ATMB ¥ News/ANG n¡15
Transcription
ATMB ¥ News/ANG n¡15
Mont Blanc Tunnel news Information on the recovery and modernisation programme of the Mont Blanc tunnel Editorial Mont Blanc Tunnel managers ATMB and SITMB have always said that their primary goal was to reopen a tunnel that meets each and every safety requirement set by the French and Italian governments. Conformity to these standards is being checked by the future single operator via a comprehensive series of tests and dry runs. Moreover, the Security Committee appointed by the French and Italian governments is supervising additional exercises. Some 4,000 technical trials are currently under way; the results so far are largely satisfactory. Some additional fine-tuning is still required, causing a slight delay in the delivery of the tunnel (originally scheduled for December 10). As a result, public authorities will conduct safety exercises after the Christmas holiday period, in January 2002. Then only will the relevant government ministers be able to announce the reopening date. This extra time will enable completion of additional work needed to organise alternate traffic routing with the Fréjus Tunnel. ■ N°15 December 2001 Info The 4,000 tests of the company trials A total of 4,000 tests must be conducted as part of the company trials prior to delivery to Mont Blanc Tunnel managers ATMB/SITMB and G.E.I.E. TMB. Launched in September while restoration work was under way, these tests are designed to control the reliability and performance of all equipment used inside the tunnel. Results fall into three categories: conclusive tests, minor reservations that do not invalidate the trial, and serious reservations that dispute the trial. To ensure optimum equipment reliability, tests that raise serious reservations are carried out again until satisfactory results are obtained in line with safety requirements. Following these tests, G.E.I.E. TMB, the future sole operator of the tunnel, will conduct dry runs and the French and Italian authorities will carry out full-scale exercises. 200 people mobilised to conduct the five-level technical tests So far, close to 2,400 tests have been performed at five successive levels to determine the following: power supply and wiring to other technical components inside the tunnel. Level 1: compliance of each equipment Level 3: equipment is classified by “function” (ventilation, lighting, thermometry, etc.) to ensure that all functions operate as specified when activated. item with its prototype and specifications defined by engineer Scetauroute-Spea. Level 4: Independent assessment of Level 2: correct installation of each equipment item, including inspections of the Centralised Technical Management (GTC) systems (without connection to other equipment). The last steps before reopening In addition to the technical trials conducted by the companies, the dry runs performed by the G.E.I.E. consortium and the exercises by the public authorities, reopening of the Mont Blanc Tunnel to traffic is subject to the finalisation of: • traffic regulations taking into account the alternate routing scheme; • toll structures, including combined Mont Blanc/Fréjus passes; • parliamentary ratification of communications exchanged between France and Italy to endorse the creation of mixed police squads assigned to impose fines on traffic offenders inside the tunnel. Telecommunications, emergency call network and public address system These tests concern the performance of data transmission and telecommunications networks. The following tests have been completed: • all Level 1 tests (a total of 170), • 94% of Level 2 tests (170). Level 5: integrated operation of the GTC systems with other equipment. In total, more than 200 people are involved in the test campaign. These include 30 technicians from the FrancoItalian engineer Scetauroute-Spea and managers ATMB and SITMB and their assistants;more than 100 people from the eight consortiums commissioned to supply equipment; and over 85 people from G.E.I.E. TMB’s departments of Security/ Traffic, Information Technology and Customer/Toll Gate. A delegation from the Security Committee has also been appointed to observe Level 5 tests. Electrical work Most of the current tests are in this field. The following have been completed: • 99% of Level 2 tests (totalling 567), • 82% of Level 3 tests (nearly 100), • 91% of Level 4 tests (240). Areas covered by these tests include unhooking fire extinguishers, door contacts, circuit breakers, transformers, high and low voltage panels, roof-mounted lighting and lighting in ducts, etc. Minor reservations concern cleaning of equipment bays and misplaced cable labels. Centralised Technical Management (GTC) These tests are designed to check the operation of the 37 programmable logic controllers (PLCs) installed in the emergency shelters, tunnel-end servers, memory boards, data network and computer terminal connections. The following tests have been completed: • all Level 1 tests (a total of 50), • all Level 2 tests (50) with 96% of minor reservations now removed, • 80% of Level 3 tests (225). CCTV and automatic incident detection system The 120 cameras have all been checked. However, they cannot be configured until the road surface is completely ready for service (cleanliness, white lines, etc.). The following tests have been completed: • all Level 2 tests (55), • 60% of Level 3 tests. Ventilation work Level 1 and 2 tests have been conclusively completed, along with: • 70% of Level 3 tests, • 93% of Level 5 tests. A special category of ventilation tests was defined for this work. The aim is to test the general functioning of the ventilation systems on the basis of predefined models beyond the actual equipment items themselves. Aspects covered include, for example, the volume of air to be extracted, checks on duct airtightness, efficient distribution throughout the length of the tunnel of air injected into the ducts, etc. The following tests have been completed: • 17% of the 61 planned tests on stagnant air, • 31% of the 48 planned tests on fresh air. Fire-fighting system The fire-fighting system ducts have been pressurised, remote control by GTC systems has been checked, and tests have been performed on all manual and automatic control valves, booster pumps, sensors, and hydrants, etc.: • all Level 3 tests (107) have been conclusively completed, • all Level 5 tests (21) have been completed. to which the cable is connected, along with configuration of the detection pitch. Signalling systems The following tests have been carried out on the variable message boards, traffic lights, charts, barriers, etc.: • all Level 1 and 2 tests, • 99% of Level 3 tests (440), • 86% of Level 5 tests (42). Radio communications system Tests of analogue, digital and FM channels have been carried out on the amplifiers, antennas, retransmission boxes, microphones and computer terminals installed at both tunnel ends. The following tests have been completed: • 97% of Level 2 tests (65), • 79% of Level 3 tests (118). These tests will be concluded by external safety services. Lighting work A luminescence test was carried on the first 1,000 meters of the French entrance to the tunnel to check that the light intensity adapted to the outside light. The same test will be conducted on the Italian entrance once the work site has been cleaned. ■ Thermometric fire detection network The 50 Level 2 tests and 85 Level 3 tests have been conclusively completed. They concerned the detection cable and computers Executive editor: Laurence Guillerm (ATMB) - Design and editorial content: Autoroutes et Tunnel du Mont Blanc - Head office: 100, avenue de Suffren - 75015 Paris - www.atmb.net Construction Division: Immeuble "Le Majestic", 74400 Chamonix - Tel.: +33 (0)4 50 53 51 80
Similar documents
The Mont-Blanc Tunnel refurbishment The Mont-Blanc Tunnel
companies involved Owners: Société des Autoroutes et Tunnel du Mont Blanc (ATMB), Società Italiana del Traforo del Monte Bianco (SITMB) Assistance to the owner (ATMB): SYSTRA Assistance to the owne...
More information