Connaect 2014
Transcription
Connaect 2014
THE MAGAZINE OF THE GLOBAL BBR NETWORK OF EXPERTS Edition 8 | 2014 NEW HORIZONS – PAST, PRESENT AND FUTURE Revealing how the BBR Network has stayed one step ahead for 70 years INNOVATIVE TUNNEL CONSTRUCTION Creating new approaches to deliver Zurich rail link tunnel UNCLOGGING THE BOTTLENECK Rising to the challenges of widening a major expressway in Singapore EUROPE’S LARGEST LIFT BRIDGE Realizing new infrastructure for expansion of Europe’s biggest port at Rotterdam GOING UNDERGROUND Specialist techniques for remedial work in major Auckland sewer www.bbrnetwork.com The BBR Network is recognized as the leading group of specialized engineering contractors in the field of post-tensioning, stay cable and related construction engineering. The innovation and technical excellence, brought together in 1944 by its three Swiss founders – Antonio Brandestini, Max Birkenmaier and Mirko Robin Ros – continues, 70 years later, in that same ethos and enterprising style. From its Technical Headquarters and Business Development Centre in Switzerland, the BBR Network reaches out around the globe and has at its disposal some of the most talented engineers and technicians, as well as the very latest internationally approved technology. THE GLOBAL BBR NETWORK Within the Global BBR Network, established traditions and strong local roots are combined with the latest thinking and leading edge technology. BBR grants each local BBR Network Member access to the latest technical knowledge and resources – and facilitates the exchange of information on a broad scale and within international partnering alliances. Such global alliances and co-operations create local competitive advantages in dealing with, for example, efficient tendering, availability of specialists and specialized equipment or transfer of technical know-how. ACTIVITIES OF THE NETWORK All BBR Network Members are well-respected within their local business communities and have built strong connections in their respective regions. They are all structured differently to suit the local market and offer a variety of construction services, in addition to the traditional core business of post-tensioning. BBR TECHNOLOGIES & BRANDS BBR technologies have been applied to a vast array of different structures – such as bridges, buildings, cryogenic LNG tanks, dams, marine structures, nuclear power stations, retaining walls, tanks, silos, towers, tunnels, wastewater treatment plants, water reservoirs and wind farms. The BBR brands and trademarks – CONA®, BBRV®, HiAm®, HiEx, DINA®, SWIF®, BBR E-Trace and CONNÆCT® – are recognized worldwide. The BBR Network has a track record of excellence and innovative approaches – with thousands of structures built using BBR technologies. While BBR’s history goes back over 70 years, the BBR Network is focused on constructing the future – with professionalism, innovation and the very latest technology. BBR VT International Ltd is the Technical Headquarters and Business Development Centre of the BBR Network located in Switzerland. The shareholders of BBR VT International Ltd are: BBR Holding Ltd (Switzerland), a subsidiary of the Tectus Group (Switzerland); KB Spennteknikk AS (Norway), BBR Polska z o.o. (Poland) and KB Vorspann-Technik GmbH (Germany) – all three are members of KB Group (Norway); BBR Pretensados y Tecnicas Especiales PTE, S.L. (Spain), a member of the FCC Group (Spain). 02 CONNÆCT | EDITION 8 INNOVATION MEETS COMMITMENT In 2014, BBR marks the 70th Anniversary of its founding which was firmly rooted in the Swiss values of technical excellence, quality service and commitment to innovation. Seven decades later, BBR Network Members continue to apply these principles to meet the challenges of new and often innovative projects, delivering the highest quality construction engineering solutions around the globe. As well as CONNÆCT 2014, this year we are producing a special BBR 70th Anniversary magazine (see next pages) – contact your local BBR Network Member to secure a copy. In the Portfolio section of this edition of CONNÆCT, you will see that teams THE MAGAZINE OF THE GLOBAL BBR NETWORK OF EXPERTS Edition 8 | 2014 of BBR PT Specialists the world over are engaging proactively with customer requirements to provide and maintain the infrastructure that we need to conduct our daily lives. Innovation and excellence can clearly be seen in recent BBR Network projects – such as the stunning new footbridge in Auckland, New Zealand and the widening of the Keppel Viaduct, a major highway in Singapore. NEW HORIZONS – PAST, PRESENT AND FUTURE Equally, a post-tensioned approach to buildings – with the support of qualified professionals from within the BBR Network – is delighting customers for Revealing how the BBR Network has stayed one step ahead for 70 years INNOVATIVE TUNNEL CONSTRUCTION Creating new approaches to deliver Zurich rail link tunnel commercial, residential and public buildings, as well as car parks. UNCLOGGING THE BOTTLENECK Rising to the challenges of widening a major expressway in Singapore EUROPE’S LARGEST LIFT BRIDGE Realizing new infrastructure for expansion of Europe’s biggest port at Rotterdam GOING UNDERGROUND Specialist techniques for remedial work in major Auckland sewer One thing shines through loud and clear – the BBR Network has the specialist technology and know-how to satisfy some of the most demanding projects on the face of the earth... and, if a solution does not already exist, they will devise and design one! This is admirably demonstrated by Members’ work on a city center railway tunnel in Zurich and on foundations for a new container port on the Adriatic. You can also check out the latest news and views in Talking BBR which, this time, includes interviews with BBR management who share their thoughts on aspects of the business and an overview of BBR events around the world over the last 12 months. www.bbrnetwork.com Last but not least, in the Technology section, we share updates on BBR technology and R&D, as well as information about specialist techniques – such as MRR and tendon prefabrication – used by BBR Network Members to deliver customer requirements effectively. In this 70th Anniversary year especially, we would like to take the opportunity to thank all the BBR project managers and engineers, BBR site managers and technicians – and, of course, the senior management within each BBR Network Member – around the world for the part they have played in carrying both our technological development and dedication to customer service forwards. Together, we have created a blueprint for sustainable success. Marcel Poser Chairman, BBR VT International Ltd José Manuel Illescas Vice Chairman, BBR VT International Ltd www.bbrnetwork.com 03 BBR 70TH ANNIVERSARY 1944-2014 TIME TRAVEL WITH BBR The award-winning Sunniberg Bridge – near the Swiss alpine ski resort of Klosters – represents the culmination of years of technological development at BBR, combined with the skills and inspiration of leading Swiss designer Christian Menn. The story of the realisation of this bridge, along with many other articles about BBR's great past, present – and future – will shortly feature in a special 70th Anniversary magazine which will mark our milestone anniversary. Prepare to be amazed at the innovation always keeping one step ahead, still has applied by BBR in the early days and wonder the very latest technology – and an at the ambitious schemes undertaken. innovative business model which reflects It's a breath-taking journey through: the current and upcoming needs of the • world-record construction projects of global market place. every size, shape and type • collaboration with some of the world's greatest engineers and architects • evolution of the BBR business This special edition examines the earliest days of BBR technology, its development over the past 70 years, our Swiss roots and values, plus an insight into some of the model into the world's first franchise pioneering techniques and most exciting of its kind projects, as well as offering a glimpse into BBR has a stunning heritage stretching the future. Copies are available from your back over seven decades and today, by local BBR Network Member. 04 CONNÆCT | EDITION 8 ANNIVERSARY QUIZ Test your knowledge of BBR and let us know if you can name the projects shown in the following photographs. To receive a special BBR 70th Anniversary prize, the winning entrant must identify all five projects correctly – stating the project name and its location. Entries should be sent to info@bbrnetwork.com and must be received by 31st July 2014. 1 2 3 4 5 www.bbrnetwork.com 05 CONTENTS EDITORIAL, SOURCES AND REFERENCES 07 TALKING BBR 08 BUSINESS REVIEW 11 CONFERENCE NOTES 12 A YEAR TO REMEMBER 14 PERSPECTIVE 15 PORTFOLIO 16 BRIDGES EDITORIAL OFFICE BBR VT International Ltd Technical Headquarters and Business Development Centre Switzerland www.bbrnetwork.com info@bbrnetwork.com EDITOR Jane Sandy CONTRIBUTING EDITOR Juan Maier DESIGNER Jenny Chillingworth 58 MRR CONTRIBUTORS George Ajaman, Kresimir Bogadi, Norbert Bogensperger, Antonio Caballero, Chee Cheong Chang, Ron van Dijk, Lee Jian Feng, Richard Gaskill, HM Goh, Christophe Gout, Peter Higgins, Warwick Ironmonger, Tomasz Jendernal, Sean Kelly, Tan Yeow Koon, Chuen Lin Lee, Bartosz Lukijaniuk, Behzad Manshadi, Valentina Mihajlovic, Claude Néant, Tim Pahapill, Fabian Persch, Jan Piekarski, Vince Ponzio, Thomas Richli, Mark Sinclair, Rey Singh, Stig Sjolbør, Oliver Smith, John Taraldsen, Tore Thorstensen, Guillaume Wastiaux, Paul Wymer, Janelle Yeo TECHNOLOGY PUBLISHER BBR VT International Ltd NUMBER OF COPIES 8,000 33 BUILDINGS 44 STAY CABLES 47 TANKS & SILOS 50 SPECIAL APPLICATIONS 63 64 RESEARCH & DEVELOPMENT 68 TECHNICAL UPDATE 70 TECHNIQUES 72 INSIGHT 77 BBR DIRECTORY Every effort is made to ensure that the content of this edition is accurate but the publisher accepts no responsibility for effects arising there from. p-ISSN 1664-6606 e-ISSN 1664-6614 © BBR VT International Ltd 2014 SOURCES AND REFERENCES Portfolio section Crushing victory: www.cimentsdelarochelle.fr (accessed January 2014) Reviving a bold statement: www.theparabola-kensington.co.uk/the_parabola_book.pdf (accessed January 2014) Symbol of progress: www.euroinfrastructure.eu & www.premier.gov.pl (accessed January 2014) Containing strength for Adriatic: www.portauthority.hr (accessed January 2014) This paper is manufactured with 15% recycled fibre, FSC certified. All pulps used are Elemental Chlorine Free (EFC) and the manufacturing mill is accredited with the ISO14001 standard for environmental management. Vegetable based inks have been used and 85% of all waste associated with this product has been recycled. 06 CONNÆCT | EDITION 8 TALKING BBR 08 BUSINESS REVIEW Thomas Richli and Dr. Antonio Caballero share observations on the past and visions for the future 11 CONFERENCE NOTES reflections on the 2013 Annual Global BBR Conference in Auckland, New Zealand, shared by Juan Maier, from BBR HQ 12 A YEAR TO REMEMBER a small selection of BBR Network highlights from around the globe – events, awards and training 14 PERSPECTIVE BBR VT International’s newest Board member, Tore Thorstensen, offers his take on what makes the BBR Network so successful www.bbrnetwork.com 07 TALKING BBR BUSINESS REVIEW BBR VT’s senior executives reflect on learning and direction NEW HORIZONS – PAST, PRESENT AND FUTURE The 70th Anniversary of BBR’s founding in 2014 presents an interesting opportunity to reflect on the past, the present and the future. BBR VT International Ltd’s CEO, Dr. Antonio Caballero and Thomas Richli, Chief Business Development Officer, share their observations and visions for the future. Why is history relevant to today – and to and then, with the enthusiasm and support the future? of contacts, commercialized it globally. TR: People sometimes say that we need As time passed, they saw opportunities to understand where we have been, so that to expand the range of technology – and, we can understand where we need to go. through the foundation of Proceq, even In the case of BBR, it’s clear that when developed a range of equipment to help Max Birkenmaier, Antonio Brandestini and in their work. Mirko Robin Roš began the partnership they knew they had created something AC: Our history gives us our identity – our special – something useful – and they were founders’ interest in and their passion for taking the right steps to ensure their ideas coming up with something new certainly would be developed further. continue today. Back then, the business They were creating something which did not was technology driven, today it is driven exist before, their goal was the development by customer needs. However, the quest of new and reliable construction technology. for further knowledge and improvement They networked energetically on the on all fronts will never end – the journey architecture and construction engineering begun in the 1940s will continue long into scene to raise awareness of their technology the future. 08 CONNÆCT | EDITION 8 TALKING BBR What are the main differences in BBR’s position today compared to 70 years ago? TR: Perhaps the biggest thing is that the BBR brand is now recognized the world over. Most engineers know the BBR brand and recognize it represents quality Swiss engineering technology. Thus, our Network Members experience a positive acceptance of BBR technology by their customers. The BBR reputation for quality and reliability has been won over 70 years – this is a great advantage for the BBR Network. AC: As well as quality, the BBR brand also represents the latest technology, qualified professionals and experience gained in literally thousands of applications. Another major difference is the Global Network of Experts we have established over recent years and will continue to strengthen. Of course, harmonization of standards – embodied by EC and ETA – has also occurred. This was one reason why the BBR Network was established – to share costs and focus. BBR HQ provides a full package of latest technology including development, testing, approval and supply chain as well as related services such as marketing support, brands, publications, training seminars and so forth for its Members. This enables Members to concentrate on local sales, installation and engineering. TR: These issues are important because they allow BBR Network Members to focus on their work, rather than becoming distracted by supply or regulatory issues. Ultimately, it allows them to provide the best possible service to their customers. How do today’s challenges compare with those the BBR founders faced? AC: The first challenges were purely technological and probably the greatest challenge – to create new technology such as BBRV from scratch and build a reputation for it. Now the situation is different, BBR technology has been used for years in many countries. The challenge today is to find new ways of using the technology. For example, the use of external post-tensioning for strengthening structures is a comparatively recent innovation which relates our technology to current needs. Extending the lifetime of mature structures is becoming a major issue today, particularly in Europe. All over the world, BBR technology is being used for new applications that simply did not exist back then – like using posttensioning in the construction of towers for wind energy projects. ➤ www.bbrnetwork.com 09 TALKING BBR TR: In the past, the economic situation TR: There has been a shift, not just in was completely different. After the Second construction, but in every industry towards World War, there was huge demand a more customer-focused business – people needed road and rail networks – environment. A deeper understanding of and a shortage of materials, engineers and the needs of customers has become vital for reliable technology. Today, cost pressures conducting successful business. Along with are perhaps greater than, say, six decades this, organizations should be able to supply ago – and the world has become a more a complete service – whether the job is small complex global trading environment. A or large. This is where having strong back up large percentage of money invested in and access to an international organization – infrastructure or buildings goes into such as the BBR Network – helps in forming strengthening or renovation. Different the right package or offering and this also techniques, equipment and know-how are keeps us constantly innovating. In fact, one needed for these and the Network can of the main strengths of the BBR Network provide the expertise to meet this demand. is that its Members are locally based The BBR Network today is able to offer a companies and professionals who have wider range of complex construction strong local knowledge, yet have the backing engineering solutions beyond post- of an international ‘Network of Experts’. tensioning and stay cables (see also pages 72-75). Cost-efficiency is the order of the What factors do you think will bring day and here, at BBR HQ, we too are always success in future decades? looking for ways to optimize costs for the AC: The wealth of know-how that has BBR Network, to give our Members greater accumulated over the past seven decades opportunity to be even more competitive. is significant. It will continue to grow and to 1 feed our commercial and technological AC: Yes, we are evaluating ways of further development in the future. Innovative streamlining cost blocks, such as material know-how – and the way in which it is sourcing, equipment, logistics and shared and used – will increasingly become centralized teams or services and where a differentiating factor for successful there is an advantage, we will make organizations. That’s why we place so much changes. With the transformation of the emphasis on creating new opportunities, corporate business model to a franchise networking with other organizations, system, centralization of certain functions developing channels and resources for makes sense as it saves time, effort and the exchange of information – this is costs. Reducing duplication of effort has something we are constantly reviewing, been at the heart of our approach in this refining and extending. context and, while there is yet more work to do, efficiencies have already been achieved. TR: As I mentioned earlier, listening and responding closely to customer And what have been the most significant requirements is essential to ensuring future changes in the market? business success. We are always striving to AC: The obvious change is that the market do this – and, again, if you look back at is now a highly competitive global one in BBR’s history, this is what we have always which the benefits of post-tensioning and done. BBR may have started with a simple stay cable technologies are generally well- prestressed beam, but progressively grew understood and established. Today, what the technology – in response to changing the BBR Network can offer as a package is customer requirements – into a full range massive. For example, packages have of technologies supporting both private included bridge construction techniques and public sector clients all over the world. and services, linked with provision of bridge And, of course, BBR also developed an construction equipment, PT bars and so entire global Network to ensure quality on. The Network continuously increases implementation of construction technology- the scope to deliver tailored solutions and based solutions. meet customer needs more effectively. So, key factors are having an excellent Collaborative ventures between BBR understanding of the market needs, Network Members are occurring more- continuous innovation and excellent quality and-more frequently and we see the basis to bring added value for our customers – for this at BBR Network gatherings. this is where we need to go. ● 10 CONNÆCT | EDITION 8 1 Dr. Antonio Caballero – CEO, BBR VT International Ltd (top). Thomas Richli – Chief Business Development Officer, BBR VT International Ltd (bottom). TALKING BBR ANNUAL BBR GLOBAL CONFERENCE, AUCKLAND, NEW ZEALAND Technical updates, networking and knowledge exchange CONFERENCE NOTES The 2013 Global BBR Conference in Auckland, New Zealand was always In session Formal conference proceedings were opened by Thomas Richli who outlined the program and officially welcomed the new Swiss franchisee, Stahlton Ltd, to the BBR Network and introduced their Product Manager PT, Fabian Persch who gave an overview of the Swiss market place. Next was a presentation by Vanesa Salva from local BBR Network Member, BBR Contech, about the innovative Pres-Lam technology set to be a stunning event – taking place as it did in the local BBR Network which combines post-tensioning with Member’s 50th Anniversary year. BBR VT International’s Senior Business laminated veneer lumber (LVL) for a Development Manager, Juan Maier, presents a report of the occasion. seismically resistant construction solution. As well as BBR news, technology updates and workshops, the conference featured 2013 BBR AWARD WINNERS BBR NETWORK PROJECT OF THE YEAR Rio Corgo Viaduct, Portugal, executed by BBR PTE (Spain) BEST ARTICLE AWARD Joint winner: BBR PTE (Spain) Title: Waltzing over the Danube (Danube Bridge 2 in Bulgaria & Romania) Most importantly of all, the Annual further keynote presentations about the Global BBR Conference is about getting benefits of PT for developers (Marcel all delegates together under one roof, to Poser, Tectus), Kuala Lumpur LRT gather the opinions of people with much Extension project (King-Bang Tie, BBR industry experience and wisdom. The Malaysia) and Sudan’s Roseires Dam ultimate goal – for all of us – is to improve project (Mark Sinclair, SSL Australia). our operations and way we go to market Guest speaker, Stuart Oliver of Holmes in the future. Consulting delivered a most informative session on seismic retrofit with PT. Joint winner: ETIC (France) Tee-ing off As always, there were ample opportunities Title: Highway to the snow (Bellegarde Viaduct, A40 Geneva to Lyon section of the A4 motorway in France) The Conference began, as is now for networking between BBR Network customary, with the BBR Charity Golf Members and the Conference concluded Tournament which highlighted a wide with site visits – taking in PT, MRR and Highly commended: BBR Polska (Poland) range of skills and abilities – and provided slab-on-ground projects in the city. an opportunity to get people talking. As For me, one of the highlights was the Title: Symbol of development & modernity (Przemysl Bridge, Southern Poland) delegates tee-ed off for the eight and ninth emergence, during our training sessions, holes of this stunning coastal golf course, of another PT Grand Master – Rob the concentration of even the most focused Robinson of BBR Contech made the grade player was challenged as they faced the and joins a select group of highly skilled dramatic view of waves crashing at the and experienced engineers with foot of the cliffs opposite. The event outstanding knowledge of the application literally got the ball rolling for a lively and of BBR post-tensioning systems. It would informative conference – while be wonderful to be able to make a similar emphasizing the importance of continuous award this June, at our 2014 Global BBR performance improvement to some of us! Conference in Interlaken, Switzerland. ● BEST