235 Replacement Pressure Control at PG&E`s Moss Landing.indd
Transcription
235 Replacement Pressure Control at PG&E`s Moss Landing.indd
Replacement Pressure Control and Superheater Bypass Valves Permit 93% Cyclic Load Cutback at PG&E’s 750 MW Units at Moss Landing ................................................... By Herbert L. Miller and Curtis G. Sterud Presented at the American Power Conference, Chicago, Illinois; April 24–26, 1989 22591 Avenida Empresa Rancho Santa Margarita, CA 92688 949.858.1877 ! Fax 949.858.1878 ! ccivalve.com 235 | 06/00 ! ©2000 CCI ! DRAG is a registered trademark of CCI. Replacement Pressure Control and Superheater Bypass Valves Permit 93% Cyclic Load Cutback at PG&E’s 750 MW Units at Moss Landing " By Herbert L. Miller, Vice President, Engineering, and Curtis G. Sterud, Principal Engineer, CCI Presented at the American Power Conference, Chicago, Illinois, in April, 1989. Sponsored by the Illinois Institute of Technology Technology Center, Chicago, IL 60616 Introduction A mong the many system and equipment modifications required to adapt Moss Landing, Units 6 and 7 for very low-power cyclic operation were the complete replacement of the pressure control valves and the superheater bypass valves. These units were originally designed for base loading and were limited to occasional cycling down to about a 30 percent load. Now they are capable of daily cycling down as low as a 7 percent load. Cycling frequency and the increased pressure drops involved served to greatly magnify the service severity imposed on the pressure control valves and superheater bypass valves. Figure 1—Pacific Gas & Electric’s Moss Landing Generating Station. Cyclic Operation at Moss Landing As originally installed for base-load service over twenty years ago, Figure 1, these gas- and oil-fired, 750 MW, super-critical units were capable of limited cyclic operation in the 240 MW to particularly troublesome in that continuous leakage to the flash tank through the old 202 valve in the original design, produced a significant heat-energy loss to the system. 750 MW range. The increased availability of lower-cost, off-peak Modified High-Cycle System Design power from alternative sources made it economically imperative Figure 2 compares the pertinent portions of the Moss Landing to reduce minimum loads on these units, since shutting them Units 6 and 7 cycle, both before and after modification for very down at night and during weekends was not considered practical. low, cyclic-load operation. Many possible methods were considered. The modification ultimately selected involved one that utilized the existing flash tank, a modified control system, and the replacement of the pressure control valves and the superheater bypass valves, among other things. As a result of these modifications, Moss Landing, Units 6 and 7 are now capable of operation from 50 MW to full load, and a minimum load under manual control as low as 30 MW has been demonstrated (¹). Figure 3 shows how turbine throttle pressure varies with load from full load down to minimum operation at 30 MW. Note that from 30 MW to about 165 MW (22 percent load), the flash tank operates essentially like a boiler drum and its pressure at 1000 psi is controlled by the 207 valve (the 200 and 201 valves are closed, and the 205 stop-check valve is wide open). The pressure drop between the steam generator and the flash tank (that is, across the 207 valve) is approximately 2950 psi as it controls steam- Prior Valve Design and Experience generator pressure. Flash tank pressure is maintained by the 240 As originally installed, the superheater bypass valves (202) and valve, and the flash tank level is controlled by the 241 valve. the pressure control valves (201), were of the single-seated, single- Turbine load is controlled by the turbine throttle valves. stage type. Typically, this valve type encounters internal velocities At about 165 MW, the turbine throttle valves are set up to 100 as high as critical or sonic speeds, depending upon whether percent open, and the 201 corresponding to load demand. Steam- the fluid is water or steam. Even under the relatively infrequent generator pressure is maintained by the boiler feedpumps. This operating conditions encountered before cycle modification, operating mode continues up the ramp to 66 percent of full load. satisfactory control was difficult and valve service life was severely compromised by seat and plug erosion. This valve design was 2 It is very important that this 22 percent load transfer (from flash Replacement Pressure