Construction of the Dewatering Dikes at
Transcription
Construction of the Dewatering Dikes at
CONSTRUCTION OF THE DEWATERING DIKES MEADOWBANK GOLD MINE, NUNAVUT Fiona Esford, M.A.Sc., P. Eng., Associate, Golder Associates Ltd., Vancouver, BC, Canada Grant R. Bonin, P. Eng., Associate, Golder Associates Ltd., Vancouver, BC, Canada Michel R. Julien, Ph.D., P.Eng, Corporate Director Environment, Agnico Eagle Mines Ltd., Toronto, ON, Canada (formerly Principal, Golder Associates Ltd.) 12 View past issues of the CDA Bulletin online at www.naylornetwork.com/cda-NXT/ AERIAL IMAGES COURTESY OF AGNICO EAGLE MINES LIMITED, MEADOWBANK DIVISION ABSTRACT: Between 2008 and 2010, a series of dikes were constructed within Second and Third Portage Lakes at Agnico Eagle Mines Limited’s Meadowbank gold mine, located approximately 80 km north of the hamlet of Baker Lake, Nunavut. The dikes are key infrastructures for the mine that permit dewatering of portions of the lakes to expose areas for the development and extraction of ore from open pits. This paper, the first in a series of three papers, previously presented and published as part of the CDA 2013 Annual Conference, describes the techniques used to construct approximately 3 km of dikes within the lakes over a three-year period. The dikes consist of broad rockfill shells, granular filters, and a central low permeability element. The low permeability element is comprised of a combination of soilbentonite and/or cement-soil-bentonite cut-off wall that was excavated using slurry trench technology through the granular filters to bedrock or into a dense foundation soil. Depth of excavation was up to 15 m below the lake elevation. In deeper portions, where the cut-off wall did not reach bedrock, jet grout columns were constructed between the base of the cut-off wall and the bedrock surface, up to a depth of 22 m. Grouting of the shallow bedrock and the interface between the bedrock and the base of the cut-off wall and/or jet grout columns was then carried out. The earthworks component of the construction, the subject of this paper, occurred over the short, open water season of each summer approximately 12 weeks in length, between mid-July and early October. The dikes were constructed within the lakes, prior to any dewatering. The construction techniques employed are now considered as viable methods for dike construction within the Canadian Arctic environment. The key lessons learnt as well as the main challenges that were faced while constructing the dikes in the Arctic environment and the logistical constraints are also presented. RÉSUMÉ: Entre les années 2008 et 2010, des digues ont été construites dans les lacs Second Portage et Third Portage à la mine d’or Meadowbank de Mines Agnico Eagle Limitée, située à environ 80 km au nord du village de Baker Lake, dans le territoire du Nunavut. Ces digues sont des infrastructures essentielles permettant le dénoyage des zones à exposer pour l’extraction du minerai par fosses à ciel ouvert. Cet article, le premier d’une série de trois, décrit les techniques utilisées dans le cadre de la construction d’environ 3 km de digues à l’intérieur des lacs, sur une période de trois ans. Les digues sont formées d’une enveloppe en enrochements, de matériaux granulaires filtrants et d’un élément central de faible conductivité hydraulique. L’élément central consiste en un mur parafouille constitué d’un mélange de sols et de bentonite, avec ou sans ajout de ciment, creusé en utilisant la technologie de la tranchée de boue à travers les matériaux granulaires jusqu’au roc ou à l’atteinte d’une couche dense de sols de fondation. La profondeur du mur parafouille atteint jusqu’à 15 m sous le niveau des lacs. Dans les sections plus profondes, là où le mur parafouille n’a pas atteint le socle rocheux, des colonnes constituées de coulis de ciment injectées sous haute pression ont été mises en place entre la base du mur parafouille et la surface du rocher jusqu’à une profondeur de 22 m. La partie superficielle du socle rocheux et l’interface entre la surface du rocher et la base du mur parafouille ou des colonnes de ciment ont ensuite été injectées par l’injection de perméation de coulis de ciment (cementitious permeation grouting). Les travaux de terrassement ont été réalisés à l’intérieur de la courte saison estivale d’eau libre des lacs entre les mois de juillet et d’octobre, soit environ 12 semaines. Les digues ont été construites à l’intérieur des lacs avant leur dénoyage. Les techniques de construction employées sont maintenant considérées comme des méthodes viables pour la construction de digues dans l’environnement de l’Arctique canadien. Les principaux défis rencontrés, les contraintes logistiques ainsi que les leçons tirées de la construction de ces ouvrages dans l’environnement arctique sont également présentés. 