Town of Harwinton Ambulance Facility Bid Package
Transcription
Town of Harwinton Ambulance Facility Bid Package
Town of Harwinton Ambulance Facility Bid Package 166 Burlington Road Town of Harwinton 100 Bentley Drive Harwinton, CT 06791 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00010 TABLE OF CONTENTS Section Title SERIES 0 DOCUMENTS MISCELLANEOUS DOCUMENTS 00010 Table of Contents 00030 Drawing List 00050 Subsurface Investigation Report 00060 Wage Scale Provisions 00070 Radio Antenna Foundation Specifications * BIDDING REQUIREMENTS 00105 Invitation to Bid 00200 Instructions to Bidders - AIA 00300 Information Available to Bidders 00311 Contractor’s Qualification Statement 00411 Bid Form - Stipulated Price 00412 Compliance with laws, regulations, rules and executive orders 00413 Non-Collusion Affidavit 00414 Corporate Resolution CONTRACTING REQUIREMENTS 00501 Agreement - AIA 00701 General Conditions - AIA 00811 Supplementary Conditions - AIA 00910 Addenda [To follow as required] DIVISION 1 - GENERAL REQUIREMENTS 01100 01200 01300 01330 01400 01410 01500 01501 01600 01700 Summary Price and Payment Procedures Administrative Requirements Submittal Procedures Quality Requirements Special Inspection and Structural Testing Temporary Facilities and Controls Project Signage Specifications Product Requirements Execution Requirements END OF SECTION Table of Contents 00010 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00030 DRAWING LIST 1.1 SUMMARY A. Document Includes: SITE: PROJECT SITE PLAN EROSION CONTROL AND DRIVEWAY DETAIL SITE PLAN FOR GROUNDWATER TESTING WELL LOCATIONS SITE SURVEY ARCHITECTURAL: A1.1 A1.2 A1.3 A1.4 A2.1 A2.2 A3.1 A3.2 A3.3 A3.4 A4.1 A4.2 A4.3 A5.1 A6.1 A6.2 A7.1 A7.2 FOUNDATION PLAN FLOOR PLAN REFLECTED CEILING PLAN ROOF PLAN EXTERIOR ELEVATIONS EXTERIOR ELEVATIONS BUILDING SECTIONS BUILDING SECTIONS WALL SECTIONS WALL SECTIONS MISC. DETAILS ACCESSIBILITY STANDARDS STRUCTURAL NOTES AND FOUNDATION DETAILS TOILET ROOM PLANS & ELEVATIONS DOOR SCHEDULE WINDOW & FINISH SCHEDULES ARCHITECTURAL OUTLINE SPECIFICATIONS ARCHITECTURAL OUTLINE SPECIFICATIONS MECHANICAL M1.1 M1.1 ALT M2.1 M4.1 HVAC FLOOR PLAN HVAC FLOOR PLAN HVAC DETAIL HVAC SPECIFICATIONS ELECTRICAL: E1.1 E2.1 E3.1 E4.1 ELECTRICAL LIGHTING PLAN ELECTRICAL POWER PLAN ELECTRICAL DETAILS ELECTRICAL RISER General Conditions - AIA 0701 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 E5.1 ELECTRICAL DETAILS E6.1 ELECTRICAL SPECIFICATIONS E6.2 ELECTRICAL SPECIFICATIONS PLUMBING: P1.1 P2.1 P3.1 P3.2 P4.1 PLUMBING PLANS PLUMBING DETAILS PLUMBING SCHEDULE PLUMBING SCHEDULE & NOTES PLUMBING SPECIFICATIONS FIRE PROTECTION: FP1.1 FP2.1 FP3.1 FIRE PROTECTION PLAN FIRE PROTECTION DETAILS FIRE PROTECTION SPECIFICATIONS END OF DOCUMENT General Conditions - AIA 0701 - 2 Appendix D Compaction Testing Report Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00060 WAGE SCALE PROVISIONS All laborers, mechanics, and workmen employed upon the work covered by this Contract shall be paid at wage rates not less than those required by all applicable provisions of the General Statutes of the State of Connecticut and other local ordinances, regardless of any contractual relationship which may be alleged to exist between the Contractor or any subcontractor and such laborers, mechanics or workers For the Contractor’s convenience and reference on those contracts where they may be applicable by State law or local ordinance, the schedule of minimum wage rates as determined by the State of Connecticut Labor Commissioner may have been included on the following pages and, if so are made a part hereof. For those projects where the minimum State wage rates need not be paid, these rates may be ignored; however, it remains the Contractor’s responsibility to determine if the minimum State wage rates should be applied when preparing their bid. The Contractor shall check with the State Labor Commission for the most recent wage rates before preparing and submitting their bid. SUMMARY OF CONNECTICUT'S PREVAILING WAGE LAW Connecticut’s prevailing wage law is codified in Connecticut General Statutes Section Section 31-53 and 31-53a. The law applies to each contract for the construction, remodeling, refinishing, refurbishing, rehabilitation, alteration or repair of any public works project by the State or its agents, or by any political subdivision of the State. Coverage: Conn. Gen. Stat. Section 31-53(g) provides monetary thresholds which must be met before the law is applicable. The prevailing wage law does not apply where the total cost of all work to be performed by all contractors and subcontractors in connection with new construction of a public works project is less than four hundred thousand ($400,000) dollars. The prevailing wages law does not apply in connection with remodeling, refinishing, refurbishing, rehabilitation, alteration or repair of any public works project under one hundred thousand ($100,000) dollars. Prevailing Rate: The prevailing rate consists of a base rate and a fringe benefit rate which may be paid in cash or benefits. Conn. Gen. Stat. Section 31-53(d) permits the Labor Commissioner to adopt and use the prevailing wage rate determinations as have been made by the Secretary of Labor of the United States under the provisions of the Davis-Bacon Act, as amended. The agent empowered to let such contract shall contact the Labor Commissioner at least ten, but not more than twenty days, prior to the date such Wage Scale Provisions 00060 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 contracts will be advertised for bid, to ascertain the proper prevailing rate. Under Connecticut General Statutes, 31-55a the rates will be adjusted annually on or before July 1st of each year. These new rates will be on the Department of Labor website. Certifications: Both the Contractor and the Contracting Agent must provide certifications to the Labor Commissioner. Prior to the award of any contract subject to the prevailing wage law, the contracting agent shall certify in writing to the Labor Commissioner the total dollar amount of work to be done in connection with the public works project, regardless of whether such project consists of one or more contracts. Upon the award of a contract subject to the prevailing wage law, the contractor who is awarded the contract shall also certify, under oath, to the Labor Commissioner the pay scale to be used by the contractor and any of his subcontractors for the work to be performed under the contract. Additionally, each employer subject to the prevailing wage law must file certified payrolls with the contracting agent including information, including but not limited to, employee names; occupations; hours worked; rates paid; and the employers compliance with various provisions of law. Penalties: There are various civil, criminal and administrative penalties for violations of the prevailing wage law. Failure to pay the prevailing rate is a crime which may be a felony depending upon the amount of unpaid wages. Knowingly filing a false certified payroll or failure to file a certified payroll is a Class D felony for which an employer may be fined up to five thousand dollars, imprisoned for up to five years, or both. Disregarding obligations under Conn. Gen. Stat. Section 31-53 may result in an administrative debarment which may preclude any firm, corporation, partnership or association in which such person or firms have an interest from receiving an award of a contract until a period of up to three years have elapsed. Additionally, civil penalties of $300 per violation of law may also be assessed upon the employer. Effective October 1, 2005, Public Act 05-50: Any person performing the work of any mechanic, laborer, or worker shall be paid prevailing wages ~~ All persons who perform work on site must be paid prevailing wage for the appropriate mechanic, laborer, or worker classification; All certified payrolls must list the hours worked and wages paid to all persons who perform work on site regardless of their ownership, i.e.: (Owners, corporate officers, LLC members, independent contractors, et. al); Reporting and payment of wages is required regardless of any contractual relationship alleged to exist between the contractor and such person. Wage Scale Provisions 00060 - 2 Project: Construction For A New EMS And EOC Center Minimum Rates and Classifications for Building Construction ID# : B 17945 Connecticut Department of Labor Wage and Workplace Standards Division By virtue of the authority vested in the Labor Commissioner under provisions of Section 31-53 of the General Statutes of Connecticut, as amended, the following are declared to be the prevailing rates and welfare payments and will apply only where the contract is advertised for bid within 20 days of the date on which the rates are established. Any contractor or subcontractor not obligated by agreement to pay to the welfare and pension fund shall pay this amount to each employee as part of his/her hourly wages. Project Number: State#: Project Town: Harwinton FAP#: Project: Construction For A New EMS And EOC Center CLASSIFICATION 1a) Asbestos Worker/Insulator (Includes application of insulating materials, protective coverings, coatings, & finishes to all types of mechanical systems; application of firestopping material for wall openings & penetrations in walls, floors, ceilings Hourly Rate Benefits 35.00 26.41 1b) Asbestos/Toxic Waste Removal Laborers: Asbestos removal and encapsulation (except its removal from mechanical systems which are not to be scrapped), toxic waste removers, blasters.**See Laborers Group 7** 2) Boilermaker As of: Wednesday, June 05, 2013 35.24 25.01 Project: Construction For A New EMS And EOC Center 3a) Bricklayer, Cement Mason, Concrete Finisher (including caulking), Stone Masons 32.50 26.21 + a 3b) Tile Setter 32.94 22.42 3c) Terrazzo Mechanics and Marble Setters 31.69 22.35 3d) Tile, Marble & Terrazzo Finishers 26.25 19.20 3e) Plasterer 32.50 26.21 ------LABORERS------ As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center 4) Group 1: Laborers (common or general), acetylene burners, carpenter tenders, concrete specialists, wrecking laborers, fire watchers. 26.40 17.15 4a) Group 2: Mortar mixers, plaster tender, power buggy operators, powdermen, fireproofer/mixer/nozzleman, fence erector. 26.65 17.15 4b) Group 3: Jackhammer Operators/Pavement Breaker, mason tender (brick) and mason tender (cement/concrete) 26.90 17.15 4c) **Group 4: Pipelayers (Installation of water, storm drainage or sewage lines outside of the building line with P6, P7 license) (the pipelayer rate shall apply only to one or two employees of the total crew who primary task is to actually perform the mating of pipe sections) P6 and P7 rate is $26.80 26.65 17.15 4d) Group 5: Air track operators, Sand blasters 27.15 17.15 4e) Group 6: Nuclear toxic waste removers, blasters 29.40 17.15 As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center 4f) Group 7: Asbestos/lead removal and encapsulation (except it's removal from mechanical systems which are not to be scrapped) 27.40 17.15 4g) Group 8: Bottom men on open air caisson, cylindrical work and boring crew 26.90 17.15 4h) Group 9: Top men on open air caisson, cylindrical work and boring crew 26.40 17.15 4i) Group 10: Traffic Control Signalman 16.00 17.15 5) Carpenter, Acoustical Ceiling Installation, Soft Floor/Carpet Laying, Metal Stud Installation, Form Work and Scaffold Building, Drywall Hanging, Modular-Furniture Systems Installers, Lathers, Piledrivers, Resilient Floor Layers. 29.65 21.00 5a) Millwrights 30.15 21.39 As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center 6) Electrical Worker (including low voltage wiring) (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2 V-1,2,7,8,9) 35.90 22.99 7a) Elevator Mechanic (Trade License required: R-1,2,5,6) 46.41 25.185+a+b Groundman 24.99 6.5% + 9.75 Linemen/Cable Splicer 45.43 6.5% + 16.20 8) Glazier (Trade License required: FG-1,2) 33.78 16.90 + a -----LINE CONSTRUCTION---- As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center 9) Ironworker, Ornamental, Reinforcing, Structural, and Precast Concrete Erection 33.50 27.98 + a Group 1: Crane handling or erecting structural steel or stone, hoisting engineer 2 drums or over, front end loader (7 cubic yards or over); work boat 26 ft. and over. (Trade License Required) 36.05 21.55 + a Group 2: Cranes (100 ton rate capacity and over); Backhoe/Excavator over 2 cubic yards; Piledriver ($3.00 premium when operator controls hammer). (Trade License Required) 35.73 21.55 + a Group 3: Excavator; Backhoe/Excavator under 2 cubic yards; Cranes (under 100 ton rated capacity), Grader/Blade; Master Mechanic; Hoisting Engineer (all types of equipment where a drum and cable are used to hoist or drag material regardless of motive power of operation), Rubber Tire Excavator (Drott-1085 or similar);Grader Operator; Bulldozer Fine Grade. (slopes, shaping, laser or GPS, etc.). (Trade License Required) 34.99 21.55 + a Group 4: Trenching Machines; Lighter Derrick; Concrete Finishing Machine; CMI Machine or Similar; Koehring Loader (Skooper). 34.60 21.55 + a ----OPERATORS---- As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center Group 5: Specialty Railroad Equipment; Asphalt Paver; Asphalt Reclaiming Machine; Line Grinder; Concrete Pumps; Drills with Self Contained Power Units; Boring Machine; Post Hole Digger; Auger; Pounder; Well Digger; Milling Machine (over 24" Mandrell) 34.01 21.55 + a Group 5 continued: Side Boom; Combination Hoe and Loader; Directional Driller; Pile Testing Machine. 34.01 21.55 + a Group 6: Front End Loader (3 up to 7 cubic yards); Bulldozer (rough grade dozer). 33.70 21.55 + a Group 7: Asphalt roller, concrete saws and cutters (ride on types), vermeer concrete cutter, Stump Grinder; Scraper; Snooper; Skidder; Milling Machine (24" and under Mandrell). 33.36 21.55 + a Group 8: Mechanic, grease truck operator, hydroblaster; barrier mover; power stone spreader; welding; work boat under 26 ft.; transfer machine. 32.96 21.55 + a Group 9: Front end loader (under 3 cubic yards), skid steer loader regardless of attachments, (Bobcat or Similar): forklift, power chipper; landscape equipment (including Hydroseeder). 32.53 21.55 + a As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center Group 10: Vibratory hammer; ice machine; diesel and air, hammer, etc. 30.49 21.55 + a Group 11: Conveyor, earth roller, power pavement breaker (whiphammer), robot demolition equipment. 30.49 21.55 + a Group 12: Wellpoint operator. 30.43 21.55 + a Group 13: Compressor battery operator. 29.85 21.55 + a Group 14: Elevator operator; tow motor operator (solid tire no rough terrain). 28.71 21.55 + a Group 15: Generator Operator; Compressor Operator; Pump Operator; Welding Machine Operator; Heater Operator. 28.30 21.55 + a As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center Group 16: Maintenance Engineer/Oiler. 27.65 21.55 + a Group 17: Portable asphalt plant operator; portable crusher plant operator; portable concrete plant operator. 31.96 21.55 + a Group 18: Power safety boat; vacuum truck; zim mixer; sweeper; (Minimum for any job requiring a CDL license). 29.54 21.55 + a 10a) Brush and Roller 30.22 16.90 10b) Taping Only/Drywall Finishing 30.97 16.90 ------PAINTERS (Including Drywall Finishing)------ As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center 10c) Paperhanger and Red Label 30.72 16.90 10e) Blast and Spray 33.22 16.90 11) Plumber (excluding HVAC pipe installation) (Trade License required: P-1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 38.67 25.56 12) Well Digger, Pile Testing Machine 33.01 19.40 + a 13) Roofer (composition) 31.70 17.36 14) Roofer (slate & tile) 32.20 17.36 As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center 15) Sheetmetal Worker (Trade License required for HVAC and Ductwork: SM-1,SM-2,SM-3,SM-4,SM-5,SM-6) 41.81 31.85 16) Pipefitter (Including HVAC work) (Trade License required: S-1,2,3,4,5,6,7,8 B-1,2,3,4 D-1,2,3,4, G-1, G-2, G-8 & G-9) 38.67 25.56 17a) 2 Axle 27.88 18.27 + a 17b) 3 Axle, 2 Axle Ready Mix 27.98 18.27 + a 17c) 3 Axle Ready Mix 28.03 18.27 + a ------TRUCK DRIVERS------ As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center 17d) 4 Axle, Heavy Duty Trailer up to 40 tons 28.08 18.27 + a 17e) 4 Axle Ready Mix 28.13 18.27 + a 17f) Heavy Duty Trailer (40 Tons and Over) 28.33 18.27 + a 17g) Specialized Earth Moving Equipment (Other Than Conventional Type on-the-Road Trucks and Semi-Trailers, Including Euclids) 28.13 18.27 + a 18) Sprinkler Fitter (Trade License required: F-1,2,3,4) 38.98 19.87 + a 19) Theatrical Stage Journeyman 22.22 6.53 As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center Welders: Rate for craft to which welding is incidental. *Note: Hazardous waste removal work receives additional $1.25 per hour for truck drivers. **Note: Hazardous waste premium $3.00 per hour over classified rate Crane with 150 ft. boom (including jib) - $1.50 extra Crane with 200 ft. boom (including jib) - $2.50 extra Crane with 250 ft. boom (including jib) - $5.00 extra Crane with 300 ft. boom (including jib) - $7.00 extra Crane with 400 ft. boom (including jib) - $10.00 extra All classifications that indicate a percentage of the fringe benefits must be calculated at the percentage rate times the "base hourly rate". Apprentices duly registered under the Commissioner of Labor's regulations on "Work Training Standards for Apprenticeship and Training Programs" Section 31-51-d-1 to 12, are allowed to be paid the appropriate percentage of the prevailing journeymen hourly base and the full fringe benefit rate, providing the work site ratio shall not be less than one full-time journeyperson instructing and supervising the work of each apprentice in a specific trade. The Prevailing wage rates applicable to this project are subject to annual adjustments each July 1st for the duration of the project. Each contractor shall pay the annual adjusted prevailing wage rate that is in effect each July 1st, as posted by the Department of Labor. It is the contractor's responsibility to obtain the annual adjusted prevailing wage rate increases directly from the Department of Labor's website. The annual adjustments will be posted on the Department of Labor's Web page: www.ct.gov/dol The Department of Labor will continue to issue the initial prevailing wage rate schedule to the Contracting Agency for the project. All subsequent annual adjustments will be posted on our Web Site for contractor access. As of: Wednesday, June 05, 2013 Project: Construction For A New EMS And EOC Center Effective October 1, 2005 - Public Act 05-50: any person performing the work of any mechanic, laborer, or worker shall be paid prevailing wage All Person who perform work ON SITE must be paid prevailing wage for the appropriate mechanic, laborer, or worker classification. All certified payrolls must list the hours worked and wages paid to All Persons who perform work ON SITE regardless of their ownership i.e.: (Owners, Corporate Officers, LLC Members, Independent Contractors, et. al) Reporting and payment of wages is required regardless of any contractual relationship alleged to exist between the contractor and such person. ~~Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clause (29 CFR 5.5 (a) (1) (ii)). Please direct any questions which you may have pertaining to classification of work and payment of prevailing wages to the Wage and Workplace Standards Division, telephone (860)263-6790. As of: Wednesday, June 05, 2013 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00105 INVITATION TO BID Project: Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 Owner: Town of Harwinton 100 Bentley Drive Harwinton, CT 06791 Architect/Engineer: Architectural Studio 3C, LLC 200 Clearview Avenue Harwinton, CT 06791 Date: 2013 (Name of Bidders to whom this letter is addressed) Your firm is invited to submit a Bid under seal to the Owner for construction of a new Ambulance Facility for Harwinton Ambulance Association to be located at 166 Burlington Road. The Owner will receive Bids until 12:00 PM local time on the Seventeenth day of July, 2013 for the following project: Description: A 4,799 square foot, one story wood framed new Ambulance Facility with associated site improvements. This is a municipal public works project, subject to the prevailing wage rate requirements of C.G.S. Section 31-53 and the performance and payment bond requirements of C.G.S. Section 49-41. Bidding Documents for a Stipulated Sum contract may be purchased from the office of Advanced Reprographics located at 50 Corporate Ave, Plainville, CT 06062, telephone (860) 410-1020 for the cost of reproduction. Bid Documents will be made available on June 24th 2013 please call to confirm availability sets are prior to pick up. A. Bidding Documents may be obtained, at cost of reproduction from Advanced Reprographics located at 50 Corporate Ave, Plainville, CT 06062, telephone (860) 410-1020 during regular business hours. Bidders will be required to provide Bid security in the form of a Bid Bond of a sum no less than 10 percent of the Bid Sum negotiable security. Invitation to Bid 00105 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 Refer to other bidding requirements described in Document 00201 - Instructions to Bidders AIA and Document 00300 - Information Available to Bidders. Submit your Bid on the Bid Form provided. Bidders are required to complete Bid Form. Bidders may supplement this form as appropriate. Your Bid will be required to be submitted under a condition of irrevocability for a period of 90 days after submission. The Owner reserves the right to reject any and all bids or portions thereof, to decline to make an award, to waive any and all informalities and/or defects in the bid documents, to negotiate directly with any bidder if it is in the Owner’s best interested to do so, and to disregard all nonconforming, non-responsive, conditional bids, and bids taking exceptions to the bid documents. The Owner reserves the right to determine the “lowest responsible bidder” based on any number and combination of specified bid items deemed to be in the best interest of the Owner. Sincerely, Michael R. Criss First Selectman Town of Harwinton END OF DOCUMENT Invitation to Bid 00105 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00200 INSTRUCTIONS TO BIDDERS 1.1 SUMMARY A. Document Includes: 1. Intent. 