Environmental Statement
Transcription
Environmental Statement
Whittlesey Washes South Barrier Bank Works Environmental Statement April 2013 We are the Environment Agency. We protect and improve the environment and make it a better place for people and wildlife. We operate at the place where environmental change has its greatest impact on people’s lives. We reduce the risks to people and properties from flooding; make sure there is enough water for people and wildlife; protect and improve air, land and water quality and apply the environmental standards within which industry can operate. Acting to reduce climate change and helping people and wildlife adapt to its consequences are at the heart of all that we do. We cannot do this alone. We work closely with a wide range of partners including government, business, local authorities, other agencies, civil society groups and the communities we serve. Published by: Environment Agency Horizon house, Deanery Road Bristol BS1 5AH Email: enquiries@environmentagency.gov.uk www.environment-agency.gov.uk © Environment Agency 2011 All rights reserved. This document may be reproduced with prior permission of the Environment Agency. Further copies of this report are available from our publications catalogue: http://publications.environmentagency.gov.uk or our National Customer Contact Centre: T: 03708 506506 Email: enquiries@environmentagency.gov.uk. i EIA Quality Mark This Environmental Statement, and the Environmental Impact Assessment (EIA) carried out to identify the significant environmental effects of the proposed development, was undertaken in line with the EIA Quality Mark Commitments. The EIA Quality Mark is a voluntary scheme, operated by the Institute of Environmental Management and Assessment (IEMA), through which EIA activity is independently reviewed, on an annual basis, to ensure it delivers excellence in the following areas: EIA Management EIA Team Capabilities EIA Regulatory Compliance EIA Context & Influence EIA Content EIA Presentation Improving EIA practice To find out more about the EIA Quality Mark please visit: www.iema.net/qmark ii CONTENTS Page 1 BACKGROUND 1.1 Introduction 1.2 Legislative Background 1.3 Objectives of the Environmental Statement 1.4 The Problem 1.5 Structure of the Report 2 PROJECT DEVELOPMENT 2.1 Strategic Context 2.2 Assessment of Alternatives 2.3 Consultation 2.4 Detailed Design Consultation 2.5 Consultation on this Environmental Statement 6 6 6 14 21 21 3 THE PREFERED OPTION 3.1 Scheme Elements 3.2 Consideration of Water Framework Directive 3.3 Land Use Requirements 3.4 Site Access Routes 3.5 Construction Works 3.6 Timing and Duration 3.7 Transport of Materials 3.8 Working Practices 3.9 Reinstatement and Use of Land following Construction 3.10 Residues and Emissions 3.11 Post-construction Phase 22 22 25 25 26 28 29 30 30 30 31 31 4 METHODOLOGY 4.1 EIA Methodology 32 32 5 HUMAN BEINGS 5.1 Introduction and Methodology 5.2 Baseline Environment 5.3 Impacts during Construction 5.4 Impacts during Operation 5.5 Impact Summary 37 37 37 40 43 43 6 FLORA AND FAUNA 6.1 Introduction and Methodology 6.2 Legislation, Policy and Guidance 6.3 Baseline Environment 6.4 Ecological Impact Assessment Methodology 6.5 Baseline Environment 6.6 Impacts during Construction 6.7 Impacts during Operation 45 45 46 47 49 51 59 66 iii Whittlesey Washes South Barrier Bank Works Environmental Statement 1 1 3 3 4 5 6.8 Impact Summary 67 7 LANDSCAPE AND VISUAL AMENITY 7.1 Introduction and Methodology 7.2 Baseline Environment 7.3 Policy and Designations 7.4 Visual Appraisal 7.5 Analysis and Landscape Strategy 7.6 Impact Summary 69 69 69 72 73 74 75 8 HISTORIC ENVIRONMENT 8.1 Introduction and Methodology 8.2 Policy and Designations 8.3 Baseline Environment 8.4 Impacts during Construction 76 76 77 81 86 9 TRAFFIC AND TRANSPORT 9.1 Introduction and Methodology 9.2 Baseline Environment 9.3 Impacts during Construction 9.4 Impacts during Operation 9.5 Impact Summary 91 91 91 94 95 95 10 CUMULATIVE EFFECTS 97 11 CONCLUSION 98 12 REFERENCES 100 13 GLOSSARY AND ABBREVIATIONS 102 Tables 2.1 2.2 2.3 4.1 4.2 4.3 4.4 5.1 5.2 6.1 6.2. 6.3 8.1 8.1 9.1 Whittlesey Washes FSR long list of options Results of the scoping exercise Comments received from internal and external stakeholders during the scoping consultation Guidance followed for development of assessment methodologies Sensitivity of receptors Magnitude of impacts Significance of effects Sensitivity criteria for human environment. Summary of human environment impacts Assessment of the value of ecological resource (table adapted from IEEM, 2006) Internationally, nationally and locally designated sites within the vicinity of the proposed works Summary of flora and fauna impacts Sensitivity criteria for the historic environment. Summary of historic environment impacts Sensitivity criteria for traffic and transport iv Whittlesey Washes South Barrier Bank Works Environmental Statement 9.2 Summary of traffic and transport impacts Figures 1.1 3.1 3.2 5.1 6.1 8.1 9.1 Location Plan Scheme Details Proposed Works and Access Routes Current Land Use Designated Sites Historic Environment Records of Study Area Local Road Network Appendices Appendix A Environmental Action Plan Appendix B Scoping Report Appendix C Water Framework Directive Water Bodies Appendix D Reed Clearance Water Framework Directive Assessment Appendix E Detailed Drawings Appendix F Ecological Survey Reports Appendix G Habitats Regulations Assessment Appendix H Noise Assessment Appendix I Precautionary Method of Working Appendix J Final Landscape Masterplan Appendix K Historical Environment Record v Whittlesey Washes South Barrier Bank Works Environmental Statement 1 BACKGROUND 1.1 Introduction This Environmental Statement (ES) has been prepared with reference to the proposed works to stabilise and strengthen the South Barrier Bank (SBB) along the Whittlesey Washes Flood Storage Reservoir (FSR). The SBB as part of the FSR is considered to be a statutory reservoir1 and therefore needs to be maintained to a standard which prevents flooding (further details of this can be found in Section 1.4). The scheme therefore involves improving the SBB so that it can safely withstand overtopping during flood events, without the need for bank raising. The proposed works to the bank involve flattening the rear slope of the embankment to a 1:5 slope with reinforced grass cover in locations which are at a higher risk of overtopping. In addition bank stabilisation works are necessary in some locations. The SBB is located along the River Nene just east of Peterborough and extends between Stanground on the south east outskirts of Peterborough (National Grid Reference (NGR) TL 201 979) and Ring’s End to the east (NGR TF 398 029). The location of the SBB is shown on Figure 1.1. Details on the area of works can be found in the engineering drawings in Appendix B. The origins of the Whittlesey Washes FSR date back to the 1600s when Sir Cornelius Vermuyden straightened and improved Morton’s Leam, constructed a new sluice at Stanground as well as raising the SBB. This construction not only aided the recovery of marsh areas for agriculture but also provided water transport and increased the flood capacity. The Whittlesey Washes FSR is approximately 20km long and in places up to 1.4km wide. It covers an area of approximately 1,450 hectares (ha). The SBB forms the dam of the reservoir. The SBB also forms the boundary between the Environment Agency’s Northern and Central Areas. Whittlesey Washes FSR protects Peterborough and nearby fenland areas from flooding events. The tidal limit of the River Nene is the Dog-in-a-Doublet Sluice that is located midway along the River Nene which is adjacent to the FSR. During periods of high tides, water is diverted into Morton’s Leam and allows the FSR to flood. When the tidal levels fall, the water is then discharged from the FSR through Ring’s End Sluice and back into the tidal River Nene. The location of these sluices and watercourses is presented on Figure 1.1. A Non-technical Summary (NTS) of this ES is also provided as a separate document. 1 A statutory reservoir is one which holds at least 25,000 cu m of water above natural ground level and therefore falls under The Reservoirs Act 1975 to ensure its safety. Whittlesey Washes South Barrier Bank Works Environmental Statement 1 ¯ Lincoln ¯ Sleaford, Lincs Key: South Barrier Bank - area of work Extent of Tidal River Nene Nene Washes FSR King's Lynn Peterborough Ring's End Sluice © OpenStreetMap (and) contributors, CC-BY-SA PETERBOROUGH Stanground Stanground Sluice Dog-in-a-Doublet Sluice Tidal River Nene River Nene Reproduced from Ordnance Survey Maps with the permission of the Controller of HM Stationary Office. Crown copyright reserved Licence AL.100026380 Eldernell Morton's Leam Whittlesey Title: Location Plan Project: Whittlesey Washes South Barrier Bank Works, Environmental Statement Client: Environment Agency Anglian Region Date: April 2013 Figure: 1.1 0 0.5 1 2 3 4 5 Kilometres Scale @ A4: 1:100,000 Path: L:\Sites\UK-Peterborough\Project\9W3627\Technical_Data\T5_GIS\Projects\Figures\Environmental Statement\Fig 1_1 Location Plan .mxd Cambridge, Cambs Ring's End 1.2 Legislative Background The basis for the Environmental Impact Assessment (EIA) legislation in England and Wales is the European Union (EU) Directive 85/337/ECC, superseded by EU Directive 97/11/EC, which came into effect in 1999. Internal screening by the Environment Agency determined that the proposed works to improve the SBB, (hereinafter referred to as the scheme) fall under Schedule 2 Part 15 of the Town and Country Planning (General Permitted Development) Order 2010 and this has subsequently been confirmed by Peterborough City Council and Fenland District Council. Because these works are considered to be improvements rather than maintenance activities, the works fall under the EIA (Land Drainage Improvement Works) Regulations SI 1999 No 1783 (as amended by SI 2005/1399 and 2006/618). Screening also determined that as the scheme exceeds 1ha, is immediately adjacent to the Whittlesey Washes Special Protection Area (SPA), Special Area of Conservation (SAC), Ramsar and Site of Special Scientific Interest (SSSI) designated site and the works have the potential to give rise to likely significant environmental effects, the scheme requires a statutory EIA. The intention to undertake a statutory EIA has been advertised in accordance with the requirements of the EIA (Land Drainage Improvement Works) Regulations SI 1999 No 1783 (as amended by SI 2005/1399 and 2006/618). This ES has been produced to record the EIA process. The Environment Agency are undertaking the scheme and the main contact is: Nicola Oldfield, Environment Agency Project Manager Environment Agency Kingfisher House Goldhay Way Orton Goldhay Peterborough PE2 5ZR Telephone: 01733 464629 Email: nicola.oldfield@environment-agency.gov.uk 1.3 Objectives of the Environmental Statement The principle objective of the EIA process is to identify the likely significant effects of a scheme that may arise through the implementation of the scheme and to identify suitable mitigation measures to avoid or reduce significance. The EIA process also seeks to identify opportunities arising from the scheme for improving the environmental value of the area. Control measures intended to avoid, mitigate or monitor potential impacts are documented in the Environmental Action Plan (EAP) (Appendix A) and will be included in the works specification. Whittlesey Washes South Barrier Bank Works Environmental Statement 3 1.4 The Problem Whittlesey Washes FSR is registered under the Reservoirs Act 1975 and is a statutory reservoir. The Environment Agency is the Undertaker for the reservoir. Following an inspection in September 2005 under Section 10(2) (b) of the Reservoirs Act2, the Inspecting Engineer recommended works to address Matters in the Interest of Safety (MIOS). A flood study was completed in December 2007 which concluded that if the FSR was full and the SBB was subject to wave action there is an unacceptable risk that the bank would breach. Along the entire length of the SBB there are low areas which could potentially lead to the failure of the SBB in being able to withstand high water levels. As such work is required to satisfy the Reservoirs Act and remove the risk of the SBB failing during high water level events. A project appraisal study, including a geotechnical stability assessment for the SBB, was then commissioned. This study revealed that the SBB is at high risk of failure due to low spots along the entire length and as such results in breach points during flood events. This assessment is supported by the reports of seepage along various lengths during the April 1998 floods and in more recent events. The stability issues and other concerns led the Environment Agency to call for a new Section 10 Inspection to enable all concerns to be addressed within any proposed works. The Section 10 inspection by Professor Hughes on 16 January 2012 resulted in a new set of MIOS which superseded those identified in 2005. These MIOS are detailed below: i. ii. iii. iv. Whittlesey to Ball Bridge: All coarse vegetation, saplings and trees be removed from the embankment faces and a good grass cover established – some trees at the base of the slope might be left with the agreement of a Panel Engineer to provide habitat and cover – by November 2012; Poplar House Farm to Eldernell: The areas near Eldernell severely affected by rabbits and burrowing animals should be repaired – by November 2012; Rings End to Poplar House Farm: Works are put in place to prevent animals burrowing into the embankment where this damage is particularly serious and the bank repaired – by November 2012; and General: Works are carried out to ensure the SBB can safely accommodate the static flood level and wave surcharge and are commenced within 18 months of the report date (i.e. January 2012 so works must commence by November 2013) and completed in a reasonable period of time. The works under parts i to iii have already been undertaken. This ES refers to works to be undertaken for part iv. 2 This section states a reservoir should be inspected “as soon as practicable after the carrying out of any alterations to the reservoir which do not increase its capacity but are such as might affect its safety and which have not been designed and supervised by a qualified civil engineer” Whittlesey Washes South Barrier Bank Works Environmental Statement 4 1.5 Structure of the Report The following Chapters are presented in this ES: Chapter1: Background; Chapter 2: Project Development; Chapter 3: The Preferred Option; Chapter 4: EIA Methodology; Chapter 5: Human Beings; Chapter 6: Flora and Fauna; Chapter 7: Water Framework Directive; Chapter 8: Landscape and Visual Amenity; Chapter 9: Historic Environment; Chapter 10: Traffic and Transport; Chapter 11: Cumulative Effects; and Chapter 12: Conclusion. A Non-Technical Summary (NTS) is available as a stand-alone document. The following appendices accompany the ES: Appendix A Environmental Action Plan; Appendix B Scoping Report; Appendix C Water Framework Directive Water Bodies; Appendix D Reed Clearance Water Framework Directive Assessment; Appendix E Detailed Drawings; Appendix F Ecological Survey Reports; o Whittlesey Washes Reservoir Works Ecological Walkover Report (Royal HaskoningDHV 2011); o Whittlesey Washes: Ecological Walkover Follow Up (Royal HaskoningDHV 2012); Appendix G Habitats Regulations Assessment; o HR01 form - Whittlesey Washes Habitat Regulations Assessment; o Natural England Letter of Support; Appendix H Noise Assessment; Appendix I Precautionary Method of Working; Appendix J Final Landscape Masterplan;and Appendix K Historical Environment Record. Whittlesey Washes South Barrier Bank Works Environmental Statement 5 2 PROJECT DEVELOPMENT 2.1 Strategic Context Whittlesey Washes FSR is a statutory reservoir as classified under the Reservoirs Act. As the “Undertaker” for the FSR, the Environment Agency has a statutory obligation to ensure regular inspections are carried out by an appropriate All Reservoirs Panel Engineer and to carry out any recommendations arising from such inspections. Failure to carry out these recommendations will leave the Environment Agency liable to criminal prosecution. Any design and/or construction works carried out on a reservoir must be supervised by a Panel Engineer, who must be selected from the All Reservoirs Panel list and appointed by the Undertaker. The proposed scheme will be carried out under: The Reservoirs Act Section 10(6); Section 165 of the Water Resources Act 1991; The Construction (Design and Management) Regulations 2007 (CDM); The Town and Country Planning (General Permitted Development) Order 2010; and The Environmental Impact Assessment (Land Drainage Improvement Works) Regulations 1999. The proposed works support the Environment Agency’s Corporate Strategy Creating a Better Place 2012-2015. The Environment Agency is working with partners and the local community to implement the proposed works which will comply with all relevant environmental and flood risk management legislation. 2.2 Assessment of Alternatives The potential options for the scheme can be classified into two categories. One is to raise the embankments to retain water to the required standard or the other being to release water in a controlled manner (i.e. via the use of spillways) which reduces or removes the need for embankment raising but not entirely remove the requirement for bank stability works. As an alternative to earthworks, sheet piling was also considered where bank raising was only required to protect against wave action and in areas of lower environmental value, as defined by Natural England (NE) (i.e. between Stanground and Whittlesey). The long list of options is provided in Table 2.1. These options were developed through a series of discussions with the project team and engagement with internal and external partners/stakeholders. The option numbering is based on how the options were developed throughout the project. Whittlesey Washes South Barrier Bank Works Environmental Statement 6 Table 2.1 – Whittlesey Washes FSR long list of options Option Summary Description Status of option Do Nothing (Option 1) This option assumes that no works or maintenance is undertaken to the Whittlesey Washes FSR including SBB. Discounted. This option is not feasible as the Environment Agency needs to comply with the requirements of the Reservoirs Act and the recommendations of the Inspecting Engineer. In addition, there is the potential that this would affect the condition of the internationally designated site which is to the north of the SBB and within the FSR. Continue current operation and maintenance regime (Option 2) This option means that the SBB would be maintained at its current crest level and condition but no action would be taken to improve the asset. Discounted. This option is not feasible as the Environment Agency need to comply with the requirements of the Reservoirs Act and the recommendations of the Inspecting Engineer. In the long term, significant works would be required to maintain its current condition which could have disturbance issues for features of the internationally designated site. Raise embankments to the design standard so no wave overtopping occurs and bank stabilisation (Option 3)3 This option involves raising the crest level of the SBB to be at or above the reservoir design standard so that there is no overtopping, equivalent to the 0.01% annual probability plus freeboard requirements for no overtopping. In addition bank stabilisation works are necessary in some locations. Raise the level of the embankment such that only tolerable wave overtopping occurs and bank stabilisation (Option 4)4 This option involves raising the crest of the embankment to the general reservoir design level so that the embankment does not fail due to overtopping and that no overtopping occurs at the lower minimum standard (standards taken from Table 1 of the Institute of Civil Engineers (ICE) Floods and Reservoir Safety 1996). In addition bank Discounted. This option would provide a standard in excess of that required to meet the MIOS and would require excessive bank raising and stabilisation with associated large costs and impacts (large environmental and social impact from transport of significant volumes of earth, larger than the 1.2 million cubic metres of earth required in Option 4). In addition, significant works would be required which could have disturbance issues for features of the internationally designated site. Discounted. Investigations revealed that the SBB crest level would need to be raised by about one metre over approximately 14km. Together with stabilisation works, it is estimated that 1.2 million cubic metres of earth would be required. With a restricted construction period, the works could take up to 8 years to construct. An outline estimate of the construction cost was in excess of £30 million. 3 4 No wave overtopping is defined by Floods and Reservoir Safety 3rd Edition (ICE 1996) Tolerable wave overtopping is defined by Floods and Reservoir Safety 3rd Edition (ICE 1996) Whittlesey Washes South Barrier Bank Works Environmental Statement 7 Option Summary Description Status of option stabilisation works are necessary in some locations. Therefore it was decided that it was not a feasible option due to time constraints and the cost involved. In addition, significant works would be required which could have disturbance issues for features of the internationally designated site. One spillway with bank stabilisation and no bank raising (Option 5) This option involves constructing a single spillway of sufficient size/ level so as to manage water levels so there is no overtopping (still water or wave) elsewhere. In addition bank stabilisation works are necessary in some locations. Discounted. This option was discounted because it is not feasible to construct a spillway large enough to lower the water levels in the reservoir to a level which would allow no bank raising. Also, allowing water to leave the FSR could have impacts on numerous environmental receptors including habitats, faunal species and areas of archaeological interest. One spillway with bank stabilisation and some bank raising (Option 6a) This option involves constructing a single spillway to reduce peak water levels in the Whittlesey Washes FSR so that only some bank raising would be required. A balance would be struck between the level and size of the spillway and amount of associated bank raising. In addition bank stabilisation works are necessary in some locations. Discounted. This option was discounted due to the disruption caused by the operation of the spillway, which would affect the A605 east of Whittlesey, the railway south of Eastrea and large areas of agricultural land. Earth would be used instead of sheet piling to raise crest levels upstream of Whittlesey, which results in larger amounts of imported material and consequently higher construction costs. The option was also unacceptable to the local partners as it lowers the current crest of the SBB. In addition, the significant works required could have disturbance issues for features of the internationally designated site in particular as works would be required within the designated area. One spillway (Fuse Plug or tipping gate) with stabilisation and some bank raising (Option 6b) This option involves constructing a single fuse plug (tipping gate) spillway to reduce peak water levels in the Whittlesey Washes FSR so that limited bank raising is necessary. A balance would be struck between the spillway dimensions and amount of associated bank raising. In addition bank stabilisation works are necessary in some locations. Discounted. This option was discounted due to being unacceptable to the local partners as it lowers the current crest level of the SBB. Other reasons include complexity of technology and construction and the need to restore it after each use. Also lengths of the SBB upstream and downstream of Whittlesey would still require raising, which would require a large amount of imported material. In addition, the significant works required could have disturbance issues for features of the internationally designated site in particular as works Whittlesey Washes South Barrier Bank Works Environmental Statement 8 Option Summary Description Status of option would be required within the designated area. One spillway with sheet piling to increase crest level where necessary and bank stabilisation (Option 7) One spillway with sheet piling to increase crest level where necessary and bank stabilisation (Option 7a) One spillway with sheet piling to increase crest level where necessary and bank stabilisation (Option 7b) This option involves constructing a single spillway to reduce peak water levels with the Whittlesey Washes FSR and installing sheet piling to increase the crest level of the embankment where required. A spillway at 4.0mAOD would be constructed to the east of Eldernell, with 3.1km of sheet piled wave wall between Stanground and Whittlesey. In addition bank stabilisation works are necessary in some locations. This option is the same as Option 7 but with a spillway at 4.2mAOD and some bank raising downstream of Whittlesey. Discounted. This option was discounted due to cost and being unacceptable to the local partners as it lowers the current crest level of the SBB. The option would also have landscape and visual amenity impacts as sheet piling would be a new element in the area. There would also be disturbance issues to the interest features of the internationally designated site as works would be required on top of the SBB and within the designated area itself. Discounted. This option was discounted due to cost and being unacceptable to the local partners as it lowers the current crest level of the SBB. Although the option provides a slightly higher standard of protection than Option 7, the higher retained water level means that about 1.2km of the SBB requires raising downstream of Whittlesey and the spillway. This increases the cost of the construction. The option would also have landscape and visual amenity impacts as sheet piling would be a new element in the area. There would also be disturbance issues to the interest features of the internationally designated site as works would be required on top of the SBB and within the designated area itself. This option is the same as Option 7 but with a spillway at 4.6mAOD and some bank raising downstream of Whittlesey. Discounted. This option was discounted due to cost and being unacceptable to the local partners as it lowers the current crest level of the SBB. Although the option provides a higher standard of protection than Option 7, the higher retained water level means that about 6.5km of the SBB requires raising downstream of Whittlesey. This increases the amount of imported material by about 80,000m3 as well as the construction costs. The option would also have landscape and visual amenity impacts as sheet piling would be a new element in the area. There would also be disturbance issues to the interest features of the internationally designated site as works would be required on top of the SBB and within the designated area itself. Whittlesey Washes South Barrier Bank Works Environmental Statement 9 Option Summary Description Status of option Two spillways with stabilisation and no bank raising (Option 8) This option involves constructing two spillways of sufficient size/ level so as to manage water levels so there is no requirement for raising of the SBB. In addition bank stabilisation works are necessary in some locations. Discounted. This option was discounted because the spillways would need to be much lower and operate considerably more than Option 7 in order to have no bank raising. This would mean that flooding would be more frequent, which is unacceptable to landowners, local partners, drainage authorities and local government. In addition the areas of flooding would be higher and over wider areas and more likely to impact on a greater population than a single spillway with no bank raising. Flood water would isolate Whittlesey since all the access roads would be flooded. There would also be disruption to the trains between Peterborough and Ely/Cambridge. There would also be disturbance issues to the interest features of the internationally designated site as works would be required on top of the SBB and within the designated area itself. Two spillways with stabilisation and limited bank raising (Option 9) This option involves constructing two spillways to reduce peak water levels in the Whittlesey Washes FSR so that only limited bank raising would be required. A balance would be struck between the level and size of the spillway and amount of associated bank raising. In addition bank stabilisation works are necessary in some locations. Discounted. This option was discounted due to the damages and disruption caused by the spillways, as well as being unacceptable to the local partners. Flood water would isolate Whittlesey since all the access roads would be flooded. There would be disruption to the trains between Peterborough and Ely/Cambridge. There is a reliance on the railway embankment upstream of Whittlesey to limit flooding in the brick works; so there is a potential hazard if the railway embankment fails. Also the flood water would affect the land allocated for commercial development between Stanground and the railway. There would also be disturbance issues to the interest features of the internationally designated site as works would be required on top of the SBB and within the designated area itself. Whittlesey Washes South Barrier Bank Works Environmental Statement 10 Option Summary Description Status of option Two spillways with stabilisation and sheet piling to increase crest level where necessary (Option 10) This option involves constructing two spillways to reduce peak water levels with the Whittlesey Washes FSR and sheet piling to increase the crest level of the embankment where required. A balance would be struck between the level and size of the spillway and amount of associated bank raising. In addition bank stabilisation works are necessary in some locations. Discounted. This option was discounted due to the damages and disruption caused by the spillways, as well as being unacceptable to the local partners. Flood water would isolate Whittlesey since all the access roads would be flooded. There would be disruption to the trains between Peterborough and Ely/Cambridge. There is a reliance on the railway embankment upstream of Whittlesey to limit flooding in the brick works; so there is a potential hazard if the railway embankment fails. Also the flood water would affect the land allocated for commercial development between Stanground and the railway. The option would also have landscape and visual amenity impacts as sheet piling would be a new element in the area. There would also be disturbance issues to the interest features of the internationally designated site as works would be required on top of the SBB and within the designated area itself. Lower the level of the Cradge Bank to form a spillway with some raising on the SBB and bank stabilisation (Option 11) This option involves reducing the level of the Cradge Bank downstream of the Dog-in-a-Doublet Sluice so that the requirements of raising of the SBB are reduced. This would enable water to be released into the tidal River Nene and reduce the peak water level in the reservoir. Therefore the required level of the SBB could be reduced. In addition bank stabilisation works are necessary in some locations. Discounted. Following investigation of the water levels in the tidal River Nene it was discovered that there is insufficient capacity to take the required volume from the reservoir. In addition lowering the Cradge Bank would increase the risk of tidal flooding of the Washes in extreme tidal events from the River Nene. This would also impact on the internationally designated site within the FSR. Pumping Station (Option 12) This option involves building a pumping station across the SBB designed to discharge water from Whittlesey Washes FSR into the surrounding drains/ rivers and so reduce water levels in the reservoir. Discounted. This option was discounted due to the magnitude of the required volume to discharge (>300 m3/s, three times the size of the recently constructed St German’s Pumping Station). In order for the surrounding area to receive this water, there would need to be considerably more drainage infrastructure in place than currently exists. It is also an active solution and so unacceptable for reservoir safety. The pumping station would need to be provided with back-up power to run the pumps during an electricity supply failure, which is likely to happen during extreme weather events. There would also be Whittlesey Washes South Barrier Bank Works Environmental Statement 11 Option Summary Description Status of option long term on-going maintenance and associated costs for the whole life (100 years) of an asset with a very low probability of being used (much less than 1%). This would have impacts on the interest features of the internationally designated site. Siphon under the SBB (Option 13) This option involves building a siphon under the SBB