Pressurized System
Transcription
Pressurized System
Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 In-Situ Measurement Campaign at the “Perućica” Hydropower Plant in Montenegro - Part 2: Pressurized System Danica Starinac1, Dragiša Žugić1, Zvonimir Predić2, Aleksandar Gajić3, Dušan Džopalić2 and Predrag Vojt1 1 Jaroslav Černi Institute for the Development of Water Resources, Jaroslava Černog 80, 11226 Pinosava, Belgrade, Serbia; E-mail: danica.starinac@jcerni.co.rs 2 A.P. Company, Koste Taušanovića 2, 11120 Belgrade; Serbia, E-mail: apcompany@sezampro.co.rs 3 University of Belgrade - Faculty of Mechanical Engineering, Kraljice Marije 16, 11120 Belgrade, Serbia; E-mail: agajic@mas.bg.ac.rs Abstract The Hydraulic Department of the Jaroslav Černi Institute for the Development of Water Resources undertook an important measurement campaign under the Perućica HPP Modernization and Revitalization Project. The campaign included in-situ measurements (water levels, discharges, pressures, displacements, stresses and vibrations) at different locations throughout the HPP system. Numerous steady-state and unsteadystate scenarios were tested, through continuous and simultaneous measurements at all measurement points. This paper presents the measurements carried out in the pressurized system, starting from the power intake structure and ending with the tailrace system. The applied measurement and data acquisition methodology is explained, followed by results and conclusions. The measurement campaign provided valuable data for the calibration of a mathematical model, as well as insight into the operation of particular parts of the system. Keywords: hydropower plant, in-situ measurements, measurement campaign, Perućica, pressurized system Introduction In June 2010, the Hydraulic Department of the Jaroslav Černi Institute for the Development of Water Resources undertook an important measurement campaign under the Modernization and Revitalization Project of the ‘‘Perućica’’ hydropower plant (HPP) (Starinac et al., 2011). During the entire period of service, the HPP has never been operated at the maximum power of 307 MW (total installed capacity), but only to 285 MW. The average annual output (1960 to 1999) was 823 million KWh, or about 63% of the potential annual capacity. Many studies and analyses, such as in-situ measurements, mathematical simulations, observations, etc. (Djonin et al. 1984; Petrović and Djonin, 1986) have been undertaken with the objective to determine the origins of the problems and to identify the measures best suited to the elimination, or at least alleviation, of the problems. Based on the outcomes, UDK: 621.311.21(497.16) the operating power level was increased to 285 MW. The main reasons for this limitation were inadmissible mechanical vibrations of the turbine housing and load fluctuations, especially in the tailrace system and particularly during load change, load rejection and shut down operations (Gajić et al. 1998). The Perućica HPP Modernization and Revitalization Project is aimed at increasing the operating capacity up to the installed power level as a first step and, after analyzing the possibilities for installing a new, eighth generating unit, increasing the capacity even further. For that purpose, it was necessary to carry out detailed analyses of the entire system, including mathematical modeling. For model calibration, parameter values based on in-situ measurements were required. The measurement campaign included in-situ recording of water levels, discharges, pressures, displacements, stresses and vibrations, at different locations throughout the Perućica HPP system, in order to identify the origin of the existing problems and 3 Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 to define the basis for rehabilitation. All measurements were continuous and simultaneous, due to the requirement to obtain real information on system behavior under different conditions and to provide adequate data for mathematical model calibration. Considering different hydraulic characteristics, the system could be divided into two parts – an open channel system (upstream of the power intake ‘’Marin Krst”) and a pressurized system (downstream of the power intake). In this paper, the measurements carried out in the pressurized system are presented through an explanation of the applied methodology, followed by results and conclusions. Description of the System The Perućica HPP is located on the Zeta River, in the central part of Montenegro, near the Town of Nikšić. The HPP has been designed for eight generating units, but only seven were constructed in the first phase, with a total installed capacity of 307 MW. The system makes use of the energy potential of the Zeta River (catchment area 850 km², gross head 550 m), between its upper course (the Upper Zeta River) at Nikšić Polje and its lower course (the Lower Zeta River) close to Glava Zete. Hydropower plant configuration The HPP has been planned and designed as a high-head run-of-the-river hydropower plant, in combination with three water storage reservoirs. According to this configuration, the Zeta River (at Nikšić Polje) was planned as the main supply source for the Perućica HPP. The initial design called for the impounding of the Zeta River by the Vrtac Dam, for controlled release and use for power generation in line with the power demand. In addition to the Zeta River, plans called for the utilization of the Moštanica River and the Opačica River, through impoundment by the Krupac Dam and the Slano Dam, respectively. This concept meant that both reservoirs, Krupac and Slano, would contribute to the power generation by releasing water into the Vrtac Reservoir, as a regulating structure for the