Heritage Impact Assessment of Stone Houses at Hau Wong Temple

Transcription

Heritage Impact Assessment of Stone Houses at Hau Wong Temple
2
CONSULTANCY FOR HERITAGE IMPACT ASSESSMENT FOR
REVITALIZATION OF THE STONE HOUSES AT JUNCTION ROAD,
KOWLOON CITY INTO STONE HOUSES FAMILY GARDEN
June 2011
Acknowledgements
We would like to acknowledge the permission given by the following organizations and person for
the use of their records, maps, photos and information in the report:
ƒ
Antiquities and Monuments Office
ƒ
Building Information Centre, Buildings Department
ƒ
Information Services Department
ƒ
The Land Registry
ƒ
Public Records Office
ƒ
Survey & Mapping Office, Lands Department
i
Research Team
Team Members
Position
Ho Puay-peng
Conservation specialist
MA(Hons), DipArch(Edin.), PhD(London), RIBA
Director, CAHR, CUHK
Director,, School of Architecture, CUHK
Honorary Professor, Department of Fine Art, CUHK
Lo Ka Yu Henry
Project Manager
BSSc(AS), MArch, MPhil(Arch), HKICON
Research Project Manager, CAHU, CUHK
Lam Sze Man Heidi
BA(History)
Research Assistant, CAHU, CUHK
ii
Researcher
TABLE OF CONTENTS
Consultancy for Heritage Impact Assessment for Revitalization of the Stone Houses at Junction
Road, Kowloon City into Stone Houses Family Garden ............................................................................... i
Acknowledgements......................................................................................................................................... i
Research Team............................................................................................................................................... ii
Table of Contents ................................................................................................................................ iii
List of Figures....................................................................................................................................... v
Introduction...................................................................................................................................... 1
1.1 Background.............................................................................................................................................. 1
1.2 Methodology ............................................................................................................................................ 1
Significance....................................................................................................................................... 3
2.1 Historic place ........................................................................................................................................... 3
2.1.1 Kowloon city in the 19th century ..................................................................................................... 3
2.1.2 Rural neighbourhood in the early 20th century ................................................................................ 8
2.1.3 Stone Houses built in the 1940s ..................................................................................................... 14
2.1.4 Hau Wong Temple New Village in the 1950s................................................................................ 18
2.1.5 Demolition of Cottage Areas in 2001............................................................................................. 20
2.1.6 Aerial photos .................................................................................................................................. 22
2.2 Heritage values....................................................................................................................................... 31
2.3 Character defining elements................................................................................................................... 31
2.3.1 External area .................................................................................................................................. 32
2.3.2 Internal area.................................................................................................................................... 34
2.3.3 Surroundings .................................................................................................................................. 35
Revitalization Proposal.................................................................................................................. 36
3.1 Project objectives ................................................................................................................................... 36
3.2 Proposed use .......................................................................................................................................... 36
3.3 User’s requirement................................................................................................................................. 37
3.4 Statutory requirement............................................................................................................................. 38
3.4.1 Planning and Land Requirement .................................................................................................... 38
3.4.2 Compliance with the Buildings Ordinance..................................................................................... 38
3.5 Condition of fabric ................................................................................................................................. 39
3.5.1 Description ..................................................................................................................................... 39
3.5.2 Structural Appraisal ....................................................................................................................... 40
3.5.3 Structural Survey............................................................................................................................ 40
3.5.4 Loading Assessment....................................................................................................................... 41
3.5.5 Recommendations .......................................................................................................................... 41
3.6 Proposed layout and setting ................................................................................................................... 42
3.6.1 Stone Houses No. 31 - 35............................................................................................................... 42
3.6.2 New Building 1 and 2..................................................................................................................... 42
iii
Assessment ......................................................................................................................................48
4.1 Conservation Principles.......................................................................................................................... 48
4.2 Potential Impact and mitigation measures.............................................................................................. 49
4.2.1 Definition of terms ......................................................................................................................... 49
4.2.2 Impact assessment .......................................................................................................................... 51
4.3 Interpretation .......................................................................................................................................... 60
Management and Implementation ................................................................................................62
5.1 Maintenance management plan .............................................................................................................. 62
5.2 Property management proposal .............................................................................................................. 63
5.3 Future development................................................................................................................................ 63
5.4 Documentation ....................................................................................................................................... 63
5.5 Financial resources................................................................................................................................. 64
5.6 Staffing and management structure ........................................................................................................ 64
5.7 Implementation programme ................................................................................................................... 64
Bibliography........................................................................................................................................66
Official Document........................................................................................................................................ 66
Books after 1911 .......................................................................................................................................... 66
Website ........................................................................................................................................................ 67
Newspaper.................................................................................................................................................... 67
Appendix I ...........................................................................................................................................68
Appendix II .........................................................................................................................................76
iv
LIST OF FIGURES
Fig. 1. Farmers in the field at Kowloon City in the early 20th century. (from Lau Yun Wo 劉潤和,
Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide to the Antiquities of Kowloon City District],
2005, p. 49.).............................................................................................................................................. 4
Fig. 2. Hau Wong Temple, Kowloon City, c. 1900. (from Zheng Baohong 鄭寶鴻, A Century of Kowloon
Roads and Streets, Hong Kong, Joint Publishing (Hong Kong) Company Limited, 2000, p. 146.)......... 5
Fig. 3. Hau Wong Temple in the 1930s. Pak Hok Shan was located at its back. (from Chiu Yu Lok 趙雨樂
and Chung Po Yin 鍾寶賢, Longchengleshan: zaoqi jiulongcheng yu leshantang yanjiu 龍城樂善: 早
期九龍城與樂善堂研究 [The Benevolent Society: A Study of the Early Kowloon City and Lok Sin
Tong], Hong Kong, Sunray Publishing Company Limited, 2000, p. 31.) ................................................ 5
Fig. 4. An annotated panoramic sketch of Kowloon City, 1845. (from Empson, Hal, Mapping Hong Kong: a
Historical Atlas, Hong Kong, Government Information Services, 1992, pp.130-131.)............................ 6
Fig. 5. Street scene in Kowloon Street in the early 20th century. (from Lau Yun Wo 劉潤和, Jiulongchengqu
fengwuzhi 九龍城區風物志 [A Guide to the Antiquities of Kowloon City District], 2005, p. 54.) ...... 6
Fig. 6. Kowloon Walled City, c. 1868. (from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風
物志 [A Guide to the Antiquities of Kowloon City District], 2005, p. 25.) ............................................ 7
Fig. 7. Kowloon Walled City in around 1920. (from Zheng Baohong 鄭寶鴻, A Century of Kowloon Roads
and Streets, Hong Kong, Joint Publishing (Hong Kong) Company Limited, 2000, p. 12.)...................... 7
Fig. 8. Longjin Bridge outside the Kowloon Street. Longjin Pavilion is located at the end of Longjin Bridge,
c. 1910. (from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide to the
Antiquities of Kowloon City District], 2005, p. 71.) ................................................................................ 8
Fig. 9. An old map of 1902-03 showing the building structure located to the northwest of Hau Wong Temple.
(from Empson, Hal, Mapping Hong Kong: a Historical Atlas, Hong Kong, Government Information
Services, 1992, p. 180.) ............................................................................................................................ 9
Fig. 10. An old map of 1922-1935 showing the layout of building located to the northwest of Hau Wong
Temple. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
survey sheet no.: CXXXVII-NE-6.) ....................................................................................................... 10
Fig. 11. The cemetery on Pak Hok Shan 白鶴山. It is seen that a chapel was built at the foot of the hill.
(from Zheng Baohong 鄭寶鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong, University
Museum and Art Gallery, The University of Hong Kong, 2007, p. 165.) .............................................. 10
Fig. 12. Street layout in Kowloon City, 1941. (from Zheng Baohong 鄭寶鴻, Early Hong Kong’s Kowloon
Peninsula, Hong Kong, University Museum and Art Gallery, The University of Hong Kong, 2007, p.
225.)........................................................................................................................................................ 11
Fig. 13. Tenement houses in Kowloon City, c.1930. (from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi
九龍城區風物志 [A Guide to the Antiquities of Kowloon City District], 2005, p. 130.)..................... 11
Fig. 14. Prince Edward Road West, 1939. Kowloon City Police Station located at the end of the road. (from
Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide to the Antiquities of
Kowloon City District], 2005, p. 130.) ................................................................................................... 12
Fig. 15. Context of Kowloon City district in the pre-war period. (Map of 1941) (from Zheng Baohong 鄭寶
鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong, University Museum and Art Gallery, The
University of Hong Kong, 2007, p. 225.) ............................................................................................... 13
Fig. 16. The scheme for extension of Kai Tak Airport, 1942. (from Lau Chi Pang 劉智鵬, Tunshengrennyu:
rizhishiqi Xianggangren de jitihuiyi 吞聲忍語: 日治時期香港人的集體回憶 [Quiet mouth: A
collective memory of Hong Kong people under the Japanese Occupation], Hong Kong, Chung Hwa
Book Co., 2009, p. 156.)......................................................................................................................... 15
v
Fig. 17. Two new runways in Kai Tak Airport, 1945. (from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi
九龍城區風物志 [A Guide to the Antiquities of Kowloon City District], 2005, p. 87.) .......................16
Fig. 18. An old map dated to 1953 showing the “Model Village” in Kowloon Tong, 1953. (from the Overseas
Chinese Daily News, 1953.) ....................................................................................................................16
Fig. 19. The “Model Village” in Kowloon Tong, 1966. (from Chiu Yu Lok 趙雨樂 and Chung Po Yin 鍾寶
賢, Longchengleshan: zaoqi jiulongcheng yu leshantang yanjiu 龍城樂善: 早期九龍城與樂善堂研究
[The Benevolent Society: A Study of the Early Kowloon City and Lok Sin Tong], Hong Kong, Sunray
Publishing Company Limited, 2000, p. 93.)............................................................................................17
Fig. 20. Squatter huts in the surroundings of Pak Hok Shan 白鶴山. (from Chiu Yu Lok 趙雨樂, Chung Po
Yin 鍾寶賢, Regional Study of Hong Kong History: Kowloon City, Hong Kong, Joint Publishing
(H.K.) Company Limited, 2001, p. 226.) ................................................................................................17
Fig. 21. Refugees poured over the Hong Kong-China border in the post-war period. (from Stephanie Holmes,
Asia’s Finest: An Illustrated account of the Royal Hong Kong Police, Hong Kong, Unicorn, 1983, p.