PHOTOGRAPHY AWARD Winner: SSL Structural Systems (Africa) Runner up: BBR Construction Systems (Malaysia) Highly commended: Spanstaal – Ballast Nedam Infra Specialiteiten B.V. (Netherlands) www.bbrnetwork.com 11 TALKING BBR NEWS HIGHLIGHTS Awards, events and more A YEAR TO REMEMBER There was much to celebrate and many activities in-and-around the BBR Network during 2013. Here, we present a brief selection of some of the year’s highlights. Fifth annual BBR Adria PT Seminar range in practical and classroom scenarios, In June, the fifth annual BBR Adria Post- as well as sharing best practices in tensioning Seminar was held in Zagreb, operational management, trouble-shooting Croatia – adjacent to two award-winning on site, procurement practices and buildings constructed with BBR technology. improvement of productivity during The audience included engineers, architects break-out knowledge sharing workshops. and designers from around the region. Among the guest lecturers was BBR VT Golden Anniversary International’s Antonio Caballero who BBR Contech, the BBR Network Member spoke about the benefits of the BBR VT in New Zealand, celebrated five decades CONA CMX range in terms of sustainability, of service to the construction industry – as well as some key points for design. a half century in which it has earned an outstanding reputation for post-tensioning, 12 CONNÆCT | EDITION 8 Workshop highlights operational success ground anchoring, seismic strengthening, A highly successful project managers’ construction engineering and structural course was held during August in Brisbane, maintenance, repair and retrofitting. Australia. The 20 BBR engineers from The company held 50th Anniversary Singapore, Malaysia, New Zealand and functions – attended by staff, directors, Australia studied the technical aspects of key clients and partners – in Auckland, the BBR VT CONA CMX post-tensioning Wellington and Christchurch. TALKING BBR 1 2 3 5 4 Singapore celebrations BBR Holdings (S) Ltd, parent company of BBR Network Member, BBR Construction Systems, marked two decades of operations in September with a celebration dinner, European Project Manager's attended by some 800 guests, at the Marina Workshop in Zagreb Bay Sands Grand Ballroom, Singapore. The most recent European Project The organization has grown beyond its Managers’ Workshop saw engineers from original specialist engineering roots to offer across Europe gathering in Zagreb, Croatia civil and building works, as well as being a for three days. This year's session focused boutique developer in this region. on PT slabs and covered a broad range of topics – including slab design Excellence award considerations, marketing and offering for The 2013 ASBI Bridge Award of Excellence PT slab projects, as well as procurement has been awarded to the Danube Bridge 2 and installation. The whole team was also in Vidin-Calafat (Bulgaria / Romania). This updated on the latest news from BBR HQ, bridge was completed by BBR PTE, Spain, given an overview of the newest range of who installed 2,100t of BBR VT CONA CMI CONA CMX accessories, while also sharing post-tensioning, 65,000m of plastic duct best practices in break-out working groups. and 208 BBR HiAm stay cables. It also At the end of the workshop, delegates featured the first use of the innovative visited a multi-storey construction project BBR HiEx CONA Bundle Saddle for the site to see the BBR VT CONA CMM Single extradosed bridge configuration. PT anchor in action. ● 1 The Danube Bridge II in Vidin-Calafat, Bulgaria / Romania was declared winner of the 2013 ASBI Bridge of Excellence Award. Photograph courtesy of FCC Construcción. 2 Singapore-based BBR Holdings' 20th Anniversary was marked with a celebration dinner for 800 guests. Pictured here is CEO Andrew Tan being presented with a commemorative Swiss cow bell. 3 Directors of BBR Contech, the New Zealandbased BBR Network Member, joined with staff, clients and business partners at functions in Auckland, Wellington and Christchurch to celebrate 50 years of serving construction in New Zealand. Left to right: Andrew Dallas, Des Mataga, David Dorrington, Paul Wymer and Dr Ian Parton. 4 BBR Network engineers working together in a break-out session during the European Project Managers’ Workshop in Zagreb, Croatia. 5 The BBR project managers’ training course in Brisbane, Australia featured technical and workshop sessions. www.bbrnetwork.com 13 TALKING BBR PERSPECTIVE Strength and success through networking GREATER THAN THE SUM OF ITS PARTS One of BBR VT International’s Over recent years, I have seen the something that, personally, I find very newest Board Members is Tore technological developments taking place exciting – partly because of the increased and witnessed the securing of European business generated by this approach for Thorstensen, CEO of KB Gruppen Approval for the range of CONA CMX those Members involved and partly Kongsvinger AS, Norway’s largest technology. This has been a great success because of the inevitable skills transfer family-owned building and for our business and – along with our other that happens in the course of executing construction company. He is also well-established brands which are the work, meaning that new technology, internationally recognized – has placed the techniques or applications can then be BBR Network in a market leading position. applied to local markets, thus opening up a member of the Board of Plantasjen – the largest retail garden center new business opportunities in a Member’s operation in Norway – where Global network previously he served as the working One of the greatest strengths of the BBR home territory. Network is, however, the network itself. Commitment to success Each Member has valuable local knowledge, While all BBR Network Members depend that, as CEO. Earlier roles include as well as specialist skills – gained on on services from BBR HQ and sharing of 18 years with Dyno Industrier, a projects particular to their region. Often, communal knowledge, the independence speciality chemicals producer, Members are part of a larger organization of franchisees’ individual businesses which, in turn, offers further specialist ensures the highest level of commitment expertise and services. to success. It is this commitment, I believe, We asked Tore to share his When you put all of the available expertise, that drives many of the good things which observations and thoughts on the skills and specialist equipment together, are happening within the BBR Network. reasons for the success of the BBR you have an organization that is truly Now is also the time for us to expand and greater than the sum of its parts. There is strengthen the BBR Network by increasing no construction challenge on the planet our geographic coverage. We are ready to that we could not rise to meet – together. bring the BBR technology to territories in chairman of the Board and before latterly as executive vice president. Network with CONNÆCT readers. which we are not currently active and 14 CONNÆCT | EDITION 8 Maximum opportunities where, through changed market conditions, The opportunities presented, through the there are growing infrastructure needs. BBR Network, for Members to literally In this, BBR’s 70th Anniversary year, we ‘network’ are also a huge advantage. There should take additional inspiration from the can be no doubt that the information and enterprise, innovation and dedication that best practice shared during such occasions the three founders applied to introduce contributes to the excellence of the service completely new technology to the world we provide to our customers – a world of market. We should continue to embrace knowledge, applied to local markets. It’s a that spirit in bringing established – and win-win situation. now the latest European Approved – When these dialogues – whether they BBR technology to new markets and actually begin face-to-face or through the applications, as well as to making our BBR Forum or by other means – turn to individual businesses even more successful broader capability issues, international through the very close ties afforded by collaborations can often form. This is being a Member of the BBR Network. ● PORTFOLIO BRIDGES 16 INTEGRATING STRUCTURE & ENVIRONMENT the new award-winning Point Resolution bridge in Auckland, New Zealand not only gives access, but also reflects local heritage BUILDINGS 33 EARLY INVOLVEMENT FOR BEST SOLUTION post-tensioned solutions for buildings, provided with BBR technology and know-how, have delivered real benefits for customers in Poland STAY CABLES 44 SYMBOL OF PROGRESS The new Przemysl Bridge, officially opened by the Polish Prime Minister, featured incremental launching and BBR HiAm CONA stay cables TANKS & SILOS 47 BUILDING FOR BIOGAS four massive digester tanks for biogas production in Hungary have been realized with BBR VT CONA CMM post-tensioning SPECIAL APPLICATIONS 50 SLIDING WITH SAFETY & SPEED Lateral bridge sliding was chosen to minimize impact on rail traffic during a regional railway link project in Western Australia MRR 58 GOING UNDERGROUND maintenance work on Auckland’s 19km long Eastern Interceptor Sewer required the team to work inside the large wastewater pipe www.bbrnetwork.com 15 PORTFOLIO BRIDGES POINT RESOLUTION TAURARUA FOOTBRIDGE, AUCKLAND, NEW ZEALAND Award-winning post-tensioned concrete and steel pedestrian bridge INTEGRATING STRUCTURE AND ENVIRONMENT 1 16 CONNÆCT | EDITION 8 PORTFOLIO BRIDGES An unassuming yet elegant pedestrian bridge giving access to Auckland’s Parnell Baths, across railway tracks and the busy Tamaki Drive – which links the Point Resolution headland to the City’s eastern suburbs, across Hobson Bay – has won the New Zealand Concrete Society’s coveted 2013 Monte Craven Architectural Building Award. BBR Contech, the BBR Network Member based in New Zealand, is pleased to have contributed to the realization of this award-winning project. The new Point Resolution Bridge replaces Architectural design one originally built in two sections to The bridge is made up of three connected connect Tamaki Drive with the Parnell precast post-tensioned concrete beams – Baths – a swimming complex built around forming a hull-like shape which makes a half-a-century ago and featuring the largest visual reference and connection to the salt water pool in New Zealand. When harbor and yachts beyond. This structure is engineering experts assessed the bridge threaded through an external framework of as having reached the end of its design life painted steel featuring three sculpted arches and thus in urgent need of refurbishment – echoing the shape of the original bridge – or replacement because of corroded connected by simple glass balustrades. steelwork, Auckland Council started looking The bridge deck provides a canvas for for a long-term solution. specially commissioned artwork that The end result is this glorious new structure, incorporates a delicate water ripple – or designed by award-winning architecture ‘pungarungaru’ – design which has been practice, Warren and Mahoney. cast into the formed face of the precast beams. The ripple design continues on the clear glass panels of the balustrades. ➤ 2 www.bbrnetwork.com 17 PORTFOLIO BRIDGES 4 3 Elegant, clever & unobtrusive In making their award for the Monte Craven Architectural Building 2013, the Judging “Fortunately, we’ve worked with BBR Complex construction Panel at the New Zealand Concrete Contech before, The bridge’s elegant visual simplicity belies Society said: the complexity of the construction task “It is an elegant, clever and unobtrusive so we knew they behind this project. Wilson Precast solution. The architecture and integration of managed the process of integrating the structure and environment works perfectly – detailed artwork into the precasting moulds, and showcases what can be achieved when coordinating all aspects of the fabrication value is placed on building structures that and then finally getting the 90t beams are highly functional and in sync with the transported to site ready for lifting – no environment. The twin-cell post-tensioned small feat. concrete bridge deck achieves the large “It was enormously challenging,” spans, provides for low maintenance and commented Duncan Peters, a Director of offers a palette for incorporating the Peters & Cheung, the bridge’s design pungarungaru (ripples on the water) design engineers. “Here were these enormous, reflected throughout other parts of the incredibly heavy concrete beams being structure. This footbridge is a striking and held up by virtual toothpicks – how could memorable landmark structure that we ensure that the structure could be built, enhances the waterfront perspective – it is let alone stay stable and survive a disaster a poster child for concrete and the public such as an earthquake?” will spend as much time admiring the bridge Duncan went on to say that great as they will the beauty of the Auckland teamwork – which included working with landscape that surrounds it.” Wilson Precast and BBR Contech to Proposed by Monte Craven, The Monte ensure integrity in the concrete beams Craven Architectural Building Award was through a comprehensive post-tensioning first introduced in 1998 to encourage process – was key to the project’s success, engineers and architects to work more especially given a construction timeframe closely together on construction projects of just 12 months. involving concrete. The Point Resolution The work started off-site, where the three Bridge is a textbook example of how the precast beams were post-tensioned using entire professional team worked closely tendons of between 22 and 25 strands, together to deliver an outstanding result each 15.2mm in diameter. The beams were for the client and the community for years stressed using our brand-new 700t jack – to come. with the largest beam stressed to 460t. BBR Contech is delighted to have been It was critical to get this process right,” added involved in this exceptional project and Duncan. “Fortunately we’ve worked with looks forward to playing its part in further BBR Contech before, so we knew they would award-winning schemes along with other deliver. It’s a credit to the whole team that members of the professional team for the this very complicated project went so well.” Point Resolution Bridge. ● 18 CONNÆCT | EDITION 8 would deliver.” Duncan Peters, Peters & Cheung 1 The deck of the award-winning Point Resolution Bridge is made up of three connected precast post-tensioned concrete beams – its hull-shape reflects the maritime setting. 2 The BBR VT CONA CMI tendons in the precast beams were stressed using a 700t jack, with the largest beam stressed to 460t. 3 Great teamwork between Wilson Precast and BBR Contech ensured integrity in the concrete beams through a comprehensive post-tensioning process. 4 The Judging Panel at the New Zealand Concrete Society commented that the project showed what could be achieved when value was placed on building structures that are highly functional and in sync with the environment. TEAM & TECHNOLOGY Client – Auckland Council Architect – Warren and Mahoney Main contractor – Hawkins Infrastructure Engineer – Peters & Cheung Precaster – Wilson Precast Technology – BBR VT CONA CMI internal BBR Network Member – BBR Contech (New Zealand) PORTFOLIO BRIDGES ROAD BRIDGES, JEDDAH, KINGDOM OF SAUDI ARABIA Post-tensioning for two city center flyovers EASING TRAFFIC FLOW Two new flyovers have been constructed as part of a long term plan to ease traffic flow around the city of Jeddah and meet the needs of the rapidly growing local population. BBR Network Member, Huta Hegerfeld Saudia Ltd, has provided post-tensioning services for both projects. The projects are located at two intersections along Prince Majid Road – at Thahlia Street and Sari Street. At the Thahlia Street intersection, a 220m long five span bridge – featuring a main span of 60m – has been completed. The 1 deck contains three types of precast beams plus a cast in-situ section. Post-tensioning for the precast sections was achieved using BBR VT CONA CMI 0706 and 1206 systems. The cast in-situ section was post-tensioned with the CONA CMI 1206 system. Meanwhile, at the Sari Street intersection, the flyover is a 315m long eight span bridge with a 41m main span, constructed entirely of prestressed precast beams. The beams were assembled in post-tensioned sets of one or two spans each and on four alignments. Longitudinal tendons were BBR VT CONA CMI 0706 and 1206, while the transversal post-tensioning for the crossheads was provided using CONA CMI 1206 and 1906 systems. The two projects required a total of 320 2 tendons and 360t of prestressing strand. The completion of these two projects is a step on the way to achieving the city’s ultimate plan of linking Prince Majid Road to Jeddah’s Southern Corniche. ● 1 Intersection of Prince Majid Road with Thahlia Street. 2 Intersection of Prince Majid Road with Sari Street. TEAM & TECHNOLOGY Owner – Municipality of Jeddah Main contractor – Huta Hegerfeld Saudia Ltd Designer – JL Cancio Martins / Trois Engineering Ltd Technology – BBR VT CONA CMI internal BBR Network Member – Huta-Hegerfeld Saudia Ltd www.bbrnetwork.com 19 PORTFOLIO BRIDGES 1 ACCESS BRIDGE, CAHAYA SPK COMMUNITY, SHAH ALAM, SELANGOR, MALAYSIA Curved viaduct launching ELEGANTLY CURVED BRIDGE Construction planning As the main bridge was being constructed directly above existing live traffic, it was impossible to adopt the cast in-situ method for the whole bridge – the setting up of temporary formwork would have caused long term closure to traffic of the highway beneath and, thus, serious inconvenience. Therefore, the precast method was adopted for the main span of the bridge. To reduce the concrete self-weight during An elevated viaduct, over-flying an The original viaduct design had an launching, the casting of the main span was existing highway, was needed to intermediate pier at the median to handle divided into two box girders – outer beam the long span and tight 60m radius and the inner beam. Each beam weighs less provide a dedicated access to the horizontal curve. Construction of the than 200t. community of Cahaya SPK, Shah intermediate pier within the narrow median There were three construction stages: Alam, Selangor. BBR Construction strip would have been disruptive to traffic • Stage 1 – Falsework and formwork were Systems successfully bid for this and dangerous to both road users and the erected to cast the approach spans. construction contractor. As well as our At the same time, precasting of the main design and build project. HM Goh keen pricing, the client liked our alternative span beams was carried out. of BBR Construction Systems proposal as it removed the need for an Malaysia explains the challenges intermediate pier – and would also result and grouting of the approach spans, the surrounding this design and in an exceptionally elegant bridge. mid-span precast beams were launched construct project for the 115m long box spine curved main viaduct. on top of the piers. Each precast beam Bridge configuration was hung in position by steel tie beams. The main bridge of the viaduct has a span Vertical 36mm diameter prestress bars configuration of 31m + 53m + 31m. The two approach ramps are comprised of cast 1 Challenges for the BBR team working on this elegant bridge included safety, terrain, buildability, aesthetics, space limitations and time constraints. 20 CONNÆCT | EDITION 8 • Stage 2 – After completion of stressing were stressed to hold the steel tie beams. • Stage 3 – After launching the precast in-situ reinforced concrete structures and beams, the deck slabs between the two reinforced earth walling. Structurally, the beams were stitched. The gaps between deck is made up of two precast box girders the ends of the precast beams and the – which provide good torsional capacity to approach beams were also stitched. resist the effects from the bridge’s curved Then the continuous BBR CONA internal geometry. Topography and terrain of the site 1906 tendons over the three spans were dictated that the bridge geometry required a stressed to complete the continuous curve of 60m radius and a pier height of 8m. bridge superstructure. PORTFOLIO BRIDGES Temporary works design & consideration Temporary steel tie beams were necessary for the whole launching process, as it served as the main support member until the three span bridge was completed. The design of the tie beams was challenging due to the curved geometry. The center of gravity of the precast beam was away from the centerline of the alignment, thus the beam would tend to rotate if lifted at the ends. Therefore, two adjustable lifting brackets with multiple adjustments were fabricated to ensure that during the lifting operation, by two mobile cranes, the original center of gravity of the curved beam would be maintained. In securing each beam to the approach beam, high torsional moments and shear forces needed to be overcome. This was achieved by using a pair of Grade 50B steel tie beams stressed with vertical 36mm bars. HUNTER EXPRESSWAY, NEW SOUTH WALES, AUSTRALIA Erection work First use of BBR VT CONA CMI for RMS project The launching of the two main beams was targeted to be completed in 48 hours, as the local authority only permitted the main road to be closed between 12am and 7am. Hence, the aim was to completely launch only one beam per night. First, the beam was lifted by two 300t capacity cranes and placed on a multi-axle loader. The multi-axle loader transferred the MILESTONE FOR BBR TECHNOLOGY beam to the launching point. The beam was Approval for use of the BBR VT CONA CMI system within Roads & lifted by 400t and 500t capacity cranes. Maritime Services (RMS) projects was granted in May 2012 and, just When the beam was in position, stressing of the bars was carried out to secure the beam. six months later, explains Project Manager Vince Ponzio, of BBR The same process was repeated for the Network Member Structural Systems, it was being installed on a major second beam during the following night. freeway project in New South Wales. Completion The whole bridge was opened to traffic on The Hunter Expressway is a $1.7 billion In total, 84 post-tensioning tendons were 8 September 2013 and now has become one 40km, four lane freeway link between installed – requiring approximately 100t of the important landmarks of the area. Road the F3 Freeway near Seahampton and the of 15.2mm strand and 3.5km of ducting. safety, challenging terrain, construction New England Highway west of Branxton. The new BBR VT CONA CMI system met practicability, aesthetic value, working The western section of the project all client expectations resulting in a space limitation and time constraints have involves completion of 27km of the highly successful project and positive made this project both truly memorable – new freeway link, including four grade client feedback. ● and extremely satisfying. ● separated interchanges and a total of 25 bridges along its length. Two interchanges – one located at Kurri Kurri (pictured above) and the other at Branxton – involved the construction of single span, cast in-situ TEAM & TECHNOLOGY post-tensioned box girder bridges over Owner – S.J Properties Sdn Bhd Main contractor – BBR Construction Systems (M) Sdn Bhd Designer – Perunding LFL Bridge contractor – BBR Construction Systems (M) Sdn Bhd Technology – BBR CONA internal, PT bars, Span-by-span precast BBR Network Member – BBR Construction Systems (M) Sdn Bhd (Malaysia) the new Hunter Expressway. Structural Systems was awarded the contract for the supply and installation of post-tensioning services for these bridges. Each of the four bridges was approximately 40m in length featuring a combination of 1906 and 3106 CONA CMI multistrand tendons. TEAM & TECHNOLOGY Owner – NSW Roads & Maritime Services (RMS) Main contractor – Abigroup Contractors Pty Ltd Designer – SMEC / SKM Technology – BBR VT CONA CMI internal BBR Network Member – Structural Systems Limited (Australia) www.bbrnetwork.com 21 PORTFOLIO BRIDGES KEPPEL VIADUCT, SINGAPORE Carriageway widening UNCLOGGING THE BOTTLENECK The Keppel Viaduct – an awkward bottleneck on Singapore’s Ayer Rajah Expressway – is being upgraded from a dual three lane carriageway to a dual four lane carriageway. Singapore-based BBR Construction Systems’ Project Manager, Tan Yeow Koon describes the project’s history and explains how existing site conditions make both the design and construction a major challenge. 