Roadscanners Publication 2003 Tyre Bales on the B871
Transcription
Roadscanners Publication 2003 Tyre Bales on the B871
ROADSCANNERS RESEARCH REPORT THE B871 TYRE BALE PROJECT The use of recycled tyre bales in a lightweight road embankment over peat 2 Colin Mackenzie, Timo Saarenketo THE B871 TYRE BALE PROJECT The use of recycled tyre bales in a lightweight road embankment over peat Research report Roadscanners Rovaniemi 2003 3 4 Abstract This research report documents the construction of a road embankment on the B871 Road in Sutherland, Scotland. This lightly trafficked road is built over deep and weak peat and has been subject to subsidence. Because of a major increase in traffic expected from timber extraction a 50 m long section of the road was excavated and replaced with a lightweight embankment of 350 compressed tyre bales. A number of practical lessons have been learned from the project and these are detailed together with suggestions as to further trials and uses of tyre bales in embankments. The high porosity of a bale embankment has also been identified as a key property that may have considerable potential for application in sustainable drainage schemes. Tyre bales are a novel product in the UK and it is recommended that it is best to advance their use in civil engineering by carrying out well documented small to medium scale trials, such as the B871 project, to build up confidence in a gradual but sustainable way. In particular it is recommended that research is carried out on: • • • • • Alternative interlock arrangements of tyre bales Alternative types of infill material Minimum depths of cover for satisfactory performance under heavy loads Reinforcement of bales at intermediate and lower levels on soft ground Drainage and water retention properties in service 5 6 CONTENTS 1 INTRODUCTION .............................................................................................10 2 BACKGROUND...............................................................................................11 2.1 TIMBER EXTRACTION ....................................................................................11 2.2 IDENTIFICATION OF THE PROBLEM SECTION ....................................................12 3.1 NEW ROAD CONSTRUCTION ..........................................................................15 3.2 DEVELOPMENTS IN THE MAINTENANCE OF EXISTING ROADS OVER PEAT...........15 4 TYRE DISPOSAL: AN ENVIRONMENTAL CHALLENGE .............................17 4.1 THE EC DIRECTIVE ......................................................................................17 4.2 PRODUCTION OF TYRE BALES .......................................................................18 4.3 PROPERTIES OF THE TYRE BALE PRODUCT ....................................................19 4.4 COST OF TYRE BALES ..................................................................................21 4.5 THE LEGAL POSITION ...................................................................................22 5 DESIGN OF THE B871 TYRE BALE PROJECT ............................................23 5.1 EXTENT OF THE PROJECT .............................................................................23 5.2 GROUND INVESTIGATION ..............................................................................23 5.3 DESIGN CONSIDERATIONS ............................................................................24 6 CONSTRUCTION PROCESS..........................................................................26 6.1 BYPASS ROAD CONSTRUCTION .....................................................................26 6.2 HANDLING OF TYRE BALES ...........................................................................27 6.3 CONSTRUCTION SEQUENCE ..........................................................................28 6.4 INSTALLATION OF SETTLEMENT MONITORING RODS .........................................29 6.5 CULVERT INSTALLATION................................................................................30 6.6 COMPLETION OF PAVEMENT STRUCTURE .......................................................30 6.7 SUBSEQUENT WORKS ..................................................................................31 7 RESULTS OF MONITORING ..........................................................................33 7.1 EMBANKMENT SETTLEMENT ..........................................................................33 7.2 BALE COMPRESSION ....................................................................................35 7.3 CULVERT SETTLEMENT .................................................................................35 7.4 ASSESSMENT OF SETTLEMENT ......................................................................36 7.5 SETTLEMENT PROBLEM ON APRIL 2003 .........................................................37 7.6 SETTLEMENT PROBLEM SEPTEMBER 2003.....................................................38 7 8 LESSONS LEARNED FROM THE PROJECT ................................................41 8.1 GENERAL ....................................................................................................41 8.2 GROUND INVESTIGATION ..............................................................................41 8.3 HANDLING ...................................................................................................41 8.4 BALE DIMENSIONS ........................................................................................42 8.5 JOINTS BETWEEN BALES ...............................................................................42 8.6 INFILL BETWEEN BALES .................................................................................43 8.7 GEOTEXTILE FABRIC.....................................................................................43 8.8 STEEL MESH REINFORCEMENT .....................................................................45 8.9 LAPS IN STEEL MESH REINFORCEMENT .........................................................45 8.10 INSTALLATION OF SERVICES ........................................................................45 8.11 MARKING AND RECORDING OF TYRE BALE EMBANKMENTS .............................46 8.12 SURFACE FINISHES AND TOLERANCES ..........................................................46 8.13 BALE TIE WIRES ........................................................................................46 8.14 CHEMICAL EFFECTS ....................................................................................46 8.15 POROSITY AND PERMEABILITY OF TYRE BALES .............................................47 8.16 DEVELOPMENTS IN THE LEGAL POSITION......................................................47 9 POSSIBLE FUTURE DEVELOPMENTS.........................................................48 10 CONCLUSION...............................................................................................49 BIBLIOGRAPHY ................................................................................................50 8 ACKNOWLEDGEMENTS The preparation of this research report has relied heavily on the constructive dialogue and exchange of information between the client, Highland Council, supplier Northern Tyre Recycling (UK) Ltd and Roadscanners. Thanks are due to the Director of TEC Services at The Highland Council and her staff, particularly Ron Munro, Community Works Manager and Garry Smith, Engineer at the Council office in Brora who were actively involved in the project at all stages. Thanks are also due to Jonathan Simm at HR Walligford for permission to reproduce in advance their recent research data on the properties of tyre bales. Inverness and Nairn Enterprise gave assistance with the funding for the report research and preparation. Finally this report would not have been commissioned without the enthusiasm of Dennis Scott, Managing Director of Northern Tyre Recycling (UK) Ltd and his determination to find beneficial end uses for his tyre bale products in civil engineering. 9 10 1 INTRODUCTION The disposal of used tyres is a challenge to modern society brought into sharp focus by recent changes in EC waste disposal legislation. Dumping of tyres in landfill is no longer acceptable and innovative solutions must be found if the problem is to be dealt with. Northern Tyre Recycling (UK) started production of compressed tyre bales in 2000 and have been active in seeking new end uses in civil engineering for their product. In the Highlands of Scotland the construction and maintenance of roads across deep peat has always been a problem. Lightweight embankments are an attractive solution but the materials required have traditionally been costly. The prospect of an economic source of lightweight tyre bales proved of immediate interest to The Highland Council, which required to deal urgently with a section of the B871 road in Sutherland that was sinking in to the underlying peat. The B871 Tyre Bale Project was designed and managed by The Highland Council TEC Service in the Sutherland Area office in Brora, Sutherland. Construction was carried out by contractor Edward Mackay of Brora over a three week period in December 2002, with additional works being carried out as necessary by the Council Direct Labour Organisation during 2003. This report has been commissioned by Northern Tyre Recycling (UK) (NTR) in an effort to learn lessons from the project and to disseminate this knowledge as widely as possible. 