Coming Through for Cargill
Transcription
Coming Through for Cargill
September 2011 TODAY A monthly newsletter for employees of RailWorks Corporation and its subsidiaries Coming Through for Cargill INSIDE LINE Nothing on this project was hard or out of the norm, but it was a lot of track to build in a short time. Managing the project took someone who could see above the fray. RailWorks overcame wet weather and resulting construction delays to provide Cargill with a new storage yard for its Eddyville, Iowa, corn milling operations. The work itself was standard stuff, but the way RailWorks crews undertook the work was exceptional. so elsewhere, just as they have done in recent months to protect track and maintain rail service for clients nationwide. RailWorks Track Systems’ job was to build a new storage yard in a Cargill corn milling facility in Eddyville, Iowa, about 70 miles southeast of Des Moines. With the added capacity, Cargill was looking to rid itself of expensive demurrage fees incurred from storing cars on Union Pacific and BNSF-owned track. In late October 2010, crews were finally able to start placing material on the track bed. After such a lengthy holdup, it would take extraordinary commitment to make up lost time. RailWorks doubled its on-site team and added extra loaders to increase daily production. Record rainfall in the Midwest delayed the work, which was to have begun in early July 2010. By the end of that month, the state of Iowa had experienced its eighth consecutive week of above-normal wet weather and three times the statewide average precipitation. The Eddyville plant itself was threatened by the rising Des Moines River. While RailWorks crews did not perform emergency flood control in Eddyville at that time, they were busy doing “We’d lost four months of construction,” said Area Manager Randy Ruppert. “We brought in about 10 more workers and additional loaders and heavy equipment to meet the needs there.” Cargill wanted about half the project completed by the end of the year. By December 31, RailWorks had constructed the requisite 17,000 feet of track along with half the turnouts. RailWorks worked through a winter that featured Continued to page 2 Randy Ruppert Area Manager RailWorks Track Systems This project worked because Bill Kadrlik served as the project manager and the on-site supervisor. He has such a mild disposition and he just kept control of his material — what was coming in and what was on site—and he effectively projected out what needed to be done and where it needed to be done. Then he assigned people accordingly. He was always a week ahead in his thinking as to where we needed to be at a given time. With this kind of overall planning of a project, Bill saw us through the extended project duration. You can always reinvent the wheel, but sometimes it just isn’t needed. It just needs clear planning, which Bill provided for us. To meet the compressed schedule, we had to hire personnel. At one time we had 16 new-hires, so not only did Bill have to plan the track work, he also had to train 16 people. That pool of workers came out of Missouri. The base crew helped out by welcoming, training and assimilating the new-hires into a tight-knit group. We gained a lot of good operators out of this project, including a guy who’s now one of our foremen. 2 September 2011 Coming Through for Cargill from page 1 extremely low temperatures in January and the outset of February, followed by warm temperatures and snowmelt that created flood threats in eastern Iowa. Still, crews reached substantial completion by the end of March. Having expanded its yard on the western edge with 37,587 feet of storage tracks and 27 turnouts, Cargill gained space to store about 564 cars. The savings from eliminating demurrage fees will pay for the expansion project in five years. The Eddyville facility processes more than a quarter of a million bushels of corn daily to produce ethanol, feed, dextrose and other corn byproducts. RailWorks enjoys preferred vendor contract status with Cargill for this facility and others in most of the United States for track inspection, maintenance, repair and construction services. RailWorks Values In Action: Integrity RailWorks employees in Minnesota for the annual Leadership Conference demonstrated the same great teamwork that makes our rail projects a success. But instead of building track, signals & communications or transit systems, their endeavor produced 124,172 meals, enough to feed 67 hungry children for an entire year. A group of 65 employees representing RailWorks Corporation and subsidiary companies in the United States and Canada took an afternoon away from meetings on September 22 to work at the Eagan, Minn., site of Feed My Starving Children, a not-for-profit organization whose mission is to eliminate starvation in children throughout the world. Working in an assembly-line fashion, employees measured and poured food into bags and then weighed, sealed and boxed the bags containing a vitamin-enriched combination of rice, soy, dried vegetables and other ingredients. Once at destinations around the world — from Haiti and El Salvador to the Sudan and the Philippines — these “manna packs” will provide porridge-type meals to nourish starving children. RailWorks Corporation Director of Operations Reporting & Analysis Ed Fenn said, “Aside from the numbers we put on the board (the number of meals packaged), it is always rewarding to be part of a team to build something or make something better.” from the Greater New York area showed L.K. Comstock & Company management areas and prepared meals sterile and work the keep help to worn off their caps dent and Controller Mike Esposito, Presi Vice r): to s.