62.) ..........................................................................................................................................................18
Fig. 22. The squatter settlements grew up around Kowloon Walled City in the 1960s. (from Lau Yun Wo 劉
潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide to the Antiquities of Kowloon City
District], 2005, p. 42.) .............................................................................................................................19
Fig. 23. Old map of 1960 showing several film studios in the vicinity of the Stone Houses. (from Zheng
Baohong 鄭寶鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong, University Museum and Art
Gallery, The University of Hong Kong, 2007, p. 227.)...........................................................................19
Fig. 24. The building of former Cheung Shing Film Studio 長城片場 in Hau Wong Temple New Village,
subsequently converted into Kam Yuen Factory. (from Chiu Yu Lok 趙雨樂, Chung Po Yin 鍾寶賢,
Regional Study of Hong Kong History: Kowloon City, Hong Kong, Joint Publishing (H.K.) Company
Limited, 2001, p. 226.)............................................................................................................................20
Fig. 25. The Stone Houses at Nos. 31-35 Hau Wong Temple New Village, 2000. (from Tung Tau Cottage
Area, Retrieved 21 April, 2011 from hk-place, Web Site: http://www.hkplace.com/db.php?post=d002031.)..........................................................................................................21
Fig. 26. The Stone Houses at Nos. 31-35 Hau Wong Temple New Village, 2002. (from Tung Tau Cottage
Area, Retrieved 21 April, 2011 from hk-place, Web Site: http://www.hkplace.com/db.php?post=d002031.)..........................................................................................................21
Fig. 27. An aerial photo of 1945 showing the site of Stone Houses. (Courtesy of Survey and Mapping Office,
Lands Department, Hong Kong SAR Government, photo ref. no. 4115.) ..............................................22
Fig. 28. An aerial photo of 1949 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. 6089.) ................................................................................................................................23
Fig. 29. An aerial photo of 1956 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. 0100.) ................................................................................................................................24
Fig. 30. An aerial photo of 1967 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. 5167.) ................................................................................................................................25
Fig. 31. An aerial photo of 1976 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. 12195.) ..............................................................................................................................26
Fig. 32. An aerial photo of 1984 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. 56293.) ..............................................................................................................................27
Fig. 33. An aerial photo of 1993 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. CN3186.) ..........................................................................................................................28
vi
Fig. 34. An aerial photo of 2002 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. CW38065.) ....................................................................................................................... 29
Fig. 35. An aerial photo of 2010 showing the site of the Stone Houses at Nos. 31-35 Hau Wong Temple New
Village. (Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government,
photo ref. no. CS29709.)......................................................................................................................... 30
Fig. 36. Proposed Landscape Plan................................................................................................................... 43
Fig. 37. Proposed General Layout Plan........................................................................................................... 44
Fig. 38. Artistic impression of the Stone Houses Family Garden (1).............................................................. 45
Fig. 39. Artistic impression of the Stone Houses Family Garden (2).............................................................. 46
Fig. 40. Proposed walkway at the rear of the historic building. ...................................................................... 47
vii
1
INTRODUCTION
1.1 Background
The Advisory Committee on Revitalization of Historic Buildings (Advisory Committee) has
completed assessment of the proposals submitted for revitalizing the 5 historic buildings under
Batch II of the Revitalizing Historic Buildings Through Partnership Scheme (Revitalization
Scheme). The Secretary for Development has accepted the Advisory Committee’s recommendation
and given the approval-in-principle to the selected non-profit-making organizations in September
2010.
The selected organization for the Stone Houses at Junction Road is Wing Kwong So-Care
Company Limited, the social service arm of Wing Kwong Pentecostal Holiness Church, specialized
in youth program and community services. Stone Houses and its site will be revitalized as a “石屋
家園” (Stone Houses Family Garden) including a themed cafeteria-cum-Visitor Information
Centre.
Stone houses were accorded as Grade 3 Historic Building by Antiquity and Advisory Board
in May 2010. Following the recommendation of Chief Executive in the 2007-2008 Policy Address
and the corresponding Technical Circular (Works) No. 6/2009 of Development Bureau, in order to
fully implement heritage conservation, it is required that all public works projects involving
historic built heritages and sites to undergo Heritage Impact Assessment (HIA).
The aim of this HIA report is to assess the impacts on the historic fabrics of Stone Houses at
Junction Road arising from the implementation of proposed project so that adverse impacts could
be avoided or minimized with appropriate mitigation measures.
1.2 Methodology
This Heritage Impact Assessment (HIA) report is prepared based on the Conservation Guidelines
drawn by Antiquities and Monuments Office in the Resource Kit for the Stone Houses under the
1
Revitalization Scheme, the Guidance Note to HIA Submission for the Revitalisation Scheme,
Technical Circular (Works) No. 06/2009 of Development Bureau, preliminary site inspections and
desktop research.
International charters and standards are followed in this study report:
ƒ
James Semple Kerr, The Conservation Plan, Australian National Trust, 1996.
ƒ
Burra Charter: the Australia ICOMOS Charter for Places of Cultural Significance,
Australia ICOMOS Incorporated, 2000.
ƒ
Neville Agnew and Martha Demas edited, Principles for the Conservation of Heritage
Sites in China, The Getty Conservation Institute, 2002.
2
2
SIGNIFICANCE
2.1 Historic place
Stone Houses, formerly the Nos. 31-35 at Hau Wong Temple New Village, were a row of Chinese
styled built of granite masonry walls and tiled timber roof at the foot of Pak Hok Shan 白鶴山 in
the late 1940s.
2.1.1 Kowloon city in the 19th century
In the early 19th century, the present-day Kowloon City was a rural district where small villages,
including Kau Lung Tsai 九龍仔, Ma Tau Chung 馬頭涌, Nga Tsin Long 衙前塱 and Ta Ku
Ling 打鼓嶺 scattered among vast area of farmland1 (Fig. 1)
Located to the southwest of Pak Hok Shan 白鶴山 is a temple dedicated to Hau Wong 侯
王 was built by the locals in the 8th year of Yongzheng 雍正 era in the Qing Dynasty (1730).
(Fig. 2 and Fig. 3) It is commonly said that Hau Wong refers to general Yeung Leung Jit 楊亮節
of Southern Sung Dynasty (1127-1279). He accompanied the young Sung emperor to fight against
the Mongol invaders. Another local legend tells that the temple was built to commemorate a
villager surnamed Yeung who cured Duanzong 端宗 when the Sung royal family fled to Kowloon
City. The inscription on a stele commemorating the renovation in 1822 found inside the temple
described the natural beauty of neighbourhood area. It reads,
松風繞韻, 潤水流香
Wind whispers melodiously through the pines, and streams flow with fragrance.
1 Wong Chongxi 王崇熙, Xin’an xianzhi 新安縣志 [Xin’an County Gazetteer], 1819, see edition in Hong Kong, s.n.,
1979, p. 35 and Map of the Sun-On-District, 1868 as cited in Empson, Hal, Mapping Hong Kong: a Historical Atlas,
Hong Kong, Government Information Services, 1992, pp. 114-115.
3
As seen on a sketch dated to 1845, there was a prosperous market place known as Kowloon
Street stretched from the water front of Kowloon Bay toward Pak Hok Shan. (Fig. 4) Before
starting a long journey to China, merchant boats temporarily anchored off Kowloon City for
replenishing their supplements. The main market streets are constructed of stone blocks with two
storey shops aligned on both sides. (Fig. 5)
After Hong Kong Island had been captured by the British in 1841, the Qing Government
urged to strengthen defence in the Kowloon Peninsula. A garrison known as Kowloon Walled City
was established to the south of Pak Hok Shan 白鶴山 in 1847. (Fig. 6 and Fig. 7) Guarded by six
watchtowers cannons and high walls, the Walled City where 150 soldiers were stationed was
commanded by Deputy Commodore of the Dapeng Brigade 大鵬協水師副將.
In the 12th year of Tongzhi 同治 era (1873) when the Kowloon Street became porsperious,
a landing pier known as Longjin Bridge 龍津橋 was built by the Qing officers and merchants to
facilitate the morring of increasing number of merchant boats among the shallow water in the bay.
(Fig. 8) Constructed by granite slabs spanning on two pillars at each segment, the stone bridge
originally measured about 213 metres long and 2 metre wide.
Fig. 1. Farmers in the field at Kowloon City in the early 20th century.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 49.)
4
Fig. 2. Hau Wong Temple, Kowloon City, c. 1900.
(from Zheng Baohong 鄭寶鴻, A Century of Kowloon Roads and Streets, Hong Kong,
Joint Publishing (Hong Kong) Company Limited, 2000, p. 146.)
Fig. 3. Hau Wong Temple in the 1930s. Pak Hok Shan was located at its back.
(from Chiu Yu Lok 趙雨樂 and Chung Po Yin 鍾寶賢, Longchengleshan: zaoqi
jiulongcheng yu leshantang yanjiu 龍城樂善: 早期九龍城與樂善堂研究 [The
Benevolent Society: A Study of the Early Kowloon City and Lok Sin Tong], Hong
Kong, Sunray Publishing Company Limited, 2000, p. 31.)
5
Pak Hok Shan
Market place,
known as
Kowloon Street
Fig. 4. An annotated panoramic sketch of Kowloon City, 1845.
(from Empson, Hal, Mapping Hong Kong: a Historical Atlas, Hong Kong,
Government Information Services, 1992, pp.130-131.)
Fig. 5. Street scene in Kowloon Street in the early 20th century.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 54.)
6
Fig. 6. Kowloon Walled City, c. 1868.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 25.)
Fig. 7. Kowloon Walled City in around 1920.
(from Zheng Baohong 鄭寶鴻, A Century of Kowloon Roads and Streets, Hong Kong,
Joint Publishing (Hong Kong) Company Limited, 2000, p. 12.)