Perućica HPP headwater. From the Vrtac Dam, water is conveyed by a feeder canal, Zeta I, to a compensation basin and the power intake at Marin Krst. The compensation basin has sufficient capacity to provide water during the startup of the power plant or when additional units are initiated. Similarly, the compensation basin preserves water when the units are shut down. Pressurized system The pressurized system includes structures located downstream of the power intake ’’Marin Krst’’: headrace pressurized system, powerhouse and tailrace system (which is analyzed in this paper even though it has the characteristics of an open channel flow). From the power intake, the headwater is conveyed to the powerhouse and to each turbine through a pressurized system (Figure 1). After passing the power intake, the water enters a headrace tunnel (length 3,323 m, diameter 4.8 m), which branches into three penstocks at a trifurcation, at some distance downstream from a surge tank. Each penstock is provided with a butterflytype emergency valve. The valves are housed in a valve chamber “Povija” (Figures 2 and 3). The penstock data are summarized in Table 1. Figure 1: Longitudinal section through the power intake, headrace tunnel, surge tank and valve chamber Figure 2: Longitudinal section through the surge tank, the lowest reach of the headrace tunnel, trifurcation, valve chamber and penstock 4 Water Research and Management, Vol. 2, No. 4 (2012) 3-17 Starinac et al. Figure 3: Plan view of the lowest reach of the headrace tunnel, trifurcation, valve chamber and penstocks Table 1: Penstock characteristics Penstock Unit I II III Diameter [m] 2.2-1.8 2.2-2.1 2.65-2.5 Length [m] 1,851 1,883 1,930 Discharge [m³/s] 17.00 25.50 38.25 1, 2 3, 4, 5 6, 7, (8) Generating units At the entrance to the powerhouse (Figure 4), the penstocks branch into manifolds for the generating units. The powerhouse of the Perucica HPP comprises seven (7) generating units. All seven existing generating units consist of horizontal axis generators. The turbines are of the Pelton type, with two runners per generating unit, located on either side of the generator. The characteristics of the generating units are presented in Table 2. Figure 4: Layout of the powerhouse, showing all eight units, tailrace tunnels and manifold cavern. Units 1 to 8 (right to left) with two-station sub-units of Unit 1 Table 2: Characteristics of generating units Number of generating unit 1 2 3 4 5 6 7 8 Rated head (m) 526 Rated discharge (m³/s) Rated capacity (MW) 8.5 8.5 8.5 8.5 8.5 12.75 12.75 12.75 38 38 38 38 38 58.5 58.5 58.5 No. of Pelton runners per unit 2 2 2 2 2 2 2 2 No. of nozzles per turbine 1 1 1 1 1 2 2 2 Each turbine has a separate turbine pit and a short tailrace tunnel to the tailrace collector tunnel and from there a tailrace canal to the confluence with the Lower Zeta River. and Un = 0.56" (for angle measurements). To determine the vertical positions (heights), a Leica DNA03 precision level was used. The accuracy of this instrument is U = (0.286* L/2) mm, L in km. Methodology and Equipment Measurements at the power intake Horizontal position and height measurements In order to generate a unique coordinate system for all measurements and to correlate these relative measurements, a geodetic survey was conducted to reference the measurements to the official coordinate system of Montenegro. The power intake is the interface between the open channel system and the pressurized system. During the measurement campaign, water levels upstream and downstream of the trash rack were measured (Figure 5). Vortex formation at the entrance to the power intake was also recorded by video camera. To determine the horizontal positions, a Leica TC 2003 total station was used. The precision of this instrument is U = (1+1*10-6*L) mm (for distance measurements) Water levels upstream of the trash rack were measured using an Eijkelkamp diver, a device with a pressure sensor and integrated data logger. The 5 Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 device was placed inside a perforated pipe, next to an existing level gauge (Figure 6). Water levels downstream of the trash rack were measured using a similar device, Solinst Levelogger Gold Model 3001, located in the roller gate shaft of the power intake. Existing devices for water level measurement were also used, together with a Datataker DT500 data logger. Vortex formation in front of the entrance to the power intake was continuously recorded by video camera, to determine any clogging or air retraction. Figure 5: Power intake at Marin Krst, longitudinal section Measurements at the surge tank Water levels in the surge tank were measured applying two methods: radar and pressure sensor. The Endress+Hausers Micropilot M FMR240 radar is a device for continuous, non-contact water level measurement, with data acquired by Datataker DT500. The radar sensor was installed above the crest of the surge tank, suspended from the structure braced to the fence of the surge tank top gallery (Figure 7). Figure 7: Measurement of surge tank water levels by radar Measurements at the penstocks Pressures Pressures were measured at the upstream ends of the penstocks, at the Povija valve chamber, and at the downstream ends of the penstocks, in the powerhouse. Four R.D.A. pressure probes (range 0-10 bar; current output 4-20 mA) were installed in the valve chamber: one at the downstream end of 6 Figure 6: Water level measurement upstream of power intake Besides the described method, water levels in the surge tank were measured by a pressure sensor. A Solinst Levelogger Gold Model 3001 was used, which is a pressure sensor with integrated data acquisition and storage. The probe was placed on the bottom of a perforated metal housing (Figure 8) and submerged to an exact elevation. Since this probe measures absolute pressure, the water levels were determined upon appropriate correction for barometric pressure. Figure 8: Measurement of surge tank water levels, pressure sensor housing the headrace tunnel, before the trifurcation, at the existing drainage pipe (Figure 9), and one at the upstream end of each penstock, at the bypass pipes (Figure 10). The probes were calibrated individually in-situ, before installation, for values of 0-5 kp/cm2, using a Deadweight Tester. The Deadweight Tester (range 0-10 bar; accuracy ±1mbar), together with a DT85G logger (sampling frequency 3.5 Hz), was also used for continuous pressure recording during steady state measurements. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 Starinac et al. Figure 9: Pressure measurement in headrace tunnel, before trifurcation Figure 10: Pressure measurement at upstream end of penstock Pressures at the downstream ends of Penstocks 1 and 2 were measured in front of the pre-turbine valves, at the entrance into auxiliary supply units 1 and 2, while pressures at the downstream end of Penstock 3 were measured at the discharge valve, just ahead of a bifurcation. During steady state tests, pressures were measured using a deadweight tester and transducers together, while in unsteady state tests only transducers were used. During unsteady state tests, pressure signals from the downstream ends of Penstocks 1 and 2 were downloaded from the HPP monitoring system and the data recorded together with other signals from Units 1 and 2, on a computer-based acquisition system ED 2000. One deadweight tester (Figure 11) was used to measure pressures at the downstream ends of Penstocks 1 and 2 during steady state tests. Another deadweight tester was installed close to the bifurcation and discharge valve on Penstock 3, and used for calibration of an HBM (Hottinger) pressure probe used during unsteady state tests, but also for steady state measurements. The data were recorded by the Datataker DT800. Discharge measurement Penstock discharges were measured about 100 m from the downstream end of the tunnel part of the penstock route, by three ultrasound flow meters. Figure 11: Deadweight tester in the Povija valve chamber Each flow meter was installed on the penstock with two pairs of ultrasonic probes – a total of four at one measurement cross section (Figures 12 and 13), in order to increase velocity measurement accuracy. The instruments included Endress+Hausers Prosonic Flow 93W (clamp on) devices, which cover a velocity range of up to 15 m/s. The logging equipment included a stand-alone DATATAKER DT800 (with data acquisition at 1 second intervals) and an Endress+Hausers Memograph (with data acquisition at 60-second intervals). Figure 12: Penstock discharge measurement point Figure 13: Ultrasound probes installed on penstock Displacement of Penstock 3 Displacement of Penstock 3 relative to the concrete block was measured at two locations: near Foundation T5 (between T5 and T6), and at the expansion joint of Foundation T8. Measurements at Foundation T5 included displacements of the penstock’s cross section in two perpendicular directions. Inductive probes HBM W50TS (for Y direction, Figure 15) and HBM W50 (for X direction, Figure 14) were used, together with HBM KWS 2 channels (for signal conditioning). Data were acquired by a DT80 7 Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 data logger. This device had an internal memory of 50 MB, from where the data could be transferred online (using a GPRS router) or downloaded later (interface ports: Ethernet, USB, RS232). Both methods were applied on instant request. Figure 14: Measurement of displacement in X direction at Foundation T5 Figure 15: Measurement of displacement in Y direction at Foundation T5 Measurements at Foundation T8 included displacements of the penstock’s cross section in two perpendicular directions, as well as axial displacement of expansion joint No. 8 at three points along the circumference: 0°, 120° and 240° (Figure 16). The methodology was similar to that applied at Foundation T5. Stresses Stresses at Penstock 3 manifolds and branches (both static and dynamic) were measured using strain gauges mounted on the surface of the penstock at the manifolds and branches. The gauges were connected to a data logger and readings were taken automatically. Figure 16: Measurement of axial displacement at Foundation T8 Twenty Tokyo Sokki Kenkyujo strain gauges were installed according to a previously defined layout (Figure 17). The strain gauges were mounted approximately at (as close as possible to) the positions (points) where maximal stresses had been observed during earlier measurements, so that the results could be compared. Based on the assumption that the directions of principal stresses in a pressurized tube with a circular cross section are known, the strain gauges were positioned as biaxial rosette gauges with an internal angle of 90°; one axis was parallel and the other perpendicular to the penstock centerline (Figure 18). Only at the most threatened points of Branch A, triaxial rosette gauges with angles of 0°, 45° and 90°, marked as R1 and R2 (Figure 19), were used. R1 and R2 were selected partly because of a not-so-cylindrical contour of the manifold, but also to verify the assumption regarding the directions of the principal stresses. The results confirmed the assumption. 