(l free of foreign substance John Sommer, President Ben and r Habe Vice Presidents of Operations Ray tteo, Vice President Bill Kelly and DeMa Sal D’Alessandro, General Superintendent Adam Penza. dent Presi Vice tant Assis dent/ rinten General Supe “The RailWorks group team excelled at this task because, although the materials are much different, the mechanics are similar to what we do every day. The success of the task revolved around teamwork. And for those of us who no longer do the physical work, it is refreshing to work up a sweat now and then,” said Ed. “The fact that we’re helping to feed starving children is very gratifying. It felt good to make a difference.” Assistant Area Manager Hal Harrison, who made a return visit after first volunteering with the Lakeville office during the last holiday season, said it was great to be able to do something to feed children who are not just hungry, but actually starving in places such as Haiti that are not far from our homeland. “If there’s a way to help these kids survive and then grow up, who knows what they can do in this world. It’s the humane thing to do that makes you feel good, and it doesn’t take anything, just an hour and a half of our time. For a little bit of effort we did a lot of good. It’s well worth it.” Although this volunteer effort was far away from our job building rail and transit lines, it provided RailWorks employees with important work to build a better world. It’s part of our broader commitment to do the right things not only on our job sites, but also in the communities where we live and work. After the “manna packs” were assembled, volunteers carried the full boxes to the shipping area and then sealed and positioned them on skids for transport around the world. Director of Operations Reporting & Analysis Ed Fenn, RailWorks Track Systems’ Regional Mana ger Steve Kadrlik, and Purchasing Manager Mike Mascelli worked up a swea t doing the heavy lifting. Our Values: Customer Focus, Employee Focus, Industry Leadership, Integrity 3 September 2011 RAILWORKSMART RAILWORKSAFE RAILWORKSMART RAILWORKSAFE Being struck by a recoiling towing chain has caused many severe injuries and fatalities in the construction industry. This occurred in two situations at RailWorks recently. While we were fortunate no injuries resulted, we can still learn from these situations to avoid them in the future. for chains in the event they break and recoil. When towing, the operator should apply power smoothly without braking hard or jerking, which puts additional stress on the towing system. Situation No. 1 – Using a loader and a tow chain, Tammy Mathews Corporate Safety, workers were removing a switch, which was Health and positioned parallel to the track where it would be Environmental Director installed. During the process of moving the switch, RailWorks Corporation a link attached to the end ring of the chain failed. The end ring let go, striking and breaking the loader windshield. One of the workers guiding the switch had to immediately jump to avoid being struck. This quick action saved him from severe injury or even death. Lessons Learned – Before using the chain, look at its rating tag to ensure the rating reflects the towing capacity required by the pull. If the tag is missing, do not use the chain. Find a chain with a suitable rating then thoroughly inspect it. Look for flaws such as cracks, excessive wear marks, excessive rust or pitting or any other damage. Do not use a chain that shows any damage. Properly store and maintain chains according to the manufacturer’s recommendations, including keeping them away from moisture whenever possible. Be sure workers are never in the “red zone” Situation No. 2 – A crew was attempting to move a 98-foot turnout by placing it on top of rail to slide it into position. The turnout moved smoothly as intended when pulled by the end loader. However, the crew had not placed enough rail under the turnout to achieve the desired position. When the end of the turnout passed the end of the slide rail, the turnout end dropped into the soil, causing it to dig in as it was being pulled by the loader. When this happened, the forces placed on the chain immediately surpassed the chain’s rated capacity and the link closest to one end snapped. The chain flew, striking the loader’s windshield. The safety glass saved the operator from probable severe injury from the striking force of the chain. Examination of the entire chain, link by link, revealed no discernible flaws, no cracked or deformed links and no excessive wear in any of the chain’s links. Lessons