1 22 CONNÆCT | EDITION 8 PORTFOLIO BRIDGES “...the live traffic environment and limitations imposed by existing structures made both the design and construction a The Keppel Viaduct was constructed as part Post-tensioned extension of the Ayer Rajah Expressway (AYE) from To accommodate the widening of deck 1983 to 1988. At that time, it was the longest slabs at both ends of the viaduct, the vehicular viaduct in Singapore – measuring design proposes an extension of the 2.2km in length – and a crucial traffic existing crossbeam, such that additional corridor for east-west commuters as it prestressed precast beams can then be connects the East Coast Park Expressway launched upon the new extended structure. (ECP) and AYE. Both the ECP and AYE had For this, a combination of utilizing two been upgraded over the years into major existing spare PT ducts and installation of dual four or five lane expressways, whereas new PT bars was proposed. the Keppel Viaduct was still only carrying a To allow the existing crossbeams to carry dual three lane carriageway. So, when the the extra loads, new secondary crossbeams Land Transport Authority (LTA) finalized the are to be constructed immediately beneath plan to re-route the ECP-AYE connection four of the existing eight beams. The new with a new expressway – the Marina Coastal crossbeams are 25m in length, with a Expressway (MCE) – a study was carried cantilevered arm of 9m. For this element out to look into the bottleneck caused by the of the work, a total of 10 post-tensioning Keppel Viaduct. While the LTA’s objective to tendons have been proposed, each having upgrade the dual three lane carriageway into 38 strands of 12.9mm diameter and each a dual four lane carriageway looked simple tendon will ultimately have to be stressed on paper, the live traffic environment and to 5,320kN. ➤ major challenge.” 1 Singapore’s Keppel Viaduct, once celebrated for being the longest in the country, had become a bottleneck on the busy east-west commuter route. 2 Site conditions and constraints dictated the use of a T-shaped cantilevered steel truss tower, designed in modular segments, for construction of the crossbeams. 3 The completed crossbeams of the Keppel Viaduct, extended to accommodate an additional three or four longitudinal beams, alongside the eight currently existing beams. limitations imposed by existing structures made both the design and construction a major challenge. Design concept Singapore Piling & Civil Engineering (SPACE), one of our sister companies within BBR Holdings Limited, was awarded the design and build contract by the LTA in February 2011. SPACE drafted in an equally well-established consultant on vehicular bridge design – YWL Engineering – and the first task on hand was to finalize the design concept for the major upgrading works. The existing crossbeams are to be extended to accommodate an additional three or four longitudinal beams, alongside the eight currently existing beams. To achieve this, the designer proposed an additional crossbeam, extension to the existing crossbeam, new columns sandwiching the existing one, plus the pile-cap resting above the existing pile-cap with new foundation pipes. With this design concept, the proposed structure will be able to accommodate additional longitudinal beams and the structural capacity of the viaduct will be enhanced. 2 www.bbrnetwork.com 23 PORTFOLIO BRIDGES “The nature and location of the Substructures Construction challenges To support the entire proposed The nature and location of the scheme superstructure, a system of foundational have brought some very specific challenges substructures must be designed and to the project team. The existing buildings constructed. Firstly, bored micropiles of and structures, high volume of pedestrian 350mm diameter were proposed as the footpaths and at-grade traffic carriageways foundation system due to existing and junctions have meant that on-site headroom limitations – the existing materials storage and extensive scaffolding headroom clearance of 10m does not allow are not possible. In such situations, rebar the deployment of standard bored-piling and system formwork structures are often rigs and service cranes. Furthermore, prefabricated off-site and then installed micropiling rigs are much smaller and are on site at night, with road closures for more applicable for installation of piles subsequent concrete pouring. Also, the right beside busy vehicular carriageways vertical working spaces are constrained by and junctions. The new pile-caps, designed the existing viaduct, so using equipment as transverse beams across the existing such as boring rigs or cranes is not an pile-caps to fit within the existing center option. Then, of course, there is a high median, are then constructed and cast volume of live traffic during the day, both at in-situ on site. viaduct level and at-grade, which makes our scheme have brought some very specific challenges to the project team.” available working time very limited indeed. Columns In many ways, we are enjoying the Similarly, to facilitate construction of the challenges and opportunities to use our proposed columns in the middle of live specialized engineering skills – and also vehicular carriageways on both sides, the our expertise in logistics – on this major steel reinforcement bars for the columns project which we know, when completed have to be prefabricated into cages, lifted in February 2015, will be appreciated by and secured into place, followed by the the very many people who drive along this installation of modular steel system route on a daily basis. ● formwork. All these activities are being carried out with the objective of causing minimal impact to the at-grade road vehicular traffic. Crossbeams To construct the new crossbeams, the conventional method of erecting falsework supports, followed by installation of reinforcement steel bars and formwork cannot be adopted. This is due to live vehicular traffic flanking both sides of the working space, as well as the headroom constraint below the viaduct restricting the use of cranes. Hence, a set of system falsework / formwork was proposed for this work. This falsework / formwork, fabricated with structural steel members, comes in the form of a T-shaped cantilevered steel truss tower. The system is designed in modular segments to facilitate the lifting operation at a more manageable level for each module. The modules are lifted, joined and fixed in place using nut-and-bolt connections. Lifting points at the viaduct soffit consist of steel pins and brackets that are fitted onto the existing beams of the viaduct. 3 24 CONNÆCT | EDITION 8 TEAM & TECHNOLOGY Owner – Land Transport Authority of Singapore (LTA) Main contractor – Singapore Piling & Civil Engineering Civil & structural engineering consultant – YWL Engineering Technology – BBR CONA internal BBR Network Member – BBR Construction Systems Pte. Ltd (Singapore) PORTFOLIO BRIDGES PENANG SECOND CROSSING, MALAYSIA Precast segment production 100 DAYS AHEAD OF SCHEDULE! BBR Malaysia was contracted The Penang Second Crossing provides an Completed segments were delivered by to carry out match-casting of additional access bridge to the island of gantry crane to the barges. The weight of a Penang which should reduce the high typical segment was 80t – while individual traffic volume on the existing bridge. pier segments weighed in at 110t. The Second Crossing bridge project The new crossing consists of two bridges segments were delivered to the working and completed their task over – one for traffic going towards the island fronts using launching gantries, as the three months ahead of schedule! and the other for traffic heading for the bridge was being erected by the span-by- mainland. Each bridge consists of precast span method. box girder segments with external post- BBR Malaysia was one of three segment tensioning. In total, 8,092 segments were precasters contracted for the task. needed for the new 24km bridge. Segment casting was completed 100 Typical segment dimensions are 14m wide days ahead of schedule – allowing main by 4m long by 3.2m deep. By casting against contractor, UEM Builders(M) Sdn Bhd, to the previously cast segment, the joint stay well on track with their program. ● precast segments for the Penang Chee Cheong Chang of BBR Malaysia outlines the project. matching of shear keys during segment erection can be assured. The other joint surface was formed by a steel bulkhead. The tendon sizes are 19 to 31 strands of 15.2mm diameter. Deviator holes in the deviator segments were formed using reusable formers. For tighter curves, bent steel pipes cast into the concrete are used to deflect the external tendons. TEAM & TECHNOLOGY Owner – Public Works Ministry of Malaysia Main contractor – UEM Builders (M) Sdn Bhd Technology – Span-by-span precast, BBR CONA external BBR Network Member – BBR Construction Systems (M) Sdn Bhd (Malaysia) www.bbrnetwork.com 25 PORTFOLIO BRIDGES SEAFORD RAIL BRIDGE, ADELAIDE, SOUTH AUSTRALIA World’s third longest incrementally launched bridge EXTRAORDINARY ENGINEERING FEAT When two teams of specialist engineers met – suspended above a river valley midway across a bridge spanning well over a kilometer in length – it marked the climax of an extraordinary engineering feat. The new rail bridge spanned the bridge in Australia and the third longest Onkaparinga River and its floodplain, in the world. linking two crews who, 20 months The rail bridge is the key feature in the previously, had started constructing 5.7km long passenger railway line different sections of bridge at either end extension from Noarlunga to Seaford, a of the project. When the two crews shook southern suburb on the outskirts of hands in celebration, they could look back Adelaide. It was commissioned by the on a unique civil engineering project that South Australian Government under a joint had crossed the large river valley creating venture arrangement with Thiess MacDow, the longest incrementally launched with Structural Systems in support. 2 1 26 CONNÆCT | EDITION 8 PORTFOLIO BRIDGES Construction sequence In order to accomplish the task, Structural Systems and the contractor’s team constructed 22 spans of up to 2.3m in length, cast in steel formwork established at either end of the bridge, then jacked progressively into place. A total of 48 segments, mainly 26.15m long were built this way and pushed using Structural Systems’ specialist bridge launching technology. Although the bridge was launched continuously from each end, it was temporarily configured as twin structures, later to be released to form seven non-linked sections. This was so that the railway line would have the ability to expand or contract with temperature changes and thereby avoid buckling. Engineering Excellence commendation Seaford Rail Bridge has been described as one of the most impressive civil construction feats ever undertaken in South Australia. The mammoth 1,123.9m long structure has received an Engineering Excellence commendation. Structural Systems significant contribution to the bridge’s concept and construction methodology was likewise recognized, noting the minimal impact on the environmentally sensitive floodplain. ● 3 TEAM & TECHNOLOGY 1 The new Seaford Rail Bridge is the key feature in a 5.7km long passenger railway line extension from Noarlunga to Seaford, South Australia. 2 A total of 48 precast segments, mainly 26.15m long were constructed on site and pushed into place using Structural Systems’ specialist bridge launching technology. 3 The segments were post-tensioned using BBR VT CONA CMI internal, BBR VT CONA CME external and PT Bars. Owner – Government of South Australia, Department for Transport, Energy and Infrastructure Main contractor – Thiess McConnell Dowell Joint Venture Designer – Aurecon Technology – BBR VT CONA CMI internal, BBR VT CONA CME external, PT Bar system, Launching BBR Network Member – Structural Systems Limited (Australia) www.bbrnetwork.com 27 PORTFOLIO BRIDGES PUSENCI FLYOVER, SLOVENIA Post-tensioning and heavy lifting technology ABOVE AND BELOW THE LINE SOLUTIONS A new flyover has been constructed over railway tracks, allowing traffic to pass above the main line from Ormoz and the old railway crossing ramp to be closed. In a two-part project, BBR Adria has posttensioned a 183m long flyover and also slid a pedestrian underpass into place – and only a two day railway possession was required. Construction of the flyover was completed in seven segments – the first, at 37m, was the longest while the remainder were between 21.4 and 29.4m in length. The flyover has eight piers with spans from 15 to 25m long. Within the same project, a pedestrian subway was also built under the railway tracks next to the flyover. Railway traffic continued during construction and only a two day possession of the tracks was permitted, so the pedestrian subway was fully constructed to one side and slid into place. During the possession, the rails above the final location for the subway were removed, excavation was completed and then the finished underpass was slid into place using PT jacks. When the subway was finally positioned, new tracks were installed above and the railway traffic recommenced. ● 1 1 The 183m long flyover across the main railway line was completed in seven segments. 2 The new underpass was slid into place using PT jacks during a railway possession. TEAM & TECHNOLOGY Client – Direction for Roads, Republic of Slovenia Main contractor – SGP Pomgrad – Gradnje d.o.o. Designer – KO-BIRO d.o.o., Maribor, Slovenia Technology – BBR VT CONA CMI internal, sliding BBR Network Member – BBR Adria d.o.o. (Croatia) 2 28 CONNÆCT | EDITION 8 PORTFOLIO BRIDGES PEDESTRIAN BRIDGE, LESOTHO The award of this specialist works contract Stressing & anchoring technology followed earlier post-tensioning services provided by Structural Systems Africa to the main contractor and involving 24 x 20m SPECTACULAR STRESSED RIBBON BRIDGE long post-tensioned precast beams for a six span bridge, about 30km away. The two-span stressed ribbon bridge in Lesotho consists of two groups of sagging tensioned strands – 25 x 15.7mm strands each – which follow a catenary arc from abutment to a central pier to abutment. These two groups of strands – or ‘bearer tendons’ – are used to suspend 84 precast concrete segments which form the concrete deck. The deck is wafer thin when looked at in comparison to the maximum 127.75m span, and is assembled by individually suspending the 2.5m long precast segments on the bearer tendons at the abutment and then shifting them along to their final position. The bearer tendons were tensioned to 42% of Minimum Breaking Load (MBL) before installation of the segments. Their load was then fine-tuned to achieve similar levels in both spans. Each group of 25 strands was made up of 2 x 8-strand and 1 x 9-strand BBR VT CONA CMI tendons to enable the fine-tuning to be carried out on multiple strands at a time, using 300t multistrand jacks. Prior to encasing the bearer tendons in permanent in-situ concrete, additional 2 x 8-strand post-tensioned tendons were installed for stressing after the in-situ concrete reached the required compressive strength. The tendons were 1 248m long and required stressing from both ends to compensate for wobble effects and friction losses. Lesotho is a landlocked country – In addition to the bearer and post-tensioned completely surrounded by tendons, the two abutments required neighboring South Africa – and is 1 Two long groups of sagging tensioned strands – or ‘bearer tendons’ – are used to suspend the 84 precast concrete segments forming the wafer-thin concrete bridge deck. TEAM & TECHNOLOGY Owner – Metalong Authority & Kingdom of Lesotho Main contractor – EXR Construction Lesotho (Pty) Ltd Designer – SSI in association with Jeffares & Green, GWC and DHV Technology – BBR VT CONA CMI internal, BBR VT CONA CMG ground BBR Network Member – Structural Systems Africa Ltd (South Africa) anchoring into the surrounding rock to enable the suspension of the large spans. now the home to a unique stressed SSA was also engaged in the preliminary ribbon pedestrian bridge. Sean works which involved the installation of 12 x Kelly of Structural Systems Africa 22-strand permanent ground anchors. This Limited (SSA) explains that the was the first ground anchoring job in Africa for SSA and, with the help of Structural 248.5m long bridge has been Systems (Civil) in Australia, a high quality constructed over a gorge which is product was achieved. The anchors have a up to 50m deep and 240m wide. MBL of 6,138kN and were proof loaded to When the dam being built 75% of this load, before locking-off at 55% MBL. With a bond length of six meters and downstream is commissioned, free length of 10m, the anchors were the tail water level will completely assembled on site and lowered into the encase the gorge from abutment- drill hole by a crane. To ensure an even to-abutment – and, without this build-up of stresses in each anchor set, the load in the anchors was increased in new bridge, it would be impassable 20% MBL increments sequentially, from by local people. the inner anchors to outer anchors. ● www.bbrnetwork.com 29 PORTFOLIO BRIDGES 1 BOTLEK CORRIDOR, ROTTERDAM, NETHERLANDS Post-tensioning for bridges, ballast blocks & pergola beams EUROPE’S LARGEST LIFT BRIDGE Europe’s biggest port, at Rotterdam, continues to expand and infrastructure is being extended and upgraded to meet the future needs of this busy port and industrial complex. The A15 motorway, giving east-west access across the country and beyond, is now being extended and Ron van Dijk of Netherlands-based BBR Network Member, Spanstaal – Ballast Nedam Infra Specialiteiten B.V., describes his company’s work in the Botlek Corridor – including how an important element of this €1.5 billion project, the existing Botlek Bridge, will be replaced by a new bridge which, when completed, will be one of the largest lift bridges in the world. FACTS & FIGURES Pergola construction – 924 x ø47 PT bar – 202 x BBR VT CONA CMI 2706 tendons – 260t prestressing steel – 72 x elastomeric blocks (ø350 x 85 and ø850 x 157) Western access ramp – 176 x BBR VT CONA CMI 1906 tendons – 280t prestressing steel Bridge counterweights – 72 x BBR VT CONA CMI 1906 tendons – 80t prestressing steel 30 CONNÆCT | EDITION 8 A major shipping bottleneck will be relieved bridge, will have two openings for shipping by the realization of the new lift bridge at – each around 90m wide and sitting around Botlek, which is being constructed by the 14m above the river. The headroom above A-Lanes A15 consortium – formed by the river will be twice the height of that Ballast Nedam, John Laing, Strabag and afforded by the current bridge – thus, larger Strukton – who are responsible for the vessels will be able to pass underneath expansion and subsequent maintenance without holding up traffic traversing the of the A15 between the Maasvlakte and bridge. Its two sections will also allow ships Vaanplein junction. The project is being coming from opposite directions to pass carried out as a ‘Design, Construct and simultaneously. When completed, the new Maintain’ contract with a term of 25 years, Botlek Bridge will be capable of being raised thus quality and lifetime considerations are 31m in a very short time. of prime importance. Spanstaal, in conjunction with Tensa, has The current Botlek Bridge is mainly used been working on the adjacent structures, by hazardous freight which is not permitted including the western access ramp (long to pass through the Botlek Tunnel. The new spans), pergola beams and trough bridges bridge, being built alongside the existing (short spans). PORTFOLIO BRIDGES 2 3 Western access ramp Three access ramps have been built on both sides of the Botlek Bridge. The two outer ones for through-traffic and the middle one for the access ramp. The ramps were built in three phases and one of the most notable features of the post-tensioning here is that we executed it using couplers. In the execution of this part of the project, we used 176 BBR VT CONA CMI tendons and 280t of prestressing steel. On the east side of these long spans are four trough bridges each 37m long and posttensioned with 12 x 2206 strand tendons. 4 Pergola construction Traffic on the Botlek Bridge will cross the Counterweights traffic exiting the Botlek Tunnel. Thus, The new bridge will be the biggest lift bridge pergola structures, made of prefabricated in Europe and, therefore, very heavy ballast I-beams, are being built to connect the new blocks are needed – the two steel bridge bridge over the tunnel entrance ramps to decks weigh 7,200t. The four 2.5t blocks – the A15. two for each bridge deck – will each be post- During one weekend, we lifted and installed tensioned with 18 CONA CMI tendons. Nine the 36 prefabricated 37-48m long, 2.8m tendons will be secured, using CONA CMI SP high I-beams – weighing up to 238t each – anchors, to the steel plates on two opposite into their final locations where they rest sides at the base of each block. on 72 elastomeric blocks. The beams are linked together by two rods and the gaps Specialist works between the beams were filled with grout. Spanstaal is also responsible for specialist After every two beams had become works involved in the construction of various completely monolithic with each other, the other access bridges on the Botlek Corridor, beams were post-tensioned using 10 to 12 some of which has involved the supply of CONA CMI tendons per grid. Then we 900 elastomeric blocks with epoxy and the grouted all the transverse tendons with a production and installation of 600m of special grout mixture. expansion joints. All of this work had to be carried out above When the new bridge is commissioned in live traffic. For this, we used three dense early 2016, demolition of the old bridge will scaffolding grids hung from the tunnel walls begin and finally the flow of both shipping so as not to impede the traffic flow beneath. and road traffic will be eased. ● 1 Pergola structures, made of prefabricated I-beams, are being built to connect the new bridge over the tunnel entrance ramps to the A15. 2 Botlek Bridge, Western Access Ramp, long spans – continuous post-tensioning tendons are placed on the deck near the construction joint, coupling cables have been stressed. 