11 2 BACKGROUND 2.1 Timber Extraction The B871 road in Central Sutherland serves one of the most remote and sparsely populated areas of the UK. Although lightly trafficked and serving few properties along its 25 km length, it is a lifeline route connecting the scattered communities of the Helmsdale and Naver river valleys and beyond. In the 1950’s extensive timber planting was seen as a solution to the limited land use opportunities, both in terms of improving the local economy and providing some diversity on the vast upland moorland. Two large conifer forests was planted near the B871 road by the government Forestry Commission. Little thought was given then to the extraction of the ultimate timber crop as it would have been inconceivable at that time that the narrow and winding single track road would stay unimproved for the next 60 years. For many years it was thought that it might be uneconomic if not impossible to get the timber to market but strenuous efforts were made by The Highland Council (the Roads Authority) and Forest Enterprise (the commercial arm of The Forestry Commission) to deal with this problem as the forests reached maturity. Eventually a unique partnership was formed between these bodies with an agreement that timber could be extracted along the B871 to Kinbrace. It would then be transferred to the North Highland Rail Line at a purpose built railside loading bank, constructed in 2002 with EC assistance. The B871 would be monitored to see how it performed under the huge increase in traffic, and to see what lessons could be learned from this. This partnership agreement between the Council and Forest Enterprise recognized their shared interest in the cost effective management and maintenance of the B871 to ensure that in remained unrestricted to both timber and normal public traffic. There has traditionally been a wide difference of approach between forestry and local authority civil engineers and this provided an opportunity to see what forest road techniques might have an application on a lightly trafficked public road. The intention was that B871 would be monitored to see how it performed under the huge increase in traffic and to share information on maintenance solutions that would be low cost, innovative yet “fit for purpose” rather than costly and over designed. 12 2.2 Identification of the Problem Section In 1997 The Highland Council engaged in an EC supported Northern Periphery ROADEX programme to exchange technical information between roads authorities in Scotland, Norway, Sweden and Finland. Considerable advantage was gained from this exchange in an increased awareness of the techniques available for assessing the condition of fragile and failing roads. In order to properly monitor the B871 and a part of B873 a baseline survey had to be carried out and Roadscanners were commissioned to do this. Roadscanners carried out a Ground Penetrating Radar survey of the road and integrated this with earlier information from: • • • • A Falling Weight Deflectometer (FWD) survey of pavement structure stiffness carried out by Scott Wilson Pavement Engineering A High Speed Road Monitor (HSRM) survey of roughness and rutting carried out by WDM Pavement cores at regular intervals carried out by Scott Wilson Pavement Engineering Video recording of the road made by Highland Council Roadscanners analysed this data using Road Doctor™ software and provided the Council client with detailed information about current road condition, road structures and their stiffness and subgrade soil quality and giving an indication of the weakest sections of road. This could then be used as a basis for maintenance planning and future monitoring of the road. The results were published in the form of GIS maps in a written report and power point show (Figure 1). One section of road near Loch Rosail was in particularly urgent need of strengthening, the pavement having sunk into the 6 m deep underlying peat (figure 2). This section was frequently covered by up to 200 mm of water as it lay at or below the moorland water table. This section of road is the subject of this report. 13 Loch Rosail test section Figure 1. Risk analysis map of B871 Kinbrace - Syre and location of Loch Rosail test section. The risk classification is from class 0 (no risk of damage) to class 3 (severe pavement damage will appear immediately after timber haulage starts). Figure 2. Loch Rosail test road section. Pavement surface is located at the ground water table level and frequently road was covered with 200 mm thick water. 14 Figure 3. Road Doctor GPR profile over Tyre Bale trial section. GPR profile shows that the embankment is about 1.5 m thick in thickest section and bituminous layer could be found from as deep as 0.7 m. 15 3 TRADITIONAL SOLUTIONS FOR BUILDING ROADS ON PEAT 3.1 New Road Construction Peat has proved a major impediment to road construction in the Northern Highlands throughout the last two centuries but particularly in the last 50 years when a major programme of road widening and improvement was carried out. Early practice was to leave shallow depths of peat in place although this inevitably resulted in eventual pavement deformation. On deeper sections reinforced concrete slab rafts were sometimes used, with some limited success. In West Sutherland timber fascine rafts were used in the 1950’s and early 1960’s. These were formed from small diameter conifer tree trunks placed on the peat in two orthogonal layers, and overlain by capping and pavement construction. Cleft chestnut paling fencing, rolled out on the peat, was tried as an alternative to fascines in some places. This had little strength but acted as a separation layer long before the advent of modern geotextiles. By the late 1960’s it was clear that the “floating” solutions that had been tried all suffered from similar problems of deformation or settlement, requiring costly resurfacing to restore shape and profile. With the advent of improved excavation techniques including hydraulic excavators it became easier and more economic to dig out all the peat, sidecasting it beside the roadworks. The resulting void was backfilled with locally won rockfill. This became the norm for new road construction in the area in recent decades. 3.2 Developments in the Maintenance of Existing Roads over Peat Up until about 15 years ago the options used for the maintenance of roads over deep peat in the Highlands were relatively limited. One was to dig out the section of failed road, preferably down to the hard, and rebuild it. High cost generally precluded this option. The other solution was to simply resurface the misshapen road. This could be more readily accommodated in annual budgets and provided a short term answer. Unfortunately, and almost inevitably, the increased deadweight resulted in further consolidation and a return of the problem within a few years if not months. It became increasingly recognized that other solutions must be tried, even at the risk of failure. Fortunately some of these had already been used and proved in other countries with similar deposits of peat. 16 In 1991 the Highland Regional Council used experience gained in Scandinavia to replace a sinking road on the A837 at Ledbeg in West Sutherland. This involved the excavation of a 200m section of road that had sunk badly. As if to demonstrate the failure of the traditional method of solving the problem it was found that no less that 1.45 m of bitumen macadam surfacing had been added to the road in its 30-year lifetime. This created a huge deadweight for the underling peat to carry. Below this pavement structure was a layer of chestnut paling fencing. This heavy pavement material was replaced with lightweight aggregate fill and capped with a new pavement construction. This has proved extremely successful, with the road holding up well after 12 years of service (Roadex 2001). In 2000 The Highland Council carried out rehabilitation works on a 1km section of the B876 where it crossed Killimster Moss, in Caithness. The problem here