designed to discharge water from Whittlesey Washes FSR and so reduce water levels in the reservoir. This method is used on the Welland Washes (Cowbit/Crowland) in Northern Area to get water into the Washes. Discounted. This option was discounted due to the magnitude of the required volume to discharge, whereby 300 m3/s would require a siphon to be about 100m wide and 1m deep. Such a siphon would produce high velocities which could endanger lives and would require additional erosion protection to prevent excessive erosion. Also more frequent flood events may result in more flooding outside the reservoir. If this was undesirable then the siphon crest would need to be higher, which would require bank raising and a significant amount of additional material for bank stabilisation. There would also be disturbance issues to the interest features of the internationally designated site as works would be required on top of the SBB and within the designated area itself. North Barrier Bank spillway and bank stabilisation (Option 14) This option involves building a spillway in the northern embankment of the River Nene, which is not deemed to be part of the Statutory Reservoir but does hold water above the Cradge Bank level. In addition bank stabilisation works are necessary on South Barrier Bank. Discounted. This option was discounted due to costs and impacts. The spillway would need to be located upstream of Whittlesey and Dog-in–the-Doublet. A spillway downstream would allow saline intrusion onto arable land from the Tidal Nene. Also upstream water levels can be reduced better with an upstream spillway. Bank raising would still be required. A spillway upstream of Whittlesey would potentially have significant impacts on the commercial Fengate area (south east Peterborough), Peterborough Power Station, Flag Fen Waste Water Treatment Works and the heritage site of Flag Fen. This would be unacceptable and therefore a substantial secondary defence line would be required to protect these assets adding to the project cost. There would also be disturbance issues to the internationally designated site. Whittlesey Washes South Barrier Bank Works Environmental Statement 12 Option Summary Description Status of option Decommission the Whittlesey Washes FSR (Option 15) This option involves removing large lengths of the SBB such that the Whittlesey Washes FSR is no longer considered a reservoir. Discounted. This option is not feasible as the long lead in time does not meet the requirements of the MIOS. Resulting flood damages would be high requiring high cost mitigation measures to be implemented. In addition, there is the potential that this would affect the internationally designated sites which require certain water levels to attract the large numbers of bird species for which they are designated. Reinforce the SBB (Option 16) This option consists of improvements to the SBB so that it can safely withstand overtopping during the design events without the need for bank raising. It involves flattening the rear slope of the embankment to a 1:5 slope with grass cover and grass reinforcement in locations at higher risk of overtopping. In addition bank stabilisation works are necessary in some locations. Preferred option being taken forward. This option has a lesser impact on the internationally designated sites as the works themselves are hidden by the SBB and would therefore not create a visual disturbance to bird species. The works are also located outside of the designated area. In addition, there are no significant changes in the existing landscape. Create a spillway to retain a minimal level in the reservoir (Option 18) This option involves constructing a spillway at a level where the retained water volume is still within the Reservoirs Act threshold but is as low as possible. The spillway will provide flood defence up to the 5% (1:20) annual probability. In addition minimal bank stabilisation works are necessary in some locations. Discounted This option was discounted due to the damages and disruption caused by the spillway both socially and environmentally. Lower SBB to avoid need for import of soil material (Option 19) This option involves lowering the SBB to provide material for stabilisation and so avoid the need for importing soil. Protection of the back slope would be limited to reinforced grass as hard concrete protection would not be aesthetically pleasing and likely to be unacceptable to local partners. Discounted. This option was discounted as not enough material could be won from the SBB for stabilisation to avoid importing soil. Lowering of the crests by more than 0.6m would require hard concrete slope protection, meaning that approximately 135,000m3 of material would be required for back slope slackening and stabilisation. Also the local partners would not accept lowering of the SBB. There would also be disturbance issues to the internationally designated site as works would be required on top of the SBB. The introduction of concrete slopes would also reduce the use of the SBB by overwintering wildfowl for foraging and be a new landscape element for the area. Whittlesey Washes South Barrier Bank Works Environmental Statement 13 2.3 Consultation 2.3.1 Pre-scoping consultation Meetings with the flood risk management partners and wider stakeholders (as listed below) were held on 9 January 2012 and 11 May 2012 to initially develop the long list and then subsequently agree the short list of options and discuss issues associated with each. Fenland District Council (FDC); Peterborough City Council (PCC); Cambridgeshire County Council (CCC); National Farmers Union (NFU); Natural England; Royal Society for the Protection of Birds (RSPB); Middle Level Commissioners (MLC); Whittlesey Consortium of Internal Drainage Boards (WCIDB); North Level District Internal Drainage Board (NLIDB); Whittlesey Town Council; and Northern and Central Regional Flood and Coastal Committees (RFCC). The stakeholders who attended the 11 May 2012 meeting agreed that their preferred option was Option 16 and that they would seek additional financial contributions from their relevant bodies in order to assist in implementing this option over the more cost effective Option 7. On confirmation that Option 16 was the preferred option, a public drop-in session was held in Whittlesey on 24 October 2012 and supported by the Whittlesey Town Council and other partners. This event was attended by approximately 75 people and included concerned residents, local landowners, local councillors and groups representing users of the area (i.e. Whittlesey Wildfowlers and Conservationists). The key comments were centred on the proposed access routes and avoidance of direct disturbance to local residents. However, the overall general feedback was positive with many attendees saying that it provided them with a greater understanding of the need and drivers for the project. Whittlesey Washes South Barrier Bank Works Environmental Statement 14 2.3.2 Scoping Assessment The purpose of the scoping process is to identify the potential likely significant environmental effects of the project during construction and operation so that they can be considered and assessed in more detail in the ES, and appropriate mitigation measures identified for adverse impacts. Likewise the scoping process should identify receptors upon which no significant effects are anticipated so that these can be scoped out as not requiring any further assessment. The following topics have been considered when establishing the baseline conditions for the scheme: Human beings; Flora and fauna; Landscape and visual amenity; Water; Soil, geology, hydrogeology and geomorphology; Archaeology and cultural heritage; Air and noise quality; Traffic and transport; and Climate change and use of natural resources. Table 2.2 presents a summary of the potential likely significant effects we have identified to date that we have scoped in as requiring further assessment. It highlights whether the potential impact is likely to be beneficial or adverse, or is unknown pending further investigation. It has been informed by: The surveys and data collection undertaken to date (refer to Section 4.1.1 for further details); Knowledge of other similar projects; and The consultation undertaken to date (refer to Section 2.3.3 for further details). Table 2.2 Results of the scoping exercise Topic Category Potential likely significant effects requiring further consideration Human beings Positive impact in addressing the failure of the SBB and ensuring its effectiveness during an extreme flood event, thus potentially providing health benefits by providing assurance in respect to flooding. Disruption to users of the Nene Way long distance path during the construction works. Noise and visual disturbance to recreational users and other visitors to the area from construction activities (re-profiling slopes and installation of toe stabilisation) and from additional traffic movements bringing fill material to the area. Potential damage to existing access tracks for access or damage to areas of farmland for siting of site compound and welfare facilities (access and site compound areas currently uncertain but wherever possible existing hard standing areas will be used). Scoped in or out of the assessment? IN Whittlesey Washes South Barrier Bank Works Environmental Statement 15 Topic Category Potential likely significant effects requiring further consideration Flora and fauna Potential likely significant effect on the interest features of the adjacent Whittlesey Washes SPA, SAC, Ramsar and SSSI site. Potential disturbance to breeding marsh harriers as well as to bitterns present within the reedbeds in the Counter Drain due to proximity of works. Potential disturbance to water voles within the Counter Drain as a result of reed strimming/clearance works (no water voles have been recorded along the bank proposed to be cleared). Potential disturbance to great crested newt terrestrial habitat (in the western section of the SBB) during the construction works. Potential impacts on other legally protected species (various reptiles and bird species and otters) during construction. Potentially likely significant impact on historic landscape result of construction in local areas There are no significant impacts considered likely as a result of the proposed works. Therefore the construction works will be managed by general good practice. There are no significant impacts considered likely as a result of the proposed works. Therefore the construction works will be managed by general good practice. Potential significant impacts to buried archaeology within peat layers as a result of construction works. Potential significant impacts to buried archaeology near Guyhirn as a result of the construction works. Potential significant impacts to the setting of designated assets. Due to the rural nature of the area where works are proposed, it is considered that there are no significant receptors on which impacts from noise and air quality would be felt. Therefore the construction works will be managed by general good practice. Temporary increases in traffic over the 3 or 4 year construction period to existing public and private local roads during construction resulting in significant disturbance and nuisance impacts on local people. The use of quarried material (approximately 335,000 cubic metres) will be required. The material suppliers are still to be selected, but these will be local and within a 20 mile radius of Whittlesey. It is envisaged that minimal waste will be generated during the construction works. Landscape and visual amenity Water Soil, geology hydrogeology, geomorphology Archaeology and cultural heritage Air and quality noise Traffic transport and Climate change and use of natural resources 2.3.3 Scoped in or out of the assessment? IN IN OUT OUT IN OUT IN OUT Scoping consultation A Scoping Report was issued to internal and external stakeholders via email between the 4th and 18th December 2012. A copy of the Scoping Report is presented in Appendix B. Internal Environment Agency specialists who received the Scoping Report included: Fisheries and Biodiversity; Archaeology; Landscape; Whittlesey Washes South Barrier Bank Works Environmental Statement 16 Planning Liaison; Environmental Management; Flood Risk Management; Groundwater and Contaminated Land; and Waterways. External stakeholders who received the Scoping Report included: NE; PCC; FDC; RSPB; NLDIDB; MLC; Bedfordshire, Cambridgeshire, Northamptonshire and Peterborough Wildlife Trust (BCNP WT); NFU; and English Heritage (EH). Table 2.3 provides a summary of the comments received from internal and external stakeholders and the responding action which has been taken. Whittlesey Washes South Barrier Bank Works Environmental Statement 17 Table 2.3 Comments received from internal and external stakeholders during the scoping consultation Organisation Comment received Response/Action taken Middle Level Commissioners Environment Agency (Environment and Performance Team) Environment Agency (Northern Waterways Operation Team) Peterborough City Council Bedfordshire, Cambridgeshire, Northamptonshire and Peterborough Wildlife Trust Royal Society for the Protection of Birds Access for the works here will cross the navigation some way south east of the lock off the Whittlesey Road (presumably using the existing bridge). The haul road will run along the bank of the navigation for a short length (presumably using an existing track) before veering off and away from out direct interests. Therefore further details of the proposals will be required that consideration of their impact on our statutory undertaking can be made. All potential impacts are covered in the scoping assessment. There is opportunity to improve the diversity of the bank through the use of a species rich seed mix. Comments noted. Further detail as and when will be provided throughout progression of the scheme. Liaison with MLC will be undertaken when investigating location of access routes. Further details in respect to access routes and proposed construction methods are provided in Chapter 3. Navigation on the River Nene (Environment Agency statutory navigation) will not be affected by these works. Therefore no further considerations are required. The character and appearance of the site would not be materially different post development and it is not considered that an EIA is required on the basis of cumulative impact. Concern is raised regarding the high number of lorry movements and the disturbance these are likely to cause with the notified bird interest of the Nene Washes. Potential for significant impact on ecology and designated sites. Archaeological desk based assessment is required. Would like to be informed regarding mitigation measures required/proposed for the County Wildlife Sites. Comment noted. The scoping information provides an adequate overview of the environmental aspects, which can be used as a basis for identifying the correct mitigation and/or avoidance techniques to minimize Comments noted and will be incorporated into mitigation measures for the scheme (see Chapter 6). Counter Drain reed and scrub clearance was undertaken in February Comments noted. Potential for use of a species rich seed mix will be assessed. Further details are provided in Chapter 8. Comment noted. Further information on the disturbance of the bird species which use the Nene Washes designated site and the impacts on ecology are presented within Chapter 6 of this document and also Appendix G. A desk based assessment of the impacts of the scheme on archaeology has been undertaken and further details are presented in Chapter 9 of this document. Mitigation measures (as detailed within Chapter 6 of this document) will be discussed and further developed in consultation with The Wildlife Trust. Whittlesey Washes South Barrier Bank Works Environmental Statement 18 Organisation Natural England Comment received Response/Action taken environmental impacts from the works. The RSPB feel that the following points should be incorporated. That best practice is observed and there is an element of flexibility allowed, we consider that it would be feasible for the working window to be extended to the end of November. We consider such flexibility could be achieved through ensuring consultation occurs with Site Managers and Natural England prior to November each year in order to establish that conditions are typical and so there will not be high numbers of sensitive species in this month (for example as may occur if the Washes are flooded at this time). Also there was no mention of the proposed counter drain mitigation and enhancement works (or proposals for other biodiversity enhancements) currently being scoped out and the RSPB has recommended that they be incorporated. Welcome confirmation of the next steps in the process for finalizing details of the mitigation and avoidance techniques, including how these will inform the program of works. Supportive of the comments made and believes that an accurate assessment of the main issues has been addressed. Natural England notes that an EIA will be required regardless of whether the proposals are granted permitted development status. Natural England welcomes this approach and believes that the production of an Environmental Statement “that describes how the work will avoid, reduce and compensate for any ecological impacts (especially visual and noise disturbance), as well as outlines opportunities for enhancements will be essential for guiding a successful project” Many of the potential impacts can be avoided by careful timing of the works to avoid sensitive areas adjacent to the Nene Washes SPA/SAC/SSSI during certain parts of the years. Close collaboration with nature conservation partners in the area 2013 to minimise impacts to nesting birds and water voles. Further vegetation clearance will also be undertaken along the access routes. Consultation with RSPB is ongoing and we have been working closely to scope mitigation and enhancement measures Comments noted. Biological records for the area have been obtained and have been used to inform the baseline of the Flora and Fauna chapter of this ES (Chapter 6). Consultation with Natural England is ongoing. Specific working window (July to November) has been agreed through consultation with Natural England and RSPB which will avoid impacts to breeding and overwintering bird species. Further information on ecological issues is presented in Chapter 6. Whittlesey Washes South Barrier Bank Works Environmental Statement 19 Organisation English Heritage Comment received Response/Action taken (notably the RSPB) could allow for the working window to cover the period between July and November inclusive, if certain safeguards and assurances are met. This will help to reduce the overall length of the project and have an overall benefit to the project by reducing disturbance, cost and disruption to local communities. Royal HaskoningDHV should consult with the Cambridgeshire and Peterborough Biological Records Centre on top of consulting with the RSPB for bird data in order to gain historic information regarding protected and notable species along the route of the works. Welcome to the opportunities for enhancement to be fully explored in the scheme and that “this is a major infrastructure development, which should make a contribution towards our (i.e. Environment Agency and NE) shared aims of protecting and enhancing the adjacent SPA”. Encourages the integration of measures along the Counter Drain to be included within the scheme as a clear biodiversity enhancement measure, as well as delivering flood management and water movement benefits. On the basis that the proposed works are either raising or reinforcing banks, new ground works appear to be limited, although the provision of a toe berm would require excavation? The location and works required for site compounds needs to be assessed. I have not had access to your archaeological assessment, but assume that your archaeological adviser has had the appropriate pre-application discussions with the local authority archaeological adviser. Comments noted. Archaeological specialists have provided input to the proposed works as well as undertaken initial liaison with County Council archaeologist. Further details are provided in Chapter 9. Whittlesey Washes South Barrier Bank Works Environmental Statement 20 2.4 Detailed Design Consultation Consultation on the scheme has continued throughout the design phase. This consultation has focused on resolving specific issues, primarily in relation to the timing of the works. Numerous meetings have been held with NE and RSPB throughout all stages of the scheme, regarding the proximity of the site to the Nene Washes SPA, SAC, Ramsar and SSSI designated site and the potential for extending the working window in less sensitive areas. It has been determined that works at the eastern and western ends of the site (i.e. Ring’s End and Stanground respectively) can be undertaken earlier than the rest of the works and can run for a longer duration. Other more environmentally sensitive areas (e.g. Eldernell) could potentially be worked on from July to October with the opportunity to extend into November but this is dependent on suitable weather conditions which are to be confirmed through consultation with RSPB and NE. 2.5 Consultation on this Environmental Statement This ES documents the EIA process. Site notices will be erected at Stanground, Eldernell and Ring’s End, an advertisement placed in two local newspapers (Fenland Citizen and Peterborough Telegraph), and on the Environment Agency’s website. A paper copy of the ES will be available at Fenland District Council and Peterborough City Council offices and also the regional Environment Agency office (Kingfisher House). Representations must be made within 28 days of the notice being published. Comments received on the ES will be addressed prior to the start of construction works commencing. If objections have been raised to the scheme and are not withdrawn following provision of further information, then the scheme will be referred to Department for Environment, Food and Rural Affairs (Defra) who will consider the ES and the representations in making its decision. Whittlesey Washes South Barrier Bank Works Environmental Statement 21 3 THE PREFERED OPTION The preferred option is Option 16: Reinforce the entire length of the SBB. This option will involve works to stabilise and strengthen the SBB along the Whittlesey Washes FSR and will include: Flattening the rear slope of the embankment to a 1:5 slope with good grass cover to resist overtopping; Flattening the rear slope of the embankment to a 1:5 slope with reinforced grass cover in locations at a higher risk of overtopping; and Extending the back berm for stabilisation of the embankment. This option will improve the overall condition and stability of the SBB so that it can withstand high water levels during flood events without the need for bank raising. This option has been chosen as the preferred option because it will achieve the legal compliance under the Reservoirs Act 1975 and has minimal impact to the landscape value of the fens. Furthermore this option attracts third party contributions to enable an option to be delivered that is supported by the local community, stakeholders and partners. It is also located on the side of the bank furthest from the Nene Washes internationally designated site and therefore reduces direct impacts to habitats and indirect impacts to interest features (such as bird species) caused by disturbance during construction. The location of the works is shown on Figure 3.1. The following sections provide further details on the construction methodology. 3.1 Scheme Elements The entire scheme (i.e. Years 1, 2, 3 and 4 of construction) comprises of the following elements of works: Selective vvegetation clearance (reed removal) along the Counter Drain which is adjacent to the proposed works. The aim of which is to prevent breeding birds nesting close to the areas where works are proposed; Construction of five new temporary access tracks at Drysides, Eldernell, St Peter’s Farm, Goosetree Farm and Guyhirn Corner which will cross arable land and the Counter Drain where applicable. Each of these new temporary access tracks will be between 500 and 1500m in length and will fit within a 10m width; Potential minor upgrading works to one pre-existing access track through Hanson’s Brick Pits. This pre-existing access track is approximately 400m in length and will fit within a 10m width; The permanent works includes a toe berm which will act as a haulage road during construction. This will become part of the SBB upon completion of the works; Removal and storage of topsoil (total quantity of which is unknown at this time) and placement of new material on the SBB and toe (as illustrated on the typical cross sections on Figure 3.1); Replace the topsoil and, where required, add a geotextile underneath when the work to extend the embankment has been completed; Reinstatement of the entire working areas with grass seed; Creation of two 1m long sections of banks suitable for kingfishers in the Counter Drain; Installation of information boards that help people better understand what they might be seeing on the Washes at key access points (e.g. Stanground, Eldernell Whittlesey Washes South Barrier Bank Works Environmental Statement 22 and Ring’s End), and creation of wetland scrapes to increase habitat and biodiversity, along with looking at opportunities to recreate wet fenland; and finally upon leaving the site; and Removal of the temporary access tracks and reinstatement of pre-existing tracks. Further details on the proposed works are shown on Figure 3.1. The landscaping elements mentioned above are indicative at this stage and will be developed further through discussions with landscape architects, the project team and other stakeholders such as NE and RSPB to ensure that they are designed appropriately. Further details on these proposed enhancements can be found within Chapter 7 Landscape and Visual Amenity. Whittlesey Washes South Barrier Bank Works Environmental Statement 23 Key: N Ring's End Sluice Access routes River Nene Morton's Leam Cradge Bank Proposed Works 1 in 5 slope with reinforcement geotextile (no toe berm required) Guyhirn Corner access Raise by 200mm - 1 in 5 slope with reinforcement geotextile (no toe berm required) Goostree Farm access 1 in 5 slope with reinforcement geotextile (with toe berm) 1 in 5 slope with grass cover (with toe berm) St Peter's Farm access Bank stabilisation only (toe berm) Eldernell access Hanson's existing access Drysides access Source: Reproduced from OS Map by Permission of Ordnance Survey on behalf of The Crown Controller of Her Majesty's Stationary Office. Crown Copyright. All Rights Reserved. Licence Number AL. 100026380 1280 REINFORCEMENT GEOTEXTILE ANCHOR SEE DETAIL 1 DWG 9W3627/16/1004 Title: MINIMUM 100mm TOPSOIL WITH REINFORCEMENT GEOTEXTILE LAID TO MANUFACTURER'S SPECIFICATIONS Scheme Details MINIMUM 100MM TOPSOIL WITH REINFORCEMENT GEOTEXTILE LAID TO MANUFACTURE SPECIFICATIONS 5 1 IMPORTED FILL WITH SIMILAR PROPERTIES TO EXISTING BANK Grassland Grass Grass Grass Drops into Moreton's Leam 4.5 1 Project: Whittlesey Washes South Barrier Bank Works, Environmental Statement FORM 600mm MAX BENCHES TO EXISTING PROFILE MINIMUM 300mm STRIPPED REINFORCEMENT GEOTEXTILE ANCHOR SEE DETAIL 1 DWG 9W3627/16/1004 Client: -0.16 -0.20 53.21 54.90 -0.20 60.00 -0.20 -0.14 47.88 2.20 44.50 1.17 42.43 2.20 2.15 37.51 2.51 27.87 2.35 4.16 35.47 4.34 24.24 35.35 4.73 5.15 20.07 23.81 4.20 16.30 22.89 3.21 13.51 5.02 2.22 10.47 5.02 2.16 8.41 21.95 1.82 Typical cross section through embankment east of Whittlesey REINFORCEMENT GEOTEXTILE ANCHOR SEE DETAIL 1 Grass 5 1 3.1 IMPORTED FILL WITH SIMILAR PROPERTIES TO EXISTING BANK Grass Grass Drops into Moreton's Leam FORM 600mm MAX BENCHES TO EXISTING PROFILE Grass REINFORCEMENT GEOTEXTILE ANCHOR SEE DETAIL 1 AREA TO BE STRIPPED OF TOPSOIL BEFORE NEW MATERIAL PLACED, THEN RE-TOPSOILED AND SEEDED 4.06 5.30 5.26 5.11 4.67 3.29 2.45 2.13 2.17 1.71 1.79 21.88 23.44 24.96 26.31 29.38 31.55 39.12 41.58 45.64 50.43 2.91 14.78 18.30 2.59 8.79 CHAINAGE 2.43 DATUM -01.00 GROUND LEVELS Date: Figure: MINIMUM 100mm TOPSOIL WITH REINFORCEMENT GEOTEXTILE LAID TO MANUFACTURER'S SPECIFICATIONS Grass Grassland Environment Agency Anglian Region April 2013 2500 0.00 CHAINAGE 0.00 GROUND LEVELS 2.35 DATUM -03.00 DESIGN LEVELS Typical cross section through embankment west of Whittlesey Scale: NTS 3.2 Consideration of Water Framework Directive The EU Water Framework Directive 2000/60/EC was transposed into law in England and Wales by the Water Environment (Water Framework Directive) (England and Wales) Regulations 2003. The Regulations mean that the requirements of the Water Framework Directive (WFD) need to be considered at all stages of the river planning and development process. The WFD requires that Environmental Objectives are set for all surface waters and ground waters in each EU Member State. The proposed scheme falls within the Nene management catchment of the Anglian River Basin District. All of the water bodies relevant to the proposed scheme are detailed in Appendix C. As part of enabling works, reed clearance has been undertaken at key locations within the Counter Drain. This measure was taken on the advice of the RSPB who identified that marsh harriers nest in the extensive reed beds present in the drain and could potentially be disturbed by the works. A WFD compliance assessment has been undertaken for these works and can be found in Appendix D. The works for the scheme involve the creation of two temporary bridge crossings over the Counter Drain in Year 1. The proposed design uses a proprietary prefabricated bridge which sits on abutments created using piling and stone infill on one side with a sleeper foundation on the other onto which the bridge is placed. Each bridge will span up to 24m and is approximately 4m wide. In-channel works will be required to create the piled abutment for the bridge; the piling area will be approximately 10m wide. No changes to the channel depth can be expected as although in-channel piling will be required to create the abutment of the bridge this activity will not change the depth of the water body. River width will be reduced slightly by approximately 5m for each of the bridges through the installation of the piling and the creation of the abutment. However, this small loss in width is not anticipated to affect this biological quality element. Overall the works represent a change to river width in approximately 20m of the 12km water body (the Counter Drain), representing a temporary impact to 1.6% of the water body. Given this small scale and the temporary nature of the impact, no overall decline in condition is anticipated. In addition, the proposed enhancement measures for the scheme include the creation of two areas of bank on the Counter Drain which are suitable for kingfishers. These works involve works to the bank of the drain to make it steeper. Given the nature of the Counter Drain and its low flows, these works are considered unlikely to affect the overall condition of this water body. Also, the works comprise approximately 20m of the drain which represents 1.6% of the total length. Therefore, based on professional judgement, it is considered that the proposed works will be compliant with the WFD and will not prevent the achievement of the status objectives identified within the Anglian RBMP. In addition, it would not compromise any adjacent water bodies from achieving their good ecological potential. 3.3 Land Use Requirements The location of the proposed main site compound is shown on Figure 3.2. The main working area is restricted to the SBB itself, with access routes cutting across land to the south. Details of the works east of Whittlesey (i.e. from Ring’s End to Eldernell) are Whittlesey Washes South Barrier Bank Works Environmental Statement 25 provided in Appendix E. The main site compound will be located away from the area of works and used as the main site office. However, one self-contained welfare facilities will be provided at the end of each of the six proposed access routes. 