VSM Group case
Transcription
VSM Group case
INTERFACE – Interfaces in Industrial Innovation Processes ©VSM Group AB VSM Group AB (Company Home) Thomas Magnusson 2008-06-23 INTERFACE – Interfaces in Industrial Innovation Processes Contents VSM Group AB ......................................................................................................................... 1 (Company Home) ....................................................................................................................... 1 Contents ...................................................................................................................................... 1 Figures ........................................................................................................................................ 1 Introduction ................................................................................................................................ 2 The Company ............................................................................................................................. 2 Product development at VSM .................................................................................................... 3 Project P08 ................................................................................................................................. 8 Background ............................................................................................................................ 8 The Technology/Product development interface ................................................................... 9 The Product development/Production interface ................................................................... 10 Lessons from the P08 development ..................................................................................... 11 Project P11 ............................................................................................................................... 12 Background .......................................................................................................................... 12 The Technology/Product development interface ................................................................. 13 The Product development/Production interface ................................................................... 14 Lessons from the development project ................................................................................. 15 Group assignment ..................................................................................................................... 16 Figures Figure 1 Internal view of sewing machine ................................................................................. 4 Figure 2 External view of sewing machine ................................................................................ 4 Figure 3 R&D organisation at VSM .......................................................................................... 5 Figure 4 Product development process ...................................................................................... 7 Figure 5 Presser foot assembly, needle threader and needle plate ............................................. 8 Figure 6 Platinum 730 - results from the P08 development project........................................... 9 Figure 7 Designer SE - results from the P11 development project .......................................... 13 1 INTERFACE – Interfaces in Industrial Innovation Processes Introduction This case report describes the company VSM Group, its R&D department and two product development projects which have been accomplished by the company. The report is based on 12 tape-recorded interviews with managers and engineers at VSM Group as well as studies of project documentation and participatory observation a project evaluation seminar. These empirical studies were conducted in March – June 2005. Hence the report describes the company in a situation as it was by the beginning of 2005. The Company VSM Group develops, manufactures and markets sewing machines under two main brands: Husqvarna Viking and Pfaff. VSM has its roots in Husqvarna AB, a company with a 300-year history as a manufacturer of a broad range of engineering products including hunting weapons, bicycles, motorcycles, kitchen appliances, sewing machines and outdoor products. Husqvarna AB started manufacturing of sewing machines about 150 years ago and application of new technologies and continuous introduction of new products and product ranges has since long been a hallmark of this company. In 2003, VSM Group employed 2246 people. The annual turnover was about 2 billion SEK and the annual sales volume is about 500 000 sewing machines. Represented in this figure are about 300 000 traded machines and 200 000 machines that are manufactured by VSM. VSM was separated from Husqvarna AB in 1997. Since then the company’s operations have been solely focused on sewing machines and sewing machine accessories including software, embroidery designs, presser feet etc. Accessories presently represent about 20% of the total turnover, but the market for accessories is expanding. The product range, which presently comprises about 40 different products, includes sewing machines in three different segments: Electronic, Computer and Embroidery. Electronic refers to a segment of lower-end basic, electronically controlled, machines; Computer refers to a more advanced mid-range segment and Embroidery comprises the most exclusive and expensive high-end machines. Present in the product range are also a number of traded sewing machines, both simpler and lower priced mechanical machines and Overlock machines that are specifically designed for overlockseams. All of VSM’s products are directed to the consumer market and they are distributed world-wide via an extensive network of dealers. North America is the largest and most important market for VSM with about 60% of their sales volume. The VSM headquarters, as well as the main manufacturing plant and R&D