Project Report - San Francisco Public Utilities Commission
Transcription
Project Report - San Francisco Public Utilities Commission
Final Report CS-199 Planning Support Services for Auxiliary Water Supply System (AWSS) Project Report Prepared for SFPUC February 2014 Prepared by A Joint Venture 300 California St, Suite 400, San Francisco, CA 94104 This report was prepared in accordance with generally accepted professional engineering practice. AECOM/AGS JV is making estimations/projections/recommendations based upon limited information that has been made available to them from SFPUC and through industry standard methodologies and techniques. Such estimations/projections/recommendations are subject to many factors that are beyond the control of AECOM/AGS JV; and thus, AECOM/AGS JV makes no representations or warranties, either expressed or implied, with respect to such estimations/projections/recommendations and disclaim any responsibility for deviations from the data presented in this report with respect to the outcome of future events. CS-199 AWSS Facilities Preliminary Options Study I Task 11 Project Report Contents Table of Contents Contents............................................................................................................................................. ii Acronyms and Abbreviations ....................................................................................................... vii Executive Summary ......................................................................................................................... ix 1.0 Introduction.............................................................................................................................. 1 1.1 Background ................................................................................................................... 1 1.2 Scope of Work ............................................................................................................... 1 1.3 Outline of Project Report .............................................................................................. 2 1.4 Methodology to Evaluate Program Alternatives ........................................................ 2 1.4.1 Needs Assessment and Project Definition ...................................................... 5 1.4.2 Development of Program Alternatives ........................................................... 5 1.4.3 Analysis and Evaluation of Alternatives ........................................................ 6 1.4.4 Preferred Program Alternative ........................................................................ 6 2.0 Needs Assessment and Project Definition ............................................................................. 7 2.1 AWSS Background and Purpose ................................................................................. 7 2.2 Facility Descriptions ................................................................................................... 11 2.3 AWSS Operations and Maintenance ......................................................................... 15 2.4 Review of Existing Information ................................................................................. 16 2.5 Condition of Existing Assets ...................................................................................... 16 2.6 Needs Definition ......................................................................................................... 17 2.7 2.6.1 LOS Criteria and Performance Goals ............................................................ 17 System Deficiencies ..................................................................................................... 22 2.8 Project Identification ................................................................................................... 27 2.9 Project Analyses .......................................................................................................... 29 2.10 Project Performance/Sizing Criteria ......................................................................... 29 2.10.1 Pipe Fragility ................................................................................................... 30 2.10.2 Non Earthquake Hydraulic Model Results .................................................. 32 2.10.3 Post-Earthquake Hydraulic Model Results .................................................. 32 2.10.4 Project Configuration ..................................................................................... 32 3.0 Program Alternatives............................................................................................................. 35 3.1 Development and Description of Program Alternatives ......................................... 35 3.2 Non-Construction Alternatives.................................................................................. 42 CS-199 AWSS Facilities Preliminary Options Study II Task 11 Project Report 3.3 Data Gaps .................................................................................................................... 43 4.0 Alternatives Evaluation and Scoring .................................................................................... 44 4.1 Evaluation Process ...................................................................................................... 44 4.2 Criteria for Analysis and Evaluation of Alternatives ............................................... 45 4.3 Cost .............................................................................................................................. 46 4.4 Operations and Maintenance ..................................................................................... 49 4.5 Schedule ....................................................................................................................... 50 4.6 Water Supply Delivery Reliability ............................................................................. 51 4.7 Fire Fighting ................................................................................................................ 55 4.8 Insurance Premiums Benefits..................................................................................... 59 4.9 Environmental/Community Impacts........................................................................ 59 5.0 Preferred Program Alternative ............................................................................................. 62 5.1 Scoring and Ranking of Preferred Program Alternative .......................................... 62 5.2 Review and Recommendations.................................................................................. 63 5.3 Environmental Review ............................................................................................... 64 5.4 Funding and Staging................................................................................................... 66 5.5 Schedule ....................................................................................................................... 68 5.6 5.5.1 Schedule Constraints ...................................................................................... 68 5.5.2 Schedule .......................................................................................................... 70 Project Considerations ................................................................................................ 72 6.0 Operational Strategy .............................................................................................................. 73 6.1 Current Operational Strategy ..................................................................................... 73 6.2 6.1.1 Normal Operations ......................................................................................... 73 6.1.2 System Roles, Responsibilities, Staffing, and Training ................................ 73 6.1.3 CDD Staffing ................................................................................................... 73 6.1.4 Normal Valve Settings ................................................................................... 75 Operational Changes Considered .............................................................................. 80 6.3 Evaluation of Operational Changes........................................................................... 80 6.4 PWSS Assumptions..................................................................................................... 82 6.5 Recommended Operational Strategy......................................................................... 86 7.0 Non-Construction Recommendations .................................................................................. 87 8.0 Additional Assessment of Risk and Use of Potable or Co-Benefit System ........................ 90 9.0 AWSS Program Justification ................................................................................................. 95 10.0 Supplemental Condition Assessments ................................................................................. 98 10.1 Task 13.2 Materials Testing ........................................................................................ 98 CS-199 AWSS Facilities Preliminary Options Study III Task 11 Project Report 10.2 Task 13.4 Pump Station 2 Alternatives .................................................................... 100 11.0 Conclusions and Recommendations .................................................................................. 102 References...................................................................................................................................... 105 Appendix A: Project Data Sheets................................................................................................. 106 Appendix B: Cost Information..................................................................................................... 107 B.1 Project Cost Estimates ................................................................................................... 107 B.2 Annual Operation & Maintenance Costs ..................................................................... 107 B.3 Program Alternative Capital Costs............................................................................... 107 B.4 Life Cycle Costs .............................................................................................................. 107 B.5 Updated Potable Co-Benefits Costs .............................................................................. 107 Appendix C: Program Alternative Schedules ............................................................................ 108 Appendix D: Insurance ................................................................................................................ 109 Appendix E: Evaluation Scoring ................................................................................................. 110 CS-199 AWSS Facilities Preliminary Options Study IV Task 11 Project Report List of Figures Figure 1-1. Evaluation Methodology Schematic ................................................................................ 4 Figure 2-1. Existing Auxiliary Water Supply System ........................................................................ 9 Figure 2-2. Loma Prieta Marina Breaks............................................................................................. 10 Figure 2-3. AWSS Pressure Schematic .............................................................................................. 14 Figure 2-4. Fire Response Areas ........................................................................................................ 19 Figure 2-5. Existing System Delivery Reliability by FRA ................................................................ 21 Figure 2-6. Gatebook vs. AECOM/AGS Infirm Zones ................................................................... 31 Figure 3-1. Step vs. Ramp Function of Pipeline vs. Cisterns ........................................................... 37 Figure 3-2. Alternative A.................................................................................................................... 39 Figure 3-3. Alternative B .................................................................................................................... 40 Figure 3-4. Alternative C .................................................................................................................... 41 Figure 4-1. Alternative A Delivery Reliability by FRA .................................................................... 52 Figure 4-2. Alternative B Delivery Reliability by FRA..................................................................... 53 Figure 4-3. Alternative C Delivery Reliability by FRA .................................................................... 54 Figure 4-4. Probability of Fire Engine Need Exceeding Availability .............................................. 57 Figure 5-1. Preferred Alternative Planning Level Schedule ............................................................ 71 Figure 6-1. Recommended AWSS Pipe With Buffers ...................................................................... 83 Figure 6-2. Distribution of PWSS Needed (Alternatives A and B) ................................................. 84 Figure 6-3. Distribution of PWSS Needed (Alt. C) ........................................................................... 85 Figure 8-1. Reliability Scores with Potable Water Contribution ..................................................... 91 Figure 8-2. Potable Co-Benefits System ............................................................................................ 93 Figure 9-1. Loss vs. Reliability Correlation....................................................................................... 96 Figure 10-1. Photograph of Unnotched Broken Samples ................................................................ 99 List of Tables Table ES-1. Non-Construction Recommendations............................................................................. x Table ES-2. Recommended Future Projects ....................................................................................... xi Table 2-1. Analysis and Modeling Tools........................................................................................... 18 Table 2-2. System Deficiencies ........................................................................................................... 22 Table 2-3. List of Potential Projects – Needs Identification ............................................................. 27 Table 2-4. Selection of Improvement Projects................................................................................... 33 Table 3-1. Alternative Program Prioritization .................................................................................. 35 Table 3-2. Potential Water Volume Loss and Tank Duration.......................................................... 36 Table 3-3. Program Alternatives ........................................................................................................ 38 Table 3-4. Deficiencies Addressed by Non-Construction Alternatives .......................................... 42 Table 4-1. Scoring of Pair-Wise Comparisons .................................................................................. 45 Table 4-2. Capital Cost Assumptions ................................................................................................ 47 Table 4-3. Life Cycle Cost Assumptions ........................................................................................... 48 Table 4-4. Cost Comparison of Original Program Alternatives including all Projects.................. 48 Table 4-5. Number of New Facilities Requiring Maintenance ........................................................ 49 Table 4-6. Comparison of Serviceability and Citywide Delivery Reliability ................................. 55 Table 4-7. Deployment Time and Resources by Water Source ....................................................... 56 Table 4-8. Firefighting Resources and Deployment Time Comparison by Alternative ................ 58 CS-199 AWSS Facilities Preliminary Options Study V Task 11 Project Report Table 4-9. Summary of Insurance Impacts (MMI Engineering) ...................................................... 59 Table 4-10. Summary of Environmental Effects ............................................................................... 61 Table 5-1. Evaluation Criteria Weighting ......................................................................................... 62 Table 5-2. Alternative Scoring ........................................................................................................... 63 Table 5-3. Evaluation Ranking of Alternatives................................................................................. 63 Table 5-4. Independent Utility Criteria ............................................................................................. 65 Table 5-5. Independent Utility of AWSS Projects............................................................................. 65 Table 5-6. Potential Funding .............................................................................................................. 67 Table 6-1. Closed Division Gate Valve Locations ............................................................................ 76 Table 6-2. Seismic Isolation Valve Locations and Status (pre-earthquake).................................... 77 Table 6-3. Seismic Isolation Valve Status (post-earthquake) ........................................................... 79 Table 6-4. Hydraulic Analysis of Operational Changes (No pipe breaks or leaks) ....................... 81 Table 6-5. GIRAFFE Comparison of Infirm Zone Isolation ............................................................. 82 Table 6-6. Summary of PWSS Needs................................................................................................. 84 Table 7-1. Non-Construction Recommendations ............................................................................. 88 Table 8-1. Comparing Reliability with Mw7.8 Event vs. All Events .............................................. 90 Table 9-1. Predicted Loss from Fire Following Earthquake ............................................................ 95 Table 9-2. Property Loss vs. Business Interruption Costs ............................................................... 97 Table 9-3. Benefits and Costs of Improved AWSS ........................................................................... 97 Table 10-1. Cast Iron Material Testing Results ................................................................................. 99 Table 11-1. Recommended Projects Post 2010 Bond ...................................................................... 104 CS-199 AWSS Facilities Preliminary Options Study VI Task 11 Project Report Acronyms and Abbreviations AECOM/AGS JV AECOM/AGS a Joint Venture AHP Analytical Hierarchy Process ATC Applied Technology Council AWSS Auxiliary Water Supply System CAPSS Community Action Plan Seismic Safety CCSF City and County of San Francisco CDD SFPUC City Distribution Division CI Cast Iron CIP Capital Improvement Program CS-199 AWSS Engineering Services Contract CS-199 ESER Earthquake Safety and Emergency Response FRA Fire Response Area GIRAFFE Graphical Iterative Response Analysis for Flow Following Earthquakes GIS Geographic Information System GPM Gallons per minute LOS Level of Service MCCGV Motorized Closed Control Gate Valve MG Million Gallons MOCGV Motorized Open Control Gate Valve Mw Moment Magnitude MWSS Municipal Water Supply System NCEER National Center for Earthquake Engineering Research NPV Net Present Value CS-199 AWSS Facilities Preliminary Options Study VII Task 11 Project Report OCGV Open Control Gate Valve psi Pounds per square inch PWSS Portable Water Supply System SCADA System Control and Data Acquisition SF San Francisco SFDPW San Francisco Department of Public Works SFFD San Francisco Fire Department SFPUC San Francisco Public Utilities Commission SoMa South of Market TAP Technical Advisory Panel TM Technical Memorandum USGS United States Geological Services WSIP Water System Improvement Program CS-199 AWSS Facilities Preliminary Options Study VIII Task 11 Project Report Executive Summary This Project Report summarizes the work performed by AECOM/AGS under the agreement CS-199 Planning Support Services for the Auxiliary Water Supply System (AWSS). A critical goal of this study is to identify the actions that, if implemented, will maximize the likelihood that the AWSS will effectively provide required firefighting capabilities after a major earthquake. This will be achieved through planning and development of a comprehensive longterm capital improvement strategy for repair, retrofitting, improvement, and expansion of the firefighting pipelines, cisterns, and tunnels. This Project Report summarizes the work performed for CS-199. The purpose of this report is to document the recommendations from tasks defined in the CS-199 Request for Proposals and subsequent task orders and summarize the preferred Capital Improvement Program (CIP), herein referred to as the preferred alternative or recommended projects. This technical memorandum incorporates responses to inputs from the AWSS Technical Advisory panel and SFPUC staff. Absent a specific regulatory requirement for AWSS performance, this study included a condition assessment, identified system needs, recommended Level of Service (LOS) Criteria, developed projects and three alternative programs to upgrade the system to meet the LOS criteria, performed an alternatives analysis and selected a preferred alternative to recommend to SFPUC for implementation. Hydraulic and reliability modeling were performed to determine the existing AWSS water supply reliability. In the context of this study, reliability is defined as the percentage of the water demand met by AWSS high pressure system and other sources. The specific demands utilized for this study are those based on median ground motions following a Mw 7.8 earthquake on the San Andreas fault. Under these conditions, the existing system is 47% reliable to provide probable fire following earthquake demands. The projects recommended for implementation with portions of the ESER 2010 bond funds will increase the citywide reliability to 68%. The recommended AWSS and Potable Co-Benefits system will extend the emergency fire fighting water system to all areas of the City and improve the citywide reliability to 94%. The planning level net present value (NPV) cost not including pipe replacement for the recommended alternative is $137 million, which assumes cost sharing with water revenues. Projects would need to be funded by future bonds, water revenues or other sources. These projects represent an investment in the AWSS and potable system to extend the benefits beyond the existing system to the balance of San Francisco. The CIP includes a variety of project types CS-199 AWSS Facilities Preliminary Options Study IX Task 11 Project Report addressing the needs and deficiencies developed in the condition assessment and reliability modeling This planning study identified certain deficiencies that are related to operations and maintenance or long term programs. These recommendations are listed in Table ES-1 and relate to emergency preparedness, training, and maintenance. Items 11 through 14 have been incorporated into a recommended pipeline testing program funded by the ESER 2010 Bond. Table ES-1. Non-Construction Recommendations AWSS Emergency pipeline repair, readiness and response program 1 2 3 Priority Maintenance Confirm that all AWSS assets are entered into CDD's asset management high system and Preventative Maintenance requirements are established Perform Regular maintenance and testing high medium 4 Establish leak detection program and a pipeline leak database to monitor potential areas of concern Check, flush and repair all suction connections regularly 5 Establish pipeline flushing program for AWSS low 6 Establish a cistern inspection, filling and testing program low 7 Operational readiness Establish regular coordination meetings with SFFD high 8 Train SFPUC personnel on system (communications, operational low strategies, emergency response requirements high 9 Develop a system outage policy and procedures for planned outages high 10 Prepare an emergency Response program and conduct training exercise high CIP Planning 11 Establish testing program for AWSS pipelines high 12 Establish program to replace hydrant laterals high 13 Establish program to locate and mitigate AWSS crossings of pile 14 supported utilities and other utility interferences high Establish regular pipeline replacement program medium CS-199 AWSS Facilities Preliminary Options Study X Task 11 Project Report Additional hydraulic, reliability, and risk assessments were performed to determine the sensitivities of the reliability scores to the following: 1. The annual risk of all potential earthquake events 2. The availability and use of potable water from the potable water system 3. The construction of a potable co-benefit system which provides daily benefit to the potable water system but will also function as a high pressure fire system when necessary 4. Possible abandonment of existing AWSS pipe in the infirm and non-infirm zones Based on the additional analyses, the following recommendations are made: The projects recommended for funding using the ESER 2010 Bond funds should continue into planning, design and construction. Projects which strengthen the existing AWSS should proceed with planning and potential funding. SFPUC should engage in a similar planning effort to assess the reliability of the existing potable water distribution downstream of the Water System Improvement Program (WSIP) hardened facilities and recommend potential areas of improvement. Once the potable system is assessed, SFPUC can determine the most appropriate methodology to achieve the LOS goals throughout the City. Table ES-2 lists the recommended future projects. Table ES-2. Recommended Future Projects Facilities Reliability Upgrades University Mound Pipeline and Pipe Pump Station Connections Silver Extension Pipeline and Water AWSS Twin Peaks Pipeline Supply Reliability Upgrades at Facilities Cisterns 27 New Sunset Main Replacement Richmond Main Replacement Potable Cobenefits Hydrants Installed on WSIPstrengthened pipes Total Cost Net Present Value $114 million $23 million* $137 million Notes: *- Assumes 75% water revenues/bonds and 25% general obligation bond cost share (associated water revenues/bonds cost = $69 million) CS-199 AWSS Facilities Preliminary Options Study XI Task 11 Project Report 1.0 Introduction 1.1 Background SFPUC has retained AECOM/AGS a Joint Venture (AECOM/AGS JV) under agreement CS-199 Planning Support Services for the Auxiliary Water Supply System (AWSS) dated October 2011 to assist in planning and alternative analysis for the AWSS pipelines, control system, seawater intake tunnels, and cisterns. The objective for AECOM/AGS JV is to review existing configurations, analyze system hydraulics, and make recommendations on pipelines, control systems, seawater intake tunnels, and cisterns to optimize benefits from repairs and improvements to the AWSS, given the potential for seismic activity in the area. A critical goal of this work is to maximize the likelihood that the AWSS will effectively provide required firefighting capabilities after a major seismic event. This Project Report summarizes the work performed for CS-199. The purpose of this report is to document the recommendations and summarize the preferred Capital Improvement Program (CIP), herein referred to as the preferred alternative or recommended projects. This project report incorporates responses to inputs from the AWSS Technical Advisory panel and SFPUC staff. 1.2 Scope of Work The Task 11 Scope of Work is as follows: Fully develop the preferred alternative and produce a project report containing a Capital Improvement Plan for funding and construction of recommended system repairs and improvements. Document all project features, including program goals and service levels, and specific criteria such as capacity, size, location, alignment, materials, etc. Perform and document supporting technical studies, such as refinement of hydraulic analysis, geotechnical and control system analyses, environmental considerations, reliability probabilities, and legal or right-of-way issues. Prepare a planninglevel Operating Strategy for operation and maintenance of the new and repaired AWSS. Deliverable: (This) Project Report. CS-199 AWSS Facilities Preliminary Options Study 1 Task 11 Project Report 1.3 Outline of Project Report This project report consists of the following sections. Section 2 includes the needs assessment and project definition Section 3 includes development and description of the project alternatives Section 4 describes the alternatives evaluation and scoring Section 5 is a discussion of the preferred CIP including discussion of the projects, schedule estimate of probable construction costs, and evaluation considerations Section 6 includes a discussion of operational strategies of the existing system and the options considered, and the recommendations for future operations Section 7 includes non-construction recommendations Section 8 includes additional assessments of reliability score sensitivities Section 9 includes a discussion of justification for the capital program Section 10 includes supplemental condition assessments Section 11 provides conclusions and recommendations 1.4 Methodology to Evaluate Program Alternatives Figure 1-1 shows the relationship between the primary analytical tasks in the project that relate to the alternatives development, analysis and selection of the Preferred Alternative. These tasks include: Task 2: Existing Performance, Operations and Needs Assessment (Condition and Needs Assessment). This task included evaluation of the existing condition of the system and provided information to analyze performance of the existing system. Task 3: Performance Goals and Evaluation Criteria. Task 3 identified and selected LOS Criteria the overall analytical approach for the study. Task 4: Geotechnical. Task 4 identified and evaluated the geologic, seismologic, and geotechnical hazards for the AWSS pipelines, tunnels, and cisterns, and provides mitigation methods. Task 5: Testing Methods. Task 5 provided detailed recommendations for pipeline testing methods to be performed by others. The testing is to determine the existing condition of installed pipes, joints, and appurtenances as it concerns serviceability, working pressure, flow capacity and characteristics, remaining life expectancy, corrosion, and related items. These methods include non-destructive testing and destructive testing, the latter being used only when required by physical constraints or when yielding justifiably superior information. Task 6: SCADA. Task 6 assessed the existing SCADA systems for AWSS and recommended software and hardware upgrades, changes in system architecture and modifications to extend the control to currently uncontrolled facilities. CS-199 AWSS Facilities Preliminary Options Study 2 Task 11 Project Report Task 7: Seawater Intake Tunnels. Task 7 documented the assessment of the Seawater intake tunnels for Pump Stations 1 and 2 and recommends modifications to increase the tunnel reliability. Task 8: Modeling. Task 8 included the quantitative and qualitative analysis of system performance and evaluation of all of the data required to assess LOS Criteria and Program Alternative considerations due to a seismic event. Task 9: Alternatives (Development and) Analysis. This task included the identification and evaluation of projects that form Programs that achieve LOS performance goals. The analysis in this task provided the information for decision-makers to select the LOS performance goals and the associated program of improvements. Task 9.1: Additional Alternatives Analysis. This task included the assessment of risk to events other than the Mw 7.8 event on the San Andreas Fault, assessed the sensitivity of the analysis to the availability of potable water and looked at several alternatives to the preferred alternative by use of potable or mixed systems. Task 10: Insurance. Task 10 assessed the impact of the existing and proposed AWSS on the Fire Insurance market in the City of San Francisco. Task 12: Supplemental Geotechnical. This task included supplemental geotechnical investigation and analysis on specific topics necessary to support the study. Task 13: Condition Assessment. This task included supplemental assessments including materials testing and assessments of potential site alternatives. Task 14: Operations and Maintenance. This task included coordination of operations strategies with SCADA improvements. CS-199 AWSS Facilities Preliminary Options Study 3 Task 11 Project Report Figure 1-1. Evaluation Methodology Schematic Task 2: Existing Condition and Needs Assessment Collect & Review Existing Data Interviews (SFFD, CDD, SFDPW) Task 4, 6, 7, 12, and 13 Document Existing Systems Existing Condition Assessment Identify System Deficiencies and Improvement Needs Task 3: Performance Goals & Evaluation Criteria Projects of Interest Identify Criteria Categories and Evaluation Criteria Select LOS Criteria Stakeholder Input Identify Evaluation Methodology Task 8: Modeling Analytical Tool Assessment (How can we model these?) Define Modeling Needs and Develop Modeling Tools Fire Model Water Supply Model Fire Ignition and Spread GIRAFFE Model Seismic Damage Fire Growth and Demand Other Water Sources System Performance Modeling for LOS Criteria Task 9: Alternatives Development & Analysis CIP Development Workshop Analyze Baseline Performance (Existing System) Prioritize Projects Identify High Risk Areas Identify Performance Gaps and Additional Projects Cost Estimating Project Alternative Considerations CS-199 AWSS Facilities Preliminary Options Study 4 Analyze System Performance Develop Incremental Improvement Program Alternatives (P1-P7) Calculate and Refine Program Packages Task 11 Project Report Stakeholder Input Selection of Preferred Program Alternative and Associated Performance Goals Program Budgets, Phasing, & Schedule Project Definitions and Functional Objectives The preferred alternative was developed and selected in accordance with the methodology described in the following SFPUC Infrastructure Division Procedures: PD 2.01 Needs and Alternatives Identification PD 2.02 Alternatives Analysis and Evaluation The methodology consists of five steps and is summarized in the following sections. 1.4.1 Needs Assessment and Project Definition A need is a recognized gap between apparent current conditions and that which is required or desirable. The need may arise from operational problems, regulatory requirements, new legislation, the age or perceived reliability of an existing piece of equipment or process, security/safety requirements, and/or increased demand. The needs assessment phase (Step 1) was completed prior to this Task, and is associated with Tasks 2, 3, 6, 7 and 8 of this contract. The process and findings from Step 1 are summarized in Section 2.0 of this report, and include the following: a. Information collection and review, including reference documents, drawings, previous studies, and other available data; b. Preliminary condition assessment of applicable facilities and assets ; c. Definition of the needs, including potential LOS criteria, performance goals, and deficiencies; d. Performance analysis of the existing system with respect to the LOS criteria and identification of potential system performance gaps; e. A discussion of ideas and potential solutions; f. Development of preliminary projects which address identified deficiencies; g. A preliminary screening of potential projects; h. Development of project performance goals/sizing criteria; and i. Analyses of potential projects included in the alternatives to collect information to be used in the evaluations, including siting and construction issues, permitting requirements, operational considerations, environmental issues, and other issues associated with the alternatives. For each project, estimate construction cost and duration, and identify potential cost and schedule risks. 1.4.2 Development of Program Alternatives The development of Program Alternatives (Step 3) is summarized in Section 3.0 of this report, and includes the following: a. Develop up to seven repair, improvement, and expansion alternatives for the AWSS. CS-199 AWSS Facilities Preliminary Options Study 5 Task 11 Project Report b. Lead the project team in ranking the alternatives based on scoring of individual attributes for each of the alternatives. c. Select the top three alternatives from these rankings. d. Formulate and refine the three Program Alternatives from the list of potential projects that meet the selected LOS performance goal and other objectives recommended by the Steering Committee. e. Perform system reliability and hydraulic analyses to confirm that each of the potential Program Alternatives meets the LOS performance goal. f. Confirm program evaluation criteria as set out in Section 4 of the SFPUC PM Procedures PD 2.02 Alternatives Analysis and Evaluation, as refined and presented in Section 4.2. g. Identify deficiencies which are not appropriately addressed by capital projects, and develop non-project alternatives to address the deficiencies. h. Confirm LOS performance goals, program evaluation criteria, and the three Program Alternatives with SFPUC staff. 1.4.3 Analysis and Evaluation of Alternatives The analysis and evaluation of Program Alternatives (Step 4) is summarized in Section 4.0 of this report, and include the following: a. Select and confirm evaluation criteria to be used to rank the Program Alternatives. b. Evaluate the three Program Alternatives based on selected evaluation criteria using an Analytical Hierarchy Process (AHP). c. Prepare draft scoring and ranking of Program Alternatives. d. Present and discuss each Program Alternative with the SFPUC Steering Committee. Present draft scoring. Refine scoring and ranking with Steering Committee input. e. If required, receive Steering Committee comments, refine analysis. f. Confirm selection of a Preferred Program Alternative. 1.4.4 Preferred Program Alternative Development of the Preferred Program Alternative (i.e., preferred alternative) included the following actions: a. Address any remaining project planning level project assumptions and unknowns. b. Develop program schedule. c. Assess independent utility of each project contained in the Preferred Program Alternative, for development of environmental permitting strategy. d. Present Preferred Program Alternative to the SFPUC. Following the presentation of the preferred alternative, further work was completed based on comments from SFPUC. This project report summarizes the latest recommendations and conclusions and supersedes the task technical memoranda. CS-199 AWSS Facilities Preliminary Options Study 6 Task 11 Project Report 2.0 Needs Assessment and Project Definition 2.1 AWSS Background and Purpose The 1906 San Francisco earthquake is considered to be one of the most severe earthquakes in recent history. Approximately 80 percent of San Francisco’s (City’s) total loss was caused by the fires following the earthquake (ATC, 2005). Separate major fires broke out at several locations to become a large conflagration, engulfing the northeast quadrant of the City. The earthquake and resulting fires caused approximately 3,000 deaths and destroyed nearly 28,000 buildings. The total estimated property loss was approximately $524 million in 1906 dollars (Scawthorn et al., 2006). The National Fire Protection Association has estimated the fire losses to be $7.8 billion in 2006 dollars (NFPA, 2007). The domestic water system was severely damaged, sustaining more than 300 breaks on water mains and 23,000 breaks on service connections. There was insufficient water available to combat the numerous fires that had transpired due to the earthquake. Roughly 50 fire events occurred throughout the city, mostly in the downtown area. When the fire was finally extinguished several days later, almost all of the downtown was destroyed. The fires caused by the 1906 earthquake accounted for 85% of the damage to residents and businesses (NCEER-94). The “Auxiliary Water System for Fire Protection” study by Marsden Manson was conducted in 1908 to evaluate the need for a dedicated water system for firefighting in the City. The 1906 earthquake highlighted the fragility of the domestic system and the necessity of an improved system. After the 1906 earthquake and resultant fires, the price of fire insurance became a severe handicap to businesses. Further protection for residents and businesses from conflagration was necessary; otherwise, the future growth of the city would be hindered. San Francisco has proven to be more susceptible to fire loss than any other large American city with many factors contributing to the City’s vulnerability. Some of the most important issues include: the large number of buildings constructed of wood, the many streets too steep to permit firefighting equipment, dry summer months, high winds during summer evenings, and the existing vulnerability of the domestic water system (Marsden, 1908). Due to these factors and the high seismic risk in the San Francisco Bay Area, City leaders approved the construction of an independent fire protection system, known as the Auxiliary Water Supply System (AWSS). The AWSS was implemented to be used as the secondary defense against fires in the event the Municipal Water Supply System (MWSS) fails. The AWSS is a water supply system consisting of pipelines, cisterns, reservoir, storage tanks, and saltwater pump stations. Studies showed the most effective system would be to have mains approximately 5 feet below the surface and sufficient pressure to replace the use of portable steam pumping engines or fire engines. The system was intended to be ready for instant use CS-199 AWSS Facilities Preliminary Options Study 7 Task 11 Project Report and allow the fire department to reach the fires and apply water more quickly. Additionally, the AWSS was designed to function in the event of a major earthquake. It was built with restrained pipeline joints as well as fewer branches than the domestic system and no service connections, thus making it less vulnerable. Planned with a normal main size of 10 to 12-inches and gate valves strategically placed within the system, breaks can be isolated to maintain the integrity of the system. This is especially important in the filled-in areas where breaks and ruptures are more likely in the event of an earthquake. Due to concern for rapid deterioration associated with salt water use in pipes, it was determined to use fresh water in most cases. In extreme cases where additional water is needed, sea water can be drawn from the bay with fire boats or pump stations and used to charge the system (Marsden, 1908). Construction of the AWSS was completed in 1913 (SFFD, 1996) at a cost of 5.2 million dollars. The original AWSS construction provided additional level of fire protection to the highly developed northeast portion of the City, including downtown. The original construction included 72 miles of distribution pipe concentrated in the densely populated northeast quadrant of the City, 889 hydrants, and the major above ground components of the system including Twin Peaks Reservoir, Ashbury & Jones St tanks, and both Pump Stations 1 and 2. The area where the AWSS was installed is considered the “Protected Area.” Because the pressure from Twin Peaks Reservoir was greater than what was deemed necessary, the protected area was separated into two zones. The Lower Zone includes everything less than 150 feet in elevation and covers approximately six square miles. That zone is fed by the Jones St Tank and included the congested value district. The Upper Zone includes everything with an elevation greater than 150 feet. That zone is approximately 2.25 square miles and is supplied by the Ashbury Tank. Each zone is supplied water under pressure up to 150 psi from their respective reservoirs. When necessary, during emergencies, the lower zone may be connected with the reservoir in the upper zone or Twin Peaks to provide a necessary increase in pressure. The AWSS has been expanded and improved through several bond measures performed in the 1930s, the 1970s, and the 1980s. The latest system configuration can be seen in Figure 2-1. The importance of maintaining and expanding the AWSS can be tied to the risk of fire losses in the City. During day-to-day firefighting operations, the AWSS supplements the domestic system. Following an earthquake, however, the AWSS may become the primary water supply for firefighting. It permits rapid concentration of powerful streams without the use of pumpers in the areas served. CS-199 AWSS Facilities Preliminary Options Study 8 Task 11 Project Report Figure 2-1. Existing Auxiliary Water Supply System Source: SFPDW GIS CS-199 AWSS Facilities Preliminary Options Study 9 Task 11 Project Report The performance of the AWSS remains untested in response to an earthquake of the same magnitude as the 1906. The 1989 Loma Prieta earthquake was the largest earthquake in northern California since the construction of the AWSS in 1913. The 1906 earthquake had a magnitude of 7.8 which is significantly higher than the 6.9 magnitude of Loma Prieta. Even so, the damage done by the Loma Prieta earthquake was still quite significant and give an indication of the level of damage that a seismic event of Mw 7 or greater may induce. Figure 2-2. Loma Prieta Marina Breaks CS-199 AWSS Facilities Preliminary Options Study 10 Task 11 Project Report Following the earthquake, approximately 69 main breaks and 54 service connection breaks were documented on the MWSS in the Marina District. Additional repairs that were not documented may have also occurred. The repairs were spread throughout the area bounded by Marina Boulevard and Chestnut Street to the north and south and by Buchanan and Baker Streets to the east and west (USGS, 1992). The breaks in the system impaired water pressure and flow to the MWSS hydrants. Refer to Figure 2-2 for the locations of the Marina breaks. The AWSS suffered damage due to liquefaction and lateral earth spread. There was one 12-inch main break in the South of Market (SOMA) area at 7th St. and Natoma St., and four fire hydrant breaks, with three located in SOMA and one in the Foot of Market area. In addition, two leaks were discovered in the Marina District and on Folsom St. in the Mission District. The events of the Loma Prieta earthquake illustrate several points regarding the need for the AWSS following a major earthquake in the future: MWSS pipes will sustain damage in certain areas of the City, which will impair the ability to deliver water for firefighting. Due to the design features of the AWSS, it is likely to be more serviceable after an earthquake. However, it may still sustain some damage after an earthquake. Multiple redundancies in fire water supply systems are necessary. In the Loma Prieta earthquake, the third line of defense, the Portable Water Supply System (PWSS), and fireboat, were successful in suppressing the fire in the Marina District. As expected, all AWSS damage was concentrated in the infirm areas. Damage in these areas could not be isolated due to loss of power to the isolation valves. While the majority of the AWSS network remained intact, specific portions of the system became inoperable as a result of the breaks. Crews needed to be deployed to manually operate valves to isolate breaks. 2.2 Facility Descriptions San Francisco possesses three major water supply systems used to deliver water throughout the City and fight fires: the MWSS, the AWSS, and the PWSS. The MWSS distribution network system serves as the primary water supply system within the City and County of San Francisco (CCSF). This system is typical of other large cities and is used to deliver potable water to customers and to the extensive network of low pressure fire hydrants. City Distribution Division (CDD) is responsible for supplying water to approximately 180,000 service connections and operating and maintaining 13 reservoirs, 20 pumping stations, a network of approximately 1,300 miles of pipeline and hydrants, and 12,000 water valves. The second water supply system is the AWSS which is an additional source of water for combating fires. It is utilized by the SFFD and operated and maintained by CDD. The AWSS CS-199 AWSS Facilities Preliminary Options Study 11 Task 11 Project Report delivers water under high pressure solely for firefighting, is independent from the MWSS, and is capable of delivering water at significantly higher pressures than the MWSS. The AWSS consists of high pressure water mains and hydrants, a storage reservoir, tanks, emergency saltwater pump stations, fireboats and cisterns. The AWSS is an independent system owned and operated by SFPUC and utilized by the SFFD exclusively for firefighting. In regards to terminology, the AWSS is defined, using standard SFFD conventions, as a combination of the following major facility components: High Pressure System: This consists of Twin Peaks Reservoir, Ashbury Tank, Jones Street Tank, the high pressure pipeline network including hydrants and branches, Pump Station 1, Pump Station 2, the fireboat manifolds, and the suction connections located at the perimeter of the Bay and Embarcadero, suction line running west on Fulton Street from lakes in Golden Gate Park, and other appurtenances (not including cisterns or fireboats). Cisterns: The collection of underground cisterns located throughout the City. Fireboats: SFFD’s two fireboats – the “Guardian” and the “Phoenix”. Water stored in one reservoir (Twin Peaks Reservoir) and two tanks (Ashbury and Jones Street tanks) and is supplied at a high pressure - up to approximately 325 psi - via hydrants with black, red, or blue tops. The color of the hydrant’s top represents the location of the hydrant in one of the three distribution zones of the AWSS, as shown in Figure 2-3. The pump stations and fire boats supply saltwater from San Francisco Bay. Where available, the AWSS is an additional source of water for combating fires. Figure 2-1 shows the two pump stations, two water storage tanks, one reservoir, 154 functional cisterns, and approximately 135 miles of pipes in the AWSS. Not shown on the map, but also part of the AWSS, are the suction connections which allow drafting directly from San Francisco Bay and the inlet manifolds which allow fireboats to charge the pipe system. The AWSS has four water supply sources: 1. The primary water storage supply for the existing AWSS is provided by the Twin Peaks Reservoir. Ashbury Tank and Jones Street Tank regulate the pressure throughout the system. Each tank is at a different elevation, the highest (Twin Peaks) being 758 feet above sea level creating a distribution system that is supplied by gravity capable of pressures up to 325 psi depending on the elevation of the hydrants within the distribution system and the division and bypass valve positions. The following items may be used to supply San Francisco Bay water when this primary storage is exhausted or becomes unavailable. 2. Two saltwater pump stations located on the San Francisco Bay side can pump bay water directly into the distribution system and AWSS storage tanks. CS-199 AWSS Facilities Preliminary Options Study 12 Task 11 Project Report 3. Two fireboats, normally berthed at Pier 22 ½, can supply bay water to the City’s waterfront, to the AWSS via five manifolds located along the bay and to PWSS hoses. 4. Approximately 154 functional underground cisterns located throughout the city can also be used as an emergency water source for combating fires. Cisterns are not connected to the piping system as they are standalone components and water must be pumped from them using engine pumpers. 5. 35 suction connections along the bay allow engine pumpers to draw by suction from the bay. 6. A suction line with low pressure hydrants along Fulton St. draws from lakes in Golden Gate Park. The AWSS is divided into three zones, Twin Peaks (black-top hydrants), the Upper Zone (redtop hydrants), and the Lower Zone (blue-top hydrants). The Twin Peaks Zone currently includes any area west of Twin Peaks and greater than 300 ft in elevation. The Upper and Lower Zones are isolated by a series of gate valves. The Upper Zone consists of the AWSS components at city areas located above 150-ft elevation. The Lower Zone consists of the AWSS components at city areas located below 150-ft elevation. Under normal operations, Jones Street Tank serves the lower zone and Ashbury Tank serves the upper zone and Twin Peaks Reservoir serves the Twin Peaks Zone. The zones can all be opened to serve as one zone at the highest pressure when needed. CS-199 AWSS Facilities Preliminary Options Study 13 Task 11 Project Report Figure 2-3. AWSS Pressure Schematic The AWSS pipeline and hydrant system is used solely for firefighting. City ordinance dictates that no municipal department, other than the Fire Department, is permitted to use the AWSS. Automatic sprinkler systems are not allowed to be connected to the system. The cost of installing AWSS pipe is significantly higher than that for typical domestic water pipe. Previous studies (Metcalf & Eddy, 2009) have estimated that each mile of AWSS costs $19 million to install vs. approximately $3.7 million for domestic water pipe. There are several factors that contribute to the higher cost. Pipe fittings and hydrants are specially cast, making them costly to procure. There is a single foundry that produces these components. For example, an AWSS hydrant costs approximately $18,000 vs. $3,000 for a standard domestic hydrant. A 45degree bend costs approximately $5,100 vs. $2,800 for the same component of the domestic water system. The pipe joints for domestic water pipes use special restrained gasketed joints which may be pushed on in the field. Thrust blocks are required at some points. Due to the higher operating pressures AWSS pipes use these similar types of joints with the joints restrained against pull-out using stainless steel tie rods. The use of tie rods increases the cost of both material and installation for AWSS pipe. CS-199 AWSS Facilities Preliminary Options Study 14 Task 11 Project Report Although it is not a major water supply system, the PWSS also provides firefighting support. This system is considered as equipment rather than as part of AWSS and the SFFD can use it as another line of defense. The PWSS is an above ground portable system consisting of large diameter hoses, pressure reducing valves, and portable hydrants. The PWSS can be used to draft water from alternative water sources and transport water over long distances when the MWSS and AWSS pipelines are not available. Section 2 of the Task 2 TM describes the AWSS and all facilities in greater detail. 