air barriers for masonry walls - Masonry Contractors Association of
Transcription
air barriers for masonry walls - Masonry Contractors Association of
Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 1 air barriers for masonry walls pat conway, aia, csi international masonry institute pconway@imiweb.org © international masonry institute 2009 international maso nry institute ! ! labor/management non-profit funded by ! international union of bricklayers and allied craftworkers & contractors who employ them brice house, annapolis INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 2 IMI national training center IMI national training center INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 3 craftworker training !"#$%&'()%*#+,$)-& 1)4&.'*.$)/%/%, )++$&%./0&12/+*.$)/%/%, 0"%.$)0."$*0"33&,& professional education .&02%/0)3*$&5/&6 -&1/,%*)6)$-1 !"7*1/.&*1&$5/0&1 1.#-&%.*+$",$)(1 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 4 free IMI services " " " " " " " " " drawing review specification review customized seminars job site troubleshooting cost information hands-on education workforce supply conceptual structural engineering support imiweb.org details, Q&A, blog, events " " " 800.464.0988 life-cycle cost analysis LEED support INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 5 imi tool kit INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 6 air barriers for masonry walls pat conway, aia, csi international masonry institute pconway@imiweb.org © international masonry institute 2009 aia policy International Masonry Institute is a Registered Provider with The American Institute of Architect’s Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 7 copyright materials this presentation is protected by U.S. and international copyright laws reproduction, distribution, display and use of the presentation without written permission of the speaker is prohibited © international masonry institute 2009 learning objectives 1. understand basic function of air barriers 2. acquire knowledge of air barrier products and installation techniques 3. learn how to design air barrier systems INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 8 seminar outline ! ! ! ! air barrier basics the perfect wall codes & standards case studies air barrier basics INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 9 moisture sources +$&0/+/.)./"% 5)+"$*$&.)$-&$ 5)+"$*-/44#1/"% +$&0/+/.)./"% 2#(/-/.' )/$*3&)8),& )/$*7)$$/&$ $/1/%,*-)(+ air ex-filtration source: ASTM STP 1432, Masonry: Opportunities for the 21st Century INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 10 top of wall air leakage 90% - 1% waterproofing principle “as much as 90% of all water intrusion problems occur within 1% of the building envelope surface area” Source: Construction Waterproofing Handbook, McGraw-Hill, 1999 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 11 90% - 1% waterproofing principle “as much as 90% of all water intrusion problems … occur within 1% of the building envelope surface area” Source: Construction Waterproofing Handbook, McGraw-Hill, 1999 plug the holes ! INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 12 air leakage quiz 1. 2. 3. 4. 5. 6. control joint lintel conduit hole brick ties stone ties door frame & wall interface 7. typical s.f. mason contractor training INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 13 vapor drive ventilated wall source: Builder’s Guide to Cold Climates, 2004, Joseph Lstiburek, Building Science Corporation, www.buildingscience.com INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 14 weep vents ventilated cavity wall INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 15 what’s wrong ? vapor drive ! INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 16 air barrier terminology air barrier = air retarder air barrier terminology “air barrier” & “vapor barrier” ARE NOT SYNONYMS INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 17 air barrier terminology “air barrier” & “vapor barrier” ARE NOT SYNONYMS air barrier terminology “air barrier” & “vapor barrier” are not synonyms INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 18 air barrier definition “a material or combination of materials collectively having maximum air leakage rates of 0.06 cfm/ft2 at 0.30 in. h2O when tested in accordance with ASTM E783, installed to resist air leakage into the exterior envelope” vapor barrier definition “a material having a permeance rating of 1.0 perm or less, when tested in accordance with ASTM E96, such as foil, plastic sheeting, or insulation facing, installed to resist the transmission of water vapor through the exterior envelope” international building code (IBC) definition INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 19 water-resistive barrier definition “a minimum of one layer of No. 15 asphalt felt, complying with ASTM D226 for Type 1 felt, shall be attached to the sheathing, with flashing as described in Section 1405.3, in such a manner as to provide a continuous waterresistive barrier behind the exterior wall veneer” International Building Code (IBC) Definition moisture management systems diffusion vapor barrier water-resistive barrier air barrier bulk water air leakage INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 20 air barrier purpose “the primary purpose of an air barrier system is to stop air from leaking into and out of the building enclosure” air barrier association of america airbarrier.org systems thinking “no single component or material has the capability to provide a complete air barrier system for a building” air barrier association of america INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 21 Sample AB specification – section 07262 9:9;<=*><9?