NEWS FLASH

Transcription

NEWS FLASH
July / August 2016
NEWS FLASH
JFC
HQ
Brunssum,
Building
H-106,
Extension
Project
PROGRESS
With this sixth newsletter we would
like to inform you on building
progress. Working closely together
with the JFCBS Base Support Group
(BSG) we aim to keep you apprised
of developments.
building process whereby some parts
are already integrated in the concrete
floors, and cable trays are installed to
the ground floor ceiling. See picture
below for the mounted cable trays.
In
the
stairwells,
we
installed
prefabricated
concrete
stairs
and
platforms. This allows us to reach the
Current Situation ‘Extend H-106’
Construction work is progressing in
accordance with the schedule. Over
recent weeks we have mounted the
prefabricated
concrete
walls
and
columns for the middle and top floors,
placed the hollow core slabs and poured
a concrete layer on both floors.
Furthermore, we have installed the
parts for the steel structure.
upper levels more easily.
Further, essential building installation
elements are already integrated in the
1
26 prefabricated concrete walls from
9 to 19 tons;
• 76 prefabricated columns with a
weight of 2.3 tons each;
• 52 steel beams with a weight of 4.5
tons each.
All of this has been achieved using a 50
ton crane, a 70 ton crane, a 42 meter
mobile tower crane, and a 400 ton crane
for assembly works.
•
Now, shortly before our summer
holiday, a part of the roof deck will be
applied. After our summer break, the
rest of the steel structure and roof deck
will be installed. This means that on
September 9th, the rough structure will
be completed.
Number of freights:
In addition, we have already welcomed
many trucks, for example:
• 24 loads of hollow core slabs;
• 16 loads of prefab deliveries;
• 32 concrete mixers (truck = 8 m³
concrete).
From August 30th we start to build up
the scaffolding around the building and
on September 12th we start with the
closing of the facades.
Project facts middle & top floors
The following statistics are associated
with the project:
Current Situation ‘H-106 A’
In building section A, the new masonry
walls are close to completion. In the
former
entrance
area,
temporary
arrangements (in order to protect
against weather influences) have been
applied.
2
Last but not least
From Tue 30th Aug, the ring road next to
the building site (Limburgstraat) will be
rearranged. There will be a temporary
road bypass indicated by signs. Also, the
sewer system will be inserted and
connected in this period.
This is executed because the existing
steel structure and the roof, including
roofing, will be demolished. See the
picture below for these temporary
arrangements in the former entrance
area.
After the holidays, a new steel structure
will be installed to connect the existing
building with the new walkways to the
new Wing – Wing J.
Also after the holidays we will start with
the preparations for the walkways and
the construction works for the new
guard post (Post 18) in the inner patio
of H106 I.
Holiday closure “bouwvak”
Due to the annual construction-industry
holiday, our company is closed from
Friday, August 5th to Monday the 29th
of August. In this period no construction
work will take place. In case of possible
calamities, the staff from “LAUDY
Bouwservice” department is ready to
assist you. During this period, our
employees can be reached by phone on:
046-4516933.
Contact
For any inquiry, or when you encounter
any inconvenience from the construction
activities, you can contact Section Head
BSG ISS IMS (Mr. Andries Bosma, 045
526 2431).