Control and Superheater Bypass Valves Permit 93% Cyclic Load Cutback at PG&E’s Moss Landing | 235 ©2000 CCI. All rights reserved. Before After Figure 2—Original steam generator startup system vs. high-cycling system. tank operation to 201 valve control) be accomplished without a disk modulates flow by exposing more disks as required flow steam-generator pressure swing to avoid a turbine trip. To have increases. such a bumpless transfer at this point, the rate of change of the Valve Design Considerations flow capacity between the opening 201 valves and the closing 207 valves must be the same. This is directly related to stroke speed, trim capacity and capacity-change rate. Therefore, these two valves must always be considered together. An overriding design consideration in these pressure-control and super-heater bypass services (201 and 207 valves) is to assure absolute velocity control, repeatability, and resolution for the high differential pressures at the variable flows encountered. This At 66 percent load, the 201 valve is wide open, and control is best accomplished in a stack of individual pressure-breakdown transfers to the turbine throttle valves. At this point the 200 valve disks that break the total flow into small flow channels. These opens without impact on system operation. small individual flow channels each incorporate the desired While this describes the three-step procedure practiced by PG&E number of abrupt, flow-direction changes, creating a tortuous at Moss Landing, alternate methods of achieving the same end path, to produce controlled pressure drops through shock loss result have been developed by other utility companies operating at each flow turn. In this way excellent control is achieved. The super critical power systems (², ³, 4, 5). In these cases, the shape number of flow turns shown in the typical disk in Figure 4 can of the curve in Figure 3 is dictated by the utility’s efficiency be varied widely to produce varying pressure drops. Disk stacks requirements and load demand. Replacement Valve Design can therefore be characterized and made up of combinations of several disk designs to provide varying pressure drops at any point throughout the range of flow control. In this way the shape Both the pressure control valves (201) and superheater bypass of the percent stroke vs. percent flow curve can be altered to valves (207) are of the “tortuous path” design. In the basic match a specific need. tortuous path valve design (Figure 4), eight disks per inch of valve stroke make up a disk stack which dissipates pressure through shock loss abrupt flow turns within the individual disks. The 201 valve disk stack contains 80 disks, and the 207 valve disk stack contains 50 disks. Since these flow paths are fixed in each disk in the stack, individual disk flow is constant at any degree Other important design considerations include such items as valve seat design, which must ensure tight closure under highpressure differentials every time the valve closes. Over the years there have been many materials and design approaches to this critical area of valve designs (6, 7). of modulation through the valve. Water velocities are thus limited Pressure Control Valve Design Details to less than 100 ft/sec. Valve plug position within the stack of Figure 5 shows the construction of the 201 valves at Moss ©2000 CCI. All rights reserved. 235 | Replacement Pressure Control and Superheater Bypass Valves Permit 93% Cyclic Load Cutback at PG&E’s Moss Landing 3 Flash Tank Operation throughout the ramp from 886 psi to 3800 psi (full turbine throttle pressure) and contributes significantly to a bumpless Straight-Through Operation transfer from 207 to 201 valve operation at 22 percent load. 25 Since this 201 valve operates in series with upstream and downstream block valves, absolute tight closure is not a prime 3000 20 15 2000 design consideration for pressure-control valve applications. mPa Throttle Pressure PSIG 4000 However, this 201 valve could easily be designed as a pressurized seat valve (as discussed later under the 207 valve), eliminating the need for and expense of these upstream and downstream 10 1000 5 block valves. Superheater Bypass Valve Design Details Figure 7 shows the construction of the 207 valves, which are 10 20 30 40 50 60 70 80 90 100 Percent Load closed at any load above 165 MW and must seal against the very high differential pressure that exists during normal operation. An exceptionally high closing pressure is needed here that would Figure 3—Throttle Pressure Variation with Load Landing. It