SUMMER EDITION 2012 TAKING TAKING THE LEAD IN WIND POWER GENERATION I N S I D E Descon Integrated Projects Ltd 04 Shaping up the Manufacturing future of boilers Lahore Manufacturing Works 06 Karachi Manufacturing Works 09 Abu Dhabi Manufacturing Works 10 Hamriyah Manufacturing Works 11 Overseas Business Area Qatar 12 United Arab Emirates 17 Cover Story FFCEL Wind Power Project 21 Kuwait 25 The world Saudi Arabia 26 welcomes a new treasure Joint Venture Presson Descon International Ltd 28 Corporate News DCH expands its product range DCH 30 DOL 31 DPS 32 E&P 34 HRD&A 35 ICT 39 IWT 41 PC&S 42 QA&QC 43 EDITOR’S NOTE Dear Readers, Here we are, with yet another issue of Descon News. This issue will brief you on the latest achievements and developments within Descon. This year has seen the culmination of Descon's diversification dreams with the award of an EPC project of FFC Energy Ltd., a step forward towards the development of the Wind Power Industry of Pakistan. Descon plays an instrumental role in this project by pioneering the manufacturing of wind tower masts, which demonstrates the confidence and trust by FFC in Descon's capabilities. The success stories of Descon performing the first heavy lift at Borouge P3A Project, introducing two new variants in its line of FR products and striking a deal with ESBI Intl., exemplify the indefatigable commitment of the Descon family. Hope you enjoy this issue. Warm Regards, Rabya Sheikh ABBREVIATIONS BPD DEL FAT HRSG MPSCS PWHT Barrels per Day Descon Engineering Limited Factory Acceptance Test Heat Recovery System Generator Manpower Strength Control System Post Weld Heat Treatment CDR EDP FR LTI OHSAS TPD Carbon Dioxide Recovery Engineering Design Package Fortified Rosins Loss Time Injury Occupational Health and Safety Advisory Services Tons per Day CSR EPC FRT LTMSA PMP TSF Corporate Social Responsibility Engineering, Procurement, Construction Floating Roof Tanks Long Term Maintenance Services Agreement Project Management Plan Temporary Site Facilities EDITORIAL TEAM Aamer Hadi Khan Rabya Sheikh Ch. Muzaffar Ali Head Business Development Coordinator Communications - BD Asst. I/C Communications - BD Adenan Hussain Sharaf Javed Sr. Engineer - Overseas Coordination Marketing Engineer Descon Integrated Projects Ltd. Yousaf Malik DIPL Management Forum DIPL conducted a forum where the senior management, including departmental heads and project managers were invited to candidly discuss organizational objectives vis-à-vis the ever-changing business environment. the following points: The forum started with the recitation of the Holy Quran, followed by an open discussion on the rejuvenated vision and core values of the company. Afterwards, the departmental heads presented an outlook of their respective departments in light of upcoming challenges and shared with the participants various initiatives taken to maximize business opportunities. Another interesting part of the forum was an interactive round of group discussions. All the participants were asked to group into eight teams of equal strength and given a task to outline key issues along with their solutions. The top eight common issues were then selected for an open discussion in order to brainstorm effective solutions to address these challenges as a team. c) At the end of the session, President DIPL, Mr. Khawar Khan re-capped the day's proceeding with special emphasis on 04 DESCON NEWS | SUMMER 2012 a) Alignment of DIPL's vision with Descon's overall vision b) Current standing and achievements of DIPL Current and upcoming challenges amid changing market trends d) The way forward and focus areas to address challenges Descon Opens EPC Office in the UAE In order to establish our strong foothold in the UAE market and cater to the long standing demand of our major clients, Descon has set up a new EPC (Engineering, Procurement, Construction) office in Abu Dhabi. With the establishment of this office, Descon will be able to effectively tap new opportunities in the GCC market to further improve upon its execution of EPC projects in the region. This office will now be the perpetrator of recently awarded Gasco Habshan Acid Gas Flare Recovery Project comprising of engineering and project management services. DIPL Habshan Acid Gas Flare Recovery Project Descon has been awarded an EPC contract to build an Acid Gas Flare Recovery System at Habshan by Abu Dhabi Gas Industries Company (Gasco). The project is scheduled to be completed by the middle of 2014. The project scope entails recovering the flare gases being burnt in the Acid Gas Flare Systems and compressing them to a higher pressure in order to re-inject them into the processing facilities. Hydrocarbon liquids and sour water separated in the Acid Gas Flare Systems are also being taken care of as per the scope of the project. This project is of great significance to Descon since it is the first EPC project received from Gasco and would act as a cornerstone for a strong, long and mutually beneficial relationship between the two companies. Takreer Gas Oil Transfer Facilities Project Erection of the towers, nacelle and rotors are considered to be the most difficult part of the construction process. The professional skill set and dedication of the team was the hallmark of its successful completion. A total of 33 wind turbine towers are to be erected for this 50 MW FFCEL project, with the final set of towers under fabrication at Descon’s Karachi Manufacturing Works. Uch II Power Project (400 MW CCPP) The Uch II Power Project, which was awarded to the consortium of Descon and Hyundai Engineering Company, is now in full swing. Phase I of the HAZOP study was successfully conducted in Seoul, South Korea in February. The next phase is planned in later half of the year. The Uch II site access road’s work has been completed and Descon has established a camp on site. Descon won an EPC contract of Abu Dhabi Oil Refining Company (Takreer) to carry out installation of gas oil pumping and its transportation facilities from Mussafah terminal to SasAI-Nakhl (SAN) terminal. The project scope includes gas oil transfer pumping, pigging and slop injection facilities along with associated piping, electrical, control and civil works. This fastpaced project is to be completed in a schedule of about ten months. At this stage, the following major activities are underway: Piling work for turbine foundations Excavation for raw water and evaporation ponds Structural work for cooling tower Construction of main administration and workshop buildings FFC Energy Ltd. Descon has successfully erected the first batch of wind turbines for Fauji Fertilizer Company Energy Limited. Each tower is 80 meters high with a rotor radius of 40 meters. DIPL Adco - EPC for Replacement of Jetty Substation The project awarded to Descon in November 2010 has been successfully completed without any LTI. This was the first EPC project of Descon which involved skid mounted substation equipment. DESCON NEWS | SUMMER 2012 05 Lahore Manufacturing Works Muhammad Mujahid READY TO SERVE YOUR INDUSTRIAL NEEDS! Boiler News Bagasse Fired Boiler for RYK Sugar Mills Being a pioneer of high pressure bagasse-based steam solutions in Pakistan, Descon has always been a trusted name for cogeneration in the sugar industry. This patronage was taken to new levels with the award of the project for the supply of 1 x 138 TPH, 65 barg, 485°C, high pressure, bagasse fired boiler for RYK Sugar Mills. This is the largest bagasse-based high pressure boiler project in Pakistan and Descon is the first company to achieve this landmark. Our scope encompasses complete design, fabr ication, supply, erection and commissioning of the boiler. The fabrication has begun and is expected to be commissioned by September, 2012. HRSG for Haji Sheikh Noor- ud- Din & Sons Other than high capacity and high pressure HRSGs for power generation and cogeneration, Descon's HRSGs have always been a reliable source for steam processing solution. LMW has been granted the project of 1 x 3.0 TPH, 10 barg, triplex type Heat Recovery Steam Gener ator from captive power plant consisting of 1 CAT and 2 JGS gas engines. Haji Sheikh Noor-ud-Din & Sons, are worldwide famous for their export quality tents. Descon's scope c ove r s c o m p l e t e turnkey services of the boiler. Fire Tube Boilers for Aisha Steel Mills The mechanical completion and commissioning of 3 x 6 TPH, 7 barg, saturated steam, natural gas fired, fire tube boilers for Bagasse Fired Boiler for Adam Sugar Mills LMW has been awarded the project of 1 x 120 TPH, 27 kg/cm2, 350°C, bagasse fired boiler. This is another major achievement by the team in the sugar sector. Descon's scope entails complete turnkey services including design, fabrication, supply, erection and commissioning. 06 DESCON NEWS | SUMMER 2012 LMW Aisha Steel Mills has been done successfully. The progress on this project is ahead of the agreed schedule. Water Tube Boilers for Rafhan Maize The manufacturing of 2 x 30 TPH, 200 psi(g) water tube boilers for Rafhan Maize Pakistan is in full swing.The hydrotest of the first boiler has been completed and the second is in progress. The project is within timelines and civil works at site have also been initiated. Drums & Heat Exchangers for Engro Descon's association with Engro goes a long way back. Last year, once again LMW was given a number of process equipment jobs by Engro for its plant at Dharki. This includes design, fabrication and supply of knock-out drums, anti-surge coolers, fuel coolers and hair-pin type exchangers for the Engro Compression Project. For the first time, LMW has undertaken process and mechanical design of such type of exchangers. Three Phase Separator for PDIL LMW has been granted the job of design, fabrication and supply of three phase production separators with its associated skid and piping by PDIL for PPL. The vessel is designed at pressure 1,000 psi(g), temperature 150˚ F and MDMT-20 ˚F. Process Equipment News Fluidized Air Cooler for FFC For the very first time, LMW has been awarded the job of design, fabrication and supply of a fluidized air cooler operating at 8 barg and 66 °C with a header plate thickness of 86 mm. The process design was prepared by DIPL which was later vetted by Uhde, while the structural analysis was carried out on Stat Pro by LMW's mechanical engineers. This air cooler will be installed at FFC's plant site at Mukhtargarh, Sadikabad. Oil & Gas Development Company Ltd. LMW is involved in a number of up-gradation, development and facility enhancement projects with OGDCL. In this regard, process equipment jobs have been carried out for OGDCL's sites in Kunner, Dakhni and Uch gas fields including design, fabrication and supply of several heat exchangers, tube bundles, NGL fractionators and amine stripper re-boilers. ARL has also awarded a number of heat exchanger jobs including the fabrication and supply of a condensate injection vessel. Communication Towers for Ufone Phase- 10 A one year contract was signed between Huawei and LMW for the fabrication of 400 communication towers, antenna mounts and other accessories which amounts to almost 2,000 tons of steel for the year 2012. Wellhead and Air Coolers for OMV After Sales Services After a span of nearly six years, LMW has achieved a breakthrough with OMV with the award of wellhead coolers for Latif North-1 site. LMW was also involved in the fabrication and supply of the tube bundle for the air-cooled exchanger. After providing the rental steam solutions to the client, LMW has been awarded with different retrofitting, spare parts and services jobs by Pakistan Ordinance Factory, Nestle Pakistan Limited, Attock Refinery Limited and Packages Pakistan Limited. LMW DESCON NEWS | SUMMER 2012 07 Circulating Fluidized Bed Technology: Your Key to Sustainable Energy Dr. Salman Zakaria, CEO, Descon (L) and Mr. Wu Jianxun, President, JBG (R) during the contract signing ceremony Keeping in view the current energy crisis and scarcity of conventional fuels, the dependency of industry on alternate fuels like Coal and Biomass has increased extensively. To cater to these requirements, Descon Engineering Ltd. and Jinan Boiler Group Co., Ltd have joined hands to offer technically and commercially viable solutions to clients in Pakistan. Both parties have signed a technical collaboration agreement for the manufacturing of solid fuel fired boilers using Circulating Fluidized Bed Combustion Technology. The