3 The precast prestressed I-beams for the pergola structures – each beam weighing up to 238t – were post-tensioned using 10 to 12 BBR VT CONA CMI tendons per grid. 4 The two steel decks of the new lift bridge weigh 7,200t and require four 2.5t posttensioned ballast blocks. TEAM & TECHNOLOGY Owner – Rijkswaterstaat Main contractor – A-Lanes A15 Consortium (Ballast Nedam, John Laing, Strabag & Strukton) Technology – BBR VT CONA CMI internal, PT bar, Bearings, Expansion joints BBR Network Member – Spanstaal – Ballast Nedam Infra Specialiteiten B.V. www.bbrnetwork.com 31 PORTFOLIO BRIDGES BATINAH EXPRESSWAY, SULTANATE OF OMAN Testing & post-tensioning works The Batinah Expressway Package-1 project for the Ministry of Transport and Communication (MOTC) is the first significant bridge project – involving nearly LONGEST BRIDGE TENDONS IN OMAN 1,400t of prestressing steel – secured by Structural Systems in Oman. Extensive testing, comprising of both static load and load transfer tests, was undertaken in accordance with project specifications to demonstrate the compliance of the BBR VT CONA CMI systems to the requirements of AASHTO LRFD Bridge Construction specification for highly aggressive environments. For further details, see Page 68. The Barka Interchange, forming part of the Batinah Expressway Package-1 project, is located at Barka near to Muscat. It has two structures – the East Bridge and the West Bridge. The length of each bridge is 160m over three continuous spans. The center Since Structural Systems began operations in the Middle span is 70m and both end spans are 45m East, the team has provided technology and expertise each. Each bridge is a three cell post- for the post-tensioning of over 50 bridges in the region. tensioned box girder structure, with depth Now, they are working on a major bridge project in Oman, Warwick Ironmonger takes up the story. varying from 2m to 4m. For the Barka Interchange, we used the BBR VT CONA CMI 4206 post-tensioning system and almost 260t of prestressing steel. The interchange is believed to feature the longest single bridge tendons – around 162m long – in Oman. With these significant bridges now under their belt, Structural Systems have now managed to secure further bridges works in Oman including the Murray to Al Ayn Bridges and the Al Jazeera Bridges at Sur, both with MOTC, and the Oman Convention and Exhibition Center civil works for OMRAN, the company set up by the Government of Oman to deliver major projects and to manage assets and investments of the tourism sector. ● 1 1 For the Batinah Expressway’s Barka Interchange project, BBR VT CONA CMI post-tensioning systems were tested to demonstrate compliance with the requirements of AASHTO LRFD Bridge Construction specification for highly aggressive environments. 2 The 162m long post-tensioning tendons used on the project are believed to be the longest single bridge tendons ever used in Oman. TEAM & TECHNOLOGY Owner – Ministry of Transport & Communication Main contractor – Galfar Consultant – Parsons Technology – BBR VT CONA CMI internal BBR Network Member – Structural Systems Limited (Oman Branch) 2 32 CONNÆCT | EDITION 8 PORTFOLIO BUILDINGS POST-TENSIONED SLAB & BEAM SOLUTIONS, POLAND Optimizing structures with versatility and strength EARLY INVOLVEMENT FOR BEST SOLUTION Structures, such as the new Business Garden offices in Warsaw, owe much to the expertise and ingenuity of BBR Polska’s dedicated team of engineers who are focused on developing and applying leading-edge post-tensioning solutions for buildings. Bartosz Lukijaniuk, Design Coordinator, of BBR Polska talks us through some recent projects which have offered clients and their main contractors some real benefits. 1 The new Business Garden office The BBR Polska team had to meet a complex in Warsaw consists of two number of challenges. There were long buildings – a further five buildings will be spans of up to 11.4m and some difficult constructed in a second phase. The complex architectural shapes – most of the slabs features post-tensioned slabs throughout – were unique. We were also targeting low even in the underground car park – and material consumption rates and, for a these cover a total area of 52,000m2. We typical slab, mild steel consumption was used the BBR VT CONA CMM unbonded around just 11kg/m2. system which best suited the project needs. Without doubt, our early involvement in the project – right from the conceptual design stage – helped to deliver exactly what the client wanted. ➤ 1 www.bbrnetwork.com 33 PORTFOLIO BUILDINGS 2 Structural optimization 3 Achieving long cantilevers “Where longer spans Another example of a building for which The architect’s vision for a new luxury are designed by we adopted an unbonded post-tensioning residential development in Warsaw approach to the slabs can be found in the included the construction of balconies architects, post-tensioned public sector – at Warsaw Medical with long cantilevers of up to 4.6m – beams are the ideal University. uneconomical to design using only For this project, post-tensioning technology reinforced concrete. Again, we were solution for minimizing was chosen as an alternative solution to brought into the project team from the beam size – and also the original design which used reinforced earliest concept stage and were thus able concrete slabs with void forming ‘plastic to offer advice on a structural solution to construction costs.” bubbles’ to make the slabs lighter. With fulfill the architectural vision. Slabs were our CONA CMM post-tensioned solution, post-tensioned with BBR VT CONA CMM the 2,800m2 of slabs were not only thinner unbonded post-tensioning tendons. but consumption of mild reinforcement was much lower. 4 Reduced materials consumption Here, we joined the project team with the Meanwhile, in Wroclaw, the structural express purpose of bringing our ideas for solution for part of a multi-purpose building optimizing the structure to the table. generated spans of around 10m – a one span slab with a small cantilevered balcony. With our help, the use of flat bonded BBR VT CONA CMF post-tensioning tendons within a 350mm thick slab was chosen as the best solution for this structure. An additional advantage offered by our solution was low consumption of mild reinforcement – at a rate of only around 6kg/m2. 2 3 34 CONNÆCT | EDITION 8 4 PORTFOLIO BUILDINGS TEAM & TECHNOLOGY 1 Business Garden, Warsaw Owner – Wi´niowy Office Park / Swede s Center Main contractor – Hochtief Polska Architect – APMD Designer – ARCADE Polska (structural), SDS & BBR Polska (post-tensioning) Technology – BBR VT CONA CMM monostrand BBR Network Member – BBR Polska Sp. z o.o. (Poland) 2 Medical University, Warsaw 5 Owner – Medical University, Warsaw Main contractor – Budimex S.A. Architect – Kontrapunkt V-projekt Designer – Kontrapunkt V-projekt (structural), POMOST & BBR Polska (post-tensioning) Technology – BBR VT CONA CMM monostrand BBR Network Member – BBR Polska Sp. z o.o. (Poland) 1 Business Garden offices, Warsaw – long spans and complex architectural shapes, as well as low material consumption rates were achieved through early project involvement and the post-tensioning expertise of the BBR Polska team. 2 Warsaw Medical University – another early involvement project where our alternative post-tensioned approach to construction produced thinner slabs and a lower consumption of mild reinforcement. 3 Residential building, Warsaw – with early advice and BBR VT CONA CMM posttensioning, we helped to fulfill the architect’s vision for this new luxury development. 4 Multi-purpose building, Wroclaw – flat bonded BBR VT CONA CMF post-tensioning was used to produce one span slabs with small cantilevered balconies. 5 Korona Kielce shopping center – beams post-tensioned using the BBR VT CONA CMI bonded system were constructed for the main access footbridge. 6 Silesian Museum, Katowice – BBR VT CONA CMI and CMM post-tensioning technology was chosen here to minimize the beam size over the main two level exhibition halls and three levels of underground parking. 3 Residential building, Warsaw Owner – Dom Development Main contractor – Eiffage Polska Budownictwo Architect – Maka.sojka.architekci Designer – ARBO (structural), SDS & BBR Polska (post-tensioning) Technology – BBR VT CONA CMM monostrand BBR Network Member – BBR Polska Sp. z o.o. (Poland) 4 Multipurpose building, Wroclaw Owner – Wisher Enterprise Main contractor – Karmar S.A Architect – Mackow Pracownia Projektowa Designer – PB Stalbet (structural), SDS & BBR Polska (post-tensioning) Technology – BBR VT CONA CMF flat BBR Network Member – BBR Polska Sp. z o.o. (Poland) 6 5 Korona Kielce shopping center, Kielce 5 6 PT beams make clear spaces CMM post-tensioning technology was Where longer spans are designed by chosen to minimize the beam size. architects, post-tensioned beams are the Post-tensioned beams were designed and ideal solution for minimizing beam size – installed over the main two level exhibition and also construction costs. One such halls and three levels of underground example of a PT beam solution was parking. The beams over the exhibition executed by BBR Polska for a shopping halls are about 25m long – one span with center in the city of Kielce. BBR VT CONA a 3m cantilever – while the parking slab CMI post-tensioned beams were used in beams are 32m long and create two spans. the footbridge forming the main access to No matter what the purpose of the the shopping center. The BBR Polska team building, the use of a post-tensioned offered a solution based on BBR VT CONA approach to construction can help to CMI bonded post-tensioning with create great usable space, fulfill multistrand tendons. architectural visions and optimize both Another interesting example showing the materials and costs. The team at BBR benefits of post-tensioning for long beams Polska has enjoyed these challenges and with heavy load capacity was at the Silesian stands ready for even more challenging Museum in Katowice where CONA CMI and early stage involvement projects. ● Owner – Church Land Development Main contractor – SPS Construction Sp. z o.o. Architect – Bose International Planning & Architecture Designer – Bartels Polska & Chodor Projekt (structural), K2 Engineering & BBR Polska (post-tensioning) Technology – BBR VT CONA CMI internal BBR Network Member – BBR Polska Sp. z o.o. (Poland) 6 Silesian Museum, Katowice Owner – Silesian Museum Main contractor – Budimex S.A. Architect – Riegler Riewe Archtekten Designer – Firma Inzynierska STATYK (structural), SDS & BBR (post-tensioning) Technology – BBR VT CONA CMI internal, BBR VT CONA CMM monostrand BBR Network Member – BBR Polska Sp. z o.o. (Poland) www.bbrnetwork.com 35 PORTFOLIO BUILDINGS 1 2 PUBLIC CAR PARK, VARAZDIN, CROATIA Famed for its baroque architecture, Post-tensioning creates large spans Varazdin in northern Croatia has long been a major center for tourism LARGE SPANS ENHANCE UNDERGROUND PARKING and commerce. It is here, below Kapucin Square, recounts Kresimir Bogadi of BBR Adria, that an acclaimed new 443-space underground city center car park has been created. Close to Varazdin Park, the railway station and all the City’s major attractions, the new underground garage has two below grade levels with a total area of 12,370m2 which have been designed in a 77m by 80m layout. At five meter intervals, there are beams running across five column spans 16m each. The lower slab will only be loaded with traffic and was designed as a 160mm slab with 500 x 600mm beams laid in one direction at five meter intervals. However, the upper slab has to carry greater load (33.5kN/m2) and was therefore designed as a 240mm thick slab with 750 x 900mm beams. Tendons in the greater span direction are located inside the beams, while in the perpendicular direction they are located in the slab. The overall quality and comfortable parking experience afforded is an advantage of being able to remove the middle columns in the 16m span direction, through the adoption of a post-tensioned approach. TEAM & TECHNOLOGY Client – Crtorad d.o.o. Main contractor – Zagorje Tehnobeton d.d. Designer – K.A. Biro d.o.o. Technology – BBR VT CONA CMM monostrand BBR Network Member – BBR Adria d.o.o. (Croatia) 3 36 CONNÆCT | EDITION 8 PORTFOLIO BUILDINGS Optimal solution There are several reasons that unbonded post-tensioning was chosen as the UNDERGROUND CAR PARK, WROCLAW, SILESIA, POLAND Material & cost savings with post-tensioning optimum solution for this project. Firstly, there was positive experience in terms of bridging these spans from the Tuskanac underground car park in Zagreb – a project carried out by BBR Adria in 2008. Next, the high water table demanded shallow excavation – and consequently, construction could only be carried out with shallow slabs. The third reason was the time schedule – project execution during the winter, with a tight time schedule, dictated use of 15 x 80m working segments. Thus, in the direction of span beams, a 15 x 80m slab was OPTIMIZED CONSTRUCTION & BUDGET concreted and stressed in one go – thanks to unbonded technology, the friction losses could be kept to a minimum. Only the first slab above foundation level was subsequently connected with the side walls after stressing, while the upper slab was cast and stressed along with the side walls. This approach resulted in an absence of shrinkage and temperature cracks, despite a large segment length of 80m. Above the car park’s upper slab, on top of a one meter bank layer, a decorative city square was constructed and landscaped. BBR Network Member, BBR Polska has recently been involved in a project which clearly highlights the benefits of early collaboration Safe, easy and attractive to use between main and specialist contractors and shows how PT technology The new car park is characterized by its used in slabs saves construction materials and allows optimization of great all-round visibility – with only minimal visual barriers – which, together with the other structural elements. Design Co-ordinator, Bartosz Lukijaniuk, wide access ramps and their gentle outlines the realization of this important new underground car park right gradients, make this new facility safe, easy next door to Wroclaw’s Centennial Hall. and attractive to use. As a result of the positive feedback from The underground car park is designed for Our post-tensioned slab solution saved investors and clients, BBR Adria is strongly around 800 cars, over two underground 12% of the construction costs compared promoting this large span approach to levels, and covers a total area of with traditional reinforced concrete. building layout as a standard ‘way to go’ 7,200m2 – with some 12,700m2 of post- In addition, our solution minimized the in the region. Meanwhile, the quality and tensioned slab. overall structural thickness – which was optimal solution offered by this type of Our early selection by the main contractor actually a crucial issue. By using our PT building have officially been recognized by meant we could contribute to concept solution, we reduced the overall height the civil engineering profession – the design and project specification. The main of the structure by 700mm – again, project’s designers were presented with contract includes design, construction compared with taking a traditional the 2013 ’Kolos’ Award by the Croatian and maintenance of the car park for reinforced concrete approach. This Chamber of Civil Engineers for a remarkable several years – so our client was structural optimization reduced achievement in the construction category. ● especially keen to use structural solutions excavation needs by about 5,000m3 too. ● and technologies offering problem-free maintenance. The client chose BBR technology because, among other 1 Installation of BBR VT CONA CMM monostrand unbonded post-tensioning underway – this system was chosen as there was good earlier experience locally and the system promoted a particularly fast construction time. 2 Post-tensioning allowed the creation of large spans at the new city center underground car park in Varazdin, Croatia. 3 Adopting a post-tensioned approach allowed removal of middle columns in the 16m span direction – and affords an overall quality and comfortable parking experience. benefits, post-tensioning promotes TEAM & TECHNOLOGY reliable slab performance – especially in Owner – Hala Ludowa Main contractor – Budimex S.A. Designer – VROA Architekci and CH+ Architekci (architectural), Bartels Polska (structural), POMOST & BBR (post-tensioning) Technology – BBR VT CONA CMM monostrand BBR Network Member – BBR Polska Sp. z o.o. (Poland) relation to reduced cracking. Also, our solution offered low construction material consumption. The rate of consumption of reinforced concrete was 12kg/m2 and for post-tensioning this was reduced to 3.5kg/m2 with a slab thickness of 250mm for spans of 7.85 x 7.85m. www.bbrnetwork.com 37 PORTFOLIO BUILDINGS PROJECT HIGHLIGHTS Brief overview of five BBR Network projects in Singapore SPACIOUS AND STRONG IN SINGAPORE With space always at a premium on the island of Singapore, it is no surprise that owners, developers and users of buildings of all types are keen to embrace the benefits of post-tensioning. Five recent schemes here demonstrate the advantages of post-tensioned beams and slabs, not only for delivering greater floor-to-ceiling heights, but also higher floor loadings – and maximized opportunities for expansive column-free spaces. 3 Eldix @ Sungei Kadut Planning Area TEAM & TECHNOLOGY This 12-storey ramp-up – featuring a delivery ramp – multi-user industrial 1 Owner – Singapore Workforce Development Agency (WDA) Main contractor – Greatearth Construction Pte. Ltd C&S Consultants – Beca Carter Hollings & Ferner (SE Asia) Pte. Ltd Technology – BBR CONA internal, BBR CONA flat BBR Network Member – BBR Construction Systems Pte. Ltd (Singapore) building is located within the Mandai Estate, northwestern Singapore. 2 Owner – Ministry of Education Singapore Main contractor – Hytech Builders Pte. Ltd C&S Consultants – Beca Carter Hollings & Ferner (SE Asia) Pte. Ltd Technology – BBR CONA internal, BBR CONA flat BBR Network Member – BBR Construction Systems Pte. Ltd (Singapore) 3 Owner – EL Development Pte. Ltd Main contractor – Evan Lim & Co. Pte. Ltd C&S Consultants – Fong Consult Pte. Ltd Technology – BBR CONA internal, BBR CONA flat BBR Network Member – BBR Construction Systems Pte. Ltd (Singapore) 1 National Continuing Education and 4 Premier @ Kaki Bukit Training (CET) East Campus, Paya Lebar This is a flexible blend of eight story 'ramp A newly completed eight storey teaching up' and nine storey flatted, industrial facility, the CET Campus East offers development aimed at expanding and industry skills training and also provides aspiring entrepreneurs. horizontal training programs, covering By adopting a post-tensioned approach to employability skills and service excellence. the scheme, the development offers high In addition, CET East Campus will also host ceilings and a column-free layout promoting short quality CET programs, such as master better space utilization, as well as allowing classes, professional development direct container access for ramp-up units programs and workshops. to enhance business efficiency. 4 Owner – Wee Hur (Kaki Bukit) Pte. Ltd. Main contractor – Wee Hur Construction Pte. Ltd C&S Consultants – LSW Consulting Engineers Pte. Ltd Technology – BBR CONA internal, BBR CONA flat BBR Network Member – BBR Construction Systems Pte. Ltd (Singapore) 5 Owner – Ascendas Pte. Ltd Main contractor – Nakano (Singapore) Pte. Ltd C&S Consultants – Ronnie & Koh Consultants Pte. Ltd Technology – BBR CONA internal, BBR CONA flat BBR Network Member – BBR Construction Systems Pte. Ltd (Singapore) 38 CONNÆCT | EDITION 8 2 New Primary School, Bukit Panjang 5 8B @ Admiralty, Admiralty Street Site 16 This multi user light industrial scheme Winning the coveted BCA Green Mark in northern Singapore features eight Platinum Award, the new school consists of post-tensioned floor levels offering high three blocks of five to six storey teaching floor loadings and excellent ceiling heights, facilities, one block containing a multi- as well as dedicated loading bays and purpose hall – with a rooftop football field – post-tensioned access ramps for trucks and other ancillary buildings. to every floor. PORTFOLIO BUILDINGS resulted in the award of post-tensioning works for this project. Our role here was to post-tension the suspended floors, typically of 13.5m x 9m floor spans involving 300t of prestressing steel. By adopting a PT approach to the MUHARRAQ SEEF MALL, BAHRAIN, UNITED ARAB EMIRATES public areas, wide open spaces have been achieved which will not only enhance Post-tensioning for floor slabs consumer experiences, but will also offer BAHRAIN’S NEWEST MALL flexibility should the client require structural As Bahrain’s new Muharraq Seef The Muharraq Seef Mall is a BD15.65m and other specialist services for buildings Mall opens its doors to the general project situated between the Muharraq Club has grown in the region, often as a result and the Arad Fort in Bahrain, facing onto the of our first class performance on newly constructed corniche and bay. The infrastructure schemes. To date, we have BBR Network Member, NASA mall has been constructed over two retail provided technology and expertise for over Structural Systems LLC, reflects floors offering approximately 30,000m2 of 200 buildings, 19 storage tanks and 50 on the challenges presented by retail space with ample parking underneath bridges throughout the Middle East. ● public, Warwick Ironmonger of this major project – one of many changes at some later stage. Our reputation for providing post-tensioning on the ground floor. The project also includes an open air amphitheater that will building projects carried out during be used for public and cultural events. the company’s 15 years in the Previous involvement on similar projects – Middle East. including a nearby mall on the Muharraq Island and the 162,000m2 Bur Juman Expansion project in Dubai – along with sound technical support at tender stage, TEAM & TECHNOLOGY Owner – Muharraq Mall Company Main contractor – Almoayyed Contracting Technology – BBR CONA flat BBR Network Member – NASA Structural Systems LLC (United Arab Emirates) CONCERTO NORTH KIARA CONDOMINIUM, KUALA LUMPUR, MALAYSIA Post-tensioned transfer slab WINNING ALTERNATIVE DESIGN Concerto North Kiara is a new condominium structural PT slab to the columns. We consisting of three high rise residential overcame this problem by increasing the blocks above a podium containing four car thickness of the PT slab by 150mm at parking levels. The unique design – several locations, making the structure When time and costs – as well as resembling a piano keyboard – results in high stiffer and distributing the loads through achieving a challenging design drops in floor level which contribute to the selected columns. By placing the two-way complexity in structural design and detailing. tendons with selected profiles at the The transfer floor was originally designed required locations, load balancing between Construction Systems Malaysia with a 2,100mm deep beam and slab the gravity loads and prestressing uplift produced a contract-winning system. We redesigned it with a post- forces was achieved. alternative design for the client, tensioned slab to support the load-bearing While the main contractor is benefitting shear walls which in turn support 30 floors from the shallow and simpler formwork above. A typical post-tensioned slab is and the shorter erection time, the owner Chuen Lin Lee, Design Engineer, 1,400mm thick and transfers the loads to will also benefit from the flat and more tells the story. columns on an 8m x 8m grid. Our client, the attractive soffit of the transfer floor. main contractor, had secured this project The post-tensioned slab was designed for based on the benefits and cost reductions two stage casting with two groups of 1205 resulting from our alternative design. Time BBR CONA internal tendons. After first TEAM & TECHNOLOGY was critical as the foundations had been stage concreting had achieved a 35N/mm2 Owner – B C B Berhad Main contractor – Awangsa Bina Sdn. Bhd. Prestressing contractor – BBR Construction Systems Malaysia Technology – BBR CONA internal BBR Network Member – BBR Construction Systems (M) Sdn Bhd (Malaysia) built, while the design using our alternative strength, the first group of tendons were post-tensioned slab was still in progress. stressed to enable the second stage Various high drops of up to 700mm – for casting. Thus, the props to support the wet landscaped gardens – with few column concrete weight and backprops required for supports below, made it difficult to achieve floors below had been halved, providing the required load transfer through the savings to the client. ● concept – were critical, BBR who was also the main contractor. www.bbrnetwork.com 39 PORTFOLIO BUILDINGS ELEPHANT HOUSE ROOF, ZURICH ZOO, SWITZERLAND Post-tensioning of ring beam TRUMPETING TRIUMPH The centerpiece of Zurich Zoo’s The giant roof with an area of 6,000m2 and additional elements as far as possible. 