7
Fig. 8. Longjin Bridge outside the Kowloon Street. Longjin Pavilion is located at the
end of Longjin Bridge, c. 1910.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 71.)
2.1.2 Rural neighbourhood in the early 20th century
Although the area of Kowloon City was leased as part of the New Territories to the British in 1899,
the district was not developed by the colonial government and merchants until the early 1920s.
It is seen on a map dated to 1902-03 that the area where Stone Houses now located was still
a sparsely populated rural neighborhood. (Fig. 9) Among which are only Hau Wong Temple and
probably some building structures located to its immediate northwest. Standing approximately at
the same site as present-day Stone Houses, these buildings were also shown on maps dated to the
20s and 30s. (Fig. 10) According to the Government Lease dated to 1st July 1898, this piece of land
within land lot 6264 in Special District (S.D.) 1, where the buildings stood, was owned by Ho To
Shing. It is likely that they are two rows of small village houses placed side by side. Collated with
descriptions on newspaper in the 30s, they might be one of the two villages in this locality, known
as Ho Ka Tsuen 何 家 村 , literately Ho’s village, where a few households were lived. 2
Subsequently, this land lot was sold to Mr. Choy Wai Hung, who eventually handed back the land
to Government in 1932.3
Located to the northeast of Stone Houses is a cemetery established on Pak Hok Shan in the
1920s, which is now known as the Hong Kong Chinese Christian Churches Union Chinese
Christian Cemetery, Kowloon. (Fig. 11)
2 Wong Puikai 黃佩佳, Xianggang Xinjie fengtu mingsheng daguan jianbaoji 香港新界風土名勝大觀剪報集
[Collection of newspaper cutting on the scenery and social customs and sights in Hong Kong New Territories], ca.
1930s, p. 136.
3 Hong Kong Public Records Office, N.K.I.L.No.1748-Grant of an Area in Exchange for Lots Nos. 576 and 6264, R.P.,
S.D.I.01.12.1931-19.12.1936, Reference File HKRS 58-1-171-56 from Hong Kong Public Records Office, Hong Kong
SAR Government, p. 1.
8
In 1926, Kowloon Street and several villages in the surroundings of Kowloon Walled City
were demolished to make way for the construction of new roads and streets. (Fig. 12) Grampian
Road 嘉林邊道, Junction Road 聯合道, Fuk Lo Tsun Road 福老村道, Lion Rock Road 獅子石
道, Hau Wong Road 侯王道, Nga Tsin Long Road 衙前塱道, Nam Kok Road 南角路, Lung
Kong Road 龍崗道, South Wall Road 城南道, Tak Ku Ling Road 打鼓嶺道, Po Kong Road 寶
崗道, Sa Po Road 沙埔道, Shek Ku Lung Road 石鼓壟道, Hak Hang Tsum Road 隔坑村道 and
Nga Tsin Wai Road 衙前圍道 were laid during the late 1920s and early 1930s.
Since the 1910s, the warlordism in Mainland led to massive flows of refugees into Hong
Kong. The population of Kowloon Peninsula rocketed from 69,703 to 264,675 in 1931. Soon after
the new roads had been completed in Kowloon City, tenement houses of 3-4 storey mushroomed
all over the newly developed area, providing accommodations for these newcomers. (Fig. 13 and
Fig. 14) On the other hand, low density European flats for the well-off class were built along
Grampian Road and Junction Road around 1930.
In 1939, the new campus of Munsang College was constructed at No. 8 Dumbarton Road.
The new school building consisted of a hall and 12 classrooms to cope with the increasing number
of students.4
Hau Wong
Temple
Fig. 9. An old map of 1902-03 showing the building structure located to the
northwest of Hau Wong Temple.
(from Empson, Hal, Mapping Hong Kong: a Historical Atlas, Hong Kong,
Government Information Services, 1992, p. 180.)
4
See
About
Munsang.
Retrieved
May
13,
2009,
http://munsang.edu.hk/secondary/about_munsang/history.php.
from
Munsang
School,
Web
Site:
9
Approximate
footprint of the
Stone Houses
Hau Wong
Temple
Fig. 10. An old map of 1922-1935 showing the layout of building located to the
northwest of Hau Wong Temple.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, survey sheet no.: CXXXVII-NE-6.)
Fig. 11. The cemetery on Pak Hok Shan 白鶴山. It is seen that a chapel was built at
the foot of the hill.
(from Zheng Baohong 鄭寶鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong,
University Museum and Art Gallery, The University of Hong Kong, 2007, p. 165.)
10
Approximate
location of
Stone Houses
Fig. 12. Street layout in Kowloon City, 1941.
(from Zheng Baohong 鄭寶鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong,
University Museum and Art Gallery, The University of Hong Kong, 2007, p. 225.)
Fig. 13. Tenement houses in Kowloon City, c.1930.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 130.)
11
Fig. 14. Prince Edward Road West, 1939.
Kowloon City Police Station located at the end of the road.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 130.)
12
Approximate
location of
Stone Houses
Cemetery
Kai Tak Bund 啟德濱
Kai Tak Airport
Fig. 15. Context of Kowloon City district in the pre-war period. (Map of 1941)
(from Zheng Baohong 鄭寶鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong, University Museum and Art Gallery, The University of Hong Kong,
2007, p. 225.)
13
2.1.3 Stone Houses built in the 1940s
A few years after Kowloon Peninsula was captured on 12th December 1941, Japanese decided to
expand Kai Tak Airport to establish an air base in Hong Kong.5 (Fig. 16) Over 24 villages
originally located to the north of the airport were torn down to make way for the new construction
in June 1942. Around 70,000 villagers were relocated to other places in Hong Kong or repatriated
to the Mainland.6 The construction for the extension of airport started in September 1942 and was
completed in 1945. (Fig. 17)
On 30th June, 1942, the Japanese authority announced to build so-called “Model Village” in
Kowloon Tong and Sheung Shui to rehouse residents who lost their home.7 (Fig. 18 and Fig. 19)
These two settlements could accommodate around only 1,000 people.8 A piece of land at today’s
Renfrew Road in Kowloon Tong was allocated to build 120 houses for the resettlement.9 Each
household was also given a piece of farmland of three acres (around 2,001 square meters) to
cultivate crops for living. This area was very close to the Stone Houses area. Thus, it is very likely
that the Japanese would treat the area along Junction Road as the easternmost part of the
resettlement district. It is also said that about 20 small cottages were built by the Japanese along
present-day Junction Road between the cemetery and Hau Wong Temple.
After the Japanese Occupation, the Stone Houses area was soon occupied by squatter
settlements where cottages were built for those newcomers fleeing the civil war in China, and
known as Hau Wong Temple New Village. (Fig. 20 and Fig. 21) Close to it are places still called
Ho Ka Yuen and Lai Chi Yuen to the south and north on the same side of Junction Road, where
cottages were gradually constructed.
As seen in the aerial photo dated to 1945, it is likely that the footprint of Ho Ka Tsuen was
still occupied by structures with similar profile as before, probably the original village houses in a
dilapidated state. (Fig. 27) However, Stone Houses as we seen day, a row of five units having a
different layout and orientation, was clearly shown on an aerial photo of 1949. (Fig. 28)
5 九龍模範村始末 [The origin of Model Villages in Kowloon], Ta Kung Pao, 30th July, 1948.
6 九龍模範村始末 [The origin of Model Villages in Kowloon], Ta Kung Pao, 30th July, 1948 and Cheng Po Hung 鄭
寶鴻, Hong Kong During the Japanese Occupation, Hong Kong, University Museum and Art Gallery, The University
of Hong Kong, 2006, p. 80.
7 Cheng Po Hung 鄭寶鴻, Hong Kong During the Japanese Occupation, Hong Kong, University Museum and Art
Gallery, The University of Hong Kong, 2006, p. 84.
8 Ibid., p. 84.
9 九龍模範村始末 [The origin of Model Villages in Kowloon], Ta Kung Pao, 30th July, 1948 and Ko Tim-keung, “二
次大戰與啟德機場 [The Second World War and Kai Tak Airport]”as cited in Chiu Yu Lok 趙雨樂, Chung Po Yin
鍾寶賢, Regional Study of Hong Kong History: Kowloon City, Hong Kong, Joint Publishing (H.K.) Company Limited,
2001, p. 198 and Chiu Yu Lok 趙雨樂, Chung Po Yin 鍾寶賢, Regional Study of Hong Kong History: Kowloon City,
Hong Kong, Joint Publishing (H.K.) Company Limited, 2001, p. 225.
14
On the other hand, Mrs. Lau Li 劉理, the owner of No. 31 at Hau Wong Temple New
Village in 1957, made an appeal to the Colonial Secretariat for keeping her premises despite the
construction of the new Junction Road.10 Lau claimed that she had spent all her savings on the
building and furniture in 10 years’ living there. Having collated these information, it is very likely
that the Stone Houses were built between 1945 and 1947.
Fig. 16. The scheme for extension of Kai Tak Airport, 1942.
(from Lau Chi Pang 劉智鵬, Tunshengrennyu: rizhishiqi Xianggangren de jitihuiyi
吞聲忍語: 日治時期香港人的集體回憶 [Quiet mouth: A collective memory of Hong
Kong people under the Japanese Occupation], Hong Kong, Chung Hwa Book Co.,
2009, p. 156.)
10 Hong Kong Public Records Office, Crown Land Near Hau Wong Temple Kowloon - Clearance of Structures on - for
Road Widening, 20.05.1957-30.07.1957, Reference File HKRS 156-1-5864 from Hong Kong Public Records Office,
Hong Kong SAR Government, p. 2.
15
Fig. 17. Two new runways in Kai Tak Airport, 1945.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 87.)
Model Village
Hau Wong
Temple
Fig. 18. An old map dated to 1953 showing the “Model Village” in Kowloon Tong,
1953.
(from the Overseas Chinese Daily News, 1953.)
16
Fig. 19. The “Model Village” in Kowloon Tong, 1966.
