Sarcelle powerhouse is taking shape - Hydro
Transcription
Sarcelle powerhouse is taking shape - Hydro
Volume 8, Issue 3, September 2010 Sarcelle powerhouse is taking shape Final sprint at Rupert Civil works are coming to an end at the Eastmain-1-A jobsite People with a powerful vision Every jobsite must come to an end! The Rupert diversion jobsite —I was there! MEM – Since 2002, thousands of people have worked on various aspects of the Rupert diversion project. By the end of 2010, everyone will have to say goodbye. This significant, inevitable step will be taken with pride! While hundreds of workers were still present at the workcamp, SEBJ organized activities to thank them and to highlight all the hard work that went into the project. Thanks to the cooperation of the Eastmain and Sarcelle jobsites, tours were organized in July and August for workers from Nemiscau workcamp. These workers really enjoyed discovering the other jobsites of the Eastmain1-A/Sarcelle/Rupert project in the company of friends and co-workers. Thank you to all participants, guides and organizers! The culmination of these Appreciation activities [activités Reconnaissance] was held on August 21. Site Manager, Gervais Savard, and Virgile Albert invited all employees and workers to a Rupert signature supper: pictures of the workers decorated the walls of the cafeteria, superb weir-shaped cakes were served and a video of progress at the jobsite from 2007 to 2010 was shown on a giant screen. The 2007–2009 souvenir album got a great reception, and the project’s colors were on display. An evening under the big tent followed, where laughter and memories joined to create memorable and touching moments! Cake representing the weir at KP 290 The imminent end of the project should be celebrated and shared—shared with the emotion, enthusiasm and respect that we developed while working to accomplish this unique project. Group from Nemiscau touring the Sarcelle jobsite The 200,000th passenger MV – On July 7, 2010, Air Creebec and SEBJ celebrated the 200,000th passenger to travel aboard Air Creebec as part of the Eastmain-1-A/Sarcelle/Rupert project. Mario Lavoie, laborer for contractor CRT-Hamel, received a watch from Connie Ragusa, an Air Creebec representative, and a laminated print from Denis Lalonde, representing SEBJ. Supervisor – Public Relations / Magazine Editor: Bionda Miotto / 819 672-2200, ext. 3854 miotto.bionda@hydro.qc.ca Advisor - Public Relations and Editor-in-Chief: Jimmy Lavoie / 819 865-2100 poste 4159, lavoie.jimmy@hydro.qc.ca Writers: Pascal Dion, Catherine Langlois, Marie-Ève Morin, Liza Perron, Mélanie Vachon Contributors: Claude Perron , Normand Faubert Translator: Margaret Kane Savage, Reviser: Isabel Fonte Graphics: Paul Salois Design / Photographer: Paul Brindamour / Printer: Imprimerie Lebonfon Eastmain Magazine is published by SEBJ Public Relations for the workers of the Eastmain-1-A/Sarcelle/Rupert project. Internet site: www.hydroquebec.com/rupert. Extranet site: www.extranetsebj.ca. (© SEBJ, All rights reserved) Eastmain Magazine is printed on chlorine- and acid-free EcoLogo certified paper, made in Québec, containing 100% post-consumer fibre, manufactured using biogas energy. 2 Eastmain Magazine, September 2010 People with a powerful vision LP – Concreting of the three sections of the Sarcelle powerhouse’s water intake began in April 2009 and will end this fall. It has required more than 10,900 cubic metres of concrete. One aspect of the special configuration of the intake’s openings is the shaping of the concrete above the gates. Two successive curves, known as lintels, will efficiently direct the flow to the generating units. Although concreting is progressing rapidly, work at the water intake is not over. The arrival of workers from company CIE Euler, assigned to install the stoplog slots and the trashrack slots, signals another step in the work on this section of the water intake. Lintels of unit 22 – Location of gate slots Upstream view – water intake Upstream view – Tower crane access road and track location Eastmain Magazine, September 2010 3 THE JOBSITE IN PICTURES Sarcelle jobsite Upstream sector Sarcelle jobsite Downstream sector MV – Diffuser construction is coming to an end. By midSeptember, more than 12,000 cubic metres of concrete will have been poured in this area. The process of installing the steel structure of the service bridge’s deck began with the concreting of nine columns. These nine columns, three per unit, will be equipped with anchors