8 Figure 17: Schematic representation of the arrangement of strain gauges on Penstock 3 Each active strain gauge had a corresponding compensation (passive) strain gauge with the same characteristics, glued to a plate made of the same material as the penstock. The plate was placed beside the active strain gauge, paying attention that the passive strain gauge would be exposed to the same temperature and humidity conditions, but not to any stress. In this way environmental effects were compensated and annulled. The principal stresses were calculated on the basis of measured strain. A DataTaker DT800/3 was used Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 for data acquisition. The device was connected (via Ethernet port) to a computerized data acquisition system in the powerhouse, providing online results of the stresses. Figure 18: Measurement of stresses at Penstock 3 Measurements at the generating units Measurements at the generating units included pressures, needle and deflector positions, rotating speed/overspeed, power at the generator outlet and vibrations. Pressures in front of spherical turbine valves and pressures at turbine inlets were measured at each generating unit (except A5), using transducers of the existing HPP monitoring system. No sensor was in place at Generating Unit A5, so an HBM (Hottinger) pressure probe was installed. This probe was calibrated in-situ, before installation, using a deadweight tester. Unfortunately, since the valves in the HPP were not set properly, measurement results for Generating Unit 5 are missing. Figure 19: Measurement of stresses using triaxial rosette gauges (galvanic isolation), and recorded by the data acquisition system described below. An exception was made at Generating Unit A6 because of the fact that all four needle positions were represented by only one signal, and both deflectors also by only one signal. For that reason, four Vishay potentiometers were installed to measure needle opening (Figure 20), and two Celesco probes to measure deflector positions (Figure 21). The rotating speed of the turbines was measured at each unit using existing tachometers (0-200%; 4-20 mA (A1-A4, A6, A7), 0-20 mA (A5)). Obviously a 100% range is better suited to rotating speed measurements, but the 0-200% range was selected in order to measure overspeed in transient regimes. The position of the needles and deflectors were observed by the existing HPP monitoring system. The signals were transmitted through interfaces, avoiding interference in the monitoring system Instantaneous power measurement signals from the existing HPP monitoring system were transmitted using galvanic isolation interfaces and recorded together with the other signals from the respective unit. Figure 20: Needle opening measurement at Generating Unit 6 Figure 21: Deflector position measurement at Generating Unit 6 All signals from the measurements at the generating units, except vibration, were recorded together using three acquisition systems: ED2000 (signals from Generating Units 1 and 2, Figure 22), Datataker DT800/2 (signals from Generating Units 3 and 4, Figure 23), and Datataker DT800/1 (signals from Generating Units 5, 6 and 7, Figure 24). 9 Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 PC notebook with CATMAN software, and was used for data acquisition from Generating Units A5-A7. Figure 22: Data acquisition system ED2000 Figure 25: Existing NI-085 sensors for vibration measurement at Generating Units 1-4 Figure 23: Data acquisition system DT800/2 Figure 26: Installed NI-085 sensors for vibration measurement at Generating Units 1-4 Water level measurements in the turbine pits Figure 24: Data acquisition system DT800/1 During all steady state tests, vibrations were measured on each generating unit using contactless displacement sensors. Sixteen (2 per turbine) Schenck NI-085 sensors had already been in place (existing HPP monitoring system) and 12 new sensors of the same type were installed (for the measurement campaign) on Generating Units A1-A4. In the niches of 4b and 6b turbine pits, Druck pressure sensors were installed on the bottom of perforated pipes (Figure 27), to measure water levels. Data were collected by a PC-based (Labtech software) acquisition system ED 300. It was difficult to install the sensors (Figure 28), but even more difficult to maintain sensor safety and position during the measurements, which explains the incompleteness of the data. Because it was impossible to better anchor and protect the sensors in such conditions, huge water turbulence in the turbine pits caused displacement, crashing into the pipe wall and damaging the sensors before the measurements were completed. Schenck NI-083 sensors were installed on the a-turbines of Generating Units A5, A6 and A7, while 2 HBM sensors (A5), 2 Baluff sensors (A6) and 2 Kaman sensors (A7) were installed on the b-turbines of Generating Units A5, A6 and A7. All contactless sensors were mounted in the same way, to measure vibrations in two perpendicular directions – horizontal and vertical. Data were collected by two acquisition systems. The first system, 16-channel ED-A2 with galvanic isolated ports 0-20 V, was used for data acquisition from Generating Units A1-A4. The other consisted of two connected Spider8 (HBM) systems, 3 RDA 2-channel signal conditioners and a 10 Figure 27: Water level measurement in turbine pit Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 The camera footage and electrical conductivity data were recorded using a PC-based acquisition system, while the data acquisition system for the ultrasound level meter was a Fluke 289. Figure 28: Installation of measurement equipment in turbine pit Measurements in the tailrace tunnel and canal The measurement campaign included water levels in the tailrace system and clogging in the tailrace tunnel. Since access to the tailrace was not easy, existing vertical aeration shafts were used (Figure 29). Water levels were measured in three points: at the upstream