was settlement and cracking of a 60 year old reinforced concrete slab laid on top of peat 2 m to 5 m deep. Using information obtained under the ROADEX international exchange programme a Ground Penetration Radar survey was carried out by Roadscanners and a severe stripping defects of bituminous layers were detected around especially in the areas with failed concrete. The designed solution involved improving the drainage, removing the existing poor quality bitumen macadam overlay, sealing the concrete cracks and replacing it with a 150 mm thick steel reinforced dense polymer modified bitumen macadam pavement. Experience so far has been extremely positive (Roadex 2001, reference). More recently surcharging (overload embankment) has been used on the A839 and A837 in Sutherland to deal with problem sections over deep peat. This technique has been commonly used in Scandinavia. On the A839 at Raemore an offset widening exercise on a single track road 10 years earlier had resulted in gross tilting of the carriageway to some 10 %, creating a hazard to traffic. On the A837 at Benmore previous attempts to add surfacing to a sinking section had only exacerbated the problem, to the extent that the road surface was frequently below the water table, by up to 0.3 m in flood conditions. The surcharging technique in both situations involved loading the existing road embankments with fill 2 m deep and leaving them unsurfaced under traffic for 2-3 weeks. The surcharge material was then recovered, the embankment regulated with subbase and the pavement replaced. This surcharging has been successful in accelerating the consolidation of the underlying peat to the extent that a reasonable life before reshaping can be now be expected. 17 4 TYRE DISPOSAL: AN ENVIRONMENTAL CHALLENGE 4.1 The EC Directive The disposal of used tyres is a major environmental challenge to the international community. The UK alone needs to dispose of some 40 million tyres per annum of which about 25 % currently go to landfill. From July 2003 the EC Directive on the Landfill of Waste banned the dumping of whole tyres in landfill, with only limited exceptions. The use of shredded tyres in landfill will be restricted from 2006. The processes for beneficial disposal of tyres include: • • • • Reuse e.g. retreading (although the carcase will eventually end up in the waste stream) Mechanical treatment to reduce size e.g. baling, ripping, cutting, grinding Reclaim technologies e.g. rubber reclaim, devulcanisation As a fuel source e.g. cement kilns and energy generation The products arising from mechanical treatment are of most immediate interest from a civil engineering point of view. These have potential for replacing aggregate at a time when quarried materials are becoming more scarce and costly. These products are: • • Bales produced from whole tyres compressed and banded Cuts, Shreds and Chips: irregular pieces of used tyre with sizes greater than 300 mm in size, 50 mm-300 mm in size and 10 mm-50 mm in size respectively Northern Tyre Recycling (UK) are based in the Scottish Highlands and have imported a portable truck tyre baler from the US. Using this NTR have baled some 390,000 tyres in the last two years and have supplied bales to a number of civil engineering applications such as haul roads, slope and river bank stabilisation. 18 4.2 Production of Tyre Bales The tyre bales are produced by Northern Tyre Recycling at their depot outside Inverness. However the mobility of their unit means that it can easily be towed to a used tyre stockpile to minimise transport costs. This is particularly attractive where stockpiles are at a remote location or where a suitable end use for the bales can be identified locally. The unit has already visited some of the Scottish Islands. The number of tyres in each block varies, depending on the sizes of tyres being compressed, as these can include all types from small car tyres to 1.5m outside diameter earthmoving plant and tractor tyres. Between 100 and 120 tyres are normally compressed into a single bale. The tyres are fed by hand into a 1.5 m by 1.2 m chamber and compressed by hydraulic rams (figure 4). Before release of compression the bales are tied with 5No bands of 9 gauge high tensile galvanized high tensile wire round their shortest dimension. The bales, weighing about 0.85 tonne each, are removed by forklift truck to storage. Figure 4. Tyre Bale production at Northern Tyre Recycling site. 19 4.3 Properties of the Tyre Bale Product The standard bale size is a nominal box shaped 1.5 x 1.2 x 0.85 (1.53 m3) but experience on the project showed that the effective size was slightly greater at 1.5 x 1.5 x 0.85, ie in plan they appeared square rather than rectangular. The density of each bale obviously depends on the number and type of tyres compressed in to it. The baling machine manufacturer quotes 250 to 600 kg/m3. HR Wallingford Ltd are currently engaged on a research project on the sustainable use of post-consumer tyres in port, coastal and river engineering. As part of this they tested the properties of two bales provided by NTR, with the results shown in Table 1. Table 1. Properties of tyre bales produced by NTR (with acknowledgement to HR Wallingford). Property Total Volume (m3) Porosity (%) Bulk Density (Kg/m3) Weight of Bale (Kg) Volume of tyre material (m3) Solids as % of whole % of voids sealed Value 1.09 – 1.25 50 – 56 580 – 655 712.5 – 725 0.54 – 0.55 0.44 – 0.50 10 - 15 An important outcome of this information is that the true volume of the bale, measured wrapped, averages 1.17 m3, considerably less than the nominal volume of 1.53 m3. This is clearly as a result of the bales not being a true box shape but having curved convex ends, as can be seen in Figure 5. This means that, when bales are stacked together in an embankment voids round the outside of the bale are likely to comprise 25 % of the total volume. Note that this does not include the voids within the bale itself which has a porosity of over 50 %. The bulk density of the NTR bales as measured (average 618 kg/m3) is rather more than the 250 - 600 kg/m3 quoted by the baling machine manufacturer. However if it is recalculated on the basis of the nominal volume rather than the actual volume the figure is 470 kg/m3. The realistic value for a bale embankment, without the voids filled but compressed under its own deadweight, would appear to be somewhere in between, say 550 kg/m3. A further reassuring outcome of the HR Wallingford research is that the bales do not have a problem with buoyancy. At the time of the B871 project the only evidence on this was anecdotal, NTR having placed a bale in the sea which reportedly sank. Given that the specific gravity of natural rubber is 0.91 and the potential for air being trapped in a bale, there was legitimate concern about this 20 issue. However the Wallingford research has shown that the specific gravity of tyre material is in fact greater than unity as it comprises materials other than rubber, including 15 – 25 % by weight metal. Furthermore only 10 – 15 % of the tyre bale voids were found to be sealed. Figure 5. A stockpile of tyre bales, showing the voids caused by convex ends. Table 2. shows a comparison with other types of compacted lightweight fills, with gravel comparison: Table 2. Unit weighs of materials used on road structures resting on peat. Product Tyre Bales Tyre Shreds Lightweight Aggregate Expanded Polystyrene Gravel Unit Weight (kg/cum) 250-600 500-600 300-600 15-30 1900-2100 Apart from low weight tyre bales have a number of other useful engineering properties, including the high porosity mentioned above, high permeability and low thermal conductivity. 