to secure the beams of the bridge slab. Downstream view – End of concrete work on diffusers Powerhouse switchyard The switchyard is bustling with activity. The six switchyard towers have been positioned on their bases. Around them, more than half of the insulators, circuit breakers and disconnect switches are in place. View of the switchyard Bases for setting up disconnect switches, circuit breakers and insulators 4 Eastmain Magazine, September 2010 People with a powerful vision THE JOBSITE IN PICTURES The two firewalls between the transformers have been completed, and the four columns supporting the wiring are 85% concreted. Construction of gravel-filled ditches for rainwater drainage, excavation of the fence site and formwork for the duct bank have begun. Meanwhile, installation of the grounding grid is continuing. The first sections LP – The first sections of the bulb turbine units arrived at Sarcelle powerhouse in June 2009. Last year, only the armoring of the three units’ draft tube cones had been installed. A section upstream of the armoring will complete that area this year. 2010 is going to be a much more eventful year. The arrival of the stay rings, stator casings, sealing rings and upstream covers by road contributed to the bustle of activity. At the jobsite, employees of contractor Alstom began installing the components of generating unit LS 23 in June. Stator casing Stay ring Viewed from the outside, this section is located between the stator casing and the sealing ring. Inside, it contains the combined bearing, which consists of the thrust bearing, counter-thrust bearing and generator guide bearing, and the shaft through its centre. Composed of four welded parts, the stay ring is anchored by concreting a portion of the vertical stay vanes extending from its top and bottom. In addition, two lateral stay vanes have been welded to the stay ring; they will be anchored in concrete to hold the generating unit in place from either side. On Sunday, June 27, three of the welded parts of the stay ring were installed in the powerhouse. This assembly, weighing just over 150 tonnes, was first placed at the bottom of unit 23 before taking its final, vertical position. It is kept upright by the lower stay vane, the lowest section of which will be concreted. The upper stay vane, attached to the fourth section, was welded in place on July 23. THE JOBSITE IN PICTURES Sarcelle jobsite BULB UNITS Unit 23’s stay ring and sealing ring 5 Eastmain Magazine, September 2010 Delivery of the rooms on level 220 to TransÉnergie BIG STEP FOR SARCELLE D’ÉTAPE EN ÉTAPE Architecture et travaux mécaniques / électriques Centrale de la Sarcelle 2010 D’ÉTAPE EN ÉTAPE Architecture et travaux mécaniques / électriques Centrale de la Sarcelle 2010 Abalin Stéphane - Achard Fabien - Arbour Yvon - Asselin Roberto - Auclair Vic - Audet Réal - Bastien Michel - Beaulieu Frédéric - Beaulieu Martin - Beauregard Lucien - Bédard Martin - Bergeron Jonathan - Bergeron François Bernier Dominic - Blackburn Martial - Blackburn Jean-Claude - Boily Marc - Boivin Yan - Bouchard Yanick - Bouchard Michael - Bouchard Michel - Bouffard Roger - Bourbeau Claude - Brisebois Jacques - Brisson Michel - Bronsard Simon - Carbonneau Guy - Carbonneau Yves - Caron Gilles - Charbonneau Gabriel - Cherrier Sébastien - Claveau Jerry - Côté Alexandre - Côté Éric - Couture Laurent - Dallaire Dominique - Delorme François - Demeules Mathieu Derome Mario - Desrosiers Raymond - Doyon Denis - Dubois Robin - Duchesne Daniel - Duchesne Dave - Duchesne Pascal - Dufour Bernard - Dufresne Jean-Guy - Duhamel Alexandre - Dupuis Gaétan - Fontaine Philippe - Fortin Maxime - Fortin André - Fortin Marc - Fortin Marius - Frappier Dominic - Gagné Serge - Gagnon Dominic - Gagnon Daniel - Gagnon Éric - Gagnon Michel - Gagnon Charles - Gaudet Ghislain - Gaudreau Marcel - Gaudreault Rémi Gaudreault Louis - Gauthier-Gaudreault Marc-André - Gingras Alain - Girard Jocelyne - Godin Réal - Gosselin Claude - Goudreault Dany - Grant Patrick - Gravel Martin - Gravel Patrick - Grenier Régent - Guérin Bernard - Lalande Jean-François - Landry Jasmin - Landry Yvon - Lapointe Bernard - Laprise Daniel - Larocque Guy - Larouche Jacky - Laurin Michel - Lavoie Gérald - Leclair Nicole - Leduc Jean-Paul - Lemelin Jean-François- Lévesque David Lévesque Guy - Macédo Patrice - Marcil Patrick - Marcotte François - Marcoux Pascal - Marineau Jean - Marion Ronald - McKoy Gérard - Ménard Dave - Minville Sébastien - Moreau Éric - Morel Réal - Munger Hervé - Murray