(from Chiu Yu Lok 趙雨樂 and Chung Po Yin 鍾寶賢, Longchengleshan: zaoqi
jiulongcheng yu leshantang yanjiu 龍城樂善: 早期九龍城與樂善堂研究 [The
Benevolent Society: A Study of the Early Kowloon City and Lok Sin Tong], Hong
Kong, Sunray Publishing Company Limited, 2000, p. 93.)
Fig. 20. Squatter huts in the surroundings of Pak Hok Shan 白鶴山.
(from Chiu Yu Lok 趙雨樂, Chung Po Yin 鍾寶賢, Regional Study of Hong Kong
History: Kowloon City, Hong Kong, Joint Publishing (H.K.) Company Limited, 2001,
p. 226.)
17
Fig. 21. Refugees poured over the Hong Kong-China border in the post-war period.
(from Stephanie Holmes, Asia’s Finest: An Illustrated account of the Royal Hong
Kong Police, Hong Kong, Unicorn, 1983, p. 62.)
2.1.4 Hau Wong Temple New Village in the 1950s
In 1951, the Hong Kong Government decided to delineate some areas in which squatters could
build cottages made of fire-resisting materials. The Hong Kong Settlers Housing Corporation was
established in the following year to manage the construction of cottages. Blocks of cottages to the
east of Stone Houses was incorporated into Tung Tau Cottage Area in 1952, where included Pok
Oi Tsuen 博愛村, Pui Man Tsuen 培民村, Tung Wo Tsuen 東和村 and Chiu Ping San Tsuen
潮平新村.
In the late 1940s and 1950s, several film studios were established in the vicinity of Stone
Houses. Sai Kwong Film Studio 世光片場 was located in Ho Ka Yuen11 adjacent to Yau Kiu
Film Studio 友僑片場, which were both combined later into Great Wall Film Production
Companies 長城電影製片公司 operated in the Hau Wong Temple New Village. (Fig. 23 and Fig.
24) Famous actors, such as Chan Po Chu 陳寶珠, Siu Fong Fong 蕭芳芳 and Fung Po Po 馮寶
寶 once worked in these film studios.12
11 Chung Po Yin 鍾寶賢, Xianggang yingshiye bainian 香港影視業百年 A Century of Hong Kong’s Movies and
Television Boardcasting Industry, Hong Kong, Joint Publishing (H.K.) Company Limited, 2004, p. 128.
12 Antiquities and Monuments Office, Historic Building Appraisal – No. 31-35 Hau Wong Temple New Village,Kowloon
City, items 949.
18
Fig. 22. The squatter settlements grew up around Kowloon Walled City in the 1960s.
(from Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide
to the Antiquities of Kowloon City District], 2005, p. 42.)
Great Wall
Film Studio
Stone Houses
Tze Yau Film
Studio
Kwok Ka Film
Studio
Fig. 23. Old map of 1960 showing several film studios in the vicinity of the Stone
Houses.
(from Zheng Baohong 鄭寶鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong,
University Museum and Art Gallery, The University of Hong Kong, 2007, p. 227.)
19
Fig. 24. The building of former Cheung Shing Film Studio 長城片場 in Hau Wong
Temple New Village, subsequently converted into Kam Yuen Factory.
(from Chiu Yu Lok 趙雨樂, Chung Po Yin 鍾寶賢, Regional Study of Hong Kong
History: Kowloon City, Hong Kong, Joint Publishing (H.K.) Company Limited, 2001,
p. 226.)
2.1.5 Demolition of Cottage Areas in 2001
Except Stone Houses at No.31- 35, the cottages built in Hau Wong Temple New Village, Ho Ka
Yuen, and Lai Chi Yuen as well as Tung Tau Cottage Area were cleared by the Housing Authority
for new development in 2001.
20
Stone Houses
Fig. 25. The Stone Houses at Nos. 31-35 Hau Wong Temple New Village, 2000.
(from Tung Tau Cottage Area, Retrieved 21 April, 2011 from hk-place, Web Site:
http://www.hk-place.com/db.php?post=d002031.)
Stone Houses
Fig. 26. The Stone Houses at Nos. 31-35 Hau Wong Temple New Village, 2002.
(from Tung Tau Cottage Area, Retrieved 21 April, 2011 from hk-place, Web Site:
http://www.hk-place.com/db.php?post=d002031.)
21
2.1.6 Aerial photos
Cemetery
Hau Wong
Temple
Munsang
College
Fig. 27. An aerial photo of 1945 showing the site of Stone Houses.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. 4115.)
22
Cemetery
Stone
Houses
Hau Wong
Temple
Munsang
College
Fig. 28. An aerial photo of 1949 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. 6089.)
23
Lai Chi Yuen
Cemetery
Ho Ka Yuen
Stone
Houses
Tung Tau
Cottage Area
Hau Wong Temple
New Village
Munsang
College
Hau Wong
Temple
Fig. 29. An aerial photo of 1956 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. 0100.)
24
Lai Chi Yuen
Cemetery
Ho Ka Yuen
Stone
Houses
Hau Wong Temple
New Village
Tung Tau
Cottage Area
Munsang
College
Hau Wong
Temple
Fig. 30. An aerial photo of 1967 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. 5167.)
25
Lai Chi Yuen
Cemetery
Ho Ka Yuen
Stone
Houses
Tung Tau
Cottage Area
Hau Wong Temple
New Village
Munsang
College
Hau Wong
Temple
Fig. 31. An aerial photo of 1976 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. 12195.)
26
Lai Chi Yuen
Cemetery
Ho Ka Yuen
Stone
Houses
Tung Tau
Cottage Area
Hau Wong Temple
New Village
Munsang
College
Hau Wong
Temple
Fig. 32. An aerial photo of 1984 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. 56293.)
27
Lai Chi Yuen
Cemetery
Ho Ka Yuen
Stone
Houses
Tung Tau
Cottage Area
Hau Wong Temple
New Village
Munsang
College
Hau Wong
Temple
Fig. 33. An aerial photo of 1993 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. CN3186.)
28
Cemetery
Stone
Houses
Hau Wong
Temple
Munsang
College
Fig. 34. An aerial photo of 2002 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. CW38065.)
29
Hong Kong
School of
Creativity
Cemetery
Stone
Houses
Hau Wong
Temple
Munsang
College
Fig. 35. An aerial photo of 2010 showing the site of the Stone Houses at Nos. 31-35
Hau Wong Temple New Village.
(Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR
Government, photo ref. no. CS29709.)
30
2.2 Heritage values
The Stone Houses at Nos. 31-35 Hau Wong Temple New Village are a row of residential units. In
view of their structural integrity, this row of houses should be viewed as a single building
consisting of five units of accommodation, each being separated by internal walls.
Architecturally, this row of units can be read as Chinese-styled cottage building. The frontal
part of the building is two storey and covered with a pitched-roof, while backyard with kitchen and
toilet enclosed by masonry walls was constructed at the rear of each units. The walls of entire
building, which are constructed of granite blocks, support the pitched roof built by timber battens
resting on purlins and covered with Chinese clay tiles. On the granite walls are rectangular timber
framed windows with glazing. The main door to each living unit is in Chinese styled construction
with timber panels, timber locks and granite sockets. Upper floor is formed by timber flooring
supported by timber joists and reinforced concrete beams resting on granite masonry walls. The
stair leading to upper floor is also in timber construction consisting of timber treads and risers
supported on beams, as well as railings. Despite that the architecture of Stone Houses is humble
and ordinary, from which we could have a glimpse of architectural style and construction
commonly found in the 40s.
The significance of the Stone Houses also lies in its linkage to the historic evolution of the
neighborhood area and Kowloon city district at different period of time: It was once part of the
squatter area in the district where cottages were built for those newcomers fleeing the civil war in
China in the 1940s. Later, the film industry boomed in the area where numerous film studios were
established in the late 1940s and 1950s.
2.3 Character defining elements
The principal character defining elements are listed below, which means the materials, forms,
location, spatial configurations, uses and cultural associations or meanings that contribute to the
heritage value of a historic place, and which must be retained in order to preserve its heritage
value13.
13 Definition extracted from Parks Canada Standards and Guidelines for the Conservation of Historic Places in
Canada. Retrieved on December 15, from Parks Canada under Her Majesty the Queen in Right of Canada, Website:
http://www.pc.gc.ca/docs/pc/guide/nldclpc-sgchpc/index_e.asp.
31
2.3.1 External area
item
E-1
Rectangular
massing formed
by a row of
building blocks
E-2
Original
building form
and spatial
layout
E-3
Signage marked
with Chinese
character “藍恩
記” (Lam Yan
Kee) at House
No. 31
E-4
Masonry walls
E-5
Chinese styled
pitched roof laid
with pan and
roll tiles
32
image
location
E-6
Gable walls with
hanging ridge
and moulding
E-7
Door openings
with concrete
lintel, plastered
surround,
Chinese styled
timber doors
with timber
locks and
granite socket,
and metal
sliding Bostwick
gates
E-8
Window
openings with
concrete lintels
and timber
framed windows
on front and side
elevations
E-9
Old metal mail
boxes
33
2.3.2 Internal area
item
I-1
Original spatial
layout
I-2
Internal walls
I-3
Timber flooring
of upper floor
including timer
planking
supported on
timber joists
I-4
Timber staircase
with railings and
balustrades, and
the last few
steps
I-5
Kitchen with
original stoves
at No. 32
34
Image
location
I-6
Timber battens
and purlins at
roof
2.3.3 Surroundings
item
S-1
Mature trees
S-2
Open space in
front
image
location
35
3
REVITALIZATION PROPOSAL
3.1 Project objectives
Wing Kwong So-Care Company Limited is planning to adaptive re-use the Stone Houses and its
site as a “石屋家園” (Stone Houses Family Garden) with objectives as follows:
ƒ
To achieve conservation goal by restoring the Stone Houses into its original look and revitalise
the “Ho Ka Yuen” site while adding carefully constructed facilities and green elements to
convey a new spirit to the site;
ƒ
To promote the values treasured by the last generation to the youth through creative activities,
programmes and events hosted in the site and an understanding of the changing context of the
district.
