation. The discussion will focus on the application of the regime in the court hierarchy, and will not touch on its role in arbitral proceedings as it is now relatively settled that the regime will not apply in such instances.11 This article will also examine the current status of the proportionate liability regime in Australia by conducting a comparative analysis of its application across several jurisdictions with a particular emphasis on the utility, or otherwise, of the contracting out provisions. It will look at the second draft model provisions drafted by the Standing Committee of Attorney’s–General (SCAG)12 and comment on the effectiveness of the proposed reforms, particularly in regard to contracting out. Following the discussion on Australia’s own law reform surrounding proportionate liability, this article will look at the current reforms under consideration in New Zealand. While New Zealand still uses joint and several liability, their Law Commission is proposing to move to a proportionate liability regime, specifically mentioning the Australian model as an example of how it can be applied in practice. This comparison is still a live topic because Australia too is still in the process of reforming, and hopefully nationally unifying, its proportionate liability regime. PROPORTIONATE LIABILITY IN AUSTRALIA BRIEF BACKGROUND TO THE REGIME Each State and Territory enacted proportionate liability legislation, which is similar but not uniform,13 between 2004 and 2005 in response to a crisis in the insurance industry in the early 2000s.14 The crisis was typified by a growing number of actions against professionals, particularly auditors, who were being singled out as targets for negligence actions not because of their culpability (which might be small) but because they were insured and had the capacity to pay large damages awards. One consequence was a sharp risk in insurance premiums payable by professionals.15 The legislation was enacted upon the recommendation of the Davis Report16 and in the draft form prepared by the SCAG in July 1996,17 which principally sought the abolition of joint and several liability in Australia for all economic loss.18 Since that time, a second draft of model provisions has been released for consultation and these are currently under consideration by SCAG.19 The legislation applies to claims for property damage or economic loss from a failure to take reasonable care, and also in relation to misleading and deceptive conduct.20 The regime seeks to limit a Court’s award of damages in such claims to amounts that solely reflect the tortfeasor’s responsibility. Under joint and several liability, a defendant could be liable for an entire judgment made against all defendants that contributed to a loss, despite personally only having a nominal percentage of the responsibility.21 ELEMENTS OF PROPORTIONATE LIABILITY At a legislative level, there are two essential elements to the regime that are shared across all Australian jurisdictions. To enliven the regime there first needs to be an apportionable claim. This is a claim for either economic loss or property damage under tort, contract or statute, arising from a failure to take reasonable care.22 Secondly, there needs to be concurrent wrongdoers, namely two or more parties whose acts or omissions have contributed to the loss in dispute.23 It is this second element that has caused the most confusion since the introduction of the proportionate liability regime, and is the area that this article will focus on. Various cases across the jurisdictions have grappled with multiple tortfeasors and what ‘damage or loss’ they are required to have contributed to in order to become concurrent wrongdoers, most notably for discussion in this article is that in Hunt & Hunt v Mitchell Morgan. One of the initial hurdles that must be established by a plaintiff is that the tortfeasor is legally liable to them for the relevant damage or loss.24 The legal uncertainty created by the wording of the legislative provisions was clarified by Besanko J of the Federal Court in Shrimp v Landmark Operations Ltd.25 His Honour held that ‘caused’ in the definition of concurrent wrongdoer ‘should be read as meaning such as to give rise to a liability in the concurrent wrongdoer to the plaintiff’.26 The effect of this jurisprudence is that to be a concurrent wrongdoer the tortfeasor must have caused the loss or damage that is the subject of the plaintiff’s claim and be liable to the plaintiff for that loss or damage.27 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 31 In the context of the building and construction industry this becomes most relevant when parties look to use deeds of warranty or tripartite agreements, or on a more immediate level, when parties are considering which contract model to use for their project. While such warranties and agreements would provide the contractual nexus for subcontractors to be liable to a principal,28 they have also been noted to ‘erode the single point responsibility the principal intended to create by entering into the head contract.29 This is demonstrated in the example of a consultant designing a building for a contractor who has a design and construct arrangement with the principal, and the consultant having to sign a warranty as to the design of a building in favour of the principal.30 Years after completion, the building collapses and the principal sues the contractor, who in turn joins the consultant as a co–defendant.31 By virtue of the warranty agreement the consultant is 100 per cent liable for the principal’s loss, without such an agreement the proportionate liability regime would be likely to apportion the loss caused between the contractor and the consultant.32 The warranty bypasses the responsibility of the contractor under the head contract and provides a mechanism for the principal to directly bring action against the consultant without needing to utilise the head contract.33 The situation could be further complicated if the consultant is insolvent by the time the building collapses, transferring the risk of being able to recover from the consultant to the principal and allowing the contractor to avoid any contribution obligations.34 Instead of utilising a design and construct model to ensure the principal has ‘single line accountability,’ it places it in a similar risk category as a construction management model.35 The advantage of a design and construct model, from a defendants perspective, is the potential for loss to be apportioned between subcontractors and head contractors, despite this not being the intention of the model.36 As the example above demonstrates, proportionate liability may attempt to be more equitable in how it apportions liability, but its application introduces new complexities into the already complex arrangement of a construction project. Given the ambiguity that this has caused, it is unsurprising that this has been identified as one of the key areas for reform.37 CONTRACTING OUT The lack of national uniformity means that proportionate liability is inconsistently38 used or commonly contracted out of in jurisdictions that expressly permit it, those being New South Wales, Tasmania and Western Australia. Contracting out essentially means that parties to a contract can expressly choose to opt–out of the proportionate liability regime and instead revert to the joint and several liability approach in the instance that that multiple tortfeasors cause the plaintiff’s loss. This encourages ‘forum shopping’ at the time of entering into a contract, which enables parties to choose a jurisdiction for their contract that allows for contracting out of the regime.39 For example, if a project is constructed in Victoria, the contractor is from Victoria also but the owner is from NSW, the parties could legitimately agree to choose NSW as the jurisdiction of their contract. On the other hand, if all parties and the project were based in Victoria, there would be no legitimate reason to choose NSW 32 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 as the jurisdiction of the contract. NSW is used in this example as it is one of the few jurisdictions that allow contracting out, and this is commonly done for construction projects that have a connection to that jurisdiction. Contracting out has also been noted as an attempt to ‘avoid a multiplicity of claims arising when something goes wrong’.40 In Tasmania, there is no need to make specific reference to the legislation in order to exclude the regime from applying to the contract.41 All that is necessary is a contractual allocation of liability that is worded in a manner inconsistent with the regime.42 Practical suggestions as to how to draft a contracting out clause have been articulated by Owen Hayford in his carefully considered analysis of the regime’s impact on contractual risk allocation.43 Hayford’s draft clause both articulates that the regime is excluded from applying to the contract as a whole, and also that it cannot be relied upon by the parties.44 Interestingly, Hayford’s clause also provides that the contractor indemnify the principal against any loss or damage that is not recoverable in the event that the contracting out is unsuccessful and the regime applies to the contract.45 While this is effectively ensuring that even if the contracting out is unsuccessful the effect of it still applies to the contract, it also removes the benefits of the regime from the contractors reach. One way to negate the contracting out provision in those jurisdictions that allow is to have it set aside on the grounds that it is contrary to public policy.46 An example of when this setting aside can occur is where a project and parties are all located in Queensland yet the law of another jurisdiction is chosen to govern the contract purely to avoid the application of the Queensland law.47 SUGGESTED REFORM ON CONTRACTING OUT Several suggestions have come forward, namely from the SCAG, to reform the proportionate liability regime in a way that ensures a more nationally consistent approach is applied. These reforms have focussed on contracting out, and either allowing48 or disallowing49 it universally, or coming to a compromise where it is only allowed to apply to certain types of contracts.50 Universally allowed v universally not allowed The first reform proposed by the SCAG is that the legislation be uniformly amended to expressly allow for contracting out across the jurisdictions.51 The second option is the polar opposite of this, to universally and expressly disallow contracting out of the regime.52 It seems contrary to the policy behind the regime to allow parties to contract out of it, and the SCAG have noted that contracting out subverts the purposes of the legislation.53 In an all or nothing reform, if it were simply disallowed in all jurisdictions, a vast portion of issues surrounding forum shopping could be eliminated. Similarities can be drawn within the building and construction industry to the way that the security of payment provisions work and their applicability, albeit in forms not yet uniform, across jurisdictions. The impetus behind the security of payment reforms was that they were essential to the commercial operation of the building construction industry, and so the various State and Territory Acts have been enacted without allowing for the statutory regime to be contracted out of.54 The suggested reforms to the disallowance of contracting out of proportionate liability reflect a similar sense that, unless uniformly applied, their purpose will be ineffective for contracting parties. Within the context of the building and construction industry, contractors in particular would welcome the prohibition of contracting out as a way to ensure that they are not liable for downstream risk associated with subcontractors and are able to benefit under the regime. Contracting out only allowed for contracts in excess of $5–10 million The third option for reform proposed by the SCAG would see contracting out prohibited except for agreements in excess of an applicable threshold value, such as $5–10 million.55 The quantum suggested reflects the value that large infrastructure contracts typically exceed, those beyond that value being the type of projects necessitating contractual risk allocation.56 The danger with attaching a monetary qualifier on the ability to enliven contracting out in any given contract is that the value of the contract might not always be clear, thus creating uncertainty as to whether contracting out can be applied.57 On a more positive note, for projects under this threshold value parties will not feel the ‘commercial pressures to relinquish the protection offered by the proportionate liability provisions’.58 Contracting out only for non– professionals or the provision of non–professional services An option proffered by Tony Horan, in his report reviewing the proportionate liability regime, is that contracting out be allowed in all jurisdictions and only not permitted for contracts dealing with professionals or the provision of professional services.59 While this does not go as far as the first two all–or–nothing options put forward by the SCAG in terms of eliminating any chance of inconsistencies in contracts, it would mean that contracts formed within the building and construction context, as they deal predominantly with professionals or the provision of professional services, would not be able to be contracted out of. This suggested reform is in line with the policy behind proportionate liability, and supports the concept that professionals are intended beneficiaries of the regime via reduced insurance premiums.60 While this reform is likely to be welcomed by parties operating in the building and construction industry, in so far as contracts for professionals and professional services are concerned, it would not resolve issues beyond the industry with the inconsistent application of contracting out. There are no foreseeable problems with the application of this reform because the experience in the building and construction industry is fairly established when it comes to identifying when a person qualifies as a professional.61 There is also an express standard of care for professionals defined in the legislation itself.62 The policy behind this reform option is much the same as the SCAG’s third option involving a value threshold, in that contracts involving professionals or for professional services are likely to require contractual risk allocation. This option also removes the pressure from a non–professional party to a contract, such as in a domestic building contract where a home owner directly contracts with a contractor, to contract out when they may not understand the implications of doing so. IMPLICATIONS OF THE REGIME IN PRACTICE The proportionate liability regime, despite commencing over a decade ago, is still observed to be wreaking havoc in the allocation and management of AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 33 risk, particularly on construction projects.63 While the concept of the regime commenced from a ‘sensible starting proposition’ it is the poor execution of the legislation that