12PS Transitional Outage
Whiting Refinery Modernization Project – WRMP –Oct 2012
Whiting Refinery Modernization Project
‘The Logistics Challenges of a Multibillion Dollar Expansion’
1
BP Whiting Business Overview
•
The refinery began operation in 1890
•
The 6th largest refinery in the U.S.
with 413,000 barrels per day of crude
distillation capacity
•
Supplied by a network of pipelines
that provides access to 3 distinct
crude markets
•
Over 15 millions gallons per day of
transportation fuels produced and
shipped via 8 pipelines
•
Transportation fuel marketed at a
network of terminals across 8 states
•
One of the largest producers of
asphalt in the U. S.
•
Other products distributed across
the country by pipeline, truck, rail
and barge
•
Existing refinery employs about
1,850 BP employs plus contractors
for capital projects, TARs, etc.
Whiting Refinery Modernization Project
2
WRMP competitively repositions Whiting Refinery
Whiting Refinery Modernization Project
•
Modernizes the Whiting Refinery with world scale assets
•
Processes incremental heavy sour and high TAN crude as substitute for
light, sweet crude
• Selective debottlenecking of fuels production
Status
•
Completion is during second half of 2013
•
Greater than 75% complete with on-site construction
•
28 million hours worked without a day-away from-work injury
3
Key Aspects of the Project
Whiting Refinery Modernization Project
BP Confidential
4
4
12 Pipestill
Whiting Refinery Modernization Project
New Vacuum Tower
One of the worlds’ largest
New Crude Tower
Old Crude and Vacuum Towers
Super Module at dock area
5
12 Pipestill
Whiting Refinery Modernization Project
August 2011
October 2012
• All modules and major equipment set
6
Coker
Whiting Refinery Modernization Project
August 2011
August 2012
• All modules and major equipment set
7
Gas Oil Hydro-Treater
Whiting Refinery Modernization Project
August 2011
August 2012
•All modules and major equipment set
8
Sulfur Recovery Facilities
Whiting Refinery Modernization Project
August 2011
August 2012
9
OSBL Facilities
Whiting Refinery Modernization Project
Overall OSBL Scope
• Several OSBL sub-projects significantly modernize the
refinery
OSBL Cooling Tower #8
• 90,000 gallons per minute of water circulation
10
Coker gantry crane and holding barn
Whiting Refinery Modernization Project
Fully automated Coker gantry crane
Coke barn holding 5 days product produced at 6,000 tons/day
11
Logistics Challenges on a Mega Project Scale
Whiting Refinery Modernization Project
Construction Statistics
• 800 modules and vessels
• 1,200 pieces of equipment
• 380 miles of pipe
• 50,000 tons of steel
• 1325 miles of wire and cable (distance from Chicago to Santa Fe, NM)
• 15,000 concrete truck deliveries
• 95,000 truckload deliveries
• 14,000 piles to be driven
• 200 material deliveries per day
• 9,000+ Staff/Craft on ‘One Whiting’ site at peak
12
Whiting Refinery Modernization Project
Key Material and Logistics Pattern
Foster
Wheeler
AG&P
(Modules)
Philippines
(EPC)
COKER
Whiting RefineryModernization Project
International
Shipment
(Jumbo via
Foster
Wheeler)
Jacobs
(EPC)
JAT (Jacobs)
_________________________
(Modules)
Sulfur (SRC)
Charleston, SC
Fluor
(EPC)
Dii
________________________
GOHT
(Modules)
Louisiana
________________________
OSBL
________________________
12 PS
Truck & Rail
Major
Engineering
Equipment
All Equipment is FAS
Barges
Mammoet
Non-Modular Material/Equipment
International
Shipment
Mammoet to point of
final Whiting location
Mammoet
Site
Placement
Logistics – Global to Last Mile
Whiting Refinery Modernization Project
• Vessels
− USA
− Spain
− Italy
− Germany
− Japan
− Korea
• Shipped by
− Jumbo Ship
− Ocean Barge
− Lake Barge
− Hopper Barge
− Freight
− Rail
14
Logistics – Global to Last Mile
Whiting Refinery Modernization Project
• Modules – 600
− New Iberia, La
− Goose Creek, SC
− Batangas, Phillipines