end, in the middle and at the downstream end of the tailrace tunnel. At the first two points, the existing aeration shafts were used for installation of the measurement equipment (Figure 30). Huge metal perforated pipes were mounted inside the aeration shafts, and then the pressure sensors inserted through them to the bottom of the tunnel. Druck pressure sensors, calibrated in-situ, were used at first, together with the ED300 data acquisition system, used also for water levels in the turbine pits. Similar to the turbine pits, huge water turbulence caused significant vibrations of the protective tubes and sensor displacement and damage before the measurement campaign was completed. These sensors were replaced by Eijkelkamp diver pressure sensors. A Solinst Levelogger Gold M5 was installed at the downstream end of the tunnel. All these instruments functioned as both pressure sensors and loggers (integrated). Figure 30: Water level measurement point Figure 31: Measurement point for clogging In-Situ Measurement Overview Considering the main objectives, the measurement campaign was divided into three groups of measurements, based on the boundary conditions in the open channel system and the HPP operating regime in the pressurized system (Table 3). Table 3: Measurement groups Group 1 2 3 Figure 29: Measurement points in the tailrace Clogging was observed by an ultrasound level meter (for detecting distance up to the liquid foam or water) and a video camera (for inspection inside the tunnel), installed in separate aeration shafts. Both measurement points were also equipped with an electrical conductivity meter, placed at the calotte of the tunnel to detect liquid foam or water. Open channel system Unsteady UP boundary (Upstream) conditions Steady S (Steady) boundary conditions Unsteady U downstream (Unsteady) boundary condition Mark Pressurized system Steady state – upstream system testing Steady state regimes Unsteady state regimes Steady state measurements: upstream system testing This measurement group was aimed at testing of the system of open canals under both steady and unsteady conditions, to provide relevant data for mathematical model calibration. The measurements are described in detail in Part 1 of this paper. 11 Water Research and Management, Vol. 2, No. 4 (2012) 3-17 Starinac et al. During all the tests, the flow conditions in the pressurized system were steady and the measurements were carried out only at the most important points. Since these measurements were not as important from a pressurized system perspective, only a description of the tested scenarios is provided (Table 4). Table 4: Scenarios of the 1st measurement group (UP) Scenario Date UP1 16.06.2010 UP2 17.06.2010 Time start end 07:00 13:00 13:00 19:00 19:00 22:00 07:00 13:00 13:00 19:00 19:00 22:00 HPP power (MW) (%) 61 20 122 40 61 20 100 ~30 180 60 100 ~30 Measurements in steady state regimes The measurements were made for six different scenarios which included, for the most part, the testing of high discharges and HPP operation at high capacities. This was partly caused by the hydrological conditions (heavy precipitation had resulted in large run-off and the discharges of the Zeta River were unexpectedly elevated), such that the HPP had to operate at high capacity in order to avoid excessive water losses. The second reason was the argument that system behavior during low discharges was properly analyzed through measurements under unsteady boundary conditions. Upon examination of the steady state regimes, the maximum power of the HPP was achieved at about 305 MW, while the water level in the compensation basin was at 603.5 m.a.s.l. During this regime, significant fluctuations were observed in the turbine pits and the tailrace system, followed by water jetting through the shafts between the turbine room and the distribution facility of the power plant. For the HPP operating at up to 290 MW, such events were not observed. In all regimes, the tailrace tunnel functioned as a conduit with a free water surface, without any air pockets or clogging. As power increased, losses along the flow conduits grew, until the pressures in the penstocks dropped and the maximum stresses at the C3 bifurcation fell from 294 MPa to 276.5 Mpa. However, when the power increased beyond 280 MW, turbine vibration grew. The measured shaft oscillations at the turbine beds were within acceptable limits. For turbines 1A, 2A, 2B, 3A, 3B, 4A and 7B, vibration status corresponded to Zone A according to ISO Standard 7919-5, and for turbines 1B, 4B, 5B and 6B it corresponded to Zone B. Turbines 5A, 6A and 7A were in Zone C. Displacements of Penstock C3 in the zone of Blocks T5 and T8 reached maximum values of up to ±2 mm in the “x” and “y” directions, and up to ±15 mm in the axial direction. Based on measured water levels at the power intake, pressure losses at the trash rack were found to depend on discharge (Figure 32). The graph shows a pressure loss at the trash rack of 1.8 m during maximum discharge. Table 5 shows the scenarios of this group, along with the planned operating conditions of the HPP. Each scenario lasted for two hours and allowed steady state flow in the pressurized system to be achieved. Table 5: Steady state scenarios Scenario Date S1 22.06.2010 S2 22.06.2010 S3 22.06.2010 S4 24.06.2010 S5 24.06.2010 S6 24.06.2010 *Planned values Time start end 10:00 12:00 16:00 18:00 18:00 20:00 11:00 13:00 13:00 15:00 18:00 20:00 HPP power* (MW) (%) 260 85 200 65 280 91 280 91 290 94 307 100 During the measurement campaign, water levels in the compensation basin were generally between 603.0 and 603.5 m.a.s.l., and the trash rack on the intake structure was regularly cleaned. Under such conditions, the system functioned quite well in all regimes. 