CITY OF SAINT LOUIS
BOARD OF PUBLIC SERVICE
Matt Poirot, P.E.
Engineering Manager
TRANSPORTATION PROJECTS ANTICIPATED TO
START CONSTRUCTION IN 2016
Road Improvement Projects
•
•
•
•
•
•
South Broadway Streetscape, Ph 2 (Courtois to River Des Peres Bridge)
North Broadway Improvements (Thrush to Walter)
Washington Streetscape (Grand Center from Grand to Sheldon Concert Hall)
Kiener Plaza Roadway Improvements (City Streets Around Kiener Plaza)
Newstead Improvements (Natural Bridge to St. Louis Ave.)
Washington Streetscape, Ph 3 (Downtown STL from 7th to Memorial)
Bridge Improvement Projects
• Forest Park Parkway over Metro (In Forest Park Just West of Kingshighway)
South Broadway Streetscape – Phase 2
Courtois to River Des Peres Bridge
Estimated Construction Cost $1.7 M
.70 miles Streetscape Involving:
•Street Lighting
•Sidewalk Reconstruction
•Traffic Signals at Marceau and Davis
•Landscaping
•Street Furniture
North Broadway Improvements
Thrush Avenue to Walter Avenue
Estimated Construction Cost $2.2 M
.33 miles of Street Improvements
In Historic Baden District:
•
•
•
•
•
•
Road Diet
Street Lighting
Bumpouts and Sidewalk Reconstruction
Traffic Signals at Halls Ferry and Baden
Landscaping and Street Furniture
Transit and Bicycling Improvements
Washington Streetscape in Grand Center
Grand Avenue to Sheldon Concert Hall
Estimated Construction Cost $1.2 M
1 Block Streetscape Involving:
•
•
•
•
Street Lighting
Sidewalk Widening, Bumpouts, Pavers
Asphalt Mill and Overlay
Landscaping and Street Furniture
Kiener Plaza Roadway Improvements
Estimated Construction Cost $1.2 M
.50 miles of Street Imp. involving:
•Asphalt Mill and Overlay
•Signal Improvements at all intersections
•Bumpouts at intersections
•Parking Protected Bike Lane on Chestnut
•This Project compliments the City Arch
River Project in Kiener Plaza
Newstead Avenue Improvements
St. Louis Avenue to Natural Bridge Avenue
Estimated Construction Cost $1.5 M
.44 miles of Street Imp. Involving:
•
•
•
•
•
Pedestrian and Roadway Lighting
Sidewalk Reconstruction
Landscaping and Street Furniture
Asphalt Mill and Overlay
Transit Upgrades
Washington Streetscape – Phase 3
Downtown St. Louis from 7th to Memorial
Estimated Construction Cost $1.9 M
.30 miles Streetscape Involving:
•Street Lighting
•Sidewalk and Curb Reconstruction
•Landscaping and Street Furniture
•Wayfinding Signage
Reconstruction of Forest Park Parkway
Bridge Over Metro in Forest Park
Estimated Construction Cost $3.0 M
Bridge Reconstruction Involving:
• New Bridge Over Metro in Forest Park
(Shown in Orange)
• Ties into BJC’s Campus Renewal Project
involving removal of Kingshighway Bridge
at Forest Park Parkway to be converted
to an “At-grade” intersection
• Multi-use Greenway Tunnel Under Forest
Park Parkway
• Extensive Landscaping in Forest Park
City of St. Louis Bidding Procedures
and Special Requirements
How to find out about City of St. Louis Public Works Projects:
• Advertised in Post-Dispatch, St. Louis American
• Bidding Documents distributed to MOKAN
• Project Plans, Specs, and Addenda found on BPS website
www.stl-bps.org
• Purchase plans/specs directly through the BPS website from INDOX
Services
Disadvantaged Business Enterprise (DBE)
Minority Business Enterprise (MBE)
Woman Business Enterprise (WBE)
Federally-Funded Projects are required to meet DBE goals
• MoDOT sets these goals and are typically 10%-20% DBE, depending on project scope
• All projects identified in this presentation are federally-funded and will be
required to meet DBE goals established by MoDOT
City-Funded Projects are required to meet Mayor’s Executive Goals
• 25% MBE
• 5% WBE
Questions?
Matt Poirot, P.E.
Engineering Manager
Board of Public Service
618-560-8679