– COVER SHEET Meeting Date: 28 November 2012
Transcription
– COVER SHEET Meeting Date: 28 November 2012
INTEGRATED PERFORMANCE REPORT – COVER SHEET Meeting Date: 28 November 2012 Agenda Item: 1.12 Paper No: G Title: Integrated Performance Report Purpose: To report on performance against key indicators for the Trust in October 2012. Summary: Financial Performance The Trust remains broadly in line with plan for the 7 months to October 2012 although there is a shortfall for the month because of additional cost pressures and shortfalls on original CIP programme: • surplus of £160k for month of October against planned surplus of £285k; • surplus of £836k for seven months ytd against planned surplus of £958k However the reported surplus includes £847k of non-recurring income/costs meaning that the underlying financial position of the Trust is broadly break-even. Financial Risk Rating remains at 3 and cash continues ahead of plan: £13.8m against plan of £12.5m. Clinical Performance & Quality All Monitor Targets were met for October 2012 (Quarter 2 for cancer) All Monitor cancer standards were achieved in Quarter 2, the most recent period available, despite the 62 day referral target being missed in September. At aggregate level all three RTT18 targets were achieved. Gynaecology sub speciality issues are likely to continue, and gynaecology will remain challenging during Quarter 3. Endoscopy waiters over 6 weeks have shown some improvement, but waiters over 6 weeks in diagnostics remain more than 1% of the overall list. No further MRSA cases have occurred since September, the year to date total remains 2. The continued improvement in Trauma and Orthopaedics, resulting in all targets being achieved in October is noted. The stroke target was failed in October. The disappointing drop in performance was directly linked to the bed reconfiguration coinciding with an increase in stroke presentations which proved challenging for a period of days. Recommend ation: Prepared by: For discussion and noting. PAUL TURNER Director of Finance / KATE THOMAS Performance Manager Presented by: PAUL TURNER Director of Finance MARY SHERRY Chief Operation Officer MARTIN SMITS Director of Nursing SARAH-JANE TAYLOR HR Director This report is relevant to: (Please tick relevant box) Assurance Framework Risk Register I/D No. Healthcare Standards: Please specify which standard Monitor compliance Financial implications Human Resources implications Internal monitoring Legal implications YES YES NO INTEGRATED PERFORMANCE REPORT TRUST PERFORMANCE SUMMARY October 2012 Target / Limit 2012-13 Mar-12 Aug-12 Sep-12 Oct-12 Direction # 2011-12 Year To Date YTD/ current Actual YTD Target / Limit 17.4 - Year End Forecast Monitor targets & weightings Ja 00 ACCESS AND TARGETS Referral to waiting time (weeks) for admitted (95th centile) 23.0 21.3 17.0 16.9 17.4 RTT Referral to waiting time (weeks) for non-admitted (95th centile) 18.3 17.0 16.7 16.4 16.7 Referral to treatment (18 weeks) for admitted 90% 92.5% 97.3% 97.6% 97.1% Referral to treatment (18 weeks) for non-admitted Referral to waiting time (18 weeks) for incomplete pathways Maximum 62 day wait from referral to treatment for all cancers 62 day wait for 1st treatment - consultant screening service (all) 95% 92% 85% 90% cancer 31 day wait for 2nd or sub treatment : Anti cancer drug treat 98% 31 day wait for 2nd or sub treatment : Surgery 94% 31 day wait for 2nd or sub treatment : Radiotherapy 94% 31 days wait diagnosis to start of 1st treatment: All cancers 96% 96.6% 93.5% 90.1% qtr 92.2% 100% qtr 98.2% 98.3% 96.3% 95.2% 98.1% 97.4% 96.9% 97.5% 97.4% 81.7% qtr 97.7% 94.4% qtr 97.9% 100% 100% qtr 100% 100.0% qtr 100% 97.9% 100% qtr 98.8% 100.0% qtr 98.9% 99.3% 97.7% qtr 99.6% 98.9% qtr 98.4% 100% 98.5% qtr 98.8% 99.4% qtr 99.3% 87.1% 95% 96.1% 97.2% 97.5% 96.9% Total time in A+E (95th centile) from Q1 =< 4 hours 3hrs 59 3hrs 58 3hrs 57 3hrs 58 Time to initial asessement (95th centile) from Q2 =< 15 mins 12 15 16 15 Time to treatment decision (median) from Q2 =< 60 mins 67 51 59 42 =< 5% 2.83% 3.00% 3.00% NR =< 5% 3.35% 2.80% 2.70% 2.50% 68% 100.0% 83.0% - 2 week maximum wait for Rapid Access Chest Pain Clinic appt 0 0 1 0 0 No waits more than 6 weeks for diagnostic investigations 0 27 37 41 26 Elective Access - rebooking 0 1 1 0 1 80% 68% 80.0% 91.0% 76% A&E cardiac access Patients who spend at least 90% of their time on a stroke unit ↑ ↑ 95% 1.0 97.4% 92% 1.0 ↑ 81.7% qtr 97.7% 94.4% qtr 97.9% ↓ 93% Heart attack patients to receive thrombolysis within 60 mins of call 1.0 97.5% ↓ percentage of patients within the 4 hour target Unplanned reattendance rate from Q2 Left without being seen from Q2 90% ↑ 2 week wait for Symptomatic Breast Patients 95.2% - 97.1% ↔ 93.5% qtr 94.8% 97.7% qtr 94.8% 93% 16.7 ↓ 95.8% qtr 96.3% 100% qtr 96.1% 2 week wait from urgent GP referral to 1st appt (susp cancer) ↓ ↓ ↓ ↓ ↓ breast screen Outpatient Access : ASIs at =< 4% 4% 8% 12% 11% 21% Screening to normal results within 14 days 90% 96.8% 96.0% 98.0% 96.0% Screening to assessment in 21 days - screening to 1st appt offer 90% 94.8% 99.0% 96.0% 99.0% Screening to assessment in 21 days - screening to attended appt 90% of eligible woman screened within 36 months 90% 92.2% 96.0% 92.0% 98.0% 90% 99.2% 99.1% 99.1% 95.4% ↓ ↓ ↑ ↑ ↑ ↑ ↔ ↑ ↓ ↓ ↓ ↓ ↑ ↑ ↓ 100% qtr 100% 100% qtr 98.9% 97.7% qtr 98.4% 98.5% qtr 99.3% 93.5% qtr 94.8% 97.7% qtr 94.8% 96.9% 85% 1.0 90% 98% 94% 1.0 94% 96% 93% 0.5 0.5 93% 95% 3hrs 58 =< 4 hours 15 =< 15 mins 42 =< 60 mins NR =< 5% 2.50% =< 5% - 68% 0 0 26 0 1 0 76% 80% 21% 4% 96.0% 90% 99.0% 90% 98.0% 90% 95.4% 90% 1.0 Target / Limit 2012-13 Mar-12 Aug-12 Sep-12 Oct-12 Delayed transfers of care to be maintained at a minimal level 3.5% 6.2% 3.5% 3.0% 3.8% Trauma inpatients (fit for surgery) receive treatment within 48 hrs Hip fractures (fit for surgery) receive treatment within 48 hrs 95% 96% 95% 94% 97% 95% 96% 84% 92% 100% Direction # 2011-12 ↓ ↑ ↑ Year To Date YTD/ current Actual YTD Target / Limit 3.8% 3.5% 97% 95% 100% 95% Year End Forecast Monitor targets & weightings CLINICAL QUALITY Dr Foster Mortality relative risk rating (3 month rolling) 100% 78 91.3 All deaths - actual as % of expected (Dr Foster) 100% 89% 112% HSMR deaths - actual as % of expected (Dr Foster) 100% 94% 115% all 1 2 2 1 0 1 2 2 1 Theatre Utilisation - Main 85% 87.0% 93.0% 87.2% 87.0% Theatre Utilisation - Day 85% 74.0% 75.0% 70.8% 77.0% Day Case Rates (basket of 25) Bed Occupancy 75% 84% 74% 95% 96% 95% 97% 99% meeting the C-Diff objective (ytd) =<24 24 11 13 14 meeting the MRSA objective (ytd) =<1 1 1 2 2 Number of SUIs reported within appropriate timeframe Number of Serious Untoward Incidents (SUIs) ↓ ↓ ↓ ↑ ↑ 91.3 100% 112% 100% 115% 100% 1 all 1 0 87% 85% 77% 85% 74% 75% 99% 95% 14 =<24 1.0 2 =<1 1.0 OPERATIONAL EFFICIENCY ↓ ↑ ↓ ↓ PATIENT EXPERIENCE ↑ ↔ STAFF EXPERIENCE Staff Turnover (Overall) Staff Turnover (Auxiliaries and HCAs) Absence <=11% 0.92% 0.90% 0.72% 0.62% <= 13.5% 1.54% 1.95% 2.37% 1.50% <=3.5% 3.85% 3.37% 3.43% 3.44% ↑ ↑ ↓ 0.62% <=11% 1.50% <= 13.5% 3.44% <=3.5% FINANCE & ACTIVITY Cash balance 15.4 16.5 13.6 13.8 13.80 12.51 13.40 Income 21.20 16.62 16.17 16.56 113.83 112.77 197.63 Operating Expenditure 20.30 15.38 15.04 15.41 106.09 104.87 184.23 EBITDA 0.70 1.07 0.93 0.95 6.34 6.51 11.00 EBITDA % 3.3% 6.4% 5.7% 5.7% 5.6% 5.6% 5.6% Surplus/Deficit -0.30 0.26 0.14 0.16 0.84 0.96 1.50 SLA over / (under) performance 0.1 0.1 - - 0.03 0.00 0.03 CIP 0.8 0.6 0.6 0.6 4.17 4.24 7.79 3 3 3 3 3.0 3.0 3.0 Financial Risk rating # : Arrow direction indicates improvement ↑, deterioration ↓, or no change ↔ in performance since the previous month INTEGRATED FINANCE AND PERFORMANCE REPORT Month Seven - October 2012 Key Issue Trust Performance – Monitor Targets Executive Summary KPI Cancer RTT The Trust achieved the targets for admitted clock stops (97.1% against 90% target) and non-admitted (97.5% against 95% target) clock stops, at aggregate level in October. The incomplete pathways target of 92% was achieved, with 97.4% of incomplete pathways waiting less than 18 weeks at the end of October. Performance Report appended. MRSA CDiff Monitor scorecard ED The Monitor A&E metric (95% within 4 hours) was achieved in October (96.9%). Performance Report appended No further MRSA cases have occurred since September. The Trust total for the year to date therefore remains at 2 cases. Only 1 C-Diff case was identified in October, brining the year to date total to 14, meeting the planned trajectory of 14 (based on 2 per month). Sch G The 2012-13 monitor scorecard is comprised of 14 key indicators, all standards have been met as at October and Quarter 2. All Monitor cancer standards were achieved in Quarter 2. The 62 day target was however failed in September. The Quarter 2 cancer report and charts, are appended RAG Key Issue Trust Performance – Finance & Activity Executive Summary However the reported surplus includes £847k of non-recurring income/costs meaning that the underlying financial position of the Trust is broadly break-even. Financial Risk Rating remains at 3 and cash continues ahead of plan: £13.8m against plan of £12.5m. All financial variances with specific focus on: •Income •EBITDA •CIP •Cash •Capital spend RAG Sch A Trust I&E table The Trust remains broadly in line with plan for the 7 months to October 2012 although there is a shortfall for the month because of additional cost pressures and shortfalls on original CIP programme: • surplus of £160k for month of October against planned surplus of £285k; • surplus of £836k for seven months ytd against planned surplus of £958k KPI Key Issue Trust Performance – Access and Targets Executive Summary KPI RAG Sch The Access and Targets scorecard is comprised of 22 key indicators, of which 5 are red rated. • • • • • RTT The Trust achieved the targets for admitted clock stops (97.1% against 90% target) and non-admitted (97.5% against 95% target) clock stops, at both aggregate and Unify specialty level in October. The incomplete pathways target was achieved (97.4% against 92% target) at both aggregate and specialty level. Performance Report appended Diagnostic Access There were 26 Endoscopy patients waiting in excess of the 6 week diagnostic target at the end of October. The percentage of diagnostic waiters over 6 weeks at the month end has reduced but is still in excess of the 1% PCT contract target for the 7th consecutive month (1.14% - 29 including endoscopy). Thi s is potentially subject to a financial penalty under the 12/13 contract arrangements. Action: The Trust will continue to work with the PCT to address capacity issues and reduce referrals where possible. Capacity will be increased before the next bowel screening campaign commences. The