21 4.4 Cost of Tyre Bales The basic cost of a bale includes: • • • • The cost of acquiring the waste tyres, (which may be negative) The cost of tyre collection, bale manufacture and storage The cost of delivery to the end user Profits and overheads, including compliance with relevant waste disposal regulations With the banning of landfill, the problem of used tyre disposal is a pressing one for the new tyre supplier who is likely to have to pay to make arrangements to dispose of the old tyre. This cost of will obviously be passed on to the consumer and will become part of the essential income stream to the baler. At present in Scotland, some tyre suppliers have a clearly identified charge to the consumer of £0.50-£1.00 for disposal of each carcase, others make allowance in their overall prices. The current ex works cost of a tyre bale is approximately £10-15 (table 3), which works out at £5-10 /m3. Table 3. Ex works costs for typical road materials used on roads resting on peat. Product Tyre Bales Tyre Shreds Lightweight Aggregate Expanded Polystyrene Gravel Ex Works Cost (£/cum) 5 - 10 10 - 20 40 - 60 50 - 150 8 - 12 These prices must be viewed as only indicative as they will vary significantly depending the location and size of project. Haulage costs to site have also to be taken into account. The cost of gravel includes the Aggregate Levy, an environmental tax on newly excavated materials to encourage recycling. At time of writing this is £1.60 per tonne. It can be seen from these figures that the tyre bale product is very competitively priced, particularly when its lightweight is taken into account. Whether that remains the case is likely to depend on: • • • • Market forces once the effects of the EC Directive bed down The range of beneficial uses that can be found for tyre bales Demand for the product Any increase in the Aggregates Levy. 22 4.5 The Legal Position The Scottish Environmental Protection Agency (SEPA) is the regulatory authority in Scotland for waste management and licensing. When approached in 2001, SEPA took a constructive view on the production and use of tyre bales. They considered the production process was eligible to be registered for an Exemption from the Waste management Licensing Regulations. At the time of construction there appeared to be no requirement for the Council to seek any special exemption or license for the use of the tyre bale product in the embankment. 23 5 DESIGN OF THE B871 TYRE BALE PROJECT 5.1 Extent of the Project Having identified the problem section of the B871 near Loch Rosail The Highland Council designed a scheme to allow for the removal of the existing sunken road construction over the peat hollow and its replacement with a lightweight embankment of tyre bales. It was decided to raise the design profile by up to 1m above the existing road to keep the surface above the water table, allowing for some eventual settlement. The overall length of the regrading scheme was 100 m with tyre bales being used over the central 55 m. 5.2 Ground Investigation The site investigations were made in order to get information about the existing road structures and thickness of the peat deposit. A good indication of the existing road construction was obtained from the Roadscanners ground penetrating radar analysis (see figure 3). Because of the narrowness of the road, and the weakness of its structure and the underlying peat the excavation of trial pits was ruled out as being likely to seriously damage the road. Peat probes were taken adjacent to the road and they indicated a depth to the hard of up to 6.5 m. Figure 4. provides information about peat depth in the area. Loch Rosail Tyre Bale Trial - Peat Depth (m) 10 8 6 4 2 0 -2 -4 -6 -8 -10 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 -1.4 -1.6 -1.8 -2 -2.1 -2.2 -2.4 -2.6 -2.8 -3 -3.2 -3.4 -3.6 -3.8 -4 -4.2 -4.4 -4.6 -4.8 -5 -5.2 -5.4 -5.6 -5.8 -6 -6.2 -6.4 -6.6 Figure 6. Peat thickness in Loch Rosail test area. The Tyre Bale trial embankment area is –4.5 - + 4.5 m (black lines). 24 5.3 Design Considerations The design of the replacement embankment assumed a tyre bale density of 550 kg/m3 compared to 2000 kg/m3 for the 1.3 m deep existing road construction being replaced. The proposed 450 mm thick road and verge construction was also assumed to have a density of 2000 kg/m3. This indicated that, despite raising the road profile a reduction in the embankment weight per square meter of about 30 % could be expected. The design assumed some 320 tyre bales would be required, placed in two layers each 0.85 m thick. The upper layer would be 5 bales wide and the lower 6 bales wide, creating a staggered joint between the bales in the different layers in the transverse direction. Consideration was given to staggering the joints in the longitudinal direction but this was ruled out as it would make the installation of rods to monitor deep deflection extremely difficult. For simplicity the transverse rows of bales were therefore to be laid directly one on top of the other. Figures 7 and 8 provide longitudinal section and cross section CAD drawings about the object. As infill to the interstices and any gaps between the bales 110 m3 lightweight aggregate was specified. This was available from Optiroc ExClay Ltd at a reasonable cost, being surplus from an earlier contract. The whole of the bale embankment was to be wrapped in a lightweight 95 g/m2 Loktrak geotextile fabric. Figure 7. Longitudinal section showing tyre bale layers (CAD drawing by Gary Smith, Highland Council) 25 Figure 8. Cross section A- A in Loch Rosail tyre bale site (CAD drawing by Gary Smith, Highland Council. 26 6 CONSTRUCTION PROCESS 6.1 Bypass Road Construction The Council held a meeting at Kinbrace to explain the proposals to the local community who expressed interest and support for the project in principle but had concerns about the possibility of the existing road being closed during construction. Because of the remoteness of the area emergency vehicles might have to make a 90km detour round any closure. The Council gave an undertaking not to close the road and engaged plant and labour local contractor Edward Mackay Ltd of Brora, a firm with considerable experience in the construction of roads on peat. Being a single track road the first matter to be addressed was how to carry out the works whilst keeping traffic moving. Experience has shown that if a tracked machine is driven carelessly on to weak moorland such as this it is easy for it to break through the fragile surface. Timber sleeper mattresses can be used to spread the machine load but they are not infallible. The fluidity of the 6 m deep peat in this situation was such that if a machine did sink through, it would be a major earthmoving task to extricate it. The contractor therefore decided to keep the construction plant on the line of the existing road where the underlying peat would have greatest strength. The moorland beside the road formed part of a Site of Special Scientific Interest in relation to its environmental value and the approval of Scottish Natural Heritage was required for any works required off the existing road. They recognized the practical difficulties of construction and were cooperative about the location of a temporary bypass road, requiring only that it be removed entirely at the end of its use. The contractor started by building the temporary bypass some 120 m long across the moorland parallel to but 10 m distant from the existing road. This bypass was constructed of 450 mm of as dug rockfill on top of the geotextile fabric separation layer laid directly on the heather clad surface. The bypass road was subject to a 7.5 tonne weight restriction but is soon became apparent that the underlying peat was so fluid that it was moving both laterally and downwards under the deadweight of the fill alone. By the end of the 3 weeks of the contract parts of the bypass road had sunk by up to 1 m, and was flooded much as the original road had been. 27 Figure 9. Bypass road had rapid settlement during the construction project. 6.2 Handling of Tyre Bales An immediate problem to be solved was that the tyre bales were more difficult to handle that expected. They did not have specific lifting points so initially lifting chains were used, hooked in to the rim bead of a tyre at each end of the bale. However because of the high compression of the tyres and the variation in their size this was not always easy and was time consuming. A fabric sling was obtained but the only place it could be secured was through the tie wires round the bales. This was tried with initial success until one of the bales burst open and its tyres spilt out. This was an instructive mishap in that, contrary to what might be expected, the tyres did not spring violently back to shape. This supported anecdotal reports that baled tyres do lose some of their “memory” when in a compressed state and spring back only slowly when released. The large pile of tyres released provided proof, if any were needed, of the space saving benefits of the compressed product. It was clear that a better method of lifting the bales had to be found. NTR had recommended that a logging grab was the best means to use, and in fact the bales had been delivered to site by a timber wagon, fitted with standard lifting gear including a 360 degree swivelling grab. Unfortunately because of limitations of reach this vehicle could not be used at the working face so an additional crawler excavator had to be requisitioned fitted with a similar grab. This proved the perfect tool for lifting the bales, preventing damage to the tying bands and enabling them to be rotated into place without manual intervention. 28 Figure 10. Machinery used in building Tyre Bale structure. 