2.3 AWSS Operations and Maintenance The AWSS is generally used for day-to-day “greater alarm” incidents and some working fires occurring within the AWSS service area. The AWSS is typically able to serve an area that extends approximately 1,000 feet to either side of the pipelines. However this distance varies due to variables such as location of fire, topography of the area, type of fire (high rise vs. low rise), pressure required, pressure within the AWSS pipeline system and whether an engine pumper is used. The SFFD utilizes the AWSS frequently for greater alarm fires because of the higher capacity and pressures and at the same time gaining experience operating the system. The need for the AWSS following an earthquake is dependent on many factors including the likelihood and severity of fires following a large earthquake and the anticipated immediate and continued ability of the MWSS mains to provide water following an earthquake. The condition of the MWSS distribution system following an earthquake has not been evaluated in this study. The SFFD utilizes the AWSS during firefighting events. CDD is responsible for the maintenance, repair, and proper operation of the system. During firefighting events, both agencies coordinate to enable the proper operation of the system to respond to the dynamic needs of the fire. During normal operations, the three AWSS zones (Twin Peaks, upper zone, and lower zone) operate independently to provide water supply for firefighting. The upper and lower zones of the AWSS are normally supplied with fresh water by gravity from the Jones St and Ashbury Tanks. The fresh water supply stored in Twin Peaks Reservoir at high elevation provides supply for the Twin Peaks zone and is also available to increase pressures in the entire system and fill the storage tanks as required. The reservoir and tanks are all connected, via air gap, to the MWSS to maintain the operating storage height. AWSS maintenance is performed on an as needed basis. Previously, when the AWSS was owned and operated exclusively by the SFFD, there was one assigned plumber to each of the 10 fire department districts. Each plumber would be responsible for their respective facilities. CDD has 40 MWSS plumbers capable of working on the AWSS. There currently is no specific CS-199 AWSS Facilities Preliminary Options Study 15 Task 11 Project Report preventative maintenance program. Fire hydrants, leaking pipe segments, pump stations, and tanks are serviced, repaired, installed, replaced, and painted on a monthly request basis and as required. 2.4 Review of Existing Information Collection and collation of existing information were performed in Tasks 2 and 5, as required for the needs assessment phase, and is summarized in the respective TMs associated with each task. In particular, the condition of existing assets (Section 2.2) was assessed by reviewing and summarizing previous inspection records, repair records and physical inspection and testing records. No detailed technical evaluations were performed in Task 2. Refer to Appendix A of the Task 2 TM for a listing of information reviewed and Appendix F of the Task 2 TM for a summary of the AWSS Geographic Information System (GIS) information collected. 2.5 Condition of Existing Assets Information about the condition of the existing AWSS assets was developed as part of Task 2 and is presented in detail in Section 5.0 of the Task 2 TM. Knowledge of the condition of the existing AWSS is based on limited available information and is not well documented. Pipeline testing and analysis of testing results is required to better understand the condition, vulnerabilities, and deterioration rate of the AWSS. In the Task 5 TM, detailed recommendations are provided for pipeline testing and implementation of a condition assessment program. Due to the time required to perform initial testing and implement a condition assessment program, the intent is that the CIP be developed based on available information, while in parallel, the condition assessment program is developed and implemented. Testing should be conducted over the next several years and on an ongoing periodic basis thereafter, and will allow identification of deficiencies not yet known, confirm the overall condition of the system, and allow refinement of a pipeline replacement program. As data are collected and interpreted, a pipeline rehabilitation and replacement program should be implemented by the SFPUC to replace, rehabilitate, or upgrade existing AWSS pipelines and other assets. Such a program is recommended in the recommended program. It is also possible that findings from future condition assessment activities will identify additional capital expenditures required to replace aged facilities as they reach the end of their useful service life. Initial replacement priorities should include the cast iron pipelines in infirm areas and utility crossings. As the pipelines are replaced or rehabilitated, portions of the system in the heavily gridded and infirm areas may be abandoned. Modeling indicates that between 26-39% of the system in the heavily gridded area could be abandoned without a loss in reliability. During project planning reliability and hydraulic modeling should be performed to confirm any abandonment or skeletonizing of the system. CS-199 AWSS Facilities Preliminary Options Study 16 Task 11 Project Report 2.6 Needs Definition The goal of the AWSS CIP is to maximize the likelihood that the AWSS will effectively provide required firefighting capabilities after a major seismic event. A major earthquake is defined as an earthquake with a moment magnitude Mw7.8 on the San Andreas Fault, Mw7.1 on the Hayward Fault, or Mw6.8 on the Calaveras Fault. The objective of the alternatives analysis phase is to develop a Preferred Program Alternative, which optimizes benefits from repairs and improvements to the AWSS, given the potential for seismic activity in the area. The developed Program Alternatives address the need as defined by the selected LOS performance goals described below in Section 2.6.1, and address system deficiencies identified under Task 2, 5, 6, 7 and 8, and listed below in Section 2.6.2. 2.6.1 LOS Criteria and Performance Goals LOS criteria are the metrics by which performance of the AWSS and the benefits of the improvement program (Program) are measured. LOS performance goals are the quantitative and qualitative targets for each criterion to be achieved by the program. These targets were selected by decision makers based on analysis of the benefits that can be achieved by the projects in the Program and their respective costs. Together, the LOS criteria and performance goals form the guiding principles for developing the program of improvements to the AWSS. The selection and development process for the selection of the LOS criteria and performance goals is detailed in the Task 3 TM. The AWSS is not bound by regulatory requirements to meet certain criteria. Instead, SFPUC must establish the LOS criteria and performance goals. These goals were set once the existing condition of the system was evaluated. LOS criteria are measured using modeling tools such as hydraulic modeling, reliability modeling, and geotechnical analyses tools, listed below in Table 2-1. CS-199 AWSS Facilities Preliminary Options Study 17 Task 11 Project Report Table 2-1. Analysis and Modeling Tools Modeling Tools Needed to Measure Criteria Criteria Category Evaluation Criteria Water Delivery Reliability Water Supply Reliability Geographic Coverage Distribution of Water Delivery Capability Hydraulic Model Reliability Model Water Supply Models Fire Ignition Model Fire Spread Model Given the input provided by Technical Advisory Panel (TAP), SFPUC Technical Steering Committee, SFPUC Management Oversight Committee, and SFPUC staff, and with considerations regarding project constraints, it was recommended that the LOS criteria should be water delivery reliability. It was also recommended that the LOS criteria address geographic distribution of water availability. Geographic areas were defined and LOS targets for water delivery reliability were attributed to individual sub-areas as well as the City as a whole. The Task 8 TM describes the modeling performed using hydraulic and reliability modeling tools in detail. The following is a brief outline of the methodology utilized to evaluate the LOS criteria for water delivery reliability and geographic coverage: a. Delineate sub-neighborhood Fire Response Areas (FRA, 46 in total) based on SFFD engine response areas, and modified in the downtown area to capture the density of AWSS. The delineation of FRAs is shown below in Figure 2-4. b. Determine a set number of ignitions derived from a Monte Carlo analysis of possible number of ignitions given the peak ground accelerations from a Mw7.8 San Andreas earthquake. c. Determine the most probable locations of the set number of ignitions. d. Estimate the representative fire demand and location for each FRA. e. Perform reliability modeling, incorporating Monte Carlo analyses of system damage, to determine system reliability (total water available divided by total demands) based on ability of AWSS to meet estimated fire demands. f. Estimate system (citywide average FRA) and individual FRA performance in terms of water delivery reliability. CS-199 AWSS Facilities Preliminary Options Study 18 Task 11 Project Report Figure 2-4. Fire Response Areas Hydraulic analyses of the system were performed using the Graphical Iterative Response Analysis for Flow Following Earthquakes (GIRAFFE) program. GIRAFFE computes a probabilistic delivery reliability accounting for multiple iterations capturing the range of possible damage scenarios. Input to GIRAFFE included facility fragilities developed for AWSS and other pipe systems as well as fire demands developed with fire ignition and spread models. GIRAFFE was developed by T. O’Rourke and colleagues at Cornell University to simulate hydraulic networks under damaged states and was used as the primary engine in the reliability CS-199 AWSS Facilities Preliminary Options Study 19 Task 11 Project Report modeling. GIRAFFE uses the open source EPANET1 model as the hydraulic engine and is capable of performing both deterministic and Monte Carlo simulations of pipe damage. Input to GIRAFFE includes the system model and projected pipe repair rates. These repair rates were calculated and compared using various methods found in the literature. A detailed analysis for the fragility rates is included in the Task 8 TM and summarized below in Section 2.9.1. Seismic assumptions governing the analysis are based on the design earthquake presented in the scope of work, a 7.8 magnitude earthquake on the San Andreas Fault. Two sources of geotechnical data were utilized in the fragility analysis for comparison: United States Geological Survey (USGS) information Project-specific AECOM/AGS developed data, compiled by AGS Consulting Engineers The development of probable fire demands is described in detail in the Task 8 Modeling TM. They have been developed for each FRA using the average of the 60 minute post fire demand for the 1000 demand sets provided by Charles Scawthorn using a Monte Carlo analysis of fire ignitions and fire growth following a 7.8 magnitude event on the San Andreas Fault. There are two methods of quantifying reliability, as summarized below: “Connectivity” - The percentage of areas satisfied (i.e., number of nodes satisfied / divided by the total number of nodes in the City) “Serviceability” - The percentage of the demand satisfied (i.e., water supplied /demand requested) It should be noted that although the true definition of connectivity is any amount of water that reaches a particular modeled node, due to the limitations of the computational tools in this study, a node is satisfied only if the full demand is met. Post processing was performed for the final alternative programs to calculate the serviceability (henceforth referred to as “reliability”) for each FRA for each of the 15 GIRAFFE Monte Carlo runs. The reliability of the existing AWSS in achieving the LOS objectives was evaluated utilizing the GIRAFFE tool, alternative water supply modules and post processing, with results shown in Figure 2-2. GIRAFFE reliability modeling indicates that the existing system has a citywide average FRA reliability score of 47% with seven FRAs scoring less than 10%. It should be pointed out that the existing AWSS high pressure system currently does not extend into nine of 1 EPANET (Version 2.0) [Software]. (2008) CS-199 AWSS Facilities Preliminary Options Study 20 Task 11 Project Report the 46 FRAs at this time. These FRAs are served by the MWSS, alternative water sources such as suction connections, and accessible major water bodies (e.g., Lake Merced). Figure 2-5. Existing System Delivery Reliability by FRA Based on input from SFPUC and others, the following are the recommended LOS performance objectives: AWSS will reliably provide water to supply the “probable fire demands” after a magnitude 7.8 San Andreas earthquake” • AWSS will be 50% reliable in supplying probable demands for each area • AWSS will be 90% reliable in supplying probable demands Citywide CS-199 AWSS Facilities Preliminary Options Study 21 Task 11 Project Report 2.7 System Deficiencies During the course of the data collection efforts associated with Tasks 2, 4, 5, 6 and 7, including performing interviews with SFFD, SFPUC, and SFDPW staff, as well as performing hydraulic and reliability modeling in Task 8, the following items were identified as deficiencies in the AWSS. These deficiencies were a primary consideration in the identification and scoping of individual projects (Section 2.8) and the selection of projects to comprise the Program Alternatives (Section 3.1). The full list of deficiencies is shown in Table 2-2. Deficiencies to be addressed by the Program Alternatives, developed in the Task 9 TM, are marked with an asterisk and those addressed by non-construction alternatives (refer to Table 3-4) are denoted by the (†) symbol. Table 2-2. System Deficiencies Deficiency ID Description Physical Deficiencies D1*,† Leaks are observable in the Fort Mason pipelines. Some of these pipelines are attached to the piers suspended above the bay and are difficult to access. D2* It is reported that there are areas of the high pressure system which do not conform to the San Francisco Department of Public Works Standard specifications. These areas should be removed and reinstalled; this included the elimination of lead joints. An example of this an AWSS hydrant lead installed at Folsom & 15th Street. D3* There is suspected pipeline leakage underneath the pier and structural concerns about the pier supporting the fireboat manifold at Pier 33 ½. Damage due to earthquake shaking might affect fireboat operations. D4 The Pump Station 1 seawater intake tunnel has a section that is mostly full of sediment as of December 2012, which limits its functionality. D5* Pump Station 1 seawater intake tunnel has damage to the lining, has some cracking and damaged concrete and has potential failure modes due to potential lateral ground movement. Further geotechnical field work and analysis is being performed under Task 12. Recommendations for repairs and structural mitigation are discussed in the Task 7 TM. D6* One of the fireboat docks at Pier 22 ½ is severely deteriorated. This may present safety and seismic reliability issues because AWSS piping is attached to the docks. D7* Areas in the high pressure piping system experience water quality issues (i.e., discolored water containing sediment). These issues may possibly indicate the presence of internal pipeline corrosion or the stagnation of AWSS water. In other systems this issue has been mitigated by uni-directional flushing. Currently the locations and the underlying reasons for these issues have not been identified. CS-199 AWSS Facilities Preliminary Options Study 22 Task 11 Project Report Deficiency ID Description D8* There are many areas of the AWSS pipeline where non-stainless steel restrained tie-rods were installed at joints. These materials are prone to corrosion and could fail during seismic events. The specific locations are unknown although locations could generally be identified by the age of the pipeline. D9* The original cast iron pipelines were installed without internal mortar lining. Current AWSS design standards specify internal concrete mortar lining to protect the internal condition of the pipelines. Specific locations of pipes without internal concrete mortar lining are currently unknown; however age of pipelines may be used as a basis (for example pipelines installed before 1945 are likely to have no internal lining). D10*,† There is no established repair and replacement plan to identify, and repair or replace the system’s most deteriorated pipelines. Seismic reliability and operations considerations should be considered to prioritize repairs. The condition and useful life of buried pipelines are dependent on site-specific conditions and can be highly variable. The amount of AWSS pipeline that needs replacement and the time frame is best determined through a comprehensive condition assessment and replacement program. D11† A database of detailed information is necessary when repairs are made to the AWSS. Information collection should include a description of the damage, likely cause or causes of damage, type of repair, and two or more photographs of damaged section of pipeline. Identification of patterns of pipe failure will assist SFPUC to prioritize pipe replacement. D12* There are reported to be approximately 98 locations where portions of the AWSS pipelines are constructed through sewer mains, in environments prone to severe corrosion. A program to identify the location and design mitigation measures should be developed. D13* SFPUC has begun a cistern repair project to address leaking cisterns. Continued attention to older cisterns, including the brick ones is necessary. D14* Many of the system pressure transducers date from 1994. There is difficulty calibrating the older transducers. D15* Approximately 250’ of rubber AWSS hose at 4th & Channel Street connecting the north and south side of 4th Street Bridge was removed during prior construction activities and never replaced. In order to provide more supply to the southern side of the bridge and improve localized system redundancy, it is important to reinstall this hose. Operational Deficiencies D16† System training should be provided for CDD gatemen and supervisors. Operational strategies for non-fire and fire situations for AWSS is different that for the MWSS system. D17† No succession plan has been developed for the senior CDD operations staff. This is especially important to maintain continuity of information for contingency purposes. D18† There are currently 3 PWSS hose tenders dedicated to San Francisco however there are no dedicated permanent storage locations for them. Recommendations for the quantity of hose tenders, storage and required staffing were addressed during Phase 9 (Alternatives Analysis). CS-199 AWSS Facilities Preliminary Options Study 23 Task 11 Project Report Deficiency ID Description D19† There are no staff dedicated PWSS hose tenders. PWSS equipment (including hose tenders) responsibilities are assigned to Fire Engine companies on a rotating basis; however these responsibilities are in addition to normal responsibilities. Therefore, when the PWSS system is used, additional staff and equipment would need to be deployed to operate it. D20* Pump Stations 1 and 2 are not currently connected to the SCADA system and do not have remote monitoring or control capabilities. Recommendations have been made in the Task 6 SCADA TM to address this issue. D21† There are no strict protocols for mandatory start up and operation of the pump stations and fireboats during seismic events or large conflagrations. It may prove helpful to formalize protocols based on specific triggers as opposed to initiating operation when requested. D22* Five motorized valves do not have backup to radio (three at Twin Peaks Reservoir, Ocean Ave. at 280 East and Ocean Ave. at 280 West). Completion of the site at Bay and Van Ness will bring the number operational valves to 32. Implementing these improvements will add operational flexibility to the system. D23* The Wonderware InTouch V7.0 program used for SCADA operations is obsolete and requires update. The Task 6 SCADA TM has recommendation for the SCADA system integration and upgrade. D24† Historical records from the Loma Prieta event indicate that during large seismic scenarios, communications lags may affect response times. It is unclear whether these issues have been addressed by recent upgrades in communications equipment and systems. D25† There is no written process regarding the limit of facilities allowed to be out of service at any time. A system outage policy and procedure should be developed. D26† There is no existing emergency pipeline repair, readiness and response program. This program would increase the capability of CDD to quickly restore AWSS pipelines to service after an earthquake. The program may be modeled after similar programs developed by the SFPUC for the City’s MWSS. The program may include the development of emergency pipe break response procedures, the stockpile of pipe and fittings, and establishing emergency access to equipment and resources to quickly repair affected pipes. D27† There are no automated leak detection and isolation capabilities along AWSS pipelines. D28 The Jones Street Tank 8” fill line may not fill the tank as quickly as needed. Upsizing the line would facilitate faster filling. D29* Jones Street Tank bypass valves are manually operated and cannot be operated from remote locations. Maintenance Deficiencies D30*,† Check, inspect, and back flush suction connections to ensure that their screens are clear of obstructions and are operational. The routine cleaning of suction connections is not currently performed. CS-199 AWSS Facilities Preliminary Options Study 24 Task 11 Project Report Deficiency ID Description D31† No routine system pipeline flushing is currently performed. A regular flushing program should be established. D32 No routine pump station operations are currently performed. A regular testing program should be reestablished. D33† Long lead times are required to acquire AWSS components due to the sole source manufacturer for pipes (Olympic Foundry). Stockpiling components is necessary for ready repairs. D34 Confirm that the proactive asset management program used for MWSS has been applied to the AWSS program. This includes utilization of a common repository of system information to be used in developing systems goals and performing maintenance and R&R activities. D35† There is no current routine for system valve exercising and maintenance. This should be included in the asset management preventative maintenance tasks. D36† There are no established protocols for routine cistern inspection, testing, and filling. D37† There is currently no established protocol for coordination between SFPUC and SFFD staff related to AWSS. It is noted, however, that development of a MOU between the two departments is underway. D38† Currently, no proactive leak detection or forensics/testing program (i.e. stress strain curves for various aged pipe) is employed for the AWSS pipeline system. The methods to be considered are written in the Task 5 TM. D39† Detailed pipeline leak records do not exist and should be maintained in a GIS format to assist with ongoing assessment of pipeline condition, identifying corrosion hot-spots and estimating actual AWSS-specific pipeline life expectancy. D40† Some of the below grade motorized valve battery bank vaults experience flooding. At Eddy St. & Larkin St., an above ground enclosure cabinet should be installed or provide a discharge pumping system to eliminate the possible flooding which damages the motorized valve batteries. D41* Several fireboat manifolds and pipelines may be susceptible to seismically induced failures. This is because they are located on piers along the waterfront – many of which are in questionable condition. In addition, the existing geologic conditions and future seismic performance of the piers may create interaction action issues with the fireboat manifold piping and cause significant damage and potentially complete failure of these facilities. According to SFPUC staff, only two of the 5 fireboat manifolds are currently installed in solid ground foundations - Islais Creek and Fisherman’s Wharf. Further analyses and consideration towards relocating these facilities may possibly improve seismic reliability of these facilities. D42*,† Failure of infirm area hydrants at elbows and branches were significant problems during the Loma Prieta earthquake. Some failures were caused by shear failures of the cast iron elbow below the hydrant. CS-199 AWSS Facilities Preliminary Options Study 25 Task 11 Project Report Deficiency ID Description D43* There are many areas where the AWSS pipelines cross over, under, or through other utilities. These crossings present seismic vulnerabilities, particularly in the infirm areas. In the areas where AWSS pipes cross pile-supported sewers, the AWSS pipes will either settle over time or due to seismically induced conditions. In these locations, construction of flexible joints is a possible mitigation method. Identification of these locations and development of a mitigation program is recommended. D44* There are still many existing cast iron pipelines located within infirm areas. These cast iron pipelines are more prone to seismically induced failures than ductile iron pipelines. SFPUC should develop a program for pipeline replacement in the infirm zones. D45* Pipeline replacement should be considered where the pipelines cross infirm zone transitions and where old cast iron pipelines with lead joints were originally installed. Replacing these joints with new ductile iron gasketed or flexible joints would allow greater deflections and improve seismic reliability. D46* Reliability upgrades are needed at several facilities that were not included as part of the 2010 bond projects were identified in SFPUC’s Condition Evaluation Reports and are described in the Task 2 TM. Hydraulic Deficiencies D47* Areas of the highest zone (Twin Peaks zone) have insufficient pressure using the Twin Peaks Reservoir. The relative lack of pressure due to the high elevations in the zone and the lack of a gridded system with multiple pipes to reach these demands are identified as a system need. D48* Areas of Laurel Heights, Cole Valley, Noe Valley, and Castro Street have low pressures. The relative lack of pressure is due to the higher elevations and the lack of a gridded system to reach this demand. This is identified as a system need. D49* Three infirm zones are not seismically isolated immediately after an earthquake by seismically-induced control valves. This is identified as a system need. D50* The areas south of Islais Creek are isolated following an earthquake. The lack of a gridded system, backboning or separate supply feeding this areas south of the infirm zones is identified as a system need. D51* Of the 46 fire response areas identified in the Task 8 modeling process, only 37 can currently be connected to the high pressure pipe system. The others are not currently served by pipelines. This is identified as a system need. D52* System supply is limited to the existing reservoir and tanks, Pump Station 1 and Pump Station 2. The total supply capacity is less than that needed to meet the system demands as modeled in Task 8. These supplies were installed when the system was first constructed and focus on the northeast quadrant of the City. This is identified as a system need. D53* A long-term pipeline replacement plan should be developed based on ongoing inspection, testing and analysis. The 77 miles of original pipeline construction should be addressed within the next 50 years. CS-199 AWSS Facilities Preliminary Options Study 26 Task 11 Project Report 2.8 Project Identification The needs assessment phase identified 47 projects (Table 2-3) which appeared feasible, provided significant benefit to the AWSS, and addressed the deficiencies identified above in Section 2.7. These projects could also be combined to produce Program Alternatives that could meet the LOS performance objectives identified in Section 2.6.1. Table 2-3. List of Potential Projects – Needs Identification AWSS Project ID Project Name Deficiency ID 1 Motorization and Addition of Seismic Switches on Gate Valves D49 2 4th Street Bridge Connection D15 3 PS1 Tunnel Upgrade 4 Twin Peaks Outlet Connection D47 5 Jones St Tank Bypass Valves D29 6 Repair Suction Connections D30 7 SCADA Improvements 8 Fireboat Manifold Rehabilitation & Replacement 9 Pipeline Investigations and Repairs D2, D7, D8, D9, D10, D12, D14, D43 10 Sutro Connection and Pump Station D47, D52 11 Reliability Upgrades at Facilities 12 Cistern Repair and Construct 30 New Cisterns, Phase 1 13 Construct 30 New Cisterns, Phase 2 D51, D52 14 Construct 37 New Cisterns, Phase 3 D51, D52 15 Construct 25 New Cisterns, Phase 3 D51, D52 16 Construct 120 New Cisterns, Phase 4 D51, D52 17 Construct 120 New Cisterns, Phase 5 D51, D52 18 Construct 111 New Cisterns, Phase 6 D51, D52 19 Balboa Tank and Booster PS D52 20 Alemany Extension Pipeline D51 21 Silver Extension Pipeline D51 22 Geneva Extension Pipeline D51 23 Lake Merced Pump Station D52 24 Sunset Extension Pipeline D51 25 Sunset Extension Rezoning Pipeline D51 26 Richmond Extension Pipeline D51 CS-199 AWSS Facilities Preliminary Options Study D4,D5,D42 D20, D22, D23 D1, D3, D6, D41 D46 27 D13, D51, D52 Task 11 Project Report AWSS Project ID Project Name Deficiency ID 27 University Mound Reservoir D52 28 Sunset Reservoir Connection and Pump Station D52 29 New Bay Suction Connections D52 30 Pipeline Replacement Program, Phase 1 D12, D42, D43, D53 31 Pipeline Replacement Program, Phase 2 D53 *32 West Side Storage Tank D52 *33 CDD Reservoir Suction Connections D52 *34 GG Park south side suction line D47 *35 Pump Station 2 Capacity Upgrade D52 *36 Southside Storage D52 *37 Cole Valley Connector Pipeline D48 *38 Twin Peaks Connector Pipeline D47 *39 Twin Peaks Extension Pipeline D51 *40 24th Street Pipeline Upgrade D48 *41 Castro Street Pipeline Upgrade D48 *42 Stanford Heights Reservoir D52 *43 Laurel Heights Connector Pipeline D48 *44 Infirm Zone Pipe Replacement Phase 1 D45, D50 *45 Infirm Zone Pipe Replacement Phase 2 D44, D50 *46 Infirm Zone Pipe Replacement Phase 3 D44, D50 *47 Infirm Zone Pipe Replacement Phase 4 D44, D50 Pipeline Investigations and Repairs (AWSS Project ID 9) has a budget of $4 million to perform initial testing as recommended in the Task 5 TM. Two phases of a Pipeline Replacement Program have also been included as capital projects (AWSS Project IDs 30 and 31). Originally a replacement rate of 1.5 miles per year was assumed, consistent with the preliminary objective to replace all original 1913 construction cast iron pipelines within 50 years. Following further analysis in Task 9.1 the replacement rate for budgeting purposes has been changed to 0.5 miles per year. Replacement rates should be adjusted as the results of testing activities are received and interpreted. Further study can consider strategic abandonment of some of the older and smaller diameter cast iron pipelines in areas where the AWSS pipe and hydrant density is high and modeling indicates that excess capacity is available. Decisions regarding pipe replacement vs. abandonment can be made during project level planning, based on the results of hydraulic and/or reliability modeling. CS-199 AWSS Facilities Preliminary Options Study 28 Task 11 Project Report From the list of projects developed during the needs identification phase, 16 projects (AWSS Project ID #s 32 to 47, denoted by an “*”) were not selected for inclusion in any of the three Program Alternatives (identified in Section 4.0), and were not carried forward for further evaluation. Projects were generally omitted because their costs and impacts did not compare favorably to those of other projects. Details for each of the 31 projects carried into the Program Alternatives are discussed in Section 3 and Appendix A. 2.9 Project Analyses Analysis of the potential projects was performed as part of the initial screening to collect information to be used in the evaluations, including consideration of siting and construction issues, permitting requirements, operational considerations, as well as potential environmental, geotechnical, and right-of-way issues. For right-of-way issues, it was generally assumed that areas located in the street from curb to curb were owned by CCSF, except for where projects cross Caltrans State Highway corridors. For each project, construction cost and duration was estimated, along with any potential cost and schedule risks. Findings for each project are presented in the project datasheets included in Appendix A. 2.10 Project Performance/Sizing Criteria Sensitivity analyses of key hydraulic modeling assumptions were performed to understand how changes to inputs may affect the results of the hydraulic analysis. Parameters evaluated include: Break and Leak assumptions Number of Monte Carlo damage scenarios Operation of infirm zones following earthquake Fireboat pumping Location of demands Dispersed vs. Concentrated Demands Ability to meet partial demands Results of the sensitivity analyses are documented in the Task 8 TM. FRAs were proposed in the development of the LOS criteria to allow review of water supply reliability performance at a more detailed level throughout the City. It was proposed that each FRA be scored and that those scores be combined using a non-weighted average to generate a city-wide score. CS-199 AWSS Facilities Preliminary Options Study 29 Task 11 Project Report Modules were developed to analyze the reliability and benefits of the cisterns, suction connections, and alternative water sources in existing and future conditions. 2.10.1 Pipe Fragility Following analysis of multiple pipe fragility estimation methodologies and review of this work with TAP members it was decided to utilize a combination of two methods for the AWSS. The mixed method consisted of: Infirm areas: TAP recommended rate of 3 repairs per kilometer Non-infirm areas: Utilize the Jeon (2002) 12-inch Cast Iron and Ductile Iron fragility curves vs. peak ground velocity methodology Historical gatebook data for liquefaction-susceptible areas was considered for infirm areas. The infirm zones are shown in Figure 2-6. CS-199 AWSS Facilities Preliminary Options Study 30 Task 11 Project Report Figure 2-6. Gatebook vs. AECOM/AGS Infirm Zones The mixed method chosen for the AWSS pipeline fragility analysis yields the following calculated results: Infirm Areas: 115 Repairs Non-Infirm Areas: 20 Repairs Total: 135 Repairs These values represent the theoretical average number of repairs based on the estimated repair rates and the pipe lengths but may not be representative of each modeled damage scenario as those are dependent on random generation. CS-199 AWSS Facilities Preliminary Options Study 31 Task 11 Project Report 2.10.2 Non Earthquake Hydraulic Model Results Non-earthquake runs were performed for both the MWSS and AWSS to review their ability to provide 1,500 gpm at set residual pressures. This analysis was performed using the SynerGEE fire flow testing module. The MWSS was capable of providing 1,500 gpm at 20 psi residual at 69% of the hydrants, and the AWSS was capable of providing 1,500 gpm at 100 psi at 80% of the hydrants with the three separate zones and 99% of the hydrants when operating as one zone. 2.10.3 Post-Earthquake Hydraulic Model Results Figure 2-5 on page 21 shows the reliability scores by FRA based on modeling using the average demands for the HPS and the full stochastic set of demands for the cisterns, alternate water sources, and suction connections. Scores above 100% were capped at 100%. The Citywide reliability score is 47%, assuming equal weighting across all FRAs. As can be seen in the figure, the vast majority of the northeastern quadrant of the city is highly reliable, as it reflects the original design and intent of the AWSS. 2.10.4 Project Configuration Projects were configured using the hydraulic and reliability modeling tools developed and described in the Task 3 and Task 8 TMs. The existing AWSS high pressure system modeling results were used to understand areas of concern and issues with the existing system. The system was reviewed first using the separate pressure zones, and then reviewed using a single pressure zone. The hydraulic model, SynerGEE, was used to identify areas of low or negative pressure with the demands applied to an unbroken system. With the separated zones, projects were added which provided supply or transmission capability to increase pressures to 20 psi minimum. The impacts of each individual project were assessed using SynerGEE. As projects were added to meet demands and reduce negative pressures, the impact with single and combined pressure zones was noted. Once a package of projects was developed that met all demands in an unbroken pipe system, these projects were used as inputs to the reliability model, GIRAFFE. GIRAFFE produced a random application of breaks and leaks so the results from GIRAFFE are different from the results of the unbroken hydraulic model. Analysis of the various failure locations (GIRAFFE was run 15 times, which was sufficient for convergence, for each project package) would indicate whether a demand node could be met in any situation with a given set of projects. CS-199 AWSS Facilities Preliminary Options Study 32 Task 11 Project Report Additional project selection and prioritization was done primarily in SynerGEE, with GIRAFFE used to confirm the selection. The project selection was performed in three rounds, as described below: Round 1: Primary objective to increase City-wide reliability in the current system by adding capacity and redundancy; Round 2: Primary objective to increase City-wide reliability to the western and southern parts of the city by adding additional pipe capacity and water sources; and Round 3: Primary objective to increase individual FRA reliabilities with focus on the southern and western portions of the city. Table 2-4 lists some of the major projects associated with each round. For the prioritization process, each group of projects was included into the hydraulic model and projects were removed one at a time to determine the project with the most impact to the demand nodes (i.e., not meeting the requested demand at 20 psi). The project with the highest impact was selected and in the next round, the projects were all evaluated again in this single elimination process but with the highest impact project removed. This process was done successively such that projects removed first were those with the highest impact to the hydraulic network and those remaining were of lowest priority. Pumps and pipes were sized using iterative methods with the hydraulic model to find the minimum capacities and diameters necessary to meet the demand set. In general, new pipes were assumed to be 20 inches in diameter or less. The pump capacities and pressures were developed iteratively using the SynerGEE model. The hydraulic and reliability models were utilized to provide an instantaneous ability to meet the demands. Storage tank capacity was calculated using a spreadsheet tool developed for this project with the assumption that the 60 minute demands could be maintained for a minimum of 6 hours without refill. 24 hour simulations were also performed to confirm the ability of the system to maintain flows for greater than 6 hours. Table 2-4. Selection of Improvement Projects Round 1 Round 2 Round 3 Pump Station 1 Sunset Loop Summit Reservoir Lake Honda Pump Station Lake Merced Pump Station Sutro Reservoir All Division Gates Open Richmond Extension Stanford Heights Reservoir West Side Storage Tank South Side Storage Sunset Reservoir Pipe Upsize (Upper Zone) Geneva Extension Balboa Tank Laurel Heights Connector Alemany Extension University Mound Reservoir Doubling Pump Station 2 Capacity Silver Extension Twin Peaks Connector CS-199 AWSS Facilities Preliminary Options Study 33 Task 11 Project Report A shift in the scoring focus (i.e., from overall citywide reliability to minimum FRA reliabilities) changed the project prioritization, as seen in Round 3. Some of the projects identified in Rounds 1 and 2 were no longer advantageous to achieve the objective of raising FRA scores equitably. CS-199 AWSS Facilities Preliminary Options Study 34 Task 11 Project Report 3.0 Program Alternatives An “alternative” is one of several ways of satisfying the needs identified in Section 2.0. This section describes the process used to develop three Program Alternatives from the list of projects developed in Section 2.10, and describes each alternative in detail as required for the alternatives analysis phase. 3.1 Development and Description of Program Alternatives Table 3-1 shows the prioritization of the major pipeline, storage, and supply projects for the three Program Alternatives that were a result of the hydraulic benefit analysis in SynerGEE described in Section 2.10. Following development of the projects and preliminary project packages, GIRAFFE runs were performed to determine citywide and FRA scores. These preliminary packages were presented to TAP, Technical Steering, and the Management Oversight Committee. Preliminary LOS objectives were recommended and modifications to the LOS and packages were made based on input from SFPUC. Additional cisterns were added to FRAs to meet the goal of 50% minimum reliability per FRA. Table 3-1. Alternative Program Prioritization Alternative A Alternative B Balboa Tank and Pump Station University Mound Pump Station and Silver Loop Alemany Loop Lake Merced Pump Station Silver Extension Sunset Loop and Sunset Reservoir Pump Station Geneva Loop Sutro Reservoir Pump Station Lake Merced Pump Station Richmond Extension Sunset Loop Alemany Loop Richmond Extension Geneva Loop Alternative C All Cistern Alternative Sutro Reservoir Pump Station and Connection to AWSS In some cases, multiple projects were identified that could each meet a specific goal. For example, new supply was identified as a need for the Twin Peaks zone. Several projects were identified which can meet that goal. One project was selected for the Program Alternatives analysis (the Sutro Reservoir Connection); however, future project level alternative analysis and environmental review should evaluate all of the identified potential projects which can achieve CS-199 AWSS Facilities Preliminary Options Study 35 Task 11 Project Report the same goal. These decisions should be revisited during project alternative analysis phases, and are discussed in Section 5.3 of this TM. During project development, input from SFPUC indicated that use of existing Water System Improvement Program (WSIP) hardened storage and transmission facilities would be acceptable and preferable. Additional projects were developed to utilize existing storage facilities using air gapped booster pump stations located on SFPUC owned land. In addition, the consultant team was made aware of existing SFPUC property adjacent to AWSS pipelines at the former Balboa reservoir location. A project was developed to utilize this site for a tank and booster pump station for south side supply. In developing storage projects, the volume of water lost in the first 60 minutes of an earthquake event (due to AWSS losses only) was calculated by taking each of the 15 Monte Carlo GIRAFFE runs damaged systems and finding the flow out of the tanks without any additional demand for firefighting. This would then be the volume of water lost just from leaks and/or breaks. The flows were then averaged and subtracted from the total tank volume. The tank duration was then the remaining volume divided by the average of the 15 damage scenario flows with the firefighting demands for each water source. The numbers in Table 3-2 assume that no refilling is occurring. Alternative B capitalizes on the large capacity of Sunset and University Mound tanks. Discussions with CDD have indicated that they would reserve some portion of the total volume for domestic water supply. It would be possible to make the proposed Balboa Tank larger to increase the available storage duration for Alternative A. Table 3-2. Potential Water Volume Loss and Tank Duration Source Total Volume (MG) Twin Peaks Reservoir 2010 Bond Alternative A Alternative B Storage Avg. Volume Lost in First Hour (gal) Storage Duration (hours) Avg. Volume Lost in First Hour (gal) Duration (hours) Avg. Volume Lost in First Hour (gal) Storage Duration (hours) 10.5 1,443,288 4.4 964,564 6.5 1,039,712 6.5 Ashbury Tank 0.5 0 - 0 - 0 - Jones Tank 0.75 107,061 2.4 0 5.2 0 3.4 Sutro Reservoir 31.4 509,083 30.9 365,332 39.9 204,632 39.6 Balboa Tank 10 489,964 8.1 Sunset Reservoir 176.7 303,212 212.4 University Mound Reservoir 140.9 463,918 147.2 CS-199 AWSS Facilities Preliminary Options Study 36 Task 11 Project Report 24 hour GIRAFFE simulations were performed which confirmed the stability of the storage at the 60 minute flows. Once the recommended LOS objectives were reviewed and additional projects developed, revised Program Alternatives were formulated. The hydraulic model was used to develop the Program Alternatives and GIRAFFE scenarios were run to confirm which sets of projects would meet the LOS objectives. Iterative GIRAFFE runs were completed to finalize the Program Alternatives. Three Program Alternatives were developed that could each achieve the LOS goals with different projects. Each was formulated with a different strategy. To meet each FRA demand with 50% reliability, either new pipe (and supply) or new cisterns were required. New pipe would increase the reliability score to greater than 50%. Cisterns can be added one by one to get to the target reliability in each FRA. For each cistern added, there is an increase in reliability. For pipeline extensions, the whole pipe needs to be installed to meet a system demand. The new pipeline would likely exceed the 50% target reliability. Figure 3-1 shows this concept. Figure 3-1. Step vs. Ramp Function of Pipeline vs. Cisterns 120 % Reliability 100 80 60 Pipeline Extensions Cistern Additions 40 20 0 1 2 3 4 5 6 7 8 9 10 Incremental Project Additions Alternatives A and B include added storage, pumping, and pipeline extensions to serve the balance of the City. Alternative A uses a new tank and booster pump station located at the former Balboa reservoir site to serve the southern portion of the City. Alternative B uses existing MWSS storage through air gaps and booster pumps at University Mound and Sunset Reservoir instead of the Balboa project. In addition to pipeline alternatives with various water sources, a “no new pipeline” alternative was developed to address feedback from the SFPUC that CS-199 AWSS Facilities Preliminary Options Study 37 Task 11 Project Report minimizing O&M costs was desirable. Calculations of O&M costs shown in Appendix B2 actually indicate that the all cisterns alternative has higher O&M costs due to the regular filling and inspection requirements. The full Program Alternatives are shown in Table 3-3. Each Program Alternative was assessed to confirm its viability in meeting the system LOS objectives. Table 3-3. Program Alternatives Alternative Project # Project Name 1 Motorization of Seismic Switches on Gate Valves 2 4th Street Bridge Connection 3 PS1 Tunnel Upgrade 4 Twin Peaks Outlet Connection 5 Jones St Tank Bypass Valves 6 Repair Suction Connections 7 SCADA Improvements 8 Fireboat Manifold Rehabilitation & Replacement 9 Pipeline Investigations and Repairs 10 Sutro Connection and Pump Station 11 Reliability Upgrades at Facilities 12 Cistern Repair and Construct 90 New Cisterns, Ph. 1-3 13 Construct 270 New Cisterns, Phases 4-6 14 Balboa Tank and Booster PS 15 Alemany Extension Pipeline 16 Silver Extension Pipeline 17 Geneva Extension Pipeline 18 Lake Merced Pump Station 19 Sunset Extension 20 Sunset Extension Rezoning 21 Richmond Extension 22 University Mound PS 23 Sunset Reservoir 24 New Bay Suction Connections 25 Pipeline Replacement Program Phase 1 26 Pipeline Replacement Program Phase 2 A CS-199 AWSS Facilities Preliminary Options Study 38 B C Task 11 Project Report Figure 3-2, Figure 3-3, and Figure 3-4 below show the project locations for the three Program Alternatives. Figure 3-2. Alternative A CS-199 AWSS Facilities Preliminary Options Study 39 Task 11 Project Report Figure 3-3. Alternative B CS-199 AWSS Facilities Preliminary Options Study 40 Task 11 Project Report Figure 3-4. Alternative C CS-199 AWSS Facilities Preliminary Options Study 41 Task 11 Project Report 3.2 Non-Construction Alternatives The list of deficiencies (Table 2-2) developed for the needs assessment phase included some needs which are not appropriately addressed by capital improvements, including such items as organization of data, training, O&M activities, etc. These deficiencies should be addressed through non-construction alternatives which are performed outside of the CIP. Recommendations listed below in Table 3-4 are developed in detail in Section 7. Table 3-4. Deficiencies Addressed by Non-Construction Alternatives Non-Construction Recommendations Deficiencies Addressed Establish a pipeline leak database to monitor potential hot spots D39 Establish a Cistern inspection, filling, and testing program D36 Train SFPUC personnel on system D16, D17 Develop a system outage policy and procedures for planned outages D16, D21, D25 Confirm that all AWSS assets are entered into CDD's asset management system and Preventative Maintenance requirements are established D11, D34, D35, D37, D40 Identify Regular pump maintenance and testing requirements D32 Provide staff to coordinate system needs and upgrades with SFFD D16, D18, D19 Prepare emergency pipeline repair, readiness and response program similar to MWSS program D10, D16, D21, D24, D26 Establish flushing program for AWSS D31 Establish leak detection program for AWSS D1, D27, D38 Check and back flush all suction connections regularly, repair or replace as needed D30 Establish program to replace hydrant laterals D42 Establish regular pipeline replacement fund/projects D33 Ongoing maintenance is required in order to avoid deterioration of the existing AWSS assets and to maintain the current reliability of the existing system. These recommendations are organized into new programs and detailed in Section 7. CS-199 AWSS Facilities Preliminary Options Study 42 Task 11 Project Report 3.3 Data Gaps The following summarizes the information data gaps that should be closed for subsequent project phases and to facilitate fully developing AWSS assessment recommendations: 1. Comprehensive detailed maps which identify the various corrosion conditions areas of the City and how they specifically relate to AWSS facilities and pipelines 2. Information to assess the site-specific condition of the AWSS pipelines. There have been no pipeline conditions assessments since V&A’s 1988 (see the Task 5 TM) to assess existing areas of current leakage, condition, corrosion rates to date, typical remaining useful lifespans, etc. 3. Comprehensive historical leak and break repair data records 4. Current pipeline system leak detection records 5. The locations and condition of old non-stainless steel tie rods 6. Condition and reliability assessment of docks, seawalls, and effects on AWSS facilities 7. Locations of known water quality/sediment issues in pipe network 8. Locations of pipes without suitable internal concrete mortar lining 9. Identification of AWSS utility pipe crossings such as through sewers, ducts, etc. 10. Condition assessment of suction connections 11. Comprehensive AWSS maintenance records and procedures 12. Comprehensive AWSS operations procedures and records 13. Assessments of SFPUC staffing needs 14. Clarification of AWSS GIS existing and missing information records CS-199 AWSS Facilities Preliminary Options Study 43 Task 11 Project Report 4.0 Alternatives Evaluation and Scoring The Alternatives Analysis step develops the potential alternatives listed above in Table 3-3 in sufficient detail such that they can be compared and ranked in an evaluation process, and described in any required environmental review. Any issues associated with an alternative should be identified with possible mitigations. Information related to the selected project criteria is identified and quantified, for the purpose of differentiating the benefits, impacts, and issues between the alternatives, and confirming viability in design and construction. 