3.4 Site Access Routes The material suppliers are still to be selected, but these will be local and within a 20 mile radius of Whittlesey. The material will be locally won sand and gravel with no or minimal processing. The route to proposed working areas varies depending on which local quarry is selected but typically envisaged to use the A47 and A605 for the section to the east of Whittlesey and the A1139 (Frank Perkins Parkway) and A605 for the section to the west of Whittlesey. The B1040 through Whittlesey may also be used for transporting materials to the east of Whittlesey. These proposed access routes are shown on Figure 3.2. Access for the proposed works will be via the six proposed access routes, five of which will cut across arable land to the south of the SBB (as shown on Figure 3.2) with the remaining one using a pre-existing track through Hanson’s Brick Pits. The access routes required for the Year 1 works have been agreed with the relevant landowners. However, the routes for the remaining years are still in early development and are yet to be formally agreed. All of the proposed access routes will not be in use at the same time and will depend on the programme and progress of the works. In order to access the site at St Peter’s Farm and Goosetree Farm, temporary single track bridges will be required to cross the Counter Drain. The proposed design uses a proprietary prefabricated bridge which sits on abutments created using piling and stone infill on one side with a sleeper foundation on the other onto which the bridge is placed. Each bridge will span up to 24m and is approximately 4m wide. Whittlesey Washes South Barrier Bank Works Environmental Statement 26 Key: ¯ Works Area Proposed Material Transport Routes Proposed Access Routes Proposed Site Compound Ring's End Guyhirn Corner Temporary Access Goosetree Farm Temporary Access Poplar House Farm Site Compound Reproduced from Ordnance Survey Maps with the permission of the Controller of HM Stationary Office. Crown copyright reserved Licence AL.100026380 St Peter's Farm Temporary Access Eldernell Stanground Hanson's Existing Access Proposed Works and Access Routes Project: Whittlesey Whittlesey Washes South Barrier Bank Works, Environmental Statement Drysides Temporary Access Client: Environment Agency Anglian Region Date: April 2013 Figure: 3.2 0 0.5 1 2 3 4 5 Kilometers Scale @ A4: 1:100,000 Path: I:\9W3627\Technical_Data\T5_GIS\Projects\Figures\Environmental Statement\Fig 3_2 Proposed Works & Access Routes.mxd Title: Eldernell Temporary Access 3.5 Construction Works The construction works for the scheme will be split over three to four years. The section to the east of Whittlesey will be commenced in the first year and will continue into Years 2 through to 4, with the section to the west of Whittlesey being undertaken in the second year. It is anticipated that for each year of construction and within the four month working window along the SBB in each of those years, the total volume of material to be imported is in the region of 120,000m3, totalling about 335,000m3. The key stages and construction activities will comprise the following tasks: Year 1 (Ring’s End to Eldernell) – May 2013 to November 2013 Vegetation clearance in Counter Drain and grass cutting along entire length of SBB; Main site compound establishment and mobilisation of plant and equipment for works. The site machinery is likely to include dumper trucks, excavators, dozers and rollers; Construction of the three new temporary access routes (Guyhirn Corner, Goosetree Farm and St Peter’s Farm). Each of these new temporary access tracks will be between 500 and 1500m in length and will fit within a 10m width; Construction of the two Counter Drain crossing points using a proprietary prefabricated bridge siting on abutments created using piling and stone infill on one side with a sleeper foundation on the other. Each bridge will span up to 24m and is approximately 4m wide. A Movax vibratory hammer will be used for the piling works as a way of reducing noise levels and the bridge sections will be lifted into place (from the south side of the Counter Drain) using a suitably sized mobile crane; Implementation of standard protection measures to avoid impacts to the gas mains running along St Peter’s Farm and Ring’s End, in consultation with National Grid; Construction of a haul road, which will form part of the permanent works, that will become part of the SBB and along the landward berm. Details of which are yet to be finalised; Transport of materials along this section of bank; Removal of topsoil which will be temporarily stored in bunds adjacent to the new works and no greater than 1m in height; Placement, compaction and trimming of new material using excavator, dozer and rollers to achieve the new design profiles along the SBB; Where required, add a geotextile to the new SBB slope; Replace topsoil and reseed the new areas of SBB; Cessation of earth works to SBB at the end of October; and Reinstatement of site in November. Further detail on these elements can be found within Appendix E. Year 2 (Eldernell to Bassenhally and Hanson’s Brick Pit to Stanground) – May 2014 to November 2014 Selective vegetation clearance in Counter Drain and grass cutting along entire length of SBB (where required); Whittlesey Washes South Barrier Bank Works Environmental Statement 28 Remobilisation of plant, equipment, temporary Counter Drain bridges and staff. The site machinery is likely to include dumper trucks, excavators, dozers and rollers; Construction of three additional temporary access routes (Eldernell, Hanson’s Brick Pits and Dryside). Each of these new temporary access tracks will be between 500 and 1500m in length and will fit within a 10m width; The permanent works includes a toe berm which will act as a haulage road during construction. This will become part of the SBB upon completion of the works; Transport of materials along this section of bank; Removal of topsoil which will be temporarily stored in bunds adjacent to the new works and no greater than 1m in height; Placement, compaction and trimming of new material using excavator, dozer and rollers to achieve the new design profiles along the SBB; Where required, add a geotextile to the new SBB slope; Replace topsoil and reseed the new areas of SBB; Cessation of works to SBB at the end of October; and Reinstatement of site in November. Years 3 and 4 (continuation of Year 2 works) – May 2015 to November 2015 and May 2016 to November 2016 Selective vegetation clearance in Counter Drain and grass cutting along entire length of SBB (where required); Remobilisation of plant, equipment, temporary Counter Drain bridges and staff. The site machinery is likely to include dumper trucks, excavators, dozers and rollers; Transport of materials along this section of bank; Removal of topsoil which will be temporarily stored in bunds adjacent to the new works and no greater than 1m in height; Placement, compaction and trimming of new material using excavator, dozer and rollers to achieve the new design profiles along the SBB; Where required, add a geotextile to the new SBB slope; Replace topsoil and reseed the new areas of SBB; Cessation of works to SBB at the end of October; and Reinstatement of site in November. When not in use, all of the site machinery will be stored within secure compounds (e.g. within a fenced area with CCTV) that will be located along the SBB. The exact locations of which are unknown at this time and are likely to change depending on the area being worked on at any one time. 3.6 Timing and Duration The proposed construction works to the SBB are anticipated to commence in July 2013 and be completed by November 2016, but will be dependent on weather conditions. However, earth works will only be undertaken between July and October within each year of construction. Mobilisation works including the creation of the five new access routes will be undertaken before July and reinstatement works (including seeding of the area) may extend into November. This four month annual working window has been agreed in consultation with NE and RSPB to avoid impacts to the Nene Washes SPA, Whittlesey Washes South Barrier Bank Works Environmental Statement 29 SAC, Ramsar and SSSI designated site and the species and habitats it is known to support, but with the following exceptions: Ring’s End and Stanground works can start at the end of March and continue to the end of November; and In areas that are more sensitive (i.e. Bassenhally to just beyond Poplar House Farm), construction can start in July if potential nesting areas are cleared beforehand and could continue into November subject to weather conditions. It is expected that the standard construction working hours will be adopted (i.e. 07.00 to 19.00 Monday to Saturday, no working on Sundays or Bank Holidays). The standard working week is five days but the inclusion of Saturday as part of the standard working week allows the contractor flexibility in undertaking the works. It is not envisaged that works will be undertaken every Saturday during the July – October annual working window of the three or four year construction period. 3.7 Transport of Materials Construction plant, equipment and materials required for the construction works will be brought to site by road as described in Section 3.3. It is anticipated that there will be a maximum of 200 lorry movements in any one day to transport material to site. This material will be taken to the working areas and placed without requiring storage. Chapter 10 Traffic and Transport presents the impact assessment of these movements on the local transport network. 3.8 Working Practices The scheme will be built in accordance with industry standard techniques and best practice. Furthermore the works will be undertaken in accordance with the appropriate Environment Agency Pollution Prevention Guidelines (PPG) including (but not restricted to): 3.9 PPG 5 Works and maintenance in or near water; PPG 6 Working at construction and demolition sites; PPG 21 Pollution incident response planning; and PPG 22 Incident response - dealing with spills. Reinstatement and Use of Land following Construction Upon completion of the works, all temporary works will be removed (including the site compounds and temporary access tracks) and the entire area reinstated. Reinstatement works will include reseeding and replacement tree and scrub planting where appropriate. All areas will be returned to their former condition. The site will be maintained by the contractor for one year after completion of the works, to ensure that grass develops on the bank. The Nene Washes form part of the North Level drainage district and as such, upon completion of the works, the NLDIDB will take on responsibility for maintenance of the SBB under agreement with the Environment Agency. This will ensure efficient management of the site into the future. Whittlesey Washes South Barrier Bank Works Environmental Statement 30 3.10 Residues and Emissions All construction vehicles for all years of construction, including the lorries used to transport material to site, will use biodegradable oil, which is a standard Environment Agency procedure as a way of reducing pollution if a leak occurs. Spill kits will also be kept on site to ensure any leaks or accidents are dealt with appropriately. There will be emissions from vehicles used during construction and the small number of vehicles which will be required for maintenance activities. However, this number is likely to be very limited. 3.11 Post-construction Phase Operation and maintenance including grass cutting and clearance of vegetation (i.e. any scrub which develops), of the site will be undertaken as part of the implementation of a maintenance statement for the Nene Washes. This has been produced for the wider Nene Washes area but will get updated to include activities specific to the SBB. Access will be via pre-existing arrangements. It is the intention of the Environment Agency and the NLDIDB to manage the SBB through sheep grazing. This will reduce maintenance costs compared to mechanical clearance and also provide environmental benefits as grazing by livestock is a less intensive management practice which helps to maintain biodiversity. Whittlesey Washes South Barrier Bank Works Environmental Statement 31 4 METHODOLOGY 4.1 EIA Methodology The following information sets out how the effects of the proposed scheme has been assessed during the detailed design stage of the project. The general EIA study area is defined as the SBB itself and the area immediately around it (as shown on the drawings in Appendix B). This includes the location of the proposed main site compound and all of the proposed access routes. For some receptors (e.g. protected species, landscape and archaeology) considered within the EIA, the study area has been widened as required to ensure that an appropriate baseline has been established. In some circumstances such as for ecology, there are accepted assessment methodologies for defining impacts and determining significance, as detailed in Table 4.1. Where specific impact assessment guidelines have been used these are detailed within each technical chapter. Where specific impact assessment guidelines are not available, and/or it is not possible to quantitatively define impacts, qualitative assessments have been carried out based on available knowledge and professional judgement. In these circumstances the general approach as outlined in the subsequent section to predicting significant impacts has been used as a framework with reference to other relevant guidance. Any specific methodologies or assumptions used in the assessments are detailed at the beginning of each chapter. Table 4.1 Guidance followed for development of assessment methodologies Technical chapter Guidance followed to develop methodology Flora and fauna (Chapter 6) Chartered Institute of Ecology and Environmental Management (CIEEM) Guidelines for Ecological Impact Assessment in the UK, 2006. Landscape and Visual Guidelines for Landscape and Visual Assessment, Institute of nd Amenity (Chapter 8) Environmental Management and Assessment, 2 Edition, 2002. Traffic and Transport Institute of Environmental Management and Assessment (IEMA) (Chapter 10) ‘Guidelines for the Environmental Assessment of Road Traffic’ (IEMA, 1993). 4.1.1 Establishment of baseline conditions To identify the aspects of the environment likely to be significantly affected by the proposed works to the SBB, it is necessary to define and describe the existing environmental baseline conditions appropriately. This includes information on the physical, biological and social attributes of the environment of the relevant study areas. The environmental baseline conditions have been defined to date by a comprehensive desktop study of data from the following sources: Information provided by the Environment Agency’s internal specialist functions on historic and ecological features; Biological and protected species records sought from the Cambridgeshire and Peterborough Environmental Records Centres (CPERC); Multi Agency Geographical Information for the Countryside (MAGIC) website, for details of statutory environmental designations; Whittlesey Washes South Barrier Bank Works Environmental Statement 32 4.1.2 Ordnance survey maps and aerial photography; Site visits; Environmental constraints walkover in 2011 and follow-up in 2012; Consultation with Philip Parker Associates regarding the Hanson’s Brick Pits reserve, A Habitats Regulations Assessment of potential impacts of proposed works upon European designated sites of wildlife conservation; Consultation with NE and RSPB regarding presence of protected and important faunal species in the area of works; Peterborough Landscape Character Assessment (Peterborough City Council, 2007); Landscape and Visual Impact Appraisal undertaken by landscape architects; Water Framework Directive Appraisal undertaken by Royal HaskoningDHV in 2013; Historic Environment Records from Peterborough City Council; Previous watching brief undertaken by Oxford Archaeology East in 2011; and Noise Impact Assessment investigation undertaken by Royal HaskoningDHV Noise specialists in 2013. Evaluation of receptors The sensitivity of the receptors was defined based on a combination of quality and relative importance to both the human and natural environment. Table 4.2 outlines the criteria used to make this judgement and provides examples of receptors for each sensitivity rating. This is a general outline methodology and the definition of the sensitivity of each receptor will need to be defined for each individual receptor. Table 4.2 Sensitivity of receptors Sensitivity Description Very High Attribute with a high quality and rarity on an international scale with limited potential for substitution. High Attribute with a high quality and rarity on a national scale with limited potential for substitution, or attribute with a medium quality or rarity on a regional or national scale with limited potential for substitution. Medium Attribute with a medium quality and rarity on a regional (including county or borough/district) or local scale with limited potential for substitution, or attribute with a low quality and rarity on a regional or national scale with limited potential for substitution. Low Attribute with a low quality and rarity on a national or regional scale with limited potential for substitution. Very Low Attribute with a low quality and rarity on a local scale with limited potential for substitution. 4.1.3 Prediction of effects The prediction of the magnitude of effects will primarily be carried out using professional judgement. The assessors will have appropriate professional experience of assessing impacts associated with water related projects and within sensitive sites. Assessments have been carried out by landscape and archaeological specialists, a licensed ecologist, hydromorphological experts and suitably experienced environmental consultants. Predictions will be made using predetermined assessment criteria, as set out below. The assessment will consider both adverse and beneficial effects and this will be stated for each impact identified. The following factors, consistent with the requirements of the Whittlesey Washes South Barrier Bank Works Environmental Statement 33 EIA Directive 85/337/EEC as amended by 97/11/EC and 2003/35/EC, will also be determined for each effect. Temporal scale: short, medium and long term: Short term means during construction and up to one year following completion, medium term extends from 15 years from the start of works, and long term extends beyond 5 years from the start of works. Direct or indirect effect: impact caused by a project and occurring at the same time and place (direct) or impact is not immediately related to the project, but which is caused indirectly by the project (indirect). Temporary or permanent: impacts may occur over the life time of the scheme or may occur for a limited period of time e.g. whilst a specific construction activity is taking place. Reversible/irreversible effect: impacts can be reversed by impact reduction / mitigation measures or by natural environmental recovery within reasonable timescales (5-10 years following cessation of operations). Geographical scale: whether the impact will be felt locally or further afield (e.g. at the regional/county level or nationally/internationally). Cumulative issues: the combined effects of different development activities within the vicinity of the proposed works or different aspects of the proposed scheme on a particular receptor. The magnitude of each effect will be assessed using the terminology and criteria summarised in Table 4.3 below. Table 4.3: Magnitude of impacts Magnitude Description Large Significant change in environmental conditions causing breaches of legislation. Likely to impact on receptors of national or international importance. Likely to affect a large scale area or a large population on frequent or permanent basis. May be an irreversible decline. Medium Unlikely to cause a breach of legislation but likely to impact on a receptor of regional or local environmental importance. Likely to affect a small number of residents/visitors on a permanent basis. Small Likely to impact an area or feature of local interest or importance. Likely to have a temporary impact on a small number of people, or be a recoverable impact. Negligible No material change predicted. 4.1.4 Defining significance The severity or significance of an impact will be determined by considering the magnitude of the effect against the sensitivity of the receptor. A matrix will be used to combine magnitude and sensitivity to generate the overall significance of the impact, as illustrated in Table 4.4 below. Whittlesey Washes South Barrier Bank Works Environmental Statement 34 Table 4.4 Significance of effects Magnitude of impact Large Sensitivity/Value of feature Very High High Medium Major Major Major Medium Major Small Major/ Moderate Negligible Negligible Major/ Moderate Moderate/ Minor Negligible Moderate Low Major/ Moderate Minor Very Low Minor/ Moderate Negligible Minor Negligible Negligible Negligible Negligible Negligible Once the assessment of significance has been undertaken, mitigation measures will be developed to reduce the level of any adverse impacts identified where feasible. Mitigation can reduce the impact to an acceptable standard for that specific receptor, or can eliminate the impact entirely. Once the application of mitigation measures has been considered, any effect that the works are still expected to have on the receptor (the residual effect) will be documented. However, depending on the type of impact and the receptor, it may not be possible to implement appropriate mitigation measures to reduce the impact. 4.1.5 Implementation of mitigation and enhancement Specific mitigation measures identified by the assessment will be set out in the EAP. Generic mitigation measures have not been included as these are considered best practice. The EAP will be incorporated within the contract documents to ensure that all issues identified by the EIA process are addressed and managed whilst on site. A copy of the EAP is provided in Appendix A. 4.1.6 Cumulative effects For the purpose of this EIA, the potential effects of the proposed scheme are initially identified in isolation for each of the environmental topics. In reality, environmental impacts cannot be considered in isolation as one effect may have secondary implications for other topics. To ensure all effects are considered appropriately, there may be some overlap between technical chapters; related effects are appropriately cross referenced between technical chapters. The proposed scheme may also result in cumulative effects when considered incombination with other ongoing or proposed developments in the study area. Cumulative effects may arise from a number of different types of interaction, including: Effects resulting from the combination of activities associated with the scheme, together with other development projects, for example, construction activities arising from the scheme under consideration may be exacerbated by other construction activities from nearby developments that are occurring at the same time; Effects arising from the accumulation of different effects at a specific location, for example, construction noise and visual intrusion affecting a receptor – these may not be significant individually but when acting in combination they may give rise to a significant effect; and Whittlesey Washes South Barrier Bank Works Environmental Statement 35 The accumulation of effects of the same type at different locations, for example, non-significant ecological effects at different sites collectively may give rise to an overall significant ecological effect in a scheme-wide context, or when considered in combination with similar effects from other schemes. Cumulative effects for all receptors will also be considered throughout the EIA process. Whittlesey Washes South Barrier Bank Works Environmental Statement 36 5 HUMAN BEINGS 5.1 Introduction and Methodology This chapter of the ES assesses the potential impacts of the scheme on human beings within the area where works are proposed during both its construction and post construction phases. The methodology used to assess potential impacts involved the following stages: Identification of potential receptors within the general EIA study area boundaries; Determination of the scale of any impacts of the scheme on receptors, including an assessment of any residual impacts; Evaluation of the significance of these impacts relative to the sensitivity and magnitude of the receptors; and Identification of appropriate mitigation measures for all phases of the scheme (all years of construction and operation) and an indication of how these measures will affect the residual significance of any impacts. Significance criteria for human beings has been based on the general approach presented in Chapter 4 Methodology. However, the sensitivity of human environment receptors has been defined using the criteria provided in Table 5.1 below. Table 5.1-Sensitivity criteria for human environment. Sensitivity Description Very High High Medium Low Very Low High density housing or large proportion of vulnerable people (e.g. elderly or infirm) immediately adjacent to the proposals. Nationally designated recreation resources. Main roads/transport links within the study area. High quality agricultural land (Grade 1, 2 or 3a). Communities or residential areas close to proposals with clear views of, or reliant on access through, the area affected by proposals. Regionally important recreational resource or transport links. Regionally important commercial area of medium quality agricultural land (Grade 3b). Commercial areas/property close to proposals with clear views of, or reliant on access through, affected area. Locally important recreational resources widely available to local people or local transport links. Locally important commercial area or lower quality agricultural land (Grade 4). Communities or residential/commercial property located away from the proposals. Privately owned or restricted access recreational resource. Local access roads. Noncommercial area or lowest quality agricultural land (Grade 5). Small scale residential property located away from the proposals. Non-agricultural land. Informal or private recreation. 5.2 Baseline Environment 5.2.1 Land use The land surrounding the proposed scheme is mostly arable land with isolated properties and farms located along minor roads. Under the Agricultural Land Classification system, the arable land to the west of Whittlesey is classified as Grade 4, whereas the land to the east is Grade 3 (Grade 1 is the best quality agricultural land and Whittlesey Washes South Barrier Bank Works Environmental Statement 37 Grade 5 is poorest quality). The SBB is currently used for cattle grazing by the current land tenants. Stanground and Ring’s End which are at the western and eastern ends of the scheme respectively are residential areas. The Fenland market town of Whittlesey is the largest residential area within the general EIA study area and is located approximately 4.5km to the east of Peterborough (see Figure 5.1). The SBB runs to Whittlesey and then starts again on the eastern edge. The town is served by the A605 which runs from Peterborough to Ring’s End and the B1040 which runs north to south through Whittlesey. One of the proposed construction access routes runs past a number of businesses including a McCain’s factory, carpet shop, potato merchants, estate agents, estate management services, agricultural contractor and a medical equipment company. It then runs through the Hanson’s Brick Pit site. This access route is anticipated to be required for use during Years 2 and 3 of the construction period. 5.2.2 Recreation A 25 mile length of The Nene Way long distance path follows the River Nene between Peterborough and Wisbech. The entire route extends from the source of the Nene in Northamptonshire to the sea at King’s Lynn in Norfolk. This route runs along the eastern length of the SBB. The area is also used by local residents for dog walking. Routes 12, 21 and 63 of the Peterborough Green Wheel cycle route run along the Peterborough end of the SBB (a distance of approximately 2km). The location of all these recreation routes is shown on Figure 5.1. Other activities undertaken in the area include fishing in the Counter Drain and Morton’s Leam and shooting by the Whittlesey Wildfowlers and Conservationists in the Nene Washes (the duck and goose shooting season runs from September 1st to January 31st). The location of these areas is shown on Figure 5.1.There is no evidence of the Counter Drain or Morton’s Leam being used for canoeing. Whittlesey Washes South Barrier Bank Works Environmental Statement 38 21 12 ¯ Key: Works Area 21 Cycle Routes 12, 21 & 63 Public Rights of Way Footpaths Nene Way LDFP Proposed Access Routes Proposed Material Transport Routes 21 Agricultural Land Use Grade 1 Grade 2 21 63 12 Stanground Nene 21 21 he Was s rt Mo am unter Le s ' Co on D ra Urban in Reproduced from Ordnance Survey Maps with the permission of the Controller of HM Stationary Office. Crown copyright reserved Licence AL.100026380 Eldernell Title: 63 Current Land Use 63 Whittlesey 12 Non Agricultural Project: 63 Whittlesey Washes South Barrier Bank Works, Environmental Statement 63 Client: Environment Agency Anglian Region 21 Date: April 2013 Figure: 5.1 0 0.5 1 2 3 4 5 Kilometres Scale @ A4: 1:100,000 Path: L:\Sites\UK-Peterborough\Project\9W3627\Technical_Data\T5_GIS\Projects\Figures\Environmental Statement\Fig 5_1 Land Use.mxd 21 63 Grade 4 63 21 12 Grade 3 Ring's End 5.3 Impacts during Construction 5.3.1 Temporary disturbance to land use Access Routes Access routes to the SBB will run through the arable land located to the south of the site and represent a temporary loss of land. In addition, areas of land adjacent to each proposed access route may be used for temporary stockpiling of material required for the works. In total this stockpiled material is not expected to exceed 500m3 on any day for each year of construction. The proposed access routes have been selected to optimise the area of works possible along the SBB. A 10m wide strip of land is required (which includes a 3m buffer for the storage of topsoil) for each proposed access route (with each access route being between 500m and 1500m in length). Topsoil for the stockpile areas will also be stripped and stored for reinstatement. Although five access routes will be across arable land, they will not all be required at the same time and will only be constructed prior to the start of works at that particular location. The access routes and stockpile areas will then be removed upon completion of works in that area. Therefore and based on this understanding, a maximum of two or three growing seasons could be affected through the implementation and usage of the access routes. The area required to enable the construction of the access routes will be minimised wherever possible to reduce the amount of land used. However, normal land practices will be able to continue on land surrounding the access routes and stockpile areas. No severance of land is anticipated. The sensitivity of the receptor is considered to be very high for the Stanground, Eldernell, St Peter’s Farm, Goosetree Farm and Ring’s End access routes as they are within high quality agricultural land, and very low for the Hanson’s access route which goes through a non-agricultural area. However, the scheme will provide compensation for landowners for the land temporarily lost from production. Due to the temporary nature of the impact the magnitude is considered to be small. Based on the criteria defined in Table 5.1, the overall impact is anticipated to be of moderate adverse significance for land use along five of the access routes and of negligible significance for the land required for the Hanson’s route as this is a pre-existing access route. Residual impact Although works to the area are temporary, the temporary loss of land arising from the construction of the proposed access routes and stockpile areas cannot be mitigated against and therefore the residual impact is considered to be moderate adverse for five access routes and negligible for the Hanson’s access route. South Barrier Bank The grazing of livestock will cease along the SBB during the works (i.e. within Years 1 to 3 or 4 of construction) for health and safety reasons. However, this restriction is limited to the area under construction at any one time, rather than the entire footprint of the works. Therefore grazing will be able to continue near Stanground until Year 2. In Whittlesey Washes South Barrier Bank Works Environmental Statement 40 addition, a requirement for no grazing will continue after a section has been completed, for a growing season, to allow for grass to establish. As the area is not currently heavily used for grazing, the sensitivity of the receptor to this short-term impact is considered to be low. The impact will be short term and of a temporary local scale which is considered to be of a small magnitude. Therefore the residual impact is considered to be negligible. 