department will be running additional Saturday lists throughout November. Performance Report appended Cancer A-G RTT Diagnostic Access Delayed Transfers of Care The percentage of patients formally delayed on the last Thursday of October (DH reporting methodology) was 3.75%. Action : Targeted actions continue to be pursued to reduce delays further. Performance Report appended Delayed Transfers of Care 48 hours standard for #NoF and Trauma The 48 hour operating target (95%) was achieved in October for general trauma patients (94%). Local and National targets for fractured NoFs were also achieved. Performance in Trauma shows a significant improvement in performance compared to recent months. Performance Report appended 48 hours standard for #NoF & Trauma • Emergency Department : 4 hour target (95%) : The 4 hour wait target of 95% was achieved in October, despite a difficult start to the month. Performance Report appended ED 4 hr target 95% • Stroke Stroke performance failed to achieve the 80% target in October (76%) Performance Report Appended Stroke Access and Targets Scorecard • Cancer All Monitor cancer standards were achieved in Quarter 2. Achievement of the 62 day standard was challenging given the target was missed in September. Review of pathways is going on to determine how to ensure performance is more robust in this area. The Quarter 2 cancer report and charts, are appended • ASI ASIs in October increased substantially to 21%, this was due mainly to Dermatology. Actions are underway to reduce the level of ASIs. ASIs • Elective cancellations rebooked within 28 days 1 pelvic floor patient due to treated in October was cancelled but could not be rebooked within 28 days. 28 day rebooks Key Issue The Clinical Quality scorecard is comprised of 5 key indicators, none of which are part of the Monitor scorecard. For the most recent year to date position (August/October 2012) there are red rated indicators relating to Mortality and SUIs • • • A Mortality performance for August (the most recent period reported by Dr Foster) has been red rated since both the HSMR subset and the overall number of deaths were more than the expected level calculated by Dr Foster for August. 3 positive alerts were reported by Dr Foster in the three month period to August 2012. One negative alert was also reported. Action : The Mortality group will commence reviewing those cases with a zero or very low co-morbidity rating in order to determine the underlying causes for the reduction in performance and devise an appropriate action plan. Mortality There was one SUI identified in October, this was reported within the prescribed timeframe. SUI The Efficiency scorecard is comprised of 4 key indicators; none of these are part of the Monitor scorecard. For the most recent year to date position (October 2012) there are two red rated indicators: • Theatre Utilisation Day theatre utilisation in October was 77%. • Bed Occupancy Average bed occupancy in October was 99%, and did not achieve the target of 95% or less. RAG A-G Theatre Utilisation Bed occupancy Sch Efficiency Scorecard Trust Performance – Efficiency KPI Clinical Quality Scorecard Trust Performance – Clinical Quality Executive Summary The Patient Experience scorecard is comprised of 6 key indicators, 3 of these are part of the Monitor scorecard. For the most recent year to date position (October 2012) there are no red rated indicators: • C-Diff There have been 14 cases of C-Diff during the period 1 April to 31 October 2012. The Trust is currently meeting its trajectory of 2 per month (14 ytd). Action: DoN to review A C Diff objective MRSA objective • MRSA The MRSA year to date total for 2012-13 remains two, the cases occurred in June and September. Action : Infection Control issues remain under continued scrutiny DoN/Infection Control. • MSA There have been no breaches of mixed sex accommodation (MSA) in October. Mixed Sex Accommo dation • VTE VTE performance was 89.1% for October narrowly missing the pct target of 90%. VTE Patient Experience Scorecard Trust Performance – Patient Experience Trust I&E Month - October Year to Date Full Year Actual Plan Variance Last Year Actual Plan Variance Last Year Forecast Plan Last Year £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 9,515 3,673 1,045 386 1,738 16,357 200 16,557 9,077 3,645 990 386 1,889 15,987 200 16,187 438 28 55 0 (151) 370 0 370 9,462 3,798 315 356 1,793 15,724 58 15,782 64,001 25,609 7,138 2,593 13,089 112,430 1,400 113,830 63,516 25,559 6,957 2,591 12,749 111,372 1,400 112,772 485 50 181 2 340 1,058 0 1,058 66,236 26,586 2,205 2,534 12,104 109,665 386 110,051 155,669 12,280 4,400 22,877 195,226 2,400 197,626 109,039 43,917 11,654 4,400 22,068 191,078 2,813 193,891 118,639 45,914 4,855 4,203 21,140 194,751 301 195,052 Pay Costs Non-Pay Costs (10,705) (4,704) (10,608) (4,301) (97) (403) (10,482) (4,253) (74,454) (31,634) (74,093) (30,772) (361) (862) (73,163) (29,966) (129,829) (54,396) (127,711) (52,172) (127,940) (54,247) Total Operating Expenditure (15,409) (14,909) (500) (14,735) (106,088) (104,865) (1,223) (103,129) (184,225) (179,883) (182,187) 0 0 0 0 0 0 0 0 0 0 (218) 948 (747) 5 (246) 1,078 (749) 6 (250) (130) 2 (1) 4 989 (744) 11 (250) 6,342 (5,227) 42 (1,721) 6,507 (5,242) 43 (1,750) (165) 15 (1) 29 6,536 (5,120) 61 (1,750) 11,001 (8,986) 85 (3,000) 11,195 (8,986) 78 (3,000) 12,346 (8,859) 95 (2,928) 160 0 160 40 120 285 0 285 40 245 (125) 0 (125) 0 (125) 64 0 64 88 (24) 836 0 836 847 (11) 958 0 958 280 678 (122) 0 (122) 567 (689) 113 0 113 626 (513) 1,500 0 1,500 1,377 123 2,100 0 2,100 400 1,700 955 (839) 116 (2,175) 3,130 Contract Income - B&P PCT Contract Income - Dorset PCT Contract Income - Specialist Commissioning Contract Income - Other Other Operating Income Total Operating Income Charitable Income Total Income Profit/(Loss) on disposal of fixed assets EBITDA Depreciation Interest Receivable/(Payable) Dividend Surplus/(Deficit) Impairment Surplus/(Deficit) after Impariment Non-recurring costs included above Normalised Surplus/(Deficit) Key Observations Forecast Key Actions Cancer Waiting Times Q2 2012/13: Poole Hospital NHS Foundation Trust – Summary report The following convention is used for indicating compliance with the performance standards. Standard achieved or exceeded Performance within 10% of standard Performance more than 10% below standard Data are taken from the Open Exeter national database for Cancer Waiting Times. Scorecard Target PHT 14 days: referral to date first seen (93%) ▼ 14 days: all breast symptom referrals (93%) ▼ 31 days: first treatment (96%) ▼ 31 days: subsequent treatment (surgery) (94%) ▼ 31 days: subsequent treatment (drug) (98%) ◄ 31 days: subsequent treatment (radiotherapy) (94%) ▼ 62 days: referral to first treatment (85%) ▼ 62 days: referral from screening programmes (90%) ▼ The arrows on the performance measures in the scorecard indicate whether performance has increased decreased or stayed the same, relative to the previous quarter. Data for the Dorset Cancer Network and other acute Trusts was not available at the time of writing 14 days: Urgent GP referral to Date First Seen Maximum 2 week wait from urgent GP referral for suspected cancer to first hospital assessment by 2000 Measure Everyone with suspected cancer will be able to see a specialist within two weeks of their GP deciding they need to be seen urgently and requesting an appointment by 2000 Target 93% or more Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 Tumour Type Total % meeting Median referrals standard wait seen in Poole during the period 93.3 National % meeting standard Suspected brain/central nervous system tumours 30 8 97.2 Suspected breast cancer 305 96.1 8 97.4 Suspected children's cancer 16 93.8 9 93.9 Suspected gynaecological cancer 111 96.4 9 95.8 Suspected haematological malignancies (excluding acute leukaemia) 13 92.3 6 96.7 Suspected head & neck cancer 196 96.9 9 95.9 Suspected lower gastrointestinal cancer 179 91.1 11 94.5 Suspected lung cancer 53 100 9 97.2 Suspected other cancer 1 100 7 94.9 Suspected sarcoma 6 100 9 96.2 Suspected skin cancer 285 94.4 9 94.5 Suspected upper gastrointestinal cancer Suspected urological malignancies (excluding testicular) Totals 110 1 1306 90.9 100 94.8 12 14 93.6 95.3 95.4 Breach reasons No. of patients Breach reasons 62 Patient cancelled/declined 1st. OPA/investigation within target 2 Endoscopy capacity issues 1 Referral form not completed appropriately 1 Patient was an inpatient for a different problem from 28/8 - 5/9 1 The patient needed to be off warfarin for a certain length of time prior to gastroscopy. However there was insufficient information on the referral form to allow appropriate triage of the patient. As a result there was a clinical delay to date first seen 1 Hospital cancelled appointment because a different procedure was needed. Trends in ‘Urgent referrals for suspected cancer’ are given in the chart below: The number of referrals first seen each quarter continues to increase. In Q2 12/13, 1306 patients were first seen - the highest number reported to date. This represents a 22% increase compared with the number seen in the same quarter 2 years ago and a 9.5% increase compared with Q2 11/12. 14 days: All breast symptom referrals Measure Maximum 2 week wait from referral of any patient with breast symptoms to first hospital assessment by December 2009 Target 93% or more Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 Totals Total referrals seen during the period % meeting standard at Poole 115 94.8 Median National wait % meeting standard 8 95.7 Breach reasons No. of patients Breach reasons 3 Patient cancelled/declined 1st. OPA/investigation within target 1 Difficulty in contacting patient 1 Admin error 1 Patient was originally referred as choose and book. 31 days: Decision to Treat to First Treatment Measure Maximum 31 day wait from decision to treat to first treatment for all cancers by 2005 Target 96% or more Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 a) By tumour site Patients treated following an urgent referral for suspected cancer Total treated Brain/Central Nervous System 0 3 3 0 100 0 98.7 Breast 36 92 90 2 97.8 19 99.2 Gynaecological 23 40 40 0 100 8 99 Haematological 17 35 35 0 100 0 99.8 Head & Neck 28 43 42 1 97.7 15 96.9 Lower Gastrointestinal 15 56 56 0 100 9 98.7 Lung 24 49 49 0 100 4 98.8 Other 1 8 8 0 100 0 98.8 Sarcoma 0 1 1 0 100 26 97.8 Skin 24 74 74 0 100 6 98.6 Upper Gastrointestinal 15 30 30 0 100 3 99.2 Urological 5 14 14 0 100 17 96.5 188 445 442 3 99.3 Tumour Type All Cancers % Median Treated on Treated or within after 31 meeting Waiting days standard Time 31 days National % meeting standard 98.4 b) By treatment type Treatment Group Patients treated following an urgent referral for suspected cancer Drug Treatments Other Treatments Palliative Treatments Radiotherapy Treatments Surgery All Treatments 44 1 26 31 86 188 Patients Patients Patients Total treated treated treated treated following following following an urgent an urgent a referral referral referral from for breast from an another symptoms NHS source or Cancer urgency Screening Service 0 2 32 78 0 0 0 1 0 0 39 65 0 1 34 66 4 51 94 235 4 54 199 445 Treated Treated % Median National on or after 31 meeting Waiting % standard within 31 days Time meeting at Poole days standard 78 1 65 66 232 442 0 0 0 0 3 3 100 100 100 100 98.7 99.3 Breach reasons Tumour Type Breast Wait Days 37 Breast 37 Head & Neck 35 Report Need time for Haematology consultant to assess patient and do any further investigations as required. Patient admitted for surgery within target but ran out of theatre time so was discharged without treatment. No capacity to bring surgery forward & surgeon on annual leave 23/7/12 - 3/8/12. 