4.1 Evaluation Process Analytical Hierarchy Process (AHP) is used for the evaluation of alternatives and the selection of a Preferred Program Alternative. AHP is a structured technique for organizing and analyzing complex decisions. Rather than prescribing a "correct" decision, the AHP helps decision makers find one that best suits their goal and their understanding of the problem. It provides a comprehensive and rational framework for structuring a decision problem, for representing and quantifying its elements, for relating those elements to overall goals, and for evaluating alternative solutions. The decision process analyzes each evaluation criteria independently. The decision makers systematically evaluate the various elements by comparing them to one another two at a time, with respect to their impact on the criteria. In making the comparisons, the decision makers use the available data and quantitative analysis but also their judgments about the elements' relative meaning and importance. It is the essence of the AHP that human judgments, and not just the underlying information, can be used in performing the evaluations. The AHP converts these comparisons to numerical values that can be processed and compared over the entire range of the problem. A numerical weight or priority may be assigned to each criterion, allowing diverse and often incommensurable elements to be compared to one another in a rational and consistent way. This capability distinguishes the AHP from other decision making techniques. A prioritization matrix approach was employed. This method compares each alternative to every other alternative and ranks them with respect to a particular criterion. The result of this evaluation work is the Alternative Ranking Matrix. The ranking matrices for this study are included in Appendix E. In comparing criteria and alternatives, the following scores for pair-wise comparisons are used. CS-199 AWSS Facilities Preliminary Options Study 44 Task 11 Project Report Table 4-1. Scoring of Pair-Wise Comparisons Results of Comparison Score for A Score for B Alternative A is extremely preferable to Alternative B 10 1/10 Alternative A is significantly preferable to Alternative B 5 1/5 Alternative A is about equally preferable to Alternative B 1 1 Alternative A is significantly less preferable to Alternative B 1/5 5 Alternative A is extremely less preferable to Alternative B 1/10 10 4.2 Criteria for Analysis and Evaluation of Alternatives The evaluation criteria are a reflection of organizational policy governing the selection of the proposed solution from a number of alternatives that satisfy or address the same problem. Ideally, evaluation criteria should: Differentiate meaningfully between solutions without bias; Apply to all organizational operations; Relate to the organizational goals; Reflect qualities that are important to the success of the projects; Reflect characteristics that can be measured or assessed; Be independent; and Be understood. The evaluation process performed under Task 3 to develop LOS Criteria and Performance Objectives also identified considerations for project alternatives analysis. Specifically, while not suitable as LOS Criteria, three of the potential objectives following were identified as criteria for project alternatives analysis (Nos. 1-3 below). To this list, four additional criteria have been added (Nos. 4-7). 1. Cost (Capital, Annual Operations and Maintenance, and Life Cycle) CS-199 AWSS Facilities Preliminary Options Study 45 Task 11 Project Report 2. 3. 4. 5. 6. 7. Operations and Maintenance Schedule Water Supply Delivery Reliability Fire Fighting (Resources and Deployment Time) Insurance Premiums Benefits Environmental/Community Impacts These considerations were quantified and compared for each Program Alternative. The project information was aggregated to evaluate and compare the Program Alternatives, and used in the AHP to select a Preferred Program Alternative. For this planning study some of the criteria commonly used by the SFPUC were not used because they were considered equivalent between the three alternatives, or not applicable. Water quality, water treatment, wastewater treatment, and flooding issues were not considered relevant to the analysis. Differences in hydraulics are addressed through delivery reliability and firefighting criteria. Geotechnical issues were considered on a project by project development basis and are generally equivalent between the three alternatives. Legal and right of way issues were considered equivalent between the three alternatives. 4.3 Cost This section presents analyses to estimate and compare the costs of each alternative of the following types: capital cost, annual operating cost, and life cycle cost (net present value). Each cost type was evaluated at the project level as documented in Appendix B; with the individual project costs summed based on which projects are included in which Program Alternative. Assumptions made in developing cost information were as follows: Construction Costs Construction cost opinions were based on project descriptions found in Appendix A. Estimates prepared by the cost estimator did not include construction contingency, design contingency, design effort contingency or soft costs. These have been added based on the percentages shown in Table 4-2 below, which were received from SFPUC and are equivalent to those percentages used in other projects for the 2010 ESER Bond. Capital Cost Planning level construction cost opinions were created for each project. To calculate capital costs, markups were applied based on the estimating assumptions listed in Table 4-2. CS-199 AWSS Facilities Preliminary Options Study 46 Task 11 Project Report Table 4-2. Capital Cost Assumptions Description Markup Soft Cost (% of Construction Cost) 25% Design Effort Contingency (% of Soft Cost) 10% Design Contingency (% of Construction Cost) 30% Construction Contingency (% of Construction Cost + Design Contingency) 10% Annual Operations and Maintenance Annual operating costs for the potential projects were developed from discussions with CDD pipeline and facility maintenance superintendents, utilizing the following labor rates: Gateman for valve operations: $ 89.30 per hour plus $20 per hour for additional cost for vehicle. Plumber (for hydrant flushing): $ 79.17 per hour plus $20 per hour for additional cost for vehicle. Estimates of annual O&M Costs for each potential project are included in Appendix B.2. Life Cycle Cost (Net Present Value) Net present value calculations were performed for each Program Alternative by incorporating capital cost expenditures by year escalated out to the year the expenditures occurred as indicated in the respective program schedules (Section 4.5). Annual O&M costs for each project were included once construction was completed and the facility was in service. All future expenses were then discounted back to the present value. Assumptions utilized for the life cycle costs are listed below in Table 4-3. CS-199 AWSS Facilities Preliminary Options Study 47 Task 11 Project Report Table 4-3. Life Cycle Cost Assumptions Value Escalation Rate Discount Rate 3.1% 4.7% Source Notes ENR Construction Cost Index, average from 1990 to 2011 For comparison, 2011 year was 3.0% General Obligation Bond Sales Based on Yield of 2011 Revenue bond sale with 2041 maturity Comparison of soft cost, construction cost, capital cost, annual O&M cost, and life cycle costs (net present value of new assets only) are presented below in Table 4-4. Existing assets were not included in the annual O&M and life cycle cost calculations because the O&M cost would not change between the three alternatives. All three alternatives include the same amount of rehabilitation and replacement of existing pipelines, and rely equally on the existing AWSS. Based on the costs presented in Table 4-4, Program Alternative pairwise comparisons for cost are as follows: Alternative A is worse than Alternative B Alternative A is significantly lower cost than Alternative C Alternative B is significantly lower cost than Alternative C Table 4-4. Cost Comparison of Original Program Alternatives including all Projects Alternative A (Ranking) Alternative B (Ranking) Alternative C (Ranking) Soft Cost $116,667,000 (2) $110,548,000(1) $161,861,000 (3) Construction Cost $606,667,000 (2) $574,849,000 (1) $841,676,000 (3) Program Capital Cost $723,333,000 (2) $685,397,000 (1) $1,003,537,000 (3) Annual Operations and Maintenance Cost (New Assets) $260,000 (1) $262,000 (2) $378,000 (3) Net Present Value (New Assets) $515,665,000 (2) $483,772,000 (1) $661,017,000 (3) Costs shown in Table 4-4 represent the full suite of projects identified for each Program Alternative including pipe replacement. These costs do not include potential cost sharing with the potable system, which the preferred program includes. In comparison, the preferred program estimated costs total $137 million without pipe replacement. CS-199 AWSS Facilities Preliminary Options Study 48 Task 11 Project Report 4.4 Operations and Maintenance This section presents operating changes, risks, and other issues related to the changes proposed to the AWSS under each alternative. The operations and maintenance criterion considers only benefits and impacts to system operators (SFPUC) and does not consider fire response, which is addressed in Section 4.6. It does consider the challenges the system operators would have in operating and maintaining the new facilities on an ongoing basis. As a starting point, the simplest way to compare O&M costs is to quantify the number of new facilities and other assets which would be constructed under each Alternative (pumps, valves, SCADA equipment, pipelines, high pressure hydrants, cisterns, etc.). This information is presented in Table 4-5 below. Table 4-5. Number of New Facilities Requiring Maintenance New Facilities Alternative A Alternative B Alternative C Pump Station at New Site(Ea.) 1 0 0 Pump Station at Existing Site (Ea.) 3 4 0 New SCADA Sites (Ea.) 32 32 22 New Motorized Actuator (Ea.) 23 23 13 New Gate Valve (Ea.) 12 12 2 New Tank/Reservoir (Ea.) 1 0 0 New Pipeline (miles) 20.9 21.4 0.1 New Suction Connection (Ea.) 0 0 10 New Cistern (Ea.) 97 85 371 Estimated Total Annual O&M Hours Associated with New Facilities 2348 2290 3500 FTE Equivalent (1760 hrs/FTE) 1.33 1.3 1.98 Also developed and presented is an estimate of the total additional annual O&M hours required to support the new facilities which would be constructed under each alternative. This does not include maintenance on existing facilities, which would be the same under each alternative. The estimates include such activities as cistern refilling, pump exercising, pipeline and hydrant CS-199 AWSS Facilities Preliminary Options Study 49 Task 11 Project Report flushing, and other activities required to maintain the new assets properly on an ongoing basis. Annual labor hour estimates attributed to each project are included in Appendix B.2. All three alternatives represent an expansion of the AWSS introducing additional maintenance requirements and operator duties compared with the existing AWSS. The primary differences are that Alternative A includes a new facility at a new site (the Balboa Tank and Pump Station) whereas Alternative B includes an additional pump station upgrade at two existing sites, and slightly more pipeline. Under Alternative C all expansion of the AWSS is in the form of cisterns. Although pipelines and pump stations require increased O&M activities to service the new assets as reflected in Table 4-5, it is notable that the cisterns also have significant O&M requirements, in the form of periodic (once every 10 years) draining, cleaning, and inspection, and more frequently visiting (twice a year for each) cisterns to check and fill as needed. Although not time consuming for one cistern, expanding the number of cisterns dramatically in the case of Alternative C would be a significant demand on CDD resources comparable with the pipelines and pump stations proposed under the other alternatives. Based on the information presented in Table 4-5 and the discussion above, Program Alternative pairwise comparisons for the operation and maintenance criterion are as follows: Alternative A is about the same as Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C 4.5 Schedule Preliminary phase durations have been estimated for each project based on three phases: planning (including environmental and permitting), design, and construction. Based on the estimated project durations, planning level program schedules were developed for each alternative considering schedule constraints as identified in the Task 3 TM, including: Available capital for construction expenditures Available staff and management time Operation constraints (minimize portions of system out of service) Construction impact minimization Other project impacts Planning level schedules for each Program Alternative are presented in Appendix C. The developed schedules show Alternatives A and B each completed by 2034, and Alternative C completed by 2046. CS-199 AWSS Facilities Preliminary Options Study 50 Task 11 Project Report Individual project work durations and relevant assumptions which drive the estimated durations are included in Appendix C. Of note regarding Alternative C is the long duration to construct the cistern projects, based on the limited ability to construct a large number of cisterns simultaneously. SFPUC experience under the 2010 ESER bond may better inform the design and construction durations as well as the number of cisterns which can be constructed simultaneously. The schedule assumed that latter phases of cistern construction achieved a higher number of simultaneous cistern projects (going from 30-40 in 1000 work days to 90 in 1000 work days). Based on the information presented above, primarily the estimated duration to construct each Program Alternative, pairwise comparisons for the schedule criterion are as follows: Alternative A is about the same as Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C 4.6 Water Supply Delivery Reliability This section presents Program Alternative evaluations on the basis of the LOS criteria of water delivery reliability and geographic coverage. Delivery reliability is evaluated at the program level only using the modeling process described in Section 2.6. Although all three Program Alternatives were developed and configured specifically to meet the two selected LOS objectives of a minimum of 50% reliability in each FRA and a minimum citywide reliability of 90%, they are not equal under both objectives. Specifically the 50% minimum by FRA generally governed the selection of projects, with all three Alternatives exceeding the 90% citywide goal as well as being much greater than 50% for many of the FRAs. The Program Alternatives can therefore be compared by their ability to exceed the minimum objectives, which translates to superior post-earthquake performance. The figures below present reliability scores by FRA for each alternative. Table 4-6 shows the citywide reliability scores (the average of the FRA reliability scores) for each alternative. CS-199 AWSS Facilities Preliminary Options Study 51 Task 11 Project Report Figure 4-1. Alternative A Delivery Reliability by FRA CS-199 AWSS Facilities Preliminary Options Study 52 Task 11 Project Report Figure 4-2. Alternative B Delivery Reliability by FRA CS-199 AWSS Facilities Preliminary Options Study 53 Task 11 Project Report Figure 4-3. Alternative C Delivery Reliability by FRA CS-199 AWSS Facilities Preliminary Options Study 54 Task 11 Project Report Table 4-6. Comparison of Serviceability and Citywide Delivery Reliability Criteria Citywide Average Reliability Alternative A Alternative B Alternative C 90% 92% 86% Based on the information presented in Table 4-6 above, pairwise comparisons for delivery reliability are as follows: Alternative B is slightly better than Alternative A Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C 4.7 Fire Fighting The firefighting criterion considers SFFD support required for each alternative, in terms of staffing and equipment, and the department’s ability to leverage the AWSS improvements to fight fires. The SFFD fights fires using various available sources of water, including AWSS hydrants, suction connections, cisterns, MWSS hydrants, and the PWSS. Setup and equipment requirements as well as deployment time are not the same for each source. In many situations, multiple water source options will be available to meet a given fire demand. Given alternatives, the SFFD will select the source with the lowest equipment needs and deployment time, associated with the quickest response and lowest demand on SFFD equipment and staff resources. Where multiple sources are required to meet the entire fire demand, demands may be met using more than one source brought online at different times. The SFFD has provided feedback that during a regional emergency they have the ability to request significant staff assistance by recalling all active staff to duty. Thus the SFFD’s capabilities are not generally limited by the availability of qualified fire fighters. By contrast, the number of fire engines available at a given time is limited by the number of engines in the City which are not being serviced or maintained, or already out on other calls at the time the emergency occurs. The Fire Department has provided input that the number of fire engines required is the critical parameter for evaluating the ability of the Department to respond to a particular emergency scenario. In the case of a major earthquake SFFD is not expecting to receive assistance from adjacent cities through mutual aid. The different sources of water have different equipment requirements. The high pressure pipe system can be utilized by firefighters with a Gleason valve and hose with appliances. Gleason valves can be delivered to the site along with firefighters as needed. No engine is required as CS-199 AWSS Facilities Preliminary Options Study 55 Task 11 Project Report long as system pressures are sufficient (60 psi or higher). Other sources require an engine to pressurize the water for use by firefighters. The approach for comparing resource needs between the alternatives is to identify the new sources of water to fight fires which would be available under each alternative under the various system damage scenarios, then to calculate the number of engines required in order to fight the fires throughout the City. When the number of resources needed exceeds that available, it means the SFFD would not be able to respond to the emergency in an appropriate fashion, or alternately that additional resources should be obtained in advance in order to support the need, specifically increasing the number of fire engines in San Francisco and increased fire department staffing levels to support those engines. Deployment time is another useful metric for evaluating fire response. It is defined as the delay between fire response being initiated by the SFFD and the fire demand being met. Deployment time includes the time to mobilize and deploy needed resources to the fire, equipment setup, ending when the needed water is applied to the fire. Deployment time is calculated as an average for each FRA and citywide based on hydraulic modeling results, using the best available source or sources to meet demand. Table 4-7 below lists deployment time and equipment requirements applicable to each source. This table was developed with SFFD input, and reflects approximate average response and setup times. Times listed are used for comparative purposes only, and do not represent actual targeted response times applicable to each source. Table 4-7. Deployment Time and Resources by Water Source No. Source Deployment Time (minutes) SFFD Resources Required 1 AWSS 20 Gleason Valve, up to 3 per hydrant 2 Cistern 30 Fire Engine 3 Bay Suction 30 Fire Engine 4 PWSS 60 Minimal pumping capacity available on PWSS trailer but can use fireboat or engine to supply water Equipment needs were calculated for all of the evaluated fire response scenarios and a probability distribution plot generated, shown below in Figure 4-4. The figure indicates a higher probability of needing more than the maximum available number of fire engines (20%) with CS-199 AWSS Facilities Preliminary Options Study 56 Task 11 Project Report Alternative C compared with A (2.2%) or B (2.1%). Up to 10 additional engines may be available if all relief engines were utilized. In some cases, fire engines may be available from neighboring cities, but assistance cannot be assumed because of the regional nature of a large earthquake, with other concurrent emergencies likely. Probability that Needed Engines will exceed x using 1000 demand sets Figure 4-4. Probability of Fire Engine Need Exceeding Availability 100% Alternative A Alternative B 80% Alternative C 45 engines (max on duty) 60% Alternative C requires 10 to 23 more engines than A or B 55 engines (w/ Relief) 40% 20% 0% 0 10 20 30 40 50 60 70 Number of Engines (x) CS-199 AWSS Facilities Preliminary Options Study 57 80 90 100 110 120 Task 11 Project Report Table 4-8. Firefighting Resources and Deployment Time Comparison by Alternative Alternative A Alternative B Alternative C % from High Pressure System 62% 65% 31% % from Cisterns 35% 33% 65% % from Suction Connections 1% 1% 2% % from Alternate Water 2% 2% 2% Average Deployment Time (minutes) 24.1 23.6 25.9 Statistics # of Fire Engines Mean 23.8 22.8 35.1 Required Max 65 60 95 45 (max available) 2.2% 2.1% 19.7% 55 (including relief) 0.4% 0.4% 7.9% Probability of inadequate Fire Equipment In evaluating fire response and deployment time, the municipal drinking water storage (tanks and reservoirs located in the City) was assumed available, but not the low pressure hydrants fed by the potable water system. The WSIP has spent considerable energy and funds in hardening storage and transmission facilities, but the potable distribution has not yet been upgraded. Additionally, the goal of the WSIP is to supply water within 24 hours after fire for delivery, compared to the use of the 60 minute demand for the AWSS use fighting fire following earthquake. Section 8.0 describes additional analyses performed to review the sensitivity of the results to the assumption of potable water availability. Based on the information presented above, Program Alternative pairwise comparisons for firefighting are as follows: Alternative A is about the same as Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C CS-199 AWSS Facilities Preliminary Options Study 58 Task 11 Project Report 4.8 Insurance Premiums Benefits The Program Alternatives were evaluated based on their potential to reduce fire insurance rates. Because Alternatives A and B extend pipelines to areas such as Richmond and Sunset and Alternative C would install cisterns in those areas, there would be a benefit to the insurance in those areas since they are not currently served by the AWSS. Based on the reliability discussed in Section 4.6, Table 4-9 provides the estimated values of fire premium for relative comparison purposes only. These are not absolute values of fire premiums, only notional (relative or theoretical) to permit relative comparison of the Alternatives A, B, and C. The results indicate that the Alternative B offers the most reduction in fire premium, with a notional fire premium of 1.8%. Alternative A results in a notional fire premium of 2%, almost as good as Alternative B. Alternative C results in a 6% notional fire premium. Table 4-9. Summary of Insurance Impacts (MMI Engineering) Existing 2010 Alternative A Alternative B Alternative C Citywide Reliability 47% 68% 90% 92% 86% Premium 32% 19% 3.9% 3.1% 5.5% Reinsurance Premium 3.3% 1.90% 0.15% 0.104% 0.105% Savings versus no HPS 7.0% 9.7% 13.1% 13.3% 12.8% Based on the information presented in Table 4-9, Program Alternative pairwise comparisons for insurance premiums benefits are as follows: Alternative A is about the same as Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C 4.9 Environmental/Community Impacts Environmental and Community effects are evaluated at the project level. Those individual project effects are summed into estimated impacts for the Program Alternatives. Preliminary scoring is based on the following general considerations which are used to quantitatively compare them: Construction footprint (square footage); CS-199 AWSS Facilities Preliminary Options Study 59 Task 11 Project Report Land ownership; Land use type (park, street, etc. also by % where more than one); Potential project interferences with known or possible archaeological zones of concern; Potential project interferences with known or possible environmental sensitivities; Construction schedule as it relates to environmental and community impacts; and Duration of impacts and whether temporary or permanent. Environmental impacts include noise, air pollution, habitat disturbance, water quality, water pollution from construction and temporary/permanent impacts. Other Project features are described in the Project Data Sheets in Appendix A. Issues of particular concern are discussed below. Construction Utility and other agency coordination is a consideration for all the Alternatives, with greater interferences for Alternatives A and B compared with C. Most facilities are located in land owned by the City and County of San Francisco, managed either by the Department of Public Works (as in the case of city streets), or the SFPUC. Some potential pipeline alignments run across or along street corridors owned by Caltrans. The Sunset Pipeline Extension runs along Sloat Blvd. (State Hwy. 35) and 19th Ave. (State Hwy. 1), both of which are managed by Caltrans. The Alemany, Geneva, and Silver Pipeline Extensions would run along streets which cross under (but do not directly conflict with) State Highways 101 and 280. Although on land owned by the SFPUC, the Balboa Reservoir project would require coordination with City College and mitigation of potential impacts to the College’s activities. Permitting Some streets within CCSF are also State Highways requiring coordination with Caltrans. Some projects are located along the waterfront or in some cases in the Bay, requiring coordination and permitting for potential work in SF Bay. Community Community effects include temporary or permanent disturbances in the functioning, lifestyle, and safety of residents living in proximity to the projects. Quantifications include the number of impacted residents, duration of the impacts (if not permanent), and traffic flow. CS-199 AWSS Facilities Preliminary Options Study 60 Task 11 Project Report Table 4-10. Summary of Environmental Effects Program Construction Duration (years) Project Footprint - new disturbance (sq. ft) Volume of soil to be disposed (CY) Cumulative Impacts (acre-year) Habitat (# of species disturbed) Habitat (sq. footage of disturbance) LF of pipe to be installed in City streets (common projects and Alt C includes pipe replacement projects) Common Projects Alt A Alt B Alt C 20 20 32 5,852,500 5,709,500 6,000,500 4,626,500 665,550 934 - 544,348 922 - 801,220 952 - 465,467 831 - 515,180 518,880 406,580 406,580 A Constraints and Opportunities Analysis of the potential projects by SFPUC Environmental staff indicates that potential constraints may be reduced by using Expanded Project Opportunity Areas for projects where there is flexibility in the final location or alignment. The potential environmental consequences and avoidance/mitigation recommendations prepared in this analysis will carry forward into the planning phase of the projects. Based on the information presented in Table 4-10, Program Alternative pairwise comparisons for Environmental/Community Impacts are as follows: Alternative A is worse than Alternative B Alternative A is better than Alternative C Alternative B is significantly better than Alternative C CS-199 AWSS Facilities Preliminary Options Study 61 Task 11 Project Report 5.0 Preferred Program Alternative 5.1 Scoring and Ranking of Preferred Program Alternative The Program Alternatives were compared using a pair-wise comparison method on seven different criteria. These evaluation criteria can be weighted. For this alternatives analysis, each criterion was weighted equally. This can be adjusted based on feedback from the SFPUC Steering Committee or other stakeholders. Table 5-1. Evaluation Criteria Weighting Evaluation Criteria Criterion Weight Cost 1 Operations and Maintenance 1 Schedule 1 Delivery Reliability 1 Firefighting Capability 1 Insurance Premiums 1 Environmental / Community Impacts 1 The following tables summarize the results of the evaluations and the reasoning behind their ranking. Table 5-2 shows the Program Alternatives score by each evaluation criteria using the pair-wise scoring system. Table 5-3 shows the ranking of the three Program Alternatives. CS-199 AWSS Facilities Preliminary Options Study 62 Task 11 Project Report Table 5-2. Alternative Scoring Evaluation Criteria Alternative A B C Delivery Reliability 40.2% 59.1% 0.8% Firefighting Capability 49.5% 49.5% 0.9% Cost 40.2% 59.1% 0.8% Schedule 48.4% 48.4% 3.2% Operations and Maintenance 25.4% 73.2% 1.5% Insurance Premiums 33.3% 33.3% 33.3% Environmental / Community Impacts 40.2% 59.1% 0.8% 40% 55% 6% Cumulative Score Table 5-3. Evaluation Ranking of Alternatives Ranking Alternative Evaluation Criteria Delivery Reliability 1 2 3 B A C Firefighting Capability A/B tie Cost B Schedule C A A/B tie Operations and Maintenance B Insurance Premiums C C A C A/B/C tie Environmental / Community Impacts Final Ranking B A C B A C Based on the rankings above, Alternative B is the Preferred Program Alternative. 5.2 Review and Recommendations AWSS needs have been identified, a LOS recommended and a program recommended that would bring AWSS to the recommended LOS in the most effective manner. These were presented to the following for review. Based on this review further analysis was performed as is described in Section 8.0. Technical Advisory Panel (consisting of Thomas Dennis O’Rourke, Thomas R. Biggs Professor, Civil & Environmental Engineering at the Sibley College of Engineering at Cornell University and Charles Scawthorn, Principal at SPA Risk LLC) Technical Steering Committee (consisting of technical supervisory staff from City departments) CS-199 AWSS Facilities Preliminary Options Study 63 Task 11 Project Report Steering Committee which was renamed Management Oversight Committee in September 2013 (consisting of the SFPUC General Manager, SFFD Chief, Department of Public Works Manager and deputies) For certain projects included in the Preferred Program Alternative, assumptions were made regarding the size, configuration, and location of the project. During the project level alternatives analyses, these assumptions should be verified, the project optimized, and other project level alternatives considered which fulfill the same objectives as the configuration which was assumed for this analysis. 5.3 Environmental Review Prior to approval of an alternative for implementation, environmental reviews for meeting local, state and federal environmental policy will be completed. For review of the Preferred Program Alternative, project-specific environmental reviews should be performed, addressing impacts related to biological species, cultural resources, water quality, hazardous materials, noise, visual issues, traffic, and air quality. The environmental review process requires that projects be evaluated together if they 1) are dependent upon one another to meet stated project objectives, or 2) together have consequences that are growth inducing, or 3) have other cumulative environmental impacts. Compared with other water infrastructure projects, expansion of the AWSS is not growth inducing in the sense that it does not lead to or encourage installation of new water services, increased water consumption, or encourage population increases. All of the potential projects are critical to the public safety by providing water to fight fires following a seismic event or other regional fire. Criteria proposed for the evaluation of independent utility of AWSS projects are directly related to the purpose of the projects and their connectivity in terms of function or purpose. In order to be considered independent, a project must satisfy the criteria shown in Table 5-4. CS-199 AWSS Facilities Preliminary Options Study 64 Task 11 Project Report Table 5-4. Independent Utility Criteria No. Criteria 1 Be a maintenance upgrade, replacement, or repair 2 Not change overall system operations 3 Be necessary even without a CIP 4 Be connected to other projects physically or operationally 5 Not drive outcomes or decisions on other projects or elements of the system Table 5-5 below assesses the independent utility of projects that would be constructed as part of the Preferred Program Alternative. Table 5-5. Independent Utility of AWSS Projects Project ID Project Name 1 Motorization and Addition of Seismic Switches on Gate Valves 2 4th Street Bridge Connection 3 PS1 Tunnel Upgrade 4 Independent Utility Criteria Independent Utility Dependent Projects Yes NA Yes NA Yes NA Twin Peaks Outlet Connection Yes NA 5 Jones St Tank Bypass Valves Yes NA 6 Repair Suction Connections Yes NA 7 SCADA Improvements Yes NA 8 Fireboat Manifold Rehabilitation & Replacement NA Yes NA 9 Pipeline Investigations & Repairs NA Yes NA 10 Sutro Connection and PS Yes NA 11 Reliability Upgrades at Facilities Yes NA 1 2 CS-199 AWSS Facilities Preliminary Options Study 3 4 NA NA NA NA 65 5 Task 11 Project Report Project ID Project Name 12 Cistern Repair & Construct 30 New Cisterns, Ph. 1 13 Pipeline Replacement Program, Phase 1 14 Independent Utility Criteria Independent Utility Dependent Projects Yes NA Yes NA Silver Extension Pipeline Yes NA 15 University Mound Reservoir Yes 14 16 Sunset Extension Pipeline Yes NA 17 Sunset Extension Rezoning Pipeline Yes 16 18 Construct 30 New Cisterns, Phase 2 Yes NA 19 Lake Merced Pump Station Yes 16 20 Sunset Reservoir Connection and PS Yes 16 21 Pipeline Replacement Program, Phase 2 Yes NA 22 Construct 25 New Cisterns, Phase 3 Yes NA 23 Richmond Extension Pipeline Yes 16 24 Alemany Extension Pipeline Yes NA 25 Geneva Extension Pipeline Yes 24 1 2 3 4 NA NA 5 Projects listed above as dependent should be evaluated together with the other projects listed as dependent during the project alternatives analysis and environmental review phases. 5.4 Funding and Staging Table 5-6. presents potential funding requirements for bond sales consistent with the proposed program schedule for the Preferred Program Alternative. The list has been compiled using the planning level schedules, but suggested size and timing do not bind the SFPUC to the project choices, project sequences, or scopes. CS-199 AWSS Facilities Preliminary Options Study 66 Task 11 Project Report Table 5-6. Potential Funding Project ID Priority Construction Start Date Project Cost ($M) 1 1 Motorization and Addition of Seismic Switches on Gate Valves 1/29/2015 $1,083,000 2 2 4th Street Bridge Connection 1/29/2015 $3,996,000 3 3 PS1 Tunnel Upgrade 3/8/2016 $529,000 4 4 Jones St Tank Bypass Valves 11/2/2017 $5,541,000 5 5 Repair Suction Connections 2/16/2018 $2,302,000 6 6 SCADA Improvements 10/15/2019 $2,643,000 7 7 Fireboat Manifold Rehabilitation & Replacement 10/15/2019 $290,000 8 8 Pipeline Investigations and Repairs 12/1/2015 $5,115,000 26 9 Sutro Connection and PS 4/18/16 $13,853,000 10 10 Reliability Upgrades at Facilities 6/10/2021 $17,050,000 11 11 Cistern Repair and Construct 27 New Cisterns 6/10/2021 $52,003,000 30 12 Pipeline Replacement/Abandonment Program, Phase 1 7/27/2017 $48,500,000 20 13 Silver Extension Pipeline 12/29/2021 $42,199,000 27 15 University Mound Reservoir 7/19/2022 $17,178,000 23 16 Sunset Extension Pipeline 2/6/2023 $43,350,000 24 17 Sunset Extension Rezoning Pipeline 8/25/2023 $3,197,000 22 19 Lake Merced Pump Station 3/14/2024 $31,244,000 28 20 Sunset Reservoir Connection and PS 10/2/2024 $16,198,000 25 23 Richmond Extension Pipeline 1/25/2028 $44,074,000 19 24 Alemany Extension Pipeline 8/14/2028 $21,457,000 12 18 Construct 30 New Cisterns 12/7/2026 $51,150,000 21 25 Geneva Extension Pipeline 3/2/2029 $32,190,000 31 21 Pipeline Replacement/Abandonment Program, Phase 2 11/23/2026 $48,500,000 14 22 Construct 25 New Cisterns 10/7/2030 $42,625,000 Project Name CS-199 AWSS Facilities Preliminary Options Study 67 Bond Issue ESER 2010 Bond Future Bonds or Other Sources Task 11 Project Report 5.5 Schedule The sections below describe the development of the capital improvement project schedule for the preferred program. 5.5.1 Schedule Constraints Project delivery constraints include the following: Available capital for construction expenditures Available staff and management time Operational constraints (minimize portions of system out of service) Construction effects minimization Other project effects 5.5.1.1 Capital Funds The AWSS is not supported by utility rates but by general funds through property tax payments. Any future construction is expected to be funded by taxpayer approved bonds. SFPUC and SFDPW are currently administering the 2010 Earthquake Safety and Emergency Response (ESER) Bond. This Bond funds a total of $412.3 million dollars of which $104 million covers various AWSS facilities divided as shown below: $34 million for AWSS core facilities $32 million for pipes $36 million for cisterns $2 million for administration The expectation is that future projects will continue to be funded in this manner. The City manages the total bonded amount and works with the Departments to manage general obligation funding schedules and potential proposals to voters. SFPUC and SFFD will need to continue to project capital needs and provide project information to be included in future bond issues. It is currently envisioned that future bonds elections will be held in 2014 and approximately 2021. These dates have been used as assumptions in the development of the program schedule. 5.5.1.2 Staff and Management Time While the 2010 ESER Bond funds some management and design time, each project also requires review and assistance by staff in SFPUC, SFFD, and SFDPW. Spreading the work out over time allows staff to continue their existing workload and also be available to assist with the capital project development. CS-199 AWSS Facilities Preliminary Options Study 68 Task 11 Project Report 5.5.1.3 Operational Constraints The AWSS provides a vital resource to SFFD in times of emergency. Whether for fighting a greater alarm fire or fighting the catastrophic fires following an earthquake, the timing of the need is unknown. The system must be able to provide at least a minimum level of service at all times. Construction projects must be phased to allow a minimum level of supply and pressure to be maintained for SFFD use at all times. The non-project recommendations include developing a standard protocol for system shutdowns. There should be a minimum amount of system storage in service at all times, as well as a minimum of system pumping capacity available at all times. These standards need to be developed based on reliability information as well as operational strategies. Construction outages for connections to the existing system need to be phased to conform to the standard protocol. Appropriate project phasing provides systematic system upgrades with a logical progression of projects. Hydraulic modeling of the existing system has identified concerns with the amount of storage and supply for the existing system. Adding new sections of pipe serving new potential demands should be concurrent with the supply or storage projects that will feed demands in those areas. 5.5.1.4 Construction Construction in the City may be mitigated in a number of ways. Typical downtown construction hours are limited to avoid peak traffic hours or night work is required. The length of open trench at any time or the number of crews can be limited. Hours can also be limited to mitigate noise to neighbors. Most of these projects will likely require mitigation for construction impacts. Phasing and grouping projects will allow the planned minimization of impacts. Projects also need to be coordinated with other City agencies as well as non-public utilities. SFPUC will coordinate with these agencies during the planning and design process to make sure that paving and utility projects are coordinated. This coordination may require some delays or acceleration in projects when possible to minimize impact or additional costs. 5.5.1.5 Other Project Considerations Project phasing and scheduling can also be affected by other major construction projects. San Francisco has a number of major public infrastructure projects ongoing at any time, in addition to major private projects. Recently, AWSS has been affected by the Transbay Terminal and Central Subway construction projects and Mission Creek development. The Transbay Terminal and Central Subway projects required utility relocation for the major underground structures. Portions of the AWSS south of Market were disconnected during this construction. The Mission Creek Development has connected new pipelines into the system which also required CS-199 AWSS Facilities Preliminary Options Study 69 Task 11 Project Report shutdowns of portions of the system during the construction of the connections. Future projects include Hunters Point, Pier 70, and Candlestick Park developments. 5.5.2 Schedule Figure 5-1 shows the draft schedule for the preferred CIP. This schedule was proposed to SFPUC for review by SFPUC, SFFD, and SFDPW staff. CS-199 AWSS Facilities Preliminary Options Study 70 Task 11 Project Report Figure 5-1. Preferred Alternative Planning Level Schedule CS-199 AWSS Facilities Preliminary Options Study 71 Task 11 Project Report 5.6 Project Considerations Considerations Alternative B Ranking Resource Location Cost (Capital, Annual Operations and Maintenance, and Life Cycle) Program Capital Cost of $391,922,974 (including pipe replacement estimated costs) is the lowest of the three alternative programs Operations and Maintenance 2290 hours estimated to operate and maintain new AWSS facilities Annual Operations and Maintenance Cost for New Assets is $249,136 which is slightly lower than Alternative A’s cost of $254,794. The developed schedules show Alternatives A and B each completed by 2045, and Alternative C completed by 2046. Alternative B citywide reliability score is 92% Schedule Water Supply Delivery Reliability Fire Fighting (Resources and Deployment Time) Insurance Premiums Benefits Environmental/Community Impacts Right of Way/Legal Number of Fire Engines Required is least at 23 mean and 60 maximum Average deployment time is least at 23.6 minutes Alternatives A and B have higher reliability and better firefighting resources requirements, therefore should have better fire insurance benefits. Project environmental review required some projects may require permits for work in SF Bay The intent is that all projects be located in public Right of Way CS-199 AWSS Facilities Preliminary Options Study See Appendix B See Appendix B See Appendix C See Section 4.6 See Task 9 TM See Appendix E See Appendix D Task 11 Project Report 72 6.0 Operational Strategy 6.1 Current Operational Strategy 6.1.1 Normal Operations The AWSS is generally used for day-to-day “greater alarm” incidents and some working fires occurring within the AWSS service area. The AWSS is typically able to serve an area that extends approximately 1,000 feet to either side of the pipelines. However this distance varies due to location of fire, topography of the area, type of fire (high rise vs. low rise), pressure required, pressure within the AWSS pipeline, and whether an engine pumper is used, etc. The SFFD utilizes the AWSS frequently for greater alarm fires for training and experience with the system. 6.1.2 System Roles, Responsibilities, Staffing, and Training The SFFD utilizes the AWSS during firefighting events, as described above. CDD is responsible for the maintenance, repair, and proper operation of the system. During firefighting events, both agencies coordinate to enable the proper operation of the system to respond to the dynamic needs of conflagrations. 6.1.3 CDD Staffing CDD is staffed with 1 Superintendent, 5 General Foremen, and 13 Gatemen. The Gatemen, who are tasked with operating both the MWSS and AWSS valves and reservoirs, are the only personnel authorized to operate MWSS and AWSS valves with the exception of hydrant valves in certain cases described below. The Gate Room is staffed 24 hours a day, 365 days a year and always has at least one person on the weekends, day shift, swing shifts, and graveyard shifts. During normal operating hours there are 10 or 11 Gatemen on duty. The General Foremen as well as the Superintendent are on standby from 4pm to 8am daily as well as 24 hours a day on weekends and can be reached through their respective mobile devices and receive the same updates as the Fire Chief. SFFD procedures prohibit the operation of CDD distribution valves by SFFD staff unless under the direction of CDD personnel or in the case of damaged hydrants. SFFD staff operates MWSS hydrant valves when they are called to an incident involving a broken hydrant to shutoff the hydrant valve, retrieves the hydrant and notifies CDD of the broken hydrant. Proper valve operation protocols must be followed to limit the risk of pipeline, water quality issues, storage, and private property damage caused by transient pressures or “water hammer” CS-199 AWSS Facilities Preliminary Options Study 73 Task 11 Project Report - caused by quick opening and closing of valves. Also, certain valves are left strategically opened and closed, during both normal and emergency scenarios, to allow the proper zoning of system pressures. There is a requirement that an "Ames Valve" is attached to every low pressure hydrant while combating a fire to prohibit possible cross connections. SFPUC’s Water Quality Division ensures that the SFFD is compliant with this regulation and is subject to fines if not compliant. Personnel from CDD respond to second and greater alarm fires. They are available to operate MWSS valves as may be necessary to provide a greater supply from other MWSS pressure zones. As necessary, they also operate AWSS valves to provide adequate pressure and supply from other AWSS zones. CDD staff also operate the pump stations, Twin Peaks Reservoir, and tanks supporting the AWSS performance. CDD emergency crews also isolate flow to broken mains as needed. Personnel from the Water Quality Division respond to second and greater alarms of fire to investigate "cross connections" that are a possible source of potable water contamination. Pump Station 1 and 2, Jones Street Tank, Ashbury Tank and Twin Peaks Reservoir staffing is subject to operational changes. For purposes of checking daily readings and security, the three storage facilities are monitored by the SCADA system and 24-hour video surveillance. CDD staff is deployed to these locations as required to provide regular and emergency operational support, and perform maintenance activities. During second alarm or greater fires, the CDD General Foreman and on duty gateman respond to the fire with an additional gateman called for support during the greater alarm, responding to either Jones Street tank or Ashbury tank or Twin Peaks reservoir. Once the General Foreman reaches the incident, he immediately becomes the SFWD Incident Commander and is responsible for the operation of non-hydrant valving. The SFWD Incident Commander reports to the SFFD Incident Commander. When an earthquake occurs, the following protocols are followed according to CDD staff: High magnitude (CDD staff indicate approximately Magnitude 5.5) earthquake – all Gatemen are required to report and perform pre-assigned roles (AWSS needs to be included in these roles). Higher earthquake (CDD staff indicate approximately Magnitude 6.0) – All supervisors respond to perform pre-assigned tasks in addition to all of the Gatemen mentioned above. Severe earthquake (CDD staff indicate approximately Magnitude 6.5 and greater) – All CDD staff are required to respond. CDD Response is determined by the on-call Supervisor. CS-199 AWSS Facilities Preliminary Options Study 74 Task 11 Project Report The CDD Superintendent, all General Foremen, and all Gateman are notified by the Department of Emergency Management Communications Center for all greater alarm fires. The on-call Supervisor (either a Superintendent or General Foreman) can then deploy Gate room Personnel to either Jones St. Tank or Ashbury Tank depending on the location of the fire. 6.1.4 Normal Valve Settings For the AWSS Post-Earthquake Fire Response simulations using the computer program GIRAFFE, the model was configured to simulate systems operations solely utilizing the Twin Peaks Reservoir pressure gradient. This assumes that following an earthquake SFPUC has operated valves at Jones Street and Ashbury Street tanks to allow the entire system to be operated off of the Twin Peaks pressure gradient to maximize delivery. Division Gates Division gate valves are currently normally closed as shown in Table 6-1. CS-199 AWSS Facilities Preliminary Options Study 75 Task 11 Project Report Table 6-1. Closed Division Gate Valve Locations Closed Division Gate Valve Location Seventeenth St. / Collingwood St. Golden Gate Ave. / Octavia St. Franklin St. / Ellis St. Sutter St. / Polk St. Powell St. / Bush St. California St. / Stockton St. Washington St. / Stockton St. Van Ness Ave. / Bay St. Powell St. / Sacramento St. Scott St. / Green St. Laguna St. / Green St. Lombard St. / Gough St. Franklin St. / Grove St. Church St. / Twenty-sixth St. Irving St. / 15th Ave. Irving St. / 7th Ave. Ocean Ave. / 280 N Ocean Ave. / 280 S Mission St. / Fair Ave. Infirm Area Isolation Valves Nine zones within the city have been identified as infirm in previous studies. These are areas that may be subject to liquefaction and this categorization was developed based on performance during previous earthquakes. This liquefaction may cause damage to the AWSS piping during an earthquake. The current strategy, developed during the 1980s, is to provide automatic isolation of these areas following an earthquake. This is done by providing one normally open motorized valve with a seismic switch that triggers closing following a Mw6.8 earthquake. Other normally closed non-motorized valves and motorized valves provide isolation to each zone. The normally closed motorized valves can be opened following an earthquake if the pressure transducers upstream and downstream of the valve indicate no pressure differential. The current normal infirm area isolation valve status is currently as shown in Table 6-2. CS-199 AWSS Facilities Preliminary Options Study 76 Task 11 Project Report Table 6-2. Seismic Isolation Valve Locations and Status (pre-earthquake) Infirm Area Inflow Valve Seismic Type Switch? MOCGV Yes Location S.E. Brannan Street/2nd Street OCGV No Sacramento/Kearny SynerGEE ID Status 27958 Open 32461 Open Alternate Inflow Valve Type Location N.W. Second MCCGV Street/Mission Street S.E. Market Street/New Montgomery Street MCCGV Kearny Street/Jackson MCCGV Street 1,2 3 4,5 6 MOCGV Yes 10 MCCGV N.E. Harrison Street/20th Street 23120 Closed MCCGV N.W. Evans Avenue/Napoleon Street 21630 Closed MCCGV S.E. Larkin Street/Eddy Street 28514 Closed S.E. Beach Street/Baker Street 34512 Closed 24015 Open No Bayshore Blvd/Cesar Chaves St. Yes N.E. Larkin Street/Market Street MOCGV Yes N.W. Fillmore Street/Cervantes 34401 Open MCCGV MOCGV Yes S.W. Powell Street/Chestnut Street 34518 Open MCCGV Open MCCGV Legend: MOCGV: OCGV: MCCGV: N.W. Leavenworth Street/Bay Street 34758 N.E. Kearny Street/Francisco Street 34806 Motorized Open Control Gate Valve Open Control Gate Valve Motorized Closed Control Gate Valve CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 77 Closed Closed 17th Street/Dolores Street 26834 33216 26140 No MOCGV Closed N.E. 4th Street/Channel Open Open 30352 MCCGV 25596 21768 Closed Closed Yes OCGV 30111 MCCGV Open MOCGV Status S.E. 6th Street/Market Street (bypass) 28130 N.E. Fifth Street/Brannan Street 26497 MCCGV 26411 Yes OCGV 9 Open S.E. 5th Street/Brannan Street S.W. 7th Street/Brannan Street MOCGV 7 8 S.E. 6th Street/Market Street 28124 SynerGEE ID Closed Closed Closed For post-earthquake analyses, infirm area isolation valve status were programmed and simulated based on the premise that the infirm area inflow valves with seismic switches have activated and closed and all motorized closed control gate valves along the perimeter of the infirm areas have been opened (Table 6-3). Recognizing that the decision to operate infirm area motorized close control valves following an earthquake is a manual decision taking into account damage in the infirm area, sensitivity analyses was performed to determine if the closed control valve status affects results. Bypass Gate Valves The existing condition assumes that the bypass gate valves at Ashbury and Jones St. Tanks are closed, keeping the three pressure zones separated. Operation of these gates currently requires dispatching a gateman to the tank to open the gates. The Ashbury tank gate valves have been motorized and have the ability to be controlled remotely, but this is not currently included in the operations due to the risk of tank overflow if the bypass valves are opened before the tank discharge valves are closed. Pump Stations The pump stations are not normally operating; however they could be operated once staff is dispatched to their locations. Reservoir and Tanks The Twin Peaks Reservoir (East and West sides), Ashbury Tank and Jones Street Tank are normally kept full. Jones and Ashbury are automatically filled with potable water using altitude valves and air gaps. Twin Peaks is also filled with potable water but done manually. CS-199 AWSS Facilities Preliminary Options Study 78 Task 11 Project Report Table 6-3. Seismic Isolation Valve Status (post-earthquake) Infirm Area Inflow Valve Seismic Type Switch? MOCGV Yes Location S.E. Brannan Street/2nd Street OCGV No Sacramento/Kearny SynerGEE ID Status 27958 Closed 32461 Open Alternate Inflow Valve Type Location N.W. Second MCCGV Street/Mission Street S.E. Market Street/New Montgomery Street MCCGV 1,2 MCCGV 3 4,5 6 MOCGV Yes 10 Open MCCGV N.E. Harrison Street/20th Street 23120 Open MCCGV N.W. Evans Avenue/Napoleon Street 21630 Open MCCGV S.E. Larkin Street/Eddy Street 28514 Open S.E. Beach Street/Baker Street 34512 Open No No Bayshore Blvd/Cesar Chaves St. Yes N.E. Larkin Street/Market Street MOCGV Yes N.W. Fillmore Street/Cervantes 34401 Closed MCCGV MOCGV Yes S.W. Powell Street/Chestnut Street 34518 Closed MCCGV OCGV MOCGV 24015 Open 21768 26834 Open Closed MCCGV Legend: MOCGV: OCGV: MCCGV: Open 26140 17th Street/Dolores Street Closed Open MCCGV Yes 25596 30352 Kearny Street/Jackson Street 33216 N.E. 4th Street/Channel MOCGV Closed Open MCCGV Yes 26411 30111 S.E. 6th Street/Market Street (bypass) 28130 N.E. Fifth Street/Brannan Street 26497 MCCGV MOCGV OCGV 9 Closed S.E. 5th Street/Brannan Street S.W. 7th Street/Brannan Street 7 8 S.E. 6th Street/Market Street 28124 N.W. Leavenworth Street/Bay Street 34758 N.E. Kearny Street/Francisco Street 34806 Motorized Open Control Gate Valve Open Control Gate Valve Motorized Closed Control Gate Valve CS-199 AWSS Facilities Preliminary Options Study 79 SynerGE E ID Status Task 11 Project Report Open Open Open Open 6.2 Operational Changes Considered Investigation of the existing operating conditions for modeling identified issues that were addressed during the modeling and project development and included issues related to the seismic switches, tanks bypass gates, and division gates. The operational changes considered included: Adding three new seismic switches to existing valves to be able to isolate three infirm zones not yet isolated. Operation as one pressure zone versus three pressure zones by either: o Automating and opening all division gates, or o Automating and opening bypass valves at Jones Street and Ashbury Tanks Isolating the AWSS along Market St. into a “North” and “South” zone Shifting the boundaries of the AWSS pressure zones Adding SCADA, new equipment and remote controls to allow remote startup and operation of Pump Stations 1 and 2 Adding SCADA, new equipment and remote controls to allow remote bypass of Jones Street and Ashbury Tanks 6.3 Evaluation of Operational Changes Hydraulic and reliability modeling tools were used to evaluate the effect of potential operational changes on system performance. Table 6-4 shows the relative scores for the operational changes using the SynerGEE hydraulic model, which were evaluated based on the existing system and its ability to meet the demands at the 3rd quintile (refer to Task 8 TM for description of the demand set and model). The evaluation criteria (i.e., percent of nodes met) are the nodes whose demands are met at a 20 psi minimum delivery pressure. CS-199 AWSS Facilities Preliminary Options Study 80 Task 11 Project Report Table 6-4. Hydraulic Analysis of Operational Changes (No pipe breaks or leaks) Case Base All Infirm Zones Isolated One pressure zone: Bypass valves Percent of Nodes Meeting 20 psi delivery minimum Description 57 57 Existing condition Adding three new seismic switches to isolate three infirm zones not yet isolated Operation as one pressure zone versus three pressure zones by automating and opening bypass valves at Jones Street and Ashbury Tanks Operation as one pressure zone versus three pressure zones by automating and opening all division gates Isolating the AWSS along Market St. into a “North” and “South” zone Shifting the boundaries of the AWSS pressure zones 63 One pressure zone: Division Gates 57 North/South Division 54 Rezoning 57 As can be seen in Table 6-4, the only operational change that shows a purely hydraulic benefit is automating and opening the bypass valves at Jones and Ashbury tanks, which allow the head at Twin Peaks to govern the system. Changing the system into north and south zones did not benefit the system. In this evaluation, the rezoning done involved relocating one of the division gate valves along Irving St. such that the pipe along Parnassus Ave. would be included in the Twin Peaks zone. This was done because of the relatively high elevations at that location. However, as the system exists now, there is no hydraulic benefit to this change. Another change that does not show any hydraulic benefit but is crucial to the reliability of the system is the complete isolation of all the infirm zones. Due to the pipe damage expected in the infirm zones, isolating them would minimize the draining of the system. The reliability scores were not calculated for this analysis; connectivity (the number of nodes where the demand was met) was used as a proxy for reliability. Table 6-5 shows an increase in the connectivity of the system when the infirm zones are completely isolated when considering breaks and leaks, which are modeled in the GIRAFFE program (refer to Task 8 TM for a description of this modeling). CS-199 AWSS Facilities Preliminary Options Study 81 Task 11 Project Report Table 6-5. GIRAFFE Comparison of Infirm Zone Isolation Case Connectivity (%) Infirm zones as is (3 not isolated) 33 Infirm zones all isolated 35 Infirm zones all open 24 Note: These values are a result of an evaluation on the existing system where the infirm zone repair rate was set to 3 repairs/km of pipe 6.4 PWSS Assumptions SFFD currently has 4 PWSS units, with one of the four dedicated to Treasure Island. While these units are not classified as capital improvements, they are important to the analysis and fire department response and flexibility. Assumptions made in the modeling analysis generally assumed that the circle of influence of a cistern or suction connection was limited to the length of fire hose available on one fire engine, meaning that PWSS was not used for these locations. The fire demands were connected to the high pressure water system using the closest possible existing high pressure hydrant. Following modeling an assessment was performed to determine the number of times this hydrant location was in excess of 707 feet from the projected demand location, whereby the 707 feet represents the Manhattan distance from a hydrant. The Manhattan distance reflects the fact that the 1000 feet of hose from a fire engine normally cannot cross through blocks and must be routed in the streets, around corners. If the approximate distance from the source to the location of demand assuming rectangular blocks exceeds 707 feet it is assumed that one fire engine’s hose would not be sufficient. This would indicate the use of PWSS or relay engines. This assessment is discussed in Section 2.10.5 and with the results summarized below. To determine the need for the PWSS in firefighting after a Mw7.8 earthquake on the San Andreas fault, a preliminary analysis was done on the preferred alternative (Alternative B) using the full stochastic set of fire ignitions. First, GIS analysis of the existing and proposed AWSS pipe was performed to determine the city blocks that fell beyond 707 feet but within 3,734 feet of the pipes, which are the Manhattan distances of 1000 feet and 1 mile. The Manhattan distance generally takes into account the need for the hose to transverse city blocks such that the effective distance is less by a factor of the square root of 2. An example using the Alternative B HPS is shown in Figure 6-1. CS-199 AWSS Facilities Preliminary Options Study 82 Task 11 Project Report Figure 6-1. Recommended AWSS Pipe With Buffers CS-199 AWSS Facilities Preliminary Options Study 83 Task 11 Project Report Table 6-6. Summary of PWSS Needs Average Number of Ignitions outside Pipe system 21 Average Number of PWSS Needed– Alternatives A and B 5 Minimum Number of PWSS Needed – Alternatives A and B 0 Maximum Number of PWSS Needed – Alternatives A and B 14 Average Number of PWSS Needed – Alternative C 4 Minimum Number of PWSS Needed – Alternative C 0 Maximum Number of PWSS Needed– Alternative C 14 Figure 6-2. Distribution of PWSS Needed (Alternatives A and B) Frequency out (number out of 1000) Number of PWSS Needed - Alternatives A and B 350 300 250 200 150 100 50 0 1 3 5 7 9 11 13 15 No. of PWSS Hose Tenders CS-199 AWSS Facilities Preliminary Options Study 84 Task 11 Project Report Figure 6-3. Distribution of PWSS Needed (Alt. C) Number of PWSS Needed - Alternative C Frequency (number out of 1000) 350 300 250 200 150 100 50 0 1 3 5 7 9 11 13 15 No. of PWSS Hose Tenders Table 6-6 summarizes the number of PWSS hose tenders needed in Alternatives A and B, where significant new HPS is proposed, and Alternative C, where no new HPS is proposed. Figure 6-2 and Figure 6-3 show the distribution of PWSS needed over the 1000 ignition simulations. It should be noted that this exercise did not consider the inaccessibility of the infirm zone pipe and the possibility that additional PWSS would be needed to reach inside the infirm zones. In addition, the number of PWSS hose tenders required to effectively fight a fire may be more than one. In the case of the 1989 Marina fire, 3 PWSS hose tenders were used to effectively extinguish the fire. Therefore, if using this as an approximation of PWSS use for a single large fire, the average number of PWSS hose tenders needed for both alternatives B and C would be 15 and 12, respectively. Furthermore, PWSS could be used to extend to larger distances for cisterns and to be filled from the fireboats. This analysis assumed more PWSS units than are currently available. Additional PWSS units would be a prudent investment for SFFD/SFPUC. CS-199 AWSS Facilities Preliminary Options Study 85 Task 11 Project Report 6.5 Recommended Operational Strategy Based on modeling, it is recommended that SFPUC: 1. Isolate the remaining three infirm zones as soon as possible. 