Exhibition Panels 2016

Transcription

Exhibition Panels 2016
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 12:59 Page 1
COALITE REGENERATION
Welcome
Thank you for visiting our
event today
Members of the project team are on hand to
answer your questions and to provide an update
on the ongoing regeneration of the former
Coalite Works site in Bolsover, North East
Derbyshire.
The boards provide details on:
• The Development Team
• Useful Background On The Site
• The Challenge
• Development Considerations
• The Story So Far
• Phasing
• Residential Masterplan
• Summary Of Proposals
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 12:59 Page 2
COALITE REGENERATION
To Clowne & Worksop
Butterm
ilk Lane
B6418
Useful Background
O
ld
Bo
Bolsover
lso
ve
rC
P
Railway line
Markham Vale
Chesterfield
Buttermilk
Lane B641
8
NE Derbyshire
To New Bolsover
M1
To M1 & Chesterfield
Site Location
Planning Update
The site is located 1.5 miles north west of Bolsover
On 23 December 2015, Bolsover District Council granted
town centre on either side of Buttermilk Lane. The
planning permission for the employment element. The
site is under 5 minutes travel time to junction 29A
focus is now on the residential element of the planning
of the M1 Motorway and sits within North East
application in North East Derbyshire due to be
Derbyshire Council and Bolsover District Council
considered in March 2016.
boundaries. The site spans an area of 140 acres.
Remediation Commitment
Site Background
In 1936, The Low Temperature Carbonisation
Company (later The Coalite Chemical Company)
established a manufacturing plant on land at
Buttermilk Lane, Bolsover, Derbyshire to manufacture
Coalite, a brand of low-temperature coke used as a
Bolsover Land Ltd has provided both councils with a firm
commitment that no development of the residential
element of the planning application will commence until
the site (in both Bolsover and North East Derbyshire) has
been fully remediated.
smokeless fuel. The manufacturing plant at Bolsover
produced other byproducts including fuel for the RAF.
Quality Design And Layout
The site closed in 2004 and is heavily contaminated
with chlorinated phenols and other noxious
compounds. It will cost millions £’s to clean up
the site.
The application has been subject to an OPUN Design
Review in October 2015. The feedback from this Review
and subsequent discussions with officers has resulted in
the remodelling of the site, to ensure high design
aspirations are met. As a part of this process, a 1.8ha
school site has now been included within the layout,
which has resulted in a reduction in the number of
residential units, from 795 to 660.
Viability
Discussions between the Developer and councils on the
viability of the scheme are still ongoing. It is anticipated
that this will be resolved within the next few weeks.
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 12:59 Page 3
COALITE REGENERATION
The Challenge
Extent of Contamination
There is a legacy of contamination on the site due to its
former use.
The northern site area contains a number of large storage
tanks, the majority of which have been cut open and
these contained a range of hydrocarbon wastes that
include coal oil, crude tyre oil, tar acid and phenolic
wastes.
There is significant contamination of the soils and
groundwater system at the site that represents a significant
risk to human health and the aquatic environment. The site
soils are contaminated with a range of complex
hydrocarbons that include chlorinated phenols and
phenolic compounds, fuels and oils, coal tars and pitch.
Some of the phenolic compounds emit strong vapours
and odours that can be detected at some distance from
the site.
There is potential risk of contamination migrating into the
River Doe Lea where it flows through the site and this could
have a detrimental effect on aquatic life within the river.
Remediation Methodology
The extent and risks associated with the soil and
groundwater contaminants at the site has been assessed
through a comprehensive sequence of ground
investigation and risk assessments. The results of a trial
remediation program at the site indicate that a
remediation treatment train based upon the following
procedures will be necessary:
• Selected excavation of known areas of contamination;
• Sorting of materials into physical and chemical groups;
• Classification of those materials and stockpiling
for processing;
• Selected treatment of organic contaminants of
concern within soils
• Selected treatment of inorganic contaminants using
soil washing
• Limited off-site disposal of persistent contaminants
unable to be economically treated on-site by the
above processes
The Developer will work closely with the local authorities
and other agencies to ensure the remediation is carried
out under strict environmental controls to limit the escape
or generation of odours and vapours, and to minimise the
potential effects of the works on the water environment
and human health.
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 13:00 Page 4
COALITE REGENERATION
Development
Considerations
Ecology
In spite of its past use and contamination, in some areas
the site supports a range of protected species including
grass snake, water vole, bats as well as a range of
interesting plants, invertebrates and mammals.
The proposed development offers an excellent opportunity
to secure a better future for these groups on the site as well
as enhancing the site's role as part of the wider area's
network of developing habitat.
Landscape and Visuals
The landscape design aims to create safe, secure and
welcoming residential and business environments whilst
integrating the development within the existing landscape
fabric, transport infrastructure and the surrounding built
form whilst protecting and enhancing views from the
historic Bolsover Castle.
Transport
The Developer has been working closely with the local
highways authority and Highways Agency to assess any
material impact of traffic related to the development
upon the highway network, including the M1,and to
specify, design and agree any required improvement
works.