31 days: Second and Subsequent Treatments Measure Maximum 1 month wait from ready to treat to treatment for all second and subsequent treatments 3 0 0 14 13 99.9 96.8 100 97.9 97.5 98.4 (chemotherapy and surgery by December 2008, all other treatments December 2009) Target 98% - Anti Cancer drug treatments ; 94% - Surgery treatments ; 94% - Radiotherapy treatments Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 a) By tumour site Tumour Type Total treated Treated on or within 31 days Brain/Central Nervous System 17 17 0 100 11 99.3 Breast 290 287 3 99 13 98.5 Gynaecological 48 47 1 97.9 7 98.7 Haematological 64 64 0 100 4 99.7 Head & Neck 38 36 2 94.7 14 97.4 Lower Gastrointestinal 49 49 0 100 8 98.8 Lung 74 74 0 100 6 99.5 Other 11 11 0 100 5 99.1 8 7 1 87.5 2 98.2 Skin 63 61 2 96.8 19 98.2 Upper Gastrointestinal 44 44 0 100 2 98.6 Urological All Cancers 146 852 145 842 1 10 99.3 98.8 6 97.8 98.5 Total treated Treated on or within 31 days 198 7 118 434 95 852 198 6 117 427 94 842 Sarcoma Treated % Median after 31 meeting Waiting days standard Time National % meeting standard b) By treatment type Treatment Group Drug Treatments Other Treatments Palliative Treatments Radiotherapy Treatments Surgery All Treatments Treated Poole % Median after 31 meeting Waiting days standard Time 0 1 1 7 1 10 100 85.7 99.2 98.4 98.9 98.8 0 14 0 14 19 National % meeting standard 99.8 97 100 97.9 97.5 98.5 Breach reasons Tumour Type Skin Treatment type Surgery Wait Days 47 Head & Neck Other 36 Urological Radiotherapy 146 Breast Radiotherapy 51 Report Unable to bring TCI date forward - spoke to management & discussed at breach meeting (Consultant on leave 29 June & 2529June). Insufficient capacity - treatment room not available. Patient requested treatment start after a holiday at the end of July 2012. Patient requested start date at the beginning of August because of son’s wedding. Skin Radiotherapy 44 Patient not due to start RT until 27/09/12 as going on holiday 17/09 - 20/09 and wanted to defer treatment until after holiday. Head & Neck Radiotherapy 36 Breast Radiotherapy 36 Technical difficulties during RT planning. A new Zentec+ CT Scan was required as the quality Imaging tolerance was unacceptable with the original orfit Patient was on holiday so treatment was delayed Gynaecological Radiotherapy 35 Breast Radiotherapy 34 Sarcoma Radiotherapy 34 Patient referred to community palliative care first contact delayed by episodes in hospital Required replanning Patient was not ready to start treatment until 6/8 due to extractions of his teeth. 62 days: Urgent GP referral to First Treatment Measure Maximum 62 day wait from urgent GP referral to first treatment for all cancers by 2005 Target 85% or more Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 a) By tumour site Breast Gynaecological Haematological (Excluding Acute Leukaemia) Head & Neck Lower Gastrointestinal Lung Other Skin Upper Gastrointestinal Urological Total Actual no. treated Accountable no. treated 36 23 17 28 16 28 1 25 16 5 195 36 16 15.5 21.5 13 22 1 23.5 14.5 3 166 Accountable Poole % National no. over meeting % target standard meeting standard 3 91.7 97.8 2 87.5 85.2 1 93.5 83.5 4.5 79.1 75.8 3 76.9 79 4 81.8 80.4 0 100 81.3 0.5 97.9 97.9 1 93.1 81 1.5 50 83 20.5 87.7 87.2 b) By treatment type Treatment Group Accountable Accountable no. treated no. over target Drug Treatments Other Treatments Palliative Treatments Radiotherapy Treatments Surgery Totals 39 1 25 20 81 166 4 0 3 6 7.5 20.5 Poole % meeting standard 89.7 100 88 70 90.7 87.7 National % meeting standard 84.1 83 92.4 64.9 89.9 87.2 Breach reasons Tumour Type First Treatment Trust RD3 Wait Days Report Breast First Seen Trust RD3 111 Breast RD3 RD3 64 Breast RD3 RD3 70 Gynaecological RBD RD3 69 Haematological (Excluding Acute Leukaemia) Head & Neck RBD RD3 147 Patient has known CLL and required lots of biopsies and diagnostic tests. Patient originally given a TCI date of 22/6/12 but at pre-assessment required various cardiac investigations to determine if fit for surgery. Patient admitted for surgery within target but ran out of theatre time so was discharged without treatment. Late referral from other trust - required staging before treatment could be considered. Complex case with many tests required RBD RD3 95 Head & Neck Head & Neck RD3 RD3 RD3 RD3 69 85 Head & Neck RD3 RD3 73 Complex pathway patient needed several diagnostic tests (trying to find primary cancer). Patient refused to travel to Southampton for a PET scan. ENT Admissions unable to book patient within target date. Complex pathway - originally referred via Haematology and then lack of capacity to book surgery within target date due to consultant being on annual leave. Patient needed numerous diagnostic tests to try and find primary cancer and also was not very compliant (would not wait in clinic to discuss treatment plan) Patient was booked to start treatment 05/09/12 but when they arrived they did not have PICC line inserted. Provisional date for surgery 17/07/12 delayed as patient needed to stop aspirin and have CPEX test before operation. Complex diagnostic pathway - referred via an Upper GI fast track patient non-compliant with investigations. Patient initially thought to be fit for RFA but was considered unfit and referred for surgery. Borderline fitness for surgery, requested anaesthetic assessment. Referral from other Trust received day 66 of pathway. Complex diagnostic pathway complex pathway Patient referred from another site - had investigations for UGI and H&N cancer CARP received day 237 of pathway. Patient non-compliant at referring trust during diagnostic investigations. Lower Gastrointestinal Lower Gastrointestinal Lung RBD RD3 66 RD3 RD3 78 RD3 RD3 75 Lung RD3 RHM 108 Lung RDZ RD3 83 Skin Upper Gastrointestinal Urological (Excluding Testicular) Urological (Excluding Testicular) Urological (Excluding Testicular) Gynaecological RD3 RD3 RDZ RD3 126 68 RDZ RD3 306 RDZ RD3 196 Cross Trust Referral received day 135 of pathway. RDZ RD3 161 Clinical referral and CARP recd day 86 of pathway from other trust - no breach reason given by referring trust RD3 RD3 80 Gynaecological RDZ RD3 83 Haematological (Excl Acute Leukaemia) Head & Neck Head & Neck RDZ RD3 114 patient was unsure whether or not she wanted to have treatment - she is an elderly lady and was persuaded to have treatment by her family. Was due to start treatment - PET scan revealed uptake in Bone marrow - had bone marrow trephine and had to be re-planned for radiotherapy. Patient declined systemic chemotherapy. RDZ RDZ RD3 RD3 72 132 Lower Gastrointestinal RD3 RD3 154 Lower Gastrointestinal RD3 RDZ 86 Lung RD3 RD3 88 Lung RD3 RD3 195 Non compliance for various investigations by patient. Patient was removed from tracking by referring trust in error following 1st diagnostic test. which was reported as inadequate sample. Patients extensive co-morbidities caused many investigations to be delayed or were cancelled by the patient both for diagnosis and to determine fitness for treatment Patient away on holiday at beginning of pathway. Patient then DNA'd OPA on 22.5.12. Many diagnostic tests USS, CT, EUS/Biopsy, PET, MRI 29 day delay for PET scan (soonest available appointment and patient didn’t wish to travel to other site for scan). Patient initially booked to start treatment on breach date but was eligible for trial so needed longer planning. Patient non compliant with appointments and DNAd surgery disease then progressed so no longer fit for any active treatment 62 days: Suspected cancer patients detected through national screening programmes Measure Maximum 2 month wait from referral from NHS Cancer Screening Programme to treatment by December 2008 Target 90% or more Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 Breast First Seen Provider First Treatment Provider Actual no. treated RD3 RD3 RD3 Total RBD RD3 RDZ 15 39 18 72 Accountable Accountable Poole % Median no. treated no. over meeting Waiting target standard Time 7.5 39 9 55.5 0 0 0 0 100 100 100 100 33 48 35 National % meeting standard 97.6 97.6 97.6 97.6 a) Gynaecological First Seen Provider First Treatment Provider Actual no. treated RD3 RD3 1 2 3 RBD RD3 Total b) First Seen Provider Accountable Accountable Poole % Median no. treated no. over meeting Waiting target standard Time 0.5 2 2.5 0 0 0 100 100 100 37 31 National % meeting standard 95.2 95.2 95.2 Lower GI First Treatment Provider Actual no. treated RD3 RHM 12 1 13 RD3 RD3 Total Accountable Accountable Poole % Median meeting Waiting no. treated no. over standard Time target 12 0.5 12.5 1 0.5 1.5 91.7 0 88 53 79 National % meeting standard 81.3 81.3 81.3 c) ALL SCREENING PROGRAMMES First Seen Provider First Treatment Provider Actual no. treated RD3 RBD RD3 RDZ RHM 1 15 53 18 1 88 RBD RD3 RD3 RD3 RD3 Total Accountable Accountable Poole % National no. treated no. over meeting % target standard meeting standard 0.5 0 100 94.9 7.5 0 100 94.9 53 1 98.1 94.9 9 0 100 94.9 0.5 0.5 0 94.9 70.5 1.5 97.9 94.9 Breach reasons Tumour Type Lower Gastrointestinal Lower Gastrointestinal First Seen Trust RD3 First Treatment Trust RD3 Wait Days Report 88 RD3 RHM 79 There was a long wait for the patients scans to be booked and then reported despite repeated attempts to expedite Complex pathway 62 days: Suspected cancer patients not referred urgently and upgraded by Consultants Measure Maximum 2 month wait from consultant upgrade of urgency of a referral to first treatment by December 2008 Target Not yet defined Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 Accountable Accountable Poole % National no. treated no. over meeting % target standard meeting standard Brain/Central Nervous System 2 0 100 100 Breast 1 0 100 98.1 Haematological 2 0 100 95.3 Lower Gastrointestinal 17 1 94.1 94.3 Lung 2.5 0 100 89.1 Skin 4 0 100 98.8 Urological 0.5 0.5 0 91 All Cancers 29 1.5 94.8 93.2 Breach reasons Tumour Type Lower Gastrointestinal Urological (Excluding Testicular) Consultant Upgrade Trust RD3 First Treatment Trust RD3 Wait Days Report 90 Several diagnostic tests required and complex investigations RDZ RD3 167 CARP and referral received after upgrade breach date from referring trust - complex diagnostic pathway at referring trust. 