15255D-Tender Specifications
Transcription
15255D-Tender Specifications
SPECIFICATIONS FOR WINDOW, DOOR, ROOF, BOILER & RTU REPLACEMENT WOODROFFE HIGH SCHOOL 2410 GEORGINA DRIVE OTTAWA, ONTARIO Prepared by 110 – 150 Katimavik Road, Ottawa, Ontario K2L 2N2 T: 613-831-7293 I F: 613-831-3812 I www.fsaeng.com FSA Project No.: 15255D April 2016 Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Division Section Division 01 General Requirements Division 02 General Requirements ................................................................... 5 01 14 00 Work Restrictions ........................................................................... 3 01 23 10 Alternatives .................................................................................... 1 01 31 19 Project Meetings ............................................................................ 2 01 33 00 Submittal Procedures..................................................................... 6 01 35 29 Health and Safety Requirements ................................................... 2 01 35 43 Environmental Procedures............................................................. 2 01 41 00 Regulatory Requirements .............................................................. 1 01 45 00 Quality Control ............................................................................... 3 01 52 00 Construction Facilities .................................................................... 2 01 56 00 Temporary Barriers and Enclosures .............................................. 2 01 71 00 Examination and Preparation......................................................... 1 01 71 01 Sitework, Removal and Preparation .............................................. 2 01 74 11 Cleaning ......................................................................................... 2 01 77 00 Closeout Procedures ..................................................................... 1 01 78 00 Closeout Submittals ....................................................................... 1 Existing Conditions Division 08 Division 22 Rough Carpentry............................................................................ 5 Thermal and Moisture Protection 07 52 00 Modified Bituminous Membrane Roofing ..................................... 26 07 62 00 Sheet Metal Flashing and Trim ...................................................... 6 07 92 00 Joint Sealants ................................................................................ 6 Openings 08 11 16 Aluminum Doors and Frames ........................................................ 8 08 44 13 Glazed Aluminum Curtain Walls .................................................. 16 08 50 00 Windows ...................................................................................... 12 08 80 50 Glazing ........................................................................................... 8 Plumbing 22 05 11 Appendix Selective Site Demolition ............................................................... 5 Wood, Plastics and Composites 06 10 00 Division 07 Pages 01 00 11 02 41 13 Division 06 Title Section 00 00 01 TABLE OF CONTENTS Page 1 of 1 Plumbing and Drainage ................................................................. 7 Designated Substances Report by CM3 Environmental ..................................... 11 END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 00 11 GENERAL REQUIREMENTS Page 1 of 5 GENERAL DESCRIPTION OF THE WORK – WINDOW & DOOR .1 Provide the necessary labour and materials to complete the removal of the existing window and door systems, sheet metal flashings and other related components, down to the existing structure and install new window and door systems as specified herein. .2 Supply and installation of related rough carpentry at window and door openings. .3 Supply and install all sheet metal caps, counter flashings, fascia and all other related metal flashings required to complete the installation. .4 Supply and installation of all sealants required to seal the transitions and related metal detailing and the termination of sheet metal and surfaces. .5 Finish and paint new and adjacent surfaces to match existing 1.2 GENERAL DESCRIPTION OF THE WORK - ROOF .1 Provide the necessary labour and materials to complete the removal of the existing roofing system, existing curbs, sheet metal flashings and membrane down to the existing structural deck and install new roofing system as specified herein. .2 Supply and installation of related rough carpentry at parapets and curbs. .3 Supply and install all sheet metal caps, counter flashings, scuppers, torch stops, fascia and all other roof related metal flashings required to complete roof installation. .4 Supply and installation of all sealants required to seal the transition of membrane and related metal detailing and the termination of sheet metal and nonmembrane surfaces. .5 Supply and installation of new roof drains and new piping as detailed and indicated on the drawings. New drains/piping shall be in the same locations and shall include all required clamps, hangers, insulation, vapour wrap and all other items required to complete the new drain installation. 1.3 GENERAL DESCRIPTION OF THE WORK - BOILERS .1 Provide the necessary labour and materials to complete the removal of the existing boilers No.3 and No.4, their flue gases venting systems serving all boilers (No.1 to No.4) and installation of new boilers No.3 and No.4 and flue gases venting systems serving all boilers (No.1 to No.4). .2 Work to include modifications to heating system and gas pipework, electrical and BMS systems, complete with replacement of pumps, pipework, valves, fittings, bracketing and wiring as described and specified on M-series drawings. 1.4 GENERAL DESCRIPTION OF THE WORK - RTU .1 April 2016 Provide the necessary labour and materials to complete the removal of the existing library roof-top unit (RTU) and installation of a new one. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 1.5 Section 01 00 11 GENERAL REQUIREMENTS Page 2 of 5 Work to include modifications to heating, electrical and BMS systems, complete with replacement of pump, pipework, valves, fittings, bracketing and wiring as described and specified on M-series drawings. DEFINITIONS .1 "CONSULTANT” and “Fishburn/Sheridan & Associates Ltd." and “FSA” are synonymous. .2 "OWNER" and “OCDSB” and “Ottawa-Carleton District School Board” are synonymous. .3 “CONSTRUCTOR” and “CONTRACTOR” are synonymous. 1.6 OTHER CONTRACTORS .1 1.7 Other Contractors, Sub-Contractors and the Owner’s own forces, may be performing work on the site at the same time as the Work is being done under this Contract. The successful bidder shall provide all reasonable co-operation and collaboration with these other forces to ensure a timely completion of the work, taking into consideration and without undermining its own role as the “Constructor”. USE OF THE SITE .1 Carry out the Work so as to have the least possible interference and disturbance to the normal use of the premises. The successful bidder is expected to include in the bid an allowance for the performance of off-hours work should it be required to conform to the above. .2 Maintain services to existing building and provide for personnel and vehicle access. .3 Restrict construction access to and from site to approved location. Do not allow construction traffic to block entrances or exits for any reason. .4 Co-ordinate any interference with Owner's operation in this area and abide by Owner's direction in this regard. In cases of conflicting requirements, Owner's operation takes precedence but all reasonable effort to accommodate Contractor's needs will be made. 1.8 EXISTING SERVICES .1 Before commencing work, establish location and extent of service lines in area of Work and notify Consultant of findings. .2 Remove abandoned service lines within 2.4 m of structures. Cap or otherwise seal lines at cut-off points as directed by Consultant. .3 Services are to be left operational unless otherwise authorized by Owner. .4 Unless otherwise specified, the Contractor will be responsible for disconnection, relocation, re-installation and extending all services required to facilitate work under this Contract. Co-ordinate work with the Owner and provide minimum 48 hours notification if services are to be interrupted. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.9 Section 01 00 11 GENERAL REQUIREMENTS Page 3 of 5 CUTTING AND PATCHING .1 1.10 Generally patch and "make good" any and all surfaces cut, damaged, exposed, or disturbed to comply with any appropriate statutory requirements and to the Owner's acceptance. PROTECTION OF PROPERTY .1 Protect surrounding private and public property from damage during the performance of the Work. .2 Be responsible for damage incurred. 1.11 FIRE PROTECTION .1 Provide and maintain temporary fire protection equipment during the performance of the Work as required by insurance companies and governing codes, regulations and by-laws having jurisdiction. .2 Open fires and burning of rubbish are not permitted on site. 1.12 OCCUPATIONAL HEALTH AND SAFETY .1 Follow the Ontario Provincial Occupational Health and Safety Act and Regulations for Construction Projects. For the purposes of the act, the person or company contracted to carry out the work shall be deemed the "Constructor". .2 Hazardous materials, not identified by the Owner, may be encountered at the worksite. Use all necessary precautions when handling such material. It is possible that asbestos may exist in some form and if encountered the Contractor is responsible to notify the Owner and to follow Ontario Ministry of Labour regulations governing the handling of asbestos in the workplace. .3 The Owner may cause those who do not comply with the O.H.S.A. and Regulations to be escorted from the site. 1.13 PROTECTION OF BUILDING FINISHES AND EQUIPMENT .1 Prevent movement, settlement, or other damage to other adjacent structures, utilities, and parts of building to remain in place. Provide bracing and shoring if required. .2 Keep noise, dust, and inconvenience to occupants to a minimum. .3 Protect building systems, services and equipment. Protect all furnishings within work area with (6 mil) polyethylene film during construction. Remove film during non-construction hours and leave premises in clean, unencumbered and safe manner for normal daytime function. .4 Provide temporary dust tight screens, partitions, covers, railings, barricades, supports and/or other protection as required. Protect workers, finished areas of work and public. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.14 Section 01 00 11 GENERAL REQUIREMENTS Page 4 of 5 PARKING .1 Parking is available on site .2 All vehicles must be parked in designated parking areas (except for reasonable loading and unloading of equipment and/or materials to a local entrance). Contractor’s vehicles on site shall be limited to reasonable loading and unloading of equipment and/or materials to a local entrance. Failure to observe these requirements may result the vehicle being ticketed and/or towed. 1.15 SIGNS AND ADVERTISEMENTS .1 No signs or advertisements of any description other than notices regarding safety shall be displayed at the Work Site without permission of the Owner. .2 Upon completion of the Work, all signs shall be removed except those specifically directed by the Owner to remain. 1.16 CLEAN-UP .1 Maintain the work area in tidy condition, free from the accumulation of waste products and debris. .2 Remove waste and materials regularly so as to maintain a tidy work site. Do not dispose of any waste in the Owner’s facilities unless specifically directed to do so by authorised personnel. .3 Store materials in areas specially designated by the Owner. Dispose of this debris in a legal manner so as to avoid causing a hazard to occupants and visitors on site. 1.17 MATCHING .1 1.18 Where new work occurs in or adjacent to existing work, it is the intent that colours and textures of visible finishes within these areas shall be matched to the satisfaction of the Owner. PERMITS, FEES, CERTIFICATES .1 Obtain and pay for all required permits. .2 Arrange and pay for all inspection certificates required by Authorities having jurisdiction, (i.e., Electrical Safety Authority Certificate). Provide the Owner with copies of these certificates upon completion. 1.19 DISRUPTION OF SERVICES .1 The Contractor is responsible to provide adequate written notice to the Owner of any interruption of services (i.e., mechanical, electrical etc.) for the connection of new services or the alteration of existing. .2 The Contractor is expected to co-operate reasonably with the Owner in the scheduling of service interruptions. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.20 Section 01 00 11 GENERAL REQUIREMENTS Page 5 of 5 SANITARY FACILITIES .1 1.21 Temporary sanitary facilities will be provided by the Constructor in compliance with the Occupational Health and Safety Act and Regulations for Construction Projects POWER .1 1.22 Contractor to provide their own electrical or any other power to perform contract work. TEMPORARY FACILITIES .1 1.23 Any temporary facilities provided at the site by the Contractor must be removed upon completion of the work and the area used must be returned to the original condition. DOCUMENTS REQUIRED .1 Maintain at the job site, one copy each of the following: .1 .2 .3 .4 .5 .6 .7 .8 1.24 Original Plans and Specifications and completed Form of Tender. Building Department stamped drawings if required. Any changes to Drawings or Details. Shop Drawings and any changes. Addenda. Change Orders. Site Instructions. Contractor's Safety Policy. WORK SCHEDULE .1 1.25 Within 5 working days of intent to award, provide a schedule showing anticipated progress stages and final completion of the Work within the specified time period, indicating each trade and inter-phasing. Allow for expected poor weather days. MAINTAIN WARRANTEES .1 Ensure that work of this Contract does not invalidate warrantees on adjacent work. Provide written confirmation and arrange and pay for all services and costs to ensure that warrantees on adjacent work are maintained. .2 The Contractor accepts full and complete responsibility of maintaining existing warrantees. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 14 00 WORK RESTRICTIONS Page 1 of 3 ACCESS AND EGRESS .1 Design, construct and maintain temporary "access to" and "egress from" work areas, including stairs, runways, ramps and scaffolding independent of finished surfaces and in accordance with relevant municipal, provincial and other regulations. .2 Access and egress is to be by scaffolding staircase, as per Occupational Health and Safety Act (OHSA). Staircase is to have secure door at ground level. 1.2 USE OF SITE AND FACILITIES .1 The size and location of work and site storage areas are to be determined at the pre-bid site meeting. .2 Areas of work and storage on site will be designated by the Owner before commencement of work at the pre-bid meeting. The boundaries established thereby shall be strictly enforced. .3 The Contractor may request the Owner to relocate or expand the work or site storage area during the EXECUTION of work. .4 The decision to make changes to the work and site storage areas will be at the sole discretion of the Owner/Consultant. .5 Do not unreasonably encumber the site with materials, stored products or equipment, which interfere with the daily operations of the Owner. .6 Prior to commencing work carefully inspect and determine the capability of set up and traffic areas to support anticipated loads without doing damage. Provide protection to protect all landscaping and paving including but not limited to installing heavy wood planks under kettles, tankers, dolly wheels of trailers and disposal bins and completely over all areas used to hoist or remove debris from the site. .7 Prior to commencement of work, inspect and provide itemized list of existing property damage accompanied with photographs or a video of site conditions and turn over a copy to the Consultant for safekeeping. This information will be used to resolve disputes should they occur. .8 Commencement of work by the Contractor is proof that the Contractor accepts the surfaces as satisfactory. .9 Clearance must be obtained from the Owner or a designate before gaining vehicular access during regular work hours. .10 All vehicles must exercise extreme care when frequenting the property, in particular, any areas near or adjacent to pedestrian traffic. Provide a flagman at the front and rear of all vehicles to protect pedestrian and property from traffic April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 01 14 00 WORK RESTRICTIONS Page 2 of 3 during garbage removal, material delivery or other such activities during work hours. .11 Locate equipment and materials at existing service roadways to provide minimal interference with the building occupants, pedestrians, staff and vehicular traffic. .12 When required, close off access routes by placing barricades or posting guards to prevent access to unauthorized personnel. Unauthorized personnel shall mean the public and anyone not directly concerned with the execution, supervision or inspection of the work. 1.3 ALTERATIONS, ADDITIONS OR REPAIRS TO EXISTING BUILDING .1 Execute work with least possible interference or disturbance to building operations and normal use of premises. Arrange with Consultant to facilitate execution of work. .2 All roof related mechanical modifications must be performed by Vision Air. .3 All roof related plumbing modifications must be performed by R.L. Diguer Plumbing. 1.4 EXISTING SERVICES .1 Notify Consultant and utility companies of intended interruption of services and obtain required permission. .2 Where Work involves breaking into or connecting to existing services, give Consultant 48 hours of notice for necessary interruption of mechanical or electrical service throughout course of work. Keep duration of interruptions minimum. Carry out interruptions after normal working hours of occupants, preferably on weekends. .3 Provide for pedestrian and vehicular traffic. .4 Construct barriers in accordance with Section 01 56 00 - Temporary Barriers and Enclosures. 1.5 SPECIAL REQUIREMENTS .1 Ensure protection of the building and products that are sensitive to damage by moisture. Do not work during rain, snow or fog or periods of high humidity. Stop work before onset of inclement weather or when inclement weather appears imminent. .2 As governed by design intent, install each part of the system only when surfaces and weather allow for a successful application and performance of completed work. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 1.6 Section 01 14 00 WORK RESTRICTIONS Page 3 of 3 Observe minimum temperature and weather conditions set out in manufacturer’s printed recommendations. BUILDING SMOKING ENVIRONMENT .1 Smoking is not permitted on property. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 23 10 ALTERNATIVES Page 1 of 1 ALTERNATIVES .1 After the Contract is awarded, requests for “acceptance” of materials in addition to those presently established as “acceptable” by the Contract documents shall be submitted in writing to the Consultant at the following address: ATTENTION: Luc Guilbeault Fishburn Sheridan & Associates Ltd. 110-150 Katimavik Road Ottawa ON K2L 2N2 .2 Such a request shall be accomplished with a complete description of the alternative proposed including the advantages and cost savings that could be realized. In addition, provide the name of manufacturer brand name, technical data and samples of both the specified and proposed substitute items. .3 Identify and allow for in the bid price, any submission of alternatives to products specified including any changes required in the related work and modifications surrounding work as required to complete the project under each alternative designated. A later claim by the Bidder for any addition to the Contract price, because of changes in work necessitated by use of alternatives shall not be considered. .4 In any case, where substitutions are permitted, the Contractor shall bear the cost to evaluate and test the equality of the materials and pay any design charges and costs to change the working drawings and specifications that occur due to their use. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 31 19 PROJECT MEETINGS Page 1 of 2 GENERAL .1 1.2 This section specifies general requirements and procedures for project meetings. Additional requirements may be specified in individual sections of the specification. ADMINISTRATIVE .1 The Consultant will administer the pre-construction meeting. .2 The Owner, Contractor, Sub-Contractors and Suppliers will be notified of the meeting. .3 Physical space and arrangements for meeting will be coordinated with the Owner. .4 Copies of minutes from all meetings will be distributed to meeting participants and affected parties not in attendance. .5 Representative of Owner, Contractor, Sub-Contractors and Suppliers attending meeting shall be qualified and authorized to act on behalf of the party each represents. 1.3 MEETINGS .1 Pre-construction Meeting: .1 .2 April 2016 The Consultant will request a meeting of parties to the Contract to discuss and resolve administrative procedures and responsibilities. Attendance of the superintendent and foreman is mandatory. The cost of attending shall be included in the Contractor’s base bid. Agenda to include the following: .1 Appointment of official representative of participants in the work. .2 Schedule of work, progress scheduling. .3 Schedule of submission of material list, shop drawings, samples, and color chips as per Section 01 33 00, Submittal Procedures. .4 Requirements for temporary facilities, site sign, equipment restrictions, storage, utilities, hoarding, barricades, as per Section 01 52 00 - Construction Facilities. .5 Site security, emergencies and protective measures. .6 Requirements for fire safety, fire watch and fire protection systems. .7 Supplementary instructions, contemplated changes, change orders, procedures, approvals required, mark-up percentages permitted, time extension, overtime, administration requirements. .8 Maintenance manuals, take-over procedures, acceptance, warrantees. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .9 .10 .11 .12 .13 .2 Section 01 31 19 PROJECT MEETINGS Page 2 of 2 Monthly progress claims, administrative procedures, holdbacks. Insurances, transcripts of policies, Workplace Safety & Insurance Board Certificate. Technical review of design intent, specifications and details. Requirements for progress meetings. In addition, during the pre-construction meeting, the existing site conditions affected by work if the Contract shall be inspected and documents by photograph or video. Progress Meetings: .1 .2 During the course of the work, scheduled progress meetings may be required until project completion. Timing and responsibility for arrangements will be determined at the pre-construction meeting. Agenda to include the following: .1 Review, acceptance of minutes of previous meeting. .2 Review of work progress since previous meeting. .3 Field observations, problems, and conflicts. .4 Problems that impede construction schedule. .5 Review off-site fabrication delivery schedules. .6 Corrective measures and procedures to regain projected schedule. .7 Revisions to construction schedule. .8 Progress schedule during succeeding work period and effect on occupants. .9 Review submittal schedules for samples and shop drawings and expedite as required. .10 Maintenance of quality standards. .11 Pending changes and substitutions. .12 Review proposed changes for effect on construction schedule and on completion date. .13 Other business. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 33 00 SUBMITTAL PROCEDURES Page 1 of 6 GENERAL .1 1.2 Work shall not commence until all Submittals (as specified in Paragraph 1.3 below) are complete. ADMINISTRATIVE .1 The Contractor shall provide all Submittals to the Consultant for review. Submittals shall be provided with reasonable promptness and in an orderly sequence so as not to cause delay in the work. Failure to submit in ample time shall not be considered sufficient reason for an extension of Contract time and no claim for extension by reason of such default will be allowed. .2 The Contractor shall not commence work affected by Submittals until Submittals are accepted and reviewed. .3 The Contractor shall be responsible for reviewing Submittals prior to submission to the Consultant. By conducting this review, the Contractor represents that all necessary requirements have been determined and verified and that each Submittal has been checked and coordinated with the requirements of the work and the Contract documents. Submittals not stamped, signed and dated by the Contractor, and identified as to the specific project, will be returned without being examined and will be considered rejected. .4 It is the responsibility of the Contractor to verify that the field measurements and affected adjacent work are coordinated. .5 The Contractor’s responsibility for errors, omissions and deviations from the requirements of the Contract documents is not relieved by the Consultant’s review. .6 The Contractor shall keep one accepted copy of each submission on site. 1.3 SUBMITTALS .1 Submittals are as follows: .1 April 2016 Prior to Construction: .1 Contact Information. .2 Performance Bond (if applicable). .3 Permits and Licenses (if applicable). .4 Ministry of Labour “Notice of Project”. .5 Schedule. .6 Shop Drawings. .7 Material List. .8 Product Data Sheets. .9 Insurance Policy. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 .3 1.4 Section 01 33 00 SUBMITTAL PROCEDURES Page 2 of 6 .10 WHMIS Data Sheets. .11 Mock-ups and Samples. .12 Contract Cost Breakdown. With Payment Claim: .1 Contract Cost Breakdown. .2 WSIB Statement. Post Construction: .1 Final Invoice. .2 Guarantees/Warrantees. .3 Daily Commercial News ad (if applicable). .4 Statutory Declaration. .5 As Built Drawings. .6 Certificate of Substantial Performance. .7 Certificate of Total Completion. .8 WSIB Statement. SHOP DRAWINGS .1 Shop drawings refer to drawings, designs, schedules, brochures and illustrations as submitted by the Contractor. .2 The Contractor is responsible to cross reference shop drawings to all applicable portions of the Contract. Identify on the shop drawings all cross references in chart form, marked "Cross References". .3 The Contractor shall submit fully detailed dimensioned shop drawings whenever requested in the specifications or Summary of Work. Shop drawings shall show clearly construction, layout, anchorage, designation of materials, finishes and all other relevant information. .4 Specific requirements for substitutions are specified in individual sections of the specifications. When specified, drawings are to be stamped by a qualified Engineer, registered and licensed in the Province in which the work is to be undertaken. .5 Until submissions are reviewed, work involving relevant products may not proceed. .6 The shop drawings submittal and re-submittal shall be completely identified by showing the following: .1 .2 .3 .4 April 2016 Project Name. Project Number/Job Number. Name and Address of Supplier and/or Manufacturer. Name of Contractor. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .5 .6 Section 01 33 00 SUBMITTAL PROCEDURES Page 3 of 6 Drawing number and Specification section to which the Submittal applies. Shop Drawings that do not comply with these requirements shall be stamped “REVISE AND RESUBMIT”. .7 The Contractor shall stamp and sign the shop drawings indicated that they have checked and reviewed the shop drawings prior to submission to the Consultant. .8 Review of shop drawings by the Consultant is for the sole purpose of ascertaining confirmation with the general design concept. This review does not constitute approval, nor does it relieve the Contractor from complying with the Contract documents. The Contractor and their Consultants are responsible for the designs inherent in the shop drawings and the performance of completed work including any oversights and errors that result. The review and any subsequent re-submittals will not be a cause for extension to the Contract completion date or schedule. .9 Shop drawings shall be submitted as directed by Consultant. .10 New information cannot be added to shop drawings previously submitted. New information shall be submitted on new shop drawings. .11 Each of the returned shop drawings will be stamped as follows: REVIEWED REVIEWED AS NOTED REVISE AND RESUBMIT NOT REVIEWED .1 .2 .3 .4 .5 .6 April 2016 [ [ [ [ ] ] ] ] If REVIEWED is checked off, the shop drawing is satisfactory. Shop drawings do not have to be resubmitted. If REVIEWED AS NOTED is checked off, the shop drawing is satisfactory subject to the requirements of remarks put on the shop drawing. Work may proceed accordingly. Shop drawings must be resubmitted for record purposes. If REVISE AND RESUBMIT is checked off, the shop drawing is unsatisfactory and must be revised in accordance with comments written on the shop drawings. Shop drawings to be revised and resubmitted for review. No work is to proceed until REVIEWED stamp is checked off. If NOT REVIEWED is checked off, the shop drawing is in error of submission or is not applicable for the project or information previously requested or marked up has not been complied with or drawings have not been revised. Do not proceed with work. Drawings must be resubmitted. Allow the Consultant a period of 10 working days from the date of receipt for a review of submitted shop drawings. Shop drawings are not Contract documents. The purpose of their submittal is to review the conformity to the general design concept expressed in the Contract documents. Review of shop drawings does not relieve the Contractor of the responsibility to comply with every aspect of Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .7 1.5 Section 01 33 00 SUBMITTAL PROCEDURES Page 4 of 6 the original Contract documents. Any deviation from the original Contract documents must be documented. Keep copies of REVIEWED drawings on site for reference. PRODUCT DATA .1 Product data: Manufacturer’s catalogue sheets, brochures, literature, performance charts and diagrams, used to illustrate standard manufactured products. .2 Submit an electronic version of product data to the Consultant. .3 Supplement standard information to provide details applicable to project. .4 Cross-reference product data information to applicable portions of Contract documents. .5 Obtain labels for material used for each day’s work. Provide labels and a list of materials, Manufacturer's serial or lot numbers. Turn over to the Consultant as requested. 1.6 SAMPLES .1 When the submission of samples are requested under the individual section, submit two samples for review. .2 Samples: examples of materials, equipment, quality, finishes, workmanship. .3 Submit full range of samples including colour, pattern or texture. .4 Reviewed and accepted samples will become standard of workmanship and material against which installed work will be verified. .5 Deliver one sample to the site. .6 Deliver one sample to the Consultant: Fishburn Sheridan & Associates Ltd. 110-150 Katimavik Road Ottawa ON K2L 2N2 Phone: 613-831-7293 Fax: 613-831-3812 .7 April 2016 The cost of delivery of samples will be paid by the Contractor and included in the Contract price. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.7 Section 01 33 00 SUBMITTAL PROCEDURES Page 5 of 6 MOCK-UPS .1 Mock-ups: When specific requirements for the construction of mock-ups are specified in individual sections of the specifications, field-erect example of work to be completed with specified materials and workmanship. .2 Erect mock-ups at locations acceptable to the Consultant. .3 Reviewed and accepted mock-ups will become standards of workmanship and material against which installed work will be verified. .4 Failure to prepare mock-up in ample time is not considered sufficient reason for an extension of Contract time. .5 The cost of providing the mock-up is to be included in the Contractor bid price. .6 Verify all dimensions and conditions and provide alterations required to adapt work to specific site conditions without additional cost. .7 The mock-up, if acceptable to the Consultant, may form part of the finished work. 1.8 PAYMENT .1 Monthly draws on account against work completed will be payable in accordance with the terms and conditions outlined by the Owner’s payment policy as agreed to before commencing work. Holdback will be 10% of the total value of work completed at date of invoicing. .2 Release of Holdback will be made in accordance with the latest requirements of the Construction Lien Act, 45 days after all work of the Contract is substantially complete. .3 Final payment will be made after all work of the Contract is 100% complete, including correction of all deficiencies. .4 All invoices for payment must be addressed to the Owner and directed to Fishburn/Sheridan & Associates Ltd. for verification. On verification, the Consultant will issue a Payment Certificate. .5 Separate invoices for holdback payments must also be submitted. The Contractor should not assume that the holdback payments will be made automatically at the end of the holdback period without first submitting an invoice. 