facilities are located in Huskvarna, Sweden. The company also runs a manufacturing plant in Brno, the Czech Republic. This plant came as part of the acquisition of the Pfaff household sewing machines division and the Pfaff brand name in 2000. The acquisition also included a manufacturing plant in Germany, which thereafter was shut down, and a R&D unit in Germany, which is in the process of being terminated. Part of the VSM Group is also VSM Software Ltd., a software development company in London, U.K., which was acquired in 1999. The VSM Group organisation has a traditional functional structure with five different departments: Finance, Research and Development (R&D), Production, Marketing and Sales. It also entails three different support functions: Quality/IT, Human Resources and an Executive Assistant. VSM has an ambition to retain the heritage from Husqvarna as an 2 INTERFACE – Interfaces in Industrial Innovation Processes innovative company and they have defined six “corporate values” that should reflect the business operations as well as the products: Trustworthy, Respect, Performance, Excellence, Goal Driven, Innovation, and Quality obsession. The brands Husqvarna Viking and Pfaff also have their individual proliferation. Husqvarna Viking stands for “values that reflect the real world and are part of your life: Innovative, Family, Caring, and Fun”. By contrast, Pfaff represents “values related to creating desire and dreams of what you can be: Elegant, Individual, and Sophisticated”. VSM generally has a smaller sales volume than their competitors, but also larger margins. In order to retain these margins it is necessary to introduce new products with improved functionality and performance, and with new technical features, at a steady pace. Especially in the high-end segment, this continuous innovation strategy has proved to be successful for VSM. Customers seem to be prepared to pay for technical novelty. In recent years, the market for sewing machines has tended to divert into two broad categories: buyers who are less price sensitive but wants the most advanced sewing machines, and buyers who consider price as a prime selection criteria for their purchase. Thus the mid-range segment is shrinking in volume and it is becoming less profitable. In the low-end segment, the competition is particularly challenging, with a large number of manufacturers represented. Especially, competition from Asian volume producers is daunting in this segment. Product development at VSM The sewing machine traditionally relies heavily on precision mechanics. However, during the last decades the product has undergone a rapid technical development. Advanced electronics and computer controls, which were implemented for the first time in the 1980s, have made it possible to add a lot of functionality to the machine and this has also propelled the development of graphical user interfaces and the use of graphical displays. New functionality such as embroidery capabilities has also resulted in additional demands in terms of enhanced accuracy and precision of the mechanical components. In addition, the amount of software in the machine has increased rapidly. As a result, today’s most advanced sewing machines rely just as much on electronics and software as on mechanics. The central mechanical component in the sewing machine is the arm, which is made from press cast aluminium. The tooling lead time for this component is about 18 months. VSM sources the arm from an external supplier. The arm forms the basis for a hardware platform, which is shared by a number of different models. Today, VSM uses a hardware platform called S2, which was developed in the mid 1980s. The S2 developments were initiated as a collaborative project involving both R&D and production departments at the company with the aim of rationalizing production and reduce the number of components. This development initiative was very successful as it meant that many functions could be integrated to the same components. As a result, the number of components in the sewing machine was reduced with about one third. Various mechanic and electronic components are attached to the arm. VSM sources all electronic components from external suppliers. Since VSM uses the same suppliers as many large consumer electronics firms, VSM is a relatively small customer and they often have to be very active in the procurement process. Mechanic components are both sourced from external suppliers and manufactured in-house. In particular, VSM have developed in house expertise in sinter-casting. This is held as an important manufacturing technique since this makes is possible to produce self-lubricating components with good precision. Another 3 INTERFACE – Interfaces in Industrial Innovation Processes important manufacturing technique, in which VSM retains expertise in-house, is injectionmoulding. The sewing machine entails a lot of injection moulded plastic parts and injectionmoulded plastic covers form the exterior of the sewing machine. VSM generally manufactures these covers as well as other plastic components in house. One exception however is the front cover because this component is too large to be manufactured at VSM’s production facilities. The lead time for manufacturing of plastic component tools is about 6-9 months. Figure 1 shows an internal view and figure 2 shows an external view of a sewing machine. Figure 1 Internal view of sewing machine (© VSM Group AB) Figure 2 External view of sewing machine (© VSM Group AB) 4 INTERFACE – Interfaces in Industrial Innovation Processes The R&D department at VSM employs about 80 people. The engineers are divided in seven groups: Project administration (6 engineers/project managers), Pre-Development and Design (6 engineers), Mechanical Development (15 engineers), Electronics Development (2 engineers), Software Development (16 engineers), Test and Verification Laboratory/Sew technique (9 engineers), and Technical documentation (5 engineers). The department also entails three product managers, one for traded products and