62 days: Breast symptomatic referral (non cancer) to first treatment Measure Maximum 2 month wait from breast symptomatic referral (non cancer) to first treatment Target No standard set Source National Cancer Waiting Times Database (Open Exeter) Time Period Q2 2012/13 First First Seen Treatment Provider Provider RD3 Total RD3 Actual Total treated Accountable no. treated 4 4 4 4 Accountable Poole % National meeting no. over % standard meeting target standard 0 100 95.6 0 100 95.6 Key of Trust Codes: RBD DORSET COUNTY HOSPITAL NHS FOUNDATION TRUST RD3 POOLE HOSPITAL NHS FOUNDATION TRUST RDZ THE ROYAL BOURNEMOUTH AND CHRISTCHURCH HOSPITALS NHS FOUNDATION TRUST RHM SOUTHAMPTON UNIVERSITY HOSPITALS NHS TRUST RAN ROYAL NATIONAL ORTHOPAEDIC HOSPITAL NHS TRUST RNZ SALISBURY NHS FOUNDATION TRUST RA4 YEOVIL DISTRICT HOSPITAL NHS FOUNDATION TRUST RPY THE ROYAL MARSDEN NHS FOUNDATION TRUST RBA TAUNTON AND SOMERSET NHS FOUNDATION TRUST RM1 NORFOLK AND NORWICH UNIVERSITY HOSPITALS NHS FOUNDATION TRUST RH8 ROYAL DEVON AND EXETER NHS FOUNDATION TRUST RJZ KING'S COLLEGE HOSPITAL NHS FOUNDATION TRUST RWA HULL AND EAST YORKSHIRE HOSPITALS NHS TRUST Prepared by Anne Foulkes Performance Manager Medical Division November 2012 CWT Trends in performance Anne Foulkes Business & Performance Manager, Medical Division November 2012 PERFORMANCE REPORT October 2012 Emergency Department Professional Standards The Risk: The first week of October presented a challenge to the performance against the 4 hour target. However, there was a rapid recovery and the performance against the 4 hour target for the remainder of the month was strong, resulting in the month-end position being 96.89%. All of the key performance indicators were met in October. Progress has been made to improve data quality for the nurse assessment times, and this has resulted in the target being met for October. Clinician seen time for October was 42 minutes (against the target of 60 minutes). This represents the best performance against the target this year. The total time spent in the department was 238 minutes (95th percentile target), which has remained steady since April 2012. The time spent in the department for admitted patients was 264, which is a worsening position from the previous month’s improvement. The position was severely affected by the first week of October when bed pressures caused a number of breaches. Whilst this is not a monitor standard, the aim is to reduce this to within 240 minutes. To date, the Quarter position shows a continuation of recent performance with all targets on track to be achieved. Current Position and Actions: The Emergency Department delivered the 4 hour target for October 2012. The first four days of October presented a significant decline in performance with a large number of breaches. Actions to identify and address the issues causing the decline were taken swiftly and the performance improved towards the end of the week and has been sustained throughout October. The full Business case for staffing remains unresolved. The medical staffing shortages continue to be managed according to plan – two SpR vacancies are filled pending visa applications, one of whom has now started in post. Until both SpRs are in post, ad-hoc locums and consultants are being used to fill the week end shifts uncovered by the gaps in the rota. ST4 or above level trained staff continue to be available 24 hours a day 7 days per week, which is the standard expected. The locum consultant has started, and the substantive replacement post, as well as the 6th consultant post, has been advertised. To date, there has not been the level of interest required to fill both posts. Some contingency plans for consultant cover may be required for 2013. The chart below demonstrates the weekly performance trend against the 95% target for 4 hours:- Poole Hospital NHS Foundation Trust Weekly Progress Chart - A&E 4 hour 95% target Weekly and Quarterly Position 100.00% 98.00% 96.00% 94.00% 92.00% 90.00% 88.00% 86.00% 84.00% 82.00% 04-Nov-12 28-Oct-12 21-Oct-12 14-Oct-12 07-Oct-12 30-Sep-12 23-Sep-12 16-Sep-12 09-Sep-12 02-Sep-12 26-Aug-12 19-Aug-12 12-Aug-12 05-Aug-12 29-Jul-12 22-Jul-12 15-Jul-12 08-Jul-12 01-Jul-12 24-Jun-12 17-Jun-12 10-Jun-12 03-Jun-12 27-May-12 20-May-12 13-May-12 06-May-12 29-Apr-12 22-Apr-12 15-Apr-12 08-Apr-12 01-Apr-12 25-Mar-12 18-Mar-12 11-Mar-12 04-Mar-12 26-Feb-12 19-Feb-12 12-Feb-12 05-Feb-12 29-Jan-12 22-Jan-12 15-Jan-12 08-Jan-12 01-Jan-12 25-Dec-11 18-Dec-11 11-Dec-11 04-Dec-11 27-Nov-11 20-Nov-11 13-Nov-11 06-Nov-11 30-Oct-11 23-Oct-11 16-Oct-11 09-Oct-11 02-Oct-11 week ended weekly % within 4 hours qtr to date % seen within 4 hours 95% target 98% target Action: There is an action plan in place which is monitored weekly. It covers a range of areas for improvement (leadership on shop floor, specialty response to ED and flow through the hospital including some specific pathway development, links with outside agencies, improving staffing resources and addressing the future medical cover gaps). The plan is adjusted regularly to also take into account seasonal / local pressures, and as such will address measures required to support continued performance through the winter period. Plans to develop space in minors have been developed with the architects, this work will also include some office space and a seminar room to facilitate training of nursing and medical staff within the department. The staff are being consulted with to ensure the plans are a “best fit” for the department, as there are a number of outstanding estates issues to be addressed which cannot all be achieved within the constraints of the current space. Further analysis of frequent attenders and re-attendance rates is due to take place. A steering group has been established, which is due to meet for the first time in November, in order to develop actions to address these issues. Prepared by: Sarah Knight Directorate Manager, Emergency Services 12.11.12 PERFORMANCE REPORT October 2012 Referral to Treatment (RTT) - Admitted: Trust performance for October is 97.2% Summary: The Trust achieved the 90% RTT Target, and Gynaecology achieved the specialty target of 90%, achieving 92.9% for October. This is a fourth month of achieving the target. Current Position: At 13th November 2012, the most recent (12th November 2012) predicted performance in October for Gynaecology is 95.7%. Whilst the target continues to be achieved, fundamental capacity challenges exist within the specialty. Actions for November and December 2012: • Work with the booking team and consultant body to accommodate the one potential November breach patient currently without a TCI. • Plan in place re- lost Gynaecology theatre capacity over Christmas – Consultant body have agreed to changes in their programme resulting in a reduced loss of theatre capacity without additional cost . • 21st November meeting with Chief Operating Officer, Gynaecology CD, MCDD - DD & DM to review capacity and demand tool re-implementation of a sustainable capacity solution for Gynaecology. • 13th November meeting with RBH information Team and PHT information team re- exploring implementation of RBH live Gynaecology capacity and demand tool. . • Working with booking team to review RJH patients with January TCI’s to identify patients ‘colleague able to do’ pooling patients re- potential capacity issues due potential for RJH to accommodate ‘urgents’ re- lost oncology capacity over Christmas. • Review of theatre utilisation has identified the potential for additional patients to be added to Gynaecology Associate Specialist theatre lists from November onwards in agreement with TCH. Prepared by: Ian Sprigmore Directorate Manager Obstetrics and Gynaecology 13.11.12 Admitted Performance RTT Performance - Admitted Patients 100 % 75 50 25 0 Oct-11 94.4 % Within 18 Wks Target 90% 95th Centile Wait (wks) 95th Centile Target Admitted Patients Total patients admitted Greater than 18 weeks Unknown Clock Starts % Within 18 Wks 95th Centile Wait (wks) Nov-11 93.0 Dec-11 90.8 Jan-12 92.2 Feb-12 88.7 Mar-12 92.5 Apr-12 94.5 May-12 95.4 Jun-12 96.0 Jul-12 97.2 Aug-12 97.3 Sep-12 97.6 Oct-12 97.1 90 90 90 90 90 90 90 90 90 90 90 90 90 19.2 20.3 22.3 19.7 24.1 21.3 18.9 17.7 17.7 17.0 17.0 16.9 17.4 23 23 23 23 23 23 23 23 23 23 23 23 23 Oct-11 947 53 0 94.4 19.2 Nov-11 1114 78 0 93.0 20.3 Dec-11 818 75 0 90.8 22.3 Jan-12 978 76 0 92.2 19.7 Feb-12 962 109 0 88.7 24.1 Mar-12 1073 81 0 92.5 21.3 Apr-12 923 51 0 94.5 18.9 May-12 1132 52 0 95.4 17.7 Jun-12 866 35 0 96.0 17.7 Jul-12 1070 30 0 97.2 17.0 Aug-12 1041 28 0 97.3 17.0 Sep-12 983 24 0 97.6 16.9 Oct-12 1186 34 0 97.1 17.4 Admitted Performance Tables Code 100 110 120 140 300 320 330 400 410 430 502 **X01 % Within 18 Wks By Specialty General Surgery Trauma & Orthopaedics Ear, Nose & Throat Oral Surgery General Medicine Cardiology Dermatology Neurology Rheumatology Eld Care Gynaecology **Other TRUST TOTAL **Breakdown of X01 (Other) 107 Vascular Surgery 141 Restorative Dentistry 191 Pain Management 301 Gastroenterology 303 Haematology 311 Genetics 314 ABI & Neurorehab 321 Paediatric Cardiology 370 Med Onc 420 Paeds 800 Clin Onc Oct-11 90.7 95.9 94.0 98.1 87.5 92.3 97.7 100.0 98.0 100.0 86.5 100.0 94.4 Nov-11 85.5 94.7 91.0 96.9 100.0 90.0 97.3 100.0 97.2 N/A N/A 88.6 92.1 93.0 Oct-11 100.0 100.0 100.0 100.0 100.0 100.0 Dec-11 73.8 96.2 91.7 97.8 100.0 100.0 98.1 Feb-12 68.2 86.0 85.0 96.7 92.9 100.0 97.2 100.0 98.9 100.0 82.6 93.1 88.7 Mar-12 81.4 95.2 89.9 96.8 100.0 95.7 99.5 100.0 100.0 100.0 85.6 100.0 92.5 Apr-12 88.9 96.7 96.6 99.1 100.0 100.0 97.3 100.0 100.0 100.0 87.2 97.1 94.5 May-12 91.0 100.0 94.6 97.6 100.0 100.0 100.0 100.0 100.0 100.0 87.9 100.0 95.4 Jun-12 94.7 96.8 97.6 98.2 100.0 100.0 99.5 100.0 98.1 82.4 97.1 90.8 Jan-12 91.2 98.2 82.0 95.1 100.0 87.5 95.6 100.0 97.5 100.0 87.2 94.4 92.2 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 100.0 100.0 100.0 92.3 100.0 84.6 100.0 88.2 100.0 96.2 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 N/A 97.0 100.0 100.0 100.0 100.0 85.7 100.0 100.0 97.6 Jul-12 96.7 98.8 95.6 98.4 100.0 100.0 99.5 Aug-12 95.6 98.9 97.2 97.1 100.0 100.0 99.0 Sep-12 94.0 100.0 96.5 98.2 100.0 100.0 99.1 Oct-12 94.4 100.0 97.5 99.3 93.3 100.0 98.9 N/A N/A 100.0 100.0 100.0 100.0 100.0 N/A 100.0 100.0 86.2 96.7 96.0 98.4 100.0 94.0 97.4 97.2 94.5 100.0 97.3 96.4 100.0 97.6 92.9 95.7 97.1 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 100.0 100.0 92.9 N/A 93.3 95.