2. Work identified in contract documents. 3. Contract Time. 4. Definitions. 5. Contract Documents identification. 6. Availability of documents. 7. Examination of documents. 8. Inquiries and Addenda. 9. Product substitutions. 10. Site examination. 11. Prebid conference. 12. Bidder qualifications. 13. Submission procedure. 14. Bid ineligibility. 15. Security deposit. 16. Performance Assurance. 17. Bid Form requirements. 18. Fees for changes in the Work. 19. Bid Form signature. 20. Selection and award of alternates. 21. Bid opening. 22. Duration of offer. 23. Acceptance of offer. B. Related Documents: 1. Document 00105 - Invitation to Bid. 2. Document 00300 - Information Available To Bidders. 3. Document 00411 - Bid Form - Stipulated Price 4. Document 00412 – Compliance with laws, regulations, rules and executive orders 5. Document 00413 - Non-Collusion Affidavit 6. Document 00811 - Supplementary Conditions - AIA a. Definitions. b. Contract Time identification. c. Tax rebate procedures. d. Tax exempt procedures. e. Contractor’s fees for changes. f. Contractor’s liability insurance. g. Bond types and values. Instructions to Bidders 00200 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.2 INTENT A. 1.3 1.4 1.5 1.6 The intent of this Bid request is to obtain an offer to perform work to complete a new Ambulance Facility to be located at 166 Burlington Road, Harwinton, Connecticut 06791 for a Stipulated Sum contract, in accordance with Contract Documents. WORK IDENTIFIED IN CONTRACT DOCUMENTS A. Work of this proposed Contract comprises general construction, site development, including structural, mechanical, electrical, plumbing, and fire protection Work. B. Site Location: 166 Burlington Road, Harwinton, Connecticut 06791. CONTRACT TIME A. Identify Contract Time in the Bid Form. The completion date in the Agreement shall be the Contract Time added to the commencement date. B. The Owner requires the work of this contract be completed as quickly as possible. Consideration will be given to time of completion when reviewing submitted Bids. DEFINITIONS A. Bidding Documents: Contract Documents supplemented with Invitation to Bid, Instructions to Bidders, Information Available to Bidders, Bid Form, Bid Form Supplements and Appendices, and bid securities, identified. B. AIA Document A201-2007 Article 1, including issued Addenda. C. Bid: Executed Bid Form and required attachments submitted in accordance with these Instructions to Bidders. D. Bid Sum: Monetary sum identified by the Bidder in the Bid Form. CONTRACT DOCUMENTS IDENTIFICATION A. The Contract Documents are identified as Project number 11002 as prepared by Architectural Studio 3C, LLC located at 200 Clearview Avenue, Harwinton, CT 06891, telephone (860) 485-9282 and identified in the Project Manual. Instructions to Bidders 00200 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.7 1.8 1.9 1.10 AVAILABILITY OF DOCUMENTS A. Bidding Documents may be obtained, at cost of reproduction from Advanced Reprographics located at 50 Corporate Ave, Plainville, CT 06062, telephone (860) 410-1020, during regular business hours. B. Bidding Documents are made available only for the purpose of obtaining offers for this Project. Their use does not grant a license for other purposes. EXAMINATION OF DOCUMENTS A. Bidding Documents may be viewed at the office of Advanced Reprographics located at 50 Corporate Ave, Plainville, CT 06062, telephone (860) 410-1020 B. Upon receipt of Bidding Documents verify documents are complete. Notify Architect/Engineer if documents are incomplete. C. Immediately notify Architect/Engineer upon finding discrepancies or omissions in Bidding Documents. INQUIRIES AND ADDENDA A. Direct questions in writing to Attn: Craig C. Chasse, AIA, LEED AP, at the office of the Architectural Studio 3C, LLC via email craig@architecturalstudio3c.com and cc chief@harwintonems.com. B. Verbal answers are not binding on any party. C. Submit questions no later than 12:00pm on July 10th, 2013. Replies will be made by Addenda. D. Addenda may be issued during bidding period. Addenda will be sent to known Bidders. Addenda become part of the Contract Documents. Include resultant costs in the Bid Sum. PRODUCT SUBSTITUTIONS A. 1.11 Requests for Product substitutions are not permitted before Notice to Proceed. Refer to Section 01600 for substitution procedures. SITE EXAMINATION A. Examine Project site before submitting a Bid. Instructions to Bidders 00200 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 B. Contact Owner at the following address and phone number to arrange date and time to visit Project site: 1. Address: Town of Harwinton 100 Bentley Drive Harwinton CT, 06791 Jason Emery – Building Committee Chair, 860-485-0544 x4 John Fredsall – Harwinton Highway Supervisor, 860-485-9051 1.12 1.13 PREBID CONFERENCE A. A Bidders conference is scheduled for June 26th at 10:00 AM at the Harwinton Town Hall – 100 Bentley Drive, Harwinton, CT 06791. B. Only prequalified General contract Bidders are invited to attend. C. Representatives of the Owner will be in attendance. D. Summarized minutes of this meeting will be circulated to known Bidders. These minutes will not form part of Contract Documents. E. Information relevant to Bidding Documents will be issued by Addendum. BIDDER QUALIFICATIONS A. 1.14 To demonstrate qualification for performing the Work of this Contract, Bidders have be requested to submit written proposals outlining project approach and proposed scope of work, detailed information on the firm’s background and experience on execution of municipal projects, key staff with resumes. Each proposal must have provided certification of insurance, proof of previous bonding capabilities. SUBMISSION PROCEDURE A. Bidders shall be solely responsible for delivery of Bids in manner and time prescribed. B. Submit two copies of executed offer on Bid Forms indicated, signed and sealed with required bid bond in a closed opaque envelope, clearly identified with Bidder’s name, Project name, contract number, and Owner's name on the outside. C. Improperly completed information, irregularities bid bond, may be cause not to open the Bid Form envelope and declare the Bid invalid or informal. Instructions to Bidders 00200 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.15 1.16 1.17 BID INELIGIBILITY A. Bids that are unsigned, improperly signed or sealed, conditional, illegible, obscure, contain arithmetical errors, erasures, alterations, or irregularities of any kind, may be declared unacceptable at Owner’s discretion. B. Bid Forms, Appendices, and enclosures which are improperly prepared may be declared unacceptable at Owner’s discretion. C. All bidders must complete, sign, and return the “CHRO Contract Compliance Regulations Notification to Bidders” form at the time of bid opening. Bids not including this form should be considered incomplete and rejected. D. Failure to provide, bonds or insurance requirements may invalidate the Bid at the discretion of the Owner. E. Bids are by invitation, only, from selected Bidders. Unsolicited Bids may be returned. SECURITY DEPOSIT A. Bids shall be accompanied by security deposit as follows: 1. Bid Bond of a sum no less than 10 percent of the Bid Sum on surety letterhead letter see standard letter format provided. B. Endorse Bid Bond in name of the Owner as oblige, signed and sealed by the principal (Contractor) and surety. C. Security deposit of accepted Bidder will be returned after delivery to the Owner of the required Performance Bonds by the accepted Bidder. D. The successful bidder shall provide a proof of payment bond to the Town of Harwinton for any subcontractors that the bidder may use. E. Include the cost of security deposit in the Bid Sum. F. After a Bid has been accepted, security deposits will be returned to the respective Bidders. G. If no contract is awarded, security deposits will be returned. PERFORMANCE ASSURANCE A. Accepted Bidder: Provide a Performance bond as described in Document 00811 Supplementary Conditions - AIA. Instructions to Bidders 00200 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 B. 1.18 1.19 1.20 BID FORM REQUIREMENTS A. Complete requested information in the Bid Form and Bid Form Supplements. B. Refer to Document 00811 - Supplementary Conditions - AIA for inclusion of taxes, procedures for tax rebate claims by the Owner and tax exempt Products. FEES FOR CHANGES IN THE WORK A. Include in the Bid Form, the overhead and profit fees on Bidder’s own Work and Work by Subcontractors, applicable for Changes in the Work, whether additions to or deductions from the Work on which the Bid Sum is based. B. Include in the Bid Form, fees proposed for subcontract work for changes (both additions and deductions) in the Work. The Contractor shall apply fees as noted, to Subcontractor's gross (net plus fee) costs on additional work. BID FORM SIGNATURE A. 1.21 Include the cost of performance assurance bonds in the Bid Sum and identify the cost when requested by the Owner. Sign Bid Form, as follows: 1. Sole Proprietorship: Signature of sole proprietor in the presence of a witness who will also sign. Insert the words "Sole Proprietor" under the signature. Affix seal. 2. Partnership: Signature of all partners in the presence of a witness who will also sign. Insert the word "Partner" under each signature. Affix seal to each signature. 3. Corporation: Signature of a duly authorized signing officer in their normal signatures. Insert the officer's capacity in which the signing officer acts, under each signature. Affix the corporate seal. If the Bid is signed by officials other than the president and secretary of the company, or the president/secretary/treasurer of the company, submit a copy of the by-law resolution of their board of directors authorizing them to do so, with the Bid Form in the bid envelope. 4. Joint Venture: Signature of each party of the joint venture under their respective seals in a manner appropriate to such party as described above, similar to requirements for Partnerships. SELECTION AND AWARD OF ALTERNATES A. Indicate variation of Bid Sum for alternates listed in Document 1200 – Price and Payment Procedures. This form requests a "difference" in Bid Sum by adding to or deducting from base Bid Sum. Instructions to Bidders 00200 - 6 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 B. 1.22 BID OPENING A. 1.23 Bids will be opened publicly immediately after time for receipt of Bids. Bidders may be present. DURATION OF OFFER A. 1.24 Bids will be evaluated on base Bid Sum. After determination of accepted Bidder, consideration will be given to alternates and Bid Sum. Bids shall remain open to acceptance and shall be irrevocable for a period of (90 days) after bid closing date. ACCEPTANCE OF OFFER A. The Owner reserves the right to reject any and all bids or portions thereof, to decline to make an award, to waive any and all informalities and/or defects in the bid documents, to negotiate directly with any bidder if it is in the Owner’s best interested to do so, and to disregard all non-conforming, non-responsive, conditional bids, and bids taking exceptions to the bid documents. The Owner reserves the right to determine the “lowest responsible bidder” based on any number and combination of specified bid items deemed to be in the best interest of the Owner. B. After acceptance by the Owner, the Architect on behalf of the Owner, will issue to the accepted Bidder, a written Notice To Proceed. C. Notwithstanding delay in the preparation and execution of the Agreement, accepted Bidder shall be prepared, upon written Notice to Proceed, to commence work within seven days following receipt of official written order of the Owner to proceed, or on date stipulated in such order. D. The accepted bidder shall assist and cooperate with the Owner to prepare the Agreement, and within 7 days following its presentation shall execute Agreement and all affidavits and return it to the Owner. Instructions to Bidders 00200 - 7 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 THESE SUPPLEMENTARY CONDITIONS supplement the instructions to Bidders Preparation of Proposal The proposal shall be made on the forms furnished herein. The blank spaces in the proposal shall be filled in correctly where indicated for each and every item for which the Contractor chooses to bid and for which a quantity is given, the prices for which they propose to do each item of the work contemplated. Ditto marks shall not be used. The bidder shall sign their proposal correctly. If the proposal is made by an individual, their name and postal address shall be shown. If made by a firm, partnership or corporation, the proposal shall be signed by an official of the firm, partnership or corporation authorized to sign the contract, and also shall show the postal address of the firm, partnership or corporation. Irregular Proposals Proposals may be rejected if they show any omissions, alterations of the form, additions not called for, conditional or alternate bids, or irregularities of any kind. Disqualification of Bidders More than one proposal for an individual, firm, partnership, corporation or association, under the same or different names, will not be considered. Reasonable ground for believing that any bidder is interested in more than one proposal for the work contemplated will cause the rejection of all proposals in which the bidder is interested. Any and all proposals in which such bidder is interested will be rejected if there is reason to believe collusion exists among the bidders, and all participants in such collusion will not be considered in future bids for the same work. PROPOSALS IN WHICH THE PRICES ARE OBVIOUSLY UNBALANCED AS DETERMINED BY THE ARCHITECT AND/OR OWNER SHALL BE REJECTED AND THE BID SHALL NOT BE CONSIDERED. Right to Reject The Owner reserves the right to reject any and all proposals or to accept any bid, should the Owner deem it to be in the best interest of the Owner. Estimate of Work The quantities shown are to be considered as approximate only. The Owner does not expressly or by implication agree that the actual quantity will correspond therewith, but reserves the right to increase or decrease the amount of any item or portion of the work as may be deemed necessary by the Architect and/or Engineer, up to 100%. Instructions to Bidders 00200 - 8 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 Familiarity with the Work Bidders are advised to carefully examine all Contract Drawings and Specifications, and to make a thorough examination of conditions at the location of the proposed work. It is the obligation of the bidder to ascertain for them self all the facts concerning conditions to be found at the location of the work. Responsibility of the Contractor Attention is particularly directed to the provisions of the Contract whereby the Contractor shall be responsible for any loss or damage that may occur to the work or any part thereof during its progress, and also whereby the Contractor shall make good any defects or faults that may occur during the progress of the work. Deposits Accompanying Bid (Bid Bond) Bid security in the form of a certified check or bid bond in the amount of 10% of the bid shall accompany each bid. The check shall be made payable to the order of the Town of Harwinton. Execution of Agreement Failure of the successful bidder to execute and deliver to the Town of Harwinton the Agreement, and to supply any required bond or insurance policies, within 10 days of receipt of written Notice of Award and presentation of such documents for signature, or within such extended period as it may grant upon reasons determined to be sufficient by the Town of Harwinton, shall constitute a default and the bidder's bond or surety shall be forfeited to the Town of Harwinton, which may either award the Contract to another bidder or re-advertise for bids. Performance and Payment Bond Requirement The successful bidder, at the time of execution of the Contract, shall deposit with the Town of Harwinton a surety company bond for the satisfactory completion of the work and the payment of debts pertaining to material or labor used or employed in the execution of the Contract (Payment Bond), in amounts equal to the amount of the Contract award. The form of the bonds and surety shall be acceptable to the Town of Harwinton. Competency of Bidders Bidders shall be experienced in the kind of work to be performed, have the necessary equipment therefore, and sufficient capital to properly execute the work within the time allowed. Bids received from bidders who have previously failed to complete contracts within the time required, or have previously performed similar work in an unsatisfactory manner, may be rejected. A bid may be rejected if the bidder cannot show that they have the necessary capital and experience, and owns, controls or can procure the necessary plant to commence the work Instructions to Bidders 00200 - 9 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 at the time prescribed, and thereafter to prosecute and complete the work at the rate or time specified, and that they are not already obligated for the performance of other work which would delay the commencement, prosecution or completion of the work. Execution of the Contract The party to whom the Contract is awarded or their authorized representative shall be required to attend a meeting at the Owner's office with the sureties offered by them, and execute the Contract that has been awarded. In case of their failure or neglect to do so, the Town of Harwinton may, at its option, determine that the bidder has abandoned the Contract, and thereupon the proposal, and acceptance of the bidder shall be null and void, and the check or bid bond accompanying the proposal shall be forfeited to the Town of Harwinton. END OF DOCUMENT Instructions to Bidders 00200 - 10 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00300 INFORMATION AVAILABLE TO BIDDERS 1.1 SUMMARY A. 1. 2. 