Jean - Nault Christian - Ouellet Alain - Ouellette Simon - Painchaud Éric - Pascal Claude - Patenaude Robert - Patoine Steeve - Payant Gilbert - Perron André - Pilote Pierre Luc - Pilote Julien - Poulin Amélie - Reimnitz Robert - Riberdy JeanPierre Rioux Éric - Robert François - Rochefort Jean-Michel - Rochefort Louis-Francis - Rondeau Jean-Marc - Rouillard Sylvain - Roy Adrien - Sabourin Patrick - Salesse Louis - Samson Marco - Savard Guy - Scopelleti Martin - Séguin Serge - Selseotes Marc - Simard Marc-André - Simard Claude - Simard Louis - St-Cyr André - Therrien Steeve - Tremblay Charles-David - Tremblay Olivier - Tremblay Martin - Tremblay Jean-Pierre - Tremblay Sylvain - Tremblay Yvon Tremblay Sylvain - Tremblay Jimmy - Tremblay Bernard - Tremblay Raymond-Mari - Van der Heyden Nicolas - Verreault Kevin - Vézina Maxime - Vinette Maxime - Zacarias Angelito Raym LP – On Saturday, July 24, joint venture Cegerco Lambert and Somec delivered various premises that will belong to HydroQuébec’s TransÉnergie division. The six rooms that were delivered, in the presence of members of the Hydro-Québec team and SEBJ employees, contain protection panels, automatic control systems, electrical equipment, batteries and a laboratory. They are all located in the level 220 service area, adjacent to the future Sarcelle powerhouse switchyard. Level 220 is the top floor of the powerhouse, 220 being the number of metres it lies above sea level—level 0. These rooms were delivered well ahead of the deadline, which was September 15. To mark this major step, a place mat commemorating how quickly the work was completed was given to every worker, and a special cake was prepared for the occasion. Congratulations to everyone who contributed directly or indirectly to this achievement! PD – The Oujeck satellite workcamp, like all camps, had a limited lifespan. Oujeck workcamp was closed on June 20, and until weir construction is finished, the workers will live either at the km 257 workcamp or at the one in Waskaganish. At peak occupation, Oujeck workcamp housed more than 225 workers from several companies working on the Rupert weirs. Closing a workcamp involves not only cutting its power, but dismantling it. Two contractors—Larouche Construction and Denis Lavoie & fils—started dismantling Oujeck workcamp in late August and will continue until late October. About 70 modules will have to be relocated. Some of the dormitories 6 Eastmain Magazine, September 2010 will be moved to Nemiscau workcamp. The rest will travel nearly 1,650 kilometres to the Romaine project’s Murailles workcamp. Users of the Route du Nord and the James Bay Highway will have to be careful, since the modules take up a good part of the road. Stop on the shoulder when you meet the escorted convoy. People with a powerful vision THE JOBSITE IN PICTURES Moving on and moving out MEM – The summer was not exactly restful for workers at the Rupert diversion project. Although four of the eight weirs had been completed, those at KP 33, 170, 223 and 290 needed a lot of work—we can now make out their final shape. Even though the project is drawing to a close, everyone is still working diligently! Here is how work is progressing: KP 33 The weir at KP 33 is now in service, making it one of the most impressive of the eight hydraulic structures on the Rupert River. The left channel is permanently closed and water is flowing over the newly built weir. From now to mid-October, various types of fill will be placed to build the dam. Meanwhile, the temporary bridge will be dismantled. KP 33 KP 170 Construction of the weir in the right branch of the Rupert River moved ahead quickly once the weir in the left branch had been started up. The concreting has been completed, as has levelling of the cofferdam. Since mid-August, water has been flowing over the weir in the right branch, signalling the end of construction at this location. Rehabilitation of the site has begun. KP 170 Eastmain Magazine, September 2010 7 THE JOBSITE IN PICTURES Rupert diversion jobsite Final sprint at Rupert Rupert diversion jobsite KP 223 MEM – Fill work on the dam has been completed since mid-August. Contractor Newco is busy with jet grouting, which is expected to continue until the end of September. This technology, already used for the cofferdam, will ensure that the gravel core of the dam is watertight. The next steps will be to dismantle the temporary bridge and remove the jetty, making it possible to complete construction of the spawning ground. KP 223 KP 