complete boiler design will be provided by JBG while local manufacturing, installation and commissioning will be conducted by Descon in collaboration with Jinan. With this step forward, Descon stands committed to delivering customer-centered steam solutions on solid fuels to its clients. Descon Engineering Limited started boiler manufacturing at its Lahore Manufacturing Works (LMW) in 1988. Since then, Descon boilers have maintained an outstanding growth in both domestic and regional markets achieving excellence in the fields of engineering, procurement, fabrication and commissioning to provide the most competitive and reliable turnkey solutions to our clients. To date, Descon has provided boilers to nearly all industrial sectors including fertilizer, oil & gas, chemical/petrochemical, power, cement, paper, textile, sugar, pharmaceutical and food sector utilizing various fuels. With more than 150 boilers and 08 DESCON NEWS | SUMMER 2012 cumulative steam production of more than 5,000 tons per hour, Descon is committed to increase this number in the near future. Currently, Descon is capable of supplying direct fired boilers up to 290 TPH, 136 barg, 540°C and heat recovery steam generators behind gas turbines up to 270 MW. Jinan Boiler Group Co., Ltd. (JBG) China, established in 1954, is the kernel subsidiary company, 100% owned by Dragon Power Co., Ltd. which is the representative enterprise of the clean energy industry. JBG is a globally-known Circulating Fluidized Boiler designer and supplier on coal and biomass fuels. With advanced technology and excellent quality service, CFB boiler products of JBG have gained major recognition not only in China, but in the international market as well. Majoring in the manufacture of medium and high pressure power boilers, JBG integrates the scientific research, manufacture, complete equipment supply, installation, maintenance, innovation and technology consultation of boilers. JBG has sold more than 2,000 sets of 35t/h~650t/h CFB boiler, which takes up 50% of the total CFB boiler market in China. CFB boilers have been exported to Mongolia, Pakistan, Thailand, Indonesia, India, Malaysia etc. LMW Karachi Manufacturing Works Wajahat Arifeen 1. Cutting 2. Rolling 3. CO2 Welding Indigenous Industrial Solutions Provider Wind Towers KMW’s team is proud to be the pioneer in manufacturing of wind towers in Pakistan. The commencement of this production facility at our Karachi Manufacturing Works, Port Qasim proves that we are continuously striving to achieve new horizons. In the recent past, the production of wind towers has taken its pace towards the completion of FFCEL Project, which is expected to be completed by the mid of the current year. Currently, the team has completed eleven sections of the wind towers, which are to be installed at Jhimpir, Sindh in the 50 MW capacity wind farm, powered by wind turbines of Nordex, Germany. The project will consist of 25 towers, each of a height of 80 meters, an individual weight (fully laden) of 147 tons and segmented into four sections per tower. Entire fabrication starting from plate cutting, rolling, welding, blasting, painting and installation of the internals is being done at KMW. KMW LTI Free One Million Man- Hours 4. Smaw Welding Karachi Manufacturing Works is proud to achieve LTI free one million safe man-hours. Achievement of this milestone is a result of the combined efforts of HSE and KMW's employees and we congratulate the entire team on achieving this milestone. 5. Fit-up Supply and Fabrication of Tube Bundle Karachi Manufacturing Works encompasses the supply and fabrication of heat exchangers as well as tube bundles. Serving companies like Asia Petroleum, Engro Polymer & Chemicals Limited and National Refinery Limited, KMW is working to add new clients for this product in the near future. 6. Inspection 7. Painting Steel Structure and Silos KMW has supplied stainless steel silos and carbon steel structure to Astro Pack Limited and Tri-Pack Limited for their packaging plants. It has worked with the designer Bruckner from Germany to deliver precision, quality and superior product specifications while maintaining close tolerance levels required for the load sensors installation on the packaging machine unit. 8. Internals 9. Storage DESCON NEWS | SUMMER 2012 09 Abu Dhabi Manufacturing Works Renowned for its tenacious capability for meeting difficult deadlines and delivery on demanding projects, Abu Dhabi Manufacturing Works is creating history in the field of piping pre-fabrication. Against a planned target of 485,627 ID (diainch) for the year 2011, AMW has successfully completed 507,026 ID. Having achieved this, another 704,387 ID of piping pre-fabrication has been planned for the year 2012, touching the unprecedented ID of 80,000 in one of the months of 2012. Sher Aslam Khan Current and Upcoming Projects Fabrication of aboveground and underground piping for Ruwais Refinery Expansion Project The project awarded by Daewoo with a scope of 216,260 ID piping (CS and SS) and 460 tons of piping supports. To manage the enormous volume of production, the dedicated efforts of a team comprising of mechanical and electrical engineers and super visors, have led to the in-house development of 12 semi-automatic welding machines. The introduction of these machines has helped in achieving huge production targets while maintaining a high level of quality and a reduction in repair rate and cost of consumables. Fabrication of CS and SS piping for Borouge P3A Project Project Highlights Completion of 07 ethylene cracking furnaces with a total of 49 convection modules for Borouge 3 together with 29,000 ID of external piping; awarded by SFPC-Linde. TSJ is Tecnimont Samsung joint venture with a total scope of CS/LTCS 235,324 ID and SS 175,096 ID and an overall expected associated piping support job of 700 tons. Fabrication of CS and SS piping for Gasco SGD Completion of piping pre-fabrication project awarded by CB&I with a total scope of 118,570.This was completed 3 months ahead of the scheduled completion date. Piping pre-fabrication for Shah Gas Development Project, awarded by Eni Saipem with a scope of 196,000 ID and an expected associated piping support job of 450 tons. Fabrication of radiant panels for two furnaces for Borouge 3, a project with a total scope of 800 tons, awarded by Sesab International against a 3 months’ completion deadline for radiant panels; the target was met with on-time delivery. Completion of piping pre-fabrication for IGD Habshan Project with a scope of 200,000 ID with associated piping support job of 480 tons. 10 DESCON NEWS | SUMMER 2012 AMW Hamriyah Manufacturing Works Mian Omer Farooq Shah Gas Development Project HMW is presently manufacturing structure weighing about 15,000 tons for the Shah Gas Field Development Project. The structure, medium to light in weight, was awarded by Saipem for Al Hosn Gas Shah Project. This job, one of the many with Saipem, once again reiterates the confidence and relationship between Saipem and Descon. First Step in Iraq TUV- NORD Recommends HMW for OHSAS 18001 Certification HMW has successfully got the ‘BS OHSAS 18001:2007 stage 2 certification’, completed by TUV-NORD in January 2012. Based on the same,TUV-NORD has issued a recommendation letter for cer tification to the concerned authorities. OHSAS 18001 certification is one of the most acknowledged proof of a company's compliance to occupational health and safety requirements in the international market today. Hence, the subject recommendation fur ther vindicates HMW's commitment towards occupational health and safety. The combined efforts of HSE, QA&QC and other departments saw the completion of the audit requirements in just four weeks' time. HMW was awarded the job for design, fabrication and supply of the cold vent stack by Fluor for the West Qurna 1 Project in Iraq.This job has helped us enter in the Iraqi market. HMW got project specific approval from Exxon Mobil, operator of the West Qurna 1 field through Fluor. This achievement will open new opportunities for business acquisition in this market. 20 Chemical Injection Sk ids for Sek oKOC Bulk handling Project The delivery of 20 chemical injection skids for Seko is expected by the end of April, 2012. Fabrication of the equipment is 95% completed and the Final Acceptance Test of the chemical injection skids will be carried out by April 2012. Manpower Supply for Alstom Middle East Alstom Middle East awarded a contract of skilled manpower supply for refurbishment job on gas turbines 25 and 27 in Ruwais Refinery, Takreer. The required skilled craft has been mobilized to the site from Pakistan and the job has already started at site. Pressure Vessels for Habshan Sulphur Granulation Plant Hyundai's Pressure Vessels for Borouge at Final Fabrication Stage The fabrication of forty pressure vessels for HDEC for Borouge 3, U&O Project is in the final stage and eleven heavy vessels, weighing 532 tons have been delivered to the client on barge. The balance vessels will be delivered in June 2012. Dodsal has recently placed an order for the supply of seventeen pressure vessels to the Habshan Sulphur Granulation Plant Project. Our scope of work includes mechanical design, fabrication, surface preparation, inspection and delivery of the vessels to the project site. The vessels carry liquid sulphur and the steam coils will ensure that the sulphur maintains its molten state. The thermal design of the steam coils also covers HMW's scope of work. HMW DESCON NEWS | SUMMER 2012 11 Qatar Highlights Inauguration of Pearl GTL Project Pearl GTL is a fully integrated upstream/downstream, worldscale project located in Ras Laffan Industrial City, 80 km north of Doha. It captures the full value chain from offshore development through onshore gas processing to refining of the finished products and distribution of these products across the world in one project. When fully operational, Pearl GTL will have the capacity to produce 140,000 barrels a day of high quality GTL products (gasoil, naphtha, kerosene, normalparaffin and lubricant base oils), to meet the increasing global demand for high quality hydrocarbon. It will also produce 120,000 barrels a day of Natural Gas Liquids (liquefied petroleum gas and condensate) and ethane. At its peak, 52,000 construction workers from 60 countries worked on the construction of Pearl GTL, a project which took 500 million-hours to design and build. The project broke many industry records in terms of safety, achieving 77 million man-hours without a lost time injury in 2010. Descon Engineering Qatar LLC participated in the construction of the world's largest gas-to-liquid project and the largest energy project in the state of Qatar with 2,800 highly skilled workforce at its peak deployment and completed 18.7 million LTI free man-hours from a total of 19.7 million man-hours. His Highness, Sheikh Hamad bin Khalifa Al-Thani, The Emir of Qatar, officially inaugurated the Pearl Gas-to-Liquids (GTL) Project, the largest GTL plant in the world. Visiting dignitaries including HRH Prince Andrew, The Duke of York, toured the facility and were briefed on state-of-the-art technologies used to convert natural gas resources from Qatar's North 12 DESCON NEWS | SUMMER 2012 M.Yaqub Field into high quality liquid fuels and products that will be sold at a premium all over the world. Dr. Salman Zakaria (CEO), Mr. Mansoor Rashid (GM), Mr. Muhammad Iqbal Jadoon (Operations Manager) and Mr. Hamid Raza (SM) attended the inaugural ceremony. Barzan Onshore Project Descon Engineering Qatar LLC has been awarded a major portion of the Barzan Onshore Project (Phase 1) by JGC who is working as the EPC contractor. The scope encompasses the common process (South) and utilities area covering general contracting works. On January 06, 2011, Qatar Petroleum and Exxon Mobil signed agreements confirming the Barzan Gas Project, which will play a significant role in meeting Qatar's rising domestic gas demand. RasGas is managing the construction of the new plant and will operate it once it is complete. The project is a powerful step forward in Qatar's overall industrial and human development, in line with the Qatar National Vision 2030. It is located in the Ras Laffan Industrial City, 80 km north of Doha and is one of the most technically innovative projects ever undertaken in Qatar. It will use proprietary technology to recover Natural Gas Liquids (NGL) and remove nitrogen from the sales gas stream. It will produce methane, ethane, propane, butane and condensate. When Barzan Gas Trains 1 and 2 are in operation, the total offshore production from all RasGas operated facilities will reach around 11 billion standard cubic feet per day (equivalent QBA of almost 2 million barrels of oil), making RasGas the largest gas producer in Qatar. Construction activities have commenced and the project is scheduled for completion in December 2013. Descon has been chosen as "The Best Contractor" for the month of May on Barzan Project.This has only happened because of the joint and consistent efforts of the team deployed at the project. 