3. Document Includes: Subsurface Investigation Report Survey Radio Tower Foundation 1. Related Documents: Document 00201 - Instructions to Bidders - AIA: Site examination. B. 1.2 1.3 1.4 SUBSURFACE INVESTIGATION REPORT A. A copy of a soil compaction reports have been included with this document. B. This report identifies properties of below grade conditions. C. This report, by its nature, cannot reveal all conditions existing on the site. Should subsurface conditions be found to vary substantially from this report, changes in design and construction of foundations will be made, with resulting credits or expenditures to Contract Price/Sum accruing to Owner. SURVEY A. A copy of a survey is included with this Document, Property survey 166 Burlington Road, October 2010, and prepared by GM2 Associates. B. This survey identifies grade elevations prepared primarily for use of Architect/Engineer in establishing new grades and identifying natural water shed. RADIO TOWER FOUNDATION A. Identifies construction details for radio tower foundation as noted on site plan. END OF DOCUMENT Information Available to Bidders 00300 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00311 CONTRACTOR’S QUALIFIATION STATEMENT - AIA 1.1 1.2 SUMMARY A. Document Includes: 1. General Conditions. B. Related Documents: 1. Document 00501 - Agreement - AIA. 2. Document 00811 - Supplementary Conditions - AIA. GENERAL CONDITIONS A. AIA Document A305, Contractor’s Qualification Statement 1.3 SUPPLEMENTARY CONDITION 1.4 SUPPLEMENTARY CONDITIONS TO THE — AIA DOCUMENT A305 - 2007 EDITION A. Add section 3.7 – List any subcontractors which may be used on this project. B. Add section 3.8 – List Contractor’s chain of command and off hours telephone numbers for this project. END OF DOCUMENT Contractor’s Statement of Qualification - AIA 00311 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00411 BID FORM - STIPULATED PRICE To: Town of Harwinton 100 Bentley Drive Harwinton, CT 06791 Project: Proposed Facility for Harwinton Ambulance, 166 Burlington Road, Harwinton CT 06791 Date: ..................... Submitted by: ................................................. (full name) (full address) ................................................. ................................................. 1. OFFER Having examined the Place of The Work and all matters referred to in the Instructions to Bidders and the Contract Documents prepared by Architectural Studio 3C, LLC. for the above mentioned project, we, the undersigned, hereby offer to enter into a Contract to perform the Work for the Sum of: $...................................................dollars, in lawful money of the United States of America. We have included the security Bid Bond as required by the Instruction to Bidders. All applicable State of Connecticut and federal taxes and all Town of Harwinton permit fees are to be excluded from the Bid Sum All Cash and Contingency Allowances described in Section 01200 - Price and Payment Procedures are included in the Bid Sum. 2. ACCEPTANCE This offer shall be open to acceptance and is irrevocable for (ninety days) from the bid closing date. If this bid is accepted by the Owner within the time period stated above, we will: - Execute the Agreement within seven days of receipt of Notice of Award. Bid Form - Stipulated Price 00411 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 - Furnish the required bonds and certificates of insurance within seven days of receipt of Notice of Award. - Commence work within fourteen days after written Notice to Proceed of this bid. If this bid is accepted within the time stated, and we fail to commence the Work [or we fail to provide the required bonds and certificates of insurance], the security deposit shall be forfeited as damages to the Owner by reason of our failure, limited in amount to the lesser of the face value of the security deposit or the difference between this bid and the bid upon which a Contract is signed. In the event our bid is not accepted within the time stated above, the required security deposit will be returned to the undersigned, in accordance with the provisions of the Instructions to Bidders; unless a mutually satisfactory arrangement is made for its retention and validity for an extended period of time. 3. CONTRACT TIME If this Bid is accepted, we will: Complete the Work in .........................(......) calendar weeks from Notice to Proceed. 5. ADDENDA The following Addenda have been received. The modifications to the Bid Documents noted below have been considered and all costs are included in the Bid Sum. Addendum # ...... Dated ................... Addendum # ...... Dated ................... 6. APPENDICES The following documents are attached to and made a condition of the Bid: Bid security in form of ............................. Bidder’s qualifications statement and supporting data. Document 01200 - Bid Form Supplements including: Appendix A - List of Subcontractors. Appendix B - List of Unit Prices. Appendix C - List of Alternates. Appendix D – Schedule of Values 7. BID FORM SIGNATURES The Corporate Seal of Bid Form - Stipulated Price 00411 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 ........................................................... (Bidder - print the full name of your firm) was hereunto affixed in the presence of: ........................................................... (Authorized signing officer Title) (Seal) ........................................................... (Authorized signing officer Title) (Seal) If the Bid is a joint venture or partnership, add additional forms of execution for each member of the joint venture in the appropriate form or forms as above. If the successful bidder is a legal entity, i.e. partnership, limited partnership, limited liability company or corporation, the bidder shall submit a certificate of good standing or authorization to do business from the CT Secretary of State within seven (7) days of receipt of Notice of Award. END OF DOCUMENT Bid Form - Stipulated Price 00411 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 Document 0412 Compliance with Laws, Regulations, Rules and Executive Orders (A) Compliance with Nondiscrimination and Affirmative Action in accordance with C.G.S. section 4a-60. (1) (a) The contractor agrees and warrants that in the performance of the contract such contractor will not discriminate or permit discrimination against any person or group of persons on the grounds of race, color, religious creed, age, marital status, national origin, ancestry, sex, mental retardation, mental disability or physical disability, including, but not limited to, blindness, unless it is shown by such contractor that such disability prevents performance of the work involved, in any manner prohibited by the laws of the United States or of the state of Connecticut. The contractor further agrees to take affirmative action to insure that applicants with job related qualifications are employed and that employees are treated when employed without regard to their race, color, religious creed, age, marital status, national origin, ancestry, sex, mental retardation, mental disability or physical disability, including, but not limited to, blindness, unless it is shown by such contractor that such disability prevents performance of the work involved; (b) the contractor agrees, in all solicitations or advertisements for employees placed by or on behalf of the contractor, to state that it is an "affirmative actionequal opportunity employer" in accordance with regulations adopted by the commission; (c) the contractor agrees to provide each labor union or representative of workers with which such contractor has a collective bargaining agreement or other contract or understanding and each vendor with which such contractor has a contract or understanding, a notice to be provided by the commission advising the labor union or workers' representative of the contractor's commitments under this section, and to post copies of the notice in conspicuous places available to employees and applicants for employment; (d) the contractor agrees to comply with each provision of this section and sections 46a-68e and 46a-68f and with each regulation or relevant order issued by said commission pursuant to sections 46a-56, 46a-68e and 46a-68f; (e) the contractor agrees to provide the Commission on Human Rights and Opportunities with such information requested by the commission, and permit access to pertinent books, records, and accounts, concerning the employment practices and procedures of the contractor as relate to the provisions of this section and section 46a-56. (2) If the contract is a public works contract, the contractor agrees and warrants that it will make good faith efforts to employ minority business enterprises as subcontractors and suppliers of materials on such public works project. (3) "Minority business enterprise" means any small contractor or supplier of materials fifty-one percent or more of the capital stock, if any, or assets of which is owned by a person or persons: (a) who are active in the daily affairs of the enterprise, (b) who have the power to direct the management and policies of the enterprise and (c) who are members of a minority, as such term is defined in subsection (a) of Conn. Gen. Stat. section 32-9n; and "good faith" means that degree of diligence which a reasonable person would exercise in the Compliance with laws, regulations, rules and executive orders 00412 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 performance of legal duties and obligations. "Good faith efforts" shall include, but not be limited to, those reasonable initial efforts necessary to comply with statutory or regulatory requirements and additional or substituted efforts when it is determined that such initial efforts will not be sufficient to comply with such requirements. (4) Determination of the contractor's good faith efforts shall include but shall not be limited to the following factors: the contractor's employment and subcontracting policies, patterns, and practices; affirmative advertising, recruitment, and training; technical assistance activities and such other reasonable activities or efforts as the commission may prescribe that are designed to ensure the participation of minority business enterprises in public works projects. (5) The contractor shall develop and maintain adequate documentation, in a manner prescribed by the commission, of its good faith efforts. (6) The contractor shall include the provisions of subsection (A)(1) and A(2) of this section in every subcontract or purchase order entered into in order to fulfill any obligation of this Agreement with the State and such provisions shall be binding on a subcontractor, vendor, or manufacturer unless exempted by regulations or orders of the commission. The contractor shall take such action with respect to any such subcontract or purchase order as the commission may direct as a means of enforcing such provisions including sanctions for noncompliance in accordance with Conn. Gen. Stat. section 46a-56; provided if such contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the commission, the contractor may request the State of Connecticut to enter into any such litigation or negotiation prior thereto to protect the interests of the State and the State may so enter. (B) Further Agreements re Compliance with Nondiscrimination. (1) (a) The contractor agrees and warrants that in the performance of the contract such contractor will not discriminate or permit discrimination against any person or group of persons on the grounds of race, color, religious creed, age, marital status, national origin, ancestry, sex, gender identity or expression, mental retardation, mental disability or physical disability, including, but not limited to, blindness, unless it is shown by such contractor that such disability prevents performance of the work involved, in any manner prohibited by the laws of the United States or of the state of Connecticut. The contractor further agrees to take affirmative action to insure that applicants with job related qualifications are employed and that employees are treated when employed without regard to their race, color, religious creed, age, marital status, national origin, ancestry, sex, gender identity or expression, mental retardation, mental disability or physical disability, including, but not limited to, blindness, unless it is shown Compliance with laws, regulations, rules and executive orders 00412 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 by such contractor that such disability prevents performance of the work involved; (b) the contractor agrees, in all solicitations or advertisements for employees placed by or on behalf of the contractor, to state that it is an "affirmative action-equal opportunity employer" in accordance with regulations adopted by the commission; (c) the contractor agrees to provide each labor union or representative of workers with which such contractor has a collective bargaining agreement or other contract or understanding and each vendor with which such contractor has a contract or understanding, a notice to be provided by the commission advising the labor union or workers' representative of the contractor's commitments under this section, and to post copies of the notice in conspicuous places available to employees and applicants for employment; (d) the contractor agrees to comply with each provision of this section and sections 46a-68e and 46a-68f and with each regulation or relevant order issued by said commission pursuant to sections 46a-56, 46a-68e and 46a-68f; (e) the contractor agrees to provide the Commission on Human Rights and Opportunities with such information requested by the commission, and permit access to pertinent books, records, and accounts, concerning the employment practices and procedures of the contractor as relate to the provisions of this section and section 46a-56.” (2) The contractor shall include the provisions of subsection (B)(1) in every subcontract or purchase order entered into in order to fulfill any obligation of a contract with the State and such provisions shall be binding on a subcontractor, vendor or manufacturer unless exempted by regulations or orders of the commission. The contractor shall take such action with respect to any such subcontract or purchase order as the commission may direct as a means of enforcing such provisions including sanctions for noncompliance in accordance with section 46a-56 of the General Statutes; provided, if such contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the commission, the contractor may request the State of Connecticut to enter into any such litigation or negotiation prior thereto to protect the interests of the State and the State may so enter. (3) For the purposes of sections (A) and (B) of this section, "contract" means the Agreement and includes any extension or modification of the contract, "contractor" includes any successors or assigns of the contractor, "Gender identity or expression" means a person's gender-related identity, appearance or behavior, whether or not that gender-related identity, appearance or behavior is different from that traditionally associated with the person's physiology or assigned sex at birth, which gender-related identity can be shown by providing evidence including, but not limited to, medical history, care or treatment of the gender-related identity, consistent and uniform assertion of the gender-related identity or any other evidence that the gender-related identity is sincerely held, part of a person's core identity or not being asserted for an improper purpose, "marital status" means being single, married as recognized by the state of Connecticut, widowed, separated or divorced, and "mental disability" means one or more mental disorders, as defined in the most recent edition of the American Psychiatric Association's "Diagnostic and Statistical Manual of Mental Disorders", or a record of or regarding a person as having one or more such disorders. Further, "contract" does not include a Compliance with laws, regulations, rules and executive orders 00412 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 contract where each contractor is: (i) a political subdivision of the state, including, but not limited to, a municipality; (ii) a quasi-public agency, as defined in section 1-120 of the Connecticut General Statutes; (iii) any other state, including but not limited to any federally recognized Indian tribal governments, as defined in section 1-267 of the Connecticut General Statutes; (iv) the federal government; (v) a foreign government; or (vi) an agency of a subdivision, agency, state or government described in the immediately preceding enumerated items (i), (ii), (iii), (iv) or (v).” (C) Executive Order No. Three. This Agreement is subject to the provisions of Executive Order No. Three of Governor Thomas J. Meskill promulgated June 16, 1971 and, as such, this Agreement may be cancelled, terminated or suspended by the State Labor Commissioner for violation or of noncompliance with said Executive Order No. Three, or any State or Federal Law concerning nondiscrimination, notwithstanding that the Labor Commissioner is not a party to this Agreement. The parties to this Agreement, as part of the consideration hereof, agree that said Executive Order No. Three is incorporated herein by reference and made a part hereof. The parties agree to abide by said Executive Order and agree that the State Labor Commissioner shall have continuing jurisdiction in respect to Agreement performance in regard to nondiscrimination, until the Agreement is completed or terminated prior to completion. The Applicant agrees as part consideration hereof, that this contract is subject to the guidelines and rules issued by the State Labor Commissioner to implement Executive Order No. Three and that it will not discriminate in its employment practices or policies, will file all reports as required, and will fully cooperate with the State and the State Labor Commissioner. (D) Executive Order No. Seventeen. This Agreement is subject to the provisions of Executive Order No. Seventeen of Governor Thomas J. Meskill promulgated February 15, 1973, and, as such, this Agreement may be cancelled, terminated or suspended by the Commissioner or the State Labor Commissioner for violation of or noncompliance with said Executive Order No. Seventeen, notwithstanding that the Labor Commissioner may not be a party to this Agreement. The parties to this Agreement, as part of the consideration hereof, agree that the Executive Order No. Seventeen is incorporated herein by reference and made a part hereof. The parties agree to abide by said Executive Order and agree that the contracting agency and the State Labor Commissioner shall have joint and several continuing jurisdiction in respect to Agreement performance in regard to listing all employment openings with the Connecticut Employment Service. Compliance with laws, regulations, rules and executive orders 00412 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 (E) Executive Order No. 16. This Agreement is subject to, and Applicant hereby agrees to abide by Executive Order No. Sixteen of Governor John G. Rowland promulgated August 4, 1999, regarding Violence in the Workplace Prevention. This Agreement may be cancelled, terminated or suspended by the State for violation or noncompliance with said Executive Order No. Sixteen. Compliance with laws, regulations, rules and executive orders 00412 - 5 COMMISSION ON HUMAN RIGHTS AND OPPORTUNITIES CONTRACT COMPLIANCE REGULATIONS NOTIFICATION TO BIDDERS (Revised 09/17/07) The contract to be awarded is subject to contract compliance requirements mandated by Sections 4a-60 and 4a60a of the Connecticut General Statutes; and, when the awarding agency is the State, Sections 46a-71(d) and 46a-81i(d) of the Connecticut General Statutes. There are Contract Compliance Regulations codified at Section 46a-68j-21 through 43 of the Regulations of Connecticut State Agencies, which establish a procedure for awarding all contracts covered by Sections 4a-60 and 46a-71(d) of the Connecticut General Statutes. According to Section 46a-68j-30(9) of the Contract Compliance Regulations, every agency awarding a contract subject to the contract compliance requirements has an obligation to “aggressively solicit the participation of legitimate minority business enterprises as bidders, contractors, subcontractors and suppliers of materials.” “Minority business enterprise” is defined in Section 4a-60 of the Connecticut General Statutes as a business wherein fifty-one percent or more of the capital stock, or assets belong to a person or persons: “(1) Who are active in daily affairs of the enterprise; (2) who have the power to direct the management and policies of the enterprise; and (3) who are members of a minority, as such term is defined in subsection (a) of Section 32-9n.” “Minority” groups are defined in Section 32-9n of the Connecticut General Statutes as “(1) Black Americans . . . (2) Hispanic Americans . . . (3) persons who have origins in the Iberian Peninsula . . . (4)Women . . . (5) Asian Pacific Americans and Pacific Islanders; (6) American Indians . . .” An individual with a disability is also a minority business enterprise as provided by Section 4a-60g of the Connecticut General Statutes. The above definitions apply to the contract compliance requirements by virtue of Section 46a-68j-21(11) of the Contract Compliance Regulations. The awarding agency will consider the following factors when reviewing the bidder’s qualifications under the contract compliance requirements: (a) the bidder’s success in implementing an affirmative action plan; (b) the bidder’s success in developing an apprenticeship program complying with Sections 46a-68-1 to 46a-68-17 of the Administrative Regulations of Connecticut State Agencies, inclusive; (c) the bidder’s promise to develop and implement a successful affirmative action plan; (d) the bidder’s submission of employment statistics contained in the “Employment Information Form”, indicating that the composition of its workforce is at or near parity when compared to the racial and sexual composition of the workforce in the relevant labor market area; and (e) the bidder’s promise to set aside a portion of the contract for legitimate minority business enterprises. See Section 46a-68j-30(10)(E) of the Contract Compliance Regulations. ___________________________________________________________________________________________ INSTRUCTIONS AND OTHER INFORMATION The following BIDDER CONTRACT COMPLIANCE MONITORING REPORT must be completed in full, signed, and submitted with the bid for this contract. The contract awarding agency and the Commission on Human Rights and Opportunities will use the information contained thereon to determine the bidders compliance to Sections 4a-60 and 4a-60a CONN. GEN. STAT., and Sections 46a-68j-23 of the Regulations of Connecticut State Agencies regarding equal employment opportunity, and the bidder’s good faith efforts to include minority business enterprises as subcontractors and suppliers for the work of the contract. 