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 Non-Admitted Performance RTT Performance - Non-Admitted Patients 100 75 % 50 25 0 % Within 18 Wks Target 95% Oct-11 98.4 Nov-11 97.9 Dec-11 97.4 Jan-12 97.6 Feb-12 97.0 Mar-12 96.6 Apr-12 96.1 May-12 97.0 Jun-12 97.5 Jul-12 98.1 Aug-12 98.3 Sep-12 97.4 95 95 95 95 95 95 95 95 95 95 95 95 95th Centile Wait (wks) 15.4 15.7 16.0 15.7 17.0 17.0 17.4 16.9 16.0 16.0 16.7 16.4 95th Centile Target 18.3 18.3 18.3 18.3 18.3 18.3 18.3 18.3 18.3 18.3 18.3 18.3 Jun-12 1808 43 0 97.5 16.0 Jul-12 2343 44 0 98.1 16.0 Aug-12 2199 37 0 98.3 16.7 Sep-12 2385 63 0 97.4 16.4 Month Non-Admitted Patients Total patients treated Greater than 18 weeks Unknown Clock Starts % Within 18 Wks 95th Centile Wait (wks) Oct-11 2150 34 0 98.4 15.4 Nov-11 2304 48 0 97.9 15.7 Dec-11 2001 52 0 97.4 16.0 Jan-12 2178 52 0 97.6 15.7 Feb-12 2038 62 0 97.0 17.0 Mar-12 2236 77 0 96.6 17.0 Apr-12 2117 82 0 96.1 17.4 May-12 2455 76 0 97.0 16.9 Oct-12 2753 68 0 97.5 16.7 Non-Admitted Performance Tables Code 100 101 110 120 130 140 150 170 300 320 330 400 410 430 502 **X01 % Within 18 Wks By Spec Gen Surg Urology T&O ENT Ophthalmology OMF Neurosurgery Cardiothoracic Surgery Gen Med Cardiology Dermatology Neurology Rheumatology Eld Care Gynae **Other TRUST TOTAL **Breakdown of X01 (Other) 107 Vascular Surgery 141 Restorative Dentistry 171 Paed Surg 191 Pain Management 303 Haematology 311 Genetics 314 ABI & Neurorehab 315 Palliative Medicine 321 Paediatric Cardiology 324 Anticoagulation 370 Med Onc 420 Paeds 421 Paed Neurology 800 Clin Onc Oct-11 99.0 80.0 97.1 97.4 100.0 98.4 100.0 N/A 97.2 100.0 100.0 98.5 99.2 96.6 98.5 97.8 98.4 Oct-11 100.0 N/A 100.0 94.7 100.0 100.0 100.0 Nov-11 97.9 75.0 98.0 96.7 96.8 97.1 100.0 100.0 98.8 99.2 99.5 96.8 98.8 97.8 98.5 97.5 97.9 Dec-11 99.4 100.0 97.4 99.3 94.6 96.9 100.0 Feb-12 97.1 100.0 97.0 97.8 90.6 99.3 94.8 99.0 99.5 92.4 96.5 98.1 98.4 96.6 97.4 Jan-12 97.3 100.0 97.3 96.3 96.2 98.4 100.0 100.0 98.7 99.3 97.8 96.3 99.2 100.0 97.4 95.9 97.6 Nov-11 100.0 100.0 100.0 92.2 100.0 100.0 100.0 Dec-11 94.1 100.0 100.0 93.9 100.0 100.0 100.0 Jan-12 100.0 100.0 100.0 90.9 100.0 100.0 100.0 Feb-12 92.3 100.0 N/A N/A 100.0 94.2 99.0 97.1 94.7 99.4 100.0 97.9 95.8 97.0 N/A 96.5 100.0 100.0 100.0 Mar-12 99.5 100.0 96.6 96.6 90.2 98.8 100.0 100.0 96.7 97.1 98.0 92.9 97.7 100.0 96.0 94.0 96.6 Apr-12 95.9 94.4 98.2 96.2 95.8 95.1 Jun-12 97.4 100.0 98.9 99.3 100.0 97.6 98.1 96.7 99.1 90.5 99.0 100.0 97.8 92.9 96.1 May-12 97.7 100.0 99.5 98.2 100.0 98.5 100.0 100.0 97.3 98.3 98.3 93.0 97.3 100.0 95.5 94.4 97.0 Mar-12 100.0 100.0 100.0 88.0 100.0 100.0 100.0 Apr-12 100.0 100.0 100.0 76.6 100.0 100.0 100.0 May-12 100.0 100.0 100.0 87.0 100.0 93.3 100.0 N/A N/A 100.0 97.1 100.0 98.8 95.9 98.3 100.0 97.2 95.2 97.5 Jul-12 96.1 100.0 99.3 99.5 100.0 99.4 100.0 100.0 97.6 96.9 99.5 98.2 98.3 100.0 97.1 97.4 98.1 Aug-12 98.4 100.0 100.0 98.3 100.0 97.8 100.0 100.0 99.4 98.1 99.5 96.0 97.4 96.7 96.4 99.1 98.3 Sep-12 97.8 97.3 95.5 97.8 96.8 97.7 100.0 100.0 96.1 98.5 99.1 95.0 97.9 100.0 99.5 95.7 97.4 Oct-12 97.3 100.0 99.2 96.6 99.1 97.0 N/A 100.0 96.0 97.7 99.6 97.1 97.3 97.5 98.2 96.9 97.5 Jun-12 100.0 100.0 100.0 85.7 100.0 100.0 100.0 Jul-12 100.0 100.0 100.0 94.7 100.0 100.0 100.0 Aug-12 100.0 100.0 100.0 98.2 100.0 100.0 100.0 Sep-12 100.0 100.0 100.0 96.5 100.0 100.0 100.0 Oct-12 100.0 100.0 100.0 92.9 100.0 100.0 100.0 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 87.5 100.0 100.0 97.9 75.0 100.0 100.0 100.0 100.0 97.6 100.0 96.8 88.2 100.0 100.0 95.8 100.0 100.0 90.0 100.0 96.3 95.7 90.0 100.0 89.5 96.0 100.0 95.0 80.0 100.0 88.9 100.0 100.0 93.9 50.0 100.0 93.1 100.0 100.0 95.1 100.0 100.0 87.0 100.0 96.0 95.8 100.0 100.0 85.7 100.0 100.0 95.7 100.0 100.0 84.0 100.0 100.0 97.9 100.0 100.0 95.8 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 92.0 100.0 98.5 93.3 100.0 100.0 95.8 100.0 100.0 PERFORMANCE REPORT October 2012 Diagnostic Access Times: Patients waiting in excess of 6 weeks The Risk: Endoscopy continues to see patients waiting past the six week target time, primarily due to the number of referrals the service receives compared to the capacity the service is able to provide. The number of patients on the surveillance waiting list continues to reduce however an influx of fast rack patients has impacted on available capacity this month. Current Position: The number of patients waiting 6 weeks and above at the end of October is 26 (36 at the end of September) as shown in the graph below. Of the total number of patients waiting, 91% are waiting less than 6 weeks. The total number of patients on the waiting list has decreased to 422 (449 at the end of September). The reduction in the number of patients waiting, despite referrals remaining high, is a result of additional activity run by the department. This has been achieved by additional weekend lists which need to be continued until sustained additional capacity is in place. In terms of the surveillance backlog, this continues to reduce as planned due to additional lists dedicated to surveillance patients and close monitoring. Currently, there are 7 surveillance patients who are breaching the 6 week target – 37 surveillance patients due to be seen in total. Endoscopy Breaches against the 6 week target 90 80 Number of Patients 70 60 50 40 30 Target 20 10 0 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Following discussions with the PCT, funding has been granted for additional lists. It is anticipated that this will support additional equipment to fully utilise the third endoscopy procedure room, allowing for maximum utilisation and increase capacity in the department. This is currently with the Purchasing department for finalisation. Following on from the JAG visit in September, the draft report has been received to be signed off. The report states various actions which need to be met by the department, mainly privacy and dignity and timeliness. Work has already begun on these. Action: The department will be running additional Saturday lists throughout November in order to keep up with demand. If increased capacity can be sustained in the long term, it is anticipated that this will ensure patients are seen within 6 weeks. Prepared by : Rebecca Gouveia Endoscopy Admissions Manager/Assistant Business Manager Surgical Division November 2012 PERFORMANCE REPORT October 2012 Bowel Cancer Screening Programme: Non-achievement of diagnostic screening target – 98.82% Target: 100% of patients are offered a diagnostic screening appointment within 14 days. 1. Summary 1.1 During October 2012, all patients who were fit for screening colonoscopy were offered a diagnostic test within 14 days. 1.2 One patient, due to a history of major abdominal trauma, was not fit for colonoscopy and was referred for a diagnostic CT colonography. 1.3 It was not possible to arrange a diagnostic CT colonography for this patient within 14 days. The first available date was 28 days after their SSP appointment. 2. Reasons for referral by the BCSP to CT colonography 2.1 Patients are referred for a diagnostic CT colonography for one of two reasons: • The screening colonoscopy could not be completed (e.g. due to looping bowel or pain) and a CT colonography is requested to complete the diagnostic test. • Following review at nurse clinic, a screening colonography is deemed not clinically suitable. 2.2 It is the patients who are deemed not clinically suitable for a colonography who have to be seen within 14 days to prevent a breach being reported. 3. Actions for November 2012 3.1 A review of all patients who have been referred directly for a diagnostic CT colonography (2012) as part of the BCSP is being undertaken to identify if any changes in practice need to take place to prevent further breaches. This review is being undertaken by the Programme Manager and Lead Nurse, in conjunction with the Clinical Director. Prepared by: Suzie Scaddan Bowel Cancer Screening Programme Manager 08.11.12 OPERATIONS SUMMARY OCTOBER 2012 st th (For the period of 1 September 2012 to 30 September 2012) This report summarises various operational aspects year to date and provides an update regarding the reconfiguration of beds. 1 ACTIVITY 1.1 The number of non elective admissions year to date is 1.6% more compared to the same period last year. 1.2 Attendances at the Emergency Department have increased negligibly by 0.03% year to date, although at times the Department is experiencing extremely high levels of attendances. There have also been a number of specialties which have seen larger than average increases in their emergency admissions as shown below; Specialty General Surgery Trauma and Orthopaedics ENT Paediatrics 2011/12 2012/13 % Increase 1365 1757 330 2423 1674 1959 406 2997 22.6% 11.5% 23.0% 23.7% 1.3 The number of Emergency admissions to the Trust has increased by 4.2% year to date, which also includes an 8.3% rise in admissions directly requested by General Practitioners and 4.7% increase from admissions directly from ED. 1.4 Elective activity has increased year to date, with 5.6% more elective admissions and 31% more day case admissions. 1.5 The number of Maternity admissions year to date has decreased by 11.9% compared to the same period last year. 1.6 The variance in Trust activity (YTD) is summarised below: Activity Year to Date Adult Emergency Admissions Adult Non Elective Admissions (Inc emergency & transfers excl maternity) Child Non Elective Admissions (Excl maternity) Maternity Admissions Emergency Dept Attendances Inpatient Electives (all ages) Day Cases (all ages) Year to date 12/13 15,284 11,906 Previous year to date 11/12 Variance 14,655 11,714 +4.2% + 1.6% 3,772 3,151 + 19.7% 5,717 30,920 2,031 13,866 6,486 30,835 1,992 10,560 - 11.9% + 0.03% + 5.6% + 31% 2 LENGTH OF STAY 2.1 Adult Non Elective average Length of Stay (LOS) for September 2012 has reduced from 5.68 bed days in September 2011 to 5.16 bed days in September 2012. This is an improvement of 9.2%. The graph below shows the average adult non elective LOS from April 10 to date LOS - Adult 8.00 LOS Adult 12/13 7.00 LOS Adult 11/12 6.00 LOS Adult 10/11 5.00 4.00 Apr 2.2 May June July Aug Sept Oct Nov Dec Jan Feb Mar The table below shows LOS by Directorate from April 2011 to date. The majority of areas have seen a reduction in LoS, however there are still a number of outlying services. The Medical statistics include the Emergency Assessment Unit. 2011 2012 Directorate Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Elderly Medicine 7.9 9.7 9.1 8.5 8.1 7.1 7.1 7.8 6.1 7.2 7.6 7.8 7.0 7.0 7.3 7.6 7.4 7.5 Gynaecology 1.9 1.8 1.8 1.8 1.7 1.5 1.8 2.0 1.5 1.6 1.9 1.9 1.6 1.9 1.9 1.8 1.7 1.6 Medical 2.1 2.6 2.7 2.1 2.4 2.3 2.4 2.4 2.9 2.9 3.2 2.8 3.2 2.7 2.7 2.9 3.1 2.8 Obstetrics and Well Babies 1.1 1.1 1.2 1.2 1.1 1.1 1.2 1.2 1.2 1.1 1.2 1.2 1.1 1.2 1.2 1.2 1.4 1.4 Oncology 5.5 6.3 6.7 6.4 7.0 7.0 5.6 6.6 6.2 5.8 5.6 5.6 7.0 7.4 6.0 7.0 7.4 4.2 Paediatric 1.9 2.2 2.1 2.1 2.1 2.0 1.4 1.7 1.7 1.7 1.9 1.8 2.4 1.8 2.0 2.0 2.0 2.1 Specialist Medical Services 23.3 9.3 18.0 6.6 17.8 9.4 15.0 10.3 8.6 16.7 14.2 16.8 19.1 19.2 9.3 14.1 9.6 9.7 Surgery 2.7 2.5 2.5 2.2 2.8 2.6 2.5 2.6 2.6 2.4 2.5 2.4 2.6 2.7 2.7 2.3 2.6 2.5 Trauma & Orthopaedics 7.0 6.0 6.9 6.0 5.8 5.6 6.4 6.5 6.4 7.0 6.1 6.3 6.6 5.5 5.9 6.1 6.1 6.2 2.3 The 4 Directorates showing the most variation in average LoS and have the highest recorded figures are Elderly Medicine, Oncology, Trauma & Orthopaedics and Specialist Medical Services. The graph below shows the variation experienced by the 4 Directorates. 