has been most critiqued.64 There have been several cases brought before courts, across the jurisdictions that have challenged the practical application of the regime. Case law dealing with the intricacies of the regime has provided ‘much–needed guidance’ over the years since its inception.65 The reliance on clarification by the common law illustrates the complex legal framework that the statutory regime creates. While there are some general observations that can be made about the application of the regime and its particular impact on the building and construction industry, there are also specific issues including quantum of damages and the ability to recover an award of damages that warrant due consideration. REQUIREMENT FOR JUDICIAL DETERMINATION One of the practical implications of the regime is that the parties in dispute will require a judicial determination to allocate the proportion of loss they are liable for, unless they have either contracted out of the regime or have allocated for apportionment in their contract. Where there is only one wrongdoer, the contract is likely to have expressly accounted for where a particular area of risk will fall. For example, under a design and construct contract it is the contractor who bears design risk.66 In a situation where there are concurrent wrongdoers, such as the contractor and a subcontractor, because the owner is not in a direct contractual relationship with a subcontractor the proportionate liability regime provides a mechanism for the owner to be able to recover from the subcontractor in the event that loss is caused where that subcontractor owed the principal a legal liability. CONCURRENT WRONGDOERS MUST BE LIABLE TO THE PLAINTIFF This discussion highlights a category that was in desperate need of clarification, that being whether or not a plaintiff could bring action under the regime against a tortfeasor who owed them no legal liability. The judgment of Besanko J in Shrimp v Landmark Operations Ltd67 clarifies this position and subsequent decisions have cemented this jurisprudence.68 Under the Commonwealth, Queensland, New South Wales and Victoria statutory regimes, to be a concurrent wrongdoer defendants are required ‘to have a independent legal liability to the plaintiff’.69 This means that unless a particular duty is owed by a party in contract, tort or under the misleading and deceptive conduct provisions, they cannot be held to be a concurrent wrongdoer. In the construction context, this means that principals cannot join a subcontractor as a concurrent wrongdoer in an action unless the subcontractor has provided an additional warranty, is contractually bound, has a duty to prevent pure economic loss, or has a duty under misleading and deceptive conduct law. Proportionate liability does not circumvent the existing requirements surrounding privity of contract and does not interfere with the existing law to provide additional avenues of recovery where they did not exist under joint and several liability. A practical example of this, and one where it is the contractor who is the plaintiff, is where a contactor brings action against a principal for the provision of 34 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 inaccurate tender information prepared by an architect or engineer.70 The principal will only be able to apportion its loss to that architect or engineer where it can demonstrate that the architect or engineer had an independent and direct liability to the contractor.71 In the absence of a contract or direct warranty between the contractor and the architect or engineer, the only duty that the architect or engineer can owe to the contractor would lie in a duty to prevent pure economic loss or under the misleading and deceptive conduct provisions.72 RISKS OF RECOVERY PASSED TO PLAINTIFF One of the key points of different between the use of joint and several liability and the proportionate liability regimes is the shifting of risk of a defendant being unable to pay because of insolvency, bankruptcy or untraceability is moved from the co–defendants to the plaintiff.73 The plaintiff and defendant role will not always be allocated to principal and contractor respectively, but there is opinion in the industry that principals are more likely to be plaintiffs in claims between it and a contractor arising out of the contractor’s failure to take reasonable care when under a duty to do so.74 It is this assumption that supports the view that principals are largely going to be in favour of contracting out, and for contactors to welcome the application of the regime.75 In situations where one co– defendant fits into one of those categories, it is no more fair or reasonable to place that risk on the plaintiff than it is to place it on the other co–defendants. Industry opinion has suggested ‘considerations of prejudice to plaintiffs weigh less strongly than the value of limiting the liability of defendants according to their share of responsibility’.76 The only advantage shifting this risk to the plaintiff is that recovery is at least attempted to be made from all defendants, not just those with the financial ability to pay if an award of damages is made against them. It also acts as an incentive for plaintiffs to bring their action against all potential defendants in the one proceeding. The ability of a plaintiff to recover an award of damages made in their favour may also be affected in the way that they bring their action initially. Depending on which jurisdiction they are in might impact who they do, and do not, bring their action against. This is a particularly important consideration because one of the key points of difference across the jurisdictions is the approach taken by the courts to wrongdoers that are not a party to the proceedings. While the Commonwealth, New South Wales, Queensland, Northern Territory and Australian Capital Territory all allow their courts discretion in whether to have regard to the liability of non–party wrongdoers, Victorian courts are expressly prohibited from having regard to the liability of non–parties with the exception of parties that are dead or insolvent.77 Western Australia, South Australia and Tasmania are at the other end of the spectrum again and mandate that regard must be had to liability of non–party wrongdoers.78 These significant jurisdictional differences can have major repercussions, particularly for defendants who are seeking to apportion loss amongst other wrongdoers. It places an onus on them to join other wrongdoers to the action against them so that they can actually benefit from the proportionate liability regime and do not end up shouldering 100 per cent of an award of damages if one is made against them. ABILITY TO RECOVER AN AWARD One benefit of the proportionate liability regime for head contractors, insurers and other parties with deep pockets is that they no longer bear the entire liability for loss caused to a principal in instances where multiple parties have failed to exercise reasonable care. Subcontractors are now also exposed to liability where they have been a concurrent wrongdoer causing the loss suffered by the principal, though only in situations where they have owed a duty of care to the plaintiff.79 As such, the principal, not the head contractor, can now carry the risk that this subcontractor may be unable to pay its proportion of the principal’s loss.80 Proportionate liability is a relatively unknown variable entirely dependent upon an act or omission, that causes a party loss, occurring ... Unless it is contracted out of, proportionate liability replaces the contractual risk allocation as arrived at between the parties in their contract to the extent that the two are inconsistent. In theory, this is beneficial because it means that each party will only be responsible for the loss that it had a share in causing, and they will not be burdened with carrying risk that is in disproportion to their actual role in the act or omission causing the loss. From a commercial perspective this may encourage parties, both principals and contractors, to enter into projects and utilise guarantees and tripartite agreements to ensure that avenues for recovery are not limited to those available under the head contract. From a project finance perspective, the balance sheet of large contractors will no longer be exposed as the sole source of recovery when multiple parties on a project contribute to the same loss or damage, so such contractors may be more likely to demand such warranties and tripartite agreements described above. The practical implications of the regime tell a different story, particularly for principals who are now precluded from recovering the entirety of their loss from just one of the concurrent wrongdoers. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 35 Where one of the concurrent wrongdoers is insolvent, bankrupt or unable to be located, this means that a plaintiff is not able to recover their proportion of the loss and can only pursue the other concurrent wrongdoers for their respective proportion of the loss cause. While this is in line with the policy behind the regime81 it does not necessarily promote principals entering into project agreements with contractors that they have not had a commercial relationship with already, for fear of not being able to recover in the event of a dispute. It also reduces the appetite of project financiers from lending to projects and reduces activity as a result of this. Commercial relationships draw on more than just the balance sheets of the contracting parties, and the risk of non–performance or non–payment on a project is already high enough without considering the risks associated with contracting with an unknown entity. UNKNOWN QUANTUM OF DAMAGES One of the major highlights of the regime from a defendant’s perspective is that it can reasonably anticipate that the quantum of damages, if such an award is made against it, will be limited to its contribution to the loss or damage suffered by the plaintiff. By the same token, one major downside of the regime is that the risk allocation between the parties is not known until the actual act or omission in question causes a plaintiff’s loss. Unless the parties have dealt with apportionment in their contract, the actual quantum of a party’s liability is not realised until a court judgment is made. As there are infinite combinations of causality and degrees of risk that could take place on any given construction project, the proportion that any given party to a project will be liable for cannot genuinely be allocated for at the time that a project commences. In the same sense, the doctrine of privity of contract limits the scope of who can be accounted for in the initial contractual risk allocation. For example, a head contract would be unable to allocate the risk that would be associated with specific contractors used in a subcontractual relationship, aside from allocating the entire risk to the contractor under a design and construct arrangement. Unlike other categories of risk in construction projects that can be traditionally allocated to the party best able to manage it, proportionate liability represents an unknown quantum and contractually unallocatable category for parties to a project and has been described as the ‘death of certainty’ for contractual risk allocation.82 MEASURING UP TO EXPECTATIONS? While the proportionate liability regime was intended to rectify serious issues concerning insurance, particularly professional indemnity insurance, it is questionable whether the practical effect of the legislation achieves this lofty ambition. As has been identified throughout this article in the discussions surrounding contracting out, the biggest hurdle to the regime achieving its intended purpose is the lack of uniformity across jurisdictions. The inconsistencies as to contracting out cause particular problems, namely in the exposure to risk that it can create. In the building and construction industry this is best demonstrated on projects across different jurisdictions and with parties from different jurisdictions. Where contracting out is allowed, parties may be exposed to a gap in what their policy covers and what they agree to pay out in the event of an apportionment claim. This is because ‘insurance policies typically do not provide cover for any liability accepted over and 36 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 above that which is provided for by the proportionate liability legislation’.83 Insurance policies typically state that liability is limited to that which would be available absent a contract. In the context of negligence a contract which limits the operation of the regime, through contracting out, changes the liability profile which would have been available absent a contract. JUDICIAL CLARIFICATION OF ‘DAMAGE OR LOSS’ While there are several aspects of the legislative provisions that have caused disputes across the jurisdictions, the recurring one of most significance recently is the phrasing of ‘the damage or loss that is the subject of the claim’.84 Recent Court of Appeal decisions in Victoria and NSW have adopted a narrow interpretation of the expression, equating it with ‘the same damage’ provision enabling parties to seek contribution from other parties.85 While the Hunt & Hunt v Mitchell Morgan decision of the High Court dealt expressly with the New South Wales jurisprudence, the decision in St George Bank v Quinerts Pty Ltd (Quinerts)86 was the last word on proportionate liability in Victoria prior to the recent High Court ruling. ST GEORGE BANK V QUINERTS PTY LTD87 The case concerned a unit that had been overvalued by the valuer (Quinerts), and on the basis of that valuation the bank (St George) had loaned a sum of money to the buyer of the unit (the borrower) in excess of what the unit was actually valued at.88 The bank sued the valuer alleging that it would never have loaned the money to the buyer if the unit had been correctly valued.89 While the valuer’s negligence was accepted, the focus of the dispute centred on the definition of the loss or damage that the bank had suffered. The bank argued it was the entire amount that it loaned the buyer, and the valuer argued that it was the amount actually loaned minus the amount that the bank would have been prepared to loan the buyer if the valuation had been accurate.90 The trial judge found in favour of the valuer’s argument, but refused to apportion loss between the valuer and the borrower on the grounds that they caused different losses to the bank.91 The relevant aspect of the judgment in this case, for the purposes of proportionate liability, pertained to the valuer’s unsuccessful cross appeal for liability to be apportioned.92 As has been mentioned earlier in this article, Nettle JA held that the regime was not ‘intended to do more by way of apportionment than in theory could previously be achieved by contribution’.93 To be successful under contribution the loss or damage caused by both tortfeasors must have been the ‘same damage’ as the ‘loss or damage that is the subject of the [plaintiff’s] claim’.94 His Honour arrived at this decision following an