Issue 19, April 2015
Transcription
Issue 19, April 2015
APRIL 2015 issue 19 TRIVANTAGE times INSIDE THIS ISSUE Editors’ Welcome Group Managing Director What’s Happening? New Staff Community Spotlight On Recipe Thank You Letter Competition Winners OH & S Staff Achievements Announcements Christmas Celebrations Apprentices Movie Review EDITORS’ WELCOME Hi Everyone! Welcome to the 19th Trivantage Times edition, it’s hard to believe we are on to number 19 already! We hope you all had a great Christmas with loved ones and managed to recharge the batteries for 2015. The New Year has commenced and by the looks of the What’s Happening articles, each branch is off to a busy start. We welcome all our new employees and in particular our new 1st year Apprentices. We also announce the winners of our Sand Castle competition, some snap shots from our Christmas celebrations and include a Thank You letter from one of our happy customers. We hope you enjoy reading this edition! Jackie Passeri & Gail Bowers MESSAGE FROM THE CEO As we move towards the end of the financial year period we reflect on the year that was. The National electrical manufacturing, contracting and services markets remain highly competitive with companies continually looking to innovate to gain a competitive advantage. Growth has become secondary to ensuring the effective delivery of service and products to our current customers to allow the delivery of a solid return to our shareholders. In December 2014 the decision was made to restructure the Trivantage Group business into four (4) new business divisions Electrical Services, Building Technologies, Manufacturing and Infrastructure. This decision was made by the Executive Management team and the Board of Directors to ensure we enable management to engage with an Executive team of key decision makers that are enabled to promptly deliver high value outcomes in line with their divisional strategic plans to both clientele and other key stakeholders within the newly restructured business. In the last three (3) months the Trivantage Group have also implemented a Manufacturing Consolidation Strategy that has not only improved efficiencies within the Victorian and Brisbane manufacturing facilities but delivered significant costs savings back into the business. 1 1 2-9 10 10 10-13 11 11 12 12 12 13 14-15 16 16 We are very proud of our dedicated management team’s determination and continued efforts. They have demonstrated a high level of commitment to the transition and restructuring that has taken place over the past year and the continual review and streamlining of our business activities in order to achieve best practice. So far in 2015 we are seeing growth in all four of our newly restructured divisions. The challenge will be to ensure we enact the new businesses divisional strategies which will allow us to maintain shareholders returns while making sure we right size the business to control our cost base. Part of these strategic plans will be to ensure we have the operational processes, procedure’s and people in place to deliver the work in hand and the sales pipeline in future. We remain committed to our people, our safety, our customers, our environment and our community. Our strong culture leads us to these basic principles and is reinforced in our corporate mission statement and the adoption of our vision and values. Both Russell Stanley and Stewart Joyce, along with the rest of the Board of Directors of the Trivantage Group would like to take this opportunity to again thank all our dedicated and skilled staff for their efforts over the financial year period. Stewart Joyce & Russell Stanley Chief Executive Officers WHAT’S HAPPENING? Eagle Farm Pump Station SJ Electric Qld was recently awarded a contract to upgrade the Control System at QUU’s Eagle Farm Pump Station in Brisbane. Queensland Urban Utilities (QUU) is responsible for supplying drinking water, recycled water and sewerage services to a population of more than 1.4 million people in South East Queensland. The Eagle Farm Pump Station is a critical asset in the Brisbane Sewage network servicing the main sewer catchment constituting the majority of the Brisbane City Council. It is the city’s largest sewerage pump station, having a design capacity of 8,000L/s (That will fill the average domestic swimming pool in approximately 6 seconds!) delivering effluent approximately 9.6km to Brisbane’s largest sewerage treatment facility, Luggage Point Waste Water Treatment Plant. The existing GE Fanuc PLC Control System was at the end of its life and was identified as being in need of replacement. The control system was quite extensive and consisted of 7 PLCs and 14 Remote IO racks