1 INTRODUCTION Agnico Eagle Mines Limited (AEM) operates the 8,500 tonne-per-day Meadowbank gold mine, located approximately 80 km north of the hamlet of Baker Lake, Nunavut (Figure 1). The mine is accessed year round by air and seasonally, between the end of July and midOctober, by barge to Baker Lake. Materials barged to Baker Lake are then transported to Meadowbank over an approximately 110 km All-Weather gravel road which is maintained throughout the year by AEM. The mean monthly temperature at the mine varies from a low of -32°C in January to a high of 12°C in July. The mean annual temperature is -11.4°C with the mean monthly temperatures below zero Celsius for eight months of the year, October through May. Average annual precipitation is 295 mm with approximately half of it falling as snow. Meadowbank is located within the zone of continuous permafrost with a mean average temperature ranging between -6 to -8°C, and estimated depth of 450 to 550 m. The thickness of the active layer varies and taliks exist beneath lakes where water depths are greater than 2 to 3 m. Mine construction began in 2008. Production commenced in the first quarter of 2010. The mine consists Canadian Dam Association • Winter 201513 Figure 1: Meadowbank Gold Mine location Figure 2: Meadowbank site of a series of open pits, with conventional processing and slurried tailings deposition within a tailings storage facility. Broad rockfill dikes with a low permeability element were constructed within Second and Third Portage Lakes and are key infrastructures for the mine to permit dewatering of portions of the lakes to expose areas for the development and extraction of ore from open pits (Figure 2). This paper, the first in a series of three papers, previously presented and published as part of the CDA 2013 Annual Conference, describes the techniques used to construct approximately 3 km of dikes within the lakes over a three-year period. The earthworks component of the construction, the subject of this paper, occurred over the short, open water season of each summer, approximately 12 weeks in length, between mid-July and early October. The dikes were constructed within the lakes, prior to any dewatering. The first dike, East Dike, was constructed in 2008, followed by the north and south portions of the Bay-Goose Dike in 2009 and 2010, respectively. The depth of water through which each dike was constructed, along with the depth to bedrock, successively increased each year of construction. As such, the complexity of the design, construction, and risk associated with each structure also increased. Designs for the dikes were prepared progressively, with adaptations made to incorporate lessons learned from the previous year of construction into the design for the subsequent construction season. The construction techniques employed are now considered viable methods for dike construction within the Canadian Arctic environment. The key lessons learnt as well as the main challenges that were faced while constructing the dikes in this challenging environment and the logistical constraints are presented in this paper. 2 DIKES Both the East Dike and Bay-Goose Dike were constructed within lakes, prior to any dewatering. The earthworks component of the East Dike was constructed, during the open water season of 2008, within Second 14 Portage Lake. The East Dike serves to isolate a portion of the lake to permit development of the Portage Open Pit and concurrently provide an area for tailings deposition. The East Dike is approximately 800 m in length and was constructed through a maximum water depth of 5.5 m and maximum depth to bedrock of 8 m. The earthworks component of the Bay-Goose Dike was constructed over two open water seasons. This dike was constructed within Third Portage Lake to isolate and permit dewatering of a portion of the lake for development of the Goose Pit. The north portion, approximately 900 m in length, was constructed in 2009 through a maximum water depth of 8 m and maximum depth to bedrock of 12 m. The south portion, approximately 1.3 km in length, was constructed in 2010 through a maximum water depth of 8.5 m and maximum depth to bedrock of 22 m. The East Dike is a permanent structure. After mine closure, flooding of the Portage Pit will occur and eventually only a 1 m head will exist across the structure. The Bay-Goose Dike is considered temporary and at closure will be breached to allow water from Third Portage Lake to enter and flood both the Goose and Portage Pits. 2.1 Investigations Bathymetric surveys were conducted during the open water season, in the year preceding construction to profile the lakebed surface. Geotechnical investigations were conducted during the winter, with drilling occurring through the ice. Investigations were performed to obtain information on the depth to bedrock and thickness of lakebed soils. Information obtained from the