BILFINGER MAUELL CORPORATION
––––––
DICKSON ELECTRIC SYSTEMS
––––––
CASE STUDY
Sum of Order
•(12) 46” HD (1920x1080) LCD Panels arranged in dual
2x3 arrays with adjustable pull-out mounts
• (4) 60” LED-based Smart HDTV with tilt wall mounts
• Nexus Display Wall Controller
• (4) Vented Rack Shelves
• Distribution Amplifiers and Multimedia Speaker System
• (2) 55” LED-based Smart HDTV with fixed wall mounts
• Full-range ceiling speakers
• (2) 60” LED-based Smart HDTV with wall mounts
• (1) Dual-Position Primary Operator Console
• (1) Dual-Position Secondary Operator Console
•(1) Single-Operator Control Supervisor Console with
Storage Credenza
• (1) Conference Table
• Large and Medium sized storage credenzas
• (3) 3D Blu-Ray DVD player
• DVI/HDMI cabling
• Communication cabling
Construction Period
May 2013 – May 2014
Dickson Electric Systems upgrades to first
full control room.
Overview
Dickson Electric Systems has an eye on the future. Through
telemetry improvements in the field and deployment of an
Outage Management System, DES needed a formal control room.
They turned to Bilfinger Mauell Corporation to design a space
within their existing building. Working with DES’s architect,
Bilfinger Mauell engineered a space to accommodate 2 separate control theaters, a supervisor office, war room, and training
space. Bilfinger Mauell was also awarded the supply of the
systems and worked directly with DES’s architect and general
contractor to manage phasing schedules and oversight of the
final construction.
1
2
6
7
5
11
8
13
10
9
Improvements
Final Solution (
This was an unfamiliar project for Dickson and their first experience
with a full control room. Bilfinger Mauell took this into consideration, guiding the process and relieving stress levels. Bilfinger Mauell
updated DES to a new system of video panels, which replaced the
old system of computers and physical maps. Dickson was provided
with an improved console system for its new control theater.
Control Theater
1 HD LCD Panels in 2x3 arrays with adjustable mounts
2 LED-based HDTV, tilt wall mounts
3 Nexus Display Wall Controller
4 Audio/Visual System
5 Primary Operator Console
6 Secondary Operator Console
7 Storage Credenzas (large and medium)
Successes
Bilfinger Mauell oversaw much of the work done by outside
companies, including the creation of construction documents with
a local A/E firm, for DES to use with a general contractor. Bilfinger
Mauell also converted what was originally a spacious basement into
a complete control room with other necessary and useful rooms
built in, such as a meeting and training rooms. Thanks to Bilfinger
Mauell, Dickson’s system restoration process has been quickened by
at least 4 hours over previous outages of similar magnitude.
The Companies
Dickson Electric Systems is a Tennessee public utility distributing electricity to 35,000 homes, businesses, and industries
across five counties. Bilfinger Mauell Corporation engineers,
deploys, and supports mission critical control rooms within
life services industries.
Power Systems
Bilfinger Mauell Corporation
31 Old Cabin Hollow Road · Dillsburg, PA 17019 · USA
Phone: 717-432-8686 · Fax: 717-432-8688
sales.bmc@bilfinger.com · www.mauell-us.bilfinger.com
= not shown)
War/Storm/Conference Room
8 LED-based HDTV, fixed wall mounts
9 Audio System
10 Conference Table
Training Room
11 LED-based HDTV
12 Audio/Visual System
13 Training desks
Supervisor Office
14 Audio/Visual System Control Supervisor Room
15 Single-operator Control Supervisor Console (w/ storage credenza)
Bilfinger Mauell also assisted in the Mechanical and IT Room
designs, a storage closet and added corridor, and a complete
restroom renovation.