1) Definition of Small Contractor Section 4a-60g CONN. GEN. STAT. defines a small contractor as a company that has been doing business under the same management and control and has maintained its principal place of business in Connecticut for a one year period immediately prior to its application for certification under this section, had gross revenues not exceeding ten million dollars in the most recently completed fiscal year, and at least fifty-one percent of the ownership of which is held by a person or persons who are active in the daily affairs of the company, and have the power to direct the management and policies of the company, except that a nonprofit corporation shall be construed to be a small contractor if such nonprofit corporation meets the requirements of subparagraphs (A) and (B) of subdivision 4a-60g CONN. GEN. STAT. 2) Description of Job Categories (as used in Part IV Bidder Employment Information) (Page 2) MANAGEMENT: Managers plan, organize, direct, and control the major functions of an organization through subordinates who are at the managerial or supervisory level. They make policy decisions and set objectives for the company or departments. They are not usually directly involved in production or providing services. Examples include top executives, public relations managers, managers of operations specialties (such as financial, human resources, or purchasing managers), and construction and engineering managers. BUSINESS AND FINANCIAL OPERATIONS: These occupations include managers and professionals who work with the financial aspects of the business. These occupations include accountants and auditors, purchasing agents, management analysts, labor relations specialists, and budget, credit, and financial analysts. MARKETING AND SALES: Occupations related to the act or process of buying and selling products and/or services such as sales engineer, retail sales workers and sales representatives including wholesale. LEGAL OCCUPATIONS: In-House Counsel who is charged with providing legal advice and services in regards to legal issues that may arise during the course of standard business practices. This category also includes assistive legal occupations such as paralegals, legal assistants. COMPUTER SPECIALISTS: Professionals responsible for the computer operations within a company are grouped in this category. Examples of job titles in this category include computer programmers, software engineers, database administrators, computer scientists, systems analysts, and computer support specialists ARCHITECTURE AND ENGINEERING: Occupations related to architecture, surveying, engineering, and drafting are included in this category. Some of the job titles in this category include electrical and electronic engineers, surveyors, architects, drafters, mechanical engineers, materials engineers, mapping technicians, and civil engineers. OFFICE AND ADMINISTRATIVE SUPPORT: All clerical-type work is included in this category. These jobs involve the preparing, transcribing, and preserving of written communications and records; collecting accounts; gathering and distributing information; operating office machines and electronic data processing equipment; and distributing mail. Job titles listed in this category include telephone operators, bill and account collectors, customer service representatives, dispatchers, secretaries and administrative assistants, computer operators and clerks (such as payroll, shipping, stock, mail and file). BUILDING AND GROUNDS CLEANING AND MAINTENANCE: This category includes occupations involving landscaping, housekeeping, and janitorial services. Job titles found in this category include supervisors of landscaping or housekeeping, janitors, maids, grounds maintenance workers, and pest control workers. CONSTRUCTION AND EXTRACTION: This category includes construction trades and related occupations. Job titles found in this category include boilermakers, masons (all types), carpenters, construction laborers, electricians, plumbers (and related trades), roofers, sheet metal workers, elevator installers, hazardous materials removal workers, paperhangers, and painters. Paving, surfacing, and tamping equipment operators; drywall and ceiling tile installers; and carpet, floor and tile installers and finishers are also included in this category. First line supervisors, foremen, and helpers in these trades are also grouped in this category.. INSTALLATION, MAINTENANCE AND REPAIR: Occupations involving the installation, maintenance, and repair of equipment are included in this group. Examples of job titles found here are heating, ac, and refrigeration mechanics and installers; telecommunication line installers and repairers; heavy vehicle and mobile equipment service technicians and mechanics; small engine mechanics; security and fire alarm systems installers; electric/electronic repair, industrial, utility and transportation equipment; millwrights; riggers; and manufactured building and mobile home installers. First line supervisors, foremen, and helpers for these jobs are also included in the category. MATERIAL MOVING WORKERS: The job titles included in this group are Crane and tower operators; dredge, excavating, and lading machine operators; hoist and winch operators; industrial truck and tractor operators; cleaners of vehicles and equipment; laborers and freight, stock, and material movers, hand; machine feeders and offbearers; packers and packagers, hand; pumping station operators; refuse and recyclable material collectors; and miscellaneous material moving workers. PRODUCTION WORKERS: The job titles included in this category are chemical production machine setters, operators and tenders; crushing/grinding workers; cutting workers; inspectors, testers sorters, samplers, weighers; precious stone/metal workers; painting workers; cementing/gluing machine operators and tenders; etchers/engravers; molders, shapers and casters except for metal and plastic; and production workers. 3) Definition of Racial and Ethnic Terms (as used in Part IV Bidder Employment Information) White (not of Hispanic Origin)- All persons having origins in any of the original peoples of Europe, North Africa, or the Middle East. Black(not of Hispanic Origin)- All persons having origins in any of the Black racial groups of Africa. Hispanic- All persons of Mexican, Puerto Rican, Cuban, Central or South American, or other Spanish culture or origin, regardless of race. (Page 3) Asian or Pacific Islander- All persons having origins in any of the original peoples of the Far East, Southeast Asia, the Indian subcontinent, or the Pacific Islands. This area includes China, India, Japan, Korea, the Philippine Islands, and Samoa. American Indian or Alaskan Native- All persons having origins in any of the original peoples of North America, and who maintain cultural identification through tribal affiliation or community recognition. BIDDER CONTRACT COMPLIANCE MONITORING REPORT PART I - Bidder Information Company Name Street Address City & State Chief Executive Bidder Federal Employer Identification Number____________________ Or Social Security Number__________________ Major Business Activity Bidder Identification (response optional/definitions on page 1) (brief description) -Bidder is a small contractor. Yes__ No__ -Bidder is a minority business enterprise Yes__ No__ (If yes, check ownership category) Black___ Hispanic___ Asian American___ American Indian/Alaskan Native___ Iberian Peninsula___ Individual(s) with a Physical Disability___ Female___ Bidder Parent Company (If any) - Bidder is certified as above by State of CT Yes__ No__ Other Locations in Ct. (If any) PART II - Bidder Nondiscrimination Policies and Procedures 1. Does your company have a written Affirmative Action/Equal Employment Opportunity statement posted on company bulletin boards? Yes__ No__ 7. Do all of your company contracts and purchase orders contain non-discrimination statements as required by Sections 4a-60 & 4a-60a Conn. Gen. Stat.? Yes__ No__ 2. Does your company have the state-mandated sexual harassment prevention in the workplace policy posted on company bulletin boards? Yes__ No__ 8. Do you, upon request, provide reasonable accommodation to employees, or applicants for employment, who have physical or mental disability? Yes__ No__ 3. Do you notify all recruitment sources in writing of your company’s Affirmative Action/Equal Employment Opportunity employment policy? 9. Does your company have a mandatory retirement age for all employees? Yes__ No__ Yes__ No__ 4. Do your company advertisements contain a written statement that you are an Affirmative Action/Equal Opportunity Employer? Yes__ No__ 10. If your company has 50 or more employees, have you provided at least two (2) hours of sexual harassment training to all of your supervisors? Yes__ No__ NA__ 5. Do you notify the Ct. State Employment Service of all employment openings with your company? Yes__ No__ 11. If your company has apprenticeship programs, do they meet the Affirmative Action/Equal Employment Opportunity requirements of the apprenticeship standards of the Ct. Dept. of Labor? Yes__ No__ NA__ 6. Does your company have a collective bargaining agreement with workers? Yes__ No__ 6a. If yes, do the collective bargaining agreements contain non-discrim ination clauses covering all workers? Yes__ No__ 12. Does your company have a written affirmative action Plan? Yes__ No__ 6b. Have you notified each union in writing of your commitments under the nondiscrimination requirements of contracts with the state of Ct? Yes__ No__ If no, please explain. 13. Is there a person in your company who is responsible for equal employment opportunity? Yes__ No__ If yes, give name and phone number. ____________________________________________________________ ____________________________________________________________ Part III - Bidder Subcontracting Practices (Page 4) 1. Will the work of this contract include subcontractors or suppliers? Yes__ No__ 1a. If yes, please list all subcontractors and suppliers and report if they are a small contractor and/or a minority business enterprise. (defined on page 1 / use additional sheet if necessary) 1b. Will the work of this contract require additional subcontractors or suppliers other than those identified in 1a. above? PART IV - Bidder Employment Information JOB CATEGORY * OVERALL TOTALS Date: WHITE BLACK (not of Hispanic origin) (not of Hispanic origin) Male Female Yes__ No__ Male Female HISPANIC Male Female ASIAN or PACIFIC ISLANDER Male Female AMERICAN INDIAN or ALASKAN NATIVE male female Management Business & Financial Ops Marketing & Sales Legal Occupations Computer Specialists Architecture/Engineering Office & Admin Support Bldg/ Grounds Cleaning/Maintenance Construction & Extraction Installation , Maintenance & Repair Material Moving Workers Production Occupations TOTALS ABOVE Total One Year Ago FORMAL ON THE JOB TRAINEES (ENTER FIGURES FOR THE SAME CATEGORIES AS ARE SHOWN ABOVE) Apprentices Trainees *NOTE: JOB CATEGORIES CAN BE CHANGED OR ADDED TO (EX. SALES CAN BE ADDED OR REPLACE A CATEGORY NOT USED IN YOUR COMPANY) PART V - Bidder Hiring and Recruitment Practices 1. Which of the following recruitment sources are used by you? (Check yes or no, and report percent used) (Page 5) 2. Check (X) any of the below listed requirements that you use as a hiring qualification 3. Describe below any other practices or actions that you take which show that you hire, train, and promote employees without discrimination (X) SOURCE YES NO % of applicants provided by source State Employment Service Work Experience Private Employment Agencies Ability to Speak or Write English Schools and Colleges Written Tests Newspaper Advertisement High School Diploma Walk Ins College Degree Present Employees Union Membership Labor Organizations Personal Recommendation Minority/Community Organizations Height or Weight Others (please identify) Car Ownership Arrest Record Wage Garnishments Certification (Read this form and check your statements on it CAREFULLY before signing). I certify that the statements made by me on this BIDDER CONTRACT COMPLIANCE MONITORING REPORT are complete and true to the best of my knowledge and belief, and are made in good faith. I understand that if I knowingly make any misstatements of facts, I am subject to be declared in non-compliance with Section 4a-60, 4a-60a, and related sections of the CONN. GEN. STAT. (Signature) (Title) (Date Signed) (Telephone) Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 AFFIDAVIT FOR BECOMING SIGNATORY TO THE DOCUMENT 0412 – COMPLIANCE WITH LAWS, REGULATIONS, RULES AND EXECUTIVE ORDERS I, ______________________________________________, being duly sworn do depose and say: (insert name and title of authorized agent) 1. I am an official of the following organization and I am authorized to submit this affidavit for and on behalf of my organization, thereby binding it to the terms and statements contained herein. 2. My organization hereby agrees to and certifies compliance with the Laws, Regulations, Rules and Executive orders contained in herein. _________________________________________ (insert name of company) ________________________________ (signature of authorized agent) Subscribed to and sworn to before me this __________________ day of ____________, 20_____ (Check appropriate box) _____________________________________ ( ) Commissioner of Superior Court ( ) Notary Public, my commission expires: Compliance with laws, regulations, rules and executive orders 00412 - 6 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00414 NON‐COLLUSION AFFIDAVIT STATE OF ______________________________ COUNTY OF _____________________________ I, _____________________________________________, being first duly sworn, deposes and says that: 1. I am ____________________________________________________________________ of __________________________________________________________, the bidder that has submitted the attached request for proposal for _______________________________________________________________________; 2. I am fully informed respecting the preparation and contents of the attached RFP and all pertinent circumstances respecting such bid; 3. Such Bid is genuine and is not a collusive or sham Bid; 4. Neither the Bidder not any of its officers, partners, owners, agents, representatives, employees or parties of interest, including this affiant, has in any way colluded, conspired, connived or agreed directly or indirectly with any other Bidder, firm or person to submit a collusive or sham Bid in connection with the work for which the attached Bid has been submitted nor has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other Bidder, firm or person to fix the price or prices in the attached Bid or of any other Bidder, or to fix any overhead, profit or cost element of the Bid price or the price of any Bidder, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantage against the Town of Harwinton or any person interested in the proposed Bid; and Non-Collusion Affidavit 00414 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 5. The price or prices quoted in the attached Bid are fair and proper and not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, owners, employees, or parties of interest, including this affiant. Signed________________________________________ Title___________________________________ Subscribed and sworn to before this __________day of_______________, 20_______, ________________________________________ ________________________________________ Notary Public My commission expires_____________________ Non-Collusion Affidavit 00414 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 CORPORATE RESOLUTION I, _________________________________________, hereby certify that I am the duly elected and acting Secretary of ________________________________________, a corporation organized and existing under the laws of the State of ________________________________, do herby certify that the following facts are true and were taken from the records of said corporation. The following resolution was adopted at a meeting of the corporation duly held on the ______________________day of ______________________, 20______. “It is hereby resolved that _________________________________________ is authorized to make, execute and approve, on behalf of this corporation, any and all contracts or amendments thereof” And I do further certify that the above resolution has not been in any way altered, amended, repealed and is now in full forces and effect. IN WITNESS WHEREOF, I hereunto set my hand and affix the corporate seal of said _____________________________________________ corporation this ______________ day of ____________________, 20_______ ______________________________________ Secretary Corporate Resolution 00414 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 LIMITED LIABILITY COMPANY RESOLUTION I, __________________________________, Hereby certify that I am the duly authorized and acting Member / Manager (circle one) of ____________________________________________, LLC, a limited liability company organized and existing under the laws of the State of ____________________________________, do hereby certify that the following facts are true and were taken from the records of said LLC. The following resolution