Alternative Delivery for Large
Transcription
Alternative Delivery for Large
October 2010 Alternative Delivery for Large Infrastructure Projects: Lessons Learned during the Tri-City WPCP Phase 1 Expansion Jude D Grounds, Project Manager, MWH Randy Rosane, Program Manager, WES Jeff Wall, Project Manager, SCI Acknowledgements • • • • • • WES Staff Slayden Construction Group, Inc. GE Water and Process Technologies URS Corp. REI MWH Design Team Water Environment Services is…. Immediate Need for Additional Treatment Capacity Tight Schedule Required Compressing Tasks Fast-track project delivery approach, focused on partnership and collaboration resulted in over 12 months of savings in the overall project schedule. Multiple Site Constraints Provide Challenges for Plant Layout Resulting Design Ensure WES is Model for Sustainability in the Region Month 22 Project Status • Currently in Month 22 of Construction • Clean-water Testing MBR System • Have Built ~1-month Float into CPM Schedule • Only received 1/2 Estimated Number of RFIs • $12M in VE prior to GMP Development • ~$1.2M in additional VE Savings since GMP – Equipment Procurement – Design Optimization Lessons Learned during MBR Procurement PreDesign MBR Procurement Design CM/GC Procurement & Construction Start-up Early MBR Selection offers significant advantages • System geometry unique to vendors • Dovetail design/submittal efforts – Buildings need to fit to equipment • Ability to work with MSS to optimize system layout – Pump-back system for overall energy savings – Maintain integrity of existing pipe/pump gallery system Performance-based RFP Ensures Quality while Optimizing Schedule • To Ensure Quality – Experience at Similar Flow/Configurations – Quality of Equipment • Schedule – Preliminary Layouts and P&IDs – Allows MSS to optimize their system, reducing risk during start-up No incentive sacrifice quality for cost! RFP Sets the Stage for Future Procurement and Performance Guarantee • Three Agreements Included in RFP – Design Support Services (MWH) – DRAFT Procurement Agreement – DRAFT Repair and Replacement Services Selection Process Lays Groundwork for Long-term Relationship with MSS • Individual Pre-proposal meetings – QA regarding RFP • Proposal Review • Interview / Workshop w/ Client Operation Staff Integrated into Selection RFP Selection • GE Water Process Technology was Ultimately selected • Proposed Criteria: – – – – 4 mgd ADDWF; 10 mgd PHF 4 Sub-trains; 9 Cassettes per Sub-train Membrane Surface Area = 527,680 sf MWWWF Ultimately Drove Design • Total Cost ~ $8M Final cost based on proposed price and pre-negotiated change orders Lessons Learned during Design PreDesign MBR Procurement Design CM/GC Procurement & Construction Start-up Elements of Successful Delivery • Early Involvement of Key Stakeholders – Dedicated staff liaison between design and operations/maintenance – Permitting Agencies – Owner’s Rep Open Design Process Fosters Partnership • Monthly Discipline-specific Brown Bags – Staff Comment Log • Quarterly Updates for Entire Staff • QC Review Summit – 30%, 50% & 70% Design – WES Engineering, Key Staff; MSS, Owners Rep & Contractor attended last meeting Discipline-specific Summits Ensure Money is spent Wisely • Decision on final design balances cost and Owner preference – Material costs and market trends – Operational flexibility – Long-term O&M Costs 3D Capability Facilitates Early Buy-in “The 3D design models really helped the maintenance crew visualize the mechanical layouts early in the design process to ensure the final design would be operator friendly…” Michael Trent, Operations Supervisor 900 Sheets in 10-months – Clarity at all Costs Hindsight is 20/20 • Not all designers are equipped to succeed in a fasttrack environment – Designers need to be proactive in IDing design problems – Contractor/Owner input is not an ‘attack’ on the design • Team turn-over can have profound impact on project • Early procurement of process equipment significantly reduces re-design in field • On-site Engineering CAD capabilities during first 18-months of construction Fast-Track Design can Challenge Longstanding Review Protocol • DBB review protocol of many agencies does not translate well in a CM/GC or DB environment Lessons Learned during CM/GC Procurement and Construction PreDesign MBR Procurement Design CM/GC Procurement & Construction Start-up Key Justification for CM/GC process: • Tight Schedule required trust and partnership for success • Incomplete drawings required experienced contractor to work in partnership