one each for the Husqvarna Viking and Pfaff brands. Three systems engineers support the product managers, two of them work for the Husqvarna Viking product manager and one for the Pfaff product manager. Present in the R&D organisation is also VSM Software Ltd., which presently employs 11 engineers and a separate German unit with four engineers working with product support on existing Pfaff machines. Figure 3 presents an organisational chart for the R&D department at VSM. R&D Director Product Manager Traded Products VSM Software Ltd. Software Appl. Product Manager Husqvarna Viking Pfaff GmbH Product Maintenance Product Manager Pfaff Project Administration PreDevelopment Design Development Mechanical Development Electronics Figure 3 R&D organisation at VSM 5 Development Software Laboratory Test & Verification Sew Tech. Technical Documentation INTERFACE – Interfaces in Industrial Innovation Processes Rapid technological developments have resulted in a significantly shortened market life for the sewing machine. Whereas a product model previously could exist on the market for several decades, today’s sewing machines have to be replaced in a cycle which runs about 5 years. In turn, this means that several development projects have to be managed simultaneously at VSM. Every year about 20 different projects are completed by the R&D department. VSM uses a phase-review model to describe their product development process. Development projects are generally initiated as a result of primary development efforts involving new technologies, or as a result of feedback signals from the market including sales companies, agents, dealers and consumers. Another factor that may trigger development projects is competitors´ activities. The R&D department at VSM continuously monitors the competition through purchase and careful examination of recently introduced competitor products. The “Strategic Product Development Group” (SPDG), involving the company CEO, R&D manager, production manager, marketing manager and product managers, takes decisions to initiate development projects. Before starting a formal project, all necessary investigations should be completed and a specification should exist. Furthermore a Sponsor (in most cases one of the product managers) and a project manager should be assigned to the project. A specific group, the “Project Initialisation group”, works out the specification, which is handed over to the project. Hence, the first phase of the product development process is denoted “Specification phase” and at the end of this phase, there is a gate at which where the project requirements are reviewed. The second phase is a concept phase, which ends in a preliminary design review. At this point, results from FMEA, detailed schedules, WBS, article trees, product cost estimates, FS-prototypes and sales forecasts should be at hand. Thereafter follows a development phase, during which the project team produces prototypes, drawings and plans for testing, quality assurance, purchasing and production. Training, launch and service plans are also set up, and environmental evaluations, required authority approvals and packaging requirements are made during this phase. The development phase ends in a “Critical design review”. The following development phases involve design and manufacturing of tools, fixtures and assembly lines. A number of test series are run before the product is approved and handed over for mass production. The product development project model is illustrated in figure 4. 6 INTERFACE – Interfaces in Industrial Innovation Processes Figure 4 Product development process (© VSM Group AB) 7 INTERFACE – Interfaces in Industrial Innovation Processes Project P08 Background The purpose of the P08 development was to up-date the existing product portfolio in the Computer-High and Embroidery segments. In total four different machines were developed in the project. The main objective was to provide the machines with a new and modern exterior design. Amongst others, this meant new keys and new displays, as well as new covers all around the machine. Customers were supposed to perceive the machines as completely new even though the interior would be quite similar compared to the existing machines. Two of the machines were based on the S2 platform and two were based on the Designer series. This meant that even though the customers were supposed to view the four machines as a coherent product family, the machines were relatively different in terms of internal technological structure and design. To some extent, this meant that there was a double workload for product development, e.g. they had to design two different arms. However, as the interior mechanical design was left relatively untouched, only a limited number of new features, such as a needle threader (see figure 5), were introduced. Software development was an important part of the project and this also turned into a bottleneck. A major reason for this was that only two software designers were involved in the project. Figure 5 Presser foot assembly, needle threader and needle plate (© VSM Group AB) The P08 project was a relatively large development project at VSM and it employed a large part of the R&D department. But the project organisation was not formally divided and no object leaders were appointed. The project started in 2001 and it was ended in 2003. The models are currently (in 2005) being produced at the VSM production facilities in Huskvarna. In terms of final deadline, the project fulfilled its target and the machines were introduced in due time. The sales, however, failed to meet expectations. A number of explanations have been offered to this. Generally it is believed that sales in the mid-range segment have been difficult to achieve because customers either prefer cheap and relatively simple machines, or advanced high-end machines and this latter category of customers seems to be prepared to pay extra to get the latest features and the most advanced technology. The implication is that it is 8 INTERFACE – Interfaces in