@AB;ACD EF E/$G*5)+"$*)%-*6).&$*7)$$/&$*(&(7$)%&*/1*/%.&%-&-*."*4"$(*)* 0"%./%#"#1 7)$$/&$*4$"(*+)$)+&.*&-,&*H0"%%&0./"%*."*$""4/%,* (&(7$)%&1I*)%-*4"#%-)./"%*).*4""./%,*3/%&F**A%1.)33)./"%*12)33*$&J#/$&* 0""$-/%)./"% 6/.2*1&J#&%0&*"4*6"$8*).*)33*6/%-"61*)%-*-""$*"+&%/%,1G* 3"#5&$1*)%-*1/(/3)$*+&%&.$)./"%1*"4*7)$$/&$*."*/%1#$&*0"%./%#/.' "4* 7)$$/&$F why install an air barrier ? ! ! ! protects building envelope from moisture related problems it’s the law…in some 1 states 2 saves energy K*L 02&08*3"0)3*7#/3-/%,*M*&%&$,'*0"-&1 N*L +&$*DA9;*H%)./"%)3*/%1./.#.&*"4*1.)%-)$-1*)%-*.&02%"3",'I*1.#-'G*NOOP INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 22 U.S. department of energy “up to 40% of energy consumed to heat or cool a building is due to air leakage into and out of buildings.” United States Department of Energy (DOE) air barriers & energy savings NIST 2005 study: ! building envelope airtightness ! 30-40% savings in energy for heating ! 10-15% savings in energy for cooling ! one of top 5 greening “no brainers” INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 23 2005 NIST study results 2005 NIST study results INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 24 2005 NIST study results 2005 NIST study results INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 25 wisconsin department of commerce ! air leakage is usually much more destructive to the integrity of the exterior wall system than is vapor transmission, in fact, air leakage into/through exterior walls in northern climates is the leading cause of wall problems” 1 State of Wisconsin, Department of Commerce, Minimum Requirements and Guidelines for the Exterior Building Envelope - 2001 air leakage ramifications ! ! ! ! ! ! higher HVAC costs increased greenhouse gas emissions reduced occupant comfort risk of mold development premature building envelope deterioration higher life-cycle cost INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 26 high internal moisture projects ! ! ! ! ! ! hospitals nursing homes museums libraries wet labs swimming pools ! ! ! ! ! greenhouses food processing showers & baths computer centers printing/copying occupancies air barrier attributes ! ! ! ! ! ! ! ! ! secure continuous strong durable heat stable impermeable ? bridging capability worker friendly environmentally friendly INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 27 sustainability issues ! ! ! ! ! non-toxic run-off benign over-spray low v.o.c. minimal manufacturing waster green spec (EBN) the perfect wall INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 28 wall without an air barrier ? ? Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 29 Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 30 Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 31 Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 the perfect wall cladding thermal control water, air, vapor control building structure Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 32 the perfect wall masonry cavity wall Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 33 masonry veneer wall Source: Joseph W. Lstiburek Ph.D, P.Eng., FASHRAE. Building Sciences, Inc. 2007 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 34 codes & standards air barrier state codes ! ! ! ! ! ! ! massachusetts (2001) wisconsin (2002) 1 michigan (2006) georgia (2007) minnesota (2008) 20 potential states ASHRAE 90.1 addendum z (2008 - draft) 1 – wisconsin repealed air barrier language from building code in 2008 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 35 ASHRAE standard 90.1-2007, addendum z ! ! ! ! will be mandatory on federal buildings establishes requirements for opaque envelope defines “continuous” sets testing standards air barrier i-codes INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 36 2006 IBC – chapter 14, section 1403 2006 IECC – chapter 4 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 37 2006 IECC – chapter 4 2006 IECC – chapter 4 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 38 case studies moisture transfer study " moisture via air diffusion # no openings = 0.00158 gal. ! # moisture via air leakage 1 in2 net opening = 3.7 gal. " 2,333 times more moisture via air leakage! 1 - Institute for Research in Construction, National Research Council, Canada 1m2, 70oF, 30% RH, 9.3 MPH wind, -4oF sheathing, 4 mil VR, 1 month INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 39 continuous air barrier air leakage testing INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 40 durability testing cmu test specimen INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 41 air leakage testing - cmu masonry wall air leakage INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 42 masonry wall air leakage air barrier adhesion testing INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 43 Improperly applied elastomeric when to install an air barrier “…shall be provided when a building component or assembly separates interior building conditioned space from the outdoors” 1 1 - wisconsin enrolled commercial building code - 2002 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 44 air barrier location “interior side of wall insulation” 1 1 - Wisconsin Enrolled Commercial Building Code - 2002 proper air barrier location INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 45 air