12 Figure 32: Pressure losses at the trash rack of the power intake as a function of discharge Knowledge of the water levels in the surge tank during steady state regimes allowed for the estimation of pressure losses along the headrace tunnel. The difference between the water level downstream of the trash rack of the power intake and the water level in the surge tank (Figure 33) shows that the pressure loss in the headrace tunnel reaches 6 m WC at maximum discharges. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 Starinac et al. The results of water level measurements in the tailrace system provided for the definition of the losses along the tunnel as a function of discharge (Figure 35). The water level at the upstream end of the tunnel did not exceed 62.00 m.a.s.l., even at maximum discharges. At the downstream end of the tunnel, the highest water level at maximum discharge was 61.6 m.a.s.l. Figure 33: Pressure losses in the headrace tunnel as a function of discharge It was possible to estimate local losses at the trifurcation based on the pressure differences between the measurement points at the downstream end of the headrace tunnel (in front of the trifurcation) and the upstream end of each penstock, recorded by a deadweight tester during steady state regimes. Since the pressures were also measured at the downstream ends of the penstocks, the pressure losses in the penstocks could also be analyzed. The clear situation at Penstock 3 and a direct pressure measurement at the upstream and downstream ends of this penstock yielded a very small dispersion of points (Figure 34). For maximum capacity conditions, pressure losses in Penstock 3 were about 10 m WC. Figure 35: Differential water level in the tailrace tunnel as a function of discharge Measurements in unsteady state regimes In the third group of measurements, unsteady flow was caused by rapid changes in HPP operation, while upstream boundary conditions were steady. In this case, the most important measurement points were those located in the pressurized system, while the purpose of the measurements in the open channel system was to provide the upstream boundary condition for the pressurized system. Figure 34: Pressure losses in Penstock 3 as a function of discharge These measurements were carried out for 9 different scenarios, presented in Table 6. The duration of each scenario was approximately one hour, including flow stabilization in the pressurized system and subsequent transient flow. Table 6: Unsteady state scenarios HPP power* Scenario U1 U2 U3 U4 U5 U6 U7 U8 U9 *Planned values Date 24.06.2010 25.06.2010 25.06.2010 25.06.2010 25.06.2010 26.06.2010 26.06.2010 26.06.2010 26.06.2010 Time 20:00 15:00 16:00 17:00 17:30 11:30 14:00 16:30 18:00 (MW) start 305 266 235 195 305 245 285 305 80 Scenario (%) end 140 305 305 305 235 0 0 0 0 start 99 87 77 64 99 80 93 99 26 end 47 99 99 99 77 0 0 0 0 Normal power decrease Normal power increase Normal power increase Normal power increase Normal power decrease Quick shutdown Quick shutdown Quick shutdown Quick shutdown 13 Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 In all unsteady state scenarios, the water level fluctuations in the surge tank were within tolerance, in the sense that the maximum water level was below the top of the surge tank gallery (no overflow), and also that the minimum water level was above the critical level (no air suction). The maximum water level of 622.5 m a.s.l. was achieved upon load rejection (quick shutdown of HPP) at 305 MW output (Scenario U8, Figure 36). The minimum water level of 585 m a.s.l. was reached on the same occasion (Scenario U8), but also during a normal power increase from 190 to 305 MW (Scenario U4, Figure 37). Figure 36: Water level variation in surge tank, Scenario U8 Figure 38: Pressures in the Povija valve chamber, Scenario U4 Throughout the campaign, the water level in the compensation basin did not descend below 603 m a.s.l. This lead to the conclusion that no problem occurs at Povija even at maximum operating capacity if the water level upstream from the trash rack is high enough. Maximum pressures reached 625 m.a.s.l. during load rejections at high operating power levels, but also at low operating power levels. However, pressures did not exceed those which were observed earlier for the existing power limitation of 285 MW. The maximal allowed pressure in the penstocks is defined as the value which is 10% greater than the static pressure. The static pressure upstream from the turbine nozzle for the maximal possible water level at the intake structure of 618.0 m.a.s.l. is 552.2 m WC (618.0-65.8), while the maximal allowed pressure is defined as 1.1*552.2, or 607.42 m WC = 59.53 bar. The maximal measured piezometric pressure in Penstock C1 was pCImax = 55.85 bar, at Generating Unit A1 it was (relative to the nozzle elevation) p1max = 55.93 bar, and finally at Generating Unit A2 it was p2max = 56.0 bar. Figure 37: Water level variation in surge tank, Scenario U4 Pressure fluctuations in the Povija valve chamber were also within tolerance limits. They were analogous to those in the surge tank (both measurement points had the same oscillation frequency), but the minimal pressures in the valve chamber during a normal power increase from 190 MW to 305 MW (Scenario U4) were lower, at 581.5 m.a.s.l. (Figure 38). Since the pressures were not lower than the penstock elevation at any point during the measurement campaign, there was no risk of negative pressures so the aeration valves were not operated. The lowest measured pressure was 582 m.a.s.l., or about 10 m above the level of the aeration valves to the penstocks. 