6.3 Construction Sequence Once the bale handling problem was resolved, work progressed in an efficient and methodical manner as follows: • The forward excavator dug to formation level, approximately 1.5 m below the existing road, over a bay length of 5 m. The material was removed to tip by dumper. • Operatives placed a strip of geotextile across the cross section, leaving surplus for wrapping over the bales. • Grab machine at rear placed lower row of tyre blocks in place, with assistance as required from forward machine to push them tightly into place. • Lightweight fill was dumped over bales and allowed to percolate the interstices. • The second (upper) layer of blocks was put in place and dressed off with lightweight fill before operatives gathered loose geotextile to complete wrapping of bale group, with overlap on top. 29 • The rear excavator spread a 3 m wide layer of fine rockfill over the geotextile, to provide a working platform for moving forward to the next bay. The construction and capping of the 50 m long tyre bale embankment, utilizing some 350 bales, took two weeks of the three week contract period to complete. 6.4 Installation of Settlement Monitoring rods In order to assess the extent of any movement of the bale embankment monitoring rods were installed at approximately 10 m centres in each verge 1m from the edge of the road. These rods comprised round steel bars sufficiently long to protrude above the final verge. They were welded at the lower end to a square steel plate. The rods were installed in the appropriate lateral position, at a convenient longitudinal position to suit a butt joint in the tyre bales. The base plate was placed on the underlying geotextile, ensuring that any settlement of the bale would draw down the rod. In order to provide additional security of monitoring and in particular to determine if there was any significant separation or compression of the two bale layers, a further 4No monitoring tubes were installed. These comprised a steel tube welded to a square steel base plate, the latter being drilled with a hole concentric with the tube. These tubes were threaded over the monitoring rods, after installation of the lower bale layer, so that the base plate could be trapped between the two layers. The tubes were shorter than the rods so that the rod protruded above the tube, enabling levels to be taken on both. There was no particular difficulty with installing these devices although there was a tendency for them to be damaged by careless machine operation. 30 Figure 11. Monitoring steel rods were placed on the tyre bale joints both sides of the road. Photo presents also the filling technique with lightweight gravel. Monitoring roads can be seen on right joint. Smaller red rods are installed on the bottom of the bales and black tube rods between the two tyre bale layers. 6.5 Culvert Installation Although the roadside drainage was by open ditch along each side of the road, a 300 mm diameter rigid plastic pipe was installed to provide a measure of balance if cross road drainage became necessary in the future. This was conveniently placed at a butt joint in the tyre bales and surrounded by lightweight fill. 6.6 Completion of Pavement Structure As soon as the bale embankment was installed the rockfill layer was topped up to 250 mm deep and dressed off to level. A nominal layer of A252 welded reinforcing mesh (8 mm bars at 200 mm centres) was included in this layer. It was considered that this mesh would provide some additional strength to the capping layer, helping to tie it together during the significant bedding in movements that could be expected. This technique has been used in Finland in similar weak subsoil situations. 31 An excavator then spread a 100 mm layer of Type1 sub-base on top of the rockfill to provide a running surface. This enabled the road to be reopened to public traffic. Work then moved to the removal of the bypass road, the rockfill used in its construction being recovered and placed as verge construction on the main road. Subsequently the verges were further dressed off with peat. Figure 12. Unbound structures over tyre bales. Steel reinforcement is installed in the sub base. 6.7 Subsequent Works After 3 months of traffic the Type1 sub-base road surface was becoming increasingly loose and a 50 mm thick layer of fine sand/gravel was added through a paving machine to bind the running surface, particularly for the heavy timber traffic that started that month. To further bind and waterproof the surface two layers of surface dressing were applied in July 2003, using 10 mm chippings and 2 litres/m2 bitumen spray on each layer. 32 Figure 12. Loch Rosail tyre bale structure after completion of pavement. 33 7 RESULTS OF MONITORING 7.1 Embankment Settlement Monitoring of the embankment settlement commenced on 11 December 2002, with leveling of the five rods and three tubes installed by that date. Further leveling of these was carried out two days later, with the first complete leveling of the total 12 rods and 4 tubes being carried out when the road was opened on 19 December 2002. Placing of rockfill verging was taking place at that time. Additional leveling was carried out on 6 January 2003, following which the contractor completed the final verging. The leveling was repeated at approximately monthly intervals thereafter, with the latest results being taken on 10th July 2003. Figure 13. presents a contour map of settlements measured in the Tyre Bale trial site untill April 8th. Figure shows that the highest settlement was measured on the left side of the embankment at 85 m. When comparing this to peat thickness info (see figure 6) this was quite surprising because the peat was thicker in the right side of the road. In general the correlation between measured settlements and peat thickness was quite good, however. It is clear from this graph that the settlement of the left hand side is much greater than that of the right, in other words the new embankment was first tilting to the left. This can also be seen from the figure 14, which compares the rate and extent of settlement of the left and right hand pins at chainage 85 m. This tilting is still slowly continuing, which can be seen in figure 15, which compares the settlement speeds on right and left side of the embankment during the time periods after the construction. The settlement rate on the left sides are still slightly bigger than on the right. However after April 8th 2003 the settlement rate has been less than 0.5 mm/day, which means that during the next year the cumulative settlements will be much less than 15 cm. 34 Loch Rosail Tyre Bail Trial - Cumulative Settlements 080403 -0.06 -0.08 -0.1 -0.12 4 2 0 -2 -4 50 -0.14 -0.16 -0.18 -0.2 -0.22 -0.24 -0.26 -0.28 -0.3 55 60 65 70 75 80 85 90 95 100 105 110 -0.32 -0.34 -0.36 Figure 13. Countour map of cumulative settlement in Tyre Bale trial structure in April 08, 2003. The biggest settlement were recorded at 85 m on the left side if the road embankment. 11-Sep 11-Aug 11-Jul 11-Jun 11-May 11-Apr 11-Mar 11-Feb 11-Jan 11-Dec Cumulative Settlement Graph Chainage 85 Settlement (m) 0.000 0.050 ch 85 left 0.100 ch 85 right 0.150 0.200 0.250 0.300 0.350 0.400 0.450 Figure 14. Cumulative settlements at chainage 85 m in Loch Rosail tyre bale trial site. 35 Average Settlement Rate per Day 5.00 4.50 Rate (mm/day) 4.00 Left 3.50 Right 3.00 2.50 2.00 1.50 1.00 0.50 19-Sep 19-Aug 19-Jul 19-Jun 19-May 19-Apr 19-Mar 19-Feb 19-Jan 19-Dec 0.00 Figure 15. Settlement rate in test site during time period a) construction – January 28th 2003, b) January 28th – April 8th and c) April 8th – July 9th. 7.2 Bale Compression There is little difference between the settlements of the 4 tubes and their associated rods, consistently in the range 0-10 mm. This indicates that there has been no great compression or separation of the bale layers. The only exception was an isolated movement difference of 37 mm recorded at Chainage 75 m left between 19 December 2002 and 6 January 2003. This suggested compression of the lower bale by that amount. However given the consistency of the other results it is thought this may have been a rogue value indicating the bedding down of the monitoring tube base plate after placing of the rockfill verging, rather than true bale compression. 7.3 Culvert Settlement A remarkable feature has been the increasing curvature of the culvert pipe. Within a month of installation it was noticed that water was flowing into both ends of the pipe, indicating that the surface water was leaking in to the tyre bale mass. It was clear that the pipe had bowed so much that the central slip joint must have pulled. Eight months later one end of the pipe rises steeply from the ditch showing the extent of the curvature. The other end of the pipe is no longer visible. 