290 Startup of the weir in the central channel occurred in early August. Contractor Newco has completed construction of the cofferdams for building the rockfill weir in the right channel, and the temporary bridge has been dismantled. The contractor is now installing the rockfill for the second weir. KP 290 Jolly Bay NF – Since late July, a control structure has been under construction in Jolly Bay, about 3 kilometres downstream of Rupert dam; it consists of a rockfill weir with sheet piles. Since the weir is more than 2.5 metres high and has a storage capacity of more than 3 hectares, it is subject to the Dam Safety Act, which introduced a series of measures governing construction and operation. 8 Eastmain Magazine, September 2010 Jolly Bay People with a powerful vision THE JOBSITE IN PICTURES Its purpose is to preserve a body of water that will prevent fish mortality, to allow fishing and to provide an environment conducive to goose hunting. Building formwork for concrete pours at unit LC 12 The second phase of concrete work is coming to an end JL – Though the civil works contracts are nearing completion, major concrete work is still underway at the Eastmain-1-A powerhouse. In August, Cegerco–Inter-Cité (CIC) finished concreting the wall of the powerhouse access road. The company is also continuing concrete work in the turbine area. The generator floor, consisting of precast concrete parts, is also part of the contract. Keep in mind that the second phase of concrete work includes a total of over 27,700 m3 of concrete. Gate slots Concreting of the powerhouse’s 12 downstream gate slots ended on July 24. Nordex, subcontractor for Canmec Industrial, was responsible for concreting the slots, weirs and lintels. The first pour took place on July 12; in all, it took only 12 days to fully embed these parts. THE JOBSITE IN PICTURES Eastmain-1-A jobsite Getting ready to install the tower crane on the downstream deck of the Eastmain-1-A powerhouse Reinforcing iron workers busy preparing to pour concrete around the scrollcase of unit LC 13. Eastmain Magazine, September 2010 9 Eastmain-1-A jobsite The Eastmain-1-A powerhouse water intake End of work at the temporary dike Neilson-EBC finished dismantling the temporary dike at the water intake in mid-August. This involved removing the sheet piles, excavating the dike using a dragline excavator and, finally, reshaping the spur dikes. Water from the reservoir can now flow freely through the water intake. End of rock excavation at the Eastmain-1-A powerhouse tailrace Starting up the tailrace JL – Neilson-EBC finished excavating the tailrace in August. A total of 525,000 m3 of rock and 530,000 m3 of overburden had to be removed to clear the channel through which the turbined water will return to the bed of the Eastmain River. Downstream of the tailrace, with the Eastmain-1-A powerhouse in the background 10 Eastmain Magazine, September 2010 People with a powerful vision THE JOBSITE IN PICTURES The tailrace will be started up once the cofferdam downstream of the canal has been removed. Startup should occur in September. Ongoing finishing work in the rooms and corridors of the powerhouse Electrical and mechanical systems Work on the first mezzanine (level 230) was completed a few weeks ago. The TAP consortium worked especially hard to deliver the mezzanine to Hydro-Québec by mid-August. Finishing work, such as the installation of doors and acoustic tiles for suspended ceilings, was carried out by the consortium, which is also continuing to supply and install equipment and electrical and mechanical systems on almost every level of the powerhouse. Installation of components inside unit LC 11’s stator casing Assembly of the first turbine JL – Most of the parts necessary for putting together unit LC 11 have arrived at the powerhouse and the work of assembling the first turbine is underway (see other articles on pages 12 and 13). Turbine manufacturer Voith Hydro installed the casing of the stator directly in the turbine shaft and has begun assembling the magnetic circuit and the winding. Now that is precision work! Rotor assembly, which will be done in the unloading bay of the powerhouse, will begin shortly. THE JOBSITE IN PICTURES Eastmain-1-A jobsite Unit LC 11 stator casing View of the stay ring from inside the scrollcase Eastmain Magazine, September 2010 11 Generating units The wicket gates arrive at the powerhouse CL – On July 28, the first wicket gates arrived at Eastmain-1-A powerhouse on a double semi-trailer. This truck