20th World Petroleum Congress and Exhibition Held every three years, the World Petroleum Congress and Exhibition is the largest and most reputable oil and gas industry gathering in the world. This year, the 20th World Petroleum Congress was hosted by Qatar Petroleum and took place at the Qatar National Convention Centre (QNCC) in Doha from December 04-08, 2011. This was the first time since its establishment in 1933 that the World Petroleum Congress was hosted in the Middle East. The 2008 and 2005 exhibitions were held in Spain and Africa respectively. Various high level company executives, CEOs and managers attended the Congress and also participated in the conference. It was also attended by a global oil and gas audience and outside stakeholders such as governments, other industry sectors, NGOs and international institutions. Descon Engineering showcased its products and services at this international gathering. A professional marketing strategy was employed which utilized eye-catching and high impact posters, banners, brochures, leaflets and newsletters. A healthy response was received from the participating organizations and visitors. Of the plethora of contracting companies engaged in the region, Descon Engineering was among the very few contractors that participated in this exhibition to and be listed in the exhibitor's and delegate's list of the 20th WPC list for years to come. The 21st WPC will be held in Moscow in 2014. Qatar Chemical Company Major Turnaround 2012 The selection as a 'Silver Category Contractor' for Overall HSE Performance in Qatar by Qatar Petroleum, played a deciding role for Qatar Chemical Company in choosing Descon Engineering Qatar LLC as the main contractor for its Major Turnaround 2012. This was the second consecutive turnaround resulting in the manpower movement from Dolphin Energy to Qatar Chemical Company and finally to the Qatargas Turnaround, April 2012. Descon successfully completed the Qatar Chemical Company (QChem) turnaround and was applauded for its technical soundness and grasp of performing a major turnaround. Over 750,000 man-hours were executed on the job that had a shutdown period of 28 days and peak manpower of 2,250. Working in the Mesaieed Industrial City is a major breakthrough for Descon in extending its presence in Qatar. And this endeavor would not be successful without the immense support of QChem management. The triennial World Petroleum Exhibition, held alongside the congress featured exhibits from the national committees of the World Petroleum Council, which included the most prestigious national oil and gas companies and agencies of the world. It also showcased the key international oil and gas companies alongside key suppliers, service companies and manufacturers. This was the most significant global exhibition dedicated to the oil and gas industry. Known as the “Olympian Event of the Oil and Gas Industry”, the Congress was attended by 4,000 delegates, 600 media personnel and 550 presenters. The event covered all aspects of the industry, from technological advances in upstream and downstream operations, to the role of natural gas, renewable and alternative energy, industry management and its social, economic and environmental impact. QBA Mr. Carl, HSE Manager and Mr. Nabeel Al-Saadi, Operations Manager of Qatar Chemical Company awarding safety appreciation gift to Mr. Ghulam Meeran, Sr. Piping Supervisor, Descon DESCON NEWS | SUMMER 2012 13 Appreciation Letter Given by Shell Dolphin Energy - Major Turnaround 2012 An award ceremony was conducted to mark the successful completion of the Dolphin Energy Turnaround 2012, which is to date the biggest turnaround executed by Descon in Qatar. This was part of the three years long-term turnaround contract (2011-2013) with Dolphin Energy. The scope of this turnaround was 30% greater than all previous turnarounds. It consisted of three phases (pre-shutdown, shutdown and post-shutdown), altogether contributing to over 1.1 million man-hours, touching a peak manpower deployment of 2,500 persons. The top management of Dolphin Energy appreciated the achievement of the 'One Day Earlier Completion' of the turnaround and assured future business with Descon. 14 DESCON NEWS | SUMMER 2012 Mr. Hassan Al Emadi, VP Qatar Operations, Dolphin Energy awarding Appreciation Certificate to Mr. Gulshan Ali, Turnaround Manager QBA Safety Excellence Award Umer Khan From L to R: Mr. Saad Al-Kubaisi (Manager, Corporate HSE, QP), Mr. Rana Hussain (Incharge HSE Qatar, Descon), Mr. Ahmed Abbas (Manager Corporate HSE, Descon) pictured along with HE Dr. Mohamed Bin Saleh Al-Sada (Minister of Energy & Industry, Chairman and MD of QP) and other delegates of the winning companies. Qatar Oil & Gas Industry Safety Excellence Award Descon Engineering Qatar LLC has been awarded the 'Silver Award' for Outstanding Safety Performance in the 'Contractors Category' during the Qatar Petroleum - Qatar Oil & Gas Industry Safety Excellence Awards ceremony held at the Ritz Carlton, Doha, Qatar. The award was presented by HE Dr. Mohamed Bin Saleh Al-Sada (Minister of Energy & Industry, Chairman and Managing Director, QP). Mr. Ahmed Abbas, Manager Corporate HSE, received the award. “We cannot be satisfied with the way we manage the HSE risks associated with our industry. We not only need to continually improve how we manage these risks, but we also need to bring innovation and creativity.” HE Dr. Al-Sada stressed in his keynote address. The Safety Excellence Awards, which has been instituted by the Corporate Health, Safety, Environment and Quality Department of Qatar Petroleum, aims to recognize outstanding safety programs and initiatives being implemented in the oil and gas industry and to promote safety measures in oil and gas companies. LLC (Silver Award) for its construction of the onshore Pearl GTL Project and Qatar Kentz (Bronze Award) for its EPC projects and services. The oil and gas business is replete with HSE risks and paying close attention to the management of HSE issues makes good business sense. The effective management of HSE risks prevents incidents and, hence, losses that can cripple an industry and put the entire economy of a country at risk. Safety of human as well as physical assets of clients and all other stakeholders has always remained top priority for us. This award not only encourages us to stick to HSE risk assessment, risk management systems and a strategy of continuous improvement, but it also boosts our overall organizational morale and dedication. It ensures we play a vital role within the industry to encourage safe practices, bring innovation in safety measures and remain committed in delivering safe projects. Under this Health and Safety program, all oil and gas companies operating in Qatar had been invited to submit their ongoing safety programs and initiatives for consideration. The winners of the Safety Excellence Awards 2010 under the QP Joint Ventures category are Qatar Shell GTL Limited (Gold Award) for its Pearl GTL Project, QChem (Silver Award) for its QSAFE Process Revamp and RasGas (Bronze Award) for its Interactive Safety Training Program. For the QP Contractors Category, the winners are Schlumberger Overseas (Gold Award) for its QTG Commentary Task Assessment, Descon Engineering Qatar QBA Mr. Ahmed Abbas receiving the award from HE Dr. Mohamed Bin Saleh Al-Sada. DESCON NEWS | SUMMER 2012 15 Mansoor Rashid: New General Manager, Qatar Mansoor Rashid, a mechanical engineer by profession, joined Descon in 1980 and worked for 26 years on various important positions including Construction Manager, Project Manager, Manager Works, Head Manufacturing and GM ODICO. After working for about 5 years at Byco, MR is back with us as the new GM, Descon Engineering, Qatar LLC. He speaks about Descon's recent activities, company's move to infrastructure projects and challenges being faced by contractors in Qatar. What were the key highlights for Descon in 2011? How does Descon see its role in the project maintenance market? MR 2011 was quite challenging for us, in which we secured two major projects. One of the notable achievements in 2011 was the completion of over 18 million LTI free man-hours. From a safety perspective, this was a major breakthrough. We also successfully completed the Pearl GTL Project and completed about 18.7m LTI free man-hours. This has led to the completion of 52 million LTI free man-hours spanned over the last 3 years. We were also awarded the Silver Award in Contractor's Category for HSE Performance by Qatar Petroleum. MR The maintenance schedule can be unpredictable because many projects are new. Generally, mega projects only run for about a year before they need a shutdown. In the case of Pearl GTL, it would comparatively need a turnaround of longer duration. Descon plans to participate in it as we already have long term turnaround contracts with QatarGas and Dolphin Energy and have been recently awarded the QChem turnaround. We want to tap the potential available in this maintenance market and we are working on it diligently. What major projects do you have under way in Qatar? How is Descon reacting to the shift in the Qatari market towards infrastructure projects? MR We have been mostly focusing on plant services/ maintenance and electromechanical construction. In the near future, there are not so many projects in electromechanical construction coming up. There are a few: Qatar Refineries Expansion Project and the Dolphin Project will be adding a couple of compressors. Now, we are focusing more on the infrastructure side. On the other hand, we are still focusing on the traditional plant services business. We are quite confident that in the next year, we will secure major shutdowns and get a further edge. MR Clearly, investment is starting to shift in Qatar away from the oil and gas industry. This is a natural consequence of its 2030 National Vision, the FIFA 2022 World Cup and Qatar's goal of achieving a diversified and sustained economy. The country is now focussed on developing its infrastructure. As these plans unfold, Descon would like to add value to these projects and explore opportunities where we can merge our existing capabilities with an international contractor and deliver value to Qatar. What are the key challenges the construction sector will face over the coming years? How does the Qatari business market compare with other countries Descon has worked in? MR For the construction companies, the major challenge is that competition is increasing and it is not very easy to cope with it. Although the global recession has reduced the cost of human resources to some extent, the increasing competition remains there with companies coming from all across the world. Also, there is a serious problem with logistics and commuting from one area to another. MR Qatar is a very small state by size, but it is a country with regional and global aspirations. That is why it is exciting to do business here. Qatar is different because it thinks differently. For example, the emphasis on women's education is very different than the approach of its neighbours. There is a feeling of uniqueness about Qatar as it wants to look different from the other GCC countries. 