is a tortuous-path, balanced plug design. It modulates flow between 22 and 85 percent throttle flow and differential pressures across the valve vary from about 2800 psid down to near zero when the 200 valve opens. Initially the 201-valve, 80-disk stack incorporated two disk designs, but since flow and differential pressures both vary, linearity in terms of percent flow vs. percent valve stroke was less than optimal. This led to higher-than-desired valve position change in response to varying demand and produced a degree of “hunting” in turbine-throttle pressure, which affected boiler feedpump speed control. To overcome this problem, the disk stacks have been re-characterized to include two additional disk designs in this 80-disk stack. Linearity has been considerably improved (Figure 6). This has stabilized turbine throttle pressures Figure 5—Sectional drawing of 201 valve. require an over-sized actuator. Therefore, this valve employs a pressurized seat design which uses an internal pilot valve to load and unload the closing force on the plug. When the valve is closed, full upstream pressure behind the plug exerts about 100,000 lb. of closing force on the plug. When the actuator is called upon to open the valve, the internal pilot opens first, bleeding this high pressure downstream through ports within the plug itself. This immediately balances the forces acting on the plug, permitting normal actuator loadings to control valve flow modulation. This 207 valve also functions as a dump valve on turbine trip to conserve condensate and minimize safety-relief valve operation. Therefore, it must be capable of absorbing an internal thermal shock during very rapid heat-up, to insure valve integrity under Figure 4—Typical torturous disk design. 4 these conditions. Belleville springs between the disk stack and the Replacement Pressure Control and Superheater Bypass Valves Permit 93% Cyclic Load Cutback at PG&E’s Moss Landing | 235 ©2000 CCI. All rights reserved. pressure valves in power plant service, has dropped dramatically. In fact, it is necessary to look at valve-stem motion to determine whether or not valves are in operation. Troublesome valve and piping vibration has been eliminated. Previous energy losses through the 207 valve have been stopped through the exceptionally high seating forces produced by this pilot-operated plug design. Conclusions At Moss Landing, Units 6 and 7 have successfully operated in this low-load mode for over two years. The application of these valves has been an important part of this achievement. References Figure 6—Enhanced linearity of 201 valves achieved through disk recharacterization. valve body allow rapid, disk stack expansion independently of the slower valve body temperature increase. Both the 201 and 207 valves at Moss Landing are electrically actuated. However, this valve design is not sensitive to actuator design, electrical, pneumatic, or hydraulic, as long as rate of change in capacity can be closely controlled by actuator stroke. Since the installation of these new tortuous-trim valves, operating noise, frequently an undesirable characteristic of high differential- 1. Laszlo, J. and Chan, B. K., “PG&E Experience in Cycling Conversion of Gas Fired Supercritical Power Plants.” Paper presented at the Electric Power Research Institute Seminar on Fossil Plant Cycling, Princeton, N.J., October 20–22, 1987. 2. Baer, R. H. and Turbiville, D., “Modifying Supercritical Pressure Boilers for Sliding Pressure Control.” Power Engineering, pp. 58-60, January 1985. 3. Schaeper, W. and Vera, R. and L. G., “Modifying Supercritical Pressure Units for Cycling Operation.” Power Engineering, pp. 54–57, June 1984. 4. Martinez, O. and Makruch, J. A., “Variable-Pressure Operation Both Flexible and Efficient.” Power, pp. 62–63, January, 1982. 5. Laney, B. E. and Vera, R. L., “Adaptation of a Supercritical Unit to a Present and Future Generation Management Plan.” Paper presented at the 25th Power Instrumentation Symposium, Instrument Society of America, Phoenix, Arizona, May 24–26, 1982. 6. Miller, H. L. and Sterud, C. G, “A High-Pressure Pump Recirculation Valve.” Paper presented at the Electric Power Research Institute Power Plant Valve Symposium, Kansas City, Mo., August 1987. 7. Miller, H. L., and Sterud, C. G., “How Feedpump Recirc Valves Withstand Severe Duty.” Power, pp. 79–88, August, 1987. Figure 7—Sectional drawing of 207 valve. ©2000 CCI. All rights reserved. 235 | Replacement Pressure Control and Superheater Bypass Valves Permit 93% Cyclic Load Cutback at PG&E’s Moss Landing 5