which controlled the five sewage pumps and the common ancillary equipment. [2] The project commenced in May last year with the extensive site investigations and planning of the individual stages of the project. Each stage of the control system changeover had to be meticulously planned as it was imperative that the Pump Station remained functional to maintain the continual operation of the QUU sewage network. The project required conversion of the existing GE Fanuc PLCs to the Siemens S7 PLC’s together with development of a new SCADA system using Schneider Citect SCADA. The developed PLC & SCADA programs went through several levels of exhaustive testing offsite on a purpose built test bench made to replicate the entire control system that was to be implemented. The testing regime had to be approved and witnessed by the Client before the new PLC & SCADA control system could be rolled out onsite. The old control system hardware then had to be removed and the new Siemens system installed, tested and commissioned while the pump station remained operational. The project is due for completion in June of this year .The changeover of the remaining three pumps and common equipment is still yet to be completed. The project has had its challenges with determining strategies to keep the site operational while carrying out the control system changeover, the Client requiring changes to the project schedule to T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 accommodate other projects on the Eagle Farm site and wet weather events. Our team on site consisting of Andy Walmsley (Site Supervisor), Alex Curley & James Ward continue to achieve great results by ensuring an operational pump station while achieving a high level of workmanship through all phases of planning, installation and testing of the new control system hardware. A few Eagle Farm Pump station facts: • Total Pump Station control is provided by a Pair of Siemens S7- 400 PLCs configured in Primary/ Standby arrangement. • Each of the five sewage pumps has a dedicated PLC for control & monitoring. • The control system is connected to over one thousand two hundred control or monitoring points. • The Eagle Farm Pump Station actually comprises of two individual pump systems to provide redundancy. Pumping System 1 has three 2000Kw pumps and the Second pumping system has two 1800kw pumps. • The pump motors operate on 6600 Volts. John Logan - Control Systems Supervisor SJ Electric QLD Select Harvets, Carina West Processing Facility HV Conversion Trivantage Power has been contracted by Select Harvests to design and construct 22kV grid connection upgrades for the Select Harvests Carina West Processing Facility located in Wemen, Victoria that will convert the LV metered supply to HV metering and additionally accommodate the connection of a 2.8MW generator that is to be installed in 2016. This project is the first part of the H2E (Hull to Energy) project for Select Harvests that will convert the Hull of Almonds grown locally to Energy. This is an exciting project that requires Trivantage Power to work with the Client, Network Service Provider, Metering Provider, Generator supplier and Regional Council to develop all the connection works and HV conversion across six different client sites. There are two sites located on the Murray River adjacent to pumping stations, three dam pump sites located within the Almond orchard itself and one at the processing facility itself. Switchboard, protection and control systems, 2.5km of 22kV underground cable and five 22kV kiosk substations. The HV conversion of the remainder of the sites is scheduled for end of March 2015. Michael Irlam Project Manager The project involves the installation of a 22kV network connecting the dam pumping stations and processing facility to enable the generator to supply power to all the pumps within the network and also to export excess power to the grid when required. The system is also designed to work in ‘island’ mode when the grid is not available. Trivantage Power has successfully commissioned the first site of the projects that required the design, supply and install of a 22kV switchroom complete with 22kV T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 [3] WHAT’S HAPPENING? Melbourne Airport T4 New Terminal Project & T2 BALT (Bus, Airline Lounge & Transit) Ladd Electric have been contracted to A.E. Smith for the mechanical electrical installation on 2 new building projects at the Melbourne Airport. Project 1 - The T2 BALT project has just been completed and was extremely challenging from many aspects, from site access (airside), to design integration with existing terminal, and builders program. A job well