Dispute Boards in Latin America: Changuinola
Transcription
Dispute Boards in Latin America: Changuinola
Dispute Boards in Latin America: Changuinola Hydro Power Project Republic of Panama Dos Mares HPP Panama Panama Canal Expansion Panama Tegucigalpa Comayaqua Highway 3 Contracts Honduras Chacayes HPP Republic of Chile Romano Allione Copyright © Dispute Resolution Board Foundation 2011 Dispute Boards in Latin America Changuinola Hydro Power Project Republic of Panama http://www.aeschanguinola.com/ Copyright © Dispute Resolution Board Foundation 2011 Dispute Boards in Latin America Dos Mares HPP Panama Copyright © Dispute Resolution Board Foundation 2011 Date of entry 15/01/2009 Beneficiary ALTERNEGY SA, BONTEX SA Description : The project consists of the construction and operation of a cascade of three run-of-river power plants with a total installed capacity of 115 MW, located in the province of Chiriqui in Panamá. Objectives: Contribution (i) to support EU presence in Latin America through Foreign Direct Investment and (ii) to the economic development of Panamá through improved electricity supply from a renewable source. Proposed EIB finance: €170 million. Total cost: € 340 million. http://www.eib.org/projects/pipeline/2008/20080581. htm Dispute Boards in Latin America Panama Canal Expansion Panama The program consists in the construction of two new sets of locks - one on the Pacific and one on the Atlantic side of the Canal. Each lock will have three chambers and each chamber will have three water reutilization basins. The program also entails the widening and deepening of existing navigational channels in Gatun Lake and the deepening of Culebra Cut. In order to open a new 6.1 km-long access channel to connect the Pacific locks and the Culebra Cut, four dry excavation projects will be executed. http://www.pancanal.com/eng/index.html Copyright © Dispute Resolution Board Foundation 2011 Dispute Boards in Latin America Tegucigalpa Comayaqua Highway 3 Contracts Honduras The Honduras government, representatives of the Millennium Challenge Cooperation, and BCIE signed an agreement Tuesday to spend 217.9 million dollars to build a fourlane highway between Tegucigalpa and Comayagua. The work will be done in two phases, one of 50.2 kilometers and the other of 57.7 kilometers. It is expected to be completed in 24 months. At the signing, which was done in the BCIE headquarters, were President Manuel Zelaya Rosales, the Assistant Secretary of State, and the president of the Millennium Challenge Corporation, John Dimitri Negroponte. http://en.centralamericadata.com/en/static/home Copyright © Dispute Resolution Board Foundation 2011 Dispute Boards in Latin America Chacayes HPP Republic of Chile Located in the Andes Mountains, the Chacayes hydro project will be the first phase of Pacific Hydro's new project development in the Cachapoal Valley. The delivery of this run of river hydro project in October 2011 is critical to solving the supply of capacity into the Chilean energy grid and the reduced reliance on energy from fossil fuels. Chacayes will generate 558GWh per annum of renewable energy for Chile's power market, which is enough electricity to supply twice the demand of the city of Rancagua and will abate approximately 340,000 tonnes per annum of greenhouse gas pollution. http://www.pacifichydro.com.au/en-us Copyright © Dispute Resolution Board Foundation 2011