2. Automate the bypass gates at the Jones Street and Ashbury tanks to allow remote operation. Other recommendations include the need to remotely startup and control the pumps at Pump Stations 1 and 2. The system as modeled using the 60 minute demands uses the full existing capacity of the pump stations. Existing practice is to respond the appropriate staff to the stations to operate them. Emergency response plans need to be developed that will prioritize the staff response to all of the CDD operated facilities. Modifying the stations to allow remote startup and control, similar to other CDD facilities, will reduce the potential wait for additional reliable water supply. Rezoning is only recommended as the expansion to the western part of the city occurs. It is recommended that the outer Sunset and Richmond extensions be operated at the “upper zone” and isolated from the higher “Twin Peaks Zone”. This will require some pipeline valve changes and short sections of new piping. In general, the zones remain the same. CS-199 AWSS Facilities Preliminary Options Study 86 Task 11 Project Report 7.0 Non-Construction Recommendations This planning study identified certain deficiencies (listed in Task 2 TM) that are not addressed in any projects included in the programs. These are not capital projects but instead relate to emergency preparedness, training, and maintenance. Table 7-1 below lists the recommendations with priorities and implementation recommendations. CS-199 AWSS Facilities Preliminary Options Study 87 Task 11 Project Report Table 7-1. Non-Construction Recommendations AWSS Emergency pipeline repair, readiness and response program Maintenance Priority Ease of Implementation Ongoing implementation Cost Cost Confirm that all AWSS assets are entered into CDD's asset management system and PM's are established high easy medium low Perform Regular maintenance and testing high medium medium medium Check, flush and repair all suction connections regularly low medium medium low M4 Establish pipeline flushing program for AWSS low easy low low M5 Establish leak detection program and a pipeline leak database to monitor potential hot spots medium easy low low low easy low med M1 M2 M3 Establish a cistern inspection, filling and testing program M6 Operational Readiness O1 Establish regular coordination meetings with SFFD high easy none low O2 Train SFPUC personnel on system (communications, operational strategies, emergency response requirements high easy low low O3 Develop a system outage policy and procedures for planned outages high easy low low O4 Prepare an emergency response program and conduct training exercise high medium medium low CS-199 AWSS Facilities Preliminary Options Study 88 Task 11 Project Report CIP Planning P1 P2 P3 Establish testing program for AWSS pipelines high medium medium low Establish program to replace hydrant laterals high medium medium high Establish regular pipeline replacement program med medium medium high Establish program to locate and mitigate AWSS crossings of pile supported utilities and other utility interferences high medium medium medium P4 CS-199 AWSS Facilities Preliminary Options Study 89 Task 11 Project Report 8.0 Additional Assessment of Risk and Use of Potable or Co-Benefit System Evaluation of the Preferred Alternative and the relative program costs and time frame led to discussions about the sensitivity of the analysis to total seismic risk and the availability of potable water to meet the fire demands. In addition, suggestions were made relative to sharing costs with planned potable system reliability improvements to reduce construction costs. In, Task 9.1, the AECOM/AGS JV performed additional hydraulic, reliability and risk assessments in support of the questions raised following the recommendation of the preferred alternative. Task 9.1 included a number of assessments which are documented in the Task 9.1 Technical Memorandum and summarized in this section of the project report. The additional analyses performed in Task 9.1 included reviewing the recommended program regarding the sensitivity of the reliability scores to: 1. The annual risk of all foreseeable potential earthquake events 2. The availability and use of potable water from the potable water system 3. The potential benefit of construction of a potable co-benefit system which provides daily benefit to the potable water system but will also function as a high pressure fire system when necessary 4. Abandonment of existing AWSS pipe in the infirm and non-infirm zones In addition, O&M costs for the existing AWSS were calculated using the same assumptions as defined in the Task 9 TM. Pipe replacement at various rates programs was also assessed. Results indicate that: 1. The effective reliability of the Existing, 2010 Bond and Preferred Alternatives increase when incorporating the annual probability of different earthquake magnitudes in the city. Table 8-1 summarizes the reliability scores based on the risk of all earthquake events on the San Andreas Fault. Table 8-1. Comparing Reliability with Mw7.8 Event vs. All Events Mw 7.8 Effective (All San Andreas events) Existing 2010 Bond Preferred Alternative 47 68 92 69 83 99 CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 90 2. The reliability scores are sensitive to the availability of water from the potable water system. Data post-processing assumed additions of potable water supply to the 2010 bond scores shows that as more potable water is available the reliability scores increase. This is shown in Figure 8-1. For the purposes of this study, the contribution from the potable system was assumed to be citywide and distributed equally among the FRAs. The reliability of the potable system to provide the water, and the cost of any improvements to the potable system to increase that reliability was not determined in these analyses. Experience from the 1989 Loma Prieta Earthquake indicates that the potable system had significant numbers of service connection failures in areas of high ground motion/deformation. Reliability Score, % Figure 8-1. Reliability Scores with Potable Water Contribution 100 90 80 70 60 50 40 30 20 10 0 Alternative B (no potable) 2010 (potable 50,000 gpm) 2010 (potable 40,000 gpm) 2010 (potable 30,000 gpm) 2010 (potable 20,000 gpm) 2010 (potable 10,000 gpm) 2010 Bond (no potable) Existing (no potable) 1 2 3 4 Quintile Demand 5 3. With contributions from the potable system, projects can be removed from the Preferred Alternative. At a reasonable level of potable water contribution (20,000 gpm citywide) one of the recommended AWSS supply projects (Lake Merced, Sunset or University Mound) can be removed. Removal of a second supply project would cause significant impact to individual FRA reliability and is not recommended. 4. A potable co-benefits system was developed and analyzed that would serve the dual purpose of potable water distribution during normal operation and high pressure flows for firefighting after a major seismic event. This system would be separate from the AWSS. Such a system would be constructed in lieu of expanding the AWSS to areas currently not served by the AWSS. The full system would include some improvements CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 91 to the AWSS (common projects), two separate potable co-benefit pipe replacement programs connected to Sunset Reservoir (Sunset Main Replacement and Richmond Main Replacement), and new cisterns that are also common to the three Program Alternatives. Hydrants will also be installed on the existing WSIP-strengthened transmission mains that feed the 5 major terminal reservoirs. The citywide reliability index score from the Potable Co-Benefits System exceeds that of the Preferred Alternative (94% for the Potable Co-Benefits vs. 92% for the Preferred Alternative). An opinion of probable costs for the Potable Co-Benefits System was also developed. CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 92 Figure 8-2. Potable Co-Benefits System CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 93 5. The calculated annual cost of O&M for the existing AWSS is $1.69 million. This is compared to maintenance costs alone for the several years where such costs are available. 6. The sensitivity of fire demands located within or outside infirm zones was tested, along with the impact of abandoning all infirm zone pipe. These analyses showed that there is not a significant difference in citywide reliability index scores. a. Abandonment of the infirm zone piping does not have a large effect for this analysis because most of the infirm zones are assumed to be hydraulically isolated following a major seismic event using seismically controlled motorized valves. b. The sensitivity analysis of fire demand placement was only applicable to those FRAs whose demands could have been placed within an infirm zone. These were largely in FRAs on the east side of the city with demands of smaller magnitudes. Although the individual FRA may have been impacted by the placement of the demand node, the overall Citywide average is not significantly affected. c. An analysis of three areas outside the infirm zone was performed. It was determined that some amount of pipe (26-39%) could be removed in FRAs that are heavily gridded and whose pipe belong primarily to one pressure zone without major detriment to the reliability index score. Pipe abandonment is FRA specific and needs to be analyzed for SFFD operational needs and preferences. 7. Options for pipe replacement programs at various rates were reviewed. A pipe condition assessment and testing program will inform SFPUC as to the relative needs for pipe replacement. Until this data is available, a replacement rate of 0.5 miles per year has been selected for budgeting purposes. The following are recommendations based on the results of the additional analyses: The projects recommended for funding using the ESER 2010 Bond funds should continue into planning, design and construction. Projects which strengthen the existing AWSS should proceed with planning and potential funding. SFPUC should engage in a similar planning effort to assess the reliability of the existing potable water distribution downstream of the Water System Improvement Program (WSIP) hardened facilities and recommend potential areas of improvement. Once the potable system is assessed, SFPUC can determine the most appropriate methodology to achieve the LOS goals throughout the City. CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 94 9.0 AWSS Program Justification Previous work gives us some potential ways to justify AWSS program investments. Looking at predicted loss due to fire following earthquake, Table 9-1 summarizes previous studies loss calculations. Table 9-1. Predicted Loss from Fire Following Earthquake Study Author Year Estimated $ loss Billion % of Total Building Value Scawthorn 1987 $21.5 8.6 Scawthorn 1992 $10 4 Grossi and MuirWood 2006 $3 Not stated Scawthorn 2010 (CAPSS) $7.6 3.7 Scawthorn 2012 (White Paper) $7.55 3.7 The 2012 white paper (Scawthorn) documented the predicted loss with and without the AWSS HPS. The values for loss and the corresponding reliability values calculated for the existing AWSS with and without the HPS are shown in Figure 9-1. CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 95 Figure 9-1. Loss vs. Reliability Correlation 100 94% with Recommended Projects 90 Percent Citywide Reliability 80 68% with ESER 2010 Projects 70 60 50 47% With AWSS 40 30 30% Without High Pressure System 20 10 0 4 5 6 7 8 Fire Following Earthquake Loss in Billion Dollars 9 10 Discussions with Dr. Scawthorn indicate that use of a power relationship would be the most appropriate trendline to connect the two calculated points and predict other points. As shown in Figure 9-1, raising the citywide reliability from 47% to 94% could reduce the potential property loss by $2 billion dollars. The indirect costs such as business interruption, loss of travel and tourism, costs to relocate following a catastrophe can be twice or more the direct costs such as loss due to fire following earthquake. Data from previous disasters are shown in Table 9-2. CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 96 Table 9-2. Property Loss vs. Business Interruption Costs Disaster Property Damage ($ billions) Business Interruption Costs ($ billions) Hurricane Katrina $100 > $100 September 11th WTC Attack $25 $40 to 100 Hypothetical 8.2 EQ on $100 $67 Southern San Andreas Source: Improving Catastrophe Modeling for Business Interruption Insurance Needs, Rose and Huyck (2012) Another justification of the maintenance and expansion of the AWSS include the potential reduction of insurance premiums in San Francisco due to the AWSS. Work by Dr. Scawthorn has indicated that insurance rates are 6 to 8% lower with the AWSS than without. This benefit has been estimated to be approximately $32 to 45 million per year. Dr. Scawthorn has estimated the net present value of the insurance savings due to the high pressure system to be $1 to 1.5 billion dollars. The Task 10 TM on Insurance estimates that the improvements recommended in the preferred program would increase the reduction in insurance premiums to approximately 13.3%. Table 9-3 shows estimated annual benefits and costs for the recommended system per $100,000 assessed value. Realizing the insurance premium savings would require an investment by the City in addressing the insurance industry and regulators to document the benefits and changes to the AWSS. Table 9-3. Benefits and Costs of Improved AWSS Benefits Costs 1. Annualized Values Annual per $100,000 Assessed Value Insurance Premium Savings 1 Reduction in Property loss Reduction in Indirect Loss $20.31 to $28.56 Property Tax from Bonds $6.35 $6.35 Total: $33.01 to $41.26 $33.90 Insurance Premium Savings would only be received by the insuree and only through efforts at lobbying and regulatory interaction. Investment in the AWSS to increase reliability and robustness is justified by the reduction in risk, direct and indirect losses, and savings in fire insurance premium costs as described above. CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 97 10.0 Supplemental Condition Assessments As part of Task 13, two additional assessments were made on pipe material testing and alternative Pump Station 2 locations. These assessments are described in the sections below. 10.1 Task 13.2 Materials Testing Concerns have been raised by SFPUC and TAP members about the strength and brittleness of the cast iron pipe especially following the damage caused by the Loma Prieta earthquake in 1989. Task 13.2 was developed as an optional condition assessment task to examine available pipe samples to inform further pipe analysis and recommendations. The full description of the task is available in the Task 13.2 TM. The existing AWSS pipe samples tested provide a limited data set. Four different standard tests were performed on eight existing available samples from AWSS pipe removed from the system. Because they were available samples, there was no way to choose representative ages, areas, or pipe sizes or to gather a larger number of samples to increase the level of comfort statistically. The four tests included thickness measurement, graphite distribution rating, tensile strength and the Charpy impact test. Additional samples were obtained from a current construction site and unnotched Charpy tests were performed. The thickness measurement results show values which are less than and greater than the stated standard thickness and show relatively low coefficient of variation in terms of consistent thickness around the pipe perimeter. Comparing with the design calculations most probably used at the time of design indicates that the pipe thickness was designed for the higher pressures of the AWSS. The graphite form, type, and size indicate typical cast iron of a variety of manufacturing processes. With the limited samples there did not appear to be any correlation between age and material characteristics. Two samples were of Flake type A which is the “strongest” distribution. All of the samples had relatively large (size 2 or 3) graphite size distributions. “The flakes of graphite have good damping characteristics and good machinability (because the graphite acts as a chip-breaker and lubricates the cutting tools. In applications involving wear, the graphite is beneficial because it helps retain lubricants. However, the flakes of graphite also are stress concentrators, leading to poor toughness. The recommended applied tensile stress is therefore only a quarter of its actual ultimate tensile strength.” (Miguel Angel Yescas-Gonzalez and H. K. D. H. Bhadeshia) CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 98 The existing AWSS pipe was tested and shows strength comparable to historically reported data for cast iron pipe. Table 10-1 shows a summary of the testing results. There was no lateral expansion, no unbroken specimens and the fracture surfaces were examined and appear to be 0% shear (ductile) or 100% brittle fractures. Figure 10-1 shows some of the fracture faces. Figure 10-1. Photograph of Unnotched Broken Samples Table 10-1. Cast Iron Material Testing Results Test Tensile Strength Sample Result 18.4 ksi Charpy Notched ½ ft-lb, all temperatures 3 ft-lb, at 70 degrees F Unnotched CS-199 AWSS Facilities Preliminary Options Study Comparison DI pipe is 60 ksi minimum DI pipe is 7 ft-lb at 70 degrees F Task 11 Project Report 99 The test results indicate that: The pipe was originally cast with thicknesses greater than required Has internal pressure capacity sufficient for design conditions based on the likely original design equations The pipe microstructure is varied The tensile strength is comparable to other pit cast iron samples The pipe breaks at low impact energy with brittle fractures These tests indicate that the cast iron pipe is of relatively low tensile strength and is brittle as would be expected of pipe of this type. Pipe testing for leakage and corrosion to identify priority areas for pipeline replacement/abandonment programs is recommended. Addressing the potential weakness of the pipe system will increase the likelihood of the AWSS to meet likely demands following a major earthquake. 10.2 Task 13.4 Pump Station 2 Alternatives The purpose of Task 13.4 was to provide additional information for the analysis of potential Pump Station 2 renovation options, specifically, alternatives that might be cost effective compared to renovation of the existing Pump Station 2. A full description of this task is available in the Task 13.4 TM. This task assessed potential sites in the north (in the proximity of the existing Pump Station 2) and in the south (on Islais Creek and in the Hunter’s Point area) for replacement of the existing Pump Station 2 with the following: Hydraulic and reliability benefit to the existing and future AWSS Opinion of probable costs Environmental and permitting issues Schedule The proposed north site is adjacent to the existing Pump Station 2. Four proposed south sites underwent a geotechnical review and with input from SFPUC, two preferred south sites were selected for the assessment. General results from this study are as follows: In both the 2010 Bond and Preferred Alternative system configurations, a pump station at south site #B results in a lower reliability index score. Our opinion of probable construction costs for a new pump with the same capacity as the existing Pump Station 2 at the north and the two potential south sites are $ 13.8, $35.9, and $32.4 million, respectively. In all instances, the construction cost of a new CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 100 pump station at either south site would be higher than a new pump station at the north site. The construction cost at south site B is slightly lower than that at the south site A. The construction cost at south site B is slightly lower than that at the south site A. Doubling the size of the pump station and removing a supply project from the preferred alternative can reduce the project cost opinion to as little as $9.6 million but with a reliability reduction from 92 to 77. The three pump station alternatives at the north site provide the lowest cost per increase in reliability index score. Construction of a new pump station involves multiple permitting and environmental issues that may adversely affect the construction schedule. The total estimated time to construct a new pump station is six and a half years, but with the following uncertainties and constraints: o CEQA and/or NEPA review o Permitting o Site negotiation and acquisition CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 101 11.0 Conclusions and Recommendations Through the development of LOS criteria and goals, modeling of the AWSS, and alternatives analysis, a recommended program has been selected and recommended to the SFPUC. Following are the recommended citywide and sub-citywide area levels of service objectives based on input from SFPUC and others: “AWSS will reliably provide water to supply the “probable fire demands” after a magnitude 7.8 San Andreas earthquake” • Each area will have a minimum of 50% reliable water supply to meet probable fire demands • The Citywide average will be a minimum of 90% reliable water supply to meet probable fire demands This study divided the City into areas based on those defined by the San Francisco Fire Department (SFFD) for initial alarm response and were called Fire Response Areas (FRAs). Probable fire demands were developed for each FRA using 1000 sets of fire demands generated by Charles Scawthorn, PhD using a Monte Carlo analysis of fire ignitions and fire growth using the ground motions from the design earthquake. The fire ignitions were generated using methods similar to those used for the Community Action Plan for Seismic Safety (CAPSS) study (ATC 2010). These water demands were aggregated into the “likely fire demands” for each FRA. These demands were then used in the reliability modeling tool GIRAFFE, developed at Cornell University by Professor Thomas D. O’Rourke and his students for studies of Los Angeles’ water supply system reliability (O’Rourke 2010). GIRAFFE performs internal Monte Carlo analysis to damage pipes in the system for multiple scenarios. GIRAFFE uses the open source EPANET (EPANET 2008) model as the hydraulic engine and is capable of performing both deterministic and Monte Carlo simulations of pipe damage. The complete GIRAFFE model consists of five modules: system definition, seismic damage, earthquake demand simulation, hydraulic network analysis, and results compilation. Currently, nine of the FRAs have no AWSS high pressure system. These FRAs are served by the City’s regular water supply system hydrants, cisterns and alternative water sources. Because this was an analysis of the AWSS, it was assumed that there was no contribution from the regular water system anywhere in the City. Options which include contributions of the regular water system are described later. CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 102 The Citywide average score for the existing AWSS is 47% with seven FRAs scoring less than 10%. The study included other tasks to assess the condition and needs of the AWSS and identified deficiencies in the existing system. The tasks included: • • • • • Testing existing cast iron pipeline material Assessing the controls systems Recommending pipeline assessment and testing methods Evaluating the impact of the AWSS on insurance costs in San Francisco Assessing the intake tunnels for the two salt water pump stations The needs assessment identified 47 projects which appeared feasible, provided significant benefit to the AWSS, and addressed the deficiencies identified in the condition assessment and hydraulic modeling These projects include repairs to the intake tunnel to Pump Station 1. The tunnel to Pump Station 2 was evaluated and found to be in good condition. The evaluation of the controls systems recommended upgrading the systems to be compatible with SFPUC’s other water operations controls. Providing motorized valves at the tanks to allow remote connection of all pipeline zones was also recommended. Pipeline testing and assessment is recommended and planned using a portion of the ESER 2010 bond. Pipeline replacement rates should be determined as the results of testing activities are received and interpreted. From the list of projects developed during the needs identification phase, three alternatives were developed that achieve the LOS objectives with different strategies. To meet each FRA demand with 50% reliability, either new pipe (and supply) or new cisterns were required. Various alternatives were considered including extension of the AWSS. Because SFPUC is committed to improving the regular water supply system reliability as well; options which included the use of a strengthened potable water system were developed. Common to these alternatives are a set of future projects that will enhance the current AWSS reliability. Details of the various alternatives are described in this report and associated Technical Memoranda. Ultimately a Potable Co-Benefit system that could serve as a regular main, post-earthquake fire supply and post-earthquake emergency water supply was developed. This would leverage existing potable water infrastructure as well as the planned potable water main replacements. The potable co-benefits system would construct new pipelines which would normally serve as regular system feeder mains, but be capable of being isolated from the regular system to serve as a backbone supply for higher pressure fire supply and emergency supply lines following an earthquake. In addition, hydrants can be added to WSIP hardened transmission mains to operate at their standard operating pressure. Projects have been recommended for planning, design and construction using the available ESER 2010 Bond funds. Additional projects to strengthen the existing AWSS should proceed CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 103 with planning and potential funding. Table 11-1 shows the recommended future projects. Additional study should be performed to determine the reliability of the potable water system, assess potential improvements and coordinate those improvements with AWSS or potable cobenefit solutions to provide water supply to fight fires following a major earthquake event. Table 11-1. Recommended Projects Post 2010 Bond Facilities AWSS Pipe Connections and Water Supply Cisterns Potable Cobenefits Net Present Value Reliability Upgrades University Mound Pipeline and Pump Station Silver Extension Pipeline Twin Peaks Pipeline Reliability Upgrades at Facilities 27 New Sunset Main Replacement Richmond Main Replacement Hydrants Installed on WSIP-strengthened pipes Total Cost $114 million $23 million* $137 million Notes: *- Assumes 75% water revenues/bonds and 25% general obligation bond cost share (associated water revenues/bonds cost = $69 million) CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 104 References 1. Applied Technology Council (2005). “San Francisco’s Earthquake Risk Report on Potential Earthquake Impacts in San Francisco”, Obtained from website: http://www.pbs.org/newshour/indepth_coverage/science/1906quake/atc-report.pdf 2. CDD interview, SFPUC/CDD: Katie Miller, Bill Gunn, AECOM/AGS: Anne Symonds, Jason Chen, Aaron Lee, Courtney Hicks, Ahmed Nisar, Alok Jha 3. Connick, HDH and Ransom, TW (1908). “Report on an Auxiliary Water Supply System for Fire Protection”. 4. Jeon, S. (2002). “Earthquake Performance of Pipelines and Residential Buildings and Rehabilitation with Cast-in-Place Pipe Lining Systems.” Ph.D Dissertation, Cornell University. 5. Markov, I., Grigoriu, M., O’Rourke T. (1994). “An Evaluation of Seismic Serviceability of Water Supply Networks with Application to the San Francisco Auxiliary Water Supply System”, Technical Report NCEER-94-0001. 6. Manson, M (1908). “Reports on an Auxiliary Water Supply System for San Francisco”. 7. Metcalf & Eddy (2009). “Auxiliary Water Supply System (AWSS) Study”. City Planning Committee, City and County of San Francisco. 8. National Fire Protection Agency (2007).”25 Largest Fire Losses in U.S. History (in 2006 dollars)”. http://www.nfpa.org/itemDetail.asp?categoryID=954&itemID=23352&URL=Research%20 &%20Reports/Fire%20statistics/Deadliest/large-loss%20fires 9. Rose, A. and Huyck, C. (2012). “Improving Catastrophe Modeling for Business Interruption Insurance Needs”. CREATE Homeland Security Center, University of Southern California. 10. Scawthorn, C., O’Rourke, T.D., Blackburn, F.T. (2006). “The 1906 San Francisco Earthquake and Fire – Enduring Lessons for Fire Protection and Water Supply”, Earthquake Spectra, Volume 22, No. S2, pages S135 – S158. 11. Scawthorn, C. (2012). “Reliablity Methods: A Report Prepared for the San Francisco Public Utilities Commission.” 12. Miguel Angel Yescas-Gonzalez and H. K. D. H. Bhadeshia, Phase Transformations & Complex Properties Research Group, University of Cambridge. CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report 105 Appendix A: Project Data Sheets CS-199 AWSS Facilities Preliminary Options Study Task 11 Project Report Appendix A Project Data Sheets AWSS Project ID Project Name 1 Motorization and Addition of Seismic Switches on Gate Valves Deficiency ID Need D49 Three pipelines crossing into infirm zones are currently not seismically isolated immediately after an earthquake by seismic motion-activated control valves. Pipelines located within and at the interface of the infirm zones are expected to experience breaks/failures during future earthquakes. Automated and immediate valve isolation of the infirm zones following an earthquake would allow the SFPUC to examine these areas for leaks/breaks before restoring service to them. Project Objective/Benefit The infirm zones are already for the most part isolated from the rest of the system by motorized valves. This project would add motorization to the 3 gate valves that are not yet motorized, allowing automatic isolation of pipelines located in the infirm zones in the immediate aftermath of an earthquake. This would preserve firefighting water storage in the aftermath of an earthquake by isolating pipelines located in the infirm zones for which water loss would be expected as a result of leaks or breaks. Assumptions and Unknowns There are currently 7 existing seismic gate valves in the AWSS which were designed to close automatically following a seismic event. This project assumes the 7 existing valves would operate as intended, working with the 3 new valves to automally isolate the infirm zones following a seismic event. There are existing manually operated gate valves which would need to be retrofitted with a Description, Design/Sizing Criteria motorized operator, battery vault, and instrumentation. Alternately a new valves could be located along the pipeline just outside of the infirm zone. - 1x 16" - 1x 14" - 1x 12" At each location, add additional below grade vault, sidewalk pedestal, Monopole w/ antenna. Assume 5' deep vault. Alternately could move actuator, batteries, etc. above grade to minimize soil disturbance when the site conditions allow. Utililze existing standard design. Trickle charged batteries. 800 mhz radio with VSAT backup. Sites are: Kearny & Sacramento, 17th and Dolores, Ceasar Chavez and Vermont Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $174,625 $908,050 $1,082,675 $8,945 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 3 3 1 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 1 Motorization and Addition of Seismic Switches on Gate Valves Assumptions 40'x40' square, each vault. 20' deep. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.1 4,800 4,622 0 0.1 CCSF - DPW (Street) Streets subjected to significant duration closures Street intersections at Kearny & Sacramento 17th and Dolores Ceasar Chavez and Vermont Land Use Types Permitting Geotechnical Environmental Street Community Construction in two street intersections to install new below ground vaults at Kearny & Sacramento and17th just East of Dolores. 3rd Vault installed along Vermont to the South of Ceasar Chavez may be in Street or in dirt area to side of road. Possible conflict with nearby archaeological site at Vermont St. Could be avoided by placing vault above ground. 2 of 62 INDIAN A ILLINOIS TENNESSEE MICHIGAN MARYL AND O 80 N IOWA I-2 N TEXAS D FF I-280 SOUTHBOUND OI S SO MISSOURI WISCONSIN RO TRE PO SAN BRUNO RHODE ISLAND ARKANSAS KAN SAS OR TH B OU N NC FRA I-2 80 TEXAS SAN BRUNO DE HARO CONNECTICUT UTAH YORK BARTLETT LILAC VIRGIL LUCKY FLORIDA TREAT ALABAMA HAMPSH IRE BRYAN T TREAT SHOTWELL CAPP LEXINGTON ALABAMA HOFF OAKWOOD CHURCH AMES FAIR OAKS DOLORES CHATTANOOGA I-2 8 0N A RY 03RD TH 06 S EN W O VERMONT I-280 N OFF H I-280 S ON TH T 07 TE KA RE DO CAROLINA TE R 05 TH H H H JULIAN ABBEY ALBION LANDERS RAMONA 2 POND NOE ISLAIS ADAM 06 N TO T 09 H T 11 T 10 TH VAL ENCIA TRE A T H C T NG LA E T 08 C RA G 12 M A D N 02 T RI E RI R HA SS A LI O M JU IE IN N AT O GUY I-8 0 EA S TB O FR H TH 05 TH SK LA FRANKL PEARL NAN BUCHA AM ED 04 18TH SHARON SAN CHEZ SAN JOSE UN D Ba y Br idg e DRUMM DAVI S FRONT Y BATTER E SANSOM OMERY MONTG KEARNY GRANT ON STOCKT L POWEL STONE T 04 OF F T AR 80 W N E IAR P E AI A L M EU S BE T T ST N 01S O EM Exist Valves MASON TAYLOR JONES WOR LEAVEN LARKIN POLK HYDE GOUGH LAGUNA R STEIN E P NA AB MIR MARIN MARIN MARIN ( ! TUL ARE N EO OL MULLEN PRECITA 4,000 EL Feet SAN CHEZ 27TH 1,000 RE WETMO OCTAVIA E CLIPPER ± 0 INCA R WEBSTE FILLMOR 25TH JERSEY DUNCAN 2,000 CESAR CHAVEZ 26TH 25TH 24TH ELIZABETH 22ND 21ST 26TH 23RD 22ND HILL MARIPOSA 24TH 23RD 23RD 22ND 21ST LIBERTY 17TH 20TH 20TH IN W IR N UN 19TH 16TH ADAIR DIVISION HBOUND 19TH 18TH ALAMEDA 14TH 15TH 15TH 15TH TH 12 Infirm Shutoff Valves NAN BUCHA ORBEN OAK LILY PAGE HAIGHT HWY 101 SO UT L NE N A H C G N KI Y R R BE DUBOCE S S JE T KE AR M FELL AWSS Pipes N O RY R BE L NE N A H C LINDEN S TI O PLUM WALLER TUR K IE NA IN M GROVE HAYES FULTON O LS FO AM H TE N IE A A M O AT E ST N SO N VE GATE GOLDEN TER MCAL LIS JE EDDY N SO N RI E O SH AR EL H I-80 W AN N N ND A T SE R N B N YA W BR TO IVY MYRTLE PA ZA M GEARY SS ELLIS OLI VE LL OFARRE IE N AN MAID EN M D AR A W N HO NTI E M LE C D W O UN D BO T ES W R 0 BE I-8 TA POST S IL SI IS M BUSH SUTTER AUSTI N AUSTI N FERN FERN Legend N JACKSO GTON WASHIN CLAY ENTO SAC RAM NIA R FO CALI PINE PACIFIC Appendix A Project Data Sheets AWSS Project ID Project Name 2 4th Street Bridge Connection Deficiency ID Need D15 The rubber AWSS hose piping at 4th & Channel Street connecting the north and south side of 4th Street Bridge was removed during prior construction activities and never replaced. (Description and details from Task 2 TM) Project Objective/Benefit This project would restore the 4th street connection by running a hose across the channel along the bottom of the Bay. This would provide more supply to the southern side of the bridge and improve localized system redundancy between Mission Bay and South Beach/SOMA. Assumptions and Unknowns Connections on either side of 4th street bridge must be in good condition Install ~ 500 LF of 12 inch diameter hose connecting to the pipelines on either side of the Description, Design/Sizing Criteria 4th St. Bridge, and running in a trench at the bottom of the Bay. The bottom would be dredged and the hose buried, protected from boat anchors, and weighted to prevent buoyant lift. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $257,813 $1,340,625 $1,598,438 $417 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 750 3 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 2 4th Street Bridge Connection Assumptions 10' wide 5' deep trench in bay sediment Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 0.5 7,500 1,806 0 0.1 Streets subjected to significant duration closures None Land Use Types Permitting Geotechnical Environmental San Francisco Bay Community Some constructon traffic impacts across 4th Street. Pedestrian impacts associated with staging of work and connection to AWSS on either side of bridge. Bay sediment disturbance, approximately 7500 sf. 4 of 62 Legend M O UX L B E Existing Valves TO SE N W G N KI ND R BE AWSS Pipes RY L NE N A CH 4th Street Bridge (not currently connected) TERRY A FRANCOIS TH 05 TH 04 R BE RY L NE AN CH ION MISS M NA UN ED 4 01 N UN 05 T 06 H ± S EN 80 NO TH R BO D TH UN 07 200 400 2 1 W O I-2 0 01 03RD M NA UN ED AM ED 800 Feet K RO C Appendix A Project Data Sheets AWSS Project ID Project Name 3 PS1 Tunnel Upgrade Deficiency ID Need D4,D5 Analyses and inspections indicate that Pump Station No. 1 seawater intake tunnel has damage to the lining and concrete, has some cracking and has potential failure modes due to potential lateral ground movement. Further geotechnical field work and analysis is being performed under Task 12. Recommendations for repairs and structural mitigation are discussed in the Task 7 TM. Project Objective/Benefit The existing seawater intake tunnel to Pump Station No.1 requires several upgrades for reliable operation. This project would improve the reliability of the tunnel by repairing areas in it as well as installing structural support at the area under the seawall footing and piping for continuity at the CSO structure connections. Assumptions and Unknowns The seawater intake tunnel at Pump Station No. 1 has a section that is currently full of silt which limits its functionality. Completion of this project requires that sediment removal is complete prior to project. The Pump Station No. 1 tunnel repair includes reinforcing the tunnel under the seawall footing as well Description, Design/Sizing Criteria as placing 3 foot diameter HDPE pipes upstream and downstream of the connection of the tunnel to the CSO box. Strengthening of the tunnel section that lies beneath the footing and for a short distance on either side is recommended by either installing ribs at 1-2 ft spacing, or a heavy HDPE sleeve inside the tunnel to transmit water even if the reinforced concrete tunnel wall is damaged. The necessary length of tunnel, wall thickness and diameter are to be determined in a subsequent phase of the study. The design criteria of the sleeve would not include strengthening the tunnel. The sleeve needs only be able to resist the collapse of the footing and to continue transmitting water. At the connection to the CSO box, remediation is recommended, potentially through installation of an inner sleeve, possibly of heavy wall HDPE, centered on the interface between CSO box and tunnel and extending at least 5 feet into the tunnel on the Bay side and 25 feet into the CSO box on the land side. The diameter of the sleeve should be 30-33 inches so that it can be accommodated within the 36 inch diameter CSO box conduit. Detailed design of the sleeve and placement are deferred to a later stage of the project Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $305,253 $1,587,314 $1,892,567 $0 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 5 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 3 PS1 Tunnel Upgrade Assumptions Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 2.2 0 0 0 0.0 Existing SFPUC Facility Streets subjected to significant duration closures None Land Use Types Permitting Geotechnical Environmental San Francisco Bay - Tunnel Intake Community Construction staging along waterfront. Marine construction - work will occur in flooded seawater intake tunnel. No sediment impacts anticipated associated with this project. 6 of 62 D UN TB O D UN O EA ST B P TR I-8 0 LO O AN SB AY M I-8 0 Y R IN O OFF I-80 W CO N I-8 0 E ON O M E W TO EN NS D BO F OF 80 N I-2 RY D G N I-280 S ON KI 2,000 Feet C EL NN A H EL N N HA C COIS UN 1,000 R BE TH 04 RT TH 07 TH 500 TH 05 BE 08 ± O HB RT NO AN IL G TE KA 0 80 I-2 DM AR OFF N TO NG LA E I-8 0 TERRY A FRAN E RY VE XO U BL TH 06 ET RI R HA 0 E C IN R BE S RI R O I-8 N RE L ER O R G M N PS1 Tunnel SK LU M AK O T N YA R B SH EL W H C H UT SH EL W N LO EE FR ER M D O FE B O E D AN N A CL W R BE TA T RI 0 E O I-8 FF O AN ZO RA LA C TH 05 LM FA N U Y AR Y LE ST RY LM IL AN BR THE EMBA RCADER EX I R AR H N SO FF WO S ES E RN O AP -L PU LA M IP SH ER AH AL R PE I-8 0 R O AL A A N AM TI H EN TE EM CL W EA N LS A Z RI ES SP AI M NT W DO TH AN N IN M E AL BE D N 02 PL S IE FO U G W HA KA S JE O EM FR Y D NT U H D AR N DE ER R 03 W O H AWSS Pipes AL M M O G NT N T AR EU ST NT FRO O M SO ST 01 EW E NI AN ON STOCKT S N VE E T IM ION E L SS I M A N IN M A M TO A N Y N N MAID EN GEARY Y BATTER T KE N O AR M NS E EV ST POST Legend Existing Valves O TH AN CAMPTON Y HARDIE SUTTER N ME SANSO OMERY MONTG BUSH HARLA CENTUR KEARNY GRA NT PINE Appendix A Project Data Sheets AWSS Project ID Project Name 4 Twin Peaks Reservoir Outlet Connection Deficiency ID Need D47 Currently the AWSS can only be directly served from the 20 inch Twin Peaks Tunnel line. In the event of an outage or failure of this line no water can be delivered into the AWSS from Twin Peaks directly. It can then only be fed by opening division gates from a lower zone. Project Objective/Benefit The AWSS is fed from a tee off the west discharge piping. The west basin can be isolated while feeding the AWSS by using the sluice gate + new balancing valve. This project would install a connection between the existing 20 inch discharge lines from Twin Peaks Reservoir after they exit the tunnels and before the tee which heads west to feed the Twin Peaks Zone. This connection would allow either 20 inch discharge line to feed the Twin Peaks zone. Assumptions and Unknowns Assuming that the connection would be a manual valve and pipe in street down hill from the tunnel ends. Install a short distance (~20 LF) of 20 inch pipe plus a 20 inch gate valve. Tee connections Description, Design/Sizing Criteria into existing pipelines. Match outlet size from Twin Peaks West. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $101,750 $529,100 $630,850 $437 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 2 20 7 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 4 Twin Peaks Reservoir Outlet Connection Assumptions buried valves, 20' x 20' square Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 0.5 400 193 20 0.0 CCSF - SFPUC Streets subjected to significant duration closures Intersection of Twin Peaks Blvd. and Raccoon Land Use Types Permitting Geotechnical Environmental Street Community Construction in residential area street intersection off Twin Peaks Blvd. None anticipated 8 of 62 SH RA DE R Legend Existing Valves BEL GRAVE UN NA M S TWIN PEAK DON CLARE N ET T CO RB BIGLER CLAYTON AWSS Pipes ED 10 8 PE M NE BE RT O O YS T GR A WN CRO N New Valve and Connecting Pipe MOUNTAIN SPRING LL VI G LE NB R O O K A RA CC SAINT GERMAIN OO N BURNETT NORTH PALO ALTO MA RV IE W BURN E VI 0FAR W 100 ± 200 TW 400 Feet IN PE AK S E TT Appendix A Project Data Sheets AWSS Project ID Project Name 5 Jones St Tank Bypass Valves Deficiency ID Need D29 Currently CDD staff must travel to the Jones St Tank to operate the manual tank discharge and bypass valves to introduce the upper zone into the lower zone. The 2010 bond funds project as currently designed will upgrade the tank discharge gates, but not the bypass valves. Project Objective/Benefit This project will allow quick response to increase system pressures in the lower zone by allowing remote operation of the tank and bypass gates. Assumptions and Unknowns Assume that Emergency valves No. 15 and 16 are motorized and can be closed so that Valves 5 through 14 and be motorized and fully opened when needed. The bypass gates will need to be motorized as well and all connected to SCADA for remote control and monitoring. Assume that a maximum of two valves would be operated at a time. Install motorized actuators and SCADA control to all 10 existing gate valves, including power Description, Design/Sizing Criteria supply and SCADA backup communications such that two gates at a time would be slowly opened. There are five 12 inch gate valves for each of the two existing bypass gates. Confirm existing emergency generator has sufficent capacity for backup power. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $412,500 $2,145,000 $2,557,500 $6,172 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 10 10 9 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 5 Jones St Tank Bypass Valves Assumptions Assumes work is contained entirely within existing facility Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 0.7 0 0 0 0.0 CCSF - SFPUC Streets subjected to significant duration closures None Land Use Types Permitting Geotechnical Environmental Within existing SFPUC Facility Community All contruction is located inside existing SFPUC Facility. Minor traffic impacts possible associated with construction activities. None anticipated 10 of 62 WA LL N JACKSO MARC Y Legend Existing Valves AWSS Pipes MASON GTO WASHIN N TRUETT PRIEST REED MALVINA T PLEASAN Jones Street Tank Valve House EWER AN TAYLOR JONES GOLDEN HYDE L KIMBAL CUSHM ENTO SAC RAM LEROY TROY LE SPR OU CLAY CALIFO RNIA ACORN HELEN WORTH LEAVEN PINE D MULFOR BUSH 0 125 ± 250 SUTTER 500 Feet HOBART Appendix A Project Data Sheets AWSS Project ID Project Name 6 Repair Suction Connections Deficiency ID Need D30 The 35 suction connections which allow fire engines to pump water from San Francisco bay are of unknown condition and operability. These connections allow fire engines to pump seawater to fight fires along the waterfront, or alternately to pump water from the Bay into the AWSS. Some of them are located on the bay bottom and may be filled with silt or marine organisms. Project Objective/Benefit This project includes inspection, evaluation of condition, and repair, replacement, or relocation of each suction connection as appropriate. This would improve the reliability of the seawater source pumped from the Bay by fire trucks to fight fires along the waterfront, or alternately to pump water from the Bay into the AWSS. The project would evaluate the condition, expected operability, and seismic performance of each suction connection individually. Alternatives applicable to each individual suction include repair, replacement, relocation, or abandonment. In some cases the suction intakes may be buried in sediment and cannot be drawn from or flushed. Dredging of Bay bottom is not included in this project. Some fittings may have been removed by vandals. Assumptions and Unknowns Inspect and evaluate the condition of each of the 35 existing suction connections. As Description, Design/Sizing Criteria appropriate based on findings, perform repairs, replace, or relocate each suction connection as appropriate. Consider pressure requirements, fitting connections to fire trucks. Consider long term operability of each siphon given sedimentation. Consider replacement with HDPE or other alternate material which may have, but superior performance in a marine environment. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $371,250 $1,930,500 $2,301,750 $0 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 11 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 6 Repair Suction Connections Assumptions Assume 10 of the 35 suction connections must be replaced, requires drilling into Bay from waterfront. Assume 20'x20' required for staging of repairs ot the others Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.3 14,000 1,204 0 1.1 Varies - SF Port and other Streets subjected to significant duration closures None Land Use Types Permitting Geotechnical Environmental Commerical, industrial, recreational along waterfront Community Varies by site. Possible visual and recreational impacts associated with construction staging. 35 different sites located along waterfront. No impacts anticipated for inspection and repair. If any siphons need to be replaced or relocated then impacts to Bay are possible associated with installation of seawater suction. Minimal excavation. 12 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 7 SCADA Improvements Deficiency ID Need D20,D22,D23 Some critical AWSS facilities cannot be remotely operated, which could limit operational response in the immediate aftermath of an earthquake. Other automated controls are either obsolete or in need of backup communications systems. Specific needs are documented in the Task 6 SCADA TM. Project Objective/Benefit This project would upgrade and expand SCADA remote operation capabilities of AWSS facilities, including remote operation of Pump Station No.1 and No. 2, gate valves and incorporation of the AWSS SCADA system into the CDD SCADA system. Controls, software and hardware will be consistent and allow better operation during emergencies. Assumptions and Unknowns See Task 6 SCADA TM 1. Upgrade Pump Stations No. 1 and No. 2 to add primary and backup SCADA connection Description, Design/Sizing Criteria and provide remote monitoring and control capabilities. 2. Upgrade five motorized valves to provide backup communications to radio (three at Twin Peaks Reservoir, Ocean Ave. at 280 East and Ocean Ave. at 280 West). Motorized actuators are already installed, need to install remote monitoring and control capabilities. 3. Add automation to the Bay and Van Ness gate valves, bringing the number of automated valves to 32 from 30. Complete automation including remote monitoring and control capabilities. 4. Upgrade obsolete Wonderware and replace hardware as necessary for all facilities. 5. Integrate emergency operation locations with potable water system operations. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $426,250 $2,216,500 $2,642,750 $1,967 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 9 13 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 7 SCADA Improvements Assumptions Assumes work is contained entirely within existing facility Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.1 0 0 0 0.0 CCSF - SFPUC Streets subjected to significant duration closures None Land Use Types Permitting Geotechnical Environmental Within existing SFPUC facilities Community All contruction is located inside existing SFPUC Facility. Minor traffic impacts possible associaetd with construction activities. None anticipated. Project is above ground 14 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 8 Fireboat Manifold Rehabilitation & Replacement Deficiency ID Need D3,D6,D41 Three of the five existing fireboat manifolds which allow fire boats to pump water from the bay into the AWSS are located on docks of of unknown condition and operability, and may be susceptible to seismically induced failures. In addition, the existing geologic conditions and future seismic performance of the piers may create interaction issues with the fireboat manifold piping and cause significant damage and potentially complete failure of these facilities. Project Objective/Benefit This project would evaluate the condition of and repair, replace, or relocate as appropriate of three of the five existing fireboat manifolds. The objective is to improve the reliability of the seawater water source pumped by fireboats into the AWSS. Assumptions and Unknowns SFPUC staff believe that only two of the 5 fireboat manifolds are currently installed in solid ground foundations - Islais Creek and Fisherman’s Wharf. Facilities may be designated historic structures, requiring abandonment in place and new construction, rather than replacement. Assume relocation of manifold located on Pier 33 1/2. Assume Pier 22 1/2 is seismically upgraded by another project. Assume Fort Mason AWSS pipeline must be relocated to a new alignment on the Pier Inspect and evaluate the condition and seismic vulnerability of each of the five existing Description, Design/Sizing Criteria fireboat manifolds. As appropriate based on findings, perform repairs, replace, or relocate each fireboat manifold. Any facilities judged to be located on seismically unsafe piers should be relocated. Manifolds could be relocated off the Piers, but need to consider bathymetry, access, etc. Pier 22 1/2 is being rehabilitated by the Fire Department and can be considered seismically retrofitted for the purpose of this project. Fort Mason - assume relocation of ~1200 LF of Pipe, recoating and flushing of manifold Fisherman's Wharf assume recoating and flushing only Islais Creek assume recoating and flushing only Pier 22 1/2 assume recoating and flushing only Pier 33 1/2 assume abandonment in place of existing pipe and manifold, construction of new manifold. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $110,000 $572,000 $682,000 $0 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 15 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 8 Fireboat Manifold Rehabilitation & Replacement Assumptions Assume relocation of manifolds and connector pipelines is required at Fort Mason and Pier 33 1/2. All facilities are above ground. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 0.9 49,200 0 0 1.0 Varies - SF Port and other Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Commerical, industrial, recreational along waterfront Community Varies by site. Possible visual and recreational impacts associated with construction staging. Potential impacts to commercial and recreational uses at Fort Mason and site near Pier 33 1/2. None anticipated for 3 of the 5 sites. Fort Mason and Pier 33 1/2 require installation of new pipeline along or underneath pier, accessed from water. Pier 33 1/2 and Fort Mason manifolds could be considered historical structures. 16 of 62 R CO PFEIFFE FRANCIS T NU T ES CH D LOMBAR ICH E GRE NW M EN DE LL MS RE VE TH O M HM ER RE AS IN GA LL S D UN TB O EA S I-8 0 O LS LP S N RA NK I A ESTA TI V RO L L TON KEITH CAS LLE SA O SC ND CAR WILL IA DS ON FA IR FA X CA RG EV AN S WIL L E GA L N NO I-2 8 0 OO D THOR N H E NEW HAL L KE IT H TO LA ND BY SE L ES OA KD E AL B E RI E BL DG B EV RO IE TO PA W PE LO KA U BAY V IE W N ISLAIS BU RK HU O IS R AR 26TH LA NE UND OUT H BO BARNE V ELD UP TO N BRE BA WST YS ER H OR LO O HWY MIS E 1 01 S HOLLA DAY BANKS NEVADA GATES ANDOVER ANDERSON W SO N M S HA RB OA KD A OR KI SK A LE INDIA BRADFORD SP EC T EL S IE ION PR O E JO S MI SS SAN KI RK DA VI D O LS LA AG NO N IN N R T EA AR S P A I N M LE EU A BE GA LV EZ FO 03RD ON OL E E ILLINOIS MARIN JE I SS TENNESSEE ELM IRA RD OU A GIR GE N IMA SILL TON FE L HB RT EM D AL UN BO TH R O 0N Y I-28 EEN SW R E SILVE HAL NO CAMBRID 100 0200 400 Feet HELENA FT ER 01 ± I-280 SOU THBOUND SH A Y1 HW CRESCENT Y AN SUTTER POST MAIDEN GEARY CESAR CHAVEZ EL T KE N AR O M SI S I M INDIAN A PARK P NA AP PA R BU S 26TH KAN SAS EUGENIA JONES WORTH LEAVEN HYDE POLK A FLORID BERNAL HEIGHTS POWHATTAN YORK ALABAMA AP PL ET ON NORWI CH RIPLEY LARKIN IN GOUGH CO RT LA ND SHOTWELL 28TH CHE FOLSOM CO SO PIO FRANKL OCTAV IA CAPP VAL ENCIA OSAGE PRECITA AWSS Pipes GREEN ST E PIERCE 27TH 25TH ENTO SAC RAM NIA R O IF CAL PINE BUSH ALTA K HALLEC CLAY GTON WASHIN WILMOT 26TH TAYLOR LAGUNA NAN BUCHA R FIL LMO R STEIN E PACIFIC N JACKSO M L POWEL A OCTAVI UNION E GRE N GLOVER VALLEJO CLAY JURI MASON FIL BERT OL U Exist Valves IN C FireboatManifold HA W GR ES IF FI TH FI TC H LIA PH E IS CO FRA NC CO FRANCIS UT CHESTN MAGNO N MOULTO Y LE X PI Legend BAY NT BEA CH POINT NORTH QU I EL L CD OW M PE ES S VAN N A PO MARIN ST DRUMM 01 DAVI S O DAVI S ER D AD FRONT N RC Y 02 BATTER BA E EM E SAN SOM TH TRINITY OMERY MONTG SPR ING KEARNY Y QUIN C ES GRANT VARENN KEARNY N STOCKTO JOICE GRANT STONE RE WETM O TONQUIN ON JEFFERS BEACH POINT NORTH Appendix A Project Data Sheets AWSS Project ID Project Name 9 Pipeline Investigations and Repairs Deficiency ID Need D2,D7,D8,D9,D10,D12,D14,D43 The condition of much of the AWSS is unknown. Additional data is required to prioritize pipeline replacement and confirm risk of failure. Project Objective/Benefit This project would conduct testing to assess the condition of the AWSS, establish remaining service, and prioritize ethe pipeline replacement program Assumptions and Unknowns Description, Design/Sizing Criteria Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $1,100,000 $5,720,000 $6,820,000 $0 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 17 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 9 Pipeline Investigations and Repairs Assumptions Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.4 0 0 0 0.0 Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Community 18 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 10 Reliability Upgrades at Facilities Deficiency ID Need D28, D46 CER's prepared by SFPUC as part of the 2010 bond projects have identified facility needs which were not included in the 2010 bond and are not being addressed in the ongoing projects. Other issues need to be addressed provide reliable operations. Project Objective/Benefit Increase reliability at the five facilities by doing the future work identified in the 2012 CER reports. Assumptions and Unknowns CER's identified issues but planning work beyond that has not been performed. Perform repairs and other improvements at the following existing facilities: Twin Peaks Description, Design/Sizing Criteria Reservoir, Ashbury Tank, Jones Street Tank, Pump Station No 1, Pump Station No 2. Suggested repairs will be developed in more detail in SFPUC Conceptual Engineering Reports associated with each listed facility (omitting items to be performed by other AWSS projects). Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $2,750,000 $14,300,000 $17,050,000 $5,270 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 19 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 10 Reliability Upgrades at Facilities Assumptions Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 2.2 0 0 0 0.0 CCSF - SFPUC Streets subjected to significant duration closures None Land Use Types Permitting Geotechnical Environmental Within existing SFPUC facilities Community All contruction is located inside existing SFPUC Facilities. Minor traffic impacts possible associated with construction activities. None anticipated. Project is above ground. 20 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 11 Cistern Repair and Construct 27 New Cisterns, Ph. 1 Deficiency ID Need D13,D51,D52 1. System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. 2. There are a number of fire response areas which the AWSS presently cannot serve. Project Objective/Benefit This project would: 1. Install 27 cisterns where needed to provide firefighting capabilities Assumptions and Unknowns Reliance on Cisterns requires Fire Engines for pumping. Install 27 cisterns at locations adjacent to areas of highest fire demand, as indicated on map Description, Design/Sizing Criteria in Task 11 TM. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $8,250,000 $42,900,000 $51,150,000 $26,181 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 33 21 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 11 Cistern Repair and Construct 27 New Cisterns, Ph. 1 Assumptions 33 Cisterns, 25' square, 30' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.8 165,000 40,431 0 14.5 CCSF - SFPUC Streets subjected to significant duration closures 33 intersections througout CCSF. Land Use Types Permitting Geotechnical Environmental Street Community Varies by site. Traffic and other impacts associated with construction. Different sites located on street intersections. No impacts anticipated for inspection and repair. New cisterns will have contruction and traffic impacts. Utilities may need to be relocated. Disposal of spoils. Archaeological impacts are possible associated with the many excavations in different locations throughout the City. 22 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 12 Cistern Repair and Construct 19 New Cisterns, Ph. 1 Deficiency ID Need D13,D51,D52 1. System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. 2. There are a number of fire response areas which the AWSS presently cannot serve. Project Objective/Benefit This project would: 1. Install 19 cisterns where needed to provide firefighting capabilities Assumptions and Unknowns Reliance on Cisterns requires Fire Engines for pumping. Install 19 cisterns in locations adjacent to areas of highest fire demand, as indicated on map Description, Design/Sizing Criteria in Task 11 TM. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $4,125,000 $21,450,000 $25,575,000 $36,495 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 46 23 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 12 Cistern Repair and Construct 19 New Cisterns, Ph. 1 Assumptions 46 Cisterns, 25' square, 30' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.8 230,000 56,359 20.2 CCSF - SFPUC Streets subjected to significant duration closures 46 intersections througout CCSF. Land Use Types Permitting Geotechnical Environmental Street Community Varies by site. Traffic and other impacts associated with construction. Different sites located on street intersections. No impacts anticipated for inspection and repair. New cisterns will have contruction and traffic impacts. Utilities may need to be relocated. Disposal of spoils. Archaeological impacts are possible associated with the many excavations in different locations throughout the City. 24 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 13 Construct 33 New Cisterns, Phase 2 Deficiency ID Need D51,D52 1. System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. 2. There are a number of fire response areas which the AWSS presently cannot serve. Project Objective/Benefit This project would install 33 cisterns where needed to provide firefighting capabilities. Assumptions and Unknowns Reliance on Cisterns requires Fire Engines for pumping. Install 33 cisterns in locations adjacent to areas of highest fire demand, as indicated on map Description, Design/Sizing Criteria in Task 11 TM. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $9,075,000 $47,190,000 $56,265,000 $26,181 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 33 25 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 13 Construct 33 New Cisterns, Phase 2 Assumptions 33 Cisterns, 25' square, 30' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.8 165,000 40,431 14.5 CCSF - SFPUC Streets subjected to significant duration closures 33 intersections througout CCSF. Land Use Types Permitting Geotechnical Environmental Street Community Varies by site. Traffic and other impacts associated with construction. Different sites located on street intersections. No impacts anticipated for inspection and repair. New cisterns will have contruction and traffic impacts. Utilities may need to be relocated. Disposal of spoils. Archaeological impacts are possible associated with the many excavations in different locations throughout the City. 26 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 14 Construct 30 New Cisterns, Phase 3 Deficiency ID Need D51,D52 1. System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. 2. There are a number of fire response areas which the AWSS presently cannot serve. Project Objective/Benefit This project would install 30 cisterns where needed to provide firefighting capabilities. Assumptions and Unknowns Reliance on Cisterns requires Fire Engines for pumping. Install 30 cisterns in locations adjacent to areas of highest fire demand, as indicated on map Description, Design/Sizing Criteria in Task 11 TM. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $8,250,000 $42,900,000 $51,150,000 $23,801 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 30 27 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 14 Construct 30 New Cisterns, Phase 3 Assumptions 30 Cisterns, 25' square, 30' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.8 150,000 36,756 13.2 CCSF - SFPUC Streets subjected to significant duration closures 30 intersections througout CCSF. Land Use Types Permitting Geotechnical Environmental Street Community Varies by site. Traffic and other impacts associated with construction. Different sites located on street intersections. No impacts anticipated for inspection and repair. New cisterns will have contruction and traffic impacts. Utilities may need to be relocated. Disposal of spoils. Archaeological impacts are possible associated with the many excavations in different locations throughout the City. 28 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 15 Construct 90 New Cisterns, Phase 4 Deficiency ID Need D51,D52 1. System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. 2. There are a number of fire response areas which the AWSS presently cannot serve. Project Objective/Benefit This project would install 30 cisterns where needed to provide firefighting capabilities. Assumptions and Unknowns Reliance on Cisterns requires Fire Engines for pumping. Install 30 cisterns in locations adjacent to areas of highest fire demand, as indicated on map Description, Design/Sizing Criteria in Task 11 TM. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $24,750,000 $128,700,000 $153,450,000 $71,402 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 90 29 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 15 Construct 90 New Cisterns, Phase 4 Assumptions 90 Cisterns, 25' square, 30' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.8 450,000 110,267 0 39.5 CCSF - SFPUC Streets subjected to significant duration closures 90 intersections througout CCSF. Land Use Types Permitting Geotechnical Environmental Street Community Varies by site. Traffic and other impacts associated with construction. Different sites located on street intersections. No impacts anticipated for inspection and repair. New cisterns will have contruction and traffic impacts. Utilities may need to be relocated. Disposal of spoils. Archaeological impacts are possible associated with the many excavations in different locations throughout the City. 30 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 16 Construct 90 New Cisterns, Phase 5 Deficiency ID Need D51,D52 1. System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. 2. There are a number of fire response areas which the AWSS presently cannot serve. Project Objective/Benefit This project would install 30 cisterns where needed to provide firefighting capabilities. Assumptions and Unknowns Reliance on Cisterns requires Fire Engines for pumping. Install 30 cisterns in locations adjacent to areas of highest fire demand, as indicated on map Description, Design/Sizing Criteria in Task 11 TM. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $24,750,000 $128,700,000 $153,450,000 $71,402 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 90 31 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 16 Construct 90 New Cisterns, Phase 5 Assumptions 90 Cisterns, 25' square, 30' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.8 450,000 110,267 39.6 CCSF - SFPUC Streets subjected to significant duration closures 90 intersections througout CCSF. Land Use Types Permitting Geotechnical Environmental Street Community Varies by site. Traffic and other impacts associated with construction. Different sites located on street intersections. No impacts anticipated for inspection and repair. New cisterns will have contruction and traffic impacts. Utilities may need to be relocated. Disposal of spoils. Archaeological impacts are possible associated with the many excavations in different locations throughout the City. 32 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 17 Construct 90 New Cisterns, Phase 6 Deficiency ID Need D51,D52 1. System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. 2. There are a number of fire response areas which the AWSS presently cannot serve. Project Objective/Benefit This project would install 30 cisterns where needed to provide firefighting capabilities. Assumptions and Unknowns Reliance on Cisterns requires Fire Engines for pumping. Install 30 cisterns in locations adjacent to areas of highest fire demand, as indicated on map Description, Design/Sizing Criteria in Task 11 TM. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $24,750,000 $128,700,000 $153,450,000 $71,402 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 90 33 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 17 Construct 90 New Cisterns, Phase 6 Assumptions 90 Cisterns, 25' square, 30' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 3.8 450,000 110,267 39.6 CCSF - SFPUC Streets subjected to significant duration closures 90 intersections througout CCSF. Land Use Types Permitting Geotechnical Environmental Street Community Varies by site. Traffic and other impacts associated with construction. Different sites located on street intersections. No impacts anticipated for inspection and repair. New cisterns will have contruction and traffic impacts. Utilities may need to be relocated. Disposal of spoils. Archaeological impacts are possible associated with the many excavations in different locations throughout the City. 34 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 18 Balboa Tank and Booster PS Deficiency ID Need D52 System supply is limited to the existing reservoir and tanks, Pump Station No.1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply to the upper zone is required to meet fire demands. Project Objective/Benefit This project would install a new tank and booster pump station located at the Balboa Reservoir site to serve as an additional supply source for the upper zone. Assumptions and Unknowns Could fill tank with new line from crosstown transmission main with air gap, or adjacent AWSS. Install a new underground tank situated under City College parking lot (north of Ocean Ave.)Description, Design/Sizing Criteria Include booster pump station, 16,500 gpm at 152 psi - Approximately 1450 LF of 20 inch pipe. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $6,001,875 $31,209,750 $37,211,625 $6,952 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 1 1 1450 35 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 18 Balboa Tank and Booster PS Assumptions Assume 5' wide trench, 5' deep, 2' native backfill. Assume 300'x300'x25' excavation for tank. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 2.8 120,000 109,583 0 7.6 CCSF - SFPUC Streets subjected to significant duration closures None Land Use Types Permitting Geotechnical Environmental Parking Lot (City College) Community Traffic impacts associated with construction activities are anticipated, including trucking of excavation spoils and disposal offsite. Disposal of excavation spoils, other construction impacts. Entire site is an existing parking lot. Trenching and soil excavation will disturb soil. 36 of 62 TIC RE T LAKEVIEW RID G E MO UN T NA HU A DE LA NO SA N JO S GE NE VA E TH BOU N HOLLOWAY I-280 NO R 0 87 THBOUND RG TH EDGAR CLOUD I-2 80 SOU TA RA LO UI S BU R BRUCE HO W WI LL IA HAROLD UNNA M ED CA IN E ES GET Z DE MONTFORT D I-2 8 0 N OFF NO I-28 0S AR C EAST WEST O SCIENCE PHELAN ATE EDNA FLOOD Balboa Tank NIA G VE RN ON TE M RO O YU CA EE MA J RG A OD FO E MINERVA LEE WESTWOOD HOM EWOOD NO RT HG EDNA FOERSTER GENNESSEE RIDGEWOOD EDNA MANGELS N AW SH MONTANA IT MM SU 800 Feet MA THRIFT JO SI AH GRAFTON PLYMOUTH GRANADA WO TH OU D BRIGHTON FAX ON A DO KEYSTONE O PLYMOUTH GRANAD A MIRAMAR CAPITOL FAXON DOR S MO O CI T NTE CCSF PARKING LOT FAXON JULES AD HE EA ST W O OOD MINERVA O M EL HAZELW PI ZA RR O D ± T VALDEZ 200 400 40 OO HW RT NO 0 D IN SA COLON KENWO O ED 0 A UEN BA B YER ON TE RE Y DA RI EN UP LA ND IP E FEL M N SA ASHTON D OO YW MA NO BA UR ORIZABA UNN AM MELROSE JOOST HEARST STAPLES JUDSON JUDSON WILDWOOD MARSTON HAVELOCK OCEAN AR A A G M RO E Appendix A Project Data Sheets AWSS Project ID Project Name 19 Alemany Extension Pipeline Deficiency ID Need D51 There are a number of fire response areas which the AWSS presently cannot serve. Some of these are located along Alemany Blvd. Project Objective/Benefit This project would Install a pipeline loop to provide AWSS water to customers located in southern San Francisco. Assumptions and Unknowns Install 13,500 LF of 16" pipe. Description, Design/Sizing Criteria Install hydrants and laterals to serve fire demands located along pipeline. Install automated gate valves at connection points into AWSS. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $3,460,875 $17,996,550 $21,457,425 $23,556 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 2 2 2 13500 37 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 19 Alemany Extension Pipeline Assumptions Assume 5' wide trench, 5' deep, 2' native backfill. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way Streets subjected to significant duration closures 2.9 135,000 11,250 13,500 9.0 CCSF - DPW (Street) Crosses under State Hwy. 280. (Caltrans) Victoria St., Alemany Blvd. Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along ~10 blocks of residential zoned streets, ~17 blocks along Alemany Blvd Disposal of excavation spoils, other construction impacts 38 of 62 BADEN CONGO 41 D0 UN NA ME SO ON DA BA GA LH I ON E ID A IOR JUN Y AN M E AL ON LO ND PA RI S BO N L EL I N TO NG ICK N S W BYR O UN R B ER V NO HA SS CRO MO PO RSE ES E ON LIS M RO SE GO DE LA N O A G TA YN DD EZ EN OT 80 THBOUND I-2 80 SOU NA HU A JU AN NA PL CAPITOL DETROIT EDNA FOERSTER WEST I-2 PHELAN BRIGHTON SU MM IT LEE J MA OSI RG AH HAROLD MA AR WI JE ET LL ST IAR CA IC SA HO IN E N WT L OU JO H ISB SE TA U RG RA PLYMOUTH MIRAMAR FAXON JULES RH IN E VICTORIA HEAD RAMSEL L SE NE CA DE LA NO DORADO FAX ON KEY STO NE ASHTON ORIZABA HEAD BRIGHT VERNON ARCH DE LO NG KEMPTON FF ION FF AT E M LA KE ANO R WO OD ES TG W ARCH ALV ISO BYXBEE RALSTON SAINT CHARLES S O CHESTER 80 I-2 S MIS A I A N TA AR ES IAG N LI EB IG ON EID R A G S YU AR A C SE R VE OLI 1,600 Feet RI CE G W O IL E SO TH N E ON N O UR H E RA RA U LA E NC RE N 80 I-2 PAL METTO BE PL ER O M SAGAMORE RU E NE D TA NE SA N SA N AW SH SADOWA CO HAVELOCK OCEAN U AY C R LA CU D R CI UN BO H RT NO T IS CUR E POP N ISO ALL D C OR G CO N BER TE N TINE GUT RE N FLO A AW A T T SA L O TE O FO E E PL LE C G IP O H D NA W O HE RH OO Alemany Loop W LA ± 400 800 BROAD MINERVA M TH LOBOS 0 87 GE NE VA RID GE MONTANA RANDOLPH HAVELOCK UNNA M ED D OO THRIFT MINERVA AR MARSTON HOLLOWAY LAKEVIEW SHIELDS 19 0 S 0 I-2 8 JUDSON CLOUD GRAFTON GARFIELD BR OT STAPLES JUDSON DE MONTFORT WAY WA LK BO RIC A CO RO NA DE SO TO VIC TO RIA PICO SARGENT FLOOD WILDWOOD W TH OU JOOST HEARST SCIENCE A CAD MON URBA N O OD GRANAD A SAN BENITO TO S AP WO KEN M RO O CIT TE ON COL ON PI ZA R GENNESSEE ND OOD ELW H AZ PALOMA ENA D UPLA MANGELS Z VAL DE NT ER EY OO YW MA DARIEN O BU YER BA M LA RI S Appendix A Project Data Sheets AWSS Project ID Project Name 20 Silver Extension Pipeline Deficiency ID Need D51 The pipelines to the south lack a looped or gridded backup system. One failure and large areas would be out of service. This is identified as a system need. In particular the Mission Street - Ocean Avenue loop and Hunters Point and Mission Bay area would greatly benefit from a connecting pipeline. Project Objective/Benefit This project would install a pipeline in the vicinity of Silver Ave. crossing under Highway 101 to interconnect the Hunters Point area pipelines to the Alemany area pipelines. Assumptions and Unknowns Install 21,500 feet of 20 inch Pipe. Description, Design/Sizing Criteria Install hydrants and laterals to serve fire demands located along pipeline. Install automated gate valves at connection points into AWSS. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $6,806,250 $35,392,500 $42,198,750 $36,545 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 2 2 2 21500 39 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 20 Silver Extension Pipeline Assumptions Assume 5' wide trench, 5' deep, 2' native backfill. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way Streets subjected to significant duration closures 4.1 215,000 17,917 21,500 20.3 CCSF - DPW (Street) Crosses under State Hwy. 101 (Caltrans) Silver St., Bayshore Blvd. Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along ~45 blocks of residential and commercial zoned streets. Disposal of excavation spoils, other construction impacts 40 of 62 NY D ( ! D OU N OU TH B IN RA NK NA NE W HA LL BRID GEV IE W THOR NTON MI TE KE IT H MENDELL 03R D RT LATO VEN U S LP S LE PH E I-2 SE LB Y S L BEL NI NG INAS JE N WH EAT P CAM RO LD QU IN T UP TO N TO LA ND 80 S UND S OU THB O BAR NE V ELD D TLA N RU WI LD E VIS ITA CIO N ALE SAL LE D WAR JA ME CO KE STO W NT Y N ME E AD E LO IS BAY VIE W PA RK BLA NKE N LAT HRO P ALANA ( ! ( ! PAU L KE 03 I RD TH MIL L SUN EN Y JE R WILL IA MS YO RO L L SE EGB E A RA RLE TA YM ON D TAL BER T CO DEL TA ELL IOT VEL AS RE Y HAH N SAW YE R GA LOE RR HR IS O N TO S BLYTH DALE SA N UE PA RQ LE OA KD A TUN NEL BRADFORD NEVADA BANKS GATES ANDERSON BRE WS TER BA YS HO LOO RE HWY MIS 101 WOOL ANDOVER DE 2,000 Feet HOLLADA PER ALTA Y TIF FA NY CO LE RID PR OS G PE E CT EL S IE EL S IE YS GL AD GT ON AR LIN N M IS SI O NA PL ES VIE NN M A MU OSC OW NI CH IN A PR A AT HE NS RG NB U ED I GU E ID LO ND ON L IS BO N LA G R AN OHLON E DIAM OND PA RI S MA DR CH ICA GO 500 1,000 R A D OV O YL NA COR ± BROOKDA Y LEL AND EV AN S ER ST HE RO LP H GE N EVA TE D D KAN SAS E ITA LY AM AZ ON AN K MAN S ELL M B S SEL AN C ON BAC D LAN WAY N RE P VE QU ALO RE E S AD U A S BRU FR PE RS IA CO C AR EY OLS WO GHT DWI Y L EO PO KA IA PE OT TO SC I-280 ILLE 01 TO ERV 1 WAT HWY NO A RD BRU ND GIR SAN A F SH EL L E VER MONT N LO S AVA R OW BUR JOHN N TON FEL S ROW BUR MARIN U BO TH RU SS I PE RU NE W ELM IRA ZI L IMA SILL E DG E YAL B RI CAM ORD OXF D VA R HAR BIER GAM N I SO MAD BR A E HAL Silver Extension SILVER R NO TRUMBULL NEY TI NG L TH EY ER ES A I-280 S OFF Y ALEMAN LS SSE BR U GEN T TIN GOE ET O IN E RS OWD B SOM UTH N T MO I LTO BY DAR HAM COL N BY DOI COL BOW I TY E RS UNIV ON CE T PRIN RST E AMH U GA CAY 01 N BENTON F OF 1S 0 Y1 ND H W H BOU T OR 0N Y I-28 EEN SW CESAR CHAVEZ L ARE APP CHARTER OAK NO BENTON MURRAY JARBOE BLAIR 26TH NA Y1 HW SE JO N SA ROUSSEAU 0 I-2 8 0 EUGENIA HIGHLAND IS Y SE EM B ER SU X N E RICHLAND RR CH COLLEG EY E CRESCENT E N SU S RIPLEY WY 101 I-2 80 TO H ON EY H IR HAMP S YORK AC BE IS O ADD LA ID L ST CO ON RT LA ND A ALT MULLEN MONTCALM TS BERNAL HEIGH POWHATTAN KIN G A FLORID 30TH ALABAMA DAY TREAT 28TH VAL LEY 29TH DAY CO SO R PE PRECITA MANCHESTER FA IR FOLSOM 27TH DUNCAN SHOTWELL 26TH CAPP 25TH VAL ENCIA NOE CASTR O SAN CHEZ CLIPPER CHURCH JERSEY OSAGE 24TH Appendix A Project Data Sheets AWSS Project ID Project Name 21 Geneva Extension Pipeline Deficiency ID Need D51 There are a number of fire response areas which the AWSS presently cannot serve. Some of these are located along Geneva Ave. Project Objective/Benefit This project would install a pipeline loop to provide AWSS water to customers located in Southern San Francisco. The pipeline would run approximately along Geneva Ave, south of McLaren Park and connect to the existing AWSS in the vicinity of 3rd St. and at Orondaga/Alemany. Assumptions and Unknowns Install 20,200 LF of 16" pipe. Description, Design/Sizing Criteria Install hydrants and laterals to serve fire demands located along pipeline. Install automated gate valves at connection points into AWSS. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $5,192,000 $26,998,400 $32,190,400 $25,901 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 2 2 2 20200 41 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 21 Geneva Extension Pipeline Assumptions Assume 5' wide trench, 5' deep, 2' native backfill. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way Streets subjected to significant duration closures 3.9 202,000 16,833 20,200 18.2 CCSF - DPW (Street) Crosses under State Hwy. 101 (Caltrans) Geveva St., San Bruno Ave. Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along ~60 blocks of residential and commercial zoned streets. Disposal of excavation spoils, other construction impacts 42 of 62 S SAN TO TER CIE LIT O CAR MIL L TLA ND DEL TA ELL IOT RE Y HAH N SAW LOE YE R HR LL O AP O P BE CAM A RA RLE TA YM ON D IO N E NEVADA GATES BANKS ANDERSON DE K WI LD E LL BAY S H OR M MU OSC NI O CH W IN A LA G R AN PR A D WAR LO IS TUN NEL NA RG VIE N BU ED IN EN S AT H PA RI S ID NA PL ES D LE B AC ISO N RU N M IS SI O DIAM OND LIPP ARD LO ND ON L IS BO N GU E BADEN A OT SE GO CA YU G MA DR ROBINSON VEL ASC O GA RR NY D AL E D OU N VIS ITA C SUN EN Y PAU L T HB SOU LEL AND T 101 Geneva Extension TE D DY A TI CH ICA GO O SC ELL KA PE MAN S TO AN K IA S SEL 2,000 Feet Y L HWY R E O YL NA A D OV E AK ± 500 1,000 DR T AT W BA LTI MO R F SH EL L E GE N EVA COR H JOHN Y LSE WOO T IGH DW S BRU TI S CUR E POP N ISO ALL 0 MU NIC N LO S AVA ROW BUR ON BAC D LAN WAY CA RR OL EG BE R D CE PE RS TON FEL S ROW BUR AR GIR A SI AN LLIM O ZI L ITA LY AM AZ ON RO LP H E HAL N BRU SAN A EC FR AN PE RU Y EEN SW IRA ND OU SILVER H RT RE VE RE ELM SS I ALEMANY NO B TH N SE KE NN Y TRUMBULL NEY 0 I-2 8 HELENA SE CA D UN BO R NO 01 STILL JUSTIN I-280 N OFF TOMPKINS LS S SE EN BRU G T TIN N GOE ET DO I E RS BOW SOM UTH N T MO I LTO BY DAR HAM COL BY N D OI COL BOW ITY E RS UNIV ON CE T PRIN RST E AMH RU MURRAY E GE YAL BRID C AM ORD OXF D VAR HAR BIER GA M N IS O MAD LE O CRESCENT BENTON E AL BR A RICHLAND COLLEG E IR M AD JU AN PARK Y1 HW UND O THB SOU 0 8 I-2 TH ER ES SA CO A NT A T TE RO R SA CO AR SA N N SA S JO Y ER EN ANDOVER CH GO JOOST IS SAD ELK SURREY M BE SS EX ELM IRA CON SU LAT HR OP Appendix A Project Data Sheets AWSS Project ID Project Name 22 Lake Merced Pump Station Deficiency ID Need D52 System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply to the Upper Zone is required to meet fire demands. Project Objective/Benefit This project would develop an additional supply of water to the AWSS upper zone. Assumptions and Unknowns Assume that construction of the Sunset loop. Assume that an air gapped connection to MWSS would not result in a larger pump station or much increased cost. Install additional pumping capacity at Lake Merced Pump Station to lift water from the lake Description, Design/Sizing Criteria into the AWSS, and optionally also an air gapped capability to lift from the MWSS. Evaluate reliability benefits, costs, other issues for optional connection to MWSS. Pump sizing is 15,000 gpm at 200 psi. Install approximately 7200 LF of 20 inch pipe to connect to the Sunset loop. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $5,039,375 $26,204,750 $31,244,125 $17,409 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 1 7200 43 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 22 Lake Merced Pump Station Assumptions Assume 5' wide trench, 5' deep, 2' native backfill. Assume pump station improvements are within existing site. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.7 72,000 6,000 7,200 2.7 CCSF - SFPUC (pump station) and DPW (Pipeline in Street) Crosses State Hwy. 35 (Caltrans) Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Community Within existing SFPUC facilities, street - residential and commercial Disposal of excavation spoils associated with connector pipeline, other construction impacts. Pump station construction would be within existing SFPUC facility footprint. No impacts to Lake Merced anticipated, as existing suction intake would be utilized and water would only be drawn from the lake during a regional emergency associated with loss of Hetch Hetchy supply. Lane closures during construction, other traffic impacts along ~15 blocks of residential and commercial zoned streets. 44 of 62 GARCES GONZAL EZ R CA LV A SER RANO HIGUERA JUA N I EL CR ES PI FUENTE C R ES PI ARE LLA NO PINTO JOSEPHA BROTHERHOOD BU GR IJA TAPIA TAPIA HOLLOWAY BAU T ISTA DENSLOWE 19TH NG DI RIVAS NT ARBALLO MORNINGSIDE SUNSET 21ST 22ND 23RD 24TH 26TH FOREST VIEW SYLVAN MIDDLEFIELD SPRINGFIELD 20TH 39TH 34TH VALE PALOS LAKESHORE EVERGLADE HAVENSIDE OCEAN MEL BA FO 1,000 Feet CLEARFIELD Lake Merced Pump Station ARBALLO N LAKE MERCED GTO 250 500 GELLERT SLOAT ESCONDIDO 25TH TIN VIDAL HUN LAKESHORE R 0 UIR ± 35TH E ST R HA 36TH A NC LA JO H NM 37TH YORBA EUCALYPTUS BUCKINGHAM WINSTON ST AT E STA TE CAR DIAZ FO NT DEN AS Appendix A Project Data Sheets AWSS Project ID Project Name 23 Sunset Extension Pipeline Deficiency ID Need D51 There are a number of fire response areas which the AWSS presently cannot serve. Many of these are located in the Sunset District. Project Objective/Benefit This project would install a pipeline loop to provide AWSS water for firefighting to customers located in the Sunset District which the AWSS presently does not serve. Assumptions and Unknowns Install 22,000 feet of 20 inch Pipe. Install new valving to separate Upper Zone from Twin Description, Design/Sizing Criteria Peaks Zone. Install hydrants and laterals to serve fire demands located along pipeline. Install automated gate valves at connection points into AWSS. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $6,991,875 $36,357,750 $43,349,625 $37,335 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 2 2 2 22000 45 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 23 Sunset Extension Pipeline Assumptions 10' wide trench, 5' deep Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 4.2 220,000 18,333 22,000 21.2 CCSF - DPW (Street) 19th Ave. and Sloat Blvd. Are State Hwys (Caltrans) Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along ~55 blocks of residential and commercial zoned streets. Pipeline will cross 19th, as well as be placed along Sloat for ~3/4 miles. Permits will be required from Caltrans for construction. Disposal of excavation spoils, other construction impacts 46 of 62 NG DI R HA STA TE FO NT 1,600 Feet TAPIA BA N O N MON CAD A PAL OM A ES TE RO SAN BE N ITO OC EA SAN LEANDRO PO RT O LA CRE S TL AKE SAN FERNANDO SAN RAFAEL TA S FUNSTON FOR EST SID MA E DR ONE 15TH ULLOA UR LA GU NI 20TH JUNIPERO SERRA BUCKINGHAM LUNAD O EUCALYPTUS JUNIPERO SERRA BROADMOOR 22ND 21ST 23RD 25TH 37TH 28TH 26TH 27TH 17TH 18TH 34TH 35TH 36TH 29TH 30TH 31ST 15TH 12TH FUNSTON RIVERA ICA ST AT E 23RD PARAISO 38TH QUIN TARA BO R WINSTON STONECREST D RCE E ME 24TH 26TH VALE SLOAT FOREST VIEW SYLVAN MIDDLEFIELD SPRINGFIELD EVERGLADE HAVENSIDE SUNSET B 39TH 40TH 41ST RIVERA STRATFORD MORNINGSIDE GELLERT E CL U N Sunset Extension 19TH DENSLOW E TR Y LAKESHORE CO UN 41ST 32ND 14TH 16TH ANGLO PACHECO SANTA ANA 400 800 12TH SK YL I PACHECO 20TH 21ST 23RD 24TH 25TH 26TH 27TH 38TH 39TH 40TH CEDRO 11TH N STO FUN TARAVAL 25TH 0 ± CLEARFIELD LAK BA YOR ESCONDIDO 22ND YORBA ORTEGA IO D RA QUIN TARA 33RD 42ND NORI EGA ROC KRID GE SANTIAGO ESC O LTA VICENTE WAWONA DARIEN Appendix A Project Data Sheets AWSS Project ID Project Name 24 Sunset Extension Rezoning Pipeline Deficiency ID Need D51 A connection between 19th Ave. and San Fernando Way would improve system hydraulics and redundancy in Western San Francisco, which lacks a looped or gridded backup system. The Sunset should be on a lower pressure zone than Twin Peaks, requiring isolation by gate valves. Project Objective/Benefit This project would install a pipeline to improve service and redundancy to customers located in the Sunset District. Installed with Sunset loop. Assumptions and Unknowns Install ~1500 LF of 20 inch pipe along Ocean avenue from 19th Ave. to San Fernando Way. Description, Design/Sizing Criteria Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $515,625 $2,681,250 $3,196,875 $1,251 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 1500 47 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 24 Sunset Extension Rezoning Pipeline Assumptions Assume 5' wide trench, 5' deep, 2' native backfill. . Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.1 15,000 1,250 1,500 0.4 CCSF - DPW (Street) Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along ~7 blocks of residential zoned streets. Pipeline will cross 19th Ave and will require permits from Caltrans for construction. Disposal of excavation spoils, other construction impacts 48 of 62 O ICA O A HE D KEYSTONE OD SAN FELIPE AT E LA GU SA N JA C 22ND BEACHMONT NI TA S W O O D AC R E 20TH 21ST 23RD 24TH IN TE RE Y LD WE S TG APTOS DARIEN TO WE S SAN BUENAVENTURA SANTA CLARA SAN BENITO TP OR TA L MAYWOOD BU EN A ASHTON A AD TR EN LEGION ING LE SID E R T MONCADA MA NO PI NE HU RS ID E A A UPL AN D N LA KE WO FA IRF IE URBAN A IN G LES JUNIPERO SERR JUNIPERO SERR BROADM OO R STONECRE ST CEDRO TO RI SO TO A ITOS CERR DE CO RO NA BO R LUNAD O JUNIPERO SERR ES TE R AL V IS O I CE LLO RD 19TH BUCKINGHAM VIC MO NT STRATF O DENSLOW E 800 Feet OC EA N 23RD 24TH 17TH 18TH 20TH 21ST PO RT OL 15TH YE RB A PAULA SANTA WYTON M O LMO HOLLOWAY H ND LY ST UR MERC EDES H TE RR AC E SE SAN AN WINSTON SAN TA ANA ± Sunset Rezoning SAN LEANDRO 200 400 SLOAT SAN FERNANDO EUCALYPTUS SAN RAFAEL MELBA 25TH 0 TLA KE 16TH CR ES 22ND WAWONA 14 T TA SAN A A NI C MO MA LO PA KEN W O OD PICO Appendix A Project Data Sheets AWSS Project ID Project Name 25 Richmond Extension Pipeline Deficiency ID Need D51 There are a number of fire response areas which the AWSS presently cannot serve. Many of these are located in the Sunset and Richmond Districts. Project Objective/Benefit This project would install a pipeline loop to provide AWSS water to customers located in the Sunset and Richmond Districts, crossing through Golden Gate Park. It would connect to the AWSS proposed Sunset Loop, to 19th Ave. in the Sunset, and to 12th. Ave in the Richmond, crossing Golden Gate Park along Chain of Lakes Dr. Assumptions and Unknowns Install 22,400 feet of 20 inch Pipe. Assumed route is along Anza St., 32nd Ave., and Description, Design/Sizing Criteria California St. Install hydrants and laterals to serve fire demands located along pipeline. Install automated gate valves at connection points into AWSS. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $7,108,750 $36,965,500 $44,074,250 $25,321 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 2 2 2 22400 49 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 25 Richmond Extension Pipeline Assumptions Assume 5' wide trench, 5' deep, 2' native backfill. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 4.3 224,000 18,667 22,400 21.9 CCSF - DPW (Street) Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along ~48 blocks of primarily residential zoned streets. Cross Golden Gate Park along Chain of Lakes Drive will have recreational impacts. Pipeline will cross 19th Ave and will require permits from Caltrans for construction. Disposal of excavation spoils, other construction impacts 50 of 62 ON GI LE MCLAREN PARK PRESIDIO 31ST FULTON ESIDIO BY PARK PR CROSSOVE R K NF R OVE E ENN DY MIDDLE WEST SV AN TR STOW LA KE SE ER 11TH 14TH LO MI TA 18TH 15TH 16TH 28TH 29TH HA ORT EG A PACHECO 12TH PACHECO 17TH 19TH 20TH 21ST 22ND 25TH 26TH 27TH 23RD 24TH 32ND 31ST 37TH 36TH 38TH 39TH 40TH 42ND 44TH 43RD 45TH 46TH 41ST 30TH NORI EGA ORTEGA 2,000 Feet AL O N STO FUN 47TH MORAGA N E LIN LAW TO A EG RI NO ± 500 1,000 CO PACHE KIRKHAM R LU PINO 0 33RD JUDAH 12TH 14TH FUNSTON 15TH LINCOLN IRVING 34TH 35TH PASS JOH K LOO MARTIN LUTHER KING JR SUNSET 12TH 14TH 22ND FORT MILEY 3 VETERAN S FUNSTON 16TH 15TH 18TH CABRILLO KE S BE ND 17TH 19TH 31ST IN S 25TH 27TH 33RD 35TH BALBOA Richmond Extension MC CL A 24TH 26TH 32ND ANZA SPRECKELS LAKE LA 20TH 30TH GEARY 34TH 37TH 36TH 39TH 38TH 41ST 40TH 42ND 44TH 43RD 46TH 45TH O F 21ST 23RD R NO CLEMENT ANZA C HA IN 11TH HO SHORE VIEW POINT LO BOS CALIFORNIA 28TH 29TH OF SEA VIEW LAKE Appendix A Project Data Sheets AWSS Project ID Project Name 26 Sutro Connection and PS Deficiency ID Need D52 System supply is limited to the existing reservoir and tanks, Pump Station No. 1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply to the Twin Peaks Zone is required to meet fire demands. Project Objective/Benefit This project would develop an additional supply of water to the AWSS Twin Peaks Zone. Assumptions and Unknowns The preferred project is a connection from Sutro Reservoir into AWSS, including an air gap Description, Design/Sizing Criteria into a wet well, a new pump station and pipeline to connection into AWSS on Clarendon Ave. - ~300 LF of 20 inch pipe. Install a new pump station located adjacent to the existing MWSS pump station, 10,000 gpm at 87 psi. Confirm sizing using hydraulic model. Subsequent planning can consider alternatives including a direct connection from Summit Reservoir to the AWSS (piping down La Avanzada Ave or other route), or a Lake Honda Pump Station. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $2,234,375 $11,618,750 $13,853,125 $10,151 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 1 300 51 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 26 Sutro Connection and PS Assumptions Pump station is in landscaped area owned by CCSF. Need to confirm no environmental impacts. Assume 5' wide trench, 5' deep, 2' native backfill. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.7 23,000 250 300 0.9 CCSF - SFPUC (pump station) and DPW (Pipeline in Street) Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Within existing SFPUC facilities, street - residential and commercial Community Lane closures during construction, other traffic impacts along ~1 block of residential zoned street. Disposal of excavation spoils associated with connector pipeline, other construction impacts. Pump station construction would be adjacent to existing SFPUC facility, likely would require removal and modification of landscaping. 52 of 62 W CRE S TL INE PARKRID GE GLADEVIEW EA KS V CITY IEW MID C C RES T LONGVIEW ROC KAW AY UL L O A RA SY DN EY TA NI UN UA N J AM EV FOWLER ED ELY 03 N 9 Y SS L HI L GE D 800 EFeet Z ID O A RC I SQ VA HERNAN DE Z UE GA C ER M WOODSIDE ETA IS E UO RQ TU BAL C ED S RE TE ± G0 RA 200 400 NV I LL E A TOL PO R E HN UG HA OS ITA DOR ANTE S N EY A W L E L D E AG SUNV IEW A AD AS TE N STARVIEW DELLBROOK A ELA LO TE C MAR CO PACH E SO AZ PL KNOLLVIEW ES OLYMPIA Sutro Reservoir PANORAMA AR A ND N A TU R VILLA CLAYTON I EW RV A M NP S IE NV EE GR D ALTON LOPEZ C W W IE RV I LA HO LI VEN M IE RV FA LOR I GLENVIEW NA GU LA OO OO N PAL O ALTO TW I JO H OD AS HW CC SKYVIE W AQUA VISTA BE HR NS T O NE FO O IRW BLA E FO RE ST KN OL L K OA K PA R MONT WOODH AVEN GLE NHA VEN RA SAINT GERMAIN R P HE ISTO CHR CRES T WARREN K LA ST RE ON O ND TR LARE U C S MOUNTAIN SPRING H LA A VAN ZA D A 06TH 07TH LEY K OA P OL AD WN CRO LOCKS A MORAG BEL GRAVE CE LAWTON T RS HU COLE N STANYA 05TH UPP ER SER VI Appendix A Project Data Sheets AWSS Project ID Project Name 27 University Mound Reservoir Deficiency ID Need D52 System supply is limited to the existing reservoir and tanks, Pump Station No.1 and Pump Station No. 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. Project Objective/Benefit This project would install an air gapped booster pump station located at the existing Alemany Pump Station site to pump potable water stored at University Mound Reservoir into the AWSS lower zone. Assumptions and Unknowns Install a connection and pump station to deliver water from University Mound Reservoir into Description, Design/Sizing Criteria the AWSS (approximate location of piping down Bacon from Hamilton St. until San Bruno Ave.) Tie into proposed Silver extension- ~2100' of 20 inch Pipe Install a new booster pump station at University Mound, likely at existing Alemany Pump Station site. Pump to 492' from 172'. 140 psi @10,000 gpm Subsequent planning can consider alternatives including a tank in McLaren Park, or Balboa Reservoir. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $2,770,625 $14,407,250 $17,177,875 $12,744 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 1 2100 53 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 27 University Mound Reservoir Assumptions Pump station portion is within University Mound site. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.7 21,000 1,750 2,100 0.8 CCSF - SFPUC (pump station) and DPW (Pipeline in Street) Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Within existing SFPUC facilities, street - residential and commercial Community Lane closures during construction, other traffic impacts along ~8 block of residential zoned street. Disposal of excavation spoils associated with connector pipeline, other construction impacts. Pump station construction would be adjacent to existing SFPUC facility, likely would require removal and modification of landscaping. 54 of 62 KE IT H OP N 10 HWY SPA RTA NO 1 01 HWY S SEL R CRA NE WA RE RE SHO D BAY OUN TH B S OU 101 HWY S BR U E YOK HOL H BIS H O N T MOU DO I BOW SALINA S KE Y T DAR LEY JOHN F SHEL BY COL ALD E I-280 N BRU D BY COL MIL L O 101 T HWY ON 1 01 S SAN AR GIR N WAY ORD PH E LP S TA VES HWY EN E O CET DEL TA QU IN T M AD D UX A TI IRA ELM ND TING N YOK HOL I LTO HA M Y LSE WOO PRIN E YAL E QU IN O SC D AR DY LE OAK S SEL T T GOE RS E E Y OK HOL E SOM S BR U U BO RTH NO 01 TON UT H DOIN BOW TMO DAR BY COL N T DG E F 1 S OF ERV IN T ELM IRA CHARTER Y1 HW ELD NEV BAR S BO YL DO IN BO W M UIR DUNS Y COLB ITY E RS UNIV O CET PRIN ERS AMH B RI CAM AN KE NY DE WIL IT VIS AD ST E OLM GHT DWI EG BE R T E YAL TIO GA 800 Feet ION AC ON BAC ES S ± 200 400 0 S ROW BUR KN HAR E WIL D ND LA WAY D WAR MAN SEL L N TO FEL NE LA D TE A S OLM Y EEN SW PAU L University Mound ND LA WAY N IMA SILL D ON RNT T HO BA NC RO CA FT RR OL L TULANE ER SILV ALEMANY EN GAV FOLSOM GATES RT H SW O ELL E HAL TH BOUND I-2 80 NOR RIC R KA S I LA IS Y AN ND EM AL OU 101 HB T WY H U O SO 0T 80 I-28 I-2 Appendix A Project Data Sheets AWSS Project ID Project Name 28 Sunset Reservoir Connection and PS Deficiency ID Need D52 System supply is limited to the existing reservoir and tanks, Pump Station 1 and Pump Station 2 and focuses on the northeast quadrant of the City. Additional supply to the Upper Zone is required to meet fire demands. Project Objective/Benefit This project would install an air gapped booster pump station located at the existing Sunset Reservoir to pump potable water stored in Sunset Reservoir into the AWSS Upper Zone. Assumptions and Unknowns Install ~1600 LF of 20" pipe. to connect Sunset Reservoir into the AWSS (piping down 28th Description, Design/Sizing Criteria Ave. from Pacheco to Noriega)Sunset booster pump to 586' (from 355'), 100 psi @ 10,000 gpm Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $2,612,500 $13,585,000 $16,197,500 $12,351 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 1 1600 55 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 28 Sunset Reservoir Connection and PS Assumptions Pump station portion is within Sunset Reservoir site. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 1.7 16,000 1,333 1,600 0.6 CCSF - SFPUC (pump station) and DPW (Pipeline in Street) Streets subjected to significant duration closures Land Use Types Permitting Geotechnical Environmental Within existing SFPUC facilities, street - residential and commercial Community Lane closures during construction, other traffic impacts along ~2 blocks of residential zoned streets. Disposal of excavation spoils associated with connector pipeline, other construction impacts. Pump station construction would be adjacent to existing SFPUC facility, likely would require removal and modification of landscaping. 56 of 62 W CRE S TL INE PARKRID GE GLADEVIEW EA KS V CITY IEW MID C C RES T LONGVIEW ROC KAW AY UL L O A RA SY DN EY TA NI UN UA N J AM EV FOWLER ED ELY 03 N 9 Y SS L HI L GE D 800 EFeet Z ID O A RC I SQ VA HERNAN DE Z UE GA C ER M WOODSIDE ETA IS E UO RQ TU BAL C ED S RE TE ± G0 RA 200 400 NV I LL E A TOL PO R E HN UG HA OS ITA DOR ANTE S N EY A W L E L D E AG SUNV IEW A AD AS TE N STARVIEW DELLBROOK A ELA LO TE C MAR CO PACH E SO AZ PL KNOLLVIEW ES OLYMPIA Sutro Reservoir PANORAMA AR A ND N A TU R VILLA CLAYTON I EW RV A M NP S IE NV EE GR D ALTON LOPEZ C W W IE RV I LA HO LI VEN M IE RV FA LOR I GLENVIEW NA GU LA OO OO N PAL O ALTO TW I JO H OD AS HW CC SKYVIE W AQUA VISTA BE HR NS T O NE FO O IRW BLA E FO RE ST KN OL L K OA K PA R MONT WOODH AVEN GLE NHA VEN RA SAINT GERMAIN R P HE ISTO CHR CRES T WARREN K LA ST RE ON O ND TR LARE U C S MOUNTAIN SPRING H LA A VAN ZA D A 06TH 07TH LEY K OA P OL AD WN CRO LOCKS A MORAG BEL GRAVE CE LAWTON T RS HU COLE N STANYA 05TH UPP ER SER VI Appendix A Project Data Sheets AWSS Project ID Project Name 29 New Bay Suction Connections Deficiency ID Need D52 System supply is limited to the existing reservoir and tanks, Pump Station 1 and Pump Station 2 and focuses on the northeast quadrant of the City. Additional supply is required to meet fire demands. Project Objective/Benefit This project would add 10 new suction connections along the bay in locations not currently served by the 35 existing suction connections to provide additional firefighting supplies as a supplemental source. Water could be used by fire engines to fight fires locally or pumped into AWSS. Assumptions and Unknowns Install 10 new suction connections located along the waterfront in locations not served by Description, Design/Sizing Criteria the existing suction connections. See map for preliminary locations Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $660,000 $3,432,000 $4,092,000 $43,720 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 10 57 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 29 New Bay Suction Connections Assumptions Assume 20'x20' construction footprint for each suction manifold. Microtunnel 50' to get to bay. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 2.2 4,000 53 0 0.2 CCSF - Port Streets subjected to significant duration closures Waterfront - Recreational, Commercial, Industrial Land Use Types Permitting Geotechnical Environmental Waterfront - recreational, commercial, Industrial Community Varies by site. Possible visual and recreational impacts associated with construction staging. Disposal of excavation spoils, other construction impacts. Impacts to Bay are possible associated with installation of seawater suction. 