• Shipped by
− Jumbo Ship
− Ocean Barge
− Lake Barge
− Deck Barge
− Hopper barge
15
Shipping Offloads – Vessels / Modules
•
Whiting Refinery Modernization Project
Via St Lawrence Seaway and
Great Lakes
− Montreal, Canada
− Port of Indiana
− IPMT Dock Facility
•
Via Mississippi and Illinois Rivers
− Port Allen, SC
− New Iberia, La
− IPMT Dock Facility
16
12 PS Vacuum Tower on Deck Barge
Whiting Refinery Modernization Project
IPMT Dock Facility
Whiting Refinery Modernization Project
• 2 Heavy Lift Berths and a Roll On / Roll-Off Ramp
− 400T crane for Hopper Barge offloads and SPMT Transporters for Deck Barge Roll Offs
18
IPMT Dock Facility–N–54 Acres, S–17+ Acres w/Roll Off Ramp – Aug 2008
Whiting Refinery Modernization Project
19
IPMT Dock Facility – N – 54 Acres, S – 17+ Acres w/Roll Off Ramp – Nov 2010
Whiting Refinery Modernization Project
20
IPMT Dock Facility – N – 54 Acres, S – 17 Acres w/Roll Off Ramp – OCT 2012
Whiting Refinery Modernization Project
Engineering, Review and 3rd Party Asssurance
Whiting Refinery Modernization Project
• Major Lifts for loading, offloading, transport to site or lifting at site
were
− Developed by EPC or Mammoet
− Stamped by Indiana PE and reviewed by Independent 3rd party,
Lowther Rolton
− Witnessed by 3rd Party Heavy Lift experts from Santis or Lowther
Rolton
− Reviews performed with Project Lift committees as additional
assurance
− Several Thousand Engineered Lifts made at site alone
• Logistics required to keep engineering and paperwork flowing without
impacting construction
12 PS Vacuum Tower Lift
Whiting Refinery Modernization Project
Heavy Haul Road Layout
• All 34KV power lines moved
underground
• 138KV Transmission Lines powered
down by NIPSCO for Transports
over 50’ tall
• Traffic Signals replaced with
Swivel design
• 4 K-Rated Gates installed at
Refinery perimeter
• New Heavy Haul roads built within
refinery
• Police escort from Barge facility to
HH Gates
• Adjacent businesses and
surrounding municipalities alerted
prior to Transports.
Whiting Refinery Modernization Project
Heavy Haul Roads and Transports
•
Whiting Refinery Modernization Project
12 PS Fractionator
25
Coker Module Transport
Whiting Refinery Modernization Project
Site Coordination
Whiting Refinery Modernization Project
• Daily Meetings with Security, Emergency Response, Fire department, Pillar
Logistics Leads, WBU Turnaround and Projects teams
• Utilize Live Map, Monthly Aerial photos and Smart Boards to visualize and
plan
− Road Closures and Emergency response Impacts
− Heavy Haul Transports
− Major Crane Lifts and Heavy Equipment locations
− Other Site Impacts due to SIMOP’s
• Weekly Logistics Meeting – Longer range view
− Staff and Craft Housing
− Craft Parking and Bussing – 9000+ Craft at peak, 9 Parking Lots
− Water distribution – 2000/day
27
4 Warehouses 850K sq/ft and 13 Lay down
Yards – 203 Acres
Whiting Refinery Modernization Project
One Whiting Parking – 9 new Lots required
Whiting Refinery Modernization Project
One Whiting Bus and Shuttle Routes/Schedule
Whiting Refinery Modernization Project
One Whiting Snow Removal
Whiting Refinery Modernization Project
47 Acres, H2 Plant, Standard Avenue Reroute – Aug 2008
Whiting Refinery Modernization Project
32
47 Complex, H2 Plant, Standard Avenue Reroute
– OCT 2012
Whiting Refinery Modernization Project
LR13000 – 3000T Crawler Crane
• One of Largest Crawler Cranes in the
World
• Delivered from Germany by Jumbo
Ship to Port of Indiana
• Offloaded in over 200 pieces
• Proof Tested at 3400T
• Crawler tracks over 11’ tall
• Tubing on Boom and Mast is 2” Thick
• Redundant State of the Art Control
systems
• What could you do with this crane and
how would that help you?
Whiting Refinery Modernization Project
12 PS Construction
Whiting Refinery Modernization Project
35
Coke Drum Lifts
Whiting Refinery Modernization Project
36