Highbanker/ Dredge Combo - The Honcoop Highbanker Company

Transcription

Highbanker/ Dredge Combo - The Honcoop Highbanker Company
P.O. Box 1139-615 Cass St.
Owosso, MI 48867
www.honcoophighbanker.com
Toll Free Phone: 1-888-988-2122
Phone: 1-989-723-3404
Email: Honcoopgold@eathlink.net
Highbanker/ Dredge Combo/
Shovel Platform
Assembly Instructions
P.O. Box 1139
615 Cass St. Owosso, MI 48867
www.honcoophighbanker.com
1-888-988-2122
HONCOOP HIGHBANKER
Shovel Platform Assembly
Leg Assembly
Rear legs are longer and heavier than
the front legs. Push on white caps.
Page 2
Page 23
1-888-988-2122
HONCOOP HIGHBANKER
Shovel Platform Assembly
3/4 x 1/4 x 20 SS Machine Screws
The Header Box Side Walls attach
under the Spray Bar top screw clamp
and the Dredge Flume holes. Rest the
Shovel Platform on the Spray Bar and
screw in place.
Page 22
3/4 x 1/4 x 20 SS Machine Screws
Side Panel Assembly
Page 3
1-888-988-2122
HONCOOP HIGHBANKER
Shovel Platform Assembly
3/4 x 1/4 x 20 SS Machine Screws
Rear Panel Assembly
Slide panel down on the inside of the
two side panel lips.
Page 4
3/4 x 1/4 x 20 SS Machine Screws
Twist the Shovel Platform Spray Bar
onto the Highbanker Valve Assembly
and mount.
Page 21
1-888-988-2122
HONCOOP HIGHBANKER
Shovel Platform Assembly
3/4 x 1/4 x 20 SS Machine Screws
Remove the Dredge Flume, Hoses and
Valve Assembly.
Page 20
Header Box Assembly
Page 5
1-888-988-2122
HONCOOP HIGHBANKER
2” Dredge Assembly
Lay Flat Hose
to Pump
Bucket Holder Assembly
Page 6
Stand the Highbanker/Combo in the
stream of water that you will be
working. Raise the Highbanker/
Dredge to a minimum height above
the water. Remember the less height
difference from the Nozzle tip to the
top of the Header Box, the better the
Nozzle suction.
Page 19
HONCOOP HIGHBANKER
1-888-988-2122
2” Dredge Assembly
1 1/4” Pressure Hose
Screw the 1 1/4” Pressure Hose onto the
P.V.C. Valve Assembly. Twist the Valve
Assembly onto the Lay Flat Hose to the
pump. Now attach to the Top Tray Spray
Bar. Then attach to Flume and Nozzle.
Page 18
Splash Screen Placement
Place the Moss on the Black Ribbed
Mat. Place the Punch Hole Screen on
the Moss. Wedge it down tight with
the two Wood Blocks placed under
the plastic pegs.
Page 7
1-888-988-2122
HONCOOP HIGHBANKER
2” Dredge Assembly
3/4 x 1/4 x 20 SS Machine Screws
Dredge “3rd Tray” Hangers
Garden
Hose Valve
& Garden Hose
Header Box Spray Bar Assembly
Thread the Spray Bar with the small
holes onto the Valve Assembly with the
longest piece of Blue Lay Flat Hose.
Mount to the Header Box with the
plastic clamps found in the tool tray.
Screw on Garden Hose Valve and
Garden Hose.
Page 8
Slide the Dredge 3rd Tray between the
Top Tray and Bottom Tray. Lift and hang
on the cross bars of the Bottom Tray.
Page 17
1-888-988-2122
HONCOOP HIGHBANKER
2” Dredge Assembly
3/4 x 1/4 x 20 SS Machine Screws
3/4 x 1/4 x 20 SS Machine Screws
Top Tray Spray Bar Assembly
Screw down the Dredge Header Box Flume
Page 16
Thread the Spray Bar with the large
holes onto the Valve Assembly with
the short Blue Lay Flat Hose. Mount
to the Side Panels with the plastic
clamps found in the tool tray.
The P.V.C. “Y”-Coupler can then be
threaded to the Spray Bars.
Page 9
HONCOOP HIGHBANKER
1-888-988-2122
2” Dredge Assembly
3/4 x 1/4 x 20 SS Machine Screws
3/4 x 1/4 x 20 SS Machine Screws
Tool Tray Assembly
Open end of Tool Tray faces the side
with the Spray Bar Valves.
Page 10
Screw in place under the Header Box
Grizzly. Rotate to touch the Tines and
tighten.
Page 15
1-888-988-2122
HONCOOP HIGHBANKER
2” Dredge Assembly
Loosen
Screws
Loosen (DO NOT REMOVE) the 4 screws that
hold down the Header Box Grizzly. Lift the
Grizzly Tines and place the 3/4” aluminum
angle between the Tines and the Back Panel.
The end tabs on the angle will hook on the
welds in the corner. Retighten the Grizzly
screws. The pressure from the Tines will hold
the angle in place.
Page 14
Top Tray Classifying Screen Assembly
Place the Classifying Screen under the Spray
Bar and rest it on the two Plastic Pegs located
on the Side Panels.. Push it all the way back so
it will hang on it’s own while you reach for the
Top Tray.
Page 11
1-888-988-2122
HONCOOP HIGHBANKER
2” Dredge Assembly
Dredge Kit
“3rd Tray Flume”
#2
#1
Wi
Nu ng
ts
Top Tray Assembly
The Moss of the Top Tray slips under
the rubber flap of the Classifying
Screen assembly. The flap is then
pinched down when the Riffle Tray is
latched tight.. Note: The Velcro on
the cross bar of the Bottom Tray mates
with the Velcro on the bottom of the
Top Tray and holds the assembly in
place.
Page 12
Remove Header Box Spray Bar Valve
Assembly & “Y”-coupler. Center “3rd Tray
Flume” under Top Tray Classifying Screen and
insert #1 screw through the first row of punch
holes. Then insert #2 screw through the
screen and wing nut the screws in place.
Replace the Classifying Screen in the
Highbanker with the Top Tray.
Page 13