Florida`s Long Span Bridges: New Forms, New Horizons
Transcription
Florida`s Long Span Bridges: New Forms, New Horizons
Florida's Long Span Bridges: New Forms, New Horizons I Antonio M. Garcia, P.E. Structures Design Engineer Florida Department of Transportation Tallahassee , Florida Antonio M. Garcia, structures design engineer, with the Florida Department of Transportation, is currently in charge of in-house design of major bridges. During his tenure as the state bridge engineer, many of the bulb-tee bridges discussed in this article were designed and constructed. Mr. Garcia also served as the FOOT's district director and project manager bringing the Sunshine Skyway Bridge to completion . Prior to coming to the FOOT in 1984, he was with consultants on various international and domestic structural projects. He is a registered engineer in Florida and has a BCE from the University of Florida and a Masters degree in structural engineering from The City College of New York. 34 After intense developmental work, an innovative continuous post-tensioned bulb-tee girder system was ready to be applied. A full-scale prototype structure - the Eau Gallie Bridge near Melbourne, Florida - was constructed and tested. The test results confirmed the overall structural efficiency, strength and ductility of the bulb-tee girder system. Also, the method of construction proved to be fairly routine and economical. The new bulb-tee girder has revolutionized bridge design in Florida, allowing longer spans and reducing the amount of substructure and foundation work. The system's efficiency and wide top flange also allow wider girder spacings while keeping deck construction costs down. Used with spans of up to 145ft (44 m), the system has become a very potent and competitive option for segmental bridge construction. Several projects, either built or in construction, are presented to show the effectiveness and aesthetic beauty of this new generation of bulb-tee bridges. y the 1980s, the technology that spawned the original AASHTO 1-beams was 30 years old. The beams had more than met their intended goals, but times were changing: sophisticated structural analysis, improved materials and fabricating techniques, and advanced constructio n methods were being introduced at a rapid pace. In 1983, patterned after work done by Washington State's Department of Transportation, Arvid Grant and Associates, Inc., Construction Technology Laboratories and other firms, Henry T. B o llm an n, c hief of th e Bureau of Structures , Florida Department of B Transportation (FDOT), and Paul F. Csagoly, then chief structural analyst, FDOT, introduced a modified bulb-tee girder combined with a staged posttensioning system. The potential saving s were apparent: continuity exte nd ed the girder's effective spa n range, allowed for wider girder spacings and provided redundancy. The FDOT' s three current bulb-tees (FBT) and a modified bulb-tee (MBT), discussed in the next section, are shown in Fig. 1. Table 1 compares the beam properties of all beams currently listed in Florida's standards plus the MBT. The time was ripe in Florida for developing the post-tensioned bulbPCI JOURNAL tee bridge. Engineering talent was there, the FDOT administration was receptive to the idea, and the need and demand were evident. All that was needed was an opportunity to apply the new system. 4'-0" "'2 E: Q) THE CHALLENGE The tragic events of May 9, 1980, when the bulk carrier Summit Venture destroyed the southbound Skyway bridge over Lower Tampa Bay with a loss of 35 lives, spurred stringent ship impact requirements. The added design load required increasing the structure's inherent load resistant capacity and/or reducing the risk by using fewer piers and longer spans. The Intracoastal Waterway (ICWW) winds its way around the Florida penninsula through many of the wide bays separating the mainland from barrier islands. Except for dredged channels, Florida' s coastal waters are relatively shallow, ranging in depth between 10 to 15 ft (3.0 to 4.6 m). Many fixed and movable bridges over the ICWW connect the barrier islands with the mainland. The fixed bridges usually consist of AASHTO 1-beam trestle portions [with spans of 50 to 80ft (15 to 24m)] and a three-span, contin uous, steelplate girder portion over the channel. Where right-of-way and other geometric requirements can be accommodated, high-level, fixed bridges are replacing the movable bridges. But with the ship impact requirements , simple span bridges are not as structurally efficient nor as economical as continuous, long span bridges. For Florida' s shallow water s and limited heavy commercial shipping (both in numbers of ships and in dead weight tonnage), a 130 to 160 ft (40 to 49 m) span range is usually most economical. Florida's first segmental bridges , built in the Florida Keys and completed in the early 1980s, have spans between 118 to 135ft (36 to 41 m). At about 145 to 150 ft (44 to 46 m), the segmental bridges' span-by-span erection method approaches its upper economical limit. Beyond that range , longer spans are achieved by balanced cantilever construction, although considerably increasing the structures ' cost. Steel superstructures can compete in the longer span ranges but are July-August 1993 1-- Q) Lt.. <oI 6Y2" '% '-!- "" I '~ "' .§ ~ 2'-6" 2'-6" FBT 54 FBT 5' - 0 63 11 4'-0" 3" 6)12" -t-1--- 7" bI <o 10" 2'-6" 2'-4' FBT 72 MBT Fig. 1. Cross section of Florida DOT standard bulb-tee girders and the nonstandard modified bulb-tee (MBT). Table 1. Florida DOT standard beam properties. Depth (in.) Weight (lb per ft) Area (in.') Moment of inertia (in.') Yt Yb (in.) (in.) Type II 36.0 384.4 369.0 50,979.0 20.17 15.83 Type III 45 .0 582.3 559.0 125,390.0 24.73 20.73 Type IV 54.0 821.9 789.0 260,74 1.0 29.27 24.73 Type V I 63 .0 1055.2 1013.0 521 ,163.0 3 1.04 31.96 Type VI I 72.0 1130.2 1085.0 733,320.0 35.62 36.38 FBT 54 54.0 817.6 784.91 311 ,765.0 28.11 25.89 FBT63 63 .0 878.6 843.4 1 458,52 1.0 32.88 30. 