14 The maximal measured piezometric pressure in Penstock C2 was pC2max = 56.0 bar, at Generating Unit A3 it was p3max = 56.8 bar, and finally at Generating Unit A5 it was p5max = 56.0 bar. The maximal measured pressure in Penstock C3 was pC3max = 56.6 bar, at Generating Unit A6 it was p6max = 57.3 bar, and at Generating Unit A7 it was p7max = 56.6 bar. An increase in the rotating speed of Generating Unit A6 of Δn= 132% was above the allowed limit (transient turbine overspeed 125%), which was also the case in earlier tests. It will be necessary to reduce the deflector closing time. It would be useful to adjust the rotating speed and deflector closing times at Generating Unit A5 as well, where the measured transient overspeed was Δn= 122.8%, and on Generating Unit A7 where it was Δn= 126%. Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 It was noted that it is necessary to adjust the needle closing speed (in order to synchronize operation of the units). During scheduled overhaul, the needle closing time needs to be adjusted to about 80 s, from a fully open to a fully closed position. This means that the closing time has to be extended at Units A3 and A5 and the closing time at Unit A6 is to be shortened accordingly. The needle closing speed should be checked from time to time, in order not to exceed recommended limits. Displacements of Penstock C3 at the points of T5 and T8 blocks were within tolerance limits, even in the transient regimes, with maximum values during load rejection of up to 5 mm axially. The displacements at Foundation T5 during the entire campaign are shown in Figure 39. It is apparent that significant displacements occurred only during discharging and filling of the penstock. The maximum displacement at T5, registered before discharging of the penstock, was ±0.5 mm in both directions. During discharging and filling of the penstock, displacements in the x-direction (transversely to the penstock axis) varied as follows: first from 0 to +10 mm, than back, up to -30 mm and then again to 0 mm. During that period, the y-direction (vertical) displacement sensor registered -25 mm, but this was not an upward displacement since the penstock was moving axially and thereby pulled the probe up while bending its core. Upon filling, the penstock went back to approximately its previous position, and the probe came back to its zero position. Further on during the campaign, the penstock dilated at T5 in both directions, but only slightly. The observed displacement range was between 1 and 2 mm. Figure 39: Displacement of Penstock 3 at Foundation T5 during the measurement campaign the case with T8-y which, beginning on June 19th, continuously showed a value of about 10 mm. This discrepancy was a consequence of the physical movement of the probe’s zero position, which took place on June 19th, 2010, after axial probe damage at the expansion joint was rectified. The damage to the probe at the 120o position (broken) and the movement of the probe at 240o for 5 mm from its bed were the consequences of significant dilation of the expansion joint. The probes were installed to measure within a range of ±55 mm. The probe which was at the 0o position (the lowest point of the expansion joint) was the only one that kept measuring all the time since the displacements did not exceed 55 mm. The probe at 120° (the left probe in the flow direction) measured the greatest displacement as it fell off and broke. The probe at 240° recorded a displacement of 55 mm plus 5 mm, which was a dislocation from its bed, but it stayed in place. During filling, the dilation itself had the opposite direction, but the penstock did not stay in its original position; instead, it moved back some 35 mm more, so the dilation trace on the penstock was approximately 100 mm. Upon reinstallation of the probes, the measurements were completed on June 25th, 2010, and the results confirmed that the displacements in the “x” and “y” directions were only a couple of mm (Figure 40). Axial displacements during normal operation were approximately the same and did not exceed 20 mm in the direction of opening or closing, while in transient regimes only axial displacements were registered, and the greatest displacements, of 5 mm, occurred upon the first load rejection from 245 MW (Scenario U6, Figure 41). Figure 40: Displacement of Penstock 3 at Foundation T8 during the measurement campaign The situation with T8 turned out to be a little different, but only with regard to axial dilatation at the location of the expansion joint, which was significantly bigger. The displacements of the penstock cross section relative to the concrete block in the “x” and “y” directions were negligible, as was the case at T5. The values measured by sensor T8-x were around zero all the time, as was 15 Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 the most critical points will increase. The maximum stresses were registered during a quick shutdown with the HPP operating at 285 MW (Scenario U7), when the values of 302 and 312 MPa were recorded (Figure 43). Rapid power variations also caused an increase in the stresses at the manifold, but it was not as significant (Figure 44). Figure 41: Displacement of Penstock 3 at Foundation T5, Scenario U6 The measured stresses at Penstock C3 of about 302 MPa were above tolerance. Measurement point R1, where these stresses were recorded, was located within the free part of Penstock C3, upstream from the first branch, close to the place where cracks had been observed in the welded junction. In addition to this place, stresses as high as 312 Mpa were observed at locations T7-T8. These maximal stresses were recorded during load rejections (quick shutdowns), when the HPP operated at a total output of 285 MW and 245 MW. Figure 43: Stresses at