Traffic facilities in central Berlin B 96 federal road

Transcription

Traffic facilities in central Berlin B 96 federal road
www.kuk.de
Traffic facilities in central Berlin
B 96 federal road
Startup Tiergarten Spreebogen tunnel (TTS)
For the central area of Germany's capital, Berlin, with its new government quarter and the newly-designed Potsdamer
Platz, a solution was needed to manage
road traffic moving in a north-south direction along the B 96 federal road.
As a result of the planning process, the
construction of a road tunnel between
Heidestraße to the north and the Landwehr canal to the south was begun in
1995. There are additional entry and exit
ramps at Invalidenstraße and Kemperplatz.
The tunnel allows through traffic to be
kept out of the government quarter and
the above-ground road that cut through
the Tiergarten park can be removed.
The tunnel is composed of three main
sections in a north-south direction:
Fully equipped tunnel
Heidestraße access ramp - Invalidenstraße access ramp
Two tunnels separated by a central wall,
each with one lane and a hard shoulder,
total width of road surface in each tunnel
6 m, plus a 1 m wide emergency footpath
on each side.
Operations buildings
There are three operations buildings to
accommodate the technical equipment;
they are all entirely below ground level.
Invalidenstraße access ramp - Kemperplatz access ramp
Two tunnels separated by a central wall,
each with one lane and a hard shoulder,
total width of road surface in each tunnel
8,5 m, plus a 1 m wide emergency footpath on each side. In the area of the main
station there is access to the German
Railways underground car park.
Kemperplatz access ramp - Reichpietschufer access ramp
Two tunnels separated by a central wall,
each with one lane and a hard shoulder,
total width of the road surface in each tunnel 6 m, plus a 1 m wide emergency footpath on each side. In this area there is access to the Sony Center and the supply
center at Potsdamer Platz (VEZ-Daimler-Chrysler).
Start of operations in the B 96 Tiergarten-tunnel
Because of delays in the construction of
the tunnel near the Lehrter station, the
tender procedure for tunnel equipment
according to the execution planning that
was current at the time was suspended in
1999.
In 2002, it appeared that the basic tunnel
structure would be completed by the end
of 2003, and because of this, the Berlin
senate administration restructured the
project leadership organization and commissioned Krebs und Kiefer to carry out
the project management for the start of
operations.
Owner
Land Berlin
Client
Senatsverwaltung für Stadtentwicklung, Hauptabteilung
Tiefbau
Object planners
Ingenieurgemeinschaft für die
Planung der Verkehrsanlagen
im Zentralen Bereich (IVZ)
Construction period
2002 - 2006
Construction costs
45 Mio. EUR
Project data
- Inner-city road tunnel
- Total length: 2,8 km
Initially, the main task was to produce revised plans that both complied with the requirements for safe road tunnels according to RABT 2003 and took into account
the existing structure, which was almost
complete.
Access ramp Reichpietschufer
1/2
www.kuk.de
Traffic facilities in central Berlin
B 96 federal road
Startup Tiergarten Spreebogen tunnel (TTS)
In order to equip the basic structure as a
safe road tunnel, the following tasks had
to be coordinated:
Minna-C-Str.
r -S
aue
MinnaC
r.
e
raß
nst
e
alid
Inv
Entry and exit
German Railways (DB AG)
underground car park
Spree
ni
es 17. Ju
Straße d
Entry and
e
straß
exit
enné
L
Kemperplatz
traße
rtens
a
Tierg
n
Gurio
Ben-ße
Stra
Truck access to
Sony-Center
ße
tra
Pots
da m
er
S
-
Additional work required before starting operations
- Installation of private cell phone operators' equipment in the operations buildings and tunnel
- Traffic technology / lights and signals
- Data connection to the Berlin tunnel
control center, the traffic control center
and the three neighboring buildings
- Construction of an outgoing air chimney
at Lehrter station
- Construction of a connecting lane to
Heidestrasse with an accompanying
lane
- Installation of lighting at the junctions
- Pilot operation
est
Technical building equipment /
tunnel equipment
- Electrical engineering
- Communications and safety technology
- Building control technology
- Public lighting
- Traffic technology
- Elevators for the operations buildings
- Ventilation for the tunnel and operations
buildings
- Sanitary engineering / gas, water and
waste water
- Rainwater pumping equipment
- Fire extinguishing pipes
Road construction
- Construction of the road surface of the
tunnel in asphalt, including sealing and
concreting the footpaths at the side
- Road markings and signs
- Bridges for mounting traffic signs / advance directional signs
Building construction
- Finishing of the operations buildings
- Metalwork in the tunnel
- Cladding of the ramps
Heid
tr.
Entry and exit
Reichpietschu
fe
Land r
w
Schöneberge ehrka
r U nal
fer
VEZ
DaimlerChrysler
Entry and exit
Krebs und Kiefer services
- Project management for the
start of operations in the
tunnel (technical equipment)
under consideration of the
changed requirements due
to RABT 2003:
- Project preparations:
- Updating basic planning
documents
- Facilitating basic decisions
- Establishing a project information database
- Planning:
- Management of adjustments to the existing planning to meet the changed
requirements of RABT
2003
- Preparation for construction:
- Decisions on contract
award units
- Management of the contract award process (partly
EU procedures)
- Establishing project accounting
- Overall schedule planning
for construction procedure
- Construction:
- Management of procedures
- Management of costs
- Public relations work
- Project finalization:
- Organizational involvement
in starting operations in the
tunnel and transition to normal use
- Involvement in producing
maintenance contracts
- Expert reports
- Safety and health coordination
G.-C.-MarshallBridge
Outgoing
air chimney
Operations
buildings
Emergency
exit
Overview
By May 2004, all the major work necessary for starting operations in the Tiergarten-tunnel had already been assigned or were the subject of invitations
to tender. Operations started in 2006.
Structural work at main station
Fire emergency lighting in operation
2/2