addendum #1
Transcription
addendum #1
ADDENDUM #1 June 29, 2010 Re: Harrisburg Area Community College Faculty & Administration Expansion – Cytec Building Solicitation #10-44 From: Eastern pcm, LLC Construction Manager – HACC 645 N. 12th Street, Suite 200 Lemoyne, PA 17043 To: All Planholders This Addendum is hereby made part of the Plans and Project Manual dated June 16, 2010 for the above referenced project. The provisions of this Addendum are intended to supplement the provisions of the Plans and Project Manual and/or supersede them where contradictory thereto. This Addendum contains changes to the requirements of the Plans and Project Manual. Such changes shall be incorporated into the Plans and Project Manual and shall apply to work with the same meaning and force as if they had been included in the original Plans and Project Manual. Where this Addendum modifies a portion of a paragraph or phrase of the Project Manual, the remaining unmodified portion of the paragraph or phrase shall remain in force. The conditions and terms of the Plans and Project Manual shall govern work described in this Addendum. Whenever the conditions of work, or the quality or quantity of materials or workmanship are not fully described in this Addendum, the conditions of work etc. included in the Plans and Project Manual for similar items of work shall apply to the work described in this Addendum. If no similar items of work are included in the Plans and Project Manual, the quality of material and workmanship shall be subject to the written acceptance of the Architect. 1.1 PROJECT MANUAL a. Specification Section 15600 – Heating and Air Conditioning Article 3.3, Paragraph E, CHANGE last sentence to read “Contact Scott Schmittel (717) 712-1804” 1.2 DRAWINGS a. Drawing A-1.00 – Overall Plan REPLACE with A-1.00R, attached. ________________________________________________________________________________ Page 1 ADDENDUM #1 June 29, 2010 b. Drawing A-2.00 – Exterior Elevations REPLACE with A-2.00R, attached. c. Drawing A-4.01 – Casework Plans & Elevations DELETE Detail No. 4. d. Drawing A-4.02 – Egress Stair Plans & Details REPLACE with A-4.02R, attached. e. Drawing M-1 – Floor Plan Mechanical REPLACE with M-1 dated June 28, 2010, attached. f. ADD the following sketches (attached) i. SKA 1.02.1 ii. SKA 1.03.1 iii. SKA1.03.2 iv. SKA 3.01.1 v. SKA 3.01.2 vi. SKA 3.01.3 vii. SKA 4.01.1 viii. SKA 6.00.1 1.3 PRE-BID MEETING MINUTES Meeting minutes from the Pre-Bid Meeting held on June 24, 2010 are attached and are a part of this Addendum. In the event of a conflict between the information contained in the Pre-Bid Meeting Notes and the Drawings, Specifications and responses to questions contained in this Addendum, the latter shall take precedence. END OF ADDENDUM ________________________________________________________________________________ Page 2 ADDENDUM #1 June 29, 2010 Please sign and return this page, via fax, to Eastern pcm, LLC at (717) 233-1666 indicating receipt of this Addendum. Faculty & Administration Expansion – Cytec Building Addendum #_____ has been received. Company: Print Company Name Received By: Print Name Signature Date: Please check one: We are bidding as a prime contractor We are not bidding We are a sub-contractor ________________________________________________________________________________ Page 3 ADDENDUM #1 June 29, 2010 06/16/2010 06/28/2010 1 D - D 06/03/2010 E DRAWN BY: CHECKED BY: ADDENDUM #1 ISSUED FOR BIDDING 75% CONSTRUCTION DOCUMENTS 800 North Charles Street, Baltimore, Maryland 21201 410-625-4823 Voice 410-625-4674 Fax 226 West Market Street, York, Pennsylvania 17401 717-848-8627 Voice 717-843-2449 Fax C - C PROJECT NO: SHEET M-1 2161 Pennsylvania Ave. - York, PA HACC, York Campus Faculty & Administration Expansion Cytec Building B 100% Schematic Design B 11 05/11/2010 A 10 - A 9 DESCRIPTION 8 DATE E 10 MARK 9 10109 DS GBF/GM FLOOR PLAN MECHANICAL HACC, Central Pennsylvania’s Community College Faculty and Administration Expansion – Cytec Building Pre-Bid Meeting June 24, 2010 9:00 AM Meeting Minutes Attendees Keith Rufalo – HACC Paul Monko – HACC Rebecca Slenker – Murphy & Dittenhafer Architects David Krepps – Gettysburg Construction John Wolffold – Sponaugle Construction Services Tom Kondracki – Sponaugle Construction Services Bruce Love – Brechbill & Helman Don Beinhaur – McCoy Brothers, Inc. Mike McKay – Premier Construction Dan Carfagno – R.S. Mowery & Sons 1.0 1.1 Jeffery Stanton – J&J & Sons Drywall Tom Brown – J&J & Sons Drywall Todd Cameron – Uhrig Construction Corey Hamberger – Markey Builders Sean Walker – Palmer Construction Joe Perkins – Trinity Construction Group Dane Fahnestock – Trinity Construction Group Brian Kauffman – Holland Construction John Page – Eastern PCM Kelly Foreman – Eastern PCM Team Introductions a) Owner HACC, Central Pennsylvania’s Community College Jean Treuthart – Campus Vice President Joan Brennan – Campus Exec. Director of Business Affairs Keith Rufalo – Campus Director of Facilities Margie Mattis – Campus Executive Dean of Academic Affairs Paul Monko – Campus Director of Technical Support b) Architect Murphy & Dittenhafer Frank Dittenhafer – Partner Bruce Johnson – Project Architect Rebecca Slenker – Designer c) MEP Engineer Schlenger/Pitz & Associates, Inc. Kent Hoffman – Vice President d) Construction Mgr Eastern PCM, LLC John Page – Project Manager Kelly Foreman – Project Engineer Bid Documents a) Drawings/Specifications dated June 16, 2010 i. Refer to Article 1.2.3 in General Conditions; Specifications and drawings are complimentary. b) Bid Form – 4 Pages – Properly completed and Signed c) Bid Security – Bid Bond Required > $10,000 d) Non-Collusion Affidavit _______________________________________________________________________________________ HACC, York Campus Faculty & Administration Expansion – Cytec Building Pre-Bid Meeting Minutes June 24, 2010 Page 2 e) MBE/WBE Utilization Form Properly completed and Signed f) Sales Tax – Refer to Article 3.6.1 in General Conditions; Refer to Article 15.3.1 in Supplementary General Conditions. Contractor is responsible for Sales Tax. HACC is entitled to receive all sales tax refunds. 