Deal sea defence scheme - South East Coastal Group
Transcription
Deal sea defence scheme - South East Coastal Group
Deal sea defence scheme October 2012 Newsletter no. 5 We are writing to update you on the progress of the Deal sea defence scheme. Work on the scheme has been progressing well since our last newsletter in September. The shingle and rock deliveries are now complete and we will be starting work on the wave wall shortly. There has been plenty to see during the works so far and we hope those of you who have been able to visit the sea front have enjoyed watching the works. Staff from our contractor Westminster Dredging and Dean & Dyball have been answering lots of questions from spectators. If you have a question, don’t hesitate to ask them! In order to complete the scheme before the worst of the winter weather arrives, we are working very quickly, so there’s always something new to see on the sea front. We are keen to hear what you think of the works. Drop us an email or write your feedback in our comment book at the Royal Hotel. Timescales Rock works Shingle works Work on new wave wall Works substantially completed From 1 October for approx 8 weeks From week commencing 17 September for approx 6 weeks From week commencing 8 October Christmas 2012 Although, the works will be substantially complete by Christmas there will be a period of tidying up and removal of our site offices in January 2013. The works Rock The new 200m long rock revetment to the north of Sandown Castle will strengthen the existing defence by absorbing the wave energy. We started delivering the rock to Deal on 15 September, bringing it on a barge which had taken five days to travel from Norway, across the North Sea. We began constructing the new rock revetment on 1 October, by removing the existing rock. We are now carefully placing the individual rocks into their correct position on the beach. We will be using three sizes of rock to build the revetment. At the base will be a layer of small rock providing a stable platform. On top of that we will position a mixture of 3-6 tonne and 6-10 tonne rocks. We can only do the rock work during low tides. In order to finish this work as quickly as possible before the winter storms we will need to work during both of the low tides each day. Due to the timing of the tides this may mean that we will need to work at night. This element of the scheme will be complete by mid December 2012. Shingle We have used an off-shore dredger, the Prins der Nederlanden, to deliver approximately 120,000 cubic metres of shingle through a pipeline to recharge the beach between Sondes Road and Sandown Castle. This part of the scheme alone will cost approximately £3 million. The new wave wall is designed to reduce the wave energy and direct the waves back into the sea. It will also reduce the amount of shingle which is thrown up onto the road. The overlapping design will reduce the power of the waves while maintaining public access to the promenade. The pipeline was placed on the beach on 12 September, with the first shingle delivery arriving on 19 September. We have started to prepare the wall site by removing the shelter and beginning some excavation works. The wall units will start arriving by road from the beginning of November. Due to the depth of the seabed off-shore, we have been limited in the number of times we have been able to reposition the pipeline. This is why we have been using dumper trucks to move shingle along the sea front. Site staff will be working on the promenade between 8am and 6pm, Monday to Saturday. We expect the wall to be substantially complete by Christmas 2012. We received our final delivery of shingle on 10 October. This was our 17th delivery. Although the off-shore dredger has left Deal, our contractors are still working on the beach to push the shingle into the correct beach shape. We expect to finish this towards the end of October. Ways to find out more Our monthly newsletters keep everyone updated on the progress of the works. Newsletters will be available on our website or at the Royal Hotel. You can sign up to receive an e-copy of the newsletter, by emailing us at: DSDS@environment-agency.gov.uk. Our webpage: www.environmentagency.gov.uk/deal Our staff - don’t hesitate to ask our site staff any questions you have or contact us by using the contact details below. Tell us what you think We are keen to hear what you think of the works. Please drop us an email or write your feedback in our comment book at the Royal Hotel. To do the works safely, we have closed the sections of beach where we are working. We expect to reopen the beach at the end of October. Wave wall We will start constructing the new wave wall shortly. It will be positioned on the promenade just south of Stanley Road and will end at King Street. The work will continue to be exciting and we are looking forward to talking to you on the seafront about the works. Please don’t hesitate to contact us with any concerns or questions you have and we will do our best to resolve them. Who can I contact about the project? Verity Kirstein, from the Partnership & Strategic Overview team on 03708 506 506 or via email: DSDS@environmentagency.gov.uk