58 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 30 Pipeline Replacement Program, Phase 1 Deficiency ID Need D12, D42, D53 A long-term pipeline replacement plan should be developed based on ongoing inspection, testing and analysis. The 77 miles of original pipeline construction should be addressed within the next 50 years. Project Objective/Benefit Replace the existing AWSS pipeline and appurtenant structures based on the findings of ongoing inspection, testing, and analysis. Assume a replacement rate of 1.5 miles per year, associated with replacing the entire system over a 50 year period. Assumptions and Unknowns Initial priorities should include the 98 locations where portions of the AWSS pipelines are constructed through sewer mains, and pipeline sections in the infirm areas (in particular, infirm area hydrants at elbows and branches were significant problems during the Loma Prieta earthquake.) Condition assessment program has not yet been initiated. Replacement priorities and rate will be confirmed based on program findings. Consider pipeline replacement with same diameter ductile iron, or alternately slip lining Description, Design/Sizing Criteria rehabilitation. For areas of high AWSS pipe density consider backboning of system by abandoning some lines through areas that are adequately served by nearby upgraded pipelines. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $24,750,000 $128,700,000 $153,450,000 $0 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 59 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 30 Pipeline Replacement Program, Phase 1 Assumptions Assume replace pipelines with new, similar impacts to new pipeline. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 8.4 1,953,600 162,800 195,360 378.1 CCSF - DPW (Street) Streets subjected to significant duration closures Varies, commercial and residential streets with existing AWSS pipelines. Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along residential and commercial zoned streets. Disposal of excavation spoils, other construction impacts. Most trenching would be to remove and replace existng pipelines. Some disturbances of adjacent soils likely. 60 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name 31 Pipeline Replacement Program, Phase 2 Deficiency ID Need D53 A long-term pipeline replacement plan should be developed based on ongoing inspection, testing and analysis. The 77 miles of original pipeline construction should be addressed within the next 50 years. Project Objective/Benefit Replace the existing AWSS pipeline and appurtenant structures based on the findings of ongoing inspection, testing, and analysis. Assume a replacement rate of 1.5 miles per year, associated with replacing the entire system over a 50 year period. Assumptions and Unknowns Condition assessment program has not yet been initiated. Replacement prioorities and rate will be based on program finidngs. Consider pipeline replacement with same diameter ductile iron, or alternately slip lining Description, Design/Sizing Criteria rehabilitation. For areas of high AWSS pipe density consider backboning of system by abandoning some lines through areas that are adequately served by nearby upgraded pipelines. Costs (2012$) Soft Costs Construction Cost Total Capital Cost Annual O&M Costs $24,750,000 $128,700,000 $153,450,000 $0 Facilities PS at New Site (Ea.) PS at Exist. Site (Ea.) New SCADA (Ea.) New Motorized Actuator for GV (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New Pipeline (LF) New Suction Connection (Ea.) New Cistern (Ea.) 61 of 62 Appendix A Project Data Sheets AWSS Project ID Project Name Impacts 31 Pipeline Replacement Program, Phase 2 Assumptions Assume replace pipelines with new, similar impacts to new pipeline. Construction Duration (years) Project Footprint new disturbance (sf) Volume of soil to be disposed (CY) LF of pipe to be installed in City streets Cumulative Impacts (acre-year) Right of Way 8.4 2,112,000 176,000 211,200 408.5 CCSF - DPW (Street) Streets subjected to significant duration closures Varies, commercial and residential streets with existing AWSS pipelines. Land Use Types Permitting Geotechnical Environmental Street - residential and commercial Community Lane closures during construction, other traffic impacts along residential and commercial zoned streets. Disposal of excavation spoils, other construction impacts. Most trenching would be to remove and replace existng pipelines. Some disturbances of adjacent soils likely. 62 of 62 Appendix B: Cost Information B.1 Project Cost Estimates B.2 Annual Operation & Maintenance Costs B.3 Program Alternative Capital Costs B.4 Life Cycle Costs CS-199 AWSS Facilities Preliminary Options Study Task 11 B.1 Project Cost Estimates Appendix B.1 Project Cost Estimates Description, Design/Sizing Criteria CS-199 AWSS Projects for cost estimating CM West Worksheet #1 10/20/2012 Project Project Name Quantity Unit ID 1 Motorization and Addition of Seismic Switches on Gate Valves 16"New Automated Gate Valve,Battery, Vault 1 EA 14"New Automated Gate Valve,Battery, Vault 1 EA 12"New Automated Gate Valve,Battery, Vault 1 EA Traffic control 3 SITES Unit Price $200,000 $185,000 $175,000 $25,000 Ballpark $ (ACS) Subtotals $200,000 $185,000 $175,000 $75,000 $635,000 2 4th Street Bridge Connection 12" Hose - furnish & install underwater 750 LF $1,250 $937,500 $937,500 3 PS1 Tunnel Upgrade 36" HDPE sleeve inside tunnel Repair at Seawall Concrete repairs in tunnel 30 1 1100 LF LS LF $6,667 $580,000 $300 $200,010 $580,000 $330,000 $1,110,010 4 Twin Peaks Outlet Connection 20" pipe 20" Automated Gate Valve,Battery, Vault 20" Tee connection Traffic control 20 1 2 1 LF EA EA SITE $1,000 $225,000 $50,000 $25,000 $20,000 $225,000 $100,000 $25,000 $370,000 5 Jones St Tank Bypass Valves SCADA Control to existing gate valves Two sets of 5x12" gate valves per bypass gates 10 10 EA EA $75,000 $75,000 $750,000 $750,000 $1,500,000 6 Repair Suction Connections Replace Suction connection assembly Rehabilitate Suction connection assembly in place 10 EA $85,000 $850,000 25 EA $20,000 $500,000 $1,350,000 7 SCADA Improvements New SCADA Control systems - 5 plants SCADA Control at backup communications systems SCADA Control at Valve stations SCADA changes at Operations center Upgrade Wonderware & hardware 5 EA $120,000 $600,000 3 EA $80,000 $240,000 2 1 1 EA LS LS $80,000 $520,000 $30,000 $160,000 $520,000 $30,000 $1,550,000 8 Fireboat Manifold Rehabilitation & Replacement Relocate Fireboat Manifold Assembly Minor servicing of Fireboat Manifold Assembly 3 2 EA EA $50,000 $10,000 $150,000 $20,000 $170,000 9 Pipeline Investigations and Repairs 10 Reliability Upgrades at Facilities Perform repairs & improve existing facilities Twin Peaks Reservoir Ashbury Tank Jones Street Tank Pump Station #1 Pump Station #2 $4,000,000 $4,000,000 5 1 1 1 1 1 EA EA EA EA EA EA $2,500,000 $2,000,000 $4,500,000 $500,000 $500,000 $10,000,000 $2,500,000 $2,000,000 $4,500,000 $500,000 $500,000 $10,000,000 1 of 4 Appendix B.1 Project Cost Estimates Project Project Name Quantity ID 11 Cistern Repair and Construct 27 New Cisterns, Ph. 1 Install New Cisterns 30 Cost Breakdown for 1 New Cistern: Traffic control Remove existing pavement and concrete Install permanent shoring system Relocate existing utility allowance Dewatering allowance Excavate & dispose class 3 hazmat material Construct Concrete Cistern Reinforcement Copper waterstop Brass steps Manholes Balast block ring Concrete under balast blocks Backfill Waterproof Coating inside new Cistern New pavement and site concrete sections New pavement striping / final clean-up Repair and line existing Cisterns Unit EA Unit Price Ballpark $ (ACS) $1,000,000 $30,000,000 1 1,300 3,200 1 1 660 146 21,000 100 19 2 300 4 116 2,780 1,300 1 SITE SF SF LS LS CY CY LB LF EA EA BLKS. CY CY SF SF LS $50,000 $15 $40 $125,000 $25,000 $150 $2,500 $1 $100 $500 $10,000 $40 $2,500 $150 $10 $35 $7,110 $50,000 $19,500 $128,000 $125,000 $25,000 $99,000 $365,000 $29,190 $10,000 $9,500 $20,000 $12,000 $10,000 $17,400 $27,800 $45,500 $7,110 0 EA $50,000 $0 Subtotals $30,000,000 12 Cistern Repair and Construct 19 New Cisterns, Ph. 1 Install New Cisterns 15 Repair and line existing Cisterns 0 EA EA $1,000,000 $50,000 $15,000,000 $0 $15,000,000 13 Construct 33 New Cisterns, Phase 2 Install New Cisterns 33 EA $1,000,000 $33,000,000 $33,000,000 14 Construct 30 New Cisterns, Phase 3 Install New Cisterns 30 EA $1,000,000 $30,000,000 $30,000,000 15 Construct 90 New Cisterns, Phase 4 Install New Cisterns 90 EA $1,000,000 $90,000,000 $90,000,000 16 Construct 90 New Cisterns, Phase 5 Install New Cisterns 90 EA $1,000,000 $90,000,000 $90,000,000 17 Construct 90 New Cisterns, Phase 6 Install New Cisterns 90 EA $1,000,000 $90,000,000 $90,000,000 18 Balboa Tank and Booster PS Install underground tank under parking lot Install booster pump station 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 1 1 1450 1 1 3 LS EA LF EA EA EA $10,000,000 $10,000,000 $1,000 $75,000 $225,000 $25,000 $10,000,000 $10,000,000 $1,450,000 $75,000 $225,000 $75,000 $21,825,000 2 of 4 Appendix B.1 Project Cost Estimates Project Project Name ID 19 Alemany Extension Pipeline 16" pipe 16" Standard Gate Valve Assembly 16"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 16"line Quantity Unit 13500 13 2 27 LF EA EA EA Unit Price $800 $65,000 $200,000 $20,000 Ballpark $ (ACS) Subtotals $10,800,000 $845,000 $400,000 $540,000 $12,585,000 20 Silver Extension Pipeline 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 21500 21 3 43 LF EA EA EA $1,000 $75,000 $200,000 $25,000 $21,500,000 $1,575,000 $600,000 $1,075,000 $24,750,000 21 Geneva Extension Pipeline 16" pipe 16" Standard Gate Valve Assembly 16"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 16"line 20200 20 3 41 LF EA EA EA $800 $65,000 $200,000 $20,000 $16,160,000 $1,300,000 $600,000 $820,000 $18,880,000 22 Lake Merced Pump Station Install additional pump capacity to lift water 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 1 7200 7 1 15 LS LF EA EA EA $10,000,000 $1,000 $75,000 $225,000 $25,000 $10,000,000 $7,200,000 $525,000 $225,000 $375,000 $18,325,000 23 Sunset Extension Pipeline 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 22000 22 3 44 LF EA EA EA $1,000 $75,000 $225,000 $25,000 $22,000,000 $1,650,000 $675,000 $1,100,000 $25,425,000 24 Sunset Extension Rezoning Pipeline 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 1500 1 1 3 LF EA EA EA $1,000 $75,000 $225,000 $25,000 $1,500,000 $75,000 $225,000 $75,000 $1,875,000 25 Richmond Extension Pipeline 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 22400 22 3 45 LF EA EA EA $1,000 $75,000 $225,000 $25,000 $22,400,000 $1,650,000 $675,000 $1,125,000 $25,850,000 3 of 4 Appendix B.1 Project Cost Estimates Project Project Name ID 26 Sutro Connection and PS New Pump Station 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line Quantity Unit 1 300 1 1 1 EA LF EA EA EA Unit Price $7,500,000 $1,000 $75,000 $225,000 $25,000 Ballpark $ (ACS) Subtotals $7,500,000 $300,000 $75,000 $225,000 $25,000 $8,125,000 27 University Mound Reservoir New Pump Station 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 1 2100 1 1 7 EA LF EA EA EA $7,500,000 $1,000 $75,000 $225,000 $25,000 $7,500,000 $2,100,000 $75,000 $225,000 $175,000 $10,075,000 28 Sunset Reservoir Connection and PS New Booster Pump 20" pipe 20" Standard Gate Valve Assembly 20"New Automated Gate Valve,Battery, Vault High Pressure Fire Hydrant Assembly to 20"line 1 1600 1 1 4 EA LF EA EA EA $7,500,000 $1,000 $75,000 $225,000 $25,000 $7,500,000 $1,600,000 $75,000 $225,000 $100,000 $9,500,000 29 New Bay Suction Connections Suction connection assembly 10 EA $240,000 $2,400,000 $2,400,000 30 Pipeline Replacement Program, Phase 1 Year 1 to 10 - 8" to 20" pipe Yr.1 to10 - '8" to 20" Standard Gate Valve Assembly Yr.1 to10 - Automated Gate V,Battery, Vault Year 1 to 10 - HP Fire Hydrant Assembly 79200 LF $1,000 $79,200,000 80 EA $65,000 $5,200,000 12 160 EA EA $200,000 $20,000 $2,400,000 $3,200,000 $90,000,000 31 Pipeline Replacement Program, Phase 2 Year 11 to 20 - 6" to 20" pipe Yr.11 to20 - '6" to 20" Standard Gate Valve Assembly Yr.11 to20 - Automated Gate V,Battery, Vault Year 11 to 20 - HP Fire Hydrant Assembly 79200 LF $1,000 $79,200,000 80 EA $65,000 $5,200,000 12 160 EA EA $200,000 $20,000 $2,400,000 $3,200,000 $90,000,000 4 of 4 B.2 Annual Operation & Maintenance Costs NBA ENGINEERING INC. San Francisco ♦ Oakland ♦ Los Angeles Assumptions and Exclusions: There is no gas fired equipment in this project that requires additional maintenance. Electrical data energy usage given to NBA by SFPUC July 1, 2012 to July 31, 2012 was used for similar facilities to calculate the energy usage for the added facilities. Assumptions have been made to use $ 600 per month per year for each new pump station and $15 per month for each motorized valve. Energy usage for each new pump station includes pumps, fans and lights. The hourly rate that was used for calculations are based on information that was given by Bill Teahan of SFPUC as follows: Gateman for valve operations $ 89.30 per hour plus $20 per hour for additional cost for vehicle. Plumber (for hydrant flushing) $ 79.17 per hour plus $ 20 per hour for additional cost for the vehicle. Assume one hydrant per 500 ft. of new pipes. No hydrant will be provided for the pipe replacements. Each hydrant requires 2 man hours per year, for flushing and another two man hours per year for each valve. Maximum h.p. for each pump at each pump station is 1,000 h.p. There is also one standby at each station. Assumed cost of flushing pipe line is about $0.35 per LF per year plus $20.00 per hour for truck per Bill Teahan. No cost was included for getting permit that is required for some of these sites since there is a full time staff on board to take care of this matter. No cost for any software maintenance is required since there is a full time IT staff on board. The cistern maintenance will happen 4 times a year, 4 man hours (2 people 2 hours each) manual drain and fill. No SCADA, automatic fill and back flow preventer is not included in this figure. For new bay suction connection maintenance including back flush, taking off caps and grease them and traffic control use 40 man hours per site per year per Bill Teahan. Diesel generator needs to be certified each year per bay area air quality management district. There will be routine maintenance every other month for 4 hours per year each one person for diesel fuel line vacuum and generator exercising maintenance per Richard Yee of SFPUC. Assume 1 hour per pump per every three months (4 hours/year) for each pump in each pump station for maintenance and exercising per Richard Yee of PUC. Assume 20 hours per vault per year for below grade vault maintenance. For project no. 5 since it is one site with 10 valves and 10 SCADA use 12 man hours per year for all the valves and SCADA connections. Use 2 man hours per motorized valve per year and 2 man hours per SCADA per year maintenance. So for motorized valve, use 4 man hours per year and for manual valve use 2 man hours per year. No painting cost for hydrants is included in the above fee. Assume every time you have SCADA you have battery. The maintenance for the battery is 2 man hours per year. The maintenance for the project no. 9 due to reliability upgrades is as follows: 2 new electrically actuated valves on each 4 fore bays sluice gate for Twin Peaks and J Jones Reservoirs that connects the new 16 inch new bypass fill line to provide filling 897 Hyde Street San Francisco, California 94109 Telephone (415) 202-9840 Facsimile (415) 202-9838 www.nbaeng.com -1- NBA ENGINEERING INC. San Francisco ♦ Oakland ♦ Los Angeles capability at each reservoir fore bay. Also remote SCADA control shall be provided for each. Use 2 man hours per valve and 2 man hours per SCADA. Maintenance for new Jones St. tank transfer switch for backup power will be 2 hours per year. No added maintenance cost for redesigning the electric redistribution for Jones Reservoir. No additional backup power is required for pump station 1 & 2 of project no. 9. 897 Hyde Street San Francisco, California 94109 Telephone (415) 202-9840 Facsimile (415) 202-9838 www.nbaeng.com -2- AWSS Projec Project Name t ID 1 There are existing manually operated gate valves which would need to be retrofitted with a motorized operator, battery vault, and instrumentation. Alternately new valves could be located along the pipeline just outside of the Motorization and infirm zone. Addition of At each location, add additional below grade vault, Seismic Switches sidewalk pedestal, Monopole w/ antenna. Assume 5' deep on Gate Valves vault. Alternately could move actuator, batteries, etc. above grade to minimize soil disturbance when the site conditions allow. Utililze existing standard design. Trickle charged batteries. 800 mhz radio with VSAT backup. 2 4th Street Hose 3 PS1 Tunnel Upgrade 4 5 6 Description, Design/Sizing Criteria 3 New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New New Suction New Pipeline Connection Cistern (LF) (Ea.) (Ea.) 3 Install ~ 750 LF of 12 inch diameter hose connecting to the pipelines on either side of the 4th St. Bridge, and running in a trench at the bottom of the Bay. The bottom would be dredged and the hose buried, protected from boat anchors, and weighted to prevent buoyant lift. 750 The Pump Station 1 tunnel repair includes reinforcing the tunnel under the seawall footing as well as placing 3 foot diameter HDPE pipes upstream and downstream of the connection of the tunnel to the CSO box. Twin Peaks Outlet Install a short distance (~20 LF) of 20 inch pipe plus a 20 Connection inch gate valve. Tee connections into existing pipelines. Match outlet size from Twin Peaks West. Install motorized actuators and SCADA control to all 10 existing gate valves, including power supply and SCADA backup communications such that two gates at a time Jones St Tank would be slowly opened. There are two sets of 5 x 12" gate Bypass Valves valves each for the existing bypass gates. Confirm existing emergency generator has sufficent capacity for backup power. Repair Suction Connections Pump Pump New Station at Station at New Motorized New Site Existing SCADA Actuator (Ea.) Site (Ea.) (Ea.) (Ea.) O&M Hours/ year O & M Cost/ Year 72 $ 2 $ 0 2 10 10 Inspect and evaluate the condition of each of the 35 existing suction connections. As appropriate based on findings, perform repairs, replace, or relocate each suction connection as appropriate. Consider pressure requirements, fitting connections to fire trucks. Consider long term operability of each siphon given sedimentation. Consider replacement with HDPE or other alternate material which may have, but superior performance in a marine environment. 20 Page 1 of 4 $ $ 40 $ - 0 $ 8,945.40 $ 0 437.20 $ 4,372.00 Total 540.00 $ 416.94 $ 0 4 0 8,405.40 Enery Cost / Year 416.94 0 - $ 437.20 1,800.00 $ 6,172.00 0 0 AWSS Projec Project Name t ID 7 SCADA Improvements Description, Design/Sizing Criteria 1. Upgrade Pump Stations No. 1 and No.2 to add primary and backup SCADA connection and provide remote monitoring and control capabilities. 2. Upgrade five motorized valves to provide backup communications to radio (three at Twin Peaks Reservoir, Ocean Ave. at 280 East and Ocean Ave. at 280 West). Motorized actuators are already installed, need to install remote monitoring and control capabilities. 3. Add automation to the Bay and Van Ness gate valves, bringing the number of automated valves to 32 from 30. Complete automation including remote monitoring and control capabilities. 4. Upgrade obsolete Wonderware and replace hardware as necessary for all facilities. Pump Pump New Station at Station at New Motorized New Site Existing SCADA Actuator (Ea.) Site (Ea.) (Ea.) (Ea.) 9 New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New New Suction New Pipeline Connection Cistern (LF) (Ea.) (Ea.) O&M Hours/ year 18 O & M Cost/ Year $ Enery Cost / Year 1,967.40 0 Total $ 1,967.40 Inspect and evaluate the condition and seismic vulnerability of each of the five existing fireboat manifolds. As appropriate based on findings, perform repairs, replace, or relocate each fireboat manifold. Any facilities judged to be located on seismically unsafe piers should be relocated. 8 Manifolds could be relocated off the Piers, but need to consider bathymetry, access, etc. Fireboat Manifold Pier 22 1/2 is being rehabilitated by the Fire Department Rehabilitation & and can be considered seismically retrofitted for the Replacement purpose of this project. 0 0 0 0 Fort Mason - assume relocation of ~1200 LF of Pipe, recoating and flushing of manifold Fisherman's Wharf assume recoating and flushing only Islais Creek assume recoating and flushing only Pier 22 1/2 assume recoating and flushing only Pier 33 1/2 assume abandonment in place of existing pipe and manifold, construction of new manifold. 9 Reliability Upgrades at Facilities Perform repairs and other improvements at the following existing facilities: Twin Peaks Reservoir, Ashbury Tank, Jones Street Tank, Pump Station No 1, Pump Station No 2. Suggested repairs are listed as future work recommendations in the Task 2 TM, and will be developed in more detail in SFPUC Conceptual Engineering Reports associated with each listed facility (omitting items to be performed by other AWSS projects). Repairs include seismic anchorage, concrete repair, backup power, installation of flexible joints, electical and security upgrades. 12 Page 2 of 4 $ 4,550.00 $ 720.00 $ 5,270.00 AWSS Projec Project Name t ID 10 11 12 13 14 15 16 17 18 Description, Design/Sizing Criteria Pump Pump New Station at Station at New Motorized New Site Existing SCADA Actuator (Ea.) Site (Ea.) (Ea.) (Ea.) New Gate Valve (Ea.) New Tank/ Reservoir (Ea.) New New Suction New Pipeline Connection Cistern (LF) (Ea.) (Ea.) Install 90 cisterns in locations adjacent to areas of highest fire demand, as indicated on map in Task 11 TM. Reinforced concrete meeting standards for design earthquake so shall have higher reliability than older Cistern Expansion cisterns. and Repair Phase 1 Inspect all of the older brick cisterns to confirm repair scope. 10 existing cisterns have already been identified as likely candidates for repair, identified in a map in the Task 11 TM map. Install 351 additional cisterns in locations adjacent to areas Cistern Expansion of highest fire demand, as indicated on map in Task 11 TM. Reinforced concrete meeting standards for design Phase 2 earthquake so shall have higher reliability than older cisterns. Install a new underground tank situated under City College parking lot (north of Ocean Ave.)- Include booster pump station, 16,500 gpm at 152 psi (2,200 hp)- Approximately 1450 LF of 20 inch pipe. Install 13,500 LF of 16" pipe. Install hydrants and laterals to serve fire demands located Alemany along pipeline. Extension Install automated gate valves at connection points into Pipeline AWSS. Install 21,500 feet of 20 inch Pipe. Install hydrants and laterals to serve fire demands located Silver Extension along pipeline. Pipeline Install automated gate valves at connection points into AWSS. Install 20,200 LF of 16" pipe. Install hydrants and laterals to serve fire demands located Geneva Extension along pipeline. Pipeline Install automated gate valves at connection points into AWSS. Install additional pumping capacity at Lake Merced Pump Station to lift water from the lake into the AWSS, and optionally also an air gapped capability to lift from the MWSS. Evaluate reliability benefits, costs, other issues for Lake Merced optional connection to MWSS. Pump Station Pump sizing is 15,000 gpm at 200 psi (2,600 hp). Install approximately 7200 LF of 20 inch pipe to connect to the Sunset loop. Install 22,000 feet of 20 inch Pipe. Install new valving to separate Upper Zone from Twin Peaks Zone. Sunset Extension Install hydrants and laterals to serve fire demands located along pipeline. Pipeline Install automated gate valves at connection points into AWSS. Balboa Tank and Booster PS 1 1 O&M Hours/ year O & M Cost/ Year Enery Cost / Year 90 1440 $ 142,804.80 0 $ 142,804.80 351 5616 $ 556,938.72 0 $ 556,938.72 0 $ 6,952.40 1450 48 $ 6,952.40 Total 2 2 2 13500 174 $ 23,196.18 $ 360.00 $ 23,556.18 2 2 2 21500 270 $ 36,184.82 $ 360.00 $ 36,544.82 2 2 2 20200 252 $ 25,541.18 $ 360.00 $ 25,901.18 7200 96 $ 10,209.16 $ 7,200.00 $ 17,409.16 22000 276 $ 36,975.36 $ 360.00 $ 37,335.36 1500 12 $ 1,250.82 1 2 2 Sunset Extension Install ~1500 LF of 20 inch pipe along Ocean avenue from Rezoning Pipeline 19th Ave. to San Fernando Way. Page 3 of 4 2 0 $ 1,250.82 AWSS Projec Project Name t ID 19 Description, Design/Sizing Criteria Install 22,400 feet of 20 inch Pipe. Assumed route is along Anza St., 32nd Ave., and California St. Install hydrants and laterals to serve fire demands located along pipeline. Install automated gate valves at connection points into AWSS. The preferred project is a connection from Sutro Reservoir into AWSS, including an air gap into a wet well, a new pump station and pipeline to connection into AWSS on Clarendon Ave. - ~300 LF of 20 inch pipe. Sutro Connection Install a new pump station located adjacent to the existing MWSS pump station, 10,000 gpm at 87 psi (800 hp). and PS Confirm sizing using hydraulic model. Subsequent planning can consider alternatives including a direct connection from Summit Reservoir to the AWSS (piping down La Avanzada Ave or other route), or a Lake Honda Pump Station. Pump Pump New Station at Station at New Motorized New Site Existing SCADA Actuator (Ea.) Site (Ea.) (Ea.) (Ea.) Richmond Extension Pipeline O&M Hours/ year O & M Cost/ Year Enery Cost / Year Total $ 24,960.56 $ 360.00 $ 25,320.56 1 300 36 $ 2,951.10 $ 7,200.00 $ 10,151.10 21 Install a connection and pump station to deliver water from University Mound Reservoir into the AWSS (approximate location of piping down Bacon from Hamilton St. until San Bruno Ave.) University Mound Tie into proposed Silver extension- ~2100' of 20 inch Pipe Install a new booster pump station at University Mound, Reservoir likely at existing Alemany Pump Station site. Pump to 492' from 172'. 10,000 gpm @ 140 psi (1,300 hp) Subsequent planning can consider alternatives including a tank in McLaren Park, or Balboa Reservoir. 1 2100 44 $ 5,544.20 $ 7,200.00 $ 12,744.20 22 Install ~1600 LF of 20" pipe. to connect Sunset Reservoir Sunset Reservoir into the AWSS (piping down 28th Ave. from Pacheco to Connection and Noriega)Sunset booster pump to 586' (from 355'), 10,000 gpm @ PS 100 psi (900 hp) 1 1600 42 $ 5,150.60 $ 7,200.00 $ 12,350.60 23 West Side Storage Tank 17500 140 $ 14,862.90 0 $ 14,862.90 400 $ 43,720.00 0 $ 43,720.00 $ 991,051.74 Install a 750,000 gallon water storage tank, and all appurtenances (not including land), Install 17,500 LF of 16 inch pipe. Tank must connect to new AWSS pipelines proposed for area as well as existng AWSS. 2 New New Suction New Pipeline Connection Cistern (LF) (Ea.) (Ea.) 276 24 2 New Tank/ Reservoir (Ea.) 22400 20 2 New Gate Valve (Ea.) 1 New Bay Suction Install 10 new suction connections located along the Connections waterfront in locations not served by the existing suction connections. See map for preliminary locations 10 TOTAL 9,270.00 $ 957,391.74 $ 33,660.00 Page 4 of 4 B.3 Program Alternative Capital Costs Alternative A Project Cost Input ID 1 2 3 4 5 6 7 8 9 10 11 29 17 18 19 20 12 21 22 23 30 13 24 25 28 14 15 16 26 27 Project Name Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Balboa Tank and Booster PS Alemany Extension Pipeline Silver Extension Pipeline Geneva Extension Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Sutro Connection and PS New Bay Suction Connections Construct 351 +/- New Cisterns, Phase 1 Construct 351 +/- New Cisterns, Phase 2 Construct 351 +/- New Cisterns, Phase 3 University Mound Reservoir Sunset Reservoir Connection and PS Estimating Assumptions Annual Inflation Rate Design Cost, % of Construction Design effort contingency Years of inflation Design contingency Construction contingency Soft Cost $158,750 $234,250 $277,503 $0 $375,000 $337,500 $387,500 $100,000 $1,000,000 $2,500,000 $6,750,000 $6,600,000 $5,456,250 $3,146,250 $6,187,500 $4,720,000 $4,750,000 $4,581,250 $6,356,250 $468,750 $6,600,000 $0 $6,462,500 $2,031,250 $214,285 $0 $0 $0 $0 $0 3% 25% 10% 2 30% 10% Design Effort Contingency $15,875 $23,425 $27,750 $0 $37,500 $33,750 $38,750 $10,000 $100,000 $250,000 $675,000 $660,000 $545,625 $314,625 $618,750 $472,000 $475,000 $458,125 $635,625 $46,875 $660,000 $0 $646,250 $203,125 $21,429 $0 $0 $0 $0 $0 Subtotal - Soft Costs $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,750,000 $7,425,000 $7,260,000 $6,001,875 $3,460,875 $6,806,250 $5,192,000 $5,225,000 $5,039,375 $6,991,875 $515,625 $7,260,000 $0 $7,108,750 $2,234,375 $235,714 $0 $0 $0 $0 $0 $76,664,266 Construction Cost $635,000 $937,000 $1,110,010 $0 $1,500,000 $1,350,000 $1,550,000 $400,000 $4,000,000 $10,000,000 $27,000,000 $26,400,000 $21,825,000 $12,585,000 $24,750,000 $18,880,000 $19,000,000 $18,325,000 $25,425,000 $1,875,000 $26,400,000 $0 $25,850,000 $8,125,000 $857,140 $0 $0 $0 $0 $0 $278,779,150 Design Contingency $190,500 $281,100 $333,003 $0 $450,000 $405,000 $465,000 $120,000 $1,200,000 $3,000,000 $8,100,000 $7,920,000 $6,547,500 $3,775,500 $7,425,000 $5,664,000 $5,700,000 $5,497,500 $7,627,500 $562,500 $7,920,000 $0 $7,755,000 $2,437,500 $257,142 $0 $0 $0 $0 $0 Subtotal $825,500 $1,218,100 $1,443,013 $0 $1,950,000 $1,755,000 $2,015,000 $520,000 $5,200,000 $13,000,000 $35,100,000 $34,320,000 $28,372,500 $16,360,500 $32,175,000 $24,544,000 $24,700,000 $23,822,500 $33,052,500 $2,437,500 $34,320,000 $0 $33,605,000 $10,562,500 $1,114,282 $0 $0 $0 $0 $0 Construction Cost w/o Inflation $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $31,209,750 $17,996,550 $35,392,500 $26,998,400 $27,170,000 $26,204,750 $36,357,750 $2,681,250 $37,752,000 $0 $36,965,500 $11,618,750 $1,225,710 $0 $0 $0 $0 $0 $398,654,185 O&M Cost $8,945 $417 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $25,321 $10,151 $43,720 A B C 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 24 13 25 17 18 15 16 20 22 23 21 15 16 13 17 18 19 14 19 $298,514 14 Alternative B Project Cost Input ID 1 2 3 4 5 6 7 8 9 10 11 29 19 26 22 23 12 21 27 30 25 13 24 18 20 28 14 15 16 17 Project Name Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline New Bay Suction Connections Construct 351 +/- New Cisterns, Phase 1 Construct 351 +/- New Cisterns, Phase 2 Construct 351 +/- New Cisterns, Phase 3 Balboa Tank and Booster PS Soft Cost $158,750 $234,250 $277,503 $0 $375,000 $337,500 $387,500 $100,000 $1,000,000 $2,500,000 $6,750,000 $6,600,000 $6,187,500 $2,518,750 $6,356,250 $468,750 $3,750,000 $4,581,250 $2,375,000 $6,600,000 $2,031,250 $0 $6,462,500 $3,146,250 $4,720,000 $600,000 $0 $0 $0 $0 Design Effort Contingency $15,875 $23,425 $27,750 $0 $37,500 $33,750 $38,750 $10,000 $100,000 $250,000 $675,000 $660,000 $618,750 $251,875 $635,625 $46,875 $375,000 $458,125 $237,500 $660,000 $203,125 $0 $646,250 $314,625 $472,000 $60,000 $0 $0 $0 $0 Subtotal - Soft Costs $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,750,000 $7,425,000 $7,260,000 $6,806,250 $2,770,625 $6,991,875 $515,625 $4,125,000 $5,039,375 $2,612,500 $7,260,000 $2,234,375 $0 $7,108,750 $3,460,875 $5,192,000 $660,000 $0 $0 $0 $0 $75,369,803 Construction Cost $635,000 $937,000 $1,110,010 $0 $1,500,000 $1,350,000 $1,550,000 $400,000 $4,000,000 $10,000,000 $27,000,000 $26,400,000 $24,750,000 $10,075,000 $25,425,000 $1,875,000 $15,000,000 $18,325,000 $9,500,000 $26,400,000 $8,125,000 $25,850,000 $12,585,000 $18,880,000 $2,400,000 $274,072,010 Design Contingency $190,500 $281,100 $333,003 $0 $450,000 $405,000 $465,000 $120,000 $1,200,000 $3,000,000 $8,100,000 $7,920,000 $7,425,000 $3,022,500 $7,627,500 $562,500 $4,500,000 $5,497,500 $2,850,000 $7,920,000 $2,437,500 $0 $7,755,000 $3,775,500 $5,664,000 $720,000 $0 $0 $0 $0 Subtotal $825,500 $1,218,100 $1,443,013 $0 $1,950,000 $1,755,000 $2,015,000 $520,000 $5,200,000 $13,000,000 $35,100,000 $34,320,000 $32,175,000 $13,097,500 $33,052,500 $2,437,500 $19,500,000 $23,822,500 $12,350,000 $34,320,000 $10,562,500 $0 $33,605,000 $16,360,500 $24,544,000 $3,120,000 $0 $0 $0 $0 Construction Cost w/o Inflation $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $35,392,500 $14,407,250 $36,357,750 $2,681,250 $21,450,000 $26,204,750 $13,585,000 $37,752,000 $11,618,750 $0 $36,965,500 $17,996,550 $26,998,400 $3,432,000 $0 $0 $0 $0 $391,922,974 O&M Cost $8,945 $417 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $17,409 $12,351 $0 $10,151 $25,321 $23,556 $25,901 A B C 1 2 3 4 5 6 7 8 9 10 11 12 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 1 2 3 4 5 6 7 8 9 10 11 12 19 20 17 18 21 24 22 23 14 16 14 15 16 13 17 18 19 13 $249,136 Alternative C Project Cost Input ID 1 2 3 4 5 6 7 8 9 10 11 29 28 12 30 13 14 15 16 19 26 22 23 21 27 25 24 18 20 17 Project Name Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 New Bay Suction Connections Construct 90 +/- New Cisterns, Phase 2 Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Construct 351 +/- New Cisterns, Phase 1 Construct 351 +/- New Cisterns, Phase 2 Construct 351 +/- New Cisterns, Phase 3 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Lake Merced Pump Station Sunset Reservoir Connection and PS Sutro Connection and PS Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline Balboa Tank and Booster PS Soft Cost $158,750 $234,250 $277,503 $0 $375,000 $337,500 $387,500 $100,000 $1,000,000 $2,500,000 $6,750,000 $6,600,000 $214,285 $7,500,000 $6,600,000 $7,500,000 $29,250,000 $29,250,000 $29,250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Design Effort Contingency $15,875 $23,425 $27,750 $0 $37,500 $33,750 $38,750 $10,000 $100,000 $250,000 $675,000 $660,000 $21,429 $750,000 $660,000 $750,000 $2,925,000 $2,925,000 $2,925,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Subtotal - Soft Costs $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,750,000 $7,425,000 $7,260,000 $235,714 $8,250,000 $7,260,000 $8,250,000 $32,175,000 $32,175,000 $32,175,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $141,113,266 Construction Cost $635,000 $937,000 $1,110,010 $0 $1,500,000 $1,350,000 $1,550,000 $400,000 $4,000,000 $10,000,000 $27,000,000 $26,400,000 $857,140 $30,000,000 $26,400,000 $30,000,000 $117,000,000 $117,000,000 $117,000,000 $513,139,150 Design Contingency $190,500 $281,100 $333,003 $0 $450,000 $405,000 $465,000 $120,000 $1,200,000 $3,000,000 $8,100,000 $7,920,000 $257,142 $9,000,000 $7,920,000 $9,000,000 $35,100,000 $35,100,000 $35,100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Subtotal $825,500 $1,218,100 $1,443,013 $0 $1,950,000 $1,755,000 $2,015,000 $520,000 $5,200,000 $13,000,000 $35,100,000 $34,320,000 $1,114,282 $39,000,000 $34,320,000 $39,000,000 $152,100,000 $152,100,000 $152,100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Construction Cost w/o Inflation $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $1,225,710 $42,900,000 $37,752,000 $42,900,000 $167,310,000 $167,310,000 $167,310,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $733,788,985 O&M Cost $8,945 $417 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $92,823 $92,823 A B C 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 17 21 22 17 20 22 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 15 13 14 15 16 18 19 21 23 24 25 19 20 18 24 23 14 16 13 $416,363 B.4 Life Cycle Costs ESTIMATED LIFE CYCLE COSTS AWSS CIP Alternative A Pipeline Output Sheet Alternative A - Pipeline Soft Cost $133,039,159 Total Project Capital Cost Construction $691,803,627 $824,842,786 Annual Operating Cost (New Asset) Net Present Value (new asset) $279,032 $727,365,526 Assumptions added in NPV Calculation: NPV Discount rate = 4.0% Construction Escalation = 3% Soft Cost Escalation = 3% Pipeline Maintenance cost = 0.5% per annum of Mechanical/Electrical estimate Pump Station Maintenance Cost = 1.5% per annum of Mechanical/Electrical estimate Alternative A Project Escalation Soft Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Balboa Tank and Booster PS Alemany Extension Pipeline Silver Extension Pipeline Geneva Extension Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Sutro Connection and PS Start Date End Date Total Budget Number of Months 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 7/2/2014 1/20/2015 7/1/2014 8/10/2015 9/15/2016 4/5/2017 10/24/2017 7/16/2020 5/14/2018 11/30/2018 6/20/2019 8/1/2024 1/12/2026 1/8/2020 7/28/2020 6/30/2014 6/30/2014 8/6/2015 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 2/25/2016 9/14/2016 2/24/2016 11/29/2018 5/11/2018 11/29/2018 6/19/2019 3/11/2022 1/7/2020 7/27/2020 2/12/2021 3/27/2026 9/7/2027 9/2/2021 3/23/2022 $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,750,000 $7,425,000 $7,260,000 $6,001,875 $3,460,875 $6,806,250 $5,192,000 $5,225,000 $5,039,375 $6,991,875 $515,625 $7,260,000 $0 $7,108,750 $2,234,375 20 20 33 20 20 20 20 20 20 20 20 20 40 20 20 20 20 20 20 20 20 20 20 20 11/2/2012 9/7/2027 $76,428,553 Start Date End Date Total Budget 7/1/2014 7/1/2014 8/7/2015 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 2/26/2016 9/15/2016 2/25/2016 11/30/2018 5/14/2018 11/30/2018 6/20/2019 3/14/2022 1/8/2020 7/28/2020 2/15/2021 3/30/2026 9/8/2027 9/3/2021 3/24/2022 8/6/2015 1/16/2015 10/20/2017 1/16/2015 3/25/2015 10/20/2017 8/6/2015 6/1/2015 8/8/2015 5/11/2018 7/15/2020 7/31/2024 9/2/2021 4/5/2021 1/13/2023 5/23/2023 1/9/2026 9/2/2021 10/8/2024 3/7/2022 9/1/2034 7/8/2031 12/8/2025 11/17/2023 7/1/2014 9/1/2034 $397,428,474 Start Date Total Budget 2012 Budget Per Month 2012 $8,731 $12,884 $9,250 $0 $20,625 $18,563 $21,313 $5,500 $55,000 $137,500 $371,250 $363,000 $150,047 $173,044 $340,313 $259,600 $261,250 $251,969 $349,594 $25,781 $363,000 $0 $355,438 $111,719 2013 $17,463 $25,768 $18,500 $0 $41,250 $37,125 $42,625 $11,000 $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $303,730 2014 $104,775 $154,605 $111,001 $0 $247,500 $222,750 $255,750 $66,000 $660,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,822,381 2015 $52,388 $77,303 $111,001 $0 $123,750 $111,375 $127,875 $33,000 $330,000 $825,000 $0 $2,178,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,969,691 2016 $0 $0 $64,751 $0 $0 $0 $0 $0 $0 $1,650,000 $4,083,750 $4,356,000 $750,234 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,904,735 2017 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000 $3,341,250 $726,000 $1,800,563 $692,175 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,834,988 2018 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,800,563 $2,076,525 $3,062,813 $519,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,459,100 2019 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,650,516 $692,175 $3,743,438 $3,115,200 $0 $2,015,750 $349,594 $0 $0 $0 $0 $0 $0 $11,566,672 2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,557,600 $0 $3,023,625 $4,195,125 $154,688 $0 $0 $0 $0 $0 $8,931,038 2021 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,567,500 $0 $2,447,156 $309,375 $0 $0 $4,265,250 $558,594 $0 $9,147,875 2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,135,000 $0 $0 $51,563 $0 $0 $2,843,500 $1,340,625 $0 $7,370,688 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $522,500 $0 $0 $0 $0 $0 $0 $335,156 $0 $857,656 2023 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Construction Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Balboa Tank and Booster PS Alemany Extension Pipeline Silver Extension Pipeline Geneva Extension Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Sutro Connection and PS Number of Months $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $31,209,750 $17,996,550 $35,392,500 $26,998,400 $27,170,000 $26,204,750 $36,357,750 $2,681,250 $37,752,000 $0 $36,965,500 $11,618,750 Budget Per Month 13 7 26 7 9 40 13 11 13 26 46 101 33 35 50 47 46 20 50 13 101 46 51 20 2012 $69,850 $191,416 $61,051 $0 $238,333 $48,263 $170,500 $52,000 $440,000 $550,000 $839,348 $373,782 $945,750 $514,187 $707,850 $574,434 $590,652 $1,310,238 $727,155 $206,250 $373,782 $0 $724,814 $580,938 2013 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2014 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2015 $419,100 $1,148,494 $0 $0 $1,430,000 $289,575 $1,023,000 $312,000 $2,640,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,262,169 2016 $488,950 $191,416 $305,253 $0 $715,000 $579,150 $1,193,500 $260,000 $3,080,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,813,268 2017 $0 $0 $732,607 $0 $0 $579,150 $0 $0 $0 $5,500,000 $3,357,391 $3,737,822 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,906,970 2018 $0 $0 $549,455 $0 $0 $482,625 $0 $0 $0 $6,600,000 $10,072,174 $4,485,386 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,189,640 2019 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,200,000 $10,072,174 $4,485,386 $945,750 $4,113,497 $707,850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,524,657 2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,072,174 $4,485,386 $11,349,000 $6,170,246 $8,494,200 $3,446,604 $0 $0 $0 $0 $0 $0 $0 $0 $0 $44,017,610 2021 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,036,087 $4,485,386 $11,349,000 $6,170,246 $8,494,200 $6,893,209 $0 $15,722,850 $3,635,775 $0 $0 $0 $0 $0 $0 $61,786,752 2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $7,566,000 $1,542,561 $8,494,200 $6,893,209 $0 $10,481,900 $8,725,860 $2,268,750 $0 $0 $2,899,255 $0 $0 $53,357,121 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $8,494,200 $6,893,209 $5,906,522 $0 $8,725,860 $412,500 $0 $0 $8,697,765 $5,228,438 $0 $48,843,879 2023 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $707,850 $2,872,170 $7,087,826 $0 $8,725,860 $0 $0 $0 $8,697,765 $6,390,313 $0 $38,967,170 O&M Cost Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Project Name Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Balboa Tank and Booster PS Alemany Extension Pipeline Silver Extension Pipeline Geneva Extension Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Sutro Connection and PS 8/7/2015 1/17/2015 10/21/2017 1/17/2015 3/26/2015 10/21/2017 8/7/2015 6/2/2015 8/9/2015 5/12/2018 7/16/2020 8/1/2024 9/3/2021 4/6/2021 1/14/2023 5/24/2023 1/10/2026 9/3/2021 10/9/2024 3/8/2022 9/2/2034 7/9/2031 12/9/2025 11/18/2023 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $0 $25,321 $10,151 $254,794 2013 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2014 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2015 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,342 $18 $0 $0 $1,420 $0 $1,175 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,956 2016 2017 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,501 2018 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,501 2019 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $1,891 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,392 2020 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,771 2021 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $12,846 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,617 2022 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $4,666 $6,131 $0 $0 $0 $11,685 $0 $0 $0 $0 $0 $0 $0 $69,055 2023 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $0 $0 $0 $17,409 $0 $226 $0 $0 $0 $0 $0 $94,715 2024 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $1,302 $10,148 $0 $17,409 $0 $1,251 $0 $0 $0 $8,927 $0 $116,116 2025 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $0 $17,409 $28,845 $1,251 $0 $0 $0 $10,151 $0 $197,182 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $0 $17,409 $37,335 $1,251 $0 $0 $23,725 $10,151 $0 $229,397 2026 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $587 $17,409 $37,335 $1,251 $0 $0 $25,321 $10,151 $0 $231,580 Alternative A Project Escalation Soft Cost 2024 2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,951,625 $0 $0 $0 $0 $7,951,625 2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,083,900 $0 $0 $0 $0 $19,083,900 2027 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,770,975 $4,950,000 $0 $0 $0 $9,720,975 2028 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,300,000 $0 $0 $0 $3,300,000 2029 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2031 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2032 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2033 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2035 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2036 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2028 2029 2030 2031 2032 2033 2034 2035 2037 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2039 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2044 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2045 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $174,625 $644,531 $85,253 $101,750 $893,750 $371,250 $426,250 $46,750 $2,750,000 $2,750,000 $8,387,500 $24,750,000 $6,001,875 $3,460,875 $6,806,250 $5,192,000 $8,250,000 $5,039,375 $6,991,875 $515,625 $31,806,500 $8,250,000 $7,108,750 $2,234,375 $0 $133,039,159 Construction Cost 2024 2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,919,802 $0 $0 $0 $0 $11,191,304 $0 $6,544,395 $0 $0 $0 $8,697,765 $0 $0 $35,353,266 2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,191,304 $0 $0 $0 $0 $0 $7,972,951 $0 $0 $19,164,255 2027 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,738,061 $0 $0 $0 $0 $14,738,061 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,650,749 $3,730,435 $0 $0 $0 $23,381,183 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,650,749 $11,191,304 $0 $0 $0 $30,842,053 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,650,749 $11,191,304 $0 $0 $0 $30,842,053 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,650,749 $11,191,304 $0 $0 $0 $30,842,053 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,650,749 $5,595,652 $0 $0 $0 $25,246,401 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,650,749 $0 $0 $0 $0 $19,650,749 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,650,749 $0 $0 $0 $0 $19,650,749 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,100,499 $0 $0 $0 $0 $13,100,499 2036 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2037 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2039 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2044 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2045 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 2039 2040 2041 2042 2043 2044 2045 2046 Total O&M Cost 2027 2028 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $0 $25,321 $10,151 $0 $255,231 2029 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $0 $25,321 $10,151 $0 $255,231 2030 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $0 $25,321 $10,151 $0 $255,231 2031 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $0 $25,321 $10,151 $0 $255,231 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $12,324 $25,321 $10,151 $0 $267,555 2032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 2033 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 2034 2035 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 2036 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 2037 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $8,945 $417 $0 $437 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $6,952 $23,556 $36,545 $25,901 $23,801 $17,409 $37,335 $1,251 $0 $23,801 $25,321 $10,151 $0 $279,032 $282,637 $12,945 $0 $13,566 $192,752 $0 $62,152 $0 $0 $149,451 $631,672 $0 $178,466 $595,031 $841,837 $605,871 $476,607 $446,910 $850,215 $30,250 $0 $369,339 $555,466 $242,400 $0 $6,537,570 2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $908,050 $3,351,563 $443,314 $529,100 $4,647,500 $1,930,500 $2,216,500 $243,100 $14,300,000 $14,300,000 $43,615,000 $128,700,000 $31,209,750 $17,996,550 $35,392,500 $26,998,400 $42,900,000 $26,204,750 $36,357,750 $2,681,250 $165,393,800 $42,900,000 $36,965,500 $11,618,750 $0 $691,803,627 Input Sheet Alternative A - Pipeline Opex Start Month 1 Project Start Year 2012 NPV Discount Rate 4.0% Construction Escalation Soft Cost Escalation 3% 3.0% 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Project Costs ($0,000) Soft Cost Construction Cost $303,730 $0 $1,822,381 $0 $3,969,691 $7,262,169 $10,904,735 $6,813,268 $6,834,988 $13,906,970 $7,459,100 $22,189,640 $11,566,672 $22,524,657 $8,931,038 $44,017,610 $9,147,875 $61,786,752 $7,370,688 $53,357,121 $857,656 $48,843,879 $0 $38,967,170 $1,815,000 $24,946,461 $4,356,000 $15,060,777 $1,089,000 $3,364,040 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $2,990,257 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Totals Soft Cost Construction Cost $76,428,553 $397,428,474 $473,857,027 O&M Cost $0 $0 $0 $7,956 $17,501 $17,501 $19,392 $22,771 $35,617 $69,055 $94,715 $116,116 $197,182 $229,397 $231,580 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 $254,794 NPV Alternative A - Pipeline Year No. Year Project Costs (Data from page 5) Soft Cost Construction Cost O&M Total 1 2012 $303,730 $303,730 2 2013 $1,877,052 $1,877,052 3 2014 $4,211,445 $7,704,435 4 2015 $11,915,898 $7,445,042 $8,694 $19,369,634 5 2016 $7,692,839 $15,652,417 $19,698 $23,364,953 6 2017 $8,647,141 $25,723,874 $20,288 $34,391,304 7 2018 $13,811,211 $26,895,619 $23,156 $40,729,985 8 2019 $10,984,050 $54,136,108 $28,005 $65,148,163 9 2020 $11,588,254 $78,269,609 $45,119 $89,902,982 10 2021 $9,617,075 $69,618,941 $90,101 $79,326,117 11 2022 $1,152,618 $65,642,088 $127,289 $66,921,996 12 2023 $53,939,676 $160,732 $54,100,408 13 2024 $2,587,756 $35,567,688 $281,135 $38,436,579 14 2025 $6,396,933 $22,117,259 $336,878 $28,851,070 15 2026 $1,647,210 $5,088,412 $350,285 $7,085,907 16 2027 $6,988,085 $396,961 $7,385,046 17 2028 $7,197,728 $408,870 $7,606,598 18 2029 $7,413,660 $421,136 $7,834,796 19 2030 $7,636,070 $433,770 $8,069,839 20 2031 $7,865,152 $446,783 $8,311,935 21 2032 $8,101,106 $460,186 $8,561,293 22 2033 $8,344,139 $473,992 $8,818,131 23 2034 $5,729,642 $488,212 $6,217,854 24 2035 $502,858 $502,858 25 2036 $517,944 $517,944 26 2037 $533,482 $533,482 $11,915,881 27 2038 $549,487 $549,487 28 2039 $565,971 $565,971 29 2040 $582,950 $582,950 30 2041 $600,439 $600,439 31 2042 $618,452 $618,452 32 2043 $637,005 $637,005 33 2044 $656,116 $656,116 34 35 2045 2046 $675,799 $696,073 $675,799 $696,073 36 2047 $716,955 $716,955 37 2048 $738,464 $738,464 38 2049 $760,618 $760,618 39 2050 $783,436 $783,436 40 2051 $806,939 $806,939 41 2052 $831,148 $831,148 42 2053 $856,082 $856,082 43 2054 $881,765 $881,765 44 2055 $908,217 $908,217 45 2056 $935,464 $935,464 46 2057 $963,528 $963,528 47 2058 $992,434 $992,434 48 2059 $1,022,207 $1,022,207 49 50 2060 2061 $1,052,873 $1,084,459 $1,052,873 $1,084,459 $25,492,453 $645,002,419 Totals $92,433,214 $527,076,752 $427,231,407 NPV Discounted @ 1 of 1 4.00% ESTIMATED LIFE CYCLE COSTS AWSS CIP Alternative B Hybrid Output Sheet Alternative B - Hybrid Soft Cost $74,709,803 Total Project Capital Cost Construction $388,490,974 $463,200,777 Annual Operating Cost (New Asset) Net Present Value (new asset) $249,136 $422,241,004 Assumptions added in NPV Calculation: NPV Discount rate = 4.0% Construction Escalation = 3% Soft Cost Escalation = 3% Pipeline Maintenance cost = 0.5% per annum of Mechanical/Electrical estimate Pump Station Maintenance Cost = 1.5% per annum of Mechanical/Electrical estimate Alternative B Project Escalation Soft Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline Start Date End Date Total Budget Number of Months 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 5/23/2013 12/11/2013 7/2/2014 7/1/2014 1/19/2015 8/7/2015 2/25/2016 6/7/2019 9/14/2016 4/4/2017 8/2/2024 10/23/2017 12/3/2024 5/11/2018 11/29/2018 6/19/2019 11/2/2012 6/30/2014 6/30/2014 8/6/2015 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 1/16/2015 8/6/2015 2/25/2016 2/24/2016 9/13/2016 4/3/2017 10/20/2017 2/1/2021 5/10/2018 11/28/2018 3/30/2026 6/18/2019 7/29/2026 1/6/2020 7/24/2020 2/11/2021 7/29/2026 $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,750,000 $7,425,000 $7,260,000 $6,806,250 $2,770,625 $6,991,875 $515,625 $4,125,000 $5,039,375 $2,612,500 $7,260,000 $2,234,375 $0 $7,108,750 $3,460,875 $5,192,000 $74,709,803 20 20 33 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 Start Date End Date Total Budget Number of Months Budget Per Month 2012 $8,731 $12,884 $9,250 $0 $20,625 $18,563 $21,313 $5,500 $55,000 $137,500 $371,250 $363,000 $340,313 $138,531 $349,594 $25,781 $206,250 $251,969 $130,625 $363,000 $111,719 $0 $355,438 $173,044 $259,600 1/1/2012 12/31/2012 $17,463 $25,768 $18,500 $0 $41,250 $37,125 $42,625 $11,000 $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $303,730 2013 2014 1/1/2013 12/31/2013 $104,775 $154,605 $111,001 $0 $247,500 $222,750 $255,750 $66,000 $660,000 $962,500 $371,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,156,131 1/1/2014 12/31/2014 $52,388 $77,303 $111,001 $0 $123,750 $111,375 $127,875 $33,000 $330,000 $1,650,000 $4,455,000 $2,178,000 $2,041,875 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,291,566 2015 2016 2017 2018 2019 2020 2021 1/1/2015 12/31/2015 1/1/2016 12/31/2016 1/1/2017 12/31/2017 1/1/2018 12/31/2018 1/1/2019 12/31/2019 1/1/2020 12/31/2020 1/1/2021 12/31/2021 $0 $0 $64,751 $0 $0 $0 $0 $0 $0 $137,500 $2,598,750 $4,356,000 $4,083,750 $1,662,375 $1,747,969 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,651,094 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $726,000 $680,625 $1,108,250 $4,195,125 $257,813 $0 $1,007,875 $0 $0 $0 $0 $0 $0 $0 $7,975,688 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,048,781 $257,813 $0 $3,023,625 $1,175,625 $0 $223,438 $0 $0 $0 $0 $5,729,281 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,007,875 $1,436,875 $0 $1,340,625 $0 $2,843,500 $173,044 $0 $6,801,919 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,443,750 $0 $0 $0 $670,313 $0 $4,265,250 $2,076,525 $1,817,200 $10,273,038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,475,000 $0 $0 $0 $0 $0 $0 $1,211,306 $3,115,200 $6,801,506 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $206,250 $0 $0 $0 $0 $0 $0 $0 $259,600 $465,850 2022 1/1/2022 12/31/2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2023 1/1/2023 12/31/2023 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2024 1/1/2024 12/31/2024 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,815,000 $0 $0 $0 $0 $0 $1,815,000 2025 1/1/2025 12/31/2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,356,000 $0 $0 $0 $0 $0 $4,356,000 Construction Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline 7/1/2014 7/1/2014 8/7/2015 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 1/19/2015 8/7/2015 2/26/2016 2/25/2016 9/14/2016 4/4/2017 10/23/2017 2/2/2021 5/11/2018 11/29/2018 3/31/2026 6/19/2019 7/30/2026 1/7/2020 7/27/2020 2/12/2021 7/1/2014 8/6/2015 1/16/2015 10/20/2017 1/16/2015 3/25/2015 10/20/2017 8/6/2015 6/1/2015 8/8/2015 4/3/2017 6/6/2019 8/1/2024 4/9/2020 5/10/2018 6/15/2021 11/12/2018 12/2/2024 1/6/2020 7/24/2020 9/4/2034 2/11/2021 5/29/2030 4/10/2024 6/19/2023 1/15/2025 9/4/2034 Start Date Total Budget $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $35,392,500 $14,407,250 $36,357,750 $2,681,250 $21,450,000 $26,204,750 $13,585,000 $37,752,000 $11,618,750 $0 $36,965,500 $17,996,550 $26,998,400 $388,490,974 Budget Per Month 13 7 26 7 9 40 13 11 13 26 46 101 50 20 50 13 46 20 20 101 20 46 51 35 47 2012 $69,850 $191,416 $61,051 $0 $238,333 $48,263 $170,500 $52,000 $440,000 $550,000 $839,348 $373,782 $707,850 $720,363 $727,155 $206,250 $466,304 $1,310,238 $679,250 $373,782 $580,938 $0 $724,814 $514,187 $574,434 1/1/2012 12/31/2012 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2013 2014 1/1/2013 12/31/2013 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 1/1/2014 12/31/2014 $419,100 $1,148,494 $0 $0 $1,430,000 $289,575 $1,023,000 $312,000 $2,640,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,262,169 2015 1/1/2015 12/31/2015 $488,950 $191,416 $305,253 $0 $715,000 $579,150 $1,193,500 $260,000 $3,080,000 $6,050,000 $4,196,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,060,008 2016 2017 2018 2019 2020 2021 1/1/2016 12/31/2016 1/1/2017 12/31/2017 1/1/2018 12/31/2018 1/1/2019 12/31/2019 1/1/2020 12/31/2020 1/1/2021 12/31/2021 $0 $0 $732,607 $0 $0 $579,150 $0 $0 $0 $6,600,000 $10,072,174 $3,737,822 $7,786,350 $2,881,450 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $32,389,552 $0 $0 $549,455 $0 $0 $482,625 $0 $0 $0 $1,650,000 $10,072,174 $4,485,386 $8,494,200 $8,644,350 $6,544,395 $618,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $41,541,335 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,072,174 $4,485,386 $8,494,200 $2,881,450 $8,725,860 $2,062,500 $0 $10,481,900 $679,250 $0 $0 $0 $0 $0 $0 $47,882,720 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,196,739 $4,485,386 $8,494,200 $0 $8,725,860 $0 $0 $15,722,850 $8,151,000 $0 $3,485,625 $0 $0 $0 $0 $53,261,660 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $2,123,550 $0 $8,725,860 $0 $0 $0 $4,754,750 $0 $6,971,250 $0 $8,697,765 $2,570,936 $0 $38,329,497 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $3,635,775 $0 $5,129,348 $0 $0 $0 $1,161,875 $0 $8,697,765 $6,170,246 $6,318,774 $35,599,169 2022 1/1/2022 12/31/2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $5,595,652 $0 $0 $0 $0 $0 $8,697,765 $6,170,246 $6,893,209 $31,842,257 2023 1/1/2023 12/31/2023 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $5,595,652 $0 $0 $0 $0 $0 $8,697,765 $3,085,123 $6,893,209 $28,757,134 2024 1/1/2024 12/31/2024 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,616,475 $0 $0 $0 $0 $5,129,348 $0 $0 $0 $0 $0 $2,174,441 $0 $6,893,209 $16,813,473 2025 1/1/2025 12/31/2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 O&M Cost Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Project Name Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline 8/7/2015 1/17/2015 10/21/2017 1/17/2015 3/26/2015 10/21/2017 8/7/2015 6/2/2015 8/9/2015 4/4/2017 6/7/2019 8/2/2024 4/10/2020 5/11/2018 6/16/2021 11/13/2018 12/3/2024 1/7/2020 7/25/2020 9/5/2034 2/12/2021 5/30/2030 4/11/2024 6/20/2023 1/16/2025 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2012 2013 2014 1/1/2012 12/31/2012 1/1/2013 12/31/2013 1/1/2014 12/31/2014 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2015 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 1/1/2015 12/31/2015 $5,342 $18 $0 $0 $1,420 $0 $1,175 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,956 2016 1/1/2016 12/31/2016 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,501 2017 1/1/2017 12/31/2017 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $1,343 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,844 2018 1/1/2018 12/31/2018 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $0 $0 $0 $4,539 $0 $1,083 $0 $0 $0 $0 $0 $0 $0 $0 $0 $28,393 2019 1/1/2019 12/31/2019 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $10,238 $0 $0 $12,744 $0 $1,251 $0 $0 $0 $0 $0 $0 $0 $0 $0 $47,004 2020 1/1/2020 12/31/2020 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $10,012 $12,744 $0 $1,251 $0 $286 $6,971 $0 $0 $0 $0 $0 $0 $77,836 2021 1/1/2021 12/31/2021 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $16,980 $1,251 $0 $17,409 $12,351 $0 $1,168 $0 $0 $0 $0 $145,020 2022 1/1/2022 12/31/2022 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $0 $0 $0 $174,358 2023 1/1/2023 12/31/2023 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $0 $10,971 $0 $185,329 2024 1/1/2024 12/31/2024 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $7,007 $23,556 $0 $204,921 2025 1/1/2025 12/31/2025 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $1,064 $224,299 2026 1/1/2026 12/31/2026 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2027 1/1/2027 12/31/2027 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2028 1/1/2028 12/31/2028 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 Alternative B Project Escalation Soft Cost 2026 1/1/2026 12/31/2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,089,000 $0 $0 $0 $0 $0 $1,089,000 2027 1/1/2027 12/31/2027 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2028 1/1/2028 12/31/2028 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2029 1/1/2029 12/31/2029 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2030 1/1/2030 12/31/2030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2031 1/1/2031 12/31/2031 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2032 1/1/2032 12/31/2032 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2033 1/1/2033 12/31/2033 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2034 1/1/2034 12/31/2034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2035 1/1/2035 12/31/2035 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2036 1/1/2036 12/31/2036 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2037 1/1/2037 12/31/2037 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 1/1/2038 12/31/2038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2039 1/1/2039 12/31/2039 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2040 1/1/2040 12/31/2040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2041 1/1/2041 12/31/2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2042 1/1/2042 12/31/2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 1/1/2043 12/31/2043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2044 1/1/2044 12/31/2044 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2045 1/1/2045 12/31/2045 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2046 1/1/2046 12/31/2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,750,000 $7,425,000 $7,260,000 $6,806,250 $2,770,625 $6,991,875 $515,625 $4,125,000 $5,039,375 $2,612,500 $7,260,000 $2,234,375 $0 $7,108,750 $3,460,875 $5,192,000 $74,709,803 Construction Cost 2026 1/1/2026 12/31/2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,364,040 $0 $0 $0 $0 $0 $3,364,040 2027 1/1/2027 12/31/2027 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $4,485,386 2028 1/1/2028 12/31/2028 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $4,485,386 2029 1/1/2029 12/31/2029 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $4,485,386 2030 1/1/2030 12/31/2030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $4,485,386 2031 1/1/2031 12/31/2031 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $4,485,386 2032 1/1/2032 12/31/2032 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $4,485,386 2033 1/1/2033 12/31/2033 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $4,485,386 2034 1/1/2034 12/31/2034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,990,257 $0 $0 $0 $0 $0 $2,990,257 2035 1/1/2035 12/31/2035 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2036 1/1/2036 12/31/2036 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2037 1/1/2037 12/31/2037 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 1/1/2038 12/31/2038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2039 1/1/2039 12/31/2039 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2040 1/1/2040 12/31/2040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2041 1/1/2041 12/31/2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2042 1/1/2042 12/31/2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 1/1/2043 12/31/2043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2044 1/1/2044 12/31/2044 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 O&M Cost 2029 1/1/2029 12/31/2029 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2030 1/1/2030 12/31/2030 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2031 1/1/2031 12/31/2031 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2032 1/1/2032 12/31/2032 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2033 1/1/2033 12/31/2033 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2034 1/1/2034 12/31/2034 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2035 1/1/2035 12/31/2035 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2036 1/1/2036 12/31/2036 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2037 1/1/2037 12/31/2037 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2038 1/1/2038 12/31/2038 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2039 1/1/2039 12/31/2039 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2040 1/1/2040 12/31/2040 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2041 1/1/2041 12/31/2041 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2042 1/1/2042 12/31/2042 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2043 1/1/2043 12/31/2043 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2044 1/1/2044 12/31/2044 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2045 1/1/2045 12/31/2045 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 2046 1/1/2046 12/31/2046 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $36,545 $12,744 $37,335 $1,251 $0 $17,409 $12,351 $0 $10,151 $0 $25,321 $23,556 $25,901 $249,136 Total $282,637 $12,945 $0 $0 $192,752 $0 $62,152 $0 $0 $154,173 $652,865 $0 $960,182 $361,371 $950,355 $36,111 $0 $452,920 $328,097 $0 $254,943 $0 $564,069 $552,759 $544,985 $6,363,317 2045 1/1/2045 12/31/2045 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2046 1/1/2046 12/31/2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $35,392,500 $14,407,250 $36,357,750 $2,681,250 $21,450,000 $26,204,750 $13,585,000 $37,752,000 $11,618,750 $0 $36,965,500 $17,996,550 $26,998,400 $388,490,974 Input Sheet Alternative B - Hybrid Opex Start Month 1 Project Start Year 2012 NPV Discount Rate 4.0% Construction Escalation 3.0% Soft Cost Escalation 3.0% 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Project Costs ($0,000) Soft Cost Construction Cost $303,730 $0 $3,156,131 $0 $11,291,566 $7,262,169 $14,651,094 $17,060,008 $7,975,688 $32,389,552 $5,729,281 $41,541,335 $6,801,919 $47,882,720 $10,273,038 $53,261,660 $6,801,506 $38,329,497 $465,850 $35,599,169 $0 $31,842,257 $0 $28,757,134 $1,815,000 $16,813,473 $4,356,000 $0 $1,089,000 $3,364,040 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $4,485,386 $0 $2,990,257 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 O&M Cost $0 $0 $0 $7,956 $17,501 $18,844 $28,393 $47,004 $77,836 $145,020 $174,358 $185,329 $204,921 $224,299 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 $249,136 Totals Soft Cost Construction Cost $74,709,803 $388,490,974 $463,200,777 $6,363,317 NPV Alternative B - Hybrid Year No. Year Project Costs (Data from page 5) Soft Cost Construction Cost O&M Total 1 2012 $303,730 $303,730 2 2013 $3,250,815 $3,250,815 3 2014 $11,979,222 $7,704,435 4 2015 $16,009,646 $18,641,931 $8,694 $34,660,271 5 2016 $8,976,707 $36,454,726 $19,698 $45,451,131 6 2017 $6,641,807 $48,157,793 $21,845 $54,821,445 7 2018 $8,121,847 $57,174,472 $33,903 $65,330,221 8 2019 $12,634,540 $65,505,124 $57,809 $78,197,473 9 2020 $8,615,945 $48,554,659 $98,601 $57,269,205 10 2021 $607,829 $46,448,841 $189,218 $47,245,887 11 2022 $42,793,331 $234,323 $43,027,654 12 2023 $39,806,599 $256,539 $40,063,139 13 2024 $2,587,756 $23,971,992 $292,168 $26,851,916 14 2025 $6,396,933 $329,391 $6,726,324 15 2026 $1,647,210 $5,088,412 $376,841 $7,112,463 16 2027 $6,988,085 $388,146 $7,376,231 17 2028 $7,197,728 $399,790 $7,597,518 18 2029 $7,413,660 $411,784 $7,825,444 19 2030 $7,636,070 $424,137 $8,060,207 20 2031 $7,865,152 $436,861 $8,302,013 21 2032 $8,101,106 $449,967 $8,551,074 22 2033 $8,344,139 $463,466 $8,807,606 23 2034 $5,729,642 $477,370 $6,207,013 24 2035 $491,691 $491,691 25 2036 $506,442 $506,442 26 2037 $521,635 $521,635 27 2038 $537,285 $537,285 28 2039 $553,403 $553,403 29 2040 $570,005 $570,005 30 2041 $587,105 $587,105 31 2042 $604,718 $604,718 32 2043 $622,860 $622,860 33 2044 $641,546 $641,546 34 35 2045 2046 $660,792 $680,616 $660,792 $680,616 36 2047 $701,034 $701,034 37 2048 $722,065 $722,065 38 2049 $743,727 $743,727 39 2050 $766,039 $766,039 40 2051 $789,020 $789,020 41 2052 $812,691 $812,691 42 2053 $837,072 $837,072 43 2054 $862,184 $862,184 44 2055 $888,049 $888,049 45 2056 $914,691 $914,691 46 2057 $942,132 $942,132 47 2058 $970,396 $970,396 48 2059 $999,507 $999,507 49 50 2060 2061 $1,029,493 $1,060,377 $1,029,493 $1,060,377 $25,387,129 $612,739,014 $7,401,402 4.00% $422,241,004 Totals $87,773,987 $68,513,879 $499,577,899 $346,325,722 NPV Discounted @ $19,683,658 ESTIMATED LIFE CYCLE COSTS AWSS CIP Alternative C Cisterns Output Sheet Alternative C - Cisterns Soft Cost $150,622,373 Total Project Capital Cost Construction $693,780,071 $844,402,445 Annual Operating Cost (New Asset) Net Present Value (new asset) $404,665 $675,954,088 Assumptions added in NPV Calculation: NPV Discount rate = 4.0% Construction Escalation = 3% Soft Cost Escalation = 3% Pipeline Maintenance cost = 0.5% per annum of Mechanical/Electrical estimate Pump Station Maintenance Cost = 1.5% per annum of Mechanical/Electrical estimate Alternative C Project Escalation Soft Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 New Bay Suction Connections Construct 90 +/- New Cisterns, Phase 2 Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Construct 351 +/- New Cisterns, Phase 1 Construct 351 +/- New Cisterns, Phase 2 Construct 351 +/- New Cisterns, Phase 3 Start Date End Date Total Budget 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 5/23/2013 12/11/2013 7/2/2014 5/23/2013 6/7/2019 8/2/2024 12/3/2024 5/30/2030 11/26/2035 5/22/2041 6/30/2014 6/30/2014 8/6/2015 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 1/16/2015 8/6/2015 2/25/2016 9/13/2016 2/1/2021 3/30/2026 7/29/2026 1/23/2032 7/21/2037 1/15/2043 $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,750,000 $7,425,000 $7,260,000 $235,714 $8,250,000 $7,260,000 $8,250,000 $32,175,000 $32,175,000 $32,175,000 11/2/2012 1/15/2043 $141,113,266 Start Date End Date Total Budget 7/1/2014 7/1/2014 8/7/2015 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 1/19/2015 8/7/2015 2/26/2016 9/14/2016 2/2/2021 3/31/2026 7/30/2026 1/26/2032 7/22/2037 1/16/2043 8/6/2015 1/16/2015 10/20/2017 1/16/2015 3/25/2015 10/20/2017 8/6/2015 6/1/2015 8/8/2015 4/3/2017 6/6/2019 8/1/2024 11/28/2018 12/2/2024 9/4/2034 5/29/2030 11/23/2035 5/21/2041 11/15/2046 7/1/2014 11/15/2046 $733,788,985 Start Date Total Budget 2012 1/1/2012 12/31/2012 Number of Months Budget Per Month 20 20 33 20 20 20 20 20 20 20 20 20 40 20 20 20 20 20 20 2012 $8,731 $12,884 $9,250 $0 $20,625 $18,563 $21,313 $5,500 $55,000 $137,500 $371,250 $363,000 $5,893 $412,500 $363,000 $412,500 $1,608,750 $1,608,750 $1,608,750 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 1/1/2015 12/31/2015 1/1/2016 12/31/2016 1/1/2017 12/31/2017 1/1/2018 12/31/2018 1/1/2019 12/31/2019 1/1/2020 12/31/2020 1/1/2021 12/31/2021 1/1/2022 12/31/2022 1/1/2023 12/31/2023 1/1/2024 12/31/2024 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,887,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,887,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,950,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,950,000 1/1/2012 12/31/2012 $17,463 $25,768 $18,500 $0 $41,250 $37,125 $42,625 $11,000 $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $303,730 1/1/2013 12/31/2013 $104,775 $154,605 $111,001 $0 $247,500 $222,750 $255,750 $66,000 $660,000 $962,500 $371,250 $0 $41,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,197,381 1/1/2014 12/31/2014 $52,388 $77,303 $111,001 $0 $123,750 $111,375 $127,875 $33,000 $330,000 $1,650,000 $4,455,000 $2,178,000 $70,714 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,320,405 $0 $0 $64,751 $0 $0 $0 $0 $0 $0 $0 $2,598,750 $4,356,000 $70,714 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,090,215 2012 1/1/2012 12/31/2012 2013 1/1/2013 12/31/2013 2014 1/1/2014 12/31/2014 $419,100 $1,148,494 $0 $0 $1,430,000 $289,575 $1,023,000 $312,000 $2,640,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,262,169 2015 1/1/2015 12/31/2015 $488,950 $191,416 $305,253 $0 $715,000 $579,150 $1,193,500 $260,000 $3,080,000 $6,050,000 $4,196,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,060,008 2017 1/1/2017 12/31/2017 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $1,343 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,844 2018 1/1/2018 12/31/2018 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $0 $0 $39,767 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $62,538 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $726,000 $47,143 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $773,143 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2016 1/1/2016 12/31/2016 2017 1/1/2017 12/31/2017 2018 1/1/2018 12/31/2018 2019 1/1/2019 12/31/2019 2020 1/1/2020 12/31/2020 $0 $0 $732,607 $0 $0 $579,150 $0 $0 $0 $6,600,000 $10,072,174 $3,737,822 $141,428 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $21,863,180 $0 $0 $549,455 $0 $0 $482,625 $0 $0 $0 $1,650,000 $10,072,174 $4,485,386 $565,712 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,805,352 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,072,174 $4,485,386 $518,570 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,076,130 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,196,739 $4,485,386 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,682,125 2019 1/1/2019 12/31/2019 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $10,238 $0 $43,720 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $76,729 2020 1/1/2020 12/31/2020 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,292 2021 1/1/2021 12/31/2021 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,292 2022 1/1/2022 12/31/2022 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,292 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $412,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $412,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,815,000 $412,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,227,500 $0 $0 2021 1/1/2021 12/31/2021 2022 1/1/2022 12/31/2022 2023 1/1/2023 12/31/2023 2024 1/1/2024 12/31/2024 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $10,258,696 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,744,082 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $11,191,304 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,676,690 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $11,191,304 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,676,690 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,616,475 $0 $10,258,696 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,875,171 2023 1/1/2023 12/31/2023 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,292 2024 1/1/2024 12/31/2024 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $21,975 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $112,267 2025 1/1/2025 12/31/2025 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,093 2026 1/1/2026 12/31/2026 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,093 2027 1/1/2027 12/31/2027 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,093 Construction Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 New Bay Suction Connections Construct 90 +/- New Cisterns, Phase 2 Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Construct 351 +/- New Cisterns, Phase 1 Construct 351 +/- New Cisterns, Phase 2 Construct 351 +/- New Cisterns, Phase 3 Number of Months $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $1,225,710 $42,900,000 $37,752,000 $42,900,000 $167,310,000 $167,310,000 $167,310,000 Budget Per Month 13 7 26 7 9 40 13 11 13 26 46 101 26 46 101 46 46 46 46 $69,850 $191,416 $61,051 $0 $238,333 $48,263 $170,500 $52,000 $440,000 $550,000 $839,348 $373,782 $47,143 $932,609 $373,782 $932,609 $3,637,174 $3,637,174 $3,637,174 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 O&M Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Bridge Connection PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 New Bay Suction Connections Construct 90 +/- New Cisterns, Phase 2 Pipeline Replacement Program, Phase 2 Construct 90 +/- New Cisterns, Phase 3 Construct 351 +/- New Cisterns, Phase 1 Construct 351 +/- New Cisterns, Phase 2 Construct 351 +/- New Cisterns, Phase 3 8/7/2015 1/17/2015 10/21/2017 1/17/2015 3/26/2015 10/21/2017 8/7/2015 6/2/2015 8/9/2015 4/4/2017 6/7/2019 8/2/2024 11/29/2018 12/3/2024 9/5/2034 5/30/2030 11/24/2035 5/22/2041 11/16/2046 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $92,823 $92,823 $416,363 2013 1/1/2013 12/31/2013 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2014 1/1/2014 12/31/2014 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2015 1/1/2015 12/31/2015 $5,342 $18 $0 $0 $1,420 $0 $1,175 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,956 2016 1/1/2016 12/31/2016 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,501 Alternative C Project Escalation Soft Cost 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 1/1/2025 12/31/2025 1/1/2026 12/31/2026 1/1/2027 12/31/2027 1/1/2028 12/31/2028 1/1/2029 12/31/2029 1/1/2030 12/31/2030 1/1/2031 12/31/2031 1/1/2032 12/31/2032 1/1/2033 12/31/2033 1/1/2034 12/31/2034 1/1/2035 12/31/2035 1/1/2036 12/31/2036 1/1/2037 12/31/2037 1/1/2038 12/31/2038 1/1/2039 12/31/2039 1/1/2040 12/31/2040 1/1/2041 12/31/2041 1/1/2042 12/31/2042 1/1/2043 12/31/2043 1/1/2044 12/31/2044 1/1/2045 12/31/2045 1/1/2046 12/31/2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,356,000 $4,950,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,306,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,089,000 $2,887,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,976,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,261,250 $0 $0 $0 $0 $0 $0 $0 $0 $11,261,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,305,000 $0 $0 $0 $0 $0 $0 $0 $0 $19,305,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,608,750 $0 $0 $0 $0 $0 $0 $0 $0 $1,608,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,608,750 $0 $0 $0 $0 $0 $0 $0 $1,608,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,305,000 $0 $0 $0 $0 $0 $0 $0 $19,305,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,261,250 $0 $0 $0 $0 $0 $0 $0 $11,261,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,261,250 $0 $0 $0 $0 $0 $0 $11,261,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,305,000 $0 $0 $0 $0 $0 $0 $19,305,000 2036 1/1/2036 12/31/2036 2042 1/1/2042 12/31/2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2026 1/1/2026 12/31/2026 2027 1/1/2027 12/31/2027 2028 1/1/2028 12/31/2028 2029 1/1/2029 12/31/2029 2030 1/1/2030 12/31/2030 2031 1/1/2031 12/31/2031 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,364,040 $4,663,043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,027,083 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $11,191,304 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,676,690 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $11,191,304 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,676,690 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $11,191,304 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,676,690 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $4,663,043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,148,430 2029 1/1/2029 12/31/2029 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,093 2030 1/1/2030 12/31/2030 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $9,716 $0 $0 $0 $0 $0 $0 $0 $0 $0 $123,809 2031 1/1/2031 12/31/2031 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $137,894 2032 1/1/2032 12/31/2032 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $137,894 2033 1/1/2033 12/31/2033 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $137,894 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2032 1/1/2032 12/31/2032 2033 1/1/2033 12/31/2033 2034 1/1/2034 12/31/2034 2035 1/1/2035 12/31/2035 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $40,008,913 $0 $0 $0 $0 $0 $0 $0 $0 $44,494,299 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,485,386 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $0 $48,131,473 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,990,257 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $0 $46,636,344 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,008,913 $0 $0 $0 $0 $0 $0 $0 $0 $40,008,913 2034 1/1/2034 12/31/2034 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $137,894 2035 1/1/2035 12/31/2035 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $83,159 $0 $0 $0 $0 $0 $0 $0 $0 $221,053 2036 1/1/2036 12/31/2036 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $0 $0 $0 $0 $0 $0 $0 $0 $230,717 2037 1/1/2037 12/31/2037 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $0 $0 $0 $0 $0 $0 $0 $0 $230,717 2038 1/1/2038 12/31/2038 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $0 $0 $0 $0 $0 $0 $0 $0 $230,717 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2037 1/1/2037 12/31/2037 2038 1/1/2038 12/31/2038 2039 1/1/2039 12/31/2039 2040 1/1/2040 12/31/2040 2041 1/1/2041 12/31/2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,185,870 $0 $0 $0 $0 $0 $0 $0 $18,185,870 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,185,870 $0 $0 $0 $0 $0 $0 $0 $18,185,870 2040 1/1/2040 12/31/2040 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $0 $0 $0 $0 $0 $0 $0 $0 $230,717 2041 1/1/2041 12/31/2041 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $35,858 $0 $0 $0 $0 $0 $0 $0 $266,575 2042 1/1/2042 12/31/2042 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $92,823 $0 $0 $0 $0 $0 $0 $0 $323,540 2043 1/1/2043 12/31/2043 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $92,823 $0 $0 $0 $0 $0 $0 $0 $323,540 2044 1/1/2044 12/31/2044 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $92,823 $0 $0 $0 $0 $0 $0 $0 $323,540 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 1/1/2043 12/31/2043 2044 1/1/2044 12/31/2044 2045 1/1/2045 12/31/2045 2046 1/1/2046 12/31/2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,008,913 $0 $0 $0 $0 $0 $0 $40,008,913 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $43,646,087 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,008,913 $0 $0 $0 $0 $0 $0 $40,008,913 2045 1/1/2045 12/31/2045 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $92,823 $0 $0 $0 $0 $0 $0 $0 $323,540 2046 1/1/2046 12/31/2046 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $92,823 $81,125 $0 $0 $0 $0 $0 $0 $404,665 $174,625 $257,675 $305,253 $0 $412,500 $371,250 $426,250 $110,000 $1,100,000 $2,612,500 $7,425,000 $7,260,000 $229,821 $8,250,000 $7,260,000 $8,250,000 $32,175,000 $32,175,000 $30,566,250 $0 $0 $0 $0 $0 $0 $139,361,123 x x x x x x x x x Construction Cost 2025 1/1/2025 12/31/2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 O&M Cost 2028 1/1/2028 12/31/2028 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,093 2039 1/1/2039 12/31/2039 $8,945 $417 $0 $0 $6,172 $0 $1,967 $0 $0 $5,270 $23,801 $0 $43,720 $23,801 $0 $23,801 $92,823 $0 $0 $0 $0 $0 $0 $0 $0 $230,717 Total $282,637 $12,945 $0 $0 $192,752 $0 $62,152 $0 $0 $154,173 $652,865 $0 $1,263,927 $545,597 $0 $390,532 $1,104,212 $499,973 $81,125 $0 $0 $0 $0 $0 $0 $5,242,891 Total $908,050 $1,339,910 $1,587,314 $0 $2,145,000 $1,930,500 $2,216,500 $572,000 $5,720,000 $14,300,000 $38,610,000 $37,752,000 $1,225,710 $42,900,000 $37,752,000 $42,900,000 $167,310,000 $167,310,000 $167,310,000 $0 $0 $0 $0 $0 $0 $733,788,985 x x x x x x Input Sheet Alternative C - Cisterns Opex Start Month 1 Project Start Year 2012 NPV Discount Rate 4.0% Construction Escalation Soft Cost Escalation 3% 3.0% 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Project Costs ($0,000) Soft Cost Construction Cost $303,730 $0 $3,197,381 $0 $9,320,405 $7,262,169 $7,090,215 $17,060,008 $773,143 $21,863,180 $0 $17,805,352 $0 $15,076,130 $2,887,500 $8,682,125 $4,950,000 $4,485,386 $412,500 $14,744,082 $0 $15,676,690 $0 $15,676,690 $2,227,500 $12,875,171 $9,306,000 $0 $3,976,500 $8,027,083 $0 $15,676,690 $0 $15,676,690 $0 $15,676,690 $11,261,250 $9,148,430 $19,305,000 $4,485,386 $1,608,750 $44,494,299 $0 $48,131,473 $0 $46,636,344 $1,608,750 $40,008,913 $19,305,000 $0 $11,261,250 $18,185,870 $0 $43,646,087 $0 $43,646,087 $0 $43,646,087 $11,261,250 $18,185,870 $11,261,250 $0 $19,305,000 $0 $0 $40,008,913 $0 $43,646,087 $0 $43,646,087 Totals Soft Cost $150,622,373 Construction Cost $693,780,071 $844,402,445 O&M Cost $0 $0 $0 $7,956 $17,501 $18,844 $62,538 $76,729 $90,292 $90,292 $90,292 $90,292 $112,267 $114,093 $114,093 $114,093 $114,093 $114,093 $123,809 $137,894 $137,894 $137,894 $137,894 $221,053 $230,717 $230,717 $230,717 $230,717 $230,717 $266,575 $323,540 $323,540 $323,540 $323,540 $404,665 NPV Alternative C - Cisterns Year No. Year Project Costs (Data from page 5) Soft Cost Construction Cost O&M Total 1 2012 $303,730 $303,730 2 2013 $3,293,302 $3,293,302 3 2014 $9,888,018 $7,704,435 4 2015 $7,747,669 $18,641,931 $8,694 $26,398,294 5 2016 $870,179 $24,607,202 $19,698 $25,497,079 6 2017 $20,641,283 $21,845 $20,663,129 7 2018 $18,001,687 $74,674 $18,076,361 8 2019 $3,551,261 $10,677,919 $94,367 $14,323,546 9 2020 $6,270,512 $5,681,953 $114,379 $12,066,844 10 2021 $538,219 $19,237,683 $117,811 $19,893,712 11 2022 $21,068,161 $121,345 $21,189,506 12 2023 $21,700,206 $124,985 $21,825,191 13 2024 $3,175,882 $18,356,915 $160,066 $21,692,864 14 2025 $13,666,175 $167,549 $13,833,724 15 2026 $6,014,813 $12,141,683 $172,576 $18,329,072 16 2027 $24,423,773 $177,753 $24,601,526 17 2028 $25,156,486 $183,086 $25,339,572 18 2029 $25,911,181 $188,578 $26,099,759 19 2030 $19,171,524 $15,574,589 $210,777 $34,956,890 20 2031 $33,851,434 $7,865,152 $241,798 $41,958,384 21 2032 $2,905,581 $80,361,654 $249,052 $83,516,287 22 2033 $89,538,718 $256,523 $89,795,242 23 2034 $89,360,058 $264,219 $89,624,278 24 2035 $3,175,007 $78,961,051 $436,268 $82,572,326 25 2036 $39,243,090 26 2037 $23,578,557 27 28 29 $17,592,453 $469,000 $39,712,090 $38,077,172 $483,070 $62,138,799 2038 $94,126,770 $497,562 $94,624,332 2039 $96,950,573 $512,489 $97,463,062 2040 $99,859,090 $527,864 $100,386,954 30 2041 $26,537,873 $628,201 $70,022,267 31 2042 $27,334,010 $785,316 $28,119,326 32 2043 $48,264,051 $808,876 $49,072,927 33 2044 $103,026,262 $833,142 $103,859,404 34 35 2045 2046 $115,764,054 $119,236,976 $858,137 $1,105,506 $116,622,191 $120,342,482 36 2047 $1,138,671 $1,138,671 37 2048 $1,172,831 $1,172,831 38 2049 $1,208,016 $1,208,016 39 2050 $1,244,257 $1,244,257 40 2051 $1,281,584 $1,281,584 41 2052 $1,320,032 $1,320,032 42 2053 $1,359,633 $1,359,633 43 2054 $1,400,422 $1,400,422 44 2055 $1,442,434 $1,442,434 45 2056 $1,485,707 $1,485,707 46 2057 $1,530,279 $1,530,279 47 2058 $1,576,187 $1,576,187 48 2059 $1,623,473 $1,623,473 49 50 2060 2061 $1,672,177 $1,722,342 $1,672,177 $1,722,342 $32,093,249 $1,656,984,949 Totals $279,380,888 $42,856,193 $1,345,510,812 $675,954,088 NPV Discounted @ 4.00% B.5 Updated Potable Co-Benefits Costs ESTIMATED LIFE CYCLE COSTS AWSS CIP Potable Co-Benefit Capital Only 1 of 1 Output Sheet Potable Co-Benefit - Capital Only Soft Cost $19,394,546 Total Project Capital Cost Construction $100,851,640 $120,246,186 Annual Operating Cost (New Asset) $0 Net Present Value (new asset) $91,420,418 Assumptions added in NPV Calculation: NPV Discount rate = 4.0% Construction Escalation = 3% Soft Cost Escalation = 3% Pipeline Maintenance cost = 0.5% per annum of Mechanical/Electrical estimate Pump Station Maintenance Cost = 1.5% per annum of Mechanical/Electrical estimate 1 of 1 NPV Potable Co-Benefit - Capital Only Project Costs (Data from page 5) Soft Cost Construction Cost Year No. Year 1 2012 2 2013 3 2014 $1,551,566 $1,551,566 4 2015 $7,560,805 $7,560,805 $7,560,805 5 2016 $10,119,500 $7,495,386 $17,614,886 $17,614,886 6 2017 $2,343,814 $25,443,350 $27,787,164 $27,787,164 7 2018 $28,642,787 $28,642,787 $28,642,787 8 2019 $28,170,666 $28,170,666 $28,170,666 9 2020 $23,235,514 $23,235,514 $23,235,514 10 2021 $9,145,008 $9,145,008 $9,145,008 11 2022 12 2023 13 2024 14 2025 15 2026 16 2027 17 2028 18 2029 19 2030 20 2031 21 2032 22 2033 23 2034 24 2035 25 2036 26 2037 27 2038 28 2039 29 2040 30 2041 31 2042 32 2043 33 2044 34 35 2045 2046 36 2047 37 2048 38 2049 39 2050 40 2051 41 2052 42 2053 43 2054 44 2055 45 2056 46 2057 47 2058 48 2059 49 50 2060 2061 $122,132,711 $143,708,396 Totals $21,575,684 $18,071,153 30 yrs $91,420,418 NPV Discounted @ 1 of 1 O&M Total $109,491,571 4.00% $1,551,566 Input Sheet Potable Co-Benefit - Capital Only Opex Start Month Project Start Year 2012 NPV Discount Rate 4.0% Construction Escalation Soft Cost Escalation Project Costs ($0,000) Soft Cost Construction Cost $0 $0 $0 $0 $1,462,500 $0 $6,919,207 $0 $8,991,044 $6,659,553 $2,021,794 $21,947,657 $0 $23,987,883 $0 $22,905,330 $0 $18,342,330 $0 $7,008,887 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 1 3% 3.0% 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 O&M Cost $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Totals Soft Cost Construction Cost $19,394,546 $100,851,640 $120,246,186 1 of 1 $0 Potable Co-Benefit Project Cost Input Project Name ID 1 2 3 4 5 6 7 8 9 10 11 29 19 26 22 23 12 21 27 30 25 13 24 18 20 28 14 15 16 17 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Hose PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline New Bay Suction Connections Construct 351 +/- New Cisterns, Phase 1 Construct 351 +/- New Cisterns, Phase 2 Construct 351 +/- New Cisterns, Phase 3 Balboa Tank and Booster PS Soft Cost $0 $0 $0 $4,431,818 $946,288 $12,253,300 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Estimating Assumptions Annual Inflation Rate 3% Design Cost, % of Construction 25% Design effort contingency 10% Design Effort Contingency $0 $0 $0 $443,182 $94,629 $1,225,330 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Subtotal - Soft Costs $0 $0 $0 $4,875,000 $1,040,917 $13,478,629 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,394,546 Construction Cost $17,727,273 $3,785,152 $49,013,198 2010 common Design Contingency $0 $0 $0 $5,318,182 $1,135,545 $14,703,959 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $23,045,455 $4,920,697 $63,717,158 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,525,622 $10,000,000 $17,632,000 $2,493,000 2 $10,000,000 Design contingency 30% $35,250,000 Construction contingency 10% $10,000,000 Years of inflation Subtotal $20,264,000 $81,811,000 $187,449,616 Construction Cost w/o Inflation $0 $0 $0 $25,350,000 $5,412,767 $70,088,873 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,851,640 O&M Cost Potable Co-Benefit Project Escalation Soft Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Hose PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline Start Date End Date Total Budget 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 11/2/2012 5/23/2013 12/11/2013 7/2/2014 7/1/2014 1/19/2015 8/7/2015 2/25/2016 6/7/2019 9/14/2016 4/4/2017 8/2/2024 10/23/2017 12/3/2024 5/11/2018 11/29/2018 6/19/2019 11/2/2012 6/30/2014 6/30/2014 8/6/2015 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 6/30/2014 1/16/2015 8/6/2015 2/25/2016 2/24/2016 9/13/2016 4/3/2017 10/20/2017 2/1/2021 5/10/2018 11/28/2018 3/30/2026 6/18/2019 7/29/2026 1/6/2020 7/24/2020 2/11/2021 7/29/2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,875,000 $1,040,917 $13,478,629 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,394,546 Start Date End Date Total Budget Number of Months 20 20 33 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 Budget Per Month $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $243,750 $52,046 $673,931 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2012 1/1/2012 12/31/2012 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2013 1/1/2013 12/31/2013 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2014 1/1/2014 12/31/2014 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,462,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,462,500 2015 1/1/2015 12/31/2015 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,925,000 $624,550 $3,369,657 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,919,207 2016 1/1/2016 12/31/2016 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $487,500 $416,367 $8,087,178 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,991,044 2017 1/1/2017 12/31/2017 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,021,794 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,021,794 2018 1/1/2018 12/31/2018 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2019 1/1/2019 12/31/2019 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2020 1/1/2020 12/31/2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2021 1/1/2021 12/31/2021 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2022 1/1/2022 12/31/2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2023 1/1/2023 12/31/2023 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2024 1/1/2024 12/31/2024 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2025 1/1/2025 12/31/2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2026 1/1/2026 12/31/2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2027 1/1/2027 12/31/2027 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2028 1/1/2028 12/31/2028 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Construction Cost Project Name Project ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Hose PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline 7/1/2014 7/1/2014 8/7/2015 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 7/1/2014 1/19/2015 8/7/2015 2/26/2016 2/25/2016 9/14/2016 4/4/2017 10/23/2017 2/2/2021 5/11/2018 11/29/2018 3/31/2026 6/19/2019 7/30/2026 1/7/2020 7/27/2020 2/12/2021 7/1/2014 8/6/2015 1/16/2015 10/20/2017 1/16/2015 3/25/2015 10/20/2017 8/6/2015 6/1/2015 8/8/2015 4/3/2017 6/6/2019 8/1/2024 4/9/2020 5/10/2018 6/15/2021 11/12/2018 12/2/2024 1/6/2020 7/24/2020 9/4/2034 2/11/2021 5/29/2030 4/10/2024 6/19/2023 1/15/2025 9/4/2034 Start Date Total Budget $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,350,000 $5,412,767 $70,088,873 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,851,640 Number of Months 13 7 26 7 9 40 13 11 13 26 46 101 50 20 50 13 46 20 20 101 20 46 51 35 47 Budget Per Month $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $507,000 $270,638 $1,401,777 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2012 1/1/2012 12/31/2012 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2013 1/1/2013 12/31/2013 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2014 1/1/2014 12/31/2014 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2015 1/1/2015 12/31/2015 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2016 1/1/2016 12/31/2016 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,577,000 $1,082,553 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,659,553 2017 1/1/2017 12/31/2017 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,084,000 $3,247,660 $12,615,997 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $21,947,657 2018 1/1/2018 12/31/2018 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,084,000 $1,082,553 $16,821,330 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $23,987,883 2019 1/1/2019 12/31/2019 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,084,000 $0 $16,821,330 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,905,330 2020 1/1/2020 12/31/2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,521,000 $0 $16,821,330 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,342,330 2021 1/1/2021 12/31/2021 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,008,887 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,008,887 2022 1/1/2022 12/31/2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2023 1/1/2023 12/31/2023 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2024 1/1/2024 12/31/2024 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2025 1/1/2025 12/31/2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2026 1/1/2026 12/31/2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2027 1/1/2027 12/31/2027 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2028 1/1/2028 12/31/2028 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 O&M Cost Project ID Project Name 2012 2013 1/1/2012 12/31/2012 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Motorization and Addition of Seismic Switches on Gate Valves 4th Street Hose PS1 Tunnel Upgrade Twin Peaks Outlet Connection Jones St Tank Bypass Valves Repair Suction Connections SCADA Improvements Fireboat Manifold Rehabilitation & Replacement Pipeline Investigations and Repairs Reliability Upgrades at Facilities Cistern Repair and Construct 90 +/- New Cisterns, Phase 1 Pipeline Replacement Program, Phase 1 Silver Extension Pipeline University Mound Reservoir Sunset Extension Pipeline Sunset Extension Rezoning Pipeline Construct 90 +/- New Cisterns, Phase 2 Lake Merced Pump Station Sunset Reservoir Connection and PS Pipeline Replacement Program, Phase 2 Sutro Connection and PS Construct 90 +/- New Cisterns, Phase 3 Richmond Extension Pipeline Alemany Extension Pipeline Geneva Extension Pipeline 8/7/2015 1/17/2015 10/21/2017 1/17/2015 3/26/2015 10/21/2017 8/7/2015 6/2/2015 8/9/2015 4/4/2017 6/7/2019 8/2/2024 4/10/2020 5/11/2018 6/16/2021 11/13/2018 12/3/2024 1/7/2020 7/25/2020 9/5/2034 2/12/2021 5/30/2030 4/11/2024 6/20/2023 1/16/2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 1/1/2013 12/31/2013 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2014 1/1/2014 12/31/2014 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2015 1/1/2015 12/31/2015 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2016 1/1/2016 12/31/2016 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2017 1/1/2017 12/31/2017 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2018 1/1/2018 12/31/2018 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2019 1/1/2019 12/31/2019 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2020 1/1/2020 12/31/2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2021 1/1/2021 12/31/2021 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2022 1/1/2022 12/31/2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2023 1/1/2023 12/31/2023 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2024 1/1/2024 12/31/2024 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2025 1/1/2025 12/31/2025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2026 1/1/2026 12/31/2026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2027 1/1/2027 12/31/2027 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2028 1/1/2028 12/31/2028 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2029 1/1/2029 12/31/2029 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2030 1/1/2030 12/31/2030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2031 1/1/2031 12/31/2031 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2029 1/1/2029 12/31/2029 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2029 1/1/2029 12/31/2029 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2032 1/1/2032 12/31/2032 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2030 1/1/2030 12/31/2030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2030 1/1/2030 12/31/2030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2033 1/1/2033 12/31/2033 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2031 1/1/2031 12/31/2031 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2031 1/1/2031 12/31/2031 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2034 1/1/2034 12/31/2034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2032 1/1/2032 12/31/2032 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2032 1/1/2032 12/31/2032 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2035 1/1/2035 12/31/2035 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2033 1/1/2033 12/31/2033 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2033 1/1/2033 12/31/2033 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2036 1/1/2036 12/31/2036 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2034 1/1/2034 12/31/2034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2034 1/1/2034 12/31/2034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2037 1/1/2037 12/31/2037 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2035 1/1/2035 12/31/2035 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2035 1/1/2035 12/31/2035 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 1/1/2038 12/31/2038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2036 1/1/2036 12/31/2036 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2036 1/1/2036 12/31/2036 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2039 1/1/2039 12/31/2039 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2037 1/1/2037 12/31/2037 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2037 1/1/2037 12/31/2037 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2040 1/1/2040 12/31/2040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 1/1/2038 12/31/2038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2038 1/1/2038 12/31/2038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2041 1/1/2041 12/31/2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2039 1/1/2039 12/31/2039 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2039 1/1/2039 12/31/2039 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2042 1/1/2042 12/31/2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2040 1/1/2040 12/31/2040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2040 1/1/2040 12/31/2040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 1/1/2043 12/31/2043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2041 1/1/2041 12/31/2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2041 1/1/2041 12/31/2041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2044 1/1/2044 12/31/2044 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2042 1/1/2042 12/31/2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2042 1/1/2042 12/31/2042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2045 1/1/2045 12/31/2045 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 1/1/2043 12/31/2043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2043 1/1/2043 12/31/2043 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2046 1/1/2046 12/31/2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2044 2045 1/1/2044 12/31/2044 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2044 1/1/2045 12/31/2045 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2045 1/1/2044 12/31/2044 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 1/1/2045 12/31/2045 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2046 1/1/2046 12/31/2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 2046 1/1/2046 12/31/2046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,875,000 $1,040,917 $13,478,629 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,394,546 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,350,000 $5,412,767 $70,088,873 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,851,640 Potable Co-benefit pipe information Alignment 2 Sunset Pipe System Diameter (in) Length (ft) 20 13099.64 24 7055.44 30 11114.08 36 9215.724 54 19056.62 60 5821.875 Connection points Total Miles 2.480992 1.336258 2.104939 1.745402 3.609209 1.102628 Revised 1 6 14 $/mile $ Million 5.2 5.2 5.2 7 8 9 10 65363.38 12.37943 Diameter (in) Length (ft) 36 1456.815 42 2217.051 48 2807.361 60 6535.388 Connection Points Total 0.275912 0.419896 0.531697 1.237763 13016.62 2.465268 Sunset Pipe System Diameter (in) Length (ft) 20 13099.64 24 7055.44 30 11114.08 36 9215.724 54 60 Connection points 12.90116 6.948539 10.94568 12.21782 28.87367 9.92365 5000000 81.81052 $ University Mound Pipe System $ 7 7 8 9 6 81,810,516 5000000 86,810,516 Total Miles 20.2641 $ 20,264,099 3000000 23,264,099 $/mile $ Million 40484.88 7.667591 5.2 5.2 5.2 7 8 9 10 12.90116 6.948539 10.94568 12.21782 0 0 5000000 200 0.037879 $ 7 0.265152 7 0 8 0 9 0 6 3000000 19 6 25 1000000 43,013,198 5000000 49,013,198 3 3 7 13 520000 0.265152 $ $ Plus 20 cisterns Miles 20 43.0132 $ University Mound Pipe System Total # hydrants $/mile $ Million FRA 29 2.480992 1.336258 2.104939 1.745402 0 0 Diameter (in) Length (ft) 36 200 0.037879 42 0 48 0 60 0 Connection Points 1.931384 2.939272 4.253577 11.13987 3000000 $ Plus 20 cisterns Revised 1 7 14 265,152 3000000 3,785,152 18,000 3.409091 Connection points Total 18000 3.409091 5.2 17.72727 10 5000000 17.72727 $ 17,727,273 Appendix C: Program Alternative Schedules CS-199 AWSS Facilities Preliminary Options Study Task 11 Appendix C Program Alternative Schedules Assumptions Schedule Notes Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Description Predicated on sufficient planning resources available. Predicated on no unforeseen encumbrances to the planning process. Predicated on sufficient design resources available. Predicated on no unforeseen encumbrances to the design process. Predicated on the use of qualified contractors experienced in this type of work. Predicated on standard materials procured domestically. Predicated on obtaining ACOE permit. Predicated on obtaining SF Port permit. Predicated on work being coordinated within access windows around fish spawn. Predicated on compatibility of communication hardware and software Predicated on the ability to complete 15 cisterns per calendar year. Predicated on 8-10 mg storage capacity. Predicated on obtaining SFMTA (DPT) special traffic permits. Predicated on obtaining DPW Excavation permit. Predicated on obtaining Caltrans Encroachment permit. Predicated on obtaining SFMTA (Muni) permission to bore under fixed guideway. Predicated on obtaining Caltrans permission to bore under freeway. Predicated on street surfacing exclusion from pavement moratorium. Predicated on ability to test and accept portions of pipeline to intermediate blind flanges/dead men. Predicated on sufficient power voltage and phasing available in time to test equipment. 