3.2 Proposed use
Wing Kwong So-Care Company Limited is to establish a themed cafeteria-cum-Visitor
Information Centre with a view to:
ƒ
Operating a themed cafe in part of the Stone Houses in the form of social enterprise to provide
full time and part-time jobs and training opportunities to the underprivileged, specifically to
meet the demand of youth group; and
ƒ
Turning the site into a youth hub and developing positive impact by offering ancillary services
such as organising experiential training courses, alternative tours and providing facilities like
the Interpretation Centre, labyrinth and open theatre.
36
3.3 User’s requirement
ƒ
Strive to preserve the architectural features of the Stone Houses, such as the wooden structures,
stone walls, pyramid roof, wooden door locks, etc. which helps to reflect the building
characteristics of Hong Kong during the Second World War and substantially convey that part
of the history to new generations;
ƒ
Convert Unit 32 into an Interpretation Centre for educational purpose, as the facilities at the
rear annex (i.e., the kitchen and chimney) are generally kept intact and the wooden floor
structure are in relatively good condition. Old-fashioned furniture will be placed in the restored
unit to reconstruct the reminiscent atmosphere;
ƒ
Keep the wooden stairs and platform in Unit 32 and provide structural strengthening works at
the same time to meet statutory requirements.
ƒ
Strengthen the wooden floor plates of other units by steel structures and provide minimum
interior fitting out works. The wooden surfaces of stairs in other units will be kept but
supported by new steel structures.
ƒ
Bring a unique and incomparable reminiscence to the visitors as the themed cafe is located
right at the historic site of the Stone Houses and is literally nostalgic;
ƒ
Adopt a Labyrinth to form the surface pattern of the open space outside the Stone Houses
which is based on an aerial photo taken for exactly the same location in 1964. The outline of
the site is blended with labyrinth design in which people can have a meditative stroll.
ƒ
Construct a new building adjacent to the existing Stone Houses which compose of a multipurpose room and toilets in order to cater for the functional needs and sustainable development.
ƒ
Construct a new building to house the new fire services installation for adaptive reuse of the
historic buildings.
ƒ
Adopt a simple structure for the new building so that it will not overshadow the existing Stone
Houses. The old and new will be blended in unity.
ƒ
Provide the exterior landscape with a theme of “home” and capture elements of history and
culture. The tone is chiefly natural and simple.
ƒ
Build concrete steps along the open lawn on restored planters; keep the existing trees and
create more greenery to attract patronage and bring to the community a backyard garden.
37
3.4 Statutory requirement
3.4.1 Planning and Land Requirement
The site is zoned “Open Space” (“O”) on the Kowloon Tong Outline Zoning Plan (OZP) No.
S/K18/16 approved on 8 December 2009. The proposed use of the buildings may be regarded as
“Place of Recreation, Sports or Cultural under Columns 2 of the OZP. A Section 16 planning
application may be required to submit to the Town Planning Board (TPB) for the proposed use.
3.4.2 Compliance with the Buildings Ordinance
3.4.2.1 Means of Escape
ƒ
The existing double leaf doors having curbs and possible sub-standard width at the
main entrance at ground floor might not meet current MOE requirement.
ƒ
The existing timber staircase leading from ground floor to the first floor could not
satisfy current fire safety requirement.
ƒ
New external staircase connecting to the first floor shall be proposed as the means of
escape.
3.4.2.2 Means of Access for Fire Fighting & Rescue
ƒ
There is no Emergency Vehicular access (EVA) for the building. Provision of EVA
shall be complied with. Necessary means of access shall be provided.
3.4.2.3 Fire Resisting Construction
ƒ
Fire engineering study may be required to demonstrate fire safety for the existing
timber structures.
ƒ
Subject to detailed study, fire rated glass might be required to be installed to existing
timber windows.
3.4.2.4 Barrier free access
ƒ
There is no barrier free access connected from the ground floor to the first floor. An
addition of a disabled lift shall be required to comply with current building regulation.
3.4.2.5 Fire Services Installation
ƒ
There is currently no fire service provision at the Stone Houses, such as wet Fire
Protection System (i.e. F.H./HR & Sprinkler System), manual fire alarm (MFA), visual
38
fire alarm and automatic fire alarm system (AFA), exit sign / emergency lights found in
the building.
ƒ
Additional fire service installation for the new use, including sprinkler system, hose
reel system, fire alarm system, emergency back-up power supply, etc, shall be installed
to meet current requirement, subject to approval and consideration of exemption or
modification by the authority.
3.4.2.6 Sanitary fitment provisions
ƒ
The present sanitary fitments provision seems inadequate. New toilets, including
disable toilets, shall be provided to comply with the statutory requirements.
3.5 Condition of fabric
3.5.1 Description
The external load bearing walls and the internal party walls are constructed of granite blocks,
jointed with cement sand mortar and rendered with plaster on the interior.
There are concrete
lintels above the door and window openings.
The ground floor is of 50mm thick cement/sand screeding paved with floor tiles. The 1/F is
constructed of softwood floor planks laid on timber joists.
They are supported by either timber
beams or concrete beams or rested on the masonry wall at the ends. There is a timber trimmer joist
along the staircase void. The trimmer joist is quite small in size and is spanning between the front
masonry wall and an r.c. beam across the centre of the unit.
The pitched roof consists of Chinese clay tiles laid on timber battens supported over timber
log joists.
The timber logs are spread across the sloping roof and built into the masonry walls at
each side with a header thickening likely of masonry block.
The lower 3 or 4 risers of the staircase are either of timber or mass concrete construction.
The rest are of timber with wooden treads and risers built over two stringer beams on each side.
The balustrade and railing of the staircase are also of timber construction.
Later additions to the original building include:
ƒ
Decking over the rear court of some units to extend their 1/F and enclose them with
metal sheeting; and
ƒ
Adding corrugated metal cover on light steel frame above the pitched roof areas as rain
shelters at units 31, 32, 34 and 35.
39
3.5.2 Structural Appraisal
ƒ
On the front elevation, the continuous reinforced concrete projecting feature above the 1/F
windows are dilapidated and some portion has fallen off.
ƒ
There are signs of dampness at the lower portion of some external walls. The dark colour
jointing mortar indicates insufficient damp proof treatment.
ƒ
The existing stone masonry walls are of fair condition.
The exterior masonry wall has some
open joints showing weathering and softening of mortar at localized areas.
Repointing is
required to prevent water ingress. There are a few rotten wooden window frames with gaps
along the wall opening.
ƒ
They are to be replaced and made good with waterproofing grouting.
One of the timber roof joists collapsed and the joists adjacent to it are in the danger of
collapsing at unit No. 33.
In view of signs of serious water leakage to most of the roof soffit
and rots on roof joists are observed, it is anticipated that there are detached and loosen roof
tiles with defective bedding, resulting rain penetration and dilapidation of the roof structure.
ƒ
Some reinforced concrete beams on 1/F are found with spalling concrete with exposed rusty
bars at the soffit.
ƒ
The external wall of No. 31, which is adjacent to Junction Road, is a retaining wall. The soil
retaining height is about 1.2m.
Also, problems of water leakage, water-ponding and surface
water drainage around the building is evident during rainfall.
ƒ
There are trees adhere to and growing on the rear masonry fence walls of Nos. 31, 32 and 35.
The continuous tree growth will render the walls unstable.
3.5.3 Structural Survey
In the previous structural survey completed by Architectural Services Departmental (ArchSD) in
2009, visual inspections, in-situ and laboratory tests have been carried out with a view to
ascertaining the material, layout, condition and strength of the existing structural members.
It was found that the structural members in the main portion (i.e. the part of building under
the pitched roof) are in poor condition.
concrete members.
Firstly, severe corrosion was noticed in some reinforced
The concrete was also found carbonated and having low strength.
a number of timber joists were found to have severe fissures.
Secondly,
It is recommended to repair and
replace members with defects for the adaptive re-use.
The stone walls are found on fill material, with or without foundation stone.
Out of the
seven inspection pits, only one has revealed loose fill, others are on dense fill substrate.
water is not encountered.
40
Ground
3.5.4 Loading Assessment
ƒ
The capacities of the structural members were investigated based on the test data obtained
during the previous structural survey.
ƒ
The existing reinforced concrete beams are of inadequate strength, they can be recast or
strengthened by addition of steel beams.
ƒ
The masonry stone walls are structurally adequate for the adaptive reuse.
Since the
foundation construction does not satisfy current safety standard, any addition of load should be
avoid.
This can be achieved by adding steel posts supported on new footings to share the
additional loadings.
ƒ
The existing timber staircase can be upgraded by adding a secondary supporting frame beneath
and adding/replacing the railings by either glass panels or metal railing.
ƒ
The roof can also be repaired by replacing the dilapidated battens and purlins and relaying the
missing pan and roll tiles.
3.5.5 Recommendations
ƒ
A more detailed and comprehensive structural investigation is to be conducted to record the
current conditions and to identify the defective elements for repair, replacement or
strengthening.
ƒ
The results will be incorporated into the detailed design.
A comprehensive restoration plan should be prepared to reinstate all other defective roof.
Appropriate repair and treatment to the other structures and architectural elements to prevent
future deterioration is recommended.
41
3.6 Proposed layout and setting
3.6.1 Stone Houses No. 31 - 35
Floor /
Unit
No. 31
No. 32
No. 33
No. 34
No. 35
G/F
旅遊資訊中心
Tourist Services
Centre
文物探知中心
Stone Houses
Interpretation
Area
懷舊冰室
Themed
Cafeteria
懷舊冰室
Themed
Cafeteria
懷舊冰室
Themed
Cafeteria
1/F
旅遊資訊中心
Tourist Services
Centre
文物探知中心
Stone Houses
Interpretation
Area
文物探知中心
Stone Houses
Interpretation
Area
懷舊冰室
Themed
Cafeteria
懷舊冰室
Themed
Cafeteria
1/F
Terrace
Sitting out area
N.A.
露天茶座
Themed
Cafeteria
露天茶座
Themed
Cafeteria
露天茶座
Themed
Cafeteria
Function
Description
旅遊資訊中心
Tourist Services
Centre
ƒ
organizes guided tours to the heritages in Kowloon City and other districts
ƒ
displays visitor information on the sight-seeing points of cultural and
heritage interest in the district
文物探知中心
Stone Houses
Interpretation Area
ƒ
displays old furniture, daily utensils, old photos and other artifacts for the
interpretation of the residents’ daily living in the past
ƒ
organizes exhibitions of various themes to introduce the historical and
cultural values of Kowloon City.
