WP2 Final Report - 17 September 2007
Transcription
WP2 Final Report - 17 September 2007
Tender ERA/2006/ERTMS/OP/01 Survey of Safety Approvals for the first ERTMS implementations Analysis of Safety Approval Process Final Report WP2 Subcontractors: Reference: BV-LZ-FW/KRTC316/WP2 Document Approval Author Checker B. Vittorini F.Walenberg Approval 17 September 2007 From the following organisations, the following persons contributed to the study: • • • • • • KEMA Rail Transport Certification: o F. Walenberg, Project Manager o L. Zigterman, WP1-leader o R. te Pas RINA: o F. Caruso, Technical Manager o B. Vittorini, WP2-leader Cetren: o J. Figuera, WP4-leader o M. Carvajal o G. Moreno Attica Advies: o J. Postmes, WP3-leader o H. Vas Visser o W. Oskam o J. Rimmelzwaan EBC: o C. Glatt o H. Müller Arsenal Research: o G. List Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 2/161 Summary This document contains a preliminary collection of information regarding the Safety Approval Process followed in the different ERTMS projects included in the scope of this Project. The information is presented in a comparative format aiming at an easy outlining of commonalities and differences. The process covers the system life cycle defined in the CENELEC Norm EN50126, although some of its phases may not be fully considered. The following main issues are included: • • • • • • • General information of the line under consideration; System definition; Safety aspects: o Risk analysis; o Safety requirements; o System requirements, including safety requirements for components, subsystems and operation; Suppliers responsibility: o System design; o Manufacturing of generic components; o Installation, configuration and commissioning; Approval: o Acceptance verification and tests; o Formal approval; Operation, maintenance and monitoring of system performances in revenue service; Modifications and retrofits. Note: The items in italics are not mandatory. The user of the guideline was asked to indicate why the “Non mandatory” subjects are not filled out (lack of information, unknown, not traceable etc.). In general, this information is deemed not necessary for the objectives of the study. The structure of this report contains the relevant chapter for each analysed project, even if it is not actually filled in for the above mentioned reasons. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 3/161 Contents SUMMARY......................................................................................................................................................... 3 CONTENTS........................................................................................................................................................ 4 1 PHASE 1 - SYSTEM CONCEPTS.......................................................................................................... 9 1.1 SYSTEM CONTEXT.............................................................................................................................. 9 The Austria-Italy project: the Brenner Basis Tunnel .................................................................................. 9 The Austrian project: Vienna-Nickelsdorf .................................................................................................. 9 The Belgian projects ................................................................................................................................. 10 The French project: LGV-Est ................................................................................................................... 11 The German project: Berlin-Halle-Leipzig............................................................................................... 13 The Italian projects ................................................................................................................................... 14 The Dutch projects.................................................................................................................................... 17 The Spanish projects ................................................................................................................................. 21 1.2 POLITICAL AND GEOGRAPHICAL CONSTRAINTS ............................................................................... 28 The Austria-Italy project: the Brenner Basis Tunnel ................................................................................ 28 The Austrian project: Vienna-Nickelsdorf ................................................................................................ 30 The Belgian projects ................................................................................................................................. 33 The French project: LGV-Est ................................................................................................................... 36 The German project: Berlin-Halle-Leipzig............................................................................................... 36 The Italian Projects .................................................................................................................................. 38 The Dutch projects.................................................................................................................................... 42 The Spanish projects ................................................................................................................................. 46 1.3 SAFETY TARGETS / RAMS POLICY................................................................................................... 59 The Austria-Italy project: the Brenner Basis Tunnel ................................................................................ 59 The Austrian project: Vienna – Nickelsdorf.............................................................................................. 60 The Belgian projects ................................................................................................................................. 60 The French project: LGV-Est ................................................................................................................... 61 The German project: Berlin-HalleLeipzig ................................................................................................ 61 The Italian Projects .................................................................................................................................. 62 The Dutch projects.................................................................................................................................... 62 The Spanish projects ................................................................................................................................. 65 2 PHASE 2 - SYSTEM DEFINITION AND APPLICATION CONDITIONS .................................... 66 2.1 THE MISSION PROFILE OF THE SYSTEM ............................................................................................. 66 Austria-Italy project: Brenner Basis Tunnel project................................................................................. 66 Austrian project: Vienna – Nickelsdorf .................................................................................................... 66 The Belgian projects ................................................................................................................................. 67 French project: LGV-Est .......................................................................................................................... 67 German project: Berlin-HalleLeipzig....................................................................................................... 67 The Italian Projects .................................................................................................................................. 69 The Dutch projects.................................................................................................................................... 69 The Spanish projects ................................................................................................................................. 70 2.2 THE SYSTEM DEFINITION .................................................................................................................. 71 The Austria-Italy project: Brenner Basis Tunnel...................................................................................... 71 The Austrian project: Vienna – Nickelsdorf.............................................................................................. 72 The Belgian projects ................................................................................................................................. 72 The French project: LGV-Est ................................................................................................................... 73 The German project: Berlin-HalleLeipzig ................................................................................................ 74 The Italian Projects .................................................................................................................................. 76 The Dutch projects.................................................................................................................................... 77 The Spanish projects ................................................................................................................................. 78 3 PHASE 3 - RISK ANALYSIS ................................................................................................................ 80 3.1 HAZARD ANALYSIS AND SYSTEM LEVEL MITIGATIONS ..................................................................... 80 The Austria-Italy project: Brenner Basis Tunnel...................................................................................... 80 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 4/161 The Austrian project: Vienna – Nickelsdorf.............................................................................................. 80 The Belgian projects ................................................................................................................................. 81 The French project: LGV-Est ................................................................................................................... 81 The German project: Berlin-Halle-Leipzig............................................................................................... 81 The Italian Projects .................................................................................................................................. 83 The Dutch projects.................................................................................................................................... 84 The Spanish projects ................................................................................................................................. 86 3.2 SPECIFIC ISSUES ............................................................................................................................... 90 The Austria-Italy project: Brenner Basis Tunnel...................................................................................... 90 The Austrian project: Vienna – Nickelsdorf.............................................................................................. 90 The Belgian projects ................................................................................................................................. 91 The French project: LGV-Est ................................................................................................................... 91 The German project: Berlin-HalleLeipzig ................................................................................................ 91 The Italian Projects .................................................................................................................................. 91 The Dutch projects.................................................................................................................................... 92 The Spanish projects ................................................................................................................................. 92 4 PHASE 4 - SYSTEM REQUIREMENTS............................................................................................. 94 4.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL ................................................................ 94 4.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF .......................................................................... 94 4.3 THE BELGIAN PROJECTS ................................................................................................................... 95 4.4 THE FRENCH PROJECT: LGV-EST..................................................................................................... 95 4.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG .............................................................................. 95 4.6 THE ITALIAN PROJECTS .................................................................................................................... 95 The Rome-Naples HSL.............................................................................................................................. 95 The Torino-Novara HSL ........................................................................................................................... 96 4.7 THE DUTCH PROJECTS ...................................................................................................................... 96 Betuweroute .............................................................................................................................................. 96 Amsterdam - Utrecht................................................................................................................................. 96 HSL ZUID................................................................................................................................................. 96 4.8 THE SPANISH PROJECTS .................................................................................................................... 96 5 PHASE 5 – APPORTIONMENT OF SYSTEM REQUIREMENTS................................................. 97 5.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL ................................................................ 97 5.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF .......................................................................... 97 5.3 THE BELGIAN PROJECTS ................................................................................................................... 97 5.4 THE FRENCH PROJECT: LGV-EST..................................................................................................... 97 5.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG .............................................................................. 97 5.6 THE ITALIAN PROJECTS .................................................................................................................... 97 The Rome-Naples HSL.............................................................................................................................. 97 The Torino-Novara HSL ........................................................................................................................... 98 5.7 THE DUTCH PROJECTS ...................................................................................................................... 98 Betuweroute .............................................................................................................................................. 98 Amsterdam - Utrecht................................................................................................................................. 98 HSL ZUID................................................................................................................................................. 99 5.8 THE SPANISH PROJECTS .................................................................................................................... 99 6 PHASE 6 – DESIGN AND IMPLEMENTATION ............................................................................ 100 6.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 100 6.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF ........................................................................ 100 6.3 THE BELGIAN PROJECTS ................................................................................................................. 100 6.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 100 6.5 THE GERMAN PROJECT: BERLIN-HALLE-LEIPZIG ........................................................................... 100 6.6 THE ITALIAN PROJECTS .................................................................................................................. 100 The Rome-Naples HSL............................................................................................................................ 100 The Torino-Novara HSL ......................................................................................................................... 103 6.7 THE DUTCH PROJECTS .................................................................................................................... 104 Betuweroute ............................................................................................................................................ 104 Amsterdam - Utrecht............................................................................................................................... 104 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 5/161 HSL ZUID............................................................................................................................................... 104 6.8 THE SPANISH PROJECTS .................................................................................................................. 104 7 PHASE 7 – MANUFACTURING........................................................................................................ 105 7.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 105 7.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF ........................................................................ 105 7.3 THE BELGIAN PROJECTS ................................................................................................................. 105 7.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 105 7.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 105 7.6 THE ITALIAN PROJECTS .................................................................................................................. 105 The Rome-Naples HSL............................................................................................................................ 105 The Torino-Novara HSL ......................................................................................................................... 106 7.7 THE DUTCH PROJECTS .................................................................................................................... 106 Betuweroute ............................................................................................................................................ 106 Amsterdam - Utrecht............................................................................................................................... 106 HSL ZUID............................................................................................................................................... 106 7.8 THE SPANISH PROJECTS .................................................................................................................. 106 8 PHASE 8 – INSTALLATION.............................................................................................................. 107 8.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 107 8.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF ........................................................................ 107 8.3 THE BELGIAN PROJECTS ................................................................................................................. 107 8.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 107 8.5 THE GERMAN PROJECT: BERLIN-HALLE-LEIPZIG ........................................................................... 107 8.6 THE ITALIAN PROJECTS .................................................................................................................. 108 The Rome-Naples HSL............................................................................................................................ 108 The Torino-Novara HSL ......................................................................................................................... 108 8.7 THE DUTCH PROJECTS .................................................................................................................... 108 Betuweroute ............................................................................................................................................ 108 Amsterdam - Utrecht............................................................................................................................... 108 HSL ZUID............................................................................................................................................... 108 8.8 THE SPANISH PROJECTS .................................................................................................................. 108 9 PHASE 9 – SYSTEM VALIDATION ................................................................................................. 109 9.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 109 9.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF ........................................................................ 109 9.3 THE BELGIAN PROJECTS ................................................................................................................. 110 The L3 and the L4 HSL ........................................................................................................................... 110 The ETCS Level 1 lines ........................................................................................................................... 110 9.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 111 9.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 111 9.6 THE ITALIAN PROJECTS .................................................................................................................. 111 The Rome-Naples HSL............................................................................................................................ 111 The Torino-Novara HSL/HCL ................................................................................................................ 113 9.7 THE DUTCH PROJECTS .................................................................................................................... 114 Betuweroute ............................................................................................................................................ 114 Amsterdam- Utrecht- HSL ...................................................................................................................... 115 HSL ZUID............................................................................................................................................... 115 9.8 THE SPANISH PROJECTS .................................................................................................................. 115 Validation&Verification guidelines ........................................................................................................ 115 Validation procedure .............................................................................................................................. 116 Compatibility and Interoperability issues............................................................................................... 117 10 PHASE 10 – SYSTEM ACCEPTANCE ............................................................................................. 119 10.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 119 10.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF ........................................................................ 119 10.3 THE BELGIAN PROJECTS ................................................................................................................. 119 The L3 and the L4 HSL ........................................................................................................................... 119 The ETCS Level 1 lines ........................................................................................................................... 120 10.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 120 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 6/161 10.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 121 10.6 THE ITALIAN PROJECTS .................................................................................................................. 122 The Rome-Naples HSL............................................................................................................................ 122 Torino-Novara HSL/HCL ....................................................................................................................... 123 10.7 THE DUTCH PROJECTS .................................................................................................................... 124 Betuweroute ............................................................................................................................................ 124 Amsterdam - Utrecht............................................................................................................................... 125 HSL ZUID............................................................................................................................................... 125 10.8 THE SPANISH PROJECTS .................................................................................................................. 127 Complementary tests............................................................................................................................... 127 11 PHASES 11-12 OPERATION, MAINTENANCE AND MONITORING ...................................... 129 11.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 129 11.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF ........................................................................ 129 11.3 THE BELGIAN PROJECTS ................................................................................................................. 129 The L3 and the L4 HSL ........................................................................................................................... 129 Belgian ETCS level 1 lines...................................................................................................................... 129 11.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 130 11.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 130 11.6 THE ITALIAN PROJECTS .................................................................................................................. 130 The Rome-Naples HSL............................................................................................................................ 130 Torino-Novara HSL ................................................................................................................................ 130 11.7 THE DUTCH PROJECTS .................................................................................................................... 130 Betuweroute ............................................................................................................................................ 130 Amsterdam - Utrecht............................................................................................................................... 130 HSL ZUID............................................................................................................................................... 130 11.8 THE SPANISH PROJECTS .................................................................................................................. 130 12 PHASE 13 – MODIFICATION AND RETROFIT............................................................................ 132 12.1 AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL PROJECT ....................................................... 132 12.2 VIENNA-NICKELSDORF .................................................................................................................. 132 12.3 THE BELGIAN PROJECTS ................................................................................................................. 132 12.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 132 12.5 THE GERMAN PROJECT: BERLIN-HALLE-LEIPZIG ........................................................................... 132 12.6 THE ITALIAN PROJECTS .................................................................................................................. 133 The Rome-Naples HSL............................................................................................................................ 133 Torino-Novara HSL ................................................................................................................................ 133 12.7 THE DUTCH PROJECTS .................................................................................................................... 133 Betuweroute ............................................................................................................................................ 133 Utrecht-Amsterdam HSL......................................................................................................................... 133 HSL ZUID............................................................................................................................................... 133 12.8 THE SPANISH PROJECTS .................................................................................................................. 133 13 ANNEX .................................................................................................................................................. 134 13.1 REFERENCES FOR THE AUSTRIAN PROJECTS .................................................................................. 134 13.2 REFERENCES FOR THE GERMAN PROJECTS ..................................................................................... 134 European Directives, Standards and Specifications ............................................................................... 134 National Rules & Regulations................................................................................................................. 135 DBAG Regulations................................................................................................................................. 135 DBAG Pilot Documentation .................................................................................................................. 135 Suppliers´ (“Consortium”) Documentation (RBC Docu as an example) ............................................... 136 Verification & Validation ....................................................................................................................... 138 Assessment .............................................................................................................................................. 138 Approval & Acceptance .......................................................................................................................... 138 Conformity .............................................................................................................................................. 141 13.3 REFERENCES FOR THE ITALIAN PROJECTS ...................................................................................... 141 Laws and Norms ..................................................................................................................................... 141 European Norms and Standards ............................................................................................................. 142 RFI Norms and Standards ...................................................................................................................... 142 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 7/161 13.4 SPECIFIC REFERENCES FOR THE TURIN-NOVARA PROJECT ............................................................ 149 RFI Specifications and assessment documents ....................................................................................... 149 Suppliers Documents .............................................................................................................................. 154 13.5 REFERENCES FOR THE DUTCH AND BELGIAN PROJECTS ................................................................. 156 13.6 REFERENCES FOR THE SPANISH PROJECTS ...................................................................................... 156 LIST OF ABBREVIATIONS AND ACRONYMS ...................................................................................... 157 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 8/161 1 Phase 1 - System Concepts 1.1 System Context This section is intended to provide the following information: • • • Official identification of each individual project under consideration. Project organisation: the infrastructure owner, the railway authority1, the system integrator, the train operators, the safety authority, the independent safety assessors, and the notified bodies. Roles and responsibilities of each entity. The Austria-Italy project: the Brenner Basis Tunnel The line, presently in the final design phase, constitutes the central part of the VeronaMunich line that will be integrated in the TEN Corridor 1 from Berlin to Palermo. It is 55.6 km long (32.6 km in Austria and 23 km in Italy) within a twin, single rail tunnel system from Fortezza-Italy to Innsbruck-Austria (circulation at left in Italy, at right in Austria). It is foreseen for mixed traffic: High speed traffic (200 km/h) for international passenger transport (20% of the overall traffic), conventional light (160 km/h) and heavy (100 km/h) freight trains (80% of the traffic). Traffic forecast: 140 trains per day and per running direction. The minimum heading has been set to 7.5 minutes. The line will be powered at 2x25 kV/50 Hz. The Parties involved are: • • • • • Inframanager: BBT SE (Brenner Basis Tunnel, a company owned by RFI, OEBB and the Tyrolean Region) System design: PGBB (an Austro-Italian Consortium) Design Verification: RABBIT Consortium (RINA-ARSENAL) assessing the conformity of the design to the CC&S TSI and to the applicable Austro-Italian Norms and Specifications. Operating companies:N/A in this phase Suppliers: N/A in this phase The Austrian project: Vienna-Nickelsdorf The line characteristics are: • Conventional line from Vienna Southern Railway station (km 3.659) to Hungarian border after Nickelsdorf (km 67.506). It constitutes the Austrian part of the Vienna – Budapest line. As the station in Vienna (Vienna central station / Wien Zentralbahnhof) has currently started to be rebuilt, the line will be equipped into the station at a later time. 1 The term “Railway authority” is used here to refer to the body that is in charge of the safety approval according to the national law or regulations (sometimes not yet compliant with the Directives). This could be for instance an Infrastructure Manager, a NSA or an other body. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 9/161 • Rolling Stock: 13 (already nationally approved) locos of type 1116 are to be equipped with ETCS equipment The involved parties are: • • • • • • • • Infrastructure owner: ÖBB BAU AG Inframanager: ÖBB Betrieb AG System integrator: ARGE Euroloop - contract with ÖBB Suppliers: ARGE Euroloop consisting of Siemens AG-Österreich, responsible for the train-borne system and a small part of the trackside system and Thales (until end of 2006: Alcatel Austria AG), responsible for the large extent of the trackside subsystem) - contract with ÖBB Train operators: ÖBB Traktion (currently the only one to be equipped with ETCS), Gysev, Wiener Lokalbahnen (WLB) - licenced railway undertakings Safety Authority: Federal Ministry of traffic and information technologiesresponsible by law Independent Safety Assessors: IPW - contract with manufacturer Notified Body: Arsenal Research (0894) - contract with ÖBB The Belgian projects The L3 and the L4 HSL The high speed lines L3 (Luik – German/Belgian border) and L4 (Antwerp – Dutch/Belgian border) are built to achieve a performance of up to 300 km/h and a 3-minute headway under continuous speed supervision provided by ERTMS/ETCS Level 2. The ERTMS/ETCS Level 2 is supplemented with ERTMS/ETCS Level 1, which takes over in case the former experiences a failure, while offering parallel operations in a mixed level application. These two separate lines are divided into three structural and two functional subsystems. These subsystems are subject to EC verification against their respective Technical Specifications of Interoperability (TSI) of Directive 96/48/EC. The L3 line is 139 km long, while the L4 line is 87 km long. Infrabel, part of NMBS-Holding, is the Infrastructure operator since January 1st 2005. Infrabel is controlled by the Belgian Federal State. NMBS-Holding also exploits the train operation (NMBS). Certifer is the Notified Body for the L3 and the L4 lines, whereas Belgorail is the NoBo for the rest of the network and assessor of national functionalities (also for L3 and L4). Certifer also checks or prepares every decision (Safety Assessment) that is taken by a division of the responsible Ministry that acts as National Safety Authority (NSA). The ETCS Level 1 conventional lines The project concerns the roll-out of ETCS Level 1 (just the equipment) over the Belgian conventional railway network. The infrastructure owner/manager is Infrabel, which is part of the NMBS (SNCB) holding. The main train operator involved is NMBS (SNCB), which is the other entity under the NMBS (SNCB) holding. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 10/161 The Safety Authority is currently being organised within the Ministry of Transportation. For phase 2, KEMA Rail Transport Certification is the ISA and the Notified Body for the trackside equipment. The French project: LGV-Est This project is identified as « Pilote ERTMS Est Européen » (pilot East European ERTMS) (PEEE). This high speed line will connect Paris-Gare de l’Est to Frankfurt Main Station. In the final stage of implementation it will be 406 km long. The following project information has been derived from the PEEE Safety Plan [ “Project PEEE sous project Equipement Sol, plan de securité, v 02, 16 nov. 2004). Role and responsibilities of the involved organisations are as follows (see Figure 1): • The Infrastructure Owner is RFF (Réseau Ferré de France) • The National Safety Authority is SIST (Securité des Infrastructures) • The Notified Body is CERTIFER • The Independent Safety Assessor for the trackside systems is SNCF • The Independent Safety Assessor for the train borne systems is SNCF • The Independent Safety Assessor for the Integral Safety is SNCF The evaluation is carried out at two levels: • A safety team from SNCF engineering division ensures the overall coherence of safety. The safety team’s tasks are described in the table below. • RFF has entrusted CERTIFER with the evaluation of the ERTMS system in the framework of the OSTI contract & Notified Body. (ref: Project PEEE: Sub-project Safety Plan Equipment, F3SJ0601, v. 011). RFF is the owner of LGV Est and the promoter of the PEEE project, and as such is responsible for safety on these projects. RFF entrusts the supply and implementation of equipment to LGV EST Européen to the manufacturers, who must provide evidence of the assured safety of the equipment delivered. In accordance with European regulations, this evidence must be evaluated by an independent organisation. RFF entrusts SNCF direction de l’Ingénierie (engineering division) with study and works management assignments, known as ‘engineering assignments’. In the context of the engineering assignments SNCF must in particular: • • • ensure, validate and approve the sub-system project, establish all operational rules, evaluate the safety evidence supplied by the manufacturers for each delivered component, • provide evidence to RFF that all safety requirements are complied with in the system (all components delivered to RFF). The tasks described above are also known as ‘integration tasks’. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 11/161 In observance of the decree [SRFN] RFF entrusts an OSTI (Certifer) with the task of evaluating safety on the whole project. Certifer will also ensure the Notified Body assignment and must issue an EC verification declaration certifying that the command & control and signals sub-system complies with the provisions of decree 2001-129 (pending transposition of the directive 96/48/EC). An “Engineering Activities Safety File” is prepared on all the activities contributing to the demonstration and construction of industrial and engineering safety in the context of the PEEE. RFF supplies this file, which is subject to evaluation by CERTIFER (OSTI and ON), to SNCF IES who prepares the Safety File. RFF promotor of LPEEE projet, owner of LGV Est project OSTI/ON SNCF IES SNCF Engineering Manufacturers Figure 1 – LPEE Project organisation The engineering activities of the PEEE trackside project are entrusted to the ERTMS sector of technical division of engineering division. The ERTMS head of sector, the Project Manager, is responsible for the safety of the PEEE sub-project and must set up the organisation and means necessary for safety in all the activities of the PEEE sub-project in accordance with this plan. The OSTI/ON awarded for this project is Certifer. The identification number assigned by the European Commission is 942 (Notified Body - directive 96/48). The COFRAC accreditation certification number is 5-0023 (standard NF EN 45011 and COFRAC application rules – Section D – under section DM – Transport Materials). This accreditation is valid until 31/11/2008. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 12/161 The German project: Berlin-Halle-Leipzig The line identification is “B-H/L”, Berlin-Halle-Leipzig. The infrastructure owner of the BHL line is “Deutsche Bahn Netz AG” (Theodor-HeussAllee 7, D-60486 Frankfurt am Main). The railway authority acting as a contact person and legal entity for all aspects like concept preparation, development, operational questions, etc. for the BHL project is the “Deutsche Bahn AG” (Potsdamer Platz 2, D-10785 Berlin) and their subsidiary companies, respectively. No "system integrator" has been explicitely defined, however the customer was undertaking most tasks of integration. The suppliers´ consortium as well played an important role in the processes of system integration. According to TSI CCS the railway undertaking and infrastructure manager have to declare conformity and EC-verification. Both acts of declaration are planned to be committed to the suppliers´ consortium. More detailed information on this intention is not available in the moment. For the moment “DB Fernverkehr AG” (Stephensonstr. 1, D-60326 Frankfurt am Main), “DB Regio AG” (Stephensonstr. 1, D-60326 Frankfurt am Main), “Railion Deutschland AG” (Rheinstr. 2, D-55116 Mainz), “InterConnex” (Ostseeland Verkehr GmbH, Ludwigsluster Chaussee 72, D-19061 Schwerin) and “Dispolok GmbH” (GeorgReismüllerstr. 32, D-80999 München) are present on the BHL line as railway undertakings. The safety authority charged with the national approval and acceptance procedures for BHL is the “Eisenbahn-Bundesamt EBA” (Vorgebirgsstr. 49, D-53119 Bonn). Nearly all verification, validation and assessment according to the refernced CENELEC norms (see Chap. 13.2) have been performed by inhouse test control centres ("Prüfleitstelle" PLS) of the two main components´ suppliers SIEMENS and ALCATEL/THALES. Both have been accredited as Qualified Development Organisations ("Qualifizierter Entwicklungsbetrieb") by the EBA, additionally fulfilling the requirements of [DB 9]. Hence they are permitted to operate their own - yet independent (conforming [DB 4], [DB 5], [DB 6]) - proving and test departments for verification, validation and assessment tasks. Independency of verification, validation and assessment is ensured by self-responsibility and stringent EBA control. Some audits (according to module D, [DB 16]) have been performed by TÜV InterTraffic GmbH (TÜV Rheinland Group). “Eisenbahn Cert EBC” (Vorgebirgsstr. 43, D-53119 Bonn) acts as “Notified Body Interoperability” according to EC directives, as well as to the national regulations [DB 19], [DB 20], that transfered the interoperability directives into German regulation. The EBC located at the Eisenbahn-Bundesamt (EBA) and accredited as independent and autonomous organisation under public law – was commissioned for the conformity and EC examinations for both trackside and onboard equipment. However the two PLSs were subcontracted by EBC to perform most of the examinations. Some audits have been done by EBC himself or TÜV InterTraffic GmbH. EBC did not perform any technical examinations for BHL. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 13/161 The Italian projects The Rome-Naples HSL The Rome-Naples HSL is a section of the High Speed / High Capacity Line Milan-Naples. The entities/companies involved in the project and their roles are listed in the following Table 1. Company RFI Role Customer, Safety Authority, Railway Authority, Safety Assessor TAV ITALFERR IRICAV TRENITALIA SATURNO Purchaser Work Director General Contractor Train Operator Technological System Integrator and Trackside Subsystem Valuator. Saturno is a consortium including Ansaldo, Alstom, Bombardier and Sirti. Supplier of Solid State Interlocking, Encoder and Eurobalise. For the supplied products – subsystems the company performed Design, Verification and Validation activities for the Generic Product, Generic and Specific Application. ASF supplied also the traffic supervisory system (SIL 0 system) Supplier of On-Board subsystem, RBC subsystem and wayside track-circuit sub-system. For the supplied products – subsystems the Company performed Design, Verification and Validation activities for the Generic Product, Generic and Specific Application. Supplier of Hot Axel Box Detector and Braked Wheels Detector subsystem Supplier of Telecommunication sub-system (Long Distance network and GSM-R network – Nortel Technology) ANSALDO (ASF) ALSTOM BOMBARDIER SIRTI Table 1 – Entities/Companies involved in Rome-Naples HSL The RFI “Direzione Movimento” and “Direzione Manutenzione” are the Customers. Different departments of “Direzione Tecnica” had the following tasks: • System Requirement Specification delivery; • Assessment and Acceptance of the system. The Rome and the Naples “Direzione Compartimentale Movimento” are the Railway Authorities supported by the corresponding “Direzioni Compartimentali Infrastrutture”. The tasks of each RFI structure are indicated with more details in the following table: Dept. PATC PATC PATC PATC PATC CESIFER PACS CC Structure “Specificazione Requisiti di Sistema e Applicazione Sistemi ATC” “Omologazione Sottosistema di Terra (SDT/SST)“ “Omologazione Sottosistema di Bordo (SDT/SSB)“ “Prodotti a Tecnologia Innovativa“ Task System specification; functional assessment and acceptance; SDT, SST and SSB system homologation; products functional assessment and homologation System specification; functional assessment and acceptance SDT/SST functional assessment and acceptance SDT/SSB functional assessment and acceptance Product functional assessment and acceptance SSB functional assessment and acceptance Interlocking System functional assessment and acceptance Systems, subsystems, products Safety Integrity Level assessment; assessment of systems and components interoperability. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 14/161 Dept. CC Structure “Valutazione di Sicurezza (Assessment) “ CC SS SS “Certificazione Standard di Interoperabilità“ “Impianti“ “Tecnologie di Base Task Systems, subsystems, products Safety Integrity Level assessment Assessment of systems and components interoperability. Interlocking logic assessment and homologation Hot Axle Box Detector System and wayside objects assessment and homologation Table 2 - RFI departments related to the Rome-Neaples HSL Project The responsibilities of the RFI structures in the assessment process are shown with more details in the following Figure 2, Figure 3 and Figure 4. GA ETCS System - CC GA System CC - VdS GA System PATC - SRS GA SST SDT - CC GA SDT CC - CSI GA SSB - CC GA SDT CC - VdS GA SDT PATC - OSST GP RBC - CC GA SSB CC - VdS GA SSB PATC - OSST GP SSB - CC GP RBC CC - CSI GP RBC CC - VdS GP SSB CC - VdS GP RBC PATC - PTI GP SSB PATC - PTI Coulor Meaning: Functional Assessment Interoperability Assessment Safety Assessment Overall Assessment Figure 2– Assessment process of the ETCS System Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 15/161 GA Interlocking Subsystem GdV - CC GA – CC VdS GP NVP + GAT GP CC - VdS GA PACS Logic – SS I Wayside Objects RTB System SS - TB SS - TB GP PACS- PTI Coulor Meaning: Functional Assessment Safety Assessment Overall Assessment Figure 3– Assessment process of the Interlocking System GA System SSAV - CC GA SSAV CC - VdS GA SSAV DT GA GdV GA ETCS (see f. 2) (see f. 1) Coulor Meaning: Functional assessment Safety Assessment Overall Assessment Figure 4– Assessment process of the Rome-Naples CCS sub-system Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 16/161 The Torino -Novara HSL The line characteristics are: • Typology: High speed/ High Capacity line for mixed passenger and freight trains linking Torino to Milano. The only section Torino-Novara is presently in operation at 300 km/h. • Maximum speed: 300 km/h The detailed organization is similar to the one in place for the Rome-Naples Project, with some differences in the suppliers. The involved parties are: • • • • • • • • • • Infrastructure manager: RFI Safety Authority: RFI Assessor: RFI Integration of existing rules with new rules applicable to ERTMS/ETCS Lev. 2: RFI and the Transportation Ministry. Operating companies (to date): Trenitalia General Contractor: Consortium CAVTOMI System Integrator: Saturno Consortium composed of Ansaldo, Alstom, Bombardier and Sirti. In addition to System Integrator Saturno has also been the Trackside Subsystem Validator. Suppliers: o Ansaldo Signal for RBC and Interlocking subsystem including ATIS audio frequency track circuit, Encoders and Eurobalises. For the supplied products – subsystems the company performed Design, Verification and Validation activities for the Generic Product, Generic and Specific Application. ASF supplied also the traffic supervisory system (SIL 0 system). The Ansaldo onboard sub-system is undergoing pre-operational acceptance tests. o Alstom Ferroviaria for the on board subsystem and wayside objects track circuits. For the supplied products – subsystems the Company performed Design, Verification and Validation activities for the Generic Product, Generic and Specific Application. o Bombardier for Hot Axle Detector and Braked Wheels Detector o Sirti for telecom subsystem including Long Distance Network and GSM-R Network (Siemens Technology) EC Conformity verification: SciroTÜV Mod. SH2. The organization of the assessment process has been very similar to the one adopted for the Rome –Naples line, described in the previous chapter. The Dutch projects Betuweroute The Betuweroute is a new international and domestic line designed for freight transport only. It is 160 km long and connects the Europe’s biggest harbour, Rotterdam, with the German border. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 17/161 It is equipped with a ERTMS Level 2 system only (no fall back). Some area’s, Kijfhoek en Zevenaar are equipped with ATB, the Dutch Legacy system, because in this area the Betuweroute is integrated in the national system. The line has been put into operation officially on June 16th 2007 by the Dutch Queen. Until now, there is little operational experience. To date, the train-infrastructure integration tests have not yet been completed. Immediately after the official opening of the line, trains were only allowed to enter into the line after the previous train had cleared it. Only the A15 section from Kijfhoek to Zevenaar (107 km) is equipped with ERTMS at this moment. The Western part (West of Rotterdam/Kijfhoek) will be equipped later. The number of trains per day will be limited heavily by the capacity of the German lines that connect the Dutch Betuweroute with the Corridor Rotterdam-Genoa. All trains will at least have to be equipped with ERTMS as there is no other system installed on the Betuweroute. About ten freight operating companies, such as Raillion by far the biggest one, will operate freight trains on the Betuweroute. Keyrail is a new company, established to manage the exploitation and maintenance of the Betuweroute, separately of the rest of the Dutch Infrastructure, managed by ProRail. ProRail however, still plays an important role in the transition of construction and tests to regular operating. The Safety Authority is IVW (www.ivw.nl). IVW which stands for “Inspectie Verkeer en Waterstaat”, is the National Safety Authority. It is a department of the Ministry of Transportation, reporting directly to the Minister and is therefore independent of the Inframanager, Train Operating Companies and Suppliers. All infrastructures added to the Dutch infrastructure and all trains running on this infrastructure have to be admitted by this organisation. The trackside Supplier is the Consortium Alstom Movares Different safety assessors have been contracted for the integral Betuweroute project: • An ISA for the generic safety system Bev21(In this case the Dutch adaptation of an Alstom safety system) • An ISA for the Specific Safety Case of the Betuweroute. The BR A15 Trackside Safety Case is available, including ISA report, for Alstom Bev21 A15 v3.4 configuration • Alstom has its own ISA for the Safety Case of its equipment included in the Bev21 Safety Case. These companies are in al cases experienced independent companies on the area of certification, contracted by each of the involved parties. Steps are not yet taken to have the track certified by a NoBo. Although the Infrastructure provider ProRail intends to approach the ideal situation as close as possible, the IMdeemes it impossible at this moment , due to the limited maturity of the TSI’s and lack of earlier references. The Trackside Assembly shall finally comply with ERTMS SRS vers. 2.3.0. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 18/161 At this moment about 100 locomotives (10 different types) are in different stages of preparation for operation on the Betuweroute. Also in this case a process is followed that approaches the ERTMS type approval as close as possible. A starting requirement for the acceptance of a train type is a Declaration of Conformity of all used ERTMS Interoperability Constituents, certified by a NoBo, and a Declaration of Verification for the Train borne Subsystem, also certified by a NoBo, as well as a completed CENELEC Safety Case for the trainborne Command and Control On Board Assembly, assessed by an ISA, with no blocking findings. Amsterdam - Utrecht The Amsterdam – Utrecht is part of the Dutch Railway Network. Several operators (26) run on this line. The line has to fulfil all the present regulations of the existing railway network. ProRail – the infrastructure manager – is the system integrator as well. The maximum design speed for the line is 200 km/h. It is only for international and domestic passenger trains. The line speed is now 140 km/h. The line speed will be raised to 200 km/h when the trains and the infrastructure have switched over the traction voltage from 1500 Volt dc to 25 kV ac and the signaling system from ATB (ATP) to ERTMS level 2. The line is 30 km long and interconnects with the rest of the ProRail Network. The involved Parties are : • • • • Infrastructure manager - ProRail Safety Authority - Railway divison of IVW (Transport and Water management Inspectorate) Suppliers Trackside: Bombardier has delivered the signalling equipment Operating companies: There are at the moment 26 operators (International traffic, domestic passengers traffic and freight traffic) HSL ZUID Scope of the HSL ZUID project is the high speed transportation system at the south of the Netherlands towards Belgium. The HSL ZUID runs from Amsterdam via Schiphol and Rotterdam to the Belgian border, with connections to The Hague and Breda. On the HSL route, the high-speed trains run on newly laid, double track rails, wherever it is possible to travel at such high speeds. However, from Amsterdam to just beyond Schiphol Airport and at the other HSL stations, the high speed trains travel on existing tracks. Accordingly, the HSL line connects with existing lines in five locations: Hoofddorp, Rotterdam-West , Rotterdam-Lombardijen, Zevenbergschen Hoek and Breda. Regular trains in the Netherlands use 1.5 kVdc and have a capacity of 6 MWatt. The high speed trains on the HSL-Zuid are fed with 25 kVac (50 Hz). Trains using both the regular Dutch network and the new European network must be able to switch between the two systems. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 19/161 Along the HSL track, spanning around 100 kilometres, no less than 170 civil engineering structures, such as viaducts, fly-overs, dive-unders, bridges and tunnels have been built. This Project has been contracted in several parts: • The Infraspeed provider for the superstructure including the CCS sub-system; the Infraspeed consortium delivers through a Design-Build-Finance-and-MaintainContract the Superstructure and provides the maintenance of superstructure and substructure over a period of 25 years. Payment of the Infraspeed Consortium will be related to the availability of the line. • The transport concession. • The contracts to provide the substructure. • The Railway Act: ProRail (Inframanager and also amongst others fulfilling the function of Traffic Control/Operation of the 25kV and Tunnel installations on the line. • The agreement with the Belgium State. The involved Parties are: • • • • • • • • • • • The Infrastructure Owner: the State of the Netherlands. The Inframanager (=Railway Authority): ProRail (www.prorail.nl ). The Safety Authority: the Railway division of the IVW (Transport and Water Management Inspectorate) (www.ivw.nl) The train operator: the High Speed Alliance company - HSA ( www.highspeedalliance.nl), with commercial name HIspeed (www.nshispeed.nl). The system integrator: the project organisation HSL Zuid acting on behalf of the principal stakeholder, the State of the Netherlands The Independent Safety Assessors: For Infraspeed supplier of superstructure including CCS: Railcert and DeltaRail; For HSA, the train operating company who has ordered rolling stock: safety assessors contracted by suppliers of the rolling stock. The Notified Bodies: For the trackside assembly: Railcert (www.railcert.nl ) For the trainside: suppliers of rolling stock who have contracted Lloyds. The Figure 5 below shows roles and responsibilities related to the CCS certification and safety approval. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 20/161 RWS / HSL Integral Safety Case L 4 by Infrabel Lux-control Integral Safety Case HSL Zuid traffic system RWS / HSL IVW (inzetcertificaat) RWS / HSL A il bilit P i d S f t Railcert (TÜV/EBC) Suppliers* Deltarail Supplier* Availability Period Safety Case Trackside assembly Functionality Assessment Safety case by supplier On board assembly Generic Application Safety Case & Specific Application Safety Case for conv. track To be done by suppliers of rolling stock; • Interoperability Assessment V250: Ansaldo delivers a certified train including ERTMS • Traxx: certified train delivered by Angels Trains, certification by Lloyds Safety Assessment • Thalys, certified by France, Lloyds certified the STM-ATB Overall Assessment The Integral Safety Case of the L4 and the HSL Zuid have to be aligned in order to assure the safety of the interface between the two lines Figure 5 – Relationship between diferent bodies in HSL ZUID The Spanish projects This report provides basic information related to the implementation and safety approval of the ERTMS projects that are currently under different status of development in Spain. They include High Speed and Conventional Railways projects as well: • Madrid-Zaragoza-Barcelona that connects the two biggest Spanish cities (>4.000.000 inhabitants each), and will be extended up to the French border, fully equipped with ERTMS. In service the sections Madrid-Zaragoza-Lleida and LleidaRoda de Bará (Tarragona). It will be completed by the end of the year 2007. Maximum speed in this moment is 300 Km/h. Maximum planned speed is 350 Km/h. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 21/161 • • • • La Sagra Toledo: a small branch with the singularity of being equipped with LZB + ERTMS. Maximum speed is 300 Km/h. Figueras-Perpignan: ERTMS, crossig border Project. Maximum speed is 350 Km/h. Córdoba-Málaga: the Córdoba-Antequera section is already in operation. It will be completed by the end of the year 2007). Madrid-Valladolid: presently under construction. Ownership of the Spanish Infrastructure In Spain, there are several publicly- owned railway networks. The owners of these networks are the State, the Autonomous Regions, or the Railway Infrastructure Administrator (ADIF). Spanish State has full powers over the General Interest Railway Network (RFIG). The General Interest Railway Network comprises all the essential railway infrastructures necessary to guarantee a common transport system throughout the national territory, or infrastructures whose joint administration is necessary for the correct operation of the common transport system, such as those connecting to international traffic routes, linking different autonomous regions and their connections and accesses to the main population centres and transport nodes, or to facilities which are vital to the economy and national defence. The General Interest Railway Network includes all the railway infrastructures managed by RENFE, before its reconversion on 1 January 2005, and those whose management has been assigned to the ADIF or is the responsibility of the Ports Authority in the general interest ports. The metric gauge network managed by FEVE is also a part of the RFIG. The decisions as to the inclusion or exclusion of railway infrastructures in the RFIG must be approved by the Ministry of Public Works, with a prior report from the autonomous regions implicated, whenever this is justified for reasons of general interest. The autonomous regions may request the transfer of any infrastructures which are agreed to be excluded from the RFIG. On the other hand the Autonomous Regions may assume powers on railway infrastructures whose routes are situated entirely in their territories. The Ministry of Transport (“Ministerio de Fomento”) The Ministry of Transport is in charge of the administration of the railway sector as a whole. According to the Railway Sector Act 39/2003 of 17 December, its main responsibilities are: • strategic planning for the railway sector, as regards both infrastructures and provision of services • general planning and regulation of the railway system, particularly in all matters relating to safety and the interoperability of the railway system, as well as to relations between the different agents in the sector • defining objectives and supervising the activity of the public railway companies, ADIF and RENFE, and their financing system For more details on the Ministry’s areas of responsibility, see art. 81 of the Act. As the Directive 2004/49/EC on Railway Safety has not yet been transposed to the Spanish Legislation, there is not any National Safety Authority (NSA). Its functions are fulfilled by Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 22/161 the Ministry of Transport through the Railway General Directorate according to the Railway Sector Act 39/2003, Real Decreto 2387/2004 and Orden Ministerial 233/2006. Railway Infrastructure Administrator (ADIF) ADIF was set up by the Railway Sector Act 39/2003 of 17 December. The ADIF by-laws were established in Royal Decree 2395/2004 of 30 December 2004. It began operating on 1 January 2005. ADIF is a public company, independently managed within the limits established by its regulations, and is part of the Ministry of Public Works. It has its own separate legal personality, is fully qualified to operate in the fulfilment of its objectives, and has its own assets. Its primary purpose is the management and construction of railway infrastructures. ADIF manages the network owned by itself and almost the whole of the general interest railway network (RFIG). ADIF currently manages a) as a commercial operation, the new high-speed and UIC gauge lines which are included in their inventory (Madrid-Seville, with the Toledo branch line, and Madrid-Zaragoza-Lleida; a total of 1,010 Km) and, b) by assignment from the State, the conventional Iberian-gauge network (11,780 Km), through an agreement subscribed for the management of this nationally-owned network. ADIF, as well as administering (operation and maintenance) the railway infrastructures mentioned above, is also responsible for the construction of new lines by order of the State, either owned by ADIF itself, financed with their own resources, or nationally-owned and financed with resources from the national budget. ADIF is currently building the MadridValladolid section of the Madrid-Valladolid-Vitoria-French border line, the LleidaBarcelona and Barcelona-Figueras sections of the Madrid-Barcelona-French border line, the lines in the Madrid-Valencia Autonomous Region-Murcia corridor, the Cordoba-Malaga section of the Madrid-Andalusia corridor, and the tunnels in the Pajares and the OrenseSantiago section of the north-east corridor. For more information on the ADIF’s areas of responsibility and functions, see art. 21 of Act There is only one exception: the high speed connexion between Figueras (Spain) and Perpignan (France). In 1995 the Spanish government and the French government signed an agreement for the construction and the operation of this new line by a concession contract. The concession was given, by a public tender, to TP Ferro, a society under Spanish law shared by the Spanish holding ACS and the French holding Eiffage. The concession is for 50 years, including the 5 years necessary for the construction. RENFE-Operadora The current RENFE was created as a public company by the Railway Sector Act 39/2003 of 17 December. RENFE’s by-laws were established in Royal Decree 2396/2004 of 30 December 2004. It began operations on 1 January 2005. RENFE was created by the segregating of the business units providing railway services and other commercial activities from the previous vertical railway company. RENFE is a public company, independently managed within the limits established by its regulations, and is part of the Ministry of Public Works. It has its own separate legal personality, is fully qualified to operate in the fulfilment of its objectives, and has its own assets. Its purpose is to provide passenger and goods transport services by rail and other Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 23/161 complementary services, and activities connected to railway transport. It also is responsible for the maintenance of railway rolling stock. RENFE will continue to receive remuneration from the State for public service obligations in providing regional and local commuter passenger services. The long-distance and highspeed passenger units are managed as commercial operations, as is the cargo unit, the only one which has been opened to competition by other operators starting in 2006. RENFE has been granted a renewal of the licence authorising it to transport passengers and goods on the national railway network. Other railway companies According to European and Spanish regulations, since 1 January 2006, all railway companies with European licences will have unrestricted access to the whole of the General Interest State Network for providing international or national freight transport by rail. To qualify, they must apply for the corresponding capacity (slot) from the ADIF, following the established procedure. At the time the capacity is granted, they must also be in possession of the safety certificate required for permission to operate, with their rolling stock and driving staff, on the requested routes. As of 1 January 2006, the Ministry of Transport has granted licences for new railway companies,. All these new railway companies will carry out their activities in freight transport by rail. At the present time ERTMS is implemented only in the High Speed Lines, which are foreseen for passenger traffic only. Freight companies operate in the conventional network that will not be equipped with ERTMS in the short term. Therefore the freight operators will not be affected by ERTMS regulations and rules. Railway Regulatory Committee The Railway Regulatory Committee is the regulatory body for the railway sector. It is a registered body which is part of the National Infrastructure and Planning Agency of the Ministry of Public Works. It comprises a president and four spokespeople who are highranking government employees in the Ministry of Transport and appointed by the Ministry, and a secretary, appointed by the committee itself. The length of the mandate, termination, incompatibilities and functions of the committee members are established in Royal Decree 2387/2004. The objectives, functions and responsibilities of the committee are: • • • • • • • To safeguard the plurality of the railway services. To guarantee the equality of all the operators in the conditions of access to the market. To ensure that the instructions comply with the regulations and are not discriminatory. To resolve any conflicts between the ADIF and the railway companies, in connection with: The assignment and use of the safety certificate. The application of the declaration’s criteria to the network. The procedures for assigning capacity. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 24/161 • • The amount, structure and application of tariffs to the operators. Resolving conflicts between railway companies in the event of actions intended to obtain discriminatory treatment in the access to infrastructures or services. • Interpreting the clauses in licences and authorizations for providing public interest services, and providing information in the bidding process. • Informing and advising the Ministry of Transport and the regional authorities on railway matters, particularly those which may affect the development of a competitive railway market The Regulatory Committee will exercise its functions in accordance with the authority granted under Act 16/1989 to the bodies established for the defence of free competition. There is an information and coordination system in place between the Committee and the Service for the Defence of Free Competition. The Committee will act ex office or at the request of the interested party. The Committee’s resolutions are binding on the parties operating in the scope of the railway, but may be appealed before the Ministry of Public Works. Non-compliance with the resolutions will be penalised according to Act 39/2003. The Safety Authority At the present time, the National Safety Authority (NSA) in Spain is the Railway General Directorate, located at the Ministry of Public Works, according to the Railway Sector Act, Royal Decree 2387/2004 and Orden Ministerial 233/2006. This Railway General Directorate is in charge of delivering the safety authorizations for putting into service any Infrastructure and Rolling Stock. The technical support for safety aspects relies on the ADIF Safety Directorate. There is an ongoing study for the creation of an independent Railway Agency which will assume those functions shortly. In the meantime, the ADIF is playing a double role in the safety authorization process. From one side, as infrastructure construction manager, is a demander of safety approval, so as the construction departments of the Ministry itself. On the other side, the Safety Direction of ADIF, acting as independent body, is in charge of the verification of the correct application of the safety prescriptions and delivers the certifications of the compliance with safety conditions required for the railway operation. The Independent Safety Assesors The interim provision of the Royal Decree 355/2006 of 29 March, on the interoperability of the trans-European high-speed rail system, lays down that the projects which were submitted to the Royal Decree 1191/2000, shall remain submitted to this regulation after the Royal Decree 355/2006 has come into force. Both Royal Decrees establish that the subsystems shall be consistent with the TSIs. The Decision 2006/860/EC, of 7 November 2006, concerning a technical specification for interoperability relating to the control-command and signalling subsystem of the transEuropean high speed rail is now in force. Its article 6 lays down: “Decision 2002/731/EC is hereby repealed. Its provisions shall however continue to apply in relation to the maintenance of projects authorised in accordance with the TSI annexed to that Decision and to projects for a new line and for the renewal or upgrading of an existing line which are at an advanced stage of development or the subject of a contract in course of Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 25/161 performance at the date of notification of the present Decision. Member States shall notify an exhaustive list of the sub-systems and interoperability constituents to which the provisions of Decision 2002/731/EC continue to apply to the Commission not later than six months after the date on which the present Decision becomes applicable.” According to the TSI set out in the Annex to Decision 2002/731/EC: • TSI § 6.1.1Conformity and suitability for use assessment procedure • TSI § 6.2.1 Control-command subsystem. “The independent assessment in the safety acceptance and approval process as described in Annex A, index 1 may be accepted by the Notified Body, without it being repeated”. Hence, Safety, which is an essential requirement, may be assessed by an ISA, which is not necessarily a Notified Body. Note that the scope of ISA assessment can be an Interoperability Constituent (IC), a subsystem, or a part of an IC or a subsystem such as an electronic board, software, or a sensor. Therefore, it is important that an ISA involved in a Directive 96/48 conformity assessment procedure, meets minimum criteria to give confidence to the NoBo accepting the ISA results, and those accepting the ISA results in a cross acceptance situation. These minimum criteria were agreed by the NB Rail Plenary Meeting on 16th February 2006 and are gathered in the RFU 2-000-16 issued by NB Rail on first of April of 2006. The Notified Body The Association of Railway Action, CETREN, was created in 1980 as a non-profit organisation, with the aim of defending the interests of the 30 companies related with the railway sector who were its founder members. More than 70 companies are currently members of CETREN and its main objective is the technical standardisation and interoperability in the railway sector. CETREN is currently registered as a certifying body, and as such was reported by the Spanish State to the Commission and the rest of the member states, within the framework of the interoperability guidelines (96/48 –high speed- and 2001/ 16 –conventional railway-). The ERTMS System suppliers The following companies are suppliers of ERTMS systems and components for the Spanish railways to date: • Ansaldo-CSEE Transport - Supplier of Trackside sub-system for Madrid-Lleida and for train-borne equipment for Trains S 120 dual gauge; • Alcatel – Invensys/Dimetronic - Supplier of Trackside sub-system for Lleida-Roda de Bará and On board GSM-R for Locos 252 and of the on-board ASFA equipment. • Bombardier - Supplier of train-borne equipment for Trains S130 (ETCS+STM LZB + STM EBICAB) • Siemens - Supplier of the GSM-R network and of train-borne equipment for Trains S 102 and S 103 (ETCS+STM LZB). The Figure 6 below shows the different roles played by the main parties of the Spanish Railway Sector. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 26/161 Infraestructure contracting Entities Train Operating Companies Equipment manufacturers General Directorate of Railways (Ministry of Public Works) Construction Departments Renfe Operadora Alcatel Ansaldo Other TOC´s Alstom Bombardier Infrastructure Manager(ADIF) Dimetronic Construction Departments Siemens …… Other Contracting Entities Safety Certificate Application for getting Interoperability Certifications Application for getting the authorization for placing in service (Mandatory documentation attached to the application) Safety AuthorityTechnical Support ADIF Opertation Safety Directorate National Safety Authority Notified Body Cetren General Directorate of Railways Certifer (Ministry of Transport) EBC Interoperability Certification Note: Authorization for placing in service of ERTMS/ Rolling Stock ADIF (Railway Infrastructure Administrator) Authorisation to placing in service is granted by the Safety Authority when all the legal requirements are fulfilled. The authorisation for running is granted by the IM, (Adif), when all the operational constraints, are satisfied. Authorization for running of Rolling Stock Figure 6 - Contracting Bodies and ERTMS Manufacturers Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 27/161 1.2 Political and Geographical constraints This section is intended to provide the following information: • • • • • • The regulatory framework (European Directives, National Railway Acts and Laws) applicable to the Project under consideration, the inter-governmental agreements, their scope and objectives, the time schedule and the major milestones and the present implementation/exploitation status. Drawings/maps showing the whole line with interconnections with other lines, terminations, stations, tunnels, bridges, distances, international borders, etc. The type, the category and the maximum speed of the line, according to the definitions of 96/48/EC or 01/16/EC directives: new high-speed line of category 1, new high speed/high capacity line, conventional line, etc. The foreseen traffic typology: only passenger traffic or mixed passenger/freight traffic (relevant percentages), commercial speeds, fixed or variable time slot characteristics, minimum headway, etc. The major physical characteristics of the line: length, double or single rails, main left/right running direction, double directivity, presence of important bridges/tunnels, curve radii, profiles, type of electrification, neutral sections etc. The main constraints to the CC&S sub-system deriving from political, geographical and topological characteristics of the Project: the ERTMS level of application, to which TSI-version the certification took place, its actual baseline (SUBSET version), the upgrading policy, the fall-back modes and systems, the interoperating modes with neighbouring systems. The Austria-Italy project: the Brenner Basis Tunnel The Project is ruled by the High Speed European Directive 96/48/EC and by the Austrian and the Italian laws and Norms for all the aspects not included in the scope of the European Directive. In particular, the Italian Ministerial Decree of 28th October 2005 giving mandatory requirements for the structural design of long tunnels and for all the related technical and security facilities must also be fulfilled. There is a special inter-governmental agreement between Austria and Italy that sets the basic political issues of the Project. In addition to the national design rules from OEBB (Austria) and RFI (Italy), there is a specific Italian Ministarial Decree (DM 28-10.2005) that imposes stringent mandatory requirements for the safety precautions to be adopted in the design long tunnel systems. It regards civil design rules as well as the use of high security measures. The Control-command and signalling sub-system foresees the ERTMS/ETCS/Level 2 system, without fall back system. The interlocking and the signalling system will be based on Austrian-German rules/technology from Innsbruck down to Fortezza. Way-side signals will be installed only at the interconnections with the conventional lines. Virtual signals, with external marker boards, will be located at the border of the block sections along the line. The main Control Centre will be placed in Innsbruck. An auxiliary Control Centre planned in Verona (or Bologna) for fallback operation. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 28/161 A GSM_R mobile telecommunication system is foreseen for all mobile telecom duties from a single GSM-R Operator. Additional redundancy is ensured by public GSM managed by Austrian and Italian commercial providers and by the TETRA system managed by the regional authorities for civil protection duties. This high level of communication redundancy is due for managing possible emergengy situations inside the tunnels. For long tunnel hazards mitigation, the technical border (for the CCS and Operation subsystems) has been moved from the political border down to the Fortezza station. Moreover, a number of additional security systems are foreseen, including Hot Box Detectors, Axial Load Monitors, Train Gabarit Monitors, Security Access Control systems etc. Possible future Train Operators are any allowed international train operator (Train typology ICE, IC, EC, EN, RoLa, EG etc.). Public and private operators of freight trains are already active in the parallel historical line. The final project will be delivered for CE conformity verification based on TSI 2002/731/EC and its amendment 2004/447/EC. Plans for Project updating to TSI 2006/860/EC are under discussion. No fall-back system is foreseen. The required level of availability will be achieved with an highly redundant ERTMS/ETCS/Lev.2 system. Interfacing with existing systems: The interconnection with the Italian hystorical line at the Fortezza Station: SCMT (v<80 km/h); with Austrian hystorical line : LZB/Indusi (v<60 km/h) at the Innsbruck station/Innsbruch railway ring; with future Italian and Austrian HSL lines at Fortezza and Innsbruck: ETCS/Lev. 2. The following Time Schedule is available to date: • Trackside: Final project to be completed with EC Conformity approval. It will be followed by Design Approval by Governments, Bids and Construction. Revenue service expected by 2015 • Train Operating Company: Any approved Operator at the time of the line availability. The following Figure 7 gives an overview of the line and of its interconnections. The former figure shows the technical border decided for the energy sub-system, the latter figure shows the technical border decided for the CC&S sub-system. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 29/161 Umfahrung Innsbruck Circonvallazione Innsbruck 3 kV = MFS Umfahrung Innsbruck MFS Steinach MFS Wiesen/Prati Bf. Innsbruck / Stazione Bf Innsbruck di Innsbruck Stazione Bf. Franzensfeste Fortezza / Stazione di Fortezza 15 kV 16 2/3 Hz 25 kV 50 Hz Umfahrung Innsbruck Circonvallazione Innsbruck MFS Umfahrung Innsbruck MFS Steinach MFS Wiesen/Prati Bf Innsbruck Stazione Fortezza Österreichische Technologie Technologia austriaca Italienische Technologie Technologia italiana Figure 7 - Layout of the Brenner Basis Tunnel line The Austrian project: Vienna-Nickelsdorf The line concerned is an existing line (No. 10118), equipped with signals and Indusi PZB system. It is the Austrian part up to the border of the Vienna-Budapest line. The ERTMS/ETCS level 1 system is an overlay system to the existing ones. The political and geographical constraints are just the European Directives - Directive 96/48/EC + 2004/50/EC, TSI CC&S (2002/731/EC and amendment 2004/447/EC). The legal framework is the National Railway law: "Eisenbahngesetz 1957" in the currently valid edition. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 30/161 The Project is supported by EC in the framework of “Indicative Multi-annual Programme for the Trans-European Transport Network 2001-2006”. The main milestones are: Start of the Project, start of NoBo activity by end of 2001, planned to be completed by end of 2003; Srtart of trial phase on 29.12.2006. The actual Status is: on one hand the track side system on the line is completely finished; on the other hand the train-borne system currently has no certificate for the group of interoperability components; the trial phase is running but not yet completed. The line is used for mixed traffic (freight and passengers). The maximum speed is 140 km/h - see VZG (summary of allowed speeds) of the line (No.10118). As for the freight/passengers mix, it actually depends of the specific sections: between Wien and Bruck a.d.L. approximately. 40%freight, 60% passengers, between Bruck a.d.L. and Hungarian border approximatly 50% each. The train frequency is: Wien - Gramtneusiedl: 140 trains/day - according to time tables and educated guess, Gramatneusiedl - Bruck a.d.L.: 120 trains/ day, Bruck a.d.L. - border: 50 trains/day. As for the line characteristics: according to the "drawings" here below; further on there are no tunnels and no relevant bridges (only some short ones). As for the interconnections with other lines: see drawings below; TEN line: Gramtneusiedl Wampersdorf, Parndorf - Kittsee (Petrcalka-Bratislava) The physical characteristics are: length: approximatly 65km, double rails, main running direction on right side, double directivity of both tracks, wide curves, total line electrified, no essential gradients, no important bridges or tunnels, Line profile in Austria D4, in Hungary D3. Speeds, stations, signals, gradients, level crossings are given in the VZG (summary of allowed speeds) of the line (No.10118). There are no particular political or geographical constraints for the choices of the CCS subsystem. The ERTMS/ETCS Level 1 (originally V. 2.0.0, during run of project changed to V 2.2.2 + several CRs of Subset 108 related to Level 1). Upgrading to V2.3.0 is envisaged. Fallback mode and neighbouring system is the conventional PZB system (also relevant for level transitions) - Customer requirements specification (Lastenheft-1-00 für das Zugbeeinflussungssystem ERTMS/ETCS Level 1 für die Strecke Wien – Hegyeshalom, 10.12.2001). No other neighbouring ETCS (or similar) systems must be considered. System transition on the Hungarian border will be of the type ETCS/Level 1 to ETCS/Level 1. The ERTMS architecture of the two track railway line Wien/Zentralverschiebebahnhof Nickelsdorf is a dual signalling ERTMS level STM/L1 architecture. The dual signaling ERTMS level STM/L1 system consists of an ERTMS STM (conventional system with wayside signals and PZB) and an overlay ETCS Level 1 system. The suppliers are Thales (former Alcatel) and Siemens. The standard system with balises is supplemented by the “infill function” realised with Euroloops. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 31/161 LEUs are used to convert the signalling information derived from a lamp current interface, for each signal lamp, to Interface C information for Eurobalises and Euroloops. The infill information is mainly used in stations where the danger points are too near to the signal. This is the case for protection signals (Austrian “Schutzsignal”) and too short overlap. The driver - traffic control voice connection is ensured by a conventional train radio communication system, GSM-R is planned. Fall-back mode: As the ETCS level 1 system is an overlay to the existing signalling system, the existing system can be considered as its fall back system. Figure 8 – Layout of the Vienna-Nickelsdorf line Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 32/161 Figure 9 – Interconnections of the Vienna-Nickelsdorf line The Belgian projects The Belgian authorities/railways have taken the following decisions: • New high speed lines will be equipped with ETCS Level 2 (this applies to the connections to Netherlands and to Germany, respectively L4 and L3 – see the description of L3/L4). • The conventional network is to be equipped with ETCS Level 1 track side equipment with the following functionalities: • TBL1+ for the largest part: ETCS-balises sending Packet 44 with TBL-information; • ETCS Level 1 for specific lines (like the Freight Corridors) • This is the first step towards the implementation of ETCS all over the Belgian network. In the first phase, a total of 4.000 way-side signals (out of of the overall 10.000 ones) will be equipped with LEU and balises under a contract stipulated in 2006 with Siemens. The Italian SCMT system has been used as a reference for the system approach: The TBL1+ information is embedded in Packet 44 of the ETCS-based telegram as step towards later use of full ETCS Level 1 telegrams. This is a national decision, as no direct impact to the national borders is involved. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 33/161 The latest TSI (Commission Decision 2006/860/EC of 7 November 2006) is used as reference scheme. The Figure 10 below shows the different levels of implementation of ERTMS/ETCS planned for the major Belgian lines, in combination with the national legacy systems. L4(ETCS2) L3(ETCS2) TBL2 TVM ETCS1 Basis=crocodile Figure 10 - Overview of the Belgian network: ETCS Levels 1 and 2, TVM, TBL2, TBL1+ The Figure 11 below shows the medium term implementation plans of ERTMS/ETCS systems in the Belgian network. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 34/161 Figure 11 - Preliminary Planning for roll-out ETCS on Belgian network Milestones: • Contract between Infrabel and Siemens signed in June 2006; • Roll out is started, to be completed by 2015. • Actual status: “under construction”. Note: according to the agreements between Infrabel and the Ministry, the TBL1-system is considered as a “SIL-zero” system. Consequently, neither assessment nor certification is contracted for this system, although ETCS-equipment is used. The network under consideration is a conventional network (according to EU-Directive 2001/16/EC) with a maximum line speed of 160 km/h. On this network both passenger services and freigt services are offered. Most lines are equipped with a 3 kV DC power supply system. On the regional lines diesel traction is used. ETCS Level 1, according to the latest specifications (Commission Decision 2006/860/EC of 7 November 2006 concerning a technical specification for interoperability relating to the control-command and signalling subsystem of the trans-European High Speed rail system and modifying Annex A to Decision 2006/679/EC of 28 March 2006 concerning the technical specification for interoperability relating to the control-command and signalling Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 35/161 subsystem of the trans-European conventional rail system. (Notified under document number C(2006) 5211) – “Official Journal of the European Union L 342/1 of 7.12.2006”.). The French project: LGV-Est The complete project (see the Figure 12 below) includes 406 km of a new line between Vaires (Seine et Marne) and Vendenheim (Bas Rhin). The first stage, includes 300 km of line from Vaires to Baudrecourt (Moselle), plus new links to the existing network in order to serve as many destinations as possible. The project also includes modifications to connecting lines and installations, in particular between Paris Gare de l'Est and Vaires sur Marne and on the line Strasbourg-Kehl in order to improve the link with the German network. The lines to Épinal and St. Dié in the Vosges will be electrified to allow the towns to be served by the TGV. Figure 12 – LGV-EST Line ERTMS L2 is implemented on the line. Trains equipped with ERTMS Level 2 will circulate on this line under ERTMS and trains equipped with TVM 430 only, under TVM. TVM 430 serves as a fall back system but only after a procedure has been followed by driver and dispatcher. The PEEE project thus covers three sub-projects: • One sub-project system ensuring coordination of the PEEE project at system level, • One sub-project supplying ERTMS Level 2 on TVM 430 trackside • One sub-project developing and supplying trains with bi-standard ERTMS/TVM. The commissioning authorisation applies to the system made up of the on board equipment (bi-standard ERTMS/TVM) installed on the POS trains and the trackside equipment regarding Level 2 superimposed on TVM430. The line is operated bidirectionally and is meant for passenger-transport only. The German project: Berlin-Halle-Leipzig The regulatory framework of the Project is summarised in the previous section. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 36/161 Since the BHL line does not touch or cross any national borders there is no need for any kind of intergovernmental agreement in the moment. BHL shall become part of an international high speed TEN connection from Stockholm/SE via Berlin and Munich to Verona/IT. As for the time schedule and milestones, a serial qualification period without safety responsibility started in 2003-03. The basic functions - trackside and onboard - should be tested and continuously amended at this phase, the concept should prove its practicality. On 7th of July and 11th of December 2003 first presentation runs took place for the customer and a UIC conference. Start of operational qualification period without safety qualification was in 2003-12. Within this phase the functions known from the Serial Qualification should be extended step-bystep up to the point that all functions depicted in the LH were realised. In 2004-10 the EBA issued the permission to start the safety qualification tests. The tests – still without safety responsibility - finally began in 2005-06 after it had been proven that the functions implemented equalled those defined in the LH. Meanwhile all preliminary safety cases had been assessed and the overall ETCS safety fulfilled the top level safety target calculated by the risk analysis. Level 2 operational and reliability qualification period under full safety relevance started in 2005-12. The national automatic train protection system LZB (LZB L72 CE2) was commissioned in 2006-05. ETCS Referenzstrecke Berlin-Halle/Leipzig Streckenübersicht Berlin RBC-Bereich Ludwigsfelde LZB-Bereich Ludwigsfelde Teltow 15 km 160 Balisen Birkengrund-Süd Ludwigfelde Ludwigsfelde Trebbin km 34,3 RBC-Bereich Jüterbog LZB-Bereich Jüterbog Scharfenbrück km 39,5 Luckenwalde km 50,0 RBC Jüterbog km 62,8 RBC-Bereich Wittenberg 40 km 250 Balisen UZ Jüterbog Steuerbezirk 1 Berlin Niedergörsdorf km 69,2 w lto e T eB ld u M i W rg b n Bte -terflhBiRC-dcd C iR B rflh cte i W rg b n te C B iR W n te C B iR W n te ic-L B h o tb Jü rg e S u ubergJütohBicL lw is B k c ü b n fe h d gw bT s B -S ru n k 5 ,9 4 3 km ld fe ig ra T C B R C B R C R B g o trb ü J C lR ödergösofZahnNi ikm75,16289LuckensdorfB N n h a fZ o d s ö rg e lw a e dealw d50, d a R n m ik w rg e B z G d R b W m k w g B fz ä G tu ra iP n e h u tsc s ,0 4 8 km 6 5 2 0 1 3 ,8 4 9 km e lb E Blönsdorf km 75,1 Zahna RBC km 84,0 Wittenberg km 94,8 Pratau Elbe km 98,3 UZ Wittenberg Steuerbezirk 6 Leipzig LZB-Bereich Wittenberg Bergwitz km 104,2 RBC-Bereich Bitterfeld Radis km 112,5 Gräfenhainichen Burgkemnitz Mulde RBC 90 km 795 Balisen km 116,1 km 121,5 Muldenstein km 126,2 Bitterfeld km 131,6 / 48,5 Roitzsch km 138,7 Landsberg km 146,5 Delitzsch Ab km 156,0 km 60,4 UZ Bitterfeld/Delitzsch Steuerbezirk 6 Leipzig LZB-Bereich Bitterfeld km 151,545 Po 159 km 152,003, Po 160 Rackwitz Halle km 70,0 km 81,3 Leipzig Figure 13 – Halle-Leipzig line The BHL relation was upgraded to a high speed line with mixed operation of passenger trains at Vmax =200 kph and freight trains at Vmax = 100 kph. It was equipped with both high speed and conventional train protection systems so that both ETCS trains and trains with legacy onboard CCS can run on the track. The length of the line is about 145 km, starting at Teltow in the south-west of Berlin, ending before Leipzig, via Ludwigsfelde, Jüterbog, Wittenberg and Bitterfeld. The main driving direction is 'right'. Trains run on double rails with crossovers at defined transfer points. The line is fitted with two legacy (national) signalling techniques: linear LZB and intermittent Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 37/161 PZB train protection systems. Optical wayside signals "KS system" and track sections with axle counters are installed. The BHL line is equipped with ETCS Level 2. It is planned to connect the route to a Level 1 section in the North. Momentarily the line is operated based on a national specification (“Rahmenlastenheft”, [DB 27]) and on UNISIG 2.2.2. The BHL line is the first German route being prepared with the new European train protection system. This was a special challenge, not only because of the new technology itself, but because of the fact that two approval/acceptance and certification processes had to be conciliated. Thus a “new” approval process had to be initiated, trying to assemble in a way that both national and European aspects with regard to technical, operational, economical and judicial demands were satisfied. Migration from LZB to ETCS is a costly long-term enterprise, since the German network is well equipped with modern, safe and effective automatic train protection systems for the main and high speed lines. Exchanging LZB to ETCS in one step would cause immense costs. Hence a period of double equipped lines and traction units are aspired by the German railway net and rolling stock operators. The re-investment in LZB and many other arguments are contrary discussed. The BHL line was initially not equipped with any type of LZB so that the specific migration at the pilot line became an “inversion of the usual migration situation” (Kollmannsberger/Kilian/Mindel, Signal & Draht, 2003-03): On the BHL pilot line ETCS was installed 3 years before LZB was added. The “Punktförmige Zugbeeinflussung” (PZB), German Class B intermittent train protection system, serves in case of ETCS malfunctions. Additionally the LZB is the part of the migration concept, allowing non-ETCS trains to run on the BHL track, too. Not all traction units running on the multifunctional line are equipped with LZB (or ETCS). In Germany some 2.000 km of track are equipped with LZB (5% of the network, all main lines). BHL, formerly named “J-H/L” (Jüterbog – Halle - Leipzig), was initially intended to be operated as a "Test Site" during the consolidation phase of the European ETCS specifications. The Italian Projects The Rome-Naples HSL The design of this line started much earlier than the entry into force of the 96/48/EC Directive. As a consequence a full EC certification was not strictly required. Nevertheless, RFI decided to pursue the EC conformity verification as a mean of anticipating activities that were to be required for the HSL projects to come. It must also be noticed that being the HSL in consideration fully contained in the national territory, the Rome-Naples HSL Project did not experience the technical and operational issues typical of a cross-border line. The regulatory framework applicable to Rome-Naples HSL project is outlined in the Annex: • European Directives regarding the HSL interoperability; • The Italian Law endorsing the Directive; Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 38/161 • The relevant CENELEC Norms and European Specifications; • The RFI Directives; • The RFI Procedures and Technical Norms. The line was put in revenue service since 12th December 2005. The HS/HC Line Rome-Naples (see Figure 15 below) is integrated in the Italian High Speed Project which integrates the trans-European High Speed Network (see Figure 14). Figure 14 - European Corridors crossing Italy The line is new high speed/high capacity line of category 1. The maximum speed of the line is 300 km/hour. A mixed traffic typology (passengers and freight) is foreseen. The commercial speed is 300 Km. per hour for passenger trains. The length of the line is 184 Km. To date, the high speed line starts in Rome from Termini Station and ends to the Gricignano interconnection whit the Foggia-Naples conventional line. The line is double track (minimum distance 5 meters) with left main running direction and the possibility of double directivity. There are a total of 40 Km. of bridges and 38 km. of tunnels the length of the longer tunnel is 6,628 Km. (Colli Albani). The minimum curve radius is 5 450 m. The maximum slope is 21 ‰. The power supply is of the type 2x25 kVac-50 Hz. There are three interconnections with conventional line: Frosinone Cassino Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 39/161 Caserta. At each interconnection plus in Salone and in Gricignano there are Neutral Sections managed by ERTMS. Figure 15 - Interconnections of Rome-Naples HSL No specific constrains deriving from political, geographical and topological characteristics are present on the Rome Naples line. The adopted signalling system is based on Solid State Interlocking supplemented by jointless, audio-frequency track-circuits. No lateral signals are used. Only Marker Boards are used at the borders of each Block Section. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 40/161 The ERTMS/ETCS Level 2 system is used for all the train operation and protection functions (according to SUBSET026 version 2.2.2) without any other fallback system. The interconnected conventional lines are equipped with the Italian BACC/SCMT signalling system. This requires the on-board train control system to be equipped with the BACC/SCMT STM. Train entrance/exit from/to interconnections are managed as normal level transition STM Æ L2 or L2 Æ STM for the train equipped by STM or L0 Æ L2 or L2 Æ L0 for those trains not equipped with the STM. RFI foresees the upgrading from the SUBSET026 version 2.2.2 to version 2.3.0 in a near future. To date, RFI is discussing the migration strategy in accordance with the European strategy. The Torino -Novara HSL The line is, in all aspects, similar to the Rome-Naples case, with the following difference: the EC conformity certification was legally required, since the works started after the Directive entered in force. It is integrated in the Italian High Speed Line Project which is integrated in TEN corridor 5 linking Lisbon to Kiev. The line is in revenue service since February 6th 2006. One of the most remarkable events pushing for a quick and very effective completion of the test and acceptance process for the Turin-Novara line was the Turin Winter Olimpiads to be held just in the early 2006. Figure 16 – Turin/Novara High Speed Line The line is new high speed/high capacity line of Category 1. The maximum speed of the line is 300 Km per hour. A mixed traffic typology (passengers and freight) is foreseen. The commercial speed is 300 Km. per hour. The length of the line is 84 Km. It is double track (minimum distance 5 meters) with left main running direction and the possibility of double directivity. The maximum slope is 15 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 41/161 ‰. The power supply is AC 2x25 Kv 50 Hz. There are two interconnections with traditional line: Stura and Novara. No special constrains deriving from political, geographical and topological characteristics are present on the Turin-Novara line. The signalling system is ERTMS Level 2 (Subset 026 version 2.2.2) without fallback system. The interconnected traditional lines use the BACC/SCMT signalling system. The BACC/SCMT is the Italian STM agreed of TSI Class B systems. Train inputs or outputs from/to interconnections are managed as normal level transition STM Æ L2 or L2 Æ STM for the train equipped by STM or L0 Æ L2 or L2 Æ L0 for those not equipped. RFI foresees the upgrading from SUBSET026 vers. 2.2.2 to version 2.3.0. Nowaday RFI is discussing the migration strategy according to the European strategy. The Dutch projects Betuweroute The technical solutions chosen for this project are: ETCS Level 2 without any other fallback system; As far as the current status (May 2007) is concerned, the following applies: although the contract between Alstom and ProRail requires Alstom to build the system according to ERTMS SRS 2.2.2, there are NoBo statements declaring the status of implementation of the CR’s in SUBSET108. The trackside system can therefore be viewed as 2.3.0 compatible. • As for the fall-back mode: Simple ATB NG system with signals and very large sections, only allowing limited capacity has not bee implemented on A15, because there was enough confidence in ERTMS. • The interfaces with existing systems are: ATB-ERTMS Lev. 2 at entrance; ERTMS Lev. 2-ATB at exit. • The controlled balises are coupled with existing Interlocking via LEUs The Project Time Schedule (to May 2007) is: • A15 Trackside Safety Case is available for BR A15v3.4, approved by ISA (no blocking remarks) and ready to start revenue service from mid June 2007. • Bev21 update to A15v4 (version that includes HHT+workzones functionality) expected Q4 2007 • Train Operating Company: Approval tests on Betuweline are foreseen in 2007. Official opening on June 16th 2007, with about 20 locomotives of different freight operators. The train-infrastructure integration tests will then not be finished completely The following figures show the profile of the line toghether with its interconnections. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 42/161 Figure 17 - The Betuweroute overview Figure 18 - The Betuweroute, Western part Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 43/161 Figure 19 - The Betuweroute, Middle part Figure 20 - The Betuweroute, Eastern part Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 44/161 Amsterdam - Utrecht The Amsterdam - Utrecht line has the architecture of Dual Signaling consisting of a conventional system with wayside signals, ATB-EG and an overlay ETCS Level 2 system. The supplier will install the overlay ETCS Level 2 on the line by 2009. The ERTMS/ETCS architecture is part of further negotiations. The supplier has developed a new and more powerful hardware for the Interlocking and the Radio Block Center and proposed to install the new hardware. The supplier has more ETCS projects and will come to RBC standard generic software modules. The country specific functionality will be hosted in a country specific interface module. The supplier proposal is to install one Master / Slave interlocking and one Master / Slave RBC. The supplier proposes at the same time to migrate the system specification from the actual SUBSET026 version 2.2.2 to version 2.3.0. The fallback scenario for ETCS Level 2 is the conventional system with way-side signals and ATB (the Dutch ATP system). At the present date, the use of GSM-R is for voice communications only. Figure 21 – Utrecht-Amsterdam HSL Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 45/161 HSL ZUID The following Figure 21 shows the route of the line from Amsterdam to the Belgian border. The signalling system is the ERTMS/ETCS Level 2, with a Level 1 fallback system. At the connecting locations with the existing tracks, a transition from Level STM to Level 2 is made, or from Level STM to Level 1 in fallback mode. The applicable CCS TSI is the 2006 version including Subset 108. The contract was initially based on TSI 2002, in a later stage it was decided to add subset 108. The applicable Operations TSI is the 2002 version. There are no derogations reported to the time being. The information about this project derives from the following official documents: • • Concept Register of Infrastructure ; Doc. nr: HSL-Zuid #743200 Operation Analysis including Capacity Simulation Doc. nr : IFS M011090085 Figure 22 - HSL Zuid The Spanish projects The main legislation items that regulate the railway sector in Spain, including high-speed and conventional rail system, are: • • Railway Sector Act 39/2003 of 17 December: the Railway Sector Act that transposes to the Spanish legislation the Directives 91/440/CEE, 2001/12/CE, 95/18/CE, 2001/13/CE, 2001/14/CE and 2001/16/CE. This law puts the administration of the railway infrastructure under the responsibility of a new entity: Railway Infrastructure Administrator (ADIF). At the same time a new public entity named RENFEOperadora is created as a railway transport enterprise to offer all kind of railway services to the citizenship. Royal Decree 2387/2004 of 30 December, approving the Railway Sector Regulation: Royal Decree that develops the Law 39/2003 and regulates the railway sector in Spain. This Royal Decree defines more precisely the procedures for the authorization to enter into service the infrastructure and the rolling stock. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 46/161 • • • • • Royal Decree 2395/2004 of 30 December approving the by-laws of the Railway Infrastructure Administrator (ADIF). Orden FOM/897/2005 of 7 April, on the Network Statement and the procedure for allocating railway infrastructure capacity. Orden FOM 233/2006 of 31 January regulating the conditions for the approval of railway rolling stock and maintenance workshops and sets the certification fee amounts for this rolling stock. Royal Decree 354/2006 of 29 March, on the interoperability of the trans-European conventional rail system. Royal Decree 355/2006 of 29 March, on the interoperability of the trans-European high-speed rail system The first transitional provision of the Royal Decree 2387/2004 lays down that until the Ministry of Transport passes the regulations which will implement the Railway Sector Act 39/2003, the applicable safety regulations are the following: • • RENFE Operational Rules and Regulations. Technical and Operating Requirements for Running and Safety on the MadridZaragoza-Lleida section of the Madrid-Barcelona-French Border line, Version 2. All the technical regulations and standards applicable to the every different ERTMS projects are gathered in the Annex [see RENFE 1]. The regulatory framework for ERTMS is the Decision 2002/731/EC of 30 May 2002 concerning the technical specification for interoperability relating to the control-command and signalling subsystem of the trans-European high-speed rail system referred to in Article 6(1) of Council Directive 96/48/EC, according to RENFE - Operadora´s tender specifications for rolling stock purchases, which figure on Annex II [see RENFE 2]. The Safety approval process: Infrastructure The art. 16 of the Royal Decree 2387/2004 of 30 December ‘04, approving the Railway Sector Regulation, lays down the way to authorize the placing in service of the new railway infrastructures. According to this article, before the railway lines enter into service, its sections and the stations belonging to the general interest railway network (RFIG), must have the Ministry of Transport’s authorisation. In addition, this authorization has to declare that the line or the section of the line has to enter into service, when it fulfils all the safety requirements of the applicable regulations. This authorisation shall be granted by the Railway General Directorate, taking into account: • • • The report on the suitability of the works to the applicable technical rules and regulations. This report has to be issued by personal responsible for the construction and its supervision. The certification of the compliance with the safety conditions required for the railway operation issued by the Railway Infrastructure Administrator or entity entitled to issue it. The supporting documents relative to the compliance with the implementation of the testing plan at the request of ADIF or, where appropriate, the General Railway Directorate. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 47/161 The authorization to enter in service can be unrestricted, or subject to some restrictions, or an interim authorization (i. e. for test runs, maintenance….). The Royal Decree, RD 2387/2004, refers implicitly to the TSIs: The “Additional disposition 1” of this RD states that the interoperability is regulated by the RD 1191/2000 and the RD 646/2003, whch respectively transpose the HS and CR EC Directives. Due to the delay in the TSI completion, the Spanish Ministry of Transport has decided to put into service the HS lines in two phases: First opening the infrastructure on the basis of the safety certification, which allows the “national” operation of the line, and in a second step the infrastructure will get the Declaration of Verification when all the constituents have the Declaration of Conformity or Certificates and then could be open to international traffic. The following Figure 23 sumarizes the safety approval process for infrastructures. A similar process is being applied to rolling stock. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 48/161 Construction manager Report on the suitability of the ERTMS subsystem to the applicable technical rules and regulations with reference to the applied technical regulations and rules Reference regulations: Directive 2004/50/EC Royal Decree 355/2006 Directive 96/48/EC Directive 2001/16 o o o o Construction manager Application for getting the authorization for placing in service of ERTMS Mandatory documentation attached to the application Construction manager Construction manager Independent assessment report Safety Case Reference rules: CENELEC standards Adif Safety Directorate Certification of the compliance with safety conditions required for the railway operation General Railway Directorate Authorization for placing in service of ERTMS Construction manager Supporting documents relative to the compliance with the implementation of the testing plan at the request of Adif or, where appropriate, the General Railway Directorate: o o Testing protocol Subsystem integration report Figure 23 – Safety approval process for infrastructural works in Spain Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 49/161 Safety approval process: rolling stock The article 4 of the Orden Ministerial 233/2006 lays down the requirements for placing in service of rolling stock. Article 4 of the above-mentioned Orden Ministerial states that: 1. Every railway vehicle must get an authorization for placing in service, granted by the General Railway Directorate, and an authorization for running, granted by the Railway Infrastructure Administrator, before running on the general interest railway network (RFIG). 2. There are two authorisation levels 3. The ”first level authorization” for placing in service shall be granted having regard to: • The “EC” certificate of conformity issued by a Notified Body which gives evidence of the compliance with the applicable Technical Specifications of Interoperabilty (TSI´s). • The validation report issued by a Certifying Body that gives evidence of the compliance with the applicable Technical Specifications for Homologation (Especificaciones Técnicas de Homologación – ETH). In fact, these specifications are under development now, refer to national requirements, and will be notified to the EC when ready). Rolling stock granted with a first level authorization is interoperable and suitable for running on the general interest railway network (RFIG). 4. The ”second level authorization” for placing in service shall be granted when the applicant rolling stock has got a validation report issued by a Certifying Body that gives evidence of the compliance with the applicable ETH. Rolling stock granted with a second level authorization suitable for running on the general interest railway network (but is not interoperable). 5. The Railway Infrastructure Administrator shall grant the authorization for running to the rolling stock that has got an authorization for placing in service and has passed satisfactorily the test runs requested by the Railway Infrastructure Administrator, in accordance with the applicable ETH´s. The ETH, now under development, are intended to complement the TSIs in safety aspects, trying to adapt the current Spanish operational rules to the TSI’s structure and philosophy. The ETH, when completed, will be notified to the EC. At the present time, any rolling stock has received the EC Declaration of verification. Consequently all the authorisations granted by the General Railway Directorate have been “second level authorisations”. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 50/161 Second level authorisation Step 1 Certifying Entity Validation report giving evidence of the compliance with the applicable ETHs Rolling Stock Manufacturer Rolling stock owner Application for getting the authorization for placing in service of Rolling Stock Mandatory document ation attached to the application Safety case Reference rules: CENELEC standards Rolling Stock Manufacturer Report on validation and verification Rolling Stock Manufacturer Railways General Directorate ISA report on safety Authorization for placing in service of Rolling Stock without interoperability Rolling stock owner To pass verification tests requested by Adif together with the General Railway Directorate Figure 24 – Safety approval process (second level) for rolling stock in Spain With reference to the interoperability certification of new lines, it is necessary to consider the followings: • • • • The new high speed lines have been built at the same time when the TSIs were being updated. This implies that the ERTMS installation was being adapted to the modification of the specifications. Consequently, the new lines are being placed into service with the required Safety Authorizations but without the Interoperability Certifications. Nevertheless, as the verification and safety tests required for the Safety Certification have been established using the TSIs and the EEIG test specifications, no interoperability problems are to be expected during the NoBos Certification process. The certification procedure of the line Figueras-Perpignan started in the beginning of the year 2005, at the same time of the beginning of the construction. The certification procedures of the other lines started at the beginning of the year 2007. As far as on board systems are concerned, the interoperability verification and certification procedures started in the year 2005 for some of the manufacturers. However, no certification has been issued yet. The geographical structure From the geographical point of view, it must be underlined that the Spanish railway network has essentially a radial structure, with Madrid as main centre. Besides this structure, there is Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 51/161 an important line along most of the Mediterranean coast from the French border to Valencia, Alicante and Murcia. Since 1992 there is an intense development of new high speed lines using standard gauge and 25 KV AC power supply. The structure of this high speed network will follow the same radial principle. The main high speed lines are: • • • • • • • Madrid –Sevilla, built in 1992 to foster the development of a wide region not well communicated up to that time, equipped with LZB as at that time the ERTMS was not developed. Maximum speed: 300 Km/h. Madrid- Zaragoza-LLeida- Roda de Bara (Tarragona) - Barcelona, that interconnects the two biggest Spanish cities (>4.000.000 inhabitants each), that will be extended up to the French border. It is equipped with ERTMS and is in service from Madrid to Roda de Bara. It will be completed by the end of the year 2007. Maximum speed in this moment is 300 Km/h. Maximum speed planned is 350 Km/h. Madrid- Valladolid, under construction, will open the high speed way to the north and northwest at the end of 2007. Maximum speed planned: 350 Km/h. La Sagra Toledo: Small branch with the singularity of being equipped with LZB + ERTMS Maximum speed: 300 Km/h. Córdoba-Málaga branch also fitted with LZB+ERTMS. Maximum speed: 300 Km/h. Zaragoza-Tardienta-Huesca: Interesting experience with ERTMS over hybrid line Spanish Broad Gauge + UIC gauge. Maximum speed: 300 Km/h. Figueras-Perpignan, ERTMS, crossig border Project. Maximum speed: 350 Km/h. In the medium term, the high speed network will be completed with the Madrid-Valencia (in the year 2010) and Madrid-Lisbon lines. The high speed network, (with the exception of the Madrid-Sevilla line) is being equipped with ERTMS. The conventional railway lines will be progressively upgraded to ERTMS. All Spanish lines are equipped with ASFA as back up system. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 52/161 Figure 25 – High speed lines in Spain The characteristics and the status of each one of the ongoing ERTMS implementation projects are given in the followings. Madrid-Lleida Line • • • • • • • • • • • Passenger traffic only Length : 492 Km Max gradient: 25 o/oo Tunnels: n. 26, with a total tunnel length: 29,5 Km Viaducts: n.40, with a total viaduct length: 25,5 Km Bridges: n. 48 with a total bridge length: 4,18 Km Maximum speed: 350 Km/h Permanent speed restrictions: 90 Km/h through Zaragoza station and 50 Km/h through Lleida station Switches in main line and speed in side position n. 12 at 50 Km/h, n. 73 at 100 Km/h, n. 9 at 150 Km/h, n. 9 at 160 Km/h and n. 89 at 220 Km/h Stations: Madrid, Guadalajara, Calatayud, Zaragoza, Lleida Interlockings: n.13 (Ansaldo) Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 53/161 • • ERTMS implementation: Level 1 and Level 2 with Specs vers. 2.2.2 ERTMS equipment: n. 361 LEU’s, n. 3262 Eurobalises, n. 5 RBC’s (Ansaldo) – GSM-R (Siemens) • Fall-back systems: ERTMS Level 1 and ASFA LLeida-Roda de Bara Line • • • • • Passengers traffic only Length: 91 km Tunnels: n. 7 (Lilla, 2000 m; la Riba 1971 m) Viaducts: n.20 Maximum speed: 350 km/h The figure below shows the route of the line Madrid-Zaragoza-LLeida-Roda de BaraBarcelona). Figure 26 - The “Madrid-Zaragoza-LLeida-Roda de Bara-(Barcelona) HSL Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 54/161 La Sagra-Toledo Line • • • • • • • • • • • Passengers traffic only Length: 21 Km Max slope: ±27,5 o/oo Viaducts: n.1, total viaduct length: 1,6 Km;. Maximum speed: 220 Km/h Switches in main line and speed in side position: n. 2 at 80 Km/h, Stations: Madrid, Toledo Interlockings: n.1 Electronic Westrace interlocking (Dimetronic) and the extension of L 90 Interlocking (Alcatel) at La Sagra ERTMS implementation: ETCS Levels 1 and Level 2 (Alcatel/Siemens) Versión 2.2.2, SUBSET026, Version 2.2.2 ERTMS equipment: n.16 LEU’s (Alcatel); n. 80 Fixed Eurobalises (Siemens); n. 32 Variable Eurobalises (Siemens); n. 1 RBC (Alcatel); n. 5 GSM-R BTS‘s (Siemens) Fall-back system: ERTMS Level 1 and ASFA Figueras-Perpignan line • • • • • • • • • • • • • • Mixed traffic Length: 44,4 km (19,8 km in Spanish territory and 24,6 in French territory Max slope: TBC Tunnels: n.1 Pertús (8,3 km) Viaducts: n. 9 (5 in Spain, 4 in France) Bridges: TBC Maximum speed: 350 km/h in passenger traffic Permanent speed restrictions: At least 100 km/h in freight trains Switches in main line and speed in side position: TBC Stations: No stations Interlockings: TBC ERTMS implementation: Levels 2 and 1 ERTMS equipment: CSEE Transport Fall-back system: ERTMS Level 1 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 55/161 Córdoba-Antequera line • • • • • • • • • • • Passengers traffic only Length: 97,4 km Max slope: 20 mm/m Viaducts: n. 8, total length: 4,3 km, maximum length: 1,4 km Tunnels: n. 2, total length: 329 m, maximum length: 275 m Maximum speed: 350 km/h Permanent speed restrictions: 220 km/h Switches in main line and speed in side position: n.1 at 220 km, n. 2 at 100 km Stations: Puente Genil, Antequera-Santa Ana Interlockings: n. 4 ERTMS implementation: Levels 2 (Alcatel, Siemens) Vers. 2.22.2, Subset-026, Vers. 2.2.2 • ERTMS equipment: n. 95 LEU’s; n. 370 fixed and variable Eurobalises; n. 22 GSM-R BTS‘s • Fall-back system: ERTMS Level 1, LZB and ASFA The Figure 27 below shows the route of the line “Córdoba-Antequera-Málaga”. Figure 27 - Córdoba-Antequera-Málaga HSL Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 56/161 Madrid-Valladolid line The Figure 28 below shows the route of the line project “Madrid-Valladolid”. Its main characteristics are: • • • • • • • • • • • Passengers traffic only Length: 226 Km Max slope: 29,5 o/oo Tunnels: n. 9, total tunnel length: 43,4 Km, maximum length 28,7 Km Viaducts: n.11, total viaducts length: 6035 km, maximum length: 1,7 km Bridges: TBC Maximum speed: 350 Km/h Permanent speed restrictions: 275 Km/h in some tunnels, 220 Km between,100 Km/h in Segovia station and Olmedo, 50 Km/h in Valladolid Station Switches in main line: Speed in side position n.1 at 30 km/h, n. 1 at 45 km/h, n. 2 at 50 km/h, n. 1 at 80 km/h, n. 5 at 100 km/h, n. 2 at 160 km/h and n. 5 at 220 km/h Stations: Madrid, Segovia, Valladolid Interlockings: n. 9 electronic Westrace Interlocking (Dimetronic) Figure 28 - Madrid-Valladolid HSL • • • ERTMS implementation: Levels 1 and Level 2 (Alcatel/Siemens) Version 4.20, Subset-026, Version 2.2.2 ERTMS equipment: n. 178 LEU’s (Alcatel); n. 689 fixed Eurobalises (Siemens); n. 377 variable Eurobalises (Siemens); n. 3 RBC’s (Alcatel); n. 44 GSM-R BTS’s (Siemens) Fall-back system: ERTMS Level 1 and ASFA Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 57/161 The tables below indicate the actual status of implementation of ERTMS/ETCS both on track-side and on board of Rolling Stock. Line Supplier ETCS Length level (Km) Speed (Km/h) Status 492 350 In operation (2004) High speed lines Madrid-Lleida Ansaldo +Siemens (CSEE) L2+L1 Lleida- Barcelona Alcatel L2+L1 90 350 Lleida-Tarragona: In operation (2006) Tarragona-Barcelona under construction (end 2007) La Sagra-Toledo Alcatel +Siemens L2+L1 21 300 In operation (2006) Madrid-Segovia-Valladolid Alcatel + Siemens L2+L1 180 350 Under construction (2007) Córdoba-Málaga Invensys L2+L1 155 300 Under construction (2007) Zaragoza-Huesca Alstom L1 80 200 In operation (2006) Figueras-Perpignan Ansaldo (CSEE) L2+L1 30 300 Under construction (2009) Bombardier L1 93 L2+L1 160 200 120 In operation (2000) Conventional lines Albacete-La Encina Madrid conmuter Pending of award Table 3 - Status of ERTMS implementation – Infrastructure Series Suppliers Number of trains Composition Seats Train length (m) Speed (Km/h) Traction power (kw) Signalling system Commissioning Gauge track S-102 Talgo-Bombardier 16 30 2 tractive heads 12 cars 314 (+2hp) 346 (+2hp) 200 330 8000 S-103 Siemens 16 10 8 powered cars S-104 CAF- Alstom20 13 4 powered cars S-120 CAF- Alstom 12 16** 4 powered cars S-252 Siemens 73 237 (+1hp) S-130 Talgo-Bombardier 27 18 2 tractive heads 11 cars 298 (+1hp) 402 (+2hp) 200 350 8800 236 (+1hp) 229 (+1hp) 107 250 4000 107 250 (220)* 4000 (2500)* 185 250 (220)* 4800 (4000)* 20,4 200 Km/h 5600 ERTMS+ STM LZB + ASFA ERTMS+STM LZB + ASFA ERTMS+ STM LZB + ASFA ERTMS+ ASFA ERTMS+ STM LZB + ASFA + EBICAB 2004 2005 Spanish 2007-2008 Spanish= 1668 mm ERTMS + STM LZB + ASFA 1992 2005 UIC 2007 UIC values into brackets applies under 3000V DC Table 4 - Status of ERTMS implementation – Rolling stock The Technical solutions chosen for the projects are: • • Current system version status: SUBSET026 Version 2.2.2 is applied although the Initial contracts were based on Version 2.0.0. Migration to Version 2.3.0 is under consideration. Due to concerns about the backwards compatibility between 2.3.0 and 2.2.2. some mitigation measures were decided: Not using some additional functions on 2.3.0, applying additional engineering rules CR 458 non compatible, pending on UNISIG decision. Fall-back mode: ETCS Level 1 when Level 2 will be in service. ASFA and conventional signals as secondary fallback Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 58/161 • Interfacing with interlocking and conventional signalling system: Level 1 balises are driven by the Interlocking system via LEU's. LEU's are concentrated at the interlocking buildings. • With ETCS Level 2, transition between Madrid-Lleida (RBC by Ansaldo) and Lleida-Roda de Bará (RBC by Alcatel) is made through Level 1 at max allowed speed of 300 km/h. No RBC-RBC interconnection is foreseen. The following implementation status is achieved to date: • • Trackside system: Safety Certificate for Level 1 approved through lab tests and on line tests according to ADIF protocols, On-going lab and on-line tests for Level 2. Approval expected at mid 2007. NoBo Certification on process started on 2007. Train borne systems: Trains series 102 (Siemens) approved on 2006 (16 units); series 103 (SIEMENS ETCS + STM LZB) foreseen on April 2007 (16 units); series 120 (Ansaldo) foreseen by the end of 2007 (12 units); series 130 (Bombardier ETCS + STM LZB + STM EBICAB) foreseen by 2008 (45 units); locos Series 252 (INVENSYS/Dimetronic) (Number of units and approval date unknown). Conventional Rail Series 490 trains (INVENSIS) Unknown approval date (10 units) 1.3 Safety targets / RAMS Policy This section is intended to provide the following information: • • The main RAMS concepts applied to the Project: the system performances, the overall system availability, the maintenance policy, etc. The higher-level documents used as input for the definition of the RAMS policy. The Austria-Italy project: the Brenner Basis Tunnel The document “Erhaltungskonzept Technischer Bericht - Concetto di Manutenzione Relazione Tecnica” defines the basic concepts of line maintenance in accordance with the CENELEC Norm EN°13306. The maintenance is particularly critical for this particular line fully included in a long tunnel. The document “Ausrüstung Technischer Bericht Festlegung der RAM-Anforderungen Attrezzaggio Relazione Tecnica Definizione dei Requisiti RAM” defines some basic concepts of system availability and then, apportions the required overall system availability figure of Avtot=0.9995, into availability, reliability and maintainability requirements for all functions of the control-command, signalling, telecommunication, security and power supply system. Taking into account mission profile of the line and the maintenance constraints recalled above, the final target for the availability of the CC&S sub-system has been preliminarily set to AVccs =0.999865 (this issue is still under discussion to date) with respect to all types of immobilising failures. The safety requirements for the staff operating in the tracks imposes that the preventive and the corrective maintenance activities are only performed during the closure of the service, that will happen only for a couple of hours during the night. This imposes a high demand in the availability of the CC&S sub-system functionality that can only be achieved by a high level of redundancies. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 59/161 The document “Tunnelsicherheit Technischer Bericht-Sicherheitkonzept- Sicurezza in Galleria Relazione Tecnica-Concetto di sicurezza” provides a wide hazard analysis for all the risks possible in a long tunnel and defines the basic conter-measures able to minimise their consequences. This document is the master document for the tunnels layout design as well as for all the hazard analysis of the technical sub-systems. In particular, the document “Leit-und Sicherungstechnik-Technischer Bericht Sicherheitplan-Sistemi di Controllo e Comando – Relazione Tecnica – Piano di Sicurezza” defines in detail the overall design, implementation and verification/validation/approval process and responsibilities (in accordance with the EN50126 norm) to be followed during the whole life-cycle. In its annexes the document presents the results of a preliminary hazard analysis based on results of similar European projects, with the related countermeasures. It finally concludes that the ERTMS/ETCS safety targets of Subset091 are also applicable to this specific case. The Austrian project: Vienna – Nickelsdorf The following basic concepts have been adopted: • • • • System performance will be increased by adopting the allowed speed limits according to the speed limit of the track and switches (the existing rule requires that a certain speed is valid form the location of the signal onwards). Availability respectively unavailability requirements are given in the customer requirements specifications (document Lastenheft-1-00 für das Zugbeeinflussungssystem ERTMS/ETCS Level 1 für die Strecke Wien – Hegyeshalom, 10.12.2001); The basic safety targets have been deduced form the carried out risk analysis (SIL4 is appropriate) - risk analysis (document 3BU 81400 3003 DUAPC, 12.11.2002). The risk analysis shows that ETCS targets are acceptable for the tolerable risk level deduced from accident statistics in Austria. The maintenance is and will be derived from the specifications and documents of the manufacturers of the interoperability components. The Belgian projects The TBL1+ system is considered as a “SIL 0” system. The aim of this project is to reduce the most important risks of at list 80 % of the existing status. For the lines to be equipped with the ETCS level 1, Infrabel conforms to the TSI, specifically to SUBSET-091. For each Project, the complete CENELEC life-cycle is followed, starting with generic safety cases with EC-verification of conformity, exporting hazards that originate from constituents. Every step of the process is closely monitored (according to EN50126, EN50128 and EN50129). There is a technical and operational HAZOP for the whole project as well as a FMEA (Failure Mode and Effect Analysis). A safety plan stipulates when and by whom safety tasks are performed. Every time there is a change, possibilities of export of hazards is considered. It is the intention of Infrabel to follow both V-cycles of Safety and Functionality in parallel. The whole process is supervised by an ISA. Pre-existing components are normally used. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 60/161 The safety cases issued by suppliers like Siemens, Alstom and Ansaldo are checked by ISA’s hired for that purpose by the same companies. For the Safety Approval of a line and its operation, the complete CENELEC cycle is follwed. Starting from safety cases of track-side constituents (e.g. RBCs, LEUs, Balises, track-circuits), generic ETCS Level 1 and Level 2 Safety Cases are developped. These safety cases are then taken as a basis for the L3 and L4 specific tracksiside system safety cases. The L3 and L4 Engineering and Programming Data Safety Cases are then added to the above safety cases,. After that, the L3 and L4 safety cases are made, including the operational rules. In parallel a safety case for the operating system EBP is made as well. The French project: LGV-Est The target operational availability of the ERTMS sub-system is set at 0.99973. The quantitative aspect to be demonstrated (connected to material breakdowns and transmission errors) is set at 0.99984. (Ref. Preliminary Safety File, 30 January 2004, F2SA891) Unavailability On board -6 Kernel (Vital functions) Kernel (non-Vital functions) BTM RTM MMI TIU Odometer < 10 -6 < 10 -8 < 10 -6 < 10 -7 < 10 -7 < 10 -7 < 10 Non-switchable Balise Switchable Balise LEU (Interoperable part) < 10 -7 < 10 -7 < 10 RBC < 10 Line -7 Trackside -6 Table 5 – Unavailability targets for Interoperability Constituents of the PEEE project The German project: Berlin-HalleLeipzig Performance and reliability requirements are specified in the operational specification´s registers (“Teillastenhefte”, [DB 28]) no. 6 and 7, RAMS onboard equipment and RAMS trackside. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 61/161 The Italian Projects The Rome-Naples HSL The maintenance is and will be derived from the specifications and documents of the manufacturers of the interoperability components.Rome-Naples HSL. The line was designed for a maximum line-speed of 300 km/h and a minimum headway of 5 minutes. The basic requirements for the line were given in RFI 38. The main availability parameter for the trackside subsystem was given as: Aintr_HW_SST = MTBF/(MTBF + MTTR) = 0,9999959 In full accordance with the requirements of SUBSET091, the overall safety target adopted for the implemented ERTMS/ETCS Level 2 system was: THR = 1*10-9 The maintenance policy is shortly described in document [RFI 21]. Both preventive and corrective maintenance is foreseen. The maintenance interventions have to be performed during the night, due to heavy diurnal traffic. The Torino-Novara HSL The line is designed to run to 300 km/h with minimum headway of 5 minutes. The main availability parameter for the trackside subsystem is [RFI 21]: Aintr_HW_SST = MTBF/(MTBF + MTTR) = 0,9999959 Regarding the safety target the project adopted the target specified in SUBSET091. Both preventive and corrective maintenance is foreseen (see RFI MO-MA-CO-TC-IN DT INES 002A “Tratta AV/AC Torino-Milano subtratta Torino-Novara Caratteristiche Infrastrutturali e Programma di Esercizio Complessivo della Sub-Tratta Torino – Novara” 25/11/2005). The maintenance interventions have to be performed during the night, due to heavy diurnal traffic. The Dutch projects Betuweroute A separate safety case was developed by ProRail for integration of Bev21 with Dutch Traffic Control system. At May 2007 it resuts available and ISA approved. ERTMS maintenance systems (LCS, etc) are part of Alstom delivery. Safety assessment is included in Alstom Bev21 Trackside Safety Case. Exported constraints are transferred to ProRail and incorporated in ProRail Safety Case (covering integration of the Dutch Traffic Control System, Bev21 and operation/maintenance). The compliance with contractual functional requirements is demonstrated in Alstom A15 Trackside Safety Case. For ETCS, a trackside Safety Plan is available as part of Consortiums A15 Trackside Safety Case, assessed by ISA (ADL). The Safety Plan addresses the V&V-process in conformity with CENELEC EN50126. For ETCS a trackside Quality Plan is available as part of Consortiums A15 Trackside Safety Case. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 62/161 The ProRail Project Plan is part of the ProRail Safety Case and has been assessed by an ISA (Praxis). The Scope of the supplier Consortium Alstom-Movares Hazard-log is the Bev21 system, which includes the ETCS system. The Hazard-log also includes measures to be exported to infra manager and train operator. The ProRail Hazard-log covers Bev21 integration with Traffic Control and operational processes. An extensive hazard transfer process has taken place between ProRail and Consortium Alstom-Movares to formally transfer hazards/measures between the two organisations. Amsterdam – Utrecht ProRail has to provide the National Railway Authority of the Minister of Transport and Water management with the complete set of safety cases to demonstrate that the line fulfils all the technical rules, regulations and safety conditions required for the domestic railway network. Figure 29 – Safety case structure for the Amsterdam-Utrecht project Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 63/161 To build the Overall Safety Case, several related safety cases were tob e prepared in accordance with the Cenelec EN50129 norm and the transfer of SRAC’s (Safety Related Application Conditions) from lower level safety case to higher level ones. The following Figure 29 shows the safety case structure for this project, where PSC stands for Project Safety Case, GASC stands for Generic Application Safety Case and SASC for Specific Application Safety Case. The next Figure 30 shows the responsibility of ProRail for the system integration and, at the end of the project, for the Overall Safety Case. Figure 30 – Scope of ProRail Integration and Acceptance plans HSL ZUID This (optional) information is not presently available. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 64/161 The Spanish projects The requirements of the Terms of Reference of the different ERTMS contracts refer to the general ERTMS specifications, in particular: • The ERTMS/ETCS equipment shall conform to the ERTMS/ETCS Class 1 System Requirements Specification of the UNISIG group, version 2.2.2, or, where applicable, the latest valid version in force during the construction of the project. It will also fulfil additional national functions specified by Infrastructure Managers and in force during the construction of the projects. • The GSM-R equipment shall conform to EIRENE Projects Requirements Specification vers. 13 and MORANE for ERTMS/ETCS Class 1 of UNISIG or, where applicable, the latest approved version available during the construction phase of the projects. It will also be equipped with the “hands free functionality”. • The trains will be equipped with a static recorder for recording and storing traffic conditions and other events. The specifications and functions of this recording equipment are left to the suplier’s responsibility.. This equipment has to be compatible with the information supplied by ERTMS and will comply with the corresponding ERTMS specifications In connection with the RAMS Policy, the following standards are applicable to the Spanish projects: • • • • EN 50126: “Railway applications – The specification and demonstration of reliability, availability, maintainability and safety (RAMS)”. EEIG 96S126: “ERTMS/ETCS RAMS Requirements Specification”. Vers. 6 EEIG 98S711: “ERTMS/ETCS RAMS Requirements” – Informative Part. Vers. 1. IEC 62278: “Railway applications. The specification and demonstration of of reliability, availability, maintainability and safety”. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 65/161 2 Phase 2 - System definition and application conditions 2.1 The mission profile of the system This section is intended to provide the main concepts of the line operation and maintenance: • • • • • • • • • • Operational rules regarding the target ERTMS system and its fall-back modes; The relationship with the applicable national rules; The rules for international traffic (e.g. border crossing); The rules and conditions for train/driver allowance in the line; The way-side signal typology; The voice communication via GSM-R and other fall-back systems; The management of emergency and degraded situations, The management of ordinary (preventive) and extraordinary (corrective) maintenance; The scope and the role of the line control centres. The V&V process to be followed for the validation and the approval of such rules together with the involved bodies and organisations. Austria-Italy project: Brenner Basis Tunnel project This line will be used for mixed traffic, passengers and freight trains. It is part of the TEN Corridor 1, and such it will be one of the most important link between Italy and the rest of the North Europe. At the end of the implementation, an average traffic of 140 trains per day is foreseen. A peak headway of 7.5 minutes is foreseen. The passenger trains (length up to 400 m) will have a maximum speed of 200 km/h, while the freight trains (length up to 800 m) run at a maximum speed of 100 km/h. The line interconnects just at the Innsbruck main station with the Austrian Network and the high speed line towards Munich, presently under construction, while at South (at the Fortezza station) it is connected with the Italian Network and with the high speed line towards Verona, presently under study. Austrian project: Vienna – Nickelsdorf The main concepts of operation and maintenance are based on the classical operation of the line; additions concerning the operation of the ETCS level 1 are introduced (opeartional rules, system description and operating conditions for drivers): DV ETCS Level 1 (operation rule; DV=Dienstvorschrift), DB 823 (description and operation manual) (DB = Dienstbehelf), DV S80 (on maintenance). Fallback modes, national emergency rules and rules for degraded situations are based on the existing rules for the PZB/LZB system (LZB is not actually used in this line). The national rules DV V2 and DV V3 for the national signalling systems will be applicable. Border crossing is not considered for the time being. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 66/161 The way-side signal typology: use of fixed standard signals, not changed in any way by ETCS. Maintenance, line control centre: no ETCS specific regulations; just national situation and rules. V&V process: ·standard process according to the manufacturer’s rules, process supervised by NoBo during validation phase and additional checks by NoBo. Work to be laid down in test reports. The Belgian projects The L3 and the L4 Lines The high speed lines L3 (Luik–German/Belgian border) and L4 (Antwerp–Dutch/Belgian border) are built to achieve a performance of up to 300 km/h and a 3-minute headway under continuous speed supervision provided by ERTMS/ETCS Level 2, supplemented by ERTMS/ETCS Level 1, which takes over in case the former experiences a failure while offering parallel operations in a mixed level application. The ETCS Level 1 lines Around the year 2000 the project started and received the name: EUROTBL. At that stage NMBS (SNCB) was one integrated railway company, i.e. Train Operating Company and Infrastructure Manager in one organisation. The basic concepts were: • • Use of ETCS-equipment in the trackside: Eurobalises and LEUs; New interface equipment in the rolling stock, which extracts “Packet 44” from ETCS-telegrams and hands the contents to the existing TBL-equipment in the rolling stock. From here the name EURO-TBL emerged – which is not to be used anymore. Currently the track-side implementation project is under management of Infrabel. Train Operating Company NMBS (SNCB) has two options under consideration for the train borne equipment: • • The solution described above; A “real” ETCS-on-board-equipment, complemented with an STM-TBL, which could deal with the “Packet 44” information. French project: LGV-Est This (optional) information is not presently available. German project: Berlin-HalleLeipzig Originally the line had mixed traffic of trains protected by PZB. ETCS Level 2 was installed in 2002/2003. Since 2006-06 the track is double-equipped with LZB/PZB and ETCS. PZB is also used as fall back mode in case of total ETCS failure. A dynamic transfer to LZB at ETCS failure is not implemented. Each train run starts in PZB mode, then being automatically transferred to ETCS L2 at defined trackside signal locations. In the moment 5 BR 101 locomotives are tested and allowed to run on the BHL track. Apart from ETCS and LZB they are equipped with both PZB and level 0. The only allowed way to come into the Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 67/161 protection of ETCS is to start in PZB mode, for regulatory and operational reasons, not for technical reasons. On the German network no train is allowed to be run without PZB or PZB/LZB. And up to the present there is no exemption for BHL. Technically any train equipped with ETCS could also start in level 0. The MFD displays the signal aspects transferred to the command variables ceiling speed (guidance/supervision speed), target speed and target distance. ETCS controlled shunting is not available on BHL. (National) Subsidiary Signals (Ersatzsignale) allow only 40km/h in the moment. The (national) Caution Signal aspect (Vorsichtssignal) is displayed to the driver by a special indication. The speed profile is controlled for 40 km/h. (Ptok/Bode, Signal & Draht, 2005-10, “Realisierung des ETCSStufe-2-Systems auf der deutschen Pilotstrecke“). One of the first tasks in the context of the development for BHL was the definition of the required operational processes, providing independency from the UNISIG specification as far as possible, considering the ETCS system as a ‘Black-box’. (Mense, Signal & Draht, 2003-01/02, “European Train Control System – Von der UNISIG-Spezifikation zur Pilotanwendung”). The main functions have been gathered in a customer specification "Lastenheft" LH, consisting of eight registers [DB 28] explaining common requirements, operational requirements, technical system requirements, system environment line, RAMS onboard equipment, RAMS trackside and operational scenarios. The operational specification has been transferred to "Use Cases", that should [Mense, S&D, 2003/01+02) use the UNISIGSRS functions. As a main basis for these requirements and the corresponding definition process the findings at a qualification test period on the test track, an operational analysis and various system tests have been taken. When the UNISIG SRS was revised and amended to release 2.2.2 the European spec became a basis for the technical implementation on BHL as well. Especially for the operational rules, the handling regulation for onboard and trackside equipment and the consistency of ETCS with the national rule book ("DB Konzernrichtlinie 408") was proved to conform to the national regular framework for PZB and LZB. Similarities and differences of ETCS in contrast to the national modes (LZB, PZB) have been structured and categorised. Common features of ETCS and LZB should be drafted equally to be handled in the same or a similar way. Well approved national principles should be generalised to become commonly valid. The ETCS pilot is an overlay system to the existing interlockings with a reduced functional range at the pilot system. [Leißner/Hansen/Beck/Kammel, Signal & Draht, “Erkenntnisse aus der Risikoanalyse für die ETCS-Pilotanwendung“, 2003-06). No international rules have been defined yet, since the track does not cross or touch any member states´ or European borders. At another phase (operational qualification) the staff (drivers and dispatchers) was trained. As a result of a national obligation in the allowance for qualification testing currently valid, drivers dispatchers and maintenance staff need to be trained on the specifics of the ETCS pilot to be licensed to operate on the BHL line. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 68/161 All national signals remained along the track. They are still used in the fall back mode and for trains protected in normal (non-ETCS) PZB- or LZB mode. In ETCS mode indication, discrepancy is accepted in the moment; wayside signals are not darkened in ETCS mode but still apparent to the train driver. The relation from Jüterbog to Halle was already intended to be equipped with GSM-R before ETCS had been specified, so that only some adaptations had to been done in this regard when ETCS was to be installed on the line. RBC-/LZB centres (Release 1.4) are located at Ludwigsfelde, Jüterbog, Wittenberg and Bitterfeld. The RBCs, LZB centres and existing interlockings are connected via the proprietary interface SZS/SAHARA. The Italian Projects The Rome-Naples HSL In the operative program [RFI 19] the main operative conditions are indicated. The maximum speed of the line is 300 Km/h. The minimum headway is 5 minutes, with all passenger trains running at the same speed (homo-kinetic train operation). To date, the line is mainly used for diurnal passenger traffic for medium and long distance journeys. Torino-Novara HSL In the operative program recalled above the main operative conditions are indicated. The maximum speed of the line is 300 Km/h with minimum headway of 5 minutes when all trains are running at the same speed. The line is mainly used for diurnal passenger traffic, medium and long distance journeys. The Dutch projects Betuweroute Basic information about the line is given above. Amsterdam – Utrecht The present system consists of eight Interlocking systems for the four tracks. For availability reasons the line is split up into four Interlockings for the two western tracks and four for the eastern tracks. The following Figure 31 gives an overview of the integrated track-side system. The supplier Bombardier has to interface with a lot of ProRail systems, the most important of which are: • • • Equipment of the traffic control; ATM network, communication network between the Central Interlocking computers and the Object Controllers in the equipment houses along the line; The object controllers and the outside equipment of ProRail. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 69/161 Figure 31 – Track-side architecture of the Amsterdam-Utrecht line HSL ZUID This (optional) information is not presently available. The Spanish projects The Figueras-Perpignan line is intended for mixed traffic between Spain and France. Traffic control will be located in Figueras and ERTMS rules will be applicable. Other rules have to be defined under the responsibility of the TP Ferro Consortium that has the concession of the line. All other high speed lines are reserved to passenger traffic only. As they are entirely inside the Spanish territory ERTMS and Spanish national rules are applicable. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 70/161 2.2 The system definition This section is intended to provide the following information: • • • The architectural layout of the trackside and train-borne sub-systems, with the help of one or more block-diagrams showing the main system components and their relationships. The identification and a short description of all the major constituents and interfaces of such layouts and their specific configurations. The list of the basic project documentation regarding the safety process for the overall system that his available (e.g. the description of the track-side and train-borne CC&S assemblies, the preliminary hazard analysis, the criteria for risk tolerability, the list of applicable technical Norms and Specifications (both European and National), the V&V plans, the safety plans, the quality plans, the available safety cases and the interoperability certificates for constituents, the plans for system acceptance. The Austria-Italy project: Brenner Basis Tunnel The functional and architectural requirements of the control-command and signalling subsystem is described in the following basic documents: • The document “Betriebe Regelungen-Regolamento di Esercizio” provides the basic principle for remote operation of the line from the main Control Centre in Innsbruck, and, in case of its unavailability, from the fall-back system to be located in Verona or in Bologna. Operation in both normal and degraded conditions is considered. Some new operational rules for taking into account the ETCS Lev. 2 systems are considered as well. • The documents “Systemarchitektur – Architettura di Sistema” and “Leit-und Sicherungstechnik Technischer Bericht – Sistemi di Controllo e Comando Relazione Tecnica” provide detailed architectural layouts of the Control-command and signalling sub-system, including all the security equipment (e.g. emergency power supply, access control, emergency radio..) required by higher level safety requirements given in the document . • The document “Telekommunikation Technischer Bericht – Telecomunicazioni Relazione Tecnica”, provides a detailed description of the telecommunication subsystem (GSM-R, TETRA, public GSM, fixed telephony, fiber optics newtwork and all the interconnected security equpment). The track side CCS system has been designed in details, on the basis of such requirement specifications. It includes: • • • • A centralised Control Centre to be located at Innsbruck main station supplemented by a reserve Centre to be located in Verona or Bologna; A couple of Solid State Interlocking (SSI): one SSI to be located at Innsbruck main station, connected to the only RBC located in the same building and onother SSI to be located at Fortezza station; A number of axle counters for train detection in the block sections along the line; A number of fixed balises for train location references; Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 71/161 • • • The extension of the Austrian GSM-R network to cover the whole line up to the CC&S sub-system border in fortezza; Harmonised Marker Boards at each block section extremity A number of train protection devices like Hot Box Detectors, Axle Load Monitors etc. The Austrian project: Vienna – Nickelsdorf For ETCS trackside system, the System and Safety requirements specification can be found in the document "ETCS Level 1 ÖBB Projektierungsanforderungen Streckeneinrichtungen", 3BU 81400 1005 BGAPC, 29.3.2005" and the “Lastenheft-1-00 für das Zugbeeinflussungssystem ERTMS/ETCS Level 1 für die Strecke Wien – Hegyeshalom, 10.12.2001”. The trackside balises are controlled by LEUs directly from the existing signal; the information is taken directly from the lamp current of the signal lamps. The main balise group consists of two balises per main signal. At each distance signal (infill), two in-fill balises are used. In the stations Euroloop is used as infill. The used interfaces are: the interface A and the national interface to the signals. Single Repositioning balises are used where necessary (not often). The train borne EVC is functionally independent from other equipment in the existing vehicle (locomotive type 1116). The existing Vehicle bus (MVB) is the interface between EVC and DMI. . Interface to the braking is via existing groups of components used for LZB. Further on interfaces are required for electric braking, switching off function for emergency brake (Notbremsüberbrückung), and driver related operations. Trackside Interoperability Constituents: constituents are all certified according to the TSI together with the relevant specifications valid at the start of the project. Certificates of Interoperability Components: • • • • LEUs (from Thales-Alcatel and Siemens): certificates by Arsenal are available. Eurobalise (Siemens): certificate by EBC is available. Euroloop (Siemens): certificate by Arsenal is available. Trainborne equipment: Certificate will be delivered by EBC for only one group of constituents. It is not yet available. The Belgian projects The L3 and the L4 HSL The high speed lines L3 (Luik – German/Belgian border) and L4 (Antwerp – Dutch/Belgian border) are built to achieve a performance of up to 300 km/h and a minimum headway of 3 minutes under continuous speed supervision provided by ERTMS/ETCS Level 2, supplemented by ERTMS/ETCS Level 1, which takes over in case the former experiences a failure while offering parallel operations in a mixed level application. The ETCS Level 1 lines The project started at around the year 2000 and received the name: EUROTBL. At that stage NMBS (SNCB) was one integrated railway company, i.e. Train Operating Company and Infrastructure Manager in one organisation. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 72/161 The basic concepts are: • • To use of ETCS-equipment in the trackside: Eurobalises and LEUs; New air-gap interface equipment in the rolling stock extracts the “Packet 44” from ETCS-telegrams and hands the contents to the existing TBL-equipment in the rolling stock. From here the name EURO-TBL emerged – which is not to be used anymore. Currently the track-side implementation project is under the management of Infrabel. The train operating company NMBS (SNCB) has two options under consideration for the train borne equipment: • • The solution described above; A “real” ETCS-on-board-equipment, complemented with an STM-TBL, which could deal with the “Packet 44” information. The French project: LGV-Est The Figure 32 below shows the overall architecture of track-side and train born systems foreseen for the PEEE project. TVM430 / KVB loaded + ETCS level 2 loaded + GSM-R loaded… FFFIS Balise KVB*, crocodile* All captors/transmittor s : CDV, BSP*…. Transmittors: Eurobalise noncommutable** FFFIS Transmittors: Eurobalise commutable** GSM-R Trackside** FIS FFFIS Other LEU** Spacing Function TVM430 LEU** Other RBC** RBC** Other SEI* SEI* Engaging Function Temporar Signals Manageme * SILAM/SICAM* Distance command station IT Systems Hubs * Equipment specific to TVM430 ** Equipment specific to ERTMS Equipment in-house, the other equipment is along the line In contact w Connection managemen Interoperabil Figure 32 – Overall Architecture ERTMS superimposed TVM 430/ SEI (ref. prel. safety file) A more detailed architectural overview of the track-side system provided by Ansaldo Signal is given in Figure 33 below. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 73/161 Figure 33 – Track-side architecture of the PEEE project The German project: Berlin-HalleLeipzig Onboard equipment To date, five traction units BR 101, one DB train control test car BR 707 and the Siemens VT 1.0/1.5 "Desiro" (basing on BR VT 642) have been equipped with ETCS functions. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 74/161 Figure 34 Train-sets of DBAG equiped with ERTMS/ETCS systems Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 75/161 The European Vital Computer (EVC) “ETCS L1/L2 Inboard Unit (OBU) ZUB710” installed in these test trains has been developed by Siemens. The generic ZUB710 core system was modified for ETCS L1 and L2 applications. Further equipment: Juridical Recording Unit (JRU) JR DSE 32 Messma, Driver Machine Interface (DMI) E2 Messma, radar, odometer pulse generator, balise antenna unit S21, radio basis system and a braking unit. Trackside 1200 balises S21 (Siemens), 4 RBCs, MMI and diagnostics computer, 20 BTS stations, marked by (signal) mast signs. Interlockings transmit the status messages in the yard to the RBCs for the MA generation. Train and RBC communicate via GSM-R, bidirectional. Leipzig/Halle-Jüterbog only: 100 points, 306 balise groups, 124 wayside signals, 258 gradients, 99 speed ranges; 7300 element attributes, 13.000 data entities. The Italian Projects The Rome-Naples HSL The document [RFI 21] is the oldest and the highest level document of the Italian high speed line Project. In this document, the high level system architecture is described (see Figure 35) Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 76/161 Central Supervisor Room Central Operative Room N O D O PCS PP PP Train PP Train N O D O PCS PP PP Train PP Train PCS PP PP Train PP Train Figure 35 – Architectural layout of the CCS sub-system for high speed lines The Torino –Novara HSL The system architecture is basically the same as in the Rome-Naples HSL outlined in Figure 35 above. This can be seen as a “Specific System Application”, while the Rome-Naples System can be considered the ERTMS/ETCS Level 2 “Generic Application” and the first Specific Application, according to the CENELEC definitions. The trackside subsystem (SST) consists of the following subsystems: • • • • Interlocking (GdV) based on the generic product NVP+GAT supplied by ASF and wayside objects supplied by Alstom; Train Separation System (DT) based on the generic product RBC and on the Eurobalise supplied by ASF; Hot Axel Box detector and braked wheels detector subsystem (RTB) supplied by BMB; TLC-LD e GSMR networks (communication systems) supplied by SIRTI. The Dutch projects Betuweroute The Betuweroute is conceived as a pure ERTMS Level 2 system without fall back solutions for train control and signalling and without dual signalling. Therefore only ERTMS equipped trains will be admitted. Amsterdam – Utrecht This (optional) information is not presently available. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 77/161 HSL ZUID The trackside architecture in a broader context is illustrated in Figure 36 below. Figure 36 – HSL ZUID Track-side Architecture The Spanish projects The system architecture follows closely the ERTMS definition according the TSIs that develop the EC interoperability Directives. The diagram below shows the main components and relationships in line with the Project definition. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 78/161 GSMR GSMR / EIRENE ASFA Conventional EVC DMI Interlocking Interlocking Interlocking RBC RBC RBC Command Command Command Figure 37 – Architectural layout of ETCS Lev. 2 and Lev. 1 lines in Spain Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 79/161 3 Phase 3 - Risk analysis 3.1 Hazard analysis and system level mitigations This section is intended to provide the following information about: • • • • • The process for carrying out the system hazard analysis, the higher level documents that were considered as higher level inputs and the documents produced as output. Which organisation(s) is (are) involved in this analysis? The results of the risk assessment: the mitigations introduced for the unacceptable risks (e.g. additional safety related requirements), the transposition of mitigations to other sub-systems (e.g. the security sub-system) or to the set of rules and procedures for operations and maintenance. The management of the Hazard Log alongside the whole System life cycle, with emphasis to the adopted measures (procedural and technical) and their effective implementation, the organisation in charge of maintaining the Hazard Log. How are the exported constraints communicated to the parties (like Train Operating Companies) involved? The relationship between the ETCS safety targets versus its reference mission profile and the actual case. Additional hazards, not included in the ERTMS list of hazards, that were eventually considered and the ways how they were handled. The Austria-Italy project: Brenner Basis Tunnel The Hazard Analysis has started with a document dealing with Trackside Tunnel Safety Concept including an high level Hazard Analysis with mitigation requirements for the tunnel safety and protection functions. The CCS Safety Plan, the functional requirements and the RAM requirements are based on the conclusions of this Hazard Analysis. The Austrian project: Vienna – Nickelsdorf The Risk Analysis document (document 3BU 81400 3003 DUAPC, 12.11.2002) was set up by a project independent collaborator (author) of one manufacturer, on behalf of the Railway Operator ÖBB. Main basis for the risk analysis (numerical target) has been the statistics of the total accidents on all lines of the railway operator. An independent safety assessor has assessed the Risk Analysis and found it appropriate. The outcome of the Risk analysis is that the specified ETCS safety level and the respective numerical target value for ETCS is, according to GAMAB/GAME, better than the existing safety level today. No specific considerations have been taken concerning procedures for operations and maintenance. No hazard log was set up. It seemed not to be required as ETCS is an overlay on the existing safe system and no further hazards (except the ETCS inherent ones can be introduced). Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 80/161 The Belgian projects For the TBL-application (usage of “Packet 44”), analyses have been taken place, which lead to the following technical solution: • Balises at each signal; • Advance (around 300 m) balises to give early signal-aspect-information. The advance balises constitute the “+” of the TBL1+ system. The advance balises and the respective locations are the results of thorough risks analyses. For the ETCS level 1 application, the HAZOP is nearly finished. The continuation of the HAZOP / risk analysis process is in progress. The French project: LGV-Est At the start of the project, before the contracting phase, a detailed risk analysis has been carried out. The risks are being monitored; a database is maintained in support of the process. Due to the “GAME” principal (dictating that no developments are allowed that will lead to a less safe operation) several studies have been conducted before contracting. This has lead to specific requirements, for example: • The train has to be stopped within 20 sec after loss of radio contact (thereby dictating the T_NV); • A double GSMR installation on the train is required mostly for RBC-to-RBC handover management. The German project: Berlin-Halle-Leipzig The risk analysis for ETCS BHL was performed to derive the targets for the safety requirements. That these, in turn, are met was demonstrated in the safety cases, supported by a hazard analysis (not to mix up with "hazard identification"), applied to apportion the safety requirements down to the subsystems and items of equipment. As a constraint the figures for random failure given for the onboard and trackside safety targets (TSI and SUBSET091) had to be adhered. Unfortunately an assertion to the acceptable amount of hazardous human error (i.e. collapse of procedures) was - and still is - missing for the analysis. This resulted in a wide scope of discretion for the apportionment and even interoperability criteria, so that the BHL risk analysis was strongly influenced by national specifics. In a primary step every hazard was allocated a THR on basis of an equal distribution of the tolerable risks. Iteratively this distribution was adapted during the design process. The degree of itemisation of the risk analysis was limited to the levels above the suppliers´ specific system designs. Hence the resulting operational and functional approach led to the hazard analysis of technical, human factors and procedures´ segments. The analysis was mainly performed by DB Systemtechnik, supported by (operational) data input from the railway authority. It was decided to use a functional hazard analysis approach, analogue the aviation process, subdivided into the sections system definition, Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 81/161 hazards´ identification, consequence analysis, risk acceptance analysis and safety requirements. The functions ‘plan train run’, ‘prepare train run’, ‘train run disposition’, ‘set up train run´s preconditions’, ‘accept train run’, ‘perform train run’ and ‘finish train run’ were defined and detailed down to a level where system specific (technical) design or operational procedures started. Relevance classifications for the ETCS pilot were added (directly relevant, indirectly relevant). At the hazards identification phase concrete hazards were assigned to each (detailed) function, assessed due to their safety relevance (three categories) and added to the hazard log. More than 70 hazards identified for the railway operation were filtered, finally 13 remained for ETCS. The task to determine the accepted level of the new ETCS risk was initially tried to be solved by a joint study of SNCF and DB, but this intention failed since the results differed up to a factor of 100 for the acceptable risk. Hence the accepted risk could only be determined preliminarily, solely based on national estimation: DB should work out an obliging position as operator responsible for the safe transport of people and goods. This should be evaluated and authorised by the EBA. As a reference the current risk for a passenger at a one hour train journey was taken, conforming [DB 22] and [DB 6]. At an ETCS failure a hazard may not only aim at passengers, but also track workers, neighbours, third parties, goods and environment, but it can be assumed that if sufficient safety were provided for passengers, it were implicitly provided for the others, too. The hazardous situations stored at the STABAG (“Statisik der Bahnbetriebsunfälle und gefährlichen Unregelmäßigkeiten”, statistic of railway operation accidents and hazardous irregularities) database were investigated for those causes that would also have been causing hazardous failure of the future ETCS system. The tolerable individual risk for ETCS passengers long distance traffic TIRFETCS-SPFV could be determined that way. 70% of this risk budget was equally distributed on the 13 ETCS hazards in a first approximation, 30% left for possible future extensions or changes in ETCS specifications or the BHL implementation. By the very simple assumption that every hazard would immediately open out to an accident the factor for external risk reduction could be set to ‘1’. This reduced the effort for the consequence analysis to zero. In case the suppliers´ hazard analysis would not be able to attest the achievement of the THRs, calculated from TIRF, a specific consequence analysis would have been performed. CENELEC EN50129 necessitates the coordination of hazards evolved from an operator´s hazard identification process and those coming from a supplier´s hazard or failure analysis. Neither a clear borderline between operational and technical hazards is stated in the standard, nor are any methods proposed for this purpose. For that reason a complex and extensive "mapping" of one hazards type towards the other was performed. Unfortunately the underlying system definitions and boundaries were not congruent so this approach did not fully succeed. Anyhow the achievement of qualitative and quantitative safety targets gained from the risk analysis - could be demonstrated. Parts of the "mapping" documentation become part of the safety case documentation. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 82/161 Several local specialities and certain operational frequencies of occurrence limit the validity of this risk analysis to the BHL line. As a consequence these specific features need to be controlled and monitored at revenue service and be adapted from time to time. As examples may be asserted: The handling of temporary speed restrictions has been specifically solved at BHL; the safety related context of a faulty input of such a restriction has not yet been fully captured. At a signal stop caused by any irregular situation it will be important for the safety of the system that the respective GSM-R message will not be delayed more than 5 sec in order to keep the calculated safety target. Hence the accordant GSM-R reliability needs to be assured. In case level crossings should be installed in future (for some reason), the RA/HA (risk/hazard analysis) needed to be recalculated, since no LC´s (and LC hazards) have been considered in the current RA/HA. The driver needs to be informed to switch off traction in case an emergency braking is released by the system, otherwise the safety target could be compromised. While computing the system hazard analysis some missing vital requirements not being stated in the UNISIG specifications yet had been identified. Change requests were issued. Therefore on BHL the incompleteness of the UNISIG specifications had to be compensated by several differences to the UNISIG specs. Additionally some considerable operational restrictions needed to be accepted to guarantee a sufficient level of safety. The Italian Projects The Rome-Naples HSL RFI issued a Preliminary Risk Analysis [RFI 37]. This document was intended as an input for the Saturno Consortium to start working on System Hazard Analysis. Such activity was then carried out, under the responsibility of the Saturno Consortium, by a Working Group including experts of the signalling system suppliers and with the technical support of RFI. The risk analysis started from the system functions foreseen for the ERTMS/ETCS Lev. 2 system and identifying the risk related to a missed or partial implementation of such functions. At the end of this activity the documents [RFI 119] and [RFI 120] were issued in version A. The documents were then reviewed prior to closing the project (version B). The deep experience of the work group participants and the working methodology has guaranteed the completeness of the analysis. Near the end of the project a final review of the analysis was performed. A new version of the same documents (version C) and a new document containing the collection of the Safety System Requirements [RFI 123] were issued The revealed hazards were inserted in the project Hazard-Log that has been kept alive during the whole duration of the project. Besides the two mentioned documents, System FTA and FMEA have been issued as well. The hazards needing operating procedures for mitigation have been evaluated by the competent structures of RFI that have issued the corresponding procedures. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 83/161 Finally the document [RFI 121] was issued, in which the system HFR (Hazardous Failure Rate), evaluated in accordance with the methodology indicated in the UNISIG SUBSET091, is finally reported. The Torino-Novara HSL The Turin-Novara system design has been largely based on the ERTMS/ETCS experience gained in the first ERTMS/ETCS Rome-Naples project. The same safety process has been put in place for hazard and risk analysis ans well as for the safety approval. The Dutch projects Betuweroute Scope of Consortium Alstom-Movares hazard log is the Bev21 system, which includes the ETCS system. The hazard log also includes measures to be exported to infra manager and train operator. ProRail hazard log covers Bev21 integration with Traffic Control and operational processes. An extensive hazard transfer process has taken place between ProRail and the Consortium to formally transfer hazards/measures between the two organisations. Amsterdam - Utrecht The line is built in accordance with the present design, installation and test constrains. At present, the risk analysis is focussed more on the introduction of new signaling equipment than on the installation of ERTMS. HSL ZUID The project organisation HSL Zuid has issued an Integral Safety Plan [HSL Zuid HAVL/567392, versie 10, 30 September 2004] that outlines the main safety concepts and allocates risks to be mitigated to each party in the Transportation System. The following organisations were involved in this analysis: • Bouwdienst Rijkswaterstaat • Projectdirectie HSL-Zuid • Predecessor of IVW; Railned Spoorwegveiligheid • NS Railinfrabeheer The responsibility for mitigating risks related to the superstructure (including CCS) has been allocated to the supplier (Infraspeed consortium, in which Siemens provides the interlocking and Alcatel provides the RBC). Therefore no risk allocation within the scope of Infraspeed has been carried out by the Project Organisation; the design responsibility in this respect lies with the Infraspeed consortium. The interfaces have been designed based on a jointly established description of the operational system. The Integral Safety Case for the traffic system consists of prove that the the hazards related to the interfaces are correctly mitigated. For the Transportation System as a whole an Integral Hazard Log is maintained by the project organisation HSL Zuid. (ref. HSL document #603704). Infraspeed maintains the Hazard Log for the HSL Assets (that form the Superstructure including the CCS sub-system) and for the HSL Activities (that mainly consists of Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 84/161 maintenance and renewal activities). This is part of the Availability Period Safety Case that has to be updated by the Infraspeed Consortium on a regular basis during the 25 years of the Infraprovider Concession. Infraspeed has performed a risk analysis (ref. “EPC System Hazard Analysis (SHA) IDE (SYS$TEX&AFF” # 000001) in which 13 top-hazards have been identified. Two of these top hazards were allocated to the trackside CCS: • H4 - Undetected erroneous movement authority/train protection resulting in derailment or collision, related to function/failure mode: • Undetected Erroneous SIG (Signalling sub-system) communication to/from train via balises (due to overspeed) • Undetected Erroneous or uncommanded SIG communication to train via fixed Balise or GSM-R (ETCS Level 2) • Undetected Erroneous communication between SIG interlocking and RBCs • Undetected Erroneous or uncommanded communication between Neighbour RBC and RBC (ETCS Level 1) • Erroneous track profile to RBC • Loss of earth • Creating of erroneous route map RBC • H5 - Undetected erroneous route protection, resulting in derailment or collision or fire, related to function/failure mode: • Undetected erroneous failure of trackside status monitoring for high water alarm • Undetected loss or failure of monitoring of trackside elements • Undetected Erroneous route setting • Undetected Erroneous or uncommanded Track occupancy (train integrity) • Undetected Erroneous communication between RAS (adjacent conventional track) interlocking and SIG (HSL) interlocking • Undetected loss of or erroneous information from SIG to AEM allows wrong escape doors to open when tunnels not train free • Loss of earth Other Top Hazards were partly allocated to the trackside CCS: • • • • • • • • • • H2 – Loss of free space profile due to: Movable Water Barrier Flood Doors Jet Fan. H3 – Loss of free space profile due to objects on track: Vehicles Vandalism Animals TPD catenary system Landslide/trees Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 85/161 • • • • • • • • • • Subsystem parts Maintenance Equipment Window penetration. H6 – Loss of incident mitigation Self Rescue Emergency Response Derailment containment. H7 – Failure to protect authorized staff (Staff/ Maintenance Personnel). H8 Undetected flooding of tunnel, cutting or open track H9 Undetected switch failures The Spanish projects The responsibility for the safety management during the design, manufacturing and integration has been left to the supplier. An ISA appointed by the customer (ADIF or RENFE) has made an assessment of the Safety Documentation brought by the supplier (Risk analysis, Safety case, Test Results, Exported Rules). The System Validation and Verification, under ADIF and RENFE test requirements, have been performed by independent laboratories and safety assessors. The Safety File compiling all the safety related documents, has been delivered to the Safety Directorate of Adif, and is the basis for the Safety Certificate that this body delivers to the National Safety Authority. The below gives the flowchart of the overall safety process in Spain. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 86/161 Beginning Contracts, regulations, directives, laws, safety requirements Safety planning Safety case System description and delimitation, safety requirements. Experience in operation Hazard and risks analysis Safety case Make changes in the system No Hazard Log Have safety aims been achieved? (Validation process) Yes Safety case conclusion Conclusion documentation End Figure 38 – Safety process in Spain Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 87/161 Safety is managed under the supervision of a suitable organisation, as shown in the figure below. TECHNICAL MANAGER OPERATING MANAGER HEAD SAFETY TECHNICIAN / CTC VERIFICATION ERTMS ENGINEERING CONTRACTS (INSTALLATION) CTC/ERTMS Design PROJECT MANAGER Tests/ERTMS CTC VALIDATION Figure 39 – Safety management organisation Once the system as a whole has been analysed, preliminary risk analysis is carried out, each manager dealing with reduction of their hazards. A Hazard Log is created with a record of all application hazards picked out, identified by techniques. These records are updated to include hazard monitoring, from their initial reduction to the final reduction. The following is specified for each hazard: • ID • Description • Severity, probability and risk initially assigned • Person responsible for risk reduction • Description of risk reduction • Severity and reduced probability and remaining risk • State: open, pending, closed The Hazard Log remains open throughout the life cycle of the project, it being possible to add new hazards and reopen closed hazards for repeated analysis if any conditions change. Hazards are closed by the Safety Manager once it is ensured that the remaining risk following reduction is tolerable according to the criteria established in CENELEC Standards. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 88/161 From the TOP hazards detected, top level safety requirements are determined and which are aimed at ensuring fulfilment of system safety functions. Figure 40 - Hazard Analysis Structure The preliminary risk analysis (ANNEX VII see RENFE 7) and the preliminary hazard analysis for the application (ANNEX VIII see RENFE 8) lead to the Safety Requirements list (ANNEX IX see RENFE 9). Safety Requirements The following list gives the top level safety requirements related to ERTMS: • • • • • • • The generic data generation process will ensure the right parameters for ERTMS data thanks to a SIL4 process. (Data entry) (REQ_APR_47) ENCE and ERTMS system connection (interface) shall ensure information is transmitted properly. (REQ_APR_48) In the event of a loss of communication between ERTMS and ENCE, the default state of each piece of information will ensure system safety. (REQ_APR_49) The interface between ERTMS system components shall ensure information is transmitted properly. (REQ_APR_50) Eurobalises will be installed on the line in accordance with diagrams of every 2 Km of track. (REQ_APR_51) The generic data generation process will ensure the right parameter setting for ERTMS data thanks to a SIL4 process. (REQ_APR_52) ERTMS L1/L2 system maintenance actions will be carried out in accordance with the adjustment and maintenance manual. (REQ_APR_53) Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 89/161 • • The ERTMS L1/L2 system will be installed in accordance with the manuals. (REQ_APR_54) The functionality supported by the ERTMS L1/L2 shall be SIL4 (REQ_APR_55) Safety documents generated are checked by the Safety and Engineering managers, considering technical aspects (design, manufacturing, installation, etc.) and aspects related to safety (CENELEC standards, safety manual, etc.). Any change or enlargement of the system will be subjected to checks. For acceptance of the system installed it is necessary that: • • • All activities are carried out throughout the life cycle of the application are checked, filling in the corresponding inspection reports. The validation phase is completed by the application of test protocols and justification that specified requirements have been observed, filling in the corresponding validation report. The Safety Case is checked by technical staff for the project, and approved by the senior safety manager at the construction company. 3.2 Specific issues This section is intended to provide information about the following specific issues: • • • • Local needs (e.g., existence of level crossings along the line), Specific judgement of risk (events that are considered “not dangerous” in one application might be judged differently in a different environment), The responsibilities allocated to ERTMS (for example, in a certain application ERTMS could be responsible of sending emergency messages to stop trains in case objects are detected on the tracks, while in other applications a physical protection of the infrastructure against intrusions could be considered sufficient to mitigate this kind of hazards). Allocation of responsibility to the driver, with respect to data-entry and display of information. The Austria-Italy project: Brenner Basis Tunnel The specificity of this line is due by its full extension within a double tube long tunnel. The safety mitigations in this case are somewhat different from the normal case. A particular point is due to the fact that, in case of serious accidents (e.g. fire on board) the trains must be allowed to run up to the next station, the only place where the possibility to escape to the other tube is existing for the passangers. This requires high availability of the controlcommand functions as well as specific redundant solutions fro telecomminications and remote control. The Austrian project: Vienna – Nickelsdorf As in the Austrian railway system there are many stopping points (e.g. protection signals – “Schutzsignale”, some standard signals) with too short (or even non-existing) overlap, these points are the sources of possible dangers. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 90/161 According to the ETCS safety principles that take into account inaccurate distance measurements (1) and the specified braking curves of the vehicle (2), calculated braking distances are always ending a certain distance before the scheduled stopping point. In the case of a signal showing a proceed aspect the scheduled stopping point can be reached by a continuous infill. In case of a stop aspect, this could have disadvantages in e.g. too short (in comparison with train length, that the rear passenger vehicle does not enter the station or platform completely) station lengths. Mostly the short stations or platforms cannot be lengthened due to lack of space. So the only method found for coping with this problem is the introduction of a certain release speed (in Austria 20km/h) even in case of 0 m overlap. Otherwise an appropriate operation of the traffic in the stations would not be possible. So in these cases the safety of ETCS could decrease due to the introduction of the release speed. As infill is only to be used to increase an MA, it could also be used in emergency cases to transmit a stop aspect to the train (consider that setting a signal immediately to a stop aspect is also possible in existing interlocking systems). In such an emergency case the effect could be useful or not (depending on the condition of train and reason), but if it is effective it could decrease a possible damage. Driver responsibility: Train data must be entered according to regulation “DV ETCS Level 1”. The Belgian projects See Chap. 3.1.7 above. The French project: LGV-Est This (optional) information is not presently available. The German project: Berlin-HalleLeipzig This (optional) information is not presently available. The Italian Projects The Rome-Naples HSL There are no particular specific issues in the ERTMS/ETCS system deployed in this line. Voice communication beween Control Centre and Drivers is performed via GSM-R Cab Radio installed on board. A redundant on-board GSM-R Data Terminal is used for tracktrain data exchange. The redundant nature of the radio is due for increased availability as well as for improving availability and response time during the RBC to RBC hand-over functions. The Cab Radio and the Data Terminals used on the Alstom trains as well as the Data Terminal of the Ansaldo trains have got Interoperability Certification by RINA. The Torino-Novara HSL Similar considerations as above apply. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 91/161 The Dutch projects Betuweroute This (optional) information is not presently available. Amsterdam - Utrecht This (optional) information is not presently available. HSL ZUID Specific issues including allocation of safety responsibilities to ERTMS are described with more details in the WP3 Report of this ERA Survey Project. Specific local needs arise from: • • • • Long tunnel (more than 7 km) that is build as a single tube in which the two tracks have been separated by a wall; the adjacent track is the safe haven in case of emergency evacuation; Risk of flooding of polders that lead to application of water barriers/flood doors; Risk of derailment on the bridge over the Hollands Diep to be mitigated by measurement of wind speed and (eventually) automated alarm calls; Driver responsibility, as far as data-entry procedures are concerned. The Spanish projects The Ministry of Transport has established the so-called National Functions, which are the packets and variables necessary to complete description of the national ERTMS functionality. These functions are deemed necessary by the gained experience on the operation of high Speed Lines. Nevertheless, the opinion of the experts is that National Functions should be avoided: if they are really necessary, they should be incorporated to TSIs, otherwise should be suppressed. These national packets and variables have to be dealt with by the ERTMS system or be addressed to other external systems, according to the values of the NID_C and NID_XUSER international variables. For authorising the commissioning of rolling stock, the latter shall comply with the above National Functions. National Infrastructure and Rolling Stock Rules introduce new risk control requirements, outlined in the Manufacturer’s Risk Analysis. National Functions, jointly defined by the Ministry of Transport and Adif are as follows: Ertms National Functions for Trainborne Equipment • • • • • FN-10: Emergency alert FN-20: Separate management of temporary speed restrictions according to level FN-23: Multiple revocation of LTV FN-24: Eurobalise default message management FN-26: Data input Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 92/161 • • • • • • • • • • • • FN-27: ERTMS management of independent ASFA equipment FN-35: Station stopping suggestion FN-36: Door control supervision FN-38: Tilting FN-71: Automatic train operation (ATO) FN-77: Degraded transition from Level 2 to Level 1 due to loss of contact with RBC when running on track with Level 1 equipment FN-40: Degraded transition from Level 1 to STM ASFA Level, running on track with ASFA equipment FN-79: Degraded transition from Level 2 to STM ASFA, running on track with ASFA equipment FN-122: Degraded transition from Level 1 to Level 0 + ASFA, running on track with ASFA equipment FN-123: Degraded transition from Level 2 to Level 0 + ASFA, running on track with ASFA equipment FN-121: Inhibition of available levels FN-124: Link response management Ertms National Functions for Level 1 track side equipment • • • • • • • • • • Tunnel management Viaduct and bridge management Neutral zones management Gauge changer management Managing passing trains in tunnels ERTMS/ETCS level transitions TSR management SR speed changes Balise default message management Detector management ERTMS introduction has meant the drafting and introduction of a series of rules into the General Traffic Regulations for using ERTMS, outlined in Chapter 24 of the Operating Manual (Annex no. 7 see RENFE 7). Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 93/161 4 Phase 4 - System requirements This section is intended to provide the following information about: • • • The process followed for defining the overall system requirements (including both the trackside and the train-borne sub-systems), based on the applicable ERTMS specifications and on the input documents produced in the previous phases, with consideration of the needs of a generic application case as well as of specific applications. The available documents produced for identification of functional (ERTMS operational modes, ERTMS options, fall-back modes, interaction with non ERTMS signalling systems like train detection, interlocking, telecoms, etc.), environmental, EMC and detailed RAMS requirements for the project. The documents produced for the project management, quality and safety assurance, version management, V&V, test and certification plans, pre-operation phases and formalities for the final system acceptance. 4.1 The Austria-Italy project: Brenner Basis Tunnel This phase of the basic project is still in still progress to date. The system design activity is closely followed by the BBT Infrastructure Manager and the RABBIT Consortium of NoBos in relation to the TSI conformity verification and to the fulfilment of the National Austrian-Italian regulations. 4.2 The Austrian project: Vienna – Nickelsdorf This Project is as well as a new generic application as well as the first specific application of ETCS in Austria. The used Subsets are according to V2.2.2. Basic document on Requirements Specifications on Data Engineering: • Lastenheft-1-00 für das Zugbeeinflussungssystem ERTMS/ETCS Level 1 für die Strecke Wien–Hegyeshalom, 10.12.2001.This documents specifies the Functional Requirements for the project. It is worth mentioning the specification of the optional ETCS requirements to be used in a mandatory way for the project (e.g. the use of Euroloop infill) as well as for trackside requirements as the trainside requirements. • ETCS Level 1 ÖBB Projektierungsanforderungen Streckeneinrichtungen, 3BU 81400 1005 BGAPC, 29.3.2005. Some of the considered issues are: • • • • • • • Braking distance, speed, gradients, infill, Positioning of balises, loops and LEUs Connections (interface C) with balises and loops Announcement of loops, Ids Coupling of signal information End of platform, Used level transistions Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 94/161 • Location reference points, danger points, speed optimization, national values, linking with link reaction and accuracy 4.3 The Belgian projects The track side ETCS-sub-system (Balises and LEUs) has to interface with: • • Existing relay interlocking systems; parallel inputs: via potential free contacts. Existing electronic interlocking systems (PLP); the LEU is adapted for the serial connection (TFM) which is available from the PLP-system. The integration of the ETCS track-side subsystem includes: • Connection to existing interlocking systems. • Placing balises in the track, according to the Engineering and Dimensioning rules. As far as the balise installation aspect is considered, Infrabel has defined specific rules, to take into account other equipment already in the track, like existing TBL-balises, crocodile (officially: “Memor”) etc. Therefore, Infrabel concluded that a Balise Group can only consist of a maximum of three balises, due to the sum of all constraints for the On-board equipment: see Chap. 2.1.7. 4.4 The French project: LGV-Est This (optional) information is not presently available. 4.5 The German project: Berlin-HalleLeipzig Several parties were participating in the requirements define process. The Deutsche Bahn Netz AG ("Technik und Beschaffung" and "DB Projektbau") acted as the contracting body. DB authors of railway rules and frameworks gave input from the operational points of view. Contributions to the requirements came from trackside operators as well as from traction and rolling stock operators. Further on GSM-R operators influenced requirements building to a certain extent. The national safety authority EBA (departments for technical systems and operational safety) shadowed the progress. BHL may best be titled to be a Specific Application. Some of the constituents may be also called Generic Applications since they can be used as modifiable or configurable platforms or subsystems for the deployment in further specific applications. 4.6 The Italian Projects The Rome-Naples HSL Starting from the high level UNISIG specifications listed in section, RFI has issued the following documents: • • • • Functional Requirements of the CCS ETCS Lev. 2 system System Requirements Annexes to the system requirements Requirements for the On Board System and its operational modes Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 95/161 Following the RFI specifications, the supplier issued the requirement documents: • Safety Requirements deriving from hazard analysis • Trackside Subsystem Requirements • On Board Subsystem Requirements Such functional requirements have been verified by the Saturno Consortium. Relevant verification reports have been issued at different stages. The lower level requirements have been traced against the corresponding upper level ones. The Torino-Novara HSL Similar considerations as above apply. 4.7 The Dutch projects Betuweroute The ProRail's project plan is part of ProRail safety case and has been assessed by ISA (Praxis). The Safety Plan for ETCS trackside is available as part of Consortiums A15 Trackside safety case. It was assessed by ISA (ADL). Safety plan addresses V&V-process in accordance with EN50126. The Quality Plan for ETCS trackside is available as part of Consortiums A15 Trackside safety case. Amsterdam - Utrecht Basic system requirements are given in the above Chap.0. HSL ZUID The system requirements activity is carried out under the full responsibility of the Infraspeed Consortium. 4.8 The Spanish projects All the technical regulations and standards applicable to the every different ERTMS projects are gathered in the Annex (see RENFE 1). Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 96/161 5 Phase 5 – Apportionment of system requirements This section is intended to provide the following information about: • • • The authority that monitored/assessed the suppliers work; The monitoring procedures adopted; The formal approving documents of this phase. 5.1 The Austria-Italy project: Brenner Basis Tunnel This activity is in progress by the system designers, under close control of the Infrastructure Manager and the NoBos in charge of conformity verification of TSI as well as of national regulations. 5.2 The Austrian project: Vienna – Nickelsdorf No special apportionments have been found necessary: just using the applicable UNISIG Subset documents. 5.3 The Belgian projects This (optional) information is not presently available. 5.4 The French project: LGV-Est This (optional) information is not presently available. 5.5 The German project: Berlin-HalleLeipzig The procedure for apportioning the system requirements to subsystems needed to be altered from the standard process for several reasons. The change of accountabilities for part systems and substructures among companies with differing economical interests led to uncertainty, since no arrangement still exists for the global accountability for the system functions. Another hurdle for the application of a standard apportionment process seemed to be the stringent adherence to the TSI and the UNISIG Subsets; obviously there had been mandatory EU requirements conflicting to habits, economic interest or even national regulation. Missing stability of the requirements - both national and European - contributed to timeconsuming iterations, caused by the unfamiliar complexity of accountabilities and processes. 5.6 The Italian Projects The Rome-Naples HSL The apportionment of the higher level requirements of the trackside system was done by RFI together with the suppliers, by issuing the specification of the on board ERTMS/ETCS Lev. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 97/161 2 sub-system: “Volume 3” [RFI 124] and the specification of the trackside ERTMS/ETCS Lev. 2 sub-system “Volume 2” [RFI 122]. For the trackside specification, the structure of “Volume 2” was split into different subvolumes, so achieving a further apportionment of the trackside system requirement The different sub-volumes are: • Track-side system: – RAMS Requirements • Track-side system: Train separation • Track-side system: RBC sub-system • Track-side system: RBC sub-system - Interface RBC-IXL • Track-side system: RBC sub-system - Interfaces – Technical Description • Track-side system: Eurobalise Sub-system • Track-side system: RTB Sub-system • Requirements Specifications for the Interlocking Sub-system • TLC/LD Telecom Sub-system • TLC/GSM-R Sub-system The requirements apportionment has been followed by the responsible of the PATC department, with the assistance of the responsible of the structure “Specificazione Requisiti di Sistema e Applicazione Sistemi ATC”, by means of monitoring and technical meetings. All the Meeting Minutes became official Project documents. The Torino-Novara HSL Similar considerations as above apply. For the trackside specification, the structure of “Volume 2” was split into different subvolumes. This realized explicitly an apportionment of trackside system requirement The different sub-volumes are: • • • • • • Specificazione di Sistema Sottosistema Distanziamento Treni Sottosistema Interlocking Interconnessioni Sottosistema RTB Sottosistema TLC/LD. 5.7 The Dutch projects Betuweroute This (optional) information is not presently available. Amsterdam - Utrecht The apportionament of system requirements is carried out under the full responsibility of the System Provider, under high level indications of the Infrastructer Manager. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 98/161 HSL ZUID The activity regarding apportionment of requirements is carried out under the full responsibility of the Infraspeed Consortium. 