geotechnical and bathymetric surveys was then utilized to assist in the selection of the dike alignment, prepare the design, construction drawings, and quantity estimates. Three drilling methods were used: rotary-percussive drilling, diamond coring and vibrosonic. Rotary-percussive drilling was effective in providing estimates of the depth to bedrock where water depths were less than 4 m, and provided chip samples of the lakebed soils in relatively shallow areas where the ice was grounded on the lakebed surface. View past issues of the CDA Bulletin online at www.naylornetwork.com/cda-NXT/ However, samples could not be obtained in deeper areas, nor was it possible to drill in deeper water due to the lack of support for the drill rods. Diamond coring was successfully used to provide estimates of the depth to bedrock and in recovering core samples of the bedrock. However, no soil samples could be recovered. Having closely spaced information points about the depth to bedrock, beneath the proposed cut-off alignment, was found to positively aid in the design, construction planning, and execution of the works. For the south portion of the Bay-Goose Dike, the thickness of lakebed soil beneath where the alignment crossed three underwater channels was considered to be more substantial (up to 14 m). As such, during the winter of 2010 a sonic drill rig was mobilized to site to investigate the lakebed soils in these areas. The sonic rig was successful in retrieving a continuous profile of the lakebed soils, through the water column and beneath the ice. This permitted visual classification, sampling, and testing to characterize the materials. The lakebed soils were found to be variable with a dense, low permeability glacial till inter-layered with lenses of silt, sand, and gravel, and mixtures thereof. Figure 3 shows the distribution of geotechnical holes drilled beneath the south portion of the Bay-Goose Dike and Figure 4 shows a sample of the stratigraphic profile developed utilizing the information obtained from the various investigation programs. Thermistor data has shown that permafrost exists on land and extends into the lakes with a transition into the talik, unfrozen area. The depth of the active layer varies as does the quantity of ice within the frozen soil. Therefore, frozen ground conditions were anticipated to be present on and near the abutments of each dike and near the islands. 2.2 Design The design intent for each dike was to isolate portions of the lakes, permit dewatering and open pit development, and to minimize seepage from the lakes entering the pits during operation. Using Canadian Dam Association (CDA, 2007) classification system, both the East Dike and Bay-Goose Dike are rated as having a high consequence due to the potential risk to workers within Figure 4: Sample of stratigraphic profile developed for Bay-Goose Dike from investigation information the open pits and the potential for economic loss for the mine. The dikes were required to have an adequate factor of safety: 1.5 long term static; and 1.0 pseudo-static. In addition, the dikes were to be situated in such a manner that the potential for pit wall instability to affect the performance of the dike would be low. The dikes consist of broad rockfill shells, granular filters and central low permeability elements. The selection of materials for construction of the low permeability element varied based on the depth to bedrock. The East Dike consists of a soil-bentonite cut-off wall that was excavated using slurry trench technology through the granular filters to bedrock. For the Bay-Goose Dike, the low permeability element was comprised of a combination of a soil-bentonite and/or cement-soil-bentonite cut-off wall, which was similarly excavated using slurry trench technology through the granular filters to bedrock or into a dense foundation soil. The maximum depth excavated for cut-off wall construction was 15 m below the lake level. In deeper portions, where the cut-off wall did not reach bedrock, jet grout columns were constructed between the base of the cut-off wall and the bedrock surface, up to a depth of 22 m. Grouting of the shallow bedrock and the interface between the bedrock and the base of the cut-off wall and/or jet grout columns was then carried out. Typical cross sections of the Bay-Goose Dike are shown in Figure 5, with the cut-off wall to bedrock and with jet grouting. Material placement angles shown in Figure 5 are approximate. Figure 6 shows the profile view of the Bay-Goose Dike low permeability elements. Based on bedrock depth, variations in the typical design cross section were specified. These included: width of rockfill platform, width of the central trench excavation, material used for construction of the low permeability element, and depth of grouting. For the deeper portions of the Bay-Goose Dike, a partial cut-off system was considered. However, once the results from the sonic drilling program were obtained, it was decided that due to the presence of potentially erodible silts and uncertainty in the continuity of lenses Figure 3: Bay-Goose Dike south portion boreholes Canadian Dam Association • Winter 201515 Figure 5: Bay-Goose Dike typical sections of soil with higher conductivity, that the low permeability element would be extended to bedrock. 