85m in diameter acts as a self-supporting The ring beam transfers the roof loads shell structure, whose loads are transferred through a limited number of shear walls via a post-tensioned concrete ring beam to to the roof foundations which are house with a striking curved wooden local roof foundations. The roof's shape is anchored by piles to resist vertical load roof structure. Fabian Persch of irregular in order to have a natural, random and by permanent ground anchors for BBR Network Member Stahlton AG appearance and to meet the building's horizontal load. utilization requirements. The 270m long It is essential for the roof's stability that ring beam was the most complex element the shear walls should only permit very of the support structure. It follows the small horizontal movements. Thus, each uneven behavior of the roof edge and, wall is prestressed with a vertical post- while bridging spans of up to 40m with tensioning tendon. To withstand the only very small deflections permitted, the design loads, as well as to act as a tension beam is intended to be thin and invisibly flange in accidental design situations – integrated in the roof. This could only be such as the failure of ground anchors achieved by using post-tensioning. and hence the horizontal support of an The aim of the concrete structure's design abutment zone – the ring beam itself is was to integrate all concrete members, prestressed with nine post-tensioning such as rain water tanks or stables, for tendons with lengths of up to 120m and transferring the roof load – and thus avoid a prestressing force of 190t per tendon. 2 10,000m Kaeng Krachan Elephant Park is a circular concrete elephant reveals the challenges behind the realization of this unusual structure. 1 Artist’s impression of the finished Elephant House at Zurich Zoo, Switzerland. 2 Reinforcement and post-tensioning tendons were installed in a ‘wooden channel’ which was subsequently closed, filled with selfcompacting concrete and became an integral part of the structure. 1 40 CONNÆCT | EDITION 8 PORTFOLIO BUILDINGS FOUNDATION SLAB FOR STONE CRUSHING BUILDING, LA ROCHELLE, FRANCE Crack-free post-tensioned ground slab CRUSHING VICTORY Holcim France – part of the Swiss group, Holcim Ltd – is constructing a new finishing and distribution center in south western France. The project, known as Ciments de La Rochelle, will create a cement manufacturing and packaging center in the heart of the city’s maritime port. BBR Network Member, ETIC, was called upon to provide post-tensioning services for one of the site’s key building complexes. Guillaume Wastiaux, 2 Sales Manager for the French market, takes up the story. The tendon layout is three-dimensional – This overall project was conceived to We supplied and installed horizontal the cables are arranged so that, vertically, support the strong growth in construction post-tensioning using 12 BBR VT CONA the ring beam lifts the roof in the spans and public works activities in the west of CMI BT 2706 tendons and vertical and, horizontally, it is tied to the wall France. The new plant will undertake the post-tensioning with 126 x 50mm abutments. Two tendons were always mechanical crushing and mixing of raw diameter PT bars. arranged in parallel to avoid twisting of materials and packaging of the finished While the PT bars were prefabricated the ring beam. Due to the sophisticated product for distribution. When completed, in the ETIC workshop, we installed the geometry of the structure, the position the site will accommodate seven zones – CONA CMI tendons on site using the of the tendons and the prestressing raw material storage silos, raw material strand-by-strand method and then niches had to be specified and measured mixing tower, crushing and drying stressed and grouted them with cement. to millimeter accuracy. complex, cement and hydraulic binder It took our team just two weeks on site Reinforcement and post-tensioning storage silos, packaging building, to complete the work. ● tendons were installed in a ‘wooden storage facility, plus an administration channel’ that when subsequently closed building with a laboratory and offices. with shuttering became a ‘wooden pipe’ Our role has been to provide post- and was filled with self-compacting tensioning for the massive 20 x 20 x 10.5m concrete. The lowest layer of the post-tensioned floor slab of the crushing multi-layer wooden roof served as the building. As the slab will carry the soffit formwork and, together with the enormous load of a stone crushing shuttering and the formwork sides, was machine – crucial to the plant’s also left in the structure. operations – the client naturally After staged stressing of the tendons, required an approach which would the roof – so far supported by falsework minimize cracking. TEAM & TECHNOLOGY Owner – Holcim Main contractor – ERC HARRANGER Technology – BBR VT CONA CMI internal, PT bar BBR Network Member – ETIC S.A. (France) – was lowered and the loads transferred to the ring beam and foundations, respectively. Structural deflections were monitored with fiber-glass sensors, such that comparisons could be made between the calculated and actual forces / moments in the ring beam. ● TEAM & TECHNOLOGY Client – Zurich Zoo Main contractor – Landolt AG Designer – Walt + Galmarini Technology – BBRV wire BBR Network Member – Stahlton AG (Switzerland) www.bbrnetwork.com 41 PORTFOLIO BUILDINGS 2 1 THE PARABOLA, LONDON, UK Post-tensioned slab design & installation, specialist heavy lifting techniques REVIVING A BOLD STATEMENT “We are using the A redevelopment scheme based around a prominent former public BBR VT CONA CMF building in Kensington, London will see the revival of an iconic structure, and CMI 1206 systems along with the creation of unique museum space and new residential with both fixed and movable couplers to accommodation. Richard Gaskill of local BBR Network Member, Structural Systems UK Limited, takes us through the project’s history and outlines the construction challenges. allow continuity of pre-stress across the The Parabola – the former Commonwealth The planning brief called for the Institute building – had been neglected for preservation of the main structure – a construction joints.” nearly 10 years before it was acquired by listed building – for use as an art gallery developers Chelsfield Partners. Their vision with a greater integration of the gardens is to bring life back to the listed building into Holland Park. After an architectural which has a quirky saddle-shaped structure competition to explore the best design at its heart. The Parabola – accommodating and practice, much discussion with The Design Museum – will become the English Heritage, the local authority and centerpiece in a development designed to other parties, planning consent was given complement the ingenuity that was the in September 2009 and construction basis of its original creation. commenced on site in 2012. History & planning PT design & installation Completed in 1962, on a 3.25 acre site Structural Systems’ role is to provide fronting onto Kensington High Street, The post-tensioning design and installation Parabola’s copper clad hyperbolic paraboloid expertise for the floor slabs of the three roof has been described as a ‘bold new residential buildings and to apply statement’ back then. The striking roof was specialist jacking services techniques for born of the architect’s desire to create a ‘tent the support of the iconic roof of The in the park’ – half of the roof was concrete, Parabola to enable the existing floors to whilst the other half was traditionally built. be demolished and rebuilt beneath it. 1 General view of Block B – PT slabs under construction using BBR CONA CMF BT 3 and 4 strand tendons. 2 View of parabolic roof structure to Block D, with post tensioned Block C undergoing fit-out work in the background. 42 CONNÆCT | EDITION 8 PORTFOLIO BUILDINGS AIR FORCE MUSEUM OF NEW ZEALAND, WIGRAM, CHRISTCHURCH Post-tensioned concrete floors GROUNDED IN EXCELLENCE Growing demand for high-performance post-tensioned concrete floors continues to keep the BBR Contech team busy. One recent project required the provision of strong floors with attractive finishes capable of holding the weight of aircraft on display at the Air Force Museum of New Zealand. Levels 1 and 2 of the structure beneath the roof of the existing Institute (Block D) are being installed using post-tensioned concrete, as are the new buildings on the site – Blocks A, B and C. We are using the BBR VT CONA CMF and CMI 1206 systems with both fixed and movable couplers to allow continuity of pre-stress across the construction joints. Supporting the roof Achieving suitable support for the roof was logistically and technically difficult. It required a combination of hydraulic jacking, flat jacking and bar jacking – in association with an extremely complex temporary works solution involving a considerable amount of steelwork. The original design of The Parabola The Museum is home to a superb Bristol Freighter, with a smooth finish and incorporated the latest techniques of collection of military aviation memorabilia, comfortable ambient temperature to suit that time and used lightweight fully restored aircraft, such as the de the room’s role as a venue for displays construction to produce a building that Havilland Vampire, Supermarine Spitfire and public functions. was functional with minimal resources. and P-51 Mustang, to medals and The second post-tensioned floor, covering The inclusion of the three apartment parachute-silk wedding dresses. 983m2, was installed in the workshop buildings along with The Design Museum In February 2013, the Museum celebrated area. Together, these two projects have will again reflect contemporary a major milestone – the official opening by helped the Museum to improve both its construction techniques and produce a the Governor-General of a NZ$15 million, public face and the working environment scheme which is energy efficient, easy 6,500m2 extension designed by Warren it provides for those responsible for its to access and is complemented by its and Mahoney. The new ‘Technology fascinating restoration projects. ● landscaped surroundings. ● Center’ – which effectively doubles the Museum’s original size – includes an elegantly spacious, hangar-styled display gallery, a large restoration area and a TEAM & TECHNOLOGY Owner – Chelsfield Partners Main contractor – MACE Architect – OMA Technology – BBR VT CONA CMI internal, BBR VT CONA CMF flat, Heavy lifting, PT bar, MRR range BBR Network Member – Structural Systems UK Limited (UK) 1 number of workshops. BBR Contech was involved in two floors in the Museum. The first was the floor in the display gallery – a 200mm-thick, 4,200m2 expanse of post-tensioned, water-pipeheated concrete, which was poured in two consecutive days. The floor has the strength to hold the 130kN axle load of a TEAM & TECHNOLOGY Client – RNZAF Museum Trust Board Architect – Warren and Mahoney Main contractor – Mainzeal Property & Construction Flooring contractor – Conslab Ltd Engineer – Alan Reay Consultants Technology – BBR CONA flat BBR Network Member – BBR Contech (New Zealand) www.bbrnetwork.com 43 PORTFOLIO STAY CABLES PRZEMYSL BRIDGE, SOUTHERN POLAND Official opening by Prime Minister SYMBOL OF PROGRESS The new Przemysl Bridge was opened by Prime Minister Donald Tusk, on the eve of Polish Independence Day – and in the full glare of the nation's media. In his speech, Prime Minister Tusk said: “The fact that today we are standing underneath these modern pylons, this modern bridge is a symbol of the distance Poland has covered.” TEAM & TECHNOLOGY Owner – Local Management of District Roads, Przemysl Main contractor – Mota-Engil Central Europe S.A. Designer – Promost Consulting Technology – BBR HiAm CONA stay, Incremental launching BBR Network Member – BBR Polska Sp. z o.o. (Poland) 44 CONNÆCT | EDITION 8 BBR Polska was represented at the opening ceremony by CEO Jan Piekarski. The project featured incremental launching of the steel bridge deck and installation of BBR HiAm CONA stay cables. The bridge, which is part of the Przemysl Ring Road, will alleviate traffic congestion in the city center and allow easier access to the border crossing with Ukraine. ● PORTFOLIO STAY CABLES NEW ACCESS FOR EUROPEAN SCHOOL, MAMER, LUXEMBOURG Stay cable technology using stainless steel ducting FLYING ENTRANCE FOR SCHOOL When the stunning new flyover with its unique geometry at Mamer, in Luxembourg, was opened in late 2013, peak time commuters and students alike must have sighed with relief. Claude Néant of BBR Network Member, ETIC, provides some insights into this unusual and very striking project. 1 The N6 highway between Bertrange and New flyover Mamer is one of the main routes into the The new flyover bridge – with two 66m city of Luxembourg and is obviously very spans – carries road traffic on a single busy during the rush hour. With the arrival unidirectional carriageway, as well as a of the new European School, right next door mixed pedestrian and bicycle track on to an existing technical high school, extra a curved radius of 102.25m. road and pedestrian traffic generated by The structure consists of two steel the two schools was set to make traffic frames connected by struts and a jams even worse. reinforced concrete slab, founded on mass abutments and further supported 1 The new flyover bridge is supported on mass abutments and two concrete piers on the outer curve, plus 10 stay cables on the inner curve. 2 Installation of the five pairs of BBR HiAm CONA stay cables began at the upper anchorages, on the inclined free-standing pylon. 3 A special feature of the design is the stainless steel ducting for the stay cables, installed using a cable winch-and-pulley system. 4 Installation of the stay cables at the lower anchorages, on the outside of the bridge structure. Improving traffic flow by two huge concrete piers on the outer To improve traffic flow on the N6, relieve edge of the curve. The inside of the pressure on a key roundabout and provide curve is supported by ten stay cables good private and public transport access to attached to an inclined free-standing the schools themselves, new dedicated steel pylon. infrastructure leading from the main road to The steel structure was prefabricated the schools was commissioned. Key features off site and delivered to the workface of this would be an underpass for the in sections for lifting by crane and technical high school and a flyover with its assembly on temporary piers. Stay distinctive inclined steel pylon and stay cable cables were installed after the concrete construction for the new European School. deck had been poured. ➤ www.bbrnetwork.com 45 PORTFOLIO STAY CABLES Stay cable system Our role was to prepare the stainless steel stay cable ducting tubes on the ground and to supply, install and tension the BBR HiAm CONA stay cable system. A special feature of this structure is that it was designed with stainless steel ducting for the stay cables which we installed by using a cable winch and pulley system. The stays consist of bundles of 15.7mm diameter galvanized strand that has been tested and validated according to BBR procedures. There were five pairs of stay cables of between 7-15 parallel strands each which were individually waxed coated and sheathed, and further enclosed in stainless steel stay cable ducting. We began installing the system from the top anchors and tensioning point on the pylon, to the lower anchors on the outside of the bridge structure. In total, we used 3,900kg of stay cable strands and 325m of stainless steel ducting, plus 16 x 15 strand HiAm CONA anchors and four 7 strand HiAm CONA anchors. The entire work was completed with great collaboration between the Tralux and ETIC teams – and without any access difficulties for guests attending the official opening of the nearby school during the construction period. ● 2 3 TEAM & TECHNOLOGY Owner – State of Luxembourg, Ministry of Sustainable Development & Infrastructure, Regional Services Division Architect – BENG Consulting engineer – Schroeder & Associates Main contractor – Tralux Construction Specialist contractors – Victor Buyck Steel Construction (steel frame) Technology – BBR HiAm CONA stay BBR Network Member – ETIC S.A. (France) 4 46 CONNÆCT | EDITION 8 PORTFOLIO TANKS & SILOS ANAEROBIC DIGESTER TANKS, HUNGARY Band post-tensioning of circular tanks BUILDING FOR BIOGAS BBR Network Member KB Vorspann- The BBR VT CONA CMM tendons Technik has recently carried out consisted of two compacted steel strands post-tensioning of four digester tanks with a 165mm2 cross-section and 1,820MPa for biogas production in North Eastern stressing steel incorporated in bands. Hungary. In the city of Miskolc, nearly A further two 1,700m3 digesters were built 200km north-east of Budapest, two at a plant in Nyiregyhaza. Here, the tanks – 16m high, 18m diameter post-tensioned both 18m high and 12m in diameter – were digester tanks have been constructed. constructed with 142 BBR VT CONA CMM monostrand tendons made from 150mm2 cross-section, 1,860MPa stressing steel. ● 1 1 Post-tensioning for the two 1,700m3 digester tanks in Nyiregyhaza consisted of 142 BBR VT CONA CMM monostrand tendons. 2 The two 16m high, 18m diameter posttensioned digester tanks in Miscolc, Hungary. TEAM & TECHNOLOGY 1 Biogas Plant, Nyiregyhaza, Hungary Owner – City of Nyiregyhaza Main contractor – Monolit – Epszer Kft. Planner – Nyirseg Konzorcium, Ke-Viz Zrt. Technology – BBR VT CONA CMM monostrand BBR Network Member – KB VorspannTechnik GmbH (Austria) 2 Biogas Plant, Miskolc, Hungary Owner – City of Miskolc Main contractor – Colas Alterra zrt. Designer – Megalit Mernoki Iroda KFT Technology – BBR VT CONA CMM band BBR Network Member – KB VorspannTechnik GmbH (Austria) 2 www.bbrnetwork.com 47 PORTFOLIO TANKS & SILOS WATER RESERVOIRS, AUSTRALIA & NEW ZEALAND PT precast concrete and design & construction of PT tanks IMPROVING WATER SUPPLY Members of the BBR Network around the world provide services which are vital to the water industry’s ability to supply fresh water for growing populations. The long term performance and structural stability of reservoirs can be greatly enhanced by taking a post-tensioned approach to their construction. 1 Wilmers Road Reservoir, New Zealand – a structure standing 6m high and measuring 31m in diameter. 2 Mount View Reservoir, Australia – the new five million liter capacity post-tensioned concrete reservoir is 28.88m in diameter and 10.6m high. 1 1 Wilmers Road Reservoir, New Zealand The Christchurch suburb of Hornby is a structure standing 6m high and measuring changing rapidly, largely owing to 31m in diameter. The work involved: residential and industrial growth that is • supplying the panel manufacturer with being encouraged as part of a long-term TEAM & TECHNOLOGY 1 Client – Stronger Christchurch Infrastructure Rebuild Team Main contractor – Downer Engineer – Opus International Consultants Technology – BBR VT CONA CMI internal BBR Network Member – BBR Contech (New Zealand) 2 Owner – Hunter Water Corporation Main contractor – Leed Engineering & Construction Pty Ltd Designer – Structural Systems Limited (Australia) Technology – BBR VT CONA CMI internal BBR Network Member – Structural Systems Limited (Australia) 48 CONNÆCT | EDITION 8 community plan. The local BBR Network Member, BBR Contech, has provided ducting for the tendons, which was cast into the panels • once the panels were assembled on site, post-tensioning for a precast concrete coupling the ducting and carefully water tank which will improve water supply installing the 11 tendons – comprising to the suburb. seven 12.7mm strands each – horizontally Recognizing that the community needed an in the panels, effectively encircling the additional water supply, Christchurch City Council has built a new water supply pump tank’s circumference • stressing the tendons to the desired station in the area. The facility comprises a load, then grouting them in place. pumping station and a freshwater holding The project is now complete, providing tank, with the latter having a capacity of the residents and businesses in the area more than 3.7 million liters. with a much-improved water supply and a BBR Contech was called on to provide structure that, thanks to the use of post-tensioning services for the precast post-tensioning technology, can withstand concrete panels that form the tank wall – the damaging forces of an earthquake. PORTFOLIO TANKS & SILOS ETHANE TANK, PORSGRUNN, NORWAY Horizontal & vertical tank post-tensioning 2 GEARING UP FOR GAS As part of an expansion plan for the 2 Cessnock & Lochinvar Hunter Region, INEOS site at Rafnes in Norway – Australia explains John Taraldsen of BBR The post-tensioning for two concrete water tanks has recently been designed Network Member, KB Spennteknikk and installed by Australian BBR Network – the company was hired to provide Member, Structural Systems. post-tensioning services for a new Increased demand led Hunter Water ethane tank. Corporation to embark upon a water supply upgrade for parts of the Hunter Region. The new tank – along with expanded Two of the projects within this program were infrastructure – is being constructed in the Cessnock Water Supply Upgrade and an industrial park in Porsgrunn, Norway – the Maitland North Rothbury Water Supply approximately 200km from Oslo. The Upgrade – each of which required the new facility for INEOS will expand the design and construction of a new reservoir. company’s ability to access ethane from At the Mount View Reservoir, part of the world markets and secure long term Cessnock Water Supply Upgrade, a five competitiveness and jobs at the site. million liter concrete reservoir was The main contractor, our client, slipformed constructed. The new reservoir is 28.88m the concrete walls of the tank and we in diameter and 10.6m in height. were on site during the operation. Meanwhile, for the Maitland North Rothbury For the horizontal tendons, we used 204 Water Supply Upgrade project, at Lochinvar, BBR VT CONA CMI 1206 tendons with a 10ML tank with a 46.28m diameter base 170t of 15.7mm diameter strand (150mm2, and 10m high walls 10m was constructed. 