1.9 STATUTORY DECLARATION (HOLDBACK) .1 April 2016 In order to release holdback, the Contractor shall submit a Statutory Declaration to the Consultant and a copy to the Owner stating that all Sub-Contractors and material Suppliers have been paid. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 Section 01 33 00 SUBMITTAL PROCEDURES Page 6 of 6 The Contractor will be responsible to publish a copy of the Certificate of Substantial Performance in the Daily Commercial News. Proof of publication of the Certificate is to be forwarded to the Consultant before the release of the holdback. The cost of publishing is to be included in the bid. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 35 29.06 HEALTH AND SAFETY REQUIREMENTS Page 1 of 2 REFERENCES .1 Health Canada/Workplace Hazardous Materials Information System (WHMIS) .1 .2 Province of Ontario .1 1.2 Material Safety Data Sheets (MSDS). Occupational Health and Safety Act, R.S.O. 1990 Updated 2014. SUBMITTALS .1 Submit in accordance with Section 01 33 00 - Submittal Procedures. .2 Submit site-specific Health and Safety Plan prior to commencement of Work. Health and Safety Plan must include: .1 .2 Results of site specific safety hazard assessment. Results of safety and health risk or hazard analysis for site tasks and operation. .3 On-site Contingency and Emergency Response Plan: address standard operating procedures to be implemented during emergency situations. .4 Submit copies of reports or directions issued by Federal, Provincial and Territorial health and safety inspectors. .5 Submit copies of incident and accident reports. .6 Submit WHMIS MSDS - Material Safety Data Sheets in accordance with Section 01 33 00 –Submittal Procedures. 1.3 FILING OF NOTICE .1 1.4 File Notice of Project with Provincial authorities prior to beginning of Work. SAFETY ASSESSMENT .1 1.5 Perform site specific safety hazard assessment related to project. REGULATORY REQUIREMENTS .1 1.6 Do Work in accordance with Section 01 41 00 - Regulatory Requirements. GENERAL REQUIREMENTS .1 April 2016 Develop written site-specific Health and Safety Plan based on hazard assessment prior to beginning site Work and continue to implement, maintain, and enforce plan until final demobilization from site. Health and Safety Plan must address project specifications. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 1.7 Section 01 35 29.06 HEALTH AND SAFETY REQUIREMENTS Page 2 of 2 Consultant may respond in writing, where deficiencies or concerns are noted and may request re-submission with correction of deficiencies or concerns. RESPONSIBILITY .1 Be responsible for health and safety of persons on site, safety of property on site and for protection of persons adjacent to site and environment to extent that they may be affected by conduct of Work. .2 Comply with and enforce compliance by employees with safety requirements of Contract Documents, applicable federal, provincial, territorial and local statutes, regulations, and ordinances, and with site-specific Health and Safety Plan. 1.8 COMPLIANCE REQUIREMENTS .1 Comply with Ontario’s Occupational Health and Safety Act, R.S.O. 1990. .2 Comply with Occupational Health and Safety Regulations. 1.9 UNFORSEEN HAZARDS .1 1.10 When unforeseen or peculiar safety-related factor, hazard, or condition occur during performance of Work, follow procedures in place for Employee's Right to Refuse Work in accordance with Acts and Regulations of Province having jurisdiction and advise Consultant verbally and in writing. CORRECTION OF NON-COMPLIANCE .1 Immediately address health and safety non-compliance issues identified by authority having jurisdiction or by Consultant. .2 Provide Consultant with written report of action taken to correct non-compliance of health and safety issues identified. .3 Consultant may stop Work if non-compliance of health and safety regulations is not corrected. 1.11 WORK STOPPAGE .1 Give precedence to safety and health of public and site personnel and protection of environment over cost and schedule considerations for Work. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 01 35 43 ENVIRONMENTAL PROCEDURES Page 1 of 2 Part 1 Products 1.1 ACTION AND INFORMATIONAL SUBMITTALS .1 1.2 Provide submittals in accordance with Section 01 33 00 - Submittal Procedures. FIRES .1 1.3 Fires and burning of rubbish on site not permitted. DRAINAGE .1 Provide temporary drainage and pumping required to keep site free from water. .2 Ensure pumped water into waterways, sewer or drainage systems is free of suspended materials. .3 Control disposal or runoff of water containing suspended materials or other harmful substances in accordance with local authority requirements. 1.4 NOTIFICATION .1 Consultant will notify Contractor in writing of observed noncompliance with Federal, Provincial or Municipal environmental laws or regulations, permits, and other elements of Contractor's Environmental Protection plan. .2 Contractor: after receipt of such notice, inform Consultant of proposed corrective action and take such action for approval by Consultant. .1 Do not take action until after receipt of written approval by Consultant. .3 Consultant will issue stop order of work until satisfactory corrective action has been taken. .4 No time extensions granted or equitable adjustments allowed to Contractor for such suspensions. Part 2 Products 2.1 NOT USED .1 Not Used. Part 3 Execution 3.1 CLEANING .1 April 2016 Clean in accordance with Section 01 74 11 - Cleaning. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 01 35 43 ENVIRONMENTAL PROCEDURES Page 2 of 2 .2 Waste Management: separate waste materials for reuse and recycling in accordance with Municipal regulations. .3 Do not bury rubbish and waste materials on site. .4 Ensure public waterways, storm and sanitary sewers remain free of waste and volatile materials disposal. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 41 00 REGULATORY REQUIREMENTS Page 1 of 1 REFERENCES AND CODES .1 Perform work in accordance with, but not limited, to the latest edition of Ontario Building Code (OBC), National Fire Code of Canada, and any other code of provincial or local application provided that in any case of conflict or discrepancy, the more stringent requirements shall apply. .2 Meet or exceed requirements of: .1 .2 .3 .4 .5 .6 .7 1.2 Contract documents, Specified standards, codes and reference documents. Canadian Roofing Contractor’s Association’s Roofing Specifications Manual. Various CSA, CGSB, ASTM, SMACNA standards referred to in the appropriate sections. Gas pipes and equipment to national or Provincial Gas Utilization Codes. Ontario Regulation 183/184 under the Power Corporation Act (Electrical Safety Code) and bulletin in force. Printed instructions of the manufacturer for materials being employed. HAZARDOUS MATERIAL DISCOVERY .1 Asbestos: demolition of spray or trowel-applied asbestos is hazardous to health. Stop work immediately when material resembling spray or trowel-applied asbestos is encountered during demolition work. Notify Consultant. .2 Mould: stop work immediately when material resembling mould is encountered during demolition work. Notify Consultant. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 45 00 QUALITY CONTROL Page 1 of 3 GENERAL .1 1.2 This section specifies general requirements and procedures for quality control. Additional requirements may be specified in individual sections of the specifications. PROCEDURES .1 The Consultant will complete a general review of the work. .2 The Consultant shall act objectively, but shall be responsible solely to the Owner. .3 Allow Consultant access to offsite manufacturing and fabrication plants as required or necessary. 1.3 NOTIFICATIONS .1 1.4 Notify the Consultant and material Manufacturer at least 48 hours before operations commence, and arrange for a site meeting for discussion of procedures. The job foreman and superintendent for the project shall be present and shall have any and all technical questions ready for discussion. Subsequently, give two working days prior notice for the commencement of each phase of work. Notify of delays and restarts. Additional costs for inspection when Contractor is not on site without notification will be back-charged to Contractor. REPORTS .1 Co-operate and afford all facilities necessary to permit inspection of the work and testing of materials prior to and during installation and throughout the Warrantee period. The issuing of reports and review of materials certificates and test reports by the Consultant shall not be construed as relieving the Contractor of responsibility for proper completion and Warrantee/Guarantee of the work in accordance with the Contract documents, drawings and specifications. .2 While every effort will be made not to impede the progress of work, the Contractor should anticipate some inconvenience and work stoppage. The Contractor should take into consideration al costs to assist the Consultant and make allowances in the bid price. 1.5 REMOVAL OF TEST SAMPLES .1 The Contractor and trades will co-operate with the Consultant as requested to facilitate inspection and testing and removal of samples from new and existing work as specified in the Tender Documents. .2 Make cut-outs for testing purposes when and where required and make good roofing of test areas and of any and all defects of materials and workmanship without additional cost. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 01 45 00 QUALITY CONTROL Page 2 of 3 .3 Assist the Consultant to remove, wrap and hoist samples to ground as requested. .4 The Contractor will have no claim against the Consultant or Owner for additional costs that result from delays, or expenses for removing or hoisting of samples. 1.6 CONTRACTOR’S RESPONSIBILITY TO REMOVE AND REPAIR CUT TEST AND TESTING .1 The Contractor shall allow for all costs associated with removing two (2) 300 mm x 300 mm roof samples randomly located by the Consultant. If sample sizes are other than specified here, Consultant will direct Contractor on site. .2 Remove samples of completed roof assembly in presence of Consultant and as directed on site by Consultant. .3 Cut with power saw around template supplied by the Consultant. Consultant will provide plastic bags and labels to retain sample and locate cut area on Roof Plan. Contractor to hoist sample undamaged to ground for Consultant. .4 In the event that test results are unsatisfactory additional cuts and lab testing may be required for which the cost will borne by the Contractor. .5 Locate cut tests away from drains, projections, curbs, etc. .6 Fill void of the samples with insulation to match original. On modified bitumen roofs, prepare membrane in accordance with Manufacturer’s instructions and repair area with 2 plies of base sheet and 1 ply of cap sheet, each ply overlapping 75 mm onto roof surface. 1.7 WORK CONTRARY TO DOCUMENTS .1 1.8 The Consultant may order any part of the work to be examined if such work is suspected to be contrary to the Contract documents. WORK COVERED BEFORE INSPECTED .1 1.9 If the Contractor covers or permits to be covered work before it has been reviewed, the Contractor shall uncover such work, have the review or test satisfactorily completed and make good such work. NON-COMPLIANCE WITH WORK .1 If the initial review and tests required to establish compliance with the Contract documents indicates non-compliance, additional testing or review shall be performed. .2 The cost of review and testing will be borne by the Contractor and deducted from the price of the Contract. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 01 45 00 QUALITY CONTROL Page 3 of 3 .3 Replace all work that results from inferior products or workmanship to meet specified requirements. .4 The Contractor shall replace or correct work not conforming to the Contract. If in the opinion of the Consultant, it is not expedient to correct work not done in accordance with the Contract, the Owner may deduct from the Contract price the difference in value between the work as done and called for by the Contract. The amount will be determined by the Consultant. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 52 00 CONSTRUCTION FACILITIES Page 1 of 2 GENERAL .1 1.2 This section specifies general requirements and procedures for construction facilities. Additional requirements may be specified in individual sections of the specifications. TRAFFIC FLOW .1 Provide and maintain fire route, access roads, sidewalks and crossings, ramps and construction runways as may be required for access to the work. .2 Maintain free access for Owner to service doors and other entrances at all times. At conclusion of the work repair and make good damages to existing construction resulting from construction operations. .3 Maintain access routes in a clean and orderly condition to the Owner’s acceptance. Make good damage due to construction activities. 1.3 CONSTRUCTION PARKING .1 1.4 Parking spaces will be made available on site and the locations and number of parking spaces will be determined at the pre-construction meeting. Maintain and administer this space to the satisfaction of the Owner. SET-UP AREAS .1 1.5 A set-up area shall be assigned to the Contractor for his use. In addition to the approved set-up area, the Contractor is permitted to hoist materials on and off the roof at other locations designated by the Owner. While the Owner will make every attempt to accommodate the Contractor’s schedule, the Contractor shall immediately vacate the space at the Owner’s request should a conflict arise. All costs that result from such occurrences will be borne by the Contractor. FENCING PROTECTION .1 Erect and maintain an enclosure around the set-up area. Maintain in good repair. Comply with OHSA. .2 Access to set-up area should be truck size hinge doors of matching material that are to be kept locked when the project is not in progress. .3 Provide Owner a duplicate key for security and fire reasons, at the beginning of the project. The key will be returned when the project is complete. 1.6 CONSTRUCTION AIDS .1 April 2016 Use only non-conductive scaffolding designated to CSA S269.2-M87 and ladders when work is being carried out within telephone and power equipment areas. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.7 Section 01 52 00 CONSTRUCTION FACILITIES Page 2 of 2 SIGNS .1 No advertisements or signs shall be erected inside or outside the building except notices regarding safety and caution as approved by the Owner. .2 If required, provide warning signs are required by governing authorities. .3 Where applicable, building permit is to be prominently displayed on the premises. 1.8 PROTECTION OF WORK AND PROPERTY .1 Provide scaffolding to protect motor vehicles and/or pedestrian traffic. .2 When working overhead, including when hoisting, provide safety inspectors or flag operators using two-way radios to control traffic flow. .3 When work will cause dust, debris or water to enter the building, provide interior protection such as plywood hoarding and/or reinforced polyethylene tarpaulins above building operation. .4 Provide interior protection, and remove protection and clean up as work progresses and risk is eliminated. .5 The cost of interior protection is to be included in the Base Price. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 01 56 00 Woodroffe High School TEMPORARY BARRIERS AND ENCLOSURES 2410 Georgina Drive, Ottawa Page 1 of 2 1.1 REFERENCES .1 Canadian Standards Association (CSA International) .1 1.2 CSA-O121-M1978 (R2003), Douglas Fir Plywood. INSTALLATION AND REMOVAL .1 Provide temporary controls in order to execute Work expeditiously. .2 Remove from site all such work after use. 1.3 GUARD RAILS AND BARRICADES .1 Provide secure, rigid guard rails and barricades around open stair wells, open edges of floors and roofs, and openings. .2 Provide as required by governing authorities. 1.4 WEATHER ENCLOSURES .1 Provide weather tight closures to unfinished door and window openings, tops of shafts and other openings in floors and roofs. .2 Close off floor areas where walls are not finished; seal off other openings; enclose building interior work for temporary heat. .3 Design enclosures to withstand wind pressure and snow loading. 1.5 DUST TIGHT SCREENS .1 Provide dust tight screens or partitions to localize dust generating activities, and for protection of workers, finished areas of Work and public. .2 Maintain and relocate protection until such work is complete. 1.6 ACCESS TO SITE .1 1.7 Provide and maintain access roads, sidewalk crossings, ramps and construction runways as may be required for access to Work. PUBLIC TRAFFIC FLOW .1 1.8 Provide and maintain competent signal flag operators, traffic signals, barricades and flares, lights, or lanterns as required to perform Work and protect public. FIRE ROUTES .1 April 2016 Maintain access to property including overhead clearances for use by emergency response vehicles. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 01 56 00 Woodroffe High School TEMPORARY BARRIERS AND ENCLOSURES 2410 Georgina Drive, Ottawa Page 2 of 2 1.9 PROTECTION FOR OFF-SITE AND PUBLIC PROPERTY .1 Protect surrounding private and public property from damage during performance of Work. .2 Be responsible for damage incurred. 1.10 PROTECTION OF BUILDING FINISHES .1 Provide protection for finished and partially finished building finishes and equipment during performance of Work. .2 Provide necessary screens, covers, and hoardings. .3 Confirm with Consultant locations and installation schedule 3 days prior to installation. .4 Be responsible for damage incurred due to lack of or improper protection. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 71 00 EXAMINATION AND PREPARATION Page 1 of 1 EXISTING SERVICES .1 Before commencing work, establish location and extent of service lines in area of Work and notify Consultant of findings. .2 Remove abandoned service lines within 2 m of structures. Cap or otherwise seal lines at cut-off points as directed by Consultant. 1.2 LOCATION OF EQUIPMENT AND FIXTURES .1 Location of equipment, fixtures and outlets indicated or specified are to be considered as approximate. .2 Locate equipment, fixtures and distribution systems to provide minimum interference and maximum usable space and in accordance with manufacturer's recommendations for safety, access and maintenance. .3 Inform Consultant of impending installation and obtain approval for actual location. .4 Submit field drawings to indicate relative position of various services and equipment when required by Consultant. 1.3 RECORDS .1 1.4 Record locations of maintained, re-routed and abandoned service lines. SUBSURFACE CONDITIONS .1 Promptly notify Consultant in writing if subsurface conditions at Place of Work differ materially from those indicated in Contract Documents, or a reasonable assumption of probable conditions based thereon. .2 After prompt investigation, should Consultant determine that conditions do differ materially, instructions will be issued for changes in Work as provided in Changes and Change Orders. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 01 71 01 Woodroffe High School SITEWORK, REMOVAL AND PREPARATION 2410 Georgina Drive, Ottawa Page 1 of 2 1.1 GENERAL .1 1.2 Conform to the requirements and procedures for Site work, Removal and Substrate Preparation as specified in this specification and as shown on the Drawings. REMOVAL AND DISPOSAL .1 No more than two (2) days prior to removal of the roofing, flashings and accessories, power vacuum and broom the roof surface free of all loose gravel. .2 Remove and dispose of the existing roofing assembly, related flashings, insulation, and vapour barrier and wood blocking to expose the existing roof deck to the specified limits and as shown on the Drawings. Make good existing surfaces. .3 Clean concrete deck by sweeping, blowing with air or by vacuum to ensure roof surface is free of all debris. .4 In compliance with the Roof Plan Drawings and the Details, remove and discard existing rooftop equipment, flashings and materials not scheduled for re-use or salvage. .5 Fill in and make good deck openings as shown on the Drawings. .6 Make good existing surfaces affected by the Work. .7 Dispose of material off site as per regulatory requirements. 1.3 PREPARE TIE-INS ON MODIFIED BITUMEN ROOF MEMBRANES .1 1.4 Where the existing roof membrane is to be tied into, prepare the existing modified bitumen membrane to receive new surface as specified. DRAINS AND DRAINAGE PLANE .1 1.5 Confirm drainage planes and identify low points. Report results to the Consultant so as to allow corrective measures to be undertaken in a timely and effective manner. REINFORCE EXISTING ROOF OPENINGS .1 April 2016 Inspect all openings from the underside of all decks to verify that any opening larger than 150 mm have been structurally reinforced. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 01 71 01 Woodroffe High School SITEWORK, REMOVAL AND PREPARATION 2410 Georgina Drive, Ottawa Page 2 of 2 1.6 NEW OPENINGS IN DECK OR LOAD BEARING WALLS .1 Provide openings in roof deck or walls to facilitate the installation of new drains, through-wall scuppers, and new electrical or mechanical equipment and services. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 74 11 CLEANING Page 1 of 2 GENERAL .1 1.2 This section specifies general requirements and procedures for cleaning. Additional requirements may be specified in individual sections of the specifications. CLEANING DURING CONSTRUCTION .1 Keep the premises free from accumulation of waste materials or rubbish at all times. At the completion of the work remove all rubbish, tools, equipment and surplus materials. .2 Store volatile waste in covered metal containers and remove from premises at end of each working day. .3 Provide adequate ventilation during use of volatile or noxious substances. Use of building ventilation systems is not permitted for this purpose. .4 Only use cleaning materials recommended by Manufacturer of surfaces to be cleaned and by cleaner Manufacturer. .5 Schedule cleaning operations so that resulting dust, debris and other contaminants will not fall on wet or newly painted surfaces. 1.3 FINAL CLEANING .1 Clean roofs, drains, gutters, and downspouts and ensure all plumbing and drainage systems are open and working freely upon completion of work. .2 Clean interior and exterior surfaces including glass and all polished surfaces of all contaminants including grease, dust, dirt, stains, labels, fingerprints and other foreign materials. .3 Markings, mortar, spills, caulking, bitumen and adhesive on HVAC equipment, soil stacks, sleeves, gas lines, vents, drains, miscellaneous roof projections and other building components are to be removed without damage to the roofing system or equipment. Make good finishes to the satisfaction of the Owner’s Project Coordinator and Consultant. .4 Leave roof clean of debris, bitumen, spills and tracking. Leave grounds and building free of debris and bitumen spread by pedestrian traffic where applicable. On gravel surfaced roofs, rake out excessive piles of aggregate for a neat and even surface. Use a magnetic sweeper to sweep the grounds around the building for stray nails, screws and construction debris. .5 Broom clean and water wash paved concrete or paving stone surfaces. Rake grounds around building of all debris. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 01 74 11 CLEANING Page 2 of 2 .6 Leave grounds and building free of debris where applicable. Use a magnetic sweeper to sweep the grounds around the building for stray nails, screws and construction debris. .7 Contractor is responsible to repair and pay all costs and fees required to rectify damage caused by work of this Contract with materials and finish to match the original. .8 All glazing to be cleaned inside and out by a professional cleaner. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 77 00 CLOSEOUT PROCEDURES Page 1 of 1 INSPECTION AND DECLARATION .1 Consultant's Inspection: Consultant and Contractor will perform inspection of Work to identify obvious defects or deficiencies of Work. Contractor to correct Work accordingly. .2 Completion: submit written certificate that following have been performed: .1 .2 .3 .4 Work has been completed and inspected for compliance with Contract Documents. Defects have been corrected and deficiencies have been completed. Equipment and systems have been tested, adjusted and balanced and are fully operational. Work is complete and ready for final inspection. .3 Final Inspection: when items noted above are completed, request final inspection of Work by Consultant, and Contractor. If Work is deemed incomplete by Consultant, complete outstanding items and request re-inspection. .4 Declaration of Substantial Performance: when Owner and Consultant consider deficiencies and defects have been corrected and it appears requirements of Contract have been substantially performed, make application for certificate of Substantial Performance. .5 Commencement of Lien and Warranty Periods: date of Owner's acceptance of submitted declaration of Substantial Performance shall be date for commencement for warranty period and commencement of lien period unless required otherwise by lien statute of Place of Work. .6 Final Payment: when Owner and Consultant consider final deficiencies and defects have been corrected and it appears requirements of Contract have been totally performed, make application for final payment. If Work is deemed incomplete by Owner and Consultant, complete outstanding items and request re-inspection. .7 Payment of Holdback: after issuance of certificate of Substantial Performance of Work, submit an application for payment of holdback amount. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.1 Section 01 78 00 CLOSEOUT SUBMITTALS Page 1 of 1 GENERAL .1 1.2 This section specifies general requirements and procedures for closeout submittals. Additional requirements may be specified in individual sections of the specifications. AS-BUILT DRAWINGS .1 On two sets of drawings, provided by the Consultant, maintain project as-built drawings, which accurately record deviations from Contract documents including field changes of dimensions, details and changes made by Change Orders. .2 Record changes on one set of prints in red. At completion of project and prior to final inspection, transfer changes to second set and submit both sets to the Consultant. 1.3 POST-CONSTRUCTION SUBMITTALS .1 Refer to Section 01 33 00 – Submittal Procedures for list of post-construction submittals. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED SECTIONS Section 02 41 13 SELECTIVE SITE DEMOLITION Page 1 of 5 .1 Section 06 10 00 – Rough Carpentry. .2 Section 07 52 00 – Modified Bituminous Membrane Roofing. .3 Section 22 05 11 – Plumbing and Drainage. 1.2 REFERENCES .1 Definitions: .1 .2 .2 Reference Standards: .1 .2 1.3 Demolition: Rapid destruction of building following removal of hazardous materials. Hazardous materials: Dangerous substances, dangerous goods, hazardous commodities and hazardous products, may include but not limited to: Asbestos PCB's, CFC's, HCFC's poisons, corrosive agents, flammable substances, ammunition, explosives, radioactive substances, or other material that can endanger human health or well being or environment if handled improperly. Health Canada/Workplace Hazardous Materials Information System (WHMIS) .1 Material Safety Data Sheets (MSDS). Transport Canada (TC) .1 Transportation of Dangerous Goods Act, 1992 (TDGA), c. 34. ACTION AND INFORMATIONAL SUBMITTALS .1 Submit in accordance with Section 01 33 00 - Submittal Procedures. .2 Shop Drawings: .1 .2 .3 Hazardous Materials: .1 .4 April 2016 Submit drawings stamped and signed by professional engineer registered or licensed in Province of Ontario, Canada. Submit for approval drawings, diagrams or details showing sequence of demolition work and supporting structures and underpinning, where required by authorities having jurisdiction. Provide description of Hazardous Materials and Notification of Filing with proper authorities prior to beginning of Work as required. Certificates: Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 1.4 Section 02 41 13 SELECTIVE SITE DEMOLITION Page 2 of 5 Submit copies of certified weigh bills, bills of lading, receipts from authorized disposal sites and reuse and recycling facilities for material removed from site on weekly basis, upon request of Consultant. QUALITY ASSURANCE .1 1.5 Regulatory Requirements: Ensure Work is performed in compliance with CEPA, CEAA, TDGA, applicable Provincial/Territorial regulations. DELIVERY, STORAGE AND HANDLING .1 Store and manage hazardous materials in accordance with Section 01 35 43 Environmental Procedures. .2 Storage and Protection. .1 .2 .3 .4 1.6 Protect existing items designated to remain and items designated for salvage. In event of damage to such items, immediately replace or make repairs to approval of Consultant and at no cost to Owner. Remove and store materials to be salvaged, in manner to prevent damage. Store and protect in accordance with requirements for maximum preservation of material. Handle salvaged materials as new materials. SITE CONDITIONS .1 Site Environmental Requirements. .1 .2 .3 .4 .5 .6 April 2016 Perform work in accordance with Section 01 35 43 - Environmental Procedures. Ensure that selective demolition work does not adversely affect adjacent watercourses, groundwater and wildlife, or contribute to excess air and noise pollution. Do not dispose of waste of volatile materials including but not limited to, mineral spirits, oil, petroleum based lubricants, or toxic cleaning solutions into watercourses, storm or sanitary sewers. .1 Ensure proper disposal procedures are maintained throughout the project. Do not pump water containing suspended materials into watercourses, storm or sanitary sewers or onto adjacent properties. Control disposal or runoff of water containing suspended materials or other harmful substances in accordance with local authorities and as directed by Consultant. If applicable, protect trees, plants and foliage on site and adjacent properties where indicated. Protect paving, sidewalks and all hard landscaping. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 Existing Conditions. .1 .2 1.7 Section 02 41 13 SELECTIVE SITE DEMOLITION Page 3 of 5 Remove contaminated or hazardous materials as defined by authorities having jurisdiction, prior to start of demolition Work, and dispose of at designated disposal facilities in safe manner in accordance with TDGA and other applicable regulatory requirements. List of hazardous materials: .1 Asbestos. .2 Lead. .3 Silica. SPECIAL CONDITIONS .1 Treasure, such as coins, bills, paper of value, and articles of antiquity, discovered during demolition work at the site shall remain property of the Owner. Part 2 Products 2.1 EQUIPMENT .1 Leave machinery running only while in use, except where extreme temperatures prohibit shutting machinery down. Part 3 Execution 3.1 PREPARATION .1 Inspect site with Consultant and verify extent and location of items designated for removal, disposal, alternative disposal, recycling, salvage and items to remain. .2 Locate and protect utilities. Preserve active utilities traversing site in operating condition. .3 Notify and obtain approval of utility companies before starting demolition. .4 Disconnect and cap designated mechanical services. .1 .2 .3 April 2016 Natural gas supply lines: Remove in accordance with gas company requirements / contact utility company to arrange for removal, as directed by Consultant. Sewer and water lines: Remove to property line, in accordance with authority having jurisdiction, contact utility company to arrange for removal, as directed by Consultant and securely plug to form watertight seal. Other underground services: Remove and dispose of as indicated and as directed by Consultant. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .4 3.2 Section 02 41 13 SELECTIVE SITE DEMOLITION Page 4 of 5 Underground storage tanks: Remove and dispose of in accordance with CCME PN1326 and directions of Consultant. REMOVAL OF HAZARDOUS WASTES .1 3.3 Remove contaminated or dangerous materials defined by authorities having jurisdiction, relating to environmental protection, from site and dispose of in safe manner to minimize danger at site or during disposal. REMOVAL OPERATIONS .1 Remove items as indicated. .2 Do not disturb items designated to remain in place. .3 Disposal of Material: .1 3.4 Dispose of materials not designated for salvage or reuse on site at authorized facilities or as instructed by Consultant. STOCKPILING .1 Label stockpiles, indicating material type and quantity. .2 Designate appropriate security resources/measures to prevent vandalism, damage and theft. .3 Locate stockpiled materials convenient for use in new construction to eliminate double handling wherever possible. 3.5 REMOVAL FROM SITE .1 Remove stockpiled material as directed by Consultant, when it interferes with operations of project. .2 Dispose of materials in accordance with applicable regulations. .3 Unless otherwise specified, materials for removal become the Contractor's property and shall be taken from site. .4 Maintain work area and site, free of accumulated waste and rubbish and dispose of all debris on a daily basis with minimum disturbance to occupants. .5 Provide garbage bins and chutes for daily disposal of debris. Co-ordinate location of bins with Client prior to commencement of work. .6 Have full garbage bins removed immediately. Unless otherwise specified, removed materials will become the Contractors property and shall be taken from site and disposed of in accordance with Municipal, Provincial and Federal regulations. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 3.6 Section 02 41 13 SELECTIVE SITE DEMOLITION Page 5 of 5 RESTORATION .1 Restore areas and existing works outside areas of demolition to conditions that existed prior to beginning of Work / match condition of adjacent, undisturbed areas. .2 Use soil treatments and procedures which are not harmful to health, are not injurious to plants, and do not endanger wildlife, adjacent water courses or ground water. 3.7 CLEANING .1 Progress Cleaning: Clean in accordance with Section 01 74 11 - Cleaning. .1 .2 .3 Leave Work area clean at end of each day. Remove debris, trim surfaces and leave work site clean, upon completion of Work Use cleaning solutions and procedures which are not harmful to health, are not injurious to plants, and do not endanger wildlife, adjacent water courses or ground water. .2 Final Cleaning: Upon completion remove surplus materials, rubbish, tools and equipment in accordance with Section 01 74 11 - Cleaning. .3 Waste Management: Separate waste materials for reuse or recycling. .1 3.8 Remove recycling containers and bins from site and dispose of materials at appropriate facility. PROTECTION .1 Repair damage to adjacent materials or property caused by selective site demolition. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED SECTIONS Section 06 10 00 ROUGH CARPENTRY Page 1 of 5 .1 Section 02 41 13 – Selective Site Demolition. .2 Section 07 52 00 – Modified Bituminous Membrane Roofing. .3 Section 07 62 00 – Sheet Metal Flashing and Trim. .4 Section 07 92 00 – Joint Sealants. .5 Section 22 05 11 – Plumbing and Drainage. 1.2 REFERENCES .1 ASTM International .1 .2 CSA International .1 .2 .3 .3 Standard Grading Rules for Canadian Lumber 2010. Underwriters' Laboratories of Canada (ULC) .1 .2 .3 1.3 CSA B111-1974 (R2003), Wire Nails, Spikes and Staples. CSA O141-05 (R2009), Softwood Lumber. CSA O151-09, Canadian Softwood Plywood. National Lumber Grades Authority (NLGA) .1 .4 ASTM A653/A653M-11, Standard Specification for Steel Sheet, ZincCoated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process. CAN/ULC-S701-05, Standard for Thermal Insulation, Polystyrene, Boards and Pipe Covering. CAN/ULC-S705.1-01, Standard for Thermal Insulation - Spray Applied Rigid Polyurethane Foam, Medium Density, Material Specification. CAN/ULC-S705.2-05, Standard for Thermal Insulation - Spray Applied Rigid Polyurethane Foam, Medium Density, Application. QUALITY ASSURANCE .1 Lumber identification: by grade stamp of an agency certified by Canadian Lumber Standards Accreditation Board. .2 Plywood identification: by grade mark in accordance with applicable CSA Standards. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.4 Section 06 10 00 ROUGH CARPENTRY Page 2 of 5 MOCK-UPS .1 Provide a 600 mm mock-up of wood blocking system, including closures for each detail or profile for review in a location designated by the Consultant in accordance with Section 01 33 00 – Submittal Procedures. .2 Review mock-up to ensure design intent can be achieved. Verify all intersecting and adjoining elevations to ensure that continuity of roofing and closures can be achieved. Verify attachment, methods for securing and pullout strengths to ensure that work can support the anticipated loads and will remain in place against all wind, weather and service conditions without warping or deforming. 1.5 PRECAUTIONS .1 Provide temporary protection, to the satisfaction of the Consultant, to render all wood blocking watertight, if for any reason permanent membrane protection cannot be provided within the same day. For roofing, ensure the base of any curbs are temporarily sealed to prevent water from entering below the curb assembly, or behind sheathing, should the roof assembly not be completed on the same day as the carpentry work. Part 2 Products 2.1 LUMBER MATERIAL .1 Lumber: Unless specified otherwise, softwood, S2S, moisture content 19% or less in accordance with following standards: .1 .2 .2 Furring, blocking, nailing strips, grounds, rough bucks, curbs, fascia backing and sleepers: .1 .2 .3 .4 2.2 CSA O141. NLGA Standard Grading Rules for Canadian Lumber. S2S is acceptable for all surfaces. Board sizes: "Standard" or better grade. Dimension sizes: "Standard" light framing or better grade. Post and timbers sizes: "Standard" or better grade. PANEL MATERIALS .1 Canadian softwood plywood (CSP): to CSA 0151. .1 2.3 Urea-formaldehyde free. FASTENERS .1 April 2016 Wood to wood fasteners: Wood screw #12 or as indicated, galvanized flat head, of sufficient length to completely penetrate through base minimum 25 mm. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 06 10 00 ROUGH CARPENTRY Page 3 of 5 .2 Wood to steel deck fasteners: Secure bottom nailer with minimum two rows of No. 10, galvanized steel screws at maximum spacing of 600 mm. Screws shall be of sufficient length to penetrate top flute of decking a minimum 13 mm and a maximum of 19 mm. Screws to be factory coated with an additional corrosion protection equivalent to ‘Climaseal’ or better. .3 Plywood to concrete, brick or hollow masonry fasteners: Tapcon 6 mm diameter screws. Length to provide minimum 32 mm and maximum 40 mm embedment into substrate as required. Drill holes 13 mm deeper than depth of fastener penetration. Type to be approved subject to results of pull tests. .4 Expansion fasteners for wood plates and steel to concrete deck: AISI Type 304 stainless steel, with stainless nuts and washers. .1 .5 Standard of acceptance or approved equivalent: .1 Hilti Kwik Bolt TZ. Exposed fastensers for metal to wood or masonry: Use #10 cadmium plated hex screws with neoprene and steel washers. Minimum length 38 mm. Use lead shields, Rawl or equal as required for anchoring. Colour of screw head to meet approval of Consultant. Provide touch-up paint as required to coat all exposed surfaces of screws damaged during the driving process. .1 Standard of acceptance or approved equivalent: .1 Atlas Bolt. .6 Proprietary fasteners: Toggle bolts, expansion shields and lag bolts, screws and lead or inorganic plugs to suit site conditions. .7 Nails, spikes and staples: To CSA B111. 2.4 ACCESSORIES .1 Interior gypsum board Type X: To ASTM C1396/1396M-13, thickness 12.7 mm unless otherwise noted. .2 Extruded polystyrene (XPS) insulation: To CAN/ULC-S701, Type 4, thickness as indicated. Where indicated, provide drainage grooves on underside of board. .3 Metal closure: 0.56 mm (26 ga.) galvanized steel unless otherwise shown or specified. .4 Spray-in-place polyurethane foam insulation: Thickness as shown or specified to CAN/ULC S705.1 Materials and CAN/ULC S705.2 Application. .5 Semi-rigid mineral wool insulation: Semi-rigid mineral wool, rockwool, or slagwool boards, to CAN/ULC 702.2. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 2.5 Section 06 10 00 ROUGH CARPENTRY Page 4 of 5 FINISHES .1 Galvanizing: To ASTM A653/A653M, use galvanized fasteners for all work. .2 Interior paint: 2 coats interior acrylic latex, colour to match existing, eggshell. Part 3 Execution 3.1 GENERAL INSTALLATION .1 Extend air/vapour barrier seals up vertical surfaces and curbs and onto the deck as shown on the Drawings, to provide continuity. .2 Slope the top of all wood blocking at the roof perimeter in towards the roof at a minimum of 5%, unless otherwise shown on the Drawings. .3 Comply with requirements of NBC, supplemented by the following paragraphs. .4 Install furring and blocking as required to space-out and support casework, cabinets, wall and ceiling finishes, facings, fascia, soffit, siding and other work as required. .5 Align and plumb faces of furring and blocking to tolerance of 1:600. .6 Install rough bucks, nailers and linings to rough openings as required to provide backing for frames and other work. .7 Install wood, fascia backing, nailers, curbs and other wood supports as required and secure using galvanized steel fasteners. .8 Install wood backing, dressed, tapered and recessed slightly below top surface of roof insulation for roof hopper. 3.2 SECUREMENT OF WOOD BLOCKING .1 Comply with more stringent requirements as required by drawings or Ontario Building Code requirements. Increase number and spacing of all fasteners by 50% for 2400 mm from all outside roof corners the corners of the roof. .2 Install fasteners to the design intent to hold all wood blocking permanently in place to prevent warping, deflection and to resist all wind and weather conditions. .3 Secure wood to concrete in a staggered pattern with each row spaced at minimum 600 mm c/c with specified fasteners. .4 Secure wood to metal in a staggered pattern with each row spaced at 450 mm c/c. with specified fasteners at minimum 450 mm c/c. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .5 3.3 Section 06 10 00 ROUGH CARPENTRY Page 5 of 5 Install fasteners in two rows in the direction of the grain, offset one to another in a staggered fashion by approximately 50%. All fasteners shall be placed minimum 10 mm from any edge of framing. SHEATHING INSTALLATION .1 Gypsum board: .1 .2 Plywood: .1 .2 3.4 Install sheathing to curbs, as indicated on the drawings and details. Not less than 2 mm gaps shall be provided between sheets, to allow for material expansion. Unless otherwise indicated, fasten plywood with a minimum of thirty-six fasteners per 1200 mm x 2400 mm sheet. ERECTION .1 Frame, anchor, fasten, tie and brace members to provide necessary strength and rigidity. .2 Countersink bolts where necessary to provide clearance for other work. .3 Bevel leading edge of wood panel products on vertical applications to facilitate membrane installation and as detailed on drawings. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 1 of 26 Part 1 General 1.1 GENERAL .1 1.2 Contractor to provide an original, complete insurance policy identifying specific coverage for torch applied systems. RELATED SECTIONS .1 Section 02 41 13 – Selective Site Demolition. .2 Section 06 10 00 - Rough Carpentry. .3 Section 07 62 00 – Sheet Metal Flashing and Trim. .4 Section 07 92 00 – Joint Sealants. .5 Section 22 05 11 – Plumbing and Drainage. 1.3 REFERENCES .1 American Society for Testing and Materials International, (ASTM) .1 .2 Canadian Standards Association (CSA International) .1 .2 .3 .3 FM 4450, Approval Standard for Class 1 Insulated Steel Roof Decks. Underwriters Laboratories' of Canada (ULC) .1 .2 .3 .4 April 2016 CAN/CGSB-1.108-M89, Bituminous Solvent Type Paint. CGSB 37-GP-56M-80b(A1985), Membrane, Modified, Bituminous, Prefabricated, and Reinforced for Roofing. CAN/CGSB-37.5-M89, Cutback Asphalt Plastic Cement. Factory Mutual (FM Global) .1 .5 CSA-A123.3-05, Asphalt Saturated Organic Roofing Felt. (updated) CAN/CSA-A123.4-04 (R2013) - Asphalt for Constructing Built-Up Roof Coverings nd Waterproofing Systems. Canadian General Standards Board (CGSB) .1 .2 .4 ASTM C1396/C1396M-13, Standard Specification for Gypsum Board. CAN/ULC-S107-10, Standard Methods of Fire Tests of Roof Coverings. CAN/ULC-S126-06, Standard Method for Test for Fire Spread Under Roof Deck Assemblies. CAN/ULC-S704-03, Standard for Thermal Insulation, Polyurethane and Polyisocyanurate Boards, Faced. CAN/ULC-S770-09, Standard Test Method for Determination of LongTerm Thermal Resistance of Closed-Cell Thermal Insulating Foams. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 2 of 26 1.4 ADMINISTRATIVE REQUIREMENTS .1 Convene pre-installation meeting one week prior to beginning Work, with contractor's representative, to: .1 .2 .3 1.5 Verify project requirements. Review installation and substrate conditions. Review manufacturer's installation instructions and warranty requirements. COORDINATION .1 1.6 Coordinate work of this Section with related work specified in other Sections to ensure construction schedule is maintained and water tightness and protection of the building and finished work is maintained at all times. SUMMARY OF WORK .1 Work of this Section includes the removal, replacement and repair of the existing roof including all related work as indicated in the drawings, as specified herein and as required for a complete project. Provide a complete roofing, insulation, flashing and air barrier system. .2 Temporarily lower existing drains and provide temporary drains and provide seals as required to make drains watertight. Remove and replace air seals and raise drain to elevations dictated by design intent before proceeding with roofing operation. .3 ‘WORK AS DESCRIBED’ is held to include all incidental items that by implication, good trade practice, or customary usage are required to complete the work even though they may not be specifically mentioned or shown. 1.7 ACTION AND INFORMATIONAL SUBMITTALS .1 Provide submittals in accordance with Section 01 33 00 - Submittal Procedures. .2 Product Data: .1 .2 .3 April 2016 Provide two copies or an electronic copy of most recent technical roofing components data sheets describing materials' physical properties and include product characteristics, performance criteria, physical size, finish and limitations. Provide two copies or an electronic copy of WHMIS for: .1 Primers. .2 Sealers. .3 Liquid membrane. .4 Adhesives. Provide shop drawings: Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 3 of 26 .1 .2 Indicate flashing, sloped insulation details. Provide layout for sloped insulation. .4 Manufacturer's Certificate: Certify that products meet or exceed specified requirements. .5 Manufacturer's field report: In accordance with Section 01 45 00 - Quality Control. 1.8 QUALITY ASSURANCE .1 Installer qualifications: Company or person specializing in application of modified bituminous roofing systems with 5 years documented experience, approved by manufacturer. .2 Only certified applicators are permitted to use torch welding equipment. .3 Hold a pre-installation meeting prior to the start of roofing works, with the roofing contractor’s representative and the Consultant, to review installation conditions particular to this project. .4 Roof membrane manufacturer shall delegate a representative to visit the work site at the start of roofing installation. Contractor shall engage membrane manufacturer’s technical representative as required to provide technical guidance for and inspection of membrane application. The Contractor shall at all times enable and facilitate access to the worksite by this representative. 1.9 FIELD QUALITY CONTROL .1 Flood Testing: .1 .2 .3 .4 .5 .2 Adhesion Testing: .1 April 2016 If requested by the Consultant, provide water test of all flashing, projections, equipment on roof and roofing system. Co-ordinate test with the Owner’s operations personnel. Temporarily plug drains during testing and raise water levels on the roof to 25 mm and maintain water depth for 24 hours. Monitor site conditions and remove test plugs in the event of inclement weather. OR Temporarily plug drains and raise water levels on the roof to 25 mm. At end of test period, remove drain plugs and check levels for ponding water to verify that specified requirements have been achieved. Repair any areas with ponds exceeding 10 mm in depth, using extra layers of base ply or other acceptable means and re-test as required. Contractor is to assume all costs of testing and correction. If requested by the Consultant, at each roof drainage area, following installation of membrane base sheet, carry out adhesion tests to confirm Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 4 of 26 .2 .3 .4 .3 Sample Testing: .1 .2 .3 .4 1.10 adhesion of membrane to substrate and substrate layers to each other, down to first mechanically attached layer. Locations and timing of tests will be directed by Consultant. Provide labour and materials as required to assist Consultant in conducting tests. If inadequate adhesion is found, conduct further testing to determine the extent of the inadequate adhesion. Replace all defective areas to the satisfaction of the Consultant. Replace substrate materials as necessary with new materials, and patch cut tests with membrane patches extending at least 150 mm beyond the cut. Contractor is to assume all costs of testing and correction. If requested by the Consultant, at each roof drainage area, following installation of membrane base sheet, carry out sample tests to confirm materials and installation of roof assembly components. Sample size to be 300 mm x 300 mm. Locations and timing of tests will be directed by Consultant. If inadequate construction is found, conduct further testing to determine the extent of the inadequate adhesion. Replace all defective areas to the satisfaction of the Consultant. Replace substrate materials as necessary with new materials, and patch cut tests with membrane patches extending at least 150 mm beyond the cut. Contractor is to assume all costs of testing and correction. FIRE PROTECTION .1 Fire Extinguishers: .1 .2 .3 .4 .5 Pressure rechargeable type with hose and shut-off nozzle, ULC labeled for ABC class protection. ULC labeled for A class protection, for wood, paper and fibreboard. Size 14 kg. Have one fully charged ABC extinguisher and one fully charged Type A extinguisher on roof per torch applicator, within 3 m of the propane source. .2 Maintain fire watch for 2 hours after each day's roofing operations cease. .3 Contractors will be required to fill out, submit and adhere to a Hot Work Permit OSBIE form provided by the OCDSB’s site personnel, each day that hot work operations take place. Hot work operations are those that involve open flames or produce heat and/or sparks. Hot Work includes, but is not limited to: .1 April 2016 Torch-applied roofing and welding, application of hot asphalt, brazing, cutting, grinding and soldering. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 5 of 26 1.11 GENERAL REQUIREMENTS .1 Comply with the General Requirements, General Instructions and Supplementary Conditions. .2 Execute work in accordance with this Section and other related Sections, Drawings and Details. .3 Attach roofing to structure to meet requirements of insurance underwriter and authorities having jurisdiction. .4 Regard manufacturer’s printed recommendations as minimum requirement for materials, methods and workmanship not otherwise specified. .5 Contact the Consultant if the specifications conflict with the manufacturer’s recommendations. Otherwise it will be assumed that the Contractor and manufacturer are in agreement with procedures outlined. .6 Advise the Consultant of adjustments to specified roofing procedures caused by weather and site conditions. Make adjustment to specified procedures only after review with the Consultant. .7 Maintain equipment in good working order to ensure control of roofing operations and protection of work. Types of roofing equipment and laying techniques to be employed are to meet the approval of the Consultant. .8 Do not penetrate roof deck with any fastening devices that would do damage or impair the function of the assembly. .9 All temporary drains shall be connected with a mechanical connection (MJ coupling) or a U-flow connection, until new drains are installed. 1.12 DELIVERY, STORAGE AND HANDLING .1 Deliver, store and handle materials in accordance with manufacturer's written instructions. .2 Safety: comply with requirements of Workplace Hazardous Materials Information System (WHMIS) regarding use, handling, storage, and disposal of, sealing compounds, primers and caulking materials. .3 Manufacturer’s recommendations for handling and storing products are to be considered a minimum requirement. .4 Materials shall be delivered to the site, undamaged and in their original packages, with manufacturer’s labels visible, attesting to their conformity to specific standards. .5 Ensure that shelf life of materials has not expired. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 6 of 26 .6 Provide bill of lading for bulk loads of bitumen clearly showing Equiviscous Temperatures (EVT), Flash Point (FP) and Final Blowing Temperature (FBT). .7 Remove damaged material from site and replace all rejected materials with new product. .8 Elevate on raised platform and store as to prevent deformation of materials. .9 Provide and maintain dry, off-ground weatherproof storage. .10 Store rolls of felt and membrane in upright position. Store membrane rolls with selvage edge up. .11 Remove only in quantities required for same day use. .12 Place plywood runways over completed Work and over areas not in Contract, as required, to enable movement of material and other traffic. .13 Store sealants at +5°C minimum. .14 Store insulation protected from daylight and weather and deleterious materials. .15 Handle roofing materials in accordance with manufacturer's written directives, to prevent damage or loss of performance. .16 Avoid stockpiling materials on decks in a way which could cause overloading. .17 On lightweight concrete decking, locate interior structural columns and locate new material packages centered directly above columns. All membrane pallets, protection board pallets and sheathing pallets shall include half loads. 1.13 ENVIRONMENTAL REQUIREMENTS .1 Ensure protection of products that are sensitive to damage by moisture. Do not work during rain, snow or fog. Stop work and make watertight before the onset of inclement weather or when weather appears imminent. .2 Ensure protection of the building from weather at all times. If inclement weather is forecast or appears imminent, postpone work that would risk the building from moisture damage. .3 If it becomes apparent that work would threaten the building watertightness, the Owner has the right to stop work. Any additional expenses due to work stoppage or postponement of work will be at the Contractor’s expense. .4 Ambient Conditions .1 April 2016 Do not install roofing when ambient temperature remains below -18°C for torch application. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 7 of 26 .2 .5 1.14 Minimum ambient temperature for solvent-based adhesive is -5°C. Install roofing on dry deck, free of snow and ice, use only dry materials and apply only during weather that will not introduce moisture into roofing system. COMPATIBILITY .1 Compatibility between materials is essential. Use only materials that are known to be compatible when incorporated in a complete assembly. Provide written declaration to Consultant stating that materials and components, as assembled in system, meet this requirement. .2 Defective work resulting from work with incompatible materials will be considered the responsibility of the Contractor. .3 Repair all work that could result in damage or interfere with performance. 1.15 EXISTING SUBSTRATES .1 Following removal of existing material to the substrate, inspect the deck for soundness and notify the Consultant of any deck found unsound and not suitable for roofing. Do not commence work until conditions are documented and the Consultant rules on the acceptability of surfaces and/or corrective measures required. The cost of any delays due to postponement of work that results from investigating the site problem or obtaining a ruling will be at the Owner’s expense. .2 The commencement of work is proof that the Contractor has accepted surfaces as satisfactory and accepts responsibility for appearance and performance of completed work. .3 Defective work resulting from application of material on unsatisfactory surfaces will be considered the responsibility of the Contractor. .4 The Contractor will be responsible for all repairs, costs and pay all cost and fees required to rectify damage or defective work. Use materials and finish to match the original preconstruction conditions. 1.16 DAILY OPERATIONS .1 1.17 Unless otherwise specified, complete the entire roofing operation up to line of termination of each day’s work, as required by design intent, in order to safeguard and protect the work and building from damage and weather. EXAMINATION .1 Before proceeding with roofing application, ensure that: .1 April 2016 All surfaces are clean and free of debris, snow, frost and moisture. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 8 of 26 .2 .3 .4 The deck is clean and sufficiently dry to ensure specified adhesion will be obtained. Adjacent construction and installation of related work (i.e. curbs, drains, penetrations, wood nailers, etc.) incorporated with the roof are complete. Roof deck is sound, existing fasteners are tight and irregularities are corrected to provide a suitable surface for new roofing. .2 Ensure substrate is smooth. Remove sharp edges or protrusions that could impair the function of the roof assembly. .3 Inform Owner/Consultant in writing of any defects. 1.18 DRAINS AND DRAINAGE PLANE .1 Inspect surfaces and ensure that roof deck is level or sloped to drains in conforming to design intent. .2 Inspect surfaces and ensure that roof drains are set at a level to drain and are connected or capped. .3 Take spot levels to verify that pools of water in excess of 13 mm depth will not form. .4 Tabulate levels and submit to Consultant. .5 Ensure plumbing is accessible and work can be completed as specified. .6 Inspect roof drains to ensure they are open and working properly. .7 Where specified or shown for areas with only one drain, provide overflow scuppers or drains to detail and specified requirements. 1.19 EXAMINE UNDERSIDE OF DECK .1 Inspect the underside of deck to ensure fasteners will not damage the structure, affect interior surfaces or electrical and mechanical services. .2 For drain alterations and pipe hangers, coordinate with plumbing subtrade as per Section 22 05 11 – Plumbing and Drainage, prior to commencement of roofing operations. 1.20 HIDDEN SERVICES .1 April 2016 Investigate the location of all known hidden services by reviewing interior conditions, plans, specifications and drawings for the original building, any subsequent alterations, completion of cut tests and interviewing those involved in the construction and maintenance of building services. These services include but are not limited to mechanical, electrical, cable, communication, computer, security or roof assembly. Ensure all services are located and will be protected Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 9 of 26 from damage under the Contract. In some cases, services may be located over the roof deck and within the roof assembly. Notify Owner/Consultant in such occurrence and proceed with installation as directed. 1.21 EQUIPMENT .1 Inspect equipment affected by the work, including but not limited to roof top equipment, curbs, existing drains and plumbing, mechanical, electrical and lightening protection services, to ensure they are in good repair and working order. Record any damage and advise the Consultant. .2 During re-roofing, ensure that all mechanical equipment, ducts, pipes, etc. are properly supported. .3 Notify Owner and/or Consultant of any equipment which is not operational or damaged prior to the commencement of work. 1.22 ADVISE CONSULTANT .1 1.23 Advise the Consultant of any unusual circumstances affecting the work. Notify the Consultant of any defective or malfunctioning equipment or drainage deficiencies. Do not commence work until defects and incorrect levels have been verified and rectified. PROTECTION OF ROOFTOP EQUIPMENT .1 Remove any equipment and flashing intended for re-use and save from harm. Store in approved location and reset at project conclusion unless specified or shown to be removed. .2 Protect all openings, vents and stacks from weather and contamination from debris. .3 Provide temporary plumber’s plugs to protect drains during roofing operations. Ensure that temporary protection is removed at completion of work period and/or at the end of each day’s work. 1.24 SERVICES .1 Services are to be left operational unless otherwise authorized by the Owner. .2 Unless otherwise specified, the Contractor will be responsible for disconnection, relocation, re-installation and extending all services required to facilitate work under this Contract. Co-ordinate work with the Owner and provide minimum of 48 hours notification if services are to be interrupted. .3 Contractor to verify location of services prior to commencement of work. Notify Owner/Consultant of any unusual conditions. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 10 of 26 .4 The Contractor and their employees must hold valid certificates for the work undertaken. .5 Complete work of this Section as required by local authorities having jurisdiction. Have work inspected and pay all fees relative to such inspection to ensure work meets with published standards and codes. .6 Submit Certificate or Letter of Approval by authority responsible for the work to the Owner and Consultant with final documentation. .7 All fans, air handling units, and any electrical equipment affected by the replacement of the roof sections under this Section, whether disconnected or extended must be inspected by an ESA representative to verify the integrity of the existing wiring and/or the new installation. .8 The roofing Contractor must obtain a "Certificate of Inspection" from the ESA (Electrical Safety Authority 1-887-ESA-7233) and fill in the attached ESA log sheet and provide the certificate to Fishburn Sheridan & Associates Ltd. Failure to do so will result in an amount deducted from the Contractor’s final invoice equal to the cost of doing this work. 1.25 WARRANTY .1 Contractor’s Warranty for Labour and Material: .1 .2 Refer to OCDSB’s Instructions to Bidders. Manufacturer’s Warranty: .1 Refer to OCDSB’s Instructions to Bidders. Part 2 Products 2.1 GENERAL .1 All standards, regulations and specifications listed herein are considered to be the latest available edition. .2 For sealants, mastic, adhesives or caulk, refer to Section 07 92 00 – Joint Sealants. 2.2 SHEATHING MATERIALS .1 Type X gypsum board, to ASTM C1396/1396M, thickness as indicated. .2 Plywood: See Section 06 10 00 - Rough Carpentry. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 11 of 26 2.3 PRIMERS .1 Asphalt Primer: To manufacturer’s recommendations. .2 Self-adhesive membrane primer. As recommended by membrane manufacturer. Use low VOC, polymer emulsion-based primer, unless directed otherwise by Consultant on site. 2.4 AIR/VAPOUR BARRIER MEMBRANE .1 Two-ply built-up membrane consisting of: .1 .2 2.5 No. 15 asphalt saturated organic roofing felts to CAN/CSA A123.3. Type 3 asphalt to CAN/CSA A123.4. MEMBRANE AND MEMBRANE FLASHINGS .1 Acceptable membrane manufacturers: .1 .2 .3 .2 Base sheet membrane and base sheet membrane flashing (non-combustible substrates): To CGSB 37-GP-56M. .1 .2 .3 .4 .5 .6 .3 April 2016 Soprema Group. IKO Industries Ltd. Henry Bakor. Styrene-Butadiene-Styrene (SBS) elastomeric polymer polyester reinforcement, having nominal weight of 180 g/m2. Type 2. Class C - plain surfaced. Grade 1 - standard service. Top and bottom surfaces: .1 polyethylene/polyethylene. Base sheet membrane properties: To CGSB 37-GP-56M. .1 Strain energy (longitudinal/transversal): 9.0/7.0 kN/m. .2 Breaking strength (longitudinal/transversal): 17.0/12.5 N/5 cm. .3 Ultimate elongation (longitudinal/transversal): 60/65 %. .4 Tear resistance: 60 N. .5 Cold bending at -30°C: No cracking. .6 Softening point: ∃ 110°C. .7 Static puncture resistance: > 400. .8 Dimensional Stability: -0.3 / 0.3 %. Self-Adhesive base sheet membrane flashing (combustible substrates): To CGSB 37-GP-56M. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 12 of 26 .1 .2 .3 .4 .5 .6 .4 Cap sheet membrane and membrane flashing: To CGSB 37-GP-56M .1 .2 .3 .4 .5 .6 .5 Styrene-Butadiene-Styrene(SBS) elastomeric polymer, prefabricated sheet, 250 g/m2. Type 1. Class A-granule surfaced. .1 Colour for granular surface: Gray. Grade 1-standard service. Bottom surface polyethylene. Cap sheet membrane properties: To CGSB 37-GP-56M. .1 Strain energy (longitudinal/transversal): 13.0/10.0 kN/m. .2 Breaking strength (longitudinal/transversal): 25.0/16.0 kN/m. .3 Ultimate elongation (longitudinal/transversal): 63/93 %. .4 Tear resistance: 118 N. .5 Cold bending at -30°C: No cracking. .6 Softening point: ∃ 110°C. .7 Static puncture resistance: > 432. .8 Dimensional Stability: -0.2 / 0.2 %. Fireguard Tape .1 .2 April 2016 Styrene-Butadiene-Styrene (SBS) elastomeric polymer prefabricated sheet, polyester and glass reinforcement. Type 2, adhered. Class C - plain surfaced. Grade 2 – heavy duty service. Top and bottom surfaces: .1 Polyethylene/release paper. Base sheet membrane properties: To CGSB 37-GP-56M. .1 Strain energy (longitudinal/transversal): 7.8/7.2 kN/m. .2 Breaking strength (longitudinal/transversal): 15/13.5 N/5 cm. .3 Ultimate elongation (longitudinal/transversal): 60/65 %. .4 Tear resistance: 125 N. .5 Cold bending at -30°C: No cracking. .6 Static puncture resistance: > 560. Modified bituminous membrane supplied in strips, 150 mm wide, 1.6 mm thick, glass fleece reinforced with self-adhesive underside. Standard of acceptance or approved equivalent: .1 Sopraguard by Soprema. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 13 of 26 2.6 LIQUID MEMBRANE .1 Two-component methacrylate or one component polyurethane/bitumen resin, solid content 80% or greater, compatible with roof membrane. .1 .2 2.7 Standard of acceptance or approved equivalent: .1 Alsan Flashing by Soprema. .2 MS Detail by IKO. Reinforcement mesh: As recommended by liquid membrane manufacturer. BITUMEN .1 2.8 Asphalt: To CAN/CSA A123.4, Type 3. POLYISOCYANURATE INSULATION .1 2.9 Rigid foam board Type II, Class 1, Grade 2, manufactured with HC blowing agent meeting requirements of CAN/ULC S-126 and CAN/ULC S107. Conforming to CAN/ULC S704 and CAN/ULC S770 for LTTR values. Approved and listed by Factory Mutual Global for 1-60 and 1-90 wind classification and FM 4450 requirements for Class 1 fire. Thickness as specified or shown with maximum board size 1200 mm x 1200 mm. Fibre-reinforced organic felt facers on both major surfaces of the core foam. SLOPED INSULATION .1 Polyisocyanurate rigid foam board Type II, Class 2, Grade 2, manufactured with HC blowing agent meeting requirements of CAN/ULC S-126 and CAN/ULC S107. Conforming to CAN/ULC S704 and CAN/ULC S770 for LTTR values. Approved and listed by Factory Mutual Global for 1-60 and 1-90 wind classification and FM 4450 requirements for Class 1 fire. Thickness as specified or shown with maximum board size 1200 mm x 1200 mm. Fibre-reinforced inorganic facers on both major surfaces of the core foam. .2 Insulation slopes shall be as indicated on the detailed drawings and roof plans. Modules shall be factory cut to correct slopes. 2.10 PROTECTION BOARD .1 2.11 Protection Board: 6 mm thick asphalt based protection board with non-woven glass facers, as recommended by the membrane manufacturer. SEMI-RIGID MINERAL WOOL INSULATION .1 2.12 Semi-rigid mineral wool, rockwool, or slagwool boards, to CAN/ULC 702.2. SEALERS .1 April 2016 Plastic cement: Asphalt, to CAN/CGSB-37.5. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 14 of 26 .2 2.13 Sealants: See Section 07 92 00 - Joint Sealants. PROTECTION MATERIALS .1 One additional ply of cap sheet membrane. .2 Rubber protection pad: Heavy duty grade, 550 mm x 550 mm or for size as indicated, 8 mm thick, masticated recycled rubber with reinforcement and UV resistant, dimpled surface. 2.14 FASTENERS .1 Vertical membrane flashing fasteners: Spiral nails, screws or masonry anchors with 25 mm solid caps. Minimum length 38 mm. Corrosion resistant. .2 Fasteners to secure existing air/vapour barrier membrane to Lightweight concrete deck: Use glass-filled nylon auger fastener with 25 mm head complete with 76 mm steel plate to secure membrane to lightweight concrete deck. .1 Standard of acceptance or approved equivalent: .1 Polymer GypTec by OMB Roofing Products Trufast TL. .3 Fasteners for exposed metal flashing and cladding to wood or steel: Minimum 38 mm #10 cadmium plated hex head screws, colour matched, with neoprene and steel washers. .4 Fasteners for plywood or sheet metal to concrete deck: Corrosion resistant purpose-made pre-drill, self-tapping concrete screws, minimum 4.78 mm diameter, minimum 25 mm penetration into concrete. .1 Standard of acceptance or approved equivalent: .1 Tapcon. .5 Fasteners for sheet metal into steel: Self-drilling, self-tapping screws, galvanized, #8 or larger size, Teks or equivalent, head to suit application. .6 Fasteners for sheet metal and wood to wood: Corrosion resistant #10 wood screws or nails to suit application. .7 Structural fasteners into wood: Lag screws, 12.7 mm diameter hot dipped galvanized steel, length 125 mm. 2.15 PLUMBING VENTS .1 2-piece spun aluminum with integral flange, diameter to suit existing pipe size, equipped with vandal proof cap. .1 April 2016 Standard of acceptance or approved equivalent: .1 Flash-tite by Lexcor, EVF-1 by Thaler. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 15 of 26 2.16 ROOF DRAINS .1 2.17 See Section 22 05 11 – Plumbing and Drainage. SCUPPERS .1 2.18 Size and materials as specified or shown, fabricated from 0.65 mm (24 ga.) prefinished steel, with minimum 125 mm roof flange and gravel guard to Consultant’s approval. Make all seams continuous and watertight by soldering or heat welding. CONDUIT SUPPORTS .1 Made from 100% recycled rubber and qualified for LEED, UV-resistant, providing a uniform load, electro plated steel for hardware, galvanized channel, 1.9 mm (14 ga.) x 25.4 mm high. .1 2.19 Standard of acceptance or approved equivalent: .1 Dura-Blok rooftop support, DBP/B2400 series. ROOF ACCESSORIES .1 Deck closure: 0.79 mm (22 ga.) galvanized steel. Size to suit opening. Part 3 Execution 3.1 QUALITY OF WORK .1 Do examination, preparation and roofing Work in accordance with Roofing Manufacturer's Specification Manual and CRCA Roofing Specification Manual .2 Do priming in accordance with manufacturer’s written recommendations. .3 Fit the interface of all walls and roof assemblies with durable rigid material sheet metal or plywood providing connection point for continuity of air barrier. .4 Make assembly, component and material connections in consideration of appropriate design loads, with reversible mechanical attachments. .5 In the event that any product contains a manufacturing defect or anomaly, the Contractor shall notify the Consultant and manufacturer immediately and request direction. 3.2 REMOVAL OF EXISTING ROOFING .1 April 2016 On Roof Area 404, remove all roofing, flashing and insulation materials down to concrete deck. Leave existing blocking and parapet construction in place where indicated. Where a built-up air/vapour barrier is present, remove this from the Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 16 of 26 deck unless agreement is otherwise obtained from the Consultant to leave in place. .2 On Roof Area 301, remove all roofing, flashing and insulation materials down to existing air/vapour barrier on gypsum on steel deck. Leave existing blocking and parapet construction in place where indicated. Where a built-up air/vapour barrier is present, remove this from the deck unless agreement is otherwise obtained from the Consultant to leave in place. .3 For lightweight concrete deck (Roof Area 202), remove all roofing, flashing and insulation materials down to existing air/vapour barrier membrane. Leave existing blocking and parapet construction in place where indicated. Secure existing air/vapour barrier membrane to Lightweight concrete deck using glassfilled nylon auger fastener complete with 76 mm steel plate. Drill pilot hole into Lightweight concrete deck a minimum 13 mm deeper than fastener embedment. Use low RPM to install nylon auger fastener. Use fastener density as indicated on Drawings. Consultant may alter fastening requirements based on field testing. .4 Remove existing rooftop equipment where indicated. 3.3 EXAMINATION OF ROOF DECKS .1 Verification of Conditions: .1 .2 Evaluation and Assessment: .1 .3 3.4 Inspect with Consultant deck conditions including parapets, construction joints, roof drains, plumbing vents and ventilation outlets to determine readiness to proceed. Prior to beginning of work ensure: .1 Decks are firm, straight, smooth, dry, free of snow, ice or frost, and swept clean of dust and debris. Do not use calcium or salt for ice or snow removal. .2 Curbs have been built. .3 Roof drains have been installed at proper elevations relative to finished roof surface. .4 Plywood and lumber nailer plates have been installed to deck, walls and parapets as indicated. Do not install roofing materials during rain or snowfall. MECHANICAL EQUIPMENT DISCONNECTION / MODIFICATION / RECONNECTION .1 April 2016 Perform disconnection, extension, modification, and reconnection of mechanical equipment in accordance with drawings provided. Obtain approval from Consultant prior to making adjustments not scheduled. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 17 of 26 .2 3.5 Contractor is responsible, by way of approved subcontractor, for disconnection extension, modification, and reconnection of all operating HVAC equipment in work area including at interior. All mechanical equipment must be properly tagged out of service (especially where gas is present). ESA certificates are required for all mechanical and electrical reconnections. Approved electrical contractors are included in OCDSB’s front end document. PROTECTION OF IN-PLACE CONDITIONS .1 Cover walls, walks and adjacent work where materials hoisted or used. .2 Use warning signs and barriers. Maintain in good order until completion of Work. .3 Protect roof from traffic and damage. Comply with precautions deemed necessary by Consultant. .4 At end of each day's work or when stoppage occurs due to inclement weather, provide protection for completed Work and materials out of storage. .5 Metal connectors and decking will be treated with rust proofing or galvanization. .6 Fit the interface of the walls and roof assemblies with durable rigid material sheet metal or plywood providing connection point for continuity of air barrier. 3.6 PRIMING .1 Unless otherwise indicated or directed by Consultant, prime all surfaces which will be in direct contact with bituminous materials at the rate of 0.15 L/m2 to manufacturer’s recommendations. For self-adhering membrane, install primer at a rate recommended by manufacturer. Ensure that surfaces are tack-free before proceeding. .2 Limit quantity of primer at deck openings and points of termination and provide supplemental protection to prevent bleedthrough to the building interior. .3 Roll primer into surface. .4 Re-prime all surfaces, including pre-primed surfaces, that become contaminated with dust or become marred due to their exposure to roof traffic or weather. 3.7 ASPHALT .1 April 2016 Heat asphalt to obtain proper application temperature and viscosity at point of contact. The EVT range of temperature is the range of roof bitumen recommended temperature (±15°C) at the mop, cart or mechanical spreader just prior to application. Obtain EVT range of the bitumen in use from the asphalt supplier. If heating temperatures are not supplied on the containers or bills of lading for the asphalt on site, heat to no more than 246°C (475°F). Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 18 of 26 .2 In cold weather, insulate pump pipes and transport bitumen on roof in insulated carriers to minimize temperature fall back between kettle and point of application. .3 Bitumen shall not be heated to flash point or held at final blowing temperature for more than 4 hours to prevent asphalt fallback. .4 Unless otherwise specified by manufacturer’s literature, use the following EVT Temperatures. Mechanical Application Type III 462°F (±25°F) 239°C (±15°C) Mop Application Type III 437°F (±25°F) 225°C (±15°C) .5 Maintain constant supervision of tankers and kettles to ensure that bitumen is not overheated. Check temperature of bitumen in kettle at a minimum of 30-minute intervals with an accurate thermometer. Maintain a record of bitumen temperatures. .6 Install all bitumen in a uniform; continuous application insuring good adhesion is achieved. For glass felts, apply at the rate of not less than 1.2 kg/m2 per ply. Ensure that bitumen bleeds out from both sides of the roll not less than 23 mm. Heat asphalt so that temperature does not fall below 204°C (400°F) during installation. .7 Do not place kettles on the roof, unless specifically authorized by the Consultant. 3.8 BUR AIR/VAPOUR BARRIER MEMBRANE .1 Air/vapour barrier membrane is to consist of 2-plies of #15 felt laid solid with Type III asphalt. .2 Complete work and maintain water tightness of assembly. .3 Cover open joints and cracks in deck in a 150 mm wide strip of #15 felt mopped with limited quantities of Type III bitumen. Keep bitumen back from deck openings and points of termination to prevent bleedthrough. Provide backing or semi-flexible insulation fill to further minimize the potential for drips. .4 Install air/vapour barrier continuously under wood blocking at perimeters and roof openings. Avoid contaminating adjacent surfaces with bitumen. .5 Install felts running with or at right angles to slope of deck as specified or dictated by roof design. Broom felts into place to ensure total contact with bitumen. .6 Surface of felts may be left temporarily uncoated if completed operation is to be finished the same day. If scheduled operation cannot be completed the Contractor shall coat all surfaces solid with bitumen and install temporary enveloping seals at all points of termination. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 19 of 26 .7 If the air/vapour barrier is to be used as a temporary roof and the Contractor chooses to leave the felts uncoated to allow for foot traffic, the Contractor shall install one additional ply of glass felt laid solid with Type III bitumen. Temporarily lower drains and provide seals to drains and roof penetrations. Remove and replace temporary seals and raise to elevations dictated by design intent before proceeding with roofing operation. .8 Extend air/vapour barrier as indicated using self-adhered membrane. 3.9 INSULATION – ALL LAYERS – ASPHALT ADHERED .1 Over bituminous air/vapour barrier and for multiple insulation layers, secure insulation laid solid with 1-1.5 kg/m2 hot asphalt. .2 Stagger all joints of insulation a minimum 300 mm. .3 Stagger both end and side joints between insulation layers. .4 Butt sheets of insulation with moderate contact. Do not force insulation into place. Cut neatly at projections and points of termination. Replace all broken, damaged or misfit boards as work progresses. Discard and dispose of all boards with moisture on facers. .5 Where necessary, back-cut insulation to allow it to conform and stay bonded to irregular surfaces without bridging. Subsequent to placement, walk insulation into place to ensure positive bonding is achieved. 3.10 SLOPED (TAPERED) INSULATION .1 At all locations of sloped insulation provide shop drawings from sloped insulation manufacturer for Consultant’s review prior to installation. .2 At all new and existing drain locations, provide sloped polyisocyanurate insulation sump around drain to promote positive drainage. Total sump size to be 1220 mm x 1220 mm with maximum depression of 25 mm, unless otherwise indicated. .3 Installation methods for sloped insulation to be same as for upper layers of base insulation, using hot asphalt as specified. 3.11 PROTECTION BOARD .1 Adhere protection board to insulation with hot asphalt fully adhered at the rate of 1.0-1.5 kg/m², as for insulation. .2 Place boards in parallel rows with end joints staggered. Tape joints in protection board with fireguard membrane where combustible surfaces are directly below. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 20 of 26 .3 3.12 Where protection board is specified on nailable vertical surfaces, secure protection board using large-head roofing nails at 200 mm centres each direction and tape all joints with fireguard tape. MODIFIED BITUMINOUS MEMBRANE - GENERAL APPLICATION .1 Inspect and seal all substrates to eliminate fire hazard. Use fireguard tape as required or recommended by manufacturer. .2 Mechanical spreaders are not permitted to install modified membranes. .3 Use only bitumen, sealants, adhesive or mastics as specified by membrane manufacturer. Provide written approval from manufacturer when proposing any alternatives or substitutions. .4 Lay out all sheets as to allow them to relax a minimum of 30 minutes. When temperatures are below 4.4°C keep and lay out rolls in heated storage. Install rolls before temperature fallback of the sheet occurs. .5 Roof membrane to be installed in one sheet if possible. .6 Lay all membrane starting at low point to ensure that seams do not face water flow. Roll all membrane into place, true to line, free of buckles, air pockets, fishmouths and tears. .7 Overlap all end laps minimum 150 mm and side laps 75 mm. .8 Offset all side laps between plies by 50%. .9 Offset all end laps between plies minimum 1200 mm. .10 At valley locations, run membrane continuously with the slope of the main roof. Lay out all sheets to ensure minimum side laps are maintained through valley area and short section of roof beyond. At these locations the side laps for the main roof will increase. Install membrane to details and Consultant’s direction onsite. .11 Ensure that a watertight seal is achieved at all overlaps and points of termination. .12 Carry base sheet flashing over face of building as shown on the drawings. .13 Carry membrane up all vertical surfaces to point shown. Cut off corners at 45° at end laps to be covered by the next roll prior to installation of following sheet. .14 Terminate base sheet up all verticals 50 mm, secure on vertical with 38 mm nails with 25 mm metal heads at 225 mm c/c Verify procedure with Consultant on site. Seal fasteners through membrane immediately with Type ‘A’ sealant. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 21 of 26 .15 3.13 Do not walk on membrane during applications and until sufficient cooling has taken place as to allow for traffic without doing damage or marking surface. MEMBRANE APPLICATION .1 In accordance with Summary of Work, drawings and details, install new membrane and flashings system. .2 Install all membrane in strict accordance with manufacturer’s latest printed instructions and application methods. 3.14 BASE SHEET (TORCH APPLICATION) .1 Install 1-ply base sheet membrane running with the roof slope, starting at the low point. Layout roll in place to verify alignment and proper overlap and re-roll prior to torching. .2 Fully torch in place base sheet membrane using proper application techniques as specified by membrane manufacturer. .3 Install membrane true to line and free of wrinkles, air pockets, voids, excessive bitumen flow or other irregularities. Ensure the membrane is not overheated at any location. Should any of these conditions occur, immediately stop membrane application and correct the deficiency before proceeding. Notify Consultant and obtain his approval for proposed repair methods. Questionable areas will require to be cut out and replaced. .4 Ensure that a watertight seal of all membrane joints and points of termination is achieved with a torch and trowel. .5 Extend membrane up vertically 50 mm. Secure with membrane flashing fasteners at 300 mm c/c, where substrate is nailable. .6 Review base membrane for low areas (ponding) and correct with additional base sheet membrane. 3.15 BASE SHEET FLASHINGS (SELF-ADHERED APPLICATION) .1 All flashings to be cut across the roll in 1 m sections. Cut off corners at end laps to be covered by next flashing piece. .2 Provide chalk lines and install all membrane true to line. Install gusset reinforcement pieces at all corner locations. .3 Ensure wall or eave surfaces are clean and dry, free of contaminants or other irregularities. Re-prime as necessary. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 22 of 26 .4 Commence flashings from the drain or low points and overlap all side laps minimum 75 mm. Base sheet flashings to extend 100 mm onto roof surface and terminate as shown in drawings. .5 Place sheet into primer or adhesive and press into place using hand roller to ensure uniform adhesion. Use hot air welder on all seams and joints to ensure a waterproof seal on all points of termination. Apply flashings free of air pockets, voids, wrinkles or fishmouths. 3.16 CAP SHEET (TORCH APPLICATION) .1 Prior to installation, unroll the cap sheet and check for granular embedment width and alignment. .2 Layout membrane to ensure side lap of cap sheet does not occur within 150 mm of roof drain. .3 Install specified cap sheet membrane running with the roof slope, starting at the low point. Layout roll in place to verify alignment and proper overlap and re-roll prior to torching. Offset cap sheet side laps 50% to base sheet side laps, ensure lap does not lie within 150 mm of a roof drain. .4 Install 1-ply cap sheet membrane full torched in place using proper application techniques as specified by the membrane manufacturer. .5 Install membrane by softening both contact surfaces simultaneously with recommended torching equipment. During application, unroll membranes slowly into fluid bitumen ensuring consistent 3 mm to 6 mm flow protrudes each side of the roll. .6 Install membrane true to line and free of wrinkles, air pockets, voids, excessive bitumen flow or other irregularities. Ensure the membrane is not overheated at any location. Should any of these conditions occur, immediately stop membrane application and correct the deficiency before proceeding. Notify Consultant and obtain his approval for proposed repair methods. Questionable areas will require to be cut out and replaced .7 Using a torch and trowel, embed granules at end laps and where required on surface of cap sheet to ensure proper bonding of membrane overlaps. 3.17 CAP SHEET FLASHINGS (TORCH APPLICATION) .1 All flashings to be cut across the roll in 1 m sections. Cut off corners at end laps to be covered by next flashing piece. .2 Provide chalk lines and install all membrane true to line. Install base sheet gusset reinforcement at all corner locations. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 23 of 26 .3 Commence flashings from the drain or low points and overlap all side laps minimum 75 mm. Cap sheet flashings to extend 150 mm onto roof surface and terminate as shown in drawings. At wall locations, unless otherwise specified, cap sheet flashings to extend up 50 mm higher than base sheet flashings. .4 Where required by Summary of Work and details, install 50 mm wide continuous strip of Type ‘A’ sealant to the tops of parapets or eaves to prevent bitumen spillage on the building exterior. .5 Install membrane by softening both contact surfaces simultaneously with recommended torching equipment. During application, unroll membrane slowly into fluid bitumen ensuring consistent 6 mm flow protrudes each side of the roll. .6 Unroll and work sheet into place using torch, trowel and wet sponge to ensure proper placement and adhesion. .7 Install membrane true to line and free of wrinkles, air pockets, voids, excessive bitumen flow or other irregularities. Ensure the membrane is not overheated at any location. Should any of these conditions occur, immediately stop membrane application and correct the deficiency before proceeding. Notify Consultant and obtain his approval for proposed repair methods. Questionable areas will require to be cut out and replaced. .8 Touch up bare spots, corners, scuffs and bleedout runs on cap sheet with granules matching membrane colour, immediately following installation. Use hot air welder, torch or Type ‘A’ sealant to adhere granules to sheet. 3.18 NEW CAST IRON ROOF DRAINS .1 See Section 22 05 11 – Plumbing and Drainage for plumbing work. .2 Install self-adhered membrane air seal around drain and extend onto air/vapour barrier minimum 150 mm. .3 Unless otherwise specified or shown, provide prefabricated sump of sloped polyisocyanurate insulation 1200 mm each side of the centre of the drain. Reduce polyisocyanurate insulation thickness to minimum 19 mm at drain to provide positive roof drainage (make allowance for thickness of all flanges and clamps) and ensure water flow will not be impeded. .4 Complete roof membrane, installing additional 1 m x 1 m base sheet flashing centred over drain opening. .5 Fully coat drain flange to receive roofing with modified sealant and continue modified bitumen over flange. Neatly trim and work membrane to interior face and seal with Type ‘A’ sealant. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 24 of 26 .6 Set clamping ring in solid bed of Type ‘A’ sealant. Secure clamp ring and integral screen as dictated by drain design immediately after membrane is installed. Tighten bolts to ensure a permanent watertight compression seal. .7 Install and bolt strainers with heavy iron mechanical bracket to ensure the drain screen remains permanently in place to the Consultant’s approval. .8 Install test plug, water test roof and repair leaks. Remove test plug once complete. .9 Restore interior finishes affected by work of this Contract to match original materials and finishes to Consultant’s approval. Insulate rainwater leader pipes as required by Summary of Work in accordance with Section 22 05 11 – Plumbing and Drainage. 3.19 SCUPPERS .1 Install new scuppers to requirements of the drawings and details. .2 Verify that location will allow for positive drainage and will not conflict with existing facilities or entrance ways. .3 Verify that drainage to lower levels can be adequately accommodated without problems. .4 Reduce insulation thickness minimum 25 mm, 1200 mm from scupper to provide positive roof drainage and ensure water flow will not be impeded. .5 Cut neat notch through membrane roofing 19 mm larger than specified scupper size. Set scupper on top of completed membrane prior to membrane flashing installation. .6 Install scupper, plumb, level and true to line. Secure flanges to the substrate at outer edges at a minimum of four locations. .7 Set and cover scupper flanges with Type ‘A’ sealant prior to roofing. .8 Flash scuppers with 1-ply modified bitumen base sheet adhered in place. Extend base sheet 125 mm beyond scupper flange. .9 Provide new downspouts in conformity with Summary of Work, drawings and details. See Section 07 62 00 - Sheet Metal Flashing and Trim for specification of eavestroughs and downspouts. 3.20 PLUMBING VENTS .1 April 2016 Inspect and clean soil pipes of debris to ensure they are operational. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 25 of 26 .2 Protect exposed surface during roofing operation and clean surfaces free of bitumen before leaving site. .3 Make all penetrations air and watertight at air/vapour barrier by installing selfadhesive membrane flashings 150 mm onto air/vapour barrier and carry up and around projection. Clamp in place and caulk. .4 Trim base sheet at roof projections. .5 Adjust existing pipes to new flashing heights by either cutting down or extending pipes with matching materials attached with mechanical couplers. Ensure pipes are 38 mm higher than flashing to allow for sealing to prevent condensation. .6 Clear all projections free of contaminants and seal junction of base sheet and roof projections with trowel applications of sealant as shown on drawings. .7 Install all metal flanges to be built into the membrane before the installation of cap sheet. Insulate sleeves in accordance with drawings as specified. Where required, install telescoping caps to detail. .8 Prime topside and underside of all flanges to be incorporated with roofing prior to application. Use primer supplied by the membrane manufacturer. All primer to be dry before installation of membrane roofing or flashing. .9 Before installing flashings, install 1-ply base sheet extending to opening. Set flanges in bed of Type ‘A’ sealant prior to membrane installation, as per manufacturer’s recommendations. .10 Install 1-ply of base sheet flashings thermofused to the flange to within 25 mm from upturn and continuing a minimum of 225 mm beyond flange. Continue cap sheet to metal upturn. Seal around upturn junction with sealant and touch up with matching granules, as per manufacturer’s recommendations. .11 Install rain collars over sleeves and stacks as indicated to match adjoining materials and seal with sealant as indicated on drawings. 3.21 CONDUIT SUPPORTS .1 Provide alterations in pipe to raise existing pipe minimum 300 mm above finished roof level as required by Summary of Work, drawings and details. .2 Elevate pipe on supports to maximum 300 mm above finished roof surface or to clear all expansion and control joints by 25 mm unless otherwise specified or shown. Provide an additional membrane ply and rubber pad under pipe supports as specified elsewhere in the Section. .3 Tighten roller assembly into bracket at desired height and secure in place with lock nuts. Ensure roller assembly is allowed 3 mm minimum spacing and will accommodate movement of pipes due to expansion and contraction. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Section 07 52 00 Woodroffe High School MODIFIED BITUMINOUS MEMBRANE ROOFING 2410 Georgina Drive, Ottawa Page 26 of 26 .4 Install supports at spacing required to support the pipe without deflection and to safeguard the roof from damage due to excessive spot loading, as per CSA B149.1. .5 Locate supports over joists, beams or other structural members wherever possible. .6 Maximum spacing between supports to be 5 m. Increase frequency of supports where pipes will be subject to snow loading. For pipes greater than 75 mm diameter, refer to manufacturer’s drawings. Double pads will be required where pipes change direction, roof elevation changes and at roof control or expansion joints. .7 Paint gas lines with gas line paint, following modifications. .8 Complete work of this Section as required by local authorities having jurisdiction. Make any adjustments to natural gas system only with fitters certified by the Ministry of Consumer And Commercial Relations. Conform to CAN/CSA B149.1-05 and all supplementary regulations. Have work inspected and pay all fees related to such inspection to ensure work meets with published standards and codes. Submit certificate or letter of approval with final documentation to Owner’s Project Coordinator and Consultant. 3.22 CLEAN UP .1 At all times, keep the premises free from accumulation of waste materials or rubbish. Stock piling of debris on the roof will not be permitted. .2 Repair defects in surface and bitumen runs with granules to match existing to leave the roof in an even consistent finish. .3 Leave roof clear of debris and bitumen left by spills and machine tracking. .4 Leave grounds and building free of debris and bitumen spread by pedestrian traffic where applicable. .5 Clean surfaces and penetrations of all contaminants and touch up to the satisfaction of the Owner. Include rooftop equipment, curbs, soil stacks, sleeves, gas lines, vents, drains and ladders. .6 Check drains to ensure they are functional and where required remove all debris by vacuum. .7 At the completion of the work remove all rubbish, tools, equipment and surplus materials. .8 Be responsible to repair and pay all costs and fees required to rectify damage caused by work of the Contract with materials and finish to match original. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED SECTIONS Section 07 62 00 SHEET METAL FLASHING AND TRIM Page 1 of 6 .1 Section 06 10 00 - Rough Carpentry. .2 Section 07 52 00 - Modified Bituminous Membrane Roofing. .3 Section 07 92 00 – Joint Sealants. .4 Section 22 05 11 – Plumbing and Drainage. 1.2 REFERENCES .1 American Society for Testing and Materials International (ASTM) .1 .2 Canadian General Standards Board (CGSB) .1 .3 1.3 Roofing Specifications Manual 1997. Health Canada/Workplace Hazardous Materials Information System (WHMIS) .1 .5 CAN/CGSB-1.108-M89, Bituminous Solvent Type Paint. Canadian Roofing Contractors Association (CRCA) .1 .4 ASTM A653/A653M-13, Standard Specification for Steel Sheet, ZincCoated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process. Material Safety Data Sheets (MSDS). SMACNA – Architectural Sheet Manual – 1993 Edition. COORDINATION .1 1.4 Coordinate work of this Section with Related Work specified in other Sections to ensure construction schedule is maintained and watertightness and protection of the building and finished work is maintained at all times. EXAMINATION .1 Do not commence work until surface to be covered has been inspected. .2 Inspect work and advise the Consultant of conditions that would adversely affect the work of this trade. .3 Commencement of work is proof that the Contractor has accepted surfaces as satisfactory for intended operations and accepts responsibility for appearances and performance of completed work. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .4 1.5 Section 07 62 00 SHEET METAL FLASHING AND TRIM Page 2 of 6 Repair damaged and inferior work caused by work of this Contract with materials and finish to match original to the Consultant’s approval. SUBMITTALS .1 Submit to the Consultant a list of materials intended for use before they are ordered. Submit samples in accordance with Section 01 33 00 – Submittal Procedures. .2 Product Data: .1 .2 .3 Shop Drawings: .1 .4 Submit duplicate 50 x 50 mm samples of each type of sheet metal material, finishes and colours. Quality assurance submittals: Submit following in accordance with Section 01 45 00 - Quality Control. .1 1.6 Shop drawings: Submit drawings stamped and signed by professional engineer registered or licensed in Province of Ontario, Canada. Samples: .1 .5 Submit manufacturer's printed product literature for sheet metal flashing systems materials, specifications and datasheet and include product characteristics, performance criteria, physical size, finish and limitations. Submit copies of WHMIS MSDS - Material Safety Data Sheets in accordance with Section 01 35 29.06 - Health and Safety Requirements and Section 01 35 43 - Environmental Procedures. Submit manufacturer's installation instructions and special handling criteria, installation sequence and cleaning procedures. MOCK-UP .1 Submit shop drawings and provide mock-up in accordance with Section 01 33 00 – Submittal Procedures. Before installing materials, provide a 1200 mm mock-up for each profile before fabrication. Cost of mock-up to be included in the Contractor’s base bid. .2 Mock-up samples to indicate type, colour, size, method of joints, seam, expansion provisions, stiffeners, cleat fasteners and method of sealing joints. Fit mock-up to each applicable roof profile or edge. .3 Review mock-up with drawings to ensure design intent can be achieved. Verify all elevations including those with matching materials and sections. Verify that continuity of air seals can be achieved. Verify attachments, methods for securing and strengths to ensure that work can support the anticipated loads and will remain in place against all wind, weather and service condition without warping or deforming. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 07 62 00 SHEET METAL FLASHING AND TRIM Page 3 of 6 .4 Make adjustments to the work that results from a review of the mock-up without additional cost. .5 Acceptable mock-ups may be left in place as part of the final product. Part 2 Products 2.1 GENERAL .1 All standards, regulations and specifications listed herein are considered to be the latest available edition. .2 Compatibility between materials is essential. Use only materials that are known to be compatible when incorporated in a completed assembly. 2.2 PREFINISHED SHEET METAL .1 Pre-finished metal flashings: As shown on drawings, fabricate from 0.65 mm (24 ga.) steel to ASTM A653 Grade 230 with G90 zinc coating. Surface with Perspectra Series baked enamel finish. Colour to match existing from manufacturer’s standard colour range. .2 Pre-finished steel cladding: Same material as metal flashings, profile to match existing. 2.3 ACCESSORIES .1 Z-girts: Preformed or break-formed profiles, commercial quality galvanized steel, 1.01 mm thick (20 ga.). .2 Metal cleat: same material as metal flashings, 50 mm wide @ 600 mm c/c. .3 Continuous metal starter strip: 0.71 mm (24 ga.) galvanized steel, secured at 400 mm c/c. .4 Use galvanized, copper, aluminum or stainless steel nails or screws as most compatible with materials and preservatives being utilized. .5 Nails: Annular threaded nails of length to penetrate into bases minimum 25 mm. No. 8 screws to penetrate wood 19 mm at 600 mm c/c. .6 Masonry fasteners: Tapcon, Permagrip or Tapgrip or Rawl. Spike sized to penetrate concrete 38 mm minimum as specified or shown. .7 Exposed fasteners: Where exposed fasteners are specified or as shown, use #10 screws with metal and neoprene washers pre-finished to match colour of flashing. Alternatively, use screws with colour match nylon caps where shown or approved by the Consultant. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 07 62 00 SHEET METAL FLASHING AND TRIM Page 4 of 6 .8 Screws for starter strips and fascia: #8 @ 400 mm c/c. .9 Sealant: Refer to Drawings and Section 07 92 00 – Joint Sealants. .10 Bitumen paint: To CAN/CGSB-1.108 Type II. Gilsonite asphalt paint. .1 2.4 Acceptable product: 810-07 by Henry or approved equivalent. FABRICATION .1 Fabricate metal flashings and other sheet metal work in accordance with applicable details, as indicated. Where not indicated, follow applicable CRCA ‘FL’ series details. .2 Metal shall be formed on a bending brake, shaping trimmed and hard seaming shall be done on bench, as far as practicable, with proper sheet metal working tools. Angles of bends and folds for interlocking metal shall be made with full regard to expansion and contraction to avoid buckling and to avoid damaging metal surfaces. .3 Fabricate all possible work in shop in maximum 2400 mm lengths by brake forming, bench cutting, drilling and shaping. Match existing profiles where metal flashing is to be repaired. .4 Hem exposed edges on underside 13 mm. Mitre and seal corners with sealant. .5 Form sections square, true and accurate to size, free from distortion and other defects detrimental to appearance or performance. .6 Dry joints are to be tight but not dented so as to permit slight adjustments of sheets and yet remain watertight. .7 Lock seams at all corners. .8 Apply isolation coating to metal surfaces to be embedded in concrete or mortar. .9 Supply all accessories required for installation of sheet metal work of this Section. Fabricate accessories of same material to which they will be used. 2.5 REGLETS AND SCUPPERS .1 April 2016 Form reglet and scupper flashings from same material as other metal flashings, unless otherwise indicated. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 3 Execution 3.1 MANUFACTURER'S INSTRUCTIONS .1 3.2 Section 07 62 00 SHEET METAL FLASHING AND TRIM Page 5 of 6 Compliance: comply with manufacturer's written recommendations, including product technical bulletins, handling, storage and installation instructions, and datasheets. INSTALLATION .1 Install sheet metal flashings at copings, walls, expansion joints, roof openings and other components required to protect the membrane flashings as shown on the drawings or otherwise required. Where not indicated, follow applicable CRCA ‘FL’ series details. .2 Install Z-girts as required for continuous support of siding panels, where indicated on drawings. Fasten to structural substrate as indicated. .3 Install continuous concealed starter strips at all exterior faces. Install cleats between lock joints and as indicated to permanently hold flashing in place. Install hook strip fasteners with 2 fasteners per cleat. .4 Sheet metal work shall be installed to cover the entire area it protects and shall be watertight under all service and weather conditions. Install in a uniform manner, true to line, free of dents, warping and distortion. .5 Back-paint sheet metal that comes into contact with another kind of metal, masonry or concrete with bituminous paint at the rate of 0.15 L/m2. .6 Install sheet metal with concealed fasteners at lock joints. Exposed fastening will only be permitted with the approval of the Consultant. When exposed fasteners are shown, space all fasteners evenly in an approved manner. Use lead plugs and screws with neoprene washers where fasteners are exposed, otherwise use concrete drive fasteners where metal flashings are installed over concrete masonry. .7 Join sheet metal by “S” lock seams, to permit thermal movement. Seal all fasteners and completely fill all joints with Type ‘B’ sealant as flashing is being installed. Clean off all excessive visible material subsequent to installation. .8 When flashing is being installed in more than one piece, offset joints in adjacent flashings by approximately 50%. .9 Form inside and outside corners by means of locked seams. Do not use pop rivets unless accepted by Consultant. .10 Slope all metal to interior of roof area to maintain slope, unless otherwise indicated. Do not form open joints or pockets that fail to drain water. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .11 3.3 Section 07 62 00 SHEET METAL FLASHING AND TRIM Page 6 of 6 Where existing reglets are to be re-used, remove existing sealant and re-cut to conform to the size requirements specified herein. REGLETS .1 Cut reglets in existing mortar joint or other materials as indicated. Unless otherwise indicated, cut continuous rectangular slot 25 mm deep height of mortar joint where metal flashings are to terminate. Clean free of dust and contaminants. .2 Install membrane flashing materials as indicated. Form metal flashing to fit into reglet slot with return. .3 Install lead wedges at maximum 300 mm c/c, keep back 6 mm from face of joint. .4 Install backer rod and sealant Type ‘B’ to fill reglet slot and shed water out onto metal flashing face. Tool uniformly. .5 Fasten metal flashing to vertical walls as indicated below reglet level, maximum 900 mm on centre. .6 Proceed in accordance with Section 01 74 11 - Cleaning. .7 On completion and verification of performance of installation, remove surplus materials, excess materials, rubbish, tools and equipment. Remove and replace all sheet metal sections that received surface damage or scratches during fabrication, delivery or installation. .8 For scratches and scuffs to be retained in the new installation, use touch up paint recommended by the metal material supplier. .9 Leave work areas clean, free from grease, finger marks and stains. 3.4 INSPECTION AND TESTING .1 Work of this section shall be inspected in accordance with Section 01 45 00 – Quality Control. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED SECTIONS .1 Section 06 10 00 - Rough Carpentry. .2 Section 07 52 00 - Modified Bituminous Membrane Roofing. .3 Section 07 62 00 – Sheet Metal Flashing and Trim. .4 Section 08 11 16 – Aluminum Doors and Frames. .5 Section 08 44 13 – Glazed Aluminum Curtain Walls. .6 Section 08 50 00 – Windows. .7 Section 08 80 50 – Glazing. .8 Section 22 05 11 – Plumbing and Drainage. 1.2 Section 07 92 00 JOINT SEALANTS Page 1 of 6 REFERENCES .1 Canadian General Standards Board (CGSB) .1 .2 .3 .2 Health Canada/Workplace Hazardous Materials Information System (WHMIS) .1 1.3 CAN/CGSB-19.13-M87, Sealing Compound, One Component, Elastomeric, Chemical Curing. CAN/CGSB-19.21-M87, Sealing and Bedding Compound Acoustical. CAN/CGSB-37.5-M89, Cutback Asphalt Plastic Cement. Material Safety Data Sheets (MSDS). COORDINATION .1 1.4 Coordinate work of this Section with Related Work specified in other Sections to ensure construction schedule is maintained and watertightness and protection of the building and finished work is maintained at all times. EXAMINATION .1 Do not commence work until surface to be covered has been inspected. .2 Inspect work and advise the Consultant of conditions that would adversely affect the work of this trade. .3 Commencement of work is proof that the Contractor has accepted surfaces as satisfactory for intended operations and accepts responsibility for appearances and performance of completed work. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.5 Section 07 92 00 JOINT SEALANTS Page 2 of 6 SAMPLES .1 1.6 Submit samples in accordance with Section 01 33 00 – Submittal Procedures. MOCK-UP .1 Construct mock-ups in accordance with Section 01 33 00 - Submittal Procedures. .2 Provide a list of materials and manufacturer’s colour charts to the Consultant for review. .3 Before proceeding with fabrication submit samples and provide a 1200 mm mock-up of all joints to be sealed showing size, shape, depth of joint, back-up material, primer and sealant. Mock-up may be part of finished work. .4 Allow 24 hours for inspection of mock-up by the Consultant before proceeding with sealant work. 1.7 DELIVERY, STORAGE AND HANDLING .1 1.8 Deliver and store materials in original wrappings and containers with manufacturer’s seals and labels, intact. Protect from freezing, moisture, water and contact with ground or floor. ENVIRONMENTAL AND SAFETY REQUIREMENTS .1 Comply with requirements of Workplace Hazardous Materials Information System (WHMIS) regarding use, handling, storage and disposal of hazardous materials; and regarding labeling and provision of material safety data sheets acceptable to Labour Canada. .2 Conform to manufacturer’s recommended temperatures, relative humidity and substrate moisture content for application and curing of sealants including special conditions governing use. .3 In confined spaces provide portable supply of outside air and exhaust fans to ensure fumes will not impact workmen or building occupants. .4 Compatibility is essential in use of any materials that will be compatible when incorporated in finished assembly. Part 2 Products 2.1 MATERIALS .1 April 2016 Sealants acceptable for use on this project must be listed on CGSB Qualified Products List issued by CGSB Qualification Board for Joint Sealants. Where sealants are qualified with primers use only these primers. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 Modified bitumen sealant (Sealant Type ‘A’): .1 .2 .3 .2 .2 .3 Single-component, paintable, suitable for interior wood, painted gypsum board, aluminum and steel surfaces. For use on interior surfaces only. Standard of acceptance or approved equivalent: .1 Alex Pus Acrylic Latex Caulk Plus Silicone by DAP. .2 Tremflex 834 by Tremco. .3 133 Siliconized Latex by Mulco. .4 AC-20 Plus Silicone by Pecora. Preformed compressible and non-compressible back-up materials: .1 .2 2.2 Non-sag: To CAN/CGSB-19.13, Type 2, MCG-2-25, colour to match surfaces. Standard of acceptance or approved equivalent: .1 Dymonic by Tremco. .2 Sonolastic NP1 Ultra by Sonneborn. Siliconized acrylic latex sealant for interior finishes (Sealant Type ‘E’): .1 .5 For penetration and terminations of bituminous and modified bituminous membrane: to CAN/CGSB-37.5. As recommended by membrane manufacturer. Standard of acceptance or approved equivalent: .1 Sopramastic 200 by Soprema. .2 MBR Flashing Cement by Johns Manville. .3 Polybitume 570-05 by Henry Bakor. Urethanes one part (Sealant Type ‘B’): .1 .4 Section 07 92 00 JOINT SEALANTS Page 3 of 6 Backer rod: .1 Polyethylene, urethane, neoprene or vinyl foam closed cell, oversized 30 to 50 %, Shore ‘A’ hardness 20, tensile strength 140 to 210 kPa. Bond breaker tape: .1 Polyethylene bond breaker tape which will not bond to sealant. JOINT CLEANER .1 2.3 Non-corrosive and non-staining type, compatible with joint forming materials and sealant recommended by sealant manufacturer. PRIMER .1 April 2016 As recommended by sealant manufacturer for specific substrate adhesion. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 3 Execution 3.1 PROTECTION .1 3.2 Section 07 92 00 JOINT SEALANTS Page 4 of 6 Protect installed work of other trades from staining or contamination. PREPARATION OF JOINT SURFACES .1 Examine joint sizes and conditions to establish correct depth to width relationship for installation of backup materials and sealants. .2 Clean bonding joint surfaces of harmful substances including dust, rust, oil, grease and other matter, which may impair work. .3 Do not apply sealants to joint surfaces treated with sealer, curing compound, water repellent, or other coatings unless tests have been performed to ensure compatibility of materials. Remove coatings as required. .4 Ensure joint surfaces are dry and frost free. .5 Prepare surfaces in accordance with manufacturer’s directions. 3.3 PRIMING .1 Where necessary to prevent staining, mask adjacent surfaces prior to priming and caulking. .2 Prime sides of joints in accordance with sealant manufacturer’s instructions immediately prior to caulking. 3.4 BACKUP MATERIAL .1 Apply bond breaker tape where required to manufacturer’s instructions. .2 Install joint filler to achieve correct joint depth and shape, with approximately 30% compression. 3.5 MIXING .1 3.6 Mix materials in strict accordance with sealant manufacturer’s instructions. APPLICATION .1 Sealant - General: .1 April 2016 Apply sealant when air and substrate temperatures are not forecast to be less than minimum recommended by manufacturer. Do not work during inclement weather. Perform all work in accordance with manufacturer’s written instructions. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 .3 .4 .5 .6 .7 .8 .9 .2 Mask edges of joint where irregular surface or sensitive joint border exists to provide neat joint. Apply sealant in continuous beads. Apply sealant using gun with proper size nozzle. Use sufficient pressure to fill voids and joints solid. Form surface of sealant with full bead, smooth, free from ridges, wrinkles, sags, air pockets and embedded impurities. Tool exposed surfaces before skinning begins to give slightly concave shape. Remove excess compound promptly as work progresses and upon completion. The use of liquid tooling aids, such as soapy water or alcohols, are prohibited as they may impact effective sealant cure, adhesion and potentially cause aesthetic issues. Sealant Type ‘A’: .1 .2 .3 .4 .5 .3 Install sealant Type ‘A’ to the top of membrane flashings where required or as shown on drawings. Modified sealant to be installed around finished flashings at all protrusions including soil stacks, sleeves, pitch boxes and fasteners securing membrane to walls. Apply sealant Type ‘A’ with hand trowel to achieve a 25 mm width and minimum 3 mm thickness. Apply sealant Type ‘A’ immediately after flashings have been installed and are still warm. No membrane flashings shall be left uncovered at the end of any work period. (Non-compliance with this mandate may result in rejection, removal and replacement of the membrane flashings to the affected area). Trowel sealant Type ‘A’ in two directions to ensure proper adhesion to substrate and that all surface irregularities are filled. Tool surface of modified sealant to smooth finish. Install sealant Type ‘A’ at the underside of drains, metal sleeves and other location where specified on drawings. Curing: .1 .2 Cure sealants in accordance with sealant manufacturer’s instructions. Do not cover up sealants until proper curing has taken place. .4 Install sealant Type ‘B’ at sheet metal terminations. .5 Install sealant Type ‘E’ at all interior window connections. 3.7 Section 07 92 00 JOINT SEALANTS Page 5 of 6 CLEANING .1 Clean adjacent surfaces immediately and leave work neat and clean. .2 Remove excess droppings using recommended cleaners as work progresses. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 07 92 00 JOINT SEALANTS Page 6 of 6 .3 Remove masking tape after initial set of sealant. .4 Clean all contaminated surfaces to Owner’s acceptance. .5 Remove all rubbish and surplus materials from the job site on a daily basis. 3.8 PROTECTION .1 Protect installed products and components from damage during construction. .2 Repair damage to adjacent materials caused by joint sealants installation. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED REQUIREMENTS Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 1 of 8 .1 Section 07 92 00 – Joint Sealants. .2 Section 08 44 13 - Glazed Aluminum Curtain Walls. .3 Section 08 50 00 - Windows. .4 Section 08 80 50 - Glazing. 1.2 REFERENCES .1 Aluminum Association (AA) .1 .2 American Architectural Manufacturers Association (AAMA) .1 .3 .2 .3 CGSB 1.40-97, Anticorrosive Structural Steel Alkyd Primer. CAN/CGSB-12.1-M90, Tempered or Laminated Safety Glass. CAN/CGSB-12.20-M89, Structural Design of Glass for Buildings. CSA International .1 .2 .3 April 2016 ASTM E283/E283M-14, Standard Test Method for Determining Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen ASTM E330330M-14, Standard Test Method for Structural Performance of Exterior Windows, Doors, Skylights and Curtain Walls by Uniform Static Air Pressure Difference. ASTM E331-00(2009), Standard Test Method for Water Penetration of Exterior Windows, Skylights, Doors and Curtain Walls by Uniform Static Air Pressure Difference Canadian General Standards Board (CGSB) .1 .2 .3 .5 AAMA 609/610-09, Cleaning and Maintenance Guide for Architecturally Finished Aluminum. ASTM International .1 .4 AA-DAF-45-2003 (R2009) Aluminum Association Designation System for Aluminum Finishes Finished Aluminum. CSA G40.20-13/G40.21-13, General Requirements for Rolled or Welded Structural Quality Steel/Structural Quality Steel. CSA-S157-05/S157.1-05(R2010), Strength Design in Aluminum/Commentary on CSA S157-05, Strength Design in Aluminum CAN/CSA G164-M92(R2003), Hot Dip Galvanizing of Irregularly Shaped Articles. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.3 Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 2 of 8 ACTION AND INFORMATIONAL SUBMITTALS .1 Submit in accordance with Section 01 33 00 - Submittal Procedures. .2 Product data: .1 .2 .3 Shop drawings: .1 .2 .3 .4 When requested by Owner, submit drawings stamped and signed by professional engineer registered or licensed in Province of Ontario, Canada. Indicate materials and profiles and provide full-size, scaled details of components for each type of door and frame. Indicate: .1 Interior trim and exterior junctions with adjacent construction. .2 Junctions between combination units. .3 Elevations of units. .4 Core thicknesses of components. .5 Type and location of exposed finishes, method of anchorage, number of anchors, supports, reinforcement, and accessories. .6 Location of caulking. .7 Each type of door system including location. .8 Arrangement of reinforcing for hardware and joints. .9 Arrangement of hardware and required clearances. Indicate each type of door and frame extrusion profile, method of assembly, section and hardware reinforcement, locations of exposed fasteners and finishes. Manufacturer’s nameplates are not allowed. Samples: .1 .2 .3 .4 .5 1.4 Submit manufacturer's instructions, printed product literature and data sheets for doors and frames and include product characteristics, performance criteria, physical size, finish and limitations. Submit catalogue details for each type of door and frame illustrating profiles, dimensions and methods of assembly. Submit for review and acceptance of each unit. Samples will be returned for inclusion into work. Submit one 300 x 300 mm corner sample of each type door and frame. Submit sample showing glazing detail, reinforcement, finish and location of manufacturer's nameplates. Frame sample to show glazing stop, door stop, jointing detail, finish, wall trim. CLOSEOUT SUBMITTALS .1 April 2016 Submit in accordance with Section 01 78 00 - Closeout Submittals. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .2 1.5 Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 3 of 8 Operation and maintenance data: Submit operation and maintenance data for cleaning and maintenance of aluminum finishes for incorporation into manual. QUALITY ASSURANCE .1 1.6 Certifications: Product certificates signed by manufacturer certifying materials comply with specified performance characteristics and criteria and physical requirements. DELIVERY, STORAGE AND HANDLING .1 Deliver, store and handle materials in accordance with manufacturer's written instructions. .2 Delivery and acceptance requirements: Deliver materials to site in original factory packaging, labelled with manufacturer's name and address. .1 .2 .3 Storage and handling requirements: .1 .2 .3 1.7 Apply temporary protective coating to finished surfaces. Remove coating after erection. Use coatings that are easy to remove and residue free. Leave protective covering in place until final cleaning of building. Store materials off ground indoors in dry location and in accordance with manufacturer's recommendations in clean, dry, well-ventilated area. Store and protect aluminum doors and frames from nicks, scratches, and blemishes. Replace defective or damaged materials with new. WARRANTY .1 Remedy all defects in the aluminum door system installed hereunder which appear within a period of five (5) years from the date of final completion. .2 Make all necessary repairs and replacements within forty-eight (48) hours of receipt of written notification. .3 Provide a written warranty confirming the above, issued on the corporate letterhead, signed and sealed by an authorized signing officer. .4 Nothing contained in this article shall be construed as in any way restricting or limiting the liability in common law and Statutory Liability of the Contractor. Part 2 Products 2.1 DESIGN CRITERIA .1 April 2016 Design frames and doors in exterior walls to: Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 .2 .3 .4 Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 4 of 8 Accommodate expansion and contraction within service temperature range of -35°C to 35°C. Limit deflection of mullions to maximum 1/175th of clear span, based on CSA-S157. Movement within system. Movement between system and perimeter framing components or substrate. .2 Size glass thickness and glass unit dimensions to limits in accordance with CAN/CGSB-12.20. .3 Design door system to provide average thermal resistance of: .1 .2 .4 2.2 Door system for whole unit: RSI of 0.493. Vision glass areas (centre of glass): RSI of 0.678 Include continuous air barrier and vapour retarder through door system. Primarily in line with inside pane of glass and heel bead of glazing compound. MATERIALS .1 Aluminum extrusions: To Aluminum Association alloy AA6063-T5, anodizing quality. .2 Sheet aluminum: To Aluminum Association alloy AA1100- H14, anodizing quality. .3 Steel reinforcement, fastening clips etc.: To CSA G40.20/G40.21, grade 300 W, hot dip galvanized. .4 Fasteners: 300 Series stainless steel or 400 Series cadmium plated stainless steel of sufficient size and quantity to perform their intended function, finished to match adjacent material. .5 Weatherstrip: Replaceable mohair metal backed wool pile. .6 Door bumpers: Black neoprene. .7 Door bottom seal: Door seal of anodized extruded aluminum frame and vinyl weather seal, recessed in door bottom closed ends. .8 Isolation coating: Alkali resistant bituminous paint to SSPC Paint-12, applied at a rate of 1.0 L/m2. .9 Glass and glazing materials: In accordance with Section 08 80 50 - Glazing. .10 Sealants: In accordance with Section 07 92 00 - Joint Sealants. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 2.3 Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 5 of 8 ALUMINUM DOORS .1 Construct doors of porthole extrusions with minimum wall thickness of 3 mm. .2 Door stiles nominal 101.6 mm wide plus or minus 6 mm. .3 Top rail nominal 98.4 mm wide plus or minus 6 mm. .4 Bottom rail nominal 177.8 mm wide plus or minus 6 mm. .5 Centre rail: Nominal 260.4 mm wide plus or minus 6 mm. .6 Reinforce mechanically-joined corners of doors to produce sturdy door unit. .7 Glazing units: In accordance with Section 08 80 50 - Glazing. .8 Glazing stops: Interlocking snap-in type for dry glazing. Exterior stops: Tamperproof type. .9 Solid lower panel: Aluminum sheet on plywood core, finished to match door and frame, overall 25 mm thickness. .10 Standard of Acceptance: Alumicor ThermaPorte 7700 Series or approved equivalent. 2.4 HARDWARE .1 Hardware shall be furnished and installed by the door manufacturer as follows: .1 .2 .3 .4 .5 .6 2.5 Hinges: All hinges to be Roton continuous hinges type 780-224HD for high traffic areas. Door push/pulls: Panic hardware to be new Von Duprin 33 series EO with Ives 8190 Series pull. New hardware to be brushed stainless finish. Locksets/Cylinder: All locks to come with temporary and permanent cylinder cores and shall be keyed into an existing 7 pin interchangeable core “best Lock” factory keying system. Closers: Single acting exposed overhead LCN closer with drop plate 18G, sized to suit doors. Threshold sill: Heavy duty extruded aluminum, finish to match door finish, serrated, maximum 16 mm high, width minimum 169 mm, length to suit. Weatherstrip interlocked with door adapter. ALUMINUM FRAMES .1 April 2016 Construct thermally broken insulated frames of aluminum extrusions with minimum wall thickness of 3 mm. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 2.6 Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 6 of 8 ALUMINUM FINISHES .1 Clear anodic finish: To designation AA-A42. .2 Appearance and properties of anodized finishes designated by Aluminum Association as Architectural Class 1, in accordance with AA DAF-45. 2.7 STEEL FINISHES .1 2.8 Steel clips and reinforcing steel to have zinc coating to CAN/CSA-G164. FABRICATION .1 Doors and framing to be by same manufacturer. .2 Fabricate doors and frames to profiles and maximum face sizes as indicated. Provide minimum 22 mm bite for insulating glazed units. .3 Provide structural steel reinforcement as required. .4 Fit joints tightly and secure mechanically. .5 Conceal fastenings. .6 Design anchorages so that they do not interfere with other work such as floor finishes or drywall finishes to walls. .7 Mortise, reinforce, drill and tap doors, frames and reinforcements to receive hardware using templates provided by door hardware supplier. .8 Co-ordinate installation of hardware in the doors and frames to ensure proper operation of the complete installation. .9 Isolate aluminum from direct contact with dissimilar metals, concrete and masonry. Part 3 Execution 3.1 EXAMINATION .1 Verification of Conditions: verify conditions of substrates previously installed under other Sections or Contracts are acceptable for aluminum doors and frames installation in accordance with manufacturer's written instructions. .1 .2 April 2016 Visually inspect substrate in presence of Consultant. Inform Consultant of unacceptable conditions immediately upon discovery. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 3.2 Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 7 of 8 Proceed with installation only after unacceptable conditions have been remedied and after receipt of written approval to proceed from Consultant. INSTALLATION .1 Manufacturer's Instructions: comply with manufacturer's written recommendations, including product technical bulletins, product catalogue installation instructions, product carton installation instructions, and data sheets. .2 Set frames plumb, square, level at correct elevation in alignment with adjacent work. .3 Anchor securely. .4 Brace frames rigidly for building-in. Install temporary horizontal wood spreaders at third points of door opening to maintain frame width. Provide vertical support at centre of head for openings over 1200 mm wide. Remove temporary spreaders and supports after frames are built-in. .5 Install doors and hardware in accordance with hardware templates and manufacturer's instructions. .6 Adjust door components to ensure smooth operation. .7 Make allowances for deflection of structure to ensure that structural loads are not transmitted to frames. .8 Install metal flashing complete with drip above exterior door. .9 Glaze aluminum doors and frames in accordance with Section 08 80 50 Glazing. .10 Ensure airtight connections with adjacent construction to maintain the air seal over the entire building envelope. .11 Co-ordinate with the building air/vapour barrier installer and install air/vapour barrier transition strips at the interface with adjacent construction. .12 Inspection the entire assembly for gaps in the air seal and make good. .13 Seal joints to provide weathertight seal at outside and air, vapour seal at inside. .14 Apply sealant in accordance with Section 07 92 00 - Joint Sealants. Conceal sealant within the aluminum work except where exposed use is permitted by Consultant. 3.3 CLEANING .1 April 2016 Progress Cleaning: Clean in accordance with Section 01 74 11 - Cleaning. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 .2 .3 .4 .5 .6 .2 3.4 Section 08 11 16 ALUMINUM DOORS AND FRAMES Page 8 of 8 Leave Work area clean at end of each day. Perform cleaning of aluminum components in accordance with AAMA 609.1 - Voluntary Guide Specification for Cleaning and Maintenance of Architectural Anodized Aluminum. Perform cleaning as soon as possible after installation to remove construction and accumulated environmental dirt. Clean aluminum with damp rag and approved non-abrasive cleaner. Remove traces of primer, caulking, epoxy and filler materials; clean doors and frames. Clean glass and glazing materials with approved non-abrasive cleaner. Final cleaning: Upon completion remove surplus materials, rubbish, tools and equipment in accordance with Section 01 74 11 - Cleaning. PROTECTION .1 Protect installed products and components from damage during construction. .2 Repair damage to adjacent materials caused by aluminum door and frame installation. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED REQUIREMENTS Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 1 of 16 .1 Section 07 92 00 – Joint Sealants. .2 Section 08 11 16 - Aluminum Doors and Frames. .3 Section 08 50 00 - Windows. .4 Section 08 80 50 - Glazing. 1.2 REFERENCES .1 Aluminum Association (AA) .1 .2 .2 American Architectural Manufacturers Association (AAMA) .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 April 2016 Aluminum Standards and Data, Metric SI, 2009. AA DAF 45-03(R2009), Designation System for Aluminum Finishes. AAMA CW-DG-1-96, Aluminum Curtain Wall Design Guide Manual. AAMA CW-10-04, Care and Handling of Architectural Aluminum From Shop to Site. AAMA CW-11-85, Design Wind Loads and Boundary Layer Wind Tunnel Testing. AAMA T1R-A1-04, Sound Control for Fenestration Products. AAMA 501-05, Methods of Test for Exterior Walls. AAMA 501.1-05, Standard Test Method for Water Penetration of Windows, Curtain Walls and Doors Using Dynamic Pressure. AAMA 501.4-09 and 501.6-09, Recommended Static Test Method for Evaluating Curtain Wall and Storefront Systems Subjected to Seismic and Window Induced Interstory Drifts and Recommended Dynamic Tests for Determining the Seismic Drift Causing Glass Fallout from a Wall System. AAMA, 503-08 Voluntary Specification for Field Testing of Storefronts, Curtain walls and Sloped Glazing Systems. AAMA 611-98, Voluntary Specifications for Anodized Finishes Architectural Aluminum. AAMA 612-02, Voluntary Specifications, Performance Requirements, and Test Procedures for Combined Coatings of Anode Oxide and Transparent Organic Coatings on Architectural Aluminum. AAMA 1503-09, Voluntary Test Method for Thermal Transmittance and Condensation Resistance of Windows, Doors and Glazed Wall Sections. AAMA 2603-02, Voluntary Specification Performance Requirements and Test Procedures for Pigmented Organic Coatings on Aluminum Extrusions and Panels. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .13 .3 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 .13 CAN/CGSB 1.108-M89, Bituminous Solvent Type Paint. CAN/CGSB-12.20-M89, Structural Design of Glass for Buildings. CSA International .1 .2 April 2016 ASTM A36/A36M-08, Specification for Carbon Structural Steel. ASTM A123/A123M-13, Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products. ASTM A167-99(2009), Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip. ASTM A653/A653M-09a, Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process. ASTM B209-07, Specification for Aluminum and Aluminum-Alloy Sheet and Plate. ASTM B221-13, Specification for Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes. ASTM C864-05(2011), Standard of Specification for Dense Elastomeric Compression Seal Gaskets, Setting Blocks and Spacers. ASTM E283/E283M-14, Test Method for Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen. ASTM E330/E330M-14, Standard Test Method for Structural Performance of Exterior Windows, Doors, Skylights, and Curtain Walls, by Uniform Static Air Pressure Difference. ASTM E331-00(2009), Standard Test Method for Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform Static Air Pressure Difference. ASTM E413-04, Classification for Rating Sound Insulation. ASTM E783-02(2010), Standard Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors. ASTM E1105-00(2008), Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference. Canadian General Standards Board (CGSB) .1 .2 .5 AAMA 2604-05, Voluntary Specification Performance Requirements and Test Procedures for High Performance Organic Coatings on Aluminum Extrusions and Panels. ASTM International .1 .2 .4 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 2 of 16 CSA G40.20-13/G40.21-13, General Requirements for Rolled or Welded Structural Quality Steel/Structural Quality Steel. CSA S136-07, North American Specification for the Design of Cold Formed Steel Structural Members. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 .6 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 3 of 16 CAN/CSA-S157/S157.1-05, Strength Design in Aluminum/Commentary on CAN/CSA-S157, Strength Design in Aluminum. Society for Protective Coatings (SSPC) .1 .2 SSPC - Paint 20-02(R2004), Zinc Rich Coating, Type I - Inorganic and Type II - Organic. SSPC - Paint 25 - 97(R2004) BCS, Zinc Oxide, Alkyd, Linseed Oil and Primer for Use Over Hand Cleaned Steel Type 1 and Type 2. .7 The work of this Section shall conform to the requirements of OBC, latest revision, and all other applicable codes and regulations, to the satisfaction of the authorities having jurisdiction. .8 Structural performance shall be based on CSA-S157 and maximum deflection of 1/175 of the span. .9 The drawings indicate the general intent only. The design of anchorages, fastenings, connections and reinforcement is the responsibility of the curtainwall fabricator. 1.3 ADMINISTRATIVE REQUIREMENTS .1 Co-ordination: co-ordinate work of this Section with installation of fire stopping, air barrier placement, vapour retarder placement, flashing placement, installing ductwork to rear of louvres, and components or materials. .2 Pre-Installation Meetings: .1 Convene pre-installation meeting one week prior to beginning work of this Section and on-site installation, with Contractor's Representative and Consultant, in accordance with Section 01 31 19 - Project Meetings to: .1 Verify project requirements. .2 Review installation and substrate conditions. .3 Co-ordination with other building subtrades. .4 Review manufacturer's written installation instructions and warranty requirements. .3 Arrange for site visit with Consultant prior to start of Work to examine existing site conditions adjacent to demolition Work. .4 Ensure key personnel, site supervisor, project manager, subcontractor representatives attend. .5 Consultant will submit written notification of change to meeting schedule established upon contract award 24 hours prior to scheduled meeting. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 1.4 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 4 of 16 QUALIFICATIONS .1 The work of this Section shall be fabricated in the factory by a manufacturer with a minimum ten years’ experience in the actual production of the specified products and shipped to the site. .2 The components of the curtainwall system shall be factory fabricated by the framing supplier, fully engineered and delivered knockdown. .3 The work of this Section shall be installed by a company licensed by the curtainwall manufacturer. .4 Employ only skilled tradesmen who are experienced in this work. 1.5 ACTION AND INFORMATIONAL SUBMITTALS .1 Submit in accordance with Section 01 33 00 - Submittal Procedures. .2 Product data: .1 .3 Shop drawings: .1 .2 .4 Submit drawings stamped and signed by professional engineer registered or licensed in Province of Ontario, Canada. Provide calculations in accordance with Ontario Building Code. Indicate system dimensions, framed opening requirements and tolerances, adjacent construction, anchor details anticipated deflection under load, affected related Work, large scale details for head, jamb, sill, transoms and mullions, profiles of components, elevations of units, anchorage details, location of isolation coating, weep drainage network, pressure equalization holes, methods of avoiding thermal bridging, maintenance of integrity of insulation and thermal break between subframe and structure, prevention of air infiltration, maintenance of the integrity of the air barrier, condensation control, expansion and contraction joint location and details, and field welding required. Samples: .1 .2 .3 April 2016 Submit manufacturer's instructions, printed product literature and data sheets for curtainwall components, anchorage and fasteners, glass and infill, and internal drainage details and include product characteristics, performance criteria, physical size, finish and limitations and water flow diagrams. Submit for review and acceptance of each unit. Samples will be returned for inclusion into work. Submit one (1) representative sample of each type of curtainwall section, 300 mm long, illustrating prefinished aluminum surface, finish, colour, texture, specified glass units, insulated infill panels, glazing materials illustrating edge and corner. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .5 Delegated design submittals: .1 .6 Include framing member structural and physical characteristics, calculations, dimensional limitations, special installation requirements. Test reports: .1 1.6 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 5 of 16 Submit substantiating engineering data, test results of previous tests by independent laboratory which purport to meet performance criteria, and supportive data. CLOSEOUT SUBMITTALS .1 Submit in accordance with Section 01 78 00 - Closeout Submittals. .2 Operation and Maintenance Data: Submit operation and maintenance data for glazed aluminum curtainwall for incorporation into manual. 1.7 MAINTENANCE MATERIAL SUBMITTALS .1 Extra stock materials: .1 .2 .3 .4 1.8 Supply extra stock materials of glass units in accordance with Section 01 78 00 - Closeout Submittals. Supply protected and packaged in wood crates suitable for storage. Clearly identify each crate. Deliver Consultant, upon completion of work of this Section. Store where directed by Consultant. QUALITY ASSURANCE .1 Regulatory Requirements: .1 .2 Mock-ups: .1 .2 .3 .4 April 2016 Conform to applicable code for acoustic attenuation, sound transmission, requirements. Construct mock-ups in accordance with Section 01 45 00 - Quality Control. Supply 1500 mm x 3000 mm mock-up including intermediate mullion, corner mullion, sill muntin, column cover, vision glass light, and insulated infill panel/glass. .1 Assemble to illustrate component assembly including glazing materials, weep drainage system, attachments, anchors, and perimeter sealant. Locate mock-up where directed by Owner. Allow 24 hours for inspection of mock-up by Consultant before proceeding with work. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .5 .6 1.9 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 6 of 16 When accepted, mock-up will demonstrate minimum standard of quality and materials for work of this Section. Mock-up may remain as part of finished work. DELIVERY, STORAGE AND HANDLING .1 Delivery and acceptance requirements: Deliver materials to site in original factory packaging, labelled with manufacturer's name and address. .2 Storage and handling requirements: .1 .2 .3 .4 .5 1.10 Handle work of this Section in accordance with AAMA CW-10. Store materials off ground, indoors, in dry location and in accordance with manufacturer's recommendations in clean, dry, well-ventilated area. Store and protect aluminum glazed curtainwall components from nicks, scratches, and blemishes. Protect prefinished aluminum surfaces with strippable coating. Do not use adhesive papers or sprayed coatings which bond when exposed to sunlight or weather. Replace defective or damaged materials with new. AMBIENT CONDITIONS .1 Install sealants when ambient and surface temperature is above 5°C minimum. .2 Maintain this minimum temperature during and for 48 hours minimum after installation of sealants. 1.11 WARRANTY .1 Contractor hereby warrants that glazed aluminum curtainwall will function as specified for 60 months. Remedy all defects which appear with in a period of five (5) years from the date of final completion. .2 Make all necessary repair and replacements within forty-eight (48) hours of receipt of written notification. .3 Provide a written warranty confirming the above, issued on the corporate letterhead, signed and sealed by an authorized signing officer. .4 Nothing contained in this article shall be construed as in any way restricting or limiting the liability in common law and statutory liability of the Contractor. Part 2 Products 2.1 SYSTEMS .1 April 2016 Description: Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 .2 .2 Vertical glazed aluminum curtainwall system includes thermally broken tubular aluminum sections with self-supporting framing, shop fabricated, factory prefinished, vision glass, insulated metal panel, spandrel infill, column covers, and louvres; related flashings, anchorage and attachment devices. Assembled system to permit re-glazing of individual glass (and infill panel) units from exterior without requiring removal of structural mullion sections. Performance Requirements: .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 April 2016 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 7 of 16 Ensure system is designed to accommodate the following without damage to components or deterioration of seals: .1 Movement within system. .2 Movement between system and perimeter framing components. .3 Dynamic loading and release of loads. .4 Deflection of structural support framing. Limit air infiltration through assembly to 0.0003 m3/s/m2 of wall area, measured at a reference differential pressure across assembly of 75 Pa as measured in accordance with AAMA 501. Vapour seal with interior atmospheric pressure of 25 mm sp, 22°C, 40% RH: no failure. Water leakage: None, when measured to ASTM E1105. Drain water entering joints, condensation occurring in glazing channels, or migrating moisture occurring within system, to exterior by weep drainage network. Design and size components to withstand dead and live loads caused by pressure and suction of wind, snow and hail for sloped glazing, acting normal to plane of system as calculated in accordance with NBC to a design pressure of 0.90 kPa as measured to AAMA CW 11 and ASTM E330. Design and size components to withstand seismic loads and sway displacement as calculated in accordance with applicable codes. Limit mullion deflection to flexure limit of glass, 19 mm or L/175, whichever is smaller, with full recovery of glazing materials. Size glass units and glass dimensions to limits established in CAN/CGSB-12.20. Ensure system allows for expansion and contraction within system components when temperature range is 95°C over 12 hour period without causing detrimental effect to system components. Drain water entering joints, condensation occurring in glazing channels, or migrating moisture occurring within system, to exterior by weep drainage network. Maintain continuous air barrier and vapour retarder throughout assembly, primarily in line with inside pane of glass and heel bead of glazing compound. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 8 of 16 .1 .13 2.2 Position thermal insulation on exterior surface of air barrier and vapour retarder. Ensure no vibration harmonics, wind whistles, noises caused by thermal movement transmitted to other building elements, loosening, weakening, or fracturing of attachments or components of system occur. MATERIALS .1 Extruded aluminum: To ASTM B221, 6063-T6 alloy and temper. .2 Sheet aluminum: To ASTM B209. .3 Sheet steel: To CSA S136 / ASTM A653/A653M; galvanized in accordance with CAN/CSA G164. .4 Steel sections: To CSA G40.20/G40.21 / Type 304 stainless; shaped to suit mullion sections. .5 Anchors: 3-way adjustable hot-dip galvanized cast iron. .6 Fasteners: Stainless or galvanized steel as indicated, finish to match curtainwall. .7 Bituminous paint: CAN/CGSB 1.108, Type 2, without thinner. .8 Fixed curtainwall system: To pass levels B7, C3, I=66 of CAN/CSA-A44-04. .1 .9 Aluminum awning windows: Top hinged projected out insulated glass units with thermal break to CSA A440-04, performance levels A3, B7, C5, I=61 ratings, and have removable insulating glass as shown on drawings. (AAMA/WDMA/CSA A440-08 CW-PG70). Windows to be equipped with heavy duty roto-operators for operation, with 2 claw locks. Equip each unit with two (2) friction arms equally spaced along lower frame. .1 .10 Standard of Acceptance: UniVent 1350 Series by Alumicor, Series 20003AR by Oldcastle or approved equivalent. Aluminum hopper windows: Bottom hinged projected in insulated glass units with thermal break to CSA A440-04 performance levels A3, B7, C5, I=61 ratings, and have removable insulating glass as shown on drawings. (AAMA/WDMA/CSA A440-08 CW-PG70) Equip each unit with two (2) friction arms. Windows to be equipped with two (2) cam handles for operation. Windows with locking device higher than 1900mm above floor to contain spring catch and keeper (transom latch). Two (2) sets of poles complete with pole hook to be provided for each room with this window type. .1 April 2016 Standard of acceptance: ThermaWall 2600 Series by Alumicor or Reliance Curtain Wall by Oldcastle, or approved equivalent. Standard of Acceptance: UniVent 1350 Series by Alumicor, Series 20003AR by Oldcastle or approved equivalent. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .11 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 9 of 16 Curtainwall spandrel panels: Internally reinforced, to provide flat, distortion free panel face, permitting internal air movement to glazing space, outside air barrier line: .1 .2 .3 .4 .5 Spandrel glass: See Section 08 80 50 – Glazing. Insulation: Recycled steel slag, volcanic rock mineral wool, density 64 kg/m3, conforming with CGSB 51-GP-10M and having RSI of 0.72 per 25 mm. Inner face to be fabricated from aluminum sheet 1.02 mm thick (18 ga.). Interior aluminum face sheet to match finish of curtainwall framing. Fasteners: Corrosion-resistant, as recommended by manufacturer. .12 Vertical glass units: See Section 08 80 50 - Glazing. .13 Sealant: See Section 07 92 00 – Joint Sealants. 2.3 COMPONENTS .1 Mullion profile: .1 .2 .3 .4 .5 .6 .7 .8 .9 Reference to tolerances for wall thickness and other cross-sectional dimensions of curtainwall members are nominal and may be varied slightly to suit manufacturer’s standard profiles Vertical members: See schedule on drawings. Horizontal members: See schedule on drawings. Comply with AA aluminum standards and data. Provide internal galvanized steel reinforcement as required. Thermally broken with interior tubular section insulated from exterior pressure plate. Matching stops and pressure plate of sufficient size and strength to ensure adequate bite on glass and infill panels. Drainage holes, deflector plates and internal flashings to accommodate internal weep drainage system. Internal mullion baffles to eliminate "stack effect" air movement within internal spaces. Co-ordinate with work of other sections to provide adaptor extrusions to receive doors where required. .2 Column covers: 1.5 mm thick aluminum, finish to match curtainwall mullion sections. .3 Flashings, drip edges and exterior panning trim: 2.0 mm thick aluminum, finish as selected, to match curtainwall mullion sections where exposed, secured with concealed fastening method, complete with joint covers, jamb drip deflectors, chairs and caps and anchoring devices. .4 Exterior Sills: April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 .2 .3 .4 .5 Standard of acceptance: Blueskin TWF by Henry Company, Sopraseal Stick 1100T by Soprema or approved equivalent. Primer and/or adhesive as recommended by membrane manufacturer. Self-adhered air/vapour barrier at other locations: .1 .7 Aluminum extrusions to profiles as detailed and to suit job conditions; minimum 3 mm thick, complete with concealed anchoring devices. Profile to be stiff enough to withstand in-service loadings without deformation. Finish aluminum after fabrication to match curtainwall framing. Generally, fabricate sills in one continuous piece for each opening. If joints are unavoidable, centre joint on window mullion and seal. Sills to be complete with end dam closures. Self-adhered air/vapour barrier at through-wall flashings: Self-adhered modified bituminous composite membrane, thickness 1.0 minimum, high temperature grade. .1 .6 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 10 of 16 Self-adhered membrane: To CSA A123.22, self-adhering membrane consisting of SBS rubberized asphalt compound laminated to a polyethylene film. Minimum thickness 1 mm. .1 Primer: Use membrane manufacturer’s recommended product. Vapour permeable self-adhered membrane: Self-adhering, vapour-permeable, water-resistive membrane consisting of an engineered film and permeable adhesive with a split-back poly release film. .1 Primer: Use membrane manufacturer’s recommended product. .8 Polyethylene sheet vapour barrier: Thickness 0.15 mm, to CAN/CGSB-51.34. .9 Interior aluminum trim: Provide extruded aluminum trim moulding of sufficient size to neatly finish the window to the interior opening. Provide snap-on trim where shown on the drawings. Exposed fasteners or brake formed shapes not acceptable. Seal joints per Section 07 92 00 – Joint Sealants between (a) trim mouldings and window, with Sealant Type ‘E’ and (b) trim moulding and interior window opening with Sealant Type ‘E’. .10 Louvres: Extruded aluminum blade and frame, 100 mm deep, 45 degree slope with weather stop dam; aluminum sheet steel blank-off panel, black colour, at rear for field cutting and sizing to suit mechanical duct attachment, finish as selected same as curtainwall mullion sections. Fabricate rigid to eliminate blade flutter. .11 Louvre screening: Supply bird screen at exhaust and insect screen at intake air louvre inside surface. .12 Screens: Heavy duty to CAN/CGSB-79.1-M91. .1 .2 April 2016 Extruded aluminum frame having a wall thickness of 1.9 mm. Screen frame colour to match window frames. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 .13 2.4 Screen cloth to be 18x24 mesh located as shown on drawings. Aluminum nest for hopper windows. Spray foam insulation: To be one or two component spray polyurethane foam to suit site conditions. Foam to be flame retardant grade. .1 .14 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 11 of 16 Standard of acceptance: Abisko Enerfoam or approved equivalent. Insulation for glazing spacer: Extruded polystyrene, to CAN/ULC S701, Type 4. HARDWARE .1 For hopper windows: Cam handles to be Model No. 27-33 as manufactured by Truth Inc. and fastened to window frame, complete with keeper. Hopper windows with lock device above 1900 mm above floor to employ spring catch and keeper (transom handle) complete with pole operator adjustment. Provide samples prior to ordering. .2 For awning windows: Heavy-duty roto-operators to be manufactured by Truth Inc. Provide samples prior to ordering. .3 Where window latching devices are above 1900 mm above floor: .1 .2 .4 2.5 Pole to CAN/CGSB-69.32-M90, Type 7-132, length to suit (2 per room). Pole hanger: To CAN/CGSB-69.32-M90, Type 7-120 (2 per room). Limiting stop device: To permit ventilation with maximum 300 mm opening. FABRICATION .1 Fabricate system components with minimum clearances and shim spacing around perimeter of assembly, yet enabling installation and dynamic movement of perimeter seal. .2 Accurately fit and secure joints and corners. Make joints flush, hairline, and weatherproof. Design framing members to drain moisture to the exterior. .3 Prepare components to receive anchor devices. Install anchors. .4 Arrange fasteners and attachments to ensure concealment from view and so that they do not interfere with other work such as drywall finishes and wood trim. .5 Mullions to be tubular extruded members, square-cut, corner bracket construction with butyl tape joint seals. .6 Prepare system components to receive exterior doors, revolving doors, and hardware. .7 Reinforce interior horizontal head rail to receive drapery track brackets and attachments. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 12 of 16 .8 Reinforce framing members for external imposed loads. .9 Frame sections are to incorporate integral screw ports for mechanical fastening of all corners and intermediate joints with self-tapping screws or spigots. No exposed fastening devices will be permitted. .10 Factory-install rigid polystyrene insulation in all tubular framing members. .11 Visible manufacturer's identification labels not permitted. .12 Fabricate curtainwall and screens square and true with maximum tolerance of plus or minus 1.5 mm for glazing units with diagonal measurements of 1.8 m or less, and plus or minus 3 mm for units with diagonal measurement over 1.8 m. .13 Make allowance for deflection of structure. Ensure that structural loads are not transmitted to glazing units. .14 Infill Panels: .1 .2 .3 .4 .5 .6 .7 .15 Finishes: .1 .2 .3 .4 .5 April 2016 Fabricate infill panels with metal covered edge seals around perimeter of panel assembly, enabling installation and minor movement of perimeter seal. Reinforce interior surface of exterior panel sheet from deflection caused by wind and suction loads. Accurately fit and secure joints and corners. Make joints flush, hairline, and weatherproof. Place insulation within panel, adhered to exterior face of interior panel sheet over entire area of sheet with impale fasteners. Ventilate and pressure equalize the air space outside the exterior surface of the insulation, to the exterior. Arrange fasteners and attachments to ensure concealment from view. Reinforce panel to receive convector cabinet brackets and attachments. Finish coatings: Conform to AAMA 611 designations. Exterior exposed aluminum surfaces: to AAMA A41 anodized to 215-R1, 0.010 mm thickness, prepared with a mechanical M pre-treatment, anodized to clear colour. Exterior exposed infill panel surfaces: to AAMA A41 anodized to 215-R1, 0.010 mm thickness, prepared with a mechanical M pretreatment, anodized to clear colour. Exterior exposed aluminum column covers: to AAMA A41 anodized to 215-R1, 0.010 mm thickness, prepared with a mechanical M pretreatment, anodized to clear colour. Interior exposed aluminum surfaces: to AAMA AA A41 anodized to 215-R1, 0.010 mm thickness, prepared with a mechanical M pretreatment, anodized to clear colour. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .6 .7 .8 .9 .10 2.6 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 13 of 16 Interior surface of infill panel surfaces: anodized to clear colour. Interior exposed aluminum column and sloped beam covers: to AAMA A41 anodized to 215-R1, 0.010 mm thickness, prepared with a mechanical M pretreatment, anodized to clear colour. Touch-up primer for galvanized steel surfaces: SSPC 20 Paint zinc rich. Concealed steel items: galvanized in accordance with ASTM A123 to 600 g/m2. Apply 1 coat of bituminous paint to concealed aluminum and steel surfaces in contact with cementitious or dissimilar materials. SOURCE QUALITY CONTROL .1 Perform work in accordance with AAMA CW-I-9. Maintain one copy on site. .2 Design structural support framing components to CAN/CSA-S157 under direct supervision of a Professional Structural Engineer experienced in design of this Work and licensed at the place where the Project is located in the Province of Ontario. .3 Perform welding Work in accordance with CSA W59.2. Part 3 Execution 3.1 EXAMINATION .1 Verification of conditions: Verify conditions of substrates previously installed under other Sections or Contracts are acceptable for aluminum curtainwall installation in accordance with manufacturer's written instructions. .1 .2 .3 .4 .5 .6 April 2016 Visually inspect substrate in presence of Consultant. Verify dimensions, tolerances, and method of attachment with other work, by field measurement before fabrication. Show recorded measurements on shop drawings. Co-ordinate field measurements and fabrication schedule with construction progress to avoid construction delays. Verify wall openings and adjoining air barrier and vapour retarder materials are ready to receive work of this Section. Inform Consultant of unacceptable conditions immediately upon discovery. Proceed with installation only after unacceptable conditions have been remedied and after receipt of written approval to proceed from Consultant. Commencement of the installation will be construed as acceptance of the site conditions and, thereafter, the Contractor shall be fully responsible for satisfactory work as specified herein. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 3.2 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 14 of 16 INSTALLATION .1 Install curtainwall and sloped glazing system in accordance with manufacturer's instructions. .2 Attach to structure to permit sufficient adjustment to accommodate construction tolerances and other irregularities. .3 Use alignment attachments and shims to permanently fasten system to building structure. Clean weld surfaces; apply protective primer to field welds and adjacent surfaces. .4 Align assembly plumb and level, free of warp or twist. Maintain assembly dimensional tolerances and align with adjacent work. .5 Attach vertical mullions to structure. Provide sliding connections as necessary to prevent structural loads from being transmitted to the curtainwall. .6 Use thermal isolation where components penetrate or disrupt building insulation. .7 Install sill flashings. .8 Install eave edge flashings at sloped glazing system. .9 Separate aluminum materials from sources of corrosion or electrolytic action contact points. .10 Each lite of glass shall be compartmentalized using joint plugs and sealant to divert water to the horizontal weep locations. Weep holes shall be located in the horizontal pressure plates and covers to divert water to the exterior of the building. .11 Co-ordinate installation of fire stop insulation, at each floor slab edge and intersection with vertical construction where indicated. .12 Co-ordinate attachment and seal of perimeter air barrier and vapour retarder materials. .13 Pack fibrous insulation in shim spaces at perimeter of assembly to maintain continuity of thermal barrier. .14 Install fire-safing in areas as indicated. .15 Install operating sash in accordance with Section 08 80 50 - Glazing, to glazing method required to achieve performance criteria exterior wet/dry method of glazing. .16 Install louvres, associated flashings, blank-off plates and screening. Fit blank-off plates tight to ductwork. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 15 of 16 .17 Install glass and infill panels in accordance with Section 08 80 50 - Glazing, to glazing method required to achieve performance criteria exterior wet/dry method of glazing. Place sealant on the up-slope side of the pressure plate cover caps; finish the surface with a slope to encourage drainage over the cap. Cover caps to conceal screws and ensure continuous sightline. .18 Install perimeter sealant to method required to achieve performance criteria. Type, backing materials, and installation criteria in accordance with Section 07 92 00 - Joint Sealants. 3.3 SITE TOLERANCES .1 Maximum variation from plumb: 1.5 mm/m non-cumulative or 12 mm/30 m, whichever is less. .2 Maximum misalignment of two adjoining members abutting in plane: 0.8 mm. .3 Maximum sealant space between curtainwall and adjacent construction: 13 mm. 3.4 FIELD QUALITY CONTROL .1 Inspection and testing will be arranged and paid for by the Owner. .2 The Owner reserves the right to have inspections made to establish quality of work. Such inspections shall be made in the presence of the Contractor. .3 Notify the Owner in the event that the specifications conflict with the recommendations of the manufacturer. .4 Inspection and testing by the Owner does not relieve the Contractor of his responsibility for quality control of production and installation. 3.5 ADJUSTING .1 3.6 Adjust operating sash for smooth operation. CLEANING .1 Progress cleaning: clean in accordance with Section 01 74 11 - Cleaning. .1 .2 .3 .4 .5 April 2016 Leave Work area clean at end of each day. Remove protective material from prefinished aluminum surfaces. Wash down surfaces with a solution of mild detergent in warm water, applied with soft, clean wiping cloths. Take care to remove dirt from corners. Wipe surfaces clean. Remove excess sealant by moderate use of mineral spirits or other solvent acceptable to sealant manufacturer. Final Cleaning: upon completion remove surplus materials, rubbish, tools and equipment in accordance with Section 01 74 11 - Cleaning. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 3.7 Section 08 44 13 GLAZED ALUMINUM CURTAIN WALLS Page 16 of 16 PROTECTION .1 Protect installed products and components from damage during construction. .2 Repair damage to adjacent materials caused by glazed aluminum curtainwall installation. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED REQUIREMENTS .1 Section 07 92 00 – Joint Sealants. .2 Section 08 11 16 – Aluminum Doors and Frames. .3 Section 08 44 13 - Glazed Aluminum Curtain Walls. .4 Section 08 80 50 - Glazing. 1.2 Section 08 50 00 WINDOWS Page 1 of 12 REFERENCES .1 Aluminum Association (AA) .1 .2 ASTM International .1 .3 .2 .3 .4 .5 .6 .7 April 2016 AAMA 1503-98, Voluntary Test Method for Thermal Transmittance and Condensation Resistance of Windows, Doors and Glazed Wall Sections. AAMA/WDMA/CSA 101/I.S.2/A440-11, NAFS - North American Fenestration Standard for Windows, Doors, and Skylights. CSA A440S1-09, Canadian Supplement to AAMA/WDMA/CSA 101/1.S.2/A440, NAFS - North American Fenestration Standard for Windows, Doors, and Skylights. CAN/CSA-A440.4-07(R2012), Window, Door, and Skylight Installation CAN/CSA-A440.2/A440.3-09, Fenestration energy performance/User guide to CSA A440.2, Fenestration energy performance. CAN/CSA-Z91-02(R2013), Health and Safety Code for Suspended Equipment Operations. CAN/CSA-Z809-08(R2013), Sustainable Forest Management. Master Painters Institute (MPI) .1 .6 CAN/CGSB-79.1-M91, Insect Screens. CSA Group .1 .5 ASTM B244-09(2014), Standard Test Method for Measurement of Thickness of Anodic Coatings on Aluminum and of Other Nonconductive Coatings on Nonmagnetic Basis Metals with Eddy-Current Instruments Canadian General Standards Board (CGSB) .1 .4 AA DAF 45-03(R2009), Designation System for Aluminum Finishes. Architectural Painting Specification Manual - current edition. .1 MPI #79, Primer, Alkyd, Anti-Corrosive for Metal. Screen Manufacturers Association (SMA) Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 1.3 Section 08 50 00 WINDOWS Page 2 of 12 SMA 1201R-2002 Specification for Insect Screens for Windows, Sliding Doors and Swinging Doors. TEST PROCEDURES AND PERFORMANCE .1 Specifications for windows, doors and unit skylights: AAMA 101. .2 Air infiltration test: ASTM E283, at 300 Pa static air pressure differential. Air infiltration shall not exceed 0.5 L/s per m². .3 Water resistance test: ASTM E331, no water leakage at 577 Pa static air pressure differential. .4 Operation and cycling performance: AAMA 910, life cycled and retested for air and water. .5 Uniform load deflection test: ASTM E330, at static air pressure of ±3 kPa. No member shall deflect more than 1/175 of its span. .6 Uniform load structural test: ASTM E330, at static air pressure difference of ±4.5 kPa. .7 Condensation resistance test: AAMA 1503.1, CRF Class shall be not less than C65. .8 Thermal transmittance test: AAMA 1503.1, U-Value Class shall not exceed U30. 1.4 QUALIFICATIONS .1 The work of this Section shall be fabricated in the factory by a manufacturer with a minimum ten years’ experience in the actual production of the specified products and shipped to the site. .2 The work of this Section shall be installed by a company licensed by the window manufacturer as an approved installer. .3 Employ only skilled tradesmen who are experienced in this work. 1.5 ACTION AND INFORMATIONAL SUBMITTALS .1 Submit in accordance with Section 01 33 00 - Submittal Procedures. .2 Contractor shall site measure all window openings to confirm all rough opening measurements prior to ordering windows and submitting shop drawings. .3 Product data: .1 April 2016 Submit manufacturer's instructions, printed product literature and data sheets for windows and include product characteristics, performance criteria, physical size, finish and limitations. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .4 Shop drawings: .1 .2 .3 .5 .5 .2 .3 Construct window mock-up at a location on the building designated by the Owner for examination and acceptance of details, jointing, assembly, alignment, finishes and glass including wood blocking, membrane, window sill and column covers. The accepted mock-ups may be incorporated into the finished work. The accepted mock-ups will be the standard of acceptance for the work of this Section. Test and evaluation reports: .1 .2 April 2016 Submit for review and acceptance of each unit. Samples will be returned for inclusion into work. Submit one complete full size window sample of each type window. Include frame, sash, sill, glazing and weatherproofing method, insect screens, surface finish and hardware. Show location of manufacturer's nameplates. Include 150 mm long samples of head, jamb, sill, mullions to indicate profile. Mock-up: .1 .7 Submit drawings stamped and signed by professional engineer registered or licensed in Province of Ontario, Canada. Indicate materials and details in full size scale for head, jamb and sill, profiles of components, interior and exterior trim, junction between combination units, elevations of unit, anchorage details, description of related components and exposed finishes fasteners, and caulking. Indicate location of manufacturer's nameplates. Indicate on shop drawings thermal breaks and drainage paths. Samples: .1 .2 .3 .4 .6 Section 08 50 00 WINDOWS Page 3 of 12 Submit test reports from approved independent testing laboratories, certifying compliance with specifications. All test reports that reference the NAFS must include, on the first page, a summary of the results including, at minimum: .1 The product manufacturer. .2 The type of product. .3 The model number/series number. .4 The primary product designation. .5 The secondary product designation. .1 Positive design pressure. .2 Negative design pressure. .3 Water penetration resistance test pressure. .4 Canadian air infiltration and exfiltration levels. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 1.6 Section 08 50 00 WINDOWS Page 4 of 12 .6 The test completion date. The report will also contain the following information: .1 Test dates. .2 Report preparation dates. .3 Test information retention period. .4 Location of testing facilities. .5 Full description of test samples, including: .1 Anodized finish, weathering characteristics. .2 Condensation resistance. .3 Safety drop - vertical sliding windows only. .4 Block operation - sliding windows only. .5 Sash strength and stiffness - operable casement and projecting. .6 Sash pull-off - vinyl windows. .7 Forced entry resistance. .8 Mullion deflection - combination and composite windows. .6 Complete description of amendments, as applicable. .7 Conclusion. .8 Drawings signed by the testing laboratory, if provided. CLOSEOUT SUBMITTALS .1 Submit in accordance with Section 01 78 00 - Closeout Submittals. .2 Operation and maintenance data: Submit operation and maintenance data for windows for incorporation into manual. 1.7 QUALITY ASSURANCE .1 1.8 Certifications: Provide product certificates signed by manufacturer certifying materials comply with specified performance characteristics and criteria and physical requirements. DELIVERY, STORAGE AND HANDLING .1 Deliver, store and handle materials in accordance with manufacturer's written instructions. .2 Delivery and acceptance requirements: Deliver materials to site in original factory packaging, labelled with manufacturer's name and address. .3 Storage and handling requirements: .1 .2 April 2016 Store materials off ground, in dry location and in accordance with manufacturer's recommendations in clean, dry, well-ventilated area. Store and protect windows from nicks, scratches, and blemishes. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 1.9 Section 08 50 00 WINDOWS Page 5 of 12 Replace defective or damaged materials with new. WARRANTY .1 Contractor hereby warrants that glazed aluminum curtainwall will function as specified for 60 months. Remedy all defects which appear with in a period of five (5) years from the date of final completion. .2 Make all necessary repair and replacements within forty-eight (48) hours of receipt of written notification. .3 Provide a written warranty confirming the above, issued on the corporate letterhead, signed and sealed by an authorized signing officer. .4 Nothing contained in this article shall be construed as in any way restricting or limiting the liability in common law and statutory liability of the Contractor. Part 2 Products 2.1 MATERIALS .1 Materials: To AAMA/WDMA/CSA 101/I.S.2/A440 supplemented as follows: .2 Aluminum to be 6063-T6 alloy with minimum wall thickness of 1.57 mm. .3 Extrusions to comply with ASTM C221, with tolerances to ANSI H35.2. .4 Aluminum sheet to comply with ASTM B209. .5 All windows by same manufacturer, aluminum, thermally broken, frame depth as indicated on drawings. .6 Sash: Aluminum thermally broken. .7 Interior aluminum trim: Provide extruded aluminum trim moulding of sufficient size to neatly finish the window to the interior opening. Provide snap-on trim where shown on the drawings. Exposed fasteners or brake formed shapes not acceptable. Seal joints per Section 07 92 00 – Joint Sealants between (a) trim mouldings and window, with Sealant Type ‘E’, and (b) trim moulding and interior window opening with Sealant Type ‘E’. .8 Spray foam insulation: To be one or two component spray polyurethane foam to suit site conditions. Foam to be flame retardant grade. Standard of acceptance: Abisko Enerfoam or approved alternative. .9 Weatherstripping: Shall be non-shrinking, resistant to ultraviolet degradation, and replaceable closed-cell elastomer, to ASTM C509. Dense elastomer shall meet ASTM C864. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 Section 08 50 00 WINDOWS Page 6 of 12 At ventilators: Provide two rows of compression type neoprene/EPDM alloy or Santoprene weatherstripping. .10 Glass: in accordance with Section 08 80 50 - Glazing. .11 Screens: To CAN/CGSB-79.1-M91 on the ventilating portion of the windows. .1 .2 .3 .4 Insect screening mesh: Heavy duty, count 18 x 24 black mesh. Fasteners: Tamper proof. Screen frames: Aluminum colour and finish to match window frames. Mount screen frames for interior replacement. .12 Exterior aluminum facings and sills: Brake formed aluminum sheet metal of type and size as detailed to suit job conditions; minimum 2 mm thick, complete with joint covers, jamb drip deflectors, chairs, anchors anchoring devices. .13 Self-adhered air/vapour barrier at through-wall flashings: Self-adhered modified bituminous composite membrane, thickness 1.0 minimum, high temperature grade. .1 .14 Self-adhered air/vapour barrier at other locations: .1 .15 Standard of acceptance: Blueskin TWF by Henry Company, Sopraseal Stick 1100T by Soprema or approved equivalent. Primer and/or adhesive as recommended by membrane manufacturer. Self-adhered membrane: To CSA A123.22, self-adhering membrane consisting of SBS rubberized asphalt compound laminated to a polyethylene film. Minimum thickness 1 mm. .1 Primer: Use membrane manufacturer’s recommended product. Vapour permeable self-adhered membrane: Self-adhering, vapour-permeable, water resistive membrane consisting of an engineered film and permeable adhesive with a split-back poly release film. .1 Primer: Use membrane manufacturer’s recommended product. .16 Polyethylene sheet vapour barrier: Thickness 0.15 mm, to CAN/CGSB-51.34. .17 Air and vapour barrier material must be compatible with existing materials where tie-ins to existing construction are to occur. .18 Sealants: See Section 07 92 00 – Joint Sealants. 2.2 WINDOW TYPE AND CLASSIFICATION .1 April 2016 Aluminum fixed windows: Fixed insulated glass window units with thermal break to CAN/CSA-A440-04, performance levels pass, B7, C5, I=70 ratings, 25mm in overall thickness and as shown on drawings. (AAMA/WDMA/CSA A440-08 CWPG70). Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 .2 Standard of Acceptance: Series 2000-3AR by Oldcastle, UniVent 1350 Series by Alumicor or approved equivalent. Aluminum hopper windows: Bottom hinged projected in, insulated glass units with thermal break to CSA A440-04, performance levels A3, B7, C5, I=61 ratings, and have removable insulating glass as shown on drawings. (AAMA/WDMA/CSA A440-08 CW-PG70). Equip each unit with two (2) friction arms. Windows to be equipped with two (2) cam handles for operation. Windows with locking device higher than 1900mm above floor to contain spring catch and keeper (transom latch). Two (2) sets of poles complete with pole hook to be provided for each room with this window type. .1 .4 Standard of Acceptance: Series 1200 Arctic by Oldcastle, Rainblade 1990 by Alumicor or approved equivalent. Aluminum awning windows: Top hinged projected out insulated glass units with thermal break to CSA A440-04 performance levels A3, B7, C5, I=61 ratings, and have removable insulating glass as shown on drawings. (AAMA/WDMA/CSA A440-08 CW-PG70). Windows to be equipped with heavy duty roto-operators for operation, with 2 claw locks. Equip each unit with two (2) friction arms equally spaced along lower frame. .1 .3 Section 08 50 00 WINDOWS Page 7 of 12 Standard of Acceptance: Series 2000-3AR by Oldcastle, UniVent 1350 Series by Alumicor or approved equivalent. Casement windows: Side hinged projected in, insulated glass units with thermal break to CSA A440-04, performance levels A3, B7, C5, I=61 ratings, and have removable insulating glass. Equip each unit with butt hinges. .1 Standard of Acceptance: Series 2000-3AR by Oldcastle, UniVent 1350 Series by Alumicor or approved equivalent. .5 All windows to follow ‘rainscreen’ principle, and drainage paths to exterior shall be shown on all shop drawings. .6 Provide test results, if so requested by the Owner, indicating that testing was performed with test window secured using concealed fasteners only. 2.3 FABRICATION .1 Fabricate in accordance with AAMA/WDMA/CSA 101/I.S.2/A440 supplemented as follows: .2 Take field measurements before starting fabrication and submitting shop drawings. .3 Fabricate units square and true with maximum tolerance of plus or minus 1.5 mm for units with a diagonal measurement of 1800 mm or less and plus or minus 3 mm for units with a diagonal measurement over 1800 mm. .4 Joints in frames and ventilators shall be machined, mechanically fastened and sealed to form a watertight joint. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 08 50 00 WINDOWS Page 8 of 12 .5 All aluminum components shall be formed free of scratches and burrs, before application of finish. .6 Manufacturer’s nameplate on windows is not acceptable. .7 Face dimensions detailed are maximum permissible sizes. .8 Brace frames to maintain squareness and rigidity during shipment and installation. .9 Finish steel clips and reinforcement with shop coat primer to ASTM A123/A123M. 2.4 ALUMINUM FINISHES .1 Finish exposed surfaces of aluminum components in accordance with Aluminum Association Designation System for Aluminum Finishes. .1 2.5 Clear anodic finish: Type II, Class 1 to ASTM B244, 0.010 mm thickness. ISOLATION COATING .1 Coatings: In accordance with manufacturer's recommendations for surface conditions. .2 Isolation coating: Alkali resistant bituminous paint. .1 .3 Isolate aluminum from following components, by means of isolation coating: .1 .2 .3 2.6 Low VOC. Dissimilar metals except stainless steel, zinc, or white bronze of small area. Concrete, mortar and masonry. Wood. GLAZING .1 Glaze windows in accordance with AAMA/WDMA/CSA 101/I.S.2/A440. .2 Prepare frames and sash to accommodate glass and glazing method specified in Section 08 80 50 - Glazing. Units shall be exterior wet glazed using silicone cap beads, setting blocks, edge blocks and accessories as recommended by and in accordance with GANA Glazing Manual. 2.7 HARDWARE .1 April 2016 All material shall be corrosion resistant and compatible with aluminum. Hardware must prove its strength and suitability by being installed on units that are tested in accordance with specifications. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 08 50 00 WINDOWS Page 9 of 12 .2 Hardware: Stainless steel or white bronze sash locks and aluminum handles to provide security and permit easy operation of units. .3 Fasteners: Provide non-magnetic stainless steel screws, epoxy adhesives, or other material warranted by the manufacturer. .4 Hopper windows: Cam handles to be Model No. 27-33 as manufactured by Truth Inc. and fastened to window frame complete with keeper. Hopper windows with lock device above 1900mm above floor to employ spring catch and keeper (transom handle) complete with pole operator adjustment. Provide samples prior to ordering. .5 Awning windows: Heavy-duty roto-operators to be manufactured by Truth Inc. Provide samples prior to ordering. .6 Casement windows: Multipoint locking hardware, butt hinges and locking handle on interior. Exterior will have slidebolt lock. Provide samples prior to ordering .7 Where window latching devices are above 1900 mm above floor: .1 .2 .3 Pole to CAN/CGSB-69.32-M90, Type 7-132, length to suit (2 per room). Pole hanger to CAN/CGSB-69.32-M90, Type 7-120 (2 per room). Equip projected and casement units with roto operators with locking handle. .8 Locks: Provide each operating sash with spring loading locking device at jamb, to provide automatic locking in closed position. .9 Include special keyed opening device for windows normally locked. 2.8 INSULATED PANELS .1 Type 1: 50 mm total thickness, with exterior face laminated to core laminated to interior face laminated to finish, as follows .1 .2 .3 .4 Exterior face: Duranar XL (3 coat) finish on 0.51 mm stucco-embossed aluminum sheet to CAN2-93.1-M85, Type 2, Class F1s, on 2.5 mm tempered hardboard. Core: Extruded polystyrene insulation to CAN/ULC S701, 72 kg/m3 density, with RSI of 0.88 per 25 mm. Inner fac: 2.5 mm tempered hardboard on aluminum sheet to gypsum wallboard of 12.7 mm thickness to CSA A82.27-M91. Finish: Fine grade natural cork, 6 mm thick, beige colour. .2 Fabricate panels so that thermal resistance of finished panel is not less than RSI 1.67. .3 Exterior colour to be selected by Owner from manufacturer’s standard colour range. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .4 2.9 Section 08 50 00 WINDOWS Page 10 of 12 Temporary panels, when required, to be constructed of plywood, sealed to provide a weathertight seal. Installation of panels may be carried out only before or after normal school hours. Temporary installations and off-hours work for this item are to be included at no additional cost to the Owner. WOOD TRIM .1 Wood sill, apron, ceiling trim, quarter round and miscellaneous trim pieces: Solid clear white pine, suitable for paint finish, sizes as shown on Drawings and to cover all areas of damage when removing window. Part 3 Execution 3.1 EXAMINATION .1 Verify conditions of substrates previously installed under other Sections or Contracts are acceptable for product installation in accordance with manufacturer's written instructions. .2 Visually inspect substrate in presence of Consultant. Verify that openings are dimensionally within allowable tolerances, plumb, level, clean, provide a solid anchoring surface and are in accordance with accepted shop drawings. .3 Verify soundness of top course of brick masonry directly below new window sill. Replace any loose or damaged brick, in locations as accepted by the Owner. Allow sufficient time for mortar to cure prior to installation of sill flashing membrane. .4 Inform Consultant of unacceptable conditions immediately upon discovery. .5 Proceed with installation only after unacceptable conditions have been remedied. .6 Commencement of the installation will be construed as acceptance of the site conditions and, thereafter, the Contractor shall be fully responsible for satisfactory work as specified herein. 3.2 INSTALLATION .1 Install air/vapour barrier as per manufacturer’s recommendations in locations indicated on drawings. .2 Window installation: .1 .2 .3 April 2016 Install in accordance with AAMA/WDMA/CSA 101/I.S.2/A440. Install drip flashing at window head. Prevent direct contact between aluminum window frame and steel, masonry or concrete using an isolation coating. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .4 .5 .6 .7 .3 .2 .3 .4 .5 .6 Foam insulate between frame members and window openings as shown on drawings. Sealant: .1 .2 April 2016 Install membrane sill flashing prior to window frame installation in accordance with manufacturer’s written instructions, with recommended overlap, such that water penetration into exterior wall is prevented. Upturn ends of membrane at jambs and seal to wood blocking/brick. Trim ends to conceal from view. Install metal sills with uniform wash to exterior, level in length, straight in alignment with plumb upstands and faces. Use one piece lengths at each location. Cut sills to fit window opening. Where joints occur in metal sill flashing, provide expansion joint covers and sealant to ensure that joints are watertight. Secure sills in place with anchoring devices located at ends joints of continuous sills and evenly spaced 600 mm on centre in between, or as shown on accepted shop drawings. Fasten expansion joint cover plates and drip deflectors with self-tapping stainless steel screws. Maintain 6 to 9 mm space between butt ends of continuous sills. For sills over 1200 mm in length, maintain 3 to 6 mm space at each end. Spray Foam Insulation: .1 .5 Plumb window faces in a single plane for each wall plane. Erect square and true. Anchor to maintain position when subjected to normal thermal and building movement, seismic forces and specified wind loads. Set glass properly centred with uniform bite and face and edge clearance, free from twist, warp or other distortion likely to develop stress. Leave glass whole and without cracks, scratches or other defects and with settings in perfect condition at completion, to approval of the Owner. Remove rejected, broken or damaged glass due to defective materials or improper setting and replace with perfect material. Units producing distorted vision shall be rejected and replaced at the reasonable discretion of the Owner. Arrange components to prevent abrupt variation in colour. Sill installation: .1 .4 Section 08 50 00 WINDOWS Page 11 of 12 Seal joints between frame members and other non-operating components with sealant to provide a weathertight seal at outside and air/vapour seal at inside. Seal joints between windows and window sills with sealant. Bed sill expansion joint cover plates and drip deflectors in bedding compound. Caulk between sill upstand and window-frame. Caulk butt joints in continuous sills. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 .6 Apply sealant in accordance with Section 07 92 00 - Joint Sealants. Conceal sealant within window units except where exposed use is permitted by Consultant. Trim Installation: .1 .2 .3 .4 3.3 Section 08 50 00 WINDOWS Page 12 of 12 Install extruded aluminum trim moulding to neatly cover joints between aluminum frame members and adjacent materials. Install wood sill, apron, ceiling trim, and all other necessary interior wood trim to provide neatly finished surfaces acceptable to the Owner, shimming as necessary to provide plumb and level finished surfaces, and to hide any defects in surface adjacent to new windows. Install wood quarter round as indicated on drawings, using 38 mm minimum finishing nails. Prime and paint all interior wood trim in accordance with Section 09 91 99 – Painting for Minor Works, to match existing paint finish around perimeter of window. Ensure adjacent surfaces are sufficiently masked to prevent damage during painting work. CLEANING .1 Progress cleaning: Clean in accordance with Section 01 74 11 - Cleaning. .1 Leave Work area clean at end of each day. .2 Final cleaning: Upon completion remove surplus materials, rubbish, tools and equipment in accordance with Section 01 74 11 - Cleaning. .3 Windows and glazing to be free of labels and be professional cleaned at interior and exterior, after installation. 3.4 PROTECTION .1 Protect installed products and components from damage during construction. .2 Repair damage to adjacent materials caused by window installation. 3.5 FIELD QUALITY CONTROL .1 Inspection and testing will be arranged and paid for by the Owner. .2 The Owner reserves the right to have inspections made to establish quality of work. Such inspections shall be made in the presence of the Contractor. .3 Notify the Owner in the event that the specifications conflict with the recommendations of the manufacturer. .4 Inspection and testing by the Owner does not relieve the Contractor of his responsibility for quality control of production and installation. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED REQUIREMENTS .1 Section 07 92 00 – Joint Sealants. .2 Section 08 11 16 – Aluminum Doors and Frames. .3 Section 08 44 13 - Glazed Aluminum Curtain Walls. .4 Section 08 50 00 - Windows. 1.2 Section 08 80 50 GLAZING Page 1 of 8 REFERENCES .1 ASTM International .1 .2 .3 .4 .5 .6 .7 .8 .2 Canadian General Standards Board (CGSB) .1 .2 .3 .3 CAN/CGSB-12.1-M90, Tempered or Laminated Safety Glass. CAN/CGSB-12.8-97, Insulating Glass Units. CAN/CGSB-12.9-M91, Spandrel Glass. Glass Association of North American (GANA) .1 .2 1.3 ASTM C542-05, Standard Specification for Lock-Strip Gaskets. ASTM D790-07e1, Standard Test Methods for Flexural Properties of Unreinforced and Reinforced Plastics and Electrical Insulating Materials. ASTM D1003-07e1, Standard Test Method for Haze and Luminous Transmittance of Plastics. ASTM D1929-96(R2001)e1, Standard Test Method for Determining Ignition Temperature of Plastics. ASTM D2240-05, Standard Test Method for Rubber Property - Durometer Hardness. ASTM E84-10, Standard Test Method for Surface Burning Characteristics of Building Materials. ASTM E330-02, Standard Test Method for Structural Performance of Exterior Windows, Doors, Skylights and Curtain Walls by Uniform Static Air Pressure Difference. ASTM F1233-08, Standard Test Method for Security Glazing Materials and Systems. GANA Glazing Manual - 2008. GANA Laminated Glazing Reference Manual - 2009. ACTION AND INFORMATIONAL SUBMITTALS .1 Submit in accordance with Section 01 33 00 - Submittal Procedures. .2 Product data: April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .1 .3 Submit manufacturer's instructions, printed product literature and data sheets for glass, sealants, and glazing accessories and include product characteristics, performance criteria, physical size, finish and limitations. Shop drawings: .1 .4 Section 08 80 50 GLAZING Page 2 of 8 Submit drawings stamped and signed by professional engineer registered or licensed in Province of Ontario, Canada. Samples: .1 .2 Submit for review and acceptance of each unit. Samples will be returned for inclusion into work. .5 Certificates: Submit product certificates signed by manufacturer certifying materials comply with specified performance characteristics and criteria and physical requirements. .6 Test reports: Certified test reports showing compliance with specified performance characteristics and physical properties. .1 .2 1.4 Submit testing and analysis of glass under provisions of Section 01 45 00 - Quality Control. Submit shop inspection and testing for glass. CLOSEOUT SUBMITTALS .1 Submit in accordance with Section 01 78 00 - Closeout Submittals. .2 Operation and maintenance data: Submit operation and maintenance data for glazing for incorporation into manual. 1.5 QUALITY ASSURANCE .1 Certificates: Product certificates signed by manufacturer certifying materials comply with specified performance characteristics and criteria and physical requirements. .2 Mock-ups: .1 .2 .3 .4 .5 April 2016 Construct mock-ups in accordance with Section 01 45 00 - Quality Control. Construct mock-up to include glass and perimeter air barrier and vapour retarder seal. Mock-up will be used: .1 To judge quality of work, substrate preparation, operation of equipment and material application. Locate where directed and where indicated. Allow 24 hours for inspection of mock-up before proceeding with work. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .6 1.6 Section 08 80 50 GLAZING Page 3 of 8 When accepted, mock-up will demonstrate minimum standard of quality required for this work. Approved mock-up may not remain as part of finished work. Remove mock-up and dispose of materials when no longer required and when directed by Consultant. WARRANTY .1 Contractor herby warrants insulating glass units against defects and for failure of seal enclosed air space and deposits on inner faces of glass detrimental to vision for five (5) years from the date of final completion. Cracked or scratched glass, shrinking, staining, hardening, sagging of materials, loosening or rattling of glass will be considered defective work. .2 Make all necessary repairs and replacements within forty-eight (48) hours of receipt of written notification. .3 Provide a written warranty confirming the above, issued on the corporate letterhead, signed and sealed by an authorized signing officer. .4 Nothing in this article shall be construed as in any way restricting or limiting the liability in common law and Statutory Liability of the Contractor. 1.7 DELIVERY, STORAGE AND HANDLING .1 Deliver, store and handle materials in accordance with manufacturer's written instructions. .2 Delivery and acceptance requirements: Deliver materials to site in original factory packaging, labelled with manufacturer's name and address. .3 Storage and handling requirements: .1 .2 .3 .4 1.8 Store materials off ground, indoors, in dry location and in accordance with manufacturer's recommendations in clean, dry, well-ventilated area. Store and protect glazing and frames from nicks, scratches, and blemishes. Protect prefinished aluminum surfaces with wrapping, strippable coating. Replace defective or damaged materials with new. AMBIENT CONDITIONS .1 Ambient requirements: .1 .2 April 2016 Install glazing when ambient temperature is 10°C minimum. Maintain ventilated environment for 24 hours after application. Maintain minimum ambient temperature before, during and 24 hours after installation of glazing compounds. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 2 Products 2.1 MATERIALS .1 Design criteria: .1 .2 .3 .2 .3 .4 .5 Float glass: To CAN/CGSB-12.3, thickness as indicated. Safety glass: To CAN/CGSB-12.1, transparent unless otherwise indicated, 6 mm thick. .1 Type 2-tempered. .2 Class B-float. .3 Category 1. Spandrel glass: To CAN/CGSB-12.9, 6 mm thick. .1 Type 2 - heat strengthened. .2 Form M – monolithic. .3 Colour for bronze window frame: Harmony Bronze, Opaci-Coat 300 #3-822. .4 Colour for clear aluminum frame: Harmony Grey, Opaci-Coat 300 #3-820. Patterned glass: To CAN/CGSB-12.13, 6 mm thick. .1 Type 1-annealed. .2 Styles A-figured one surface. .3 Surface treatment: etching. Low emissivity (LOW E) glass, thickness as indicated. .1 Metallic coating: hard, pyrolitic. .2 Shading co-efficient: maximum 0.41 (summer). .3 U-Value: winter 1.36 maximum, summer 1.19 maximum (metric). Insulating glass units: .1 .2 April 2016 Ensure continuity of building enclosure vapour and air barrier using glass and glazing materials as follow: .1 Utilize inner light of multiple light sealed units for continuity of air and vapour seal. Size glass to withstand wind loads, dead loads and positive and negative live loads acting normal to plane of glass to design pressure of 0.80 kPa. Limit glass deflection to flexural limit of glass with full recovery of glazing materials. Flat glass: .1 .2 .3 Section 08 80 50 GLAZING Page 4 of 8 Insulating glass units: To CAN/CGSB-12.8, double unit, 25 mm overall thickness. Standard IGU construction. .1 Exterior lite: 6 mm tempered glass, 20% grey tint. .2 Low-E coating on #2 face, Solarban 60 or approved equivalent. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .3 .4 .5 .4 2.2 Section 08 80 50 GLAZING Page 5 of 8 12.7 mm warm-edge spacer. Argon-filled cavity. Interior lite: 6 mm clear tempered glass (use patterned glass at washroom areas). Sealant: In accordance with Section 07 92 00 - Joint Sealants. ACCESSORIES .1 Setting blocks: Neoprene, 70-80 Shore A durometer hardness to ASTM D2240, minimum 100 mm x 6 mm high width to suit glazing method, glass light weight and area. Design blocks to not restrict water flow to weep holes. .2 Spacer shims: Neoprene, 70-80 Shore A durometer hardness to ASTM D2240, 75 mm long x 9 mm high x 2.4 mm thick. Self adhesive on one face. .3 Glazing tape: .1 Preformed butyl compound with integral resilient tube spacing device,10-15 Shore A durometer hardness to ASTM D2240; coiled on release paper; self-adhesive, black colour. .4 Glazing splines: Resilient polyvinyl chloride, extruded shape to suit glazing channel retaining slot. .5 Glazing clips: Manufacturer's standard type. .6 Primers, sealers and cleaners: To glass manufacturer’s recommendations. Part 3 Execution 3.1 EXAMINATION .1 Verification of conditions: Verify conditions of substrates previously installed under other Sections or Contracts are acceptable for glazing installation in accordance with manufacturer's written instructions. .1 .2 .3 .4 .5 April 2016 Verify that openings for glazing are correctly sized and within tolerance. Verify that surfaces of glazing channels or recesses are clean, free of obstructions, and ready to receive glazing. Inform Owner in writing of unacceptable conditions immediately upon discovery. Proceed with installation only after unacceptable conditions have been remedied. Commencement of the installation will be construed as acceptance of the site conditions and, thereafter, the Contractor shall be fully responsible for satisfactory work as specified herein. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 3.2 Section 08 80 50 GLAZING Page 6 of 8 PREPARATION .1 Remove protective coatings, clean contact surfaces with solvent and wipe dry. .2 Seal porous glazing channels or recesses with substrate compatible primer or sealer. .3 Prime surfaces scheduled to receive sealant. .4 Place setting blocks as per manufacturer’ instructions. .5 Install glass to ensure full bearing and contact with setting block. .6 Install removable stops, without displacing glazing tape or sealant. Exert pressure as required to provide full continuous contact. .7 Provide edge clearance of at least 3 mm in all locations. .8 Insert spacer shims to centre glass in space. Place shims at 600 mm centres and keep 6 mm below sight line. 3.3 CURTAINWALL GLAZING INSTALLATION: EXTERIOR WET/DRY METHOD (PREFORMED TAPE AND SEALANT) .1 Perform work in accordance with GANA Glazing Manual for glazing installation methods. .2 Cut glazing tape to length and set against permanent stops, 6 mm below sight line. Seal corners by butting tape and dabbing with sealant. .3 Apply heel bead of sealant along intersection of permanent stop with frame ensuring full perimeter seal between glass and frame to complete continuity of air and vapour seal. .4 Place setting blocks at 1/4 points, with edge block maximum 150 mm from corners. Do not block drainage cavities. .5 Centre glass unit in opening. Rest glazing on setting blocks and push against tape and heel head of sealant with sufficient pressure to attain full contact at perimeter of light or glass unit. .6 Install pressure plates with gaskets or glazing tape as required. Ensure proper alignment of weep holes for drainage at base of glass unit. Ensure proper compression of gaskets or glazing tape. Seal ends of abutting pressure plates. 3.4 WINDOW GLAZING INSTALLATION: INTERIOR DRY METHOD (TAPE AND TAPE) .1 April 2016 Perform work in accordance with GANA Glazing Manual for glazing installation methods. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 08 80 50 GLAZING Page 7 of 8 .2 Cut glazing tape to length and set against permanent stops, projecting 1.6 mm above sight line. .3 Place setting blocks at 1/3 points, with edge block maximum 150 mm from corners. .4 Rest glazing on setting blocks and push against tape for full contact at perimeter of light or unit. .5 Place glazing tape on free perimeter of glazing in same manner described. .6 Install removable stop without displacement of tape. Exert pressure on tape for full continuous contact. .7 Knife trim protruding tape. .8 For gaskets 3.5 WINDOW GLAZING INSTALLATION: INTERIOR WET/DRY METHOD (TAPE AND SEALANT) .1 Perform work in accordance with GANA Glazing Manual for glazing installation methods. .2 Cut glazing tape to length and install against permanent stops, projecting 1.6 mm above sight line. .3 Place setting blocks at 1/3 points, with edge block maximum 150 mm from corners. .4 Rest glazing on setting blocks and push against tape to ensure full contact at perimeter of light or unit. .5 Install removable stops, with spacer shims inserted between glazing and applied stops at 600 mm intervals, 6 mm below sight line. .6 Fill gaps between light and applied stop with sealant to depth equal to bite on glazing, to uniform and level line. .7 Trim protruding tape edge. 3.6 FINISHING .1 Make good damage to adjacent finished surfaces. .2 Leave glass whole and without cracks, scratches or other defects, and with settings in perfect condition at completion, to the approval of the Owner. Remove rejected, broken, or damaged glass due to defective materials or April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 08 80 50 GLAZING Page 8 of 8 improper setting and replace with perfect materials. Units producing distorted vision shall be rejected and replaced at the reasonable discretion of the Owner. 3.7 CLEANING .1 Progress cleaning: Clean in accordance with Section 01 74 11 - Cleaning. .1 .2 3.8 Leave work area clean at end of each day. .1 Remove traces of primer, caulking. .2 Remove glazing materials from finish surfaces. .3 Remove labels. .4 Clean glass using approved non-abrasive cleaner in accordance with manufacturer's instructions. Final cleaning: Upon completion remove surplus materials, rubbish, tools and equipment in accordance with Section 01 74 11 - Cleaning. Have glazing exterior and interior professionally cleaned. PROTECTION .1 Protect installed products and components from damage during construction. .2 After installation, mark each light with an "X" by using removable plastic tape or paste. .1 .3 Do not mark heat absorbing or reflective glass units. Repair damage to adjacent materials caused by glazing installation. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Part 1 General 1.1 RELATED SECTIONS Section 22 05 11 PLUMBING AND DRAINAGE Page 1 of 7 .1 Section 02 41 13 – Selective Site Demolition. .2 Section 06 10 00 - Rough Carpentry. .3 Section 07 52 00 - Modified Bituminous Membrane Roofing. .4 Section 07 62 00 – Sheet Metal Flashing and Trim. .5 Section 07 92 00 – Joint Sealants. 1.2 REFERENCES .1 American Water Works Association (AWWA). .1 .2 .2 Cast Iron Soil Pipe Institute (CISPI) .1 .3 CISPI 310-12, Specification for Coupling for Use in Connection with Hubless Cast Iron Soil Pipe and Fittings for Sanitary and Storm Drain, Waste, and Vent Piping Applications. Canadian Standards Association (CSA International) .1 .2 .3 .4 1.3 ANSI/AWWA C110/A21.10-08, American National Standard for DuctileIron and Gray-Iron Fittings for Water. ANSI/AWWA C111/A21.11-12, Standard for Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings. CAN/CSA B70.1-03 (R2013), Frames and Covers for Maintenance Holes and Catchbasins. CAN/CSA-B70-12, Cast Iron Soil Pipe, Fittings, and Means of Joining. CSA B79-08 (R2013), Commercial and residential drains and cleanouts. CAN/CSA B1800-11, Thermoplastic Nonpressure Piping Compendium. SUBMITTAL / APPROVAL .1 Do not commence work until satisfactory installation of related work has been completed and approved. .2 Inspect work and advise Consultant of conditions that would adversely affect the work of this trade. .3 Commencement of work is proof that the Contractor has accepted surfaces as satisfactory for intended operations and accepted responsibility for appearance and performance of completed work. .4 Defective work resulting from work on unsatisfactory surfaces will be considered the responsibility of those performing the work of this Section. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 22 05 11 PLUMBING AND DRAINAGE Page 2 of 7 .5 Repair damage and inferior work caused by the work of this Contract with materials and finish to match the original to Consultant’s approval. .6 Submit to the Consultant a list of materials intended for use before they are ordered. .7 Provide samples of material without additional cost, to the Consultant for review as requested. 1.4 SHOP DRAWINGS .1 1.5 When drainpipes are required to pass through a structural or masonry wall, fire wall, structural member or ductwork, provide shop drawings as per Section 01 33 00 – Submittal Procedures. The intent of the design is to ensure the proper slope of plumbing is maintained through the structure, the structure is properly reinforced or strengthened, that fire protection and sound control is maintained and work complies with relevant codes. QUALITY ASSURANCE .1 All drain installations shall be completed by plumbing subtrades licensed to undertake plumbing work in Ontario. .2 Equipment and materials must be new and free of imperfections. Part 2 Products 2.1 MATERIALS .1 All standards, regulations and specifications listed herein are considered to be the latest available edition. .2 Compatibility between materials is essential. Use only materials that are known to be compatible when incorporated in a completed assembly. .3 Cast iron roof drains: Controlled flow, cast iron body, under deck clamp and sump receiver to suit roof construction, flashing clamp ring with bearing pan, flow control weir assembly, and cast iron dome. .1 .4 April 2016 Standard of acceptance or approved equivalent: .1 Watts Drain RD-100. Pipe: 75 mm cast iron water pipe shall conform to CAN/CSA-B70 cast iron pipe, fittings and methods of joining. PVC drain waste and vent pipe and pipe fittings to CAN/CSA B1800. ABS drain waste and vent pipe and pipe fittings to CAN/CSA B1800 Copper pipes to ASTM B42. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 22 05 11 PLUMBING AND DRAINAGE Page 3 of 7 .5 Pipe hangers: Adjustable type wrought iron design to allow pipe movement and insulation to pass unbroken through hanger. .6 Mechanical joints: Neoprene or butyl rubber gasket with stainless steel clamp type joint to CISPI 310-12. .7 Drain connector: .1 Standard of acceptance or approved equivalent: .1 Fernco Couplings. .2 U-Flow Connector by U-Flow Inc. .8 Fittings: Iron fittings for cast iron or ductile-iron water pipes shall conform to ANSI/AWWA C110/A21.10, 75 mm through 1200 mm, for water and other liquids. .9 Rubber gasket joints: For cast iron and ductile-iron pressure pipe for water piping shall conform to ANSI/AWWA C111/A21.11. For connection of copper drain pipe to cast iron drain pipe use Fernco 975 mm x 100 mm rubber gasket. .10 Downpipe clamp: 1.21 mm (18 ga.) galvanized 2-hole clamp. Profile to suit pipe and size. .11 Insulation for pipes: 25 mm thick performed type mineral fibre insulation to ASTM C547. .1 Standard of acceptance or approved equivalent: .1 Roxul Techton 1200 or SSL II Fiberglas by Owens Corning. .12 Insulation for drains: 2 component 1 kg density polyurethane foam as detailed. .13 Insulation covering: .1 .2 .14 Firestop sealant: Approved by manufacturer for use in fire-rated firestop assembly. .1 .15 April 2016 Standard of acceptance or approved equivalent: .1 A/D Firebarrier Silicone, 3M Fire Barrier. Firestop insulation: Mineral wool approved by manufacturer for use in fire-rated firestop assembly. .1 .16 Cover pipe insulation with canvas membrane wrap and paint. Where exposed, use preformed PVC. Standard of acceptance or approved equivalent: .1 Roxul ‘Safe’, AD Firebarrier. Steel deck reinforcement: 0.79 mm (22 ga.) galvanized steel to cover opening in deck at drain removal locations. Steel plate to extend a minimum of 300 mm from edge of opening on all sides, as per detail. Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 2.2 Section 22 05 11 PLUMBING AND DRAINAGE Page 4 of 7 DRAIN ACCESS DOOR .1 New access panels shall be of galvanized steel construction with hinged openings and a decorative flange to cover the ceiling cut edges. Units shall have a factory applied white paint finish. Minimum steel thickness shall be 0.7 mm and have self-locking access. Part 3 Execution 3.1 PREPARATION .1 Inspect surfaces and ensure that: .1 .2 .3 .4 .5 Roof deck is level or sloped to provide proper and complete drainage from the roofing system in conformity to design intent. Roof drains are set at a level to allow for positive drainage and are connected or capped. Plumbing is accessible and work can be completed as specified. Notify Consultant of any adverse conditions. Existing roof drains are open and functioning properly. For costing and practical purposes, location of new drains and plumbing are approximate and should be considered accurate within 3 m. Advise Consultant of variances and adjust locations as required to facilitate installation without additional cost, to the Consultant’s approval. .2 Contractor shall advise Consultant in the event that the existing system or materials do not meet current code requirements. .3 Unless indicated otherwise, the plumbing sub-trade shall be responsible for the removal and reinstatement of furniture, plants and interior equipment, excluding computers, monitors, copiers and the like. .4 Contractor to provide interior protection to all areas where plumbing work is being completed. Provide sufficient dust and debris protection for the temporary removal of ceiling tiles, and include for any supplemental clean up to return interiors to pre-construction conditions. .5 Remove all ceiling panels and plaster finish to provide access to the work. Reinstall and make good all existing finishes to match original materials and conditions. Repainting of surfaces shall include all ceiling all wall areas up to a break in plane, unless otherwise indicated on drawings. .6 Remove and discard all existing drains and plumbing not designated for re-use. Notify Owner of any hazardous materials encountered. .7 In poured concrete decks, scan roof deck for presence of reinforcing steel or cast-in conduits, prior to coring. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa 3.2 Section 22 05 11 PLUMBING AND DRAINAGE Page 5 of 7 INSTALLATION OF NEW DRAIN LOCATIONS .1 Provide core holes through substrate for new drain locations. .2 Reinforce holes in deck in accordance with drawings. .3 Relocate drains at locations shown on drawings. Provide new openings and new plumbing to connect to existing drainage system. Remove and roof over existing drain of these locations. .4 Where new plumbing is required, install cast iron pipe of 75 mm minimum diameter. New plumbing lines are to be connected into existing plumbing. Contractor responsible for determining plumbing runs. Allow for penetrating block walls, structural members, rerouting ductwork and any other mechanical services required. Provide any required fireproofing of new penetrations. .5 Ensure water conductor has proper slope to meet design requirements to ensure adequate drainage. Slope horizontal drain pipe at 20 mm/1000 mm unless otherwise specified. .6 Provide clean-outs for drains and soil pipes in straight runs at end of branches. .7 Piping shall be provided with support that is capable of keeping the pipe in alignment and bearing the weight of the pipe and its contents. Provide solid support to existing structure. Secure to underside of concrete decks or steel decks with approved anchors. Support cast iron pipe: .1 .2 .3 At or adjacent to each hub or joint. At intervals not exceeding 1800 mm with 13 mm diameter rods and At intervals not exceeding 900 mm if the pipe has mechanical joints and the length of pipe between adjacent fittings is 300 mm or less. .8 Join pipe by means of rubber gaskets or mechanical couplings. .9 Include means to accommodate expansion and contraction of the piping system caused by temperature change. .10 Fill voids around drain opening on concrete or lightweight concrete decks with quick dry concrete grout flush with top and bottom of deck. .11 Insulate all new plumbing lines to meet acoustical and thermal requirements. .12 Wrap all new insulated plumbing lines with PVC covering at exposed locations. .13 Extend insulation from pipes to drain hub. Cover with pipe wrapping and finish to general standards. If blanket insulation is used, ensure that all insulation fits tight to drain hub. Seal overlaps, edges and joints with reinforced vapour proof tape suitable to permanently hold insulation in place. Alternatively, in conformance with drawings, protect hubs with spray foam insulation, minimum thickness April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa Section 22 05 11 PLUMBING AND DRAINAGE Page 6 of 7 38 mm unless otherwise specified or shown. Provide metal protection pan over deck as detailed. .14 Provide firestop material around plumbing penetrations through firewalls. .15 All ceilings to be restored to original condition. Suspended ceilings to be restored to original condition and painted to match existing colour and finish. If paint colour cannot be matched, entire wall or ceiling area to be painted to blend into existing room to Owner’s approval. .16 Restore all existing surfaces affected by work of this trade to match existing material and finish. .17 Cap all drain lines that are no longer required. .18 Ensure each roof is provided with operational drainage at the end of each work day. 3.3 INSTALLATION AT EXISTING DRAIN LOCATIONS .1 Increase openings in structures to facilitate plumbing as required. .2 Join pipe by means of rubber gaskets or mechanical couplings. .3 Fill voids around drain opening on concrete or lightweight concrete decks with quick dry concrete grout flush with top and bottom of deck. .4 Where area is inaccessible to install couplings, advise and request Consultant to obtain a ruling on acceptability. Where directed by Consultant, install antibackflow seals to match pipe size and secure in place. .5 Extend insulation from pipes to drain hub. Cover with pipe wrapping and finish to general standards. If blanket insulation is used, ensure that all insulation fits tight to drain hub. Seal overlaps, edges and joints with reinforced vapour proof tape suitable to permanently hold insulation in place. Alternatively, in conformance with drawings, protect hubs with spray foam insulation, minimum thickness 38 mm unless otherwise specified or shown. Provide metal protection pan over deck as detailed. .6 Install PVC covering over insulated piping where plumbing is exposed on the interior of the building. .7 All ceilings to be restored to original condition. Suspended ceilings to be restored to original condition and painted to match existing colour and finish. If paint colour cannot be matched, entire wall or ceiling area to be painted to blend into existing room to Owner’s approval. .8 Restore all existing surfaces affected by work of this trade to match existing material and finish. April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D Window, Door, Roof, Boiler & RTU Replacement Woodroffe High School 2410 Georgina Drive, Ottawa .9 3.4 Section 22 05 11 PLUMBING AND DRAINAGE Page 7 of 7 Ensure each roof is provided with operational drainage at the end of each work day. DRAIN ACCESS DOOR .1 3.5 Cut access opening in existing finished ceiling in most optimum location to access new drain/piping or as indicated on drawings. Cut edges neatly and install hatch, ensuring that door opening is in the direction of the larger area of ceiling space to facilitate ease of future ladder use. Install hatch plumb level with decorative flange flush with ceiling and anchor in position in accordance with manufacturers printed instructions. PLUMBING VENT MODIFICATIONS .1 3.6 Cut down or extend existing soil stacks to a minimum height of 300 mm above finished roof surface. Extensions to match existing material and connections to be made with mechanical joint couplings. PIPING TEST .1 Perform water tests before restoring interior ceilings and finishes. .2 Install plumbing line plugs below the level of connection and water test new plumbing installation. Correct all leaks. .3 Make leaks watertight while systems are still under test. If this is impossible, remove and refit defective parts. Caulking of threaded joints will not be permitted. .4 After leaks have been repaired, repeat tests as often as necessary to obtain approval and to ensure watertightness of each system. .5 Correct level of drains or pipes, if roof or pipes hold water. 3.7 FINISH .1 Reset existing ceiling finishes removed to execute work of this Contract. .2 Restore and repair all existing surfaces affected by the work to match existing materials and finish. .3 Re-paint entire ceiling or walls where it is required to make patching work undisguisable with existing surfaces. END OF SECTION April 2016 Fishburn Sheridan & Associates Ltd. FSA Project No.: 15255D February 29, 2016 Ms. Jean Voth, P.Eng. Ottawa Carleton District School Board 1224 Main Street, Stittsville, ON K2S 0E2 Our Ref.: RM1845 Targeted Designated Substance Investigation Woodroffe High School – Window Replacement 2016 CM3 Environmental (CM3) was commissioned by the Ottawa Carleton District School Board (OCDSB) to complete a project-specific review for designated substances and hazardous materials at the above referenced site. The assessed area was limited to the parts of the building within the area to be renovated. The extent of the assessed area was outlined by the Client and is shown on the attached drawings (Refer to Appendix A). The building was previously assessed by Others in 2007 as per the report entitled “Designated Substance Survey Ottawa Carleton District School Board, Woodroffe High School Ottawa, Ontario”, dated September 2007. Findings from this report have been relied upon for the purposes of this assessment. Regulatory Requirements The completion of this survey and the presentation of the findings herein were made to fulfill the Owner's requirement to complete a project specific/targeted Designated Substance Survey(DSS) to comply with Ontario Regulation 278/05, “Regulation Respecting Asbestos on Construction Projects and in Buildings and Repair Operations” and Section 30 of the “Occupational Health and Safety Act”. CM3 further enhanced the survey to include all other designated substances regulated under Ontario Regulation 490/09 of the Occupational Health and Safety Act OHSA. Under Section 30 of the OHSA, a project “owner shall determine whether any designated substances are present at the project site and shall prepare a list of all designated substances that are present”. The following is a list of substances regulated by O.Reg 490/09: Acrylonitrile; Arsenic; Asbestos; Benzene; CM3 Environmental Inc. 208-2120 Robertson Road, Ottawa, Ontario, K2H 5Z1 CM3 Environmental Inc. Woodroffe High School – Window Replacement 2016 File: RM1845 February 2016 Coke Oven Emissions; Ethylene Oxide; Isocyanates; Lead; Mercury; Silica; and Vinyl Chloride. The following Hazardous Building Materials are not Designated Substances regulated by 490/09, but could pose a significant risk to health and safety of workers, occupants, and the environment are included as part of this report. The Ministry of Labour (MOL) recognizes them as workplace hazards and enforces worker protection under the General Duty Clause 25(2)(h) of the OHSA. Clause 25(2)(h) states that the employers are required to “take every precaution reasonable in the circumstances for the protection of a worker”. In such cases the MOL will refer to industry standards and guidelines for the safe handling and management of such materials. Ozone Depleting Substances (ODSs) - Federal Halocarbon Regulation 2003; and Polychlorinated Biphenyls (PCBs) - SOR/2008-273. Scope This report is based on the site inspection that was conducted on February 15, 2016 by Adam Nguyen of CM3 Environmental Inc. (CM3). The subject facility is owned and operated by the OCDSB and is located at 2410 Georgina Drive, Ottawa, Ontario. Non-destructive survey techniques were employed during the site reconnaissance. The visual inspection and sampling (in the original DSS), was limited to readily accessible areas and was completed to comply with all applicable regulations. The survey did not include the demolition of ceilings or walls, or other areas to examine concealed conditions. The designated substances mentioned above may be present in partial and non-accessed areas and concealed spaces (i.e. wall, columns and ceiling cavities). Furthermore, materials located within wall cavities and in columns could not be observed in order to determine their content or condition. In addition, CM3 would extrapolate quantities based on quantities observed in fully accessible locations. This targeted designated substance survey report has been prepared using the information provided to CM3 by the OCDSB, through information obtained during the site reconnaissance and analytical data. In addition, the survey does not refer to substances that may be present in the day-to-day usage for other specialized equipment or areas in buildings (i.e. portable equipment, lead shields, fume hoods, etc.). There is a possibility that materials may exist which could not be reasonably identified within the scope of this assessment, or which were not apparent during previous site visits. 2 CM3 Environmental Inc. Woodroffe High School – Window Replacement 2016 File: RM1845 February 2016 Analytical Procedure Suspect materials were primarily assessed by visual inspection. On the basis of this inspection, select samples were collected from discrete locations using industry-accepted, safe sampling techniques that include the pre-wetting of materials and concealment of materials after collection. The number of samples collected is based on the suspect building materials present and the sampling criteria outlined in Table 1 “Bulk Materials Samples” of Ontario Regulation 278/05. A total of 206 asbestos bulk samples were previously collected by others. Nine (9) additional samples collected were submitted to EMSL Canada Inc in Ottawa, Ontario. Samples were analyzed by polarized light microscopy with dispersion staining, following USEPA method 600/R-93/116. EMSL Canada Inc.participates in the National Voluntary Laboratory Accreditation Program (NVLAP # 200877-0). All samples were submitted on a positive stop basis, meaning that similar samples were not analyzed if the preceding sample was confirmed to contain asbestos. The laboratory analytical reports are presented in APPENDIX B. Findings The following hazardous materials could be disturbed as part of the window replacement. Asbestos 1960 Phase of Construction Plaster walls found around windows. (3% Chrysotile asbestos) Plaster walls with texture finish found around windows. (2% Chrysotile asbestos) Plaster ceiling found above windows. (5% Chrysotile asbestos) Transite boards found as soffits on the exterior of building above windows. (20% Chrysotile asbestos) Red black and grey exterior finish found above and below windows. (2% Chrysotile asbestos) 1961 Phase of Construction Plaster walls found around windows. (3% Chrysotile asbestos) Plaster ceilings found above windows. (3% Chrysotile asbestos) Plaster walls with texture finish found around windows. (2% Chrysotile asbestos) Exterior brick mortar around windows. (1-2% Chrysotile asbestos) Red black and grey exterior finish found above and below windows. (2% Chrysotile asbestos) Exterior grey caulking found around windows. (2% Chrysotile asbestos) 3 CM3 Environmental Inc. Woodroffe High School – Window Replacement 2016 File: RM1845 February 2016 Other asbestos-containing materials are present within the building. Lead Lead is a naturally occurring metal element and is the most common metal found in the environment. Pure metallic lead was primarily used to make products such as electric storage batteries, ammunition, solder, radiation shields, pipes and sheaths for electric cables. The most common organic lead compounds are tetraethyl (TEL) and tetra methyl (TML) lead that were used as anti-knock agents in gasoline. Inorganic lead compounds such as lead oxides, chromates, carbonates and nitrates are commonly found in insecticides, pigments, paints, frits, glasses, plastics and rubber compounds. A total of 25 samples of paint chip samples were collected by others. Paint chip samples were collected from painted surfaces within the building. All paint chip samples were collected by scraping the paint down to the base material substrate to ensure collection of all layers of paint. Care was taken to avoid collection of the underlying substrate to reduce analytical substrate matrix interference. A variety of paints were observed throughout the building. The paint samples submitted for analysis represent the overall majority of paint that exists within the assessed area. Paints that exist on a single door, a cabinet, a small area, etc., may be considered lead based paint. Portions of the building have been painted with new products, and are unlikely to contain lead (Pb). No additional lead samples were taken. The following paint samples with elevated concentrations of lead that may be affected during the window replacement project are as follows: SL-08 White Wall Paint – 1620ppm SL-11 Beige Wall Paint – 1010ppm Silica Free crystalline silica is expected to be present within all plaster finishes, concrete and mortar based building materials as well as acoustic ceiling tiles. Recommendations Asbestos Since some of the window framing extents right to the ceiling, and due to the presence of asbestoscontaining ceiling plaster, wall plaster and plaster with texture finish, transite boards, caulking, brick mortar and exterior texture finish, asbestos abatement measures and procedures are required prior to the window extraction. Based on the scope of the window replacement, the friable nature of the ceiling and wall plaster, the exterior red, black and grey colored finish and brick mortar a minimum Type 2 measures and procedures are recommended if less than 1 meter square of the ACM materials are being removed using hand held tools only; although Type 3 abatement precautions may be required if power tools are being used or quantities exceed more than 1 meter square as per Ontario Regulation 278/05 “Regulation respecting asbestos in Construction Projects and in Buildings and Repair Operations”. 4 CM3 Environmental Inc. Woodroffe High School – Window Replacement 2016 File: RM1845 February 2016 Type 1 abatement procedures will be required for the removal of the exterior caulking around the windows and the transite boards above the windows. Lead If work on lead containing materials is likely to produce lead dust or fumes, for example during welding, torch cutting, grinding, sanding or sandblasting, then proper precautions should be followed. As best industry practice, CM3 recommends that the ministry of Labour “Guideline for Lead on Construction Projects” be followed when working with potential lead hazards. The Time-Weighted Average Exposure Limits (TWAEL) of a worker to lead is to be maintained at the lowest practical level and not exceed an eight hour average concentration of 0.05 mg/m³ of air for non-tetraethyl lead and 0.10 mg/m³ of air in the case of tetraethyl lead. Silica Silica occurs naturally as crystalline material in concrete and cement. Crystalline silica is significantly more toxic than amorphous silica. Therefore for health reasons, only crystalline varieties are regulated under Ontario Regulation 490/09 as one of the designated substances. Silica dust can be generated through such processes such as blasting, grinding, crushing or sandblasting silica-containing material. Silica is often found contained within concrete walls, stairs and ramps. Therefore, appropriate respiratory protection and ventilation must be utilized during construction and demolition. As best industry practice CM3 recommends that the ministry of Labour “Guideline for Silica on Construction Projects” is followed when dealing with potential silica hazards. All other designated substances pose no health and safety concern for the window renovations. Limitations This report has been prepared and the work referred to in this report has been undertaken by CM3 Environmental Inc. for the Ottawa Carleton District School Board (OCDSB). It is intended for the sole and exclusive use of OCDSB and its authorized agents for the purpose(s) set out in this report. Any use of, reliance on or decision made based on this report by any person other than OCDSB for any purpose, or by OCDSB for a purpose other than the purpose(s) set out in this report, is the sole responsibility of such other person or OCDSB. OCDSB and CM3 Environmental Inc. make no representation or warranty to any other person with regard to this report and the work referred to in this report and they accept no duty of care to any other person or any liability or responsibility whatsoever for any losses, expenses, damages, fines, penalties or other harm that may be suffered or incurred by any other person as a result of the use of, reliance on, any decision made or any action taken based on this report or the work referred to in this report. Any conclusions or recommendations made in this report reflect CM3 Environmental Inc.’s judgment based on the following limited investigations: visual site inspection(s) on the date(s) set out in this report; examination of public records; and interviews with individuals having information about the site. While efforts have been made to substantiate information provided by third parties, CM3 Environmental Inc. makes no representation or warranty as to its completeness or accuracy. This report has been prepared for specific application to this site. Unless otherwise stated, the findings cannot be extended to previous or future site conditions; portions of the site which were unavailable for direct investigation; subsurface locations which were not investigated directly; or chemical parameters, materials or analysis which were not addressed. Substances other than those addressed by the investigation described in this report may exist within the site; and 5 CM3 Environmental Inc. Woodroffe High School – Window Replacement 2016 File: RM1845 February 2016 substances addressed by the investigation may exist in areas of the site not investigated or in quantities not ascertained. Nothing in this report is intended to constitute or provide a legal opinion. CM3 Environmental Inc. makes no representation as to the requirements of or compliance with environmental laws, rules, regulations or policies established by federal, provincial or local government bodies. Revisions to the regulatory standards referred to in this report may be expected over time. As a result, modifications to the findings, conclusions and recommendations in this report may be necessary. Other than by OCDSB and its authorized agents and as set out herein, copying or distribution of this report or use of or reliance on the information contained herein, in whole or in part, is not permitted without the express written permission of CM3 Environmental Inc. Respectfully submitted, CM3 Environmental Inc. Prepared by: Reviewed by: Adam Nguyen Environmental Technician adam@cm3environmental.com Robert D. McGrath, B.E.S. Principal/Environmental Consultant rob@cm3environmental.com 6 CM3 Environmental Inc. Woodroffe High School – Window Replacement 2016 File: RM1845 February 2016 APPENDIX A Drawings Project Specific Designated Substance Survey Report Ottawa Carleton District School Board – Woodroffe High School 2410 Georgina Drive, Ottawa, Ontario 7 CM3 Environmental Inc. Woodroffe High School – Window Replacement 2016 File: RM1845 February 2016 APPENDIX B Analytical Results Project Specific Designated Substance Survey Report Ottawa Carleton District School Board – Woodroffe High School 2410 Georgina Drive, Ottawa, Ontario 8 EMSL Canada Inc. EMSL Canada Order 671600256 ID: 55CMTE42 Customer ID: Customer PO: Project ID: 22 Antares Drive Suite 102 Ottawa, ON K2E 7Z6 Phone/Fax: 343-882-6076 / (343) 882-6077 http://www.EMSL.com / ottawalab@EMSL.com Attn: Proj: Phone: Fax: Collected: Received: Analyzed: Robert McGrath CM3 Environmental Inc. Unit 208 120 Robertson Rd. Nepean, ON K2H 5Z1 (613) 820-4343 2/15/2016 2/25/2016 2/26/2016 RM 1845 Test Report: Asbestos Analysis of Bulk Materials for Ontario Regulation 278/05 via EPA600/R-93/116 Method Client Sample ID: Sample Description: Lab Sample ID: EF02A Exterior finish/Exterior of Building Analyzed TEST Non-Asbestos Date PLM Color 2/26/2016 Client Sample ID: Sample Description: White White White 2% Non-Fibrous 98% Fibrous 2% Non-Fibrous 98% Asbestos Comment 671600256-0004 Non-Asbestos Date Color Gray/Red/Black Fibrous 4% Non-Fibrous 94% Asbestos Comment 2% Chrysotile Lab Sample ID: EF01B 671600256-0005 Exterior finish/Exterior of Building Analyzed TEST Date PLM Non-Asbestos Color Fibrous Non-Fibrous 2/26/2016 Asbestos Comment Stop Positive (Not Analyzed) Lab Sample ID: EF01C 671600256-0006 Exterior finish/Exterior of Building Analyzed TEST Date PLM Non-Asbestos Color Fibrous Non-Fibrous 2/26/2016 Asbestos Comment Stop Positive (Not Analyzed) Lab Sample ID: CLK01A 671600256-0007 Exterior caulking - phase 2/Exterior caulking Analyzed TEST 671600256-0003 None Detected Lab Sample ID: 2/26/2016 Sample Description: Comment Exterior finish/Exterior of Building PLM Client Sample ID: Asbestos None Detected EF01A Analyzed Sample Description: 671600256-0002 Non-Asbestos Color 2/26/2016 TEST PLM Fibrous Lab Sample ID: Date PLM Client Sample ID: Comment Exterior finish/Exterior of Building Analyzed Sample Description: Asbestos None Detected EF02C TEST Client Sample ID: 98% Non-Asbestos Color 2/26/2016 Sample Description: Non-Fibrous Lab Sample ID: Date PLM Client Sample ID: 2% Exterior finish/Exterior of Building Analyzed Sample Description: Fibrous EF02B TEST Client Sample ID: 671600256-0001 Date 2/26/2016 Test Report:EPAMultiTests-7.32.2.D Printed: 2/26/2016 02:51PM Non-Asbestos Color Gray Fibrous 7% Non-Fibrous 93% Asbestos Comment None Detected Page 1 of 2 EMSL Canada Inc. EMSL Canada Order 671600256 ID: 55CMTE42 Customer ID: Customer PO: Project ID: 22 Antares Drive Suite 102 Ottawa, ON K2E 7Z6 Phone/Fax: 343-882-6076 / (343) 882-6077 http://www.EMSL.com / ottawalab@EMSL.com Test Report: Asbestos Analysis of Bulk Materials for Ontario Regulation 278/05 via EPA600/R-93/116 Method Lab Sample ID: CLK01B Client Sample ID: Sample Description: Exterior caulking - phase 2/Exterior caulking Analyzed TEST Date PLM 2/26/2016 Non-Asbestos Color Gray Fibrous 7% Non-Fibrous 91% Asbestos Sample Description: Comment 2% Chrysotile Lab Sample ID: CLK01C Client Sample ID: 671600256-0008 671600256-0009 Exterior caulking - phase 2/Exterior caulking Analyzed TEST Date PLM Non-Asbestos Color 2/26/2016 Fibrous Non-Fibrous Asbestos Comment Stop Positive (Not Analyzed) Analyst(s): Hilary Roberts PLM (2) Simon Parent PLM (4) Reviewed and approved by: Lemma Mohammad , Laboratory Manager or Other Approved Signatory None Detected = <0.5%. EMSL maintains liability limited to cost of analysis. This report relates only to the samples reported above and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. Interpretation and use of test results are the responsibility of the client. Samples received in good condition unless otherwise noted. This report must not be used to claim product endorsement by NVLAP of any agency of the U.S. Government. Samples analyzed by EMSL Canada Inc. Ottawa, ON Initial report from: 02/26/201614:51:01 Test Report:EPAMultiTests-7.32.2.D Printed: 2/26/2016 02:51PM Page 2 of 2