25.0 20.0 15.0 Elderly Medicine Oncology 10.0 Specialist Medical Services Trauma & Orthopaedics 5.0 0.0 2.4 The percentage of time the Trust is in a Green/Amber bed state position is a clear indication of how pressurised the whole system is. The Hospital was in a red bed state for 63% of the time during September 2012, it was recorded as 43% the previous year. The graph below shows the Amber/Green bed state since April 2010. Monthly Comparison Bed State: Green & Amber Amalgamated 125% 100% 75% 50% 25% 0% Apr May June July Aug Sept Bed State 12/13 30% 29% 30% 32% 35% 37% Oct Nov Dec Jan Feb Mar Bed State 11/12 30% 19% 40% 84% 87% 57% 29% 77% 52% 48% 24% 48% Bed State 10/11 90% 97% 100% 100% 90% 90% 97% 73% 45% 48% 68% 52% 3 DELAYS 3.1 The percentage of Delayed Transfers of Care has significantly reduced this year compared to last, with decreases in the number of waits reported for Social Services and Community Hospitals and Intermediate Care. Continuing Healthcare and Community Hospitals represent the majority of all waits. 3.2 The table below shows the variance in bed delays lost due to formal delays as a comparison with the same period in 2011. The largest improvements are seen in Intermediate Care (-85%) and Social Service delays (-57%). Further work needs to be undertaken with our Housing and Continuing Healthcare colleagues. Bed Days Lost YTD 12/13 Previous YTD 11/12 Variance Overall Bed Days Lost 4059 5900 -31% Community Hospitals 1077 1765 -39% Social Services 487 1123 -57% Continuing Healthcare 753 662 +14% Housing 103 58 +77% Self Funding 597 805 -26% Intermediate Care 105 685 -85% 3.3 The graph below demonstrates the total number of bed days lost due to formal delays since April 2010. September 2012 and May 2012 had the lowest number of delays recorded since April 2010 at 3%. Total Bed Days Lost 1750 1500 1250 TOTAL Delays 12/13 1000 TOTAL Delays 11/12 750 TOTAL Delays 10/11 500 250 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar 4 CANCELLATIONS 4.1 All waiting list cancellations 4.1.1 Elective admissions cancelled have reduced compared to the same period last year with 24.3% cancellations recorded in September 2011 and 15.5% in September 2012. This continues to be the trend this financial year. 4.1.2 The graph below shows the % of elective admissions cancelled as a % of all elective admissions Elective Admissions Cancelled as % of All Elective Admissions 40% 30% % Elective Cancellations 12/13 20% % Elective Cancellations 11/12 % Elective Cancellations 09/10 10% Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar 4.2 Waiting list cancellations within 1 day of the TCI (to come in) date 4.2.1 Elective admissions cancelled within a day of their TCI date (a subset of the total in the previous paragraph) have reduced over the financial year but is still in higher than the same period last year. When compared to the same period last year with 4.0% cancellations recorded in September 2011 and 3.2% in September 2012. 4.2.2 The graph below shows the % of elective admissions cancelled within a day of their TCI date as a % of all elective admissions. Elective Admissions Cancelled within 1 day of TCI date as % of All Elective Admissions 6% % Elective cancellations <= 1 day 12/13 5% 4% % Elective cancellations <= 1 day 11/12 3% 2% % Elective cancellations <= 1 day 10/11 1% 0% Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar 4.3 Cancelled operations 4.3.1 Operations cancelled either on the day of admission or the planned day of operating fluctuates month by month but on a cumulative basis has increased slightly when compared with last year and. The year to date position for September 2012 was 133 cancellations, compared with 130 for September 2011, and 128 for September 2010. 4.3.2 The graph below shows the cumulative position for cancelled operations on the day of admission or operation. Monthly cumulative position for cancelled operations 300 250 200 cancelled ops 2012/13 150 cancelled ops 2011/12 cancelled ops 2010/11 100 50 0 Apr 4.3.3 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar The graph below shows monthly numbers of cancelled operations on the day of admission or operation, split by cause. Cancelled operations per month split by cause 40 35 30 25 other no bed 20 staff sickness 15 no theatre time list cancelled 10 5 Sep-12 Jul-12 Aug-12 Jun-12 Apr-12 May-12 Mar-12 Jan-12 Feb-12 Dec-11 Oct-11 Nov-11 Sep-11 Jul-11 Aug-11 Jun-11 Apr-11 May-11 Mar-11 Jan-11 Feb-11 Dec-10 Oct-10 Nov-10 Sep-10 Jul-10 Aug-10 Jun-10 Apr-10 May-10 0 5 READMISSIONS 5.1 The readmission rate is calculated by dividing the number of discharges that were followed by an emergency readmission within 30 days by total number of discharges (excluding deaths). 5.2 The table below shows the readmission rates by specialty from April 2012 to date. Month of Dis c har ge of O r iginal Admis s ion Dis c har ging s pec ialty of or iginal admis s ion Apr May Jun Jul Aug Sep ACCIDENT AND EMERGENCY 10.4% 2.6% 5.6% 11.7% 8.3% 6.8% ACUTE INTERNAL MEDICINE 13.8% 9.6% 9.1% 8.2% 8.4% 7.1% CARDIOLOGY 6.8% 6.1% 7.5% 14.7% 7.7% 13.1% CLINICAL ONCOLOGY 0.3% 0.3% 0.0% 1.4% 0.3% 1.5% DERMATOLOGY 1.0% 0.6% 0.5% 0.0% 0.9% 0.9% EAR, NOSE AND THROAT 4.7% 6.5% 3.0% 3.5% 1.2% 1.8% GASTROENTEROLOGY 0.0% 2.1% 1.3% 3.0% 1.5% 2.1% GENERAL MEDICINE 8.2% 8.7% 9.9% 9.9% 9.9% 7.1% GENERAL SURGERY 7.3% 6.5% 5.1% 7.4% 5.0% 7.9% 15.1% GERIATRIC MEDICINE 14.2% 17.0% 15.5% 14.7% 13.8% GYNAECOLOGY 5.7% 5.2% 4.3% 9.0% 4.1% 3.3% HAEMATOLOGY (CLINICAL) 2.0% 0.0% 0.9% 0.8% 0.5% 1.3% Max Fax & Oral Surgery 5.4% 0.6% 0.6% 0.5% 0.6% 3.4% MEDICAL ONCOLOGY 0.0% 0.0% 0.5% 0.0% 0.0% 0.0% NEUROLOGY 0.0% 3.2% 2.2% 4.0% 0.0% 0.0% OBSTETRICS 0.0% 0.1% 0.0% 0.0% 0.0% 0.0% PAEDIATRICS 5.2% 5.9% 5.4% 3.2% 3.4% 3.9% PAIN MANAGEMENT 4.5% 0.0% 5.4% 0.0% 7.1% 3.3% REHABILITATION 0.0% 0.0% 0.0% 0.0% 12.5% 0.0% RHEUMATOLOGY 0.0% 3.5% 2.0% 0.8% 1.6% 2.3% TRAUMA AND ORTHOPAEDICS 6.1% 3.4% 5.9% 5.3% 6.5% 4.3% Grand Total 4.8% 4.5% 4.3% 4.6% 4.1% 4.1% Oct Nov Dec Jan Feb Mar 5.3 There are significant readmission rates in September (>10%) within Cardiology (13.1%) and Geriatric Medicine (15.1%). 6 BED RECONFIGURATION 6.1 There are a number of bed reconfigurations planned from January 2013 which have been developed to support the Trust cost improvement programme, with a net loss of 15 beds within DME. The impact on patient quality and hospital flow has been carefully considered and a number of initiatives introduced to support the changes. 6.2 Cranborne Ward will close on 2nd January 2013 resulting in the loss of 15 General Medical bed. There will be a transfer of DME beds on Avonbourne Ward to General Medicine which will balance the bed stock for the Directorate. 6.3 Lychett Ward (Furzey) will open in January 2013 as a DME ward. There will be a loss of 15 beds across DME due to a clinical improvement plan to introduce more cubicles to improve infection control within the Directorate and the loss of beds on Avonbourne. 6.4 A number of actions are in place to improve Trust resilience due to the bed reductions. They are as follows; • • • • • An integrated discharge facility (Discharge Lounge) will allow for proactive discharge with an additional 5 cubicles and a trained nurse. Stroke ESD team in place Nurse Practitioner for Older People present in Emergency Department to reduce admissions. Additional community service (Intermediate Care) at weekends to facilitate discharge Wards will where possible absorb escalation areas/beds into their bed compliment with appropriate staffing, improving the flow of patients • • • • • MIU will increase the range of tests undertaken on the unit to support early discharge and reduce admissions. Ansty Ward will look to increase capacity over winter months to support the surgical admissions pathway. Review of top 10 frequent flyers for multiple admissions Increase in the number of board rounds on General Medical wards, resulting in speedier access to senior decision making Introduction of Red Cross Assisted Discharge service for DME patients (in place) 7 SUMMARY 7.1 Despite a 4.2% increase in non elective admissions to the Trust, the length of stay is 9.2% lower than the previous year. There has been a drive across all Directorates to manage patient flow with a reduced bed capacity which has been supported by a number of innovative initiatives across teams. The next challenge will present itself in January 2013 as the bed stock is reduced by a further 15 DME beds. 7.2 Discharge delays continue to decrease however the focus must remain on working with partner agencies to provide robust services out of hours and to improve internal processes to reduce avoidable ‘informal’ delays. 