5.3.2 Temporary disturbance to recreation Access along the Nene Way long distance path and parts of Routes 21 and 63 will be restricted during the construction works. Whilst exact usage of these paths/routes is unknown, observations during site visits have recorded local residents using the SBB for recreational purposes (i.e. walking and bird watching). Through discussions with Cambridgeshire County Council (CCC) it has been determined that the long distance path and the cycle routes will be temporarily diverted during the works so that access is still available along the northern side of the SBB. This diversion will be limited to the extent of construction works in each year and whilst grass establishes post-construction. Therefore access along the majority of the SBB will be maintained throughout all years of construction. In addition and once works have finished in a particular section, the diversion will be removed, thus allowing people to access the area from December until June (considered to be a growing season to allow grass to establish). Fishing activities along the Counter Drain will also be restricted during the construction periods of Years 1 and 2. Due to the timing of shooting seasons, it is anticipated this activity will be able to continue as normal and will therefore not be affected by the proposed works. The long distance footpath and cycle routes are considered to be important at a county level and as such the sensitivity of the receptor is considered to be medium. Fishing is considered to be of local importance with a low sensitivity. Without appropriate mitigation, this temporary disruption could lead to a significant disruption over the proposed 3 or 4 years of construction. The magnitude of disruption is considered small and as such a minor adverse impact is anticipated for usage of the long distance path and cycle routes and fishing. Mitigation, Management and Monitoring Mitigation All known interested parties (e.g. local residents and fishing groups) will be informed in writing, at least 1 month prior to the works commencing. Letters will be sent to local residents and notices will be placed on site to inform other users of the area. The information will include a timetable of works, a schedule of working hours, the location and extent of works, type of disturbances likely to be encountered and a contact name, address and telephone number in case of complaint or problem. Management Signs will be erected around site notifying users of the area of the works and the expected impacts that will occur. Signs will be clearly visible and maintained throughout each construction periods. Residual impact Although mitigation measures will be implemented to manage the anticipated impacts associated with the long distance path and cycle routes and recreational users of the Whittlesey Washes South Barrier Bank Works Environmental Statement 41 area, it is anticipated that a temporary minor adverse residual impact will remain as it is not possible to reduce the full extent of the potential disturbance to this receptor. 5.3.3 Temporary disturbance to residents and other users of the site. The proposed works will include the movement of eight wheel lorries (refer to Chapter 10 for details), which has the potential to cause an increase in noise and vibration to local residents and users of the site. In addition, the proposed works will be undertaken close to five residential properties at Poplar House Farm and Ring’s End (approximately 50m from nearest receptor at Ring’s End), although the noise and visual disruption will be short term. Whilst the daily lorry numbers do not represent a significant change to existing traffic conditions in the wider area (refer to Chapter 10 Traffic and Transport for details), there is potential for their movements to cause disturbance to the local farms along the proposed access routes and properties located adjacent to the SBB. It is envisaged that the disruption arising from the proposed works will be short term and temporary, the magnitude is considered to be small. Whilst there are a limited number of residents (approximately six properties at Poplar House Farm and Ring’s End) adjacent to the work area, the impact is anticipated to be minor adverse on a receptor with medium sensitivity. Mitigation, Management and Monitoring Mitigation Pre-construction structural condition surveys of two buildings at Poplar House Farm and four properties at Ring’s End will be undertaken to provide a baseline should any structural impacts from the proposed scheme arise. All local residents will be informed by letter, at least 1 month prior to the works commencing. The information will include a timetable of works, a schedule of working hours, the location and extent of works, type of disturbances likely to occur and a contact name, address and telephone number in case of complaint or problem. Management The contractor will work with tenants and owners to ensure their continued access during the works. Residual impact Although mitigation measures will be implemented to better manage the anticipated impacts associated with the works, it is anticipated that a temporary minor adverse residual impact will remain as it is not possible to fully reduce the potential disturbance associated with the proposed scheme. 5.3.4 Temporary disturbance to local businesses The likely movement of construction vehicles along Funtham’s Lane to the Hanson’s Brick Pit access route represents a potential temporary increase in noise and visual disturbance in that area. There will be approximately 200 lorry movements each day of the works in this area. However, the area is already subjected to a high number of vehicles due to Hanson’s Brick Pit, the McCain’s factory and other distribution related Whittlesey Washes South Barrier Bank Works Environmental Statement 42 businesses. As the area is considered locally important for businesses the sensitivity of this receptor is considered to be medium. The impact is envisaged to be local in scale, short term and temporary which would result in a negligible magnitude. Therefore it is anticipated that there will be a negligible impact on businesses. 5.4 Impacts during Operation 5.4.1 Permanent disturbance to recreation Upon completion of the works, the area will be reinstated and recreational activities will be able to continue as before. Therefore a negligible impact is anticipated. 5.4.2 Permanent disturbance to residents. Land use within the proposed scheme will not be significantly altered as a result of the scheme with areas and roads being reinstated on completion of the works. Signs that were erected to advise affected residents of the proposed works will be removed. Addressing the failure of the SBB and ensuring its effectiveness during extreme flood events results in a major beneficial impact for this proposed scope of works for local residents given that they are considered to be of medium sensitivity and flooding would be a high magnitude impact. 5.5 Impact Summary Table 5.2 below summarises the anticipated impacts (above negligible) on the human environment (and associated effects) before and after mitigation during both the construction and operation phases of all three or four years of the construction programme. Table 5.2 Summary of human environment impacts Description of Impact before Key Mitigation, Management and Impact Mitigation Monitoring Construction Temporary disturbance to land use from access routes Temporary disturbance to recreation Residual Impact Minor adverse None appropriate Minor adverse Minor adverse All known interested parties (e.g. local residents, users of the area) will be informed in writing, well in advance of the works commencing. The information will include a timetable of works, a schedule of working hours, the location and extent of works, type of disturbances likely to be occurred and a contact name, address and telephone number in case of complaint or problem; and Signs will be erected around site notifying users of the area of the works and the expected impacts that will occur. Ensure signs are clearly visible and maintained Minor adverse Whittlesey Washes South Barrier Bank Works Environmental Statement 43 Description of Impact Impact before Mitigation Key Mitigation, Management and Monitoring Temporary disturbance to residents Minor adverse throughout construction period. Pre-construction surveys of local houses will be undertaken to provide a baseline should any impacts from the works arise; All local residents will be informed in writing, well in advance of the works commencing. The information will include a timetable of works, a schedule of working hours, the location and extent of works, type of disturbances likely to be occurred and a contact name, address and telephone number in case of complaint or problem; and Farm owners along access routes will be provided with programme of lorry movements to ensure that daily routine can be coordinated around peak delivery times. Residual Impact Minor adverse Operation Permanent disturbance to residents Major beneficial None required Major beneficial Whittlesey Washes South Barrier Bank Works Environmental Statement 44 6 FLORA AND FAUNA 6.1 Introduction and Methodology This chapter of the ES presents the ecological information gathered from a desk study and walkover surveys undertaken in 2011 and 2012. These studies have allowed an understanding on the key terrestrial and freshwater habitats and the flora and fauna found within the immediate and surrounding area of the scheme (as shown on Figure 6.1). This includes information on individual species and assemblages of flora and fauna protected under European and UK wildlife legislation. In addition, relevant habitats and species identified within other UK nature conservation strategies, such as the UK Biodiversity Action Plan (BAP), are also considered. The potential impacts on these ecological receptors arising from the construction and operation of the scheme have been assessed based on site visits, a suite of ecological surveys, consultation and an analysis of related literature. Mitigation measures are outlined where appropriate. Zone of influence or spatial scope To define the total extent of the study area for ecological assessment, the proposed activities were reviewed in order to identify the spatial scale at which ecological features could be affected. The zone of influence is the area encompassing all predicted positive and negative ecological effects from the proposed scheme, both those which will occur by land–take and habitat loss and those which will occur through disturbance such as noise. Due to the scale of the scheme and the localised nature, it is not considered that the impacts of the scheme will extend beyond the scheme’s footprint and its immediate surroundings. Therefore a zone of 2km around the scheme is considered appropriate for the gathering of information during the desk study. For the field survey, the scheme’s footprint plus a 50m zone around the scheme boundary is considered an appropriate area to survey, primarily due to the Nene Washes and the A605 separating the site from the surrounding area. Temporal scope Impacts have been assessed in the context of the predicted baseline conditions within the zone of influence during the lifetime of the project (i.e. the assessment takes into account how the existing conditions might change between the surveys and the start of construction and/or post construction). For this scheme, construction is expected to start in July 2013 and finish in November 2016, with an annual working window of July until October in each of the three or four years of construction. On this understanding, potential changes in existing conditions up to 2016 have been considered. Whittlesey Washes South Barrier Bank Works Environmental Statement 45 6.2 Legislation, Policy and Guidance The ecological assessment was undertaken with reference to the following legislation, policy and guidance documents: Habitats Directive (Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora) [referred to throughout this assessment as the ‘Habitats Regulations’] The Habitats Directive (together with the Birds Directive) forms the cornerstone of Europe's nature conservation policy. The directive protects over 1,000 animals and plant species and over 200 habitat types, which are of European importance. The directive is transposed into UK legislation by the Conservation of Habitats and Species Regulations (England and Wales) 2010 (as amended). Birds Directive (Directive 2009/147/EC of the European Parliament and of the Council of 30 November 2009 on the Conservation of Wild Birds (codified version)) This Directive provides a framework for the conservation and management of, and human interactions with, wild birds in Europe. In Great Britain this replaces Council Directive 79/409/EEC on the conservation of wild birds (Birds Directive). Wildlife and Countryside Act 1981 (as amended) The Wildlife and Countryside Act 1981 consolidates and amends existing national legislation to implement the Convention on the Conservation of European Wildlife and Natural Habitats (Bern Convention) and Council Directive 79/409/EEC on the conservation of wild birds (Birds Directive) in Great Britain (NB Council Directive 79/409/EEC has now been replaced by Directive 2009/147/EC of the European Parliament and of the Council of 30 November 2009 on the conservation of wild birds (codified version)). Natural Environment and Rural Communities Act 2006 The Natural Environment and Rural Communities (NERC) Act came into force in 2006. The act created Natural England and placed a duty on the Secretary of State to publish a list of habitats and species which are of principal importance for the conservation of biodiversity in England (section 41). The list has been drawn up in consultation with Natural England, as required by the Act. Local and regional authorities must have regard to the list in implementing their duty to conserve biodiversity (section 40), when carrying out their normal functions. Countryside Rights of Way (CRoW) Act 2000 A list of habitats and species of principal importance for the conservation of biological diversity in England has been produced by the Secretary of State for Environment, Food and Rural Affairs, in compliance with Section 74(2) of the Countryside and Rights of Way Act 2000. The need to avoid or mitigate impacts on the species and habitats identified within these documents has been recognised in this assessment. Whittlesey Washes South Barrier Bank Works Environmental Statement 46 Protection of Badgers Act 1992 This Act consolidates the Badgers Act 1973, the Badgers Act 1991 and Badgers (Further Protection) Act 1991. The act affords protection to badgers and their setts. National Planning Policy Framework The National Planning Policy Framework (NPPF) came into force in 2012. Section 11: Conserving and Enhancing the Natural Environment is relevant to this chapter. The policy objective of particular relevance in this section is that the planning system should contribute to enhancing the natural and local environment by ‘minimising impacts on biodiversity and providing net gains in biodiversity where possible, contributing to the Government’s commitment to halt the overall decline in biodiversity, including by establishing coherent ecological networks that are more resilient to current and future pressures’. This policy replaces the Planning Policy Statement (PPS) 9: Biodiversity and Geological Conservation (16 August 2005), UK and Local BAP BAPs are strategies to conserve, protect and enhance biodiversity. The UK BAP sets out a national strategy for the conservation of biodiversity, and local BAPs (LBAPs) have also been produced to address biodiversity issues specific to particular areas in the UK. The LBAP relevant to this project is the Cambridgeshire BAP. Guidelines for Ecological Impact Assessment in the United Kingdom (Chartered Institute of Ecology and Environmental Management (CIEEM, formally IEEM), 2006) The guidelines provide a recommended procedure for the ecological component of Environmental Impact Assessment. The guidelines aim to: 6.3 Promote a scientifically rigorous and transparent approach to EcIA; Provide a common framework to EcIA in order to promote better communication and closer cooperation between ecologists involved in EcIA; and Provide decision-makers with relevant information about the ecological impacts associated with a project, positive and negative. Baseline Environment Data gathering The MAGIC website was used to identify all statutory designated sites of importance for nature conservation and ancient woodlands (a notable habitat) within, and up to 2km from the scheme boundaries. Information was obtained from CPERC on all records of legally protected, BAP and locally notable or rare species within, and up to 2km from, the scheme boundary and on any locally designated non-statutory sites of importance for nature conservation (protected by planning policies at a local level). Ordnance Survey (OS) maps were used to identify the presence of water bodies within a 500m zone from the scheme boundaries in order to establish if the scheme contained any potential breeding ponds and any potential terrestrial habitat for great crested Whittlesey Washes South Barrier Bank Works Environmental Statement 47 newts, a species protected by both British and European law. Great crested newts use water bodies as breeding habitat and can use terrestrial habitat up to 500m from their breeding ponds as a foraging area (English Nature, 2001). OS maps were also used to identify any water bodies within or adjacent to the scheme to identify the potential for impacts on them and on other protected species including otter, water vole and white clawed crayfish which might use them. Aerial photos were reviewed where available to assist in identifying other notable habitats and species of conservation concern that may be present within the survey area. Discussions with the Environment Agency were also undertaken to obtain information and an understanding of the scheme and its potential to support protected species, such as otters and bats. Field surveys An ecological walkover survey of the entire length of the SBB and land within a 50m zone around the SBB where access was allowed (the survey area) was initially undertaken by two suitably qualified ecologists, during the optimum survey period in September/October 2011 and updated to include the eastern section of the SBB in July 2012 (again within the optimum survey period). The purpose of these walkovers was to assess the area for its potential to support protected species and they broadly followed the ‘Extended Phase 1’ methodology as set out in the Guidelines for Baseline Ecological Assessment (Institute of Environmental Management and Assessment (IEMA) 1995). The full survey reports for the 2011 and 2012 walkovers are provided within Appendix F. Preliminary investigations were undertaken in respect of the presence of the following legally protected species within the survey area: A visual inspection from the ground of trees and structures within the scheme’s footprint to assess their suitability for roosting bats; An assessment of habitat potential for nesting birds (including Schedule 1 species which are afforded special protection such as barn owls, marsh harriers and kingfishers) within the scheme’s footprint; A search for signs of badger activity including setts, tracks, snuffles holes and latrines within and up to 50m for the scheme boundaries; An assessment of habitat potential for amphibians, in particular great crested newts, and assessment of potential aquatic and terrestrial habitats including ponds located within 500m of the scheme boundaries and where access permission was available; An assessment of potential habitat to support reptiles within the scheme’s footprint; A search for evidence of water vole activity such as the presence of burrows, feeding stations, faeces and latrines along the Counter Drain (the nearest watercourse to the works) adjacent to the SBB which historically fed into the Old River Nene; Whittlesey Washes South Barrier Bank Works Environmental Statement 48 6.4 A search for evidence of otter activity such as the presence of spraints, lying up places and holts along the Counter Drain which historically fed into the Old River Nene; An assessment of potential habitat to support white clawed crayfish within the Counter Drain which historically fed into the Old River Nene; An assessment of potential habitat to support dormice within the scheme boundaries; and Any evidence of the presence of any invasive species listed in Schedule 9 Part II of the Wildlife & Countryside Act 1981 (including Japanese knotweed and giant hogweed) within the survey area. Ecological Impact Assessment Methodology Nature conservation evaluation The nature conservation value or potential value of an ecological feature is determined within a defined geographic context as defined in Table 6.1. Table 6.1. Assessment of the value of ecological resource (table adapted from CIEEM, 2006) Value Habitats Species International Internationally designated or proposed sites, such as Ramsar sites, Special Protection Areas, Biosphere Reserves, Special Areas of Conservation, or otherwise meeting criteria for international designation. A viable area of a habitat listed in Annex 1 of the Habitats’ Directive. National Nationally designated sites such as Sites of Special Scientific Interest (SSSIs), or non-designated sites meeting SSSI selection criteria, National Nature Reserves (NNRs), Marine Nature Reserves, Nature Conservation Review Grade 1 sites. A viable area of a priority habitat identified in the UK BAP, or of smaller areas of habitat which are essential to maintain the viability of a larger whole. Sites containing viable areas of key habitats listed in a regional BAP. Or smaller areas of such habitat which are essential to maintain the viability of the larger whole. Sites should comfortably exceed local designation criteria if those exist, but not meet national level criteria. Regional County County sites and other sites which the designating authority has determined meet the published ecological selection criteria for designation including Local Nature Reserves selected on County criteria (e.g. County Wildlife Sites). Sites supporting populations of internationally or European important species. Any regularly occurring population of an internationally important species which is rare or threatened in the UK, i.e. a UK Red Data Book species, or listed as occurring in 15 or fewer 10km squares in the UK (categories 1 and 2 in the UK BAP), or of uncertain conservation status or of global conservation concern in the UK BAP. Any regularly occurring population of a nationally important species which is threatened or rare at a regional scale (see LBAP). A regularly occurring, regionally significant population of any nationally important species. A regularly occurring, regionally significant population of any nationally important species during a critical phase of its life cycle. Sites supporting viable breeding populations of Nationally Scarce species (occurring in 16-100 10km squares in the UK) or those included in a regional BAP on account of their rarity, or supplying critical elements of their habitat requirements. A regularly occurring, locally significant number of a regionally important species during a critical phase of its life cycle. Sites supporting viable breeding populations of species known to be rarities on a county scale. A regularly occurring, locally significant number of a county important species during a critical phase of its life-cycle. Whittlesey Washes South Barrier Bank Works Environmental Statement 49 Value Habitats Species Local (district, parish scales) Locally designated or undesignated sites of varied quality containing habitat types of local interest, including amenity and educational functions. Areas of habitat considered to enrich appreciably the habitat resource of a parish e.g., speciesrich hedgerows Low grade and widespread habitats. Sites supporting viable breeding populations of species known to be rarities on a local scale. A regularly occurring, locally significant number of a locally important species during a critical phase of its life-cycle. Negligible No value beyond project site Sites or areas which support few or no communities or species populations of nature conservation interest. No value beyond project site. It must be noted that it is usual to consider habitats and species together when ascribing a value to a feature using this geographic context. However, there are circumstances where an ecologist may feel it is necessary to assign a value to a particularly valuable species. In assigning values to species it is necessary to consider the species’ distribution and status including a consideration of trends based on available historical records and to make use of any relevant published evaluation criteria. For instance, the presence of a significant population of European protected species such as bats and great crested newts may be worth separate consideration. Impact assessment The assessments of the potential impacts of the proposed scheme takes into account both on-site impacts and those that may occur to adjacent and more distant ecological features. Impacts can be positive or negative. Negative impacts can include: Direct loss of wildlife habitats. Fragmentation and isolation of habitats. Disturbance to species from noise, light or other visual stimuli. Changes to key habitat features. Changes to the local hydrology, water quality and/or air quality. Negative and positive impacts on nature conservation features have been characterised based on predicted changes as a result of the proposed scheme. In order to characterise the impacts on each feature, the following parameters are taken account of: The magnitude of the impact. The spatial extent over which the impact will occur. The temporal duration of the impact. Whether the impact is reversible and over what timeframe. The timing and frequency of the impact. The assessment identifies those positive and negative impacts which will be significant, based on the integrity and the conservation status of the ecological feature. Impacts are unlikely to be significant where features of local value or sensitivity are subject to small scale or short term impacts. However, where there are a number of small scale impacts that are not significant alone, it may be that, cumulatively, these may result in an overall significant impact. Whittlesey Washes South Barrier Bank Works Environmental Statement 50 The integrity of ‘defined’ sites is described as follows and has been used in this assessment to determine whether the impacts of the proposals on a designated site are likely to be significant: “The integrity of a site is the coherence of the ecological structure and function across its whole area that enables it to sustain the habitat, complex of habitats and/or the levels of populations of the species for which is was classified” (IEEM. June 2006). The conservation status of habitats and species within a defined geographical area is described as follows and has been used in this assessment to determine whether the impacts of the scheme on non-designated habitats and species are likely to be significant: For habitats, conservation status is determined by the sum of influences acting on the habitat and its typical species that may affect its long term distribution, structure and functions as well as the long term survival of its typical species within a given geographical area; (CIEEM, formally IEEM, June 2006). For species, conservation status is determined by the sum of influences acting on the species concerned that may affect the long term distribution and abundance of its population within a given geographical area (CIEEM, formally IEEM, June 2006). The mitigation measures described have been agreed and are incorporated into the design and programme as well as being taken into account in the assessment of impacts. These measures include those required to achieve the minimum standard of established practice plus additional measures to further reduce the negative impacts of the scheme. In addition, measures to enhance the biodiversity value of the application site are also identified and incorporated into the design. In addition to determining the significance of an impact on any ecological features, this ecological assessment also identifies any legal requirements in relation to wildlife. 6.5 Baseline Environment 6.5.1 Designated sites Figure 6.1 and Table 6.2 shows the internationally, nationally and locally designated sites which were identified within a 2km search area of the scheme (1km for county-level sites). Whittlesey Washes South Barrier Bank Works Environmental Statement 51 Table 6.2. Internationally, nationally and locally designated sites within the vicinity of the proposed works Site Level of Qualifying features / interest features / reasons for selection designation Nene Washes Ramsar International Nene Washes SPA International Nene Washes SAC Nene Washes SSSI International Bassenhally Pit SSSI National Eldernell Gravel Pits County Wildlife Site (CWS) Goosetree Heronry CWS Nene Washes Counter Drain (East) CWS Nene Washes Counter Drain (West) CWS County 5 6 National County County County Nene Washes is an extensive area of seasonally flooded wet grassland. The site is notable for several nationally scarce plants and vulnerable, rare or relict fenland invertebrates. Bewick’s swan Cygnus columbianus bewickii overwinters in internationally important numbers (1,300). The site is also important for various breeding and overwintering waterbirds. Under Article 4.1 (rare or vulnerable species) the site is supports Bewick’s swan over winter. Under Article 4.2 (regularly occurring migratory species) the site supports pintail Anas acuta, northern shoveler Anas clypeata, teal Anas crecca, wigeon Anas penelope, and gadwall Anas strepera over winter; and northern shoveler, garganey Anas querquedula, gadwall Anas strepera, black-tailed godwit Limosa limosa limosa during breeding season. Under Annex II the site supports spined loach Cobitis taenia, the highest recorded density in the UK. ‘This site represents one of the country’s few remaining areas of washland habitat which is essential to the survival nationally and internationally of populations of wildfowl and waders. The site is additionally notable for the diversity of plant and associated animal life within its network of dykes.’5 ‘Bassenhally Pit holds a wide range of habitat types which have developed over shallow gravel workings. Of primary interest are the grassland and aquatic habitats and particularly a small marsh where many locally uncommon vascular plants have been recorded. The latter area represents a habitat type rare in 6 Cambridgeshire and one which is nationally scarce.’ This site (23.49ha) supports at least 0.5ha of National Vegetation Classification (NVC) community S4 common reed Phragimites australis swamp. The site (0.93ha) qualifies as a County Wildlife Site (CWS) because it contains one of the five largest breeding colonies of herons in the county. This site (16.84ha) supports at least 0.5ha of NVC community S4 common reed swamp; at least 0.05ha S13 lesser reedmace Typha angustifolia swamp; at least 5 species of submerged, floating and emergent vascular plant per 20 metre stretch; populations of nationally scarce vascular plant species This site (6.13ha) supports at least 0.5ha of NVC community S4 common reed swamp; contains at least 5 species of submerged, floating and emergent vascular plant per 20 metre stretch. Distance and direction from proposed works Adjacent to, immediately north Adjacent to, immediately north Adjacent to, immediately north Adjacent to, immediately north Adjacent to, immediately south <50m south <500m south Immediately adjacent <100m south Nene Washes SSSI Citation taken from: http://www.sssi.naturalengland.org.uk/citation/citation_photo/1002071.pdf. Accessed 26/02/2013 Bassenhally Pit SSSI Citation taken from: http://www.sssi.naturalengland.org.uk/citation/citation_photo/1000060.pdf. Accessed 26/02/2013 Whittlesey Washes South Barrier Bank Works Environmental Statement 52 Site Level of designation Qualifying features / interest features / reasons for selection Pit Southeast of Bassenhally Pit CWS Stanground Wash Local Wildlife Site (LWS) County This site (1.41ha) qualifies as CWS because it is a Grade C site in the Joint Nature Conservation Committee (JNCC) Invertebrate Site Register. Local King’s Dyke Nature Reserve LWS Local A wetland reserve with its own distinctive habitat. The site is flooded in winter and grazed in summer. Supports overwintering waterfowl, and breeding waders such as snipe Gallinago gallinago, redshank Tringa totanus and sandpipers. Peregrine Falco peregrinus is also notable. Network of ditches support rare beetles and nationally scarce plants including fringed water-lily Nymphoides peltata and grass-wrack pondweed Potamogeton compressus are present within the Back River in the southern part of the reserve. The site is a former quarry established in 1995 and extending 70 hectares. A large range of wildlife has been recorded on the nature reserve. The bird list currently stands at 144 species (turtle dove Streptopelia turtur, marsh harrier Circus aeruginosus, grasshopper warbler Locustella naevia, Cettis warbler Cettia cetti regularly breed plus a host of others, bittern bred for the first time in 2011), 23 species of butterfly, 19 species of dragonfly, over 2000 species of other invertebrates. The site supports a healthy population of grass snake Natrix natrix, common lizard Zootoca vivipara and slow worm Anguis fragilis and a very large population of great crested newts Triturus cristatus . Mammals include otter Lutra lutra and water vole Arvicola amphibius whilst several deer species have been recorded. The site also supports a wide and diverse range of plants, including 10 species of stonewort (including bearded stonewort Chara canescens) making it one of the richest sites in the country for this group. It also includes a number of unusual plant communities (including salt marsh and Breckland type heath) plus County 7 important plant populations. ‘ 7 Distance and direction from proposed works <500m south Adjacent to, immediately north Approx. 