interpretation of the terms based on their plain and ordinary meaning,95 based on judicial opinion in previous cases,96 and agreed that the ‘legislative context did not justify an expansive interpretation of ‘the same damage’’.97 The loss the borrower caused was their failure to repay the money under the loan, and the valuer’s damage was causing the bank to ‘accept inadequate security from which to recover the amount of the loan,’ so were clearly not the same damage as required under his Honour’s interpretation of the legislation.98 The requirement that the loss or damage the subject of the claim be the same damage as required under contribution is what limits the scope of this judgment to be of assistance to subsequent defendants. WOODS V DE GABRIELE99 While this case pre–dated the appeal decision in Quinerts, it is useful to note the outcome of the dispute as it is one of the few decisions from the State jurisdiction to actually expand upon the interpretation of proportionate liability. Quinerts may have restrained the scope available to defendants to benefit from the statutory regime,100 but this decision raised the possibility of proportionate liability applying to all claims under services contracts due to the implied term in those contracts that services will be performed with reasonable care and skill.101 This clarified some of the ‘considerable uncertainty’ that surrounded the impact proportionate liability would have on risk allocation under professional services contracts.102 It also supports the substance of a claim being more powerful than its form, and the notion that the type of claim or the manner in which it is pleaded will not prevent the Victorian proportionate liability applying to a particular situation.103 HUNT & HUNT V MITCHELL MORGAN Counsel for Hunt & Hunt described the decision of the High Court as one that ‘breathes life back into laws that were severely constrained after the Courts of Appeal in Victoria and New South Wales had limited the practical operation of those laws’.104 Following the discussion above regarding the Quinerts decision, it is understandable why defendants across all jurisdictions would share this view. Despite these advances in interpretation of the legislation, Hunt & Hunt v Mitchell Morgan takes the clarification a much needed step further, allowing greater scope for defendants to benefit from the regime.105 This case, and others that expand on the practical application of proportionate liability, are necessary to clarify the ‘sufficiently unsettled’ questions of law that are raised by the statutory provisions across the Acts, such as those surrounding the onus of proof in proportionate liability claims.106 The majority decision is so important because the Court of Appeal decision was effectively undermining the policy behind the proportionate liability reforms. It was placing professional service providers ‘solely in the firing line again in circumstances where other wrongdoers lacked financial resources’.107 In some respects it was a decision that the regime needed in order to move forward in its jurisprudential development. THE FACTUAL AND CASE HISTORY The dispute concerned funds that had been transferred to Mr Caradonna, with the assistance of his solicitor Mr Flammia (collectively, ‘the fraudsters’), on the security of a mortgage provided to him and his business associate, Mr Vella, by Mitchell Morgan.108 Caradonna had forged Vella’s signature on the mortgage documents, and Flammia had dishonestly certified them, to acquire the mortgage.109 The debt owed to Mitchell Morgan was secured by these mortgage documents and a loan agreement that had been drawn up by Mitchell Morgan’s solicitors, Hunt & Hunt.110 By the time proceedings were initiated, both fraudsters were bankrupt so action was brought against Mr Vella by Mitchell Morgan in the New South Wales Supreme Court. Due to the forged nature of the documents, Mr Vella was not liable for Mitchell Morgan’s loss. Hunt & Hunt were also joined in that proceeding for their breach of their duty of care to Mitchell Morgan. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 37 They were found to be negligent for not drafting a mortgage that could ‘obtain the benefit of indefeasibility despite being procured by fraud’.111 as making enquiries about the authenticity of the mortgage documents or using a particular form, and concluded that this burden was ‘not very great’.117 The crux of the appeal process was debating the quantum of the loss or damage that Mitchell Morgan suffered that could be apportioned, if at all, to Hunt & Hunt. His Honour found that Mitchell Morgan’s claim against Hunt & Hunt was an apportionable one,118 and Hunt & Hunt’s liability was limited to 12.5 per cent of Mitchell Morgan’s loss.119 Interestingly, Young CJ did not articulate what exactly the loss was that Hunt & Hunt and the fraudsters caused. His Honour continues his analysis of apportionment by looking at how the fraudster, Flammia, caused Hunt & Hunt’s loss, that loss being defined as the 12.5 per cent that they have to contribute to Mitchell Morgan’s loss.120 It is worth examining the case history to gain insight into the full– circle that the decisions travelled in, and the potentially drastic outcomes for the regime more broadly if the Court of Appeal decision had been the final word in the dispute. The judgments at all three stages of the process display a tendency to deliberate the true meaning of ‘damage or loss’ in its legislative context, the majority judgment in the High Court drawing much of its logic from the trial judgment of Young CJ. TRIAL JUDGMENT Hunt & Hunt argued that the fraudsters were concurrent wrongdoers within the meaning of the proportionate liability regime, and that their own liability should be limited to a proportion of the loss that reflects their responsibility for Mitchell Morgan’s damage.112 In assessing Hunt & Hunt’s claim for apportionment, his Honour highlighted that professional advisers such as solicitors are neither insurers113 nor ‘superhuman’ in their abilities114 and are not obliged to warn commercially sophisticated clients of risks which a reasonable person would assume that client was aware of, such as the risk of fraud in these circumstances.115 Failing to draft a mortgage that adequately dealt with the risk of fraud was quite another matter.116 Young CJ also undertook an analysis of the steps that Hunt & Hunt and Flammia would have needed to have undertaken to avoid the risk of harm, such This application of the regime tends towards an approach for contribution that would have existed under joint and several liability, less an apportionment of the same loss or damage that Mitchell Morgan were claiming. Aside from such discussions the actual explanation that his Honour provided was criticised in the Court of Appeal as being ‘not very revealing’.121 The mentions made by his Honour of the damages claimed by Mitchell Morgan against Hunt & Hunt are for the financial value of the forged mortgage plus interest.122 This is picked up in the majority judgment of the High Court and could partly explain their emphasis on the difference between loss or damage and damages made by way of an award, though this will be discussed later in this article. This judgment is particularly critical to an analysis of the High Court’s decision as it was cited by the majority judgment as finding, without a doubt, that ‘Hunt & Hunt was a wrongdoer whose actions were a cause of Mitchell Morgan’s inability to recover the monies it advanced’.123 38 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 NEW SOUTH WALES COURT OF APPEAL The basis for Mitchell Morgan’s appeal to the New South Wales Court of Appeal was that Hunt & Hunt were not concurrent wrongdoers with the fraudsters and therefore they should not have had their liability limited.124 Their successful appeal turned on the judicial interpretation of the wording in the legislation of the same loss or damage, and the loss caused by Hunt & Hunt was held to have been caused without any part played by the fraudsters.125 Giles JA based his analysis on the fact that Mitchell Morgan’s relevant loss for the purpose of the legislative provision ‘the damage or loss that is the subject of the claim,’ was economic loss.126 Although, as the majority judgment in the High Court points out, this merely draws points to the ‘immediate effects of the fraudsters’ conduct and of the negligence of Hunt & Hunt’,127 not the actual loss that Mitchell Morgan suffered. This identification of the loss or damage as Mitchell Morgan’s paying out of money that they would not otherwise have had to128 should not have been equated with the actual loss or damage itself.129 That this definition is not clarified until much later in the judgment, when Giles JA raises the distinction, is surprising.130 His Honour does conclude by stating the relevant economic loss suffered by Mitchell Morgan to be ‘not having the benefit of security’ over the property that was the subject of their mortgage.131 Due to the acts or omissions of the fraudsters not being a cause of this loss, his Honour held that they were not concurrent wrongdoers and thus Hunt & Hunt were liable for the entirety of that loss.132 Following the discussion in Quinerts it is evident that this case was determined under the same interpretation of the authorities. Their Honours of the High Court majority judgment looked at the practical implications of Giles JA finding Mitchell Morgan to have incurred a loss simply by virtue of entering into their negligently drawn mortgage, and found that at that point no loss had actually occurred.133 Their Honours held that the more correct interpretation of the legislation, and the one that correctly measures when Mitchell Morgan’s damage began to accrue, was to consider Mitchell Morgan’s economic loss and damage as commencing when the money became unrecoverable.134 The policy rationale behind this is that it would be ‘unjust to compel a plaintiff to commence proceedings before the existence of his or her loss is ascertainable’.135 HIGH COURT OF AUSTRALIA MAJORITY JUDGMENT The key issue in Hunt & Hunt’s appeal to the High Court, as identified in the joint majority judgment, was the ‘proper identification’ of the loss or damage that Mitchell Morgan claimed against Hunt & Hunt136 and whether there was another party whose acts or omissions caused that loss or damage.137 After being found to be liable for 100 per cent of the damage or loss by the Court of Appeal, Hunt & Hunt sought relief from the High Court in terms of an apportionment of this loss or damage. It was already established, and not disputed, that Mitchell Morgan’s claim against Hunt & Hunt was an apportionable one for the purposes of the statutory regime.138 As previously mentioned, their Honours placed particular emphasis on the importance of correctly identifying loss or damage, ‘damage’ being the ‘injury and other foreseeable consequences suffered by a plaintiff’ that are fundamentally different to ‘damages’ which are claimed by way of compensation.139 This emphasis was particularly necessary given that Mitchell Morgan did not expressly state what loss or damage it was that they were claiming, and also because Hunt & Hunt alleged that it had been incorrectly classified by the Court of Appeal.140 Mitchell Morgan only stated that their loss and damage was continuing and included the sum they advanced and other expenses.141 It is from this that their Honours inferred Mitchell Morgan’s claim to be for the inability to recover the monies it had advanced.142 On this basis, while the claims against the three named concurrent wrongdoers were based on different causes of action, they each were ‘founded on Mitchell Morgan’s inability to recover the monies it advanced and the acts or omissions of all of them materially contributed to Mitchell Morgan’s inability to recover that amount’.143 This is a much broader interpretation of the legislation, and applies a causative approach rather than limiting a defendant’s recovery to that which would have been available under contribution. The line of authorities cited by their Honours reflected that under causation it was enough that a defendants conduct be one of the causes that caused the loss or damage suffered by the plaintiff.144 With this loss defined as Mitchell Morgan’s inability to recover monies, the relevant test to be applied to both Hunt & Hunt and the fraudsters was whether their conduct or omissions materially contributed to that loss.145 Even if the loss or damage had been defined in the same way in the Court of Appeal, the approach taken there was so narrow that both parties would have only been found to be concurrent wrongdoers if their acts or omissions were the same. Given the complexities of commercial arrangements, particularly in situations similar to those in this instance, it is highly unlikely that any two parties would be able to be concurrent wrongdoers under such a strict application of the law. DISSENTING MINORITY JUDGMENT Bell and Gageler JJ, in a joint dissenting judgment, upheld the approach to defining the phrase ‘damage or loss’ as used by the Court of Appeal. In their view, the relevant loss or damage that Hunt & Hunt caused was the lack of a security for the loan.146 While their Honours drew the same distinction between damage or loss that is the subject of the claim, and damages that form an award of compensation,147 the judgment differs in regard to the definition of the act or omission that caused the respective loss or damage that is the subject of the claim.148 While the majority judgment favoured a broad causation based approach, the minority focussed on the causation which results in legal liability and whether each wrongdoer was a contributor to that same loss or damage.149 As the fraudsters had no role in causing the lack of security suffered by Mitchell Morgan, their Honours held that they were not concurrent wrongdoers with Hunt & Hunt.150 IMPLICATIONS OF THE DECISION FOR THE BUILDING AND CONSTRUCTION INDUSTRY The decision in Hunt & Hunt v Mitchell Morgan has a broad impact on the proportionate liability regime generally, but also has some specific implications for the Australian building and construction industry. Many aspects of the judgment and what it represents in practice are AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 39 implications of the proportionate liability regime itself. While the decision does not revolutionise the impact of the regime, it does provide confirmation of the interpretation of ‘same loss or damage’. It by no means settles the way that the phrase should be interpreted and applied in future cases, this issue being compounded by the Court’s 3:2 split. The split highlights the ‘complexities’ at play in determining whether tortfeasors are concurrent wrongdoers, and is a reminder to parties to ‘carefully analyse claims against wrongdoers’.151 However, it does give breadth to the direction the law is taking in regards to interpreting legislative provisions, and return the progression of the law to the position it was taking following the trial judgment in this same dispute.152 On a broad level this decision has been