1,860MPa). The vertical post-tensioning Structural Systems provided the detail is made up of 52 CONA CMI 0406 loop design for the reservoirs, including post- tendons and we used 17t of strand. TEAM & TECHNOLOGY tensioning services. The design Standing 32m high with an external incorporated the use of a post-tensioned diameter of 45.7m, the new tank will be slab on ground, vertical precast panels for capable of holding 30,000m3 of ethane and the walls with post-tensioning both vertically will be ready to receive its first consignment and circumferentially. in the second quarter of 2015. ● Owner – INEOS / Noretyl Client – Veidekke Entreprenør AS Designer – TGE Gas Engineering GmbH Technology – BBR VT CONA CMI internal BBR Network Member – Spennteknikk AS (Norway) The slabs on ground consisted of a 150mm thick concrete slab connected to a 600mm deep x 2000mm wide ring beam. Precast panels were cast on site and lifted into position. The panels were 280mm thick varying in width from 3300mm to 4100mm – and weighing up to 28t. Individual panels were joined with circumferential post-tensioning tendons stitched together by a cast in-situ concrete infill joint. Due to program constraints the reservoirs were constructed concurrently and successfully completed on time and within budget. ● www.bbrnetwork.com 49 PORTFOLIO SPECIAL APPLICATIONS BRIDGE SLIDING, WESTERN AUSTRALIA Development & execution of specialist bridge slide operation SLIDING WITH SAFETY & SPEED A bridge sliding operation carried out in connection with a regional railway link project admirably demonstrates the care, skill and precision with which the BBR Network delivers customer requirements. Mark Sinclair, General Manager (Civil Engineering), of Structural Systems – the BBR Network Member in Australia – recounts how a lateral bridge slide design and sliding operation was jointly developed with the main contractor for Package C of the Melbourne Regional Rail Link Project. 1 50 CONNÆCT | EDITION 8 PORTFOLIO SPECIAL APPLICATIONS “The lateral slide method was chosen to minimize the impact on rail traffic as part of the grade separation works, thus allowing Anderson Road traffic to pass under the rail line.” 2 1 Regional rail link, Melbourne – sliding of the twin track rail bridge to the rail alignment during a possession of the tracks. 2 SSL Australia’s site team executed the bridge slide during three consecutive 12 hour shifts. Pictured here is the night crew (left to right): Jeff Babbage, Kennedy David, Alan Denning, Kane Goodrope and Daniel Reardon – Mark Sinclair was behind the camera. 3 Two of the three jacks can be seen in this photo. The isoflow pump and control system ensured equal hydraulic flow to all jacks regardless of any load difference, which ensured constant movement in all locations and no unexpected loads or movements on the bridge during sliding. 3 The project involved the lateral sliding of a A pull back system was designed, detailed two span, twin track skewed composite rail and supplied should the need arise to bridge from its assembly area, to the rail reverse the bridge, but this was not needed alignment during a shutdown. The lateral in this instance, but is a necessary slide method was chosen to minimize the insurance considering that launch timing impact on rail traffic as part of the grade is always critical. separation works, thus allowing Anderson The site works were carried out over three Road traffic to pass under the rail line. consecutive 12 hour shifts starting on the The 45m long, 11m wide, 1,350t bridge was morning of 7th October 2013. The day launched laterally using three of our 145t crew set up and tested the system, then by 1.4m stroke lifting system jacks and a the night shift came in to launch the bridge TEAM & TECHNOLOGY modular 56mm coupled segmental high 25m into the final position and achieved an tensile bar system. This system provides accuracy, both longitudinally and laterally, a factor of safety in excess of 2.5. of 2mm. The actual launching works took The hydraulic jacks were controlled by an seven hours, then the day crew returned Isoflow pump and console, which enables and completed decommissioning and equal hydraulic flow and therefore equal packing up the system. ● Owner – VicTrack Access (V Line, Metro and ARTC) Main contractor – Thiess Balfour Beatty Joint Venture Designer – Parsons Brinckerhoff & SKM (lead designers), Structural Systems (specialist launching system) Technology – Sliding BBR Network Member – Structural Systems Limited (Australia) jack extension regardless of the individual load in each of the bars. www.bbrnetwork.com 51 PORTFOLIO SPECIAL APPLICATIONS 1 ZURICH MAIN RAILWAY STATION, SWITZERLAND Tunneling under southern wing INNOVATIVE TUNNEL CONSTRUCTION With the Cross City Link project, a new railway line is currently under construction in Zurich to connect the western part of the city with the main station and Oerlikon station to the north. A significant part of the project is the 4.8 km long Weinberg Tunnel – which runs into a newly built station directly underneath the historical main station. Fabian Persch of local BBR Network Member, Stahlton AG, describes his company’s innovative approach to meeting the post-tensioning challenges of this major project. 1 Trolley with stressing jack. 2 Reinforcement and formwork of the end beam. 3 Installation of monostrands with deviation device. TEAM & TECHNOLOGY Client – Swiss Federal Railways (SBB) Main contractor – ARGE Tunnel Weinberg Oerlikon Designer – Pöyry Schweiz AG Technology – CONA electrically isolated BBR Network Member – Stahlton AG (Switzerland) 52 CONNÆCT | EDITION 8 For a length of 110m, the new Weinberg on diaphragm walls that provide lateral Tunnel runs below the 150-year old heritage- support as the basement is excavated. protected southern wing of the station – Due to the lack of access above ground, thus, the tunnel had to be constructed the slab and the diaphragm walls had to without causing any structural damage to be constructed using a conventionally the building. Construction in close proximity driven system of longitudinal and to the southern wing, as well as the transverse tunnels. logistical difficulties involved with tunneling A total of 29 support beams, which were beneath an intensively used railway hub, cast inside the transverse tunnels, form a has required innovative solutions. slab supported by the diaphragm walls. Protected by this structure the actual Construction method tunnel works could be carried out. Once The construction method chosen for the completed the longitudinal tunnels will undercrossing was a variation of the top- function as access passages, from which down solution. Top-down construction the post-tensioning of the support beams consists of a basement roof slab supported can be checked and replaced if necessary. PORTFOLIO SPECIAL APPLICATIONS Construction sequence PT challenges The size of the two 110m long longitudinal For the design of the slab post-tensioning, tunnels was designed to enable the a multitude of boundary conditions had to construction of the diaphragm walls and be considered. Swiss Federal Railways’ the driving of the transverse tunnels. The guidelines require all tendons to be size of the transverse tunnels was given electrically insulated. Also, potential by the driving requirements and the static replacement of tendons at a later stage analysis for the support beams that had to had to be ensured. The main challenge, be installed. The driving of the transverse however, was the extremely limited working tunnels and the concreting of the beams space in the tunnels. After concreting of the was carried out using a step-back end beam, the clear distance to the tunnel procedure – that is, starting with the walls was very narrow with a maximum primary tunnels and followed by secondary width of 1.50m. A strand overlength that is tunnels between them. On average, every normally required for tensioning tendons eight working days a support beam could be or destressing them for later replacement, filled with up to 380m3 of self-compacting was not available. Neither could concrete. Subsequently, the end girders conventional lifting equipment for the which transfer the loads to the diaphragm stressing jack be used in the narrow tunnel. walls were concreted. The end girders also contained the anchorages of the Unique PT system design post-tensioning tendons. The post-tensioning system that was eventually designed can certainly be 2 considered unique. The tendons consisted of sheathed monostrands, which were pushed into cast in-situ plastic pipes in the transverse beams. To make sure that they withstand the concrete pressure, the pipes were filled with water during concreting. The strand coils had to be placed outside the tunnel – and the monostrands had to be pushed through using a long guide tube and special deviation device. In total, 3,600m of post-tensioning tendons – amounting to 80t of prestressing steel – were installed in the supporting load transfer slab. Tendon stressing was carried out with a bell-shaped grip, which was screwed onto the threaded anchor-heads and pulled by a specially manufactured stressing jack. Shims were placed between the stressed anchor heads and the bearing plates to maintain the elongation. Destressing of the cables at a later stage is achieved by simply removing the shims. Thus a strand overlength was not needed for stressing or for replacement. For placing the jack which weighed around 1,000kg, we designed and manufactured a suitable lifting trolley that could be moved along the end girder. After tendon stressing, the anchorages were sealed and the tendons were electrically insulated from the structure. After completion of the post-tensioning, the bracing loads from the slab were transferred actively to both diaphragm walls – then the tunnel excavation works under the completed transfer slab could begin. ● 3 www.bbrnetwork.com 53 PORTFOLIO SPECIAL APPLICATIONS 1 CONTAINER TERMINAL, PORT OF RIJEKA, CROATIA Post-tensioned beams CONTAINING STRENGTH FOR ADRIATIC Since it first opened some 25 years ago, container traffic through Rijeka’s Brajdica Container Terminal has constantly increased. Despite the economic recession, this trend has continued and increasing its capacity was vital to ensure future success of the facility. Kresimir Bogadi of Croatia-based BBR Adria takes up the story. The Brajdica Container Terminal sits on Croatia’s Northern Adriatic Sea coastline, on the southern side of the Rjecina river delta, south of the city of Rijeka. The project to increase capacity at Brajdica is part of the wider Rijeka Gateway Program to improve life and facilities for citizens, as well as to attract private investment into the area – and maximize the use of the port in a competitive market place. The Terminal’s busiest year, in 2008, saw more than 170,000 TEU (20 foot equivalent units) containers being transshipped. 1 The new quay for the Adriatic Gate Container Terminal near Rijeka takes shape at the busy container port. 2 Work in progress to connect the coastal ring beam and anchor wall behind using BBR VT CONA CMI / CME tendons. The capacity of the existing container terminal is estimated to be 250,000 TEUs per year, mainly due to the limited container storage space. 2 54 CONNÆCT | EDITION 8 PORTFOLIO SPECIAL APPLICATIONS Phase II outline Construction of Phase II of the Terminal includes a 328m extension of the coast INDUSTRIAL HARBOR, HORSØY, NORWAY Two stage installation of ground anchored crane base and construction of a 50,000m2 storage area – effectively doubling container services arriving or departing. Improved LIFTING POWER rail loading facilities for a larger number In Kleppestø, near Bergen in western Norway, BBR Network Member storage capacity. There will also be a new checkpoint on the D404 road to enable rapid truck transit and unify all of containers is also part of the planned upgrading program. Spennteknikk has carried out a two-staged ground anchoring operation As a part of the second phase of for foundations forming a harbor crane base. Stig Sjolbør describes his construction of the Brajdica Container company’s work. Terminal, 14.5m deep berths have been built to enable safe mooring of larger Stage 1, the foundation works, started in Making the connection container ships. BBR Adria is installing spring 2010 with plans already in place to We returned to site, some months later, 25 BBR VT CONA CMI / CME tendons in install a crane on the harbor in the future. to carry out the second stage of the the quay wall – to connect the coastal Therefore, when constructing the harbor, project. We installed a further 18 BBR VT ring beam and anchor wall behind. The the foundations were built with this in CONA CMG ground tendons of lengths tendons are formed in two parts. mind – a ground anchor with a K-coupler between 4.5-6.6m and connected the was installed to allow later connection of strands to the K-couplers already the crane to the foundation. installed during Stage 1, then the concrete Two part PT tendons The first part is in the coastal ring beams wall was poured. and is 3m long, consisting of a CONA CMI Post-tensioning works The steel crane connection was fixed in 1206 passive anchorage and CONA CMI We used 16 x 150mm2 BBR VT CONA CMG place after the concrete had hardened 1206 coupling anchorage. This part of the ground tendons with a length of between and then we stressed and grouted the tendon was grouted with cement grout 28-33m. The post-tensioning strands tendons. When the crane itself had been after stressing. were 15.7mm in diameter with an Ultimate mounted, it was successfully tested with The second part of the tendon is a Breaking Strength of 1860N/mm2 – a load of 400t. ● replaceable BBR VT CONA CME tendon greased and plastic coated on the free connected to the first part with a CONA length. CMI 1206 coupler. Construction of these The main contractor performed the removable tendons was performed such casting of the foundations and our client that the tensioning element has multiple performed the drilling works. We installed corrosion protection on its whole length. and grouted the permanent anchors and The CONA CME tendons are each made then we stressed the K-coupler anchors. up of 12 galvanized strands individually Then, we mounted a protective grease- greased and sheathed and further filled cover over the anchorage, for protected in a 110mm diameter HDPE pipe. connection when the crane was ready to The new quay, at the now renamed be installed. TEAM & TECHNOLOGY Owner – Horsøy Industrihavn AS Client – Kynningsrud Fundamentering AS (Stage 1), Framo Engineering AS (Stage 2) Main contractor – Veidekke AS Designer – Norconsult AS Technology – BBR VT CONA CMG ground BBR Network Member – KB Spennteknikk AS (Norway) Adriatic Gate Container Terminal (AGCT), was officially opened by Sinisa Hajdas Doncic, the Croatian Minister of Maritime Affairs, Transport and Infrastructure, during 2013. AGCT is now poised to support the Port of Rijeka in becoming one of the most competitive container ports on the Adriatic. ● TEAM & TECHNOLOGY Client – Port of Rijeka Main contractor – GP Krk Designer – Rijeka projekt Technology – BBR VT CONA CMI internal, BBR VT CONA CME external BBR Network Member – BBR Adria d.o.o. (Croatia) www.bbrnetwork.com 55 PORTFOLIO SPECIAL APPLICATIONS 1 2 EARTHQUAKE RESISTANT BUILDINGS, CANTERBURY, NEW ZEALAND Application of PRESSS technology DIVERSITY IN PRESSS TECHNOLOGY 2 Trimble Navigation offices, Christchurch While Trimble Navigation’s Christchurch office survived the 2010 and 2011 earthquakes, it was not destined to last for long – in 2011, the entire building was destroyed by fire. Replacing it will be the first building in New Zealand constructed with post-tensioned LVL frames and post-tensioned LVL walls. Standing two storeys high, it will also include clever devices that reduce earthquake PRESSS (PRecast Seismic Suited to steel, concrete and LVL damage by dissipating the energy and Structural System) technology (laminated veneer lumber) structures, controlling movement in the structure itself, PRESSS technology delivers protection as well as beam column joints with forced against serious earthquakes while rocking points which control joint movement especially in Canterbury, as minimizing seismic damage and the and damage. The energy dissipaters can be part of the post-earthquake associated costs of smaller tremors. easily replaced after an earthquake, is taking New Zealand by storm, providing economical repair alternatives. rebuild program says BBR Contech Southern Regional Manager, Peter Higgins. 1 Police station, Rotorua building’s nine LVL shear walls and 19 will soon be based in a brand new police horizontal LVL beams. That means: station – and not a moment too soon • installing 54 x 50mm diameter PT bar according to those working in the existing tendons vertically through the walls and premises. connecting them to screwpiles that The two-storey station is being constructed using PRESSS technology, with tensioning TEAM & TECHNOLOGY 1 Client – New Zealand Police Main contractor – Canam Construction Engineer – Spiire Technology – BBR VT CONA CME external BBR Network Member – BBR Contech (New Zealand) 2 Client – Birmingham Drive Properties Ltd Main contractor – City Care Limited Engineer – Opus International Consultants Technology – BBR VT CONA CME external, PT bar BBR Network Member – BBR Contech (New Zealand) 56 CONNÆCT | EDITION 8 BBR Contech’s role is to post-tension the Police officers serving in the Rotorua area terminate in the gravel layer • installing six multi-strand, 15.2mm cables installed in the concrete shear diameter strand tendons in each beam. walls, beams and columns to allow it to The tendons are greased and sheathed move in an earthquake without sustaining to protect against corrosion and the ends serious damage. are wrapped in corrosion protection tape For this project, the BBR Contech team is and capped to provide an additional installing 62 BBR VT CONA CME 12-strand, barrier against the elements. greased and sheathed tendons into the In another innovation, the building’s precast walls. strength will be constantly monitored – and The new station is due to open in March tendons easily removed and replaced if 2014, offering an environment eminently necessary. The project, and its impressive suited to modern-day policing while commitment to earthquake resistance, is reflecting the unique features of Rotorua, already earning accolades – it won a ‘highly particularly the prominence of Maori art commended’ award in the 2012 Timber and culture. Design Awards. ● PORTFOLIO SPECIAL APPLICATIONS DENISON ROAD GRADE SEPARATION, TORONTO, CANADA Ground anchoring ANCHORING IN TORONTO 1 2 3 4 5 6 Work is underway in the Denison 1 Road area of Toronto on a major grade separation project to improve railway services and A tieback drilling machine bored holes, minimum grout strength of 28MPa 38m long ground anchors which would had been achieved, the tendons were later be grouted and tensioned against stressed, proof tested and locked-in. the sheet piled wall. A typical stressing activity is shown accommodate a new airport rail link. Tim Pahapill of BBR Canada explains, through the photographs 5 After installing the anchors and a under artesian conditions, for the up to here with the team stressing the ground 2 For ease of fabrication, transportation anchors against the external bracket and to save time on site, tendons were mounted on the sheet piled retaining delivered in cut-to-length coils and an wall beneath the new railway bridge. below, how their work involves the uncoiling turntable was used to unwind installation of up to four layers of them during installation. 6 The first two rows of ground anchors are fully installed and stressed to their ground anchors along a sheet-piled 3 Once installed and the bored hole fully prescribed lock-in loads. The first row grouted, the strands were individually is finally capped and the second row is below the railway line. As can be secured in the anchor heads by placing being prepared for capping. ● seen, the ground conditions are wedges into the anchor head wedge extremely challenging. holes. retaining wall which forms a cutting 4 After installation, the ground anchors were filled with a special grout mixture as a corrosion inhibitor and to create the bonded length, while the free stressing lengths remained greased and sheathed for protection. TEAM & TECHNOLOGY Owner – Metrolinx Main contractor – Dufferin Construction Company Shoring & drilling contractor – Deep Foundations Contractors Inc. Technology – BBR CONA ground BBR Network Member – Canadian bbr Inc. (Canada) www.bbrnetwork.com 57 PORTFOLIO MRR EASTERN INTERCEPTOR SEWER, AUCKLAND, NEW ZEALAND Specialist refurbishment & treatment of damaged sewer GOING UNDERGROUND The term ‘Eastern Interceptor’ may sound like a fighter jet left over from the days of the Cold War, but for the BBR Contech team the expression has a distinctly different meaning explains their Project Manager, Oliver Smith. 1 58 CONNÆCT | EDITION 8 Completed in 1962, the Eastern Interceptor Watercare – the company providing water is a large-diameter, reinforced-concrete and wastewater services to the Auckland wastewater pipe that follows a 19km path region – maintains a rigorous monitoring, from Auckland’s Okahu Bay to the maintenance and, where necessary, repair Mangere Wastewater Treatment Plant. program. BBR Contech was most recently It is a vital part of the city’s wastewater involved in 2005, when we repaired several management system, carrying about sections in what was thought to be the first two-thirds of its wastewater and acting large-scale remedial concrete works to be as the main collection point for many carried out in a fully live, man-entry sewer large and small sewers. For this reason, in New Zealand. PORTFOLIO MRR “This has required us to take a scrupulous approach to planning and implementing the project, and to keeping the affected community well-informed along the way.” 2 Meticulous detail Work like this is never pleasant for the BBR Contech team, with a hazardous working environment in which everyone is required to follow stringent health and safety policies. These include wearing dry suits equipped with adequate supplies of fresh air – and maintaining a strict limit on the time spent in the underground pipe environment. In Mount Wellington, the team also has to have a constant focus on minimizing noise and other disruptions to the residents nearby. Spread over two stages and due for completion in early 2015, the project involves: 3 • preparing the surface using robotic high-pressure water blasting, which is very effective in removing the affected 1 Auckland’s Eastern Interceptor Sewer is a 19km long reinforced concrete pipe which required vital man-entry maintenance works. 