done by all involved and led on site by Daniel Argyle. Project 2 - The T4 project is currently 75% complete and is an extremely large site requiring 2 separate work crews. There is the main terminal located landside [4] consisting of approximate 100 Fan Coil Unit’s, Smoke Exhaust Fans, Ventilation Fans, Split Units, Pumps, and large Air Handling Units located on roof (Pictures attached). We have also manufactured and installed a total of 6 x Mechanical Switchboards for this part of the project. The other part of the project is the Cross Concourse and Pier G buildings which are both located airside. These buildings consist of ERV’s, Daikin VRV air conditioning systems, Smoke Exhaust Fans and ventilation fans. Ladd have also manufactured and installed a total of 5 x Mechanical Switchboards for this part of the project. The boys have done a great job to date led by Ben Notley. Patrick Gigliotti Project Manager T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 Barangaroo Project Sydney Barangaroo is a $6 billion landmark Sydney project on the western foreshore of Sydney harbour aimed at being the first precinct in the world of its size to be climate positive. The project is hoping to achieve a minimum 5 star NABERS energy rating and 6 star office energy design rating. Due to the sheer size of the project (22 hectares) the area has been broken down into three zones. Ladd Electric NSW conduct works within the Barangaroo South zone which consists of 3 commercial towers, Crown 6 star casino, 2 residential towers, and two low level apartments along with retail, ferry and subway services. Common basement plant areas supply the whole precinct and Ladd’s contract consists of the electrical for the chilled water systems, seawater intake systems (taken in from the harbour to be used for cooling and pumped back out) and the seawater backwash filtration systems including instrumentation and controls. Additional specialised protection had to be implemented to combat the highly corrosive and submersible environment. Some of the switchboards installed on site were over 6 metres in length and pumps and T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 VSD’s with active harmonic filtering ranged up to 220kW. Stage one is now nearing completion and I would like to thank Geoff Ladd (design), Frank Franjkovic and team (manufacture) as well as Craig Copland and Scott Campbell (installation) who have been on site for 8 months now. Andrew Stevens Project Manager [5] WHAT’S HAPPENING? Mooka Ore Car Repair Soh (OCRS) Project The Mooka OCRS project is a BHP site which is situated in the remote north of Western Australia, about 30 minutes out of the town of Port Hedland. SEME has been engaged by McConnell Dowell to supply, install and commission a fully integrated CCTV, access control and security solution to the entire OCRS facility. Some of the equipment to be installed and commissioned by SEME includes: industrial swing, sliding and pedestrian gates, PTZ CCTV cameras and poles, Gallagher access control, Jacques intercoms and intruder detection devices to name a selection. Safety on all projects are always of the highest concern and BHP projects are considered to be one of the most safety conscious clients around. However there are a few additional considerations which need to be added into the daily SWMS’ and toolbox talks when working in remote locations such as Mooka. Spiders, snakes, cyclones, high temperatures, etc. all need to be part of everyone’s daily focus above and beyond the normal safety concerns. Engineered out of Perth by Hiren Patel, SEME was able to ensure that all of the usual BHP processes and submissions were completed and approved before our nominated mobilisation date. The site team of 4 Leigh Bradbury, Richard Vial, Adam Berry, led by Liam McSheffrey will be flying in and out of site for approximately 6 months until the estimated completion in July 2015. Site progress to date is on schedule and progressing well with some very good opportunities for additional works being realised. Thanks to the excellent relationship with our client and BHP, to date SEME has been able to increase the project value by over a third, with more opportunities still available. Geoff Woolrich Engineering Manager Woolworths Blackwood SJE SA recently completed Woolworths Blackwood. This project involved the full light and power refurbishment of the existing 40 year old supermarket to the latest Woolworths standards. The project included new main switchboard, distribution boards, emergency standby generator, lighting, power and data throughout the store. Majority of work involved both day and night shift of an operational store. Matt Belperio was