City of Muncie
GSC CSO
Total Contract: $10,587,335
MUNCIE
INDIANA
Multiple Guaranteed Savings Contract Community
City of Muncie
GSC CSO / Muncie, IN
Project Size: $10,587,335
Bowen, teaming with United Consulting used a collaborative approach to bring
this project in under budget and under schedule.
CSO Separation
Diversion Structures
The project consisted of installing piping and structures that convey stormwater
from the ARC Hotel & Parking Structure, at Victor Street, and continue along High
Street and then Franklin Street ending at Gilbert Street where it discharges storm
water into the White River. The project includes the appropriate road work along
with a canal structure that discharges into the White River.
PROJECT SPECS
Scope:
• CSO Separation
• Diversion Structures
Project Highlights
• Open-Book Pricing
Project Team
• Project Manager: Paul Creasey
• Superintendent: Howard McClanahan
Storm water runoff in the areas affected by this project will have the ability to
separate the stormwater and the sanitary flow into two different sewer pipes.
Currently this runoff is combined with sanitary sewage into one sewer pipe.
Overflows from the current sewer system release raw sewage into the White
River during significant storm events.
The sewer separation will helps Muncie Sanitary District comply with a mandated
requirement from the Indiana Department of Environmental Management. When
the overall project is completed, over 70 million gallons of storm water annually
will be diverted from the Muncie Sanitary District wastewater treatment plant
reducing wastewater treatment costs.
Nikki Grigsby, District Administrator
Muncie Sanitary District
765.747.4742
ngrigsby@msdeng.com