with two trailers is the first of three required to deliver the 72 wicket gates—24 per unit. These parts, manufactured by Voith Hydro, were meticulously designed and manufactured to have an optimal hydraulic profile. How does it work? The water flows into the penstock and then to the scrollcase where it is evenly distributed by the stay ring. The water then reaches a second set of blades, which are adjustable: the wicket gates. Their opening (also called the gate position) can vary from 0 to 100%. Well-traveled wicket gates The initial stage—design— was carried out at Voith Hydro’s factory in Germany. “The shape of the wicket gates was developed and designed specifically for the Eastmain-1-A generating units,” said Dany Morin, Voith Hydro Project Manager. “A scale model was used to adjust and check their hydraulic profile.” 12 Eastmain Magazine, September 2010 The 24 wicket gates of unit LC 11 were inserted vertically between the stay ring and the turbine runner. Once the optimal shape had been established, “the 72 wicket gates were cast at Voith Hydro’s foundry in Brazil. Then, after being machined, they were sent by ship from Brazil to the United States,” said Mr. Morin. “The wicket gates for the first unit completed their long trip to the jobsite on a flatbed truck, while the other two sets are still in storage in Montréal,” he added. Installation At the end of August, the first 24 were inserted one by one into the bottom ring of unit LC 11. The overhead travelling crane raised each wicket gate to its final position using the longer journal—the upper wicket-gate journal. The shorter journal will be inserted into the bottom ring. The head cover will then be fitted over the longer journal. Once installation is complete, the only visible part of the wicket gates will be their blades, which will remain in contact with the water. Wicket gate numbers Number of wicket gates per unit: 24 Weight of a single wicket gate: 2,980 kg (6,570 lb.) Alloy: ASTM A743 grade CA6NM stainless steel Arrival of wicket gates for units LC 12 and LC 13: mid-October and early December People with a powerful vision THE JOBSITE IN PICTURES A key role The wicket gates will be inserted between the turbine runner and the stay ring of each unit. They will be in direct contact with the water, where their role is to channel more or less water to the turbine runner depending on demand for electricity and operating strategy. Contrary to popular belief, it is the wicket gates—not the main gates of the water intake—that govern flow to the generating unit. Their role is therefore crucial. Turbine runners for the Eastmain-1-A powerhouse An epic journey from Brazil to Chisasibi! JL – This unprecedented operation was required because of the unusual size of the Eastmain-1-A powerhouse’s three turbine runners. Since the runners weigh in at around 120 tonnes and have a diameter of about 7 metres, hauling them up the continent across so many roads and bridges would have been difficult, if not impossible. The only viable solution was to ship them. A long trip A long trip covering thousands of kilometres had to be organized between São Paulo and Chisasibi. This enormous undertaking was meticulously planned over a year in advance. “Our main constraint was the short period of ice-free navigation in James Bay, which only lasts from June to September,” said Jean-Pierre Motard, Section Manager – Project Control. “We had to make sure the manufacturing was completed in time for shipping to be done within this window.” Since the ships could not dock directly on the banks at the village of Chisasibi, a delicate ship-to-barge transfer operation was required. Weight Number of blades Diameter Height Type of steel 120 tonnes 13 6.8 metres (at the base) 4.19 metres ASTM A743 grade CA6NM stainless steel Turbine manufacturer Voith Hydro was responsible for manufacturing and transporting the Eastmain1-A powerhouse’s three runners. It subcontracted the transportation to an expert in the field: Panprojects of the Panalpina group. To minimize risks during transportation, the three runners were sent on two different ships. After travelling along the east coast and around Québec by way of Hudson Strait, the ships entered Hudson Bay and then headed down to James Bay. The first ship, carrying two runners, reached Chisasibi on August 8 and the second arrived three days later. Why Brazil? The steel runners were cast in one piece. To protect against corrosion and cavitation, they were coated with stainless steel. Since