Untitled

Transcription

Untitled
02
03
50 years
of solid
experience
In the
recent
years,
KDS has expanded its activities to the residen-
Major KDS projects
for 2014-2015:
• Construction of the strategically
tial sector and implemented several successful
important Gas Transmission Pipeline
apartment building projects in Vilnius and in
Klaipėda-Kuršėnai. Length: approx. 111
the resort town of Palanga. Numerous fuel
km, diameter: 800 mm, MOP: 5.4 MPa.
base reconstruction projects for the Lithuanian
Railways were also completed.
• Panevėžys Gas Distribution Station
Reconstruction. Maximum capacity:
In cooperation with LMR Drilling GmbH, KDS
50 000 nm³/h.
implemented the first stage of the strategic
NordBalt Submarine Cable Connection be-
• Reconstruction of Ukmergė Boiler
tween Sweden and Lithuania, installing protec-
Plant No. 1. The project includes
KDS is the leading member of the
tive 400 kV cable casing pipes DN300 (2x800 m
installation of a new 6,5 MW biofuel
KDS Business Group. The company
and 2x1700 m). The second stage is currently
boiler, a 1,3 MW economizer and all
was founded on the basis of a state
being implemented in joint cooperation with
other necessary equipment.
company that started its activity
another Lithuanian contractor and KDS is
in 1964. In 1992, after privatization,
performing land cable laying operations (a total
it was registered with the State
of 13 km of 400 kV cable within the territory of
Heating Supply Network
Register as stock company Kauno
Lithuania).
Modernization.
• Raseiniai Area DN250 District
dujotiekio statyba.
KDS utilizes its own construction and instalThe company takes pride in its
KDS Business Group unites 10
lation machinery and benefits from its huge
seaside residence buildings in the
50-year experience of gas and oil
companies of diverse business
transportation vehicle depot: pipe-layers, ex-
resort of Palanga.
pipeline, gas compressor and distri-
profiles ranging from industrial
cavators, earthmovers, heavy-duty trucks, off-
bution station, boiler plant con-
construction to residential devel-
road and pipe transportation vehicles, welding
struction, district heating, potable
opment and to recreational facil-
aggregates, compressors and pipe bending
Networks in the Towns of Ukmergė
and wastewater network design and
ities. The Group’s annual turnover
machines, to name a few. As a result of recent
and Anykščiai. Diameter: DN160-
installation and residential property
amounts to EUR 60 million and in
cooperation with Magnatech Pipeline Equip-
DN200, total length: 40 km.
development.
total there are almost 300 people
ment BV, modern automatic welding equipment
working for these companies.
was also acquired.
When choosing materials, KDS relies upon certified manufacturers with established experience and appreciated know-how.
KDS
• Construction of three luxurious
• Installation of Water Distribution
05
04
Gas distribution and gas
compressor stations
2014-2015
Panevėžys Gas Distribution Station Reconstruction
Maximum capacity: 50 000 nm³/h.
Client: AB Amber Grid, Lithuania.
Project
references
Gas
pipelines
2011-2012
Girininkai Gas Distribution Station Reconstruction
Inlet pressure: 20-55 bar, outlet pressure: 10 bar,
maximum capacity: 45 000 nm³/h.
Client: AB Lietuvos dujos, Lithuania.
2009-2010
Jauniūnai Gas Compressor Station
The project was significant to the entire Republic of
Lithuania as the gas compressor station increased the
gas pipeline capacity in the territory of Lithuania and
enabled the full supply to the national network as well
as transit to Kaliningrad.
The main functions of the station include gas cleaning, gas compression and gas cooling. The station is
Lithuanian
Railways fuel
bases
2011-2012
Vilnius Fuel Base Reconstruction
The reconstruction project was awarded by the
Lithuanian Confederation of Industrialists as the
“Product of the Year 2012”.
The old aboveground and underground fuel reservoirs
were replaced and the total number was increased to
eight: 6x83m³ reservoirs + 2 interim and fuel transfer
reservoirs. New tank-car loading and unloading units as
well as a new railway branch were constructed. A new
technological pipeline was designed and installed and so
was a new and completely automated system. Contaminants were removed from the soil in the area.
equipped with three compressors, 11,5 MW each. Minimum inlet pressure: 28 bar, maximum outlet pressure:
2013-2014
55 bar. Gas transfer rate: 1,3 million m³/h.
Gas Transmission Pipeline
Szczecin-Lwówek
2011-2012
Diameter: DN700, MOP: 8,4 MPa,
Gas transmission pipeline Kolnik-Gdansk
total length: 38,6 km.
