Success of the Iwaki Platform Decommissioning
Transcription
Success of the Iwaki Platform Decommissioning
What’s Up Social & Community Climbing Fuji San There is an ancient Japanese saying that it is a fool who does not climb Mt. Fuji but it is a bigger fool that climbs her twice. If this is true then I am surely one of the fortunate who can count themselves to exist within this happy limbo. When the idea first came to me, I decided to make it worthwhile by making this a sponsored event for charity. As my family had recently lost my mother to cancer, the charity which immediately came to mind was Cancer Research UK as they perform important and life-saving work in investigating this devastating disease. Having limited time due to the vessel’s movements and the short official climbing season, I promptly made use of our vessel’s internet facilities to set up a webpage for online donations (www.justgiving.com/Daniel-Chinn) so that I was able to accept donations from friends at home. Encouraged by the positive reaction which I received, I then decided to approach our company which I did by writing to our CEO, C.J.D’Cort. At the time I was hoping for a gesture of support on behalf of SapuraAcergy, basically an endorsement of my planned expedition and a small donation. I was therefore both delighted and very pleasantly surprised when a few days later I received a response that our company wished to donate RM3000! Spurred on by this official support, I redoubled my preparations in our excellent gym each day after the end of my watch. On the day of our departure from the vessel, I found myself both eager and apprehensive of the forthcoming climb, as I set off to a small town called Gotenba in the Fuji Five Lakes national park. Arriving late in the afternoon I packed my rucksack and settled into an early night’s sleep, ready for next day’s climb. Rising early the next day, I took the longest trail in appreciation of the significant sponsorship I’d received in such a short span of time. The bus dropped me off at the 5th station and from there; the summit lay 5.8 miles away over fields of lava ash, rocks and boulders. Climbing in this terrain is difficult as feet slip backwards due to the treacherous nature of the soil. After a few hours on the deserted trail I noticed that the vegetation was becoming sparse and increasingly stunted whilst the air became thinner and noticeably colder. There are a number of mountain huts on each trail at various “stations”. I was counting on these to replenish my water supply as although I had set off carrying two litres, the exertion was draining this reserve with alarming speed. The only horizon and the summit was as bleak and noise that accompanied me was the wind whistling through the rocks and barren a place as could be imagined. An unreal my own laboured breathing as my lungs struggled to strip the oxygen vista of vicious rock teeth, sharpened by the from the thin air. Passing the seventh station, I was feeling very weary elements ringed the crater which seemingly and a real effort of self-motivation was required to resume walking plummeted hundreds of feet within the mountain. It was after each breather. Boots seemingly heavier than at the base, strange to realise that somewhere beneath the layer of pack bearing more achingly upon my back I am still unsure snow and frozen rock, Fuji still bore a fiery heart. what was more difficult: overcoming the physical fatigue or the mental urge to stop and rest longer. However, my The highest point is actually the site of a meteorological station and arrival at the eighth station brought relief to my as the wind whistled unhindered by I could understand why: nothing dwindling water supplies and I drank greedily and could be more exposed. I was alone on the highest point in Japan.The gratefully once there. temperature had now plummeted so I broke out my cold weather gear and walked around the crater’s rim to where I had planned to start my descent. Eventually, as I trudged onwards I was greeted by the welcome sight of a After some time, I began to encounter other climbers on this shorter trail. wooden Torii gate marking the last few Technically, I had begun my ascent on the first day of the climbing season and these yards of the trail to the summit. were people who were going to overnight in the mountain huts and complete their climb Gratefully, I forced the last few the next day. Eventually, I found myself walking through woodland and a distant lightening steps from my weary legs and of the sky heralded twighlight and the coming dawn. As the glow in the east grew, birdsong arrived, finally, at the began to fill the trees. Finally, after 18 hours trekking, I reached journey’s end, heaved off my summit after eight and a pack and bought myself a coffee, gratefully relieving the weight from blistered feet. I sat back, put half hours of trudging. my feet up and relaxed as I lounged in the growing light watching the sun break over the clouds and lesser peaks. The sun was about to dip Distance covered: 10.2 miles, Summit altitude: 3776m, Time taken: 18 hrs (including breaks) below the Money raised: £1600 and counting, Pain level: Immense! Wester n Thanks to the generosity of all my sponsors, especially colleagues and SapuraAcergy