Road, rail and subway tunnels by the Reichtag, Berlin
Transcription
Road, rail and subway tunnels by the Reichtag, Berlin
Road, rail and subway tunnels by the Reichtag, Berlin, Germany Ole Peter Jensen &KLHI3URMHFW0DQDJHU&2:,$6'HQPDUN ABSTRACT: After reunion of West and East Germany, there has been a great effort to re-connect and upgrade the infrastructure between the two former German States. The project consists of three tunnels, constructed as cut & cover tunnels. The eastern tunnel is a two tracks U-Bahn (Metro) ending in an underground station close to the new parliament for Germany (Reichstag). The central tunnel contains tracks for the ICErailway, starting with eight tracks at the north end and narrowing down to four tracks at the south end of the project. The western tunnel is a four-lane highway tunnel. All tunnels were constructed in one single construction pit. 1 GENERAL DESCRIPTON In 1995 the contractor Spie Batignolles GmbH together with COWI as consultant won the project “Projektlos 2 - Spreebogen” for a contract sum of 0.2 billion US$. COWI was responsible for the detailed design and planning of the construction pit and the tunnel structures. Furthermore, for the planning of the diversion and the following re-establishing of the river Spree. Other temporary works were included in the design. )LJXUH3URMHFWORV Reichstag (Projektlos - 2). The tunnels then continues in bored tunnels (Projektlos - 3) under the Tiergarten to the new station at Potsdamer Platz. 2 PROJEKTLOS 2 - SPREEBOGEN The project consists of three tunnels, constructed as cut and cover tunnels. The eastern tunnel is two tracks U-Bahn (Metro) ending in an underground station close to the new German parliament ("Reichstag"). The central tunnel contains tracks for the ICErailway, starting with the possibility for eight tracks at the north end and narrowing down to four tracks at the south end of the project. The western tunnel is a highway tunnel with two bores, each with two traffic lanes. Special construction methods were implemented for construction of the tunnels, as groundwater lowering was not permitted. The tunnels were therefore constructed in a special construction pit made watertight in order to minimise the water volumes to be pumped. 3 CONSTRUCTION PIT The Projektlos 2 is a part of a concept to strengthen the infrastructure of the “Central Area” in Berlin with the Lehrte Bahnhof (Projektlos -1) at the north end of the development zone continued in cut & cover tunnels under River Spree to the front of the 3.1 *HQHUDOOD\RXW The underground in Berlin consists mainly of sand. In order to avoid lowering of the water table Page 1 3.2 *URXQGZDWHUUHTXLUHPHQWVDQGH[FDYDWLRQRI FRQVWUXFWLRQSLW )LJXUH7\SLFDOFURVVVHFWLRQRIWKHWKUHHFXWDQG FRYHUWXQQHOV under the entire city, an agency was established to co-ordinate and balance the water volumes that were pumped out with the water volumes re-injected into the ground. The construction pit was divided into four sections surrounded by 1.20 meters thick diaphragm walls. The diaphragm walls were designed with one layer of ground anchors at the top of the wall and a free standing height of up to 20 metres. After construction of the diaphragm walls and installation of ground anchors the pit was excavated wet. The underground in Berlin consists mainly of highly permeable sand layers. Lowering ground water in order to construct the cut and cover tunnels would have impact on the water levels over a wide area and therefore major ground water lowering schemes were not permitted Due to the great number of construction sites working at the same time in Berlin, the city had established a water management company which took care of the water pumped up and the re-injection of water to keep a balance of the volumes and levels in the city. Excavation of the different parts of the construction pit was done wet excavation. The ground water level was close to the surface and by excavating a hole close to the diaphragm wall a basin was created. A small cut and suction dredger was lifted into the excavated basin from where the dredger starts to dredge the closed part of the construction pit by pumping the materials to barges in the river. At all time during the dredging work, the water level inside the pit was kept higher than the ground water level outside the pit. The maximum allowable volume of water intruding the construction pit, when it was finalized and empty for water, was 1.5 l/sec per 1,000 m². 3.3 &RQVWUXFWLRQRIGLDSKUDJPZDOOV 3KRWR $ULHO SKRWR RYHU 3URMHNWORV 6SUHH ERJHQ On completing the excavation, vertical tension piles in the form of H-piles were installed, underwater concrete was placed and the pit was finally dewatered. The construction pit was 500 meters long and varied in width from 120 meters to 60 meters. The pit was divided into four parts, where part E (95 x 120 m) was placed in the river, hereafter followed in land part H1 (112 x 90 m), H2 (253 x 80 m) and last part I (40 x 60 m). Page 2 The diaphragm walls were constructed in a traditional way with guide beams and bentonite slurry to keep the overpressure. The diaphragm walls have a thickness of 1.20 meters and a length varying from 25 to 30 meters. The walls were divided into a general panel width of 7 meters. The diaphragm walls are temporary walls that do not have any structural function after the constructions of the tunnels are finalized. The walls are designed for several load cases depending on different construction phases. When the construction sequence for the different parts of the construction pit were agreed, the amount of reinforcement in each wall panel were optimized Along the inner side of the diaphragm wall was excavated a trench for allowing installation of ground anchors in the top of the wall. The holes for the ground anchors are drilled through a preinstalled pipe in the diaphragm wall, fixed to the reinforcement cage. There were placed two anchors in each reinforcement cage and with two cages in each diaphragm panel give four anchors per wall panel. 