Aux Sable, Amine Project

Transcription

Aux Sable, Amine Project
Aux Sable, Amine Project
Three towers were dressed out on their sides and then set on their pads.
 30V-351 – 185,000 lbs. & 76’ Tall
 30V-354 – 155,000 lbs. & 106’ Tall
 60V-670 – 164,000 lbs. & 64’ Tall
We used a Manitowac M2250 Series 3 Crawler Crane (300T Capacity) for the main crane and a Liebherr
LTM 1250 6.1 Hydro Crane (300T Capacity) as the tail crane. All three lifts went according to plan and all
three towers were set within a 4 day window.
Shown in the picture – 30V-354 on the left, 60V-670 on the right
Aux Sable, Prover Skid Fabrication @ Hammond Shop
November 2012
Fabrication of a “Prover Skid” to meter gas transferred from the Aux Sable facility to their customer
Lyondell installed at the Lyondell Plant.
Weight 39,000 Lbs.
BP- Whiting Refinery,
Precision Lifting
New Coker Downcomer Piping
Weight: 28,000 Pounds
Top Platform elevation: 300 + Feet
New Coker, Hair Pin Piping, 1 of 6 units
Weight: 21,000 Pounds
Large fabrication assembled at grade to
minimize elevated work.
Carmeuse - Grinding Mill (Low Ceiling)
Everything done two times for two units: Unit 7 & Unit 8
Section One, Low Ceiling, Weight:
25,000 lbs.
Section Two, Low Ceiling, Weight:
42,000 lbs.
Carmeuse - Grinding Mill (Low Ceiling), Continued
# 7 Grinding Mill, 40,000
lbs., set inside of another piece
Top Piece of Feed Bin: 22,000
lbs.
Prefab Building, Awkward Weight Distribution, heavier at one end and side,
Weight: 78,000 lbs.
Praxair, Lakeside Facility- Argon Recondenser Project
December 2012
Installation of Foundations, Equipment, Piping and Electrical to facilitate the recovery of argon that is
lost at the facility.
This was a “Rush” project successfully completed in 4 weeks.
Weight: 15,000 lbs.
PRAXAIR - Whiting
Hydrogen Facility, SMR 5 & 6 Skid Installation
There were four large skids and two small skids that were off loaded with rigging shown then set on
skates and pulled into the building with grip hoist. This was tight quarters with limited access.
Weight 60,000 Lbs. Large Skids (4)
Weight 35,000 Lbs. Small Skids (2)
Ratner Steel,
New Equipment Line, Steel Coil Stretcher/Cutter Installation
March 2013
Weight 147,000 Lbs. (2) stretchers,
LOW CEILING, Close Quarters
Safety-Kleen,
Tank Farm
March 2013
Long Reach over existing equipment, 18 tanks total
Weight 20,000 Lbs.
Vantage Oleo, Splitter Column #5
Installation of the middle section of Splitter Column #5
Due to site restrictions, the vessel was shipped in 3 sections and welded together in place.
In order to meet QC requirements, Amex Nooter LLC and Nooter Corp. combined resources to complete the project.
2205 Stainless Steel Material
Weight: 35,000 pounds