12 FBT72 72.0 938.8 901.26 638,672.0 37.64 34.36 MBT 78.0 1137.5 1092.00 930,538.0 37.2 1 40.79 Bea m type Notes: MBT is the modified bulb-tee de veloped by Janssen & Spaans Engineering, Inc., for Odebrecht Contractors of Florida on the Golden Glades HOY Viaduct project in Miami , Florida. It is not a Florida DOT Standard Beam. Metric (Sl) equi valents: I in . = 25 .4 mm, 1 in.' = 645.2 mm' , 1 in.' = 416,23 1 rnm' , I lb per ft = 1.488 kg!m. 35 0 TALLAHASSEE JACKSONVILLE Clearwater Pass () FT. MYERS Fig. 2. Location of Florida's bulb-tee girder bridges (as of May 1993). less desirable in Florida's extremely aggressive coastal environments. Simple span AASHTO 1-beam bridges cannot compete in span ranges of over 150ft (46 m). After Illinois, Florida was the next state to use post-tensioning combined with pretensioning on a limited number of projects in the late 1970s. Having designed AASHTO 1-beams in continuous post-tensioned bridge applications, accepting a more efficient beam was a logical sequence. Hence, the field was narrowed to concrete segmental bridges, using the span-byspan method, and to continuous posttensioned bulb-tee bridges. TESTING After developing the bulb-tee design on paper, the opportunity to test a fullscale prototype and a completed 36 bridge became a reality on the Eau Gallie Bridge project over the Indian River near Melbourne, Florida. The tests proved the system' s innovation, efficiency and cost effectiveness. The project was selected because: • As a state-funded project, the state had full and sole control of the project' s design (by in-house staff) , testing (by FDOT personnel) and construction (supervised by FDOT personnel). • Its size, 2900 ft (884 m) with a 91 ft (28 m) wide deck , allowed the amortizing of the new form costs without severely impacting the persquare-foot cost of the bridge. The construction contract called for testing a prototype "bridge" prior to the girder's full production. The prototype, tested at Gates Concrete Products Co. yard in Jacksonville, Florida, consisted of two full y instrumented girders, fabricated as they would be for the project and placed on simulated bridge supports, with a partial composite deck section cast-in-place, with the post-tensioning applied as called for in the bridge' s design. Two tests were performed: the first, on June 11 , 1985, tested the girders for design or service loads and to 80 percent of factored or ultimate load; the second , on December 5, 1985 , tested the girders to failure. The second test was described in Engineering News-Re cord' and later in Concrete International.2 After the Eau Gallie Bridge was constructed, it was load tested by the FDOT Structure Research and Testing ' s personnel and equipment in 1990. The results were published in a FDOT report by Mohsen A. Shahawy. 3 Both the prototype and the full bridge load tests, discussed in this artiPCI JOURNAL Concrete Blocks Test Live Loads (TypJ 290.00' (2 Span Continuous unitJ 145.00' 145.00' 48 .33' 48.33' 48.33' Fig. 3. Elevation of prototype bridge showing location of test live loads. Note: 1 ft = 0.3048 m. cle, validated the girder's efficiency and guided the development of standards for major bridges in the state. Fig. 2, a map of Florida, shows the location and distribution of the FDOT bulb-tee bridges as of 1993. 14 00' I .33' July-August 1993 I .33' I ~ 100 TonJocko--~ Pre-Construction Tests The prototype bridge consisted of two 145 ft (44 m) post-tensioned girders with a 10.33 ft (3.15 m) wide, 7 .5 in. (191 mm) thick slab. Concrete blocks, each weighing 2150 lb (975 kg) , simulated superimposed dead loads that the actual girders would experience. Live load was applied by four 100 ton (91 Mg) capacity hydraulic jacks placed at the third points of each span. Figs. 3 and 4 show the elevation and section, respectively , of the live load test arrangement. Fig . 5 shows the prototype bridge being tested. Load cells monitored the applied loads at the supports, embedded strain gauges monitored flexural strains , Whittemore gauges measured multidirectional strains at gauge points glued to each girder' s web, and thermocouples measured the temperature in the girders. Electronic deflectometers measured small deflections while optical methods were used for the larger deflections during the final test to failure. All electronic data were gathered in a computer-controlled data acquisition system housed in a mobile van parked adjacent to the test site. II .34' I II II II II - - - - -u ~r----- ~Concrete Blocks IL----..-----+i--~----JI w . .______ : r--' H 7.5" I I I +I Q "' - t- 10 .33' aq r- (\J Ground Line ·~~::f/ 14 .00' 1.33 8 2 1.33 11.34' I §L I I I I I I I I I I I I I Fig. 4. Section through prototype bridge girder showing concentrated live load test assembly. 37 Fig. 5. Test setup at Gate Concrete Products Co. yard, Jacksonville, Florida, June 1985- Eau Gallie Bridge prototype. June Test The first test simulated the design or service conditions required by the 1977 AASHTO Standard Specifications for Highway Bridges. These were: Live Load Factors Distribution factor (wheel line) Impact, I = 1.722 = 0.185 Design Moments, ft-kips (kN-m) Live load = 1805 (2447) Impact 334 (453) LL + I = 2139 (2900) Dead load = 4979 (6752) DL + LL +I = 7118 (9652) After the test, again, no cracking or signs of distress were found . December Test The second test carried the prototype bridge to failure, which occurred in compression in the bottom flange at the intermediate support. When initial crushing began, the girders had midspan deflections exceeding 18 in. (457 mm), evidence of a highly ductile system. A close-up of a deflected girder is shown in Fig. SA . At failure , the maximum applied load at the hydraulic jacks measured 185 kips (823 kN), corresponding to a live load moment of 8843 ft-kips (11990 kN-m) or 4.90 times the 1805 ft-kips (2447 kN-m) design live load without impact. The corresponding AASHTO requirement is 2.57 times (i.e., 2.17 x 1.185). The factored shear was 473 .5 kips (2106 kN) at the support, 1.13 times higher than the 420 kips (1868 kN) as determined by AASHTO. Factored Moments, ft-kips (kN-m) Live load 3911 (5304) Impact = 723 (980) LL +I 4634 (6284) Dead load 64 73 (8777) DL + LL +I = 11,107 (15061) The bulb-tee girders carried the full AASHTO design load with no cracking or any signs of distress. After the design load test, the girders were taken to 80 percent of factored loads in anticipation of the later test to failure. 