36 Figure 15. Deflection of culvert outlet. 7.4 Assessment of Settlement It is clear from the monitoring that the embankment has settled by up to 0.4 m over seven months. However the rate of settlement has reduced steadily and it is reasonable to assume that it is the normal consolidation of the underlying peat. If a conventional rockfill embankment of equal dimensions but three times the weight had been installed, the situation would have been considerably worse. Of interest is the clear tendency for the embankment to slightly tilt to the left. Given that the new embankment is centered on the old road this sort of differential consolidation was not expected. The most likely answer appears to lie in the construction of the temporary bypass road on the right hand side of the new road. Immediately the bypass road was constructed it started to sink and cracks were noticed in the peat between the bypass road and the existing road suggesting that the peat was bulging and moving under the compressive load of the bypass road. It is concluded that this had the effect of pre consolidating and strengthening the peat on the right hand side of the new embankment, over the three weeks the bypass road was in place. 37 Another explanation can be that a better drainage system was located on the left side of the road where there were ditches and also the hill slope was to the left. This better drainage in the left side allowed also faster settlement. The same phenomenon could be seen also in the temporary road that had faster settlement on the left side (see figure 9). 7.5 Settlement Problem on April 2003 On 25 April it became clear that two major sharp transverse settlements were forming on the road near chainage 60 and 70 m (figure 16). Significant vertical movement of the road surface could be seen during the passage of laden trucks although, apart from the rutting damage, the road apparently recovered to its original level when the vehicle had passed. A few days later the road surface was excavated at the position of the rut near chainage 60 m. It was discovered that the problem lay in a lack of shear resistance where joints in the steel fabric reinforcement (2.4 m centres) coincided with a joint in the wrapped bale mass (1.5 m centres). Because of the shearing movement under traffic load road material flowed between the tyre bales and this resulted a sharp settlement on the road surface. This was repaired by stripping off the capping material over a 5 m section above the joint and placing two additional sheets of steel mesh to provide additional strength. The capping was reinstated and the repair has since worked well. The cause of the rut at Chainage 70 was less clear but may have been related to the adjacent culvert, which has suffered substantial movement as described in Section 7.3 above. The surface over this rut was regraded and has since performed satisfactorily. 38 Figure 16. A sharp transverse settlement in late April 2003 at chainage 70 m. 7.6 Settlement Problem September 2003 In September 2003 it became apparent that a regular pattern of settlement was occurring which was clearly detectable when driving along the road. On visiting the site after light rain this could be seen from the pattern of pools of water retained on the surface. This is shown on Figure 17. On measuring the distance between 11 of these depressions it was found that they varied between 1.4 m and 1.7 m apart, with an average of 1.58 m. This is remarkably close to the 1.5 m nominal dimension of the tyre bales in plan. On measuring the distance between the next 5 depressions outwith the bale embankment, the average dimension was noticeably higher at 2.0 m. 39 Figure 17. Pools of water at regular intervals on road surface 30 September 2003. The obvious conclusion is that the surface irregularity is being caused by settlement at the joints between the rows of tyre bales. Unlike the April settlement problem at Chainage 60 it does not appear to be connected to the spacing of the mesh reinforcement (2.4 m sheet size). Without further research it is not clear what the exact cause is but it is believed to be one or a combination of: • • • • the lightweight fill slipping down the joints between the bales groundwater pumping up the joints, weakening the road structure locally the difference in compressibility between the infill and the bales the dynamic movement of the bale structure. Unfortunately this is one area where the bales are not behaving as predictably as a conventional fill embankment. With the benefit of hindsight it would have been better to have taken extra steps to ensure good interlock and load distribution between the blocks. Options would have been: • • • additional reinforcement between and below the bales an alternative infill material greater cover over the bales. 40 At the time of writing The Highland Council has not decided on the best course of remedial action. Roadscanners have suggested that a detailed Ground Penetrating Radar (GPR) survey of the embankment is likely to give valuable information on the relative positions of the capping fill, bale layers, lightweight aggregate infill, underlying peat and any voids between these components. This will be carried out in the near future. Excavation into the bale mass to retrospectively install low level reinforcement is unlikely to be realistic. Depending on the results of the GPR survey it is expected that work to enhance the live load distribution properties of the embankment may include: • • Installing additional steel reinforcing mesh in the capping layer Increasing the cover to the bales by adding lightweight fill It is clearly undesirable to add significant extra weight to the embankment so some of the existing capping layer and running surface may have to be stripped off and replaced at a higher level. Any work of this type will pose practical problems given the single track nature of the road and the need to keep traffic running. 41 8 LESSONS LEARNED FROM THE PROJECT 8.1 General The B871 tyre bale embankment has now been in operation for nine months. The experience gained from its construction and maintenance so far suggests the following are issues to be taken into account in considering the use of tyre bales in similar and other civil engineering projects. 8.2 Ground Investigation It goes without saying that a good ground investigation is essential to any civil engineering project, and this project was no exception. A frequent grid of peat probes around the existing road indicated soft peat consistently about 6m in depth. The Roadscanners Ground Penetrating Radar run along the centre of the road gave an excellent picture of the existing road construction and correctly predicted the 1.3 m depth of construction below the existing road. What was not anticipated was the fact that the road construction box was cut off vertically at the edge of the road running surface. There was no road construction of any sort under the verge and there was none of the lateral dispersion of the original gravel foundation that might have been expected. With the benefit of hindsight it explained the clear vertical movement crack which ran along each side of the road, between the running surface and the verge, prior to work starting. It will be recalled that the project design assumed that heavy road construction materials were being replaced with lighter weight tyre bales, resulting in a 30 % saving in weight. In reality this was only true over the narrow 2.8 m width of the existing road with the remainder of the bale embankment replacing only saturated peat. The predicted saving in deadweight will not have been achieved but the spread of dead and live loads over the greater width of the new embankment is clearly working satisfactorily in practice. 8.3 Handling The selection of appropriate plant for handling the bales is essential for efficient installation and the rotating grab proved invaluable on this project. On a smaller project it might be helpful if lifting points were provided on the bales so that conventional lifting equipment could be used. Northern Tyre Recycling (UK) Ltd can now supply bales of this type. 42 8.4 Bale dimensions It is important to recognize that tyre bales do not have a fixed geometry like bricks or concrete blocks. The sides and ends of the bales are slightly convex making them difficult to measure exactly and this variability must be allowed for in any design. This did not cause major problems on the B871 but where close tolerances are needed the more generous the capping layer the easier it will be to correct level differences. Figure 18. Because of tyre bale dimensions there was a tendency that the bales became easily concave. 