5.8 The Spanish projects As exposed in point 1.2.8.1, the Infrastructure Manager ADIF plays a double role in the safety monitoring process: • • • • • Adif (construction departments) is the author of the Terms of Reference for the supply and installation of safety equipment, including ERTMS for each line section, The corresponding contracts have been each awarded to an unique supplier (usually a consortium), who has been given the responsibility for the design, manufacturing and installation, as well as the safety management and the elaboration of the safety case of the whole delivery. The supplier has developed and implemented all the needed equipment under the assessment of an ISA appointed by the supplier himself. This task has been fully performed and validated by the suppliers. ADIF (Safety Directorate) - at the request of Adif (construction departments) - does the Certification of the Compliance with safety conditions required for the railway operation (Safety Certificate). In this task it is assited by a Technical Committee and by an appointed ISA. ADIF (Construction Department) applies to the National Safety Authority – the General Directorate of Railways within the Ministry of Transport – to get the authorization for placing in service of ERTMS. This application has to be accompanied by the Safety Certificate and the supporting documents relative to the compliance with the implementation of the testing plan at the request of Adif or, where appropriate, the Railways General Directorate. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 99/161 6 Phase 6 – Design and implementation This section is intended to provide the following information about: • • • The authority that monitored/assessed the suppliers work; The monitoring procedures adopted; The formal approving documents of the phase. 6.1 The Austria-Italy project: Brenner Basis Tunnel This section is not applicable to the present stage of the Project. 6.2 The Austrian project: Vienna – Nickelsdorf The document "Requirements Specifications on Data Engineering" (ETCS Level 1 ÖBB Projektierungsanforderungen Streckeneinrichtungen, 3BU 81400 1005 BGAPC, 29.3.2005) has been produced as common work between Railway Operator and the Manufacturers. The Manufacturer specific procedures for design have been assessed by the NoBo. The Safety Cases have been approved by an Independent Safety Assessor and after by the NoBo. 6.3 The Belgian projects This (optional) information is not presently available. 6.4 The French project: LGV-Est This (optional) information is not presently available. 6.5 The German project: Berlin-Halle-Leipzig This (optional) information is not presently available. 6.6 The Italian Projects The Rome-Naples HSL The design and implementation phase was monitored by ITALFER (Engineering Company owned by RFI) and the relevant RFI Departments. The supplier and the relevant RFI structure that assessed each subsystem/product from both the functional and the safety point of view are indicated in Table 6 and in Table 7 below. Subsystem Supplier RFI Structure in charge of functional RFI Structure in charge of safety Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 100/161 SST SSB Saturno Consortium AF SDT GdV/NVP+GAT RTB AF ASF BMB assessment PATC - SRS PATC - OSSB /CESIFER PATC - OSST PACS/SS - I SS - TB assessment CC CC CC CC CC Table 6 - Assessment of sub-systems AF stands for Alstom Ferroviaria, ASF for Ansaldo Segnalamento Ferroviario, BMB fore Bombardier. Product RBC EVC NVP Wayside objects Supplier AF AF ASF AF RFI Structure in charge of functional assessment PATC- PTI PATC- PTI PACS SS – TB RFI Structure in charge of safety assessment CC CC CC CC Table 7 - Assessment of products Alstom Ferroviaria provided the main part of the track-side system including the RBC as well as the on-board system on the first set of trains enabled for the revenue service. Ansaldo provided the Interlocking system and the balises (mostly of the fixed type), with some Encoders for some controlled balises (informing the train about the status of the Hot Box Detectors). The project has been monitored, at system level, by the responsible of department PATC by means of monitoring and technical meetings. During the technical meetings the responsible of PATC has been assisted in his work by the responsible structures that managed the specific technical issue. All the Meeting Minutes became official Project documents. The CENELEC norms have been used as reference for this activity. The assessment activity consisted in technical meetings, audits, tests witnessing and review of documents. The trackside subsystem (SST) consists of the following subsystems: • Interlocking (GdV) based on the generic product NVP+GAT supplied by ASF and wayside objects supplied by Alstom; • Train Separation System (DT) (based on the generic product RBC supplied by AF and on the Eurobalise supplied by ASF); • Hot Axel Box detector and braked wheels detector subsystem (RTB) supplied by BMB; • TLC-LD e GSMR networks (communication systems)supplied by SIRTI. In Figure 41 below the trackside system architecture is shown. Each dotted frame contains the set of the products included in a Generic Application (GdV, DT and SST). Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 101/161 Figure 41 – Block diagram of the trackside subsystem The System is composed of: • A Central Operating Room (PCS) allocated to the overall line control and Peripheral Rooms (PPF) distribuited on the line; • The PPF’s control the wayside objects and are linked to PCS and to the neighbouring PPF’s (next and previous) with which exchanged vital data. • The Supervisor system (SCC AV) is linked with signalling system (IS) both with PPF and PCS. This system was considered out of the trackside signaling system during the safety approval process. • TLC-LD network is a ring built in optical fibres that connects all the PPF’s and the PCS. • The LF system is the power supplier for all the devices. The communication system between trackside and on-board is indicated with TT in the figure. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 102/161 The Torino-Novara HSL The same organisation for products supplying and system assessment as shown in the Rome-Naples case was put in place for this line, with the only difference that the most part of the track-side system including RBC and Interlocking were provided by Ansaldo. The high speed trains firstly used for the revenue service were provided by Alstom while Ansaldo trains are still under pre-operational service. In Figure 42 below, the implemented track-side system architecture is shown. Each dotted frame contains the set of the products included in a Generic Application (GdV, DT and SST). Figure 42 – Block diagram of trackside subsystem The System is composed of: • • • A Central Operating Room (PCS) allocated to the overall line control and Peripheral Rooms (PPF) distribuited on the line; The PPF’s control the wayside objects and are linked to PCS and to the neighbouring PPF’s (next and previous) with which exchanged vital data. The Supervisor system (SCC AV) is linked with signalling system (IS) both with PPF and PCS. This system was considered out of the trackside signaling system during the safety approval process. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 103/161 • TLC-LD network is a ring built in optical fibres that connects all the PPF’s and the PCS. • The LF system is the power supplier of all devices. The communication system between trackside and on-board is indicated with TT in the figure. 6.7 The Dutch projects Betuweroute This (optional) information is not presently available. Amsterdam - Utrecht The design and implementation activity is carried out under the full responsibility of the System Provider. The line equipment does not completely fulfill the CCS TSI. HSL ZUID The design and implementation activity is carried out under the full responsibility of the Infraspeed Consortium. 6.8 The Spanish projects The comment under Chapter 5.8 applies. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 104/161 7 Phase 7 – Manufacturing This section is intended to provide the following information: • • • The authority that monitored/assessed the suppliers work; The monitoring procedures adopted; The formal approving documents of this phase. 7.1 The Austria-Italy project: Brenner Basis Tunnel This section is not applicable to the present stage of the Project. 7.2 The Austrian project: Vienna – Nickelsdorf The Interoperability Constituents have been manufactured according to the certified process which has been assessed by the NoBo responsible for the component. The track-side installation is covered in the next chapter on phase 8. For the locomotive, the NoBo assessed the process of the equipment of the locomotive with the interoperability component (in this project the group of components). 7.3 The Belgian projects This (optional) information is not presently available. 7.4 The French project: LGV-Est This (optional) information is not presently available. 7.5 The German project: Berlin-HalleLeipzig For the test trains momentarily running on the BHL line, Siemens AG was charged to develop/deploy the onboard equipment. Alcatel SEL AG (now: Thales) developed the trackside equipment. Bombardier Transportation carried out the adaptation of the machine-technical facilities (train control computer and machine-technical display). Deuta performed the adaptation of the recording equipment (DSK) and the displays for the train protection systems. 7.6 The Italian Projects The Rome-Naples HSL The Saturno Consortium was the supplier responsible for the manufacturing and installation phases. ITALFER has been the controller. The Saturno Consortium issued a guideline for classifying against the criticality the devices. Furthermore the Consortium issued procedures/guidelines for managing the manufacturing, the assembly, the installation and the acceptance phases of the most critical devices. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 105/161 The ITALFER verification phases, the formal documents to be issued (“Piano Controllo Qualità” - PCQ) and their contents have been defined in these procedures. ITALFER has verified each single document that classified the devices. ITALFER has then witnessed the test phases on a sample basis. The main documents issued are “Piano Controllo Qualità” (Quality Control Plan). In addition to all PCQ’s, for both the supply and the installation phases, the following documents were issued: • • “Elenco EPC/PCQ di fornitura - A104.00.CI1.CQ.IT.00.0.0.052 rev I” (Supply) “Elenco PCQ di installazione - A104.00.CI1.CQ.IT.00.0.0.053 rev R” (Installation) The Torino-Novara HSL A similar manufacturing control process mainly managed by ITALFER, as for RomeNaples, was put in place. 7.7 The Dutch projects Betuweroute This (optional) information is not presently available. Amsterdam - Utrecht The manufacturing activity is carried out under the full responsibility of the System Provider, in accordance with the ProRail general regulations. HSL ZUID The manufacturing activity is carried out under the full responsibility of the Infraspeed Consortium. 7.8 The Spanish projects This task has been fully performed and validated by the suppliers. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 106/161 8 Phase 8 – Installation This section is intended to provide the following information: • • • The authority that monitored/assessed the suppliers work; The monitoring procedures adopted; The formal approving documents of this phase. 8.1 The Austria-Italy project: Brenner Basis Tunnel This section is not applicable to the present stage of the Project. 8.2 The Austrian project: Vienna – Nickelsdorf The installation of the balises was performed partly by the Railway Operator and partly by the manufacturers. The NoBo assessed the quality of installation of balises by assessing each balise at the main signals and samples at the other locations outside of railway stations. This corresponds to a sort of “Module F” assessment of the installation, as the NoBo was not involved in the project from the very beginning. The installation of the loops was performed partly by the Railway Operator and partly by the manufacturer. All Loops have been assessed individually by the NoBo. This was due partly resulting because Module F for the certification of the loops has been used, partly because the installation of the loops presented problems in the beginning and the NoBo was not involved in the project from the very beginning. The results and component installations assessed will be contained in the NoBo report. 8.3 The Belgian projects This (optional) information is not presently available. 8.4 The French project: LGV-Est This (optional) information is not presently available. 8.5 The German project: Berlin-Halle-Leipzig Apart from the operational framework for the parallel handling of all three modes (ETCS, LZB and PZB) a framework for the installation, acceptance procedure and maintenance has been set up. The installation was split into several steps, called "ETCS releases". The first release only served test purposes and was implemented in 2001-07. Experience was gathered with regard to the GSM-R infrastructure, odometry and general UNISIG procedures. Until 2003-07 further tree releases followed, when qualification tests were started in 200312. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 107/161 At that time the RBCs were connected to the interlockings and on-board CC infrastructure was integrated. The track was equipped with the balises. Further releases und upgrades followed. 8.6 The Italian Projects The Rome-Naples HSL See above. The Torino-Novara HSL See above. 8.7 The Dutch projects Betuweroute This (optional) information is not presently available. Amsterdam - Utrecht The installation activity is carried out under the full responsibility of the System Provider, in accordance with the ProRail general regulations. HSL ZUID The installation activity is carried out under the full responsibility of the Infraspeed Consortium. 8.8 The Spanish projects This task has been fully performed and validated by the suppliers. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 108/161 9 Phase 9 – System validation This section is intended to provide the following information: • • • The authority that monitored/assessed the suppliers work; The monitoring procedures adopted; The formal approving documents of this phase. 9.1 The Austria-Italy project: Brenner Basis Tunnel This section is not applicable to the present stage of the Project. 9.2 The Austrian project: Vienna – Nickelsdorf Safety of the existing operational line is not influenced (approval of LEUs by safety authority) by the ETCS equipment. ISA report and safety cases for project specific design from manufacturers are available. Detailed technical validation (content of each telegram) performed by the NoBo. Safety Cases were delivered by suppliers for the project; V&V plans, quality plans are referenced therein. Final Safety Cases for ETCS train borne equipment are not yet available. The conventional part is nationally approved in 1116 type locomotives, enhanced by ETCS equipment by Siemens, whose certification work is ongoing. Compliance verifications with the functional and safety requirements have been carried out by NoBo. The physical installation of each LEU, balise and loop along the line has also been checked by the NoBo (see Chapter 8.2 above). Assessment by the NoBo of the procedures carried out by the manufacturers. A diverse way of testing all data (content of each telegram) was chosen and done by the NoBo itself but not with safety responsibility. The NoBo Report on testing and validation of the telegram data was basis for approval of running operational tests with trains (locomotive double manned, no passenger transport). Because the approbatory tests have not fully been carried out up to now, the NoBo certificate is not available yet. For interoperability constituents and application related design EN50126 conform within the manufacturers. Availability of Certificates for track-side Interoperability Constituents: • Eurobalise issued by EBC in 2004 • Euroloop issued by Arsenal Research in 2004 + 2005 • LEU issued by Arsenal Research for both suppliers in 2004 • Trainside not available now, foreseen from EBC Some sorts of cross tests have been carried out: Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 109/161 • • Runs of the DB ETCS test car (with Siemens software for the EVC) have been carried out successfully. Test runs with a Hungarian vehicle from MAV (EVC level 1 without infill, produced by Alcatel) were successful and showed the necessity of the infill function within the train-borne equipment. 9.3 The Belgian projects For the Safety Approval of a line and its operation, the complete CENELEC cycle is applied. Starting from safety cases for constituents as RBCs, LEUs, Balises and trackcircuits, generic application safety cases are made. These safety cases are then taken as a basis for the L3 and the L4 and level 1 on the conventional network specific application safety cases. The L3 and L4 Engineering and Programming data safety cases are added to these safety cases. After that, the L3 and L4 safety cases are made, including the operational rules. In parallel a safety case for the operating system EBP is made. The L3 and the L4 HSL A complete RAMS analyses has been performed. The ETCS Level 1 lines KEMA Rail Transport Certification is the ISA (Independent Safety Assessor) for this project and the Notified Body for the track-side assembly. The contracting entity is: Infrabel, the Infrastructure Manager of the Belgian railway network. The lifecycle of CENELEC is used as framework for the ISA activities. The module SG is used for the EC conformity certification. KEMA Rail Transport Certification reports to Infrabel, where Infrabel reports to the Ministry. At important milestones, KEMA Rail Transport Certification presents its results to Infrabel and to the Ministry in joint meetings. The supplier is: Siemens for balises, LEUs and for the engineering data, which is required to program balises and LEUs. The following tests were carried out: • Firstly regarding EUROTBL2; • Secondly regarding TBL1+ (tests are still going on); • Tests regarding ETCS Lev. 1 are still to be executed. KEMA Rail Transport Certification (as ISA+NoBo) monitors the supplier’s tests and the tests executed by Infrabel. There have been some compatibility problems between the train-borne KVB-system (in Thalys trains) and Eurobalises. This problem is well known at European level and still under debate within UNISIG. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 110/161 Derogation is foreseen to deal with the KVB vs. Eurobalise compatibility problem, but not formally defined yet. Also the integration with LEU’s and existing interlocking systems are not flawless, partly related to EMC and not precisely defined signal levels. The safety cases of suppliers as Siemens, Alstom and Ansaldo are checked by ISA’s hired for that purpose by the same companies. 9.4 The French project: LGV-Est The system validation has been done via a step by step process by the NSA. The safety case has been produced by SNCF and evaluated/checked by RFF. At the moment this report was drafted the safety case was not completed yet. In order to obtain approval of the safety case tests under real operational conditions, without real passengers, is necessary in order to have a new certificate. This also requires proof of the availability of the system. The exact procedure is being discussed with the NSA. 9.5 The German project: Berlin-HalleLeipzig The Eisenbahn-Bundesamt (EBA) was monitoring the whole process from the beginning. 9.6 The Italian Projects The Rome-Naples HSL The suppliers have performed the validation activities regarding the Generic Products, the Generic Application and the first Specific Application. The following Safety Cases were issued by the suppliers at the end of the validation activities: • Safety Case for the Trackside Sub-system (Generic and Specific Application); • Safety Case for the Train Separation Sub-system (Generic and Specific Application); • Safety Case for the On Board Sub-system. • Safety Case for the Interlocking Sub-system; The assessment of Generic Application / First Specific Application was performed on the Labico–S. Giovanni line stretch (km. 31+933 – km. 115+841) that is representative of all the characteristics and the equipment of the entire line. On the line stretch Labico–S. Giovanni all the ERTMS/ETCS lev. 2 functionalities have been tested with a high speed train especially equipped for functional test and verification purposes. In addition to the suppliers on field validation activities, RFI has performed some field test sessions to assess the correct implementation of the signalling system functionalities [see documents listed in the annex]. The RFI trackside assessment activities are described in the document [RFI 107]. For the first specific application, a Technical Committee of RFI verified, by means of on field test, the correctness of installation, assembly and system configuration. The activities of the Technical Committee were performed in compliance with the applicable RFI directives [see the annex]. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 111/161 A functional assessment of the Trains Separation System (SDT- both trackside and on board functions) was carried out. The assessment borders are highlighted by means of a grey box in Figure 43 below. TLC SCC Conventional Line NVP Information Points (Eurobalises) RBC/ RTB SDT SSB Figure 43 - Borders of the Train Separation System - SDT For the validation and the assessment of the field tests the general contractor has issued some operational rules to ensure the overall safety during the tests. A general contractor on board people (IBT) radio linked with a trackside safety responsible (RPT) has been foreseen. During the test the pertinent suppliers personnel have controlled on site all the interlockings and the RBCs. In the interconnection test the RFI personnel have ensured the safety of the trains on the conventional line momentarily closing the commercial services during the tests. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 112/161 After the assessment of the products, the generic and the first specific application, on 2005 September the 12th, RFI proceeded to a preliminary acceptance (see phase 10) of the line to start the approbatory period in compliance with the procedure [RFI 35]. During this period, RFI assessed the following issues: • Operational rules, especially developed for ERTMS/ETCS Lev. 2 • Rolling stock and infrastructure functionalities and their interfaces • Organisational model for the commercial operation of the line • Infrastructure management (effectiveness of the organisation and diagnostic devices) • Potentiality of the line revenue service. Furthermore the train Operator TRENITALIA has carried out the assessment of: • Adequacy of service management; • Effectiveness of the training courses for the operative personnel; • Effectiveness of the rolling stock maintenance. During the approbatory period suppliers and RFI personnel have carried out all the tests together. A RFI test manager has been performed the test run on train borne together with IBT. During the test trains and RBC data have been collected by means of specific tools (Canapè for the on board data and LDR for RBC). A fine tuning on the products and configurations has been carried out after the completion of the tests. The results of the approbatory period tests were made available on monthly reports [RFI 103]. The Torino-Novara HSL/HCL The suppliers have performed the validation activities regarding the Generic Products, Generic and Specific Applications. The Safety Cases issued by the suppliers at the end of the validation activities have been: • Trackside Subsystem; • Train Separation Subsystem; • Interlocking Subsystem; • On Board Subsystem. • System integration of Alstom On-bBoard sub-system versus Ansaldo Trackside subsystem. In addition to the field validation activities carried out by the suppliers, RFI performed some field test sessions to assess the implementation of the signalling system functionalities. For the specific application, a technical commission has verified, by means of field test, the correctness of the installation, the assembly and the system configuration. A functional assessment of the overall Train Separation System (trackside and on board), as described in the Rome-Naples line documents, has been carried out. A similar test management process, as the one adopted for the Rome – Naples line has been put in place also on the Turin-Novara line for validation and assessment of the field tests. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 113/161 After the assessment of the products, generic and specific applications, on 2005 november the 28th RFI gave a preliminary acceptance of the line, enabling the start the approbatory period. The results of the approbatory period tests were made available on monthly reports. 9.7 The Dutch projects Betuweroute The BR A15 Trackside Safety Case according to EN50126, including ISA report (ADL), for Alstom-Movares Bev21- A15v3.4 configuration (ERTMS Lev. 2 system), is available. A separate Safety Case was developed by Prorail for integration of Bev21 with Dutch Traffic Control system and results to date approved by ISA (Praxis). The safety assessment included in Alstom Bev21 Trackside Safety Case exported constraints transferred to ProRail and incorporated in the ProRail Safety Case (covering integration the Dutch Traffic Control System, Bev21 and operation/maintenance). The ERTMS maintenance system (LCS, etc) was part of the Alstom delivery. The compliance with contractual functional requirements is demonstrated in Alstom A15 Trackside safety case. For ETCS a trackside Safety Plan is available as part of Consortiums A15 Trackside safety case, assessed by ISA (ADL). The safety plan addresses the V&Vprocess in conformity with EN50126. For ETCS a trackside Quality Plan is available as part of Consortiums A15 Trackside safety case. The ProRail project plan is part of the ProRail safety case and has been assessed by an ISA (Praxis). The Scope of the supplier Consortium Alstom-Movares hazard log is the Bev21 system, which includes the ETCS system. The hazard log also includes measures to be exported to infra manager and train operator. The ProRail Hazard Log covers Bev21 integration with Traffic Control and operational processes. An extensive hazard transfer process has taken place between ProRail and Consortium Alstom-Movares to formally transfer hazards/measures between the two organisations. After the NoBo statements and the safety cases for the trackside and train borne subsystem have been obtained, as well as permission for test exploitation has been granted, a technical and operational hazard analyses is performed for the integrated trackside and train borne systems. On this basis a specific test plan is made on the basis of a default track train integration testplan. This can lead to a “verklaring van geen bezwaar” (a declaration of no objection) by IVW. After a subsequent system qualification test the “inzetcertificaat” (operation certificate) can be issued. These tests include testing trainborne and trackside sub-systems for 10.000 km, absolved by a train of a specific type. The results from monitoring are needed to finalise the trackside as well as the train borne CENELEC safety cases. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 114/161 Amsterdam- Utrecht- HSL The line is built in accordance with the CENELEC procedures, but the line covers the rules, regulations and safety requirements of a domestic line. By the end of 2009, the line will be equipped with dual signaling ERTMS level STM / 2. ProRail has to provide the National Railway Authority of the Minister of Transport and Water management with the complete set of safety cases to demonstrate that the line fulfils all the technical rules, regulations and safety conditions required for the domestic railway network. All the safety cases are assessed by an ISA. HSL ZUID The authority that monitored the work of the CCS sub-system was the supplier itself (i.e. the Infraspeed Consortium). The risk for the performance of the systems is part of the Design-Build-Finance-andMaintain Contract. This is taken into account by means of the Performance Payment Regime: payments will be done by the State of the Netherlands during the 25 years of the contract in accordance with the availability performance of the systems. 9.8 The Spanish projects Validation&Verification guidelines The validation and verification process is evolving according to the experiences acquired in the implementation of the different ERTMS implementations. Up to now, the V&V process is performed following closely the prescriptions of the Railway Sector Act 39/2003 and the Ministry Order FOM 233/2006, under the survey of the Ministry of Transport. In particular, this Order develops the following concepts, as a transposition of the EC Directives: • • • Technical Specifications for Homologation (Especificaciones Técnicas de Homologación, ETH), that compile the Safety requirements, the essential requirements, the functional requirements including interoperability, maintenance requirements, and evaluation modules for the assessments of conformity and fitness for use. This ETH should be completed and published by August 2008. In the meantime, the STI and the National standards are applicable. Validation procedures, to assess the conformity of constituents and subsystems with the ETH CE Verification procedures, how the Notified Bodies certify the compliance with the Interoperability Directives In accordance with the above rules, the Validation and Verification processes can be summarized as follows: Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 115/161 Validation CE Verification Certification Entity (Accredited by ENAC) Notified Body ETH STI Object RAMS, Environment, Health Interoperability Scope National European Community Responsible body Applicable specifications Validation procedure The procedures and supporting documents for ERTMS trackside and on board equipment is very similar. In both cases the Declaration of Conformity is prepared by the supplier who is also the applicant versus the Certification Body. The Authorization for Operation is issued by ADIF. The figure below summarizes the procedure: Validation CE Verification Issued by a Certification Entity Issued by a Notified Body Authorization to enter in service Issued by G. Dir. of Railways (NSA) Interim Authorization for Operation Issued by Adif Running tests specified in ETH Authorization for Operation Issued by Adif Figure 44 - Validation process The Validation is organized in two separate parts, for the European and the National functions, as shown in the following table: Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 116/161 EC pre declaration Object Generic product + Specific application + Specific trackside tests File contents Definition of the products and the application (according to the relevant consolidated TSI in force) Verification and Validation Dossier Safety Case Independent Safety Assessment report for the products and the trackside or on board unit Specific trackside tests report Specific National Declaration National Functions + Specific trackside tests Definition of the national application according to NF Verification and Validation Dossier Safety case Independent Safety Assessment Specific trackside tests The most significant part in the whole process is the specification of the “complementary tests”, that has been a joint task of Adif, the manufacturers, the CEDEX laboratory (as reference laboratory) and Tifsa (as Independent Safety Assessor). The role of ISA has been played by different entities in each project: Train series ISA 102 – 103 SAC 120 Certifer - Tifsa 100 – 104 Certifer - Cetren Complementary tests (for all series) Test realisation Renfe – Adif – Tifsa - CEDEX Test technical reports Tifsa - CEDEX At the present time there is not a consolidated policy related to the endurance tests. For instance for ERTMS Level 1, the trains of series 102 have had to run 100 000 kms without incidents before being authorized to operate (at the same time the trackside equipment was verified). But for trains of series 103 this requirement has been reduced to 50 000 kms. The criteria that is currently applied for other trains is to complete 30 000 kms under ERTMS plus 10 000 with STM, without incidents. Compatibility and Interoperability issues In all the Spanish ERTMS projects, the ERTMS/ETCS equipment installed is conform to the ERTMS/ETCS Class 1 System Requirements Specification of the UNISIG group, vers. 2.2.2, plus a number of Change Requests included in the Subset 108. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 117/161 There were several technical discussions between the manufacturers, Adif and Renfe, to assess the interoperability aspects of these Change requests. No problems were identified in the trackside subassembly, but 15 change requests related to On board Unit require further analysis. These CR are: Level 1: CR218, CR219, CR231, CR234, CR633 y CR464 Livel 2: CR226, CR475, CR633, CR441, CR458, CR508, CR512, CR50, CR146 y CR126. Alter the discussion it seems that the only CR that produces interoperability problems is the CR 458. It has been decided to wait for a clarification from UNISIG before its implementation. A survey on the implementation of the CRs by the different manufacturers has been done. It is summarized in the document CHANGE_REQUEST_LIST_.doc. The EC conformity certificates for the track-side system and the train borne systems are not yet available. CETREN will be in charge of this task. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 118/161 10 Phase 10 – System acceptance This section is intended to provide the following information about: • • • • • The process followed for the final acceptance of the trackside (and train-borne subsystems) by the Infrastructure manger, the relevant acceptance formalities regarding the fulfilment of the operational, functional, RAMS and interoperability requirements. The authorisation process followed and the bodies involved in the acceptance of minor non-conformities evidenced during the previous phases not endangering safety and interoperability of the sub-systems. The formalities and the relevant bodies required for authorising the start of revenue service of the trackside and train-borne sub-systems. Rules for the operational use; Rules for (periodic) maintenance. 10.1 The Austria-Italy project: Brenner Basis Tunnel This section is not applicable to the present stage of the Project. 10.2 The Austrian project: Vienna – Nickelsdorf Trackside subsystem: NoBo Assessments and procedures described in the phases before, together with an interim report on the safety of the trackside data, the approval authority (Austrian Ministry for Traffic and Innovation Technologies) allowed the operation. The EC conformity certificate for the ETCS train-borne subsystem is still unavailable. Integration tests have been partly carried out together with the validation tests of the vehicle. Basis for approval of the Ministry is, on one hand, the documentation by the railway operator and the manufacturers and, on the other hand, the NoBo’s interim assessment report on the safety of the trackside system. Train-borne Subsystem: Assessment reports by the Independent Safety Assessors, one for the ETCS part and an other for the locomotive specific part (national integration of the ETCS equipment into the locomotive and changes resulting from the use of ETCS in the national system of the locomotive) led to approval for tests with certain conditions. Operational Rules: They are summarized in “DV ETCS level 1”, containing rules for the driver, especially the rules in case of errors of parts of the ETCS system with fallback to the national signalling system. No special periodic maintenance for the trackside subsystem is required. 10.3 The Belgian projects The L3 and the L4 HSL There is no intention to establish an overall safety case for train-borne + track-side together with operations. There will not be such a document but the NSA will give separate Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 119/161 certificates for Rolling Stock after different tests. There is a process underway for Proof of Safety, but not a safety case. It is considered very complicated to match Phases 9 (system validation) and 10 (system acceptance) of the CENELEC lifecycle with the fulfilment of the safety requirements. Infrabel uses the GAME-principle (This stands for: Globalement Aussi Moins Equivalent; in English: globally at least as good as) with regard to the existing line L2. In principle, everything (Interlocking, Control Room, Detection, Hot Boxes, Points) is the same. The apportionment of risks is considered and the industry has to prove that new hazards, such as the ones related to the Interlocking-RBC interface do not result in greater overall risks. The ETCS Level 1 lines See previous chapter 9.1.7. No final acceptance has taken place to date. 10.4 The French project: LGV-Est The following process has been followed regarding the system acceptance: The systems acceptance is done via a site-laboratory test in which two RBCs, one EVC and one BTS are used. Although cross-acceptance is welcomed, specific homologation tests are deemed unavoidable for the time being. Safety procedures plan TRACKSIDE ON BOARD Overall APR DS DS LGV EE Without C/C and Signals MR Train POS DS DS Total mobile with full Bi Std C/C and Signals DPS DPS DS Total mobile with reduced Bi Std TVM DPS APR APR Bi Standard APR APR ERTMS TVM DPS APR Figure 45 – Plan for the PEEE safety acceptance Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 120/161 10.5 The German project: Berlin-HalleLeipzig After comprehensive testing in the suppliers´ laboratories, integrative and field testing mostly started in 2003 - both net operator and railway operator performed various system test runs. 260 operational test scenarios have been derived from the national functional specification (LH) and the European specifications in order to demonstrate correct concurrence of rolling stock and network in both regular and fall back mode. For the purpose of evaluation and faults documentation an integrated fault data base was set up, depicting and classifying all faults and open points from suppliers´ tests, DB testing, as well as from risk- and hazard analysis and rules frameworks. Safety related topics have been extracted to a hazard log. Suppliers and operators assessed the findings at periodical reviews, corrected, decided upon and finally closed the faults and open points before the start of the safety probation period. Safety cases have also been finalized and assessed before starting the probation. Cross exchange tests on other member states lines or by other member states trains on the BHL line were not performed. Before starting full service on the line, qualification testing was conducted in several steps, accompanied by a theoretical verification of the safety cases. Test classes were defined and performed: a) Verification of functional requirements on components level and components interfaces. b) Common testing for principal system interrelations. c) Acceptance of balise assembly, route atlas, RBC projection, and onboard equipment (Distribution of roles acc. to national regulations. For every train route - signalling, locations of speed changes - a separate acceptance procedure was performed). d) System validation of overall system requirements. e) Safety probation/safety testing of the overall system (track and train) after successful theoretical safety case verification; performing step-by-step speed enhancements up to 160 and 200 km/h. Since the development of trackside and train born equipment went nearly hand-in-hand - the suppliers in the consortium were working in close contacts - both timeframe and formalities were very similar. BHL is in revenue service basing on a national allowance for qualification testing (“Zustimmung zur Erprobung”) according to [DB 21]. The underlying processes of development, verification, validation and assessment comply with [DB 1], [DB 2] and [DB 3]. (More detailed information on the approval/acceptance activity of the NSA will be provided in the final version of this report). A final approval on the basis of national regulations as well as European requirements [DB 16] could not be issued yet, because no certificates and declarations of conformity or EUverification are available yet. The line is allowed to be run until 2007/12. Several limitations regarding the fulfilment of the functions as specified by UNISIG have been found for both trackside and onboard equipment, as e.g. being depicted in [DB 143] for the trackside equipment: Not all types of OBU messages, packets within the OBU messages, modes and levels the will be accepted by the RBC. Non-conformities were found, both resulting from deficiency in the UNISIG specifications and from “national add-ons”. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 121/161 In 2004 the suppliers´ consortium applied for conformity examinations at the EBC, Notified Body. To this day not all conformity and EC certificates could be issued; the process is still pending. The assessment of the safety cases started in the middle of 2003. Activity towards certification started later but was mainly restricted to the RBCs. There have not yet been issued any conformity or EC certificates and declarations by any Notified Body or operator, although some examinations have been performed. TÜV InterTraffic GmbH (TÜV Rheinland Group) performed a "quality assurance, production" investigation according to Module D for the ETCS2000 RBC at the supplier Alcatel SEL AG on behalf of the Notified Body EBC, ending up in an Independent Safety Assessment Report of the audit. For onboard equipment EC verification was not applied for at any Notified Body. In Germany there was uncertainty in the question if a Notified Body is intended to assess "the safety" on components and assembly level and if this may be part of any conformity or EU assessment. The TSI CCS requires the Notified Body "to ensure the completeness of the safety approval process" ([DB 16], table 6.1, 6.2). However, the German view is that a module for such an investigation or assessment is not been provided by the TSI. In addition, the German regulation still prohibits assessment by others than the "Eisenbahn-Bundesamt EBA" in any question of "safety judgement" ("Sicherheitliches Ermessen"). CENELEC verification, validation and assessment is mostly done by test control centres ("Prüfleitstelle PLS"), or independent assessors under strict control of the EBA. 10.6 The Italian Projects The Rome-Naples HSL At the end of the assessment activities, carried out during the project lifecycle by the relevant RFI departments and structures, the signalling system has been accepted. The activation of the line has been carried out in two subsequent steps: • Approbatory Period; • Start of the revenue service. The suppliers official documents issued for activating the line on the approbatory period have been three conformity declarations [from [RFI 142] to [RFI 144]), one document for each of the following subsystems: • Trains Separation Sub-system; • Interlocking sub-system; • Trackside CCS sub-system. The Generic Applications documents issued for the approbatory period line activation are listed in Annex. Moreover for the specific application of the Train Separation System, RFI have issued some technical reports [from RFI 142 to RFI 144] and the final declaration “Dichiarazione di Applicabilità Tecnica”. Following the test activities and the assessment of some minor modifications, carried out by the suppliers during the approbatory period, RFI has issued further documentation. For putting the line in revenue service, RFI has issued the following documents regarding the generic ETCS Lev. 2 application [RFI 107 to RFI 116]. These documents have been Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 122/161 based on the suppliers’ documents [RFI 142 to RFI 144], meanwhile for the specific applications all the necessary technical reports have been updated. Moreover to put in service the line, as stated by the RFI directive [RFI 19], the units “Direzione Movimento”, “Direzione Tecnica” and “Direzione Investimenti e Manutenzione” have finally assessed the system vs. the maintenance and the service requirements. In Italy two track side assembly EC certificates of Verification (under module SH2) have been issued: • Roma - Napoli: CE Certificate no. 1287/6/SH2/2006/CCS/IT/ZN 39 27 0006 of 10 July 2006. • Torino Novara: CE Certificate no. 1287/6/SH2/2006/CCS/IT/ZN 39 27 0009 of 27 November 2006 This two certificates are both included in the CIRCA Database of NB Rail. Torino-Novara HSL/HCL The suppliers have performed the validation activities regarding the Generic Products, Generic and Specific Applications. The Safety Cases issued by the suppliers at the end of the validation activities regarded: • Trackside Subsystem (Ansaldo); • Train Separation Subsystem (Ansaldo); • Interlocking Subsystem (Ansaldo); • On Board Subsystem (Alstom and Ansaldo); • Integration of On Board equipment by Alstom with the Ansaldo Trackside system. Besides, the suppliers on field validation activities RFI have performed some on field test sessions to assess the implementation of the signalling system functionalities. For specific application a technical commission has verified, by means of on field test, the correctness of the installation, assembly and system configuration. A functional assessment of overall train separation system (trackside and on board) as described in the Roma Napoli line document has been carried out Test management Similar rules, issued by the General Contractor, as those applied on the Rome – Naples line have been adopted on the Torino Novara line for the validation and assessment on field tests. A general contractor on board people (IBT) radio linked with a trackside safety responsible (RPT) has been foreseen. During the test the pertinent supplier’s personnel have controlled on site all the interlockings and the RBCs. In the interconnection test the RFI personnel have ensured the safety of the trains on the traditional line suspending the commercial services during the tests. After the assessment of the products, generic and specific applications on 2005 November the 28th RFI proceeded to a preliminary acceptance (see phase 10) of the line to start the probatory period. During this period RFI assessed the following issues: Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 123/161 • Operating rules • Rolling stock and infrastructure functionalities and their interfaces • Railway Operations model; • Infrastructure management (effectiveness of the organisation and diagnostic devices) • Potentiality of the line revenue service. Furthermore the transport company Trenitalia has carried out the assessment of: • Adequacy of service management; • Effectiveness of the training courses for the operative personnel; • Effectiveness of the rolling stock maintenance. During the probatory period suppliers and RFI personnel have carried out the tests together. A RFI test manager has been performed the test run on train borne together with IBT. During the test trains and RBC data have been collected by means of specific tools (“Canapè” for the on-board data and LDR for RBC). A fine tuning on the products and configurations has been carried out after the tests execution. The results of the probatory period tests have been reported on monthly reports. 10.7 The Dutch projects Betuweroute Steps are not yet taken to have the track certified by a NoBo. Although the Infrastructure provider ProRail intends to approach the ideal situation as close as possible, it is deemed impossible at this moment by all parties involved, due to the limited maturity of the TSI’s and lack of earlier references. The same is valid for locomotives. At this moment about 100 locomotives (10 different types) are in different stages of preparation for operation on the Betuweroute. Also in this case a process is followed that approaches the ERTMS type approval as close as possible. A starting requirement, however, for a train type is a Declaration of Conformity of all ERTMS constituents used, certified by a NoBo and a Declaration of Verification for the Train borne Subsystem, certified by a NoBo as well as a completed CENELEC safety case for the trainborne Command and Control subsystem, assessed by an ISA, with no blocking findings. Also for the trackside certificates of conformance for ERTMS constituents are used as well as certificates for the trackside subassembly, all certified by NoBo’s. IVW and ProRail will not allow for operation on the ERTMS track with ERTMS trains on the basis of NoBo certificates only. Although the Infrastructure provider ProRail intends to approach the ideal situation as close as possible, it is deemed impossible at this moment by all parties involved, due to the limited maturity gained on the TSI and lack of earlier references. After the NoBo statements and the safety cases for the trackside and train borne subsystem have been obtained, as well as permission for test exploitation has been granted, a technical and operational hazard analyses is performed for the integrated trackside and train borne Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 124/161 systems. On this basis a specific test plan is made on the basis of a default track train integration test plan. This can lead to a “verklaring van geen bezwaar” (a declaration of no objection) by IVW. After a subsequent system qualification test the “inzetcertificaat” (operation certificate) can be issued. These tests include testing trainborne and trackside equipment for 10.000 km, absolved by a train of a specific type. The results of monitoring are needed to finalise the trackside as well as the train borne safety cases. Amsterdam - Utrecht ProRail is the system integrator, the responsible organization on behalf of the Ministry. As such, it is responsible for the commissioning of the system. The ProRail organization is responsible for all the activities including system acceptance. HSL ZUID The system acceptance consists of several stages. The first stage is the approval of the evidence that the system is working correctly and safely. Approval is given by the HSL-Zuid project by acceptance of the “Compliance Demonstration of the Infrastructure Supplier”. Important part of the Compliance Demonstration is the delivery of the “Availability Period Safety Case (APSC)” that has to be approved by an Independent Safety Assessor (i.e. DeltaRail) (ref. “Report on the safety assessment of the Availability Safety Case (rev E) of the HSL Assets and HSL Activities”, 23 march 2007). The supplier has also to deliver interoperability certification for the Trackside Assembly. To date, the APSC has been approved with remarks; NoBo Conformity Certificates for the Interoperability Constituents regarding ETCS vers. 2.2.2 are available. Update Safety Case for vers. 2.3.0 and NoBo Certificates for vers. 2.3.0 are still to be determined. This approval by HSL-Zuid is a pre-condition for the next stage regarding “Test of Safe Usage”. In this stage the behaviour of the system is tested in the context of operational procedures carried out by operating personnel (i.e. signalmen and train driver). In addition endurance tests and cross exchange tests are executed during the same stage. On the base of the test results, Prorail (i.e. the Inframanager) gives the approval for the folowing stage. This regards Trial Exploitation. In this stage the train operating company tests its operations (e.g. logistics, commercial etc). At the successful completion of this stage, the approval has to be given by the Dutch Safety Authority IVW for the next, final stage that regards Normal Exploitation. For the HSL-Zuid the process is complicated by the fact that during this acceptance process the ERTMS system has to be upgraded from 2.2.2 to 2.3.0 via an intermediate step 2.3.0 minus. After each upgrade, regression tests and delta tests have to be carried out. The picture below shows the relationship between the differet stages. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 125/161 HSL Appr. for Testing PR/IVW Appr. Test Exploitation Infra=OK Process Building Test safe functioning Test safe useage IVW Appr. Expoitation Headway=OK Trial exploitation Normal exploitation Test safe useage ERTMS 2.2.2 Building Test safe function. ERTMS 2.3.0- Building Test safe function. Test safe useage Trial exploitation Normal exploitation ERTMS 2.3.0 Building Test safe function. Test safe useage Trial exploitation Normal exploitation Figure 46 – Safety approval proces in HSL ZUID For approval of Normal Exploitation a number of requirements have to be fulfilled, the most important of which are: • Acceptance of the Integral Safety Case, to be delivered by HSL-Zuid based on the underlying Safety Cases or Safety Evidence for Track, Rolling Stock and Operations; • NoBo Certificate for Track Assembly and OBU; • Certificate for Deployment (Inzetcertificaat) of Rolling Stock. Approval tests on HSL-Zuid are foreseen by 2007 with Traxx locomotives, Bombardier OBU, 160 km /hr. Approval tests for Thalys (CSEE EVS and Alstom STM) at 300 km/h are foreseen by 2008. Next to the above, in order to assure the interface of the L4 (connecting Belgium High Speed Line) and the HSL Zuid to be safe, the Integral Safety Cases of the two lines have to be aligned. The related process is under construction. To date, this report has been drafted. As far as rules for operational use are concerned, a number of documents were delivered by the supplier of the trackside systems (Infraspeed) to assure proper operation: • • • • Signalling Rules for the Customer (SIGNALING SUBSYSTEM RULES FOR THE CUSTOMERS IDE (SIG=S$T&EEC # 000019) Safety Related application Conditions (SAFETY RELATED APPLICATION CONDITIONS FOR OPERATION AND MAINTENANCE IDE (SIG=S$TEX&EQB # 000015) Operational Restrictions (SIG TEMPORARY RULES FOR OPERATION IDE (SIG=S$T&EEC # 000027 Temporary Rules (in the phase that additions still have to be made to the deliveries) (SIG TEMPORARY RULES FOR OPERATION IDE(SIG=S$T&EEC # 000027) Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 126/161 These rules provide instructions how to use the system, but do not affect any rule in the referenced TSI’s. The supplier also is responsible for maintaining the superstructure and has also devised internal rules for maintenance. Under the performance contract this is the responsibility for the supplier. As far as the interoperability certification is concerned, the NoBo for the trackside assembly (integrated in the traffic system) was contracted in the acceptance phase. The certification of the on-board assemblies is determined by the rolling stock suppliers. 10.8 The Spanish projects Complementary tests The acceptance process has already been described. What can be added here is the concept of “Complementary tests” Besides the internal tests performed by the manufacturer, and the agreed acceptance tests, that were carried out in the Madrid-Lleida line with ERTMS track-side and on-board equipment delivered by the same manufacturer, the Ministry of Transport, together with Adif and Renfe, have defined the so-called “Complementary tests”, additional tests to those already carried out and documented in the verification and validation dossier. The tests have been specially established for the new Madrid-Lleida line to check the functionality of the new trainborne equipment. They cover in particular the following topics: 1. Speed and braking curves supervision 2. Transitions between ERTMS application levels 3. Mode transitions 4. Management of Temporary Speed Restrictions 5. Failures in balise detection 6. Management of timing in Movement Authorizations 7. Odometry 8. Train Interface 9. ATO and pre-fixed speed 10. DMI 11. National functions 12. Signal balise group reading in PT mode This is an additional requirement from the Ministry of Transportfor authorising the commissioning of rolling stock. The phases 5 to 10 are summarised in the figure below. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 127/161 Delivery record/Receipt of Works Construction Manager Coordination Infrastructure Maintenance Directorate Investments Stations/Terminals Dossier on safety (Safety case, CENELEC standards) Safety Directorate Construction Manager Functional Projects, Verification and Placing in Service Directorate Instructions, Notices and News Installations Directorate Planning and Deveplopment of Networks Directorate Functional Projects, Verification Excutive Traffic Directorate and Placing in Service Directorate Executive Infrastructure Maintenance Directorate Maximum Speed Table Operative Assets Excutive Traffic Directorate Management Directorate Functional Projects, Verification and Placing in Service Directorate Infrastructures Verification and Recording (TSI´s ) Functional Projects, Verification Ministry of Public Works and Placing in Service Directorate and the Distribution List Reliability Testing / Subsystems Interfaces/ Report on the placing in service Functional Projects, Verification Ministry of Public Works and Placing in Service Directorate and the Distribution List Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 128/161 11 Phases 11-12 Operation, maintenance and monitoring This section is intended to provide the following information about: • • The process followed for collecting statistical data regarding functional and RAMS performances during the revenue service of the trackside and train-borne subsystems by the Infrastructure owner, for their subsequent evaluation and for planning the consequent maintenance actions. The authorisation process followed and the bodies involved in the postponed solution of minor non-conformities evidenced during the previous phases without endangering safety and interoperability of the sub-systems. 11.1 The Austria-Italy project: Brenner Basis Tunnel This section is not applicable to the present stage of the Project. 11.2 The Austrian project: Vienna – Nickelsdorf No statement is available up to now as the system is not in operation. 11.3 The Belgian projects The L3 and the L4 HSL In Belgium, the national operational rules are conceived for TBL 2. For ERTMS these rules had to be adapted. There are specific Belgian Rules as “grote beweging en kleine beweging” meaning large movement and small movement that do not exist in ERTMS. So the ERTMS term had to comply with one of this types of movement. As far as L3, L4 and other parts of the network are not uniform, this might be an issue in future. Infrabel considers European rules to be insufficiently present. Therefore they considered their own adaptation of national rules necessary. It is self-understood that these rules won´t be interoperable. There was a problem to connect with the HSL/Zuid concerning Hot Box Axle Detection (HBAD). This is not required in the Netherlands. The Belgian party involved would not allow a train, coming from Holland on their L4 line without detecting possible hot axes. As a solution, a HBAD was placed on the Dutch side of the border. There has been joint work on a safety case “border” . Safety requirements and operational rules, only valid for this transition, were agreed upon jointly Belgian ETCS level 1 lines Not applicable, as the system did not pass phase 9 to the present date. No final acceptance has taken place to date. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 129/161 11.4 The French project: LGV-Est This (optional) information is not presently available. 11.5 The German project: Berlin-HalleLeipzig Conforming [DB 24] the Operator is committed to gather any incidents and accidents at a database. The DB database served as a vital source of information for the risk and hazard analyses and the migration. 11.6 The Italian Projects The Rome-Naples HSL The ERTMS trackside and on board subsystem have been monitored during the approbatory period. The results have been collected in four monthly reports issued by RFI [0] in accordance with the procedure [RFI 103]. The evaluations of the performances of the railway system are collected in such reports. For example, during the first two months of the approbatory period, 209 train runs between Rome and Naples or vice versa plus 109 not incomplete runs have been carried out with the following punctuality figures: • 21% of the trains have arrived on schedule; • 29% of the trains have suffered a delay up to 15 minutes • 50% of the trains have suffered a delay longer than 15 minutes. The summary of the approbatory period troubleshooting is in the [RFI 106]. Torino-Novara HSL This (optional) information is not presently available. 11.7 The Dutch projects Betuweroute This (optional) information is not presently available. Amsterdam - Utrecht On behalf of the Ministry, ProRail has the tasks of Operation, Maintenance and Monitoring of the line. HSL ZUID This (optional) information is not presently available. 11.8 The Spanish projects The only reported malfunction has been the one related with the tele-powering of the balises. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 130/161 The problem has been temporary solved installing a second balise holding identical information, mounted in an adjacent sleeper. At the present time the origin of this malfunction is still unknown. The laboratory tests have always been satisfactory, and line tests performed during several months with balises of several manufacturers have proven that every balise, including the new ones developed by the previous manufacturer, works satisfactorily. After the test has been finished it is very probably that ADIF decides to remove the duplicated balises. In any case, this is not considered a safety, nor an interoperability problem, but an operational inconvenience. If a train fails to read a balise, the only consequence is an unwanted stop. The operation under ERTMS is very recent, there are not available statistics. There are only punctual observations that do not allow the deduction of any conclusion about ERTMS functional and RAMS performances The results of the operation of the Madrid-Lleida section since 19/06/2006 to 18/12/2006, and of the Madrid – Tarragona sectiom since 10/12/06 to 08/03707 can be summarized as follows: • • • • Number of train runs: 4.445 Number of kilometres: 1.767.553 Number of incidences (dealay greater than 5 min):26 (16 of which are due to odometry malfunction under ice and snow environment) Punctuality index: 99,5 % Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 131/161 12 Phase 13 – Modification and retrofit This section is intended to provide the following information about: • • The process followed for implementing change request procedures or for the system updating to the most recent ERTMS baseline, with due consideration of RAMS implications for such modifications and retrofit. The authorisation process followed and the bodies involved in the implementation, validation and acceptance of modifications, without endangering safety and interoperability of the sub-systems. 12.1 Austria-Italy project: Brenner Basis Tunnel project This section is not applicable to the present stage of the Project. 12.2 Vienna-Nickelsdorf It seems to be envisaged by the Railway Operator to upgrade ETCS level 1 to version 2.3.0, but this is not officially fixed to date. Because of the use of Euroloop equipment (both track-side and train-borne equipment) produced and certified according to the old Euroloop Specifications (i.e. before the up-link signal frequency was changed), it will become necessary to update the frequency relevant components, according to the presently available Specifications, during a due time. Also one type of certified LEU doesn´t conform to the present Specifications, due to technical changes in the Specifications used for the certification. It has not been defined yet, to date, what will be done as the change of specification has in course of this project no influence on the function, the safety, the reliability of the component and most important also no influence on the interoperability of the ETCS railway system. 12.3 The Belgian projects Not applicable, as the system did not pass phase 9 to the present date. 12.4 The French project: LGV-Est This (optional) information is not presently available. 12.5 The German project: Berlin-Halle-Leipzig This (optional) information is not presently available. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 132/161 12.6 The Italian Projects The Rome-Naples HSL Starting from the beginning of approbatory period, the following procedure has been defined to install new Sw versions or Hw modifications to the sub-systems or to the components: • • • • • • The modification has to be agreed between RFI and the involved suppliers; A revision plan has to be issued and agreed upon; The supplier has to validate the modification, according to his Verification and Validation Plan (phase 13), and issue the related set of documents; RFI has to perform the documental assessment; Based on the extension of the modification, RFI and the suppliers have to carry out a on field validation and acceptance test session, prior to put in service the new version. The test sessions are carried out during the night when the commercial service is suspended. A positive assessment report has to be issued and accepted by RFI. Torino-Novara HSL There are still some tests in progress regarding the evaluation of the Quality of Service of the GSM-R communications, as a measure to quantify the level of availability of the complete ERTMS/ETCS system. 12.7 The Dutch projects Betuweroute This (optional) information is not presently available. Utrecht-Amsterdam HSL This section is not applicable to the present stage of the Project. HSL ZUID This (optional) information is not presently available. 12.8 The Spanish projects This (optional) information is not presently available. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 133/161 13 Annex 13.1 References for the Austrian Projects OEBB 1 DV V2 Signalvorschrift (signalling rules) OEBB 2 DV V3 Betriebsvorschrift (operation rules) OEBB 3 DV ETCS level 1 European Train Control System - ETCS Level 1 OEBB 4 DV S80 OEBB 5 DB 823 Beschreibung und Bedienung (description and operation manual) 13.2 References for the German projects European Directives, Standards and Specifications EC-Directives DB 1. EC-directive 96/48/EC DB 2. EC-directive 2001/16/EC DB 3. EC-directive 1999/36/EC EC-Standards DB 4. EN 50126, Railway applications – The specification and demonstration of dependability, reliability, availability, maintainability and safety (RAMS), 2000-03 DB 5. EN 50128, Railway Applications – Communications, signalling and processing systems – Software for railway control and protection systems, 2001-11 DB 6. EN 50129, Railway Applications: Safety related electronic systems for signalling, Issue: 2000-11 DB 7. EN 50159-1 Railway Applications – Communication, signalling and processing systems – Part 2: Safety related communication in closed transmission systems, 2001 DB 8. EN 50159-2 Railway Applications – Communication, signalling and processing systems – Part 2: Safety related communication in open transmission systems, 2001-12 DB 9. EN 45004 DB 10. EN 50170-2 DB 11. EN 29000 DB 12. EN 29001 DB 13. EN 50121-4 DB 14. EN 50125-1 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 134/161 DB 15. EN 50155 EC-Specifications DB 16. TSI Command Control Signalling, 2002-05-30 DB 17. FFFIS STM DB 18. UNISIG Specifications V2.2.2 Class 1, 2002-05-30 Subsets 026, 037, 039, 041, 055, 076, 091, 092, and further National Rules & Regulations DB 19. Eisenbahn-Interoperabilitätsverordnung (EIV), 1999-05-20 DB 20. Konventioneller Verkehr – Eisenbahn Interoperabilitätsverordnung (KonVEIV) DB 21. Verwaltungsvorschrift für die Bauaufsicht über Signal-, Telekommunikation- und Elektrotechnische Anlagen BAU-STE; 2003-01-01 DB 22. Eisenbahn-Bau- und Betriebsordnung (EBO); 1967-05-08 ff. DB 23. Allgemeines Eisenbahngesetz (AEG); 1993-12-27 ff. DB 24. Technische Grundsätze für die Typzulassung von Sicherungsanlagen (Mü 8004) DBAG Regulations DB 25. Konzernrichtlinie 408 (former “Fahrdienstvorschrift”) DB 26. further rules and regulations DBAG Pilot Documentation DB 27. Rahmenlastenheft der DB AG; 2.5.1; 2004-07-15 DB 28. Teillastenhefte Teile 1 bis 8, inkl. Anhängen DB 29. Erprobungsplan ETCS Release 1.4/1.3.6 und Doppelausrüstung ETCS/LZB auf BHL DB 30. Inbetriebnahmekonzept für Ludwigfelde – Teltow und Lückenschlüsse auf der ETCS Pilotstrecke Berlin – Halle/Leipzig DB 31. Konzept für die Sicherheitserprobung (ZE) für die ETCS Teilsysteme Fahrzeug und Strecke Mapping” Risk Analysis – Hazard Analysis DB 32. Systemdefinition DB 33. Beschreibung betrieblicher Situationen zu den Gefährdungen DB 34. Betriebliche Ursachenanalyse – Teil 1 DB 35. Betriebliche Ursachenanalyse – Teil 2, mit Fehlerbäumen DB 36. Quantifizierung, Betriebs- und Infrastrukturparameter, mit Anlagen 1 und 2 DB 37. Zusammenfassung Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 135/161 DB 38. Vorgehensweise DB 39. Gutachten zum Mapping RA/GA im Projekt ETCS2000 (not DB AG) Suppliers´ (“Consortium”) Documentation (RBC Docu as an example) Concepts and Plans DB 40. Safety Case Concept RBC DB 41. Safety Concept ETCS 2000 Crypto Module DB 42. Sicherheitskonzept des Kryptomoduls von ETCS2000 DB 43. Sicherheitskonzept Core auf TAS Plattform, Safety DB 44. Sicherheitskonzept zur Eingabe von Daten über den RBC Bedienplatz DB 45. Sicherheitsnachweiskonzept RBC Release 1 DB 46. Verification Plan of ETCS2000 RBC DB 47. Validation Plan of ETCS 2000 RBC DB 48. RBC Validation Plan DB 49. Quality Assurance Plan, Project RBC DB 50. Sicherheitsplan ETCS 2000 RBC DB 51. RBC Safety Plan DB 52. RAM Plan (RAMP) System Radio Block Centre (RBC) DB 53. Datengenerierungsplan Streckendaten ETCS RBC DB 54. Datentestplan der Streckendaten ETCS RBC DB 55. Conformity Plan of ETCS2000 RBC Specifications and Descriptions DB 56. Systemanforderungsspezifikation ETCS 2000 DB 57. Safety Requirements Specification of RBC DB 58. Descriptions of RBC equipment (core system, PC´s, monitors, switches, ...) DB 59. Anforderungen an die Planung der ETCS-Zentrale DB 60. RBC Operator Panel Requirement Specification DB 61. Software Architecture RBC Core DB 62. Requirement Specification and SW Architecture PCU, Protocol Converter SAHARA RACOON DB 63. Interface Specification RBC-IL / Double Equipment /Application Level DB 64. Interface Specification RBC-IL / Presentation Layer Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 136/161 DB 65. Architecture Design Document Hardware DB 66. Insulation Coordination Hardware RBC DB 67. Hardware Beschreibung RCS für RBC DB 68. System Test Specification for RBC Transitions Manuals DB 69. Handbuch Bedienplatz ETCS-Zentrale DB 70. Handbuch Diagnoseterminal ETCS Zentrale DB 71. Meldungshandbuch ETCS Zentrale Release 1 DB 72. Wartungs- und Instandhaltungshandbuch ETCS-Zentrale Conditions and Obligations DB 73. Betreiberhinweise für das ETCS2000 RBC Release x DB 74. Safety Application Conditions DB 75. Security Gateway: Sicherheitsbezogene Anwendungsvorschriften DB 76. Prüfvorschrift FZB Schrank Streckenzentrale DB 77. Projektierungsregeln der Streckendaten Release x Analyses DB 78. Systemgefährdungsanalyse ETCS2000 – Fehlerbaumanalyse DB 79. RAM Analyse RBC DB 80. Implication Analysis (assessment of changes from one RBC release to the next) Safety Cases DB 81. Sicherheitsnachweis Teil 1: Definition dess Systems DB 82. Sicherheitsnachweis Teil 2: Qualitätsmanagementbericht für ETCS2000 RBC Release x DB 83. Sicherheitsnachweis Teil 3: Sicherheitsmanagementbericht (SMR) DB 84. Sicherheitsnachweis Teil 4: Technischer Sicherheitsbericht (Technical Safety Report) DB 85. Sicherheitsnachweis Teil 4: Anhang A, Fehlerbaumanalyse (Fault Tree Analysis) DB 86. Sicherheitsnachweis Teil 4: Anhang B, FMEA DB 87. Sicherheitsnachweis Teil 4: Anhang B, FMEA Interface IL DB 88. Sicherheitsnachweis Teil 4: Anhang B, FMEA PCU DB 89. Verfahrenssicherheitsnachweis für den RBC-Bedienplatz DB 90. Ergänzende Betrachtung zum Bedienplatz Rel. 1: Einsatz im offenen Netz Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 137/161 DB 91. Verfahrenssicherheitsnachweis für die sichere Kommunikation zwischen RBC – Stellwerk (Alcatel) unter Nutzung des CIRNet Protokolls DB 92. Technischer Sicherheitsbericht Verfahren Kommunikation OBU-RBC über EuroRadio ETCS2000 DB 93. Verfahrenssicherheitsnachweis für die sichere Kommunikation in geschlossenen Netzen unter Nutzung des RACOON Stacks DB 94. Sicherheitsnachweis Teil 5: Beziehung zu anderen Sicherheitsnachweisen DB 95. Sicherheitsnachweis TFT-Monitor für den RBC Bedienplatz Verification & Validation DB 96. Journal Sicherheitslogbuch Projekt RBC DB 97. Gefährdungslogbuch RBC DB 98. Validation Report of ETCS2000 RBC DB 99. Hardware Validation Report of RBC Release x DB 100. Validation Test Database RBC Reports and Proofs DB 101. Release Notes DB 102. Version Descriptions DB 103. Qualification Test Report Hardware RBC Assessment DB 104. Sicherheitsgutachten Alcatel SEL RBC Rel. 1 DB 105. Nachweis der Rückwirkungsfreiheit im Testbetrieb auf der ETCS Teststrecke für die Zentralen Bitterfeld, Wittenberg und Jüterbog; Schrb. v. TS/AT DB 106. Nachweis der Rückwirkungsfreiheit im Testbetrieb auf der ETCS Teststrecke für die Zentrale Ludwigsfelde; Sicherheitsgutachten RBC Rel. 1 DB 107. Feldtest-Bericht ETCS L2 Bitterfeld, RBC Wittenberg Approval & Acceptance DB 108. Zustimmung zur Betriebserprobung des Alcatel „Radio Block Centre“ (RBC) auf der Strecke Jüterbog – Halle/Leipzig, 2003-12-12 DB 109. Zustimmung zur Betriebserprobung der Fahrzeugeinrichtung ETCS-OBU auf dem Testcar (BR 707) und DESIRO (BR 642) auf der Strecke Jüterbog – Halle/Leipzig, 2003-12-12 DB 110. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung für das SW Release 1.4 in den RBC-Zentralen Jüterbog, Wittenberg und Bitterfeld der ETCS Pilotstrecke J-H/L, 2005-05-02 DB 111. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Strecke / RBC) auf der Pilotstrecke Jüterbog – Halle/Leipzig, 2005-09-14 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 138/161 DB 112. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Fahrzeug / OBU) auf der Pilotstrecke Jüterbog – Halle/Leipzig, 2005-09-14 DB 113. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Strecke / RBC) auf der Pilotstrecke Jüterbog – Halle/Leipzig, 2005-11-21 DB 114. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU) auf der Pilotstrecke Jüterbog – Halle/Leipzig, 2005-11-21 DB 115. Zustimmung zur erweiterten Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Fahrzeug / OBU) zur Durchführung von Hochgeschwindigkeitsfahrten (200 km/h) auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Bitterfeld und Wittenberg; Fortschreibung des Bescheides vom 14.09.2005, 2006-01-31 DB 116. Zustimmung zur erweiterten Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Strecke / RBC) zur Durchführung von Hochgeschwindigkeitsfahrten (200 km/h) auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Bitterfeld und Wittenberg; Fortschreibung des Bescheides vom 14.09.2005, 2006-01-31 DB 117. DB 118. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS Level 2 (Strecke / RBC, Version 1.4) auf der Pilotstrecke Ludwigsfelde – Halle/Leipzig im Bereich der RBC Bitterfeld, Wittenberg und Jüterbog, 2006-02-14 Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS Level 2 (Fahrzeugeinrichtung OBU BR 101) auf der Pilotstrecke Ludwigsfelde – Halle/Leipzig in den RBC Bereichen Bitterfeld, Wittenberg und Jüterbog, 2006-02-14 DB 119. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS Level 2 (Fahrzeugeinrichtung OBU BR 101) auf der Pilotstrecke Ludwigsfelde – Halle/Leipzig im Bereich des RBC Jüterbog, 2006-03-01 DB 120. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS Level 2 (Strecke / RBC, Version 1.4) auf der Pilotstrecke Ludwigsfelde – Halle/Leipzig im Bereich des RBC Jüterbog, 2006-03-01 DB 121. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS Level 2 (Fahrzeugeinrichtung OBU BR 101) in den RBC-Zentralen Wittenberg und Bitterfeld der ETCS Pilotstrecke J-H/L, 2006-10-04 DB 122. Zustimmung zur Sicherheitserprobung für das SW Release 1.4 in den RBC-Zentralen Wittenberg und Bitterfeld der ETCS Pilotstrecke J-H/L, 2006-04-10 DB 123. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS Level 2 (Fahrzeugeinrichtung OBU BR 101) in den RBC-Zentralen Jüterbog, Wittenberg und Bitterfeld der ETCS Pilotstrecke J-H/L, 2006-05-02 Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Fahrzeugeinrichtung OBU BR 101) im Bereich des RBC Jüterbog auf der ETCS Pilotstrecke J-H/L, 2006-05-02 DB 124. Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 139/161 DB 125. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung für das SW Release 1.4 im Bereich des RBC Jüterbog auf der ETCS Pilotstrecke J-H/L, 2006-0502 DB 126. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung für das SW Release 1.4 im Bereich der RBC Wittenberg und Bitterfeld auf der ETCS Pilotstrecke J-H/L, 2006-05-05 Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Fahrzeugeinrichtung OBU BR 101) im Bereich der RBC Wittenberg und Bitterfeld auf der ETCS Pilotstrecke J-H/L, 2006-05-05 DB 127. DB 128. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 Streckenzentrale / RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung / OBU, Version 1.3.5.1, auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-07-03 DB 129. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU, Version 1.3.5.1) in Kombination mit der Streckenzentrale / RBC, Version 1.4 auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-07-03 DB 130. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Streckenzentrale /RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung / OBU, Version 1.3.6.2) auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-07-26 DB 131. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2 (Fahrzeug / OBU, Version 1.3.6.2 in Kombination mit der Streckenzentrale /RBC, Version 1.4) auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-07-26 DB 132. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 Streckenzentrale / RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung / OBU, Version 1.3.6.2, auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-10-10 DB 133. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU, Verision 1.3.6.2) in Kombination mit der Streckenzentrale / RBC, Version 1.4, auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-10-10 DB 134. Zustimmung zum Testbetrieb für das SW Release 1.4.1.6 in den RBC-Zentralen Bitterfeld, Wittenberg, Jüterbog sowie 1.4.1.4 in der RBC-Zentrale Ludwigsfelde der ETCS Pilotstrecke B-H/L, 2006-10-24 DB 135. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 Streckenzentrale / RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung / OBU, Version 1.3.6.2, auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-11-17 DB 136. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU, Version 1.3.6.2) in Kombination mit der Streckenzentrale / RBC, Version 1.4 auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und Bitterfeld, 2006-11-17 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 140/161 DB 137. Zustimmung zum Testbetrieb für das SW Release 1.4.1.6 in den RBC-Zentralen Bitterfeld, Wittenberg, Jüterbog und Ludwigsfelde der ETCS Pilotstrecke B-H/L, 200611-21 DB 138. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von Level 2 (Fahrzeug / OBU, Version 1.3.6.2) in Kombination mit der Streckenzentrale / RBC, Version 1.4.1.6, auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Ludwigsfelde, Jüterbog, Wittenberg und Bitterfeld, 2006-12-21 DB 139. Zustimmung zur Sicherheitserprobung für das SW Release 1.4.1.6 auf der ETCS pilotstrecke Berlin – Halle/Leipzig im Bereich der RBC-Zentralen Ludwigsfelde, Jüterbog, Wittenberg und Bitterfeld, 2006-12-21 Warranty of documents (“Zusicherung”) DB 140. Zusicherung für Mapping Dokumente, 2005-11-21 DB 141. Zusicherung für das Rahmenlastenheft der DB AG, 2.5.1 v. 2004-07-15 DB 142. Zusicherung der Risikoanalyse Conformity DB 143. Conformity Report of ETCS2000 RBC Release 1.3 DB 144. Unisig Conformity Matrix (for RBC) DB 145. TÜV Intertraffic GmbH: Bericht zum Modul D Audit ETCS2000 RBC 13.3 References for the Italian projects Laws and Norms RFI 1. Direttiva 96/48/CE del Consiglio del 23 luglio 1996 relativa all'Interoperabilità del Sistema Ferroviario Transeuropeo ad Alta Velocità RFI 2. Direttiva 2001/16/CE del Parlamento Europeo e del Consiglio del 19/03/2001 relativa all’interoperabilità del Sistema Ferroviario Transeuropeo Convenzionale RFI 3. Decisione 2002/731/CE della Commissione Europea del 30 maggio 2002 relativa alle “Specifiche Tecniche di Interoperabilità per il sottosistema controllo-comando e segnalamento del sistema ferroviario transeuropeo ad alta velocità di cui all’articolo 6, paragrafo 1, della direttiva 96/48/CE”; RFI 4. Decreto Legislativo n. 299 del 24 Maggio 2001 “Attuazione della direttiva 96/48/CE relativa all’interoperabilità del Sistema Ferroviario Transeuropeo ad Alta Velocità RFI 5. Decreto Legislativo n. 268 del 30 Settembre 2004 “Attuazione della direttiva 2001/16/CE in materia di interoperabilità del Sistema Ferroviario Transeuropeo Convenzionale Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 141/161 European Norms and Standards RFI 6. EN 50126, Railway applications – The specification and demonstration of dependability, reliability, availability, maintainability and safety (RAMS), Issue: September 1999 RFI 7. EN 50129, Railway Applications: Safety related electronic systems for signalling, Issue: February 2003 RFI 8. EN 50128, Railway Applications – Communications, signalling and processing systems – Software for railway control and protection systems, Issue: March 2001 RFI 9. EN 50159-1 Railway Applications – Communication, signalling and processing systems – Part 2: Safety related communication in closed transmission systems, Issue: March 2001 RFI 10. EN 50159-2 Railway Applications – Communication, signalling and processing systems – Part 2: Safety related communication in open transmission systems, Issue: March 2001 RFI 11. Subset 026 - issue 2.2.2 UNISIG ERTMS/ETCS - Class 1 – System Requirements Specification RFI 12. Subset 040 rev 2.0.0 Dimensioning and Engineering rules RFI 13. Subset 041 rev 2.0.0 Performance Requirements for Interoperability RFI 14. Subset 091 rev 2.2.2 Safety Requirements for the Technical Interoperability of ETCS in Levels 1 & 2 RFI 15. EIRENE System Requirement Specification ver. 14 RFI 16. A11 P6001.11 Morane Radio Trasmission FFFIS for Euroradio RFI 17. ERTMS/ETCS Class 1 FIS for the RBC/RBC Handover”, issue 2.0.0 RFI Norms and Standards EC Directives RFI 18. Disposizione 16/2003 del 12/08/2003 Norme per il progetto di base, le verifiche, le consegne e l’attivazione all’esercizio degli impianti di sicurezza e segnalamento, di controllo e di regolazione della circolazione e di smistamento a gravità RFI 19. Disposizione n. 19 del 18 Aprile 2005 Messa in esercizio della tratta Roma-Napoli e della sub tratta Torino-Novara della linea AV/AC Torino-Milano-Napoli RFI 20. Disposizione n. 22 del 27 Aprile 2005 Disciplina operativa per la messa in esercizio della tratta Roma-Napoli e della sub tratta Torino-Novara della linea AV/AC Torino-Milano-Napoli RFI 21. Disposizione n. 29 del 15/10/2002 “Sviluppo e realizzazione di prodotti e sistemi tecnologici per il segnalamento ferroviario” RFI 22. Disposizione n. 32 del 12/11/2002 “Applicazione della normativa CENELEC di settore allo sviluppo e realizzazione di sistemi e prodotti elettronici in sicurezza per il segnalamento ferroviario” Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 142/161 Standards, Procedures and Specifications RFI TC PR IS 00 009 Applicazione della normativa CENELEC di settore di RFI 23. settore allo sviluppo e realizzazione di sistemi e prodotti elettronici in sicurezza per il segnalamento ferroviario” Rev A del 26/09/2003 RFI 24. Istruzione per le verifiche che devono precedere l’attivazione degli impianti di segnalamento (IS46 Ed. 71) RFI 25. Norme tecniche per l’esecuzione e la certificazione di verifiche di impianti di segnalamento effettuate dalla ditta appaltatrice (IS717 Ed. 91), RFI 26. Norme tecniche per la progettazione, esecuzione, verifiche e prove di impianti di segnalamento (IS381 Ed.82), RFI 27. Nota RFI-DTC\A0011\P\2005\0000688 Tratta di linea AV/AC Roma-Napoli. Nomina delle Commissioni di Verifica Tecnica RFI 28. Linee Guida per le attività della CVT-SA.TLC del 25/05/2005 RFI 29. RFI TC PSCC AVSC 27 002 B Istruzioni CVT SCC AV RFI TC.PATC VT AV02 R01 A “Specifica per verifica tecnica per l’attivazione RFI 30. degli impianti Rilevamento Temperatura Boccole (RTB) e Temperatura Freni (RTF) per tratte AV/AC del 13/06/2005 RFI 31. Procedura “Impianti NVP – Procedura di Verifica Tecnica” Rev. 1 del 30/05/2005 RFI 32. RFI TC.PATC PR AV 02 R21 Procedura di Valutazione Funzionale Progettazione e Realizz.ne Applic. Spec.che Sistema di Segnalamento. ERTMS-SST-SDT Rev B del 08/07/2005 RFI 33. RFI TC.PATC PR AV 02 R02 Definizione dei Confini di Responsabilità sugli Elaborati di un Progetto di Base Applicazione Specifica ERTMS/SST/SDT Rev. A del 09/09/05 RFI 34. RFI TC.PATC VV AV R12 Piano di omologazione Applicazione Generica – I Applicazione Specifica SST – ETCS Livello 2 Rev. A RFI 35. RFI MO-MA-TC DT PRES 001 Procedura per l’effettuazione del Pre-esercizio della Linea AV/AC Roma - Napoli Rev A del 02/09/2005 RFI 36. RFI MO-MA-TC-IN DT INES 001 Tratta AV/AC Roma – Napoli Caratteristiche Infrastrutturali e Programma di Esercizio Complessivo della Tratta del 01/09/2005 RFI Specifications RFI 37. Rif. 1 RFI TC.STEC RS AV 01 G01 Analisi Preliminare del Rischio per la Tratta AV Roma Napoli Rev 4 del 11/02/02 RFI 38. XXXX 00 0 IF SP 000.01 001 Sistema Italiano Alta Velocità - Specifiche di Base del 29/05/1992 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 143/161 RFI 39. DI TC PATC SR AV 01 E02 Specifiche dei Requisiti Funzionali del Sistema di “Controllo Automatico della Marcia del Treno” per la linea ad alta velocità Roma Napoli Rev 0.2 + allegati RFI 40. TC PATC SR AV 01 D01/D02/D03 Linea AV ROMA-NAPOLI - Sistema di Comando/Controllo della marcia dei treni ERTMS/ETCS L2 - Specifica dei Requisiti di Sistema – Volume 1 Rev. B RFI 41. DI TC PATC AV 01 D06 A, Linea AV ROMA-NAPOLI - Sistema di Comando/Controllo della marcia dei treni ERTMS/ETCS L2 - Specifica dei Requisiti di Sistema – Volume 1 - Appendice Gestione Interconnessioni Rev. A01 RFI 42. RFI TC.PATC AV 01 D07 Alimentazione delle Stazioni Radio Base GSM-R Appendice Volume 1 Rev. A del 12/05/2004 RFI 43. RFI TC PATC DC AV 01 R01 Funzionalità Essenziali per Attivazione Sistema di Segnalamento Rev. B del 17/11/2004 RFI 44. RFI TC PATC AV 01 K01 Specifica dei Requisiti di SSB Generale - Volume 3 Rev. A del 31/01/2003 RFI 45. RFI TC PATC AV 01 K02 Specifica dei Requisiti di SSB Gestione Stati e Modi Operativi - Volume 3 Rev A del 31/12/2003 System assessment and approvals RFI 46. RFI-DTC.PATC 032 Valutazione Funzionale Specifica dei Requisiti di Sistema Volume 2 Rev. C del 30/01/2004 RFI 47. RFI-DTC.PATC 126 Linea AV RM-NA. Gestione Interconnessioni - Approvazione Schemi di Principio per il Cambio Sistema del 29/03/2004 RFI 48. RFI-DTC.PATC 322 Linea AV RM-NA. Gestione Interconnessioni - Approvazione Schemi di Principio per il Cambio Sistema del 07/07/2004 RFI 49. RFI-DTC.PATC Approvazione Profili di Linea RTB del 13/02/2004 RFI 50. RFI TC.PATC VV AV R01 Piano di Valutazione Funzionale Applicazione Generica – Prima Applicazione Specifica SST ETCS Livello 2 Rev A RFI 51. RFI TC.PATC VV AV 02 R01 Valutazione Funzionale Specifiche di Test di Sistema Saturno Rev B del 02/02/2005 RFI 52. RFI TC.PATC VV AV 02 R05 Logica RBC - Schemi di principio Rev B del 07/09/2005 RFI 53. RFI TC.PATC VV AV 02 R04 Gestione Non Conformità/ Punti Aperti Rev D del 09/12/2005 RFI 54. RFI TC PATC ST AV 01 DBC A Valutazione Funzionale di Sistema ERTMS/ETCS livello 2 Tratta AV/AC Roma – Napoli, Rev A (presente documento) del 12/12/2005 RFI 55. RFI TC PATC VV AV 02 R79 A Rapporto di Valutazione Funzionale Test in campo, Rev. A Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 144/161 RFI 56. RFI TC PATC VM AV 01 DBD A Test di Valutazione Funzionale sistema ERTMS/ETCS Livello 2 Tratta AV/AC Roma - Napoli, Rev. A del 14/12/2005 RFI 57. Linea AC/AV Roma Napoli Sistema ACS AC/AV – Dossier di Assessment Funzionale – attivazione all’esercizio ferroviario Rev. A RFI 58. RFI TC.PATC VV AV 02 R16 Rapporto di Valutazione Funzionale. Prima Applicazione Specifica 2a Sottotratta Labico-S.Giovanni Rev C del 07/12/2005 RFI 59. CVT-SA.SDT1 A104.24 Rapporto di valutazione funzionale Applicazione Specifica Sottosistema di Terra ETCS livello 2 Tratta AV/AC Roma-Napoli (2° Sottotratta) Rev B del 07/12/05 RFI 60. CVT - AS.SS/TT Verbale Verifica Tecnica dell'applicazione Segnalamento/ Telecomunicazione SST ETCS livello 2 Rev B del 15/12/2005 RFI 61. CVT-SA.SDT1.A104.01 RdV Piani schematici ERTMS Rev A del 09/09/2005 RFI 62. CVT-SA.SDT1.A104.02 RdV delle Tabelle delle Condizioni di RBC Rev B del 06/09/2005 RFI 63. CVT – SA.SDT1.A104.3 Rapporto di Valutazione degli Allacciamenti Rev A del 15/07/2005 RFI 64. CVT – SA.SDT1.A104.4 Rapporto di Valutazione del Layout Interfacce Operatore Rev A del 15/07/2005 RFI 65. CVT – SA.SDT1.A104.5 Rapporto di Valutazione del Layout Apparecchiature nei Locali Rev A del 15/07/2005 RFI 66. CVT – SA.SDT1.A104.6 Rapporto di Valutazione del Layout Armadi Rev A del 15/07/2005 RFI 67. CVT-SA.SDT1.A104.7 Rapporto di Valutazione funzionale PI ERTMS/ETCS Rev C del 09/09/2005 RFI 68. CVT-SA.SDT1.A104.11 Rapporto di Valutazione Funzionale - Misure in Campo Rev C del 09/09/2005 RFI 69. CVT – SA.SDT1.A104.13 Rapporto di Valutazione dell’Interfacciamento TLC-LD Rev A del 09/09/2005 RFI 70. CVT-SA.SDT1.A104.14 Rapporto di Valutazione sulla corretta fornitura, Installazione e Configurazione delle apparecchiature ERTMS/ETCS LIVELLO 2 presso PCS Rev B del 09/09/2005 RFI 71. CVT-SA.SDT1.A104.15 RdV Messaggi Radio Rev A del 04/07/2005 RFI 72. CVT-SA.SDT1.A104.16 RdV Tabelle Intermedie RBC Rev A del 04/07/2005 RFI 73. CVT-SA.SDT1.A104.18 Rapporto di Valutazione sulla correttezza concordanze NVPRBC Rev B del 07/09/2005 RFI 74. CVT – SA.SDT1.A104.19 Rapporto di Valutazione dell’Interfacciamento GSM-R Rev A del 09/09/2005 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 145/161 RFI 75. CVT-SA.SDT1.A104.20 Rapporto di Valutazione Funzionale - Configurazione RBC (MA, CES) Labico - Supino Rev A del 09/09/2005 RFI 76. CVT-SA.SDT1.A104.21 Rapporto di Valutazione Funzionale - Configurazione RBC (MA, CES) Ceccano – S. Giovanni Rev A del 09/09/2005 RFI 77. CVT-SA.SDT1.A104.22 Rapporto di Valutazione Funzionale - Configurazione RBC (MA, CES) Percorsi Deviatoi Labico – S. Giovanni Rev A del 09/09/2005 RFI 78. CVT-SA.SDT1.A104.23 Rapporto di Valutazione Funzionale - Configurazione RBC (ED) Labico – S. Giovanni Rev A del 09/09/2005 RFI 79. CVT – SA.SDT1.A104.25 Relazione Tecnica – Evoluzione della configurazione e relativa analisi di impatto e Non Regressione Rev D del 07/12/2005 RFI 80. CVT – SA.SDT1.A104.26 Rapporto di valutazione funzionale sulla Progettazione Applicativa Eurobalise Rev A del 09/09/2005 RFI 81. CVT – SA.SDT1.A104.27 Rapporto di valutazione funzionale telegrammi Allarmi RTB Rev B del 07/12/2005 RFI 82. RFI TC.PATC RR AV 06 R01 Ricognizione sulla linea AV Roma Napoli, PJ Ceccano, per verifica anormalità CdB Digicode Rev A del 07/09/2005 RFI 83. NVP Colleferro (PT) – Report CVT delle prove in ambiente reale CVT-SA.GdV C1.1 RFI 84. NVP Labico (PC) – Report CVT delle prove in ambiente reale CVT-SA.GdV C1.1 RFI 85. NVP Anagni (PM/PJ) – Report CVT delle prove in ambiente realeCVT-SA.GdV C1.1 RFI 86. NVP Ceccano (PC) – Report CVT delle prove in ambiente reale CVT-SA.GdV C1.2 RFI 87. NVP Ceprano (PT) – Report CVT delle prove in ambiente reale CVT-SA.GdV C1.2 RFI 88. NVP Supino (PT) – Report CVT delle prove in ambiente reale CVT-SA.GdV C1.2 RFI 89. NVP S. Giovanni (PM) – Report CVT delle prove in ambiente reale CVT-SA.GdV C1.2 Permissions RFI 90. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale SST per rilascio Nulla Osta Distanziamento Treni a velocità < 150 km/h sottotratta Labico-Supino Rev. A del 04/07/2005 RFI 91. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale SST per rilascio Nulla Osta Distanziamento Treni a velocità < 300 km/h sottotratta Labico S.Giovanni Rev. B del 18/07/2005 RFI 92. RFI TC PATC SR AV 03 E02 Processo di Omologazione SSB ERTMS Rev. A RFI 93. Nulla Osta Installazione ETR 500 59 del 30/12/04 RFI 94. Nulla Osta SSB per Distanziamento Treni v < 150 Km/h del 25/06/05 RFI 95. Nulla Osta SSB per Distanziamento Treni v < 200 Km/h del 15/07/05 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 146/161 RFI 96. Nulla Osta SSB per Distanziamento Treni v < 275 Km/h del 26/07/05 RFI 97. Nulla Osta SSB per Distanziamento Treni v < 300 Km/h del 08/08/05 RFI 98. Linea Roma Napoli Sistema ACS AC/AV - Dossier di Assessment Funzionale – attivazione al pre-esercizio Rev. A RFI 99. RFI TC.PATC RR AV 03 E06 Relazione conclusiva per il rilascio del Nulla Osta al Pre esercizio del Sotto Sistema di Bordo ERTMS/AV Alstom Rev. A RFI 100. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale Sottosistema di Terra ETCS Livello 2 intera tratta Rev C del 09/09/2005 RFI 101. RFI DT.PATC CO AV 02 Applicazione Generica Sottosistema di Terra ETCS livello 2 della Impresa Alstom Ferroviaria SpA – Certificato per la Accettazione Preliminare Rev A del 12/09/2005 RFI 102. RFI/TC.CC/2927 del 09/09/2005 – Risultanze del processo di Safety Assessment RFI 103. Rapporti mensili del pre-esercizio della Linea AV/AC Roma (n. 4 rapporti) RFI 104. RFI DTC A0011 P 2005 0002025 Rapporto finale sulla esaustività e idoneità del Sistema Regolamentare del 19/12/2005 RFI 105. RFI TC PATC VV AV 02 R89 Relazione sull’esito del pre-esercizio della tratta AV/AC Roma Napoli emesso dalle Direzioni Compartimentali Movimento ed Infrastruttura di Roma e di Napoli Rev A del 09/12/2005 RFI 106. RFI TC PATC VV AV 02 R89 Rapporto di Valutazione Funzionale Applicazione Generica SST ETCS Livello 2 – Risultanze del Pre-esercizio Rev. A RFI 107. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale Sottosistema di Terra ETCS Livello 2 intera tratta Rev D del 09/12/2005 RFI 108. Nota RFI/DTC – PATC.191 del 16/12/2004 RFI 109. Nota DI/TC.SS.TB/009/425 del 29/11/1999 RFI 110. Nota RFI-DTC A0011/P/2005/0001995 del 15/12/2005 RFI 111. Nota RFI-DTC/A0011/P/2005/000663 del 16/05/2005 RFI 112. Nota RFI DT PATC CO AV 02 E01 B Applicazione Generica Sottosistema di Terra ETCS Livello 2 della impresa Alstom Ferroviaria S.p.A. – Certificazione per l’Accettazione Preliminare RFI 113. RFI TC PATC ST AV 01 DBC Rev. A Valutazione Funzionale di Sistema ERTMS/ETCS Livello 2 – Applicazione Generica - Tratta AV/AC Roma Napoli del 14/12/2005 RFI 114. RFI TC CC RR AS 11 001 A Rapporto di Valutazione (Assessment Report) relativo al Sistema di Segnalamento Linea AV Roma – Napoli del 14/12/2005 RFI 115. Linea AC/AV Roma Napoli Sistema ACS AC/AV - Dossier di Assessment Funzionale – attivazione all’esercizio ferroviario Rev. B Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 147/161 RFI 116. RFI TC PATC RR AV 03E09 Relazione conclusiva per il rilascio del Nulla Osta all’esercizio del Sotto Sistema di Bordo ERTMS/AV Alstom – Fase 1 (Progetto ATC/CESIFER) del 09/12/2005 Suppliers Documents Hazard Analysis RFI 117. A104 00 CI1 SQ IS 00 0 0 R07, Fault Tree Analysis – Sistema di Comando e Controllo della marcia dei treni ERTMS/ETCS Livello 2 RFI 118. A104 00 CI1 SQ IS 00 0 0 R06, Analisi FMEA – Sistema di Comando e Controllo della marcia dei treni ERTMS/ETCS Livello 2 RFI 119. A104 00 CI1 2Z IT 0000 020, Hazard Analysis delle Funzioni del SSAV-SST RFI 120. A104 00 CI1 2Z IT 0000 022, Hazard Analysis delle Funzioni del SSAV-SST - Allegato B - Hazard-Log relativo agli Hazard in Stato “Cancellato” RFI 121. A104 00 CI1 2Z IT 0000 039 Analisi dell' Hazardous Failure Rate (HFR) del Sottosistema di Terra ERTMS/ETCS L2 per la linea AV tratta Roma-Napoli RFI 122. Linea AV Roma-Napoli – Specifica dei Requisiti di Sistema, Vol.2 – Sottosistema di Terra RFI 123. A104 00 CI1 2Z IT 0000 063 SSAV-SST - Hazard Analysis delle Funzioni del Sistema SSAV-SST – Specifica dei Requisiti di Sicurezza, rev. A RFI 124. A104 00 CI1 SP IT 0000 003 Linea AV Roma-Napoli Specifica dei Requisiti di Sistema Volume 3 - Sotto Sistema di Bordo Rev A del 01/08/03 RFI 125. A104 00 BI1 RP IS 0000 R14 Tabelle delle Condizioni (TdC) di Linea-Stazione 1-2-3 Sottotratta Rev. A del 04/11/2005 RFI 126. A104 Tabelle delle Condizioni RBC / Integrazione Funzionale di Sottosistema di Terra RFI 127. A104 00 BI 1 PX IS 00 00 R01 Piano Schematico As Build rev.B del 04/11/2005 RFI 128. 37X.B22.C.IS.005641 Sottosistema NVP + GAT Applicazione Generica Safety Case (vers. Logica NVP 5.0) Rev. 00.00 RFI 129. 37X.B22.C.IS.007-641 Sottosistema NVP + GAT Applicazione Generica Safety Case aggiornamento per le nuove versioni di logica NVP (successive a VLA 5.3C1) Rev. 02.00 del 07/11/2005 RFI 130. A104 00 CI1 SP IS 0000 AH2B001 Applicazione Generica Gestione della Via Safety Case (25/01/2005) RFI 131. A104 00 CI1 IS0000 AJ0 Applicazione Generica Gestione della Via Safety Case Aggiornamenti successivi alla versione del 25/01/2005 Rev. C del 30/11/2005 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 148/161 RFI 132. A104 00 CI1 SP IS 0000 AJ2 Sottosistema Segnalamento Terra Gestione della Via Applicazione Specifica seconda sottotratta e PPF di S.Giovanni in Carico Safety Case Aggiornamenti Successivi alla Versione del 16/03/05 Rev. D del 28/11/2005 RFI 133. A104 00 CI1 IS0000 AJ2 Sottosistema Segnalamento Terra Gestione della Via Applicazione Specifica seconda sottotratta e PPF di S.Giovanni in Carico Safety Case Aggiornamenti Successivi alla Versione del 16/03/05 Rev. D del 28/11/2005 RFI 134. A104 00 CI1 IS0000 AJ2 Sottosistema Segnalamento Terra Gestione della Via Applicazione Specifica seconda sottotratta e PPF di S.Giovanni in Carico Safety Case Aggiornamenti Successivi alla Versione del 16/03/05 Rev. D del 28/11/2005 RFI 135. A104 00 CI1 SP IS 0000RG5 Tratta AV Roma Napoli Sottosistema Distanziamento Treni Safety Case di Applicazione Generica del 23/11/2005 RFI 136. A104 00 CI1 SP IS 0000RN0 Tratta AV Roma Napoli Safety Case SDT Applicazione Specifica 2 sottotratta Rev G del 29/11/05 RFI 137. A104 00 CI1 SP IS 0000 RP9 Tratta AV Roma Napoli SDT – Relazione tecnica di sicurezza Rev G del 06/12/2005 RFI 138. A104 00 CI1 2Z IT0000036 Tratta AV Roma Napoli Applicazione Generica Sottosistema di Segnalamento di Terra Safety Case Rev. D del 29/07/2005 RFI 139. A104 00 CI1 2Z IT0000056 Tratta AV Roma Napoli Sottosistema di Segnalamento di Terra Applicazione Specifica II Sottotratta - Safety Case Rev. D del 31/07/2005 RFI 140. A104 00 CI1 2Z IT0000095 Tratta AV Roma Napoli Applicazione Generica – Applicazione Specifica II Sottotratta Sottosistema di Segnalamento di Terra - Safety Case aggiornamento Rev. A del 09/12/2005 RFI 141. [GATC_BSI_RAMS_0040] GATC Trainborne Safety Case, Version 5.4 del 28.10.2005 RFI 142. Dichiarazione di Conformità di Consorzio Saturno DC/001 del 07/09/2005 RFI 143. Dichiarazione di Conformità di Alstom Transport n. AV RM/NA 604/05 del 08/09/2005 RFI 144. Dichiarazione di Conformità di Ansaldo Segnalamento Ferroviario Gestione della Via ASF/05/7501 del 07/09/2005 RFI 145. DC002 Linea AV Roma Napoli Applicazione Specifica di I, II e III Sottotratta Dichiarazione di Conformità del Consorzio Saturno del 09/12/2005 RFI 146. 7513300/1007/05 del 07/12/05 Dichiarazione di Conformità linea AV/AC Milano Napoli Tratta Roma Napoli (Alstom) RFI 147. ASF/05/10636 Linea AV Roma Napoli Applicazione Specifica di I, II e III Sottotratta Dichiarazione di Conformità di ASF del 09/12/2005 13.4 Specific References for the Turin-Novara Project RFI Specifications and assessment documents Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 149/161 RFI 148. RFI TC PATC SR AV 01 E02 Linea AV Torino Novara Funzionalità essenziali per le attivazioni Rev. B del 17/11/2004 RFI 149. RFI-DTC.PATC 187 Valutazione funzionale distanziamento tratta Torino-Novara Logica RBC del 14/012/2004 RFI 150. RFI-DTC.PATC 003 Assessment Funzionale SST ETCS L2 Linea AV/AC Tratte RomaNapoli e Torino-Novara. Non conformità/Punti Aperti del 21/01/2005 RFI 151. RFI-DTC.PATC 078 Assessment Funzionale SST ETCS L2 Linea AV/AC Tratte RomaNapoli e Torino-Novara. Non conformità/Punti Aperti del 21/03/2005 RFI 152. RFI-DTC.PATC 032 Assessment Funzionale SST ETCS L2 Linea AV/AC Tratta Torino-Novara. Non conformità/Chiarimenti del 04/08/2005 RFI 153. RFI-DTC.PATC 347 Sistema Distanziamento Treni ERTMS/ETCS L2 Assessment Funzionale SST ETCS L2 Tratta Torino – Novara: Azioni correttive e soluzioni per Non Conformità/Punti aperti del 17/10/2005 RFI 154. RFI-DTC.PATC 362 Sistema Distanziamento Treni ERTMS/ETCS L2 Assessment Funzionale SST ETCS L2 Tratta Torino – Novara: del 21/10/2005 RFI 155. RFI-DTC.PATC 364 Sistema Distanziamento Treni ERTMS/ETCS L2 Assessment Funzionale SST ETCS L2 Tratta Torino – Novara: del 21/10/2005 Lista delle Non Conformità del 25/10/2005 RFI 156. RFI-DTC.PATC 126 Linea AV RM-NA. Gestione Interconnessioni - Approvazione Schemi di Principio per il Cambio Sistema del 29/03/2004 RFI 157. RFI-DTC.PATC 322 Linea AV RM-NA. Gestione Interconnessioni - Approvazione Schemi di Principio per il Cambio Sistema del 07/07/2004 RFI 158. RFI TC.PATC VV AV 02 R01 Piano di Valutazione Funzionale Applicazione Generica – I Applicazione Specifica SST ETCS Livello 2 Rev A RFI 159. RFI TC PATC VV AV 02 R79 Rapporto di Valutazione Funzionale Sottosistema di Terra Sottosistema di Bordo ETCS Liv. 2 Tratta AV/AC Torino Novara Rev. E del 06/02/2006 RFI 160. RFI TC.PATC VV AV 02 R82 Gestione Non Conformità/ Punti Aperti Rev C del 06/02/2006 RFI 161. RFI TC PATC VM AV 01 DBE A Valutazione Funzionale di Sistema ERTMS/ETCS livello 2 Tratta AV/AC Torino-Novara, Rev A (presente documento) del 06/02/2006 RFI 162. RFI TC PATC VM AV 01 DA3 A Test di Valutazione Funzionale sistema ERTMS/ETCS Livello 2 Tratta AV/AC Torino – Novara, Rev. A del 06/11/2005 RFI 163. RFI TC PATC VV AV 01 DA5 A Test Report di Valutazione Funzionale sistema ERTMS/ETCS Livello 2 Tratta AV/AC Torino – Novara, Rev. A del 04/02/2006 RFI 164. RFI.TCPA RT SI 08 044 Linea AC/AV Tratta Torino-Novara Sistema ACS AC/AV Dossier di Assessment Funzionale – attivazione all’esercizio ferroviario Rev. B Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 150/161 RFI 165. CVT – SA.SDT.A201.24 - Rapporto di valutazione funzionale Applicazione Specifica Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. D del 06/02/06 RFI 166. CVT – SA.SDT.A201.01 - CVT – SA.SDT Rapporto di Valutazione Funzionale Piano Schematico ERTMS/ETCS LIVELLO 2 Torino – Novara Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev.B del 16/01/06 RFI 167. CVT-SA.SDT.A201.02 - CVT-SA.SDT Rapporto di valutazione funzionale Tabella delle Condizioni di RBC Sottosistema di Terra ETCS livello 2 Tratta AV/AC TorinoNovara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del 25/10/05 RFI 168. CVT-SA.SDT.A201.03 - CVT-SA.SDT Rapporto di valutazione funzionale Layout interfaccia operatore Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del 25/10/05 RFI 169. CVT-SA.SDT.A201.04 - CVT-SA.SDT Rapporto di valutazione funzionale Allacciamenti Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del 25/10/05 RFI 170. CVT-SA.SDT.A201.05 - CVT-SA.SDT Rapporto di valutazione funzionale Layout apparecchiature nei locali Sottosistema di Terra ETCS livello 2 Tratta AV/AC TorinoNovara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del 25/10/05 RFI 171. CVT-SA.SDT.A201.06 - CVT-SA.SDT Rapporto di valutazione funzionale Layout Armadi Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del 25/10/05 RFI 172. CVT – SA.SDT.A201.07 - CVT – SA.SDT Rapporto di valutazione funzionale Punti Informativi ERTMS/ETCS Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. B del 16/01/06 RFI 173. CVT – SA.SDT.A201.08 -CVT – SA.SDT Rapporto di valutazione funzionale Punti Informativi ERTMS/ETCS Tratta Settimo – Novara da km. 0+786 a km. 84+758 Letture Punti Informativi e Confronto con Telegrammi di Progetto Rev. A del 25/10/05 RFI 174. CVT – SA.SDT.A201.09 - CVT – SA.SDT Rapporto di valutazione funzionale Misure in Campo ERTMS/ETCS LIVELLO 2 e non Tratta Settimo – Novara da km. 0+786 a km. 84+758 Tabelle misure (punte scambi, traverse limite, punti informativi, cartelli EoA, giunti elettrici) Rev. A del 25/10/05 RFI 175. CVT – SA.SDT.A201.11- CVT – SA.SDT Rapporto di valutazione funzionale Misure in Campo ERTMS/ETCS LIVELLO 2 e non Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. B del 16/01/06 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 151/161 RFI 176. CVT - SA.SDT.A201.13 - CVT-SA.SDT Rapporto di valutazione funzionale Corretta Configurazione delle Interfacce TLC-LD Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del 25/10/05 RFI 177. CVT - SA.SDT.A201.14 - CVT-SA.SDT Rapporto di Valutazione Funzionale Fornitura, Installazione e Configurazione delle apparecchiature ERTMS/ETCS Livello 2 presso PCS Rev. A del 19/10/05 RFI 178. CVT-SA.SDT1.A201.15 - CVT-SA.SDT Rapporto di valutazione funzionale Tabelle delle MA Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. B del 17/01/06 RFI 179. CVT-SA.SDT.A201.18 - CVT-SA.SDT Rapporto di valutazione funzionale Concordanza dati NVP – RBC Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. B del 13/01/06 RFI 180. CVT - SA.SDT1.A201.19 - CVT - SA.SDT1.A201.19 - CVT-SA.SDT Rapporto di Valutazione Funzionale Configurazione delle Interfacce GSM-R Rev. A del 19/10/05 RFI 181. CVT-SA.SDT.A201.20 - CVT-SA.SDT Rapporto di valutazione funzionale della Configurazione RBC (Tabelle delle Condizioni / Tabelle dei Messaggi Radio) Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione Specifica Intera Sottotratta Rev. B del 17/01/06 RFI 182. CVT – SA.SDT.A201. 25 - CVT – SA.SDT Relazione Tecnica SSAV To-No SDT ANSALDO Tratta Settimo – Novara da km. 0+786 a km. 84+758 Evoluzione della configurazione e relative analisi di impatto e non regressione Rev. D del 05/02/06 RFI 183. CVT – SA.SDT.A201.26 - CVT – SA.SDT Rapporto di valutazione funzionale Progettazione Applicativa Eurobalise Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. B del 16/01/06 RFI 184. CVT – SA.SDT.A201.27 - CVT – SA.SDT Rapporto di valutazione funzionale Progettazione Applicativa Eurobalise RTB Rev A del 21/11/05. RFI 185. CVT –SA.SDT/SA.TLC Rapporto di Valutazione Interrelazione CVT SDT – TLC – LD Rev. A del 09/11/2005 RFI 186. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS L2 per rilascio Nulla Osta Distanziamento Treni a velocità < 150 km/h Rev. B del 30/12/2005 RFI 187. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS L2 per rilascio Nulla Osta Distanziamento Treni a velocità < 300 km/h Rev. D del 02/02/2005 RFI 188. RFI TC PATC SR AV 03 E02 Processo di Omologazione SSB ERTMS Rev. A RFI 189. Nulla Osta Installazione ETR 500 59 del 30/12/04 RFI 190. RFI-DTC/A0011/P/2005/0001853 Nulla Osta SSB per Distanziamento Treni v < 150 Km/h del 24/11/05 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 152/161 RFI 191. Nulla Osta SSB per Distanziamento Treni v < 200 Km/h del 15/07/05 RFI 192. Nulla Osta SSB per Distanziamento Treni v < 275 Km/h del 26/07/05 RFI 193. Nulla Osta SSB per Distanziamento Treni v < 300 Km/h del 08/08/05 Documents about approbatory period RFI 194. RFI.TCPA RT SI 08 044 Linea AC/AV Tratta Torino-Novara Sistema ACS AC/AV Dossier di Assessment Funzionale – attivazione al pre-esercizio Rev. A RFI 195. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS L2 per Pre-esercizio Rev. A del 25/11/2005 RFI 196. RFI DT PATC CO AV 02 E02 A Applicazione Generica Sottosistema di Terra ETCS Livello 2 della impresa Ansaldo Segnalamento Ferroviario S.p.A. – Certificazione per l’Accettazione Preliminare RFI 197. RFI/TC.CC/2972 del 28/10/2005 – Risultanze del processo di Safety Assessment Sistema di Segnalamento AV Torino – Novara RFI 198. RFI DTC A0011 P 2005 0002025 Rapporto finale sulla esaustività e idoneità del Sistema Regolamentare del 19/12/2005 (Attività svolta nella fase di pre-esercizio della Roma Napoli) RFI 199. RFI TC PATC VV AV 02 R91 Rapporto di Valutazione Funzionale Applicazione Generica SST ETCS Livello 2 Tratta Torino – Novara – Risultanze del Pre-esercizio Rev. A del 06/02/06 Documents about revenue service RFI 200. Nota RFI/DTC – PATC.191 del 16/12/2004 RFI 201. Nota DI/TC.SS.TB/009/425 del 29/11/1999 RFI 202. Nota RFI-DTC/A0011/P/2006/0000184 del 02/02/2006 RFI 203. Nota RFI-DTC/A0011/P/2005/000663 del 16/05/2005 RFI 204. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS L2 per Pre-esercizio Rev. E del 06/02/2006 RFI 205. RFI.TCPA RT SI 08 044 Linea AC/AV Tratta Torino-Novara Sistema ACS AC/AV Dossier di Assessment Funzionale – attivazione all’esercizio ferroviario Rev. B RFI 206. RFI DT PATC CO AV 02 E02 B Applicazione Generica Sottosistema di Terra ETCS Livello 2 della impresa Ansaldo Segnalamento Ferroviario S.p.A. – Certificazione per l’Accettazione Preliminare RFI 207. RFI TC PATC VM AV 01 DBE Rev. A Valutazione Funzionale di Sistema ERTMS/ETCS Livello 2 – Applicazione Generica - Tratta AV/AC Torino Novara del 06/02/2006 (Presente report) RFI 208. RFI TC CC RR AS 11 002 A Rapporto di Valutazione (Assessment Report) relativo al Sistema di Segnalamento Linea AV Torino - Novara del 06/02/2006 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 153/161 RFI 209. RFI TC PATC RR AV 03E09 Relazione conclusiva per il rilascio del Nulla Osta all’esercizio del Sotto Sistema di Bordo ERTMS/AV Alstom – Fase 1 (Progetto ATC/CESIFER) del 09/12/2005 Suppliers Documents Hazard Analysis RFI 210. A104 00 CI1 SQ IS 00 0 0 R07, Fault Tree Analysis – Sistema di Comando e Controllo della marcia dei treni ERTMS/ETCS Livello 2 RFI 211. A104 00 CI1 SQ IS 00 0 0 R06, Analisi FMEA – Sistema di Comando e Controllo della marcia dei treni ERTMS/ETCS Livello 2 RFI 212. A104 00 CI1 2Z IT 0000 020, Hazard Analysis delle Funzioni del SSAV-SST RFI 213. A104 00 CI1 2Z IT 0000 022, Hazard Analysis delle Funzioni del SSAV-SST - Allegato B - Hazard-Log relativo agli Hazard in Stato “Cancellato” RFI 214. A104 00 CI1 2Z IT 0000 039 Analisi dell' Hazardous Failure Rate (HFR) del Sottosistema di Terra ERTMS/ETCS L2 per la linea AV tratta Roma-Napoli RFI 215. A201 19 C F2 IS 00 0B A01 F Safety Case della integrazione tra SST ASF e SSB ALSTOM tratto Torino Novara del 04/02/06 Specifications RFI 216. A201 19 CF2 1S IS0000 A04 Volume 2 – Specifica Generale di Sistema –Sistema di Segnalamento Rev. A RFI 217. A201 19 CF2 1W IS0000 A01 Volume 2 – Sottosistema di Distanziamento Rev. E RFI 218. A201 09 CF2 1W IS0000 A01 Volume 2 – Sottosistema Interlocking Rev. A RFI 219. A201 09 CF2 1W IS0000 A01 Volume 2 – Sottosistema Interconnessioni AC/AV –LS (Transizione L2 LT) Rev. A RFI 220. A201 09 CF2 1RLD 0000 X01 Volume 2 – Sottosistema Lunga Distanza-Relazioni _Architettura di Rete e Descrizione Funzionale Sottosistema Lunga Distanza Rev. B RFI 221. A104 00 CI1 2Z IT 0000 063 SSAV-SST - Hazard Analysis delle Funzioni del Sistema SSAV-SST – Specifica dei Requisiti di Sicurezza, rev. A RFI 222. A104 00 CI1 SP IT 0000 003 Linea AV Roma-Napoli Specifica dei Requisiti di Sistema Volume 3 - Sotto Sistema di Bordo Rev A del 01/08/03 RFI 223. A201 09 C F2 1T IS 00 0B A02 Tabella delle Condizioni RBC1 (Settimo – Balocco) Rev E RFI 224. A201 09 C F2 1T IS 00 0B A03 Tabella delle Condizioni RBC2 (Recetto – Novara Ovest) Rev.E RFI 225. A201 19 C F2 1P IS 00 00 A01 Piano Schematico di linea ERTMS Liv.2 Tratta TorinoNovara Rev. F Safety Cases Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 154/161 RFI 226. 37X.B22.C.IS.005641 Sottosistema NVP + GAT Applicazione Generica Safety Case (vers. Logica NVP 5.0) Rev. 00.00 RFI 227. 37X.B22.C.IS.007-641 Sottosistema NVP + GAT Applicazione Generica Safety Case aggiornamento per le nuove versioni di logica NVP (successive a VLA 5.3C1) Rev. 02.00 del 07/11/2005 RFI 228. A104 00 CI1 SP IS 0000 AH2B001 Applicazione Generica Gestione della Via Safety Case (25/01/2005) RFI 229. A104 00 CI1 IS0000 AJ0 Applicazione Generica Gestione della Via Safety Case Aggiornamenti successivi alla versione del 25/01/2005 Rev. C del 30/11/2005 RFI 230. A201 19 C F2 1S IS 00 00 A33 APPLICAZIONE GENERICA GESTIONE DELLA VIA Safety Case Rev.C 25/10/05 RFI 231. A201 19 C F2 3W IS 00 00 A21 SOTTOSISTEMA SEGNALAMENTO TERRA GESTIONE DELLA VIA - APPLICAZIONE SPECIFICA - Tratta Torino – Novara SAFETY CASE Rev C del 24/11/05 RFI 232. A201 19 C F2 3W IS 00 00 A11 Tratta AV Torino-Novara - Applicazione Generica Sottosistema di Distanziamento Treni - Safety Case Rev. M 15/12/06 RFI 233. A201 19 C F2 3W IS 00 00 A20 Tratta AV Torino-Novara - Applicazione Specifica Sottosistema di Distanziamento Treni - Safety Case Rev L Emesso in data: 15/12/06 RFI 234. A201 19 CF2 3W IS0000 A15 Tratta AV Torino Novara Applicazione Generica Sottosistema di Segnalamento di Terra Safety Case Rev. D del 31/01/2006 RFI 235. A201 19 CF2 3W IS0000 A19 Tratta AV Torino Novara Applicazione Specifica Sottosistema di Segnalamento di Terra - Safety Case Rev. C del 31/01/2006 RFI 236. [GATC_BSI_RAMS_0040] GATC Trainborne Safety Case, Version 5.4 del 28.10.2005 RFI 237. A201 19 C F2 IS 00 0B A01 F Safety Case della integrazione tra SST ASF e SSB ALSTOM tratto Torino Novara del 04/02/06 RFI 238. A201 19 C F2 IS 00 0B A01 F Safety Case della integrazione tra SST ASF e SSB ALSTOM tratto Torino Novara del 04/02/06 Conformity declarations for the approbatory period RFI 239. ASF/2005/10062 Tratta AV Torino Milano Sottotratta Torino Novara Sottosistema di Segnalamento di Terra Applicazione Specifica Dichiarazione di conformità del 25/11/05 RFI 240. A201 19 C F2 IS 00 0B A01 A Rapporto delle Verifiche di integrazione tra SST ASF e SSB ALSTOM del 25/11/05 Conformity declarations for the revenue service RFI 241. ASF/RMS 726/2006 Tratta AV Torino Milano Sottotratta Torino Novara Sottosistema di Segnalamento di Terra Applicazione Specifica Dichiarazione di conformità del 06/02/06 Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 155/161 13.5 References for the Dutch and Belgian projects PROR 1. Wikipedia (General information) PROR 2. www.infrabel.be PROR 3. Implementing ERTMS on the Betuweroute, Signal+Draht 5/2007 PROR 4. ERTMS/ETCS/GSM-R on the Belgian high speed lines L3 and L4, Signal+Draht 6/2007 PROR 5. ProRail ERTMS trainborne integration plan A15 tracé, Version 2.0 PROR 6. www.prorail.nl 13.6 References for the Spanish projects RENFE 1 Annex 1 – GIF “III Normativa y Recomendaciones de Aplication” RENFE 2 Annex II – “Condiciones tecnicas de los trenes (CTT)” RENFE 3 Annex III – SIEMENS TS Rolling Stock “Estudio de la seguridad funcional Vehiculos Ferroviarios AVE S103” RENFE 4 Annex IV – SIEMENS “Sicherheitsnachweis S103 EVC España AVE S102/S103 TRAINGUARD 200 EVC” RENFE 5 Annex V – SIEMENS “Informe de validacion del sistema del S103 EVC España AVE S102/S103 TRAINGUARD 200 EVC” RENFE 6 Annex VI – SIEMENS TS Rolling Stock “Estudio de la seguridad funcional Vehiculos Ferroviarios AVE S103 – Exported rules ” RENFE 7 Annex VII – “Alta Velocidad Cordoba-Malaga Analisis preliminar de riesgos de la aplication especifica de la linea Cordoba-Malaga” RENFE 8 Annex VIII – “Analisis preliminar de amenacas de la aplication especifica de la linea Cordoba-Malaga de Dimetronic ” RENFE 9 Annex IX – “Caso de seguridad-Applicacion Especifica Cordoba-Malaga” RENFE 10 Annex X – ADIF “Sistema Europeo de circulation de trenes ERTMS/ETCS” Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 156/161 List of abbreviations and acronyms AC Alternating Current ACS Apparato Centrale Statico (Italy) ADIF Administrador de Infrastructuras Ferroviarias (Spain) ADL Arthur D. Little AEIF Association Européenne pour l’Interopérabilité Ferroviaire AF Alstom Ferroviaria (Italy) APR Analyse Préliminaire des Risques (Preliminary Risk Analysis) ASF Ansaldo Segnalamento Ferroviario (Italy) ASFA Anuncio de Señales y Frenado Automáticoe (Spain) ATB Automatische TreinBeïnvloeding ATO Automatic Train Operation ATP Automatic Train Protection B Belgium BACC Blocco Automatico a Correnti Codificate (Italy) BBT Brenner Basis Tunnel BHL Berlin Halle Leipzig BMB Bombardier BSC Base Station Controller BTM Balise Transmission Module BTS Base Transceiver Station CCS Command, Control and Signalling CERTIFER French Notified Body Cetren Spanish Notified Body CIRCA Communication & Information Resource Centre Administrator CR Change Request CSI Concentrateur de Systèmes Informatiques (IT Systems Hub) CTT Condiciones Tecnica de los Trenes (Spain) DB Deutsche Bahn (German Railways) DC Direct Current Designers choice DMI Driver Machine Interface DPS Dossier Préliminaire de Sécurité (Preliminary Safety File) DS Dossier de Sécurité (Safety File) DTS Directives pour Travaux de Signalisation (Signalling Works Directives) DTT Direction des Transports Terrestres (Land Transport Division) Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 157/161 DV Dienstvorschrift (Service order) EBC German Notified Body EC European Commission EEIG European Economic Interest Group EIRENE European Integrated Railway radio Enhanced NEtwork ENCE Enclavamiento Electrónico (Electronic interlocking) EOA End Of movement Authority EOQA Expert ou Organisme Qualifié, Agréé (Qualified Approved Expert or Organisation) ERA European Railway Agency ERTMS European Rail Traffic Management System ETCS European Train Control System ETG Elément à Turbine à Gaz (Gas Turbine Element) ETH Especificacion Técnica de Homologación (Technical Specification for Homologation) EU European Union EVC European Vital Computer FDMS Fiabilité, Disponibilité, Maintenabilité, Sécurité (Reliability, Availability, Maintainability, Safety) FFFIS Form Fit Function Interface Specification FIS Functional Interface Specification FMEA Failure Mode Effect Analysis FN Funcion Nacional (National Function) FS Full Supervision mode FTA Fault Tree Analysis GAMAB Globalement Au Moins Aussi Bon (Overall At Least As Good) GAME Globalement Au Moins Equivalent (Overall At Least Equivalent) GASC Generic Application Safety Case GAT Gestione ATtuatori (Italy) GdV Gestione della Via (Italy) GEST Poste de Gestion des Signalisations Temporaires (Temporary Signals Management Station) GSM-R Global System for Mobile Communications - Railways HA Hazard Analysis HABD Hot Axle Box Detector HC/HSL High Capacity/High Speed Line HSL High Speed Line Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 158/161 IC Interoperability Constituent ICE 3 Inter City Express – 3rd generation IM Infrastructure Manager IS Impianto di Segnalamento (Italy) ISA Independent Safety Assessor IVW Inspectie Verkeer en Waterstaat (Dutch Safety Authority) IXL Interlocking KMAC Authentication Key KMC Key Management Centre KVB Contrôle de Vitesse par Balise (Balise Speed Control) LAV Línea de Alta Velocidad (High speed line) LC Level crossing LD Long Distance LEU Line side Electronic Unit LGV-Est Ligne à Grande Vitesse Est (French High Speed Line to the East) LTV Limitation Temporaire de Vitesse (Temporary Speed Limit) LZB Linien ZugBeeinflüssung (German ATP-system) MA Movement Authority MISTRAL Modules Informatiques de Signalisation, de Transmission et d’Alarmes (Signal, Transmission and Alarm IT Modules) MSC Mobile-services Switching Centre MTBF Mean Time Between Failures MTTR Mean Time To Repair NL The Netherlands NMBS Nationale Maatschappij der Belgische Spoorwegen (Belgian Railways) NoBo Notified Body NSA National Safety Authority NVP Nucleo Vitale Periferico (Italy) OBB Österreichische Bundesbahn (Austrian Railways) OBU On Board Unit ON Organisme Notifié (Notified Body) OS On Sight mode OSTI Organisme ou Service Technique Indépendant (Independent Technical Organisation or Service) PCS Posto Centrale Satellite (Italy) POS Paris-Ost-Frankreich-Süd-Deutschland (Paris – Eastern France – Southern Germany) Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 159/161 PPF Posto Periferico Fisso (Italy) PRCI Poste a Relais a Commande Informatisée (France) PSC Project Safety Case PZB Punktförmige ZugBeeinflüssung (German ATP-system) QoS Quality of Service RA Risk Analysis RAMS Reliability, Availability, Maintainability, Safety RBC Radio Block Centre RENFE Red Nacional de Ferrocarriles Españoles (Spain) RFF Réseau Ferré de France (French Infrastructure Manager) RFI Rete Ferroviaria Italiana (Italian Infrastructure Manager) RFIG Red Ferroviaria de Interes General (Main Railway Network of Spain) RFU Recommendation For Use RTB Rilevatore Temperature Boccole (Hot Axle Box Detector) SAM Système d’Aide à la Maintenance (Maintenance Support System) SCC-AV Sistema Controllo e Comando - Alta Velocità (Control-Command System – High Speed) SCMT Sistema Controllo Marcia Treno (Italian ATP-system) SDT Sistema Distanziamento Treni (Italy) SEI Système d’Enclenchements Intégrés (France) SH SHunting mode SIST Sécurité des Infrastructures et des Systèmes de Transport (Infrastructure and Transport Systems Safety) SMB StopMerkBorden (Marker Boards) SNCB Société Nationale des Chemins de fer Belges (Belgian Railways) SNCF Société Nationale des Chemins de Fer (French Railways) SNCF IES SNCF Direction Déléguée Système d’Exploitation et Sécurité (SNCF Operational and Safety System Delegated Division) SNCF IG.SF SNCF Direction de l’InGénierie - Signalisation Ferroviaire (SNCF Engineering Division – Rail Signals) SNCF IG.T.ERTMS SNCF direction de l’InGénierie – Projet ERTMS (SNCF Engineering Division – ERTMS Project) SNCF IG.T.SE SNCF direction de l’InGénierie – Systèmes et Exploitation (SNCF Engineering Division – Systems and Operation) SR Staff Responsible mode SRAC Safety Related Application Condition SRFN Sécurité du Réseau Ferré National (France) SRS System Requirement Specification Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 160/161 SSB Sottosistema di Bordo (On Board assembly) SST Sottosistema di Terra (Track side assembly) STM Specific Transmission Module STTE Signalisations Temporaires propres à la Traction Electrique (Electronic Traction Temporary Signals) TAF Track Ahead Free TBL Transmission Balise Locomotive (Belgian ATP-system) THR Tolerable Hazard Rate TIRF Tolerable Individual Rate of Fatalities TIU Train Interface Unit TLC Telecommunication TOC Train Operating Company TSI Technical Specification for Interoperability TSI CR Technical Specification for Interoperability Conventional Rail system TSI HS Technical Specification for Interoperability High Speed Rail system TSI OPE Technical Specification for Interoperability of the subsystem Traffic Operation and Management TSR Temporary Speed Restriction TVM430 Track to Train Transmission 430 (French ATP-system) UN UNfitted mode UNISIG UNion Industry of SIGnaling WP Work Package ZN Zona Neutra (Neutral Zone in catenary system) Survey of safety approvals for the first ERTMS implementations WP2 Final Report on Analysis of Safety Approval Process – 17 September 2007 161/161