was adopted at a meeting of this LLC duly held on the __________________ day of ___________________, 20________. “It is hereby resolved that _____________________________________ is authorized to make, execute and approve, on behalf of the LLC, any and all contracts or amendments thereof.” And I do further certify that the above resolution has not in any way been altered, amended, repealed and is now in full force and effect. IN WITNESS WHEREOF, I hereunto set my hand and affix the corporate seal of said _____________________________________________, LLC this ______________ day of _________________, 20_______ ______________________________________ Member / Manager Corporate Resolution 00414 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00501 AGREEMENT 1.1 1.2 SUMMARY A. Document Includes: 1. Agreement. B. Related Documents: 1. Document 00701 - General Conditions - AIA. 2. Document 00811 - Supplementary Conditions - AIA. AGREEMENT A. AIA document A101 – 2007 “Standard Form of Agreement between Owner and Contractor” where the Basis of Payment is a Stipulated Sum, forms the basis of Agreement between the Owner and Contractor. B. Upon award, Contractor shall be responsible providing the contract with the following changes for Owner review and signatures. Article 5 - Payments: Section 5.1 Progress Payment: Section 5.1.3 – change the “Tenth” to the “Twentieth” day of the same month. Change “Thirty (30)” to “Forty (40)” days. Section 5.2 Final Payment: Section 5.2.2 – change “30” days to “40” days. Article 6 – Dispute Resolution: Section 6.2 – Binding Dispute Resolution: Shall read “[X] Other: Litigation in the Connecticut Superior Court for the Judicial District of Litchfield.” Article 8 – Miscellaneous Provisions Section 8.2 - Changed to “10% per annum” to “The State of Connecticut Public Works rate for prompt payment under C.G.S. Sections 4a-71 and 4a-72.” Agreement - AIA 00501 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 Section 8.3 –Owner’s representatives Jason Emery – Chief Harwinton Ambulance Association Chief@harwintonems.org 860-601-0129 John Fredsall – Highway Supervisor Town of Harwinton jfredsall@harwinton.us 860-485-3892 The signatures lines for the Agreement under Owner shall be: “Town of Harwinton by Michael R. Criss, First Selectman” and “Harwinton Ambulance Association, Inc. by Jason Emery, Chief.” Agreement - AIA 00501 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00701 GENERAL CONDITIONS - AIA 1.1 1.2 SUMMARY A. Document Includes: 1. General Conditions. B. Related Documents: 1. Document 00501 - Agreement - AIA. 2. Document 00811 - Supplementary Conditions - AIA. GENERAL CONDITIONS A. 1.3 AIA Document A201-2007, General Conditions of the Contract for Construction, is the General Conditions of the Contract. SUPPLEMENTARY CONDITIONS A. Refer to Document 00811 for modifications to General Conditions. END OF DOCUMENT General Conditions - AIA 0701 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 DOCUMENT 00811 SUPPLEMENTARY CONDITIONS TO THE GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION — AIA DOCUMENT A201 - 2007 EDITION Article 2 – Owner Section 2.1 - General Section 2.1.2: delete in its entirety. Article 3 - Contractor Add the following paragraphs: 3.2.2.1. After reporting to the Architect any error, inconsistency or omission discovered in the Contract Documents, the Contractor shall not proceed with any work so affected without the Architect's written modifications to the Drawings and/or Specifications. Article 4 – Architect Section 4.2 - Administration Section 4.2.2: Architect’s schedule to be determined at the initial meeting with contractor. Article 7 - Changes in the Work Change paragraph 7.3.3 to read as follows: The Owner, without invalidating the Contract, may order extra work or make changes by altering, adding to or deducting from the work, the Contract Price being adjusted accordingly. All such work shall be executed under the work items and conditions of the original Contract, except that any claim for extension of time caused thereby shall be requested in writing by the Contractor at the time of ordering such change and subsequently adjusted. Extra work or changes for work items not appearing in the original contract must be approved by the Architect, and a change order must be executed by the Owner. The value of any such extra work or change shall be determined by estimate and acceptance on a lump sum or per unit basis shall be agreed to and included in the change order before the extra work shall progress. Supplementary Conditions - AIA 00811 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 If such changes make the work less expensive for the Contractor, the proper deductions shall be made from the contract price, said deductions to be computed in accordance with the provisions listed below in this article. It is distinctly agreed and understood that any changes made to the Contract for this work (whether such changes increase or decrease the amount thereof) shall in no way annul, release or affect the liability and surety on the bonds given by the contractor The amount of compensation to be paid to the Contractor for any additional work so ordered shall be determined I by unit prices as stated in the contract documents (or subsequently agreed upon) or by a lump sum, mutually agreed upon by the Owner and the Contractor, If a dispute arises as to the cost of the extra work, the fee for such I work shall be computed as follows: 1. The cost of labor performed and material used by the Contractor with his own forces. 2. The cost of Workmen's Compensation, Federal Social Security and Connecticut Unemployment Compensation in established rates as well as all fringe benefits inherent to the particular trades involved. 3. Actual cost of rented equipment used directly on the work. 4. On work to be performed by the General Contractor, his allowances for change orders up to and including $5,000 - 10 overhead and 10 profit; for change orders from $5,001 to $15,000 – 10% overhead and 7% profit; for change orders from $15,001 to $25,000 – 10% overhead and 5% profit; for change orders from $25,001 and up 12% (total). If the work to be performed results in a credit to the Owner, no percentage of overhead and profit will apply. 5. On work to be performed by a subcontractor, the General Contractor's allowance for overhead and profit will be as follows: a. b. c. d. $0 to $5,000 $5,001 to $15,000 $15,001 to $25;000 $25,001 and up - 10% - 8% - 6% - 4% The percentage above shall be applied to the total cost of the Subcontractor's work including Subcontractor’s allowance as per item 4, above. 6. On any changes involving one subcontractor, his total costs and/or omissions shall be combined as one before the application of the percentage allowed for overhead and profit in accordance with item b(4). The General Contractor's percentage of overhead and profit shall then be applied in accordance with item b(5) above. On any changes involving more than one Subcontractor; the additional charges; if any, shall have overhead and profit added to Supplementary Conditions - AIA 00811 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 them before credits are applied. The General Contractor's percentage of overhead and profit may then be applied. 7. On work performed by a subcontractor, IDS allowance is to be the same as item 4, above. 8. The Contractor shall, when requested, promptly furnish in a form satisfactory to the Owner itemized statements of the cost of work so ordered, including but not limited to certified payrolls and copies of accounts, bills and vouchers to substantiate the above actual costs. If the Contractor wishes to make a claim for an increase in the contract sum or for any damages sustained as a result of changes in the work, he shall give the Owner written notice thereof within seven (7) calendar days after the occurrence of the event giving rise to such claims; no such claim shall be valid unless the notice is in writing. In addition, the Contractor shall provide daily or weekly (as determined by the Owner) itemized statements of the details and cost of such work performed or damage sustained. The provisions hereof shall not affect the power of the Contractor to act in case of emergency, threatened injury to persons or damage to work or any adjoining property. in which case the Owner shall issue a written order for such amount as he finds to be reasonable cost of such work. Article 9 - Payments and Completion Add the following paragraph 9.6.1.2: On the last day of each month, the Contractor may submit a request for progress payment. The Architect may certify and the Owner may approve up to ninety-five percent (95) of the amount requested. Add the following paragraph 9.10.1.1.: Upon completion of work, the Architect may issue final certification up to ninety-five percent (95) of the final cost. Final payment of the retained five percent (5) will be made within 30 days of final certification, if all work is completed at that time. Add the following paragraph 9.10.1.2 Failure to supply waivers of lien or evidence of final payment of all current accounts will be considered grounds for withholding partial payments. Supplementary Conditions - AIA 00811 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 Add the following paragraph 9.10.1.3: Before payment of the final estimate, the Contractor shall submit a notarized statement to the Town of Harwinton verifying that payment in full has been made for all material, labor and equipment used on this contract. If a subcontractor has been used in this Contract, the statement shall also note that their services have been paid for in full. Article 10 – Protection of Persons and Property: Section 10.3.3: delete in its entirety. Article 11 – Insurance and Bonds: Add the following paragraph: 11.1.1.1 The Contractor and all Sub-Contractors shall provide evidence of insurance coverage from a company or companies with an A.M. Best rating of A- (VII) or better. Such insurance shall protect and indemnify the Town of Harwinton, the Harwinton Ambulance Association, Inc. and the State of Connecticut from claims which may arise out of or result from any obligation under this agreement, whether such obligations are the Contractor's or those of a subcontractor or any person or entity directly or indirectly employed by said Contractor. Minimum coverage is as follows: 1. Workers Compensation: Contractor shall provide workers compensation and employers liability insurance that complies with the regulations of the State of Connecticut with limits no less than $1,000,000 each accident by bodily injury; $1,000,000 each accident by disease and a policy limit of $1,000,000. 2. Commercial General Liability Insurance: Contractor shall provide commercial general liability insurance policy that includes products, operations and completed operations (with no exclusion for sexual abuse or molestation). Limits should be at least: Bodily injury & property damage with an occurrence limit of $1,000,000: Personal & advertising injury limit of $1,000,000 per occurrence: General aggregate limit of $2,000,000 (other than products and completed operations): Products and completed operations aggregate limit of $2,000,000. The policy shall name the Town of Harwinton and Harwinton Ambulance Association, Inc. as additional insureds. Such coverage shall be provided on an occurrence basis and shall be primary and shall not contribute in any way to any insurance or self-insured retention carried by the Town of Harwinton and the Harwinton Ambulance Association, Inc. . Such coverage shall contain a broad form contractual liability endorsement or similar wording within the policy form. Supplementary Conditions - AIA 00811 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 3. Commercial Automobile Insurance: Contractor shall provide commercial automobile insurance for any owned autos (symbol 1 or equivalent) in the amount of $1,000,000 for each accident covering bodily injury and property damage on a combined single limit basis. Such coverage shall also include hired and non-owned automobile coverage. 4. Umbrella Liability Insurance: Contractor shall provide an umbrella liability policy in excess (without restriction or limitation) of those limits described in items (1) through (3). Such policy shall contain limits of liability in the amount of $5,000,000 each occurrence and $5,000,000 in the aggregate which may be amended during the term of the contract if deemed reasonable and customary by the Town of Harwinton at the sole cost and expense of the Contractor. 5. The Contractor will be required to add the Town of Harwinton, the Harwinton Ambulance Association, Inc and the State of Connecticut as additional insured on the policies. 6. As to the insurance required, the insurers and/or their authorized agents shall provide the Town of Harwinton with certificates of insurance prior to execution of the agreement by the Town of Harwinton, describing the coverage, including a copy of the endorsement that names the Town of Harwinton, the Harwinton Ambulance Association, Inc. and the State of Connecticut as an additional insureds and waiving the right of subrogation with regard to the additional insureds. The coverage shall be carried until final payment is made to the Contractor on this project. The Contractor shall procure, pay for and maintain a site work all risk insurance policy to the full value of the work until final payment has been made. All the above policies will be endorsed to include 30 day prior notice of cancellation, termination or modification to the Owner's representatives as identified herein above. Section 11.3.3: delete the second sentence – “The Owner waives all rights of action against the Contractor for loss of use of the Owner’s property, including consequential losses due to fire or other hazards however caused.” . Section 11.3.5: delete in its entirety. Section 11.3.7: delete in its entirety. Supplementary Conditions - AIA 00811 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01100 SUMMARY PART 1 GENERAL 1.1 SECTION INCLUDES A. Contract description. B. Work by Owner. C. Owner supplied products. D. Contractor's use of site. E. Specification Conventions. 1.2 CONTRACT DESCRIPTION Work of the Project includes construction of a new 4,799 square foot, one story wood framed ambulance facility. With associated site improvements. A. 1.3 1.4 Perform Work of Contract under stipulated sum contract with Owner in accordance with Conditions of Contract. WORK BY OWNER A. The Owner will award contracts for supply and installation of Phone, Data, Security Alarm System, and radio system B. Work under this contract will include: Owner intends to award a separate contract for Phone, Data, Security and Radio work to (contractor(s) – to be determined). The General Contractor shall be responsible for coordination of this work with all trades and should contact (contractor(s) – to be determined) to perform a scope review prior to submitting a bid associated with this Contract. C. Items noted NIC (Not in Contract), movable cabinets, and furnishings, will be furnished and installed by Owner upon substantial completion. OWNER SUPPLIED PRODUCTS A. Owner's Responsibilities: 1. Arrange for and deliver Owner-reviewed Shop Drawings, Product Data, and Samples, to Contractor. 2. Arrange and pay for delivery to site. 3. On delivery, inspect products jointly with Contractor. Summary 01100 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 4. 5. 1.5 1.6 Submit claims for transportation damage and replace damaged, defective, or deficient items. Arrange for manufacturers' warranties, inspections, and service. B. Contractor's Responsibilities: 1. Review Owner-reviewed Shop Drawings, Product Data, and Samples. 2. Receive and unload products at site; inspect for completeness or damage jointly with Owner. 3. Handle, store, install and finish products. 4. Repair or replace items damaged after receipt. C. Products furnished to site and installed by Owner: 1. Furnishings. 2. Owner reserves the right to furnish and install ancillary items D. Items furnished by Owner for installation by Contractor: 1. Owner reserves the right to furnish ancillary items and request change order for installation. CONTRACTOR'S USE OF SITE [AND PREMISES] A. Limit use of site and premises to allow: 1. Owner representatives visits 2. Work by Others and Work by Owner representatives. B. Additional Restrictions 1. The contractor shall not disturb or block access to the active groundwater monitoring wells shown on the environmental site plan prepared by Corporate Environmental Advisors (CEA) and must allow access to the monitoring wells by authorized representatives of CEA, HRP Associates (HRP), CT DEEP and the Town of Harwinton for sampling purposes. 2. The contractor cannot disturb, stock pile or park vehicles and equipment on the area designated for the proposed septic system leach fields and reserve area on the easterly side of the site. 3. No bulk storage of fuels and oils (diesel, gasoline, etc.) is allowed on the site SPECIFICATION CONVENTIONS A. These specifications are written in imperative mood and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise. The words “shall be” are included by inference where a colon (:) is used within sentences or phrases. Summary 01100 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 PART 2 PRODUCTS Not Used. PART 3 EXECUTION Not Used. END OF SECTION Summary 01100 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01200 PRICE AND PAYMENT PROCEDURES PART 1 GENERAL 1.1 1.2 SECTION INCLUDES A. Cash allowances. B. Contingency allowances. C. Testing and inspection allowances. D. Schedule of values. E. Applications for payment. F. Change procedures. G. Defect assessment. H. Unit prices. I. Alternates. CASH ALLOWANCES A. Costs Included in Cash Allowances: Cost of product to Contractor or Subcontractor, less applicable trade discounts; delivery to site and applicable taxes. B. Costs Not Included in Cash Allowances but Included in Contract Sum/Price: Product handling at site, including unloading, uncrating, and storage; protection of products from elements and from damage; and labor for installation and finishing. C. Architect/Engineer Responsibilities: 1. Consult with Contractor for consideration and selection of products 2. Select products in consultation with Owner and transmit decision to Contractor. 3. Prepare Change Order. D. Contractor Responsibilities: Price and Payment Procedures 01200 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1. 2. 3. 4. 5. 1.3 CONTINGENCY ALLOWANCES A. 1.4 1.6 Not used TESTING AND INSPECTION ALLOWANCES A. 1.5 Assist Architect/Engineer in selection of products, suppliers and installers. Obtain proposals from suppliers and installers and offer recommendations. On notification of selection by Architect, Engineer, or Owner, execute purchase agreement with designated supplier and installer. Arrange for and process shop drawings, product data, and samples. Arrange for delivery. Promptly inspect products upon delivery for completeness, damage, and defects. Submit claims for transportation damage. Not used SCHEDULE OF VALUES A. Submit printed schedule on AIA Form G703 - Continuation Sheet for G702. B. Submit Schedule of Values in duplicate within 15 days after date of OwnerContractor Agreement. C. Format: Utilize Table of Contents of this Project Manual. Identify each line item with number and title of major specification Section. Identify site mobilization, bonds and insurance. D. Include in each line item, amount of Allowances specified in this section. E. Include each line item, direct proportional amount of Contractor's overhead and profit. F. Revise schedule to list approved Change Orders, with each Application for Payment. APPLICATIONS FOR PAYMENT A. Submit [three] copies of each application on AIA Form G702 - Application and Certificate for Payment and AIA G703 - Continuation Sheet for G702. B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment. Price and Payment Procedures 01200 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 C. Submit updated three construction schedule with each Application for Payment. D. Payment Period: Submit at intervals stipulated in the Agreement. E. Submit with transmittal letter as specified for Submittals in Section 01330. F. Substantiating Data: When Architect/Engineer requires substantiating information, submit data justifying dollar amounts in question. Include the following with Application for Payment: 1. 