8.5 Joints between Bales The B871 design allowed for a stagger in the transverse joints between the bales in the two layers. With the benefit of hindsight it would have been better to also have had a stagger in the longitudinal direction. This might be slightly less convenient from a construction point of view, requiring a stepped working face and plant with a slightly greater reach. However it would offer considerably enhanced shearing resistance and load distribution, and would have helped prevent the problems experienced in April and possibly in September. Because of this it is recommended that staggered joints be used wherever possible in weak ground conditions or under traffic. 43 The plan shown in figure 19. shows a bond pattern that gives good interlock but uses an extra bale every second row. Whilst it would be easy to build this pattern in rows up the page, it might be difficult to build left to right as this would involve threading bales into the gaps between those previously installed. The practicalities of this are worthy of investigation on another project, as would any difficulties of offsetting of the upper layer. Figure 19. A proposed system for getting better interlock for tyre bales. 8.6 Infill between bales Lightweight aggregate fill was used to fill the interstices between the bales prior to them being wrapped in geotextile (see figure 18). This material had the advantage of being clean and easy to use and obviously offers significant weight savings compared to using conventional fine aggregate. This was attractive in the extremely weak ground conditions on the B871 but it is costly and a design judgment will have to be made in each case to see if the benefits compensate for this. Angular crushed rock chippings, say 10-25 mm, will be a cheaper if heavier option and will be likely to offer a good frictional bond between the blocks. Sand infill is understood to have been used in the USA, washed into the interstices by water jet. 8.7 Geotextile Fabric It is not clear how much the geotextile fabric contributes to the overall strength of the tyre bale embankment in a situation like this where the settlements are high. The movements are such that, if the geotextile has not torn at the basal level, it may well have slipped at the laps. The geotextile did provide a useful separation layer, preventing contamination of the bales and the lightweight infill. In addition it provided an invaluable working surface when placed on the underlying soft peat, without which operatives would have sunk up to their knees. 44 The project started with the bales being wrapped in individual transverse rows i.e. the lap in the wrapping fabric was on top of the bale and transverse to the road. This method of wrapping gave no continuity of fabric across the joint and is felt to have been a significant contributory factor to the settlement experienced in April. Later in the project the bales were wrapped with the fabric lapped along the centre of the road, giving better continuity of the fabric. This is the method that would be recommended. In weak ground conditions such as here, generous laps of should be allowed to prevent loss of fines from capping or infill, particularly where there is a risk of pumping occurring. Figure 20. An example of possibly too short geofabric overlap. Even though a new geofabric will be place on the top of old fabric, there is a risk that embankment settlement and tyre bale movements due to traffic load may cause that subgrade soil can squeeze up to bale joints. This photo shows also that the edges of the embankment were resting on virgin peat and old road construction was located only in the middle. 45 8.8 Steel Mesh Reinforcement It is considered that the nominal steel mesh reinforcement was an extremely valuable inclusion in the design, particularly in view of the high movements expected here. The steel mesh might have given slightly better support if the installation depth had been deeper than 10 – 15 cm. Ideal depth would have been about 25 cm from the surface. Because of the tyre bale movements and the settlement problems in April and September, steel mesh might have been a good structure on the bottom and intermediate level as well as on the top of bales to prevent them moving against each other. As mentioned earlier this was based on experience in Finland where unprotected mesh is used. With high levels of the use in the UK of road salt for deicing the life of unprotected mesh must be considered although this has not been a problem in Finland. Given the experimental nature of the B871 embankment this is not a major issue but if there is a concern galvanised or epoxy coated mesh can be considered. 8.9 Laps in Steel Mesh Reinforcement The Finnish experience mentioned above suggests that it is best to ensure transverse continuity of the mesh laid on the road embankment, to prevent the road breaking its back. In accordance with this principle the sheets were laid on the B871 with no attempt to lap or join them longitudinally. The failure in April suggests a weakness in this approach when using tyre bales, particularly where joints in the tyre bales can coincide with mesh joints. It is recommended that further work be done to see if this difficulty can be overcome by staggering the bale joints as suggested above, or by lapping the mesh in some manner. 8.10 Installation of Services Excavation through a tyre bale embankment would be a major task, not to be undertaken lightly. If pipes and services require to be installed it is recommended that they are placed outwith the tyre matrix as access for maintenance would otherwise be extremely difficult. Depending on the circumstances this can be achieved by increasing the cover over the bales to provide sufficient depth to carry any services. The same difficulties would apply to the installation of roadside furniture such as traffic signs, safety fences, lamp standards etc. 46 8.11 Marking and recording of Tyre Bale embankments It is recommended that the location and extent of any tyre bale embankment should be properly recorded and marked on site to ensure that it is not accidentally damaged during routine maintenance such as ditching operations. 8.12 Surface finishes and tolerances The B871 embankment is highly flexible because of the weakness of the underlying peat. It is therefore not possible do draw any firm conclusions on the ability of a tyre bale embankment to carry hard surfacing or urban landscaping such as paviors, kerbs, slab paving etc. It is recommended that further trials should be done on this aspect, using a bale embankment founded on material other than weak peat. Similarly the B871 has not been built to high tolerances, and the road is of such a character that settlements and movements under traffic can be accommodated. If bales are to be used under a high speed road requiring high surface tolerances it would be best to do further trials or to research their use in other countries. This would establish if high tolerance surfacing can be laid and maintained, and what the minimum capping requirements are in such a situation. 8.13 Bale Tie Wires The bale tie wires stood up well to the forces involved in handling and placing, apart from the mishap when the single bale burst. Galvanised fencing wire can have a life of over 30 years but it is not known what life can be predicted for the tie wires underground and possibly under the action of deicing salt. This may not be relevant in the long term if as is claimed the tyres do not rebound to their original shape. 8.14 Chemical effects Research on the long term effects of leachate from tyres reaching groundwater is ongoing in a number of countries. It is understood that research so far indicates that the leachate is unlikely to be a serious problem. No work on this aspect has been undertaken on the B871 project. 47 8.15 Porosity and Permeability of Tyre Bales The porosity of tyre bales and bale embankments were discussed in Section 4.3 above when it was calculated that some 25% of the embankment was likely to be voids between the bales. The theoretical volume of the B871 embankment was 500 m3, suggesting 125 m3 would be voids. It is interesting to note that the 110 m3 of lightweight infill provided was fully utilised on the project, suggesting that, despite the mobility of lightweight fill, some voids may have remained unfilled. This may not be unconnected with some of the settlement difficulties discussed above. Whilst completely infilling the voids may be difficult it must be recognised that the high porosity of the bales themselves, taken with the inevitable voids round about them create an attractive product in terms of drainage and water retention capacity. The figures suggest that a tyre bale embankment will have a porosity of over 60 % and potentially even more if it is loosely built for that purpose. Taken together with the good permeability of the bales themselves this suggests considerable potential for use in sustainable land drainage and retention schemes. Further research will be required to determine the effective properties in service and to identify any problems that might arise. 