the leading hand on site and his crew ensured the project was carried out smoothly and efficiently. The project was delivered within a tight time frame and on budget. Special Thanks to John Gauci in NSW for delivering high quality switchboards within the required timeframe. Wes Frahn Project Manager [6] T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 Osborne Park Hospital SJ Electric has recently completed the Electrical/ Data/ Installation to Osborne Park Hospital in Perth. This installation has been staged to complete an area before progressing onto others. Ian Henry project managed these works and monitored many variations due to design changes by the hospital & consultant. Phil Day Project Manager Stage 1- New theatre recovery area Stage 2 – New stand alone building for doctor patient consultation with 10 medical cubicles & reception Stage 3- Roof mounted plant area with UPS installation, with alteration and addition of existing communication rack and relocating services Stage 4 – Two new operating theatres Installation of body protected earthing with separate company accreditation of testing to all required areas. Our thanks go out to SJE WA site electrician Daniel Robertson, with the aid of Steven Oliver, who completed these work from the start. Coles Cranbourne Park Project This project was a long time in the making with a significant size supermarket and multiple tenancies adjoined to an existing large shopping centre. Being the nominated electrical refrigeration contractor for the Coles supermarket phase, SJ Electric had the task of working in with hundreds of other trades on this substantial sized project. Melbourne Refrigeration is the client contractor and Hacer being the principle contractor, both of which SJ Electric have worked alongside is the past and have a good relationship with. Designs for the refrigeration on this Coles project did not differ much from numerous previous projects with the low temperature department consisting of a Co2 refrigerant configuration and both Medium temperature departments being 134a. SJ Electric have entrusted this project to one of our commercial refrigeration foreman, Brett Gebbing and working under him was a handful of very capable employees. With the knowledge of the refrigeration expert Bill Cope, SJE are well aware of all modifications and changes made to new refrigeration systems. Wiring of a Co2 Configuration system takes some tedious time in sorting through new components that are introduced on a regular basis; also, the introduction of some new suppliers for Co2 safety equipment meant more time efficient working for our onsite personnel. The Cranbourne Park site is due to open towards the end of March 2015. Blake Henry Supervisor T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 [7] Project Velocity, Woolworths Facility, Truganina VIC Following tough competition, SJ Electric secured the light and power switchboards from IES on behalf of Vaughn constriction. SJ Electric was also awarded the refrigeration portion of the job which meant the manufacturing department were required to supply over 25 switchboards totalling 60 meters in length. These two contracts were to be delivered and installed within 7 months from the award date. shedding and generator supplies can be enabled through the key locking system with the use of the automatic changeover system in each switchboard as well. Given the complexity detailed design essential to success of the project, the team showed great commitment and drive to produce a successful result for the business. Well done to all involved. Ken Fitzgerald Engineer & Estimation Manager The main supply to the site is from four substations which include four 1500KVA transformers. The four main switchboards, rated at 2500 amps each are connected together by bus ducts rated 2500A through bustie ACBs installed in each of the main switchboard. The backup generator supplies were connected through an automatic transfer switch arrangement in each of the boards. A castel key locking system is installed throughout to enable isolation of the supply from individual transformers by the use of bustie switches. This enables the four switchboards to remain operational while a transformer is disconnected for replacement or maintenance. Load SJE NSW & Maser Communications Partnership SJE NSW is currently undertaking four major projects with Maser Communications and more are on the way. They are installing a Voltage Optimiser at the Masters DC in Hoxton Park, two voltage optimisers at the Woolworths RDC in Wyong and installing over 300 LED Hi Bay replacement fittings at Swires Cold Storage in Hoxton Park. SJE NSW were first contacted by Maser last