described as a ‘victory of substance over form’ that will be welcomed by professional indemnity insurers of parties but frowned upon by financiers and similar parties seeking to recover their losses.153 This is in line with the response to proportionate liability more generally, but its impact is heightened in the wake of this decision because of the re–broadening of the scope for joining concurrent wrongdoers to an action. For the industry specifically there is also an increased risk of parties, such as subcontractors, being found to be concurrent wrongdoers with a contractor where they have provided a direct warranty or guarantee to the principal or are in a direct contractual arrangement with the principal. This is because the entering into a direct warranty arrangement or a direct contract creates a duty of care obligation in a situation where such a duty would not have ordinarily have existed, as discussed above While this may be a quality that assists subcontractors and suppliers at the tender application level and may make their bids more attractive to both contractors and principals alike, it is adding a risk onto the subcontractor or supplier where non–compliance or breach of the duty of care arises. THE EXPERIENCE IN NEW ZEALAND While the proportionate liability regime has a broad reach within the Australian jurisdictions and is influencing the operation of similar regimes domestically,154 it is also being used as a comparative model in the current New Zealand proposal to reform their joint and several liability regime. Australia has developed the most extensive proportionate liability regime, while other international models in jurisdictions including Canada, the United States, South Africa and Ireland have limited their reform to the liability of professional advisors.155 The New Zealand Law Commission is currently investigating a proposed reform to alter their joint and several liability regime to a proportionate liability model, and are drawing on the Australian experience as part of this study.156 The particular impact of proportionate liability on Australia’s building and construction industry is of significance in the New Zealand context because of the complex litigation involving leaky building cases that they are experiencing.157 In the course of the study, it was observed that under joint and several liability and proportionate liability, the burden of risk is merely shifted between the parties without reducing the complexity of proceedings.158 This concern is mirrored in the Australian context,159 the most appropriate example demonstrated in Gunston v Lawley160 where Byrne J commented that the owners’ fairly straightforward 40 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 claims were transformed into a complex and doubtless expensive suite of proceedings, a phenomenon which is regrettably a not uncommon product of the proportionate liability regime now in force.161 While this observation suggests that the utility of the proportionate liability regime is constrained by the complexities it operates within, it does highlight an area of the Australian experience that is currently under consideration itself for reform. CONCLUSION While the Hunt & Hunt v Mitchell Morgan decision represents the first High Court judgment on proportionate liability, the 3:2 split indicates that the regime is still marred by uncertainty and a divergence in legal opinion. This is evident not just in the differences between the majority and minority judgments, but also the tests each applied to enliven when ‘damage or loss’ is caused by concurrent wrongdoers. The direction that the High Court is likely to take if another proportionate liability dispute came before it is certain to the extent that subsequent decisions are bound by the doctrine of precedent, but the narrow split in legal opinion does raise a glimmer of uncertainty. Hunt & Hunt v Mitchell Morgan solidifies the place that the regime has within Australian jurisdictions. The particular fact matrix of Hunt & Hunt v Mitchell Morgan typifies the type of disputes that benefit from the application of apportionment of damage and demonstrates how beneficial the regime is for defendants. Within the building and construction industry, for large scale projects with multiple contractual arrangements the decision shifts risk downstream and confirms that each party is only liable for their contribution to the loss or damage suffered. Reflecting on the decisions leading up to the final High Court judgment, it is interesting to see how varied the quantum of apportionment can be depending on how the phrase ‘loss or damage’ is interpreted. The New South Wales Court of Appeal judgment, if left as the final authority in this matter, set a very narrow precedent for interpreting the clause and one that would have severely hampered the ability of defendants to apportion loss to other wrongdoers. The Court found Hunt & Hunt liable for 100 per cent of the loss they caused Mitchell Morgan and denied their claim apportionment. For plaintiffs, that decision would have placed them in a relatively similar position to that which they held under the joint and several liability regime, perhaps even improved it given the intricate separation of the loss or damage suffered by Mitchell Morgan. In both the Supreme Court and High Court decisions the judicial interpretation of the legislative expression expanded the ability to apportion loss, which is why the decision is particularly welcomed from a defendant’s perspective. The fact that Hunt & Hunt’s liability changed from 100 per cent to 12.5 per cent shows the scope and capacity of the law in this area to vary immensely in its practical application depending on the judicial interpretation given. This dramatically different figure is enough to highlight the immediacy required for reform of the regime, in particular an express clarification in terms similar to that expressed by the majority judgment. It will be interesting to observe the further development of proportionate liability in the State and Territory jurisdictions following the High Court decision in Hunt & Hunt v Mitchell Morgan, and any further guidance the High Court provides on the application of the regime will be eagerly anticipated. Planning and Assessment Act 1979 (NSW) section 109ZJ For the building and construction industry, the most immediate impact of this decision will be that defendants, namely contractors, will once again look to the regime as a broad protection and a means of limiting their liability to that which they have personally caused. Until further legislative reform takes place though, it is highly unlikely that this decision will change the views of parties on either side of a construction project to alter their perspective on contracting out of the regime. 5. Patrick Mead, ‘Current trends in risk allocation in construction projects and their implications for industry stakeholders’ (2006) 22 Building and Construction Law 407, 424 The results of the SCAG consultation have the capacity to drastically shift the liability landscape in Australia, and with the focus on reforming contracting out provisions for contracts of a certain value and contracts involving professionals or professional services, there is great potential for the building and construction industry to benefit under such reforms. It is the legislative, not the jurisprudential development, that will be of most utility both generally and specifically within the building and construction industry. REFERENCES 1.See Tony Horan, Proportionate Liability: Toward National Consistency (Report for National Justice CEOs, 2007) 2. David Ulbrick and Edward Harrison, ‘Enforcement of upstream duties relating to OHS in Victoria: Lessons from proportionate liability?’ (2012) 28 Building and Construction Law 176, 186 3. Hunt & Hunt v Mitchell Morgan Nominees Pty Ltd [2013] HCA 10 4. See e.g. Building Act 1993 (Vic) section 131; Environmental 6. See e.g. Adeline Pang, ‘Building protection into professional risk: The operation of professional indemnity insurance in construction’ (2007) 18 Insurance Law Journal 68 7. St George Bank Ltd v Quinerts Pty Ltd [2009] VSCA 245, [58] (Nettle JA) 8. [2013] HCA 10, above n 3 at [10]–[15] (French CJ, Hayne and Kiefel JJ) 9. Ivan Griscti, ‘Developments in proportionate liability: The High Court rules on ‘same damage or loss,’ (2013) Australian Insurance Law Bulletin (April/May) 66, 66 10. See e.g. Nick Rudge and Anne–Marie Wholley ‘Proportionate liability legislation: Further judicial guidance on its application’ (2008) Australian Construction Law Bulletin 20(3) 28; David Rodighero, ‘Proportionate liability: An update on who is a ‘concurrent wrongdoer’’ (2008) Australian Construction Law Bulletin 20(3) 26 11. See e.g. Andrew Stephenson, Jey Nandacumaran and Sarah Southwell, ‘Commercial arbitration—A proportionate liability–free zone?’ (2013) Australian Construction Law Newsletter (149) 50; Ashley Jones, ‘All blown out of proportion? Contracting out and proportionate liability in Queensland.’ (2011) Australian Construction Law Newsletter (141) 6; David Levin, ‘Proportionate liability in arbitrations in Australia: Resolution of some uncertainties,’ (2013) 29 Building and Construction Law 230 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 41 12. The Standing Committee of Attorneys–General transitioned to the Standing Council on Law and Justice on 17 September 2011, but for consistency and the fact that all reports are still authored under the title SCAG, it is this title that will be utilised throughout this article. 13. Owen Hayford, ‘Proportionate liability—Its impact on contractual risk allocation’ (2010) 26 Building and Construction Law 11, 13 14. Standing Committee of Attorneys–General, Proportionate Liability Regulation Impact Statement (September 2011), 4 15. BHPB Freight Pty Ltd v Cosco Oceania Chartering Pty Ltd (No 2) [2008] FCA 1656, [4]–[5] (Finkelstein J) 16. JLR Davis Inquiry into the Law of Joint and Several Liability: Report of Stage Two (Commonwealth and New South Wales Attorney–Generals, 1995) 17. Standing Committee of Attorneys–General, Draft Model Provisions to Implement the Recommendations of the Inquiry into the Law of Joint and Several Liability, (1996). Negligence and Apportionment of Liability) Act 2001 (SA), Part 3; Civil Liability Act 2002 (Tas), Part 9A; Wrongs Act 1958 (Vic), Part IVAA; Civil Liability Act 2002 (WA), section 4A and Part 1F 35. Phillip Greenham, Kate Morrow and Shelley Naylor, ‘Single line accountability! Proportionate liability and joint and several liability’ (2011) 6 (1) Construction Law International 6, 10 21. Ian Bailey and Matthew Bell, Construction Law in Australia (Lawbook, 3rd ed, 2012), 153. 36. Ibid 22. Wrongs Act 1958 (Vic) section 24AF; Law Reform (Contributory Negligence and Apportionment of Liability’ Act 2001 (SA) section 3(2) (a); Civil Liability Act 2003 (Qld) section 28(1); Civil Liability Act 2002 (Tas) section 43A(1); Civil Liability Act 2002 (WA) section 5AI; Civil Liability Act 2002 (NSW) section 34(1) 23. Wrongs Act 1958 (Vic) section 24AH; Law Reform (Contributory Negligence and Apportionment of Liability’ Act 2001 (SA) section 3(2) (b); Civil Liability Act 2003 (Qld) section 30; Civil Liability Act 2002 (Tas) section 43A(2); Civil Liability Act 2002 (WA) section 5AI; Civil Liability Act 2002 (NSW) section 34(2) 24. Shrimp v Landmark Operations Ltd (2007) 163 FCR 510 37. Tony Horan, Proportionate Liability: Toward National Consistency (Report for National Justice CEOs, 2007), 112 38. Jennifer Galatas, ‘Top Ten Issues in Construction Law for 2012’ (2012) Australian Construction Law Newsletter (143) 21, 23 39. Hayford, above n 13, 28 40. Ray Giblett and Scott Laycock, ‘Proportionate Liability—Still causing insurance havoc’ 23 (6) Australian Construction Law Bulletin (September 2011) 83, 83 41. Aquagenics Pty Ltd v Break O’Day Council (2010) 26 BCL 263, [71] (Tennent J). 42. (2010) 26 BCL 263, above n 41 at [71] (Tennent J). See e.g. Peter Voss, Leigh Warnick and Camilla Wayland, ‘Proportionate liability and contractual risk’ (2011) Australian Construction Law Bulletin (Dec/Jan) 90, 91 18. Commonwealth of Australia, Inquiry into the Law of Joint and Several Liability: Report of Stage Two, (1995), 34 25. (2007) 163 FCR 510, above n 24 26. (2007) 163 FCR 510, above n 24 at [62] (Besanko J) 43. Hayford, above n 13, 29 19. Standing Committee of Attorneys–General, Consultation Draft: Proportionate Liability Model Provisions (15 September 2011). 27. (2007) 163 FCR 510, above n 24 at [59]–[62] (Besanko J) 45. Ibid 20. See Competition and Consumer Act 2010 (Cth) Part VIA, ss 87CB–87CI; Australian Securities and Investments Commission Act 2001 (Cth) Part 2, Division 2, Subdivision GA, ss 12GP–12GW; Corporations Act 2001 (Cth), Part 7.10, Division 2A, ss 1041L–1041S; Civil Liability Act 2002 (NSW) Part 4; Civil Law (Wrongs) Act 2002 (ACT), Chapter 7A; Proportionate Liability Act 2005 (NT); Civil Liability Act 2003 (Qld); Law Reform (Contributory 28. James Morgan–Payler, ‘Proportionate liability in building cases: Possible erosion of single point responsibility for principals’ (2006) 18 Australian Construction Law Bulletin (3) 49, 50 29. Ibid at 51 30. Ibid at 50 31. Ibid 32. Ibid 33. Ibid 34. Ibid 42 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 44. Ibid 46. Ashley Jones, ‘All blown out of proportion? Contracting out and proportionate liability in Queensland.’ (2011) Australian Construction Law Newsletter (141) 6, 9. 47. Ibid 48. SCAG, above n 14, 37 49. SCAG, above n 14, 38 50. SCAG, above n 14, 39–41 51. SCAG, above n 14, 37 52. SCAG, above n 14, 37 53. SCAG, above n 14, 37 54. See e.g. New South Wales, Parliamentary Debates, Legislative Assembly, 29 June 1999, ’Second Reading Speech for Building and Construction Industry Security of Payment Bill’ (Morris Iemma) 74. Ibid 24–25 55. SCAG, above n 14, 39 78. Ibid 56. SCAG, above n 14, 39 98. [2009] VSCA 245, at n 7 at [76] (Nettle JA) 79. (2010) 26 BCL 263, above n 41 57. SCAG, above n 14, 39 99. [2007] VSC 177 80. Hayford, above n 13, 15 58. SCAG, above n 14, 40 81. Commonwealth of Australia, Inquiry into the Law of Joint and Several Liability: Report of Stage Two, (1995), 33 100. Pearsall, Boomer and Ursino, above n 85, 134 59. Anthony Horan, Proportionate Liability: Toward National Consistency (Report for National Justice CEOs, 2007) 113 60. Bailey and Bell, above n 21, 281 61. See e.g. Gunston v Lawley (2008) VR 33, 37 (Byrne J) 62. See e.g. Civil Liability Act 2002 (NSW) section 5O 63. Giblett and Laycock, above n 40, 83 64. David Ulbrick, ‘Tradies and the Trade Practices Act‘ (2009) 25 Building and Construction Law 8, 25 65. David Rodighiero, ‘Proportionate liability: An update on who is a ‘concurrent wrongdoer’’ (2008) Australian Construction Law Bulletin 20(3) 26, 26 75. Ibid 25 76. Greenham, Morrow and Naylor, above n 35, 8 77. Ibid 82. Andrew Stephenson, ’Proportional liability in Australia— The death of certainty in risk allocation in contract’ (2005) International Construction Law Review 64 83. SCAG, above n 14, 37 84. See e.g. Civil Liability Act 2002 (NSW) section 34(2) 85. Angela Pearsall, Kate Boomer and Anthony Ursino, ‘Proportionate liability: High Court broadens scope of ‘same damage’ test: Hunt & Hunt Lawyers v Mitchell Morgan Nominees Pty Ltd,’ (2013) Australian Civil Liability (Newsletter) (May) 134, 134. 