8.16 Developments in the Legal Position It was stated earlier that The Scottish Environmental Protection Agency (SEPA) had taken a constructive position on the production and use of tyre bales at the time they were approached in 2001. However, more recently, it is understood that the Environment Agency (the regulatory body in England) has taken a more cautious view. This follows recent rulings by the European Court that throw some doubt on exactly at what point in law tyres going through a baling process cease to become waste but become a recycled product. Until the legal position becomes clearer it is recommended that detailed discussion with the regulatory body is essential at the outset of any project involving the use of tyre bales. There is an international dimension to this problem and from an engineering point of view it is vital that the position is clarified for all concerned. If tyre bales are to become an established engineering product, ways must be found to simplify their use within the constraints of the law and sound environmental management. 48 9 POSSIBLE FUTURE DEVELOPMENTS Tyre bales have already been used in a number of civil engineering applications in the UK, including haul road construction, drainage and slope stabilisation. The major project currently being undertaken by HR Wallingford to evaluate the use of tyre bales as void fillers in sea defence works and river bank protection has also been mentioned above and the full results of this are awaited with interest. The previous Section suggested a number of issues that would benefit from further investigation or trial and it is to be hoped that the knowledge gained from such schemes is widely published. Looking to the future it is interesting to note that an embankment the size of a football pitch and 2 m in depth would need sufficient tyre bales to consume 10 % of the tyres currently dumped in landfill in the UK each year. Large scale projects of this type might be: • • • • • Embankments carrying roads across flood plains, wetland or peat moorland Raising and drainage of low lying agricultural land Land reclamation Sustainable drainage schemes using the permeability and storage capacity of tyre bales Infill to create public amenity land or large scale parking and utilizing the above sustainable drainge properties It is difficult to predict how quickly such large scale schemes can develop until the tyre bale market becomes more mature. In the meantime it must be remembered that this is an innovative product in the UK and it may be best to advance its use in civil engineering by pressing on with small to medium scale trials, such as the B871 project, to build up confidence in a gradual but sustainable way. 49 10 CONCLUSION The B871 Tyre Bale Project has now been in operation for nine months and has successfully dealt with public traffic, including 30,000 tonnes of timber traffic. It has shown that it is possible to construct a lightweight road embankment over exceptionally soft peat using recycled tyre bales. Remarkably, this small project has found a new use for about 40,000 used tyres, 0.4 % of the annual UK tyre throughput to landfill. A number of practical lessons have been learned from the project and these are detailed above, together with suggestions as to further trials and uses in embankments. The high porosity of a bale embankment has also been identified as a key property which may have considerable potential for application in sustainable drainage schemes. Tyre bales are an innovative product in the UK and it is recommended that it is best to advance their use in civil engineering by carrying out well documented small to medium scale trials, such as the B871 project, to build up confidence in a gradual but sustainable way. In particular it is recommended that research is carried out on: • • • • • Alternative interlock arrangements of tyre bales Alternative types of infill material Minimum depths of cover for satisfactory performance under heavy loads Reinforcement of bales at intermediate and lower levels on soft ground Drainage and water retention properties in service 50 BIBLIOGRAPHY Carlsten, P. 1988. Peat, Geotechnical Properties and Uptodate Methods of Design and Construction. State-of-the-Art-Report. Varia 215. Statens Geotekniska Institut, Linköping Sweden, 35 p. CEN Workshop Agreement CWA 14243: Post-consumer tyre materials and applications (FINAL 18.3.02) Evaluation of the Impact of Timber Transportation on Roads: B871 Kinbrace to Syre and B873 South of Syre; Timo Saarenketo and Tomi Herronen; Roadscanners Oy, 2001. Roadex Multimedia CD rom www.roadex.org Road Construction over Peat; A report of a Winston Churchill Travelling Fellowship; Ron Munro, 1990. Road rehabilitation of B876 Killimster Moss, Caithness; CR Guest; Highways and Transportation, March 2002. Saarenketo, Timo; Hietala, Kari; Salmi, Tiina 1992. GPR applications in geotechnical investigations of peat for road survey purposes. In: Hänninen, P., Autio, S. (eds.) Fourth international conference on ground penetrating radar, June 8-13, 1992, Rovaniemi, Finland. Geological Survey of Finland. Special Paper 16, 293-305. Saarenketo, T. 2001. GPR Based Road Analysis – a Cost Effective Tool for Road Rehabilitation – Case History from Highway 21, Finland. In Proceeding of 20th ARRB Conference, Melbourne, Australia 19-21 March, 19 p. Saarenketo, Timo. 2002. ROADEX – low volume road condition management in EY Northern Periphery Area. Finncontact. Vol. 10 / No. 2. July 2002, p. 7-8. Saari, J. and Saarenketo, T. 2002. Road Condition Management of Low Traffic Volumer Roads in the Northern Periphery. A state-of-the-art report. www.roadex.org 51 APPENDIX 1 Figure 1. Photo showing Northern Tyre Disposals Ltd (now Northern Tyre Recycling UK Ltd) mobile tyre bale press. Figure 2. Dennis Scott with tractor tyre in open press chamber. 52 Figure 3. Tyre chamber filled with 30 tyres, ready for for first press. Figure 4. Bale compressed, doors open, tie wires being inserted. 53 Figure 5. Tie wires now looped, ready for pressure release. Figure 6. Pressure off, bale ready for offloading to stockpile. 54 Figure 7. Showing bales in stockpile. Note voids between bales. Figure 8. Another view of stockpiled bales, showing even greater voiding. Visually the bales appear to be more rectangular on the tied faces. The untied faces, which were at the ends of the compression chamber exhibit more of the curvature of the original tyres. 55 APPENDIX 2 Figure 1. Existing B871 at site prior to start. Note subsidence, surface slippage and edge failure. Figure 2. Showing the Railside Loading Bank at Kinbrace where timber has to go. 56 Figure 3. Work starts with construction of bypass road. Figure 4. First bales go in, on top of geotextile. 57 Figure 5. Second Row, showing monitoring rods in place below bale layer. Figure 6. Bales delivered to site on timber truck. 58 Figure 7. Transition wedge between single and double layers formed of lightweight fill (covered by geotextile. Figure 8. Monitoring tubes formed from 50dia tube, for placing over rods. 59 Figure 9. Timber grab on crawler excavator placing bales. Figure 10. Showing right hand excavator moving up chainage digging out existing road; left hand machine is placing bales towards it. 60 Figure 11. Placing lightweight aggregate fill by dumper. Note voids between bales. Figure 12. Extremely weak saturated peat underlay the existing road construction. 61 Figure 13. As work progressed the bypass sunk into the peat 1.0m, despite being subject to a 7.5 tonne weight restriction. Figure 14. Capping in place, showing steel mesh reinforcement within it. 62 Figure 15. Road open to traffic, with bypass being removed. Figure 16. A 50 mm layer of sand/fine gravel being added to bind the surface and improve running quality. 63 Figure 17. Typical timber truck. A monitoring tube can be seen painted yellow on left. Figure 18. April 2003. Excavation showed localised rutting failure was related to bale joint coinciding with mesh reinforcement joint. 64 Figure 19. August 2003. The extent of the culvert deflection is remarkable, and not yet fully explained. Figure 20. September 2003. Regular transverse rutting is clearly related to joints in bale structure.