no Canadian foundry is capable of producing such large parts, Voith Hydro manufactured the runners at its plant in São Paulo, Brazil. The three runners are the only components of all the James Bay projects that had to be transported by sea to their destination. Land transportation It was impossible for the ships to dock directly on the banks at the village of Chisasibi because of their size and draft, evaluated at more than 9 metres. Instead, a delicate ship-to-barge transfer operation was necessary—this took five days. Finally, the first runner left Chisasibi on a specially prepared flatbed truck. The convoy took the James Bay highway and the Muskeg–Eastmain-1 road. The first runner was delivered to the jobsite on August 14. In all, the land transportation of the three runners lasted from August 13 to 21. Each runner left Chisasibi on a specially prepared flatbed truck and travelled on the James Bay highway and the Muskeg–Eastmain-1 road. The runner for the first generating unit was lowered into the turbine shaft on August 28, nearly two months ahead of schedule. Even before the turbine runners started to turn, you could say that they had “been around.” Manufactured in Brazil at the Voith plant, the runners had to be transported by sea because of their size and weight. Eastmain Magazine, September 2010 13 THE JOBSITE IN PICTURES After an ocean voyage from Brazil, along the continent and around eastern North America, three turbine runners arrived in James Bay before traveling by road to the Eastmain-1-A powerhouse. PROFILE So much gets done behind the scenes CL – Annie Villeneuve, the brilliant lawyer at the SEBJ head office, is every bit as interesting as the singer who shares her name. She loves to travel and her unique and colorful career is an accurate reflection of her personality: she is curious, eager to learn and determined to meet the many challenges facing the project of the decade. There are a number of steps involved in determining which approvals are needed and expediting the process of obtaining them from government departments. Note that, since the project began, SEBJ has had to acquire nearly 1,000 sector-related authorizations and meet several conditions. “Every day, I work to ensure that these conditions are met Annie Villeneuve and advise various stakeholders to ensure that our operations is a governmental comply with legislation, as well,” she added. approvals advisor who has been Her master’s degree in international law, with a specialization in working at SEBJ environmental law, gave wings to her legal career. She studied in for the Eastmain- Montpellier and Paris and worked in Rome, but it was at Hydro1-A/Sarcelle/ Québec that she decided to put down roots in January 2007, Rupert project joining the SEBJ team in early March 2007. “There are considersince 2007. able challenges at SEBJ. You have to be able to give the right She answers to advice at the right time, and a quick turnaround is required to Philippe Mora meet tight construction schedules,” said Ms. Villeneuve, who is and appreciates very proud that construction has never been delayed or stopped her team and the for lack of a timely authorization. many challenges her work proIn addition to being responsible for transmitting documents to vides. That work, the various government departments, she will be participating which starts in in a major process that will require her services until 2012: public the earliest stages of the project, is done behind the consultations. “One of the conditions the provincial Certificate scenes and sometimes goes unnoticed. So, what does of Authorization imposes on Hydro-Québec is to hold public she do? “For the most part, I advise and support man- consultations to find out what our Cree partners think of the efagers so that SEBJ can obtain, within the anticipated fectiveness of mitigation measures that were implemented as timeframes, the government approvals it needs to part of the project. I will be asked to prepare the documentation carry out work in accordance with applicable environ- that shows that we fulfilled our commitments,” she said. This is mental legislation. I also ensure compliance with the another major challenge that she will undoubtedly meet with conditions stemming from the broad authorizations enthusiasm and flair! obtained for starting up this great project,” stated Ms. Villeneuve. SEATBELTS Not buckling up is still one of the leading causes of death on the road. Today, back-seat passengers are most often at risk. It is essential to avoid using certain devices intended to loosen seatbelts. They actually reduce seatbelt effectiveness and could lead to a risk of trauma in a crash. In fact, automakers have enhanced the performance of traditional seatbelts by installing pre-tensioner systems to tighten the belts and improve their ability to minimize occupant movement in a crash. For maximum safety, there should be no slack in your seatbelt. 