Site Visit Report #043

Transcription

Site Visit Report #043
Site Visit Report #043
PROJECT: Lakewood High School
DATE: August 1, 2016
Project: 2014-05
OBSERVATIONS:
1. North Classroom Wing, 2nd Floor, west end: steel deck is welded.
2. Formwork removal underway at various stem walls.
3. Masons have laid CMU wall in vicinity of toilet rooms at west side of Commons up to almost 8’.
They are placing plastic sheet to protect Food Service area slab from mortar, in preparation for
laying wall between Food Service and Locker Rooms.
4. Most Commons-area roof framing is installed. Welder working on perimeter of steel plate at west
end of south wall. Library floor framing in place.
5. Allied’s steel stud / drywall subcontractor has installed several partitions between classrooms, NCW
1st Floor.
6. Some ductwork and overhead water piping installed at NCW 1st Floor.
7. Electricians are laying conduit in Aux Gym and installing conduit which will pass up into CMU walls.
8. Center-West Parking: curbs along southerly driveway have been formed; some sections poured.
9. Stadium turf installation continues. Workers are installing sideline markings for soccer (yellow).
North Classroom Wing from northeast. Beginnings of partition framing visible.
Closer view of NCW partition framing.
View south from NCW east stair landing. Edge of Library floor framing visible at right.
Library floor framing, Commons beyond, viewed from Gridline H/13 – near NE corner of Library.
West portion of NCW, steel deck is welded, ready for welded-headed studs.
Commons framing viewed from Main Entry
CMU production and materials storage setup, west of Commons / Main Entry
Panorama from NE corner of Theaters. Workers at right are forming tall stem wall, adjacent to the
recessed portion of seating area.
Looking east toward Commons. Hall between Performing Arts (left) and Gyms (right) is in center.
Southwest corner of Fitness / Wrestling Room. Fill placement against inside of wall is underway.
View from SE corner of Fitness/Wrestling. Workers building form for stem wall at south side of Weight
Room.
Panorama from Service Yard.
View north towards Commons. Progress on Commons & Library framing is evident.
SCW from SE corner of Fabrication Shop.
Courtyard from east.
Center-west parking, viewed from east.
Ticketbooth from south.
Stadium viewed from track level, at NW.
Stadium viewed from NE
Field Turf workers installing marking striping.
Excavating and placing drain rock near Visitor seating.
SE corner of field – soccer corner-kick markings