38 Fig. 5A. View of deflected girder- Eau Gallie Bridge prototype. PCI JOURNAL @@ 4.50' @@ I I 4.50' I 21.50' 15.50' 45 .50' 15.630 lb 83 .720 lb 104 ,650 lb Weights : 72 ballast blocks Equipment Trailer Tractor 154,800 lb 8 ,200 lb 24 ,000 lb 17,000 lb Toto! Load Transfer: Steering axle Drive tandem Trailer tandem /5,630 lb 83,720 lb 104 .650 lb 204,000 lb Note : All weights and dimensions ore approximate and f or information only. /000 /b = 4.448 kN Fig. 6. Bridge testi ng vehicle. Post-Construction Tests The post-construction tests on the co mpleted Eau Galli e Bridge were conducted using the test vehicles of th e FDOT Structures Research and Testing.• Fig. 6 shows the vehicles ' dimensions and load distribution, Fig. 7 show s the Eau Gallie Bridge under construction and Fig. 8 shows the vehicles in position. The ballast blocks allow incremental loading up to the maximum AASHTO allowable lo ad Fig. 7. Eau Gallie Bridge under construction. July-Aug ust 1993 39 Table 4 lists the physical characteristics of the tensioning systems used (either pre- or post-), and Table 5 Jjsts the current total number of bulb-tee girders at various stages. Table 6 lists the total cost per square foot for the bridges, including substructure and superstructure, plus the bid cost per lineal foot of girder. Costs are from the contractor's bid tabulations as of the bid dates shown. BULB-TEE VS. SEGMENTAL BRIDGES Fig. 8. FOOT's Structures Research and Testing test vehicle in position to test the Eau Gallie Bridge. without endangering the structure. As with the prototype test, all electronic data were collected by the data acquisition system in the mobile van. Girders in the first two spans on the east end of the bridge had been instrumented with Carlson strain gauges . Vertical deflection was measured .at the bottom of the girders with linear vertical transducers (LVTDs) mounted on an independently supported aluminum frame. The two test vehicles were placed at six different locations and ultimate live load moments and shears were measured. The field test data were compared to an analysis of the bridge using BRUFEM (Bridge Rating Using Finite Element Methods). The finite element computer program was developed at the University of Florida, Gainesville. The maximum measured deflection was approximate'iy 1 in. (25 mm) compared to a calculated value of 1.35 in. (34 mm) , or about 75 percent of the predicted value. Maximum measured stresses were 76 percent of the analytical prediction and no shear cracks or other distress signs were observed. loads and small deflections in carrying actual loads. The testing gave the FDOT the impetus for developing standards and promoting the system's usage on later bridges. IMPACT OF BULB-TEE GIRDERS IN FLORIDA Test Conclusions The results of the pre-construction . (prototype) and post-constructwn (completed bridge) testing indicated excellent performance of the system, extreme ductility in carrying very high 40 0 The continuous post-tensioned bulbtee girder has revolutionized bridge design in Florida. First, it allows longer spans and reduces the amount of substructure and foundation work. Second, its efficiency and wide top flange allow wider girder spacings yet keep deck construction costs down. The post-tensioned bulb-tee bridge used with spans up to about 145 ft (44 m) became a very potent and very competitive ~ ption for the segmental bridges available for those spans. In addition, the girders are more economical, as prestressed simple span girders, than the Type V and VI AASHTO I-beams. Tables 2 and 3 list Florida's current bulb-tee bridges for post-tensioned "continuous spans and simple spans, respectively. In some cases, simple span I-beams or' bulb-tees are used for the approaches while the channel section is a three-span, continuous unit with a drop-in segment. As of 1993, five alternate designs of bulb-tee and span-by-span segmental concrete bridges have been let. In all cases the bulb-tee was the low bid, thus confirming our belief in the girders' competitiveness. The results have been conclusive, allowing us to forego alternate design s and thu s adding to the savings. The Howard Frankland Bridge over Upper Tampa Bay, which connects Tampa with St. Petersburg, is 16,000 ft (4880 m) long with a 70.83 ft (22m) wide deck. The project was bid as three alternate de signs : continuous post-tensioned bulb-tee, span-by-span segmental, and a combination of continuous post-tensioned bulb-tee approaches and a three-span, continuous steel channel section. Except for the steel channel alternate, all designs used 143 ft (44 m) spans. There were four bidders, one for the segmental (at 5 percent above the low bulb-tee bid), three for the bulb-tee, and none for the steel channel alternate. At the time, the FDOT design criteria for the segmental option called for internal post-tensioning. The second project, the Thomas A. Edison Bridge in Ft. Myers, Florida, consists of two separate bridges, each about 5000 ft (1520 m) long with 143 ft (44 m) typical spans, with girders spaced at 10 and 11 ft (3.05 and 3.35 m). The span -by-span concrete segmental alternate also used 143 ft (44 m) spans but with external posttensioning. Eight bids were received, with only one contractor bidding the segmental (at 15 percent above the low bulb-tee bid). The third bridge, not a Florida DOT project, was the 49th Street Causeway PCI JOURNAL in Clearwater, Florida. In this case, a simple span bulb-tee design was the low bid over a number of other option s, including a span-by-span concrete segmental bridge with external post-tensioning. The fourth bridge, the Golden Glades Viaduct in Miami, Florida, is entirely over land and was bid as a span-byspan segmental concrete bridge vs . a simple span AASHTO Type VI beam bridge. The project's strict maintenance of traffic requirements, at a location where 1-95 and the Florida Turnpike are intertwined with a number of other major state and local roads, gave the segmental design an advantage because it could