2. 3. 1.7 Partial release of liens from major subcontractors and vendors. Affidavits attesting to off-site stored products. Construction progress schedules, revised and current. CHANGE PROCEDURES A. Submittals: Submit name of individual authorized to receive change documents, and be responsible for informing others in Contractor's employ or Subcontractors of changes to the Work. B. The Architect will advise of minor changes in the Work not involving adjustment to Contract Sum/Price or Contract Time by issuing supplemental instructions on AIA Form G710. C. The Architect may issue a Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and specifications, a change in Contract Time for executing the change. Contractor will prepare and submit estimate within seven days. D. Stipulated Sum/Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for Change Order as approved by Architect/Engineer. E. Construction Change Directive: Architect may issue directive, on AIA Form G713 Construction Change Directive signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Sum/Price or Contract Time. Promptly execute change. F. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in Conditions of the Contract. Architect/Engineer will determine change allowable in Contract Sum/Price and Contract Time as provided in Contract Documents. Price and Payment Procedures 01200 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.8 G. Maintain detailed records of work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work. H. Document each quotation for change in cost or time with sufficient data to allow evaluation of quotation. I. Change Order Forms: AIA G701Change Order. J. Execution of Change Orders: Architect/Engineer will issue Change Orders for signatures of parties as provided in Conditions of the Contract. K. Correlation Of Contractor Submittals: 1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Sum/Price. 2. Promptly revise progress schedules to reflect change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit. 3. Promptly enter changes in Project Record Documents. DEFECT ASSESSMENT A. Replace the Work, or portions of the Work, not conforming to specified requirements. B. If, in the opinion of the Architect and/or Owner, it is not practical to remove and replace the Work, the Architect and/or Owner will direct appropriate remedy or adjust payment. C. Defective Work will be partially repaired to instructions of Architect and/or Owner, and unit sum/price will be adjusted to new sum/price at discretion of Architect and/or Owner. D. Individual specification sections may modify these options or may identify specific formula or percentage sum/price reduction. E. Authority of Architect and/or Owner to assess defects and identify payment adjustments, is final. F. Non-Payment For Rejected Products: Payment will not be made for rejected products for any of the following: 1. Products wasted or disposed of in a manner that is not acceptable. 2. Products determined as unacceptable before or after placement. 3. Products not completely unloaded from transporting vehicle. 4. Products placed beyond lines and levels of required Work. Price and Payment Procedures 01200 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 5. 6. 1.9 Products remaining on hand after completion of the Work. Loading, hauling, and disposing of rejected products. ALTERNATES A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owner's option. Accepted Alternates will be identified in Owner-Contractor Agreement. B. Coordinate related work and modify surrounding work. C. Schedule of Alternates: 1. Alternate No. 1: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to complete the work to paint interior wall and trim. 2. Alternate No. 2: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install kitchen millwork on elevation 3 on drawing A5.1 3. Alternate No. 3: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install floor finishes and base indicated on drawing A6.2 (flooring in ambulance bay 119 to remain in contract) 4. Alternate No. 4: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install exterior signage as indicated on South Elevation on drawing A2.1 5. Alternate No. 5: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install Generator, Generator Pad, Wire and Conduit. Transfer switch and conduit to generator shall be stubbed to the location indicated on the site plan and capped shall remain in contract. 6. Alternate No. 6: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide Radiant Floor Heating as indicated on drawing M1.1 alt. (if this alternate is accepted eliminate the radiant tube heaters and associated work from M1.1) 7. Alternate No. 7 : (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide Plymovent vehicle exhaust system as indicated on key note 15 on drawing M1.1 (blocking, power, penetration, and flashing shall remain in Price and Payment Procedures 01200 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 contract. If accepted, contractor shall coordinate power, blocking, penetration, and flashing requirements with owner’s contractor.) 8. Alternate No. 8: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install lockers indicated on Drawings A1.2 and Section 10500 on Drawing A7.2 9. Alternate No. 9: (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install low voltage wiring and outlets, security system (including cameras) and fire alarm system as indicated on drawing E2.1 10. Alternate No. 10: Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install driveway paving as indicated on the site plan 11. Alternate No. 11 (Provide Add Alternated price on bid form): Provide all material labor and all else whatsoever may be necessary to provide and install concrete foundation for radio tower as noted on site plan and attached specification. PART 2 PRODUCTS Not Used. PART 3 EXECUTION Not Used. END OF SECTION Price and Payment Procedures 01200 - 6 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01300 ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.1 1.2 SECTION INCLUDES A. Coordination and project conditions. B. Field engineering. C. Preconstruction meeting. D. Site mobilization meeting. E. Progress meetings. F. Pre-installation meetings. G. Cutting and patching. H. Special procedures. COORDINATION AND PROJECT CONDITIONS A. Coordinate scheduling, submittals, and Work of various sections of Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later. B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, operating equipment. C. Coordinate space requirements, supports, and installation of mechanical and electrical Work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs. D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within construction. Coordinate locations of fixtures and outlets with finish elements. Administrative Requirements 01300 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.3 1.4 E. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion and for portions of Work designated for Owner's partial occupancy. F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities. FIELD ENGINEERING A. Employ Land Surveyor registered in State of Connecticut and acceptable to Architect/Engineer. B. Locate and protect survey control and reference points. Promptly notify Architect/Engineer of discrepancies discovered. C. Control datum for survey is that established by Owner provided survey. D. Verify set-backs and easements; confirm drawing dimensions and elevations. E. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices. F. Submit copy of site drawing and certificate signed by Land Surveyor certifying elevations and locations of the Work are in conformance with Contract Documents. G. Maintain complete and accurate log of control and survey work as Work progresses. H. On completion of foundation walls and major site improvements, prepare certified survey illustrating dimensions, locations, angles, and elevations of construction and site work. I. Protect survey control points prior to starting site work; preserve permanent reference points during construction. J. Promptly report to Architect/Engineer loss or destruction of reference point or relocation required because of changes in grades or other reasons. K. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Architect/Engineer. PRECONSTRUCTION MEETING A. Architect will schedule meeting after Notice of Award. Administrative Requirements 01300 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.5 B. Attendance Required: Owner, Architect, Engineer, and Contractor. C. Agenda: 1. Execution of Owner-Contractor Agreement. 2. Submission of executed bonds and insurance certificates. 3. Distribution of Contract Documents. 4. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule. 5. Designation of personnel representing parties in Contract, and Architect/Engineer. 6. Procedures and processing of field decisions, submittals, and substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures. 7. Scheduling. D. Record minutes and distribute copies within two days after meeting to participants, with one copy to Architect, Engineers, Owner, and those affected by decisions made. SITE MOBILIZATION MEETING A. Architect/ Owner will schedule meeting at Project site prior to Contractor occupancy. B. Attendance Required: Owner, Architect Special Consultants, and, Contractor, Contractor's Superintendent, and major Subcontractors. C. Agenda: 1. Use of premises by Owner and Contractor. 2. Owner's requirements and partial occupancy. 3. Construction facilities and controls provided by Owner. 4. Temporary utilities provided by Owner. 5. Survey and building layout. 6. Security and housekeeping procedures. 7. Schedules. 8. Application for payment procedures. 9. Procedures for testing. 10. Procedures for maintaining record documents. 11. Requirements for start-up of equipment. 12. Inspection and acceptance of equipment put into service during construction period. D. Record minutes and distribute copies within two days after meeting to participants, with one copies to Architect, Engineers, Owner, and those affected by decisions made. Administrative Requirements 01300 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.6 1.7 PROGRESS MEETINGS A. Schedule and administer meetings throughout progress of the Work at maximum bi-monthly intervals. B. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings. C. Attendance Required: Job superintendent, major subcontractors and suppliers, Owner, Architect, as appropriate to agenda topics for each meeting. D. Agenda: 1. Review minutes of previous meetings. 2. Review of Work progress. 3. Field observations, problems, and decisions. 4. Identification of problems impeding planned progress. 5. Review of submittals schedule and status of submittals. 6. Review of off-site fabrication and delivery schedules. 7. Maintenance of progress schedule. 8. Corrective measures to regain projected schedules. 9. Planned progress during succeeding work period. 10. Coordination of projected progress. 11. Maintenance of quality and work standards. 12. Effect of proposed changes on progress schedule and coordination. 13. Other business relating to Work. E. Record minutes and distribute copies within two days after meeting to participants, with one copies to Architect, Engineers, Owner, and those affected by decisions made. PRE-INSTALLATION MEETINGS A. When required in individual specification sections, convene pre-installation meetings at Project site prior to commencing work of specific section. B. Require attendance of parties directly affecting, or affected by, Work of specific section. C. Notify Architect/Engineer four days in advance of meeting date. D. Prepare agenda and preside at meeting: 1. Review conditions of installation, preparation and installation procedures. 2. Review coordination with related work. E. Record minutes and distribute copies within two days after meeting to participants, with one copies to Architect, Engineer, Owner, and those affected by decisions made. Administrative Requirements 01300 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 PART 2 PRODUCTS Not Used. PART 3 EXECUTION 3.1 CUTTING AND PATCHING A. Employ skilled and experienced installer to perform cutting and patching. B. Submit written request in advance of cutting or altering elements affecting: 1. Structural integrity of element. 2. Integrity of weather-exposed or moisture-resistant elements. 3. Efficiency, maintenance, or safety of element. 4. Visual qualities of sight exposed elements. 5. Work of Owner or separate contractor. C. Execute cutting, fitting, and patching including excavation and fill, to complete Work, and to: 1. Fit the several parts together, to integrate with other Work. 2. Uncover Work to install or correct ill-timed Work. 3. Remove and replace defective and non-conforming Work. 4. Remove samples of installed Work for testing. 5. Provide openings in elements of Work for penetrations of mechanical and electrical Work. D. Execute work by methods to avoid damage to other Work, and to provide proper surfaces to receive patching and finishing. E. Cut masonry and concrete materials using masonry saw or core drill. F. Restore Work with new products in accordance with requirements of Contract Documents. G. Fit Work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces. H. Maintain integrity of wall, ceiling, or floor construction; completely seal voids. I. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material, to full thickness of penetrated element. J. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit. Administrative Requirements 01300 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 K. 3.2 Identify hazardous substances or conditions exposed during the Work to Architect/Engineer for decision or remedy. SPECIAL PROCEDURES A. Remove debris and abandoned items from area and from concealed spaces. B. Prepare surface and remove surface finishes to permit installation of new work and finishes. C. Close openings in exterior surfaces to protect existing work from weather and extremes of temperature and humidity. D. Remove, cut, and patch Work in manner to minimize damage and to permit restoring products and finishes to original or specified condition. E. Refinish existing visible surfaces to remain in renovated rooms and spaces, to renewed condition for each material, with neat transition to adjacent finishes. F. When finished surfaces are cut so that smooth transition with new Work is not possible, terminate existing surface along straight line at natural line of division and submit recommendation to Architect/Engineer for review. G. Where change of plane of 1/4 inch or more occurs, submit recommendation for providing smooth transition; to Architect/Engineer for review. H. Finish surfaces as specified in individual product sections. END OF SECTION Administrative Requirements 01300 - 6 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01330 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 1.2 SECTION INCLUDES A. Submittal procedures. B. Construction progress schedules. C. Proposed products list. D. Product data. E. Shop drawings. F. Samples. G. Design data. H. Test reports. I. Certificates. J. Manufacturer's instructions. K. Manufacturer's field reports. L. Erection drawings. M. Construction photographs. SUBMITTAL PROCEDURES A. Transmit each submittal with Architect/Engineer accepted form. B. Sequentially number transmittal forms. Mark revised submittals with original number and sequential alphabetic suffix. C. Identify Project, Contractor, subcontractor and supplier; pertinent drawing and detail number, and specification section number, appropriate to submittal. D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, Submittal Procedures 01330 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 and coordination of information is in accordance with requirements of the Work and Contract Documents. 1.3 E. Schedule submittals to expedite Project, and deliver to Architectural Studio 3C, LLC, 200 Clearview Ave, Harwinton, CT 06791. Coordinate submission of related items. F. For each submittal for review, allow 15days excluding delivery time to and from Contractor. G. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of completed Work. H. Allow space on submittals for Contractor and Architect/Engineer review stamps. I. When revised for resubmission, identify changes made since previous submission. J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements. K. Submittals not requested will not be recognized or processed. CONSTRUCTION PROGRESS SCHEDULES A. Submit preliminary outline Schedules within 15 days after date of OwnerContractor Agreement for coordination with Owner's requirements. After review, submit detailed schedules within 10 days modified to accommodate revisions recommended by Architect. B. Submit revised Progress Schedules with each Application for Payment. C. Distribute copies of reviewed schedules to Project site file, subcontractors, suppliers, and other concerned parties. D. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules. E. Submit computer generated horizontal bar chart with separate line for each major portion of Work or operation, identifying first work day of each week. F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate early and late start, early and late finish, float dates, and duration. G. Indicate estimated percentage of completion for each item of Work at each submission. Submittal Procedures 01330 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.4 1.5 H. Submit separate schedule of submittal dates for shop drawings, product data, and samples, including Owner furnished products, and dates reviewed submittals will be required from Architect/Engineer. Indicate decision dates for selection of finishes. I. Indicate delivery dates for Owner furnished products. J. Revisions To Schedules: 1. Indicate progress of each activity to date of submittal, and projected completion date of each activity. 2. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes. 3. Prepare narrative report to define problem areas, anticipated delays, and impact on Schedule. Report corrective action taken, or proposed, and its effect. PROPOSED PRODUCTS LIST A. Within 15 days after date of Owner-Contractor Agreement, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product. B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards. PRODUCT DATA A. Product Data: Submit to Architect/Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents. B. Submit number of copies Contractor requires, plus two copies Architect will retain. C. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project. D. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances. E. After review, produce copies and distribute in accordance with SUBMITTAL PROCEDURES article and for record documents described in Section 01700. Submittal Procedures 01330 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.6 1.7 SHOP DRAWINGS A. Shop Drawings: Submit to Architect/Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents. B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances. C. Submit number of opaque reproductions Contractor requires, plus two copies Architect/Engineer will retain. D. After review, produce copies and distribute in accordance with SUBMITTAL PROCEDURES article and for record documents described in Section 01700. SAMPLES A. Samples: Submit to Architect/Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents. B. Samples For Selection as Specified in Product Sections: 1. Submit to Architect/Engineer for aesthetic, color, or finish selection. 