Diameter: DN500, MOP: 8,4 MPa,
Client: Sp. Z.o.o ZRUG, Poland.
total gas pipeline length: 6,5 km.
Client: Sp. Z.o.o. ZRUG, Poland.
2012-2013
Construction of Gas Transmission Pipeline
2009
Branch from Tauragė Gas Distribution Station
Gas Transmission Pipeline Šakiai-Kaliningrad
to Klaipėda Gas Distribution Station No. 2 and
and Šakiai Gas Distribution Station
Klaipėda Gas Distribution Station
Diameter: DN700, MOP: 5,5 MPa, total length: 18,6
Diameter: DN400, MOP: 5,5 MPa, total length:
km including construction of valve fields and gas
35,9 km including construction of two DN400
metering station expansion to 470 000 nm³/h.
valve fields.
Client: AB Lietuvos dujos, Lithuania.
2009
Šakiai Gas Distribution Station Reconstruction
Gas metering station expansion to 470 000 nm³/h.
Client: AB Lietuvos dujos, Lithuania.
2008
Zapyškis Gas Distribution Station Reconstruction
Inlet pressure: 20-55 bar, outlet pressure: 3 bar, maximum capacity: 3000 nm³/h.
Client: AB Lietuvos dujos, Lithuania.
2012-2013
Kaunas Fuel Base Reconstruction
The old fuel bases were dismantled and replaced, four
new 80 m³ underground fuel reservoirs, a brand new
technological pipeline, new oil storage and fuel pumping
units and fully automated systems were designed and
installed.
2012-2013
Vaidotai Fuel Base Reconstruction
The old oil pumping station was dismantled; one of the
three 3000 m³ fuel reservoirs was replaced with two 1000
m³ reservoirs. A new technological pipeline and fire safety systems were designed and installed, as were the two
Client: AB Amber Grid, Lithuania.
KDS
Client: AB Lietuvos dujos, Lithuania.
Total length of medium pressure gas distribu-
new railway branches. New completely automatic and
tion pipelines constructed in the territory of
self-sufficient tank-car loading and unloading systems
Lithuania - approx. 181 km.
and fuel pumping units were installed.
06
07
Potable and wastewater
supply systems
Employees
In total, KDS has already constructed and reconstructed:
• 60 km of potable water networks
• 80 km of wastewater networks
• 25 wastewater pumping stations and treatment plants
Utilities
2013
First stage of the NordBalt Submarine Cable Connection
Installation of DN300 protective cable casing pipes (two
800 m strings for the outfall and two 1700 m strings for the
lagoon crossing) which were later installed under the
Curonian lagoon via HDD.
Client: LMR Drilling GmbH, Germany.
2014-present
Second stage of the NordBalt Submarine Cable Connection
Land cable laying operations, a total of 13 km within the
KDS is based in Kaunas, Lithuania,
awareness of our unlimited
and performs its operations within
potential to grow. We dedicate
entire national territory and the
our utmost attention to selecting
neighboring countries. The current
the most diversely experienced,
number of our employees is 200.
skilled and talented people,
Each and every one of us rep-
knowing that a great team is key
resents the spirit of the company:
to ensuring our success and im-
drive, commitment, and perfect
provement.
Certifications,
Licenses,
Approvals
territory of Lithuania.
Client: ABB AB HVC, Sweden.
Residential property
development
• Trinapolis Apartment Building in Vilnius,
a total of 43 388 m².
• Žirgų takas Apartment Complex in the resort
town of Palanga, a total of 4406 m².
• Smilčių trio Seaside Apartment Complex in the
resort town of Palanga, a total of 2583 m².
www.smilciutrio.lt/en
KDS is certified by the Lithuanian Certifi-
In 2005, the environmental man-
cation Center of Building Products (SPSC),
agement standard ISO 14001:2004
Public Institution Technical Supervision
was also introduced, as were the
Service (TPT) and State Energy Inspec-
OHSAS 18001:2007 in 2010 and
torate Under the Ministry of Energy of the
ISO 3834-2:2005 in 2014.
Republic of Lithuania.
Also in 2014, KDS became qualiIn January 1997, TÜV Thüringen e.V award-
fied by the Scandinavian Achilles
ed KDS with ISO 9001 certificate, making it
Joint Qualification System (JQS).
the first quality system certificate issued
to a Lithuanian construction company at
that time. ISO 9001 audits are performed
every year and this allows for constant
improvement of the quality control system. The company is currently operating
according to ISO 9001:2008.
AB Kauno dujotiekio statyba
Elektrėnų g. 7
LT-51193 Kaunas
Lithuania
Tel. +370 37 451970
Fax +370 37 797673
info@kds.lt
www.kds.lt