500m south King’s Dyke Nature Reserve. Taken from: http://www.kingsdykenaturereserve.com/key-points/. Accessed 26/02/2013 Whittlesey Washes South Barrier Bank Works Environmental Statement 53 Key: ¯ Works Area Nene Washes - Special Protected Area, Ramsar and Site of Special Scientific Interest Bassenhally Site of Special Scientific Interest County Wildlife Sites (CWS) Local Wildlife Site (LWS) Guyhirn Ring's End Goosetree Heronry CWS Stanground Wash LWS Bassenhally Pit SSSI Stanground Bassenhally Pit CWS Whittlesey Nene Washes Counter Drain (East) CWS Eldernell Gravel Pits CWS Eldernell Reproduced from Ordnance Survey Maps with the permission of the Controller of HM Stationary Office. Crown copyright reserved Licence AL.100026380 Title: Designated Sites Nene Washes Counter Drain (West) CWS Project: Whittlesey Washes South Barrier Bank Works, Environmental Statement Kings Dyke LWS Client: Environment Agency Anglian Region Date: April 2013 Figure: 6.1 0 0.5 1 2 3 4 5 Kilometres Scale @ A4: 1:100,000 Path: L:\Sites\UK-Peterborough\Project\9W3627\Technical_Data\T5_GIS\Projects\Figures\Environmental Statement\Fig 6_1 Designated Sites.mxd Bassenhally 6.5.2 Habitats The main habitats present within the survey areas are shown on the figures in Appendix F. The key habitats (some of these are outside the scheme boundaries and the 50m zone either side of its boundaries) noted during the 2012 walk-over survey include: Grassland; Running water; Marginal vegetation; Scrub; Tall ruderal vegetation; Hedgerow; and Trees (both scattered and lines). No UK BAP or Local BAP priority habitats were identified within the scheme boundaries, with the exception of the Counter Drain and Morton’s Leam as all rivers and streams are classed as BAP habitat. The following paragraphs provide a brief summary of the main habitats found within the scheme boundaries. Further details can be found within Appendix F. The SBB is comprised of improved grassland which is maintained by grazing cattle and horses. Herbaceous species present include common mallow Malva sylvestris, various dock and thistle species, wild teasel Dipsacus follonum, greater burdock Arctium lappa, fat hen Chenopodium album, common ragwort Senecio jacobaea, ground ivy Glechoma hederacea, creeping buttercup Ranunculus repens and catsear Hypochaeris glabra. Some small stands of scrub including hawthorn and bramble are present on the tops of the banks but these sections are limited in size and predominantly restricted to the western sections of the SBB near the Hanson’s brick pits. A large sycamore Acer pseudoplatanus is also present in this area in the grassland to the south of the site. The SBB is bordered by two watercourses, Morton’s Leam and the Counter Drain. Both watercourses are heavily poached by cattle and have shallow banks. Aquatic and marginal plants present including pendulous sedge Carex pendula, branched bur-reed Sparganium erectum, common reed Phragmites australis, bulrush Typha latifolia, water forget-me-not Myosotis scorpioides, water mint Mentha aquatica and lesser water parsnip Berula erecta. The Counter Drain is overgrown with reeds in a number of locations. Its banks are typically open, with little scrub or tree growth. However, east of Eldernell the Counter Drain is densely covered by hawthorn which heavily shades the channel and prevents the growth of other bank vegetation. Pendulous sedge, water mint, common duckweed Lemna minor and water crowfoot species are all present in the channel. Towards the eastern section of the SBB the grass has grown up along the edge of the Counter Drain. Adjacent to the railway bridge is a stand of hybrid black poplar Populus x canandensis surrounded by dense bramble Rubus fruticosus scrub , elder Sambucus nigra and Whittlesey Washes South Barrier Bank Works Environmental Statement 55 midlands hawthorn Crataegus laevigata. This area forms a narrow strip of habitat surrounded by arable fields. 6.5.3 Legally protected and notable species The results of the protected species surveys are summarised in the appropriate sections below together with the desk study results. Water voles Water vole Arvicola amphibious was recorded as present in Morton’s Leam (approximately 30m from the SBB) during the 2011 ecological walkover survey and the CPERC provided several of records for water vole in the study area including the Counter Drain. Records of water voles including latrines, feeding remains and pathways were found at three locations within 2km of the works. Locations included in the Counter Drain at Eldernell and Goosetree Farm, approximately 100m and 400m from the SBB, respectively. The habitats within the survey area were all assessed as having low potential to support water voles due to the lack of suitable resting up places, lack of shelter opportunities to hide from predators and the absence of suitable berm habitat for burrowing. Bats Records of bats including sightings, roosts and droppings, were found at two locations (both within the village of Coates) within 2km of the works. The 2011 and 2012 ecological walkover surveys did not assess any trees as having potential to support roosting bats. A small stand of willows on the edge of the Counter Drain were considered to have limited bat roost potential but further assessment undertaken in 2012 determined that there was no potential due to the absence of suitable cracks and crevices. Potential foraging habitat for bat species was identified along the Counter Drain and hedgerows and potential bat roosting habitat was identified in the crack willows in the western extent. Trees in the Bassenhally area also have the potential to support bat species due to the presence of suitable cracks and crevices. Birds Whilst the wider area to the north of the site is internationally designated for its bird species, the SBB and Counter Drain are also known to support a range of bird species. Consultation with RSPB has indicated that marsh harrier, bittern and crane use the Counter Drain and adjacent land (RSPB, personal communication with RSPB site manager). The biological records search provided 7,973 records of birds protected internationally, nationally and locally by the: Bonn Convention, Wildlife and Countryside Act 1981 (as amended) (Schedule 1); NERC Act section 41; Whittlesey Washes South Barrier Bank Works Environmental Statement 56 UK BAP; and LBAP. Potential nesting habitat for birds was identified within Morton’s Leam and the Counter Drain as well as within areas of reeds, hedgerows, trees and scrub within the survey area. The grassland was considered unsuitable for ground nesting birds due to the grazing regime which maintains a short grass sward. Heron Ardea cinerea, and curlew Numenius arquata were recorded in the Nene Washes during the 2011 walkover survey with buzzard Buteo buteo being seen flying over the trees on the south of the Counter Drain and meadow pipit Anthus pratensis flying along the SBB in the same walkover. Reptiles No records of reptiles have been recorded within 2km of the works. During the 2012 walkover, a snake skin was recorded on site. Also on further visits to site grass snakes have been seen near St Peter’s Farm. Suitable reptile habitat for foraging, basking, hibernacula and refugia were present within the survey area and evidence of their presence has been recorded in the eastern section of the SBB. It is therefore anticipated that common reptile species (e.g. grass snake, common lizard and adder) will be present within the scheme boundaries. Great crested newts Great crested newts are known to breed in a number of ponds within the Hanson’s Brick Pits site which is approximately 500m to the south of the SBB and in a pond approximately 250m to the east of the SBB (Phil Parker Associates, personal communication). They have also been recorded within the wider area (as identified in the King’s Dyke Nature Reserve information). No records of great crested newts were provided by CPERC. No signs of great crested newts were noted in the area of proposed works during the 2011 and 2012 ecological walkover surveys. The area of proposed works contains sub optimal terrestrial habitat for great crested newts due to a lack of connectivity (i.e. hedgerows) between their ‘known’ aquatic habitats (i.e. the ponds within the Hanson’s Brick Pits site) and where the proposed works will be undertaken. On this basis, it is considered that their potential to be present within the works area is low. Otters CPBRC returned two records of otters Lutra lutra (five spraints at two locations) within 2km of the works, one of which was at Eldernell Sluice on Morton’s Leam, the other at Poplar House Farm. No evidence of otters (i.e. holts, potential holts or resting places) were found within the scheme boundaries during the 2011 or the 2012 surveys. However due to the transient nature of this species and the presence of wider flowing water bodies, it is feasible that they could on occasion use these as migrating routes. Whittlesey Washes South Barrier Bank Works Environmental Statement 57 Badgers No records of badgers Meles meles have been recorded within 2km of the works. During the 2011 and 2012 ecological walkover surveys, no signs of badgers were found within the scheme boundaries and no setts were noted within a 50m zone of the scheme boundary. However, there is potential for badgers to use the area for foraging given their transient nature. The most optimal habitat within the area of works was identified along the railway embankment due to the slopes and surrounding habitat (farmland and trees). Invertebrates A number of protected invertebrate species are associated with the surrounding designated sites, including small heath and wall butterflies, and cinnabar moth, according to CPBRC. One record of the protected beetle Bembidion genei was provided for the Nene Washes SSSI. Given the existing management and grazing regime present on the SBB it was decided that surveys for invertebrate species would not be required. White clawed crayfish No records of white-clawed crayfish within 2km of the proposed works were provided by CPBRC. Whilst dedicated surveys for white clawed crayfish have not been undertaken, it is considered that the Counter Drain is sub-optimal habitat for this species due to the lack of suitable substrate. Dormice No records of dormice within 2km of the proposed works were provided by CPBRC. No habitat suitable for dormice (i.e. hazel stands or hedgerows) is present within the study area. Other species and invasive species Numerous rabbit burrows were seen along the entire survey area, many within the embankment itself. Burrows were most abundant in the western section of the embankment, from the Hanson’s Brick Pits to Stanground. Bank and/or field vole holes (the holes were of a size to potentially be either species) were recorded within the grassland to the south of the embankment along both sections. A mink Mustela lutreola scat was found near Morton’s Leam in the eastern section of the study area. No evidence of invasive flora and fauna were noted during the 2011 or the 2012 walk over surveys. Whittlesey Washes South Barrier Bank Works Environmental Statement 58 6.6 Impacts during Construction 6.6.1 Disturbance to designated sites Internationally designated sites The proposed scheme will not directly affect any statutory sites of nature conservation importance. However, there is a risk of potential disturbance to the adjacent Nene Washes SAC, SPA and Ramsar site. The proposed works have been programmed so that they avoid the main breeding bird and overwintering seasons which reduces the potential impacts on the habitats and species for which this site is afforded its designation. In addition, as the works are restricted to the southern side of the SSB, there is no direct disturbance to the internationally designated sites. A Habitats Regulations Assessment (HRA) in the form of the Environment Agency Appendix 11, has been prepared for the works, which concluded that there would not be a likely significant effect on the designated sites as a result of the proposed works. This HRA has been submitted to Natural England. The HRA (in the form of an Appendix 11 which is a proforma used by the Environment Agency to document the first stage of a HRA and apply the test of likely significant effect) and letter of support can be found in Appendix G. Through discussions with Natural England, noise modelling was undertaken for the study area. The aim of this modelling was to assess noise levels arising from the works and if noise levels reduced significantly enough in the designated area to not pose a disturbance issue to bird species. The results indicate that noise levels reduce away from the SSB to levels in the range of 40 to 58 decibels (dB). Studies undertaken on behalf of the Environment Agency (Construction and Waterfowl: Defining Sensitivity, Response, Impacts and Guidance, February 2009) into noise disturbance on bird species have shown that birds are tolerant of noise levels below 55dB in less disturbed areas and 55 - 72dB in heavily disturbed locations. Further information on the noise assessment is presented in Appendix H. Therefore, a not significant effect is anticipated on the internationally designated site. Nene Washes SSSI and Bassenhally Pits SSSI There is a risk of potential disturbance from the proposed works to the adjacent SSSI sites. However, the Nene Washes SSSI comprises the same area as the internationally designated sites and as detailed above there will be no direct disturbance to this area. Under the Countryside and Rights of Way Act, an assessment of the potential impacts on these sites has been undertaken. It concluded that given the proposed working window and that there were no direct impacts to the sites themselves, it was unlikely that any significant effects would arise as a result of the works. Therefore, a not significant effect is anticipated on the nationally designated sites. Stanground Wash LNR and King’s Dyke Nature Reserve LNR Whilst both of the sites are not within the actual works area (Stanground Wash lies adjacent to the western end of the proposed works) there is the potential for the works to Whittlesey Washes South Barrier Bank Works Environmental Statement 59 indirectly disturb the interest features of these sites, in particular bird species. However, no direct disturbance to these sites will arise due to the works. As detailed before, the working window is being designed to specifically avoid impacts to breeding and overwintering bird species. Therefore impacts to bird interest features for these sites will be negligible. As the King’s Dyke Nature Reserve is located 500m to the south of the area of works and is located within the Hanson’s Brick Pits site, an area which currently experiences high levels of disturbed due to the movement of lorries, no impact is anticipated on this site. Overall, it is considered that there will be a not significant effect on these LNRs as a result of the proposed works. County Wildlife Sites Goosetree Heronry, Pit Southeast of Bassenhally Pit and Eldernell Gravel Pits are all located approximately 500m away from the area of works. Due to this distance and the interest features for which the sites are afforded protection, it is considered unlikely that these sites will be affected by the proposed works. The Nene Washes Counter Drain (East) and Nene Washes Counter Drain (West) are located close to the area of works, and the two temporary bridge crossings are to be constructed across the Counter Drain to provide access to the eastern section of the SBB. However, these bridge crossings will be temporary and it is anticipated that they will be required for the Year 1 and potentially Year 2 works. The proposed bridge design involves works to the bank of the drain, creating an abutment on which the bridge will rest. This abutment will extend approximately 5m into the Counter Drain. However, these works are limited to approximately 20m of the drain. Although these sites are designated for their aquatic vegetation it is considered that the piling work involved in the creation of the abutments is unlikely to significantly affect plant communities. The rest of the Counter Drain will be able to continue to support these rare species. Therefore, it is considered that the features of the two Counter Drain CWSs will not be affected by the proposed works. Overall, it is anticipated that there will be a not significant effect on these CWSs as a result of the two temporary Counter Drain bridge crossings. 6.6.2 Habitats The proposed works will directly affect the areas of grassland, scrub and trees of nature conservation value in the local context. The proposed works are approximately 15-20m from the Counter Drain at their closest point. All rivers and streams are identified as UK BAP Priority Habitat. Similarly hedgerows are also a UKBAP habitat and a hawthorn dominated hedgerow is present within the proposed works area, running along the cycle route in the western section (see figures in Appendix E). Whittlesey Washes South Barrier Bank Works Environmental Statement 60 The proposed works will result in temporary, localised habitat loss of 0.03ha of improved grassland throughout the works footprint for the duration of the works each year. However, this habitat is common in the wider area and is considered to be of limited ecological value. In addition, there will be localised disturbance of arable land for the proposed access routes. A topsoil strip will be undertaken and the topsoil stored adjacent to the access route. Whilst arable land can support a range of faunal species, it is considered to be of limited value for floral species. These works will also involve localised vegetation clearance at the two crossing points across the Counter Drain, although no in-channel clearance will be required as a result of this activity. The loss of trees and scrub along the Counter Drain and SBB as a result of the vegetation clearance is being undertaken to deter breeding birds from using these area during the proposed works. Given the limited ecological value of the works area, it is considered to be of local importance and the magnitude of the impact is predicted to be minor adverse, therefore the impact is considered to be not significant. 6.6.3 Disturbance to notable and legally protected species Disturbance to water voles A water vole was recorded in Morton’s Leam during the 2011 ecological walkover survey and the CPERC provided several records for water vole in the study area including the Counter Drain. However, the habitat within the area of works is considered to be suboptimal for this species. The main works to the SBB are located approximately 5m away from both Morton’s Leam and the Counter Drain and therefore direct disturbance to animals and their burrows is unlikely to occur. However, the scheme involves the creation of two temporary bridge crossings across the Counter Drain to provide access to the SBB in the eastern section for the Year 1 works. Surveys of these sections of the Counter Drain indicate that the area is sub optimal for water voles due to the lack of suitable bank substrate and the profile of the banks. No signs of water voles were recorded in this area and therefore this species is not considered to be impacted by the installation of these two temporary bridge crossings. The impact is considered to be of minor magnitude due to the poor habitat and low presence of water vole, and the temporary nature of the works. The water vole is of national ecological value and therefore the impact is considered to be not significant. Mitigation, Management and Monitoring Mitigation Should a water vole be discovered during the works, works should cease and Natural England consulted prior to works commencing. Management A toolbox talk on water voles will be given to all site personnel by an ecologist. Whittlesey Washes South Barrier Bank Works Environmental Statement 61 Disturbance to bats Foraging habitat for bats in the area of works was identified during the 2011 and 2012 ecological walkover surveys, including wildlife corridors such as the Counter Drain CWS and the hedgerow running adjacent to the cycle route. The railway bridge in the eastern section of the works has been identified having potential to support roosting bats due to the presence of suitable cracks and crevices. However, given that this bridge is already subjected to disturbance from trains and that no evidence of bats was recorded during the 2011 and 2012 ecological surveys the presence of bats is considered unlikely. The proposed works may lead to disturbance / displacement of commuting and foraging bats as a result of general site presence, noise, and lighting. The works are proposed to take place between the overwintering and breeding bird periods (i.e. from July-October) and given long daylight hours in the summer, the potential for works to impact commuting and foraging bats is considered to be minimal. Works carrying on into autumn may be more likely to coincide with emerging bats. However, it is not anticipated that lighting will be required for the works. Whilst the works will result in a small loss of grassland habitat, the wider area including Morton’s Leam and the Nene Washes, provide more suitable foraging and commuting habitat. Therefore the loss of habitat as a result of the scheme is considered unlikely to affect foraging and commuting bats. Overall, the proposed works are considered to have an impact on bats of negligible magnitude, given bats are of European ecological value, the impact is considered not significant. However, as the works near the railway bridge are to commence in Year 2, mitigation measures have been provided as a precaution to ensure that any bats which move into the area are not affected by the works. Mitigation, Management and Monitoring Mitigation Due to the presence of cracks and crevices within the railway bridge, a suitably qualified ecologist to undertake a day time inspection of the railway bridge at least one month prior to works commencing, followed by dusk/dawn surveys if required. These surveys will be undertaken in accordance with the Bat Conservation Trust (BCT) Bat Surveys Good Practice Guidelines (2012). Management A toolbox talk on bats will be given to all site personnel. Disturbance to breeding bird species There is the potential for disturbance of marsh harrier, bittern and crane species associated with the Counter Drain and adjacent land and other breeding birds to occur from the works. Ground nesting birds were not considered to be likely within the study area due to the maintained nature of the grassland. The works are being timed to avoid disturbing breeding bird species in the Nene Washes internationally designated site. This time frame will also mean that impacts to other breeding bird species are also largely avoided. Through consultation with NE and Whittlesey Washes South Barrier Bank Works Environmental Statement 62 RSPB, reed clearance will be undertaken in the Counter Drain prior to works commencing to avoid disturbing nesting marsh harrier and bittern. Surrounding ditches and drains also contain habitat to support these species and it is therefore considered that the short term reduction in reedbed habitat as a result of works in Years 1 and 2 are unlikely to affect populations of these species. This clearance (if required in Year 2) is to be carried out prior to the breeding bird season starting. Other vegetation clearance required for the site involves the cutting of grass along the SBB. This will also be undertaken outside of the breeding bird season. As nesting birds are protected and therefore considered to be of national ecological value. However and due to the management measures being put into place, the magnitude of potential effects is considered to be negligible. Therefore the impact is predicted to be not significant. Disturbance to reptiles The proposed works may result in temporary, localised disturbance, and displacement of common reptile species from habitats present in the survey area. However, it is considered that the wider area also provides suitable habitat and therefore any impacts on reptiles species would be reduced. As vegetation clearance is proposed as part of the scheme in order to avoid impacting nesting birds, this activity will also make the area less suitable for reptile species. A licence is not required to trap and translocate reptiles. However, a Precautionary Method of Working (PMoW) document has been produced and will cover the initial site works associated with the proposed scheme to avoid the killing or injury of individuals. A copy of the PMoW is available in Appendix I. The key points that the PMoW covers include: That a tool box talk will be presented to all site personnel by an ecologist outlining the legislation afforded to reptiles, their identification and how to proceed should reptiles be found. The requirement that the contractor will need to remove any surface debris (such as branches) from the works area (if present) before works commence. Areas within the scheme boundaries will be made inhospitable for reptiles by undertaking a strimming exercise and will involve cutting the vegetation to approximately 5cm in height with immediate removal of all arisings from site. All advanced habitat manipulation works will be supervised by an ecologist and clearance of potential reptile refuges and strimming exercises will be undertaken outside the reptile hibernation season, which is generally between October and February when temperatures are below 10oC. Reptiles are protected species and are therefore considered to be of national ecological value. The magnitude of the impact is considered to be minor and therefore this results in an impact that is not significant. Following a precautionary approach, mitigation has been recommended. Whittlesey Washes South Barrier Bank Works Environmental Statement 63 Mitigation, Management and Monitoring Mitigation All surface debris will be removed from the works area prior to works. To discourage reptiles from using the areas within the proposed works footprint prior to and during construction, vegetation will be maintained at low levels (in agreement with the landowners) to prevent vegetation establishing and offering suitable habitat for reptiles. In agreement with landowners, hibernacula (in the form of log piles) will be placed in the study area on completion of the works. Management A toolbox talk on reptiles will be given to all site personnel which will inform them of the reptile species which may be present in the area. Disturbance to great crested newts Operations that are reasonably likely to result in an offence under the Conservation of Habitats and Species Regulations 2010 can be undertaken under a licence issued by Natural England (formally issued by Defra). Natural England’s view is that “if the consultant ecologist, on the basis of survey information and specialist knowledge of the species concerned, considers that on balance the proposed activity is reasonably unlikely to result in an offence under the Habitats Regulations then no licence is required” (European Protected Species Guidance Note, Natural England 2007). However, in these circumstances reasonable precautions need to be taken to minimise the effect on European protected species and to avoid causing offences under the Wildlife and Countryside Act 1981. The terrestrial habitat surrounding the ponds within the Hanson’s Brick Pits site (approximately 500m to the south of the SBB) and in the pond approximately 250m to the east of the SBB is considered to be optimal habitat for supporting the various life stages of newts as well as during hibernation. Due to a lack of connectivity (i.e. hedgerows) between their ‘known’ aquatic habitats (i.e. the ponds within the Hanson’s Brick Pits site) and where the proposed works will be undertaken, the SBB is assessed as being of sub optimal terrestrial habitat for great crested newts. As such it is considered that the potential for great crested newts to be present within the works area is low. Consequently and on the basis of the survey information and specialist knowledge of the species concerned, the proposed works are reasonably unlikely to result in an offence under either the Wildlife and Countryside Act 1981 or the Conservation of Habitats and Species Regulations 2010. As such it is considered that no licence will be required. However, in these circumstances reasonable precautions need to be taken to minimise the effect on European protected species and to avoid causing offences under the Wildlife and Countryside Act 1981. Such measures will be outlined in a PMoW. A discussion with NE has been undertaken to confirm this conclusion and that a license would not be required. It was agreed that a PMoW would be produced for the works and a copy of the PMoW is provided in Appendix I. Whittlesey Washes South Barrier Bank Works Environmental Statement 64 The PMoW covers the following key points: A toolbox talk will be presented to all site personnel by an ecologist outlining the legislation afforded to great crested newts, their identification and how to proceed should a great crested newt be found. The requirement that the contractor will need to remove any surface debris (such as branches) from the works area (if present) before works commence. It will also include details of the procedure should a newt be found on-site to ensure that no great crested newts are harmed and to reduce the risk of a legal offence being committed. The PMoW will be in place and agreed with the Contractor before works commence on site. Whilst great crested newts are a protected species and therefore can be considered to be of national ecological value, the implementation of the PMoW will ensure that the magnitude of effect is negligible and therefore the effect on great crested newts is not significant. Disturbance to otters The 2011 and 2012 ecological walkover surveys concluded that the habitat within the Counter Drain and Morton’s Leam was suitable for foraging and commuting, but no otter field signs were noted and no holts were identified. This assessment is supported by the presence of biological records for otters in the wider area. There is the potential that works could disturb otters using the surrounding watercourses given their proximity, although the watercourses themselves will not be directly affected during the works. As otters are typically more active during the night, disturbance as a result of the works to the SBB is unlikely to occur. No trenches are proposed and therefore there is no risk of animals becoming trapped overnight. In addition, the watercourses will not be fenced off and therefore movement along Morton’s Leam or the Counter Drain will not be restricted. Otters are protected species and are therefore considered to be of national ecological value. The magnitude of the impact is considered to be negligible and therefore this results in an impact that is not significant. Disturbance to badgers No badger setts have been recorded during ecological surveys, although their presence in the wider area has been identified through consultation (RSPB, personal communication). Badgers given their protected status are considered to be of national ecological value. Whilst they have not been identified within the working area, badgers are mobile species and could potentially forage or move through the area. The magnitude of any effects on badgers is considered to be limited and negligible, therefore impacts to badgers are considered not significant. However, given the national value of these species the following mitigation measures are recommended. Whittlesey Washes South Barrier Bank Works Environmental Statement 65 Mitigation, Management and Monitoring Mitigation A walkover survey will be undertaken prior to construction to confirm the presence / absence of active badger setts, which may not have been previously recorded. If works are to occur within 30m of an active sett, a Natural England licence to disturb a badger sett may be required to allow the proposed works to take place. In order to ensure that badgers are not impacted during the construction phase simple construction house-keeping activities will minimise any disturbance. This includes: o Construction materials are safely stored away at the end of the day. o Natural linear access features are left unobstructed; and o A toolbox talk on badgers will be given to all site personnel. Management A toolbox talk will be provided to construction staff on this species. Disturbance to invertebrates The species associated with surrounding SSSIs are not considered to be present within the area of works given the lack of suitable habitat and are therefore not considered likely to be significantly impacted by them. Disturbance to white-clawed crayfish It is considered unlikely that this species is present within the Counter Drain. Given the nature of the works and that they are predominantly land based (with the exception of the installation of the two proposed Counter Drain bridge crossings); it is considered that there will not be a significant impact on this species. Disturbance to dormice No suitable habitat for this species has been identified within the area of works and therefore it is not anticipated that there will be any significant impacts to this species. 