2. Submit samples of finishes from full range of manufacturers' standard colors, textures, and patterns for Architect/Engineer selection. C. Submit samples to illustrate functional and aesthetic characteristics of Products, with integral parts and attachment devices. Coordinate sample submittals for interfacing work. D. Include identification on each sample, with full Project information. E. Submit number of samples specified in individual specification sections; Architect/Engineer will retain one sample. F. Reviewed samples which may be used in the Work are indicated in individual specification sections. G. Samples will not be used for testing purposes unless specifically stated in specification section. H. After review, produce duplicates and distribute in accordance with SUBMITTAL PROCEDURES article and for record documents purposes described in Section 01700. Submittal Procedures 01330 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.8 1.9 1.10 1.11 1.12 DESIGN DATA A. Submit for Architect/Engineer's knowledge as contract administrator or for Owner. B. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents. TEST REPORTS A. Submit for Architect/Engineer's knowledge as contract administrator or for Owner. B. Submit test reports for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents. CERTIFICATES A. When specified in individual specification sections, submit certification by manufacturer, installation/application subcontractor, or Contractor to Architect/Engineer, in quantities specified for Product Data. B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate. C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Architect/Engineer. MANUFACTURER'S INSTRUCTIONS A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Architect/Engineer for delivery to Owner in quantities specified for Product Data. B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation. MANUFACTURER'S FIELD REPORTS A. Submit reports for Architect/Engineer's benefit as contract administrator or for Owner. B. Submit report in duplicate within 30 days of observation to Architect/Engineer for information. C. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents. Submittal Procedures 01330 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.13 ERECTION DRAWINGS A. Submit drawings for Architect/Engineer's benefit as contract administrator or for Owner. B. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents. C. Data indicating inappropriate or unacceptable Work may be subject to action by Architect/Engineer or Owner. PART 2 PRODUCTS Not Used. PART 3 EXECUTION Not Used. END OF SECTION Submittal Procedures 01330 - 6 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01400 QUALITY REQUIREMENTS PART 1 GENERAL 1.1 1.2 SECTION INCLUDES A. Quality control and control of installation. B. Tolerances C. References. D. Mock-up requirements. E. Testing and inspection services. F. Manufacturers' field services. G. Examination. H. Preparation. QUALITY CONTROL AND CONTROL OF INSTALLATION A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality. B. Comply with manufacturers' instructions, including each step in sequence. C. When manufacturers' instructions conflict with Contract Documents, request clarification from Architect before proceeding. D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship. E. Perform Work by persons qualified to produce required and specified quality. F. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer. G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement. Quality Requirements 01400 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.3 1.4 1.5 1.6 TOLERANCES A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate. B. Comply with manufacturers' tolerances. When manufacturers' tolerances conflict with Contract Documents, request clarification from Architect before proceeding. C. Adjust products to appropriate dimensions; position before securing products in place. REFERENCES A. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of standard, except when more rigid requirements are specified or are required by applicable codes. B. Conform to reference standard by date of issue current on date of Contract Documents, except where specific date is established by code. C. Obtain copies of standards where required by product specification sections. D. When specified reference standards conflict with Contract Documents, request clarification from Architect before proceeding. E. Neither contractual relationships, duties, nor responsibilities of parties in Contract nor those of Architect/Engineer shall be altered from Contract Documents by mention or inference otherwise in reference documents. MOCK-UP REQUIREMENTS A. Tests will be performed under provisions identified in this section and identified in respective product specification sections. B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes. C. Accepted mock-ups shall be comparison standard for remaining Work. D. Where mock-up has been accepted by Architect/Engineer and is specified in product specification sections to be removed; remove mock-up and clear area when directed to do so by Architect/Engineer. TESTING AND INSPECTION SERVICES A. Owner will employ services of an independent firm to perform testing and inspection. Quality Requirements 01400 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 B. The independent firm will perform tests, inspections and other services specified in individual specification sections and as required by Architect/Engineer. 1. Laboratory: Authorized to operate in State of Connecticut. 2. Laboratory Staff: Maintain full time registered Engineer on staff to review services. 3. Testing Equipment: Calibrated at reasonable intervals with devices of an accuracy traceable to National Bureau of Standards or accepted values of natural physical constants. C. Testing, inspections and source quality control may occur on or off project site. Perform off-site testing as required by Architect/Engineer or Owner. D. Reports will be submitted by independent firm to Architect, Engineer, and Contractor, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents. E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested. 1. Notify Independent firm 24 hours prior to expected time for operations requiring services. 2. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use. F. Testing and employment of testing agency or laboratory shall not relieve Contractor of obligation to perform Work in accordance with requirements of Contract Documents. G. Re-testing or re-inspection required because of non-conformance to specified requirements shall be performed by same independent firm on instructions by Architect. Payment for re-testing or re-inspection will be charged to Contractor by deducting testing charges from Contract Sum. H. Agency Responsibilities: 1. Test samples of mixes submitted by Contractor. 2. Provide qualified personnel at site. Cooperate with Architect, Engineer, and Contractor in performance of services. 3. Perform specified sampling and testing of products in accordance with specified standards. 4. Ascertain compliance of materials and mixes with requirements of Contract Documents. 5. Promptly notify Architect/Engineer and Contractor of observed irregularities or non-conformance of Work or products. 6. Perform additional tests required by Architect/Engineer. 7. Attend preconstruction meetings and progress meetings. Quality Requirements 01400 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.7 I. Agency Reports: After each test, promptly submit two copies of report to Architect, Engineer, and Contractor. When requested by Architect, provide interpretation of test results. Include the following: 1. Date issued. 2. Project title and number. 3. Name of inspector. 4. Date and time of sampling or inspection. 5. Identification of product and specifications section. 6. Location in Project. 7. Type of inspection or test. 8. Date of test. 9. Results of tests. 10. Conformance with Contract Documents. J. Limits On Testing Authority: 1. Agency or laboratory may not release, revoke, alter, or enlarge on requirements of Contract Documents. 2. Agency or laboratory may not approve or accept any portion of the Work. 3. Agency or laboratory may not assume duties of Contractor. 4. Agency or laboratory has no authority to stop the Work. MANUFACTURERS' FIELD SERVICES A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, startup of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary. B. Submit qualifications of observer to Architect 30 days in advance of required observations. [Observer subject to approval of [Architect. C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions. D. Refer to Section 01330 - SUBMITTAL PROCEDURES, MANUFACTURERS' FIELD REPORTS article. PART 2 PRODUCTS Not Used. Quality Requirements 01400 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 PART 3 EXECUTION 3.1 3.2 EXAMINATION A. Verify existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions. B. Verify existing substrate is capable of structural support or attachment of new Work being applied or attached. C. Examine and verify specific conditions described in individual specification sections. D. Verify utility services are available, of correct characteristics, and in correct locations. PREPARATION A. Clean substrate surfaces prior to applying next material or substance. B. Seal cracks or openings of substrate prior to applying next material or substance. C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond. END OF SECTION Quality Requirements 01400 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01500 TEMPORARY FACILITIES AND CONTROLS PART 1 GENERAL 1.1 SECTION INCLUDES A. Temporary Utilities: 1. Temporary electricity. 2. Temporary lighting for construction purposes. 3. Temporary heating. 4. Temporary cooling. 5. Temporary ventilation. 6. Telephone service. 7. Facsimile service. 8. Temporary water service. 9. Temporary sanitary facilities. B. Construction Facilities: 1. Field offices and sheds. 2. Vehicular access. 3. Parking. 4. Progress cleaning and waste removal. 5. Project identification. 6. Traffic regulation. C. Temporary Controls: 1. Barriers. 2. Enclosures and fencing. 3. Security. 4. Water control. 5. Dust control. 6. Erosion and sediment control. 7. Noise control. 8. Pest control. 9. Pollution control. 10. Rodent control. D. Removal of utilities, facilities, and controls. Temporary Facilities and Controls 01500 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.2 1.3 1.4 TEMPORARY ELECTRICITY A. Provide temporary electrical service, and meter. Include the cost of energy used in contract. B. Complement existing power service capacity and characteristics as required for construction operations. C. Provide power outlets, with branch wiring and distribution boxes located as required for construction operations. Provide flexible power cords as required for portable construction tools and equipment. D. Provide main service disconnect and over-current protection at convenient location feeder switch at source distribution equipment and meter. E. Permanent convenience receptacles may not be utilized during construction. TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES A. Provide and maintain incandescent lighting for construction operations to achieve minimum lighting level of 2 watt/sq ft. B. Provide and maintain 1 watt/sq ft lighting to exterior staging and storage areas after dark for security purposes. C. Provide and maintain 0.25 watt/sq ft HID lighting to interior work areas after dark for security purposes. D. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps for specified lighting levels. E. Maintain lighting and provide routine repairs. F. Permanent building lighting may not be utilized during construction. TEMPORARY HEATING A. Provide and pay for heating devices and heat as needed to maintain specified conditions for construction operations. Prior to operation of permanent equipment for temporary heating purposes, verify installation is approved for operation, equipment is lubricated and filters are in place. Provide and pay for operation, maintenance, and regular replacement of filters and worn or consumed parts. B. Maintain minimum ambient temperature of 50 degrees F in areas where construction is in progress, unless indicated otherwise in product sections. Temporary Facilities and Controls 01500 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.5 TEMPORARY VENTILATION A. 1.6 TELEPHONE SERVICE A. 1.7 1.9 Provide, maintain and pay for facsimile service and dedicated telephone line to field office at time of project mobilization. TEMPORARY WATER SERVICE A. Owner will pay cost of temporary water. Exercise measures to conserve energy. Utilize Owner's existing water system, extend and supplement with temporary devices as needed to maintain specified conditions for construction operations. B. Extend branch piping with outlets located so water is available by hoses with threaded connections. Provide temporary pipe insulation to prevent freezing. TEMPORARY SANITARY FACILITIES A. 1.10 Provide, maintain, and pay for telephone service to field office at time of project mobilization. FACSIMILE SERVICE A. 1.8 Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases. Provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of project mobilization. FIELD OFFICES AND SHEDS A. Office: Weather tight, with lighting, electrical outlets, heating, cooling and ventilating equipment, and equipped with sturdy furniture drawing rack, and drawing display table. B. Provide space for Project meetings, with table and chairs to accommodate 6 persons. C. Locate offices and sheds minimum distance of 30 feet from existing and new structures. D. Do not use permanent facilities for field offices or for storage. E. Construction: Portable or mobile buildings, or buildings constructed with floors raised above ground, securely fixed to foundations with steps and landings at entrance doors. Temporary Facilities and Controls 01500 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1. 2. 3. 4. 5. 6. 7. Construction: Structurally sound, secure, weather tight enclosures for office and storage spaces. Maintain during progress of Work; remove at completion of Work. Temperature Transmission Resistance of Floors, Walls, and Ceilings: Compatible with occupancy and storage requirements. Exterior Materials: Weather resistant, finished in one color acceptable to Architect/Engineer.] Interior Materials in Offices: Sheet type materials for walls and ceilings, pre-finished or painted; resilient floors and bases. Lighting for Offices: 50 ft C at desk top height, exterior lighting at entrance doors. Fire Extinguishers: Appropriate type fire extinguisher at each office and each storage area. Interior Materials in Storage Sheds: As required to provide specified conditions for storage of products. F. Environmental Control: 1. Heating, Cooling, and Ventilating for Offices: Automatic equipment to maintain comfort conditions 2. Storage Spaces: Heating and ventilation as needed to maintain products in accordance with Contract Documents; lighting for maintenance and inspection of products. G. Storage Areas And Sheds: Size to storage requirements for products of individual Sections, allowing for access and orderly provision for maintenance and for inspection of products to requirements of Section 01600. H. Preparation: Fill and grade sites for temporary structures sloped for drainage away from buildings. I. Installation: 1. Install office spaces ready for occupancy 15 days after date fixed in Owner-Contractor Agreement. 2. Parking: Two hard surfaced parking spaces for use by Owner and Architect connected to office by hard surfaced walk. 3. Employee Residential Occupancy: Not allowed on Owner's property. J. Maintenance And Cleaning: 1. Weekly janitorial services for offices; periodic cleaning and maintenance for office and storage areas. 2. Maintain approach walks free of mud, water, and snow. K. Removal: At completion of Work remove buildings, foundations, utility services, and debris. Restore areas. Temporary Facilities and Controls 01500 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.11 1.12 VEHICULAR ACCESS A. Construct temporary all-weather access roads from public thoroughfares to serve construction area, of width and load bearing capacity to accommodate unimpeded traffic for construction purposes. B. Extend and relocate vehicular access as Work progress requires, provide detours as necessary for unimpeded traffic flow. C. Location as approved by Owner. D. Provide unimpeded access for emergency vehicles. Maintain 20 feet wide driveways with turning space between and around combustible materials. E. Provide means of removing mud from vehicle wheels before entering streets. F. Use existing on-site roads for construction traffic. PARKING A. Provide for parking areas to accommodate construction personnel. B. Locate as approved by Owner. C. Permanent Pavements And Parking Facilities: 1. Bases for permanent roads and parking areas may be used for construction traffic. 2. Avoid traffic loading beyond paving design capacity. Tracked vehicles not allowed. D. Maintenance: 1. Maintain traffic and parking areas in sound condition free of excavated material, construction equipment, products, mud, snow, and ice. 2. Maintain existing and permanent paved areas used for construction; promptly repair breaks, potholes, low areas, standing water, and other deficiencies, to maintain paving and drainage in original, or specified, condition. E. Removal, Repair: 1. Remove temporary materials and construction when permanent paving is usable. 2. Remove underground work and compacted materials to depth of 2 feet; fill and grade site as specified. 3. Repair permanent facilities damaged by use, to original condition. F. Mud From Site Vehicles: Provide means of removing mud from vehicle wheels before entering streets. Temporary Facilities and Controls 01500 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.13 1.14 PROGRESS CLEANING AND WASTE REMOVAL A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition. B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing spaces. C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust. D. Collect and remove waste materials, debris, and rubbish from site periodically and dispose off-site. E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids. PROJECT IDENTIFICATION A. Project Identification Sign: 1. See document 01501 for sign specifications and requirements per State of CT DECD. 2. Additional requirements: a. Design sign and structure to withstand 60 miles/hr wind velocity. b. Finishes, Painting: Adequate to withstand weathering, fading, and chipping for duration of construction. c. Sign Materials: 1) Structure and Framing: New wood, structurally adequate. 2) Sign Surfaces: Exterior grade plywood with medium density overlay, minimum 3/4 inches thick, standard large sizes to minimize joints. 3) Rough Hardware: Galvanized. 4) Paint and Primers: Exterior quality, two coats; sign background of as selected. d. Installation: 1) Install project identification sign upon beginning of construction. 2) Erect at designated location. 3) Erect supports and framing on secure foundation, rigidly braced and framed to resist wind loadings. 4) Install sign surface plumb and level, with butt joints. Anchor securely. Temporary Facilities and Controls 01500 - 6 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 5) 1.15 1.16 Paint exposed surfaces of sign, supports, and framing. e. Maintenance: Maintain signs and supports clean, repair deterioration and damage. f. Removal: Remove signs, framing, supports, and foundations at completion of Project and restore area. TRAFFIC REGULATION A. Signs, Signals, And Devices: 1. Post Mounted and Wall Mounted Traffic Control and Informational Signs: As approved by authority having jurisdiction. 2. Traffic Cones and Drums, Flares and Lights: As approved by authority having jurisdiction. 3. Flag person Equipment: As required by authority having jurisdiction. B. Flag Persons: Provide trained and equipped flag persons to regulate traffic when construction operations or traffic encroach on public traffic lanes. C. Flares and Lights: Use flares and lights during hours of low visibility to delineate traffic lanes and to guide traffic. D. Haul Routes: 1. Consult with authority having jurisdiction, establish public thoroughfares to be used for haul routes and site access. E. Traffic Signs And Signals: 1. Provide signs at approaches to site and on site, at crossroads, detours, parking areas, and elsewhere as needed to direct construction and affected public traffic. 