employ "from the top" construction; yet none of the bidders chose the segmental design. The AASHTO Type VI I-beam aJternate was the low bid, but the contractor submitted a Value Engineering Change Proposal (VECP) for a modified bulb-tee (MBT), shown in Fig. 1. Although not a true comparison between two similar designs (a simple span girder bridge without post-tensioning vs. a post-tensioned continuous segmental bridge), the contractor saw his bulb-tee system as even more economical and efficient than the AASHTO 1-beam. The fifth bridge , the MacArthur Causeway Bridge in Mjarru , is part of 1-195 and consists of twin bridges, each about 2200 ft (671 m), over the ICWW connecting Mjami and Miami Beach. The new bridge will replace an existing two-leaf bascule bridge. The de s ign alternates were a bulb - tee bridge and a span-by-span concrete segmental bridge. Both alternates used 144 ft (44 m) span arrangements with a smaller three-span section at both ends. There were eight bidders and all bid the bulb-tee bridge alternate. CONSTRUCTION Web Width and Duct Characteristics The web width and duct configuration have evolved from the Eau Gallie Bridge until the most recent project, and is a case study of how design and construction are interrelated. Each step in the girder's fabrication, transportation and erection was considered in July-August 1993 Table 2. Post-tensioned, continuous bub-tee bridges. Location Eau Gallie Number of spans Span length (ft) 20 1-15 Total length (ft ) 2900 Deck width (ft ) Girder spacing 90.64 10.33 (ft) ---~ Howard Frankland 110 143 15.873 AP 42 142 5964 c 3 160. 200. 160 520 NB 36 143 SB 32 3 Choctawhatchee 70.83 10.00 46.83 9.76 51-18 59.08 10.00 143 4576 6508 11.00 196. 250. 196 642 47.08 9.50 142 3834 49.04 10.00 140.5 3372 54.04 11 .00 130. 145 2130 68.08 10.00 43.08 11 .33 85.08 9.56 Edison Highland View. channel span NB 27 SB 27 Merrill Barber Anna Marie 24 EB 15 MacArthur WB AP 90 144 12.960 c 3 144, 234.5 , 144 522.5 3 160, 200, 160 3 122.25 8 137.0 8 148.0 8 149.0 16 132 Gandy Bridge St. John's River. channel span 520 11.25 Vilano 3839 53.04 9.00 AP EB 2 11 2 10.00 49.04 c Flagler Beach 3 c 161. 230. 161 8.00 552 8.50 WB 43.08 AP 16 132 2 11 2 11 .33 Notes: C denotes a continuous, three-s pan channe l unit in which the centra l unit is a drop-in segment. AP denotes the approaches which may be made up of groups of three of four continuous spans. NB = northbound, EB =eastbound, WB = westbound , SB = southbound. l ft = 0. 3048 m. achieving an optimal and efficient design. Each preceding project contributed lessons for the next project until we arrived at our current standard - and we continue to improvise certain details, as di scussed in the following paragraphs. A critical issue is that post-tension- ing systems require close attention to detail s. Actual dimensions should be used rather than nominal dimensions. For example, for reinforcing bars, the out-to-out dimension at the bar deformations is used rather than the nominal bar diameter. Duct out-to-out dimensions, including the corrugations 41 Table 3. Simple span bub-tee bridges. Number of spans location Span length (ft) Total length 113, 122* 2834 (ft) Deck width (ft) Girder spacing 43.08 8.75 (ft) -- 25 SB Structure "A" NB EB WB 1 9.50 I 116 2088 3 108 324 I 52.54 3 White City, approaches 4 6 I 21 65 1 112.56 I 10.00 I 1- 1133 116.05 112.58 120 - 12.00 338 113.33 - 10.75 68.08 10 Golden Glades 56.04 2834 18 St. John's River Clearwater Pass I 113,122* --+---25 West Bay, approaches MacArthur -- I - 85.08 9.56 1140 46.03 9.25 2520 59.00 I -- 10.00 : I 135 to 150 6308 Vary Vary Notes: The * denotes the channel span length. NB = northbound, EB =eastbound, WB =westbound. SB =southbound. I ft = 0.3048 m. and manufacturing tolerances, must be used. Duct splice locations within the beam need to be carefully considered because the splice constitutes a thickening of the duct. Also, placement tolerances allowed in both the side form manufacture and installation, and placement of the reinforcement cages and ducts, must be taken into consideration. The saving grace is that the tolerances are not cumulative since the ducts and reinforcement are all tied together prior to setting the side forms. Once the forms are set in place, the fit is easier to achieve. However, there is little tolerance for sloppy workmanship, thus requiring the best from the fabricator and the inspectors. The Eau Gallie Bridge design used four circular ducts in a 6.5 in. (165 mm) web, #4 (#15) vertical web reinforcement and a minimum 1.5 in. (38 mm) of cover. After the job was awarded, the contractor proposed three circular ducts and a modified post-tensio ning sequence. One less duct and anchorage was a real savings in both material and labor in manufacturing the girders and in the post-tensioning. The fewer ducts required parti al post-tensioning (tendons stressed to 50 percent of design) at the first stage , 42 thus exposing the stressed tendons to the elements for an extended period of time prior to grouting. Although subsequent tests showed that the tendons were sati sfactory, the FDOT now requires 100 percent of the specified post-tensioning force at each stage and fully grouted ducts as soon as possible. For the Howard Frankland Bridge design, the web was increased to 7 in. (178 mm) to accommodate increased cover requirements [from 1.5 to 1.75 in. (38 to 44 mm)], three round ducts, and #4 (#15) vertical reinforcement. External vibration was required in all areas except in the anchor block region where the wider web could accommodate internal vibrators. However, the ducts , as designed , provided a net area of twice the tendon area as allowed by Section 9.24.4.1 of the AASHTO Specifications and the Post-Tensioning Institute (PTI) - yet the post-tensioning specifications for the segmental alternate called for 2.5 times the tendon area. The contractor pointed out that he could not concurrently meet the larger net area requirements and the placement tolerances and, as a solution, proposed a 7.5 in. ( 191 mm) web which was accepted by the FDOT. For the Choctawhatchee Bay Bridge, designed entirely by the FDOT Structures Design