3 CONSTRUCTION Construction occurred during the limited open water season of each year. At Meadowbank, ice typically melts from the surface of the lakes by mid-July and begins to re-form by mid-October. The general sequence of construction activities consisted of: installation of silt curtains for turbidity control; construction of the rockfill platform; excavation of the central trench to bedrock or target surface; backfilling of the trench with granular material (fine and coarse filters); vibro-densification (deep areas); raising the height of the rockfill platform; dynamic compaction of fine filter; excavation of the slurry trench; and backfilling of the slurry trench with soil-bentonite and/or cement-soil-bentonite. Throughout the construction period, multiple activities were carried out concurrently along the length of the dike. The following subsections provide details of each of the construction activities. Following the open water season, the following construction activities occurred, and are described in Part 2 (Bonin et al., 2013) and Part 3 (Esford and Julien, 2013)of this series of papers: jet grouting of soil, where the cut-off wall was not extended to bedrock (carried out during the winter months); grouting of bedrock and the interface with the base of the cut-off wall (carried out during the winter months); and installation of instrumentation for dike performance monitoring. n n n n n n n n n to reduce the migration of suspended particles (turbidity) beyond the active work area. Control of turbidity was found to be challenging and each year modifications to the method of turbidity control were employed to improve conditions for the subsequent year of construction. During construction of the East Dike, a single row of silt curtains was installed on each side of the proposed dike alignment, approximately 25 m from the dike crest. The barriers were found to be too close to the active work front, as construction activities were found to be affecting the volume of water between the barriers which caused pressure, in the form of wave action, to be applied to the curtains. Based on the East Dike silt curtain performance, a double line of silt curtains was installed during construction of the north portion of the Bay-Goose Dike. Upstream from the dike, the inner curtain was installed approximately 50 m from the dike and the outer curtain approximately 100 m. Downstream from the dike, the inner curtain was installed approximately 150 m from the dike and the outer curtain approximately 200 m. The intent of the outer curtain was to provide secondary containment in the event that turbidity migration occurred through the inner curtain. The locations of the inner and outer curtains were selected based on water depths and information on currents and water movement within Third Portage Lake. Significant improvement in the control of turbidity was noted with the double curtain system. However, in early September, 2009 a large storm with heavy winds lifted portions of the curtains out of the water and strong waves and currents destroyed some segments. Prior to construction of the south portion of the Bay-Goose Dike, turbidity control measures were again re-evaluated. The benefit of the double curtain system was recognized. However, to improve the security of the inner curtain, protection from wind and currents was n n n 3.1 Turbidity Control Methods Each year, prior to commencement of construction activities, silt curtains were installed within the lakes Figure 6: Bay-Goose Dike profile of the low permeability elements Canadian Dam Association • Winter 201517 Figure 7: Bay-Goose Dike; aerial view of turbidity curtain configuration (deployment in progress) and rockfill platform construction required. Ideally, the inner curtain would be constructed in smaller cells such that if one portion of the curtain failed, the entire control system would not be compromised. To accomplish this, the upstream portion of the rockfill platform was constructed during the winter by breaking and removing ice, and dumping rockfill into the lake at a slow rate. The completed upstream portion of the platform provided the required protection and anchoring system for the inner cells of the turbidity curtain. Upstream from the dike, the inner curtains were installed approximately 20 m from the dike. The distance between the outer curtain and the dike varied with a minimum separation of 100 m. Downstream from the dike, a single curtain was installed with the minimum separation of 150 m. This sequence of construction and method of turbidity curtain installation was successful in maintaining adequate control. Figure 7 shows an aerial view of this turbidity curtain configuration (in progress). Additionally, to reduce the potential pressure applied to the curtains due to water movement caused by the construction, submersible pumps were used to remove water from between the curtains during rockfill placement, central trench excavation, and filter placement. 