2. Relocate as Work progresses, to maintain effective traffic control. F. Removal: 1. Remove equipment and devices when no longer required. 2. Repair damage caused by installation. 3. Remove post settings to depth of 2 feet. BARRIERS A. Provide barriers to prevent unauthorized entry to construction areas and to adjacent properties from damage from construction operations. B. Provide barricades and covered walkways required by authorities having jurisdiction for public rights-of-way. C. Provide protection for plants to remain. Replace damaged plants. Temporary Facilities and Controls 01500 - 7 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 D. 1.17 1.18 1.19 1.20 Protect non-owned vehicular traffic, stored materials, site, and structures from damage. ENCLOSURES AND FENCING A. Construction: Commercial grade chain link fence. B. Provide 6 feet high fence around construction site; equip with vehicular and pedestrian gates with locks. C. Exterior Enclosures: 1. Provide temporary [insulated] weather tight closure of exterior openings to accommodate acceptable working conditions and protection for products, to allow for temporary heating and maintenance of required ambient temperatures identified in individual specification sections, and to prevent entry of unauthorized persons. Provide access doors with self-closing hardware and locks. SECURITY A. Security Program: 1. Protect Work from theft, vandalism, and unauthorized entry. 2. Initiate program in coordination with Owner at project mobilization. 3. Maintain program throughout construction period until Owner occupancy. B. Entry Control: 1. Restrict entrance of persons and vehicles into Project site 2. Allow entrance only to authorized persons. 3. Maintain log of workers and visitors, make available to Owner on request. 4. Coordinate access of Owner's personnel to site in coordination with Owner. C. Restrictions: 1. Do no work on Sundays. WATER CONTROL A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment. B. Protect site from puddling or running water. Provide water barriers as required to protect site from soil erosion. DUST CONTROL A. Execute Work by methods to minimize raising dust from construction operations. Temporary Facilities and Controls 01500 - 8 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 B. 1.21 Provide positive means to prevent air-borne dust from dispersing into atmosphere. EROSION AND SEDIMENT CONTROL A. Plan and execute construction by methods to control surface drainage from cuts and fills, from borrow and waste disposal areas. Prevent erosion and sedimentation. B. Minimize surface area of bare soil exposed at one time. C. Provide temporary measures including berms, dikes, and drains, and other devices to prevent water flow. D. Construct fill and waste areas by selective placement to avoid erosive surface silts or clays. E. Periodically inspect earthwork to detect evidence of erosion and sedimentation; promptly apply corrective measures. 1.22 POLLUTION CONTROL 1.23 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial Completion inspection. B. Remove underground installations to minimum depth of 2 feet. Grade site as indicated on Drawings. C. Clean and repair damage caused by installation or use of temporary work. D. Restore existing and permanent facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition. PART 2 PRODUCTS Not Used. PART 3 EXECUTION Not Used. END OF SECTION Temporary Facilities and Controls 01500 - 9 DEPARTMENT OF ECONOMIC AND COMMUNITY DEVELOPMENT PROJECT SIGN – ECONOMIC & COMMUNITY DEVELOPMENT 8’-0” NAME OF THE PROJECT NAME OF THE SPONSOR/DEVELOPER 4’-0” Constructed in cooperation with the STATE OF CONNECTICUT DANNEL P. MALLOY, GOVERNOR Department of Economic and Community Development Catherine Smith, Commissioner and the Name of Town/City Name of Chief Elected Official and title Name of Architect Name of General Contractor SIGN PANEL: ¾” MDO-EXT-APA PLYWOOD SUPPORTED WITH (2) 4X4 TREATED WOOD COLUMNS AND SECURED 4’ INTO GRADE. TOP OF SIGN AT 8’-0” ABOVE GRADE. COLORS: ALL LETTERS AND SYMBOLS ARE TO BE ROYAL BLUE. THE BACKGROUND WILL BE WHITE ENAMEL. BACK OF PLYWOOD AND SUPPORT STRUCTURE SHALL BE PAINTED MATTE BLACK. TYPEFACE: HELVETICA MEDIUM LOCATION: SIGN MUST BE LOCATED TO BE CLEARLY VISIBLE TO THE PUBLIC. TIMING: INSTALL AT THE START OF CONSTRUCTION AND REMOVE AT CONSTRUCTION COMPLETION. STATE SEAL & DECD LOGO: ATTACHED 01501 Project Signage Specifications STATE SEAL DECD LOGO 01501 Project Signage Specifications Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01600 PRODUCT REQUIREMENTS PART 1 GENERAL 1.1 1.2 1.3 1.4 SECTION INCLUDES A. Products. B. Product delivery requirements. C. Product storage and handling requirements. D. Product options. E. Product substitution procedures. F. Equipment electrical characteristics and components. PRODUCTS A. Furnish products of qualified manufacturers suitable for intended use. Furnish products of each type by single manufacturer unless specified otherwise. B. Do not use materials and equipment removed from existing premises, except as specifically permitted by Contract Documents. C. Furnish interchangeable components from same manufacturer for components being replaced. PRODUCT DELIVERY REQUIREMENTS A. Transport and handle products in accordance with manufacturer's instructions. B. Promptly inspect shipments to ensure products comply with requirements, quantities are correct, and products are undamaged. C. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage. PRODUCT STORAGE AND HANDLING REQUIREMENTS A. Store and protect products in accordance with manufacturers' instructions. B. Store with seals and labels intact and legible. Product Requirements 01600 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.5 1.6 C. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to product. D. For exterior storage of fabricated products, place on sloped supports above ground. E. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products. F. Store loose granular materials on solid flat surfaces in well-drained area. Prevent mixing with foreign matter. G. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage. H. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition. PRODUCT OPTIONS A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description. B. Products Specified by Naming One or More Manufacturers with Provision for Substitutions: Submit request for substitution for any manufacturer not named in accordance with the following article. PRODUCT SUBSTITUTION PROCEDURES A. Architect/Engineer will consider requests for Substitutions only within 30 days after date of Owner-Contractor Agreement. B. Substitutions may be considered when a product becomes unavailable through no fault of Contractor. C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents. D. A request constitutes a representation that Contractor: 1. Has investigated proposed product and determined that it meets or exceeds quality level of specified product. 2. Will provide same warranty for Substitution as for specified product. 3. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner. 4. Waives claims for additional costs or time extension which may subsequently become apparent. Product Requirements 01600 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 5. Will reimburse Owner and Architect for review or redesign services associated with re-approval by authorities having jurisdiction. E. Substitutions will not be considered when they are indicated or implied on Shop Drawing or Product Data submittals, without separate written request, or when acceptance will require revision to Contract Documents. F. Substitution Submittal Procedure: 1. Submit three copies of request for Substitution for consideration. Limit each request to one proposed Substitution. 2. Submit Shop Drawings, Product Data, and certified test results attesting to proposed product equivalence. Burden of proof is on proposer. 3. Architect will notify Contractor in writing of decision to accept or reject request. PART 2 PRODUCTS 2.1 EQUIPMENT ELECTRICAL CHARACTERISTICS AND COMPONENTS A. Wiring Terminations: Furnish terminal lugs to match branch circuit conductor quantities, sizes, and materials indicated. Include lugs for terminal box. B. Cord and Plug: Furnish minimum 6 foot cord and plug including grounding connector for connection to electric wiring system. Cord of longer length is specified in individual specification sections. PART 3 EXECUTION Not Used. END OF SECTION Product Requirements 01600 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 SECTION 01700 EXECUTION REQUIREMENTS PART 1 GENERAL 1.1 1.2 SECTION INCLUDES A. Closeout procedures. B. Final cleaning. C. Starting of systems. D. Demonstration and instructions. E. Testing, adjusting and balancing. F. Protecting installed construction. G. Project record documents. H. Operation and maintenance data. I. Manual for materials and finishes. J. Manual for equipment and systems. K. Spare parts and maintenance products. L. Product warranties and product bonds. M. Maintenance service. CLOSEOUT PROCEDURES A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Architect’s review. B. Provide submittals to Owner required by authorities having jurisdiction. C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due. Execution Requirements 01700 - 1 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.3 1.4 1.5 FINAL CLEANING A. Execute final cleaning prior to final project assessment. B. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces. C. Clean equipment and fixtures to sanitary condition with cleaning materials appropriate to surface and material being cleaned. D. Replace filters of operating equipment. E. Clean debris from roofs, gutters, downspouts, and drainage systems. F. Clean site; sweep paved areas, rake clean landscaped surfaces. G. Remove waste and surplus materials, rubbish, and construction facilities from site. STARTING OF SYSTEMS A. Coordinate schedule for start-up of various equipment and systems. B. Notify Architect seven days prior to start-up of each item. C. Verify each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage. D. Verify tests, meter readings, and specified electrical characteristics agree with those required by equipment or system manufacturer. E. Verify wiring and support components for equipment are complete and tested. F. Execute start-up under supervision of applicable Contractors' personnel in accordance with manufacturers' instructions. Submit a written report in accordance with Section 01330 that equipment or system has been properly installed and is functioning correctly. DEMONSTRATION AND INSTRUCTIONS A. Demonstrate operation and maintenance of products to Owner's personnel two weeks prior to date of Substantial Completion. Execution Requirements 01700 - 2 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.6 1.7 B. Demonstrate Project equipment and instructed by qualified manufacturer's representative who is knowledgeable about the Project. C. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months. D. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance. E. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at agreed time, at equipment location. F. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction. G. Required instruction time for each item of equipment and system is specified in individual sections. TESTING, ADJUSTING AND BALANCING A. Owner will appoint and employ services of independent firm to perform testing, adjusting, and balancing. B. Independent firm will perform services specified in Section 15950. C. Reports will be submitted by independent firm to Architect indicating observations and results of tests and indicating compliance or noncompliance with requirements of Contract Documents. PROTECTING INSTALLED CONSTRUCTION A. Protect installed Work and provide special protection where specified in individual specification sections. B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage. C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings. D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials. Execution Requirements 01700 - 3 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.8 E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer. F. Prohibit traffic from landscaped areas. PROJECT RECORD DOCUMENTS A. 1. 2. 3. 4. 5. 6. Maintain on site one set of the following record documents; record actual revisions to the Work: Drawings. Specifications. Addenda. Change Orders and other modifications to the Contract. Reviewed Shop Drawings, Product Data, and Samples. Manufacturer's instruction for assembly, installation, and adjusting. B. Ensure entries are complete and accurate, enabling future reference by Owner. C. Store record construction. D. Record information concurrent with construction progress, not less than weekly. E. Specifications: Legibly mark and record at each product section description of actual products installed, including the following: Manufacturer's name and product model and number. Product substitutions or alternates utilized. Changes made by Addenda and modifications. 1. 2. 3. F. 1. 2. 3. 4. 5. G. documents separate from documents used for Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including: Measured depths of foundations in relation to finish main floor datum. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work. Field changes of dimension and detail. Details not on original Contract drawings. Submit documents to Architect with claim for final Application for Payment. Execution Requirements 01700 - 4 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.9 OPERATION AND MAINTENANCE DATA A. Submit data bound in 8-1/2 x 11 inch (A4) text pages, three D side ring binders with durable plastic covers. B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required. C. Internally subdivide binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs. D. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages. E. Contents: Prepare Table of Contents for each volume, with each product or system description identified, typed on white paper, in three parts as follows: Part 1: Directory, listing names, addresses, and telephone numbers of Architect/Engineer, Contractor, Subcontractors, and major equipment suppliers. Part 2: Operation and maintenance instructions, arranged by system and subdivided by specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following: a. Significant design criteria. b. List of equipment. c. Parts list for each component. d. Operating instructions. e. Maintenance instructions for equipment and systems. f. Maintenance instructions for special finishes, including recommended cleaning methods and materials, and special precautions identifying detrimental agents. Part 3: Project documents and certificates, including the following: a. Shop drawings and product data. b. Air and water balance reports. c. Certificates. d. Originals of warranties and bonds. 1. 2. 3. 1.10 MANUAL FOR MATERIALS AND FINISHES A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Architect/Engineer will review draft and return one copy with comments. Execution Requirements 01700 - 5 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.11 B. For equipment, or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance. C. Submit one copy of completed volumes 15 days prior to final inspection. Draft copy be reviewed and returned after final inspection, with Architect/Engineer comments. Revise content of document sets as required prior to final submission. D. Submit two sets of revised final volumes in final form within 10 days after final inspection. E. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Include information for re-ordering custom manufactured products. F. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance. G. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair. H. Additional Requirements: As specified in individual product specification sections. I. Include listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data. MANUAL FOR EQUIPMENT AND SYSTEMS A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Architect/Engineer will review draft and return one copy with comments. B. For equipment, or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance. C. Submit one copy of completed volumes 15 days prior to final inspection. Draft copy be reviewed and returned after final inspection, with Architect/Engineer comments. Revise content of document sets as required prior to final submission. Execution Requirements 01700 - 6 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 D. Submit two sets of revised final volumes in final form within 10 days after final inspection. E. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineering data and tests, and complete nomenclature and model number of replaceable parts. F. Panelboard Circuit Directories: Provide electrical service characteristics, controls, and communications; typed. G. Include color coded wiring diagrams as installed. H. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and special operating instructions. I. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and trouble shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions. J. Include servicing and lubrication schedule, and list of lubricants required. K. Include manufacturer's printed operation and maintenance instructions. L. Include sequence of operation by controls manufacturer. M. Include original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance. N. Include control diagrams by controls manufacturer as installed. O. Include Contractor's coordination drawings, with color coded piping diagrams as installed. P. Include charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams. Q. Include list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage. R. Include test and balancing reports as specified in Section 01400. Execution Requirements 01700 - 7 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 1.12 1.13 S. Additional Requirements: As specified in individual product specification sections. T. Include listing in Table of Contents for design data, with tabbed dividers and space for insertion of data. SPARE PARTS AND MAINTENANCE PRODUCTS A. Furnish spare parts, maintenance, and extra products in quantities specified in individual specification sections. B. Deliver to Project site; obtain receipt prior to final payment. PRODUCT WARRANTIES AND PRODUCT BONDS A. Obtain warranties and bonds executed in duplicate by responsible subcontractors, suppliers, and manufacturers, within ten days after completion of applicable item of work. B. Execute and assemble transferable warranty documents and bonds from subcontractors, suppliers, and manufacturers. C. Verify documents are in proper form, contain full information, and are notarized. D. Co-execute submittals when required. E. Include Table of Contents and assemble in three D side ring binder with durable plastic cover. F. Submit prior to final Application for Payment. G. 1. 2. 3. 1.14 Time Of Submittals: For equipment or component parts of equipment put into service during construction with Owner's permission, submit documents within ten days after acceptance. Make other submittals within ten days after Date of Substantial Completion, prior to final Application for Payment. For items of Work for which acceptance is delayed beyond Date of Substantial Completion, submit within ten days after acceptance, listing date of acceptance as beginning of warranty or bond period. MAINTENANCE SERVICE A. Furnish service and maintenance of components indicated in specification sections for 1 year from date of Substantial Completion. Execution Requirements 01700 - 8 Proposed Facility For HARWINTON AMBULANCE 166 Burlington Road Harwinton, CT 06791 B. Examine system components at frequency consistent with reliable operation. Clean, adjust, and lubricate as required. C. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by manufacturer of original component. D. Do not assign or transfer maintenance service to agent or Subcontractor without prior written consent of Owner. PART 2 PRODUCTS Not Used. PART 3 EXECUTION Not Used. END OF SECTION Execution Requirements 01700 - 9