Flood Risk
The Developer will also be undertaking flood alleviation
assessment and significant new drainage works to ensure
that the development has suitable and considered
drainage outfalls and that any effect upon the hydrology
of the area is fully considered to ensure the development
does not cause any material impacts.
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 13:00 Page 5
COALITE REGENERATION
The Residential Masterplan
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 13:00 Page 6
COALITE REGENERATION
Phasing Plans
Phase 1
Years 1-2
• Decontamination and remediation of
site and construction of the primary
road and service infrastructure.
• Flood risk alleviation works
• Creation of wildlife corridors/
ecological habitats and sustainable
drainage solutions.
Phase 2
Years 3-4
• Remediation of the commercial sites
on a plot by plot basis.
• Design and development of individual
B1/B2 & B8 industrial facilities on a
demand led basis.
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 13:00 Page 7
COALITE REGENERATION
Phase 3
Years 5-6
• Establishment of primary highway,
footway and cycleway infrastructure
together with landscape corridor on
Chesterfield Road.
• Residential plots to be developed
sequentially in sub plot phases from
the new access.
Phase 4
Years 5-7
• Residential plots to be developed
sequentially in sub plot phases from
the new access.
Phase 5
Years 7-10
• Establishment of Local
Neighbourhood Centre with full
connectivity to remainder of
development.
• Residential plots to be developed
sequentially in sub plot phases from
the new access.
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 13:00 Page 8
COALITE REGENERATION
The Story So Far
1936
Manufacturing plant opened at land near Buttermilk Lane in Bolsover,
North East Derbyshire.
1948
Company changed its name to the Coalite Chemical Company to reflect the
diversified nature of the business.
1996
Coalite prosecuted and a fine of £150,000 for contamination of the river Doe Lea
and surrounding farmland.
2004
Coalite closed leaving a heavily contaminated site with chlorinated phenols and
other noxious compounds with clean-up costs estimated at several millions of £’s.
2008
Unsuccessful planning application by Goodman to develop large sheds on the site.
2012
November
Bolsover Land Ltd, a joint venture between Marcol and St Francis Group
acquired the site.
December
Tour of site organised for councillors and officers of both North East
Derbyshire District Council and Bolsover District Council.
March
Emerging Masterplan presented to Bolsover District Council and
North East Derbyshire District Council.
May
Consultation begins with local groups and wider community on
the new vision for the site. 15,000 newsletters distributed to local
residents and businesses publicising consultation event.
June
Public consultation events held in Clowne and Bolsover attended by
over 200 people.
2013
Project website launched www.coalite-regeneration.com
August
strong public support captured from community engagement events.
2014
February
The Bolsover and North East Derbyshire applications are validated.
2015
August
Bolsover District Council Planning Committee move to approve
employment element of application.
October
An OPUN Design Review is held to discuss the residential element
in North East Derbyshire.
November
Weekly Steering Group meetings begin between key parties to
progress the residential element in North East Derbyshire.
December
Bolsover District Council issue the Decision Notice for the
employment element.
January
Consultation event organised for elected members and
the wider public.
March
Residential application in North East Derbyshire to be presented to
Members at Bolsover District Council Planning Committee, for their
view on the neighbouring scheme.
2016
Residential application to be presented to Members at North East
Derbyshire District Council Planning Committee for determination.
May
Anticipated submission of first Reserved Matters application, for an
employment development in Bolsover.
www.coalite-regeneration.com
Pull up AW 22 01 16 JO copy_Layout 1 26/01/2016 13:00 Page 9
COALITE REGENERATION
Summary of Proposals
Benefits
Tell Us What You Think
1. A financially viable scheme – creating value in
Thank you for visiting our event today.
order to fund the extensive remediation and
infrastructure required to regenerate the wider site.
2. The remediation of a site which has long been
synonymous with contamination – the wider benefits of
this to the local population in terms of health and air
quality will be wide reaching.
3. Site’s remediation will be completed before any
Please take a moment to fill out our feedback form.
The residential element of the scheme is due to be
considered by North East Derbyshire’s Planning
Committee in March 2016.
If you have any further questions please do not hesitate
to e-mail Alun Hayes on.
residential occupation.
alun@uk-nlp.co.uk
4. Deliver a significant number of jobs – based on
Or write to us using the Freepost address:
similar schemes and using the Homes and Communities
Freepost Plus RTRA-YHAE-ZAYU
Agency (HCA) job creation formula we would expect
UK Networks
to see in the region of 1,500 new jobs created when the
29 Larkhill Lane,
site is fully occupied.
Formby,
5. Creation of new and extensive landscaping and
L37 1LT
ecological habitat – greatly enhancing the current state
of the site, with benefits to the Doe Lea as it is cleared
and allowed to flourish.
6. Provide 660 high quality new homes – enhanced by
green infrastructure well connected to footpaths and
cycleways.
7. Offsite highway works and public transport
improvements – serving the existing communities and
new employees.
8. New community facilities – incorporating a local
retail offer, attractive public realm, children’s play space
and land safeguarded for a new primary school.
www.coalite-regeneration.com