itself, this event has been a resounding success; so much so if fact, that I have been inspired to plan a similar climb but this time of Mt Kinabalu, the highest point between the Himalayas and Papua New Guinea. This should fit in conveniently with the movements of Sapura 3000, our floating home from home.I am therefore leaving open my charity webpage at www.justgiving.com/Daniel-Chinn should anyone wish to contribute (obviously I am not asking for anything other than moral support from those who sponsored my last climb!). My thanks go out to everyone who got behind me and gave me a metaphorical push up the slopes: your support gave me the motivation I needed to get to the top! Tea Party with Sapura Community OurWorld As the saying goes, a little help goes a long way. As all of you know, one of our campbosses, Jayan anak Jawa, has been facing a hard time since his son was diagnosed with leukemia. SapuraAcergy had successfully collected over RM 23,300 to help ease Jayan’s burden. However, during the recent Sapura 3000 Expedition, a member of the Sapura Group who had followed the Expedition was touched by Jayan’s plight as well as SapuraAcergy’s efforts in collecting funds. He had appealed to the Sapura Community and they had in turn managed to match our donation of RM 23,300. To show our heartfelt appreciation, SapuraAcergy had organised a ‘ThankYou Tea Party’ for the Sapura Community with Datuk Shahril, Datin Yazreen and En Syariman as our guests of Honor. We flew Jayan in from East Malaysia, giving him the chance to personally thank the committee and all involved. During the tea party, both Datuk Shahril and En Syariman pledged to top-up the remaining amount needed for Jayan’s son’s treatment and operation. Another First for SapuraAcergy SapuraAcergy proudly welcomes the first differentlyabled member of our team; Ms. Gurmit Singh. Gurmit, who joins us as our receptionist is partially blind and has worked in multiple organisations prior to joining SapuraAcergy. She is also a member of MAB – the Malaysian Association for the blind. In order to help staff better understand the condition, we invited representatives from MAB to give us an awareness talk on how to treat and help differentlyabled people, should the need arise. Besides the awareness talk, members of MAB also serenaded us with a medley of classic tunes. Vol. 2/2010 (Issue 2) Though rendered speechless, Jayan was very much grateful and presented some tokens of appreciation that he had brought with him from Sarawak. We at SapuraAcergy would like to thank Datuk Shahril, Datin Yazreen, En Syariman and the whole of the Sapura Community for their efforts and contribution to help ease Jayan’s pain and hardship. May you be blessed for your generosity! Thank you! Success of the Iwaki Platform Decommissioning Project SapuraAcergy was subcontracted by Nippon Steel Engineering Co. Ltd. for the decommissioning of the topsides, jacket and associated section of 12” gas export pipeline of the Iwaki platform. The Iwaki platform, which was installed in 1983 at a water depth of 154m, is located approximately 40km east of Nahara Cho in Fukushima prefecture of Japan. SapuraAcergy’s client for the Iwaki Platform Decommissioning Project was Offshore Iwaki Petroleum Co., Ltd. Led by Stig Adolfsen, the project management team was based in Kuala Lumpur, with a Japan Branch Office (JBO) team based in Onahama led by Mohd Ruzaihizal Bin. Zakaria. The Technical team was led by Tom O’Malley with the support of Phoon Kok Huei, Kyu Sik Son and their engineering teams who successfully completed the technical work scope. The subsea cutting package was headed up by Kingsley Wood with the assistance of Emma Killip. We welcome Gurmit and hope that she will have a long and prosperous career with us! First Aid Training SapuraAcergy sees it as imperative that our employees are provided a safe and secure environment to work in at all times. As such, a two-day First Aid Training session was held on the 8th and 9th July 2010 at the VIP Room, Sapura@Mines. The capabilities of the Sapura 3000 were fully exploited in performing a multitude of tasks in this project, including the following heavy lifts: • 16 modular lifts ranging between 100MT to 1100MT removal of topside facilities and Module Support Frame • Cutting the jacket into two pieces at approximately EL-92m • Lifting the upper section of jacket (2625MT), and lowering it to the seabed MAY-JULY KDN No. PQ/PP1505(16900) • Toppling of the upper section through 90 deg. adjacent to original location • Cutting and stabilising the remaining export pipeline The Sapura 3000 commenced her mobilisation in Johor Baru on the 19th April 2010, where all project equipment was mobilised onto the vessel over a period of 3 days. Considering the large quantity of equipment required for this project, the layout on the Sapura 3000’s deck was a project in itself. The vessel departed from Johor Baru with Onahama, Japan as its destination on 22nd April 2010. The Sapura 3000 arrived in Onahama, Japan 7th May 2010, after approximately 14 days of transit. During her port call to Onahama, the Sapura 3000 received all custom & immigration clearances in less than 1 day prior to departing for a short transit to the field. As soon as the vessel arrived at the platform