with engineer and owner to complete construction • MBR Treatment is a highly specialized construction 4 Step Process to Contractor Selection Step 1 Pre-proposal Conference Step 2 Statement of Qualifications Step 3 Proposal Step 4 Interview Request for Qualifications Criteria Firm Experience 25% Background 12.5% Partnering 12.5% Alt Delivery Experience 30% Plant Construction Experience 12.5% Health & Safety 12.5% Request for Proposal Criteria Workload 6% Experience of Key Personnel 12.5% Value Engineering 12% LEED Experience 12.5% Basis of Contract Price 23% Project Scheduling and Coordination 23% Project Understanding 12% RFP Selection • Slayden Construction Group was ultimately selected – – – – SCG – Self-performed Concrete SCG – Awarded Mechanical Subcontract Team Electric – Electrical Subcontractor Portland Engineering – System Integrator • 24 Month CPM Schedule • Total GMP $79.8M Benefits of CM/GC approach • Accurate Cost Estimate • $12M VE at 70% Level - Design Optimized for – – – – Cost Function Constructability Schedule • 85% of Work was Competitively Bid: No loss of competition Early Procurement of CM/GC Maximizes Value… • … but CM/GC Procurement Takes Time – RFQ issued at 30% – RFP issued at 50% – NTP for CM/GC at 70% • Project would have benefited from earlier involvement from CM/GC VE Ideas have diminishing returns as project progresses. Early Coordination Efforts Result in Big Savings “…the revision of construction joint location and structural reinforcement at wall and upper slab connections to allow the contractor to more easily remove and reuse formwork reduced labor costs and saved approximately 2-months on the construction schedule.” -Floyd Bayless, (URS) Recent Trends in CM/GC Procurement Threaten to Undermine Process • Early Procurement Criteria – Qualifications – LS for General Conditions (WA) – % Fee • To compete, CM/GC contractors propose unrealistically low fees, making them hard not to hire – Push responsibility for DIV 00 and 01 on to subs This trend creates DBB Quality (i.e. Low Bid) at CM/GC Price! Percentage of Self-performed Work Significantly Impacts Projects • Too much Self-performed Work – Reduces competition – Increases cost • Too little Self-performed Work – Potentially reduces CM/GC VE effectiveness For the Tri-City WPCP, the CM/GC was allowed to self-perform 15% of the work; SCI elected to self-perform the concrete placement and finishing work. Timing of GMP Development Impacts Cost/Risk • Early development of GMP may result in ‘hidden’ contingencies – Risk ‘shouldered’ by CM/GC – Typically requires sharing of cost savings w/ CM/GC • Deferring GMP development until design is 100% complete (and bid?) – Minimizes contingencies – Minimizes risk of Change Orders (HVAC) For the Tri-City WPCP, a ‘third-party’ HVAC design specialist would have reduced risk and re-design efforts in the field. CM/GC Allows OWNER to provide ‘real time’ adjustments to Business Case Analysis • Owner/Engineer ‘in the room’ when Equipment and Key Subcontractors are selected • Allows team to adjust approach based on differing site/market conditions, w/ little impact to Engineer or CM/GC • Impacts of design modifications need to be weighed against potential capital savings when selecting equipment ‘Real-time As-builts’ Resulted in 1.2% Net Positive Change Orders (so far…) “Innovative ideas like ‘real time’ as-builts …go a long way to ensuring clear communications on site, an essential element in fast-track project delivery.” - Jeff Wall, Project Manager (SCI) Hindsight is 20/20 • Budgeting for ESDC is VERY challenging • Owner/Operator involvement during submittal review is critical for overall project success – Risks of being too involved; sometimes you want to minimize ‘exposure’ – Risks of not being involved at all; things that matter to operations staff do not matter to designer or CM/GC In this case, the Owner and CM/GC were sophisticated and knowledgeable of this process. This will not always be the case. Tri-City WPCP Phase 1 Expansion Month 5 Month 9 Month 15 Month 22 Lessons Learned during Start-up PreDesign MBR Procurement Design CM/GC Procurement & Construction Start-up Start-up Considerations Should Begin during Pre-Design Internal flow ‘loops’ facilitate Clean-water Testing ‘Issues List’ Items must be Identified Prior to Trades Leaving Site • WES SOP for project completion is to maintain an updated Early Issues List • Ensures trades are present for ‘punch-list’ activities Questions? randyr@co.clackamas.or.us jude.d.grounds@mwhglobal.com jwall@slayden.com