16 DESCON NEWS | SUMMER 2012 QBA United Arab Emirates Highlights IGD Habshan- 5 Project M.Yousaf Even the land of hydro carbons is not free from the energy related troubles of modern times. The Integrated Gas Development Habshan-5 Project was conceived in the same backdrop. The construction work started in early 2010 and is fast approaching completion to provide on time gas to Abu Dhabi. The project is designated to treat core units including gas processing unit of approximately 2,000 million standard cubic feet per day (mmscfd) capacity, sulphur recovery unit of approximately 5,000 tons per day and NGL recovery unit of approximately 1,200 million standard cubic feet per day. Situated at 130 km south west of the city of Abu Dhabi, the project is in full swing with our 25,000 workers. The installation of about 3 x 130 meters high flares i.e. LT, HC and AG by Descon in the months of January and February 2012 has changed the sky line of the project and can be seen from as far as the E-11 highway entry to Habshan Oil and Gas Field at Tarif. To recall some memories, Habshan field is the same area where Descon did its first work around thirty years back at Thamama C. gears and MCC panels have been installed successfully. Currently, loop testing of fire & gas and HVAC precommissioning is on going after having completed the construction work of the three buildings. In general, construction, major civil works, steel structure erection, stationary and rotary equipment has been installed including pumps and compressors, underground piping circuits, underground cabling, street lighting, area lighting and above ground piping. The asphalt roads in Descon area are set to start in April 2012. The project now typically buzzes with the rush of test packages and instrument loop packages; and overall construction activities are fast converging towards completion in November 2012. Descon’s part of the project encompasses construction of civil, mechanical, electrical and installation work for feed gas compression & flare area and EPC works of sour water tanks and buildings, i.e. a substation (SS), Instrument & Equipment Shelter and Operation and Maintenance Shelter. The switch UAE DESCON NEWS | SUMMER 2012 17 HSE being the cornerstone of our operations remains the top priority at the project. Gasco and JT-JV (JGC -Tecnimont Joint Venture) have given a number of awards to Descon. The most recent one is the 'Safety Milestone Award' presented on the achievement of ten million safe man-hours without Lost Time Injury. Descon project at IGD remains an LTI free project since its inception. Three thousand workers from Descon have completed IIF (Incident & Injury Free) training. The equipment erection work has commenced at the project with the erection of furnace heater in the month of December 2011. Saipem delivered the first shipment of vessels in the month of January 2012 which have been erected successfully on their foundation. Award of PMT Camp Descon has been awarded an extra works package of building a residential camp to accommodate company's 500 personnel. The scope entails procurement and construction activities to be completed within a challenging deadline of five months. Shah Gas Development Project Anees Sheikh The achievement of one million safe man-hours at Shah Gas Development Project without LTI speaks of Descon's commitment to excel in harmony with Safety, Quality and on time delivery. Descon has been presented a Souvenir Shield by the client Saipem on achieving this milestone. The PMT camp is intended to house the project management team and workforce providing a safe and comfor table environment. It will also accommodate Adco's staff that must be moved to the Shah Field due to their proximity to the drilling of Shah Gas Development Program’s sour gas wells. The camp will be located approximately 10 km east of the SGD plant. The camp will remain even after the project completion to accommodate staff deployed on turnarounds or other operations. Descon has completed Phase-I and Phase-II works of the camp and has also achieved an important milestone of the Civil Defense Approval Certificate. Adco Jebbel Dhanna Project Salim Shahid Souvenir presented by the client, Saipem Descon erecting the first vessel of SGD Project 18 DESCON NEWS | SUMMER 2012 Adco Jebel Dhanna (JD) is 250km away from Abu Dhabi City and is the critical crude oil storage terminal of the UAE. It is one of the main export terminals and upstream feed facility to Takreer Refinery. Adco JD terminal has a storage capacity of 8.35 million barrels and comprises of sixteen single and double deck floating roof tanks. The objective of the project is refurbishment of storage tanks in accordance with the operational pre-schedule for major overhaul of C.O.S tanks at Jebel Dhanna as per the client's requirements. Descon carried out refurbishment of six tanks from 50~80mD. The current contract of four small and medium diameter tanks was awarded in October 2010. The first phase of two tanks was completed in November 2011, whereas the second phase of two medium 80mD tanks started in February 2012 and will be completed by March 2013. The scope of work includes de-sludging, mechanical, civil and electrical works with pre-commissioning and commissioning of tanks c/w dossier documentations. The state-of-the-ar t de-sludging by decanter centrifuge techniques will help recover 90% of crude oil which is a huge saving for the company and the UAE economy. UAE Achieved Milestones 5 million safe man-hours at AMW 9 million safe man-hours at IGD, Habshan-5 1 million safe man-hours at SGD 1 million safe man-hours at Daewoo, RRE HSE Activities Jamshed Ahmed Satti Safety Culture Building Seminar housekeeping in order to keep the site tidy and safe. The campaign was a big success and the entire workshop's employees from managers to helpers actively participated in the campaign. Housekeeping campaigns would now be a regular feature of AMW. Considering the fact that the management can greatly influence its workforce to promote a safety culture within the organization, Descon Engineering AUH-HSE organized brainstorming seminars involving execution Managers and Engineers. Open discussions, group activities and exercises were the highlight of the seminars. Medical Evacuation Drill at IGD Project A medical evacuation drill was arranged and carried out at the IGD work site to spread awareness on how to rescue an injured person from an elevated work area. Site paramedics, first aiders and HSE staff participated in the drill. Environmental Drill An environmental drill was conducted by Daewoo RRE Project. The purpose of the drill was to identify the reasons of the hydraulic oil leakage while it was being shifted from store to workshop. Spill prevention and site cleanup was practically demonstrated during the drill. Housekeeping Campaign A housekeeping campaign was conducted by AMW-HSE.The purpose of the campaign was to highlight the importance of UAE DESCON NEWS | SUMMER 2012 19 Borouge P3A Project Established in 1998, Borouge is a joint venture between the Abu Dhabi National Oil Company (ADNOC) and Austria based Borealis. Having tripled its annual production capacity to 2 million tons in 2010, Borouge will produce an additional 2.5 million tons annually by mid 2014, creating the world's largest Integrated Polyolefins Plant. Previously, Borouge was involved in manufacturing Borstar-based Polyolefin. With this innovative approach in plastic solutions, they provide material solutions for pipe systems, communication and power cables, automotive as well as advanced packaging markets. In June 2010, a major EPC LTSK contract was awarded to a Joint Venture between Tecnimont (Maire Tecnimont Group) and Samsung Engineering to carry out construction work on the Borouge 3 Expansion Project in Ruwais Industrial area, Abu Dhabi. In April 2011, Descon was awarded mechanical works on the P3A Project based on Descon's impressive track record that existed between Descon and Borouge. Descon commenced steel structure erection works with a prime focus on the interconnecting pipe and process pipe racks. As the name suggests, these massive pipe racks will carry various fluids during the numerous processes of polymerization, purification, product handling and storage units. Erection of the main interconnecting pipe rack is complete and has been handed over for piping erection. Structure works are now progressing towards the steel structure buildings with a major highlight of two 173 m high purge bin steel structure buildings of 1,500 tons each in the polymerization areas. Piping, fabrication, erection works are on full speed on the interconnecting and main process pipe racks & associated scaffolding and are progressing on schedule. Pre-fabricated 20 DESCON NEWS | SUMMER 2012 Syed Qaiser Naqvi spools and supports are continuously being transported to and from the workshop and are offloaded in Descon's lay down area. A dedicated tower crane has been erected to address the 197,000 sq. meters of painting and 153,000 sq. meters of surface preparation. A separate fabrication workshop for fabrication works of 106,000 dia-inches has also been erected. The heart of the polyolefin polymerization process comprises of the gas phase reactor and the loop reactors. The deliveries of these heavy lifts equipment have already commenced. The first heavy lift of the GPR weighing 455T was successfully completed within four hours utilizing Demag, the 1,250 tons crane along with the 450 tons tailing crane. Apart from the heavy lifts, Descon's equipment erection scope includes 1,200 static equipment, 108 rotary equipment packages, 32 silos and 42 transformers. The project comprises of around 4.3 million man-hours and Descon has successfully completed half a million man-hours without any LTI. UAE FFCEL Wind Power Project Ammad Hassan (Corporate E&P) Descon starts the First Wind Power Project in Pakistan “Descon is proud to have initiated Pakistan's first commercial IPP Wind Power Project in Jhimpir, Sindh.This 50 MW project for FFC Energy Ltd. called on Descon's expert leadership in Engineering, Procurement and Construction to make this eco-friendly initiative a success. To promote indigenization in the wind farm field, Descon has established the first wind tower manufacturing facility in Pakistan. With over 3 decades of experience as industry leaders in providing innovative solutions, Descon welcomes green energy in Pakistan.” Cover Story DESCON NEWS | SUMMER 2012 21 Winds of Change … for a Green Future Descon makes the nation proud by commencing the first Independent Wind Power Project in Jhimpir, Sindh. This is the beginning of a green power revolution in Pakistan. The 50 MW project namely FFC Energy Ltd is an endeavor of Fauji Fertilizer Company Limited. Fauji Fertilizer Company Limited being one of the most progressive industrial groups has once again taken a lead in venturing and pioneering as a developer in the Green Energy Field. The proposed wind farm site is located in the south-eastern part of Pakistan between Hyderabad and Karachi, approximately 100 km inland from the coast in a semi-desert area. The nearest settlements are Jhimpir (2.5 km southeast) and Nooriabad (22 km northwest). This unique green power project promises to be environment friendly, with zero-carbon emissions, powering the nation towards a greener tomorrow. Pakistan is a country with tremendous potential in the energy resources. It is not only blessed with the natural energy resources like Hydro Power and Natural Gas, but also with thousands of Mega Watt potential for Wind Power Projects. It has a coastline of 1,050 km out of which only the potential of 250 km Sindh coastline has been evaluated. Wind energy and power transmission technologies are rapidly evolving to accommodate the impressive growth of wind power. The wind corridor in which the FFCEL Project is being established carries a massive potential of energy production owing to conditions feasible for power generation. Descon with its 3 decades' experience is the only Pakistani company who has the specialized resources to undertake such a unique project. Wind energy projects are a blend of modern technology and robust engineering. The award of this project has strategically placed Descon as a leader in the development I feel honored to be a part of the team executing the first ever Wind Power Project in Pakistan which will contribute to a sizeable quantum of electricity to the national grid. We fully recognize that the success of the project is not only a matter of strategic importance for the company, but it shall also boost up the confidence of many other investors. We are the beginners in Pakistan and by Allah Almighty's Grace, hard work, dedication of all stakeholders and the project team, we are all set to be the leading conglomerate dealing in the future Wind Energy business. Faisal Iftikhar Project Manager, Wind Energy Projects 22 DESCON NEWS | SUMMER 2012 of Green Energy in Pakistan. Descon, as an EPC is providing