7.3 The bed state position year to date has significantly declined compared to previous years with the Trust remaining in a Red bed state for 63% of the time in September 2012 compared to 43% in September 2011. This is a consistent trend with performance ranging between 63% and 71% red state recorded throughout the financial year. This will become unsustainable during winter pressures and will be the main focus of operational and Directorate teams over coming months. Prepared by Sophie Jordan Operations and Performance Manager November 2012 PERFORMANCE EXCEPTION REPORT Department: Delayed Transfers of Care The Risk: Delayed Transfers of Care have an adverse effect on patient length of stay and hospital capacity Current Position: Using DH reporting methodology, the percentage of patients formally delayed on the last Thursday of October was 3.75%, 0.25% over the Trust target. This is an increase of 0.75% on the September figure. The total number of bed days remains low in month with 590 days compared to August (798) and September (533). The method for measuring delayed transfers of care has been altered to replicate methods undertaken by local acute trusts and to follow DH guidance to ensure consistency. The majority of delays during October were as follows: Community hospitals (41%) CHC assessment process (13%) Social service delays (9%) Self-funding patients (6%) Angio waits (29%) Actions: The following actions continue to be progressed to achieve a continuous reduction in bed days: • • • • • • • • • • • • • The implementation of an integrated approach between the hospital, social services, CHC staff, community services, including community hospitals has commenced, confirmation of additional accommodation to complete full integration of teams has been agreed. The aim is to reduce administrative duplication and improve communication in support of discharge. Dorset County Council are reviewing funding a Social Worker to support the RACE Unit for a further year, this has a major impact on discharging patients within 48hours and keeping packages of care open in order to reduce future delays in the patient pathway. Teams from Local Authorities (LA) and Poole Hospital, are liaising to enable better IT access for both organisations Daily review of delays whiteboard between all partner services. Twice weekly discharge surgeries are taking place with the aim of reviewing complex cases and new referrals leading to improved communication and a reduction in unnecessary delays Successful recruitment for a senior nurse to a 6 month trial of a dedicated CHC discharge support worker, working in partnership with the PCT in order to give greater focus on reducing unnecessary delays in gathering evidence and completion of the assessment process started on 15th October 2012. The screening service pilot led by the PCT, continues to be reviewed on a monthly basis. Lead the development of a pan Dorset set of reporting principles to ensure consistent and transparent application of DH guidance. NHS Bournemouth & Poole and Dorset have allocated a member of staff to each acute hospital as a link nurse to support the DST process and improve communication. Added to an improved Funding out of Hospital funding agreement, looks set to reduce delays for patients referred to CHC for consideration. Trust discharge staff have adapted their role, to improve support given to ward staff, visiting each ward most days. Discharge, Therapy, Nursing and IT development staff are using EPR to refer to single point of access to improve referral and communication, plan in place to roll out across Trust. Help & Care or social services are also utilising this system via EPR on a selection of wards, replacing several forms including social services section 2s and 5s. Weekly validation communication with Dorset Community Hospital lead, to review all patients on formal delay list awaiting a community bed. Transfers of Care (ToC) Update October 2012 The percentage of patients formally delayed on the last Thursday of October (DH reporting methodology) was 3.75%, 0.25% over the Trust target. Delays during October were due to: Community Hospitals (41%), the CHC assessment process (13%), Social Services (9%), Self-Funding patients (6%), and transfer of patients for Angiography/Angioplasty at RBCHFT (29%). Actions continue to be progressed on a continuous basis to improve delays overall and tackle the main causes of delays Total Bed Days Lost 1750 1500 1250 TOTAL Delays 12/13 1000 TOTAL Delays 11/12 750 TOTAL Delays 10/11 500 250 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar The total number of bed days lost during October (590) an increase compared to September (533), however this continues to remain low compared to recent years. Number of Bed Days lost due to awaiting Self-Funding (data started Aug-09) 350 300 250 Self-Funding 12/13 Self-Funding 11/12 Self-Funding 10/11 200 150 100 50 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar The number of bed days lost due to self funding patients decreased in October to 36 bed days compared to 74 in August and 59 in September. This appears to show a downward trend since July 2012. The new screening service implemented from June has assisted in the early identification of self funding patients and consequently a further reduction in delays, this will be closely monitored on a monthly basis but appears to have some impact on the improvement. Number of Bed Days lost due to awaiting transfer to Community Hospitals 1250 1000 Community Hospitals 12/13 Community Hospitals 11/12 750 500 250 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar The number of patients delayed waiting for a community hospital has increased to an average of 8 patients per day, compared to 5 last month. The Discharge Team are undertaking weekly validation of delays with the Community Hospital Matron, however demand for community hospital beds has been high across all 3 local acute trusts. Community beds delays in October (244 bed days) have been the highest so far this year. Number of Bed Days lost due to awaiting CHC (data started Aug-09) 500 400 CHC: Bed Days 12/13 CHC: Bed Days 11/12 300 200 100 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar The number of patients delayed as a result of the Continuing Health Care (CHC) assessment process has increased in month to an average of 3 per day, compared to an average of 2 per day during September. Joint work with the PCT continues and a trial of a dedicated CHC discharge support worker from mid October will help to support ward staff and reduce delays as they gather evidence and assist in completing the assessment paperwork. Number of Bed Days lost due to awaiting Intermediate Care (data started Mar11) 350 300 250 Intermediat e Care 12/13 200 Intermediat e Care 11/12 150 100 Intermediat e Care 10/11 50 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Delays for intermediate care have reduced significantly, with 1 bed day lost in October. Number of Bed Days lost due to awaiting Social Services (Section5) 400 300 Social Services 12/13 200 Social Services 11/12 100 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar On average 2 patients were delayed each day during October due to social services, which remains consistent with September figures. Key focus areas are: increased social services support within the RACE unit and the further support from Bournemouth social services. Poole local authority is planning to commence a weekend service in the near future further supporting weekend discharge and also 7 day discharge planning. Number of Bed Days lost due to awaiting Angio 300 200 Angio Waits: Bed Days 12/13 Angio Waits: Bed Days 11/12 100 0 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Delays for patients awaiting transfer for cardiac intervention/imaging (Angio wait) has decreased in month to 29% of all delays being attributable to this issue, a reduction of 6% compared to September. There are a number of internal issues that impact on a timely discharge of this patient cohort and the Operational team will be focusing on reducing this delay. The delay in transferring patients once medically fit continues to be raised at executive level with the Royal Bournemouth Hospital. Sophie Jordan Operations and Performance Manager PERFORMANCE REPORT October 2012 Trauma Directorate: Waiting Times for Surgery: Fractured Neck of Femur within 36 hours of admission (Best Practice Tariff Criteria) Fractured Neck of Femur within 36 hours of being clinically appropriate for surgery (PCT) Trauma Patients within 48 hours of being deemed fit for surgery The Risk: Fractured neck of femur patients 99% within 36 hours of being clinically appropriate for surgery (PCT target: 85% by September 2012 and 95% by March 2013) 93% within 36 hours of admission (Best Practice Tariff: Internal target 90%) All trauma patients 97% within 48 hours of being fit for surgery (target 95%) Further improvement against fractured neck of femur targets for October 2012. The risk remains in consistently achieving and improving compliance, balanced against maintaining the Trauma target of 95%, particularly at times of peak demand. Current Position: The graph below shows that the overall number of trauma admissions was slightly higher than in September at 427. This month included 67 patients admitted with a fractured neck of femur, which as can be seen on the graph below, was the lowest number since November 2011. Unusually, the preceding nine months had not seen the usual levels of variation in fractured neck of femur numbers experienced in previous years. Combined with the continued drive from all staff within the MDT to manage individual patients through their pathway to avoid breaching access times, the lower number of admissions contributed to the Directorate achieving its best performance against the neck of femur and trauma targets to date. Of the fractured neck of femur patients, 5 patients did not meet the NHFD target of theatre within 36 hours; 4 patients because they were unfit upon admission and one who required a surgeon with specific experience due to their associated co-morbidities. There were 9 general trauma patients who failed the 48 hour (from fit) target; 4 that awaited a specialist surgeon and five due to lack of capacity, in 3 cases due to prioritisation of fractured neck of femur patients. The challenge remains maintaining these performance levels going forward and a considerable amount of work is required on individual days, particularly on the part of main theatres and the TAC Team, to ensure that the patients do not breach. The fluctuation in daily admission numbers, the complexity of the case mix and the management of competing access targets in theatres across all the specialties, which include cancer waiting times, RTT times and CEPOD access times, all present significant challenges on a daily basis. The accompanying graphs show the treatment times for fractured neck of femur and general trauma patients after they have breached their respective targets and it can be seen that the waiting times for surgery for those as patients that breached their access times were considerably lower in October. % operated within 36hrs of admission % Patients Operated on within 36hrs Number of NOF's admitted 500 100% 450 400 80% 350 300 60% 250 200 40% 150 20% 95 92 67 74 79 72 77 79 77 81 73 73 67 0% 100 50 0 Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct11 11 11 12 12 12 12 12 12 12 12 12 12 % Patients Operated on within 36hrs Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 55% 77% 72% 77% 78% 73% 69% 80% 68% 52% 58% 75% 93% Number of NOF's admitted 95 67 92 74 79 72 77 79 77 