14 Eastmain Magazine, September 2010 People with a powerful vision PROFILE A smile is worth a thousand words! MEM – If you’ve ever met him, he has definitely smiled at you. If you smiled back, you became one of his friends. Respectful and generous, Ghislain Lévesque is one of those people you never forget. Carpenter-joinercabinetmaker by trade, he works for Nemaska Eenou Company (NEC) doing technical maintenance at Nemiscau workcamp. With his very talented hands, he can build, renovate or repair anything. Despite being far away from the two children he is so proud of, he worked at the Eastmain project for two years (2005–2007) and the day after his birthday, on March 25, 2007, he joined the group working on the Rupert diversion project. This handyman is thankful that throughout his childhood his mother gave him planks of wood and bags of nails to build with! Most of his tasks relate to routine building maintenance, but some require a bit more creativity, which he loves! He is meticulous and a perfectionist. He and the Cree workers around him respect one another, and Ghislain takes a real interest in their culture and language, of which he has learned several words. No challenge is too great. Ghislain is ready for anything! In fact, three years ago he took up powered parachuting, enabling him to see the most beautiful landscapes of the James Bay area from above. Ghislain was born in Price (25 minutes from Rimouski) and now lives in Mont-Joli. He apprenticed as a steel erector for two years and owned his own business as a carpenter-joiner general contractor for six years. “I enjoyed being my own boss, but I’m very happy here. I have great conditions, the perfect work atmosphere and a tremendous team.” The idea of working on the James Bay projects came from his feisty personality, eager for challenges. Life isn’t always easy, but Ghislain has always had confidence in himself. “You have to believe in yourself, your ideas, your goals and your talents and then dare!” Don’t forget to smile at him—he deserves it! To illustrate the importance of road safety, here are the numbers for an ordinary day on the streets and picturesque roads of British Columbia, according to Transport Canada statistics. This is data for a single province and a single day. • • 695 motor vehicle collisions will occur • At least one person will die 215 people will be injured, including 4 cyclists and 6 pedestrians Here are more sobering numbers. They are from Transport Canada’s annual statistics for 2006. Collisions and their victims in Canada – 2006 • • 2,604 fatal accidents • 2,889 deaths • 144,756 bodily injuries (not resulting in death) 199,337 serious injuries (requiring hospitalization) So remember: Be sure to buckle up! Claude Perron Direction principale Sécurité industrielle Eastmain Magazine, September 2010 15 NF – Seeding of exposed banks is one of the measures being implemented to mitigate the impacts of the Rupert River diversion by reducing erosion and sediment transport on the one hand, and improving wildlife habitat, on the other. Aerial seeding along the Rupert River Only areas with silty substrate that were more than 15 metres wide were selected, for a total of 155 hectares (ha); approximately 80% of these were in the section extending from KP 110 to 165. The seed mix was the one SEBJ usually uses for revegetation of affected areas in humid conditions, and it was applied at a rate of 225 kg/ha. It should be noted that the seeds were coated with an environmentally safe lime-based product. GDG Environnement of Trois-Rivières carried out the work from July 2 to 19. The operation was conducted from the Nemiscau airport using two Piper PA-25 Pawnee aircraft with a load capacity of 500 kg. On site, the operation went very quickly since one hectare was covered every 15 seconds! The aircraft flew at a speed of 160 km/h, an altitude of about 10 metres and, of course, in low- or no-wind conditions (<15 km/h). On the ground, the marking of planting plots and quality control of application rates was carried out by a team from environmental consulting firm Biofilia.