6 of 6 ID Task Name 1 Alternative A Duration 2 720 valves days Motorization & addition of seismic switches on three gate 1 day Start Mon 6/3/13 Finish Tue 6/4/13 Mon 3/7/16 3 Planning 144 days Tue 6/4/13 Fri 12/20/13 4 Design 288 days Mon 12/23/13 Wed 1/28/15 5 Construction 288 days Thu 1/29/15 Mon 3/7/16 576 days Tue 6/4/13 Tue 8/18/15 6 4th Street Bridge Connection 7 Planning 144 days Tue 6/4/13 Fri 12/20/13 8 Design 288 days Mon 12/23/13 Wed 1/28/15 144 days Thu 1/29/15 Tue 8/18/15 1296 days Tue 6/4/13 Tue 5/22/18 Thu 7/10/14 9 10 Construction PS1 Tunnel upgrade 11 Planning 288 days Tue 6/4/13 12 Design 432 days Fri 7/11/14 Mon 3/7/16 13 Construction 576 days Tue 3/8/16 Tue 5/22/18 Tue 5/22/18 576 days Tue 3/8/16 15 Planning 144 days Tue 3/8/16 Fri 9/23/16 16 Design 288 days Mon 9/26/16 Wed 11/1/17 14 17 18 Twin Peaks Outlet Connection Construction Jones St. Tank Bypass Valves 144 days Thu 11/2/17 Tue 5/22/18 624 days Tue 3/8/16 Fri 7/27/18 19 Planning 144 days Tue 3/8/16 Fri 9/23/16 20 Design 288 days Mon 9/26/16 Wed 11/1/17 192 days Thu 11/2/17 Fri 7/27/18 1296 days Tue 3/8/16 Tue 2/23/21 21 22 Construction Repair suction connections 23 Planning 144 days Tue 3/8/16 Fri 9/23/16 24 Design 288 days Mon 9/26/16 Wed 11/1/17 25 Construction 864 days Thu 11/2/17 Tue 2/23/21 26 SCADA improvements 720 days Thu 11/2/17 Wed 8/5/20 Tue 5/22/18 27 Planning 144 days Thu 11/2/17 28 Design 288 days Wed 5/23/18 Fri 6/28/19 29 Construction 288 days Mon 7/1/19 Wed 8/5/20 30 FB Manifold R&R 672 days Thu 11/2/17 Fri 5/29/20 31 Planning 144 days Thu 11/2/17 Tue 5/22/18 32 Design 288 days Wed 5/23/18 Fri 6/28/19 33 Construction 240 days Mon 7/1/19 Fri 5/29/20 797 days Tue 6/4/13 Wed 6/22/16 34 Pipe Testing 35 Planning 144 days Tue 6/4/13 Fri 12/20/13 36 Design 288 days Mon 12/23/13 Wed 1/28/15 Construction 365 days Thu 1/29/15 Wed 6/22/16 1488 days Tue 6/4/13 Thu 2/14/19 Tue 4/15/14 37 38 Sutro Connection and Pump Station 39 Planning 226 days Tue 6/4/13 40 Design 523 days Wed 4/16/14 Fri 4/15/16 41 Construction 739 days Mon 4/18/16 Thu 2/14/19 42 2014 Bond 43 Reliability Upgrades at Facilities 1 day? Mon 6/1/15 Mon 6/1/15 1008 days Tue 6/2/15 Thu 4/11/19 44 Planning 144 days Tue 6/2/15 Fri 12/18/15 45 Design 288 days Mon 12/21/15 Wed 1/25/17 Construction 46 47 576 days Thu 1/26/17 Thu 4/11/19 Cistern Repair and Construct 33 New Cisterns, Ph. 1 1432 days Mon 12/21/15 Tue 6/15/21 48 Planning 144 days Mon 12/21/15 Thu 7/7/16 49 Design 288 days Fri 7/8/16 Tue 8/15/17 50 Construction 51 2021 Bond 52 Pipeline Replacement Program Phase 1 1000 days Wed 8/16/17 Tue 6/15/21 1 day? Wed 6/16/21 Wed 6/16/21 2632 days Thu 6/17/21 Fri 7/18/31 53 Planning 144 days Thu 6/17/21 Tue 1/4/22 54 Design 288 days Wed 1/5/22 Fri 2/10/23 55 Construction 2200 days Mon 2/13/23 Fri 7/18/31 1584 days Thu 6/17/21 Tue 7/13/27 56 Balboa Tank and Booster PS Project: Alternative A Schedule extended Date: Wed 1/30/13 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 204 1H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1 H Mon 6/3/13 Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 1 Deadline ID Task Name Duration 57 Planning 288 days 58 Design 59 Construction Start Finish Thu 6/17/21 Mon 7/25/22 576 days Tue 7/26/22 Tue 10/8/24 720 days Wed 10/9/24 Tue 7/13/27 1 day? Thu 6/1/28 Thu 6/1/28 60 2027 Bond 61 Alemany Extension 1188 days Fri 6/2/28 Tue 12/21/32 62 Planning 144 days Fri 6/2/28 Wed 12/20/28 63 Design 288 days Thu 12/21/28 Mon 1/28/30 64 Construction 756 days Tue 1/29/30 Tue 12/21/32 65 Silver Extension 1508 days Thu 12/21/28 Mon 10/2/34 66 Planning 144 days Thu 12/21/28 Tue 7/10/29 67 Design 288 days Wed 7/11/29 Fri 8/16/30 68 Construction 1076 days Mon 8/19/30 Mon 10/2/34 1456 days Wed 7/11/29 Wed 2/7/35 144 days Wed 7/11/29 Mon 1/28/30 69 Geneva Extension 70 Planning 71 Design 72 Construction 73 Construct 33 new Cisterns, Phase 2 74 Planning 75 Design 76 Construction 77 2033 Bond 78 Lake Merced Pump Station 288 days Tue 1/29/30 Thu 3/6/31 1024 days Fri 3/7/31 Wed 2/7/35 1432 days Wed 7/11/29 Thu 1/4/35 144 days Wed 7/11/29 Mon 1/28/30 Thu 3/6/31 288 days Tue 1/29/30 1000 days Fri 3/7/31 Thu 1/4/35 1 day? Thu 6/1/34 Thu 6/1/34 864 days Fri 6/2/34 Wed 9/23/37 79 Planning 144 days Fri 6/2/34 Wed 12/20/34 80 Design 288 days Thu 12/21/34 Mon 1/28/36 81 Construction 432 days Tue 1/29/36 Wed 9/23/37 82 Sunset Extension 1528 days Thu 12/21/34 Mon 10/29/40 83 Planning 144 days Thu 12/21/34 Tue 7/10/35 84 Design 288 days Wed 7/11/35 Fri 8/15/36 85 Construction 1096 days Mon 8/18/36 Mon 10/29/40 86 Sunset Rezoning 708 days Wed 7/11/35 Fri 3/26/38 87 Planning 144 days Wed 7/11/35 Mon 1/28/36 88 Design 288 days Tue 1/29/36 Thu 3/5/37 89 Construction 276 days Fri 3/6/37 Fri 3/26/38 90 2039 Bond 91 Pipeline Replacement Program Phase 2 1 day? Fri 6/1/40 Fri 6/1/40 2500 days Mon 6/4/40 Fri 12/31/49 92 Planning 144 days Mon 6/4/40 Thu 12/20/40 93 Design 288 days Fri 12/21/40 Tue 1/28/42 94 Construction 2068 days Wed 1/29/42 Fri 12/31/49 1 day? Fri 6/1/46 Fri 6/1/46 935 days Mon 6/4/46 Fri 12/31/49 Mon 6/4/46 Thu 12/20/46 95 2045 Bond 96 Richmond Extension 97 Planning 144 days 98 Design 288 days Fri 12/21/46 Tue 1/28/48 99 Construction 503 days Wed 1/29/48 Fri 12/31/49 Project: Alternative A Schedule extended Date: Wed 1/30/13 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 204 1H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1H2 H1 H2H1 H2 H1 H2 H1 H2H1 H2 H1 H2 H1 H Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 2 Deadline Appendix C Program Alternative Schedules Assumptions Alternative A Motorization & addition of seismic switches on three gate valves Planning Design Construction 4th Street Bridge Connection Planning Design Construction PS1 Tunnel upgrade Planning Design Construction Twin Peaks Outlet Connection Planning Design Construction Jones St. Tank Bypass Valves Planning Design Construction Repair suction connections Planning Design Construction SCADA improvements Planning Design Construction FB Manifold R&R Planning Design Construction Pipe Testing Planning Design Construction Sutro Connection and Pump Station Planning Design Construction 2014 Bond Reliability Upgrades at Facilities WDs Notes 144 days 288 days 288 days 1,2 3,4 5,6,10,13,14,18,20 144 days 288 days 144 days 1,2 3,4 5,6,7,9 288 days 432 days 576 days 1,2 3,4 5,6,13,14,18 144 days 288 days 144 days 1,2 3,4 5,6,10,13,14,18 144 days 288 days 192 days 1,2 3,4 5,6,7,8,9 144 days 288 days 864 days 1,2 3,4 5,6,7,8,9 144 days 288 days 288 days 1,2 3,4 5,6,10,13,14,18,20 144 days 288 days 240 days 1,2 3,4 5,6,7,8,9 144 days 288 days 365 days 1,2 3,4 5,6,10,13,14,15,17,18,19 226 days 523 days 739 days 1,2 3,4 5,6,10,13,14,18,19,20 Planning Design Construction Cistern Repair and Construct 33 New Cisterns, Ph. 1 Planning Design Construction 2021 Bond Pipeline Replacement Program Phase 1 Planning Design Construction Balboa Tank and Booster PS Planning Design Construction 2027 Bond Alemany Extension Planning Design Construction Silver Extension Planning Design Construction Geneva Extension Planning Design Construction Construct 33 new Cisterns, Phase 2 Planning Design Construction 2033 Bond Lake Merced Pump Station Planning Design Construction Sunset Extension Planning Design Construction Sunset Rezoning Planning Design Construction 2039 Bond 144 days 288 days 576 days 1,2 3,4 5,6,10,13,14,18,20 144 days 288 days 1000 days 1,2 3,4 5,6,10,11,13,14,18,20 144 days 288 days 2200 days 1,2 3,4 5,6,10,13,14,15,17,18,19 288 days 576 days 720 days 1,2 3,4 5,6,10,12,13,14,18,20 144 days 288 days 756 days 1,2 3,4 5,6,10,13,14,15,17,18,19 144 days 288 days 1076 days 1,2 3,4 5,6,10,13,14,15,17,18,19 144 days 288 days 1024 days 1,2 3,4 5,6,10,13,14,15,17,18,19 144 days 288 days 1000 days 1,2 3,4 5,6,10,11,13,14,18,20 144 days 288 days 432 days 1,2 3,4 5,6,10,13,14,18,19,20 144 days 288 days 1096 days 1,2 3,4 5,6,10,13,14,18,19 144 days 288 days 276 days 1,2 3,4 5,6,10,13,14,16,18,19 Pipeline Replacement Program Phase 2 Planning Design Construction 2045 Bond Richmond Extension Planning Design Construction 144 days 288 days 2068 days 1,2 3,4 5,6,10,13,14,15,17,18,19 144 days 288 days 503 days 1,2 3,4 5,6,10,13,14,18,19 ID Task Name Duration Start Finish 2011 2014 H1 1 Alternative B 2 Motorization & addition of seismic switches on three gate valves 3 4 5 6 7 8 Planning Design Construction 4th Street Bridge Connection Planning Design 1 day Mon 6/3/13 Mon 6/3/13 720 days Tue 6/4/13 Mon 3/7/16 144 days Tue 6/4/13 Fri 12/20/13 288 days Mon 12/23/13 Wed 1/28/15 288 days Thu 1/29/15 Mon 3/7/16 576 days Tue 6/4/13 Tue 8/18/15 144 days Tue 6/4/13 Fri 12/20/13 288 days Mon 12/23/13 Wed 1/28/15 144 days Thu 1/29/15 Tue 8/18/15 1296 days Tue 6/4/13 Tue 5/22/18 11 Planning 288 days Tue 6/4/13 Thu 7/10/14 12 Design 432 days Fri 7/11/14 Mon 3/7/16 576 days Tue 3/8/16 Tue 5/22/18 624 days Tue 3/8/16 9 10 13 14 Construction PS1 Tunnel upgrade Construction Jones St. Tank Bypass Valves Planning 144 days Tue 3/8/16 Fri 9/23/16 16 Design 288 days Mon 9/26/16 Wed 11/1/17 17 Construction 192 days Thu 11/2/17 Fri 7/27/18 1372 days Tue 3/8/16 Wed 6/9/21 220 days Tue 3/8/16 Mon 1/9/17 288 days Tue 1/10/17 19 20 Repair suction connections Planning Design Fri 2/16/18 Wed 6/9/21 Fri 2/16/18 Thu 11/19/20 Planning 144 days Fri 2/16/18 Wed 9/5/18 24 Design 288 days Thu 9/6/18 Mon 10/14/19 25 Construction 288 days Tue 10/15/19 Thu 11/19/20 672 days Fri 2/16/18 Mon 9/14/20 21 26 27 28 29 30 Construction SCADA improvements FB Manifold R&R 144 days Planning Design Construction Pipe Investigation and Repair Fri 2/16/18 Thu 9/6/18 240 days Tue 10/15/19 Mon 9/14/20 Tue 6/4/13 Mon 6/12/17 31 Planning 250 days Tue 6/4/13 Mon 5/19/14 Design 400 days Tue 5/20/14 Mon 11/30/15 Construction 400 days Tue 12/1/15 Mon 6/12/17 Tue 6/4/13 Thu 2/14/19 35 Planning 226 days Tue 6/4/13 Tue 4/15/14 36 Design 523 days Wed 4/16/14 37 Construction 739 days Mon 4/18/16 Thu 2/14/19 1 day? Mon 6/1/15 Mon 6/1/15 Tue 5/19/20 38 2014 Bond 39 Reliability Upgrades at Facilities 1488 days 1296 days Tue 6/2/15 Planning 288 days Tue 6/2/15 41 Design 432 days Fri 7/8/16 Mon 3/5/18 42 Construction 576 days Tue 3/6/18 Tue 5/19/20 1432 days Fri 7/8/16 Mon 1/3/22 43 44 45 46 144 days Planning 288 days Design Construction 47 2021 Bond 48 Pipeline Replacement Program Phase 1 49 50 51 52 Planning Design Construction Silver Extension 53 Planning 54 Design 55 Construction 56 2027 Bond 57 University Mound Connection and PS Fri 7/8/16 Thu 1/26/17 Mon 1/3/22 Wed 6/1/22 2548 days Thu 6/2/22 Mon 3/8/32 260 days Thu 6/2/22 W ed 5/31/23 288 days Thu 6/1/23 2000 days Tue 7/9/24 1508 days Thu 6/2/22 Mon 3/13/28 144 days Thu 6/2/22 Tue 12/20/22 Mon 7/8/24 288 days Wed 12/21/22 1076 days Mon 1/29/24 Mon 3/13/28 1 day? Thu 6/1/28 Thu 6/1/28 Mon 3/8/32 Fri 1/26/24 Fri 6/2/28 Wed 9/24/31 Planning 144 days Fri 6/2/28 Wed 12/20/28 Design 288 days Thu 12/21/28 Mon 1/28/30 60 Construction 432 days Tue 1/29/30 Wed 9/24/31 61 Sunset Extension 1528 days Thu 12/21/28 Mon 10/30/34 144 days Thu 12/21/28 62 Design 64 Construction 65 66 67 68 Wed 7/11/29 Fri 8/16/30 Mon 8/19/30 Mon 10/30/34 708 days Wed 7/11/29 Fri 3/26/32 144 days Wed 7/11/29 Mon 1/28/30 Design 288 days Construction 276 days Fri 3/7/31 Fri 3/26/32 1 day? Thu 6/1/34 Thu 6/1/34 864 days Fri 6/2/34 Wed 9/23/37 Fri 6/2/34 Wed 12/20/34 69 2033 Bond 70 Lake Merced Pump Station 71 Tue 7/10/29 288 days 1096 days Planning Sunset Rezoning 144 days Planning Thu 3/6/31 Thu 12/21/34 Mon 1/28/36 432 days Tue 1/29/36 Wed 9/23/37 864 days Thu 12/21/34 Tue 4/13/38 75 Planning 144 days Thu 12/21/34 Tue 7/10/35 76 Design 288 days Wed 7/11/35 77 Construction 432 days Mon 8/18/36 72 73 74 288 days Tue 1/29/30 Design Construction Sunset Connection and PS 78 2039 Bond 79 Pipeline Replacement Program Phase 2 80 Planning 81 Design 82 Construction 83 2045 Bond 84 Richmond Extension Fri 8/15/36 Tue 4/13/38 1 day? Fri 6/1/40 Fri 6/1/40 2432 days Mon 6/4/40 Tue 9/28/49 144 days Mon 6/4/40 Thu 12/20/40 288 days Fri 12/21/40 Tue 1/28/42 2000 days Wed 1/29/42 Tue 9/28/49 1 day? Fri 6/1/46 Fri 6/1/46 935 days Mon 6/4/46 Fri 12/31/49 85 Planning 144 days Mon 6/4/46 Thu 12/20/46 86 Design 288 days Fri 12/21/46 87 Construction 503 days Wed 1/29/48 Fri 12/31/49 88 Alemany Extension 791 days Fri 12/21/46 Fri 12/31/49 Fri 12/21/46 Wed 7/10/47 Thu 7/11/47 Mon 8/17/48 89 90 144 days Planning 288 days Design Tue 1/28/48 91 Construction 359 days Tue 8/18/48 Fri 12/31/49 92 Geneva Extension 647 days Thu 7/11/47 Fri 12/31/49 93 Planning 144 days Thu 7/11/47 94 Design 288 days Wed 1/29/48 Fri 3/5/49 95 Construction 215 days Mon 3/8/49 Fri 12/31/49 Project: Alternative B Schedule extended Date: Wed 11/6/13 H2 Mon 3/5/18 W ed 6/1/22 58 63 2026 H1 Wed 1/25/17 Tue 3/6/18 1 day? 59 Planning H2 Thu 7/7/16 1000 days 864 days 2023 H1 Fri 4/15/16 40 Cistern Construct 27 New Cisterns H2 Mon 10/14/19 33 Sutro Connection and PS 2020 H1 Wed 9/5/18 288 days 1050 days 32 34 H2 Thu 2/15/18 864 days 720 days 23 22 2017 H1 Fri 7/27/18 15 18 H2 Tue 1/28/48 Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Progress Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Deadline Page 1 2029 H1 H2 H1 ID Task Name Duration Start Finish 2032 H2 1 Alternative B 2 Motorization & addition of seismic switches on three gate valves 3 4 5 6 7 Planning Design Construction 4th Street Bridge Connection Planning 1 day Mon 6/3/13 Mon 6/3/13 720 days Tue 6/4/13 Mon 3/7/16 144 days Tue 6/4/13 Fri 12/20/13 288 days Mon 12/23/13 Wed 1/28/15 288 days Thu 1/29/15 Mon 3/7/16 576 days Tue 6/4/13 Tue 8/18/15 144 days Tue 6/4/13 Fri 12/20/13 288 days Mon 12/23/13 Wed 1/28/15 144 days Thu 1/29/15 Tue 8/18/15 1296 days Tue 6/4/13 Tue 5/22/18 11 Planning 288 days Tue 6/4/13 Thu 7/10/14 12 Design 432 days Fri 7/11/14 Mon 3/7/16 Construction 576 days Tue 3/8/16 Tue 5/22/18 624 days Tue 3/8/16 8 9 10 13 14 Design Construction PS1 Tunnel upgrade Jones St. Tank Bypass Valves Planning 144 days Tue 3/8/16 Fri 9/23/16 16 Design 288 days Mon 9/26/16 Wed 11/1/17 Construction 192 days Thu 11/2/17 Fri 7/27/18 1372 days Tue 3/8/16 Wed 6/9/21 220 days Tue 3/8/16 Mon 1/9/17 288 days Tue 1/10/17 19 20 Repair suction connections Planning Design Fri 2/16/18 Wed 6/9/21 Fri 2/16/18 Thu 11/19/20 Planning 144 days Fri 2/16/18 Wed 9/5/18 24 Design 288 days Thu 9/6/18 Mon 10/14/19 25 Construction 288 days Tue 10/15/19 Thu 11/19/20 672 days Fri 2/16/18 Mon 9/14/20 21 26 27 28 29 30 Construction SCADA improvements FB Manifold R&R 144 days Planning Design Construction Pipe Investigation and Repair Fri 2/16/18 Thu 9/6/18 240 days Tue 10/15/19 Mon 9/14/20 Tue 6/4/13 Mon 6/12/17 31 Planning 250 days Tue 6/4/13 Mon 5/19/14 Design 400 days Tue 5/20/14 Mon 11/30/15 Construction 400 days Tue 12/1/15 Mon 6/12/17 Tue 6/4/13 Thu 2/14/19 35 Planning 226 days Tue 6/4/13 Tue 4/15/14 36 Design 523 days Wed 4/16/14 37 Construction 739 days Mon 4/18/16 Thu 2/14/19 1 day? Mon 6/1/15 Mon 6/1/15 Tue 5/19/20 38 2014 Bond 39 Reliability Upgrades at Facilities 1488 days 1296 days Tue 6/2/15 Planning 288 days Tue 6/2/15 41 Design 432 days Fri 7/8/16 Mon 3/5/18 42 Construction 576 days Tue 3/6/18 Tue 5/19/20 1432 days Fri 7/8/16 Mon 1/3/22 43 44 45 46 144 days Planning 288 days Design Construction 47 2021 Bond 48 Pipeline Replacement Program Phase 1 49 50 51 52 Planning Design Construction Silver Extension 53 Planning 54 Design 55 Construction 56 2027 Bond 57 University Mound Connection and PS Fri 7/8/16 Thu 1/26/17 Mon 1/3/22 W ed 6/1/22 2548 days Thu 6/2/22 Mon 3/8/32 260 days Thu 6/2/22 Wed 5/31/23 288 days Thu 6/1/23 2000 days Tue 7/9/24 1508 days Thu 6/2/22 Mon 3/13/28 144 days Thu 6/2/22 Tue 12/20/22 288 days Wed 12/21/22 1076 days Mon 1/29/24 Mon 3/13/28 1 day? Thu 6/1/28 Thu 6/1/28 Mon 7/8/24 Mon 3/8/32 Fri 1/26/24 Fri 6/2/28 Wed 9/24/31 Planning 144 days Fri 6/2/28 Wed 12/20/28 Design 288 days Thu 12/21/28 60 Construction 432 days Tue 1/29/30 Wed 9/24/31 61 Sunset Extension 1528 days Thu 12/21/28 Mon 10/30/34 144 days Thu 12/21/28 62 Design 64 Construction 65 66 67 68 Mon 1/28/30 Tue 7/10/29 288 days Wed 7/11/29 Fri 8/16/30 1096 days Mon 8/19/30 Mon 10/30/34 708 days Wed 7/11/29 Fri 3/26/32 Planning 144 days Wed 7/11/29 Mon 1/28/30 Design 288 days Construction 276 days Fri 3/7/31 Fri 3/26/32 1 day? Thu 6/1/34 Thu 6/1/34 Sunset Rezoning 69 2033 Bond 70 Lake Merced Pump Station 864 days Tue 1/29/30 Thu 3/6/31 Fri 6/2/34 Wed 9/23/37 71 Planning 144 days Fri 6/2/34 Wed 12/20/34 72 Design 288 days Thu 12/21/34 Mon 1/28/36 73 Construction 432 days Tue 1/29/36 Wed 9/23/37 864 days Thu 12/21/34 Tue 4/13/38 75 Planning 144 days Thu 12/21/34 Tue 7/10/35 76 Design 288 days Wed 7/11/35 77 Construction 432 days Mon 8/18/36 74 Sunset Connection and PS 78 2039 Bond 79 Pipeline Replacement Program Phase 2 80 Planning 81 Design 82 Construction 83 2045 Bond 84 Richmond Extension Fri 8/15/36 Tue 4/13/38 1 day? Fri 6/1/40 Fri 6/1/40 2432 days Mon 6/4/40 Tue 9/28/49 Mon 6/4/40 Thu 12/20/40 288 days Fri 12/21/40 Tue 1/28/42 2000 days 144 days W ed 1/29/42 Tue 9/28/49 1 day? Fri 6/1/46 Fri 6/1/46 935 days Mon 6/4/46 Fri 12/31/49 85 Planning 144 days Mon 6/4/46 Thu 12/20/46 86 Design 288 days Fri 12/21/46 87 Construction 503 days Wed 1/29/48 Fri 12/31/49 88 Alemany Extension 791 days Fri 12/21/46 Fri 12/31/49 144 days Fri 12/21/46 Wed 7/10/47 Thu 7/11/47 Mon 8/17/48 89 90 Planning 288 days Design Tue 1/28/48 359 days Tue 8/18/48 Fri 12/31/49 647 days Thu 7/11/47 Fri 12/31/49 93 Planning 144 days Thu 7/11/47 Tue 1/28/48 94 Design 288 days Wed 1/29/48 Fri 3/5/49 95 Construction 215 days Mon 3/8/49 Fri 12/31/49 91 Construction 92 Geneva Extension Project: Alternative B Schedule extended Date: W ed 11/6/13 Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Progress Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Deadline Page 2 2047 H1 Mon 3/5/18 Wed 6/1/22 58 63 H2 Wed 1/25/17 Tue 3/6/18 1 day? 59 Planning 2044 H1 Thu 7/7/16 1000 days 864 days H2 Fri 4/15/16 40 Cistern Construct 27 New Cisterns 2041 H1 Mon 10/14/19 33 Sutro Connection and PS H2 Wed 9/5/18 288 days 1050 days 32 34 2038 H1 Thu 2/15/18 864 days 720 days 23 22 H2 Fri 7/27/18 15 17 18 2035 H1 H2 H1 H2 Appendix C Program Alternative Schedules Assumptions Alternative B Motorization & addition of seismic switches on three gate valves Planning Design Construction 4th Street Bridge Connection Planning Design Construction PS1 Tunnel upgrade Planning Design Construction Jones St. Tank Bypass Valves Planning Design Construction Repair suction connections Planning Design Construction SCADA improvements Planning Design Construction FB Manifold R&R Planning Design Construction Pipe Investigation and Repair Planning Design Construction Sutro Connection and PS Planning Design Construction 2014 Bond Reliability Upgrades at Facilities Planning Design Construction Cistern Construct 27 New Cisterns WDs Notes 144 days 1,2 288 days 3,4 288 days 5,6,10,13,14,18,20 144 days 1,2 288 days 3,4 144 days 5,6,7,9 288 days 1,2 432 days 3,4 576 days 5,6,13,14,18 144 days 1,2 288 days 3,4 192 days 5,6,10,13,14,18 220 days 1,2 288 days 3,4 864 days 5,6,7,8,9 144 days 1,2 288 days 3,4 288 days 5,6,10,13,14,18,20 144 days 1,2 288 days 3,4 240 days 5,6,7,8,9 250 days 1,2 400 days 3,4 400 days 5,6,10,13,14,15,17,18,19 226 days 1,2 523 days 3,4 739 days 5,6,10,13,14,18,19,20 288 days 1,2 432 days 3,4 576 days 5,6,10,13,14,18,20 Planning Design Construction 2021 Bond Pipeline Replacement Program Phase 1 Planning Design Construction Silver Extension Planning Design Construction 2027 Bond University Mound Connection and PS Planning Design Construction Sunset Extension Planning Design Construction Sunset Rezoning Planning Design Construction 2033 Bond Lake Merced Pump Station Planning Design Construction Sunset Connection and PS Planning Design Construction 2039 Bond Pipeline Replacement Program Phase 2 Planning Design Construction 2045 Bond Richmond Extension Planning Design Construction 144 days 1,2 288 days 3,4 1000 days 5,6,10,11,13,14,18,20 260 days 1,2 288 days 3,4 2000 days 5,6,10,13,14,15,17,18,19 144 days 1,2 288 days 3,4 1076 days 5,6,10,13,14,15,17,18,19 144 days 1,2 288 days 3,4 432 days 5,6,10,12,13,14,18,19,20 144 days 1,2 288 days 3,4 1096 days 5,6,10,13,14,18,19 144 days 1,2 288 days 3,4 276 days 5,6,10,13,14,16,18,19 144 days 1,2 288 days 3,4 432 days 5,6,10,13,14,18,19,20 144 days 1,2 288 days 3,4 432 days 5,6,10,13,14,18,19,20 144 days 1,2 288 days 3,4 2000 days 5,6,10,13,14,15,17,18,19 144 days 1,2 288 days 3,4 503 days 5,6,10,13,14,18,19 Alemany Extension Planning Design Construction Geneva Extension Planning Design Construction 144 days 1,2 288 days 3,4 359 days 5,6,10,13,14,16,18,19 144 days 1,2 288 days 3,4 215 days 5,6,10,13,14,15,17,18,19 CS-199 AWSS Alternative C Schedule ID Task Name Duration 2013 2014 H1 1 Alternative C 2 Tue Motorization & addition of seismic switches 720 on days three gate valv es 6/4/13 3 4 5 6 1 day Planning Design Construction 4th Street Bridge Connection Tue 6/4/13 288 days Mon 12/23/13 288 days Thu 1/29/15 Planning 144 days Tue 6/4/13 8 Design 288 days Mon 12/23/13 9 Construction 144 days Thu 1/29/15 PS1 Tunnel upgrade 1296 days Tue 6/4/13 11 Planning 288 days Tue 6/4/13 12 Design 432 days 13 Construction 576 days Tue 3/8/16 576 days Tue 3/8/16 14 Twin Peaks Outlet Connection Planning 144 days Tue 3/8/16 16 Design 288 days Mo n 9/26/16 17 Construction 144 days Thu 11/2/17 Jones St. Tank Bypass Valves 624 days Planning 144 days Tue 3/8/16 20 Design 288 days Mo n 9/26/16 21 Construction 192 days Thu 11/2/17 Repair suction connections 1296 days Planning 144 days Tue 3/8/16 24 Design 288 days Mo n 9/26/16 25 Construction 864 days Thu 11/2/17 SCADA improvements 720 days Planning 144 days Thu 11/2/17 28 Design 288 days We d 5/23/18 29 Construction 288 days Mon 7/1/19 672 days Thu 1 1/2/17 144 days Thu 11/2/17 288 days We d 5/23/18 240 days Mon 7/1/19 31 32 33 34 FB Manifold R&R Planning Design Construction Pipe Inv estigation and Repair 720 days Planning 144 days Tue 6/4/13 36 Design 288 days Mon 12/23/13 37 Construction 288 days Thu 1/29/15 1488 days Sutro Connection and PS Planning 226 days Tue 6/4/13 40 Design 523 days Wed 4/16/14 41 Construction 739 days Mon 4/18/16 1 day? Mon 6/1/15 2014 Bond 43 Reliability Upgrades at Facilities 1008 days Planning 144 days Tue 6/2/15 45 Design 288 days Mon 12/21/15 46 Construction 576 days Thu 1/26/17 Cistern Construct 46 New Cisterns, Ph. 1 1432 days Mon 12/21/15 48 Planning 144 days 49 Design 288 days 50 Construction 1 day? Wed 6/1/22 52 Pipeline Replacement Program Phase 1 2632 days Thu 6/2/22 55 56 Planning Design Construction New Bay Suction Connections 144 days Thu 6/2/22 288 days W ed 12/21/22 2200 days Mon 1/29/24 1440 days Thu 6/2/22 57 Planning 288 days 58 Design 576 days Tue 7/11/23 59 Construction 576 days W ed 9/24/25 60 2027 Bond 61 Construct 33 New Cisterns Phase 2 1 day? 1432 days Fri 6/2/28 288 days Thu 12/21/28 64 Construction 1000 days Tue 1/29/30 Pipeline Replacement Program Phase 2 2632 days 1 day? 144 days Fri 6/2/34 68 Design 288 days Thu 12/21/34 69 Construction 2200 days Tue 1/29/36 1432 days Planning 144 days Fri 6/2/34 72 Design 288 days Thu 12/21/34 73 Construction 1000 days Tue 1/29/36 2039 Bond 75 Construct 123 New Cisterns Ph. 4 76 77 78 Planning Design Construction 79 2045 Bond 80 Construct 123 New Cisterns Ph. 5 81 82 83 1 day? Fri 6/1/40 1432 days Mon 6/4/40 144 days Mon 6/4/40 288 days Fri 12/21/40 1000 days W ed 1/29/42 1 day? Fri 6/1/46 935 days Mon 6/4/46 Planning 144 days Mon 6/4/46 Design 288 days Fri 12/21/46 Construction 503 days W ed 1/29/48 84 2051 Bond 0 days? 85 Construct 123 New Cisterns, Ph 6 154 days 86 Planning 87 Design 88 Construction Project: Alternative C Schedule extende Date: Wed 11/6/13 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 Fri 6/2/34 71 74 H1 Fri 6/2/34 Planning Construct 31 New Cisterns Ph. 3 H2 Thu 6/1/34 67 70 H1 Fri 6/2/28 144 days Design 2033 Bond H2 2027 Thu 6/1/28 Planning 63 66 H1 2026 Thu 6/2/22 62 65 H2 2025 Fri 7/8/16 W ed 8/16/17 2021 Bond 54 H1 2024 Mon 12/21/15 1000 days 51 53 H2 2023 Tue 6/2/15 44 47 H1 2022 Tue 6/4/13 39 42 H2 2021 Tue 6/4/13 35 38 H1 2020 Thu 1 1/2/17 27 30 H2 2019 Tue 3/8/16 23 26 H1 2018 Tue 3/8/16 19 22 H2 2017 Fri 7/11/14 15 18 H1 2016 Tue 6/4/13 7 10 H2 2015 Mon 6/3/13 144 days 576 days Wed 11/6/13 Start Tue 6/1/49 Tue 6/1/49 144 days Tue 6/1/49 10 days Mon 12/20/49 0 days Fri 12/31/49 Task Milestone Project Summary External Milestone Inactive Milestone Split Summary External Tasks Inactive Task Inactive Summary Page 1 Manual Task Manual Summary Rollup Start-only Progress Duration-only Manual Summary Finish-only Deadline H2 2028 H1 H2 2029 H1 H2 2030 H1 H2 H1 H2 CS-199 AW SS Alternative C Schedule 2031 H2 2032 H1 H2 2033 H1 H2 2034 H1 H2 2035 H1 H2 2036 H1 H2 2037 H1 H2 2038 H1 H2 2039 H1 H2 2040 H1 H2 Wed 11/6/13 2041 H1 H2 2042 H1 H2 2043 H1 H2 2044 H1 H2 2045 H1 H2 2046 H1 H2 2047 H1 H2 2048 H1 H2 2049 H1 H2 H1 H2 6/1 Project: Alternative C Schedule extende Date: Wed 11/6/13 Task Milestone Project Summary External Milestone Inactive Milestone Split Summary External Tasks Inactive Task Inactive Summary Page 2 Manual Task Manual Summary Rollup Start-only Progress Duration-only Manual Summary Finish-only Deadline Appendix C Program Alternative Schedules Assumptions Alternative C Motorization & addition of seismic switches on three gate valves Planning Design Construction 4th Street Bridge Connection Planning Design Construction PS1 Tunnel upgrade Planning Design Construction Twin Peaks Outlet Connection Planning Design Construction Jones St. Tank Bypass Valves Planning Design Construction Repair suction connections Planning Design Construction SCADA improvements Planning Design Construction FB Manifold R&R Planning Design Construction Pipe Investigation and Repair Planning Design Construction Sutro Connection and PS Planning Design Construction 2014 Bond Reliability Upgrades at Facilities WDs Notes 144 days 1,2 288 days 3,4 288 days 5,6,10,13,14,18,20 144 days 1,2 288 days 3,4 144 days 5,6,7,9 288 days 1,2 432 days 3,4 576 days 5,6,13,14,18 144 days 1,2 288 days 3,4 144 days 5,6,13,14,18 144 days 1,2 288 days 3,4 192 days 5,6,10,13,14,18 144 days 1,2 288 days 3,4 864 days 5,6,7,8,9 144 days 1,2 288 days 3,4 288 days 5,6,10,13,14,18,20 144 days 1,2 288 days 3,4 240 days 5,6,7,8,9 144 days 1,2 288 days 3,4 288 days 5,6,10,13,14,15,17,18,19 226 days 1,2 523 days 3,4 739 days 5,6,10,13,14,18,19,20 Planning Design Construction Cistern Construct 46 New Cisterns, Ph. 1 Planning Design Construction 2021 Bond Pipeline Replacement Program Phase 1 Planning Design Construction New Bay Suction Connections Planning Design Construction 2027 Bond Construct 33 New Cisterns Phase 2 Planning Design Construction 2033 Bond Pipeline Replacement Program Phase 2 Planning Design Construction Construct 31 New Cisterns Ph. 3 Planning Design Construction 2039 Bond Construct 123 New Cisterns Ph. 4 Planning Design Construction 2045 Bond Construct 123 New Cisterns Ph. 5 Planning Design Construction 2051 Bond Construct 123 New Cisterns, Ph 6 Planning Design Construction 144 days 1,2 288 days 3,4 576 days 5,6,10,13,14,18,20 144 days 1,2 288 days 3,4 1000 days 5,6,10,11,13,14,18,20 144 days 1,2 288 days 3,4 2200 days 5,6,10,13,14,15,17,18,19 288 days 1,2 576 days 3,4 576 days 5,6,7,8,9 144 days 1,2 288 days 3,4 1000 days 5,6,10,11,13,14,18,20 144 days 1,2 288 days 3,4 2200 days 5,6,10,13,14,15,17,18,19 144 days 1,2 288 days 3,4 1000 days 5,6,10,11,13,14,18,20 144 days 1,2 288 days 3,4 1000 days 5,6,10,11,13,14,18,20 144 days 1,2 288 days 3,4 503 days 5,6,10,11,13,14,18,20 144 days 1,2 10 days 3,4 0 days 5,6,10,11,13,14,18,20 Appendix D: Insurance CS-199 AWSS Facilities Preliminary Options Study Task 11 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Submitted by MMI Engineering Oakland, California Updated: February 19, 2013 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Contents Introduction and Background ....................................................................................................................... 4 Methodology................................................................................................................................................. 4 Results ........................................................................................................................................................... 6 FRA 36 as an Example of Methodology .............................................................................................. 11 Overall Results .................................................................................................................................... 14 Conclusion ................................................................................................................................................... 20 Work Cited .................................................................................................................................................. 20 Prepared by MMI Engineering February 19, 2013 Page 2 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements List of Figures Figure 1: The cumulative annual rate of occurrence for earthquakes from Type A faults in California (San Andreas Fault affecting San Francisco is a Type A fault). ............................................................................. 6 Figure 2: Comparison of Base+2010 reliability to Base case reliability (the dots are reliability values for the 46 FRAs, and the line is a 45-degree line for reference). ....................................................................... 8 Figure 3: Comparison of Base+2010+A reliability to Base+2010 reliability to assess change in reliability .. 9 Figure 4: Comparison of Base+2010+B reliability to Base+2010 reliability to assess change in reliability .. 9 Figure 5: Comparison of Base+2010+C reliability versus Base+2010 reliability to assess change in reliability ..................................................................................................................................................... 10 Figure 6 : Base case reliabilities with FRA 36 circled. Figure provided by AECOM. .................................... 11 Figure 7: Estimated trends for reliability by earthquake magnitude for FRA 36 that are pegged to the reliability values for M7.8 developed by AECOM. ...................................................................................... 12 Figure 8: Probability Mass Functions (PMFs) for each case of FRA 36 ....................................................... 13 Figure 9: Estimated trends for reliability by earthquake magnitude for the entire city that are based on the population weighted average reliability values for M7.8 developed by AECOM. ............................... 14 Figure 10: Premium percent versus percent savings for city wide premiums ........................................... 16 Figure 11: Reliability Percentage for each FRA (provided by AECOM) ....................................................... 17 Figure 12: Premium Percentages based on Expected Loss for each FRA ................................................... 18 Figure 13: Percentage savings versus no HPS for each FRA ....................................................................... 19 List of Tables Table 1: Reliability Values by FRA for each of the four cases provided by AECOM ...................................... 7 Table 2: Provided Reliability values for FRA 36 for a 7.8 M earthquake .................................................... 11 Table 3: Estimated premium values for relative comparisons of different cases for FRA 36..................... 13 Table 4: Citywide Premiums and Reliabilities averaged by population of each FRA .................................. 15 Table 5: Population weighted citywide reliability, premiums and savings for entire city .......................... 20 Prepared by MMI Engineering February 19, 2013 Page 3 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Introduction and Background AECOM provided MMI with planning levels results on the AWSS for the following cases: • • • • • Base Case: With current infrastructure on ground in San Francisco 2010 Bond Improvements, referred to as “2010” case in this document Alternative A: Proposed improvement alternative beyond 2010 Bond improvements Alternative B: Another proposed alternative Alternative C: A third proposed alternative Brief descriptions of each alternative were provided in presentation slides and exhibits by AECOM. From the above cases, the following cases were articulated by MMI as indicative of options of the final state of AWSS infrastructure in the city of San Francisco. • • • • • Base Case Base Case + 2010 Improvements Base case + 2010 improvements + Alternative A Base case + 2010 improvements + Alternative B Base case + 2010 improvements + Alternative C Neighborhood specific reliability percentages are provided for 46 different zones (referred to as fire response areas, FRAs) in San Francisco for each of the above case. Reliability being defined as percent of imposed water demand that is met by AWSS infrastructure, from fires resulting due to a median ground motion for a magnitude 7.8 earthquake on the San Andreas fault. The objective for MMI is to gage whether any planning level assessment can be made on impact of above cases (referred to as Base Case, 2010, A, B, and C in the remainder of the document) on fire premiums in a relative sense. Meaning exact absolute values of fire insurance premiums are not sought in this task, rather a relative comparison of specifically alternatives A, B, and C is sought on fire premiums. Indicative values of savings in fire premiums for each case is also provided based on use of data provided for the Base Case in (Scawthorn, November 2012). Methodology MMI developed a methodology to estimate the fire premium for the purpose of conducting a relative comparison of impact on fire premium of the different cases to be analyzed. What is available from fire simulations is the reliability (see definition in previous section) of the AWSS for M7.8 earthquake on the San Andreas fault for 46 FRAs in the city of San Francisco. Fire premiums are influenced not just by a M7.8 earthquake but by the entire spectrum of possible earthquakes and also from non-earthquake fires. The steps in the methodology devised are: Prepared by MMI Engineering February 19, 2013 Page 4 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements • • • • • First, utilize the earthquake magnitude recurrence relationship for the city of San Francisco, which gives the annual frequency of earthquakes of different magnitudes. From this we develop annual probabilities of different earthquakes assuming a Poisson occurrence of earthquakes. Next, we develop reliability values of the AWSS system for a wide range of earthquakes pegging the M7.8 reliability values to those provided by AECOM for the four cases for each of the FRAs. This extrapolation is with the simple intent of modeling higher resulting reliabilities in smaller earthquakes 1. Then for each earthquake, for each case and for each FRA a beta distribution of loss risk is developed assuming the average loss risk is [1-Reliability] and the COV is assumed to be 50%. This coefficient of variation (COV, ratio of standard deviation to the mean value) is assumed to model in a simple fashion the uncertainty in fire loss given a reliability value (meaning given a reliability value in an FRA, the actual fire loss still could have a range of loss values). Then the probability mass function of loss risk for each earthquake is convolved with the annual probabilities of different earthquakes to obtain mean values and standard deviation of fire loss risk for each case of each FRA. Finally, we combine the mean and 75% of standard deviation to develop a notional fire premium to conduct the relative comparison. The value of 75% is arbitrary and is utilized to include the uncertainty in loss risk around the mean, and the same value of 75% is used in all cases compared. The above simplifying assumptions provided a planning level assessment of the impact of the AWSS on fire insurance premiums. All assumptions made can be improved upon in future studies. The estimated trends of reliability for magnitudes other than M7.8 are largely subjective and can also be improved by detailed analysis of the infrastructure, and also by inclusion of non-earthquake fires. 1 The approach adopted was to fit a lognormal distribution with parameters of the distribution tuned so as to replicate the reliability values for M7.8 earthquake for each FRA (see Figure 7, for example). Prepared by MMI Engineering February 19, 2013 Page 5 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Results Figure 1 shows the earthquake magnitude recurrence relationship, which is the annual rate of occurrence for earthquake greater than or equal to a given magnitude. For example, the average rate of earthquakes of magnitude 6 or greater is about 0.1 per year. 1 Cumulative Rate (per year) 0.1 0.01 0.001 0.0001 5 5.25 5.5 5.75 6 6.25 6.5 6.75 7 7.25 7.5 7.75 8 8.25 8.5 Magnitude Figure 1: The cumulative annual rate of occurrence for earthquakes from Type A faults in California (San Andreas Fault 2 affecting San Francisco is a Type A fault) . AECOM provided the following reliability values for M7.8 San Andreas earthquake for this study. The population weighted averages are found using the population of each FRA. Note that a population weighting is used here as a proxy for building density across FRAs in the city; this has been done in order to reflect the loss of property value to fire in a very simple manner. One could use an arithmetic average (referred to as “cumulative” average in the Table 1) for simplicity. The population weighted averages are generally similar to the cumulative average. These FRAs are plotted for comparison purposes in Figure 11. 2 These are cumulative earthquake occurrence rates for Fault Type A taken from Bulletin of the Seismological Society of America, Vol. 99, No. 4, pp. 2053–2107, August 2009, doi: 10.1785/0120080049. Uniform California Earthquake Rupture Forecast, Version 2 (UCERF 2) by E. H. Field, T. E. Dawson, K. R. Felzer, A. D. Frankel, V. Gupta, T. H. Jordan, T. Parsons, M. D. Petersen, R. S. Stein, R. J. Weldon II, and C. J. Wills. The data from this reference is also used by (Scawthorn, November 2012). Prepared by MMI Engineering February 19, 2013 Page 6 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Table 1: Reliability Values by FRA for each of the four cases provided by AECOM Reliability FRA Pop Weighted Cumulative 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 20 21 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 Prepared by MMI Engineering Base Case Base+2010 Base+2010+A Base+2010+B Base+2010+C 0.420 0.474 0.035 0.035 0.249 0.116 0.285 0.137 0.013 0.224 0.067 0.258 0.200 0.158 0.033 0.211 0.527 0.222 0.159 0.055 0.053 0.443 0.305 0.996 0.933 0.552 0.988 1.000 0.810 1.000 0.658 0.340 0.570 0.437 1.000 0.202 0.362 0.662 0.367 1.000 1.000 0.931 0.977 1.000 0.251 0.239 0.753 1.000 0.623 0.678 0.044 0.035 0.470 0.192 0.738 0.155 0.093 0.174 0.095 0.804 0.205 0.384 0.260 0.626 0.765 0.754 0.344 0.082 0.103 1.000 0.781 1.000 1.000 1.000 1.000 1.000 0.893 1.000 0.818 1.000 1.000 0.443 1.000 0.942 0.427 0.810 0.758 1.000 1.000 1.000 1.000 1.000 1.000 1.000 0.978 1.000 0.886 0.896 0.631 0.585 0.813 0.945 0.817 0.930 0.817 0.640 0.530 0.829 1.000 1.000 0.721 0.847 0.948 0.767 0.526 0.835 0.856 1.000 0.887 1.000 1.000 1.000 1.000 1.000 0.906 1.000 0.772 1.000 1.000 1.000 1.000 0.956 1.000 0.908 0.758 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 February 19, 2013 0.912 0.918 0.714 0.527 0.848 0.992 0.836 0.955 0.893 0.794 0.515 0.876 1.000 1.000 0.698 0.853 0.995 0.814 0.553 0.882 0.903 1.000 0.928 1.000 1.000 1.000 1.000 1.000 0.953 1.000 0.921 1.000 1.000 1.000 1.000 1.000 1.000 1.000 0.758 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 0.841 0.859 0.524 0.553 0.924 0.593 1.000 0.612 0.525 0.584 0.505 1.000 0.586 0.824 0.709 0.987 0.815 1.000 0.596 0.521 0.563 1.000 1.000 1.000 1.000 1.000 1.000 1.000 0.893 1.000 1.000 1.000 1.000 0.700 1.000 0.942 0.669 1.000 0.869 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 Page 7 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements It is also informative to look at changes in reliability across different cases by pair-wise comparisons of reliability as in the Figures below. These comparisons have been made to understand how the fire premium results can be anticipated to change by each FRA (and for entire city) for the different improvement packages, since the reliability values form the basis of fire premium results. These figure show that for most FRAs the reliability value increases owing to improvements made; however, there appear to some FRAs for which the reliability may decreases owing to improvements made city-wide; this is likely due to rerouting of water. 120 Base+2010 Reliability (%) 100 80 60 40 20 0 0 20 40 60 80 100 120 Base Case Reliability (%) Figure 2: Comparison of Base+2010 reliability to Base case reliability (the dots are reliability values for the 46 FRAs, and the line is a 45-degree line for reference). Prepared by MMI Engineering February 19, 2013 Page 8 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Base+2010+A Reliability (%) 120 100 80 60 40 20 0 0 20 40 60 80 100 120 Base+2010 Reliability (%) Figure 3: Comparison of Base+2010+A reliability to Base+2010 reliability to assess change in reliability Base+2010+B Reliability (%) 120 100 80 60 40 20 0 0 20 40 60 80 100 120 Base+2010 Reliability (%) Figure 4: Comparison of Base+2010+B reliability to Base+2010 reliability to assess change in reliability Prepared by MMI Engineering February 19, 2013 Page 9 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Base+2010+C Reliability (%) 120 100 80 60 40 20 0 0 20 40 60 80 100 120 Base+2010 Reliability (%) Figure 5: Comparison of Base+2010+C reliability versus Base+2010 reliability to assess change in reliability Prepared by MMI Engineering February 19, 2013 Page 10 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements FRA 36 as an Example of Methodology To better convey the methodology, the intermediate and final results of FRA 36 are provided before the city wide and overall results are presented. FRA 36 is located in downtown San Francisco. It can be seen in Figure 6 below (FRA 36 has a reliability number of 20% for base case, and the location of FRA 36 is shown using black circle in figure below) which shows the reliability values for all FRAs for the base case. Figure 6 : Base case reliabilities with FRA 36 circled. Figure provided by AECOM. Reliabilities for all four cases were estimated for a range of earthquakes based on the provided values for the 7.8 M earthquake (see Section Methodology for approach adopted for this estimation). The 7.8 M reliabilities are shown in Table 2. Table 2: Provided Reliability values for FRA 36 for a 7.8 M earthquake Base Case 0.202 Base + 2010 0.942 Prepared by MMI Engineering Base + 2010 +A 0.956 February 19, 2013 Base + 2010 + B 1.000 Base + 2010 + C 0.942 Page 11 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements For FRA 36 the extrapolated reliabilities for a range of earthquakes are shown in the figure below. This figure indicates that case 2010 and case C have the same reliabilities. This is true for FRA 36, but not true for all the FRAs. For an overall reliability by earthquake magnitude plot see Figure 9, this figure shows each case has its own set of citywide reliabilities. 1.0 0.9 0.8 0.7 Base Case Reliability 0.6 Base+2010 0.5 Base+2010+A Base+2010+B 0.4 Base+2010+C 0.3 M7.8 0.2 0.1 0.0 5.5 6 6.5 7 7.5 8 8.5 9 9.5 Magnitude Figure 7: Estimated trends for reliability by earthquake magnitude for FRA 36 that are pegged to the reliability values for M7.8 developed by AECOM. Recall from the Methodology section that we combine the earthquake magnitude cumulative rates (or the annual probability of occurrence of each earthquake magnitude) with reliability values to develop a fire loss risk probability distribution. For each case for FRA 36 a Beta probability distribution for loss is calculated, these distributions are based on mean and standard deviation of loss risk for each earthquake, and on the annual occurrence probability of different earthquake magnitudes (from Figure 1). The reason for selecting a Beta distribution (vs. other probability distribution types, e.g. Normal or Lognormal) is that this distribution permits specification of minimum (0%) and maximum (100% of value) loss values for an FRA. The probability mass functions (PMFs) of fire loss value of FRA 36 can be seen for each of the five cases in Figure 8. The x-axis represents the fraction of value of lost to fire in a given FRA, and the y-axis the probability of loss of a given value. Note that case 2010, A, B and C are all very close and overlap on the figure. Figure 8 clearly shows that as the reliability increases in value (as in Cases 2010, A, B, and C), the loss distribution shifts to the left Prepared by MMI Engineering February 19, 2013 Page 12 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements (to lower loss values) compared to the base case which has a lower reliability value compared to 2010, A, B or C. Figure 8: Probability Mass Functions (PMFs) for each case of FRA 36 The expected value of loss is then calculated for each case based on the PMF (mathematically the expected value is the probability weighted sum of the loss risk values). These values for FRA 36 are provided in Table 3 for relative comparison purposes only. The Premium value is based on the expected loss (E [Loss]) plus 75% of the standard deviation (Sig [Loss]). Again, as noted in the Methodology section, 75% is somewhat arbitrary and has been used to reflect what is done typically in the insurance industry to account for year to year variability of loss in the fire premium calculation. Note that this is not an absolute value of a fire premium, only notional to permit relative comparison of the Alternatives A, B, and C being proposed. Table 3: Estimated premium values for relative comparisons of different cases for FRA 36. Base Case Base+2010 Base+2010+A Base+2010+B Base+2010+C Premium Sig [ Loss ] E [ Loss ] 38% 23% 21% 2.0% 2.3% 0.33% 1.8% 2.1% 0.24% 0.18% 0.24% 0.0021% 2.0% 2.3% 0.33% The calculations done for FRA 36 were done for each FRA in the city. These premium results were then combined across all FRAs, and analyzed to find quantitative comparisons between the four cases. Prepared by MMI Engineering February 19, 2013 Page 13 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Overall Results Figure 9 shows the city wide estimate trend assumed for a range of earthquakes that are based on the population weighted reliability values 3 for M7.8 (see for Table 1 city-wide reliability value). The intent is to capture the possible increase in reliability with decreasing earthquake magnitude. The figure shown is for the entire city reliability values, but during analysis these were created for each FRA. 1.0 0.9 0.8 0.7 Base Case Reliability 0.6 Base+2010 0.5 Base+2010+A Base+2010+B 0.4 Base+2010+C 0.3 M7.8 0.2 0.1 0.0 5.5 6 6.5 7 7.5 8 8.5 9 9.5 Magnitude Figure 9: Estimated trends for reliability by earthquake magnitude for the entire city that are based on the population weighted average reliability values for M7.8 developed by AECOM. Figure 11 provides the reliability percentages per FRA per case. Average values for two cases are indicated in the figure to gage the spread of results across FRAs compared to the city-wide (population weighted) average. Figure 12 provides the calculated premiums for each FRA. As a quick check between Figure 11 and Figure 12, it can be seen that as reliability approaches 100%, the premium approaches zero. A weighted average was applied to the premiums of each FRA by population of each FRA compared to the entire city. These values are shown in Table 4. This table also provides estimates of reinsurance premiums. These premiums are based on the assumption that only loss percentages over 80% are covered by a 3 Note that as mentioned earlier, a simple arithmetic average instead of a populated weighted average would yield similar results. Here the population-weighted average is adopted for account for the varying population across the FRAs covering the city. Prepared by MMI Engineering February 19, 2013 Page 14 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements reinsurance policy. As an example, in Figure 8, the area under the entire Base Case (red, dash-dot) curve is the mean loss used to calculate fire premium, while the area under the same Base Case curve above loss risk values of 0.8 is the mean loss for reinsurance premium calculation. Table 4: Citywide Premiums and Reliabilities averaged by population of each FRA Base Case Base+2010 Base+2010+A Base+2010+B Base+2010+C Reliability Premium Reinsurance Premium 42% 32% 3.3% 62% 19% 1.9% 89% 3.9% 0.15% 91% 3.1% 0.104% 84% 5.5% 0.105% The premium and reinsurance calculations follow similar trends. Both results indicate that the Alternative B offers the most reduction in fire premium, with a notional fire premium of 3.1%. Alternative A results in a notional fire premium of 3.9%, which is almost as good as Alternative B. Finally, Alternative C results in 5.5% notional fire premium. This appears to follow the relative trend among the city wide populated-weighted reliability values of 89%, 91%, and 84% for Alternative A, B, and C, respectively, with the most reliable alternative (i.e., B) resulting in the least fire premium, while Alternative C with highest notional premium due to the smallest reliability value of the three alternatives A, B, and C. The final piece of results to discuss is the amount of savings in terms of the premiums described in “Insurance Aspects: A report prepared for the San Francisco Public Utilities Commission” (Scawthorn, November 2012). In this report it states “the AWSS HPS can be thought of as reducing San Francisco’s insurance premiums by about 6-8%.” To equilibrate those numbers to the premiums found in this paper, the citywide premium savings for the Base Case was set to 7%. From there all the other savings percentages were calculated based on their percent difference from the citywide Base Case. These conversions can be seen in Figure 10. As the calculated premiums go down, the percent savings go up. Prepared by MMI Engineering February 19, 2013 Page 15 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements % Premium (Population Weighted) 35% % Savings versus no HPS 31.7% 30% 25% 19.3% 20% 15% 10% 13.1% 13.3% 12.8% 9.7% 7.0% 3.9% 5% 5.5% 3.1% 0% Base Case Base + 2010 Base + 2010 + A Base + 2010 + B Base + 2010 + C Figure 10: Premium percent versus percent savings for city wide premiums This same procedure can be used on individual FRAs, which is shown in Figure 13. Based on the calculation method, the maximum savings possible is 14%. The savings are expected to plateau as premiums go down; updates to the AWSS system will never produce 100% savings on insurance. The 14% value seen in these calculations is based on the initial savings value of 7%. Note that this is an approximate analysis for use in planning and further detailed analysis can be performed. Prepared by MMI Engineering February 19, 2013 Page 16 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements (Base Case) Average (Base + 2010 + B) Average (Base Case) (Base + 2010) (Base + 2010 + A) (Base + 2010 + B) (Base + 2010 + C) 100% 90% 80% Reliability Percentage 70% 60% 50% 40% 30% 20% 10% 0% 0 5 10 15 20 25 30 35 FRA by number Figure 11: Reliability Percentage for each FRA (provided by AECOM) Prepared by MMI Engineering February 19, 2013 Page 17 40 45 50 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements (Base Case) Average (Base + 2010 + B) Average (Base Case) (Base + 2010) (Base + 2010 + A) (Base + 2010 + B) (Base + 2010 + C) 100% 90% 80% Premium Percentage 70% 60% 50% 40% 30% 20% 10% 0% 0 5 10 15 20 25 30 35 FRA by number Figure 12: Premium Percentages based on Expected Loss for each FRA Prepared by MMI Engineering February 19, 2013 Page 18 40 45 50 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements (Base + 2010) (Base Case) (Base + 2010 + A) (Base + 2010 + B) (Base + 2010 + C) 15% Percentage Savings versus no HPS 10% 5% 0% -5% -10% 0 5 10 15 20 25 30 35 FRA by number Figure 13: Percentage savings versus no HPS for each FRA Prepared by MMI Engineering February 19, 2013 Page 19 40 45 50 Assessing Planning Level Impact on Fire Premiums from AWSS Improvements Conclusion Table 5 summarizes the key results of this study for the entire city; the results include AWSS reliability for the five cases analyzed, the notional fire premium, the estimated reinsurance premium, and finally the fire premium savings for the five cases. Comparison of the notional fire premiums indicates that Alternative B results in the least premium, followed by Alternative A with marginally higher premium. This is followed by Alternative C, with the highest resulting premium of the three, due largely to Alternative C having the least reliability of the three alternatives (A, B, and C). Alternative B results in a 13.3% savings versus not having a HPS at all. Table 5: Population weighted citywide reliability, premiums and savings for entire city Base Case Base+2010 Base+2010+A Base+2010+B Base+2010+C Reliability Premium Reinsurance Premium 42% 32% 3.3% 62% 19% 1.9% 89% 3.9% 0.15% 91% 3.1% 0.104% 84% 5.5% 0.105% Savings versus no HPS 7.0% 9.7% 13.1% 13.3% 12.8% Work Cited Scawthorn, C. (November 2012). Insurance Aspects: A Report prepared for the San Francisco Public Utilities Commission. San Francisco. E. H. Field, T. E. Dawson, K. R. Felzer, A. D. Frankel, V. Gupta, T. H. Jordan, T. Parsons, M. D. Petersen, R. S. Stein, R. J. Weldon II, and C. J. Wills. August 2009. Bulletin of the Seismological Society of America, Vol. 99, No. 4, pp. 2053–2107 doi: 10.1785/0120080049. Uniform California Earthquake Rupture Forecast, Version 2 (UCERF 2). Prepared by MMI Engineering February 19, 2013 Page 20 Appendix E: Evaluation Scoring CS-199 AWSS Facilities Preliminary Options Study Task 11 Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Evaluation Criteria: Capital & Life Cycle Cost Pairwise Comparisons: Alternative A is worse than Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C How to Score: Comparing Alternative 1 (Row) to Alternative 2 (Column) SCORE 1 is significantly better than 2 10 1 is better than 2 5 1 is about the same as 2 1 1 is worse than 2 1/5 1 is significantly worse than 2 1/10 Scoring Matrix: A A B 5.00 C 0.10 B C TOTAL % OF TOTAL 0.20 10.00 10.20 40.16% 10.00 15.00 59.06% 0.20 0.79% 25.40 100.00% 0.10 Total 1 of 8 Cost Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Evaluation Criteria: Operations & Maintenance Pairwise Comparisons: Alternative A is worse than Alternative B Alternative A is better than Alternative C Alternative B is significantly better than Alternative C How to Score: Comparing Alternative 1 (Row) to Alternative 2 (Column) SCORE 1 is significantly better than 2 10 1 is better than 2 5 1 is about the same as 2 1 1 is worse than 2 1/5 1 is significantly worse than 2 1/10 Scoring Matrix: A A B 5.00 C 0.20 B C TOTAL % OF TOTAL 0.20 5.00 5.20 25.37% 10.00 15.00 73.17% 0.30 1.46% 20.50 100.00% 0.10 Total 2 of 8 Operations and Maintenance Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Evaluation Criteria: Schedule Pairwise Comparisons: Alternative A is about the same as Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C How to Score: Comparing Alternative 1 (Row) to Alternative 2 (Column) SCORE 1 is significantly better than 2 10 1 is better than 2 5 1 is about the same as 2 1 1 is worse than 2 1/5 1 is significantly worse than 2 1/10 Scoring Matrix: A A B 1.00 C 0.10 B C TOTAL % OF TOTAL 1.00 10.00 11.00 49.55% 10.00 11.00 49.55% 0.20 0.90% 22.20 100.00% 0.10 Total 3 of 8 Schedule Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Evaluation Criteria: Delivery Reliability Pairwise Comparisons: Alternative A is worse than Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C How to Score: Comparing Alternative 1 (Row) to Alternative 2 (Column) SCORE 1 is significantly better than 2 10 1 is better than 2 5 1 is about the same as 2 1 1 is worse than 2 1/5 1 is significantly worse than 2 1/10 Scoring Matrix: A A B 5.00 C 0.10 B C TOTAL % OF TOTAL 0.20 10.00 10.20 40.16% 10.00 15.00 59.06% 0.20 0.79% 25.40 100.00% 0.10 Total 4 of 8 Delivery Reliability Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Evaluation Criteria: Firefighting Capability Pairwise Comparisons: Alternative A is about the same as Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C How to Score: Comparing Alternative 1 (Row) to Alternative 2 (Column) SCORE 1 is significantly better than 2 10 1 is better than 2 5 1 is about the same as 2 1 1 is worse than 2 1/5 1 is significantly worse than 2 1/10 Scoring Matrix: A A B 1.00 C 0.10 B C TOTAL % OF TOTAL 1.00 10.00 11.00 49.55% 10.00 11.00 49.55% 0.20 0.90% 22.20 100.00% 0.10 Total 5 of 8 Firefighting Capability Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Evaluation Criteria: Insurance Premiums Pairwise Comparisons: Alternative A is worse than Alternative B Alternative A is significantly better than Alternative C Alternative B is significantly better than Alternative C How to Score: Comparing Alternative 1 (Row) to Alternative 2 (Column) SCORE 1 is significantly better than 2 10 1 is better than 2 5 1 is about the same as 2 1 1 is worse than 2 1/5 1 is significantly worse than 2 1/10 Scoring Matrix: A A B 5.00 C 0.10 B C TOTAL % OF TOTAL 0.20 10.00 10.20 40.16% 10.00 15.00 59.06% 0.20 0.79% 25.40 100.00% 0.10 Total 6 of 8 Insurance Premiums Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Evaluation Criteria: Environmental / Community Impacts Pairwise Comparisons: Alternative A is worse than Alternative B Alternative A is better than Alternative C Alternative B is significantly better than Alternative C How to Score: Comparing Alternative 1 (Row) to Alternative 2 (Column) SCORE 1 is significantly better than 2 10 1 is better than 2 5 1 is about the same as 2 1 1 is worse than 2 1/5 1 is significantly worse than 2 1/10 Scoring Matrix: A A B 5.00 C 0.20 B C TOTAL % OF TOTAL 0.20 5.00 5.20 25.37% 10.00 15.00 73.17% 0.30 1.46% 20.50 100.00% 0.10 Total 7 of 8 Environmental Impacts Auxiliary Water Supply System Capital Improvement Program Alternatives Analysis Pairwise Comparisons Weighting of Evaluation Criteria Criterion Weight Ranked Alternative Score Capital & Life Cycle Cost 1.00 1. Alternative B 60% Operations & Maintenance 1.00 2. Alternative A 39% Schedule 1.00 3. Alternative C 1% Delivery Reliability 1.00 Firefighting Capability 1.00 Insurance Premiums 1.00 Environmental / Community Impacts 1.00 Evaluation Criteria Total 7.00 Weighted Cumulative Scores Evaluation Criteira Alternative Capital & Life Cycle Cost Operations & Maintenance Delivery Reliability Firefighting Capability Insurance Premiums Environmental / Community Impacts Score Schedule A 40% 25% 50% 40% 50% 40% 25% 39% B 59% 73% 50% 59% 50% 59% 73% 60% C 1% 1% 1% 1% 1% 1% 1% 1% Total 100% 100% 100% 100% 100% 100% 100% 100% 8 of 8 Cumulative Scores