81 73 73 67 Number of Trauma Admissions 435 384 381 364 360 358 386 436 439 450 488 407 427 Patients not fit pre-op & needed optimising Other trauma cases taking priority/ran out of time Insufficient theatre capacity Awaited specialist surgeon for THR Patient refused surgery on the day 4 0 0 1 0 Actions: The improvement programme continues and in October the focus remained on: - Breach avoidance/breach management plans for individual patients in conjunction with reporting and understanding by relevant staff of the position on a daily basis. - Highlighting crucial patients and their breach times on the main theatre white board so that all staff can see which patients require prioritisation, in particular where lists have to be reorganised. - Prioritising of fractured neck of femur patients over other trauma (where appropriate) and on-going involvement of consultant surgeons in the process and planning of lists, particularly at weekends. - Clinical Director led training programme to increase the number of middle grade surgeons able to operate on fractured neck of femur patients requiring a total hip replacement, with one additional surgeon signed off so far. - Completion of an in depth demand and capacity study, which will be reported on shortly... - Implementation of a second all day Sunday theatre list from 14 October 2012, which has been fully utilised on all but the first week and has contributed to a much improved situation at the start of each week. - Full implementation and consolidation of the Trauma business case, phased in between April and September. This has included not only the additional theatre capacity, but also DME weekend ward rounds, an additional therapist and the introduction of the Older Persons’ Mental Health Nurse, which have all contributed to an improved performance over against all the Best Practice Tariff criteria over the last two months. Prepared by Yvonne Hunter Directorate Manager 9 November 2012 NOFs - Treatment Times for Patients Breaching the 36 hour Target: October 2011 - October 2012 36-48 hours 2-3 days 3-4 days > 4 days 30 Number of patients Breaching 25 20 15 10 5 0 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Month Non NOFs: Treament times for Patients Breaching the 48 Hour Target: October 2011 - October 2012 2-3 days 3-4 days 4-5 days >5 days 14 12 Number of Patients Breached 10 8 6 4 2 0 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 Month May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 PERFORMANCE REPORT October 2012 Stroke : Target: ≥80% of patients should spend > 90% of their LOS on the Stroke Unit The Risk: The Trust met this target in Quarter 1 & Quarter 2 2012/13. Current Position: In October 76% (39) of patients spent > 90% of their LOS on the Stroke Unit (target ≥ 80%). The following table indicates the number of stroke patients admitted and the % that achieved the target in the previous 3 months. No. of stroke pts admitted % of patients should spend > 90% of their LOS on the Stroke Unit Jul 56 Aug 50 Sep 43 Oct 51 89 80 91 76 OCTOBER 39 (76%) patients had >90% of their stay on the Stroke Unit out of 43 patients discharged during October. The Trust had achieved this target in Quarters 1& 2 2012/13. This is a disappointing outcome after achieving this target for the last 2 quarters. The movement of beds to support the reconfiguration plan impacted badly on the ability for ASU to manage a higher than usual number of Stroke presentations and admissions over the weekend the initial moves took place. The remainder of the month was managed very well, with reduced bed numbers on the new ASU location; however this has resulted in us breaching this target for the month of October despite thorough validation of the data. Direct access also dropped to 75% after a positive rise to 86% in October (66% in August). There remains a variety of clinical reasons necessitating initial care elsewhere or inpatient Strokes with delayed diagnosis which will continue to effect figures though these are reviewed upon validation and managed onwards and appropriately actioned. CT scan access <24 hours was 78%, this figure being reduced due to delay in scan requests, this will be addressed by the clinical teams. TIA ‘First Professional to Clinic’ remained below target at 43% (target 60%), this has been discussed at PCT level and recording of this target will be reviewed once the Capture TIA IT system is in place from December. The TIA referral pathway is being currently reviewed and will be put into place to support the reporting of data from the new system. Delays in clinical appointments are due to a number of factors, these mainly being a delay in the referral from being sent from the GP after initial contact, this then causes delay in appointing into TIA clinics held daily at PHT. We did not close the Stroke pathway or re-designated any other area as Stroke in the month of October. There have been some delays in discharge due to care packages being arranged/agreed, these issues are picked up weekly with ward discharge coordinators meetings with our secondary and council colleagues. Actions: th 1. Work on the DME bed reconfiguration plan is underway with initial staff consultation commenced on August 13 . Building work has now commenced and the first of the ward moves have taken place. 2. Ward processes continually reviewed. Staffing and skill mix managed appropriately during times of sickness and during high levels of leave during the month of July and August. Outcomes of the consultation and decisions for staffing of the new ward based on the old Furzey footprint will be made available soon. 3. Winter plans are being drawn up and discussed at a ward and management level and will feed into capacity meetings. Prepared by : Barry Duell Directorate Manager Medical Division (DME, Diabetes, Rheumatology, Neurology & Gastroenterology) November 2012 PERFORMANCE REPORT October 2012 Month 7 Contract Performance Position Statement Elective Elective activity was at planned levels in October and so reduces year to date over performance to 3% in activity and 2.4% in income terms. Elective over-performance is seen particularly in Chapters C (Mouth, Head, Neck and Ears), Chapter D (Respiratory), E (Cardiology), F (Digestive) and G (Hepato-billiary & Pancreatic). A contract variation for additional colonoscopy activity is not yet reflected in these figures and will reduce, but not eliminate, the over performance under Chapter F. At specialty level, over performance is seen under General Surgery in particular, but also Pain Management, Cardiology, Neurology and Oncology. Non-elective Total non-elective activity remains 2.5% below target as over performance in emergency spells is outweighed by the substantial reduction in short say antenatal admissions. Emergency activity remains cumulatively 1.2% above plan but with a 3.9% shortfall against planned income arising from the reduction in excess bed days. The Trust is exceeding emergency spell targets in General Surgery, T&O, General and Elderly Medicine and Paediatrics but of these, only General Surgery and Trauma and &Orthopaedics show a positive income variance. Over-performance in these specialties largely compensates for fewer admissions being recorded under A&E since the closure of CDU. Obstetrics Volumes of activity in Obstetrics have been substantially below contract all year, regardless of new systems, with major reductions in the number of recorded short stay admissions at Poole for investigation/observation. Conversely, income has increased as the additional clinical data recorded within the new Medway system enables ‘augmented’ births to be identified and more fully reflected within our casemix. Outpatients First outpatients continue to exceed the year to date activity target now by 8.5 % above contract targets, income by 9.8%. Both percentages exceed those quoted for the year to date position last month. Outpatient follow-ups remain under contract by 1.9% for activity and 1.3% in terms of value, this is unchanged since lasts month. 1st to follow up ratios should not be cause for concern by commissioners in next year’s contract negotiations. A&E A&E attendances were relatively high in October and are now 3.2% above the year to date target. This is generating 7% more income which is believed to be due to improvements in recording of clinical data which drives up the acuity of our HRG-based casemix. The performance against contract for both activity and income is summarised in the following table. Prepared by Paul Stebbings Head of Information November 2012 Poole Hospital NHS Foundation Trust Contract Performance 2012/13 All Contracted PCTs Summary : 2012/13 year to date (month 7) Year to Date 2012/13 Contract activity £ Contract activity Over/Under Performance @ full tariff diff % diff activity £ activity £ Actual £ activity £ Marginal tariff YTD/Year end est £ £ Elective Inpatients Day Case 24,908 3,818 21,090 £23,479,335 £8,356,892 £15,122,443 14,646 2,245 12,401 £13,805,849 £4,913,852 £8,891,996 15,083 2,267 12,816 £14,136,580 £4,938,556 £9,198,024 437 22 415 £330,731 £24,704 £306,028 3.0% 1.0% 3.3% 2.4% 0.5% 3.4% £165,366 £12,352 £153,014 £281,234 £21,006 £260,227 Non Elective Emergency Other 41,375 28,145 13,230 £60,942,274 £48,365,841 £12,576,433 24,258 16,502 7,757 £35,730,539 £28,356,959 £7,373,580 23,659 16,701 6,958 £35,015,667 £27,251,204 £7,764,463 - 599 199 799 -£714,872 -£1,105,755 £390,883 -2.5% 1.2% -10.3% -2.0% -3.9% 5.3% -£915,641 -£1,111,083 £195,442 -£1,561,725 -£1,895,071 £333,347 Outpatients First Followup Procedures 173,102 56,070 101,676 15,356 £21,073,988 £9,647,971 £9,353,764 £2,072,253 101,784 32,969 59,785 9,029 £12,391,505 £5,673,007 £5,500,013 £1,218,485 103,802 35,776 58,649 9,377 £12,944,681 £6,231,379 £5,426,130 £1,287,172 2,018 2,807 1,136 348 £553,176 £558,372 -£73,883 £68,687 2.0% 8.5% -1.9% 3.9% 4.5% 9.8% -1.3% 5.6% £276,588 £279,186 -£36,941 £34,344 £470,388 £474,806 -£62,825 £58,408 55,558 £4,699,596 32,574 £2,755,380 33,605 £2,947,639 1,031 £192,259 3.2% 7.0% £96,130 £163,960 -5.0% -£8,298 -£14,154 A&E Attds Direct Access £562,669 £329,894 £313,297 -£16,596 Readmissions -£2,229,432 -£1,300,502 -£1,300,502 £0 Best Practice £1,457,175 £850,019 £850,019 £0 £107,509 £62,714 £53,384 -£9,330 -£4,665 -£7,997 £7,331,553 £4,276,739 £4,357,350 £80,611 £40,305 £69,095 £117,424,667 £68,902,135 £69,318,115 £415,980 -£350,216 -£599,199 £36,060,871 £21,035,508 £21,035,508 £0 -£40,232 -£68,968 -£390,447 -£668,167 Other Activity MFF @6.66% Cost per Case Contract Sub Total Non-PbR CQUIN Spec services Contract Total @2.5% £4,010,235 £2,339,304 £2,258,841 -£80,463 £11,984,834 £6,991,153 £6,991,153 £0 £169,480,607 £99,268,100 £99,603,617 £335,516 1% 0.3%