Construction Program Update
June 2012
Progress to Date
ƒ
The District elected to replace the roof and HVAC systems in the kindergarten classrooms in addition to the multipurpose room and classrooms 13‐17. Per the District’s direction, funds from the deferred maintenance budget will be repurposed for the replacement of the roof and HVAC systems in the kindergarten classrooms
ƒ
Projects and budget for the summer 2012 construction program were approved by the Board in April
ƒ
Meetings were held with Schaefer ES and Olivet ES principals to discuss safety plans, logistics, fencing locations, and summer construction schedules for each site
ƒ
Bid walks and final bids were completed in May and contracts were prepared for Board approval
ƒ
The environmental review process was initiated for the construction of three water wells at Olivet ES
1
Proposed Program Team & Roles
Piner-Olivet Union
School District
Program
Administrator (CFW)
Wright Constructing
Quattrocchi Kwok
Architects
Schaefer
Elementary Projects
Wrigth Constructing
TLCD Architecture
Olivet Elementary
Projects
Contractual
Communication
2
Proposed Summer 2012 Projects
Kindergarten Classrooms
Multipurpose Room
Classrooms 13‐17
Buildings to be completed summer 2012
Buildings to be completed in a later phase
Buildings completed in summer 2011
3
Water Tanks
Disabled Parking Stall Re‐grade
Multipurpose Room & Kitchen
Phase I Master Budget General Obligation Bond
Interest Earnings
Projects
$
$
$
PHASE I - COMPLETED SUMMER 2011
Total Expended
Current Budget
(thru Apr. 30, 2012)
District Wide
Solar Installation
Technology Improvements
Maintenance & Equipment
Schaefer ES - Re-roof & Replace
HVAC in Classrooms (3-7 & 9-12)
Olivet ES - Improve Circulation
Subtotal - Summer 2011
Projects
8,033,225
27,561
8,060,786
Est. Remaining
Budget
$3,368,113
$675,000
$409,648
$3,306,453
$408,497
$114,667
$61,660
$266,503
$294,981
$1,431,615
$1,431,615
$0
$515,155
$6,399,531
$386,266
$5,647,499
$128,889
$752,032
PHASE I - PROPOSED SUMMER 2012
Total Expended
Ending Balance
Proposed
(thru Apr. 30, 2012) (thru Apr. 30, 2012)
Budget
Schaefer ES Projects:
Replace Roof & HVAC
$766,338
$69,643
$696,695
$894,917
$108,745
$786,172
$1,661,255
$8,060,786
$178,387
$5,825,886
$1,482,868
$2,234,900
Multipurpose Room
Classsrooms 13-17
Kindergarten Classrooms
Olivet ES Projects:
Install Water Tanks
Regrade Parking Stall
Modernize MPR & Kitchen
Subtotal - Summer 2012
Phase I Total
5
Next Steps ƒ
Approve Schaefer ES and Olivet ES construction contracts
ƒ
Finalize scheduling, safety, and coordination with the school sites
ƒ
Complete design, bid, and California Environmental Quality Act (CEQA) process for water tanks at Olivet
ƒ
Begin construction
6