86. [2009] VSCA 245, at n 7 87. [2009] VSCA 245, at n 7 66. See e.g. Standards Australia, General conditions of contract for design and construct (AS 4902– 2000) cl 2.2 88. [2009] VSCA 245, at n 7 at [1] (Nettle JA) 67. [2007] FCA 1468 90. [2009] VSCA 245, at n 7 at [1]– [2] (Nettle JA) 68. See e.g. Gunston v Lawley [2008] VSC 97 89. [2009] VSCA 245, at n 7 at [1] (Nettle JA) 69. Rodighiero, above n 65, 27 91. [2009] VSCA 245, at n 7 at [3]– [4] (Nettle JA) 70. Richard Wilkinson, ‘Risky business: Compiling a tender package,’ (2008) 24 Building and Construction Law 377, 390 92. [2009] VSCA 245, at n 7 at [53]–[98] (Nettle JA) 93. [2009] VSCA 245, at n 7 at [59] (Nettle JA) 71. Ibid 94. [2009] VSCA 245, at n 7 at [63] (Nettle JA) 72. Ibid 73. Hayford, above n 13, 11 95. [2009] VSCA 245, at n 7 at [68] (Nettle JA) 96. Royal Brompton Hospital NHS Trust v Trustees WA Ltd [2002] 1 WLR 1397 97. [2009] VSCA 245, at n 7 at [72] (Nettle JA) 101. Woods v De Gabriele [2007] VSC 177, [58] (Hollingworth J) 102. James Ioannou, ‘Construction industry be warned’ (2012) 28 Building and Construction Law 394, 397–398 103. Woods v De Gabriele [2007] VSC 177, [58] (Hollingworth J); Richard Wilkinson, ‘Risky business: Compiling a tender package,’ (2008) 24 Building and Construction Law 377, 390 104. Peter Stockdale and Travis Toemoe ‘Proportionate liability– Restored to working order’ (4 April 2013) King & Wood Mallesons Alerts http://www.mallesons.com/ publications/marketAlerts/2013/ Pages/proportionate–liability– restored–to–working–order.aspx. 105. Pearsall, Boomer and Ursino, above n 85, 134 106. Barbara McDonald, ‘Proportionate liability in Australia: The devil in the detail,’ (2005) 26 Australian Bar Review 30, 50 107. Georgie Farrant and Elizabeth Huckerby, ‘First High Court decision in relation to proportionate liability provides comfort to professional services providers,’ (2012) Inhouse Counsel (May) 92, 92 108. [2013] HCA 10, above n 3 at [2] (French CJ, Hayne and Kiefel JJ) 109. [2013] HCA 10, above n 3 at [2] (French CJ, Hayne and Kiefel JJ) AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 43 110. [2013] HCA 10, above n 3 at [2] (French CJ, Hayne and Kiefel JJ) 111. Vella v Permanent Mortgagees Pty Ltd [2008] NSWSC 505, [466] (Young CJ) 112. [2008] NSWSC 505, above n 111 at [470] (Young CJ) 113. [2008] NSWSC 505, above n 111 at [492] (Young CJ) 114. [2008] NSWSC 505, above n 111 at [499] (Young CJ) 115. [2008] NSWSC 505, above n 111 at [504]–[505] (Young CJ) 116. [2008] NSWSC 505, above n 111 at [507] (Young CJ) 117. [2008] NSWSC 505, above n 111 at [534] (Young CJ) 118. [2008] NSWSC 505, above n 111 at [575] and [588] (Young CJ) 119. [2008] NSWSC 505, above n 111 at [598] (Young CJ) 131. [2011] NSWCA 390, above n 121 at [44] (Giles JA) 149. [2013] HCA 10, above n 3 at [97] (Bell and Gageler JJ) 132. [2011] NSWCA 390, above n 121 at [44] (Giles JA) 150. [2013] HCA 10, above n 3 at [100]–[101] (Bell and Gageler JJ) 133. [2013] HCA 10, above n 3 at [31]–[33] (French CJ, Hayne and Kiefel JJ) 151. Pearsall, Boomer and Ursino, above n 85, 136 134. [2013] HCA 10, above n 3 at [32] (French CJ, Hayne and Kiefel JJ) 135. [2013] HCA 10, above n 3 at [32] (French CJ, Hayne and Kiefel JJ) 136. [2013] HCA 10, above n 3 at [8] (French CJ, Hayne and Kiefel JJ) 137. [2013] HCA 10, above n 3 at [19] (French CJ, Hayne and Kiefel JJ) 138. [2013] HCA 10, above n 3 at [18] (French CJ, Hayne and Kiefel JJ) 120. [2008] NSWSC 505, above n 111 at [603]–[613] (Young CJ) 139. [2013] HCA 10, above n 3 at [2013] HCA 10, [24] (French CJ, Hayne and Kiefel JJ) 121. Mitchell Morgan Nominees Pty Ltd v Vella [2011] NSWCA 390, [29] (Giles JA) 140. [2013] HCA 10, above n 3 at [30] (French CJ, Hayne and Kiefel JJ) 122. [2008] NSWSC 505, above n 111 at [680] (Young CJ) 141. [2013] HCA 10, above n 3 at [24] (French CJ, Hayne and Kiefel JJ) 123. [2013] HCA 10, above n 3 at [46] (French CJ, Hayne and Kiefel JJ) 124. [2011] NSWCA 390, above n 121 at [31] (Giles JA) 125. [2011] NSWCA 390, above n 121 at [85] (Giles JA) 126. [2011] NSWCA 390, above n 121 at [34] (Giles JA) 127. [2013] HCA 10, above n 3 at [30] (French CJ, Hayne and Kiefel JJ) 128. [2011] NSWCA 390, above n 121 at [41] (Giles JA) 129. [2013] HCA 10, above n 3 at [30] (French CJ, Hayne and Kiefel JJ) 130. [2011] NSWCA 390, above n 121 at [38] and [41] (Giles JA) 142. [2013] HCA 10, above n 3 at [24] (French CJ, Hayne and Kiefel JJ) 143. [2013] HCA 10, above n 3 at [9] (French CJ, Hayne and Kiefel JJ) 144. [2013] HCA 10, above n 3 at [45] (French CJ, Hayne and Kiefel JJ) 145. [2013] HCA 10, above n 3 at [53] (French CJ, Hayne and Kiefel JJ) 146. [2013] HCA 10, above n 3 at [100] (Bell and Gageler JJ) 147. [2013] HCA 10, above n 3 at [90] (Bell and Gageler JJ) 148. [2013] HCA 10, above n 3 at [91] (Bell and Gageler JJ) 44 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 152. Vella v Permanent Mortgagees Pty Ltd [2008] NSWSC 505 153. Griscti, above n 9, 67 154. See e.g. David Ulbrick and Edward Harrison, ‘Enforcement of upstream duties relating to OHS in Victoria: Lessons from proportionate liability?’ (2012) 28 Building and Construction Law 176 155. Greenham, Morrow and Naylor, above n 35, 10 156. New Zealand Law Commission, Review of Joint and Several Liability: Issues Paper 32, <http://www.lawcom.govt.nz/ project/review–joint–and–several– liability> 157. Ibid at [6.12] 158. Ibid at [6.14] 159. Greenham, Morrow and Naylor, above n 35, 8 160. [2008] VSC 97 161. Gunston v Lawley [2008] VSC 97, at [5] (Byrne J) Jaclyn Smith’s article is based on an essay originally prepared for the Melbourne Law Masters subject Construction Dispute Resolution. The author thanks Andrew Stephenson for his helpful feedback on the essay as submitted for that subject. ARBITRATION ARBITRATION IN AUSTRALIA— SUPREME COURT SUPPORTS DOMESTIC ARBITRATION IRRESPECTIVE OF THE PROSPECT OF SPLIT PROCEEDINGS Geoff Hansen, Partner Jennifer Galatas, Senior Associate Herbert Smith Freehills, Melbourne INTRODUCTION In recent years, the landscape for domestic and international commercial arbitration in Australia has changed dramatically. At the domestic level, all Australian States and Territories except for the Australian Capital Territory (ACT) have now embraced substantially similar arbitration legislation commonly referred to as the uniform Commercial Arbitration Acts. At the Federal level, significant amendments have been made to the International Arbitration Act 1974 (Cth) governing international commercial arbitrations. These legislative changes were primarily aimed at increasing the efficiency of the arbitration process and making arbitration in Australia more attractive. Many of these changes have significant implications for parties considering which dispute resolution regime to include in their commercial contracts, as well as those parties who have already entered into commercial arrangements containing arbitration clauses. The Victorian Supreme Court has recently been provided with an opportunity to consider the operation of the domestic arbitration regime and in particular, the provisions designed to remove the discretion of the Courts in considering an application for a stay of Court proceedings where there is a valid arbitration agreement. A BRIEF RECAP ON THE AUSTRALIAN SYSTEM FOR INTERNATIONAL AND DOMESTIC COMMERCIAL ARBITRATIONS Australia has a ‘dual track’ system for international and domestic commercial arbitrations. International arbitrations are governed by the International Arbitration Act (IAA), whereas domestic arbitrations are governed by State or Territory–based arbitration legislation. The IAA adopts and applies the UNCITRAL Model Law on International Commercial Arbitration (Model Law), the Convention on the Recognition and Enforcement of Foreign Arbitral Awards 1958 (New York Convention), and the Convention on the Settlement of Investment Disputes Between States and Nationals of Other States (ICSID Convention). Recent amendments to the IAA in 2010 were aimed at further supporting and improving the conduct of international arbitration by, for example, clarifying that the Model Law is now the mandatory ‘supervisory procedural law’ for international arbitration (section 21 of IAA) and more closely aligning the position with respect to recognition and enforcement of arbitration agreements and awards with the Model Law and the New York Convention. At a domestic level, all States and Territories (except for the ACT) have now introduced uniform Commercial Arbitration Acts (uniform CAAs). The key objective of the changes introduced by this legislation was to modernise the domestic arbitration regimes and bring them in line with international best practice by basing the legislation on the Model Law. It was envisaged that this would create national consistency in the regulation and conduct of international and domestic commercial arbitration and ultimately increase confidence in the arbitration system both in Australia and overseas. The effect of the legislative changes introduced by the uniform CAAs is far–reaching. Some of the key changes introduced by this legislation concern: AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 45 Australia has a ‘dual track’ system for international and domestic commercial arbitrations. International arbitrations are governed by the International Arbitration Act ... whereas domestic arbitrations are governed by State or Territory–based arbitration legislation. (a) confidentiality of arbitration proceedings—in contrast with the position with respect to international arbitrations which provides an ‘opt–in’ regime, the uniform CAAs impose a statutory duty of confidence (subject to certain exceptions), unless otherwise agreed by the parties; (b) limited rights of recourse— appeals are limited to errors of law and require the agreement of the parties (either in their arbitration agreement or subsequently) and leave from the Court; and (c) enforceability of arbitration agreements—previously the Courts had a discretion whether to stay Court proceedings commenced in circumstances where an arbitration agreement existed. This has been replaced by a mandatory requirement that the Courts must grant a stay of any Court proceedings unless the relevant arbitration agreement is found to be ‘null and void, inoperative or incapable of being performed’ (this is similar to the provision that appears in the IAA and the Model Law). This provision was recently considered by the Victorian Supreme Court in Lysaght Building Solutions Pty Ltd v Blanalko Pty Ltd [No 3] [2013] VSC 435 (Lysaght v Blanalko). LYSAGHT V BLANALKO FACTS Blanalko Pty Ltd (Blanalko) engaged Lysaght Building Solutions Pty Ltd (Lysaght) to undertake various design and construction works in Penfield, South Australia pursuant to a contract based on Australian Standard Contract AS4300–1995. The contract was governed by Victorian law and contained a dispute resolution clause (clause 47) which: 46 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 (a) provided two alternative paths for dispute resolution following the issuing of a notice of dispute (one path requiring the parties to meet and the other path requiring the superintendent to make a decision prior to the parties meeting), both ultimately concluding with the dispute being referred to arbitration; and (b) expressly carved out claims for payment due under the contract. Lysaght sought payment of various progress payment claims in relation to works undertaken, which Blanalko failed to pay. Lysaght sought summary judgment with respect to its payment claims. In response, Blanalko filed a defence denying liability and issued a counterclaim alleging various breaches of contract and seeking payment of certain amounts said to be owing to it. Blanalko separately sought summary judgment with respect to its claims. Lysaght applied for a stay of the matters referred to in Blanalko’s counterclaim pursuant to section 8 of the Commercial Arbitration Act 2011 (Vic) (Act) which is the relevant provision in Victoria requiring that a Court: ... must ... refer the parties to arbitration unless it finds that the agreement is null and void, inoperative or incapable of being performed. In response, Blanalko argued that the dispute resolution clause constituted a ‘non–exclusive arbitration clause’ and therefore section 8 of the Act did not apply as it only operated where the parties had clearly contracted to an arbitration to the exclusion of the Courts. DECISION Justice Vickery of the Supreme Court of Victoria granted the application for a stay with respect to those disputes that did not fall within the carve out in the contract for payment claims. In reaching this decision, Justice Vickery observed that the word ‘must’ in section 8 of the Act: ... removes the court’s discretion to refuse to grant a stay, and renders the provision mandatory….This means that if the requirements of the section are met the Court has no choice but to grant a stay of the proceeding before it and refer the matter to arbitration (at [125[). The Court observed that in some cases, such as the current case where payment claims were expressly carved out: ... [t]his may result in some inefficiencies in case management…arising from the potential for litigation on the same project being conducted before different tribunals. Nevertheless the statutory meaning is clear (at [126]). Further, the Court rejected Blanalko’s contention that the dispute resolution clause constituted a non–exclusive arbitration clause, observing that irrespective of which alternative was invoked by the parties once a notice of dispute had been served, if the dispute remained unresolved within 28 days of service of the notice or the date on which the superintendent gave their decision, the dispute: ... shall be and is hereby referred to arbitration.’ The Court commented that: ... provided these pre–conditions have been met, the parties have expressed a clear intention in their written agreement that an outstanding dispute, in the circumstances described, is required to be referred to arbitration, and is not to be heard and determined by a Court (at [142]). IMPLICATIONS This is an important decision for a number of reasons. It is one of the first reported judgments on the construction of the legislative provisions requiring the Courts to grant a stay in the context of an arbitration clause based on clause 47 of the AS4300–1995 standard form contract (which is a reasonably popular standard form contract in Australia). arbitration for at least some of their disputes can no longer expect the Courts to intervene and refer all disputes to one forum (i.e. litigation) where there is a valid arbitration agreement. The Court’s decision to grant a stay on the facts of the case clearly accords with the legislature’s intention to limit the discretion of the Courts. In addition, the approach of the Court in seeking to construe the arbitration agreement as a whole and refusing to accept a narrow and pedantic interpretation of the arbitration clause is likely to provide additional comfort to commercial parties that the Courts will not readily seek to overturn agreements to arbitrate. The decision is, however, also an important reminder for commercial parties to carefully consider all provisions in their arbitration agreement (particularly provisions in standard form contracts) and in particular, whether they intend to resolve certain disputes (in this case, payment claim disputes) using other methods of dispute resolution. In some cases, there may be good reason why parties would prefer to resolve particular disputes using an alternative method. For example, valuation disputes may be well suited to expert appraisal or expert determination depending on the circumstances. However, in many cases, it may be undesirable to split the proceedings as there is a significant risk that this may result in inconsistencies and increased time and cost. Ultimately this is a matter that requires careful consideration as parties who have selected AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 47 SECURITY OF PAYMENT DO YOU HAVE A STANDING TRADE CREDIT AGREEMENT TO SUPPLY CONSTRUCTION SERVICES OR MATERIALS? Alisa Taylor, Senior Associate Kimberly Moore, Senior Lawyer Meyer Vandenberg Lawyers, Canberra INTRODUCTION A new New South Wales Supreme Court decision has confirmed that you cannot use the security of payment regime to enforce multiple invoices under a standing order contract in the same payment claim or same adjudication. The decision is also relevant to claims made under the ACT security of payment legislation. THE CASE On 11 April 2013, the NSW Supreme Court handed down its decision in Class Electrical Services v Go Electrical [2013] NSWSC 363. Go Electrical (Go) and Class Electrical (Class) had a standing contract under which Class would issue purchase orders to Go, and Go would then supply construction goods to Class. Go issued a single $1.8m payment claim to Class under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) seeking payment of several outstanding invoices for separate purchase orders. The claim went to adjudication and Go was awarded the full amount of its claim. Class appealed to the NSW Supreme Court. Class’ key argument was that because the payment claim referred to multiple separate contracts in the one claim it was invalid. Class argued that as a result the adjudicator’s determination was void and that Go was not entitled to recover payment. THE LAW Under the Act (and equivalent ACT legislation) an adjudicator cannot make a decision unless all of the technical requirements of the Act have been met. One such requirement is that the right to claim payment under the Act must come from a single construction contract. 48 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 ... an adjudicator cannot make a decision unless all of the technical requirements of the Act have been met. One such requirement is that the right to claim payment under the Act must come from a single construction contract. This has been confirmed in a number of cases, including: • Rail Corporation of NSW v Nebax Constructions [2012] NSWSC 6, in which Nebax (the contractor) served five payment claims simultaneously for construction of platform resurfacing works at different train stations, all dated the same date. Nebax then made a separate adjudication application for each payment claim. The Court decided that ‘there can only be one adjudication application for any particular payment claim for any particular contract’. • Matrix Projects (QLD) Pty Ltd v Luscombe & Ors [2013] QSC 4, in which Luscombe (the builder) had a ‘period subcontract’ with Matrix Homes for undetermined building work, the scope and locations of which would be agreed at a later date. Luscombe ultimately completed building work on instruction from Matrix Homes at a range of locations over a nine– month period. Some work was completed under the terms of the period subcontract, with individual purchase orders made as required by Matrix, and some on a ‘do and charge’ basis after verbal requests. Luscombe issued one payment claim for all of the work, and specifically referred in the payment claim to the fact that there were multiple contracts. Citing Rail Corporation, the Queensland Supreme Court decided that the fact that the payment claim covered multiple contracts was ‘fatal to its validity’. In Class Electrical Services, Go argued that there was a single credit agreement that covered all of the purchase orders, and this meant that there was just one construction contract. Class, on the other hand, argued that the credit agreement was not a construction contract for the provision of construction work or related goods and services (as required by the Act), but simply an overarching agreement to provide credit. The court agreed with Class, finding that, although the individual purchase orders were each a separate construction contract under the Act, and the credit agreement setting out the broad terms was not a construction contract. If this is the case, then you can only issue one payment claim per reference date and any others will be invalid. If you are in doubt, it is important to check with a lawyer–particularly if you are on the receiving end of a payment claim. The court therefore held that the adjudicator’s decision was void and unenforceable. WHAT DOES CLASS ELECTRICAL SERVICES MEAN WHEN I’M TRYING TO GET PAID? If you have a standing contract where: • your clients sign up to broad terms for the supply of construction–related goods or services not referring to a particular project, quantity or price; and • once signed, your client submits purchase orders from time to time as required, with the terms of the credit arrangement applying to all purchases, then it is likely that each purchase order will be a separate ‘construction contract’ for the purposes of the Act. If you issue a payment claim for multiple purchase orders, it will be invalid. Each purchase order must be dealt with as if it is a separate contract, which means a separate payment claim and a separate adjudication application. However the terms of each contract need to be looked at separately. It is possible that if your overarching terms of credit actually specify details such as timing, quantity, quality and cost for the items to be supplied, it might be a construction contract under the Act. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 49 SECURITY OF PAYMENT THE CURATE’S EGG REVISITED Philip Davenport, Solicitor Sydney In ‘Adjudications and the curate’s egg’ (2011 #141 ACLN at 38) I asked the question: If only part of an adjudicator’s determination is bad, must the claimant lose the whole of the adjudicated amount? I contrasted the approach of the Queensland Supreme Court and the NSW Supreme Court. I was critical of the approach of the NSW Supreme Court. Subsequently, Basten JA in the NSW Court of Appeal in Cardinal Project Services v Hanave [2011] NSWCA 399 referred to the curate’s egg at [52] where he said: If the determination is indeed legally ineffective in all respects, it would be doubtful whether the Court could condition declaratory relief (or an order setting aside the decision) upon the applicant making such payment as would be required by the determination if validity could be determined part by part, like the curate’s egg. Accordingly, the underlying assumption was inconsistent with the total invalidity for all purposes. The issue arose again in BM Alliance Coal Operations v BGC Contracting (No 2) [2013] QSC 67 where Applegarth J in the Queensland Supreme Court found that the respondent had only established one of three jurisdictional errors by the adjudicator. Since the error related to approximately $4 million (which the claimant agreed to repay to the respondent) of the approximately $28 million assessed as the progress payment, Applegarth J refused to declare the adjudicator’s decision void. The result was that the claimant was able to recover as a progress payment the balance of approximately $24 million. By contrast, in Anderson Street Banksmeadow v Helcon Contracting Australia [2013] NSWSC 657 Stevenson J in the 50 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 If only part of an adjudicator’s determination is bad, must the claimant lose the whole of the adjudicated amount? NSW Supreme Court considered the decision of Applegarth J & came to the opposite conclusion. At [17] Stevenson J said that he was initially attracted to the approach of Applegarth J in BM Alliance Coal Operations but at [18]–[19] he said: However, on reflection, I have some to the conclusion that in light of what fell from the Court of Appeal in Brodyn Pty Ltd t/as Time Cost and Quality v Davenport [2004] NSWCA 394 I cannot accept that submission. In Brodyn, Hodgson JA (with whom Mason P and Giles JA agreed) held that a determination made in breach of the rules of natural justice is void, and not merely voidable. At [22] Stevenson J said that he could not see any basis upon which would not accede to the respondent’s application that he should make a declaration that the determination is void even assuming that he has a discretion. Stevenson J does not cite what it is in Brodyn that precluded him from accepting the submission. I can’t see anything in Brodyn to support Stevenson J’s conclusion. Hodgson JA referred to ‘void and voidable’. Hodgson JA did not say that the fact that an adjudication determination is void means that the court must make necessarily make a declaration to that effect. Anderson Street was decided on 30 May 2013 before State of NSW v Kable [2013] HCA 26 was decided by the High Court on 5 June 2013. The High Court took a quite different view to that of the NSW Court of Appeal on ‘void and voidable’. Had Stevenson J had the benefit of reading the judgment in Kable, he might have come to a quite different conclusion. Briefly, in Kable, Levine J in the NSW Supreme Court, purporting to act under an Act that was subsequently held to be invalid, ordered the detention of Mr Kable. The question for the High Court was what effect, if any, the decision of Levine J had in the period before the Act was held to be invalid. The NSW Court of Appeal held that the order of Levine J was void and Mr Kable was entitled to damages for false imprisonment. In Kable at [22] the majority in the High Court said: The difficulties associated with using words like ‘void’ and ‘voidable’ in connection with administrative actions have long been recognized. Writing in 1967, H W R Wade said that: [T]here is no such thing as voidness in an absolute sense, for the whole question is, void against whom? It makes no sense to speak of an act being void unless there is some person to whom the law gives a remedy. If and when that remedy is taken away, what was void must be treated as valid, being now by law unchallengeable. It is fallacious to suppose that an act can be effective in law only if it has always had some element of validity from the beginning. However destitute of legitimacy at its birth, it is legitimated when the law refuses to assist anyone who wants to bastardise it. What cannot be disputed has to be accepted. The point is that Applegarth J in BM Alliance recognised that if he refused to make the declaration of invalidity of the adjudicator’s decision, the claimant could enforce it. Once the respondent has no remedy, the adjudication decision is in law unchallengeable. That is consistent with the High Court’s approach. Stevenson J erred in finding that he had no alternative but to make the declaration of invalidity. In R v Commonwealth Court of Conciliation and Arbitration; Ex parte Ozone Theatres (Aust) Ltd [1949} HCA 33] and in later cases the High Court has recognised that a Court may exercise judicially its discretion to decline to grant relief where the circumstances make it just that the remedy should be withheld. This is such a case. The order which I propose to make takes account of both the policy underlying the granting of relief in the exercise of the Court’s supervisory jurisdiction to correct jurisdictional error and the statutory context in which the application for such relief was made. The orders proposed by BGC are appropriate to remedy the jurisdictional error, whilst permitting BGC to retain the amount which would have been awarded to it if the second respondent had made his adjudication decision free of jurisdictional error. Such a course advances the policy of the Act. The particular circumstances of the case make it just that I decline to declare the decision void, subject to the condition that BGC pay BMA that part of the award which was affected by jurisdictional error, together with interest and GST. A declaration is an equitable remedy. The very reason why the Court has a discretion as to whether it will make a declaration is so that the Court can do what is just. Perhaps, following Kable, the NSW Supreme Court will see its way to decline to make the declaration where the circumstances make it just that the declaration should be withheld even though the adjudication determination is void. At [48] Applegarth said: AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 51 BUILDING REGULATION UNCERTAIN TIMES AHEAD—THE QUEENSLAND BUILDING SERVICES AUTHORITY NO LONGER! Ren Niemann, Partner Goran Gelic, Lawyer Allens Linklaters, Brisbane IN BRIEF The Queensland Government recently launched its ‘Ten Point Action Plan’ which it proposes will restructure the regulation of Queenland’s construction industry. As part of that process, the Queensland Building Services Authority will be replaced by the Queensland Building and Construction Commission. HOW IT AFFECTS YOU There are no immediate changes to building law compliance obligations. Until the extent of the changes and their commencement are known, it is ‘business as usual’. All participants in the construction, energy and resource sectors in Queensland will need to carefully monitor this space. Some of the changes, if implemented in their current form, could have a significant impact on the regulatory framework. WHAT WILL HAPPEN AND WHEN? In response to the recommendations from the Inquiry into the Operation and Performance of the Queensland Building Services Authority 2012 undertaken by the Transport, Housing and Local Government Committee, the Queensland Government has issued the Ten Point Action Plan for restructuring the regulation of the Queensland construction industry. It is proposed the Queensland Building and Construction Commission (the QBCC) will be responsible for giving effect to this plan. The changes proposed, together with their timeframe, are set out below. 