Industrial Innovation Processes difficult to compete with mid-range machines, which are lower priced but do not comprise the latest and most advanced functions and technology. Another explanation for the limited sales is the exterior design, which was intended as expressing “Nordic Elegance”, seemed to be too indifferent and anonymous. A third explanation to the limited sales is that the product price is too high, especially when compared to the price of machines that are imported from the Far East. Figure 6 shows Platinum 730, which is one of the sewing machine models that were developed in the P08 project. Figure 6 Platinum 730 - results from the P08 development project (© VSM Group AB) The Technology/Product development interface In this project, the primary role of the Pre-Development and Design group was related to exterior design and graphical user interfaces. Before the Product development project was initiated, two different design bureaus were engaged to carry out design studies for the new machines. These design studies, as well as the work on graphical user interfaces were coordinated by the Pre-Development and Design group. The engineer who was to be appointed project manager was part of the Pre-Development and Design group, so she was also involved at this stage. During 2001 Pre-development gradually turned into product development, the project manager was appointed and a steering group, consisting of the technical manager, the technical product manager, the commercial product manager and the marketing manager, was assembled. The technical product manager was also appointed as project sponsor. Decisions on design were delayed by the Pre-Development and Design group until the turn of the year 2001-2002 and this meant that the start of the development project was slightly delayed. The design coordinator from the Pre-Development and Design group followed the project. One problem with the design of the plastic cover was that it blocked insight to the needle. This was not discovered until a while after the project initiation, and it resulted in a lot of rework because the cover had to be adjusted and some inside components had to be moved. Remarkably, a previous development project (Designer 1) had experienced a similar problem, but the P08 project nevertheless failed to learn from that experience. 9 INTERFACE – Interfaces in Industrial Innovation Processes Another problem that arose had to do with the illumination of the display. According to the initial specification, this was to be accomplished by diodes. This was an inexpensive solution, but it was not proven that it actually worked in this application and it was considered a risk initially in the project. During subsequent prototype tests it proved to be difficult to reach the desired functionality level. The problem was discussed with the Pre-Development and Design manager, who had an informal role in the development project as a “concept owner”. He had initially stipulated the diode illumination, but as this solution did not produce sufficient contrasts, the engineers had to turn to a back-up solution with traditional light bulbs and reflectors very late in the project. The back-up solution demanded a slight adjustment of the mechanical design and it also affected the electronic control unit of the machine. According to the electronics design manager, this decision could and should have been taken much earlier: Against better judgement they insisted to use a solution that I thought we had good reason to believe that it would not work. Sometimes you drive the cost issue too hard and then you won’t fulfil the demands according to the specification. Initially it was decided that the machine should have a key board comprising a plastic cover with holes for the keys, similar to the key board of a mobile phone. But relatively late in the development project, due to cost reasons, the Strategic product development group (SPDG) decided that the project should switch to a key board with foil keys. This did not affect the final deadline and the project manager was not involved in the decision, so the practical implications for the project were not considered. The new key board technology later resulted in technical problems in one of the models, the embroidery model Platinum Plus/950E. The problem was due to bad contact because the key board was bending, which resulted in a displacement of the complete printed circuit board. It was discovered in prototype tests during the development project, but the problem was underestimated. Some late changes in the injection moulds were made but it was not properly verified that these changes would actually solve the problem. As a result, the contacting problems were still present in the machine when it was introduced to the market and released for sales and production. Due to these problems, which had not been properly solved in the product development project, correction had to be made after production release and a number of delivered products had to be called back. The Product development/Production interface Before product development was initiated there had been a discussion on the number of different models that were to be included in the project. The initial idea was to make a comprehensive design update of the whole model program, involving both basic and midrange machines. Then it was decided to delimit the project to fewer models. This limitation of the production volume meant that the injection moulding tools were designed with two instead of four dies. However, after this decision a couple of additional models were again included in the project, and this resulted in higher production volumes for the plastic covers. In retrospect, it would have better to design the injection moulding tools with four dies, since this would have resulted in lower unit costs of the plastic covers. During the development project, there was a continuous dialogue between design and production. As soon as the initial drawings were completed, there was a review, which brought design engineers, production