懷舊冰室
Themed Cafeteria
ƒ
provides catering
ƒ
provides board game services for young people
3.6.2 New Building 1 and 2
Building 1
教育研究中心
Education / Visitor Center
Ground Floor
Building 2
FS water tank and pump
room
Lift for disable, Storage, Switch room, Toilet
Roof
First floor
Roof top for maintenance
Roof top for greenery
Corridor / staircase
N.A.
Function
Description
教育研究中心
Education / Visitor Center
ƒ
42
Organizes educational courses related to local cultural and historical
context, leisure interests, arts, etc.
Fig. 36. Proposed Landscape Plan
43
Fig. 37. Proposed General Layout Plan
44
Fig. 38. Artistic impression of the Stone Houses Family Garden (1).
45
Fig. 39. Artistic impression of the Stone Houses Family Garden (2).
46
Fig. 40. Proposed walkway at the rear of the historic building.
47
4
ASSESSMENT
4.1 Conservation Principles
The conservation process of making a possible compatible use for Stone Houses adopted the
following guiding conservation principles in developing the appropriate treatments and level of
intervention for character defining elements and other historic building fabrics with reference to
international charters and other relevant conservation standards.
Conserve heritage value
ƒ
Respect its changes over time and its various uses that represent particular periods. Thus, it is
not necessary to return its state to the original period when the building or the site was firstly
erected. Only remove, and/or replace the physical fabric that has substantially altered the
overall intactness of the buildings and the character defining elements.
ƒ
Restore any deformed, collapsed, or misplaced components, and later additions considered of
no significance or intrusive should be removed.
Retain authenticity and integrity
ƒ
Respect the original character or architectural style of the building fabric and retain its
traditional building materials or construction system as much as possible.
ƒ
Recognize each historic place as a physical record of its time, place and use.
ƒ
Do not create a false sense of historical development by adding elements from other historic
places or by combining features of the same property that never co-existed.
48
Minimum Intervention
ƒ
Keep any treatment or intervention to building fabric to the minimum and respect the heritage
value when undertaking an intervention.
ƒ
Use the gentlest means possible for any intervention.
ƒ
Make any intervention physically and visually compatible and identifiable upon close
inspection, and document any intervention for future reference.
Repair rather than Replace
ƒ
Repair rather than replace character-defining elements.
ƒ
Only when such elements are too severely deteriorated to repair, and with sufficient physical
evidence, replace them with new elements that match the forms, materials and detailing of the
same elements.
ƒ
Where there is no sufficient evidence, make the form, material and detailing of the new
elements compatible with the character of the historic place.
Reversibility
ƒ
Make any intervention or adaptation to the building fabric reversible, without causing any
damage to the existing structure when such intervention is to be removed in future.
ƒ
Any new additions should be reversible and should not affect the essential form and integrity of
the historic place, or that the building fabric should not be impaired if the new work is to be
removed in the future.
Integrating old and new
ƒ
When adding new construction to heritage buildings, the proposed new works and
developments should be sympathetic to the heritage place in terms of its compatible proportion,
form, design and materials. Make the new works physically and visually compatible with and
distinguishable from the original fabric of the historic place.
4.2 Potential Impact and mitigation measures
4.2.1 Definition of terms14
14 The definition of terms is developed based on James Semple Kerr, Conservation Plan: A Guide to the Preparation of
Conservation Plans for Places of European Cultural Significance, National Trust, 2004.
49
Levels of
Significance
Meaning
High
Elements which make a major contribution to the overall significance of the place.
Spaces, elements or fabric originally of substantial intrinsic quality, and exhibit high
degree of intactness and quality, though minor alterations or degradation may be
evident.
Moderate
Elements which make a moderate contribution to the overall significance of the place.
Spaces, elements or fabric originally of some intrinsic quality, and may have undergone
minor or extensive alteration or degradation.
Low
Elements which make a minor contribution to the overall significance of the place.
Spaces, elements or fabric originally of little intrinsic quality, and may have undergone
alteration or degradation.
Original spaces, elements or fabrics of some quality, which have undergone extensive
alteration or adaptation to the extent that only isolated remnants survive.
Neutral
Items which are of little consequence in terms of understanding or appreciating the site
and its developments, without being actually intrusive
intrusive
Items which are visually intrusive or which obscure understanding of significant
elements of the site, and may be identified for removal
Mitigation
measures
- Practical advice is given to mitigation adverse impact affects.
Impact level
- Overall level of impact on elements, after application of mitigation measures, is
assessed as follows:
50
High
- an impact that significant alters or obliterates significant characteristics
of the heritage resource;
Medium
- an impact that alters the character or surroundings of the heritage
resource, but is consistent with existing and emerging treads;
Low
- an impact capable of measurement but with no alteration of significant
characteristics; and
Neutral
- a change that does not affect the value of the heritage resource and/or
its surroundings.
4.2.2 Impact assessment
Assessment Items
Affected CDEs / fabric
Level of
significance
Impact
Level
Treatment/ Mitigation Measures
Convert the buildings and its
site into a “Stone Houses
Family Garden”
N.A.
N.A.
low
ƒ
Photographic and cartographic survey of the buildings and its site
shall be carried out before the commencement of works.
ƒ
Interpretation strategy shall be properly formulated and present the
historic development and changes of the buildings and site to enhance
and reinforce the understanding of the cultural significances of the
historic place.
Convert the open space into a
neighborhood garden
Open space in front
low
neutral
ƒ
Such conversion work is considered beneficial as a more welcoming
open space with designed landscaping is provided for public leisure
use as well as appreciating the historic buildings. (refer to the
assessment items in following section)
Addition of hard landscape
paving including a labyrinth
Open space in front
low
neutral
ƒ
The paving should be of compatible design, in terms of suitable
design, colour and texture.
ƒ
The design of the labyrinth and the associated structure erected in the
open area shall not overwhelm the appearance of the Stone Houses
and create visual impact to the front façades of the Houses.
ƒ
They should be discernible form the original historic fabric and be
understated in character.
ƒ
Such improvement work is considered beneficial as a more
welcoming space is provided for public uses.
General
A-1
A-2
Site
B-1
B-2
Make good and improve the soft
landscape
Open space in front
low
neutral
51
B-3
B-4
B-5
B-6
52
Addition of new concrete steps
for outdoor seating
Addition of new outdoor
furniture, lamp posts, signage,
display stands and art works
Addition of a new building
block with a multi-purpose
room for Education / Visitor
Centre
Addition of a new building
block for new E&M
installations for adaptive reuse
Openness and ambiance
of the open space
Openness and ambiance
of the open space
Openness and ambiance
of the open space
Openness and ambiance
of the open space
low
low
low
low
neutral
neutral
neutral
neutral
ƒ
Such new structure shall be of compatible design, in term of suitable
material, colour and texture for the finishes.
ƒ
They should be placed in the open space so that the main facade of
the stone houses can still be well conceived.
ƒ
Such new structure shall be of compatible design, in term of suitable
material, colour and texture for the finishes.
ƒ
They should be discernible from the original historic fabric and be
understated in character.
ƒ
They should be placed in the open space so that the main facade of
the stone houses can still be well conceived.
ƒ
The Education / Visitor Centre shall offer potential to enhance and
enrich the values of the place.
ƒ
Such new structure shall be of compatible design, in term of suitable
material, colour and texture for the finishes.
ƒ
It should be discernible form the original historic fabric and be
understated in character.
ƒ
Its location should be selected with least visual impact to the historic
building away from the historic building without blocking the front
facade.
ƒ
Its location should be away from the historic buildings, i.e., at the
peripheral location of the site.
ƒ
Its height should not exceed the roofline of the historic buildings.
ƒ
The overall width of the new structure shall be compatible to the
historic buildings.
ƒ
Such new structure shall be of compatible design, in term of suitable
material, colour and texture for the finishes.
ƒ
It should be discernible form the original historic fabric and be
understated in character.
ƒ
Its location should be away from the historic buildings as far as
possible to avoid adverse visually impact.
B-7
Replace the existing fencing
around the building premises
with new fencing for better
security
N.A.
N.A.
neutral
ƒ
The design of the new fencing shall be understated in character and
would not induce any serious visual impact to the historic buildings.
Chinese styled pitched
roof laid with pan and
roll tiles;
high
medium
ƒ
Subject to statutory requirement and approval, the restored roof shall
match with exiting with reference to the traditional Chinese styled
architectures and available information. The design of the roof
restoration shall be submitted to AMO for approval.
ƒ
Documentation should be prepared during the course of the
restoration works.
ƒ
Information should be provided in-situ clarifying the authenticity of
the newly added timber roof structure, for example, the date of
restoration could be branded on each timber member.
Exterior of Stone Houses
C-1
Repair and restore the timber
roof with Chinese styled roofing
consisting of pan and roll tiles
supported by timber battens and
purlins
Gable walls with hanging
ridge and moulding
C-2
Demolish the later-added
structures to the rear annex of
the historic buildings
N.A.
intrusive
neutral
ƒ
Such improvement works is considered beneficial as the original
building form and spatial layout is revealed.
C-3
Repair, restore and clean the
external masonry walls
external masonry walls
high
neutral
ƒ
Such improvement works is considered beneficial as the original
appearance and textures of the external wall could be revealed.
ƒ
The mortar shall be raked out and the joints shall be repointed with
ribbon pointing using a suitable mortar mix.
ƒ
Later added rendering on masonry surface shall be hacked off.
ƒ
The external masonry walls should not be painted or treated with
permanent coating system.
53
C-4
C-5
C-6
C-7
54
Restore the signage marked
with Chinese characters “藍恩
記” (Lam Yan Kee) at House
No. 31 and preserved in-situ
Restore and repair the door
openings with concrete lintel,
plastered surround, Chinese
styled timber doors with timber
locks and granite socket, and
metal sliding Bostwick gates
signage marked with
Chinese character “藍恩
記”
Door openings with
associated components
Restore and repair the window
openings with concrete lintels
and timber framed windows on
front and side elevations
window openings with
concrete lintels and
timber framed windows
Repair the old metal mail boxes
and preserve in-stiu
old metal mail boxes
high
high
high
moderate
neutral
neutral
low
neutral
ƒ
Such restoration works is considered beneficial and acceptable
provided that the works is minimal and carried out by experienced
workmen under the guidance of conservationists.