3.2 Rockfill Platform The broad rockfill platform of each dike provided structural support for each dike and a working surface for the remainder of the construction activities. The platforms were constructed using rockfill sourced from either a designated quarry (East Dike) or from open pit development activities (Bay-Goose Dike). Rockfill was transported to the leading edge of the platform using mine haulage equipment, dumped on the surface and then pushed into the water by dozers. Figure 7 shows an aerial view of the upstream portion of the rockfill platform that was constructed during the winter of 2010 and the partially completed expansion of the platform during the summer of 2010. Figure 8 shows the expansion of the platform and excavation of the central trench. 3.3 Central Trench Excavation Behind the advancing front of the rockfill platform construction, the central trench was excavated. The Figure 8: Bay-Goose Dike: rockfill platform construction and central trench excavation excavation was conducted to remove lakebed soils down to bedrock or target surface. In deep areas, where bedrock was located beyond the reach of the available equipment, the excavation was terminated on a target surface, defined as competent (dense to compact) well graded soil (i.e. till not silt). For the majority of the alignment, the central trench was excavated to bedrock, thereby removing lakebed soil, including boulders or potentially erodible materials. The excavation was backfilled with granular material, and thereby provided a downstream filter and improved the ability to excavate the cut-off trench. Excavation of the central trench from the single rockfill platform was found to be faster and eased construction rather than if the excavation was done from two parallel platforms. The dimensions of the trench varied based on the depth to bedrock. For the East Dike the base of the trench was approximately 5 m wide, while for the BayGoose Dike it ranged between 8 and 12 m, with the width increasing as the depth to bedrock increased. As portions of the excavation were completed, a detailed bathymetric survey of the excavated trench was conducted with either sonar and/or dip tape and rod sounding measurements. Verification of excavation depths using a dip tape and rod soundings were important and also used to detect silt accumulation. Cross-sections through the trench at 5 m intervals and profiles along the centreline of the trench were created using the survey data by the Contractor as part of the foundation approval process. Foundation approval, by the Engineer, for the base excavation depth, width, and termination point (bedrock or target surface) was required before backfilling of the trench with filter material could commence. Figure 9 shows the central trench and long reach excavator. 3.4 Filter Placement with Central Trench Upon approval of the foundation, the trench was then backfilled with crushed granular materials. Fine filter was placed in the middle, coarse filter on the downstream side, and either coarse filter or fine rockfill on the upstream side. The grain size distribution envelopes for the fine filter and coarse filter are shown in Figure 10. Canadian Dam Association • Winter 201519 Figure 9: Bay-Goose Dike central trench excavation with long reach excavator Placement of the materials occurred simultaneously, with the fine filter being advanced slightly ahead of the coarser materials. An excavator was used to push the fine filter material into the excavation from the water surface to minimize the potential for segregation. The coarser materials on the upstream and downstream sides were either placed by the excavator or dozer using the same method. Figure 11 shows the placement of backfill within the central trench excavation, with the fine filter in the middle of the excavation, fine rockfill on the right (upstream) and coarse filter on the left (downstream). Samples of the fine filter were collected above and below the waterline to check gradations. Results indicated that gradations met the specification and that significant segregation was not apparent. Periodic measurements of the slope of the fine filter and coarse filter were taken longitudinally along the placement front as a general check on the geometry of the backfill. They indicated that the zone of fine filter placement was sufficient for excavation of the cutoff wall. In some locations, based on the geometry of the section, fine filter was placed on the downstream slope of the excavation, so that this material was in contact with the lakebed soils, to provide filter compatibility. 