engineers and an economic controller together. During this review, the product was scrutinized on a component level in order to assess the cost of tools and components with the ambition to bring about ideas for improvement and cost 10 INTERFACE – Interfaces in Industrial Innovation Processes reductions. However, the project manager felt that the designers tended to prioritize functionality and forget about the cost issue. For production the different internal technological structure and design meant that the machines were to be assembled on two different assembly lines. The first two models required a completely new assembly line, something that made the product development-production hand-over more difficult. The production capacity was unknown and the assembly philosophy was different. Whereas the previous assembly line was more controlling, the current system entails more autonomous assembly stations, something that makes it possible to build buffers of unfinished products between stations. Initially this possibility resulted in a shortage of fixtures, because each product requires a fixture and the buffers meant that more products than usual were present in the assembly line. So there was a disagreement between production engineers and assembly personnel regarding the number of fixtures required. The product development/production interface in the P08 project contained a number of test series. In the first test series, 10 units were produced, in the second 25 units were produced for sewing education. In the last test series, 100 units were produced in the final production line. These products undergo thorough product approval tests. Product approval means that the product is verified and that it functions with an appropriate quality. For this purpose, a grading system is used, in which the complete machine is assessed. The scale is 10, 50 and 100 points, where 10 refer to a minor blemish and 100 refers to problems that customers will make complaints about. If a product passes product approval, mass production may start. The first model in the P08 project was introduced during autumn 2002 and the second model obtained product approval in April 2003. Lessons from the P08 development The P08 project was the first development project that was managed according to the formal project model. The project manager feels that there was a problem to attract people to come to project reviews and gate meetings, because the interest is low. Additionally, since a large number of projects were running simultaneously, it was difficult to attract attention for individual projects, and particularly for a mid-range project like P08. Development of top-ofthe-line models is different in this respect because such projects automatically attract attention in the organisation. Another problem is that the line organisation is very strong and the status of the project manager is relatively low in the organisation. As illustrated in the P08 development and the change of key board technology, the project manager may not even be invited to take part in important decisions which have significant implications for the project. The project manager was put under pressure from the steering group to reach the stipulated deadline. In order to attract the resources needed, she had to negotiate with powerful line managers with different agendas and priorities, something that resulted in a very stressful situation for the project manager. Additionally, different roles and responsibilities were not clear. Which problems and decisions were to be addressed by the Strategic product development group (SPDG), the Steering group, the Sponsor and the Concept owner respectively? For example, even though the concept owner did not have a formal role in the project, as illustrated by the display illumination problem, he was very influential in decisions on technical solutions during the project. 11 INTERFACE – Interfaces in Industrial Innovation Processes As a consequence of the design related problem, where the needle was blocked by the plastic cover, sewing experts are now more actively involved early on in the design review process. The product cost and its relation to the level of ambition was not sufficiently addressed during the project and this resulted in a product that was more expensive than originally intended. An important lesson is that it is critical to relate the desired level of performance and functionality to an assessment of product cost during product specification. Project P11 Background The purpose of project P11 was to develop a new high-end embroidery machine, which was to replace the existing Designer 1 model. Designer 1 had been released in 98/99 and it had been very successful on the market, but now there was a need to add functionality in order to stay competitive. Thus an upgrade was needed. The initial specification was based on an inventory of requests for improvements made by a small group of people from sales companies, marketing and R&D. This inventory included requests such as: • Exterior design; improved sense of quality with a soft lid closing. • Separate winding motor. • Better display with higher resolution • More integrated customizing capabilities • USB-port • Capabilities of reading embroideries directly in HUS and VIP-format • Better electronics with faster generation of graphics and larger memory. SPDG started working on the specification in early 2001. Initially the idea was to base much of the design on existing hardware and focus on software development. P11 was the first project which had such a clear software focus. A larger display was also part of the initial specification. The development project was scheduled for about 1.5 years, starting in late 2001 and finishing during the first quarter of 2003. However an assessment of the amount of software development effort needed to reach the desired functionality showed that the project would require much more time. Since the complete software package had to be rewritten, the project could not deliver until the beginning