location and tried setting up, it became obvious that problems lay in store with adverse vessel and crane tip motion caused by a long confused bi-directional swell. Transfer of equipment, personnel and any lifting operations became a challenge. Subsequently several changes to the sequence of work and execution methodologies needed to be engineered. Once topside preparations were completed, and the vessel motion was within limits, the topside modules and the MSF were removed and placed upon four cargo barges. These cargo barges were subsequently towed to port in Japan for the modules to be stripped and scrapped as required. Eight sections of 100m long piles were then removed, each weighing in excess of 220MT. The removal of piles was again very weather sensitive and required the vessel to set up at a range of headings. This was a very restrictive operation, however, it was performed successfully. The Jacket removal operations required each of the eight jacket legs to be sealed with the use of large pressure caps, four of these caps had integral lifting padeyes to be used for the jacket The training session which saw about 20 employees participating is conducted to ensure that each department will have their own ‘first-aiders’ in case of emergency. Participants are required to sit for theory and practical assessment, which includes multiplechoice questions, skill demonstrations and mock-drills (scenario based). Once they have completed and passed the assessment, they will receive a Completion Card which is valid for 2 years. Strength and Depth I am proud to say that a total of 92 days of the Sapura3000 was utilised to perform the Iwaki Platform Decommissioning Project, With approximately 276,500 manhours onboard, without a lost time incident and only one number of first aid case. continued on page 3... - Stig Adolfsen CEO’s Update It is clear that our shareholders are more than pleased with our progress and performance, but this also presents the challenge of coming up with a balanced commercial progression between Acergy, TLO and SapuraAcergy for the next 3 to 5 years. There has been no indication of need for a change in the name “SapuraAcergy” and it is my view that we should retain the name as I believe that our branding is paying dividends and our reputation is gaining traction within the Asia Pacific region. Therefore the possibility of registering the name SapuraAcergy as a separate trademark is very much existent. Project & Operations updates 1. Completion of Iwaki Platform Decommissioning Project Decommissioning projects are notorious for their execution challenges but the Iwaki Platform Project has been a wonderful success story for SapuraAcergy from start to finish from a technical, commercial and client relationship point of view. The project team and all the support divisions have done a tremendous job. If the Kikeh and MHSRP II projects were not enough to convince the regional market of our potential, then I am sure that the outcome of the Iwaki Platform Decommissioning project will have the desired effect. HSSEQ - Safe Operations 1. Safety measures throughout the Iwaki Project. We definitely had some HSE challenges on the Iwaki project, but after all was said and done, the client was very impressed with our commitment to HSE at all levels in the company throughout the project. Our safety management team and our system functioned well under sometimes testing circumstances and a third party safety audit by Acergy during the project confirmed that SapuraAcergy is on the right HSE track. However, safety is an area where we can never allow ourselves to become complacent and therefore we need to continue to drive ourselves towards HSE excellence everyday and everywhere. 2. Mobilization of Sapura 3000 for the Gumusut-Kakap Once the jacket rigging was removed, the water within the jacket legs was further pumped out, replacing it with air; making the jacket approximately 450MT in weight. The vessel’s A&R line was connected to rigging on the jacket top. The vessel then moved 500m clear of the jacket site and on the evening of the 3rd July 2010 the jacket was pulled over and toppled onto the seabed. This completed the work scope of the project. All infield operations were completed on the 5th July 2010. The planned duration to complete removal works was 51.58 days (including weather downtime) while the actual duration for offshore works was 59.32 days. The Sapura 3000 was the ideal tool for the decommissioning scope, the vessel’s crane had significant capacity to perform the topside lifting operations. In parallel with this, the fully integrated ACV’s on the vessel completed the subsea cutting operations. The vessel’s crane also had the redundancy required to complete the jacket lift and land operation. The vessel’s A&R winch (integrated into the pipelay system) was used for the toppling operations. The Sapura 3000 completed the entire decommissioning work scope without the support of any 3rd party construction vessel. Highlights 3rd – 6th May 2010 4th May 2010 6th May 2010 7th May 2010 7th May 2010 29th May 2010 16th June 2010 24th June 2010 June 2010 29th June 2010 July 2010 5th July 2010 8th – 9th July 2010 19th July 2010 20th July 2010 22nd July 2010 27th July 2010 Acergy/SapuraAcergy