Office staff, a new duct shape was introd uced that wou ld achieve all the requirements within the 7 in. (178 mm) web. The oval duct has become the standard in all subsequent post-tensioned bulb-tee bridges. Several manufacturing methods for the oval duct were considered, with an extruded corrugated polyethylene duct meeting the design requirements. The supplier had first tried compressing a round galvanized metal duct into the oval shape, but the results were not acceptable bec ause sharp edges were formed at the top and bottom of the duct. The corrugated polyethylene duct require s close wall thickness tolerances. If the walls are too thick, placement tolerances are reduced ; if they are too thin, they will collapse under the wet concrete's hydrostatic pressure . A test was devised whereby a small section of duct is placed in a form and concreted to a level above the top of the duct representing the hydrostatic press ure expected in girder production. After the concrete has set, a "torpedo," with dimensions slightly less than the duct but providing the desired gross area, is run through the duct. If the torpedo passes through, it indicates that the duct wall s have minimal deformation in resisting the hydrostatic pressures. For the Highland View Bridge (see Fig. 17) under construction in May 1993, the contractor proposed an oval metal duct whose manufacturing process eliminated the unacceptable sharp edges mentioned earlier. Some projects bid in May 1993 have requested substituting the metal oval duct for the polyethylene shown in the plans while projects under design as of May 1993 will show the metal oval duct. L imiti ng the number of splices is important and achieved with very flex ible ducts that can follow the desired tendon trajectory with few splices. Both the polyethylene and the new metal oval ducts can easily accommodate the trajectories called for in the bulb-tee. The metal oval duct can be formed to the required radii without crimping the surfaces. Also, each splice must be considered a potential leakage point and the PCI JOURNAL Table 4. Physical characteristics of tensioning systems. Post-tensioning tendons Pretensioning strands I Concrete strength I Number of ducts Strands per duct Force (kips per strand) Duct shape 4 6 each 41.5 RS I Project Eau Gallie Howard Frankland Approach 3 7 each 2,1 8 each, 12 45 Choctawhatchee I I 46.9 Channel RS 12, 9, 10 NB 3 9 each SB* I, 2 10, II 122 3 7 each 46.9 137 2, I 9 each , 7 46.9 3 8 each 46.9 llighland View* 3 14 each 46.9 OS Anna Mariat 3 10 each 46.9 OS EB 2, I 8 each, 13 WB 2, I 7 each, 12 Vi lano* 46.9 I I Flagler Beach* 148, 149 Pier St. John ' s River 3 8 each I 12 3 9 each 9 each 9/16 38.88 36 1/2 31.0 26 1/2 31.0 24 1/2 J I Girder (psi) r 3400 3400 6000 I 6000 4500 6500 31.0 3400 6000 1/2 38.89 3400 6500 24 1/2 3 1.0 3400 6500 28 J/2 31.0 3400 6500 1/2 30.99 3400 6500 36 1/2 31.0 5500 6500 26 1/2 31.0 3400 6500 32 1/2 31.0 3400 6500 22 4 and 26 OS 28 B 18 OS B 30 45.4 3 24 ! Deck (psi) T26 I 46.9 MacArthur* I I Merrill Barber 41.36 I 13, 9, 8 Drop-in 9/16 OP 46.9 3 22 (kips) 26 Back span I Size (i n.) I Force of strands OP I, I, I Edison I Number I OS OS I Notes: Continuous bulb-tee usage is listed (May 1993). The * denotes under construction and the t denotes in design. All strands are 0.6 in. diameter, 270 ksi low-relaxation strands except Eau Gall.ie, which are 9/16 in. diameter. RS refers to round steel ducts, OP refers to oval polyethylene ducts, and OS refers to oval steel ducts. NB =northbound, EB =eastbound, WB =westbound, SB = southbound. l in . = 25.4 mm, 1000 psi = 6.895 kPa, I kip= 4.448 kN. duct corrugations must be such to allow placement of a tight sleeve. It is important to prevent duct di splacement during casting by securely tying it off at close intervals along the girder length. Inspectors a nd yard personnel should understand the importance of the duct' s placement and trajectory . The indiscriminate use of internal vibrators can physically damage the duct itself as well as affect its horizontal positioning within the web. Di splacements which create kink s can damage the girder once it is post-tenJuly-August 1993 sioned. Only external vibration should be allowed along most of the beam length, and internal vibration should be allowed only in the thicker anchorage areas. In all cases, once a girder is cast, a torpedo s hould be pulled though the duct and all interferences removed before the girder is accepted and shipped to the job site. The task is not as complicated as it may appear. Its economical success is evident in the number of successful bridges built in Florida, and in the even deeper and thinner webs used in other parts of the United States and Canada. There have not been any reported problems in placing tendons in the oval ducts , in providing the required tolerances or in consolidating the concrete. Pretensioning The bulb-tees are pretensioned for their own se lf-weight plus an allowance, ranging between 30 and 40 percent of the girder's self-weight, for handling , shipping and construction loads. Others may find that their fabrication and construction requirements 43 Table 5. Number of bub-tee bridges- various stages. Total span Girders length I per (ft) span Bridge Eau Gallie Total number of girders I Duct shape Under In I construction design I Built 2900 9 RS 180 15.873 7 RS I 777 6484 5 OP 325 5148 6 OP 216 4576 6 OP 642 5 OS 3834 10 OS 3372 5 OS ~~ Howard Frankland I Choctawhatchee j I - -Edison -': j ~ B Highland V1ew l 192 15 - I - _..,.;u """'= I Anna Maria 270 ~ 120 1463 Vilano I I I 5 OS 6 OS 5/6 OS '--- 2376 I 55 I 96 -~~-- Flagler Beach I :~t 2664 2664 4/5 OS 2834 617 n/a 2834 617 n/a 2088 5 n/a 1653 9 n/a 2520 7 n/a Vary n/a 7 OS 6 OS 4 OS 98 I - I 79 I - NB Structure "A" - - I SB r-------- l I West Bay ~ I --- St. John ' s River - 1- I 90 6308 EB - WB Total r- - 90 147 I r 2454 I 13,483 88,638 I 266 126 ~ 2468 Gandy Bridge I - Golden Glades MacArthur 175 ~ + Clearwater Pass - 175 I I 1763 _==r 1008 - 108 - 829 Notes: Girders per span is the number of girder lines per span. Where two numbers are given, the first refers to the approaches and the second to the