services from project management to engineering and construction, working with the same stringent standards which are the hallmarks of its workmanship. Descon teamed up with Nordex Singapore Equipment Pvt. Ltd (subsidiary of Nordex Aktiengesellshaft) for the Engineering, Procurement and Construction of this 50 MW Wind Power Project. The contract for this project was signed with the owner, M/s FFC Energy Limited on February 27, 2010. Our scope of work included civil works, fabrication of 33 towers, EPC of 20/132kV substation and installation of towers and nacelles. Moving the turbines from the port to the site was a challenge. Therefore a comprehensive transportation plan was devised to move the complete set at the installation site consisting of three rotor blades and one nacelle on multi-axle hydraulic trailers, Cover Story hub on low bed trailer and containers on flat bed trailers. A safety plan was also devised to transport the 40 m long blade. The equipment and rigging gears were certified by the third party. A comprehensive, delivery inspection was carried out by QA&QC to scrutinize damages and irregularities during onshore and offshore handling. The consignment of parts was placed according to the stacking plan at Port Qasim, so that the components could be delivered as per the SEP (Site Erection Plan). The purchase of Liebherr LR-1750 crawler crane was a strategic move. Liebherr is the world's leading brand when it comes to cranes. Descon acquired this crane in SL Configuration perfectly equipped for the erection of wind turbines. LR-1750 is equipped with state-of-the-art electronic control systems, monitoring screens, wind speed indicators and radio transceivers for communication. Cover Story BA Management and site team was enthusiastic while entering into a new business horizon of Alternate Energy. Good home work, well-coordinated efforts, valuable support from all BSDs and courageous and proactive approach of the team paved the way for timely and successful completion of the project. However, we believe that 'Success is a journey, not a destination'; therefore, all best practices and lessons learnt will be exercised on all upcoming projects to improve our norms and profitability. Shakeel Ghani Manager Projects, DC&S DESCON NEWS | SUMMER 2012 23 The crane with a boom length of 105m was rigged in wind power configuration bearing a load capacity of 95 tons. Experts from both Liebherr and DEL carried out the first heavy lift under their supervision. It was the major capital acquisition by Descon with regards to this project (FFC Wind Turbine). On January 21, 2012 Descon performed the first lift of 1.5 MW wind turbine. This 1.5 MW Wind Turbine is supplied by Nordex Germany and all the other equipment including the tubular towers is manufactured by Descon. This localization in manufacturing of Wind Towers has also made Descon the first to embark in the field of Wind Energy equipment manufacturing in Pakistan. This project is the first of its kind in Pakistan and shall greatly contribute to the development of wind industry in the country where a substantial growth is expected in the coming future. Keeping in view the huge opportunity available in this sector we are determined to maintain a strong presence and lend our engineering expertise to upcoming investors. This continued commitment has resulted in the signing of EPC contracts with other major investors like Fauji Foundation, Yunus Energy, Gul Ahmed Energy and Metro Wind Power. Equipment, Plant & Heavy Lift Services Dept. took a lead role in Wind Power Project by initiating a look ahead program on the logistics, transportation, safety, erection and execution of heavy lifts. A training workshop was arranged in April, 2011 for different stakeholders. Our team took the responsibility of off-loading the consignment and transporting it to the site through a Total Logistics & Transportation Solution. This venture was partnered with Mr. Stephen Dickel, representing Liebherr, Germany. I, being the lead feel honoured to execute the first lift of Wind Turbine. Mushtaq Ahmed I/C Heavy Lift Services, DC&S Keeping in view the production of wind towers at KMW, a comprehensive plan was developed. This included complete revamping of the site both in terms of infrastructure and equipment. Dual production line with column and boom welding machines in addition to CNC plate cutting and rolling machines were introduced along with separate grit blasting and painting sheds. We feel proud to be a part of this new endeavor for the company as well as the country towards a Green future. Javaid Khan Resident Manager, KMW 24 DESCON NEWS | SUMMER 2012 Cover Story Kuwait Highlights KCC 5500 TPD Line - II Expansion Project The year 2011 ended with the remarkable achievement of 1.15 million safe man-hours through the combined efforts of all project team members. Safety training at induction, site safety training, daily toolbox talks, management safety audits and HSE observation reports including, but not limited, to personal protective equipment, fire safety, unsafe acts and conditions were strictly followed in every area for the preventive measures. It is worth mentioning that various businesses of Descon performed as one team on the KCC project. Be it Hamriyah Manufacturing Works, HR, PP&A, Commercial, CMD, QA&QC, HSE, Finance, E&P or AUH office, there was always strong coordination and team work in all aspects of the project lifecycle. Recognition must be given to Mr. Abdul Shakoor Shaheen from PPMS, who was instrumental in providing timely cautions and raising flags during the project execution. Pervaiz Iqbal which has resulted in significant variance in originally planned schedule. Revised scope comprises of more than 15,000 tons of steel structure and plate work in addition to a supply of approximately 25,000 m2 of wall-cladding and roofing sheets. Approximately 12,000 tons of fabricated material has been delivered at site. Fabrication activities are expected to be completed by the end of June 2012. In the erection phase, more than 10,000 tons of steel structure and equipment/plate work was erected. Specialized activities, including Refractory and Insulation are being executed through local subcontractors approved by the Kuwait Cement Company. Electrical & Instrumentation activities have been accelerated to match the completion schedule of the pyroline by enhancing the cable tray and cable laying activities. The Pre-heater, 185 meter tall, the tallest ever structure erected by Descon comprising of eight floors, is the most critical area of the project to produce clinker. The erection activities have reached the seventh floor. Other areas including raw mill, kiln, CF silo, DLD tank, ESP, clinker cooler, EGC are also progressing in specific sub areas. The fabrication and construction phases of the project are going at full swing both at HMW and in Kuwait. The project comprises of approximately 0.55 million man-hours of fabrication and 2.7 million man-hours of erection. It is planned to start pyroline by May 2012. The erection of balance activities including material handling areas will be completed by the end of September 2012. A major percentage of different nationalities, has also been deployed in those areas which are directly executed by Descon. Fabrication in Phase-I has increased substantially through gradual issuance of a new scope in the material handling area KBA DESCON NEWS | SUMMER 2012 25 Olayan Descon Industrial Company Olay an Des co n an d Sau d i A ramco Strategic Partnership Olayan Descon is in communication with Saudi Aramco for a strategic partnership to design, procure and fabricate air coolers within the Kingdom of Saudi Arabia. A formal understanding has been signed between Olayan Descon and Saudi Aramco to promote local industry and localize the manufacturing of air coolers. As part of this partnership, Olayan Descon shall develop the capabilities for this type of work and Saudi Aramco will ensure a substantial amount of jobs to be executed by Olayan Descon. This will be an excellent opportunity to enhance our portfolio and increase our business volume. Samref Clean Fuel Project In a bid to meet US environmental regulations by 2013, Saudi Aramco has planned to upgrade all of its refineries. The new regulations make it compulsory for refiners to reduce the sulphur content of the gasoline produced. Olayan Descon has been awarded manufacturing of thirteen types of equipment for the upgrade of Samref (Saudi Aramco & Mobil Refinery). Of these, two have already been delivered. Linde AG - Cold Box Revamp Project at Petrokemya Cold Box Revamp Project at Sabic, Petrokemya Plant located in Jubail, Saudi Arabia includes structure detail engineering, fabrication, civil work pertaining to new cold box, mechanical erection works on site including system tie-ins during the shutdown in May 2012. Currently site works and shop 26 DESCON NEWS | SUMMER 2012 Waqar Ahmad fabrication of SIP (Structure for Infrastructure Piping) is in progress and within schedule. Strong coordination with the Linde team and successful completion of the project will ensure our success in the KSA market. Sasref - Shutdown 2012 We have a five year contract with Sasref (Saudi Aramco Shell Refinery), Jubail KSA, for their planned shutdown jobs till 2013. In January-February 2012, they had planned turnarounds on their two units and Olayan Descon successfully completed and received recognition from the client. Samref - Shutdown 2013 Samref, located at Yanbu, has planned a major turnaround in February-March 2013. We have been shortlisted to participate in five different packages. In 2010, Olayan Descon successfully executed Samref’s shutdown as a major contractor and their management awarded the ‘Golden Helmet’ to Olayan Descon for successful completion and on time completion of the job. One of the packages related to FCCU shutdown submitted in December 2011 has been awarded to us, whereas the bids for the remaining four packages are under review by the client. Electrical Emergency Power Back - Up System Up- Gradation at Sabtank, KFIP Our scope of work comprises of design, engineering, construction, testing and commissioning works at ten different areas of Sabtank which are Petrokemya, Sadaf, Sharq, Ar-razi, ODICO Kemya, Ibn-zahr, Al-bayroni, Gulf farabi, S-Chem, Ibn-al-baytar. 90% EDP (Engineering Design Package) has been submitted to the client for review. Soil investigation for civil design has been completed and shop drawings for UPS and GIS have been submitted to the client for approval. Vendor visits are scheduled with the client and procurement for long delivery items is in progress. The final project completion and complete hand over is by end August 2012. while the heat exchangers are being manufactured at the Jubail Workshop. The delivery is expected in August 2012. Karan Gas Project, Khursaniyah The project scope includes field erection of piping for a Gas Processing Plant. The project has been progressing well and demobilization is underway. This project marks our relationship with Saudi Aramco and Hyundai Engineering & Construction Company. Heat Exchanger SADAF, SABIC Bulk Liquid Chemical Terminal Project, JCP, Jubail The EPC project to build a 65,000 m3 Storage Facility at Jubail Commercial Port, Jubail, is under progress. This project marks our strength in building Liquid Storage Facilities on an EPC basis and is opening avenues in this area. Olayan Descon has recently delivered heat exchanger and pressure vessel job for SADAF, a SABIC affiliate company. Due to the critical nature of the job and tight delivery schedule, this job was executed in close coordination and involvement of the client's team at all stages, i.e. design, procurement, fabrication, testing and delivery. This job has further strengthened our business relationship with our valued client. Olayan Descon's New Office Building Storage Tanks, Hail Power Plant Expansion Project Olayan Descon is building 2 x 20,000 M3 tanks for Saudi Electricity Company for Hail Power Plant Expansion Project. This project is being executed on behalf of Al-Fanar Construction Company and is expected to be completed by September 2012. This is our first storage tanks job for Saudi Electricity Company. Olayan Descon's new facility comprises of office building, storage tanks workshop and E&I workshop. The office building includes a capacity of 150 personnel and covers an area of 945 square metre. Construction