CVUHSD Measure CV Master Plan Update_July 23 2012

Transcription

CVUHSD Measure CV Master Plan Update_July 23 2012
Centinela Valley Union High
School District
Measure CV Program Update
July 23, 2012
Site Construction Progress Site Updates
2
™
Hawthorne High School
™
Lawndale High School
™
Leuzinger High School
TELACU Construction Management
Hawthorne High School – Existing Site
3
TELACU Construction Management
Hawthorne High School
Site Master Plan
Phase 0 Access Road
Phase 1A Construction
4
TELACU Construction Management
Hawthorne High School
June 2012 to Aug. 2012
The full removal of building #4
to make way for a new access
road for the campus.
5
Demolition of multiple buildings this Summer to make way
for Phase 1A.
TELACU Construction Management
Hawthorne High School
June 2012 to July 2012
Many of the casework inside of
building 11 was reused from the
previous Administration
buildings.
6
The Hawthorne Administration has been relocated to building
#11 temporarily until August of 2013 then the staff will find a
home in the new Administration building A.
TELACU Construction Management
Hawthorne High School
June 2012 to August 2012
New gas lines will be installed
for the whole campus to feed
new and existing buildings.
7
New utility lines were installed through underground boring to
bring new electrical feeds for the new buildings to minimize
removal and repair to the existing site.
TELACU Construction Management
Hawthorne High School – Phase 1
8
™
The first buildings scheduled for construction at Hawthorne High
School will be a science building that will sit at the corner of El
Segundo Blvd. and Inglewood Ave.
™
There will be a new Administration building & Media Center as
well.
TELACU Construction Management
Hawthorne High School Phases 0, 1, & 2
9
™
Phase 0 (Summer Work) will reroute existing utilities and relocate
the cafeteria driveway. New temporary parking lots will be
installed as well to provide parking for the 2012/2013 school year.
™
Phase 1 will provide the campus with upgraded science and
engineering facilities. The science department will be moved into a
new 14 lab building and 10 specialized classrooms and labs will be
built for the engineering academy.
™
New gas lines will be installed for the whole campus to replace the
existing aging gas pipes.
™
Phase 2 will provide the campus with an additional 40 classrooms
and labs.
TELACU Construction Management
Lawndale High School – Existing Site
10
TELACU Construction Management
Lawndale High School Site Master Plan
11
TELACU Construction Management
Lawndale High School – Phase 1
Demolition
Buildings 1, 2, 5 and 6 were demolished in
preparation for the Phase 1 Building. Demo
included removal of foundations, utility lines
and asbestos pipe.
12
TELACU Construction Management
Lawndale High School – Interim Housing
We are currently installing five classrooms by
the Softball field. Fire Alarm and data
systems are going in right now and the project
will be complete for the District to occupy in 2
weeks.
Electrical, data and sewer pathways for the
future Restroom and Concession stand
permanent building are being installed right
now.
13
TELACU Construction Management
Lawndale High School – Electrical Reroute
™ Power cables that currently feed buildings
3, 4, Gymnasium and the CVCA (dotted blue
line) are in the footprint of the Phase 1
building.
™Excavation for Phase 1 cannot begin till
cables are rerouted along new path (red)
installed last summer.
™ Project will involve disconnecting, remove
old cabling and installation of new along new
utility pathway.
14
TELACU Construction Management
Lawndale High School – Phase 1
The Phase 1 Student Services Building
consists of a single (3) story 115,000 sf Type
IIA building with Administration, Library
and Campus Security spaces including 42
teaching stations.
Guaranteed Project Costs (GPC) from the six
General Contractors are due mid August.
Construction scheduled to start late September.
It is a two year project and will be ready for 201415 school year.
15
TELACU Construction Management
Leuzinger High School – Existing Site
16
TELACU Construction Management
Leuzinger High School Site Master Plan
17
TELACU Construction Management
Leuzinger High School Projects
™
™
™
18
Demolition & Abatement
Library Electrical Re-route
Phase 2A Grading & North Parking Lot
New Parking Lot Close to Completion
TELACU Construction Management
Leuzinger High School
Phase II Hospitality and Culinary Arts Academy Additions
District Received Bids on July 17, 2012
19
TELACU Construction Management
Leuzinger High School
Phase II Hospitality and Culinary Arts Academy Additions
OPENING FALL 2014
20
TELACU Construction Management
21
TELACU Construction Management
22
TELACU Construction Management
23
TELACU Construction Management
24
TELACU Construction Management
25
TELACU Construction Management
26
TELACU Construction Management
27
TELACU Construction Management
28
TELACU Construction Management
29
TELACU Construction Management
30
TELACU Construction Management
31
TELACU Construction Management
32
TELACU Construction Management
33
TELACU Construction Management
34
TELACU Construction Management
35
TELACU Construction Management