ƒ
The Chinese characters “藍恩記” (Lam Yan Kee) and associated
descriptive wordings shall be re-painted if necessary to match with
existing.
ƒ
Coating of protective paint may be applied provided that it is
reversible with causing damage to the signage.
ƒ
Such restoration works is considered beneficial and acceptable
provided that the works is minimal and carried out by experienced
workmen under the guidance of conservationists.
ƒ
Existing openings to front and side elevations should not be altered.
ƒ
The metal gate shall be cleaned, repaired and treated with corrosion
protection as appropriate.
ƒ
The timber components shall be treated with preservative paint
against decay and insect attack.
ƒ
Information should be provided in-situ clarifying the authenticity of
the newly added timber framed windows, for example, the date of
restoration could be branded on the each timber window.
ƒ
Such restoration works is considered beneficial and acceptable
provided that the works is minimal and carried out by experienced
workmen under the guidance of conservationists.
ƒ
All later added items, including metal sheet canopies, window type
air-conditioners with supports and exhaust fans should be removed.
ƒ
Such repair works is considered beneficial and acceptable provided
that the works is minimal and carried out by experienced workmen
under the guidance of conservationists.
ƒ
The metal mail boxes shall be repaired by de-dusting if necessary.
ƒ
The existing wordings painted on the mail boxes should not be
covered up or erased.
C-8
Addition of a new walkway and
connecting platform at the rear
of the historic building for
barrier free access
Original building form
moderate
high
ƒ
Such new walkway is acceptable providing it is of compatible design,
in term of suitable material, colour and texture.
ƒ
Such addition should be reversible without causing permanent
damage to the historic fabric.
ƒ
The new structure should be discernible form the original historic
fabric and be understated in character.
ƒ
It should be structurally independent and will not disturb to the
historic fabrics.
ƒ
The rear annex at Unit 32 will be preserved in-situ and restored to
include in the “Stone Houses Interpretation Area”. A viewing well
shall be left on the outdoor walkway for public appreciation.
C-9
Existing trees (5 nos.) at the rear
and immediate front of the
historic buildings will be
transplanted
trees
low
low
ƒ
The transplantation shall be carried out with adequate guidance from
tree specialist.
C-10
Existing Ficus trees (6 nos.) at
the rear of the historic buildings
will be fell
trees
intrusive
neutral
ƒ
The aggressive and extensive root system of these trees are imposing
structural problem to the building structure.
ƒ
New trees shall be planted in the open space as compensation.
Addition of split-type air
conditioning unit and pipe
works to enhance the comfort of
visitors
Masonry external walls
ƒ
The outdoor units should be placed at the rear of the building to
minimize visual impact to the front façade.
ƒ
They shall be placed under the new walkway and concealed with
cover of subtle design to minimize the visual impact to the rear of the
building from Junction Road.
C-11
high
low
55
C-12
Form new openings on walls for
installation of new building
services such as electrical
system, fire services system,
plumbing and drainage system,
air conditioning system, etc.
Masonry external walls
high
medium
ƒ
All the pipes and ducts of all kinds of building services installation
should be grouped together when entering the building so that
minimum number of holes will be made on the walls surfaces.
ƒ
Instead of forming new holes, existing openings on granite walls
should be utilized.
ƒ
Location of new openings for passage of piping shall be agreed prior
the works.
ƒ
Disturbance to the historic granite walls shall be minimized as far as
possible.
ƒ
The openings shall be formed by removal of granite masonry or
coring at the joint and shall be subject to the advice from Registered
Structural Engineer.
ƒ
Coring of holes in the middle of granite masonry block should be
avoided.
ƒ
No window-type air conditioner is allowed to be used at the Stone
Houses.
ƒ
Such repair works is considered beneficial.
ƒ
Structural condition of the walls shall be checked.
ƒ
The defects at internal walls shall be repaired with materials matching
original without adverse impact on the historic fabrics.
Interior of Stone Houses
D-1
56
Repair internal walls, including
spalling plaster, cracks and
deteriorated finishes
Internal walls
low
neutral
D-2
D-3
Form new door openings
between units (2 nos.) at the rear
annex for functionality
Addition of structural
strengthening works to the
timber flooring at No. 32 to
comply with modern day safety
standards
Internal walls
Timber joists and
planking
low
high
low
medium
ƒ
Investigation on the structural condition of the building shall be
carried out. The structural stability of the building should not be
affected by such alteration which should be subject to the advice from
Registered Structural Engineer.
ƒ
Disturbance to historic fabrics shall be minimized.
ƒ
New structural support shall be minimized in size without
overwhelming the interior.
ƒ
Documentation should be prepared during the course of such
alteration works.
ƒ
All the original timber joists and planking shall be retained in situ.
ƒ
Numbers of the new structural members should be limited to basically
suit the strengthening purpose. The original timber elements,
including the joists, top and soffit of timber planking, shall be
exposed for public appreciation unless being covered-up due to the
structural strengthening elements which are in the minimum extent.
ƒ
New structures shall be discernible form the original historic fabric
and minimized in size as far as practicable without overwhelming the
interior.
ƒ
Portion of the original timber structures shall be retained without
being covered up for display and interpretation.
ƒ
Documentation should be prepared during the course of such
alteration works.
ƒ
New structures shall be minimized in size without overwhelming the
interior and shall be in compatible design to the historic ambience of
the historic buildings.
ƒ
The existing timber planks shall be inspected and salvaged as much as
possible for reuse on the new metal decking to form the new flooring
of the 1/F.
ƒ
Disturbance to historic fabrics shall be minimized.
ƒ
Documentation should be prepared during the course of such
alteration works.
(see Appendix II)
D-4
Convert the timber flooring of
inadequate structural integrity at
No. 31, 33, 34 and 35 into metal
decking for functionality
Timber joists and
planking
high
high
(see Appendix II)
57
D-5
Addition of strengthening works
to all timber staircases to
comply with modern day safety
standards
Timber staircase with
railings and balustrades
high
medium
(see Appendix II)
D-6
Replace exiting floor screeding
with on-grade concrete slab to
support the structural
strengthening works
N.A.
low
low
ƒ
The original timber members (e.g., railings and steps) shall be
retained.
ƒ
New structures shall be concealed at the underside and minimized in
size without adverse visual impact to the historic fabrics.
ƒ
Disturbance to original timber members shall be minimized.
ƒ
Documentation should be prepared during the course of such
alteration works.
ƒ
The structural strengthening framework shall be installed underneath
the timber staircase or at a position which will not overwhelm the
appearance of the staircases. The upgrading works for the balustrade
could also be connected to such structural strengthening framework in
subtle design. Thus, the visual impact to the timber stair can be
minimized.
ƒ
The new internal decoration should be compatible to the historic
ambience of the interior.
ƒ
The floor tiles in good condition should be salvaged for reuse as
necessary.
ƒ
Such restoration works is considered beneficial and acceptable
provided that the works is minimal and carried out by experienced
workmen under the guidance of conservationists.
ƒ
The structural integrity of the stoves, chimney, and working bench
shall be checked. They shall be repaired as necessary with materials to
match with original.
ƒ
The brickworks shall receive proper preservative treatment, such as
cleaning, application of moss retardant and protective coating,
prevention of rising damp, etc.
(see Annex II)
D-7
58
Repair and restore the kitchen
with original stoves at No. 32.
Kitchen with original
stoves
high
neutral
D-8
D-9
Repair and restore the timber
roofing
Installation of new building
services such as light fittings,
electrical trucking and conduits,
air conditioning units, visual fire
alarms, socket outlets, etc.
Timber battens and
purlins
Internal walls
high
low
medium
medium
ƒ
Subject to statutory requirement and approval, the restored roof shall
match with exiting with reference to the traditional Chinese styled
architectures and available information. The design of the roof
restoration shall be submitted to AMO for approval.
ƒ
Documentation should be prepared during the course of the
restoration works.
ƒ
Information should be provided in-situ clarifying the authenticity of
the newly added timber roof structure, for example, the date of
restoration could be branded on each timber member.
ƒ
All the pipes and ducts of all kinds of building services installation
should be grouped together when entering the building so that
minimum number of holes will be made on the walls surfaces and
floor.
ƒ
Cable trunking should be used instead of individual electrical
conduits.
ƒ
Disturbance to historic granite walls shall be minimized to avoid
adverse visual impact and affect the structural integrity of the
building.
ƒ
Instead of forming new holes, existing openings on granite walls
should be utilized.
59
4.3 Interpretation
Stone Houses Family Garden aims to promote the values treasured by the last generation to the
youth through creative activities, programmes and events hosted in the site and an understanding of
the changing context of the district.
It is recommended that the focus of interpretation of Stone Houses shall be its linkage to the
historic evolution of the neighborhood area and Kowloon city district at different period of time:
ƒ
Stone Houses area are part of the cottage area in the district where refugees from mainland
settled during the Chinese Civil War in 1947-49.
ƒ
Several film studios were established in the vicinity of Stone Houses in the late 1940s and
1950s.
ƒ
Small workshops were operated in the cottage area, such as the tombstone factory at Stone
Houses, reflecting the mixed industrial and residential use in the grassroots class area during
the 1960s-70s.
Clever and imaginative interpretation of the historic changing uses of the heritage building
and grounds as well as the people involved will set the context for a comprehensive understanding
of cultural and social evolution of Kowloon City district and greater Hong Kong. Activities and
programs in the Garden shall be designed to forge a sense of belonging and serve the community of
Kowloon City district.