year thanks to a recommendation from Woolworths and have quickly grown into a great partnership for both companies. Maser has been installing the Digital Lumens LED Hi Bay product for some time. Utilising wireless technology, it allows the client to fully control the lighting needs. They’ve also just become the Australian [8] distributor for the EMS Powerstar Voltage Optimiser. A UK market-leading product making a large push into Australia. Digital Lumen Hi Bays are to be installed at the Woolworths Wyong RDC and there are more Voltage Optimisers in the pipeline Each site has its own particular challenge but the SJE staff continue to get through them all. For example, the Swires Cold Storage job involves working in -25oC all day, and the shutting down of a Distribution Centre means all hands on deck for many hours working very hard to get the job done and power back on. SJE NSW is looking forward to a long and successful relationship with Maser. As of the current moment, SJE NSW have successfully installed one of the Voltage Optimisers at the Wyong RDC, with the second VO to be installed in April. The Masters DC Voltage Optimiser is also scheduled to be installed in April. The Swires LED changeover is very nearly complete. In the immediate future, over 700 T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 Luke Van Soest Supervisor Manufacturing Update South East Water opted to construct an Odour Control Facility (OCF) for containment and treatment of odorous emissions from the primary treatment area of the Mt Martha Sewage Treatment Plant (STP). The project was undertaken with Fulton Hogan as the lead contractor. CEI’s involvement in the project undertook the electrical installation of the main bio tracking filter, heaters, carbon activation filters, extraction fans throughout the treatment plant all dosing pumps and instrumentation. The electrical works required a 140meter cable tray installation through the treatment plant tunnels and also included retrofitting the existing switchboard with new motor control cabinets. within the existing PLC. This program was designed and implemented by CEI. The principal of the design was to draw contaminated air through the associated upstream ductwork with the use of an extraction fan. The system then forces the air to enter the base of the bio tracking filter before entering the carbon filters. The contaminated air now treated is dissipated through a ventilation stack into air. Part of the electrical scope was the development of software which had to conform to the EPA regulation. The system electrical design was completed in-house by Michael Eaton; Michael’s commitment to the project was first class and much appreciated. Our electrical install was overviewed by Alain Rozic who always gives 100%, Thanks for the effort guys. The operational mode of the Odour Control Facility is displayed on the South East Water SCADA system, which was configured The project hit all targets and was handed to South East Water in time and on budget. I would like to thank everyone for their involvement; we are looking forward to upcoming projects with Fulton Hogan and South East Water. John Mackenzie Water Project Manager Woolworths Torrensville The new Torrensville Shopping centre is located on the original brick manufacturing site just to the west of the Adelaide CBD and was completed by SJE SA. The site is a state heritage listed site and as such has its own restrictions as the original chimney stack and surrounding building has been included in the complex. SJE SA, through Control Air, were awarded the contract for the refrigeration electrical works in the Woolworths supermarket and the Dan Murphys. Neil Moore was the leading hand on this project and was assisted on site by Matt Bunfield. Well done to all who worked on site! Greg Moncrieff Project Manager T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 [9] new staff community SJ Electric WA Greg Carless Purchasing/Stores Manager Dec 2014 Matthew Byrne Electrical Mechanic Jan 2015 Jamie Noble Electrical Mechanic Jan 2015 Victor Rodriguez Electrical Mechanic March 2015 Adam Fielder 1st year Apprentice Dec 2015 Charles Kay 1st year Apprentice Feb 2015 Brooke Jenkinson Project Admin Jan 2015 Christopher Kelleher Service Technician Feb 2015 Timothy Prinsloo 4th Year Apprentice Feb 2015 Michael Tomlinson 1st Year Apprentice March 2015 Yzelle Strydom Office Assistant March 2015 Fred Swart WA/SA Commercial Manager March 2015 SJ Electric SA Mitch Dobson (Electrician, SJE NSW) raised over $1000 for Movember late last year, what a great effort for a wonderful charity! SEME Solutions Later this month, employees from SJE VIC and Ladd are taking part