channel spans. Duct shape is the post-tensioning duct shape used. RS is for round, steel; OP is for oval, polyeth ylene; and OS is for oval, steel. NB =northbound, EB = eastbound, WB = westbound, SB = southbound. I ft = 0.3048 m. differ from these. Nevertheless, some allowance should be used. In addition, the pretensioning force causes a slight positive camber to the beam. The result is a nearly flat profile without the noticeable upward bowing common to AASHTO 1-beams. Because the pretensioning is only for slightly more than the girder weight, camber growth is reduced, thus eliminating problems when decks are cast. 44 Post-Tensioning and End Anchorage Post-tensioning should proceed simultaneously from both ends of the unit. We have found that a reasonable strand pull is 580ft (177m) [i.e. , four spans of 145 ft (44 m) each] . Longer pulls, the equivalent of five 145 ft (44 m) spans, may be possible but have not been used yet. For longer pulls, post-tensioning wobble and fric- tion losses may significantly affect the girder' s load carrying capacity at interior locations. The post-tensioning sequences are s hown for the Howard Frankland Bridge in Fig. 10, the Cboctawhatchee Bay Bridge in Fig. 11 and the Edison Bridge in Fig. 12. Generally, post-tensioning is done in the following stages: First Stage: After the pretensioned beams are placed on their supports and end diaphragms are cast, the continuity post-tensioning, top- or bottom-most duct, is completed. This is followed by the middle duct post-tensioning, designed to carry the form and deck concrete loads. Second Stage: The third duct posttensioning force acts on the composite section and is designed to resist live load and secondary dead load effects. Grouting is done after completing each post-tensioning operation . The post-tensioning sequence should start with the middle girder line and proceed outward toward the fascia girder lines. In dimensioning the girder's anchor block-outs , the dimensions of the stressing equipment and clearances to adjacent girders are important. Early anchorage layouts had them coplanar with the web and exiting through the girder' s top flange. The exposed anchorages will collect debris, dirt and water. It is important to seal the duct openings after girder fabrication and to provide some means of positive drainage at the low points. The evolution of the anchorage layout from project to project can be seen in Figs. 9 through 13. For the Eau Gallie Bridge, a rectangular opening was left exposed (see Fig. 9) which was concreted at completion of the post-tensioning. For the Howard Frankland Bridge, the entire deck width between the expansion joint and the third tendon's anchorage was left open (see Fig. 10) until after the post-tensioning was completed . The deck reinforcement was then placed and the last of the deck concrete poured. The advantage was that the jacking operation could proceed uninterrupted by any reinforcement; the disadvantage was that the screeds had to be brought back to finish the deck. For the Choctawhatchee Bay Bridge, a small rectangular area (see Fig. 11) PCI JOURNAL Table 6. Unit costs for completed Florida bulb-tee bridges (as of bid date). Bridge Eau Gal!ie Bid date Bridge ($per sq ft) Girder ($per ft) June 1984 33.37 104.24 Howard Frankland May 1987 35.33 109.51 Choctawhatchee June 1988 55.56 109.08 Edison, NB August 1990 46.58 139.70 Edison, SB Augu st 1990 47.05 147.04 White City* October 1989 55.53 92.00 West Bay * March 1990 52.63 125.00 Highland View May 1991 46.93 119.10 Structure "A." NB* July 1991 55.82 87.11 Structure ''A," SB * July 1991 54.60 87.11 June 1992 62.9 1 St. John 's River I I 143.94 Notes: Simple span bridges are denoted with*; tbe others are continuous systems. The girder costs include all the post-tensioning costs, i.e., material and installation labor. NB =northbound, SB =southbound. $ 1 per sq ft = $ 10.76/m' , $ 1 per ft = $3.28/m. exposed only the last anchor. This was accomplished by stressing tendons two and three in Stage 1 and tendon one in Stage 2. The advantage was that only a small pour remained; the disadvantage was that the previously placed reinforcement had to be bent out of the way , bent back in place, and then lapped prior to pouring the concrete. An innovative anchoring arrangement was developed by the consultant for the Edison Bridge. Only one anchorage exited through the girder' s top flange, while the other two exited at a sloped cut in the web near the end of the girder. Figs. 12 and 13 show the arrangement. The advantage was that only a small pour was required, and it could be done in conjunction with placing the expansion joint. This arrangement appears to be the best, although a variation on this would place all three anchors in the sloped girder surface. before the release of the pretensioned strand. In any case, curing is very important and each location needs to use the best method possible. AESTHETICS The longer spans achieved with the bulb-tee result in a very slender looking bridge. Al so, the rounded comers where the web meets the flanges eliminate horizontal lines that would normally detract from the fascia's aesthet- Aggregate Size Smaller aggregates [ ~ and 7:1 in. (13 and 19 mm)] are preferable, along with, in some cases, superplasticizers. It is important that concrete fills all the voids, especially in the areas between ducts and in the commonly congested anchorage. ics. The rounded corners also facilitate the concrete pour by eliminating air pockets, thus reducing honeycombing. Several other items have helped improve bridge aesthetics and some have improved the rideability. For example, since the girders are pretensioned for a little more than their dead load, they do not have the "scalloped" appearance of simple span A;.SHTO 1beams that are pretensioned for all the loads . The added benefit is an improved rideabi lity in contrast to the camber growth common with time in AASHTO 1-beams. Expansion joints are a never ending maintenance problem that, in time, will leak. Post-tensioning eliminates at least half the number of expansion joints and the attendant problems. One other consideration that affects