of 2004, at the best. This opened up for discussions on possible changes of the exterior design, making the machine more attractive and up-to-date. Thus the initial specification, which had been released in 2001, was reopened, and this resulted in a major re-design effort, involving changes of the plastic covers all over the machine. In the end, 44 injection moulding tools were affected and only one was left untouched (initially only 2 tools were to be affected). This also meant that the initial specification phase, before the project was officially started (PRR gate), was quite extensive. In the end, the specification phase took about one year and the project turned from a limited upgrade to a complete redesign resulting in a completely new top-of-the line embroidery machine. The product development project involved almost the entire R&D department. The engineers were divided into a hardware group and a software group, with a small electronics group in between. A marketing group and personnel from Production, Verification and Quality were 12 INTERFACE – Interfaces in Industrial Innovation Processes also included in the project organization. In September 2004 the machine was finally released and production was started. The market response was very positive and the project is generally regarded as one of the most successful product development projects so far. Figure 7 shows Designer SE, which was developed in the P11 project. Figure 7 Designer SE - results from the P11 development project (© VSM Group AB) The Technology/Product development interface A number of new concepts and technologies were introduced in the P11 project. The technology development group was initially involved in electronics development, with the work on implementing new and quicker processor being their main task. At a later stage, in March 2003, it was decided to replace the existing floppy with a USB-port, because this new technology had developed very fast. Thus the task of integrating the USB with the sewing machine was added to the responsibilities of the technology development group. In retrospect it appears as a relatively straightforward decision, but there was some hesitation around the USB implementation, mainly on behalf of marketing and sales. The complete USB-module was purchased from an American supplier, but the effort needed to integrate it to the system was underestimated and the functionality could not be verified until very late in the project. Therefore the technology development group, which was in charge of the USB implementation, followed the project until the end of 2003. Another technology that was implemented for the first time in the P11 project was the use of LED instead of traditional light bulbs for illumination. Initially, technology development was run in parallel to the product development project. This development effort was undertaken in collaboration with a university research group. After a demonstration, the decision was taken to implement this new illumination technology in the P11 project. The LED illumination affected both electronics and mechanics; modifications were necessary. Additionally, a new software module had to be added to the existing software package. According to the project manager, this was the single largest technological change in the development project: It was completely new and untried and in the end, these were the parts that we had a lot of trouble with. He further asserts that since the LED-illumination was not part of the initial specification, it did not go through the normal product development process scrutiny. This is probably one of the reasons why the project group experienced problems with the technology at a later stage. 13 INTERFACE – Interfaces in Industrial Innovation Processes Related to the product development was also a technology development effort aiming for the implementation of thread portioning instead of a traditional friction based thread-tensioner. This technology development was conducted within the product development project and the traditional solution was developed in parallel as a back-up. The traditional solution was later preferred. The final decision was postponed until May 2004, just a few months before production start. A problem that arose was related to an accessory, a small tool that it used to loosen a screw in order to change needles, as the design prevented the use of this tool. The project manager concludes that although the machine itself was thoroughly checked, it seems as if it is difficult to include everything in the reviews. Additionally, there was an ambition to implement automatic feed teeth drop in the P11 project. Also in this case, technology development was conducted within the project. The mechanical design manager relates: Pre-development proceeded within the project, something that unfortunately is relatively common here. So it took quite a while before we were sure that we could use it and we took a large risk. But we had a back-up; we could use the old technology, but it would not have been without problems to switch back, because other components would have been affected. (…) We will never reach the ideal situation of having ready technologies, which we just can go and get from the shelf. In terms of software development, there is no formal separation between technology development (or platform development) and product development. In the P11 project a completely new software platform was developed. The software manager felt that the time pressure meant that short term solutions may have been preferred to more long term solutions. He further states that there was too much of research going on within the product development project; that the initial specifications were too fuzzy and that the specification continuously evolved during the course of the project. This made it very difficult to estimate time requirements and altogether it resulted in severe delays in the software development: When there is a poor hand-over from us to production, I would say that the reason is almost always