barrier @ masonry rain screen wall air barrier @ masonry rain screen wall INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 46 air barrier @ masonry rain screen wall air barrier @ masonry rain screen wall INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 47 air barrier @ masonry rain screen wall air barrier @ masonry rain screen wall INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 48 air barrier @ masonry rain screen wall air barrier @ channel-anchored masonry INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 49 air barrier @ channel-anchored masonry problem with “poly” air barriers INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 50 discontinuous poly “air barrier” hospital INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 51 hospital hospital INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 52 air barriers solution for veneer walls weep vent insultation back-up wall (uninsulated or foamed – no batts!) air barrier what’s wrong ? INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 53 what’s wrong ? what’s wrong ? INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 54 what’s wrong ? what’s wrong ? INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 55 swimming pool swimming pool INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 56 swimming pool university laboratory INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 57 university laboratory car wash INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 58 car wash car wash INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 59 rolled-on bituminous air barrier brush-applied elastomeric air barrier INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 60 adhesive membrane – improper installation adhesive air barrier membrane INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 61 membrane air barrier veneer replacement case study INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 62 veneer replacement case study veneer replacement case study INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 63 veneer replacement case study veneer replacement case study INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 64 air space compartmentalization air space compartmentalization INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 65 air space compartmentalization air space compartmentalization INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 66 air space compartmentalization c spray-applied urethane foam air barrier INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 67 typical foam use spray-applied urethane foam air barrier INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 68 spray-applied urethane foam air barrier air barrier mock-ups INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 69 dripping bituminous AB @ 55oF overture center air barrier INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 70 air barrier as water-resistive barrier substrate prep INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 71 substrate prep spray-applied elastomeric INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 72 spray-applied elastomeric air barrier quality control INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 73 complete air barrier system air barrier & flashing interface INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 74 air barrier & flashing interface air barrier & insulation interface INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 75 Rigid Insulation tape as an air barrier ? Building Structure Rigid Insulation Tape Cladding Building Structure Rigid Insulation Cladding Rigid Insulation better location for the air barrier INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 76 rigid insulation joints continuous rigid insulation ? INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 77 air barrier & window interface air barrier window detail INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 78 membrane air barrier membrane air barrier INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 79 membrane air barrier membrane air barrier INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 80 air barrier & top-of-wall interface air barrier parapet detail INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 81 air barrier & top-of-wall interface harley-davidson museum INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 82 harley-davidson museum harley-davidson museum INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 83 harley-davidson museum harley-davidson museum INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 84 harley-davidson museum harley-davidson museum INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 85 harley-davidson museum harley-davidson museum INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 86 conclusion key take-away points ! air barrier goals " " " ! ! ! protects building envelope saves energy code compliance typical vapor barrier is not an air barrier specify air barriers as a system require certified installers INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org Air Barriers For Masonry Walls MCACP/IMI/BAC Seminar February 25, 20089 87 thank you for your time questions this concludes the american institute of architects continuing education system program /%.&$%)./"%)3*()1"%$'*/%1./.#.& /(/F6&7F"$, QOOFRSRFOTQQ air barriers for masonry walls pat conway, aia, csi international masonry institute pconway@imiweb.org © international masonry institute 2009 INTERNATIONAL MASONRY INSTITUTE 800-IMI-0988, imiweb.org