6.7 Impacts during Operation 6.7.1 Disturbance to designated site The proposed scheme will not result in any permanent loss of any statutory sites of nature conservation importance. Upon completion of the works, the area will be reinstated and current maintenance regimes will continue. As such there will not be a significant effect on designated sites. 6.7.2 Damage to habitats and flora Upon completion of the works, the area will be reinstated and current maintenance regimes including grazing will continue. As such there will not be a significant effect on habitats and flora. Whittlesey Washes South Barrier Bank Works Environmental Statement 66 6.7.3 Disturbance to notable and legally protected species The proposed landscape scheme and ecological mitigation work will result in increased opportunities to support legally protected species within the scheme boundaries and adjacent areas. Through the implementation of the mitigation measures, together with the creation of reptile hibernacula etc, there will be an increase in the biodiversity value of the scheme’s footprint. 6.8 Impact Summary Although there are no significant impacts on ecological receptors, Table 6.3 below outlines the identified precautionary mitigation which will be implemented during the construction works associated with each of the three or four years of construction phase. Table 6.3 Summary of flora and fauna impacts Description of Impact before Key Mitigation, Impact Mitigation Monitoring Construction Disturbance water voles to Not significant Disturbance bats to Not significant Disturbance reptiles to Not significant Management and A toolbox talk on water vole will be given to all site personnel. Should water vole be discovered during the works, works should cease and Natural England consulted prior to works commencing. Due to the presence of cracks and crevices within the railway bridge, a suitably qualified ecologist to undertake a day time inspection of the railway bridge at least one month prior to works commencing, followed by dusk/dawn surveys if required. These surveys will be undertaken in accordance with the Bat Conservation Trust (BCT) Bat Surveys Good Practice Guidelines (2012). A toolbox talk on bats will be given to all site personnel. Vegetation clearance will be supervised by a suitably qualified ecologist and ideally undertaken outside of the hibernating period (November to February, dependent on weather conditions). To discourage reptiles from using the areas within the proposed works footprint prior to and during construction, vegetation will be maintained at low levels (in agreement with the landowners) to prevent vegetation establishing and offering suitable habitat for reptiles. Residual Impact Not significant Not significant Not significant Whittlesey Washes South Barrier Bank Works Environmental Statement 67 Description of Impact Impact before Mitigation Key Mitigation, Monitoring Disturbance badgers to Not significant Management and In agreement with landowners, hibernacula (in the form of log piles) will be placed in the study area on completion of the works. A toolbox talk on reptiles will be given to all site personnel which will inform them of the reptile species which may be present in the area. A walkover survey will be undertaken prior to construction to confirm the presence / absence of active badger setts, which may not have been previously recorded. If works are to occur within 30m of an active sett, a Natural England licence to disturb a badger sett may be required to allow the proposed works to take place. In order to ensure that badgers are not impacted during the construction phase simple construction housekeeping activities will minimise any disturbance. This includes: • Construction materials are safely stored away at the end of the day. • Natural linear access features are left unobstructed; and • A toolbox talk on badgers will be given to all site personnel. A toolbox talk will be provided to construction staff on this species. Residual Impact Not significant Whittlesey Washes South Barrier Bank Works Environmental Statement 68 7 LANDSCAPE AND VISUAL AMENITY 7.1 Introduction and Methodology This chapter of the ES assesses the potential impacts of the scheme on the landscape and visual amenity within the area where works are proposed during both its construction and post construction phases. A Landscape and Visual Appraisal (LVA) for the proposed scheme has been undertaken by LDA Design. The purpose of this LVA is to identify the visual and landscape issues associated with the site and, where necessary, inform the design proposals for the scheme. The LVA has been prepared, as most appropriate to an appraisal of this nature, in accordance with the methodology recommended in Guidelines of Landscape and Visual Impact Assessment, 2002, published jointly by the Landscape Institute and Institute of Environmental Management and Assessment. The LVA includes findings of a desk based review of baseline information together with a field assessment undertaken in February 2013. 7.2 Baseline Environment 7.2.1 Location The site is located along the flood plain of the River Nene, known as the Whittlesey Washes. In times when the river is in spate, the low-lying ground adjacent to the watercourse floods and provides a valuable wetland habitat, as well as important flood alleviation. To ensure that settlements and infrastructure are not affected by inundation, earth flood embankments to the north and south of the river have been constructed between Peterborough to Ring’s End. The site itself is limited to the embankments found to the south of the River Nene, which protect a number of settlements, including Stanground, Whittlesey, Eastrea, Coates and infrastructure such as the A605 which links Peterborough with Guyhirn, via Whittlesey. Generally, the embankment passes through flat arable landscape, although with fields of grassland found north adjacent to the River Nene. 7.2.2 Topography The site is located within the valley floor of the River Nene at approximately 1-3m AOD. As the site sits within the Fens landscape, which is a drained marshland, the surrounding landscape shares the same landform characteristics being flat, low-lying ground drained by field drains in a generally rectilinear formation. The SBB is approximately 3.5-4m higher than the surrounding flat landscape, and is therefore a relatively significant landform within the general topography of the area. 7.2.3 Vegetation The majority of the vegetation across the scheme area consists of grassland managed by livestock. To the east of the site, relatively new plantations of woodland and hedgerows are found at the base of the embankment, whereas generally, the rest of the site is open and lacking in tree and shrub cover. To the west of the site, a line of mature trees is found south of the embankment between Goosetree Farm and Guyhirn, which forms an important vertical feature in the otherwise low-lying landscape. Whittlesey Washes South Barrier Bank Works Environmental Statement 69 South of the embankment lies the Counter Drain where areas of reed and wetland are found. 7.2.4 Landscape character The site and its immediate setting (within a 1km radius) is covered by a hierarchy of landscape character assessments at a national, regional and local scale. For the purposes of a preliminary stage appraisal of this nature, the local landscape character assessment is usually deemed to be the most appropriate scale in terms of defining the baseline context and informing the landscape strategy. The local scale landscape character assessments that cover the scheme are the Cambridgeshire Landscape Guidelines (Cambridgeshire County Council, 1991) and the Peterborough Landscape Character Assessment (Peterborough City Council, 2007). The following high level appraisal of landscape character is based on information in these documents together with observations made during the site visit . Cambridgeshire Landscape Guidelines states that: The site lies within Character 8 – Fenlands, the characteristics of which include: Large open landscape and although appearing monotonous, it is in fact characterised by continuous change as the visual characteristics of one fen merge into the next; Open landscape provides distant views where the scattering of clumps and individual trees merge together to produce a feeling of a more densely tree-covered horizon; Many ‘islands’ which rise above the flat ocean of the fens, usually occupied by settlements or farmsteads which, with their associated tree cover, give them special prominence; and Expansive open landscape against a vast background of a constantly changing sky. In addition to the general characteristics given above, the Guidelines also refer to areas of Fenland with strong individual character, which includes ‘land adjacent to the Ouse and Nene Washes, and other large drainage channels where huge linear grassy banks dominate the landscape.’ Under Principles for Landscape Improvement and Management in the Fenland Area, it states that ‘the essential character is the open view of land, sky and the field drains. Any landscape proposal must suit the massive scale of the landscape and be in keeping with the local character of the particular area’. With regard to tree and hedge planting, the Guidelines indicate that planting should be retained and encouraged in locations associated with settlements and farmsteads to enhance the ‘island’ character of the fen. However, planting in the open fen is generally not recommended. Therefore, no tree or hedgerow planting should be proposed alongside the works at Whittlesey Washes to maintain the open fen character. Under the Management of Dykes and Drains, the Guidelines state that opportunities to enhance the landscape and conservation value of these features should be taken ‘by reprofiling banks, creating dyke deltas or by encouraging more diverse grass and flora’. As the site runs along the Counter Drain in sections, there would be scope to include the above enhancements within the proposals for the scheme. The Guidelines also recommend that ‘all practical opportunities for recreating wet fenland should be exploited’. As seepage through the flood embankments cannot be ruled out, Whittlesey Washes South Barrier Bank Works Environmental Statement 70 there may be scope to encourage wet fenland in certain areas of the site between the embankment and adjacent drains where various grasses and sedges with occasional pockets of reed can establish. Peterborough Landscape Character Assessment states that: The site lies within Character Area 4 – Peterborough Fens, the key characteristics of which include: Flat extensive and open landscape with panoramic views and large skies; Rectilinear field patter reflecting the artificial drainage pattern; Predominantly arable farmland; Isolated farmsteads mainly of Victorian to modern origin; Sparse tree cover generally limited to shelter belts/copses around farmsteads and avenues along drove roads; Road pattern typically rectilinear and raised above the surrounding peat fen; Scattered active and former mineral extraction sites; Settlement on the drained fen mainly of recent origin; and Organic pattern of fields and stronger hedgerows around Thorney. The assessment splits the character area into sub-areas, of which the site is within 4C – Nene Washes, which is an area of grassland that provides seasonal flood storage. Under the evaluation section of the character area, it states that the strength of character is strong and its condition is good, which results in a landscape strategy of ‘safeguard and manage’. Under the guidelines section, the assessment provides a list of countryside management recommendation, the following being the most relevant in relation to what could be achieved within the site: Ensure right of way signage is clear but appropriate to the location using local materials where possible; Encourage appropriate management of all drainage ditches to improve wildlife value, but improving water quality and establishing grass headlands; Discourage the planting of inappropriate woodland blocks throughout the Fens; Encourage seasonal grazing on the Washes; Improve public access where not adversely affecting the ecology of the area; Protect from development that would alter its visual or environmental character; and Improve links out into the area from Peterborough City centre. Summary The landscape character of the site and its setting is typical of that for the Fenlands with its open, flat landscape, large skies and grass embankments running along drainage channels and watercourses. However, both local character assessments recognise that the fen landscape is deteriorating from decades of intensive agriculture and is therefore encouraging enhancement of positive fen features such as diversifying dykes and drains and recreating wet fenland. As the site already has strong characteristics of the Fen landscape, opportunities to enhance dykes and drains and the possibility of recreating wet fenland would enhance the already notable Whittlesey Washes. There are also opportunities to enhance recreation value of the embankments through improved signage and interpretation boards. Whittlesey Washes South Barrier Bank Works Environmental Statement 71 7.2.5 Other designations Public Rights of Way There is a network of public rights of way that extend through the site and across the wider landscape. In particular, the long distance walks of the Nene Way and Hereward Way at various points either cross or follow the flood embankments south of the River Nene, using local public footpaths. These comprise the closest public rights of way to the proposed works. In addition, two regional SUSTRANS routes (Route 21 and Route 63) follow and/or pass over the flood embankments to the Whittlesey Washes, primarily to the west of the site. Further information and assessment of these features can be found In Chapter 5 Human Beings. 7.3 Policy and Designations This section provides an overview of the relevant landscape planning policies and designations which are applicable to the scheme, and which will inform the landscape strategy. 7.3.1 Local Planning Policies Generally, the scheme is located within Fenland District Council (the local planning authority), with the far western parts of the site within the authority of Peterborough City Council. Fenland’s Core Strategy is still emerging, therefore until it is adopted, the planning framework for the site is established at local level through saved policies contained within the Fenland Local Plan (adopted 1993). Peterborough has its Development Planning Policies and Core Strategy adopted (December 2012 and February 2011 respectively) which therefore provide the local level planning framework for the site within this authority. Fenland Local Plan There are no landscape designations within the scheme or surrounding area. However, Policies E1 (Conservation of the Rural Environment) and E3 (Important landscape and townscape features) indicate that any proposed development within the rural landscapes should not detract from the unique, open character of the fenland landscape and that existing trees and hedgerows should be retained. Peterborough Development Plan Document Under Policy PP15 – Nene Valley, it states that: ‘Within the area of the Nene Valley…the city council will support development that would safeguard and enhance recreation or bring landscape, nature conservation, heritage, cultural or amenity benefits. The proposal would need to be appropriate in terms of use, scale and character with its urban or countryside location and the townscape or landscape character of the areas in which it would be situated. Development would be particularly supported if: ‘(b) it would create a more natural water’s edge and contribute to enhancing biodiversity’ Therefore, the proposed scheme should ‘further the conservation and enhancement of the features’ currently found within the SSSI (para 2.15.3). Refer to Section 1.5 for landscape strategy. Whittlesey Washes South Barrier Bank Works Environmental Statement 72 Peterborough Core Strategy Under Core Strategy CS20 – Landscape Character, it states that: ‘New development in and adjoining the countryside should be located and designed in a way that is sensitive to its landscape setting, retaining and enhancing the distinctive qualities of the landscape character area and sub area in which it would be situated. There are six landscape character areas (with associated sub-areas), which have been identified in the Peterborough Landscape Character Assessment... …For each Landscape Character Area and sub area, specific details of which are provided in the LCA, criteria will need to be satisfied in order for development to be approved. Planning permission will only be granted if the proposed development would: (a) recognise and, where possible, enhance the character and qualities of the local landscape through appropriate design and management; (b) reflect and enhance local distinctiveness and diversity; (c) make adequate provision as far as is reasonably practicable for the retention of features and habitats of significant landscape, historic, wildlife and geological importance; (d) safeguard and enhance important views within the development layout; (e) protect the landscape settings and separate identities of settlements; and (f) provide appropriate landscape mitigation proportionate in scale and design, and/or suitable off-site enhancements.’ Therefore, the guidelines provided for Area 4 (Peterborough Fens) of the Peterborough Landscape Character Assessment listed under Section 9.2.6, should be followed and taken forward within the proposed scheme wherever possible. Summary As there are no landscape designations across the site or local area, there are no significant constraints on the proposed scheme with regards to landscape matters. However, there is policy regarding the landscape character of the Fens to ensure that the area is protected and enhanced through guidance provided within the Cambridgeshire Landscape Guidelines and Peterborough Landscape Character Assessment. 7.4 Visual Appraisal The extent to which the site is visible within the surrounding landscape has been established using field based observations. As the proposed works are relatively small in scale and limited to the south facing slope of the SBB, most views towards the site will be from the south of the site or from public rights of way/roads that follow or cross the site. The main visual changes to the SBB will be during construction where the grass and associated topsoil will be removed from the south face. Subsequently, additional material will be delivered and located along the southern slope of the SBB to provide strengthening to the structure. Therefore views to the site will be of construction activity including vehicle movement, material storage and earth movement. On completion, the SBB will be sown with grass seed which will eventually recreate the green bund as it was perceived before, although with a different profile when viewed on site. Whittlesey Washes South Barrier Bank Works Environmental Statement 73 Views from the footpaths and cycleways that cross or follow the site will be the visual receptors that will be the most affected by the works, either by visual changes at close proximity or by diversions that takes the receptors away from the site. These views will be as described above where a usually isolated and tranquil part of the Fens will be temporarily affected by construction activity. On completion, any signage and interpretation boards that will be installed will improve the experience of rights of way users, as well as informing users as to the importance of the Whittlesey Washes and the performance of the SBB. Installation of such signage will be conditional upon obtaining consent from landowners and the Local Authorities. Where re-profiling of the drains is proposed, the resulting increase in habitat will provide a more diverse landscape for users of the rights of way/cycleways to pass through. Views from the northern edges of settlements (i.e. Stanground, Whittlesey, Eastrea and Coates), and farmsteads, that are found along the southern edge of the site will be at distances of approximately between 50-100m, and will generally only be available from locations where vegetation and buildings do not screen available views towards the SBB. Where views to the SBB are available, the construction of the proposed works will provide the most visual effects to receptors, although this will only be temporary. Once completed, grass will quickly green the embankments and views will largely be perceived as unchanged. As with settlements and farmsteads above, the A605 (shown on Figure 3.2) which largely runs parallel to the SBB will occasionally have views towards the proposed works where vegetation and buildings do not intervene. Views will generally be perpendicular to the direction of travel and be of distances approximately between 50-200m from the proposed works. During construction, views of the works will be visible at occasions while passing through the landscape towards construction activity along the SBB. On completion, the greening of the structure will recreate views towards a grassed bank as before. 7.5 Analysis and Landscape Strategy The main issues that need to be addressed from a landscape perspective within the proposed scheme are to maintain the existing open Fenland character and where possible as an integral part of the scheme, benefit any biodiversity/environmental value of the area either within or near to the Nene Washes nature conservation designated sites. As tree and hedgerow planting is generally not a characteristic of the Fenland landscape, it is not recommended that any additional vegetation is proposed as part of the scheme. There are, however, opportunities to re-profile short sections (for example 2 x 10 metre lengths) of the Counter Drain to provide nesting sites for kingfishers in suitable locations such as near Guyhirn, as well as longer stretches of scrapes (100 linear m) to create wetland areas further west along the north of the Counter Drain (see Appendix J). Further information on the wider ecological value of this drain is presented in Chapter 6 Flora and Fauna. In addition, the recreational value of the Whittlesey Washes can be enhanced by providing improved signage that utilise a consistent local material and design where SUSTRANS routes and long distance paths cross the site. In addition, interpretation boards will be provided at key locations of the site (i.e. Eldernell car park, Millennium bridge cross road, Stanground and Ring’s End) to allow users to understand the value of the internationally and nationally designated area and the work that the Environment Agency do in order to alleviate flood water along the Nene and protect local residents. This will be discussed with the relevant authorities. Whittlesey Washes South Barrier Bank Works Environmental Statement 74 7.6 Impact Summary Analysis of the site, its setting and local planning policy has identified that the site has good potential to absorb the proposed landscape and visual effects of the strengthening works to the SBB with minimal impacts. This chapter has identified the main landscape and visual receptors of the proposed scheme and that the main effects to these receptors will be during construction. However, these effects will quickly reverse as the SBB returns to a grassed structure, although with a subtle change to its southern profile. Proposals to increase habitat and biodiversity including the creation of wetland scrapes and two areas of kingfisher nesting habitat will be taken forward following agreement from landowners. Opportunities to recreate wet fenland between the Counter Drain and the SBB to the east of Peterborough would help to meet the landscape and ecology aspirations identified by the local planning authorities. Therefore the landscape character of the Fens will benefit from the proposed scheme from the creation of a variety of wetland habitat. These features are shown on the Final Landscape Masterplan in Appendix J. Users of the rights of way network that cross or follow the site will look to benefit by improved signage and interpretation boards (if approved), as well as passing through an improved diversity of the Fenland landscape proposed through re-profiling of drains and the possible recreation of wet fenland. Whittlesey Washes South Barrier Bank Works Environmental Statement 75 8 HISTORIC ENVIRONMENT 8.1 Introduction and Methodology This chapter of the ES assesses the potential impacts of the scheme on the historic environment within the area where works are proposed during both its construction and post construction phases. The methodology used to identify the baseline conditions within the site involved the following stages: Identification of potential heritage receptors within the scheme boundaries. Determination of the short term, medium term and long term impacts of the scheme on receptors, including an assessment of any residual impacts. Evaluation of the significance of these impacts relative to the sensitivity and quantity of the receptors. Identification of appropriate mitigation measures for all phases of the scheme (all years of construction, post construction and any maintenance requirements) and an indication of how these measures will affect the residual significance of any impacts. Significance criteria for the historic environment have been based on the general approach presented in Chapter 4 Methodology. However, the sensitivity of heritage receptors has been defined using the criteria provided in Table 8.1 below. Table 8.1-Sensitivity criteria for the historic environment Sensitivity Description Very High High Medium Low Remains of inscribed international importance, such as World Heritage Sites. Grade I and Grade II* Listed Buildings. Grade I and Grade II* Registered Parks and Gardens. Scheduled Monuments. Registered battlefields Undesignated archaeological assets of schedulable quality and importance. Undesignated buildings, monuments, sites or landscapes that can be shown to have particularly important qualities in their fabric or historical association. Grade II listed Buildings. Conservation Areas. Grade II Registered Parks. Sites of high archaeological resource value as identified through consultation. Locally listed buildings as recorded on a local authority list Undesignated buildings, monuments, sites or landscapes that can be shown to have important qualities in their fabric or historical association. Historic Townscapes with historic integrity in that the assets that constitute their make-up are clearly legible. Undesignated buildings, monuments, sites or landscapes of local importance and of modest quality Locally important historic or archaeological sites, sites with a local value for education or cultural appreciation and of medium archaeological resource rating, Assets that are so badly damaged that too little remains to justify inclusion into a higher grade, Parks and gardens of local interest. Whittlesey Washes South Barrier Bank Works Environmental Statement 76 8.2 Policy and Designations This section provides a summary of the relevant cultural heritage policies and designations which are applicable to the scheme, and which will inform the historic environment assessment. 8.2.1 Legislative framework (heritage) The Ancient Monuments and Archaeological Areas Act (1979) is the central piece of legislation that protects the archaeological resource. The first section of the Act requires the Secretary of State responsible for National Heritage (now DCMS) to maintain a schedule of nationally important sites. For the purposes of the Act, a monument is defined in Section 61 (7) as: a) “any building, structure or work, whether above or below the surface of the land, and any cave or excavation; b) any site comprising the remains of any such building, structure or work or of any cave or excavation; c) any site comprising, or comprising the remains of, any vehicle, vessel, aircraft or other moveable structure or part thereof which neither constitutes nor forms part of any work which is a monument as defined within paragraph a) above; and d) any machinery attached to a monument shall be regarded as part of the monument if it could not be detached without being dismantled.” A set of criteria, defined as survival / condition, period, rarity, fragility / vulnerability, diversity, documentation, group value and potential, assist in the decision making process as to whether a site is deemed of national importance and best managed by scheduling. English Heritage is enabled by section 8C of the Historic Buildings and Ancient Monuments Act (1953), introduced by paragraph 10 of Schedule 4, of the National Heritage Act (1983), to compile a Register of Parks and Gardens of Special Historic Interest in England. Though designated as being of national interest, a park or garden on the register is not otherwise statutorily protected, although local planning authorities are required to include policies for their protection in their development plan. Section 72 of the Planning (Listed Buildings and Conservation Areas) Act (1990) establishes a desirability to preserve or enhance the character or appearance of a Conservation Area. A Conservation Area is an area of local interest designated principally by the local planning authority. 8.2.2 National Planning Policy Framework The NPPF (Department for Communities and Local Government (DCLG), 2012) was published on 27th March 2012. It took immediate effect and represents a significant change to the national planning policy landscape. The NPPF is a material consideration in planning decisions and forms a single overarching planning policy for England, replacing all other Planning Policy Statements and Planning Policy Guidelines. It is also the basis for the preparation of local development plans. The conservation and enhancement of the historic environment is granted an entire section (section 12) within the NPPF which, in summary, highlights the following issues: Whittlesey Washes South Barrier Bank Works Environmental Statement 77 The Local Plan should set a positive strategy for conservation and enjoyment of the historic environment, recognising that heritage assets are an irreplaceable resource (paragraph 126); Substantial harm to or loss of designated heritage assets of the highest significance, should be wholly exceptional. Where a development will lead to substantial harm to or total loss of significance of a designated heritage asset, local planning authorities should refuse consent, unless there are substantial public benefits (paragraph 132 and paragraph 133); In the case of non-designated heritage assets, a balanced judgment will be required having regard to the scale of any harm or loss and the significance of the heritage asset; and Similarly to Planning Policy Statement 5: Planning for the Historic Environment (PPS5) (Department for Culture Media and Sport (DCMS), 2010), local planning authorities should make gathered information about the significance of the historic environment publicly accessible. They should also require developers to record and advance understanding of the significance of any heritage assets to be lost, proportionate to the value of the asset. Applications that may impact upon undesignated assets should be balanced, considering the presumption in favour of sustainable development, scale of harm or loss and the significance of the heritage asset. In the case of all heritage assets, those applications that will make a positive contribution to the significance or setting of the asset should be treated favourably. 