work is on schedule. The expected completion date is June 2012. Pressure Vessels, Rabigh Power Plant No. 2 ODICO is manufacturing pressure vessels and heat exchangers for Rabigh Power Plant No 2. The client is Doosan Heavy Industries, Korea and Saudi Electricity is the plant owner. Project execution is progressing on schedule. The pressure vessels are being manufactured at our Yanbu Workshop, ODICO DESCON NEWS | SUMMER 2012 27 Presson Descon International (Pvt) Ltd. Second Global HR Excellence Award 2011 PDIL was awarded the Global HR Excellence Award 2011 for the second consecutive year by Global Media Links and Business Milestones in collaboration with International Human Resource Information Management, a US based global certification and standard monitoring body. The Global HR Excellence Awards recognize organizations which have made significant contributions to Human Resource in Pakistan. Syed Fareeduddin Habib Rahi limestone gas reservoir. A three phase separator is required at the upstream of gas compression facility. PPL awarded the job for the complete design, manufacturing and supply of a skid mounted three phase separator. The project was awarded in November 2011 and is scheduled to be delivered at site within 26 weeks. Schlumberger Issues Basic Engineering Services LOI for Its Early Production Facility in Sudan Apart from the Global HR Excellence Award, PDIL was also awarded for its focus and excellence in Training and Development Strategy. The Senior Minister for Commerce, Mr. Makhdoom Ameen Fahim and Chairman Intellectual Property Organization, Mr. Hameedullah Jan, presented the awards to the winners in a ceremony held on October 21, 2011 at Avari Towers, Karachi. Schlumberger, the leading oilfield services provider, intends to setup an Early Production Facility in Sudan. For this purpose, it awarded the Basic Engineering Study to PDIL. This study will involve process simulation, generation of plot plans, creating a fire protection philosophy, hazardous area classification and equipment design basis, datasheets and corresponding specifications. The forum greatly appreciated the effective HR strategies of PDIL that have resulted in a positive and efficient company culture and performance. SPE- PAPG- Annual Technical Conference - 2011 Pakistan Petroleum Ltd Phase- 3 Separator Pakistan Petroleum Ltd. is setting up a gas compression facility with an anticipated delivery of 30 mmscfd gas at the Sui 28 DESCON NEWS | SUMMER 2012 The Annual Technical Conference 2011 was held on November 21 and 22 at Serena Hotel in Islamabad. The event was organized by the Society of Petroleum Engineers (SPE) and the Pakistan Association of Petroleum Geoscientists (PAPG). The Conference was attended by the well-known names of the Oil & Gas industry. Mr. M. Aijaz Choudhry, the Secretary PDIL of Petroleum and Natural Resources was the inaugurating chief guest at the two-day event PDIL had the honor of hosting the first day’s evening tea of the conference. PDIL and its EPCC capabilities were also highlighted through the sponsored advertisement in the Conference's Souvenir Publication. The Society of Petroleum Engineers, Pakistan Chapter presented PDIL with a shield due to its corporate membership status for the year. The efforts were highly appreciated by the management committee of ATC-2011. HR Development Activities To develop employee excellence and inspiration, internal trainings named 'Personal Excellence' and 'Lead by Inspiration' were conducted by internal trainers to maximize PDIL's internal training resources. External training sessions were arranged on PPRA rules, PMP Certification Exam Preparation and Advanced Piping Design. Birthday parties for company employees were arranged by HCMD (Human Capital Management Department). Warm wishes and feelings were shared by many on this occasion. PDIL DESCON NEWS | SUMMER 2012 29 Descon Chemicals Limited DCH Expands Its Paper Chemicals Sizing Products Range Descon Chemicals Limited introduced two new variants in its line of Fortified Rosin products. FR products are generally used as sizing agents for the wet-end process of paper manufacturing. The use of Fortified Rosin for sizing purposes is a conventional and widely utilized method for treating paper across Pakistan. De-Size 500 and De-Sol 300 are the two latest additions to Descon's Fortified Rosin product line and provide enhanced versions of the products already available in the market for the same process. De-Size 500, an Anionic Rosin is an improved form of FR, modified and sponified, which provides greater economy per unit consumption as compared to alternate brands available in the market. De-Size 500, also has the added advantage of working better on paper process machinery; reducing service costs, minimizing machine breaks and consequently leading to improved machine life. De-Size 500 serves the added advantage of being readily soluble at room temperature and therefore not requiring any pre-process heating or treatment. Currently, this product is available in conventional packaging of 100 kg drums and is recommended for sizing purposes for craft, paper and board machines. 30 DESCON NEWS | SUMMER 2012 Rafay Shahid DeSol 300 is a light viscous liquid emulsion, used as a PseudoNeutral Sizing solution for the paper and board manufacturing industry, particularly used for sizing, writing and printing paper. DeSol has a higher pH value (6.25 - 6.50), as compared to Delta Size and DeSize. An impressive factor about DeSol 300 is that, unlike other brands used for the same purpose, it can either be used as such or in diluted form with Alum (Feric/ Non-Feric/PAC) to attain the desired COBB value with back water. This characteristic provides users of DeSol the advantage of reducing their overall Alum consumption and thereby minimizing manufacturing costs. Just as Desize, DeSol is also soluble at room temperature and is machine friendly, causing least possible wear and tear. 'Your Solutions, Our Chemicals', Descon Chemical's slogan, highlights the integrated relationship between our customers and our products.This relationship is at the core of the services we offer; we at Descon Chemicals are committed to provide our customers: quality, innovation and satisfaction. “We don’t sell a commodity, we sell a product. Our actions on how we sell it makes it either a commodity or a specialty.” DCH Descon Oxychem Limited Rafay Shahid PRODUCT RANGE INDUSTRIAL APPLICATION STANDARD TEXTILE PAPER CONCENTRATION (%) 60 50 35 30 DOLOX DOLOX DOLOX DOLOX 60 50 35 30 TEXTOX TEXTOX 60 50 PRINTOX PRINTOX 60 50 FOOD FOODOX ASEPTIC ASEPTOX 35 35 DOL Brand Development Takes Centre Stage True to its vision of becoming the ‘Leading Chemical Solutions Provider to Industry Worldwide’, Descon Oxychem Limited took another stride in establishing itself as a global manufacturer of Hydrogen Peroxide, by successfully implementing its branding strategy to create and sustain brand value. A four pronged strategy has been adopted to ensure Descon Oxychem creates visibility for itself and its product range, both nationally and globally. With the successful launch of the Customer Care Centre, this year saw the induction of DOL's Branded Tanker Fleet, the successful setup of DOL Bulk Solutions at three big volume customers and the launch of DOL's Brand Names. DOL's Tanker Fleet currently comprises of tankers with 20 metric tons and 25 metric tons capacities, installed with state-of-the-art tracking systems, operated by a dedicated team specifically trained in safety and precautionary regulations for hazardous materials. Our tankers have been branded with Descon's logo, corporate colors and Customer Care Centre's contact details clearly visible for customers in order to reach us easily. The branded tankers serve as an excellent channel for promoting Descon's name and image, since our fleet operates across Pakistan 24/7, rendering wide exposure wherever they travel. all facilities. DOL's established presence at these locations pays testament to the fact that these customers are investing in a brand that matches their highest standards of quality and excellence. This fiscal year also saw the launch of the much anticipated DOL Brands. It was a firm belief of the Marketing team that to distinguish ourselves from other hydrogen peroxide manufacturers, we would have to market ourselves in a more unique way as opposed to marketing the generic chemical name. Hence we focused on marketing the brand; one that epitomizes quality, backed by technical and customer support excellence. Descon Oxychem is now proud to have ten different product variants, across four separate concentrations in five different grades, making us the only manufacturer of hydrogen peroxide in Pakistan to provide such an extensive line of product offerings. In the time to follow, we aim to build upon the value of creation through our branding strategy and to sustain brand equity by ensuring that the highest standards of quality are backed with superior technical support and a determination to provide the best services possible. DOL Bulk Solutions provide a storage facility to house large quantities of hydrogen peroxide at the customer's premises. Descon Oxychem has thus far successfully installed bulk tanks at customer bases across Pakistan, including Sapphire Finishing Mills Lahore, Interloop Limited Faisalabad and International Textile Limited, three of the largest export units operating within Pakistan. These specially designed tanks also carry Descon's logo, corporate colors and are fully operational at DOL DESCON NEWS | SUMMER 2012 31 Descon Power Solutions We Offer You Tomorrow The Pakistani industrial sector is at a take-off stage with companies having to compete globally, all the while dealing with an ever-increasing need of power. To help you achieve your goals, we adopt a global approach and put it in practice. We, at Descon Power Solutions know that if a company is to succeed it needs an uninterrupted source of electricity. Local Strength, Global Partnership, Successful Solutions DPS brings the cutting edge German technology with MWM gensets. DPS, the local face of MWM, provides a comprehensive range of flexible integrated customized solutions. MWM GmbH is one of the world's leading suppliers of highly efficient and eco-friendly energy generation plants with an electrical power output range from 400 kW up to 4300 kW. Based in Germany, it has an experience of more than 140 years in the development and optimisation of 32 DESCON NEWS | SUMMER 2012 Shayan Hundal combustion engines for natural gas, special gases (bio gas, syn gas, coal mine gas, sewage gas) and diesel fuel. DPS Powers a Greener Tomorrow The MWM engines maximize performance, while the extensive range of environmental solutions enable us to supply the cleanest power generators. MWM has been able to reduce the environmental impact of power generators by integrating the environmental impact analysis into the design process, so that all the products have minimal harm to the environment thus reducing CO2 emissions. 