1.2 All Bid Documents must be properly and completely filled out. Contractors are encouraged to contact Eastern PCM with any administrative questions regarding their Bid Package. 1.3 Schedule a) Bid Date: Thursday, July 15, 2010, 2:00 PM EST at Harrisburg Campus; Rm. 130 Whitaker Hall b) Contract Award & Notice to Proceed: July 30, 2010; subject to Board of Trustees Approval c) Substantial Completion: December 15, 2010 1.4 A public bid opening will be held at 2:00 PM in Whitaker Hall at the Harrisburg Campus on July 15, 2010. 1.5 Questions to Construction Manager in writing via fax or e-mail; No questions will be fielded by phone. a) EPCM Fax: (717) 233-1666 b) EPCM E-mail: epcm@easternpcm.com Re: Faculty & Administartion Expansion – Cytec Building c) Last day for questions: July 9, 2010 by Noon. 1.6 Addenda Expected to be issued via fax or UPS (depending on size) on the following dates subject to number and substance of questions received: a) Addendum No. 1 – Tuesday, June 29, 2010; Will include Pre-Bid Meeting Minutes b) Addendum No. 2 – Monday, July 12, 2010, if needed 1.7 Prevailing Wage Rate Project – Refer to Spec. Section 00820. 1.8 The Building Permit will be obtained and paid for by Owner. Any other trade specific permits, such as Sprinkler Permit, the Contractor must obtain. 1.9 Scope of Work The work will be performed under a Single Prime Contract and consists of interior renovations to approximately 5,000 square feet of tenant space in an existing building. The work will entail selective demolition to non-structural interior partitions, tenant separation CMU wall, and MEP systems. It will include interior framing and all wall, ceiling, and floor finishes to create office and reception areas, minor structural framing for mezzanine, and the extension and modification of mechanical and electrical systems from adjacent space to serve the new offices. It will also require modifications to the existing sprinkler system. 1.10 There is one (1) alternate which includes the removal of the existing storefront windows and masonry wall from the existing sill to the floor level and replacing it with a new storefront within an enlarged opening. _______________________________________________________________________________________ HACC, York Campus Faculty & Administration Expansion – Cytec Building Pre-Bid Meeting Minutes June 24, 2010 Page 3 1.11 Contractors may not stage materials inside the work area. Contractors must provide storage trailers or any other means and methods for storing their materials. 1.12 Contractors must provide their own on-site office and storage trailers. Trailers may be placed at the East end of parking lot, at the end of the loading dock drive. Power may be taken from the panel in loading dock area. Contractors must supply conduit through the loading dock to the outside wall with a 100amp disconnect located on the wall behind the loading dock stairs (power to trailer from this location), which will remain intact after job is finished. 1.13 The General Contractor is required to create a construction schedule. The construction schedule must appear as a line item on the schedule of values. The schedule must be submitted by the Contractor and approved by Eastern PCM prior to the first request for payment. No payments will be made until the Contractor has an approved construction schedule for the project. 1.14 Working Hours a) 6:30am to 5:00pm Monday through Friday. b) Contractors must plan for Demolition to be performed during Night Work. Night work hours may range from 6:00pm to 6:00am. 1.15 Contractors are not allowed to use the HACC restrooms and must provide their own. 1.16 The building is occupied on both sides of the area being renovated. 1.17 HACC will be removing the following items prior to start of construction: a) The Kitchenette b) All Track Lighting The Contractor does not have to salvage any items for HACC. 1.18 The Contractor will salvage the existing light fixtures for possible use for temporary lighting. If not used they may discarded at end of job. 1.19 Deliveries may only be made from 6:00am to 8:00am or after 4:30pm on weekdays. Deliveries may be accepted anytime on weekends. 1.20 The sidewalk in front of the Cytec Building cannot be obstructed. This is the only ADA access to the HACC York Campus Cytec Building. Respectfully Submitted, Kelly Foreman, Eastern PCM, LLC The above summations are the interpretation of the author as to the items discussed and the decisions reached. Corrections or additions to these minutes are to be made in writing and sent to the attention of the writer no later than 5 days after receipt; otherwise, these minutes will stand as written. cc: All Attendees _______________________________________________________________________________________