52 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 All participants in the construction, energy and resources sectors in Queensland will be, to some extent, affected by the proposed changes. Industry participants will need to be familiar with the proposed changes and ensure they are in a position to appropriately respond to them. TIMEFRAME FOR COMMENCEMENT Immediate changes (expected to commence end of 2013) RELEVANT ‘ACTION’ Replace the Queensland Building Services Authority (the BSA) with the QBCC. Establish an appropriate commission structure with functional business units (e.g. licensing) headed by their own general managers. As soon as possible changes Establish appropriate mechanisms of review. It is proposed that the QBCC will establish an internal review unit and procedures for review of insurance decisions and homeowner complaints to reduce the number of applications for review being made to QCAT. Develop an improved suite of domestic building contracts (with a view to providing a more fair and equitable base for consumers and licensees). Review the current system of licensing and compliance (particularly the difficulty with section 42 of the Queensland Building Services Authority Act 1991 (Qld) (the QBSA Act). Develop improved education and training for home owners and consumers. Progressive changes (subject to industry consultation). It is anticipated that these changes may take up to 12 months after the appointment of the QBCC. In conjunction with the current industry review of the Building and Construction Industry Payments Act 2004 (Qld), consider the development and implementation of a rapid domestic adjudication model to fast track building disputes with mandated response timelines. Retain the Queensland Home Warranty Scheme but review the scheme to provide greater definition and clarity. Review the role of private certifier with emphasis on probity, conflict of interest, quality and appropriate penalty regimes for failure to perform. Expand the licensing role of the new QBCC. COMMENTARY The introduction of the QBCC to replace the BSA is the most significant change to the industry regulator since its inception some 22 years ago. Many of the proposed functions of the QBCC will be significantly different to that of BSA. The QBCC, for example, will have a stronger focus on licensing, certification and dispute avoidance and management. One of the key changes flowing from the Ten Point Action Plan are the proposed amendments to section 42 of the QBSA Act. It is proposed that section 42 will be revised to make it clear that there will be no breach of the Act if the ‘building work’ is carried out by an appropriately licensed builder (this is contrary to the current position which requires a company to be licensed even though the company may contract with a registered building company to perform the ‘building work’). The Government has acknowledged that the current approach to section 42 may at times lead to unintended consequences. The Queensland Government is already starting to give effect to the Ten Point Action Plan. Recently, the Queensland Government introduced the Queensland Building Services Authority Amendment Bill 2013 (Qld) which aims to give effect to the ‘immediate’ changes. the proposed changes and ensure they are in a position to appropriately respond to them. That said, until we fully know the precise nature of the changes and their commencement, it is ‘business as usual’ for the time being. This is definitely a space to monitor carefully. Ren Niemann and Goran Gelic’s article was previously published in Allens Linklaters’ Construction & Major Projects—June 2013. Reprinted with permission. All participants in the construction, energy and resources sectors in Queensland will be, to some extent, affected by the proposed changes. Industry participants will need to be familiar with AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 53 SECURITY OF PAYMENT SECURITY OF PAYMENT LEGISLATION MAY NOT APPLY TO CONTRACTS FOR WORKS INVOLVING MINING PLANT Scott Laycock, Partner Rohan Dias, Solicitor Gadens, Sydney THE APPLICABILITY OF SECURITY OF PAYMENTS LEGISLATION TO THE MINING SECTOR—THE STORY SO FAR Security of payment legislation, such as the Building and Construction Industry Payments Act 2004 (QLD) (Act), will not apply to a contract unless some of the work under the contract satisfies the Act’s definition of ‘construction work’ or ‘related goods and services’. We previously reported on two Queensland Court of Appeal cases (HM Hire Pty Ltd v National Plant and Equipment Pty Ltd & Anor [2013] QCA 6 and Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd & Anor [2012] QCA 276), from which we learned that the ‘mining exclusions’ to the Act’s definition of ‘construction work’ (at section 10(3)) is to be interpreted narrowly, and will only exclude from the Act’s application contracts for works involving the direct physical extraction of materials. Accordingly, it was found in those cases that contracts relating to the construction of access roads, dams and drains at the Burton Coal Mine were caught by the Act. It followed that contracts for works at mining sites, other than for works involving the direct extraction of minerals, were capable of being caught by the Act. However, in an apparent contradiction, the Queensland Supreme Court in the case of Agripower Australia Ltd v J & D Rigging Pty Ltd [2013] QSC 164 found that a contract involving the dismantling of mining plant (such as baghouses, storage tanks and kilns) originally installed for the purposes of a mining lease will not attract the Act’s operation. This article will consider the reasoning adopted by the court in arriving at its decision in Agripower and the implications for participants in the mining sector. DISPUTE The case relates to mining plant (including mixing tanks, storage bins, baghouses, a large kiln, electrical motor control centre and cabling, two kiln baghouses and corresponding screw conveyors) originally installed by the mining lease holder at the Skardon River Mine in Cape York, Queensland. Agripower Australia Ltd (Agripower) purchased this plant, and engaged J & D Rigging Pty Ltd (J & D) to dismantle it and transport it from the mining site to its new destination (contract). J & D issued a payment claim under the Act for the dismantling works, and the claim proceeded to adjudication. The adjudicator found in favour of J & D. Agripower appealed the adjudicator’s decision, arguing that the Act did not apply to contract as the contract work was not ‘construction work’ as defined by section 10 of the Act. The definition of ‘construction work’ under section 10 of the Act relevantly includes: (a) the construction, … demolition or dismantling of buildings or structures, whether permanent or 54 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 not, forming, or to form, part of the land; (b) the construction, … demolition or dismantling of any works forming, or to form, part of land, including walls, roadworks, powerlines … Agripower submitted that the contract works did not satisfy this definition because the works did not ‘form part of the land’. DECISION The Court agreed with Agripower, concluding that the mining plant did not ‘form part of the land’ as required. In arriving at this conclusion, the court found: (1) From its definition under the Acts Interpretation Act 1954 (Qld) and its meaning under the common law, the word ‘land’ included estates and interests in land (which are essentially certain legal rights in respect of land). (2) At common law, something may be attached to land so that it becomes part of the land (i.e. becomes a fixture), and whether that thing becomes a fixture depends essentially upon the objective intention with which it was put in place. Relevant factors to this are the purpose of annexation and the degree annexation. (3) There is nothing in the language of the Act to displace the meaning of ‘land’ under the Acts Interpretation Act 1954 (Qld), or to suggest that buildings or structures, works or fittings may form part of the land under that Act when they would not do so at common law. (4) From section 10 of the Mineral Resources Act 1989 (Qld) and common law principals relating to mining tenements set down by the High Court, a ‘mining lease’ (which essentially grants the holder the right to remove minerals from specified land) is not ‘land’ and does not give rise to an estate or interest in the subject land. Applying the above findings to the facts of the case, the Court held: (1) The purpose for which the mining plant was initially put in place on the land was for the mining lease (which, from 4 above, is neither ‘land’ nor and ‘interest in land’), rather than to add some additional feature to the land the subject of the mining lease, and accordingly it could not be said that it ‘formed part of the land’ as required by the Act. (2) This conclusion is supported by the fact that the Mineral Resources Act 1989 (Qld) actually mandated the removal of the mining plant prior to the expiration of the mining lease. However, consistent with the terms of section 10 of the Act and the common law concept of forming part of the land, permanence is not a necessary or decisive criterion, but merely a relevant factor. (3) To the extent that the plant being physically attached to the land might have been a relevant consideration, the plant was affixed to the land for the mere purpose of stabilisation for efficient operation. Since the mining plant could not be said to ‘form part of the land’, the dismantling of that plant was not ‘construction work’ within the meaning of the Act. Accordingly, the Act was held to not apply to the contract. IMPLICATIONS APPLICABILITY TO OTHER STATE JURISDICTIONS Though the Court’s reasoning involves Queensland specific legislation, it would seem that the reasoning will be at least relevant in all jurisdictions since it focused keenly on the common law concept of fixtures. However, that reasoning may be overridden if the concepts of ‘land’ or ‘mining leases’ are given a materially different definition under the legislative regimes of the different states. For example, the Western Australian Interpretation Act 1984 defines ‘land’ in a similarly broad fashion to the Queensland legislation; however, in addition to expressly including ‘estates’ and ‘interests’ in land, it also expressly includes ‘buildings and other structures’. So a similar case in Western Australia might have turned on a question not asked by the Court in Agripower, namely, what physical requirements are necessary for something to be considered a ‘structure’ on a parcel of land. Further, there is a growing difference between states in their courts’ approaches to interpreting the Act. For example, the Chief Justice of the NSW Supreme Court held in Edelbrand Pty Ltd v H M Australia Holdings Pty Ltd [2012] NSWCA 31 that the Act should be given a more liberal interpretation in favour of claimants on the basis that it is remedial legislation, however Queensland courts have expressed a reluctance to follow suit (see Agripower at [37]–[42]). Accordingly, NSW courts may adopt a broader interpretation to the definition of ‘construction work’ in a similar case. CAN AGRIPOWER BE RECONCILED WITH HM HIRE AND WARREN BROTHERS? It is very difficult to reconcile these cases. In HM Hire and Warren Brothers, the subject works (the construction of dams, drains and access roads) were also constructed for the purposes of mining leases, yet the Act was found to apply. Unfortunately, in those cases, whether or not the works ‘formed part of the land’ was not a major point in dispute between parties. While it is difficult to speculate, the key distinction between those cases and Agripower might be the fact that the mining plant in Agripower, by its physical nature (being something which could be dismantled, carried off, and reassembled at another site), had the capability of being regarded as personal property as opposed to realty (the same could not be said for dams, drains and access roads), and therefore lent itself to an analysis analogous to the common law doctrine of fixtures to determine whether it relevantly ‘formed part of the land’. CONCLUSION The decision in Agripower should come as good news for mining principals in Queensland (and potentially in other jurisdictions) as it limits their exposure to the Act’s onerous regime in relation to contracts for works involving mining plant. However, due to the apparent and yet unresolved contradiction with previous Queensland Court of Appeal cases, and the uncertainty as to whether the same principles will apply Australia–wide, principals under mining related contracts must remain vigilant to ensure they respond to all claims which on their face purport to be made under the Act with a payment schedule that complies with the Act. Scott Laycock and Rohan Dias’ article was previously published on the Gadens website—September 2013. Reprinted with permission. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 55 COMPETITION LAW IMPACT OF COMPETITION LAW ON THE CONSTRUCTION INDUSTRY Malcolm Chin, Partner Minter Ellison Lawyers, Hong Kong Miranda Noble, Senior Associate Minter Ellison Lawyers, Melbourne The new Competition Ordinance, which prohibits anticompetitive conduct affecting Hong Kong, applies to all sectors and levels of the Hong Kong economy. This article, drawing on overseas examples, provides a practical look at the potential impact of the new law on the construction industry in Hong Kong. ANTI–COMPETITIVE CONDUCT IN THE INDUSTRY The construction industry has been a common target for competition regulators in other jurisdictions. A number of significant enforcement proceedings relating to cartel conduct have been brought over the years, in particular for price fixing (including cover pricing, where pre–determined unsuccessful bidders submit an artificially high price so that the pre–determined successful bidder’s price would come under), market sharing and bid–rigging. In many of those cases, penalties and other consequences were ordered against both companies and individual executives. Lessons can be learnt from these cases and other action taken by regulators. For example, in 2012 the Australian competition regulator (the Australian Competition and Consumer Commission) took the step of writing to more than 2,500 executives in the construction industry to raise awareness of cartel conduct and the potential consequences for engaging in such conduct, as well as offering the executives the chance to apply for immunity if they revealed their involvement in a cartel. TENDER PROCESSES & COVER PRICING Anti–competitive conduct frequently occurs through bid, tender and request for proposal/ quotation processes. Overseas examples demonstrate how such processes raise real risks of bid– rigging, market sharing and price fixing (particularly, cover pricing and bid rotation) in the industry. They underscore the importance of acting independently in relation to all decisions about tender/bid participation, pricing and terms. Of interest to those running a bid or tender, overseas examples also highlight the need to implement procurement processes which detect and prevent possible collusion amongst suppliers, including training procurement staff to be on the lookout for suspicious bidding practices. For example: JAPAN Companies have been heavily fined for engaging in bid–rigging in relation to harbour engineering works, offshore works (including dredging operations), various engineering works and tunnel ventilation construction for a highway. The companies agreed which company would be the designated successful bidder for each tender and cooperated so that the designated successful bidder could win the tender. 