in the annual Royal Children’s Hospital Run for the Kids. A team donation page has been set up to raise funds for the Good Friday Appeal, please go to http://runforthekids2015.gofundraise.com. au/page/WoolyMammoths if you wish to support our team & a great cause! Ladd Electric Dharsh Abeysundara Sales Engineer Jan 2015 Madhuka Ranatunga Graduate Project Engineer Jan 2015 Adam Masters A Grade Electrician Jan 2015 Petros Mavroidakos A Grade Electrician Jan 2015 Nicholas Martignago L&P Electrician Feb 2015 Shannon Stokes L&P Electrician Feb 2015 Owen Tootill L&P Trades Assistant Feb 2015 Ebony Gorincu Project Administrator Feb 2015 Samantha Warren Purchasing Officer Feb 2015 Zachary Holmes L&P Trades Assistant March 2015 Jason Martin Switchboard Electrician March 2015 Mitchell Rhys 1st year Apprentice Feb 2015 Jack Duke 1st year Apprentice Feb 2015 Liam Kinsella 1st year Apprentice Feb 2015 Luke Milner 1st year Apprentice Feb 2015 York Sebastian 1st year Apprentice Feb 2015 spotlight on SJ Electric QLD SJ Electric VIC Trivantage Power David Barshevski Project Manager Feb 2015 Trivantage Head Office [10] Anthea Droszczak Payroll Officer Feb 2015 Cheysha Alexander Assistant Accountant March 2015 Adrian Di Martino VIC Commercial Manager March 2015 Name: Gail Bowers Company: SJ Electric Group (QLD) Pty Ltd Position: PA/Administration How long have you worked for SJ Electric? 13 years. Hobbies and Interests? Playing with my son Jack and (in the rare quiet times) reading. Favourite Holiday Destination? Neurum Creek Bush Retreat – every new year’s we go camping for a week with our extended family. What I am looking forward to most this year? Welcoming our newest member into our little family! T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 recipe Chocolate and Peanut Caramel shortbread spotlight on Ingredients 240g unsalted butter, softened 55g (1/4 cup) caster sugar 250g (12/3 cups) plain flour 1 1/2 x 380g cans Nestle Top ‘n’ Fill Caramel 100g roasted salted peanuts, chopped 175g (1 cup) chopped bitter dark chocolate Method 1. Preheat oven to 180°C. Line the base and sides of a 20cm x 30cm slice tin with baking paper. 2. Using an electric mixer, beat 175g butter, sugar and 1/4 teaspoon sea salt until light and fluffy. Add flour and beat until the mixture just comes together. Press into the prepared tin, then bake for 25 minutes or golden. Cool. 3. Place the caramel and 40g butter in a small saucepan and whisk over low heat until mixture boils and is smooth. Scatter the peanuts over the shortbread layer, then spread over the caramel mixture and refrigerate for 20 minutes or until firm. 4. Stir chocolate and remaining butter in a heatproof bowl over a saucepan of simmering water until melted. Cool slightly, then spread over the caramel layer and refrigerate until set. To serve, cut into squares with a sharp knife. thaNk you letter Name: Mario Kovac Company: SEME Solutions Pty Ltd Position: Service Scheduler & Security Technician How long have you worked for SEME: 21 months. Hobbies & Interests: Soccer, watching sports, Model Crafts. What is your favourite all time food: Everything my fiancé cooks. What is your ideal holiday location: Coast to coast trip of the USA. If you could take 3 people to dinner who would they be: Zlatan Ibrahimovic – Never a dull moment, Russell Peters– For a laugh and Olivia Munn – Easy on the eyes! Congratulations to the Service department on receiving this thank you letter from one of our valued clients, Optus! From: Baha Kaya [mailto:Baha.Kaya@optus.com.au] Sent: Monday, 19 January 2015 9:41 AM To: Carly Linton; Phil Neumann; Geoff Buckley Cc: Andrew Ward; Stewart Joyce Subject: Thank you... Dear Carly, Phil and Geoff, The purpose of this email is to formally thank you all for the excellent service you provided me during sourcing, installation and commissioning of an EMX3 soft starter module to resolve a critical chiller problem at Mascot Exchange. Please convey my thanks to Will and Matt as well. Excellent customer service that you have provided should be shown as an example for others to try to emulate. Kind regards. Baha Kaya Facilities Services Manager National Technical Facilities Management IConsumerI Optus T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 [11] staff achievement OH&S Message Safety Awareness – Electrical Safety Awareness As individuals we all have our own work ethics but it is important that part of our work ethics include as a minimum our obligations to Health and Safety by: Q. What can’t you see or smell but it is deadly if not treated with respect? >Ensuring our own safety and health at work. > Avoid adversely affecting the safety and health of any other person through