12 MW Agar Textiles DPS has been awarded with 12 MW Agar Textiles New Captive Power Plant Project. DPS will supply six units of MWM's natural gas genset model TCG 2020 V20. The project is located at Kotri and the power generated will be supplied to the Hyderabad Electric Supply Company . DPS Opening New Horizons… Descon Power Solutions has acquired Operation & Maintenance (O&M) for Rousch Power Plant Limited (RPPL), a 450 MW Combined Cycle Project. The O&M contract is effective from December, 2011 till December 2016. With the implementation of the O&M contract, Descon assumes the first ever O&M role of a modern medium size CCGT Power Plant, which opens new horizons for Descon Power Solutions. Since March 31, 1996, an Irish company ESB International (ESBI) was taking care of O&M of RPPL. The O&M agreement was amended on September 23, 2003. RPPL entered into the O&M contract arrangement with a consortium of ESBI and DPS effective from December 01, 2011. As per the new contract, DPS is responsible for procurement, local staffing, finance and colony maintenance. ESBI, as the consortium leader shall be handling all technical matters relating to the plant's O&M activities along with the support of DPS members. Shayan Hundal and compressors during the first half of the year 2012. This will be carried out by Siemens AG Germany, the OEM of gas turbines. Opportunities The O&M Agreement is a win-win for both parties, ESBI and DPS. DPS got partnership of a world-class O&M service provider that will help improve its standing in the O&M market. ESBI has had its contract renewed and acquired more business opportunities in Pakistan. In this regard, a considerable number of ESBI employees have been moved to DPS on the same employment terms and conditions; leading to a mutually beneficial union of both parties. Gas turbines have already completed more than 100,000 equivalent operations hours and to ensure the highest level of performance over the next 100,000 operating hours, the company has planned Life Time Extension measures, which include replacement of all major components of gas turbines DPS A family ceremonial dinner for DPS-RPP employees was arranged followed by a communication meeting in which the DPS-RPP team presented the working methodology and the way forward to run the contract. The CEO of RPPL, Mr. Fazal Hussain Asim and the O&M Manager of ESBI, Mr. Dave Shephard were also invited to grace the occasion. DESCON NEWS | SUMMER 2012 33 Equipment and Plant Zahak Jamal proven track record in the development of wind farms in several countries across the globe. Revamp of American Hoist 11320 It is a matter of great pride that the Central Maintenance Shop, Lahore, has completed the refurbishment of the 450 tons crane: American Hoist 11320. A team of highly skilled technicians did the engine overhauling, restoring the hoisting mechanism, electrical rewiring, denting and painting of the crane. The crane was then successfully load tested on March 05, 2012. Specialized Trainings & Dossiers The department has successfully carried out the following special training sessions in coordination with DC&S and MDC: Training of incumbents on LR-1750 in windmill configuration by Mr. Stephen Dickel from Liebherr, Germany, who visited Jhimpir from December 17 to 23, 2011. Maintenance Management Training session for management personnel. Transportation and logistics training for top management “Energy and persistence conquer all things.” Following dossiers regarding E&P training and execution were also issued : Benjamin Franklin Over the years, the Equipment and Plant Department has established itself as a specialist in Heavy Lifts and Services (HLS). With strategic assets such as Gottwald AK-912 (1,200 tons) and Liebherr LR-1750 (750 tons), we have developed a competitive edge over others in the region. The book named Wind Turbine Transpor tation and Erection addresses the typical aspects of wind turbine installation procedures, starting from logistics of the equipment to final erection at site. Rigging & Heavy Lifts is a comprehensive handbook which serves as a guide for young engineers entering in the field of rigging and heavy lifts. Wind Turbine Project The E&P Department is proud to accomplish the successful erection of the first ever locally manufactured wind turbines in Pakistan.The Jhimpir Wind Farm consists of 33 wind turbine generators each capable of generating 1.5 MW of power giving the farm a total capacity of 49.5 MW. It will be connected to Hyderabad grid at the high level transmission line of 132 kV to furnish electricity demands for the region. On January 25, 2012, a team of E&P professionals successfully erected the first wind turbine with the help of specialized equipment. The Liebherr LR-1750, which has a maximum capacity of 750 tons, was especially procured considering its 34 DESCON NEWS | SUMMER 2012 E&P Human Resource & Administration GETP - Batch 25 December 01, 2011 - January 24, 2012 The 25th batch of GETP trainees was welcomed into the company on December 01, 2011. These 32 bright young engineers were hired from a pool of 7,559 applicants through a robust selection process conducted by the Corporate R&S team.The program was spread over eight weeks and included classroom training on various BA/BSD business processes, PMS modules and soft skills, besides site visits to Descon Oxychem and Lahore Manufacturing Works. A total of 40 'subject matter experts' from various BAs and BSDs conducted the actual training comprising of sixty topics. The dedication of this faculty contributed significantly towards the effectiveness of the program. Aamir Iqbal Salient Features of GETP- 25 A total of 9,000 training man-hours were recorded. 60 topics were delivered by various trainers. 40 trainers rendered their services for delivering various topics. 2 site visits were arranged (LMW and DOL). 12 days were dedicated towards learning of PMS computer-based training modules. Every training day started with a brief motivational clip and discussion on the same. Training effectiveness was checked through feedback and quizzes at the end of each topic. Upon completion of the GETP, a graduation ceremony was held on the evening of January 24. Mir Anwaar-ul-Haq, Mechanical Engineer, UAE BA, was declared ‘Trainee of the Batch’. The highlight of the event was an inspiring speech by the chief guest, Mr. Abdul Razak Dawood, in which he traced the history of Descon's evolution from a small office in Wapda House in 1977 up to the present time and envisioned the role these young engineers would play in the years to come. All trainee engineers have now been assigned to various local and overseas BAs/BSDs, in line with the company's manpower deployment plan. HRD&A DESCON NEWS | SUMMER 2012 35 Descon Institute of Technical Training “The areas we will be focusing on would be improvement and accreditation of DITT courses from external agencies, ensuring international standard and acquiring capability to enroll higher numbers of students.” Tahir Majeed, Principal DITT Contract Signing with PSDF Descon Engineering Ltd. signed a contract with the Punjab Skill Development Fund on November 24, 2011. This initiative was for the training of 1,035 persons from Bahawalpur, Bahawalnagar, Lodhran and Muzaffargarh districts. Uzma Nadia PSDF is a non-profit organization funded by Government of Punjab and Department for International Development UK, and is funding a Skills Development Program for the underprivileged population of these four districts of Southern Punjab. PSDF's Hunar Mela / Skill Fair on December 28, 2011 PSDF launched the program by arranging a Hunar Mela in Bahawalpur from December 29 to 31, 2011. The Chief Minister of Punjab, Mr. Shahbaz Sharif, was the guest of honour Ali Sarfraz CEO, PSDF, (centre-L) & Mr. Asim Aziz, Head MDC (centre-R) during the contract signing ceremony 36 DESCON NEWS | SUMMER 2012 HRD&A at this mela, in which selected training institutions, including DITT had set up stalls to explain various free courses being offered to the local youth. There was a large turnout of potential trainees, who were excited and inquisitive regarding details about DITT courses offerings. to more than 5,000 students within ten years' time. An area of 10 acres has been allocated for this future expansion plan. Welder Qualification Tests Quality manpower is the key to success for any project. DITT has provided valuable support by conducting the Welder Qualification Test of over 600 welders for Descon's overseas projects since August 2011. Joining of New Team Members We welcome the following new staff members who joined DITT recently: Tahir Majeed, Principal Col (R) Manzoor Hussain, Consultant M. Imran, Junior Instructor Electrical Giving a New Look to DITT Campus M. Nadeem, Instructor Pipe and General Fitter DITT was originally established to train the workforce for the company's own expected and ongoing projects. Now, it is envisioned to expand it in a broader way. The Chairman aspires to impart skills’ training to as many as possible of the unemployed and unskilled youth of the country. Accordingly, it is planned to enhance the capacity of the institute from 400 trainees to 1,000 in the next year and then progressively Tahir Majeed HRD&A Col (R) Manzoor Hussain M. Imran M. Nadeem Jahanzeb Sharif, Instructor Safety Zafar Nawaz, Junior Instructor Welding Iftikhar Khan, Demonstrator Millwright Jahanzeb Sharif Zafar Nawaz Iftikhar Khan DESCON NEWS | SUMMER 2012 37 Project Personnel and Administration In order to provide the best services to seek excellence in all business areas, PP&A department is always up to new innovations and progression. Nofil Zaheer projects. This has been made possible due to the commendable efforts of the team members of the department. Implementation of CMPS New Counter System The department has introduced a new counter system within the department to make personnel handling more efficient. In this regard, three new counter systems have been designed and built to deal with different business areas, depending on the work load. Mobilization in Last Six Months In the last six months, the department has mobilized almost 4,000 personnel to various UAE and Qatar shutdowns and CMPS, an online web application program for the complete monitoring of Descon's manpower and resources, has already been implemented in Qatar and UAE. Now it is in the implementation phase in Kingdom of Saudi Arabia. Our Strength Our strength is our staff. We welcome the following staff members. Khawaja Nadeem Afzal : Lead, PP&A Department Burshra Riaz : Junior Executive Hasan Iqbal : Junior Executive Team Building Sessions Different sessions have been conducted in the department by In-charges to raise the team morale and to bring all team members in unison to combine their efforts and achieve milestone targets. 38 DESCON NEWS | SUMMER 2012 HRD&A Information and Communication Technology Note From CIO It gives me great pleasure to communicate that the SAP Project Phase 2 of SAP Program went live on February 01, 2012. Like any major SAP implementation, this project posed its own unique blend of challenges and opportunities. SAP is a market leader in enterprise solutions and will enable Descon to adopt industry’s best practices in all facets of organizational management tools, which include project management, financial management, human resources management, supply chain management, sales & distribution, plant maintenance and quality assurance management. A change of such magnitude might be uncomforting or unsettling at the start, however, this is typical; we believe that with honest commitment and firmness of the execution team, success is certain. the go-live.There will be teething issues. We have to collectively facilitate, resolve and move beyond them. Finally, I am thankful to the entire project EDGE team (Descon's SAP team, SMEs and end users) for its sustained and unflinching dedication during turbulent & testing times and seeing them through successfully. Also a note of appreciation is due to the senior management of Descon who remained committed and have wholeheartedly supported us in every possible way. Wishing you a very happy startup and a smooth transition to SAP. Syed Aftab Afzal No matter how deeply embedded or user-friendly the legacy systems might have been in the past, the real value of an ERP lies in its enterprise-wide integration, which helps achieve a greater focus on analytics, quick decision making, robust and accurate business information, improved financial reporting and simple easy-to-use interfaces. SAP will empower the workforce leading to eventual devolution of decision making. Real value will become visible a couple of months after ICT DESCON NEWS | SUMMER 2012 39 What Happens Next Achievements After the go-live, business users are requested to use SAP system in order to perform business functions. Our objective is to swiftly adopt new system in our business lives to avoid additional cost of legacy applications. As they will now not only become redundant, but will also require additional cost for their maintenance. Descon's ICT has put another feather in its cap by upgrading SAP ECC 6.0 from EHP4 to EHP5. This milestone will lead to enhanced functionality within the SAP system. Despite extensive trainings of the staff, some problems are bound to arise, as users familiarize themselves with the new system. A helpdesk has been established to assist users with such issues. All are requested to contact the Key Business Users for SAP support related issues. Successful implementation of the support desk through a solution manager as per ASAP methodology with escalation management and mobile alerts gives an edge to Descon among other SAP implemented companies in Pakistan. Another breakthrough has been the implementation of Mobile Sap Solution to facilitate the