Ringsted-fehmarn - Holeby June 8th
Transcription
Ringsted-fehmarn - Holeby June 8th
Status on Upgrading of the Fehmarn Railway Ringsted-Fehmarn 08.06.2016 Presented by Project Director Jens Ole Kaslund 1 Ringsted – Fehmarn Banen so far 2012 – 2013: Programme Phase 2013: Political decision of 200 km/h and financial act for early works. Tendering of early and other works started 2014: Early works 2015: Construction law past parliament April 28 th 2015. 2016: Political decision of upgrade in 2021 to Nykøbing F and electrification of the same line in 2024 latest. Work at Lolland will be coordiniated with tunnel opening. 2 3 Ringsted – Fehmarn – Outcomes Outcomes/Benefits - More departures for both freight and passenger trains - Reduced travel times – less than an hour between Nykøbing F and Copenhagen. Close to 2½ hours between Copenhagen and Hamburg - Reduced freight traffic across Funen - More flexibility and improved punctuality - More effective railway projects 4 Full scope - Double tracks Vordingborg – Rødby - Upgrading the speed limit to 200 km/h Ringsted - Rødby - New station north of Rødby - Passing tracks for 1000 meter long freight trains - Catenary system Ringsted – Rødby - New double tracked bridge across Masnedsund - New single track bascule bridge across Guldborgsund - ERTMS baseline 3 level 2 from Ringsted - Rødby 5 Political decision of way forward for Femern A political agreement was reached Marth 4th 2016 For the related Danish rail work it means: – – Double track, ERTMS baseline 3 level 2 and speed upgrade to 200 km/h from Ringsted to Nykøbing F will be finished in 2021 Electrification from Ringsted to Nykøbing F will be finished latest at 2024 – Work on the line on Lolland – Nykøbing F to the tunnel – are postponed and will be coordinated with opening og the tunnel – The Storstrøms Bridge is not part of this agreement, but it is expected to open in 2024 at the latest. – Budget are still 9.5 billion DKK (pl2105) including reserves. – It is financed by A/S Femern Landanlæg and EU 6 Major track possessions The major track possessions are expected within the following where a large amount of the work are expected: Between Ringsted and Næstved Total possession in 7 weeks, spring 2020 Total possession 6 months, middle of 2021 Between Næstved and Orehoved. Total possession one week in 2017 Total possession in 3 months in the summer of 2019. Falster Total possession in 7 weeks in 2018 Total possession 6 month in the middle of 2019 Total possession 4½ month in middle of 2021 Lolland The current line will be renewed as needed to keep it open until the upgrade starts. Other possessions are going to be during nights and weekends / bank holidays 7 Status and Schedule for the Major Tenders Contract Arkil March 2014 Contract MT Højgaard March 22nd Contract Aarsleff May 9th Contract Rohde Nielsen January Awarded MJ Eriksson March Tender autumn 2016 Tender now – due June 9th Tender 2017 Smaller tenders 8 Contact us Jens Ole Kaslund Project Director Ringsted-Fehmarn Mail: joka@bane.dk Phone: 8234 0584 Klaus S. Jørgensen Technical Director Ringsted-Fehmarn Mail: klsj@bane.dk Tlf: 8234 9057 Email to the project: femern@bane.dk www.banedanmark.dk/ringsted-fehmarn 9