8.2.3 Setting The NPPF (DCLG, 2012) replaces previous guidance relating to the setting of heritage assets, whether designated or not, that was detailed in Planning Policy Statement 5 (DCMS, 2010) and the accompanying Historic Environment Practice Guide (DCLG, 2010). Within the NPPF (DCLG, 2012), the setting of a heritage asset is defined as the “...surroundings in which a heritage asset is experienced. Its extent is not fixed and may change as the asset and its surroundings evolve. Elements of a setting may make a positive or negative contribution to the significance of an asset, may affect the ability to appreciate that significance or may be neutral.” In section 7 ‘Requiring good design’ of the NPPF (DCLG, 2012), paragraph 65 states that local planning authorities can refuse planning permission for buildings or infrastructure if it impacts a designated heritage asset and the impact “…would cause material harm to the asset or its setting which is not outweighed by the proposal’s economic, social and environmental benefits.” In section 12 ‘Conserving and enhancing the historic environment’ of the NPPF (DCLG, 2012), paragraph 128 and paragraph 129 state that the significance of heritage asset needs to be taken into account any contribution made by their setting. “Local planning authorities should identify and assess the particular significance of any heritage asset that may be affected by a proposal (including by development affecting the setting of a heritage asset) taking account of the available evidence and any necessary expertise. They should take this assessment into account when considering the impact of a proposal on a heritage asset, to avoid or minimise conflict between the heritage asset’s conservation and any aspect of the proposal.” Whittlesey Washes South Barrier Bank Works Environmental Statement 78 Paragraph 132 states that “When considering the impact of a proposed development on the significance of a designated heritage asset, great weight should be given to the asset’s conservation. The more important the asset, the greater the weight should be. Significance can be harmed or lost through alteration or destruction of the heritage asset or development within its setting. As heritage assets are irreplaceable, any harm or loss should require clear and convincing justification. Substantial harm to or loss of a grade II listed building, park or garden should be exceptional. Substantial harm to or loss of designated heritage assets of the highest significance, notably scheduled monuments, protected wreck sites, battlefields, grade I and II* listed buildings, grade I and II* registered parks and gardens, and World Heritage Sites, should be wholly exceptional.” English Heritage (2011) has also produced ‘The Setting of Heritage Assets: English Heritage Guidance’, which notes that an assessment of the impact of a proposed development should identify whether the development would be acceptable in terms of the degree of harm to an asset’s setting. This can be identified by using a broad five step approach that: 1) Identifies which assets and settings are affected; 2) Identifies how and what degree these settings make a contribution to the significance of the heritage asset; 3) Assesses the effects of the proposed development; 4) Explores ways to minimise harm and maximise enhancement; and 5) Identifies how to document the decision and monitor outcomes. Setting is understood to embrace all of the surroundings from which the heritage asset can be experienced, and does not have a fixed boundary. Views to and from an asset will play an important part in the way that the asset is experienced. Other factors such as the ‘character’ of the view, screening and cumulative impacts of existing structures within the view need to be taken into consideration. This separates the concept of ‘setting’ from that of the ‘view’; the perception or understanding of an asset or its context can still be appreciated despite changes within its view. For many development proposals, visual effects may be the primary or sole issue requiring assessment for setting (English Heritage, 2011a) and may merit a formal views analysis such as that proposed in ‘Seeing History in the View: A Method for Assessing Heritage Significance within Views‘(English Heritage, 2011b). 8.2.4 English Heritage policy and guidance English Heritage has produced a number of guidance papers in respect of a variety of heritage conservation issues, which are intended to establish broad frameworks and guidance to assist in the making of decisions about England’s historic environment. The guidance documents address specific aspects of the historic environment, and consider them within the context of current English Heritage frameworks and guidelines for best practice and decision making. In 2008, English Heritage published ‘Conservation principles, policies and guidance for the sustainable management of the Historic Environment’ (English Heritage, 2008). The aim of this document is to ensure consistency of approach in English Heritage’s role as the Government’s statutory advisor on the historic environment in England. It aims to set out a logical approach to decision making and offers guidance about all aspects of Whittlesey Washes South Barrier Bank Works Environmental Statement 79 the historic environment and reconciling its protection with the economic and social needs and aspirations of the people who live in it. Whilst the policy guidance is intended to inform English Heritage’s approach to the management of the historic environment as a whole, it also aims to provide a set of principles and policies that may be used by other relevant bodies, such as local planning authorities, property owners, developers and advisers. The document sets out the qualities that contribute to the significance of a heritage asset. It expands upon how these qualities can be appreciated and how a development could impact upon these concepts. These qualities are aesthetic, evidential, communal and historical. The document states that the designation of an asset does not necessarily increase its significance, for example, there may be a Scheduled Monument of a boundary cross dating from the medieval period in a town which may hold evidential and historical value but is of little aesthetic or communal value. In the same town, there may be an undesignated structure which is of great importance to the town’s people. It may be the focus of a local annual celebration or be linked with a famous former resident. Therefore, whilst this structure may be undesignated, its significance is likely to be of equal importance to the Scheduled Monument. 8.2.5 Local planning policies Generally, the scheme is located within Fenland District Council (the local planning authority), with the far western parts of the site within the authority of Peterborough City Council. Fenland’s Core Strategy is still emerging, therefore until it is adopted, the planning framework for the site is established at local level through saved policies contained within the Fenland Local Plan (adopted 1993). Peterborough has its Development Planning Policies and Core Strategy adopted (December 2012 and February 2011 respectively) which therefore provide the local level planning framework for the site within this authority. Fenland Local Plan (adopted 1993) There is one scheduled archaeological site within the scheme boundary, that of a Roman field system comprising a trackway on the line of the Fen Causeway. Policy E6 (Impact on Ancient Monuments and Archaeology) states that: “Planning permission will not normally be granted for development which would adversely affect the preservation or setting of an ancient monument or other important archaeological site. The local planning authority will normally require all planning applications for development on sites of recognised or suspected archaeological importance to be accompanied by an archaeological evaluation.” Peterborough Development Plan Document (December 2012) Under Policy PP17 – Heritage Assets, it states that: “All development proposals that would affect any heritage asset will be required to: (a) describe and assess the significance of the asset and/or its setting to determine its architectural, historic, artistic or archaeological interest; and Whittlesey Washes South Barrier Bank Works Environmental Statement 80 (b) identify the impact of works on the special character of the asset; and (c) provide a clear justification for the works, especially if these would harm the asset or its setting, so that the harm can be weighed against public benefits. The level of detail required should be proportionate to the asset’s importance and sufficient to understand the potential impact of the proposal on its significance and/or setting. Designated heritage assets in Peterborough comprise Scheduled Monuments, Listed Buildings, Conservation Areas and Registered Parks and Gardens. Non-designated (Local) heritage assets are those included in the Peterborough Historic Environment Record; Buildings of Local Importance identified in Appendix C; and, in villages, those green spaces, open spaces and gaps in frontages, treed and hedged frontages, and substantial walls and railings, all as identified on the Policies Map. The work required under (a) to (c) should reference the Historic Environment Record (HER) and other information such as historic maps; the Peterborough Landscape Character Assessment (2007); Conservation Area Appraisals and Management Plans; Peterborough’s List of Buildings of Local Importance; the Design and Development in Selected Villages SPD; and the Peterborough Special Character Areas. All development proposals that would affect a heritage asset will be determined in accordance with national policy in the National Planning Policy Framework.” Peterborough Core Strategy (February 2011) Under Core Strategy CS20 – The Historic Environment, it states that: “The Council will protect, conserve and enhance the historic environment throughout Peterborough, through the special protection afforded to listed buildings, conservation areas and scheduled ancient monuments and through careful control of development that might adversely affect non-scheduled, nationally important archaeological remains; other areas of archaeological potential or importance; historic features and their settings; buildings of local importance; and areas of historic landscape or parkland (including, but not limited to, those on the English Heritage Register of Parks and Gardens of Special Historic Interest). All new development must respect and enhance the local character and distinctiveness of the area in which it would be situated, particularly in areas of high heritage value.” 8.3 Baseline Environment 8.3.1 Topography The site is located within the valley floor of the River Nene and is flat and low-lying at approximately 1-3m AOD. As the site sits within the Fens landscape, which is a drained marshland, the surrounding landscape shares the same landform characteristics being flat, low-lying ground drained by field drains in a generally rectilinear formation. The SBB is approximately 3.5-4m higher than the surrounding flat landscape, and is therefore a relatively significant landform within the general topography of the area. Historically, the topography has been characterised by a series of fossilized silt and sand-filled tidal creek systems dating to the mid to late Holocene period, incised into Whittlesey Washes South Barrier Bank Works Environmental Statement 81 contemporaneous clay deposits. However, anthropogenic change (drainage and agriculture) resulting in a dessication of the peat and it’s loss through “wind blow” has caused the former channels to become positive topographical features known as roddons. The importance of roddons to the regional historic record and local historical landscape character is discussed in more detail in Section 9.3.2 below. 8.3.2 Background history and archaeological potential The majority of the known archaeological records along the scheme relate to the prehistoric (16 records) and Roman (14 records) periods. The impact of people on the natural landscape can be traced back to these periods. Roddons in the English Fenlands are fossilized tidal creek systems commonly infilled during the mid to late Holocene age (6000 to 2000 years Before Present- BP) with many already present in the early Holocene and Devensian, incised into contemporaneous clay deposits. The sedimentary deposits are up to 30m (typically averaging 20m) in thickness. Roddons are of value to the historical record as they show evidence of a complex palaeoenvironmental past including the development of drainage systems. Roddons are seen in the landscape as subtle ridges, up to 1 m high with many examples visible at Whittlesey (Smith et al, 2010). Roddons are evidence to a vanished, natural landscape, that have become exposed as a result of human activity causing peat wastage by harnessing the land for agriculture, domestic and commercial needs. Despite this, they represent an important repository of information regarding post- glacial environmental change. The Fenlands were locally drained during Roman and medieval times, but the roddons became positive features after the phase of 17th century drainage due to the differential compaction of the silts, clays and peats, together with oxidisation and ablation of the peat. Thus, the modern landscape is dominated by evidence of anthropogenic activities associated with drainage and agriculture. The following information is taken from ‘A History of the County of Huntingdon’ (1936). There is little documentary evidence of land reclamation in the medieval period until the work of Bishop Morton shortly before the end of the 15th century. He was head of the commissioners of the district and the streams of the Nene were under his management; and it was clear that effective drainage management was required. At considerable expense, a cut was made from Stanground near Peterborough to Guyhirn, on the assumption that the upland waters would seek the greater gradient of the direct route, in preference to their original course; this cut still bears the name of “Morton's Leam”. It was 12 miles long and by means of it and its associated dams; the Nene was conveyed in a direct line to Wisbech. At Guyhirn, the bishop built Tower House so that he could observe his workmen. Though no longer standing, the brick tower was often referred to in later Inquisitions and Drainage Acts, and was still standing in 1810 when the Barrier Banks Act was passed. The significance of Bishop Morton's work lay in the fact that he confirmed the practice of straight cuts and artificial rivers; and this practice developed into a system which became the basis for all subsequent drainage work in the fenland. The wetland nature of the study area is an important consideration for the potential survival of archaeological deposits. Archaeological organic artefacts can be preserved in damp peat, which in the study area is generally dessicated and eroded as a result of long term agricultural practises, but may have remains in these wetter areas at depth as evidence by recent discoveries in quarries close by. Settlement ddeposits are more likely to lie on/in localised sand and gravel lenses and on the slightly higher land associated with roddons and islands within the fen landscape where there was more Whittlesey Washes South Barrier Bank Works Environmental Statement 82 likelihood of past human habitation. The wet areas near are most likely to contain deposits of an archaeological nature. 8.3.3 Work to date An archaeological watching brief (Oxford Archaeology East, 2011) was conducted on geotechnical site works and the results used to appraise the archaeological potential of subsurface deposits. Based on the stratigraphy recorded the likelihood of encountering preserved archaeology within the first 0.6m is exceedingly small. With the exception of one test pit, the peat horizons where archaeological deposits would be well preserved, occur below 1m of depth (1.15m being the shallowest) and averaging out at around 1.61.7m. Above this level lies a stratigraphy containing the topsoil followed by a layer(s) of redeposited made-ground comprising sands and clayey silts. The analysis comprised 17 test pits at regular intervals along the length of the south face of the southern embankment where the proposed works are planned. However, at the location of one test pit at the far west of the scheme, peat was revealed at 0.5m. This is likely a shallow peat cap but has the potential to preserve archaeological remains. The lack of a peat horizon in other test pits is unclear, though it may be that the peat has been degraded or may be present at a lower depth. 8.3.4 Historic Environment Records (HER) Designated assets The HER were searched for archaeological finds within the scheme boundaries. The HER are listed by period and grid reference in the attached gazetteer (see Appendix K) and their locations shown on Figure 8.1 and overlaid on the modern OS map. Morton's Leam was used as a centre line with a 250m zone either side of it between Peterborough and Guyhirn Bridge and two designated assets were identified. The first is a scheduled monument (07730) - a Roman field system and trackway with later field ditches and droveways located immediately north of Whittlesey Washes, 60m south of Bedford House between Stanground and Whittlesey. The second is a grade II listed building (11750) at the eastern end of the scheme. The building was a Toll-house and is approximately dated to 1860. It is single storey and octagonal in plan and comprises carstone walls and a hipped roof of slate with central octagonal stack. Once the building was historically used for collecting tolls from drovers on the banks of Morton’s Leam. Non-designated assets The known prehistoric records are mostly thought to be Bronze Age in date, several of which are round barrows or ring-ditches and may have had a funerary or monumental function. The majority of the prehistoric remains are recorded in the area between Peterborough and Whittlesey. Prehistoric finds elsewhere along Morton's Leam are limited to stray finds such as a Neolithic flint axe (CHER 01728a) found at Chapel Farm. Important early prehistoric and Bronze Age finds and sites are known from the area around Whittlesey with particular concentrations around the fen edge. Barrow mounds have been identified at Eldernell and Suet Hill, to the south of Whittlesey. In Whittlesey itself a possible bronze age skeleton was discovered in a gravel pit in 1944 (CHER 01482). At the Brickworks Clay Pit, to the south a number of excavations were carried out between 1995 and 2004 which revealed evidence of settlement within this area Whittlesey Washes South Barrier Bank Works Environmental Statement 83 during the Neolithic, Bronze Age and Iron Age periods, including round houses, storage pits and beam slot structures (CHERs 03151a, 01496, CBN14614 and MCB15862). In addition monuments including henges, ring ditches, barrows, an urned cremation and inhumations were also noted within the surrounding area. Ongoing excavations at Must Farm (ECB2096, ECB2093) to the south of Morton's Leam between Peterborough and Whittlesey are revealing an important and rich prehistoric landscape and have included several log boats dating to different periods of prehistory, settlement and burial evidence. To the north of Morton's Leam lies the internationally important prehistoric site of Flag Fen. Roman finds and monuments are almost as prolific as prehistoric with the majority again being located in the area around Whittlesey. Elsewhere along the route Roman remains include a cropmark complex at Elm (CHER 09425) possibly representing a series of field systems and trackways. Whilst Earthworks (MCB17827) including Banks, ditches, enclosures, mounds, turbarys and waterways may be the remains of a Roman harbour at the Nene Washes to the east. A similar ancient fens waterway, Car Dyke, is an eighty mile artificial water channel, thought to have been constructed by the Romans from the first century AD. The Dyke runs along the western edge of the fens and many stretches are protected as a scheduled ancient monument. Several reasons have been postulated as to why the Romans constructed Car Dyke. It may have been a way of providing drainage or a defensible boundary, or a canal to transport goods. A site walkover was undertaken on 5th February 2013 by archaeologists from Environment Agency and from Royal HaskoningDHV. A series of raised ridges and impressions were observed in a field at Guyhirn comprising linear features and trackways maintained in to the modern period where they are being use for pasture. The remains of a bridge (undated, but modern) were also observed on the banks of the counter-drain at the southern boundary of the field. The records state that the earthworks are potentially droveways with integral enclosures (possibly paddocks) lying in the curve of a roddon- the continuation of which can be seen on the other side of the Washes. The gravel island on which Whittlesey is built formed a secure crossing point for a 2nd century Roman road, known as The Fen Causeway, that crossed the fenland between Peterborough and Denver, Norfolk (CHER No. 11048/9 and MCB15033). The significance of the road is undisputed and has been much discussed but seldom investigated. While information about its construction is reasonably well known, evidence of roadside activities is less well understood. Settlements along the southern edge of the fen have been investigated to some extent, where internal roads that may have linked up to the major fen route were in evidence. Consideration of how frequently the road was a focus of roadside activities, at least on the former island crests, is a high priority on the regional research agenda. The projected course of the Fen Causeway, from Peterborough to Grandford, near March crosses close to Morton's Leam at its western end. It enters the island of Whittlesey from Flag Fen and Northey, where portions of gravel road have been recorded (Hall, 1987). Excavations at Stonald Field in Whittlesey, have confirmed the route of the Roman road in the eastern portion of the parish (Knight, 2000). A short 200m length of the causeway has also been identified in the parish through aerial photography. Excavations at the brickworks revealed extensive field systems and possible settlement structures dating from the Roman period (CHERs 029141, 09962 and MCB15855). Roman occupation debris has also been recorded, east of Whittlesey. Whittlesey Washes South Barrier Bank Works Environmental Statement 84 A Saxon cemetery was discovered in the 19th century in the north west part of Whittlesey and contained seven east to west aligned inhumations with associated grave goods (CHER 10594). In the northern part of the town further Anglo Saxon remains were discovered ahead of the building of a new housing estate, these consisted of a number of ring ditches, nine sunken featured buildings representing a small settlement and a square enclosure (CHER No. 04281). The majority of the medieval records (CHER 07827, MCB4673, MCB17919, CHER 03827, MCB4673) relate to Morton's Leam. Morton's Leam is an artificial course of the River Nene, first dug in the medieval period (1478-90) under the direction of Bishop Morton of Ely from Back River to Wisbech. It was largely replaced in the first half of the 17th century and the bank on the south side of Morton's Leam is thought to date to this period. Evidence for Medieval occupation in Whittlesey itself comes from sites producing an abundance of finds. Archaeological evaluation of a school site in the town discovered a series of medieval furrows representing a field system (Fletcher 2004, Bailey and Macaulay 2005, MCB17606). In summary, Morton’s Leam is a significant medieval and post-medieval landscape feature and the field pattern hanging off it are a significant medieval designed landscape the character of which survives in good condition in some areas. Current knowledge suggests that the west end of Morton's Leam (between Peterborough and Whittlesey passes through a highly sensitive archaeological landscape, particularly for the prehistoric period, although there are also cropmarks of probable Roman date that lie both within and just outside the search area. The Roman Fen Causeway to the south of Morton's Leam certainly attracted settlement along its route. The eastern end of the route, although less densely populated in terms of known archaeological remains, is the location for significant Roman remains (possible Roman harbour and related features). The remainder of the route is more sparsely populated, but this may be more a result of the limited development and investigation that has taken place here rather than a true reflection of its archaeological potential. Whittlesey Washes South Barrier Bank Works Environmental Statement 85 Key: Evaluation of Guyhirn Bridge Earthwork Survey of Morton's Leam MCB17827 Morton's Leam ECB2065 old course MCB17919 MCB16889 ^ _ ^ _ 12246 ^ _ ¯ ^ _ 51654 51655 02971 50404 _ ^^ _ _ _ ^ _^ ^ _ ^ _ ^ _ ^ ^ _ _ ^ _ ^ _ _^ ^ _ ^ _ ^ Historic Environment Records search area _ ^ _ ^ _ ^ ^ _ _ ^_ ^ _ ^ ^ _ _ ^ ^ _ MCB16890 ^ _ _ ^ ^ _ MCB15862 02941 03496 CB14614 CB14615 CB15033 Reproduced from Ordnance Survey Maps with the permission of the Controller of HM Stationary Office. Crown copyright reserved Licence AL.100026380 Title: Historic Environment Records of 02292 Study Area Project: ^ _ Whittlesey Washes South Barrier Bank Works, Environmental Statement Client: Environment Agency Anglian Region ^ _ ^ _ MCB15855 51652 52283 09806 52301 Must Farm 02813 AP assessment excavation MCB16889 MCB15856 MCB15859 CB15190 ( ! Listed Building Monument (line) Listed Building 480901 Toll House CB15225 CB15221 Stonald Field evaluation 10161 Scheduled Monument ( Monument (area) Morton's Leam 03827 CB14606 08195 Bradley Fen excavations Monument (point) s e wa y Fen C au 3 03 5 1 B C King's Dyke excavations 51650 51649 ^ _ 07729 03827 52302 51653 51261 03708 01728a ^ __ ^ 07730 Scheduled Monument 51651 10647 03820 02292 ^ _ _ ^ ( ! ^ _ ^ _ _ ^ 09425 ^ _ MCB16744 MCB16617 ^ _ Morton's Leam modern course 03827 Morton's Leam 03827 Archaeological Study CB15217 11750 Date: MCB16748 MCB17514 11047 CB15033 (Fen Causeway) April 2013 Figure: 8.1 Scale @ A4: 1:60,000 Path: I:\9W3627\Technical_Data\T5_GIS\Projects\Figures\Environmental Statement\Fig 8_1 Historic Environment Records.mxd ¯ 8.4 Impacts during Construction 8.4.1 Pre-application mitigation A series of design criteria were considered during the project design process in order to minimise the potential effects to heritage assets. These design criteria sought to avoid direct impacts upon heritage assets and their setting. In addition, the layout of the proposed access routes and temporary construction areas have been developed to avoid impacts to known non-designated heritage assets where possible. The avoidance of significant archaeological remains (including the scheduled monument and listed building) has also been informed by a programme of archaeological fieldwork comprising a walkover survey and a watching brief during geotechnical survey works, the results of which have informed the proposed development design. 8.4.2 Post-application mitigation Potential direct impacts to non-designated archaeological deposits have been identified in the area of access roads- notably at Guyhirn and the crossing of the Fen Causeway near St Peter’s Farm; and during the re-shaping of the SBB. The construction of these components of the proposed development has the potential to impact buried remains relating to prehistoric and Roman settlement features. An archaeological mitigation strategy is proposed below, which sets out the methodology for conserving the archaeological resource. The mitigation strategy will be developed in consultation with the Environment Agency archaeologist and any subsequent detailed written schemes of investigation will be agreed with PCC archaeologist as the local planning authority in consultation with CCC and EH where necessary. 8.4.3 Direct impacts on buried archaeology Access Routes The proposed access routes to the SBB will run through the arable land located to the south of the site and could potentially truncate unknown shallow archaeological deposits. Access for the works will be via five new proposed access routes, cutting across arable land to the south of the SBB (as shown on Figure 3.2), with an existing track through Hanson’s Brick Pits also being used. The location of the access routes for Year 2-4 works has yet to be formally agreed/confirmed with the appropriate landowner. Each of these new temporary access tracks will be between 500 and 1500m in length and will fit within a 10m width. These routes will not all be in use, but will be staged according to the location of the works. A haul road will be constructed parallel to the SBB which will allow access to the whole site. The construction of the access routes will require the widening of some existing trackways as well as areas of topsoil strip and a laydown area to deposit soil prior to reinstatement. The impact of access routes would be created through the topsoil strip and compaction from site vehicles and topsoil storage. However, a substantial amount of the access is planned along the existing banks and so no archaeological works are proposed in these areas. The sensitivity of the receptor is considered to be low to medium. One access route is proposed to run across the Fen Causeway at the location of a pre-existing farm track which would require widening to the above specifications. Due to the permanent nature Whittlesey Washes South Barrier Bank Works Environmental Statement 87 of the impact the magnitude is considered to be large. Without mitigation, the impact is anticipated to be major/moderate adverse. Mitigation, Management and Monitoring Mitigation All works will be subject to a specification of archaeological works in consultation with the Environment Agency archaeologist and agreed with the PCC archaeologist as the local planning authority in consultation with CCC. Management Avoidance of areas identified as archaeologically sensitive e.g. Guyhirn, where possible. Where appropriate a watching brief will be conducted during topsoil strip to identify and record any significant archaeological deposits disturbed as a result of the works. Residual impact Pre-construction mitigation comprising a watching brief following an agreed programme of archaeological works during topsoil strip is proposed to identify the potential for subsurface archaeological deposits. Following mitigation the impact will be negligible/minor adverse. South Barrier Bank There is a potential to impact buried archaeological deposits on the SBB in the area near Stanground. An archaeological watching brief and appraisal (Oxford Archaeology East 2011) of geotechnical boreholes revealed that this area comprised shallow peat deposits which have the potential to preserve archaeological remains. These peat layers lie at a sufficiently shallow depth that they would be truncated by the proposed reshaping of the flood bank. The sensitivity of the receptor is considered to be low to medium and due to the permanent nature of the impact the magnitude is considered to be large. Without mitigation, the impact is anticipated to be major/moderate adverse. Mitigation, Management and Monitoring Mitigation Pre-construction field surveys comprising trial trenching and a watching brief on geotechnical works will be conducted to help identify the existence of areas of archaeological potential which can be used to aid in the project design and avoid where possible; and All works will be subject to a specification of archaeological works in consultation with the Environment Agency archaeologist and agreed with the PCC archaeologist as the local planning authority in consultation with CCC. Residual impact Pre-construction mitigation comprising a watching brief following an agreed programme of archaeological works during topsoil strip is proposed to identify the potential for subsurface archaeological deposits. Following mitigation the impact will be negligible/minor adverse. 8.4.4 Impacts on the setting of designated assets There are two designated assets within the scheme boundary- a scheduled monument comprising a Roman field system (07730); and one listed building identified within the Whittlesey Washes South Barrier Bank Works Environmental Statement 88 scheme boundary, a post-medieval toll house (11750) at Ring’s End on the eastern end of the proposed works. There will be temporary visual and noise impacts from the movement of lorries along access routes. A key element of the setting of these assets is the quiet of the surrounding area and therefore noise from the construction works and vehicles will detract from that setting. The assets are of high sensitivity, though as the disruption will be short term and temporary, the magnitude is considered to be small. The impact is anticipated to be moderate/minor adverse. Residual impact No mitigation is proposed due to the temporary nature of the impact, so a temporary moderate/minor adverse impact will remain as it is not possible to reduce the potential disturbance. 8.5 Impacts during Operation 8.5.1 Direct impacts on buried archaeology Any direct impacts to buried archaeological deposits will occur during the construction phase. No direct impacts are anticipated during the operation of the scheme. 8.5.2 Setting impacts Land character within the area will not be significantly altered as a result of the proposed works and there will be a negligible operational impact on the setting of the scheduled monument and the listed toll house at Ring’s End. Addressing the failure of the SBB and ensuring its effectiveness during extreme flood events results in a major beneficial impact for building. No mitigation is required during the operational stage. 