any act or omission. > Comply with all reasonable instructions. >Follow correct procedures when doing the job. Answer: Electricity You are probably all aware of the tragic events that occurred recently at the Morley Shopping Centre Western Australia, where an Electrical Incident took place resulting in the death of 2 electricians and seriously injuring 2 other electricians. At this stage there has been no official report from the Electrical Safety Office or Work Safe WA on the causes of this tragic event. This is a reminder of the dangers that our industry can present when things go wrong. The following message is not designed to speculate on what may or may not have happened at Morley Shopping Centre but to look at ourselves, our systems of work, our policies and procedures. Prevention There are three basic steps that should be taken to ensure a safe and healthy workplace and prevent incidents. These three steps are: >Identifying the Hazard: This involves recognising things which may cause injury or harm to the health of a person. For instance – Electrical Works, Working at Heights, Poor Housekeeping. > Assessing the Risk: This involves looking at the possibility of injury or harm occurring to a person if exposed to a hazard. > Controlling the Risk: By introducing measures to eliminate or reduce the risk of a person being exposed to a hazard. Definitions: Accident means an unplanned occurrence or incident that causes or contributes to personal injury or damage to property. Incident means any unplanned event resulting in, or having a potential for injury, ill health, damage or other loss. So what can we do? We have policies and procedures that are designed to provide a safe platform/ foundation. It is important we all understand and comply with them and where there is room for improvement, provide feedback – as you are the users of the systems it is important that they work for you. The above steps are the basic requirements for your development of your Safe Work Method Statement. Work Safe - Be Safe – TriSafe Mick Thomson Safety Risk and Quality Manager Competition Winners!! Congratulations to the winners of our Sandcastle competition – Joshua & Nathan Gauci (under 5’s) and Jake & Eden Long (over 5’s). The Gauci family photo was taken at Clontarf Beach, Sydney and the Long family photo at Batemans Bay, NSW Thank you to everyone who entered, we hope you all had a wonderful summer! [12] Luke DeLeon T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 Damien Edbrooke Trivantage would like to congratulate Luke DeLeon (Electrician) for 10 years of service with SJE QLD, and Damien Edbrooke (Electrician) for 20 years of service with SJE VIC. What great experience to retain in our team! Congratulations to Elayne Geltch (State Accountant, SJE QLD) on winning a Photography award in December for one of her photos in the Brisbane Annual Awards. She was also was placed 5th in the Caboolture Camera Club for the year - one point behind her husband! announcements BIRTHS Nathan Copping (Electrical Fitter, Ladd) and wife Nelly welcome the beautiful Milla Joyce, born on 28th December, 2014. Milla is a little sister to brother Casey. Murray Brown (Installation Supervisor, SJE QLD) and wife Krystal welcomed daughter Florence Lee on the 10th December 2014 weighing 7lb 12oz. Florence is little sister to Tanna. Jason Devine (Estimator - Water, SJE QLD) and wife Helen welcomed son Ari Terence on the 16th February 2015 weighing 3320g. Ari is little brother to Euan. Brett Gebbing (Supervisor, SJE VIC) and wife Meg welcomed Lewis Kenneth on 14th January 2015, weighing in at 7lbs 9oz. Lewis is their 3rd child, and a little brother to sisters Holly and Rosie. Vanessa Gallagher (Service Supervisor, SJE VIC) and husband Terry welcomed their 2nd child, Spencer Edward, into the world on 23rd Feb 2015, weighing in at just under 9lbs. Spencer is a little brother to a very excited Blake! Michelle Davis (Admin & Account Manager, Group CCTV) and her husband Dan welcomed their first child, William Joseph into the world on 27th November 2014. William weighted 3.325kg and was 51cm long. spotlight on Name: Bill Collins Company: SJ Electric SA Position: Maintenance Electrician How long have you worked for Church Electrical Industries? 