2 Wearing of dry suits equipped with fresh air supplies and adhering to strict underground time limits form part of the health and safety regime on BBR Contech’s sewer maintenance projects. 3 Preparation of the sewer pipe surface is carried out using high pressure blasting, then a specialist spray is applied to the walls to protect against biogenic sulphide corrosion. TEAM & TECHNOLOGY Client – Watercare Services Engineer – AECOM Technology – MRR range BBR Network Member – BBR Contech (New Zealand) Latest contract We have recently been called upon again, concrete without disturbing raw sewage • applying 350t of specialized coating – this time to remove and replace damaged a technologically sophisticated calcium concrete in two other parts of this critical aluminate product that is sprayed on to element of Auckland’s infrastructure – provide highly effective, high-strength, one a 205m-long section at the wastewater corrosion-resistant protection against plant itself, and the other a 440m-long biogenic sulphide corrosion. section in Mount Wellington. The latter is While those working on the project will no posing some particularly complex doubt be relieved to see it completed, they challenges for the team, as it is located in can be very proud of their role in helping to a heavily populated residential area which ensure that Auckland’s wastewater system includes a primary school. This has continues to perform well into the future. required us to take a scrupulous approach For our part, the project has reflected the to planning and implementing the project, very best of expertise, experience and and to keeping the affected community collaboration – qualities that we at BBR well-informed along the way. Contech promote and value highly. ● www.bbrnetwork.com 59 PORTFOLIO MRR 1 2 BULACAN LINE 2 CEMENT SILO 9, NORZAGARAY, BULACAN PROVINCE, PHILIPPINES Design, retrofitting & post-tensioned construction STRENGTHENING FOR EUROCODE COMPLIANCE BBR Network Member, BBR Philippines Corporation has provided “A retrofitting system post-tensioning services at a plant belonging to one of the world’s largest was needed that would cement producers – the Swiss-based Holcim Group. Rey Singh outlines not require a shutdown the story behind the project. of the silo while the works The existing cement plant in Norzagaray, Technical aspects were being executed.” Bulacan Province was acquired by Holcim Time was now of the essence and pressure in 2004 to increase their local production was on to increase much-needed storage capacity. As they require their structures to capacity without disrupting the plant’s be compliant with both local and European commercial operations. A retrofitting construction codes, they tasked a European system was needed that would not require engineering consultancy firm to undertake a shutdown of the silo while the works were the necessary design reviews. being executed. Their study for Cement Silo 9, which was Silo 9 is a 41m high, 10,000MT cement built in 1995, showed that it needed to be storage silo with an inside diameter of structurally upgraded to conform with the 20m and wall thickness of 650mm. It also local codes, ACI provisions and European has an annex wall with a 10.524m curvature code requirements for silos considering the length jutting out on one side as this was dynamic forces acting during extraction in intended for the future construction of concrete silos with inverted cones. They Cement Silo 10 – Cement Silo 9’s twin silo. 1 External post-tensioning is being applied to the external wall of the cement silo for strengthening in line with Eurocode requirements. 2 Work at the cement plant was able to continue while work was in progress – a benefit of adopting an external post-tensioning solution. TEAM & TECHNOLOGY Owner – Holcim Philippines, Inc. Main contractor – BBR Philippines Corporation Technology – BBR CONA external BBR Network Member – BBR Philippines Corporation (Philippines) 60 CONNÆCT | EDITION 8 recommended that Cement Silo 9 be limited to a 40% storage capacity until it had been strengthened to conform to Eurocode standards. PORTFOLIO MRR MOUNT VICTORIA TUNNEL, WELLINGTON, NEW ZEALAND Strengthening with ground anchors ORCHESTRATING TUNNEL ACTIVITIES The journey between the City of Wellington and its airport, takes motorists through the Mt Victoria tunnel – where many take part in the symphony of tooting horns that’s long been customary practice as the vehicles pass through. With more than 620m to cover, there’s plenty of time to raise a tune! Recently, motorists have acquired a new audience – External post-tensioning works We proposed to upgrade the structural the team from BBR Contech which has been carrying out strengthening work on concrete walls at the tunnel’s entrance and exit portals. capacity of the existing Cement Silo 9 through external post-tensioning tendons. Opened in 1931, the tunnel was the first Therefore, New Zealand Transport Agency The use of external post-tensioning tendons road tunnel in New Zealand to be have awarded BBR Contech the contract has the flexibility to avoid obstructions, mechanically ventilated. The technology for strengthening the tunnel’s concrete like the existing structures and services remains an important feature today, as walls at the entry and exit portals. attached to Silo 9, and allows the contractor the tunnel is now a thoroughfare for about The project will anchor the walls in place to work on the outside surface of the silo 45,000 vehicles a day, as well as hundreds to reduce the risk of damage or collapse wall without interfering with the cement of pedestrians and cyclists. in an earthquake. Given the weak ground plant’s operations. The tunnel is a vital piece of infrastructure conditions at the site, this is a complex The post-tensioning tendons are BBR on State Highway 1 and keeping it in top task involving building a concrete beam to CONA external tendons, each with four condition is of prime importance. link the anchors through the walls, adding 0.5” unbonded strands. The grease and steel as extra reinforcement, installing the polyethylene sheathing of the unbonded anchors and cementing them in place with strands serve as corrosion barriers as they high-pressure grouting to ensure a firm, are exposed to the elements in the sectors long-lasting bond. between the three reinforced concrete The work has been arranged to have buttresses built to house the tendon minimal impact on those using the tunnel anchorages. A total of 89 BBR CONA and, thanks to some careful screening, the external tendons were looped around the construction workers are no distraction cement silo. for drivers. Noise and traffic management Besides overcoming obstructions, limited plans are also helping to reduce the working spaces and access problems due to effects for those in the neighboring the height of the silo, another major obstacle community, while a communication was the removal and demolition of the strategy ensures that those directly annex wall as this obstructed the installation affected are kept up-to-date on progress. ● of the post-tensioning tendons in its sector. 1 Diamond saw cutting machines, set up on 1 The tunnel walls are being strengthened at the entry and exit portals. 2 The BBR team is screened from the road beneath while they grout the new anchors installed for the tunnel strengthening program. heavy duty modular ring lock scaffolding, were used to cut the annex wall segment-bysegment. The segments were individually brought to ground level by a mobile, telescopic crane and hauled away from the construction site. Cement Silo 9 has now been loaded to 100% filling capacity – and its owners can TEAM & TECHNOLOGY be confident that it meets all required Client – New Zealand Transport Agency Engineer – Opus International Consultants Technology – BBR CONA ground BBR Network Member – BBR Contech (New Zealand) construction codes. Mabuhay!* ● * For our non-Filipino readers, this is a frequently used local greeting meaning 'live' – as in 'live your life' or 'live long'. 2 www.bbrnetwork.com 61 PORTFOLIO MRR 1 2 NORTH RJECINA MOTORWAY BRIDGE, CROATIA Rehabilitation with external post-tensioning FIRST REHAB IN 30 YEARS The old northern Rjecina bridge was built between 1980 and 1984 and opened to traffic in 1988 when the whole section of motorway around the city of Rijeka had been completed. Since it opened, no rehabilitation work had been carried out on the bridge. 1 External post-tensioning tendons were replaced as part of the bridge abutment rehabilitation project. 2 View of one of the carriageways as work had almost been completed – this was the first rehabilitation project carried out since the bridge opened in 1988. TEAM & TECHNOLOGY Client – HAC, Zagreb Main contractor – Viadukt d.d., Zagreb Designer – Institit IGH d.d., Zagreb Technology – BBRV wire BBR Network Member – BBR Adria d.o.o. (Croatia) 62 CONNÆCT | EDITION 8 The bridge is positioned around 100m above PT tendon replacement the river valley. The bridge main span is As a part of the abutment rehabilitation, 98.4m with lateral 45m spans supported on the external tendons which take over lifting sloping piers and an additional independent force were replaced. In accordance with the 17.5m span on the west side which was design specifications, 32 x 7mm diameter required for tricky geological conditions. BBRV Wire post-tensioning tendons were The foundation axis span is 131.65m. used. The upper part of the tendons were anchored with movable anchor heads, while Rehabilitation work the lower parts were anchored with passive Rehabilitation work consisted of asphalt non-movable anchor heads. and superstructure hydro-isolation Each strand was fixed into the anchor head replacement, abutment rehabilitation, using the cold-formed button heading abutment expansion joint replacement process which ensures maximum efficiency. and rehabilitation of other installations. There were four 4.5m long tendons on each abutment. After replacing the wires and anchor heads, each tendon was stressed to a force of 200kN. Corrosion protection of the tendons was completed using new grease-filled HDPE pipes and protection caps. ● TECHNOLOGY 64 RESEARCH & DEVELOPMENT improving all round performance – stay cable dampers to counter vibration, plus cost-effective grouting accessories 68 TECHNICAL UPDATE securing of AASHTO approval and current status of the BBR VT CONA CMX range 70 TECHNIQUES Fabian Persch of Stahlton, the BBR Network Member for Switzerland, reveals the benefits of and method for prefabricating PT tendons 72 INSIGHT technology and expertise from the BBR Network can breathe new life into weakened or damaged infrastructure and buildings – some of the techniques are showcased here www.bbrnetwork.com 63 TECHNOLOGY RESEARCH & DEVELOPMENT Superior countermeasure for stay cable vibration SOLUTIONS FOR COUNTERING CABLE VIBRATIONS Cable-stayed bridges have been built in greatly increasing Even newly constructed cable-stayed numbers since 1950. Despite their wide use, there are bridges have experienced quite severe still several areas of great concern, especially the effects vibrations – such as, for example, the Fred Hartman Bridge in Houston, Texas and elimination of cable vibration phenomena. Within the which has a main span of 381m and 192 BBR technology range, we offer a superior supplemental stay cables. Excessive cable vibrations passive damping device – the BBR Square Damper – to have also been observed on numerous combat cable vibrations. other bridge structures. Several cable vibration mechanisms have been identified – such as vortex shedding, cable galloping, parametric excitation (deck / pylon and cable interaction) and wind-rain induced vibrations – which create concern generally. 1 64 CONNÆCT | EDITION 8 TECHNOLOGY Cable galloping were of the order of 0.55m when subjected Galloping was firstly detected in power to the effects of a 14 m/s wind. lines which – under certain weather Today, it is also known that the action of conditions – were observed to be vibrating the rain leads to the formation of two water and exhibiting high amplitudes at rivulets, one on the upper cable side relatively low frequencies. Curiously, this (unstable rivulet) and another on the down phenomenon has never been reported in cable side (stable rivulet). Although the countries with a warm climate, but it is presence of the rivulets slightly changes very common during the winter months the outer cable shape, some experiments in northern states of USA and Canada. performed by Yamaguchi in the 1990s Oscillations are transversal to the wind showed that the vibration was very unlikely direction, occurring at frequencies close to be caused by a ‘galloping-like’ to some natural frequency and generally – mechanism – but rather the oscillatory for all wind speeds – above a critical value. movement of the top rivulet, caused by the In general, to ensure stability of the stay combination of gravity and aerodynamic cable under galloping-like mechanisms, the forces. Past experience and intensive following expression must remain negative: experiments in the field demonstrated that rain-wind instability occurs under the following conditions: • wind flows in the same direction as the cables decline from the pylon to the deck In which m, fk and D are, respectively, the linear mass, natural frequency and outer diameter of the cable. On the other side, • combination of light rain with relatively • outer surface of the stay pipe is smooth U corresponds to wind speed and the term and not equipped with any in brackets to the Den Hartog Coefficient. countermeasure, such as helical rib or A detailed analysis of the above expression Analysis from earlier stay cable bridges subjected to galloping when the Den Hartog shows that rain-wind induced vibration Coefficient becomes negative, which may may be overcome if the Scruton number is happen under the following conditions: high enough: • outer shape of the stay pipe is not circular • Sc > 10, if stay pipe has a smooth outer which noticeably modifies outer shape to non-circular Upper rivulet (unstable) dimples. will show that stay cables will only be • accumulation of ice on the stay pipe Rain moderate wind speeds of around 8-15 m/s Lower rivulet (stable) surface • Sc > 5, if stay pipe is equipped with a helical rib or similar countermeasure. ➤ Illustration showing a cross section of an HDPE stay pipe • wind flows on a plane non-orthogonal to the stay cable’s axis. Wind-rain induced vibrations The phenomenon of rain-wind induced HDPE stay pipe vibration is brought about by the simultaneous action of a low / moderate wind speed, together with the action of rain. Upper rivulet (after) Upper rivulet (before)) Nowadays, it is considered that rain-wind induced oscillations cause about 95% of the reported vibration problems in cablestayed bridges. In spite of this, it was not 1) 2) until the construction of the Meiko-Nishi Bridge in the 1980s that this phenomenon in cable-stayed bridges was reported for the first time. During construction, it was observed that the cables of the bridge – initially stable with respect to the action of the wind – started to become unstable in Illustration showing the movement of rivulet due to gravity (1) Illustration showing the movement of rivulet due to wind flow (2) rainy conditions. Oscillations observed www.bbrnetwork.com 65 TECHNOLOGY Dampers for Rio Corgo Due to its simple design, high efficiency, Completed in 2013 by BBR Network easy adjustability and low maintenance Member BBR PTE, Portugal’s Rio Corgo requirements, the BBR Square Damper Viaduct features 88 HiAM CONA stay is superior compared to other damping cables – ranging in size from 42 to 69 products available on the international strands, with the longest cable measuring market. The device can be fine-tuned 159m. Following extensive cable vibration and adjusted during its entire service life analysis, performed by the BBR HQ to best suit a particular cable configuration Technology and R&D team based in and specific susceptibilities to particular Switzerland, it was determined that 16 vibrations. All components of the damper of the 88 stay cables would require can be inspected individually and are additional supplemental damping to replaceable if required – for example, if eliminate cable vibrations. there has been external damage or The BBR Square Damper is a superior vandalism. ● supplemental passive damping device which is based on friction. The device can be used as an internal damper, where it is installed inside the steel guide pipe or alternatively as an external damper, attached to the cable free length using a damper housing and external brace. The main advantages of the BBR Square Damper are: • the damper is not activated at low and non-critical cable vibration amplitudes, avoiding constant working of the damper and minimizing maintenance requirements • the damping efficiency is independent of the acceleration and mode of cable vibration • the damper has been proven, by testing, to achieve the Maximum Passive Supplemental Damping considered for a ‘perfect damper’ and thus the safety factors relating to Required Supplemental Damping can be reduced • free longitudinal movement of the stay cable at the damper location is provided, allowing for temperature elongation and force variations of the stay cable without constraints • the damping characteristics can be adjusted at any time by changing the ‘clamping’ force • high endurance and constant performance • easy inspection and low maintenance. 66 CONNÆCT | EDITION 8 2 1 For Portugal’s Rio Corgo Bridge – completed by Spanish BBR Network Member, BBR PTE – the BBR HQ Technology and R&D team performed extensive cable vibration analysis and determined that 16 of the 88 stay cables would require damping. 2 The BBR Square Damper is a superior supplemental passive damping device which is based on friction and can be installed as an internal or external damper. TECHNOLOGY RESEARCH & DEVELOPMENT New generation of grouting accessories GREEN AND COST-EFFECTIVE Grouting plays a key role in the In the industry as a whole, there have This has enabled us to ensure that material corrosion protection of post- been concerns associated with the grouting usage was fully optimized – so that we use process for post-tensioning tendons and just what is needed and no more. these are associated with potential impacts The range of accessories also includes BBR Network has developed on both the construction program and a newer series of BBR grouting caps, excellent techniques for environment. Therefore, we have developed made of organic polymer. They are able completing this important task. a new range of grouting accessories to withstand grouting pressures of up specifically for the BBR VT CONA CMI and to 15 bars and are fully compatible with CONA CMM post-tensioning systems which anchorages and couplers. The new caps accessories this process has improve efficiency and sustainability. showed significant cost reduction and become even more cost-effective Among the tools our team used during the an extraordinary reduction of the CO2 and environmentally friendly. development process of our new range was emissions to the atmosphere. ● tensioning tendons and the Now, with our new range of grouting non-linear finite element analysis. 1 1 The new grouting caps reduce costs and environmental impact. 2 Finite element analysis of the new grouting caps. 2 www.bbrnetwork.com 67 TECHNOLOGY TECHNICAL UPDATE New approvals & renewals AASHTO APPROVAL FOR CONA CMI 1 While ETAG 013 has become BBR HQ has recently carried out additional Finite element modeling state of the art in Europe and initial type testing on the CONA CMI BT While experimental testing gives global system according to AASHTO LRFD information about the performance of the Bridge Construction Specifications, CONA CMI BT anchorage system – for 2nd Edition, 2004. example, wedge slippage, deflection, etc – other regions worldwide, some regions – such as the Middle East – specify post-tensioning projects according to AASHTO. no internal information, such as stress / System testing strain in the anchorage core at service and Among other items, the system testing ultimate state, can be obtained. In addition, included: experimental tests are recognized as being • static load tests including the deviation time-consuming and expensive. However, of the strands to represent the transition by using the latest finite element modeling zone at the exits of the anchorage and technology, our numerical analyses have at the coupler unit on PT tendons with complemented laboratory testing and up to 6106 strands confirmed geometrical, material and • load transfer tests for highly aggressive surface anchorage properties. environments and concrete strength The finite element model takes into account range from 19/23MPa to 35/43MPa on all the mechanical behavior complexities PT anchorages with up to 6106 strands. which occur on CONA CMI anchorages The recent AASHTO approval tests when subjected to heavy prestressing confirmed the benefits of the loads, such as the wedge-tendon gripping CONA CMI BT system, with static load interaction, the friction at the wedge-anchor efficiency greater than 96% AUTS and head interfaces, as well as at the anchor reduced crack width at the local zone for head-anchor plate interface, local plasticity its application in those special aggressive and large displacements at the wedge- environments described in AASHTO LRFD anchor head interfaces. Bridge Construction Specifications. Anchor head deflection and radial deformation data collected from the testing formed the basis for comparison with the numerical results. The agreement observed, between the experimental and numerical results, clearly showed the benefits of finite element modeling for assessing both the global and local behavior of the anchorage system. 1 Finite element modeling (FEM) also proved to be beneficial for assessing both the global and local behavior of the CONA CMI BT anchorage system. 