3.5 Vibro-Densification (Deeper Areas) Along portions of the alignment where the depth to bedrock was 8 to 10 m or greater below the initial platform elevation, or where the excavation did not extend to bedrock, vibro-densification was required to compact the fine filter materials sufficiently to permit excavation of the slurry trench. Vibro-densification was used to compact the lower portion of the fine filter material, beyond the depth where dynamic compaction is effective to achieve the required compaction. Vibro-densification was performed from the initial rockfill platform elevation, with probe holes either side of the centerline, approximately 3 m centre to centre. Subsequently, dynamic compaction was used to compact the upper portion of the fine filter material and is described in Section 3.7. 3.6 Raising Height of the Initial Rockfill Platform Above the central trench, the elevation of the rockfill platform was increased by 2 m to provide a working Figure 10: Fine filter and coarse filter particle size distribution envelopes Figure 11: Bay-Goose Dike backfilling of central trench excavation with fine rockfill, fine filter, and coarse filter [from upstream (right) to downstream (left) of the photograph] surface for the dynamic compaction and slurry trench excavation, for construction of the cut-off wall. The raised platform consisted of zones of fine filter, coarse filter, fine rockfill, and rockfill. 3.7 Dynamic Compaction of Fine Filter Dynamic compaction was conducted to increase the density of the fine filter material to permit the excavation of the cut-off wall. A crane was used to drop the 15 tonne weight from a height of 18 m for the dynamic compaction. Figure 12 shows the craters created by dropping of the weight from the crane, used for the dynamic compaction. Multiple passes were made with craters being measured and backfilled, prior to the next round of densification. The pattern for each phase of compaction varied based on conditions. Canadian Dam Association • Winter 201521 3.8 Cut-off Wall Construction (Excavation and Backfilling) Following compaction of the fine filter material, an approximately 1 m wide (i.e., width of excavator bucket) cut-off wall was excavated using the slurry trench method, along the designated alignment. A 5% bentonite slurry was pumped into the trench as excavation occurred and the slurry level was continually maintained in order to provide wall support. The working platform for the cut-off trench excavation was 2 m above the lake elevation which provided a positive hydraulic head between the trench and lake for further wall support. The trench was excavated to bedrock or target elevation. The cut-off wall was excavated to bedrock along the entire East Dike alignment and majority of the Bay-Goose alignment. In deeper areas of the Bay-Goose Dike, where bedrock was located beyond the reach of the excavation equipment, the cut-off trench was extended until competent soil was reached, approximately 1 m beyond the depth where the central trench excavation was terminated. Soundings of the base of the trench were taken at 2 m intervals and compared to the design depth and surveyed base elevation of the central trench excavation. Figure 13 shows the excavation of the slurry trench. 664282_Thurber.indd 1 24/10/13 12:42 AM © 2013, by AMETEK. All rights reserved. Dam good positioning technologies. AMETEK has the most complete line of automation products for sensing the position of mechanical motion gear in locks and dams, cranes, gantries, bridges and more. If it moves, it’s tracked with absolute accuracy by our industry-leading rotary and linear sensors. ametekapt.com Toll free: 1-800-635-0289 Phone: 248-435-0700 22627241_Ametek.indd 1 View past issues of the CDA Bulletin online at www.naylornetwork.com/cda-NXT/ 12/02/13 5:29 PM Figure 12: Bay-Goose Dike dynamic compaction of fine filter Figure 13: Dike cut-off trench excavation using slurry trench method and dozer backfilling trench with soil-bentonite The requirement for construction was that the excavaTo prepare the cement-soil-bentonite mixture, a voltion and backfilling of the cut-off trench was to be comume of till with the dry bentonite was placed within a pleted prior to the onset of freezing conditions, which container, along with approximately 6% dry cement (by occurs approximately during the first week of October. weight of till), and the bentonite slurry. An excavator was Soil-bentonite material was used to construct the cutthen used to mix the materials. Once a uniform mix was off wall for the East Dike. For