CPI Duri Field - INTECH Process Automation
Transcription
CPI Duri Field - INTECH Process Automation
Project: Engineering, Design, Comissioning and Maintenance of CPI PI Interface for various sites and Interface with OPC server End User: Chevron Pacific Indonesia Year: 2010 Location: Duri Field, South Sumatra Basin, Indonesia. Duri oil field is approximately 18km long and 18km wide. It is located in the Riau Province, in the South Sumatra Basin on the eastern coast of Sumatra, Indonesia. Duri Field was discovered in 1941. The onshore oil field was brought on stream in 1954. The daily production from the Duri field currently averages to approximately 185,000 barrels accounting for nearly half of Chevron Pacific Indonesia's total production. PT. Chevron Pacific Indonesia requested INTECH for technical support and services for Industrial control system Engineering, installation, commissioning and maintenance support for new and already running industrial control system at different platform’s. Build interface with Yokogawa & Honeywell OPC Servers Installation of PI Server for remote data historians for CGS Work with Yokogawa and Honeywell on OPC Server bitmap, interface and tag quality Provide project documentation and training to local operations and engineering team Work with Base Business and Engineering Team to verify data integration and system design Provide on-site Assistance and provide Remote Support Services (RSS). The supply of hardware included: INTECH’s project scope included collection of data from all the different sub-stations, five gathering stations, steam injection stations and heavy oil stations to a central PI server. Human Machine Interface (HMI) - WonderWare INTECH’s Scope of Work included: OPC Servers for Modicon, GE & Siemens Installation of PI Historian at remote sites and integration of data at the central data repository, Programming, Function Test and Commissioning for modification of Honeywell logic and HMI project CGS-10 Kill Water Pump to CIF Installation of MAX SCADA at wellhead RTU and Data Acquisition from rod pumps using GPRS Maintenance of OSIsoft. The overall Scope of Supply included: Installation of PI Connectors CGS1, 3, 4, 5 & 10 for local data historians USA UAE France Angola Indonesia KSA InTouch Runtime Remote Terminals Units (RTUs) - Modicon M340 Since 1992, INTECH has completed over 700 major upstream onshore and offshore Oil & Gas projects for most Majors, leading NOCs, and many IOCs working both directly as well as subcontractor to leading global as well as local EPCs. INTECH has delivered many projects and systems under collaborative relationship with key Oil & Gas OEMs including Schlumberger, Halliburton, Weatherford, Superior, Cameron and others. INTECH is a vendor neutral automation solutions provider with expertise with almost all instrumentation and control vendor equipment. Singapore Nigeria China Peru Kazakhstan Pakistan