5.4 Case Studies of VDC for Lean Project Delivery
Transcription
5.4 Case Studies of VDC for Lean Project Delivery
Please comply with the Lean Construction Institute’s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. Bruce Cousins, AIA National Manager Virtual Design and Construction National Manager Virtual Design and Construction The Weitz Company Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 West Des Moines Health LEAN & VDC‐BIM & Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 West Des Moines Health VDC‐BIM Modeling d li • Project Chronology ‐‐ j gy Lean and VDC • Owner saw no value in Lean or BIM • BU Management agreed to do Last Planner – No BIM • No 3D model by Design Team – No 3D model by Design Team Project already Underway Project already Underway “Doing Doing this this will delay the project.” • Project Mgt. Team decided to use 3D coordination • Outsourced Arch/Structural Model – O d h/S l d l • Several Trades Provided 3D and others outsourced • Conducted BIM kickoff meeting with key trades • Used the 3D and 4D models for 6 week look ahead • Used 3D for Scope definition • PE ran 3D & 4D simulations at OAC, Job Site and Others PE ran 3D & 4D simulations at OAC Job Site and Others Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 3 3D MEP Coordination Findings 416 Logged and Corrected Collision Findings 416 Logged and Corrected Collision Findings Affecting a Minimum of 2 Subcontractors for Each Collision Hundreds of unlogged collisions by way of Hundreds of unlogged collisions by way of additional coordination tools for Subcontractor draftsmen Assume 2 Foreman (45/hr) and 1 hour saved per ( / ) p each collision corrected for the noted 416 items: $37,440… Time Saved: Minimum of 832 hours of focus on i items other than field fires (10.4 weeks for two h h fi ld fi (10 4 k f Foreman)… Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 West Des Moines Health 3D&4D C di i 3D&4D Coordination of Shoring Contractor f Sh i C Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Central Park Tower • • • • Broomfield, Colorado 305,331 SF Pursuing LEED Gold Certification 11 stories plus one level below grade 11 stories, plus one level below grade Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Central Park Tower Leveraging the Supply Chain h l h Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Leveraging the Supply Chain Leveraging the Supply Chain • Game changer for the way we: Game changer for the way we: – 3D Shop Drawings from BIM model – Define scope, procure, Define scope procure “buyout” buyout – Fabricate – Erect and place work E t d l k • Plan, Do, Check, Act! Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Copyright © The Weitz Company 2009 Structural Steel – Interactive Design Model / / Detail Model Handoffs il d l d ff Prepare Structural CD CDs INTERACTIVE Improve ImproveDelivery Delivery 35 Days 30 Days Total Structural Steel “Shop Drawings” – by Enhancing Design Model Review Steel Shop Drawings Review Steel Shop Drawings Fabricate and Deliver First Steel Package Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Integrated Cast in Place Concrete Design and C Construction i Structural Steel Embeds The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. Cast in Place Concrete O Openings And Blockouts i A d Bl k t Precast Concrete Embeds Steel Reinforcing for C t i Pl Cast in Place Concrete C t Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Comparison of Results Similar Projects Comparison of Results Similar Projects Village Center Station • • • April 2008 9 Stories Completed on Schedule Completed on Schedule Central Park Tower • • • April 2009 11 stories Currently ahead of schedule Currently ahead of schedule Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Comparison of Results Comparison of Results Village Center Station • 44 RFIs CIP core walls: – Reinforcing – Penetrations – Embeds Central Park Tower • Zero RFIs to date CIP core walls • These RFIs accounted for 14.77% of total on project • Cost range of RFIs $9 $97,549 ‐ 9 $161,549 $ 6 9 Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Summary of Owner Savings Central Park Tower l k • $25,986 $ , savings on rebar supply bid tab g pp y • $78,320 savings to date from actual quantity vs budget • $97,549 ‐ $161,549 savings when compared to RFIs on similar project • $201,855 ‐ $201 855 $265,855 $265 855 total savings to date with t t l i t d t ith model‐based CIP detail, fabrication, erection Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 VDC‐LEAN VDC LEAN Lessons Learned Lessons Learned • Project Project schedule “pulls” schedule “pulls” Erect → Fab → Check Shops (model) → Detail (modeling) → CDs! E Ensure schedule properly accounts for all tasks h d l l f ll k • Allow more time for model‐based CIP concrete design, fabrication, erection up front The time spent up front will pay for itself many times over •Work out means and methods preferences •Ensure printed lift drawings are in color, on proper page size. If not, readability suffers Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 VDC‐LEAN VDC LEAN Lessons Learned Lessons Learned • Timing is critical‐ especially initially • Challenge to project team to stay disciplined with design issuance – Major structural bulletin issued one week before caissons scheduled to start – Overcome feeling of “Just get the bar here.” – Balance benefit of achieving better quality with not starting on initial schedule Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Target Value Design (TVD) • Project Teams are responsible to the Owner to define the Problem • Problem Seeking vs Problem Solving • The Architect and the Contractor create solutions after The Architect and the Contractor create solutions after defining the “Problem” • The Owner, Architect and Contractor work as a team to solve the Problem solve the Problem Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 Charter Projects Charter Projects Charter Project – Concept Public School Reform Freed from rules in exchange for producing results Charter defines the “use use cases cases” • Target Value Design • Integrated Project Delivery Deli er • Revised project team – Sub Contractors & Suppliers • Shared Sh d risk i k with ith mostt tteam members b • Interrupting the supply chain Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 17 Charter Projects Charter Projects Top 10 Compelling Reasons for Charter Projects 1. Creates an incubation environment 2. Provides a structure for radical innovation 3. Innovation investments are concentrated & accounted for 4 Defines 4. D fi performance f standards t d d – “Use “U Cases” C ” 5. Allows rethinking of both financial & risk approaches 6 Targets brightest managers for future leadership 6. 7. Allows for Game Changing Ideas to develop & transfer 8. Experimentation is not done on owners dime 9. The charter is a “business plan” for the project 10. Grows Firm’s reputation as an Innovator Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009 18 Contact Information Contact Information Bruce C. Cousins AIA National Manager of Virtual Design and Construction The Weitz Company 4725 S. Monaco St., Suite 100 D e n v e r, C O 8 0 2 3 7 303-860-6631 bruce.cousins@weitz.com Leveraging Virtual Design & Construction for Lean Project Delivery Lean Design Forum ● St. Louis, MO ● June 18, 2009