time pressure, there is such hurry in the end and you cannot cope. My solution to that problem is to remove research from product development. Although there was an obvious software focus in the P11 project, the software manager feels that the development process and organisation is very much based on requirements from hardware development and particularly mechanics. For example, whereas it is fairly obvious what a critical design review means for mechanics, the implications are less clear for software development. The Product development/Production interface In terms of production the P11 machine was similar to Designer 1. Initially, the plan was to run two parallel assembly lines, but in the end it was decided to use the existing Designer 1 assembly line. Production engineers were involved in the hardware development team and the development project had recurrent meetings with production planners, but these were not included in the project organization. The initial plan was to start production in April 2004 but due to problems with the LED illumination and the late decision to replace the floppy with USB, production start was postponed until September 2004. 14 INTERFACE – Interfaces in Industrial Innovation Processes Because of late software, it was impossible to run the machine in order to verify the functionality. When the machine eventually could be run, it was discovered that the electronic circuit board was sensitive for ESD, i.e. the machine disturbed itself. This was discovered very late and resulted in a late design modification of the electronics. Five different preproduction series were scheduled, but the test series were squeezed together due to time constraints. This meant that the difference between consecutive test series became marginalthere were not sufficient time to learn from the previous series and implement changes. The time between two series was about 4 weeks, but at least 6 weeks were required to make modifications of tools. In the end only three separate pre-production series were run. Another problem was that the number of components available was insufficient to produce the planned number of machines. One particular component that caused problems in production was the lid. Originally the intention was to mould the window into the plastic cover, but this resulted in tensions which twisted the lid. So they were forced to mould the window separately and use ultra-sonic welding to attach it to the cover, something that had effects on the design. The lid was the last component to pass the final check. Lessons from the development project The P11 project is considered the largest development project ever at VSM and the R&D department grew considerably during the course of the project. This meant that much new personnel became involved and they did not have the background information which was required to understand various technological concepts and decision. This meant that demands on communication and learning were extraordinary in this project. Systems integration became a primary issue and particularly the integration between hardware and software. An important lesson is that systems integration has to be focused from the start; it cannot be solved at the end of the project. There seems to be a desire to make a clear distinction between technology development and product development at VSM. But at the same time it is not feasible to separate technology development fully from product development and conduct technology development and product development sequentially. This is because there is a continuous push towards innovation. To a certain extent it is necessary to embrace possibilities of implementing new technologies that may arise during the course of product development projects. Otherwise competitors will be first. The sliding specification was problematic, especially for software development; there seems to be a need to formalize software specification, development and testing. This is perhaps due to the fact that the software part of the development has grown considerably in a few years and the R&D processes, organizations and routines at VSM are still very much adapted to traditional requirements of mechanical design. One particular requirement of software engineering is the need for clarity in specifications. Another requirement is to devote sufficient time for verification and de-bugging. In contrast to mechanics and electronics, software technology development is not organisationally separated from product development. The implication is that technology development tends to be conducted within product development projects. This makes it difficult to predict software development lead times, which, in turn, may jeopardize the eventual deadline of the complete project. Furthermore, there is a risk that time pressure 15 INTERFACE – Interfaces in Industrial Innovation Processes means that short term and project specific solutions are preferred in favour of long term and more general solutions. With regards to the product development – production interface, a critical lesson from the project is to be cautious when compressing time between test series. To be able to implement changes between the test series, such as modifications of tools, a certain time slack is necessary. Group assignment Imagine yourself as management consultants who have been engaged by the VSM senior management to conduct a thorough review of the R&D department and its core processes. The senior managers have asked you to recommend measures to improve the efficiency and effectiveness of the organisation. In particular, they have encouraged “out-of-the-box thinking”, but the recommendations should nevertheless be founded in an analysis of the organisation’s current problems. The measures that you recommend may refer to changes of the product development process and its application, to routines for portfolio management and resource allocation, or to changes of the organisational structure of the R&D department. You will report your recommendations to the R&D director. 16