participates in OTC Houston Commencement of 2nd Cycle of SIGMUS inspections Main Uddin’s heroic efforts in saving his co-worker’s life has him dubbed Gumusut’s “Goal Zero Hero” Jayan’s ‘Appreciation Tea-Party’ with the Sapura Community Sapura 3000 arrives in Onahama, Japan Sponsorship of the ‘SapuraAcergy – OGAS Cup’ 1st Town Hall Meeting FYE2010/2011 Malaysian Association of the Blind (MAB) Awareness Talk OHSAS Surveillance Audit Completion of the English Language Classes Mt Fuji Charity Climb by Dan Chin (Sapura 3000 crew member) Successfully completed the Iwaki Decommissioning project First Aid Training course Shahar Bin Hashim joins SapuraAcergy as Deputy Director HSSEQ - Corporate Sapura 3000 arrives in Labuan from Japan 2nd Board of Directors’ Meeting FYE2010/2011 Commencement of Gumusut-Kakap project What’s Up Long Service Awards Ceremony SapuraAcergy held a Long-Service Awards ceremony at our 2nd Quarter Town Hall meeting on 6th June 2010 in recognition of continuous service with the company. Congratulations to the following employees: “How did he come about working for Sapura Acergy?,” we muse out loud. Hilmy replies, “A friend asked me for my resume to submit it to Brooke International, and after it was passed around a bit, it came to SapuraAcergy. I hadn’t heard of SapuraAcergy but had heard of the established Sapura organisation and was interested in the offer.” He goes on to say “What sealed the deal was the lure of offshore work and the opportunity to start from scratch with a new company.” The highlight of Hilmy’s daily routine is the toolbox talk he has with the crew. These are essential as he discusses safety issues related to any safety bulletin here and reads out the U-See U-Act submissions of the preceding day for affirmative action. When asked what his greatest challenges are, working on the Sapura 3000, he replied “...to educate people, especially the mid-level management on the importance of HSE and that it is not just the responsibility of one person. HSE is for all!” His advice to any who wish to become Safety Officers like himself, is to always expect the unexpected and to be sure of the decisions one makes as situations may arise between the company and the safety acts/laws, “where you’ll have to be careful and stand by your decision.” In parting Hilmy says with a smile “Good luck!”. The crane experienced 1050MT during the lifting operation, 1543MT of buoyancy was gained from 75% of the leg length being filled with air. Once at site, the project team was challenged with re-engineering many of their solutions to reduce the use of the main crane and maximise the use of the 40T cranes along with manual handling and local rigging methodologies to lift smaller items on the platform. The supply of material and equipment from Japan was kept to a minimum, however dealing with local Japanese presented both language and cultural challenges that needed to be overcome. With the aid of local Japanese employees these challenges were managed with ease. Kong, Norhisham b Harun, Mohd Asri b Ariffin, Ang Kim Puay, Daryl Leo Wakelin, David Ramoo, Yeo Cheng Kwan, Daniel Carre, Gunawan, Zulkarnain b Saim, Nazlida bt Mohd Noor, Fadzlina bt Tokiman, Iain Gray, Juliana bt Yahya, Nurman Harris, Norwahida bt Ahmad, Azhar b Hasan, A. Gilbert D’Cruz, Thomas Fontaine. 4 YEARS C.J. D’Cort, Shawn Wong Chow Hong, Nurul Afiqah Kong bt Abdullah, Syed Takhiruddin b Syed Abd Bari, Azizah bt Abu Hassan. 3 YEARS Frank Tilborg, Arizal b Abu Hassan Masri, Haznim bt Othman, Mithlan b Mahyuddin, Zalifah bt Mustafa, Ameliza bt Abu Yazid, Mohd Yusmi b Abd Mutalib, Alfred a/l G. Veeriah, Norhazita bt Mohammed Nor, Aisyah bt Hj. Dzulfakar, Nurul Syariza bt Ahmad Kamsuri, Lim Swee Lin, Tai Kien Hock, Riva Suliawan, Phang Yoke Khim, Norliza bt Mohd Tajuddin, Nora ’Ain bt Saharudin, Azmi b Ajman, Vincent Fromont, Laurent Rinaudo, Rozita bt A. Rahman, Natasha Lee Sing Yee, Joel Sheng Kian However, destiny had other things in store for him, and although this adventure seeker didn’t become a firefighter, he says “I found my true calling in being an offshore safety officer”. Having been in the industry for twelve years, Hilmy’s first posting was in Vastalux where he served as a safety officer for one year. Jacket lift; the estimated overall jacket weight was well in excess of the maximum lift capacity of the Sapura 3000 main crane. In order to achieve the lift, the legs of the jacket needed to be sealed and used as buoyancy chambers to reduce the lift weight. Environmental conditions in the Pacific Ocean were the biggest of the project challenges. The location of the site presented the vessel with bi-directional swells. This caused the vessel to roll continuously which reduced the operational ability of the main crane. Heeding His Calling Hilmy Ishak is a self-professed happily married man with three children aged 11, 9 and 3 years. Describing himself as a serious worker, yet happy-go-lucky otherwise, and a crowd-pleaser, this motor enthusiast originally aspired to be a fire fighter – joining the ‘Kadet Bomba’ during his school days. As there were so many unknowns, it is very difficult to engineer the exact jacket weight, therefore to prevent the jacket being buoyant, the jacket needed to be lifted in stages, this allowed