2yrs. Hobbies & interests? Football, Golf, Water skiing, Jet skiing, Softball. If you could take 3 people to dinner with you, who would it be? Leigh Matthews, My wife Gen and Johnny Depp. Proudest Moment? Birth of my daughter Lani. Share something interesting about yourself? Played Softball in the World Masters Games in Sydney in 2009! How do you plan on spending your Easter break? I’m on call so I plan at relaxing at home and doing some odd jobs around the place. T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 [13] christmas celebrations SJ Electric QLD On 6 December 2014 all SJ Electric QLD and Trivantage QLD employees, partners, and children were invited to attend a break up party at the Everton Park Hotel with a special visit from Santa! SJE VIC, CCS, POS, Trivantage, Ladd & Church All the Victoria branches celebrated together with family day held at Melbourne Zoo and the break up day function at the Barkly Hotel. SJ Electric SA Staff were treated to a fishing charter where they caught snapper, snook, shark and had an attempt at stingray. There was an added bonus for the person who caught the largest fish; Lukas Ongel and also a prize for the unluckiest fisherman for the day; Ben Adamou who spent most of the day leaning over the side of the boat! [14] T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 Group CCTV Group CCTV celebrated with a low key BBQ at Andrew’s home. Instead of the old Secret Santa they decided to mix it up a bit and each employee was asked to bring a neutral present to take part in a present stealing game. There was one item that everyone seemed to want which was a Radio Esky filled with Lollies and it was stolen several times with Ashleigh Lotherington taking it home! SJ Electric NSW An enjoyable time was had by all staff at Panorotti’s Restaurant at the Panther’s Leagues Club. They filled up on pizza, pasta and some beautiful desserts and then outside at the Squires Terrace Bar where the boys filled up on...........well, I’m sure you can work out the rest! Cassie Shorten (Service Coordinator) also gifted these cool reinbeer to some of the guys! SEME & SJ Electric WA In addition to the staff party, all the kids were treated to a family day including a clown, face painter, jumping castle, lolly buffet and a visit from Santa at the Como Bowling Club! T R I V A N TA G E - I S S U E 1 9 A P R I L 2 0 1 5 [15] apprentices Trivantage is pleased to announce that we have 8 new 1st year apprentices staring with us this year. We welcome you all aboard and hope you find your employment with Trivantage to be a valuable learning experience, after all you are being trained by the best in the business! We would also like to congratulate all the 4th year apprentices who have recently completed their time and are now fully qualified, including: Ladd – Jamie Paraga, Chris Tairych SJE QLD – Ryan Lassen, Michael Cundy SJE VIC – Ryan Burton, Aaron Ciantar, Dean Coventry, Thomas Cutter, Jarryd Dean, Daniel Pietryka SJE NSW – Daniel Hodonj, Troy Rosier Well done everyone! Since 2005 SJ Electric QLD has been presenting the Apprentice of the Year award. The 2014 Apprentice of the Year winner was 1st Year Apprentice Daniel Jones. Congratulations! MOVIE REVIEW Gone Girl (MA15+) 149min It is few and far between in our household that we are able to have a movie night that doesn’t consist of Cars, Monsters Inc and Shrek, and when we do it is always hit and miss as to whether we picked one worth watching. Finally we hit the mark! Gone Girl is a 2014 American psychological thriller directed by David Fincher and adapted by Gillian Flynn from her 2012 novel of the same name. It stars Ben Affleck and Rosamund Pike. On the occasion of his fifth wedding anniversary, Nick Dunne reports his wife Amy missing. Under pressure from the police and growing media frenzy, Nick’s portrait of a perfect relationship begins to crumble. Soon his lies, deceits and strange behaviour have everyone asking the same question: Did Nick Dunne kill his wife? L-R. Paul Stanley, Rob Lassen, Daniel Jones, Bev Walker and Russell Stanley. NECA Apprentice of the Year Awards Trivantage would like to congratulate Ben Krieg on winning the NECA State Apprentice of the Year Award in the Commercial/Domestic Category for South Australia as a 4th year apprentice. What an outstanding achievement! With 49 wins, 98 Nominations and Oscar Nominated for Best Performance by an Actress in a Leading Role (Rosamund Pike), this mystery thriller shifts emphasis and perspective continuously. Taking a right turn, then a left and flipping upside down, you will find yourself asking “did he or didn’t he” so many times you lose count. It is a plotobsessed picture that’s determined to stay one step ahead of the audience at all times. Some other pleasant surprises include the appearance of Neil Patrick-Harris and Trent Reznor (Nine Inch Nails) and Atticus Ross’s creepy-optimistic synthesized score. This film never drags, nor does its mood settle. I found this movie thoroughly entertaining and often brilliant from beginning to end. Gail Bowers SJE QLD PA / Administration Well done everyone! www.trivantage.com.au