56 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 AUSTRALIA Penalties of more than AUD20 million were imposed against three pre–mixed concrete suppliers for engaging in cartel conduct by agreeing, during more than 50 meetings and telephone conversations, on pricing in relation to large government construction projects, and agreeing not to compete for specified customers or on specified major projects. In another case, building companies were penalised for cover pricing in connection with tenders for four government building projects (despite certifying in their bids that they had not discussed prices with other tenderers). SINGAPORE Fourteen electrical and building works companies were fined for bid–rigging after they colluded to submit bids for electrical or building works projects for various properties. Typically, the company that was interested in winning the project would request for a cover bid from at least one other company. The requesting company would inform other companies of its bid price so that the latter could submit higher quotes. In some instances, the requesting company even prepared the quotations for the other companies. UNITED KINGDOM Over 100 construction companies were fined more than GBP100 million for engaging in bid–rigging activities in respect of nearly 200 tenders for a wide range of building projects, largely involving cover pricing. In some cases, the successful bidder paid an agreed sum of money to the unsuccessful bidders (known as a ‘compensation payment’) facilitated by the raising of false invoices. Demonstrating a continued focus on the industry, the UK competition regulator (the Competition Commission) also recently arrested seven people as part of a separate investigation into a suspected cartel for the supply of construction products. In Hong Kong, cartel conduct in the construction industry has been the subject of litigation, even before the enactment of the Competition Ordinance. A 2010 case concerned cartel conduct by a group of suppliers of stainless steel gates. The suppliers, who were the only contractors approved by the HK Housing Authority to supply gates for the Authority’s projects, agreed between themselves on the minimum prices for tenders to be submitted to the main contractors of the Authority. When a main contractor would invite tenders from some or all of the suppliers, they would then designate one supplier who would put in a tender at the agreed minimum tender price. If the other suppliers put in a tender, they only did so at a higher price in order to enhance the chances of the designated supplier obtaining the contract. Although the court was unable to take action given the absence of a competition law in Hong Kong at the time, it was nevertheless critical of this conduct, commenting that: ... the Housing Authority and the main contractors were cheated into believing that the tendering system was working and the market forces were at play. They also thought that the prefixed minimum tender price was a genuine lowest bid given by a tenderer. The Housing Authority in the end had to pay what the cartel had decided rather than what the market dictated, and it still thought that the market was working through the tendering process. LONG ESTABLISHED BEHAVIOUR Many overseas cases involving cartel conduct in the construction industry relate to conduct which took place over a long period of time. Such behaviour is likely to have been entrenched in the way that companies did business and widely accepted as the norm, despite its illegality. In some instances the parties may not have knowingly broken the law. To the extent that this may currently be occurring in Hong Kong, companies must take action to break away from and discontinue any established arrangements which would fall foul of the Competition Ordinance before it comes into full effect. In Europe, 17 producers of pre– stressing steel were fined a total of EUR269 million for operating a cartel that lasted 18 years. Through more than 550 cartel meetings, the companies agreed to fix individual quotas and prices, allocate clients and exchange sensitive commercial information. In another cartel lasting more than 11 years, eight companies in the concrete reinforcing bars sector were fined over EUR83 million for fixing various elements of price, and limiting or controlling output and sales. INDUSTRY ASSOCIATIONS Overseas experience confirms that participation in an industry association can raise risks, particularly in relation to decisions or other steps taken by the association to influence the conduct and activities of members (for example, the issuing of recommendations relating to price or suggested fee schedules), and by providing a readily available forum for discussion and information exchange among competitors. Being attune to potential competition risks in relation to participation in any association and knowing how to respond in the face of such risks (for example, leaving a meeting if inappropriate discussion takes place) is key to avoiding a potential breach. In Australia, penalties were imposed against construction companies tendering for a government construction contract who, before submitting their bids, met at an industry association and agreed that the successful bidder would pay the unsuccessful bidders an ‘unsuccessful tendering fee’. In another case, three companies were fined for a price fixing arrangement and for engaging in a collective boycott. They had agreed, through annual negotiations with a roof tilers association, to fix the rates paid to roof tile contractors and to only engage the services of roof tile contractors who were members of the association. INFORMAL MEETINGS Anti–competitive agreements do not need to be in writing and can often occur outside formal settings. Caution must be exercised at social events and informal meetings where competitors are present, since these can create high risk environments for cartel conduct. Referred to as the ‘Coffee Club’, participants in a cartel who installed fire sprinkler and fire alarm systems met regularly over coffee at hotels, cafes and various sporting and social clubs agreed who would win particular tenders, who would not submit a tender for a particular job, or who submit a tender with a cover price. They were ultimately fined more than AUD14 million. In another case, suppliers of plastic pipes for water and sewerage systems, and pipe fittings and valves met in restaurants and cafes, where they agreed to increase prices, limit AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 57 discounts, collude on tenders and to avoid competing for each other’s customers. They were also fined. ABUSE OF MARKET POWER Another key prohibition under the Competition Ordinance provides that those with a ‘substantial degree’ of market power may not abuse that power in an anti– competitive way. Participants in the construction industry in a strong market position (such as a high market share) should exercise caution before engaging in any conduct which may be perceived as an abuse of market power. This includes predatory or exclusionary conduct such as a refusal to supply, price discrimination or tying/bundling goods and services. In Australia, BHP was found to have abused its market power when it refused to supply a type of steel known as ‘Y bar’ (used in the making of star picket fence posts) at competitive prices to another company wishing to supply star picket fence posts. BHP was found to have taken advantage of its market power in steel to prevent the competitor from entering the market for the supply of star picket fences. PROTECTION FROM ANTI–COMPETITIVE CONDUCT While competition law regulates conduct of your business, it also regulates the conduct of others. The Competition Ordinance should therefore be viewed as protecting participants in the construction industry (including you) from anti– competitive behaviour by other parties such as suppliers and competitors. Businesses who are victims of anti– competitive behaviour will be able to lodge complaints with the Hong Kong Competition Commission (HKCC) and potentially prompt an investigation and proceedings. They may also take private action for loss or damage incurred once the HKCC has taken action or received an admission from the party breaching the law. For instance, a principal calling for bids for a new project who suspects that bidders have colluded in making their bids, could refer such conduct to the HKCC for investigation. Equally, a company whose competitor contacts them and proposes a course of action that would breach the new law (eg proposing that they cover price on an upcoming project) could notify the HKCC of that attempted breach. In the UK, construction companies were affected as a result of cartel conduct by six recruitment agencies who supplied candidates to construction companies. The agencies had engaged in cartel conduct in relation to the supply of candidates, including collectively boycotting an intermediary and agreeing to fix the fee rates to be charged to certain construction companies, driving up staffing costs. Such conduct would be reportable to the HKCC. CONFESSING TO ANTI– COMPETITIVE CONDUCT In many of the cases outlined above, one or more parties to the anti–competitive conduct were granted leniency in their punishment by the regulator in return for cooperation and disclosure. Like most competition regulators, the HKCC also has the power to enter into ‘leniency agreements’, offering an offender immunity from penalty proceedings in exchange for cooperation in an investigation or legal proceeding. By rewarding disclosure and cooperation, these leniency arrangements are intended to encourage parties to come forward and confess to their illegal conduct. Details of the HKCC’s approach to leniency will be announced by the HKCC in due course. 58 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 Those in Hong Kong’s construction industry need to be aware of the HKCC’s leniency program. Appropriate procedures should be put in place to ensure that any possible breach of the Competition Ordinance is promptly reported to management and escalated as needed, so that legal advice can be sought as to whether an application for leniency can or should be made. Since leniency policies often provide the greatest benefit to the first applicant through the regulator’s door, acting quickly can be critical. COMPLIANCE IS CRITICAL The best defence to protecting your business and staff from involvement in anti–competitive conduct and a breach of the Competition Ordinance is ensuring that adequate and effective compliance systems are in place. Among other steps, staff in high risk areas in the construction industry (such as those responsible for tendering/ procurement, pricing, contracting or participating in an industry association) should receive tailored training so that they have a solid understanding of the law and its practical application. With the HKCC now formed, taking proactive compliance steps is a priority. Malcolm Chin and Miranda Noble’s article was previously published in Minter Ellison Lawyers’ Construction Law Asia—June 2013. Reprinted with permission. CASE NOTE NEW SOUTH WALES COURT OF APPEAL FINDS DEFECTS DUTY Peter Pether, Partner Adam Wallwork, Partner Jennifer Turner, Special Counsel King & Wood Mallesons, Sydney In the present case, the building involved was a serviced apartment block. Accordingly, it was outside the protection afforded by the Home Building Act (NSW). McDougall J held, following his other reasons in Star of the Sea, that the builder did not owe a duty of care to the Owners’ Corporation and dismissed the Owners’ Corporation claim. The Owners’ Corporation appealed. THE COURT OF APPEAL The Court of Appeal judgment overturns the reasoning of McDougall J. It is troubling in several respects including: In a judgment dated 25 September 2013 in The Owners—Strata Plan No 61288 v Brookfield Australia Investments Ltd (2013) NSWCA 317, the NSW Court of Appeal has found that a builder owed a duty to exercise reasonable care in the construction of a building, to avoid causing an Owners’ Corporation to suffer loss resulting from latent defects in the common property which were structural, constituted a danger to persons or property in the vicinity or made those apartments uninhabitable. Along the way, the Court found the builder owed a concurrent duty in tort to a developer with whom it had a detailed written building contract, although both were major, sophisticated corporations. This is a surprising judgment, which will rightly concern the construction industry in Australia. BACKGROUND In Star of the Sea [2012] NSWSC 712, McDougall J had found that a builder did not owe a duty of care to an Owners’ Corporation in constructing a residential apartment block. At least part of the reasoning in Star of the Sea was that Parliament had legislated in the Home Building Act (NSW) for a system of warranties to protect residential owners from defects. (1) The legislature has imposed a statutory protection regime for defects in residential dwellings but has chosen not to impose such a scheme on serviced apartment or commercial buildings. (2) The Court of Appeal relies heavily on the High Court’s judgment in Bryan v Maloney (1995) 182 CLR 609, which has been trenchantly and appropriately criticised. Courts have avoided following Bryan v Maloney and have distinguished it. Court of Appeal’s ultimate finding that the builder owes a duty of care to the Owners’ Corporation—the successor in title to the developer. One anticipates that the builder will give very serious consideration to an appeal to the High Court of Australia over this decision. In the interim, builders should note that there will be a concurrent duty in contract and tort in design and construct contracts unless the duty is expressly excluded. One anticipates that until the High Court has an opportunity to deal with the Court of Appeal’s judgment, there will be an increase in claims in tort and concurrent claims in tort and contract, concerning defects in both residential and non– residential buildings. Peter Pether, Adam Wallwork and Jennifer Turner’s case note was previously published on the King & Wood Mallesons website— September 2013. Reprinted with permission. (3) The Court of Appeal acknowledges that the High Court in Perre v Apand Pty Ltd (1999) 198 CLR 180 has held that vulnerability is now a key indicia of whether a duty of care exists. However, at para 120 the Court of Appeal finds that a builder owes a duty of care to a developer in circumstances where both are major sophisticated commercial parties who have entered into a detailed written building contract which regulates, among other things, how defects are to be dealt with. (4) That finding, that a commercial developer who lets a detailed contract to a builder, is owed a concurrent duty of care by the builder is surprising in the face of concepts of vulnerability and is a necessary springboard for the AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #152 SEPTEMBER/OCTOBER 2013 59 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER SWAP EXCHANGE PTY. LTD. PO BOX R1140 ROYAL EXCHANGE SYDNEY NSW 1225 AUSTRALIA