the Bay-Goose Dike, in achieved, the density and slump were measured. Upon shallower conditions (i.e., less than approximately 6 m approval, the excavator would then remove the cementto bedrock) where the hydraulic gradient acting on the soil-bentonite mix and place it at the crest of the leading structure was low, soil-bentonite material was also used front. At the beginning of each shift, measurements of to construct the cut-off wall. Where the hydraulic gradithe slope of the leading front of the soil-bentonite or ent was higher, in deeper water, the cut-off wall was cement-soil-bentonite mixture within the trench were constructed using cement-soil-bentonite to reduce the recorded to track progress. potential for erosion. During construction of the southFigure 6 shows the longitudinal profile of the cut-off ern portion of the Bay-Goose Dike, plugs of cement-soilwall constructed for the Bay-Goose Dike, the depth of bentonite were constructed in select locations along the cut-off trench excavation, and backfill material placecut-off wall alignment. The plugs served to separate work ment: soil-bentonite (SB), or cement-soil-bentonite fronts for the cut-off wall construction and facilitated (CSB) are depicted, along with zones where jet groutchanges in backfill material. ing was conducted and the extend of bedrock groutPrior to construction, samples of till were collected ing. Jet grouting and grouting works are described in from site and mix design testing was performed by the greater detail in Part 2 of this series of papers (Bonin slurry trench contractor to determine relative ratios of et al, 2013). materials to be used. To prepare either the soil-bentonite Permeability testing was carried out on representative or cement-soil-bentonite mixtures for backfill, till was samples of the soil-bentonite and cement-soil bentonite farmed either from on-land borrow areas for the East materials. Samples were collected during placement Dike, or for the Bay-Goose Dike from the dewatered in cylindrical molds or as a bulk sample. Testing was lakebed, downstream of the East Dike. Oversized cobconducted in rigid wall or flexible wall permeameters. bles and boulders were removed by the excavator and A summary of the results from the quality assurance approximately 1.5 to 2% dry bentonite powder (by weight and quality control testing are presented in Table 1. of till) was mixed into the till. Once prepared, the till-bentonite mixture Table 1: Summary of permeability results from quality assurance (QA) and quality control (QC) testing Structure Material QA/QC Min. Permeability Max. Permeability Avg. Permeability No. of was then hauled to the crest of the m/s m/s m/s Samples soil-bentonite QA/QC 3.4x10-10 2.7x10-10 4.6x10-9 32 dike and stockpiled along one side East Dike QA 1.4x10-10 2.5x10-8 4.4x10-9 8 of the cut-off trench alignment. To Bay-Goose Dike soil-bentonite soil-bentonite QC 1.1x10-10 5.9x10-10 2.4x10-10 11 prepare the soil-bentonite mixture, Bay-Goose Dike cement-soil-bentonite QA 9.8x10-10 2.5x10-8 8.6x10-9 6 cement-soil-bentonite QC 2.2x10-9 4.5x10-8 1.4x10-8 6 5% bentonite slurry was then added to the dry till-bentonite, and the tracks and blade of a dozer were used to mix the slurry and dry 3.9 Subsequent Construction Activities mixture until a uniform semi-fluid mix was achieved. Following completion of the cut-off wall construcThe slump and density of the mix was tested, and upon tion, an additional 1 m high working platform was approval, the excavator would gradually push the soilconstructed over the cut-off wall centreline from which bentonite mixture into the trench at the crest of the subsequent construction activities were carried out. In leading front. Figure 13 shows mixing and placement deeper portions, where the cut-off wall did not reach of the soil-bentonite mix into the trench. bedrock, jet grout columns were constructed between the Canadian Dam Association • Winter 201523 Figure 14: Bay-Goose Dike following dewatering and Goose Pit development (Spring 2012) base of the cut-off wall and the bedrock surface. Grouting of the shallow bedrock and the interface between the bedrock and the base of the cutoff wall and/or jet grout columns was also carried out. Further details of the grouting and jet grouting works are provided in Part 2 of this series of papers (Bonin et al. 2013). Instrumentation to monitor the performance of the dikes was also installed from this platform. Part 3 of this series of papers describes the instrumentation and presents results from the monitoring (Esford and Julien, 2013). Figure 14 shows the Bay-Goose Dike following dewatering along with development of the Goose Pit. 4 SUMMARY AND LESSONS LEARNED Dikes were successfully constructed over three open water seasons, on the shoulders of extreme Arctic conditions (freezing temperatures over most of the year, ice, high