The conceptual framework of the interpretation is proposed to tie in with the different uses of
the buildings as follows:
Location
Interpretation
Presentation
旅遊資訊中心
Tourist Services
Centre
ƒ
organizes guided tours to the heritages
in Kowloon City and other districts
ƒ
guiding map
ƒ
informational panels
ƒ
displays visitor information on the sightseeing points of cultural and heritage interest
in the district
ƒ
leaflet
ƒ
displays old furniture, daily utensils, old
photos and other artifacts for the interpretation
of the residents’ daily living in the past
ƒ
exhibits
ƒ
informational panels
ƒ
audio
installations
文物探知中心
Stone Houses
Interpretation
Area
60
ƒ
organizes exhibitions of various themes to
introduce the historical and cultural values of
Kowloon City.
visual
Open Space
ƒ
ƒ
教育研究中心
Education /
Visitor Center
懷舊冰室
Themed
Cafeteria
adopts a Labyrinth to form the surface pattern
which is based on an aerial photo taken for
exactly the same location in 1964.
includes some small art works reflecting
different period of time in the history of
Kowloon city district or signage displaying
textual information on the historic evolution of
the district.
ƒ
organizes weekly performance to introduce
the historical and cultural interest to the
visitors.
ƒ
organizes educational courses related to local
cultural and historical context, leisure
interests, arts, etc
ƒ
operates a hangout café that once existed at
the site.
ƒ
displays old photos for the interpretation of
the daily living and surrounding context in
the past
ƒ
ƒ
art work
ƒ
informational panels
ƒ
performances
ƒ
community activities
ƒ
educational
programme
ƒ
lectures
ƒ
training
ƒ
themed café with
restored setting and
old-fashioned menu
ƒ
historic photographs
sells old-fashioned snacks
61
5
MANAGEMENT AND IMPLEMENTATION
5.1 Maintenance management plan
Once the conservation and adaption work is completed on a historic and significant building,
ongoing maintenance is necessary to keep the building in good order. Maintenance is an essential
part of the conservation/preservation process.
Repairs required as part of ongoing maintenance should be undertaken to match the existing
materials, colour or texture of existing, and must blend in with existing fabric. Maintenance work
should be governed by the Burra Charter principle of “Do as much as necessary and as little as
possible”.
A maintenance schedule should be developed which includes:
ƒ
Regular inspection to check the degree of deterioration of all Character defining elements
ƒ
Annual inspection of the condition of the roof
ƒ
Quarterly monitoring of the termite control and eradication system to the timber roof structures
ƒ
Regular inspection of internal finishes and fittings
ƒ
Regular monitoring of site drainage
ƒ
Regular maintenance to the plants and garden
The maintenance management plan will be reviewed annually by building management
professionals, conservationists and professionals with thorough understanding of managing a
historic building to ensure the execution of a proper maintenances programme.
A maintenance manual or handbook delineating the recommended procedures of carrying
out necessary maintenance works and identified conservation items will be complied and provided
to future frontline maintenance staffs to ensure their adequate understanding of their duties and
necessity in better maintaining the historic building.
62
5.2 Property management proposal
The conservation and adaption of the building is only the first stage in an ongoing process of care
and management. It is important that everyone involved with the use of the building is aware of its
value and the level of care which must be taken when any works are proposed.
Damaging and often irreversible changes can inadvertently occur through ill-considered
actions or ignorance. To avoid this situation occurring, all staff involved in any aspect of the
management of the Stone Houses must be briefed on the significance and appropriate management
of the building and its setting. An operation manual detailing the significance and appropriate
management of the building and its setting, as well as the identified conservation items will be
complied and provided to future users for guiding the operation of the building without degrading
its heritage significance in any aspect.
No new work, however minor or seemingly insignificant should occur without approval and
checking. For example, nothing should be fixed on or into internal or external walls without prior
approval.
The property management plan will be reviewed annually by building management
professionals, conservationists and professionals with thorough understanding of managing a
historic building to ensure the execution of a proper management programme.
5.3 Future development
For any future development to the historic building and site, including renovation works,
alterations and additions, is intended, prior consultation and consent should be sought from the
Wing Kwong So-Care Company Limited, Development Bureau and Antiquities & Monuments
Office. The proposed works should follow the internationally recognized conservation principles
and be designed by qualified conservationists such as a Conservation Architect or a Heritage
Consultant.
5.4 Documentation
Before the commencement of any works on site, a detailed photographic and cartographic survey
will be conducted by experienced surveyors/conservationist to provide important reference to all
later restoration and renovation works. Besides, as-built drawings and photos to the historic
buildings upon the completion of the restoration works will be prepared for record purpose. These
survey reports and all conservation studies, site inspection records will be kept at the site office and
made available to the users and professionals who are responsible for up-keeping the historic
building and managing the changes of the historical place.
63
Documentation of the whole conservation process, from conceptualization to implementation
stage will also be required, so that an understanding of the changes to the historic fabrics is
recorded to inform future care and maintenance. Such documentation, say measured drawings and
photos of the conservation works in process, may also from educational materials displayed to the
public as part of the interpretation strategies. Upon the completion of conservation works, all these
documentations should be well kept in the future exhibition rooms.
5.5 Financial resources
Under the Revitalizing Historic Buildings through Partnership Scheme, budget is allocated for the
general maintenance work of the buildings in coming 3 years. The maintenance cost will be
allocated from the operational surplus after the first 3 years.
5.6 Staffing and management structure
ƒ
A heritage expert should be appointed in the project team during the design and construction
stage to ensure that the conservation policies stated in the conservation management plan can
be appropriately and effectively executed.
ƒ
A project officer/curator should be appointed for the interpretation strategy.
ƒ
A management committee consisting of building professionals will be set up to oversee the
implementation and operation of the scheme as well as draw the operation manual and
maintenance manual.
5.7 Implementation programme
The proposed work progranmme for the revitalization of the Stone Houses into Stone Houses
Family Garden is as follows:
64
65
BIBLIOGRAPHY
Official Document
Antiquities and Monuments Office, Historic Building Appraisal – No. 31-35 Hau Wong Temple New
Village,Kowloon City, items 949.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, survey sheet
no.: CXXXVII-NE-6.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
4115.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
6089.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
0100.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
5167.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
12195.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
56293.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
CN3186.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
CW38065.
Courtesy of Survey and Mapping Office, Lands Department, Hong Kong SAR Government, photo ref. no.
CS29709.
Books after 1911
Cheng Po Hung 鄭寶鴻, Hong Kong During the Japanese Occupation, Hong Kong, University Museum and
Art Gallery, The University of Hong Kong, 2006.
Chiu Yu Lok 趙雨樂 and Chung Po Yin 鍾寶賢, Longchengleshan: zaoqi jiulongcheng yu leshantang
yanjiu 龍城樂善: 早期九龍城與樂善堂研究 [The Benevolent Society: A Study of the Early Kowloon
City and Lok Sin Tong], Hong Kong, Sunray Publishing Company Limited, 2000
Chiu Yu Lok 趙雨樂, Chung Po Yin 鍾寶賢, Regional Study of Hong Kong History: Kowloon City, Hong
Kong, Joint Publishing (H.K.) Company Limited, 2001.
Chu Wai Tak 朱維德, Xhianjiang jiumao 香江舊貌 [The Old Scenery of Hong Kong], Hong Kong,
Cosmos Books Ltd., 1993.
Empson, Hal, Mapping Hong Kong: a Historical Atlas, Hong Kong, Government Information Services,
1992.
Fung Sze Man 馮思敏, Munsang College 75th anniversary, 1926-2001, Hong Kong, Munsang College,
2001.
66
James Semple Kerr, Conservation Plan: A Guide to the Preparation of Conservation Plans for Places of
European Cultural Significance, National Trust, 2004
Lau Yun Wo 劉潤和, Jiulongchengqu fengwuzhi 九龍城區風物志 [A Guide to the Antiquities of Kowloon
City District], 2005.
Lau Chi Pang 劉智鵬, Tunshengrennyu: rizhishiqi Xianggangren de jitihuiyi 吞聲忍語: 日治時期香港人
的集體回憶 [Quiet mouth: A collective memory of Hong Kong people under the Japanese Occupation],
Hong Kong, Chung Hwa Book Co., 2009
The Overseas Chinese Daily News, 1953.
Wong Puikai 黃佩佳, Xianggang Xinjie fengtu mingsheng daguan jianbaoji 香港新界風土名勝大觀剪報
集 [Collection of newspaper cutting on the scenery and social customs and sights in Hong Kong New
Territories], ca. 1930s.
Zheng Baohong 鄭寶鴻, A Century of Kowloon Roads and Streets, Hong Kong, Joint Publishing (Hong
Kong) Company Limited, 2000.
Zheng Baohong 鄭寶鴻, Early Hong Kong’s Kowloon Peninsula, Hong Kong, University Museum and Art
Gallery, The University of Hong Kong, 2007.
Website
Tung Tau Cottage Area, Retrieved 21 April, 2011 from hk-place, Web Site: http://www.hkplace.com/db.php?post=d002031.
Parks Canada Standards and Guidelines for the Conservation of Historic Places in Canada. Retrieved on
December 15, from Parks Canada under Her Majesty the Queen in Right of Canada, Website:
http://www.pc.gc.ca/docs/pc/guide/nldclpc-sgchpc/index_e.asp.
Newspaper
九龍模範村始末 [The origin of Model Villages in Kowloon], Ta Kung Pao, 30th July, 1948.
67
APPENDIX I
Architectural Drawings
Drawing No.
Title
SH-P-01
Site Plan
SH-P-02
Ground Floor Plan, 31-35 Hau Wong Temple New Village
SH-P-03
First Floor Plan, 31-35 Hau Wong Temple New Village
SH-P-04
Roof Plan, 31-35 Hau Wong Temple New Village
SH-E-01
Front Elevation, 31-35 Hau Wong Temple New Village
SH-S-01
Section A-A’, 31-35 Hau Wong Temple New Village
SH-S-02
Section B-B’, 31-35 Hau Wong Temple New Village
68
69
70
71
72
73
74
75
APPENDIX II
Proposed structural scheme
Drawing No.
Title
0930/1/AA/FIG/01(A)
Addition and alteration details for House no. 31 and 33 – 35
0930/1/AA/FIG/02(B)
Addition and alteration details for House no. 32
0930/1/AA/EX/01(B)
Footing details
0930/1/AA/FIG/04(A)
Structural details for new wall opening
76