manifolds and branches of Penstock 3 during unsteady state regimes – quick shutdowns The stresses on the manifold of Penstock C3, static and dynamic state, are shown in Figures 42-44, which support a certain penstock operating mode. Different points on the manifolds exhibited different stress levels. The highest stress was measured at points T7-T8 (up to 294 MPa) and R1 (up to 278 MPa). A static state of stresses on the manifold, as a consequence of static pressure within the penstock, remained almost unchanged from the time of filling of the penstock to the loading to 260 MW. Following a further power increase, losses within the system also grew, and the pressure at the manifold dropped to 50.9 bar, while the stresses were reduced to 276.5 and 256.5 MPa (Figure 42). Figure 44: Stresses at manifolds and branches of Penstock 3 during unsteady state regimes – normal power increase No problems were noted in the tailrace tunnel even upon load rejection at maximum power, but on that occasion significant pressure fluctuations occurred within the turbine pits, which were not a result of water level variations. Figure 42: Stresses at manifolds and branches of Penstock 3 during steady state regimes Based upon the above, it seems that more favorable conditions at the manifold are provided during operation at high capacities, but only if no load rejection occurs. Should this happen, the stresses at 16 Upon quick shutdown of the HPP operating at 285 MW (Scenario U7), or that of Unit A4 at 35 MW, rapid pressure variations were from -0.75 to +5.5 m WC, after which a longer-lasting negative pressure with a peak of up to -1.5 m WC occurred (Figure 45). These changes somehow influenced probe behavior, since in the next experiment, upon shutdown from a power level of 305 MW, the respective probe showed illogical results, but rapid pressure variations, both positive and negative values, were present. Starinac et al. Water Research and Management, Vol. 2, No. 4 (2012) 3-17 An increase in the plant output up to the installed power of 307 MW causes a certain increase in vibrations and shifting of the 5A, 6A and 7A turbines into Zone C, as well as higher pressure pulsation within the turbine pits, followed by the ejection of a mixture of water and air through the aeration shafts located immediately downstream from the turbine pits. Acknowledgments Figure 45: Water depths in Turbine Pit 4b, Scenario U7 The initial idea behind measuring water levels in the turbine pits was based on the assumption that open flow conditions are present and that the value of pressure (static head) in any floor point is defined by the water depth (open flow conditions). However, measurements showed that this was not the case and that atmospheric pressure occurred in the turbine pits only when the units were stopped. The fact that water from the turbine pits did not flood the powerhouse confirmed that the water level was in the turbine pits, but the air pressure varied (some mean value before load rejection, max. value at load rejection and min. value after load rejection). That is the reason why the measurement results are not presented as absolute levels, but as water depths. Apparently, the situation in A6B was even more turbulent since the probe in this turbine pit had stopped functioning earlier (Probe S3 at Turbine Pit A6B operated until 24.06.2010 at 14:00 hrs (Scenario S5), while at 19:00 hrs (in Scenario S6) it was destroyed. Pressure pulsations were 3 to 4 times stronger, and average water levels were lower. Conclusion The measurement campaign was considered a success, as it provided valuable information with regard to the data required for both calibration of the mathematical model and insight into the operation of particular parts of the system. These facts should be kept in mind while planning further upgrades. Regardless of the maximum power at which the HPP will operate, it is necessary to keep the water levels in the settling basin (upstream from the intake structure) above the critical level of 603 m a.s.l. and to clean the trash rack regularly. It is also necessary to resolve the problem of insufficient strain capacity of the Penstock C3 bifurcation, which is equally jeopardized even at an output of 285 MW; the regulators of some turbines should also be calibrated to ensure tolerable overspeed at all places. We would especially like to thank the Electric Power Industry of Montenegro for giving us the opportunity to participate in the Project, and for providing technical support during field measurements. References Gajić, A., Z. Predić (1998): Izvještaj o kompleksnom ispitivanju HE "Perućica" [Report on Comprehensive Testing of the Perućica HPP]. Faculty of Mechanical Engineering of the University of Belgrade (FME), Belgrade. Djonin, K. (1984): Izvještaj o ispitivanju odvodne vade i pojava u turbinskim jamama HE "Perućica" [Report on Tailrace-Outflow Channel and Turbine Pit Phenomena Investigations at the Perućica Hydropower Plant]. Jaroslav Cerni Institute for the Development of Water Resources, Belgrade, June 1984. Petrović, N., K. Djonin (1986): Izvještaj o ispitivanju ulazne gradjevine Marin Krst i spoja kanala Zeta sa kompenzacionim bazenom i taložnicama [Report on Model Investigations of the “Marin Krst” Inlet Structure and Connection of the Zeta Canal with Balancing Reservoir and Sedimentation Tanks]. Jaroslav Cerni Institute for the Development of Water Resources, Belgrade, September 1986. Starinac, D., Džopalić, D., Predić, Z., Gajić, A., Vojt, P. and M. Dimitrijevic (2011): Final Report on Insitu Measurement Campaign at Perućica HPP, Montenegro – Part 2: Pressurized system. Jaroslav Cerni Institute for the Development of Water Resources (JCI), Belgrade, October 2011. 17