8.6 Impact Summary Table 8.2 below outlines the impacts to the historic environment which are considered to be above negligible, before and after mitigation during both the construction and operation phases for all years of construction. Table 8.2 Summary of historic environment impacts Description of Impact before Key Mitigation, Management and Impact Mitigation Monitoring Construction Direct impact to archaeological deposits from access routes Major/moderate adverse Setting impacts on designated assets Moderate/Minor adverse A programme of archaeological works comprising of a targeted watching brief will be conducted during topsoil strip to identify and record any archaeological deposits; and All works will be subject to a Written Scheme of Investigation agreed with the Cambridgeshire and Peterborough council archaeologists. No mitigation proposed due to the temporary nature of impact. Residual Impact Negligible/Minor adverse Moderate/Minor adverse Whittlesey Washes South Barrier Bank Works Environmental Statement 89 Description of Impact Operation Impact before Mitigation Key Mitigation, Management and Monitoring Residual Impact Operational setting impacts Major beneficial Major beneficial None applicable Whittlesey Washes South Barrier Bank Works Environmental Statement 90 9 TRAFFIC AND TRANSPORT 9.1 Introduction and Methodology This chapter of the ES assesses the potential impacts of the scheme on traffic and transport within the area where works are proposed during both its construction and post construction phases for the entire three or four year construction period. The assessment focuses on the main construction access routes (see Figure 3.1), therefore the EIA criteria relates to whether the mitigation works required to facilitate access have a detrimental impact on the identified receptors. The potential impacts of construction related traffic associated with the construction of the scheme over the three or four construction period have been assessed using the qualitative significance criteria presented in Table 9.1 below. Table 9.1-Sensitivity criteria for traffic and transport Sensitivity Description High beneficial Low beneficial Negligible Low adverse High adverse The scheme will not impact on congestion on the local highway network. The scheme will not impact on sustainable access to the site and surrounding areas. The scheme will not impact on congestion on the local highway network. No change to existing travel patterns or highway congestion will arise from the scheme The scheme will provide some measures which discourage sustainable access to the site and surrounding areas and/or will slightly detrimentally impact on conditions on the local highway network. The scheme will greatly discourage sustainable access to the site and surrounding areas and/or will have major detrimental impacts on conditions on the local highway network and cause substantial traffic congestion. The methodology used to identify the baseline conditions within the scheme is detailed within Chapter 4 Methodology. 9.2 Baseline Environment Details of the construction equipment, routes, working locations and timeframes are provided within Chapter 3 Preferred Option. 9.2.1 Local road network The scheme is adjacent to Whittlesey a small country town which connects to the A1139 in Peterborough to the east and the A141 and the A47 leading to Wisbech to the north west, via the A605. The B1040 runs to the south and through Whittlesey connecting it to Thorney in the north and Ramsey in the south (see Figure 9.1). These roads already receive large numbers of lorry movements due to the location of the quarries and other businesses such as Hanson’s Brick Pits and the McCain’s factory. The A605 and part of the A47 are classed as Strategic Heavy Commercial Vehicle (HCV) routes by CCCl (as shown on Figure 9.1). Local roads which are currently used by local businesses and residents include Eldernell Lane, Funtham’s Lane, Drybread Road and Long Drove (see Figure 9.1). The majority of these roads lead to residential areas and have an imposed 30mph speed limit. Eldernell Lane also has a 30mph speed limit but is a narrow single lane road with space Whittlesey Washes South Barrier Bank Works Environmental Statement 91 for only one car for the majority of its length. There are car passing points along this road. Funtham’s Lane leads to the Hanson’s Brick Pits and is currently used by heavy goods vehicles (HGVs) and site vehicles. This lane also provides access for a number of other businesses including the McCain’s factory. Whittlesey Washes South Barrier Bank Works Environmental Statement 92 Key: ¯ Works Area Local Road Main Road CC Strategic HCV Route A47 A47 A47 A47 A141 B1040 A1139 A605 Long Drove Drybread Road A1139 A605 Title: Local Road Network Project: A605 A141 A605 Whittlesey Washes South Barrier Bank Works, Environmental Statement Client: Environment Agency Anglian Region Date: April 2013 Figure: 9.1 0 0.5 1 2 3 4 5 Kilometers Scale @ A4: 1:100,000 Path: I:\9W3627\Technical_Data\T5_GIS\Projects\Figures\Environmental Statement\Fig 9_1 Local Road Network.mxd Hanson's Existing Access Edernell Lane Reproduced from Ordnance Survey Maps with the permission of the Controller of HM Stationary Office. Crown copyright reserved Licence AL.100026380 9.2.2 Other forms of transport Route 31 of the Stagecoach bus network connects Peterborough to Ramsey via Whittlesey. It runs eight times each day with no service on a Sunday or bank holiday. Route 33 also runs from Peterborough via Whittlesey and goes to March. It is a regular service, running to Whittlesey every hour with a reduced service on Sundays. Route 701 run by Judds Coaches runs on an hourly basis from Coates to Peterborough via Whittlesey. There are a number of PRoW’s and cycle paths that serve the Whittlesey area. The locations of these routes and the potential impacts on these receptors are provided in Chapter 5 Human Beings. 9.3 Impacts during Construction 9.3.1 Disruption to local road network from construction traffic There is the potential that the traffic movements associated with the supply of materials and the general construction works of the proposed scheme could cause a disruption to users of the local road network. Through the development of the proposed scheme, it is envisaged that there will be approximately 200 lorry movements each day of construction in order to supply the material needed for the proposed scheme. This represents a total of 28,000 lorry movements each year of construction based on a four month construction period each year with a six day working week (with the potential for this to be reduced in the final months of Year 3 and Year 4 as the works are likely to be nearly completed). It is estimated that there will be approximately 70 lorry movements per access route which equates to a lorry on each access road every ten minutes. In addition, it is estimated that there will be approximately 50 movements every day for staff travelling to site and also for travel between the area of works (the SBB) and the site compound. Access to the site will be via a number of existing public and private roads (see Figure 3.1). The routes from the quarries (i.e. the source of materials) to the site will primarily be via the A47, A605 and the B1040. In order to access the SBB, access routes on to the site and specific working areas will be created using existing roads and newly constructed ones. Due to the staging of the works over three or four years, lorries will not being using all of the proposed access routes (see Figure 3.1) at any one time. The proposed access routes to the site have been selected to minimise disruption to local residents. Furthermore, daily access for residents within these areas will be maintained throughout the works. The potential impacts from the construction traffic are therefore associated with the wider movement of lorries from the quarries to the site. In order to reduce the carbon footprint of the scheme, local sources of material will be used and quarries within a 20 mile radius of Whittlesey will be used. There is already a high number of lorry movements from the quarries which will be used for the sourcing of the required material. This lorry movement meets a specific quota set on the company. It is proposed that this quota will be ‘transferred’ to the scheme. Therefore the lorry movements required for the transfer of materials to site will not represent a significant change from the current conditions. However, the increase in vehicles on the local roads and the need to turn into the smaller access routes could cause delays to local road users and also poses a health and safety issue. Right turns will be required to access the smaller routes on to the SBB and these are likely to result in traffic backing up. Whittlesey Washes South Barrier Bank Works Environmental Statement 94 The sensitivity of the local road network is considered to be medium due to the local importance of the road network. Whilst the impact is temporary it will exist for the duration of the works (approximately four months of each year of construction), although there will not be any transportation of materials outside of the July to November working window. Best practice measures such as road cleaning will be put in place to ensure that the conditions of the roads are not affected during the construction phase of the scheme. However, as the existing road network is of local usage and the movement of material does not represent a significant change to the existing conditions the magnitude of the impact is considered to be medium. As a result a moderate adverse impact is anticipated. Mitigation, Management and Monitoring Mitigation Liaise with CCC’s Highways team regarding the proposed lorry movements. Implementation of traffic control measures (e.g. traffic lights or reduction in speed limit along haulage routes). Produce a Traffic Management Plan which details the proposed lorry movements to site each day and the management of this activity on the B1040, A47 and A605 for each year of construction. Consult with (at least 1 month in advance of works starting) landowners, adjacent businesses and residents along the 4 proposed access routes so that they are fully aware of the proposed works to the routes, the duration of the works and the impact that lorry movements will have. The plan will seek to avoid heavy use of existing minor roads by using separate haul roads if possible or less used roads. Management Assign banksmen in combination with access warning signs to ensure safe access and egress of construction vehicles from all proposed entrances and exits. Notices to be placed along the main transport routes informing local residents of the proposed works. Residual impact Whilst implementation of the mitigation measures will help to manage the impacts on the local road network, it is not considered significant enough to fully reduce the impact and therefore a minor adverse residual impact on the local transport network will be anticipated. 9.4 Impacts during Operation 9.4.1 Permanent disturbance to local road network Once the scheme is complete, it is considered that there will be no discernible changes to the traffic flows compared to baseline conditions. As a result operational impacts on traffic will be negligible. 9.5 Impact Summary Table 9.2 below outlines the identified traffic and transport impacts (those above negligible) before and after mitigation during construction for all three or four years of the construction programme. Whittlesey Washes South Barrier Bank Works Environmental Statement 95 Table 9.2 Summary of traffic and transport impacts Description of Impact before Key Mitigation, Impact Mitigation Monitoring Management and Residual Impact Construction Disturbance to local road network from construction traffic Moderate adverse Liaise with Cambridgeshire County Council’s Highways team regarding the proposed lorry movements. Implementation of traffic control measures (e.g. traffic lights or reduction in speed limit along haulage routes). Produce a Traffic Management Plan which details the proposed lorry movements to site each day and the management of this activity on the B1040, A47 and A605 for each year of construction. Consult with (at least 1 month in advance of works starting) landowners, adjacent businesses and residents along the 4 proposed access routes so that they are fully aware of the proposed works to the routes, the duration of the works and the impact that lorry movements will have. The plan will seek to avoid heavy use of existing minor roads by using separate haul roads if possible or less used roads. Assign banksmen in combination with access warning signs to ensure safe access and egress of construction vehicles from all proposed entrances and exits. Notices to be placed along the main transport routes informing local residents of the proposed works. Minor adverse Whittlesey Washes South Barrier Bank Works Environmental Statement 96 10 CUMULATIVE EFFECTS This section details the potential interactions and in-combination effects which could arise from this scheme with other projects in the area, and also between the different elements of the scheme on the receptors which have been identified in Chapter 5 - 9 of this ES. Maintenance activities are proposed for the wider Nene Wash area in order to maintain the condition of the River Nene and Morton’s Leam watercourses. These annual activities include desilting, vegetation clearance and localised bank repairs. These works have been designed and programmed to minimise impacts to the Nene Washes designated site and its interest features, including the breeding and overwintering bird species. Therefore cumulative effects on flora and fauna receptors are unlikely to arise as a result of these maintenance activities and the works to the SBB. Given the localised nature of the maintenance works, no other receptors are likely to be affected by cumulative effects from the two schemes. A search of planning applications from Peterborough City Council and Fenland District Council websites has not identified any other significant developments in the vicinity of the SBB that have been granted consent. There is the potential for the scheme to have cumulative effects on local residents who use the road network for travel and also the SBB for recreation. Disruption to recreation will be limited to the area of works and is therefore unlikely to cause a cumulative effect on local residents each year of the three or four year of construction. For any given year there is the potential that both transport and recreation will be disturbed for approximately four months (July to October). However, it is considered that these two impacts are also exclusive of each other, in that a person using the SBB for recreation purposes will not be using the local road network at the same time. Therefore the impact as a result of these impacts remains at minor adverse. No further significant cumulative effects are anticipated during the construction of the SBB. During its operation, regular management and maintenance activities will be undertaken similar to those which are already undertaken and therefore no operational cumulative effects are predicted. Whittlesey Washes South Barrier Bank Works Environmental Statement 97 11 CONCLUSION Whilst leading to some temporary negative impacts during construction the scheme will provide benefits in the medium to long term. The proposed works will maintain the condition of the SBB providing flood protection to Whittlesey, Stanground and other small settlements to the south of the bank. The key significant impacts predicted through the EIA, and presented in the ES (Chapters 5 to 9), are set out below. During construction, impacts (upon implementation of mitigation measures) are expected to be: Temporary disturbance to land use in the surrounding arable land from access routes during all years of construction; Temporary disturbance to recreation during all years of construction; Temporary disturbance to residents in proximity to the area of works and the access routes through a combination of increased noise levels and the visual impacts of the works; Potential impacts on buried archaeology during Year 2 works; and Temporary impacts to the setting of a scheduled monument and listed building during Year 1 works; and Temporary disruption to local road network during all years of construction. During operation, the scheme is expected to have the following impacts: Improvements for reptile species from the creation of hibernacula on surrounding land; Improvements for great crested newts from the creation of hibernacula in the Hanson’s Brick Pits site; and Improvements to the biodiversity in the Counter Drain as a result of enhancement measures. Measures which have been identified through the EIA process, and which will be delivered as mitigation for the impacts above include: Timely and effective on-going information to the local residents and users of the area, ahead, during and post construction works. Pre-construction condition surveys of local houses to provide a baseline; The contractor will work with tenants and owners to ensure their continued access during the works; Liaison with Cambridgeshire County Councils Highways team regarding the proposed lorry movements; Production of a Traffic Management Plan in order to manage impacts to the local road network; Best practice ecological guidance will be adhered to in relation to animal species protected by legislation, including the avoidance of site clearance works during the bird breeding season (March to August inclusive); Presentation of a toolbox talk on the key environmental issues including information on protected species to construction staff; A suitably qualified ecologist to undertake a day time inspection of the railway bridge prior to works commencing; A watching brief will be conducted during topsoil strip along the Fen Causeway to identify and record any archaeological deposits; Whittlesey Washes South Barrier Bank Works Environmental Statement 98 Pre-construction field surveys comprising trial trenching and a watching brief on geotechnical works will be conducted near Stanground to help identify the existence of areas of archaeological potential which can be used to aid in the project design; and Production of a Written Scheme of Investigation in consultation with the Environment Agency archaeologist and agreed with the archaeological advisors from Cambridgeshire County Council and from Peterborough Council. Once mitigation measures have been implemented, the scheme is expected to result in temporary construction impacts of negligible to minor adverse significance. The only exception is the temporary impacts on designated assets (a scheduled monument and listed building). These impacts arise from noise and visual impacts and are only related to the construction phase of the works. However, mitigation measures are not possible and therefore a moderate/minor adverse significance remains. Once the works are complete the impact on these assets will be removed. There are also enhancement measures proposed for the Counter Drain to improve its ecological and visual value. These enhancement measures include reprofiling of the Counter Drain to create shallow areas along its edge and the creation of a bank for kingfishers. An area of fenland in the western section of the works, near the Hanson’s Brick Pits, is also proposed. These enhancement measures will be developed through consultation with Natural England and RSPB. In addition, interpretation boards will be erected at key access sites on to the SBB, informing users of the area of the ecological, historical and landscape features in the area as well as the importance of the SBB. Overall, the scheme will provide flood protection to the community and assets of Whittlesey and Peterborough, which will be felt across a much wider area. The scheme has been designed to minimise or avoid adverse impacts, such that the benefits considerably outweigh the adverse aspects of the scheme. Over and above the provision of flood protection, there will be local enhancements to the biodiversity value and landscape of the area. Whittlesey Washes South Barrier Bank Works Environmental Statement 99 12 REFERENCES Atkins (2010) Whittlesey Washes Probable Maximum Flood Stage 1 Reservoir Strategy A History of the County of Huntingdon (1936) Volume 3: 'The Middle Level of the Fens and its reclamation', pp. 249-290. URL: http://www.britishhistory.ac.uk/report.aspx?compid=66187&strquery=leam Date accessed: 26 February 2013 Bat Conservation Trust (BCT) (2012) Bat Surveys Good Practice Guidelines Bailey.G and Macaulay.S (2005) Medieval Field Systems at Sir Harry Smith Community College, Whittlesey, Cambridgeshire Cambridgeshire County Council (1991). Cambridgeshire Landscape Guidelines Department for Communities and Local Government (2012) National Planning Policy Framework Department for Culture Media and Sport (2010) Planning Policy Statement 5: Planning for the Historic Environment English Heritage (2008) Conservation Principles, Policies and Guidance for the Sustainable Management of the Historic Environment English Nature (2001) Great Crested Newt Mitigation Guidelines Environment Agency (2009) Anglian River Basin Management Plan Environment Agency (2010) Assessing New Modifications: NEAS Guidance Fletcher. T (2004) Medieval features at Manor View, Whittlesey, Cambridgeshire: An Archaeological Evaluation. Fulbourn: CAM ARC, AFU Report No. 718 Halcrow (2007) Whittlesey Washes Flood Study Hall.D (1987) The Fenland Project No. 2: Cambridgeshire Survey, Peterborough to March. East Anglian Archaeology No. 35 Institution of Civil Engineers (1996) Floods and Reservoir Safety 3rd Edition Institute of Ecology and Environmental Management (2006) Guidelines for Ecological Impact Assessment in the United Kingdom Institute of Environmental Assessment (1995) Guidelines for Baseline Ecological Assessment Knight. M (2000) Whittlesey Pits - The Bradley Fen Site. An archaeological evaluation. Phase I. Unpublished Report Natural England (2007) European Protected Species Guidance Note Whittlesey Washes South Barrier Bank Works Environmental Statement 100 Oxford Archaeology East (2011) Archaeological monitoring and recording of geotechnical test pits in Whittlesey Washes Peterborough City Council (2007) Peterborough Landscape Character Assessment Smith, D.M. et al. (2010) Holocene drainage systems of the English Fenland: roddons and their environmental significance. Proceedings of the Geologists’ Association 121,256-269 Whittlesey Washes South Barrier Bank Works Environmental Statement 101 13 GLOSSARY AND ABBREVIATIONS Glossary A Acidification The term is used to describe the loss of nutrient bases (calcium, magnesium and potassium) through the process of leaching and their replacement by acidic elements (hydrogen and aluminium). Anthropogenic Are causes or effects produced by human activity. Aquifer A body of permeable material (e.g. rock, gravel or sand) containing significant amounts of groundwater. Arisings Waste generated within a defined locality over a given period of time. B Baseline Studies or Survey Collection of information about the environment which is likely to be affected by the project. Berm A level space, shelf, or raised barrier separating two areas and can also be used to control erosion and sedimentation by reducing the rate of surface run-off. Biodiversity Action Plan (BAP) Strategies to conserve, protect and enhance biodiversity. The UKBAP sets out a national strategy for the conservation of biodiversity, and local BAPS (LBAPS) have also been produced to address biodiversity issues specific to particular areas in the UK. Buffer strip An area of land maintained in permanent vegetation that helps to control air, soil and water quality. Bypass Channels A channel built to divert water from a primary channel (main river). C Catchment Flood Management Plan These documents give an overview of the flood risk across each river catchment. They recommend ways of managing those risks now and over the next 50-100 years. Conservation Area A tract of land that has been awarded protected status because of its special architectural or historic interest, "the character or appearance of which it is desirable to preserve or enhance," as required by the Planning (Listed Buildings and Conservation Areas) Act 1990 (Section 69 and 70). Culvert A device used to channel water, typically beneath a road, railway or embankment. D Dredging Process of gathering bottom sediments and disposing them at different locations. Usually done partly underwater, in shallow seas or in freshwater areas. E Environmental Action Plan (EAP) A subsection of the ES / ER which defines the environmental activities, targets and objectives that are required to be followed through subsequent stages of the design and implementation. This may also be used as a stand-alone document during implementation stages. Environmental Impact Assessment (EIA) EIA applied at the project level is a process intended to ensure that environmental impacts of schemes are identified prior to the work being carried out so that proposals can be modified or managed in Whittlesey Washes South Barrier Bank Works Environmental Statement 102 Glossary such a way that adverse impacts are avoided or minimised and the positive impacts maximised. The extent of the likely significance of environmental impacts is assessed, as far as it can be determined from an early stage, using three categories of significance (1) major, (2) moderate and (3) minor. Environmental Impact Assessment Regulations This is used in the Guidance to refer to the Regulations by which EIA has been adopted in the UK. For Agency projects this is principally the Environmental Impact Assessment (Land Drainage Improvement) Regulations SI 1999/1783 and the Town and Country Planning (Environmental Impact Assessment) Regulations SI 1999/293. Environmental Statement (ES) The document produced to assess and describe the environmental impacts of a project subject to EIA under the EIA Regulations (q.v.). The ES is a consultation document and sets out mitigation and enhancement measures for the project. F Fauna Animal life. Flora Plant life. Fluvial The processes associated with rivers and streams and the deposits and landforms created by them. Flood Storage Reservoir (FSR) Area where water is temporarily stored within the river channel. G Geomorphology Pertaining to landforms, their structure, origin and development. Geotechnical The application of the science of soil mechanics, rock mechanics, engineering geology and other related disciplines to engineering and environmental projects. Groundwater Water occurring below ground, occupying openings, cavities and spaces in rocks. Groundwater Source Protection Zones Mapped zones around groundwater sources (wells, boreholes, and springs used for public drinking water supplies) which show the risk of contamination from any activities that might cause pollution in the area. The closer the activity, the greater the risk. The maps show three main zones (inner, outer and total catchment) and a fourth zone of special interest, which we occasionally apply, to a groundwater source. H Holt Resting or breeding site of an otter, usually located underground in the roots of bankside trees, piles of logs, caves in rock falls or drains. Hydraulic The analysis of water movement, for example calculating flood water levels. Hydrogeology The science of water within the ground. Hydrology The calculation of flow rate and volume within the catchment. I Impoundment Process by which water is held back by a structure or barrier. Flow is held up or prevented. Indirect effects Effects on the environment, which are nor a direct result of the Whittlesey Washes South Barrier Bank Works Environmental Statement 103 Glossary development but are often produced away from it or as a result of a complex pathway. Sometimes referred to as secondary impacts. Invasive species Non-native plants or animals that adversely affect the habitats or bioregions they invade. L Landscape character Means the distinct and recognisable pattern of elements that occur consistently in a particular type of landscape, and how these are perceived by people. It reflects particular combinations of geology, landform, soils, vegetation, land use and human settlement. It creates the particular sense of place of different areas of the landscape. Landscape character type A landscape type will have broadly similar patterns of geology, landform, soils, vegetation, land use, settlement and field pattern discernible in maps and field survey records. Local Development Framework (LDF) This is the spatial planning strategy introduced in England by the Planning and Compulsory Purchase Act 2004. replaces the previous system of county level Structure district level Local Plans, and Unitary Development Plans authorities. and Wales The LDF Plans and for Unitary M Macrophyte An aquatic plant that grows in or near water and is either emergent, submergent, or floating. Made ground Solid ground made from artificial sources such as brick, rubble, concrete or aggregates. Magnitude A combination of the scale, extent and duration of an effect. Mitigation Steps that may be taken to minimise, eliminate or compensate the adverse effects of a development. N National Planning Policy Framework Contains all UK government planning policy and guidance to be considered during all planning applications. O Overtopping To extend or rise over or beyond the top of. P Penstocks A sluice or gate that controls the water flow, or an enclosed pipe that delivers water to hydraulic turbines and sewerage systems. Piling A type of foundation that is driven into the ground. Planning Policy Statements Are UK government statements of national policy and principles towards certain aspects of the town planning framework. R Receptor Physical landscape resource, special interest or viewer group that will experience an effect. Residual impact The level of significance assigned to an impact following the successful implementation of the stated mitigation measures, good construction or operational practice, is referred to as the residual impact. Whittlesey Washes South Barrier Bank Works Environmental Statement 104 Glossary Riparian vegetation Relating to or situated on the bank of a river or stream. River Basin Management Plan (RBMP) RBMPS are a requirement of the Water Framework Directive and a means of achieving the protection, improvement and sustainable use of the water environment across Europe. S Scoping The process of explaining the nature and likely impacts of a project, identifying stakeholders and defining how the EIA process will be carried out. Screening The process of deciding which developments require an EIA to be carried out and at what level of detail. Sedimentation The act or process of depositing or forming a sediment. Sluice A water channel controlled at its head by a gate. Strategic Environmental Assessment (SEA) EIA applied at the programme, plan or policy level (i.e. earlier in the decision making process than project level EIA). Strategic Flood Risk Assessment (SFRA) The SFRA process is essentially an assessment of flood risk issues at a strategic scale undertaken to inform the spatial planning process at a local scale and forms part of the LDF evidence base. T Topography The topography of an area means the surface shape and features. Topsoil Is the fertile upper layer of soil, usually 2 to 8 inches in depth. Tributary A stream or river which feeds into a larger one. V Visual amenity The value of a particular area or view in terms of what is seen. Visual effect Change in the appearance of the landscape as a result of development. This can be positive (i.e. beneficial or an improvement) or negative (i.e. adverse or a detraction). Whittlesey Washes South Barrier Bank Works Environmental Statement 105 Abbreviation A AOD Above Ordnance Datum B BAP Biodiversity Action Plan BCNP WT Bedfordshire, Cambridgeshire, Northamptonshire and Peterborough Wildlife Trust BCT Bat Conservation Trust C CCC Cambridgeshire County Council CDM Construction Design and Management CFMP Catchment Flood Management Plan CIEEM Chartered Institute of Ecology and Environmental Management CPERC Cambridgeshire and Peterborough Environmental Records Centre CRoW Countryside Rights of Way CWS County Wildlife Site D DCLG Department for Communities and Local Government Defra Department for Environment, Food and Rural Affairs E EAP Environmental Action Plan EcIA Ecological Impact Assessment EEC European Economic Community EH English Heritage EIA Environmental Impact Assessment ES Environmental Statement EU European Union F FDC Fenland District Council FSR Flood Storage Reservoir H Ha Hectare HER Historic Environment Record HGV Heavy Goods Vehicle Whittlesey Washes South Barrier Bank Works Environmental Statement 106 Abbreviation HRA Habitats Regulations Assessment I ICE Institute of Civil Engineers IDB Internal Drainage Board IEEM Institute of Ecology and Environmental Management IEMA Institute of Environmental Management and Assessment J JNCC Joint Nature Conservation Committee L LBAP Local Biodiversity Action Plan LCA Landscape Character Assessment LNR Local Nature Reserve LVA Landscape and Visual Appraisal M MAGIC Multi-Agency Geographical Information for the Countryside MIOS Matters in the Interest Of Safety MLC Middle Level Commissioners N NE Natural England NEAS National Environmental Assessment Service NERC The Natural Environment and Rural Communities Act NFU National Farmers’ Union NGR National Grid Reference NLDIDB North Level District Internal Drainage Board NNR National Nature Reserves NPPF National Planning Policy Framework NTS Non-Technical Summary NVC National Vegetation Classification O OS Ordnance Survey P PCC Peterborough City Council PMoW Precautionary Method of Working Whittlesey Washes South Barrier Bank Works Environmental Statement 107 Abbreviation PPG Planning Policy Guidance PPG Pollution Prevention Guidelines PPS Planning Policy Statement PRoW Public Right of Way R RBMP River Basin Management Plan RFCC Regional Flood and Coastal Committee RSPB Royal Society for the Protection of Birds S SAC Special Area of Conservation SBB South Barrier Bank SPA Special Protection Area SSSI Site of Special Scientific Interest W WFD Water Framework Directive WSI Written Scheme of Investigation Whittlesey Washes South Barrier Bank Works Environmental Statement 108