the overall appearance is the continuity of the superstructure' s soffit for the full length of the bridge. That is , rather than use a variety of spans with changing girder depths, we encourage designers to keep the span lengths constant from end to end. Proper deck drainage is very important. Some Florida bridges allow water to fall freely to the ground. If deck scuppers exit the bottom of the deck near the girder, we extend the lip 1 in. (25 mm) below the deck soffit to prevent unsightly stains along the girder' s fascia. Drainage requirements can be very costly if, for example, an expensive collector system is used. Using larger deck drains with down spout into the first interior bay and piped down through the pier to an outfall near the ground or water surface is a viable solution in Florida. Our climate allows us this luxury that would cause severe problems in areas of the country where freezing is a common winter occurrence. The piers, however, offer the most exciting potential for improving the aesthetic qualities of our bridges. The Edison Bridge (see Fig. 14) is an example of what can be done . In this particular case, a series of precast concrete segmental pier units* have been designed that, together, offer increased Curing Wet curing with burlap and soaker hoses is very effective in eliminating the shrinkage cracks that can develop July-August 1993 Fig. 9. Anchor block-out in the Eau Gallie Bridge deck. * "Precasting the Edi son Bridge" by Theun is A. van der Veen (HDR, Inc.), paper presented at the PC! Convention, Nashvi lle, Tennessee, October I 992. 45 I I L -1£-~-~~ ~ -------------- ------+------------ ~ -----·----- 1~ -------- - ----- DECK PLAN I' I' I' i ~-~~?Z~~~~~~==~ I #'0 #2 ; ~--------------------~ Tl ~~ if Expansion joint m ;......___if Pier BEAll ELEVATION I . Placed stee.tes on ducts 2. Pour closure ond diapllrO(}m corcrete 3 . Stress tendons #f and #2 and grout 4. Pour deck up to tendon #3 onchorO()e. Note all ducts at intermediate pier located in or below the beam top flange 5 . Stress tendon #3 and grout 6. Pour rerooinder of deck leaving opening for expansion joint Fig. 10. Post-tensioning sequence for Howard Frankland Bridge. I rl"7"ti'z'+::.~::-:: : .: .· -- --- - --L - ~~~ -- ~~ -------- ii.,.<-H;.,.<-,.+':.:. -~:!- ~: :':~ - - -- - - - - - -- tzc~~;~~+~~~~~~~--~--~~ - - ---------~-------------1 ' ! DECK PLAN #3 "~""""'"""'.... #2 ~.,..,..,........_ #t m f-.-___ I£ Pier BEAU ELEVATION I. Placed slee.tes on ducts 2. Pour closure and diophrO(}m corcrete 3. Stress tendons #2 and #3 and grout. Exposed tendon #3 slee.te at intermediate pier was difficult to seat becouse corrugated CNol duct connection could not be properly aligned between two ends 4. Pour deck leoving tendon #f orchorO(}e exposed. SletNes for tendon #3 ore thus ercosed 5. Stress tendon #t and grout 6. Pour rerooinder of deck t00o1ing opening for expansion joint Fig. 11 . Post-tensioning sequence for Choctawhatchee Bay Bridge. 46 savings and an aesthetically pleasing solution . Both the pier columns and the pier cap are precast, shipped to the site, placed, post-tensioned vertically and grouted. It is a quick, efficient, effective and elegant solution. Bridge aesthetics is in revival and many articles, publications and conferences are addressing the issue. Some states, such as Maryland, are preparing extensive guidelines addressing aesthetics; other states such as California, have for many years made aesthetics an integral part of design. FURTHER DEVELOPMENT NEEDS A series of issues, related to design, specifications, construction and maintenance, have developed since we first began working with the post-tensioned bulb-tee. Some are presented for further consideration, but not in any particular order of importance: 1. Vibrations -- Vibrations have become more noticeable with the advent of longer span bridges. Maintenance inspectors have begun questioning this common phenomenon and we are considering means of measuring, quantifying and comparing the vibrations experienced on these bridges with that of other bridges. During the early development of the bulb-tee, the calculations showed a potential for a low and acceptable frequency. 2. Negative Camber -- On the Howard Frankland Bridge, negative camber, between 0.5 and 1.5 in. (13 and 38 mm), was evident in many girders at the time they were placed on their bearings. This indicates that a higher pretensioning force might have solved the problem. 3. Top Flange Edge -- Initially , there was concern that the unreinforced top flange edges would be easily broken off. The edge, 2 in. (51 mm) thick, is vulnerable to numerous actions during fabrication, yard movement, transportation and erection. Of all the girders used to date, very few have experienced damage and none so severe that corrective action or rejection was necessary. 4. Discoloration -- This phenomenon is sometimes seen as a darkening that accentuates the duct profile. PCI JOURNAL / ~Beam I f -- z -==-=-~=-----~- -==-=-~=- - ~- -==-===----~--, --------------~ --- ------- ---1 I I I DECK /"LAN m 1---....__ ~ Pier BEAll ELEVATION I. Placed sleetes on ducts 2. Pour C1osure and diaphragm roxrete 3. Stress tendons #! and #z and grout 4. Pour deck except for cross-hatched area ixluding rendon #J axlrJroge 5. Stress tendon #3 and grout 6. Pour remainder of deck IB<Ning opening for ex{XJnsion joint Fig. 12. Post-tensioning sequence for Edison Bridge. This does not occur in all post-tensioned girders but appears randomly. Its cause and elimination are still to be determined. 