management approving SAP workflows (PR/PO) through blackberry and the web. This is an initiative to achieve ICT’s vision of “right information to the right person at the right time.” ICT’s team at the launch of SAP Go-Live Improvement of Network’s Infrastructure To provide secure connectivity, Virtual Private Network (VPN) has been established between main locations through Wide Area Network (WAN). The network infrastructure has also been redesigned to provide secure and reliable access to users with central management. For cost reduction, server consolidation has been conducted at DHQ data centers. The NC Section has also established facilities like audio conferencing and online monitoring through LCDs. 40 DESCON NEWS | SUMMER 2012 ICT Information Systems Improvement The ICT Information Systems Section has managed to integrate GDMS legacy system with SAP Project System (PS). This would enable the end-users to avoid redundant efforts in managing information in multiple systems. Similarly, it would also reduce chances of data miss-match across the systems. Fingerprint reader machines (biometric) have also been integrated to provide real-time attendance data to the SAP HCM module. The Information Systems Section has played a major role in the data migration activity of SAP. ICT Interworld Travels Rabya Sheikh Strengthening Relationship with PIA IWT strengthens its relationship with PIA by being nominated as one of the Top Ten PIA Agents. This award reinforces Descon's commitment to promote our national carrier. Training Session Interworld Receives Best Seller Award Keeping up the tradition of being chosen as one of the top travel solution providers, Interworld was again this year, nominated as the Best Agent for 2011. Mr. Sohail Abbas, GM Interworld Travels, received the award from Mr. Zafar Ahmad, GM Sales, Amadeus, in a ceremony held at PC, Lahore. The ceremony ended with a sumptuous dinner and musical evening where the participants got a chance to converse with other agencies and stakeholders. A training session was conducted at DHQ by Mr. Waseem Ahmed, GM Sales, Amadeus. The focus of the training was to disseminate awareness on the usage of Amadeus, a leading transaction processor and provider of advanced technology solutions for the travel and tourism industry. The features offered by this user-friendly program were explained through an interesting video, detailed presentation and later discussed on one-to-one basis by the consultant himself. The training was attended by the administration and secretarial staff across board. The session ended with tea hosted by DEL administration. Iman Clinches Subh- e- Nau Tennis Title Iman Qureshi, a young talent playing under the sponsorship of Descon beats Pakistan's No. 1, Saba Aziz to win the Subhe-Nau National Ladies Championship. She displayed brilliant ground strokes to overcome a stronger opponent. This is her second National title, but the first time she has beaten Pakistan’s No. 1 player. Iman has been a top ranked Asian under 14 player winning trophies in Syria, Qatar and Burma. She also participated in the 11th Abu Dhabi Country Club ITF Junior Championship 2012 held between January 09 January 15, 2012. She beat Simran Kaur of India, 6-0, 6-1 and Kristina Djamalova of Uzbekistan, 6-3, 7-5. 64 players from all over the world participated in this tournament. Making its Mark with Abacus In continuation to delivering positive results, Interworld has strived for excellence by selling the highest number of tickets through Abacus, world's leading online platform for travel agencies to sell tickets of the leading airlines. The Highest Seller Award 2011 is a reflection of our ongoing commitment to facilitating customers promptly. IWT DESCON NEWS | SUMMER 2012 41 Plant Construction and Services Pioneering Construction of Coal and Biomass Power Project Descon has been awarded construction work of 6 MW Coal and Biomass-Based Power Plant at Nishat Mills Limited, which included both mechanical and electrical construction. This realization of the project is due to the confidence of Nishat Group in Descon’s engineering expertise and their mutual long term commitment, which have resulted in endeavors like D.G. Khan Cement and AES Lalpir maintenance services to name a few. Nishat Group has always been a pioneer in introducing new technologies and the initiation of this 6 MW Coal and Biomass Project is another laurel in its feats. Syed Mustafa Shah Furthermore, keeping in view technology advancements in the power sector, Descon has signed a Technology Transfer Agreement with Jinan Boiler Group to provide EPC solutions on coal and biomass-based projects. Major Turnarounds Executed FFBL ATA 2012 PARCO Turnaround 2012 OMV Sawan ATA 2012 Ongoing Long Term Maintenance Contracts Engro Polymer & Chemicals, Karachi Lotte-PPTA, Karachi Descon Engineering Limited, which has played a key role in the development of power sector in Pakistan and has executed 7,000 MW's in different contractual capacities, is proud to be a part of this project. Through its manufacturing capacity, Descon has provided general industry boilers on different fossilized and non-fossilized fuels for industries including the sugar industry. It has the privilege of being in the league of boiler manufacturers providing 200 tons per hour or higher capacities at medium and high pressures. 42 DESCON NEWS | SUMMER 2012 PC&S Quality Assurance and Quality Control At Descon, QA&QC begins from the very initial stage of project inception by development of Project Quality Plan and other documents and remains till project hand over is completed. QA&QC Human Resource Development As to-date, 453 training man-hours have been spent on a Professional Enrichment Program at DHQ. QA&QC participated in the 12th International Convention on Quality Improvement and 2nd ANQ Regional Conference. It also participated in a training program on Leadership for Quality, arranged by PIQC. Imran Jamil OHSAS 18001:2007 of UAE BA has been recertified under UKAS scheme by Moody International. Stage 2 Cer tification Audit of HMW for OHSAS 18001:2007 by TUV Nord. Achievements Completion of hydro testing of two 10 KT jet fuel storage tanks for shell at Karachi. Successful completion of the Mirfa Air Separation Unit Project at AUH encompassed critical piping works involving aluminium and cryogenic piping. Consultant, Mr. Guard Frade, trained KMW engineers for wind towers manufacturing and welding techniques. Acquisition of 'Easy Laser', a tool to carry out the sensitive and accurate measurement of wind towers' flanges. An Awareness Program on ASME Process Piping B31.3 Basics and Impact Test was carried out in UAE by Velosi. Air coolers for Litwin and Takreer successfully dispatched in November, 2011 by HMW. 3rd Party IMS internal auditor training by TUV, Middle East was held in the UAE. LMW has been involved for the first time in the erection and commissioning of partial stamped HRSG at Lotte PPTA Cogen Project. The boiler is fabricated for Daekyung Machinery & Engg Co. Ltd., Korea. LMW’s scope also includes power piping (S. Stamp). Training for ASME Sec VIII has been carried out at HMW by Mr. Amit Palit, HSB authorised team lead, Kuwait. Audits in the Last Quarter, 2011 Phased array ultrasonic, an advanced method of ultrasonic testing, is being used at IGD-5 Project. Contracts Management, E&P, BD, HR, LMW & KMW Public Buildings at Mangla Project PDIL An external audit of DIPL was carried out by SGS for IMS certification. DIPL has been certified against ISO 9001, 14001 and 18001 standards. The external surveillance audit of PDIL was successfully conducted by Moody Intl., based on the requirements of ISO 14001:2004 and OHSAS 18001:2007. QA&QC DESCON NEWS | SUMMER 2012 43 DESCON HEADQUARTERS 18 km., Ferozepur Road, Lahore 54760, Pakistan Tel: +92 42 35990034, 35805134 UAN: +92 42 111- DES-CON Fax: +92 42 3581 1005, 3581 1135 Email: descon@descon.com w w w .descon.com ENGINEERING Descon Integrated Projects Limited (DIPL) 18 km., Ferozepur Road, Lahore 54760, Pakistan Tel: +92 42 3599 0053 Fax: +92 42 3581 0867 Email: dipl@descon.com Descon Integrated Projects Limited (DIPL) 9th Floor Business Avenue, 26-A Block 6, P.E.C.H.S, Main Shahrah-e-Faisal, Karachi 75400, Pakistan Tel: +92 21 3439 1591-5 Fax: +92 21 3439 8565 Email: descon@descon.com Abu Dhabi Office - UAE (DIPL) Descon Engineering Prestige Tower, Building No. 17, Floor No. 16 MBZ (Muhammad Bin Zayed), P.O Box 46821, Abu Dhabi, UAE Tel: +971 (0) 2 553 9801 Fax: +971 (0) 2 553 980 Email: descon@emirates.net.ae Abu Dhabi - UAE (Main Office) Mussafah Industrial Area, ME-14 United Bank Limited Building, P.O.Box 46821, Abu Dhabi, UAE Tel: +971 2 555 5807 Fax: +971 2 555 5784 Email: descon@emirates.net.ae Doha - QATAR Descon Engineering Qatar LLC 2nd Floor, Al-Hitmi Village, Umm Ghuwailina P.O.Box 23364, Doha, Qatar Tel: +974 4405 4777 +974 4405 4717 Fax: +974 4405 4778 Email: qba@descon.com Abu Dhabi - UAE (City Office) Al Nowais Building, Office 302 Electra Street, Tourist Club Area Abu Dhabi, P.O.Box 46821, UAE Tel: +971 2 644 0903 Fax: +971 2 644 6786 Email: descon@emirates.net.ae Descon Institute of Technical Training 2 km., Defence Road, off 24 km., Multan Road, Lahore 53800, Pakistan Tel: +92 42 3596 6696 Fax: +92 42 3596 6687-8 Email: ditt@descon.com Mangaf - KUWAIT Descon Engineering FZE Building No. 14, Street No. 21, Block 3, Mangaf, Kuwait Tel: +965 237 304 71, 237 302 04 Fax: +965 237 301 48 Email: zuhasan@descon.com JOINT VENTURES Presson Descon International (Pvt.) Ltd 18 km., Ferozepur Road, Lahore 54760, Pakistan Tel: + 92 42 3588 0390 Fax: + 92 42 3592 3720 Email: info@pdil.com www.pdil.com POWER Olayan Descon Industrial Company P.O.Box 10108, Jubail Industrial City 31961, Kingdom of Saudi Arabia Tel: +966 (0) 3 341 0671 Fax: +966 3 341 0950 Email: odico@olayandescon.com www.olayandescon.com MANUFACTURING Lahore - PAKISTAN 2 km., Defence Road, off 24 km., Multan Road, Lahore 53800, Pakistan Tel: +92 42 3596 6681-6 Fax: +92 42 3596 6687-8 Email: manufacturing@descon.com Karachi - PAKISTAN Plot No. A 35-36, Eastern Industrial Zone, Port Qasim Industrial Area, Karachi, Pakistan Tel: +92 21 3474 0031-36 Fax: +92 21 3474 0037 Email: kmw-info@descon.com Abu Dhabi - UAE P.O.Box 46821, Ghayathi Road, Ruwais Industrial Area, Abu Dhabi, UAE Tel: +971 2 876 1287 Fax: +971 2 876 0423 Email: mumtaz.khan@descon.com Sharjah - UAE Descon Engineering FZE Plot No. HE- 5, 6, 7 & HD-19, P.O.Box 42576, Hamriyah Free Zone, Sharjah, UAE Tel: +971 6 526 9020 Fax: +971 6 526 9053 Email: hmw@descon.com Al Jubail - SAUDI ARABIA Plot No 3 & 4, Street No. 124 P.O.Box 10108, Jubail Industrial City 31961, Kingdom of Saudi Arabia Tel: +966 (0) 3 341 0671 Fax: +966 (0) 3 341 0950 Email: odico@olayandescon.com Yanbu - SAUDI ARABIA Block No. 4, Street No. 6, Light Industrial Park, P.O.Box 31120, Yanbu Industrial City 41912, Kingdom of Saudi Arabia Tel: +966 (0) 4 321 0354 Fax: +966 (0) 4 321 0334 Email: odico@olayandescon.com Al Khor - QATAR Descon Engineering Qatar LLC Al Khor Industrial Area, Al Khor, Qatar Tel: +974 4405 4777 Fax: +974 4405 4778 Email: qba@descon.com Descon Power Solutions 18 km., Ferozepur Road, Lahore 54760, Pakistan Tel: +92 42 3592 3760-64 Fax: +92 42 3592 3765 info@desconpower.com Karachi - PAKISTAN 9th Floor Business Avenue, 26-A Block 6, P.E.C.H.S, Main Shahrah-e-Faisal, Karachi 75400, Pakistan Tel: +92 21 3452 6564 Fax: +92 21 3454 4480 CHEMICALS Descon Chemicals Limited Descon Oxychem Limited Descon Corporation Limited Interworld Travels (Pvt) Limited 18 km., Ferozepur Road, Lahore 54760, Pakistan Tel: +92 42 3592 3721-26 Fax: +92 42 3592 3749 Email: info@desconchemicals.com Email: info@desconoxychem.com Email: info@desconcorporation.com Email: info@interworldtravels.com.pk
Similar documents
Olayan Descon
way on the opposite side of it. To fulfill our corporate mission and provide customers with progressive, strategic Manufacturing and services, we offer talent unmatched in the industry. The strengt...
More informationvolume 1 | 2014
Descon has started execution of its second Wind Project 50 MW at Gharo, Sindh. Descon is working on this project with Nordex (Germany) as its technology partner. The successful completion of this p...
More informationlaunched
The EPC Project was awarded to Descon Engineering on July 19, 2007. The project required upgrading of the existing Urea Plant and enhancing its capacity from 1600 tons per day to 2300 tons per day....