3.4 'LYHUVLRQRIULYHU6SUHH For construction of the three tunnels under the river Spree it was necessary temporally to divert the river, as it can be seen on the Ariel photo, picture 2. The river diversion made it possible to construct a construction pit for the part of the three tunnels, which finally will be placed below the river. A new channel was excavated and bonds were constructed out in the old channel to allow for construction of diaphragm walls forming the construction pit. Measures were taken to protect the construction pit for impact from the river barges. 3KRWR )HQGHU VWUXFWXUH DORQJ WKH ULYHU GLYHU VLRQ 3KRWR([FDYDWLRQRIGLDSKUDJPSDQHO The fender structure consists of steel H-profiles both as vertical piles and as horizontal beams between the piles. The horizontal beams were also pre-stressed by cables that would absorb the energy from a barge impact during large deflection of the fender structure. The fender system was designed for a barge impact force of 4 MN over a width of 2 meters. The construction pit in the river was demolished after the tunnels were constructed and back filled with sand before the river was re-established. 3.5 7KH6ZLVVHPEDVV\ 3KRWR,QVWDOODWLRQRIJURXQGDQFKRUV The ground anchors are installed inclined and staggered with an angle of 20 deg and 35 deg from horizontal. The anchors consist of 8 lines diameter 0.6 inch and with an average length of 20 to 30 meters and are stressed to a maximum of 1,200 kN per anchor. The anchors are in general stressed twice depending on the construction sequence of the pit, excavation, empty pit for water etc. The construction pit passes close to the corner of the Swiss embassy. The Swiss embassy is an old, heavy, three story building that is protected by a preservation order. Settlements of the building, which could cause cracking or damage, were therefore of great importance. At this particular location the standard plane diaphragm panel was replaced with T-shape panels to increase the stiffness. The tops of the T-shape panels were connected to a 3 x 3 meter horizontal prestressed concrete beam. At the ends of the beam were placed 18 numbers of ground anchors with a Page 3 length of 50 to 70 meters and were reaching to the opposite site of the building. There was a program monitoring the behavior of the building and there were no critical settlements at any time during the construction period. 3.6 3LWIRU8%DKQDWVWDWLRQ The U-bahn vertical alignment was rising toward the station placed in pit "H2". The part of the pit, which contains the U-bahn, was separated with a longitudinal diaphragm wall. This was doing to avoid excessive excavation and re-filling before construction of the U-bahn tunnel could commence. To seal off from intruding ground water, a jetgrout layer was installed between the diaphragm walls and deep under the U-bahn tunnel. The other section of "H2" was constructed in the usually way, with wet excavation and underwater concrete with tension piles. This arrangement can be seen on picture 2. 3KRWR ,QVWDOODWLRQ RI 7VKDSH GLDSKUDJP SDQHO DW6ZLVVHPEDVV\ By using a stiff wall and by placing the grouted part of the ground anchors opposite the building, the soil volume under the building was pre-stressed, thereby reducing the settlements. 3KRWR &RQVWUXFWLRQ SLW + ZLWK HPEUDFHG SLW IRU 8EDKQ WXQQHOV 5HLFKWDJ FDQ EH VHHQ LQ WKH EDFNJURXQG It was necessary to use temporary steel bracing between the diaphragm walls in the pit for the Ubahn tunnel due to the water pressure from the other part of "H2 ". 3.7 8QGHUZDWHUFRQFUHWHDQGWHQVLRQSLOHV 3KRWR *URXQG DQFKRUV SRVLWLRQ LQ SUHVWUHVVHG EHDP Page 4 The bottom of the construction pit was sealed off with a concrete slab cast under water, anchored with tension piles. When the dredging in an enclosed part of the construction pit was finalized the bottom was cleaned and prepared for installation of tension piles. The tension piles consist of H-profiles, HEB 220, with shear brackets welded on the toe of the piles and a steel plate welded on the top of the piles forming the head. At the inside corners in the H-profile were installed two injection pipes running down to the pile toe. The piles had a length of 19.8 meters. The piles were vibrated down into the bottom of the pit from a floating barge. The piles were placed in a pattern of 3 x 3 meters. After the piles were installed the toe of the piles were grouted by injection of mortar through the pre-installed injection pipes. A 1.5 meters thick concrete slab was casted under water and the head of the piles were