Learned – In this instance, better planning, such as placing more slide rail along the intended path, would have prevented the end of the turnout from dropping into the dirt and causing the sudden impact on the chain, shock-loading it beyond its rated capacity. This incident is a good example of what can happen when planning for an operation fails to completely account for the existing conditions and the desired objective. News Across the Line AREMA, REMSA, RSI and RSSI with one huge yet unique gathering. RailWorks Corporation RailWorks had a strong presence with a track exhibit in the REMSA exhibition hall and a larger exhibit representing all of RailWorks Corporation’s capabilities in the RSSI hall. Field management took advantage of extensive outdoor and indoor equipment exhibits to evaluate what’s new in the industry and to provide comments to manufacturers and suppliers. Our Human Resources (HR) team networked with student job-seekers while highlighting why RailWorks is a great place to build their careers. The third week of September was a busy time for the company beginning with the Railway Interchange conference and exhibition in downtown Minneapolis, Minn., and concluding with RaiWorks’ annual Leadership Conference held down the road in Lakeville. More than 8,000 industry professionals attended Railway Interchange 2011 sponsored by four trade associations September 17-21. Billed as the largest railroad supply event in North America, Railway Interchange replaced separate exhibitions and conferences traditionally sponsored by the four organizations RailWorks Corporation’s Railway Interchange exhibit highlighted its three primary areas of Continued on page 4 RailWorks Corporation’s Railway Interchange exhibit highlighted its three primary areas of service: Track, Transit Systems and Signals & Communications. 4 September 2011 News Across the Line Continued from page 3 Executive Vice President John August led the Leadership Conference, including an accountability breakout session on linking consequences. service: Track, Transit Systems and Signals & Communications. On Wednesday, September 21, the focus shifted to Lakeville for the kickoff of the annual Leadership Conference. RailWorks President & CEO Jeff Levy discussed the state of the company, citing our unique business, range of services and markets, competitive position, strong resource base and growing opportunities. He asserted, “We are building a company that will last forever.” Executive Vice President John August explained how the meeting’s theme – RailWorks University – tied in with its agenda HSQ Technology President Hal Spence shared results of the accountability breakout session focusing on evaluating effectiveness. to be an organization characterized by learning and development. He referenced progress since last year’s meeting and spoke about the necessity of accountability to grow and sustain our business. Attendees then broke into groups to brainstorm best practices in the areas of setting expectations, inviting commitment, measuring progress, inviting feedback, linking consequences and evaluating effectiveness. Day One concluded with remarks by HR Training & Development Manager Dave Mason on how the company is developing its learning and development program. Day Two featured Respect in the Workplace Day Three included departmental updates and 2012 objectives from Finance, Human Resources and Equipment as well as recaps from the prior day’s breakout sessions. The meeting concluded with a discussion of the 2012 business plan and wrap-up comments about the three-day meeting. Calendar Notes PNR RailWorks PNR RailWorks celebrated its 50th anniversary on September 12 at a special dinner near the location of its founding 50 years ago this month: Abbotsford, British Columbia. Members of late-founder George Braun’s family, including sons Henry, Erwin and Rudy Braun, joined with about 75 customers and employees to look back at the company’s transformation from a familyowned startup in British Columbia in 1961 to Canada’s largest railway track and signals & communications contractor. Other customer celebrations are scheduled in provinces across Canada throughout the remainder of 2011. Check out a 50-year timeline of milestones in the company’s history along with an anniversary video featuring comments from current employees. See PNR RailWorks’ homepage at www.pnrrailworks.com. training, a safety update, industry compliance considerations and breakout sessions on market opportunities, training and development and enterprise resource planning (ERP). During the afternoon the group worked at the not-for-profit organization Feed My Starving Children to prepare meals to feed starving children around the world. A new PNR RailWorks brochure highlights milestones in the company’s 50-year history. Sept. 28 Finance and Managerial Leadership Training, New York, NY Sept. 28 Employee Recruiting, University of Illinois, Urbana, IL Sept. 29 Employee Recruiting, Youngstown State, Youngstown, OH Oct. 2-5 APTA Annual Conference and Expo, New Orleans, LA Oct. 25-27 Annual Safety Summit, Long Island, NY Nov. 1-2 RailTrends, New York, NY