5. Specifications - Although the 1989 AASHTO "Guide Specifications for Design and Construction of Segmental Concrete Bridges" covers posttensioned bulb-tee girder bridges (Section 1.1, General), on some issues we rely on our research and experience. There are some issues applicable to post-tensioned segmental box girder bridges that are questionable for the bulb-tee. One is the net duct area, mentioned earlier. Both AASHTO and PTI recommend that the net duct area be twice the strand area. For segmental bridges with larger tendons and a tendon profile that varies both vertically and horizontally, the 2.0 value may cause undue tendon placement problems and 2.5 is usually required. But on bulb-tee bridges, with a tendon profile that varies only in the vertical plane, we have not seen any problems in placing tendons. This may suggest that a value of 2.0 is applicable to bulb-tees. July-August 1993 6. Fabrication- Unquestionably, good workmanship is imperative for these girders; if it is not available or enforceable, problems will arise. A conscientious workforce at the yard is essential and personnel must understand what and why they need to do what they must do. As in all work of this nature, whether it be precast or cast-in-place, segmental or bulb-tees, good workmanship is essential to a successful job. There is little room for sloppy work. 7. Ducts- Some problems with the polyethylene ducts have surfaced. They relate, however, to thin walls and improper storage that result in "hour-glass" shapes that create blockages in the trajectory. Artificial means of maintaining the oval shape, such as inflatable hoses, have had limited success and should not be relied on in place of properly manufactured ducts. Of all the girders cast and in place (see Table 5), four have each developed a crack following the tendon trajectory, extending from the web transition area (the area where the web thickness begins to neck down) into the 7 in. (178 mm) web area for a few feet. The cracks were not noticed until the final cleanup work had begun. An analysis of these girders by an independent laboratory has shown that, aside from the visible cracks, some vertical delamination occurred in the webs. Tests along the remaining length of each girder showed neither an external nor internal crack. Why these four girders, out of the more than 408 placed, should have cracked has not yet been determined. Excessive grout pressure resulting from a blockage may be a possibility. A series of tests Fig. 13. Post-tensioning anchorages are located in sloped portion of the end blocks of the Edison Bridge. 47 have been proposed to resolve and answer questions raised by this phenomenon. In the meantime, the girders were analyzed and found to be acceptable after pressure grouting the cracks. EXAMPLES OF FLORIDA'S BULB-TEE BRIDGES Fig. 14. The completed north bound Edison Bridge. A sampling of bulb-tee bridges in service or at various stages of construction as of March 1993 is included. These are: Fig. 14 shows the Thomas Alva Edison Bridge across the Caloosahatchee River in Ft. Myers, Florida. The completed northbound bridge is shown; the southbound bridge was still under construction in early 1993. Fig. 15 shows the Choctawhatchee Bay Bridge under construction and Fig. 16 shows the completed bridge. It was Florida's first drop-in design with a center span of 200ft (61 m). Fig. 17 shows the Highland View Bridge, near Port Saint Joe, Florida, under construction in March 1993. At the time of construction , it was the longest - 250 ft (76 m) - drop-in span bridge in Florida. CONCLUSION Fig. 15. Channel span erection for the Choctawhatchee Bay Bridge, back span support and hangers for drop-in segment shown . Fig. 16. Completed channel span and approaches for the Choctawhatchee Bay Bridge. 48 The continuous post-tensioned bulbtee bridge has become common in Florida. Many fabricators have purchased forms and many more designs are being produced (see Tables 2 and 3). Our consultants have gained the design experience necessary to produce the contract plans and our field forces , both those in the yards and at the job sites, have gained much experience with the bulb-tee girders. Costs have been very competitive and are not much more than the costs for simple span AASHTO 1-beam bridges. Table 6 lists some of the cost data available as of March 1993. All post-tensioning work requires a high level of care in design, fabrication and construction . The bulb-tee is no exception; it is not "idiot proof' - no system can be. Yet when proper care and attention is given to the details, when the fabricator and the suppliers perform acceptable work, and when the contractor pays attention to his PCI JOURNAL in some of the later testing and offered invaluable assistance in interpreting the results. Douglas Edwards , FHW A's Florida Division Bridge Engineer, has listened to many of our arguments and agreed with most. Others in the FDOT Structures Design Office in Tallahassee, such as Clark Williams, and members of his Consultant Plans Review Group, helped gather the data, review the document and, more often than not, kept me in line. To all of them I respectfully acknowledge their assistance and offer my thanks. REFERENCES Fig. 17. Highland View Bridge under construction, May 1993, showing 250 ft (76 m) drop-in section in place. work, the results are beneficial to all. In Florida, we have seen the results of good work in the many bulb-tee bridges successfully built and in service. There will be the occasional bad duct, poor consolidation or cracks, as seen in every system used ; but this system is viable, economical and aesthetically pleasing. We are approaching the era when even longer spans, in the 150 to 160ft (46 to 49 m) range, should be considered. Also, with the proliferation July-August 1993 of the drop-in segment design, spans of 250 ft (76 m) may become more common. ACKNOWLEDGMENT There are many individuals who have , in one way or another, contributed to the preparation of this paper. Henry Bollmann and Paul Csagoly were instrumental in implementing the girder's use in the first place. Mohsen Shahawy was involved 1. "Test Girder Shows Strength," Engi- neering Ne ws-Record, December 19, 1985, p. 29. 2. Csagoly, Paul F. , and Nickas, William N. , "Florida Bulb-Tee and Double-Tee Beams," Concrete International, V. 9, No. 11 , November 1987, pp. 18-23 . 3. Shahawy , M. , and Garcia , A. M ., " Structural Research and Testing in Florida ," Transportation Research Record 1275, Transportation Research Board , National Research Council , Washington, D.C. , 1990. 4. Shahawy , M. , " Strength Evaluation and Load Testing of the Eau Gallie Bridge," Structures Design Office Report, Florida Department of Transportation, Tallahassee, FL, 1991. 49