embedded in the concrete. The water in the pit was pumped out after the concrete had reached its strength and the pressure below the slab were then taken over as tension in the piles. The concrete slab was not reinforced the forces were carried by a compression arch between the pile heads. soil in between the piles were monitored in three level for vertical and horizontal stresses and with rod extensiometers the vertical movement of the soils. Based on all the results from the pile tests the allowable shear stress to be used in the calculation of the pile bearing capacity was fixed to τ = 150 kN/m². 3.8 7HVWRIWHQVLRQSLOHV The U-Bahn tunnel is constructed as one cross section with two tubes and a constant overall width of 15 meters. The cross section separates into two independent tunnels close to the underground station to make room for a central platform in the station area. The ICE-railway tunnel varies in width from 69 meters at the north end under river Spree to 24 meters at the south end. Under river Spree the tunnel is tied to the vertical tension piles used for the underwater concrete in order to get enough safety against uplift; those piles will work as permanent tension anchors for the tunnel. The highway tunnel (road B96) has a constant width of 24 meters and the cross section is divided into two tubes with two lanes in each. An extensive full-scale field test of the piles was carried out before any of the piles were installed. A test area was excavated down to a level just above ground water level, so the test piles would be placed in water. An area of 20 x 54 meters was prepared for testing of five single piles with different lengths and a group test of five piles. Two geotechnical boring were carried out in the area together with SPT tests, all to give a good knowledge of the ground conditions. The necessary anchor lengths of the piles were calculated to 18.20 meters and the necessary working load was calculated to be 1,000 kN. The single pile test were carried out with pile lengths varying from 13.76 to 17.30 meters and the test load of 700 kN, 1,200 kN and 2,000 kN were applied to the piles in three steps with full load release between the steps. Some of the single piles were even tested up to 2,900 kN. The results from the tests were plotted for each pile in two diagrams load versus time the load was applied and deformation of pile head versus load. The distribution of the axial force, based on strain, was measured by strain gauges placed along the pile. 4 TUNNEL CONSTRUCTION 4.1 *HQHUDO 4.2 &RQVWUXFWLRQ The tunnel construction was traditional cut and cover tunnel construction, with the tunnels divided into 10 to 20 meters casting segments. The concrete used was dense B-35 concrete also classified as watertight concrete. By casting in segments of 10 to 20 meters it was possible to control the crack development from the concrete temperature and keep the crack width below the required 0.15 mm. )LJXUH3ODQRYHUWHVWDUHD A group of five piles were likewise tested and for any group effect. Besides monitoring each pile the 3KRWR &RQVWUXFWLRQ RI WXQQHO ERWWRP IRU WKH PDLQUDLOZD\ Page 5 The construction sequence was simply to construct bottom slab, walls and last the roof slab. For tunnels along the pit walls, highway and metro, the pit walls were utilized as outer formwork. In this case the pit walls were cleaned and straighten out and a thin drain layer was placed before the tunnel wall was casted. In the final condition, when ground water rises the drainage layer ensures that the tunnel wall is subject to the full water pressure. Special measures were taken to ensure that the tunnel bottom and roof slabs were supporting the pit wall when the ground anchors were released. The effects of this arrangement is that in final condition the tunnel wall carries the water pressure and the pit wall carries the soil pressure and transfers the load to the tunnel bottom and roof slab. The joint between the tunnel segments were equipped with waterstops and shear keys which allows the segments to contract and expand, and that accommodate small rotations. 3KRWR([WHQGHGWHQVLRQSLOHV 5 REMARKS 4.3 6SHFLDOGHWDLO All of the tunnels had sufficient safety against uplift by their weight, except for the part of the main railway tunnel under the river where the available space was limited. The tension piles below the railway tunnel were extended and were cast into the bottom slab of the tunnel. In the final condition when the river is back in position the uplift from that part of the railway tunnel will be taken as permanent tension in the piles. All other tension piles will not have any effect in the final condition. )LJXUH3ODQRYHUWXQQHOFRQVWUXFWLRQVHJPHQWV Page 6 The project was very complex with special construction pit and three tunnels side by side. Especially the construction of the pit had several obstructions. Bunkers from world war two, unexploded ammunition, cellars, pieces of tunnels etc. which could not be located due to registrations and drawings have been lost or burned during the war. But, also the tunnel construction calls for an experience contractor to handle huge quantities of concrete, reinforcement and steel. The contractor has in professional way and with high standard finalized this complex project in time.