the jacket’s actual weight to be established. Once as-left surveys were completed the vessel transitted to Onahama port, completed custom & immigration clearances and set-sail for Malaysia on the 5th July 2010. After negotiating her way past typhoon Conson, the vessel arrived in Labuan on the 20th July 2010 and completed the demobilisation of equipment onto an awaiting cargo barge. campaign The Gumusut-Kakap mobilisation went reasonably well despite some technical delays. The project team did a good The decommissioning of offshore installations is the next part of our industry. The successful completion of this work scope allows SapuraAcergy together with the Sapura 3000, to be a market leader in this field of operation. Challenge 2 Although no dramatic changes to our company have been foreseen, we have been in discussion with our shareholders for the past 6 months in order to gain clarity on the commercial and growth objectives of the company. We have also discussed the possibility of acquiring a second vessel. 3. Devil Creek Development Project (DCDP) project progress The DCDP project is largely on schedule with the offshore pre-lay survey recently completed and the shallow water lay barge, the Leighton Stealth, scheduled to commence operations on xx September 2010. The Sapura 3000 will proceed to mobilise for the DCDP immediately upon completion of the Gumusut-Kakap campaign for 2010. When the environmental conditions were right, the vessel’s crane was connected to the jacket via 65m long 14” diameter slings, and the water within the jacket legs was pumped out making the jacket approximately 1000MT in weight. The jacket was then lifted clear of the lower section and moved 80m to the landing site. The jacket was then lowered to the seabed using a series of crane moves and de-ballasting steps, and was set on the seabed on the 3rd of July. Challenge 3 One of our joint venture partners, Acergy, recently announced its imminent merger with Subsea 7, a world leader in subsea engineering and construction. The merger will be completed in 6 to 12 months’ time, until which time it will be business as usual for SapuraAcergy. job, keeping in mind that Shell is a technically demanding client. The vessel is currently laying an 18” diameter pipeline towards a 1200m water depth and early indications are that the project and vessel are making good production progress. From day one throughout the entire project cycle, the project team worked together as one, with excellent team morale. The challenges of working in a country in which no one had worked before and successfully completing a decommissioning job is a great achievement for us as a company as well as a personal achievement for all team members. Challenge 1 lifting operation. Prior to the jacket lift, a manifold of air lines were arranged around the top deck of the structure, tested, and connected to an air compressor spread located on the deck of the vessel. On the right track On the merger: Over A Cup Of Coffee Continued from cover story... HSEQ Gumusut Goal Zero Hero Safety is at the core of who Shell is, and delivering on our Goal Zero vision requires everyone to constantly identify possible hazards and deal with them. A safe environment is also synonymous with a tight-knit community, where people look after each other and themselves. Nowhere is this more evident than on our project sites around the world. The story of Main Uddin, a general worker with a contractor firm on the Shell led GumusutKakap Project in Malaysia, shows how quick thinking and simple safety rules save lives. (The Gumusut-Kakap field, also called “Gumusut”, is a field located in the Baram Delta Basin, offshore north-west Sabah in water depths ranging from 850-1200m.) On the morning of 6 may 2010, Main was assisting a Contractor Site Supervisor in routine bolting activity on a J-Lay tower installation when something unexpected happened. When picking up a torque wrench, the supervisor suffered an electrical shock. Main reacted immediately by first disconnecting the power connection before assisting his injured co-worker, effectively saving his life. The victim was subsequently referred to the nearest hospital within 30 minutes where doctors confirmed him to be okay. Learning from this unfortunate incident is key and an investigations process was carried out. The incident has now been properly documented, classified and the knowledge gained is being shared. As for Main, he was absolutely clear about what needed to be done when the incident occurred. He knew the rules, applied them and by doing so, he saved the life of his co-worker. Shell’s commitment to relentlessly pursuing a goal of no harm to people and protecting the environment is a mandatory requirement for all contractors, Shell companies and joint ventures under operational control. Safe organisations are high-performing organisations, and delivering high performance across the board is what success looks like. Thanks to Main’s exemplary actions one of our co-workers was able to go home to his family, and he has been dubbed Gumusut’s “Goal Zero Hero”. Main Uddin is presented a certificate of recognition by The SapuraAcergy employees who received Long Service Awards Winfried Arens, VP Projects, UI East, at a large Safety Day