2 Laboratory testing of the CONA CMI BT system confirmed the benefits of the CONA CMI BT system for application in special aggressive environments as described in AASHTO LRFD Bridge Construction Specifications. The CONA CMI BT system has now been applied to the two 160m long flyovers at the Barka Interchange, part of the new Batinah Expressway project near Muscat, Oman. More information about the project is on page 32. ● 2 68 CONNÆCT | EDITION 8 TECHNOLOGY BBR VT Plastic Duct The European Technical Approval for the BBR VT CONA CMI internal bonded posttensioning system with 04 to 31 Strands – ETA-06/0147, has been recently renewed up to March 2018. This approval now includes the BBR VT Plastic Duct which has the following key features: • BBR VT Plastic Ducts are circular with inner diameters from 50mm to 130mm and they are made of polypropylene with toroidal corrugations TECHNICAL UPDATE • BBR VT Plastic Ducts were tested in accordance to fib bulletin 7, for a working New approvals & renewals temperature range of –20°C to +50°C • Enhanced corrosion protection against aggressive chloride environment STATUS OF CONA CMX APPROVALS • Lower and more reliable friction coefficient, beneficial for longer tendons and circular tank construction • Reduced risk of fretting fatigue of tendons Recent renewal of ETAs The following European Technical Approvals have been renewed for the next five years: • BBR VT CONA CMI SP – Internal bonded post-tensioning system with 01 to 61 strands – European Technical Approval ETA-09/0287, renewed up to June 2018 • BBR VT CONA CMI BT – Internal bonded post-tensioning system with 02 to 61 strands – European Technical Approval Our BBR VT CONA CMX range of completely new post-tensioning technology was launched in 2006 and, since then, European Technical ETA-09/0286, renewed up to June 2018 • BBR VT CONA CME – External posttensioning system with 04 to 31 strands – Approvals (ETAs) have been progressively sought, awarded and renewed European Technical Approval ETA-07/0168, for different systems within the CONA CMX range. This is a significant renewed up to December 2017. investment – in terms of both time and costs – however, it has ensured that the BBR Network has the latest CE-marked, high quality technology to offer its customers. National CONA CMX approval updates In Australia, CONA CMI BT has been approved for sizes up to 6106 by the Roads and Maritime Service (RMS) and The CONA CMX range was developed BBR VT CONA CMM Single has been used by local BBR Network in response to market needs and offers The new BBR VT CONA CMM Single Member, Structural Systems on the considerable budget, program and European Technical Approval ETA-12/0282 Hunter Expressway project (see page 21). environmental benefits – such as less has been issued and is valid until June 2018. CONA CMI has also been approved in space needed in the anchorage zone, The key features and benefits of the new Switzerland, with Stahlton as the local stressing at lower concrete strengths internal system with single strand are: PT Specialist. This approval is based on and reduced requirement for • Applicable for bonded applications the CONA CMI European Technical reinforcement in the anchorage zone. with corrugated steel or plastic duct Approval ETA-06/0147 and includes the Securing and maintaining ETAs for our • Applicable for unbonded tendons with full range of BBR VT Plastic Ducts (both CONA CMX systems is important, as grease / wax as filling material or with round and flat) and specifications relating they are the everyday technologies used monostrands to prefabricated tendons. by BBR Network Members for delivering the highest quality services to their customers worldwide. • Exchangeable and restressable for unbonded tendons • Full stressing at low minimum concrete strength (20/24MPa). Meanwhile, in Germany, the Deutsches Institut für Bautechnik (DIBt) has extended approval of our external band systems for general use for another term. ● A complete series of the latest approvals – along with CAD drawings and technical brochures – is now available for download from our website – www.bbrnetwork.com/downloads/approvals.html. www.bbrnetwork.com 69 TECHNOLOGY 1 TECHNIQUES 2 Prefabrication of post-tensioning tendons REELING WITH SUCCESS While it is not a new idea, the Our experience of prefabricating post- off-site prefabrication of post- tensioning tendons stretches back to the tensioning tendons can offer great early days of the shared BBR and Stahlton history. Unlike strand tendons, wire cables benefits for certain construction need to be cut to an exact length, which projects. With its history of being can be best carried out in a workshop. a wire tendon supplier, the BBR So it has become customary for us to Network Member for Switzerland, fabricate our tendons off-site. We have found that prefabrication offers Stahlton AG developed the a number of advantages for both the infrastructure and capability BBR PT Specialist and the client: necessary to prefabricate tendons • greater program / time flexibility for many years ago. Today, they still both fabrication and installation on site • clean and efficient fabrication prefabricate the bulk of tendons • speedy installation on site for use on their projects. Fabian • smooth, problem-free strand-pushing Persch, Product Manager PT, of Stahlton outlines the background, advantages and the process. operation • potentially smaller ducting diameter and hence greater effective depth achievable Generally, the prefabricated tendons are coiled onto reels, shorter tendons might, however, be delivered loose or on trusses. While off-site tendon prefabrication is our preferred option, this is not always possible. A number of factors – such as length and weight of tendons, duct diameter, as well as the available space and clearance on site – may dictate that on-site cable fabrication is necessary. 70 CONNÆCT | EDITION 8 TECHNOLOGY 3 5 1 Strand installation in the workshop The fixed strand pushing arrangement allows for speedy and efficient strand installation. 4 2 Coiling onto reel Usually, tendons are coiled onto the reels with the help of a fork-lift truck. The reels must be of an appropriate diameter, to avoid cracking or kinking of the sheathing. 3 Transportation to site The reels of tendons are loaded onto a truck, along with the uncoiling frame, for delivery to the construction site. 4 Storage Tendons must be stored in sheltered conditions prior to installation to protect them from water ingress. 5 Uncoiling Here, the tendon reel is being secured to the uncoiling frame and being lifted by a crane. 6 Tendon placement Placing of a tendon into position as it is being uncoiled. The uncoiling frame, with its braking device, must be operated by experienced staff only. The handling requires certain procedures to avoid uncontrolled 6 overturning or uncoiling. ● www.bbrnetwork.com 71 TECHNOLOGY INSIGHT MRR technology and techniques used by BBR Network Members REVIVING THE BUILT ENVIRONMENT It is well-recognized that BBR technology promotes leaner new construction, but what about maintenance, retrofit and restoration or renovation (MRR) projects? With the three ‘Rs’ – Reduce, Reuse, Recycle – playing an ever greater role in a cost-conscious and environmentally aware world, specialist techniques and technology used by BBR Network Members are also delivering leading edge green and economic solutions. The need for the BBR Network’s range of MRR techniques arises from a number of factors. Often, it is a case of repairing damage whether through prolonged or heavier-than-planned usage or insufficiencies in the original design of a building – although constructed to the highest standards of the day, several decades ago. However, sometimes such techniques are used to assist the repurposing of a building or structure or to ensure its continued life through a change in environmental conditions. Four key techniques feature again-andagain in our project portfolio – fiber reinforced polymer (FRP) application, bearing replacement, external posttensioning and Impressed Current Cathodic Protection (ICCP). These are sometimes used together and sometimes with other specialist procedures, such as heavy lifting. 1 72 CONNÆCT | EDITION 8 TECHNOLOGY 3 4 2 Bearing replacement Typically, bearings are found in bridges and form a cushion between the bridge piers and the bridge deck. Replacing bridge Fiber reinforced polymer bearings, when they have reached the end FRP has the advantage of being lightweight, of their design life, requires the development yet strong. Additional shear capacity, of precise procedures and the application flexural strength and ductility can be applied of heavy lifting techniques – jacking – to to beams, columns, slabs and walls by the raise the bridge deck to allow removal and application of fiber reinforced polymer insertion of bearings. materials – with minimal disturbance to The type of challenges met and occupancy and rentable asset space. professionally executed by BBR Network It is applied as a ‘wrap’ or in strips to Members is well demonstrated by a project strengthen weak or damaged concrete. carried out on the Morshead Overpass in Following the New Zealand earthquakes in Melbourne, Australia. Here, there were two 2011, many concrete columns at The Palms types of bearing – elastomeric and Shopping Center in Christchurch needed mechanical – and replacement procedures repair. The local BBR Network Member, for each type of bearing were specifically BBR Contech, carried out repairs to the designed. Working space limitations and column extremities, including forming and further structural issues led to the creation pouring with fine aggregate concrete and of prefabricated steel angle brackets to structural mortar before confining the support the jacks for replacement of the columns with carbon fiber wrap. elastomeric bearings. The replacement In another project, this time executed by method for the mechanical bearings was BBR Polska, FRP strips were applied for much simpler in terms of jacking, as there strengthening to the underside of floor was enough space on the crosshead to seat slabs in an office building in Warsaw. the jack behind the existing bearing. ➤ www.bbrnetwork.com 73 TECHNOLOGY External PT strengthening Also in Poland, girders supporting the The use of externally placed post-tensioning concrete slab of a staff car park in Siedlce tendons to increase load carrying capacity were discovered to be deflecting. BBR is a well-established practice. In principle, Polska was contracted to come up with induced tensile stresses in concrete due to a strengthening solution and to deliver, additional loading can be negated by install, stress and grout the tendons. applying compressive stresses induced by Stressing force was calculated for each post-tensioning. The technique is used girder individually and then four strand mainly in bridges, where additional load BBR VT CONA CME external tendons carrying capacity is often required. were installed under each steel girder. For example, BBR VT CONA CMB external band tendons were applied to three large bridges on Germany’s A45 federal 5 motorway by BBR Network Member KBVT. The bridges were built in the 1960s and 70s and damage made the repairs a matter of urgency. These emergency repairs have ensured the continued service of the bridges for a further ten years – by which time they will have been replaced by new ones. External post-tensioning can be applied to buildings to increase structural strength. “External tendons strengthen and increase the load capacity of a structure and their effect comes into play immediately after they are stressed,” says Bartosz Lukijaniuk of BBR Polska, “hence the technology often being called ‘active’ strengthening.” He and his team designed and installed the external post-tensioning system for the strengthening of three leaking concrete tanks at Warsaw’s ‘South’ sewage plant. The BBR VT CONA CME external system was used, anchored in steel blocks fixed to the corners of the tanks. 6 7 74 CONNÆCT | EDITION 8 TECHNOLOGY “External tendons strengthen and increase the load capacity of a structure and their effect comes into play immediately after they are stressed,” 8 Impressed Current Cathodic Protection control corrosion on a section of the Impressed Current Cathodic Protection Central Expressway under the Singapore (ICCP) systems are installed to inhibit the River. There had been significant problems corrosion of steel reinforcing bars in with water seepage and chunks of concrete concrete structures – particularly if the had fallen from the tunnel ceiling. Early latter are in aggressive marine data collected has indicated that the system environments. The systems operate by will offer considerable savings in long-term passing a low voltage current through repair costs. strategically placed anodes inserted into The expertise of the BBR Network in the the concrete which forces the reinforcing area of maintenance, repair and retrofit or steel into a cathodic state and protects it renovation is founded on a long experience from corrosion. The ICCP control system and understanding of structures, as well monitors and records performance. as the professional, effective and safe An ICCP system was installed by BBR application of the latest technologies. Contech on the Kaikorai estuary bridge in As building and asset owners and Dunedin, New Zealand. The system can be managers seek to manage their risks – monitored and adjusted as necessary. Strict whether they are building new structures operational specifications were applied or repairing, protecting or strengthening during the repair and installation work to existing ones – the BBR Network is ready protect the estuary’s wetlands ecosystem. with robust, well thought-out solutions to Meanwhile, in Singapore, BBR Construction help them ensure structural resilience for Systems installed an ICCP system to the long term. ● 1 The roof structure of the Olivia Sports Hall, Gdansk – consisting of ten 80m long 3D steel trusses – was strengthened externally with 18 BBR VT CONA CME tendons by BBR Polska. 2 At The Palms Shopping Center, Christchurch, New Zealand, many concrete columns were repaired by BBR Contech using fiber reinforced polymer wrap after the 2011 earthquakes. 3 The elastomeric and mechanical bearings on Morshead Overpass, Melbourne, Australia were replaced using innovative techniques devised by local BBR Network Member, Structural Systems. 4 Fiber reinforced polymer strips were applied to the underside of floor slabs within the an office building Warsaw by BBR Polska. 5 BBR VT CONA CMB external band tendons were applied to strengthen three large bridges on Germany’s A45 federal motorway by BBR Network Member KB Vorspann-Technik. 6 BBR Polska designed and installed the external post-tensioning system – using the BBR VT CONA CME external system – for the strengthening of three leaking concrete tanks at Warsaw’s ‘South’ sewage plant. 7 Deflecting girders supporting the concrete slab of a staff car park in Siedlce were strengthened by BBR Polska using four strand BBR VT CONA CME external tendons installed under each steel girder. 8 An ICCP system is monitored and adjusted by BBR Contech on the Kaikorai estuary bridge installation in Dunedin, New Zealand. www.bbrnetwork.com 75 THINKING ALOUD Paul Wymer, Managing Director of BBR Contech, the New Zealand-based BBR Network Member shares some thoughts about how to adapt successfully to changed circumstances EMBRACING NEW BEGINNINGS Over the past few years in New Zealand, we’ve all had to act and adapt to changed circumstances that were caused by factors outside of our control. After the Canterbury earthquakes, we deployed our people – according to their skills, experience and expertise – to help in the recovery. Life here will never be quite the same again – the ‘old normal’ has gone forever and we are working together to establish a ‘new normal’. In a sense, this is a new beginning for us and it has made me think about the wider issue of the global economy and how a similar approach may be needed. 76 CONNÆCT | EDITION 8 After one of the longest and deepest brutal facts about what may lay ahead recessions in living memory, we must and be prepared to change our habits. acknowledge that the world economy is, This takes courage and conviction in this at best, volatile and uncertain – and that it ‘new normal’ environment where the may never return to what we previously outcomes can be uncertain. considered to be ‘normal’. Yet, as we look We need to listen carefully to new people around us, there are indeed businesses and new ways of doing things – and then which are prospering – even new businesses apply all of our experience and wisdom to starting – despite the vagaries of the discovering how we can integrate these economic climate. This is happening insights to move forward successfully. because we’re creating a new order of things If we suppress these new ideas, we risk – realigning ourselves and our aspirations to standing still – and even worse, we will fail compete in this challenging environment. to encourage and exploit the maximum We have begun a new phase in our journey. from our new emerging talent. It is one that must bring new people The 2012 New Zealander of the Year, together, foster different ways of thinking Sir Ray Avery said “Live like you are going and introduce new technologies into the to die tomorrow and learn like you are market to enable us to contend with our new going to live forever.” We can gain some circumstances. While our market strategies inspiration from this as we diligently might need a little polishing, the core values pursue new ideas – not always without risk which underpin everything we do must – and at the same time nurture a strong remain the same – dedication and learning culture. These things certainly commitment to innovation, collaboration, help to expand our horizons, reset our quality and service excellence. personal navigation devices along the way As we navigate down this new path, we and make us ready and able to embrace must all expand our thinking, face some new beginnings. ● BBR DIRECTORY HEADQUARTERS BBR VT International Ltd Bahnstrasse 23 8603 Schwerzenbach-Zurich Switzerland Tel +41 44 806 80 60 Fax +41 44 806 80 50 www.bbrnetwork.com info@bbrnetwork.com EUROPE AUSTRIA KB Vorspann-Technik GmbH Schillerstrasse 25 5020 Salzburg Tel +43 662 456516 Fax +43 662 456516-11 www.kb-vt.com office@kb-vt.com BELGIUM see Netherlands BOSNIA & HERZEGOVINA see Croatia BULGARIA see Spain CROATIA BBR Adria d.o.o. Kalinovica 3, 10000 Zagreb Tel +385 1 3839 220 Fax +385 1 3839 243 www.bbr-adria.com bbr-adria@bbr-adria.com DENMARK see Norway ESTONIA see Austria FINLAND see Norway FRANCE ETIC S.A.S. 3 rue de Marly 78 000 Versailles Tel +33 1 39 50 11 20 Fax +33 1 39 50 11 03 www.etic-sas.fr contact@etic-sas.fr GERMANY KB Vorspann-Technik GmbH Furstenrieder Strasse 275 81377 Munchen Tel +49 89 72 44 969-0 Fax +49 89 72 44 969-12 www.kb-vt.com office@kb-vt.com LATVIA see Austria RUSSIA see Germany LITHUANIA see Austria SERBIA see Croatia MONTENEGRO see Croatia SLOVENIA see Croatia NETHERLANDS Spanstaal – Ballast Nedam Infra Specialiteiten B.V. Nijverheidstraat 12, 4143 HM Leerdam Post Address: PO Box 236, 4140 AE Leerdam Tel +31 345 63 92 00 Fax +31 345 61 91 07 www.spanstaal.nl info@spanstaal.nl SPAIN BBR Pretensados y Técnicas Especiales, S.L. Antigua Carretera N-III, Km. 31, 150 28500 Arganda del Rey, Madrid Tel +34 91 876 09 00 Fax +34 91 876 09 01 www.bbrpte.com bbrpte@bbrpte.com NORWAY KB Spennteknikk AS Siva Industrial Estate, N. Strandsveg 19-21 Postboks 1213, 2206 Kongsvinger Tel +47 62 81 00 30 Fax +47 62 81 00 55 www.spennteknikk.no spennteknikk@spennteknikk.no POLAND BBR Polska Sp. z o.o. (Head Office) ul. Annopol 14, 03-236 Warszawa Tel +48 22 811 50 53 Fax +48 22 676 92 31 www.bbr.pl bbrpolska@bbr.pl BBR Polska Sp. z o.o. ul. Tarnogorska 214a, 44-105 Gliwice Tel +48 32 331 47 98 Fax +48 32 330 24 11 www.bbr.pl bbrpolska.gliwice@bbr.pl IRELAND see United Kingdom PORTUGAL see Spain KOSOVO see Croatia ROMANIA see Spain SWEDEN Spännteknik AB Sjöängsvägen 7, 192 72 Sollentuna Tel +46 8 510 678 10 Fax +46 8 510 678 19 www.spannteknik.se info@spannteknik.se SWITZERLAND Stahlton AG Hauptstrasse 131 5070 Frick Tel +41 44 938 99 00 Fax +41 44 422 11 16 www.stahlton.ch info@stahlton.ch UKRAINE see Poland UNITED KINGDOM Structural Systems (UK) Ltd 12 Collett Way Great Western Industrial Estate Southall, Middlesex, UB2 4SE Tel +44 20 8843 6500 Fax +44 20 8843 6509 www.structuralsystemsuk.com info@structuralsystemsuk.com www.bbrnetwork.com 77 BBR DIRECTORY AFRICA SOUTH AFRICA Structural Systems (Africa) Group Five House 9 Country Estate Drive Waterfall Business Estate Jukskei View Johannesburg 2090 Tel +27 10 060 1555 Fax +27 86 616 7482 www.structuralsystemsafrica.com info@sslafrica.com MIDDLE EAST BAHRAIN see United Arab Emirates SYRIA see Jordan JORDAN Marwan Alkurdi & Partners Co. Ltd PO Box 506, Amman 11821 Tel +962 6 581 9489 Fax +962 6 581 9488 www.mkurdi.com ali@mkurdi.com UNITED ARAB EMIRATES NASA Structural Systems LLC (Head Office) Office M 03, Bu Shaqar Building Garhoud PO Box 28987 Dubai Tel +971 4 2522 501 Fax +971 4 2522 502 www.bbrstructuralsystems.com bbr@bbrstructuralsystems.com KUWAIT see Jordan OMAN Structural Systems Limited (Oman Branch) Office A-11, Al Souroh Building Al Ghala Industrial PO Box 1946, PC-130 Muscat, Sultanate of Oman Tel +968 2459 5279 Fax +968 2459 5252 www.bbrstructuralsystems.com bbr@bbrstructuralsystems.com QATAR see United Arab Emirates AMERICAS EASTERN CANADA Canadian bbr Inc. 3450 Midland Ave. Scarborough Ontario M1V 4V4 Tel +1 416 291 1618 Fax +1 416 291 9960 mducommun@bbrcanada.com 78 CONNÆCT | EDITION 8 KINGDOM OF SAUDI ARABIA Huta-Hegerfeld Saudia Ltd BBR Prestressing Division Prince Sultan St. Lotus Building PO Box 1830, Jeddah 21441 Tel +966 12 662 3205 Fax +966 12 683 1838 www.hutahegerfeld.com.sa bbr@huta.com.sa Structural Systems Middle East LLC Office 38, Sheikh Abdullah Bin Zayed Al Nahyan Industrial Area Musaffah-2 P O Box 126740 Abu Dhabi Tel +971 2 5554 347 Fax +971 2 5554 348 www.bbrstructuralsystems.com bbr@bbrstructuralsystems.com Emirates & Australia Const. Systems LLC Office 112 Hatem Kamal Farah Building Beirut Street PO Box 62174 Sharjah Tel +971 6 5437 490 Fax +971 6 5437 491 www.bbrstructuralsystems.com bbr@bbrstructuralsystems.com BBR DIRECTORY ASIA PACIFIC MALAYSIA BBR Construction Systems (M) Sdn Bhd No. 17, Jalan PJS 11/2 Bandar Sunway 46150 Subang Jaya Selangor Darul Ehsan Tel +60 3 5636 3270 Fax +60 3 5636 3285 www.bbr.com.my enquiry@bbr.com.my PHILIPPINES BBR Philippines Corporation Suite 502, 7 East Capitol Building No.7 East Capitol Drive Barangay Kapitolyo Pasig City, Metro Manila 1603 Tel +632 638 7261 Fax +632 638 7260 jcf.admin@bbr.com.ph SINGAPORE BBR Construction Systems Pte Ltd BBR Building 50 Changi South Street I Singapore 486126 Republic of Singapore Tel +65 6546 2280 Fax +65 6546 2268 www.bbr.com.sg enquiry@bbr.com.sg THAILAND see Singapore VIETNAM see Singapore AUSTRALIA Structural Systems (Northern) Pty Ltd 20 Hilly Street, Mortlake New South Wales 2137 Tel +61 2 8767 6200 Fax +61 2 8767 6299 www.structuralsystems.com.au info@nsw.structural.com.au Structural Systems (Northern) Pty Ltd Unit 1/12 Commerce Circuit Yatala, Queensland 4207 Tel +61 7 3442 3500 Fax +61 7 3442 3555 www.structuralsystems.com.au info@qld.structural.com.au Structural Systems (Southern) Pty Ltd PO Box 1303 112 Munro Street, South Melbourne Victoria 3205 Tel +61 3 9296 8100 Fax +61 3 9646 7133 www.structuralsystems.com.au info@structural.com.au Structural Systems (Southern) Pty Ltd 39 Howards Road Beverley SA 5009 Tel +61 8 8268 0400 Fax +61 8 8268 0401 www.structuralsystems.com.au info@structural.com.au Structural Systems (Western) Pty Ltd 3 Craig St, Burswood Western Australia 6100 Tel +61 8 9267 5400 Fax +61 8 9267 5499 www.structuralsystems.com.au info@wa.structural.com.au FIJI see New Zealand NEW ZEALAND BBR Contech 6 Neil Park Drive, East Tamaki PO Box 51-391 Pakuranga, Auckland 2140 Tel +64 9 274 9259 Fax +64 9 274 5258 www.contech.co.nz akl@contech.co.nz BBR Contech 38 Waione Street, Petone PO Box 30-854 Lower Hutt, Wellington 5040 Tel +64 4 569 1167 Fax +64 4 569 4269 www.contech.co.nz wgn@contech.co.nz BBR Contech 7A Birmingham Drive, Middleton PO Box 8939 Riccarton, Christchurch 8440 Tel +64 3 339 0426 Fax +64 3 339 0526 www.contech.co.nz chc@contech.co.nz Additional BBR technology licenses have been granted in Europe, Asia Pacific and Americas – for more information, please contact the BBR Headquarters. www.bbrnetwork.com 79 CONNÆCT The magazine of the Global BBR Network of Experts 2013