winds, frozen ground, blizzards). Isolation and limited access necessitated a high level of logistical support, planning and sequencing. Challenges for the construction included: A limited construction season and short period free of ice (mid-July to mid-October); Continuous permafrost (frozen ground, active zone, ice-rich soils); Thawing of the active zone – high water content, potential for differential settlement and/or lateral spreading; and Limited availability of soil and alluvial materials suitable for dike construction. The key lessons learnt during the construction included: Pre-construction information on the depth to bedrock along the longitudinal profile of the cut-off wall aids in design, construction planning and execution. Geometry of the central trench (base width and side slopes) should minimize the occurrence of rocks from side slopes falling down on to the base, and in particular entering the cut-off wall alignment. During the final verification stage for each segment of the central trench excavation, the excavator bucket should make multiple passes across the surface and the quality assurance/control team should witness this activity (visual movement and sound of bucket moving) for approval. Compare bathymetric survey data recorded within central trench excavation with estimated depth to bedrock from investigation n n n n n n n n 24 639828_Sorensen.indd 1 View past issues of the CDA Bulletin online at www.naylornetwork.com/cda-NXT/ 06/05/13 4:28 PM n n n n n n n n n n n data and with manual soundings (tape and rod) to verify depths and determine if sediment/silt has accumulated at the base of the trench. If silt is present, quantify the elevation of sediment and remove as much as possible, prior to backfilling. Be cognisant of potential silt during densification and cut-off trench excavation. Be aware of areas of potential silt accumulation and if removal is not possible, adjust the grouting program and treat the zone by jet grouting. Carry out cut-off wall construction using cement-soil-bentonite in deeper portions to reduce erosion potential. Use plugs constructed of cementsoil-bentonite for transitions between materials being utilized for backfilling the cut-off wall or for joining multiple work fronts. Dynamic compaction is suitable for densification up to 8 to 10 m below lake elevation, where the central trench was excavated to bedrock. Vibro-densification is required to densify fine filter materials beyond depths where dynamic compaction is effective, or when the central trench was not excavated to bedrock. Track and cross-check elevations of the bedrock and/or target surface through each stage of the construction to avoid potential windows of untreated material within the low permeability element of the dike. Construction pre-planning, and sequencing of the works are essential to make use of the short construction season. Identify potential contingency measure where simplified dike design components are to be utilized. Incorporate experience gained through the construction process (by owner, engineer, contractor) and carry forward the adaptations in subsequent construction seasons. E mploy very experienced (i.e. senior) construction supervision staff on site to make key design decisions. Document and rigorously checktrench, cut-off wall, bedrock and platform elevations throughout works for comparison and verification purposes. I nstall instrumentation (thermistors and piezometers) for real-time monitoring during dewatering. ■ n n n The effectiveness and high efficiency of Smith-Root electric barriers successfully prevented fish from entering the tailrace of the hydroelectric facility. GREN Biologie Appliquée Sàrl REFERENCES Canadian Dam Association, 2007. Dam Safety Guidelines. Bonin, G., Rombough, V. and Julien, M., 2013. “Part 2: Grouting Techniques Employed for Dike Construction at the Meadowbank Gold Mine, Nunavut” CDA 2013 Montreal Conference. Esford, F. and Julien, M., 2013. “Part 3: Performance Monitoring of Dikes During Dewatering and Operation at the Meadowbank Gold Mine, Nunavut” CDA 2013 Montreal Conference. The authors would like to thank Agnico Eagle Mines Limited for its support and leadership during the design and construction of these dikes. The successful completion of these works would not have been possible without collaboration between the owner, the contractor and the designer. VESSY HYDROELECTRIC Arve River, Switzerland WE PROVIDE EXPERTISE AND TECHNOLOGY FOR: • Fish entrainment and impingement prevention • Safe fish passage • Endangered species recovery • Comprehensive watershed management • Controlling the spread of invasive species Smith-Root has fifty years of expertise in fish guidance solutions WWW.SMITH-ROOT.COM info@smith-root.com • (360) 573-0202 • Vancouver, Washington, USA Canadian Dam Association • Winter 201525 714544_Smith.indd 1 29/10/14 3:43 PM